Created byFuzzy Cloud

Supreme Court of India

MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LIMITEDversusADANI POWER MAHARASHTRA LIMITED AND OTHERS

Citation
2023 INSC 399
Decided
20 April 2023
Disposal
Dismissed

Holding

The deallocation of the Lohara Coal Blocks is a ‘Change in Law’ event under the PPAs, entitling APML to restitutionary compensation calculated on the basis of the coal cost (including transportation) as determined by the expert committee.

Summary

Maharashtra State Electricity Distribution Company Ltd (MSEDCL) appealed against the Appellate Tribunal for Electricity’s (APTEL) order that held the deallocation of the Lohara Coal Blocks was a ‘Change in Law’ event under the Power Project Agreements (PPAs) and entitled Adani Power Maharashtra Ltd (APML) to restitutionary compensation. The Supreme Court examined whether the notification creating a buffer zone under the Wildlife (Protection) Act, 1972, which led to the deallocation, fell within the definition of ‘Law’ in the PPA, and whether the methodology adopted by the expert committee – using transfer pricing and including transportation costs – was appropriate. The Court affirmed that any order or notification by a governmental instrumentality constitutes ‘Law’, and that the deallocation after the cut‑off date was indeed a ‘Change in Law’ event. It held that APML must be compensated on the basis of the coal cost (including transport) as determined by the expert committee, rejecting MSEDCL’s objections to the methodology and to the findings of MERC and APTEL. Consequently, the appeals were dismissed.

Issues considered

  • Whether the deallocation of the Lohara Coal Blocks constitutes a ‘Change in Law’ event under the Power Project Agreements.
  • Whether APML is entitled to restitutionary compensation for the loss of coal allocation.
  • Whether the methodology (transfer pricing method, inclusion of transportation costs) adopted by the expert committee for calculating compensation is appropriate.
  • Whether MERC erred in using linkage coal cost as the base for compensation, thereby violating the restitution principle.
  • Whether MSEDCL can contest the expert committee’s findings and raise claims contrary to its earlier submissions before the State Commission.
  • Whether the notification creating a buffer zone under the Wildlife (Protection) Act, 1972, falls within the definition of ‘Law’ in the PPA.
  • Whether the cut‑off date in the PPA precludes the deallocation from being treated as a ‘Change in Law’.

Legislation cited

Subjects

Change in LawPower Purchase AgreementCoal AllocationRestitutionCompensationExpert CommitteeElectricity RegulationTransfer PricingWildlife Protection ActDeallocation of Coal Blocks

Judgment

648                      [2023]
              SUPREME COURT     7 S.C.R. 648
                             REPORTS                        [2023] 7 S.C.R.


A        MAHARASHTRA STATE ELECTRICITY DISTRIBUTION
                    COMPANY LIMITED
                                      v.
        ADANI POWER MAHARASHTRA LIMITED AND OTHERS
B                     (Civil Appeal Nos. 687-688 of 2021)
                               APRIL 20, 2023
                 [B. R. GAVAI AND VIKRAM NATH, JJ.]
            Electricity – ‘Change in Law’ event – Deallocation of Lohara
      Coal Blocks, if a ‘Change in Law’ event – Held: Yes – Deallocation
C
      of Lohara Coal Blocks would amount to ‘Change in Law’ event as
      defined under the Power Project Agreements – No interference
      warranted with the concurrent findings of MERC and APTEL –
      Methodology of arriving at the compensation payable on account
      of ‘Change in Law’ event also not interfered with – Wild Life
D     (Protection) Act, 1972 – s.38(V) – Principle of Restitution.
           Dismissing the appeals, the Court
            HELD: 1.1 In the case of MSEDCL v. APML and Others,
      this Court held that the ‘Change in Law’ relief for domestic coal
      shortfall should be on ‘actuals’ i.e. as against 100% of normative
E     coal requirement assured in terms of NCDP, 2007. The Station
      Heat Rate (“SHR”) and Auxiliary consumption should be
      considered as per the Regulations or actuals, whichever is lower.
      The Start date for the ‘Change in Law’ event for the NCDP, 2013
      was held to be 1st April 2013. Compensation for shortfall of
F     domestic coal on account of ‘Change in Law’ on account of
      amendment to the SHAKTI Policy stands covered by the
      judgment dated 3rd March 2023 in the case of MSEDCL v. APML
      and Others. [Paras 31-33][661-C-F]
           Maharashtra State Electricity Distribution Company
G          Limited v. Adani Power Maharashtra Limited and
           Others 2023 SCC OnLine SC 233 – relied on.
            1.2 The issue with regard to SHAKTI Policy is concerned,
      the same is considered by this Court in judgments of even date,
      in Civil Appeal Nos. 677-678 of 2021 and Civil Appeal No. 5684
H
                                     648
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                 649
         ADANI POWER MAHARASHTRA LTD.

of 2021, holding therein that the restitutionary principle, as has     A
been applied by this Court on account of ‘Change in Law’, will
also be applicable on account of change occurring due to
introduction of SHAKTI Policy. As such, no interference would
be warranted with the findings of APTEL in light of the view taken
by this Court in the aforesaid three judgments. [Paras 34][661-
                                                                       B
F-H]
      1.3 A perusal of the impugned judgment and order would
reveal that MSEDCL itself had sought the carrying cost
prescribed in the MYT Tariff Regulations before the State
Commission. APTEL has rightly held that MSEDCL could not
be permitted to raise its claim contrary to what was sought before     C
the State Commission. As such, interference would not be
warranted with the said issue also. [Para 35][662-A-B]
      1.4 In the case of MSEDCL v. APML and Others, this Court
has upheld the view taken by CERC as well as APTEL, holding
that the actual GCV of coal ‘as received’ at the plant site has to     D
be taken into consideration. As such, no interference would be
warranted with regard to the said issue also. [Para 38][662-F-G]
       1.5 The only issue that is required to be considered is as to
whether deallocation of Lohara Coal Blocks would amount to
‘Change in Law’ and as to whether APML would be entitled to            E
restitution on account of the same. The same is concurrently held
in favour of APML by both the MERC and the APTEL, thereby
declaring the event of deallocation of Lohara Coal Blocks as
‘Change in Law’. Unless the said issue is found to be perverse
or in ignorance of the mandatory statutory provisions or is based      F
on extraneous considerations, it will not be permissible for this
Court to interfere with the same. A perusal of the definition of
‘Law’ as found in Article 1.1 of the PPA would reveal that any
order or notification, rule or regulation by an Indian Governmental
Instrumentality would constitute ‘Law’. It cannot be disputed that
Government of Maharashtra, Government of India and various             G
statutory authorities would fall under the term ‘Governmental
Instrumentalities’. In the present case, the cutoff date under the
PPA was 14th August 2008. It is to be noted that the power to
notify a Tiger Reserve as a Buffer Zone is vested with the State
                                                                       H
650            SUPREME COURT REPORTS                      [2023] 7 S.C.R.


A     Government under Section 38V of the Wildlife (Protection) Act.
      For consideration and creation of Buffer Zone, three statutory
      requirements have to be complied with. From the material placed
      on record, it is clear that prior to 14th August 2008, the area
      where Lohara Coal Block is situated was not even proposed to
      be notified as a Buffer Zone. It is only seven days after the cut-off
B
      date, i.e., 21st February 2008, that the Chief Conservator, Forests
      gave approval for constitution of an Expert Committee for creating
      the Buffer Zone surrounding the core area. Thereafter, on 7th
      March 2008, the Conservator, TATR submitted the proposed
      demarcation to the Chief Conservator of Forest for creating the
C     Buffer Zone surrounding the core area of TATR. The consultation
      of the Gram Sabha happened only between May 2008 and
      November 2008, i.e., much after the cut-off date. Subsequently,
      on 8th October 2008, the Conservator, TATR submitted the
      revised proposal for Buffer Zone to TATR. After numerous other
      deliberations, including the one with National Tiger Conservation
D
      Authority (NTCA), the Government of Maharashtra issued a
      notification on 5th May 2010 notifying 1101.7711 sq. km. as the
      Buffer Zone of TATR. As such, the notification dated 5th May
      2010, which included the area where Lohara Coal Blocks were
      situated, will have to be construed to be a ‘Change in Law’. It is
E     only because of issuance of the said notification, the coal block,
      which would have otherwise been available to APML, was not
      available to it. [Paras 40, 42-45][663-A-B; C-H; 664-A-F]
             1.6 MoC had allocated Lohara Coal Blocks vide allocation
      letter dated 6th November 2007 and MoEF granted the ToR for
F     Lohara Coal Blocks on 16th May 2008 pursuant to EAC’s
      recommendation in the meeting dated 28th April 2008. A perusal
      of the said letter of MoC dated 6th November 2007 would clearly
      reveal that allocation of Lohara West and Lohara Extension Coal
      Block to APML has been specifically made to meet the coal
      requirements of their 1000 MW power plant in District Gondia,
G     Maharashtra. It is, thus, clear that the bid submitted by the
      appellant on the cut-off date was on the basis of the assurance
      that the coal would be available to it from Lohara Coal Blocks.
      Had the notification dated 5th May 2010 not been issued, APML
      could have utilized the coal from Lohara Coal Blocks which was
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                 651
         ADANI POWER MAHARASHTRA LTD.

allotted to it by MoC. Apart from that, it is to be noted that         A
MSEDCL was a part of the Expert Committee which was
constituted by MERC vide its order dated 21st August 2013.
Having participated in the proceedings of the meeting of the
Expert Committee, MSEDCL cannot be permitted to take a stand
contrary to the decision of the said Expert Committee.
                                                                       B
Deallocation of Lohara Coal Blocks was not on account of any
fault of APML and this is recognized by CIL itself, inasmuch as it
has returned the Bank Guarantee which was furnished by APML.
No interference would be warranted with the concurrent findings
of MERC and APTEL that deallocation of Lohara Coal Blocks
would amount to ‘Change in Law’ event as defined under the             C
PPA. [Paras 46-48][664-F-H; 665-A-C]
      1.7 Insofar as methodology is concerned, APTEL has
referred to the report of the Expert Committee appointed by
MERC, which recommended determination of the price of coal
from Lohara Coal Blocks using “transfer pricing method” which          D
is one of the commonly used methods. It has accepted the report
of the Expert Committee which provided a reasonable
methodology to arrive at the cost of mining from Lohara Coal
Blocks. the finding of APTEL is based on the report of the Expert
Committee, which was ignored by MERC. The Expert Committee
had found that APML had entered into a PPA based on the                E
assurance of an instrumentality of the Government of India that
coal would be provided to it from the Lohara Coal Blocks.
However, on account of the reasons that have been elaborately
discussed, Lohara Coal Blocks, which was allocated to APML,
came to be deallocated for no fault on the part of APML. It is to      F
be noted that the Expert Committee, while arriving at its finding,
had also appointed external industry experts, i.e. legal consultant,
financial experts and independent auditors. It is worthwhile to
mention that one of the Members of the said Expert Committee
was a representative of MSEDCL. What has been granted under
the said methodology is the additional cost of transport which         G
APML would be required to incur for transporting the coal from
other locations on account of deallocation of Lohara Coal Blocks.
We, therefore, find no reason to interfere with the said finding

                                                                       H
652            SUPREME COURT REPORTS                         [2023] 7 S.C.R.


A     with regard to methodology of arriving at the compensation
      payable on account of ‘Change in Law’ event. [Paras 49 and
      50][665-D-F; 668-F-H; 669-A;]
            Manohar Lal Sharma v. The Principal Secretary and
            Others (2014) 9 SCC 516 : [2014] 8 SCR 446; Energy
B           Watchdog v. Central Electricity Regulatory Commission
            and Others (2017) 14 SCC 80 : [2017] 3 SCR 153
            Tata Power Company Limited Transmission v.
            Maharashtra Electricity Regulatory Commission 2022
            SCC OnLine SC 1615; Maharashtra State Electricity
            Distribution Company Limited v. GMR Warora Energy
C           Ltd. and Others in Civil Appeal No. 6927 of 2021 –
            referred to.
                              Case Law Reference
      [2014] 8 SCR 446                 referred to              Para 15
D     (2017) 3 SCR 153                 referred to              Para 17
            CIVIL APPELLATE JURISDICTION : Civil Appeal Nos.687-
      688 of 2021.
            From the Judgment and Order dated 05.10.2020 of the Appellate
      Tribunal for Electricity in Appeal Nos.340 and 354 of 2019.
E
            M. G. Ramachandran, G. Umapathy, Niranjan Reddy, Dr. A.M.
      Singhvi, Darius J. Khambata, Sajan Poovayya, Vikram Nankani, Sr. Advs.,
      Ms. Poorva Saigal, Shubham Arya, Nikunj Dayal, Ms. Pallavi Saigal,
      Ravi Nair, Ms. Shikha Sood, Ms. Reeha Singh, Ms. Anumeha Smiti,
      Aneesh Bajaj, Anup Jain, Udit Gupta for M/s. Udit Kishan and Associates,
F     Vishrov Mukherjee, Pukhrambam Ramesh Kumar, Yashaswi Kant, Karun
      Sharma, Ms. Juhi Senguttuvan, Mahesh Agarwal, Amit Kapur, Ms.
      Poonam Sengupta, Avishkar Singhvi, Arshit Anand, Saunak Rajguru,
      Aman Sharma, Ms. Aparajita, Ms. Deepshikha Mishra, Ankitesh Ojha,
      Karan Rukhana, E. C. Agrawala, Ms. Pallavi Sharma, Advs. for the
      appearing parties.
G
            The Judgment of the Court was delivered by
            B. R. GAVAI, J.
            1. The present appeals challenge the judgment and order dated
       th
      5 October 2020 passed by the Appellate Tribunal for Electricity
H     (hereinafter referred to as ‘APTEL’), in cross appeals being Appeal
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                        653
   ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]

No. 340 of 2019, filed by Maharashtra State Electricity Distribution          A
Company Limited (hereinafter referred to as ‘MSEDCL’), the appellant
herein, and Appeal No. 354 of 2019, filed by Adani Power Maharashtra
Limited (hereinafter referred to as ‘APML’), respondent No. 1 herein,
thereby challenging the order dated 6th September 2019, passed by
Maharashtra Electricity Regulatory Commission (hereinafter referred
                                                                              B
to as ‘MERC’).
        2. APML and MSEDCL had entered into four long term Power
Project Agreements (hereinafter referred to as ‘PPA’) dated (a) 8th
September, 2008 for 1230 MW (hereinafter referred to as ‘1230 MW
PPA’); (b) 21st March, 2010 for 1200 MW (hereinafter referred to as
‘1200 MW PPA’); (c) 9th August, 2010 for 120 MW (hereinafter referred         C
to as ‘120 MW PPA’) and (d)16th February, 2013 for 440 MW (hereinafter
referred to as ‘440 MW PPA’), pursuant to the competitive bidding
process conducted by MSEDCL.
       3. Prior to the signing of the PPAs between the parties, APML
had applied to the Ministry of Coal, Government of India (for short,          D
“MoC”) for allotment of Lohara Coal Blocks on 10th January 2007.
Thereafter, on 6th November 2007, the MoC issued a Letter of Allocation
(LoA) to APML conveying the allocation of Lohara (West) and Lohara
Extension (E) Coal Blocks as the allocated source of fuel. Subsequently,
on 23 rd November 2007, APML applied to the Standing Linkage                  E
Committee (Long-Term) (hereinafter referred to as “SLC (LT)”) for
grant of coal linkage for balance capacity to cover the coal requirement
of Units 1, 2 and 3 of the Tiroda Thermal Power Station (TPS).
       4. On 27th December 2007, the Government of Maharashtra issued
a statutory Notification under Section 38 (V) of the Wild Life (Protection)   F
Act, 1972, classifying 625.82 sq. km. of the Tadoba National Park and
Andheri Wildlife Sanctuary as a Critical Tiger Habitat (CTH). It is
pertinent to note that, at this point in time, the area demarcating the
CTH, did not include the area of Lohara Coal Blocks and as such, there
were no restrictions on coal mining in the allotted mining lease area. As
per the revised Request for Proposal (RFP), the bid deadline was 21st         G
February 2008 and the cut-off date was 14th February 2008, being seven
days before the deadline. APML submitted its bid for supply of 1320
MW Power to MSEDCL, wherein it specified that the fuel source for a
portion of the contracted capacity, viz. 800 MW capacity out of 1320
                                                                              H
654            SUPREME COURT REPORTS                           [2023] 7 S.C.R.


A     MW, would be the Lohara Coal Blocks. A copy of the MoC’s allocation
      letter dated 6th November 2007 was appended to the bid, as per the bid
      requirements.
             5. Thereafter, on 21st February 2008, i.e., seven days after the bid
      cut-off date, the Conservator of the Tadoba Andheri Tiger Reserve (for
B     short, “TATR”) approved the constitution of an Expert Committee for
      the creation of a Buffer Zone surrounding the core area of TATR under
      Section 38(V) of the Wildlife (Protection) Act.
              6. Twenty-four days after the bid cut-off date, the Conservator,
      TATR submitted a proposal to the Chief Conservator of Forest,
C     Maharashtra for creation of the aforesaid Buffer Zone. During the
      pendency of this proposal, the Ministry of Environment, Forests and
      Climate Change, Government of India (for short, “MoEF”), in exercise
      of its powers in terms of Regulation 7 of MoEF’s Notification dated 14 th
      September 2006, granted the Terms of Reference (ToR), to APML for
      mining in the Lohara Coal Blocks, on the basis of the recommendation
D     made by the Expert Appraisal Committee, MoEF (for short, “EAC”) in
      its 21st Meeting.
             7. Thereafter, the 1320 MW PPA was executed between the
      parties on 8th September 2008, for supply of the contracted capacity
      from Units 2 and 3 of the Tiroda TPS. In pursuance of APML’s
E     application for coal linkage, the SLC(LT) issued a Letter of Assurance
      (LoA) dated 12th November 2008, authorising the coal linkage sought,
      whilst at the same time, acknowledging that the Lohara Coal Blocks
      catered to the requirement for generation of a portion of APML’s
      contracted capacity, i.e. 800 MW to MSEDCL.
F            8. In the meanwhile, on 8th October 2008, the Conservator, TATR
      submitted a revised proposal for creating the aforesaid Buffer Zone,
      which, for the first time, included the mining lease area of about 176
      hectares of the Lohara Coal Blocks. These proposals were discussed in
      a meeting of the EAC, where an area of 1067.21 sq. km. was proposed
G     to be the Buffer Zone of TATR. Thereafter, in its 59th Meeting held on
      24-25 November 2009, the EAC decided to withdraw the ToR issued to
      the Lohara Coal Blocks since the proposed mining lease areas were
      falling in the proposed Buffer Zone, which included a tiger corridor in
      the midst of a rich forest. Thereafter, vide notification dated 5 th May
      2010, the Government of Maharashtra notified 1101.7 sq. km. as the
H     Buffer Zone of TATR.
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                      655
   ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]

        9. Since the Lohara Coal Blocks could not be utilized to meet the   A
requirements under the 1320 MW PPA, APML first informed MSEDCL
of its inability to supply power, vide letter dated 22nd May 2010 and,
thereafter, issued a termination notice to MSEDCL dated 16th February
2011 due to the occurrence of force majeure, on account of cancellation
of Lohara Coal Blocks, in terms of Article 12 of the 1320 MW PPA.
                                                                            B
       10. On 22nd May 2010, APML informed MSEDCL regarding its
inability to supply power under the PPA from Units II and III at the
PPA-agreed tariff due to cancellation of Lohara Coal Blocks. On 14 th
June 2010, APML also informed MSEDCL regarding the occurrence of
a force majeure event in terms of Article 12 of the PPA. Consequently,
a termination notice dated 16th February 2011was issued to MSEDCL.          C

       11. On 17th July 2012, APML filed a petition, being Case No. 68
of 2012 before MERC, claiming ‘Change in Law’ and ‘force majeure’
reliefs on account of cancellation of Lohara Coal Blocks. On 21st August
2013, MERC passed an order in the said petition directing for a meeting
of the Expert Committee to be constituted to evaluate the impact of         D
withdrawal of the ToR on Units II and III of Tiroda TPS and determine
a compensatory charge to be paid to APML. MERC also worked out an
interim relief at Rs.3.124 per KWH, which would be applicable only for
sale of power above the initial 520 MW from the date of commercial
operation. However, the claim of APML’s with regard to force majeure        E
was rejected by the said order.
       12. Being aggrieved by the said order dated 21st August 2013, M/
s Prayas Energy Group, the consumer representative (hereinafter referred
to as “Prayas”) filed an appeal being Appeal No. 296 of 2013 challenging
the order passed by MERC. A cross-appeal also came to be filed by           F
APML being Appeal No. 241 of 2016 challenging the rejection of plea
of force majeure.
      13. In pursuance of the order passed by MERC dated 21st August
2013, the Government of Maharashtra constituted a High-Level Expert
Committee on 9 th December 2013. The said High-Level Expert                 G
Committee filed its report on 17th February 2014 recommending grant of
compensatory tariff to APML for 800 MW capacity which was entirely
dependent on coal from Lohara Coal Blocks.
      14. On 17th February 2014, MoC cancelled and deallocated Lohara
Coal Blocks on the ground that Environmental Clearance (EC) and Forest
                                                                            H
656               SUPREME COURT REPORTS                       [2023] 7 S.C.R.


A     Clearance (FC) were not given to the said coal blocks. Vide order dated
      5th May 2014, MERC, in Suo Motu Case No. 63 of 2014, devised a
      mechanism for calculating the compensatory fuel charges payable to
      APML by MSEDCL. The said order was challenged by MSEDCL and
      Prayas in Appeal No. 166 of 2014 and Appeal No. 218 of 2014
      respectively.
B
             15. On 25th August 2014, this Court, in its judgment in the case of
      Manohar Lal Sharma v. The Principal Secretary and Others1, held
      the allocation of coal blocks made by the Screening Committee from
      14th July 1993 onwards to be illegal. On 16th April 2015, Ministry of
      Power (for short, “MoP”) issued a policy direction under Section 107 of
C     the Electricity Act, 2003 to treat allocation of coal block under Coal
      Mine (Special Provisions) Ordinance, 2014 as a ‘Change in Law’ event.
      On 28th January 2016, the MoP notified the revised Tariff Policy.
             16. On 11th May 2016, APTEL partly allowed Appeal No. 296 of
      2013 filed by Prayas setting aside the order of MERC dated 21st August
D     2013, except on the issue of ToR cancellation not being a force majeure
      event. Vide the said order dated 11th May 2016, APTEL also allowed
      the appeals filed by MSEDCL and Prayas against the MERC’s order
      dated 5th May 2014. APTEL held that MERC cannot exercise regulatory
      powers, thereby setting aside the award of compensatory fuel charge to
E     APML by MERC in exercise of its regulatory power. APTEL, however,
      kept the force majeure issue open for the decision on the issue of
      withdrawal of ToR.
             17. In the meantime, on 11th April 2017, this Court delivered a
      judgment in the case of Energy Watchdog v. Central Electricity
F     Regulatory Commission and Others2, wherein the Court held that
      change in policies of the Government affecting availability of domestic
      coal to the generating companies qualifies as a ‘Change in Law’ event
      as defined in the PPAs. Consequently, vide order dated 31st May 2019,
      APTEL allowed the appeal filed by APML being Appeal No. 241 of
      2016 and set aside the order of the MERC dated 21 st August 2013 and
G     remanded the matter to MERC for fresh consideration in the light of
      judgment of this Court in the case of Energy Watchdog (supra).
           18. Being aggrieved thereby, MSEDCL preferred an appeal, being
      Appeal No. 340 of 2019, on the ground that MERC erred in declaring
      1
          (2014) 9 SCC 516
H     2
          (2017) 14 SCC 80
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                      657
   ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]

the event of deallocation of Lohara Coal Blocks as ‘Change in Law’          A
event under the PPA. APML preferred a cross-appeal, being Appeal
No. 354 of 2019, on the ground that, while granting relief on account of
‘Change in Law’, MERC had adopted an erroneous methodology which
does not restore it to the same economic position as if no ‘Change in
Law’ had occurred.
                                                                            B
      19. The APTEL framed the following issues for consideration:
      (1)    “Whether MERC was justified in declaring the event of
             de-allocation of the Lohara Coal Blocks as a change in law
             event?
      (2)    Whether MERC was justified in considering the landed cost      C
             of linkage coal as the basis for computing change in law
             compensation to Adani when Lohara Coal Blocks were the
             bid-identified source of coal?
      (3)    Whether MERC was justified in pegging the carrying cost
             to the rate specified in prevalent Multi Year Tariff (“MYT”)   D
             Regulations?
      (4)    Whether MERC was justified in restricting the change in
             law relief to the difference between 100% assurance in
             New Coal Distribution Policy (“NCDP”), 2007 and 75%
             assurance under the SHAKTI Policy based on the Fuel            E
             Supply Agreement (“FSA”) dated 29.03.2018 being signed
             under the SHAKTI Policy?
      (5)    Whether MERC was justified in linking NCDP 2007 with
             allotment of the Lohara Coal Blocks?
                                                                            F
      (6)    Whether deallocation of the Lohara Coal Blocks was a
             foreseeable risk for Adani and whether the same has any
             implication on change in law relief allowed to Adani?
      (7)    Whether MERC adopted the correct methodology regarding
             Station Heat Rate (“SHR”) and Gross Calorific Value
             (“GCV’) in the Impugned Order while computing the change       G
             in law relief allowed to Adani? Whether such methodology
             adheres to the principle of restitution?”
     20. The APTEL, vide the impugned judgment and order dated 5th
October 2020, answered the issues as under:
                                                                            H
658      SUPREME COURT REPORTS                         [2023] 7 S.C.R.


A     “14.1 Issue No.1:- We hold that the Appellant was affected by
            change in law on account of the de-allocation of Lohara
            Coal Blocks. Accordingly, the impugned order is
            upheld on this issue.
      14.2 Issue No.2:- We hold that the Appellant is entitled to be
B          paid Lohara Coal cost including transportation cost as base
           while computing the compensations for the change in law
           events. The issue is decided in favour of the Appellant.
      14.3 Issue No.3:- As the Appellant itself had sought the carrying
           cost at the rate prescribed in the MYT Tariff Regulations
C          in its petition before the State Commission, we see no
           reason to interfere with the impugned order on this issue.
           Hence, the Appellant cannot raise its claim contrary to what
           has been sought before the State Commission. The issue
           is decided against the Appellant.
D     14.4 Issue No.4:- ln line with our judgment dated 28.9.2020 in
           A.No.116 of 2019 & batch, we hold that findings in the
           impugned order relating to the issue of restricting the
           quantum of shortfall in domestic coal to a maximum of 25%
           are against the principles of restitution under the change in
           law provisions of the PPA. The issue is decided in favour
E          of the Appellant.
      14.5 Issue No.5:- Since this issue was not pressed during the
           proceedings, we do not find it necessary to return a finding
           on this issue. No decision required.

F     14.6 Issue No.6:- We hold that the Appellant’s rights and
           obligation in the PPA cannot be thwarted based on omissions
           on part of Government instrumentalities and hence, the de-
           allocation of the Lohara Coal Blocks was not a feaseable
           risk for the Appellant. The issue is decided in favour of
           the Appellant.
G
      14.7 Issue No.7:- In line with our judgment dated 28.9.2020 in
           A.No.116 of 2019 & batch, we hold that the change in law
           compensation shall be calculated based on the SHR
           specified in the MERC MYT Regulations, 2011 or the actual
           SHR whichever is lower and actual GCV of coal as
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                      659
   ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]

              received at the plant site. The issue is decided in favour    A
              of the Appellant.”
      21. Consequently, the APTEL allowed the appeal filed by APML,
while rejecting the appeal preferred by MSEDCL. Aggrieved thereby,
MSEDCL has preferred the present appeals.
     22. We have heard Shri M.G. Ramchandran, learned Senior                B
Counsel appearing on behalf of the appellant-MSEDCL and Shri Sajjan
Poovayya, learned Senior Counsel appearing on behalf of respondent
No. 1–APML.
       23. Shri Ramchandran submitted that both the MERC and APTEL
have grossly erred in holding the deallocation of Lohara Coal Blocks to     C
be a ‘Change in Law’ event. It is submitted that deallocation of coal
blocks is a matter between APML and Coal India Limited (for short,
“CIL”) and the MSEDCL has nothing to do with the same. It is further
submitted that any change to clearances/consents cannot be regarded
as ‘Change in Law’. It is submitted that Clause 4.1.1 of the PPA devolves   D
an obligation and responsibility on APML to obtain and maintain all
consents required under the PPA and, as such, mere deallocation of
Lohara Coal Blocks could not be treated as ‘Change in Law’. It is further
submitted that in Case-1 bidding, the arrangement of fuel was the
responsibility of the bidder and, as such, APTEL is not concerned as to
from what sources APML would obtain the coal. It is further submitted       E
that as per the PPA, it was APML’s sole responsibility to transport the
coal and, as such, APTEL erred in granting compensation by factoring
the additional cost of transportation.
      24. As against this, Shri Poovayya submitted that, as consistently
held by this Court in the cases of Energy Watchdog (supra), Adani           F
Rajasthan and Maharashtra State Electricity Distribution Company
Limited v. Adani Power Maharashtra Limited and Others 3
[“MSEDCL v. APML and Others”, for short], since the deallocation of
Lohara Coal Blocks was on account of inclusion of the said area into
Buffer Zone of TATR vide notification of Government of Maharashtra          G
dated 5th May 2010, which was much after the cut-off date, both MERC
and APTEL have correctly held that the said event would amount to
‘Change in Law’. It is submitted that the bid of the appellant was
submitted on the basis that Lohara Coal Blocks was allotted to it.
3
    2023 SCC OnLine SC 233                                                  H
660              SUPREME COURT REPORTS                          [2023] 7 S.C.R.


A     However, much after the cut-off date, on account of the notification
      issued by the State of Maharashtra, the coal block was deallocated and,
      as such, APML was required to obtain the coal from other sources which
      incurred additional costs.
              25. Shri Poovayya further submitted that in view of the judgment
B     of this Court in the case of Tata Power Company Limited Transmission
      v. Maharashtra Electricity Regulatory Commission4and MSEDCL
      v. APML and Others (supra), an interference in the concurrent findings
      of fact would not be warranted.
             26. It is further submitted by Shri Poovayya that the Bank
C     Guarantee furnished by APML was also returned by CIL, finding no
      fault on the part of APML thereby fortifying its claim for Change in Law
      benefit.
             27. It is further submitted by Shri Poovayya that MSEDCL was a
      part of the Expert Committee, which was constituted by the MERC vide
D     its order dated 21st August 2013. Having participated in the said meeting
      in which the Expert Committee held that APML was entitled for
      compensation on account of deallocation of Lohara Coal Blocks, it does
      not lie in the mouth of MSEDCL to contend that APML is not entitled to
      ‘Change in Law’ compensation.

E           28. Out of the seven issues framed by APTEL, the 5th issue was
      not pressed before the APTEL.
             29. When we heard this batch of Electricity appeals, it was agreed
      between all the parties that this Court should first decide Civil Appeal
      No. 684 of 2021 (MSEDCL v. APML and Others (supra)) and Civil
F     Appeal No. 6927 of 2021 (Maharashtra State Electricity Distribution
      Company Limited v. GMR Warora Energy Ltd. and Others) inasmuch
      as three of the issues involved in all the appeals in the batch were common.
      It was submitted that those two appeals could be decided by deciding
      the three common issues. However, insofar as the other appeals are
      concerned, it was submitted that, in addition to the three common issues,
G     certain additional issues were also involved and it was agreed that after
      those two appeals are decided, the other appeals should be heard for
      considering these additional issues.
               30. The said three common issues are thus:
      4
H         2022 SCC OnLine SC 1615
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                          661
   ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]

      (i)     Whether ‘Change in Law’ relief on account of NCDP 2013            A
              should be on ‘actuals’ viz. as against 100% of normative
              coal requirement assured in terms of NCDP 2007 OR
              restricted to trigger levels in NCDP 2013 viz. 65%, 65%,
              67% and 75% of Assured Coal Quantity (ACQ)?
      (ii)    Whether for computing ‘Change in Law’ relief, the                 B
              operating parameters be considered on ‘actuals’ OR as per
              technical information submitted in bid?
      (iii)   Whether ‘Change in Law’ relief compensation is to be
              granted from 1st April 2013 (start of Financial Year) or 31st
              July 2013 (date of NCDP 2013)?                                    C
       31. After extensively hearing all the learned counsel for the parties,
vide the judgment and order dated 3rd March 2023 in the case of MSEDCL
v. APML and Others (supra), this Court decided those two appeals
after considering the aforesaid three issues.
        32. The first issue was answered by this Court, holding that the        D
‘Change in Law’ relief for domestic coal shortfall should be on ‘actuals’
i.e. as against 100% of normative coal requirement assured in terms of
NCDP, 2007. Insofar as the second issue is concerned, it was held that
the Station Heat Rate (“SHR” for short) and Auxiliary consumption
should be considered as per the Regulations or actuals, whichever is            E
lower. The third issue was answered holding that the Start date for the
‘Change in Law’ event for the NCDP, 2013 is 1 st April 2013.
      33. As such, Issue No. 4 with regard to compensation for shortfall
of domestic coal on account of ‘Change in Law’ on account of
amendment to the SHAKTI Policy stands covered by our judgment dated             F
3rd March 2023 in the case of MSEDCL v. APML and Others (supra).
       34. Insofar as the issue with regard to SHAKTI Policy is
concerned, the same is considered by us in our judgments of even date,
in Civil Appeal Nos. 677-678 of 2021 and Civil Appeal No. 5684 of 2021,
holding therein that the restitutionary principle, as has been applied by
                                                                                G
this Court on account of ‘Change in Law’, will also be applicable on
account of change occurring due to introduction of SHAKTI Policy. As
such, no interference would be warranted with the findings of APTEL
on Issue No. 4 in light of the view taken by us in the aforesaid three
judgments.
                                                                                H
662            SUPREME COURT REPORTS                            [2023] 7 S.C.R.


A           35. Insofar as Issue No. 3 is concerned, a perusal of the impugned
      judgment and order would reveal that MSEDCL itself had sought the
      carrying cost prescribed in the MYT Tariff Regulations before the State
      Commission. We, therefore, find that APTEL has rightly held that
      MSEDCL could not be permitted to raise its claim contrary to what was
      sought before the State Commission. As such, interference would not
B
      be warranted with the said issue also.
             36. Insofar as Issue No. 7 is concerned, in the judgment of this
      Court in the case of MSEDCL v. APML and Others (supra), we have
      already held that ‘Change in Law’ compensation shall be calculated
      based on the SHR specified in the MERC MYT Regulations or the
C     actual SHR whichever is lower.
             37. This Court, in the case of MSEDCL v. APML and
      Others(supra), after considering the relevant provisions under the
      Electricity Act, 2003 with regard to constitution of various expert bodies
      like the CEA, CERC and the learned APTEL, has held that these bodies
D     are bodies consisting of experts in the field. After considering various
      judgments on the issue, this Court observed thus:
            “123. Recently, the Constitution Bench of this Court in the case
            of Vivek Narayan Sharma v. Union of India has held that the
            Courts should be slow in interfering with the decisions taken by
E           the experts in the field and unless it is found that the expert bodies
            have failed to take into consideration the mandatory statutory
            provisions or the decisions taken are based on extraneous
            considerations or they are ex facie arbitrary and illegal, it will not
            be appropriate for this Court to substitute its views with that of
F           the expert bodies.”
             38. In the case of MSEDCL v. APML and Others (supra), we
      have upheld the view taken by CERC as well as APTEL, holding that
      the actual GCV of coal ‘as received’ at the plant site has to be taken into
      consideration. As such, no interference would be warranted with regard
G     to the said issue also.
             39. The other three issues, in our view, are interlinked. We find
      that the only issue that is required to be considered is as to whether
      deallocation of Lohara Coal Blocks would amount to ‘Change in Law’
      and as to whether APML would be entitled to restitution on account of
      the same.
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                        663
   ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]

      40. Insofar as the said issue is concerned, the same is concurrently    A
held in favour of APML by both the MERC and the APTEL, thereby
declaring the event of deallocation of Lohara Coal Blocks as ‘Change in
Law’. Unless the said issue is found to be perverse or in ignorance of
the mandatory statutory provisions or is based on extraneous
considerations, it will not be permissible for this Court to interfere with
                                                                              B
the same.
    41. We will, therefore, have to examine the concurrent findings of
MERC as well as APTEL, guided by these factors.
       42. It will be relevant to refer to the definition of ‘Law’ as found
in Article 1.1 of the PPA, which reads thus:                                  C
      “”Law” - means, in relation to this Agreement, all laws including
      Electricity Law in force in India and any statute, ordinance,
      regulation, Notification or code, rule. or any interpretation of any
      of them by an Indian Governmental Instrumentality and having
      force of law and shall further include all applicable rules.
                                                                              D
      regulations. orders. Notifications by an Indian
      Governmental Instrumentality pursuant to or under any of
      them and shall include all rules. regulations. decisions and
      orders of the CERC and the MERC.
      “Indian Governmental Instrumentality” means the GOI,
      Government of Maharashtra and any ministry or, department of            E
      or, board, agency or other regulatory or quasi-judicial authority
      controlled by GOI or Government of States where the Procurer
      and Project are located and includes the CERC and MERC.”
                                                    [Emphasis supplied]
       43. A perusal of the said definition would reveal that any order or    F
notification, rule or regulation by an Indian Governmental Instrumentality
would constitute ‘Law’. It cannot be disputed that Government of
Maharashtra, Government of India and various statutory authorities would
fall under the term ‘Governmental Instrumentalities’.
      44. It cannot be disputed that in the present case, the cut-off date    G
under the PPA was 14th August 2008. It is to be noted that the power to
notify a Tiger Reserve as a Buffer Zone is vested with the State
Government under Section 38V of the Wildlife (Protection) Act. For
consideration and creation of Buffer Zone, three statutory requirements
have to be complied with, which are thus:                                     H
664                 SUPREME COURT REPORTS                         [2023] 7 S.C.R.


A            (i)      “an Expert Committee must be constituted for identifying
                      and establishing a Buffer Zone;
             (ii)     Gram Sabha should be consulted before any such
                      notification and
             (iii)    the identification and establishment of a Buffer Zone shall
B                     be based on scientific and objective criteria.”
              45. From the material placed on record, it is clear that prior to 14 th
      August 2008, the area where Lohara Coal Block is situated was not
      even proposed to be notified as a Buffer Zone. It is only seven days
      after the cut-off date, i.e., 21st February 2008, that the Chief Conservator,
C     Forests gave approval for constitution of an Expert Committee for
      creating the Buffer Zone surrounding the core area. Thereafter, on 7 th
      March 2008, the Conservator, TATR submitted the proposed demarcation
      to the Chief Conservator of Forest for creating the Buffer Zone
      surrounding the core area of TATR. The consultation of the Gram Sabha
D     happened only between May 2008 and November 2008, i.e., much after
      the cut-off date. Subsequently, on 8th October 2008, the Conservator,
      TATR submitted the revised proposal for Buffer Zone to TATR. After
      numerous other deliberations, including the one with National Tiger
      Conservation Authority (NTCA), the Government of Maharashtra issued
      a notification on 5th May 2010 notifying 1101.7711 sq. km. as the Buffer
E     Zone of TATR. As such, the notification dated 5th May 2010, which
      included the area where Lohara Coal Blocks were situated, will have to
      be construed to be a ‘Change in Law’. It is only because of issuance of
      the said notification, the coal block, which would have otherwise been
      available to APML, was not available to it.
F            46. It is further clear from the record that MoC had allocated
      Lohara Coal Blocks vide allocation letter dated 6th November 2007 and
      MoEF granted the ToR for Lohara Coal Blocks on 16th May 2008
      pursuant to EAC’s recommendation in the meeting dated 28th April 2008.
      A perusal of the said letter of MoC dated 6th November 2007 would
G     clearly reveal that allocation of Lohara West and Lohara Extension Coal
      Block to APML has been specifically made to meet the coal requirements
      of their 1000 MW power plant in District Gondia, Maharashtra. It is,
      thus, clear that the bid submitted by the appellant on the cut-off date
      was on the basis of the assurance that the coal would be available to it
      from Lohara Coal Blocks. Had the notification dated 5th May 2010 not
H     been issued, APML could have utilized the coal from Lohara Coal Blocks
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                          665
   ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]

which was allotted to it by MoC. Apart from that, it is to be noted that        A
MSEDCL was a part of the Expert Committee which was constituted
by MERC vide its order dated 21st August 2013. Having participated in
the proceedings of the meeting of the Expert Committee, MSEDCL
cannot be permitted to take a stand contrary to the decision of the said
Expert Committee.
                                                                                B
        47. It is further to be noted that deallocation of Lohara Coal Blocks
was not on account of any fault of APML and this is recognized by CIL
itself, inasmuch as it has returned the Bank Guarantee which was
furnished by APML.
      48. We find that no interference would be warranted with the              C
concurrent findings of MERC and APTEL that deallocation of Lohara
Coal Blocks would amount to ‘Change in Law’ event as defined under
the PPA.
      49. Insofar as methodology is concerned, APTEL has referred to
the report of the Expert Committee appointed by MERC, which                     D
recommended determination of the price of coal from Lohara Coal Blocks
using “transfer pricing method” which is one of the commonly used
methods. It has accepted the report of the Expert Committee which
provided a reasonable methodology to arrive at the cost of mining from
Lohara Coal Blocks. It will be relevant to refer to the following
paragraphs of the impugned judgment and order:                                  E

      “8.9 We also observe that MSEDCL ought not to cast aspersions
      on such use of methodology of transfer pricing to deduce/determine
      the coal cost. Expert Committee Report was furnished after
      carrying out a detailed exercise of analysing all relevant technical,
      commercial, and financial aspects through a consultative process.         F
      The Expert Committee had also appointed external industry experts
      i.e. legal consultant, financial experts and independent auditors.
      Admittedly, the Expert Committee took cognizance of view of all
      the stakeholders (including MSEDCL) and it is not the case of
      MSEDCL that it was not heard before submission of the Report              G
      to MERC. In fact, we are mindful of the fact that the cover letter
      submitted to MERC records MSEDCL representative being one
      of the members which submitted the Report. As such, we see no
      reason why the recommendations of the Expert Committee cannot
      be relied upon.
                                                                                H
666      SUPREME COURT REPORTS                         [2023] 7 S.C.R.


A     8.10 It is also not a case where MSEDCL produced any document
      to contradict such determination of Lohara coal cost by Expert
      Committee. We therefore hold that MERC ought to have conducted
      a prudence check to arrive at a conclusion regarding the
      correctness of the figures so derived/determined towards coal
      costs by the Expert Committee. Prudence check, however, does
B
      not mean taking linkage coal cost as the base to grant or determine
      change in law compensation to Adani. The MERC clearly fell in
      error on this issue.
      8.11 The MERC’s erroneous approach erodes the restitutionary
      principle enshrined under Article 13 of the PPA. In fact, Adani
C     submitted that the Lohara coal cost cross-subsidizes fuel cost from
      Linkage portion, which has also been noted by the Expert
      Committee in its Report, but ignored by MERC. MSEDCL has
      not disputed this fact.
      8.12 The Expert Committee Report further notes that based on
D     the said cost parameters, Adani had arrived at two different bid
      streams for each of the fuel source (i.e. captive coal and linkage
      coal). The overall bid numbers were based on a weighted average
      of the individual bid streams. Observing thus, in Chapter 7, the
      Expert Committee suggested MERC to consider the Lohara coal
E     cost to be considered as the base for restituting Adani. Expert
      Committee gave the following rationale for the recommended
      methodology:
         “7.1 ... The company had entered into a PPA based on the
         assurance of one of the instrumentality of GoI to provide the
F        coal mine. Therefore, other instrumentality of a state
         government may need to consider the fact of subsequent non-
         availability of coal mine. This fact has been acknowledged by
         MERC….”
      8.13 We are in agreement with this rationale. This rationale
G     conforms to the Tribunal’s findings in the judgment dated
      14.09.2019 (Appeal No 202 of 2018 & 305 of 2018) (Adani
      Rajasthan judgment) wherein it was held that:
         “11.13. The purpose of change in law relief/compensation is to
         restore the affected party to the same economic position as if
         the change in law had not occurred. In the instant case, this
H
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                        667
   ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]

       would involve compensating Adani Rajasthan for the cost                A
       incurred in purchasing alternate coal to meet the non-availability
       of domestic coal promised under the NCDP 2007. The MoP
       letter of 31.07.2013 as well as the Revised Tariff Policy of
       2016 support the principle of compensation to the generators
       for the additional cost incurred in procuring alternate coal. The
                                                                              B
       methodology proposed by Adani Rajasthan prima facie appears
       to be consistent with the principle/basis of compensation for
       shortfall/non-availability of domestic coal given by the MoP
       and we do not find any reason to interfere with the same.”
    8.13 In the aforesaid case, the principle which was considered by
    us is that to restore the affected party to the same economic             C
    position as prevailing at the time of bid submission, the affected
    party shall be compensated for any additional cost incurred in
    procuring alternate coal to mitigate the nonavailability/shortfall of
    coal from the bid-identified source. Since the bid identified source
    of coal in the aforesaid case was linkage coal, the compensation          D
    allowed by the Tribunal was the difference between alternate
    coal cost and linkage coal cost. The formula for such computation
    is: Compensation = A - B [where ‘A’ is cost of alternate coal and
    ‘B’ is cost of coal from the bid-identified source of fuel i.e. linkage
    coal.] Here, we find it important to note that the methodology
    approved in Adani Rajasthan Judgment has not been interfered              E
    with by the Hon’ble Supreme Court in its order dated 31.08.2020
    in Jaipur Vidyut Vitran Nigam v. Adani Power Rajasthan Limited
    and Anr. (Civil Appeal No. 8625-8626 of 2019).
    8.14 Applying the same ratio as held in Adani Rajasthan Judgment,
    the formula for compensation for non-availability of coal from            F
    Lohara Coal Blocks should have been Compensation = A - B
    [where, ‘A’ is cost of alternate coal and ‘B’ is cost of coal from
    the bid-identified source of fuel i.e. Lohara Coal Blocks.]
    Considering linkage coal cost as base will not restitute Adani to
    the same economic position as if no change in law had occurred            G
    and thus runs contrary to the mandate laid down by the Energy
    Watchdog Judgment, the Uttar Haryana Judgment and the revised
    Tariff Policy 2016.
    8.15 Adani further prayed before to direct MSEDCL that in so
    far as the costs incurred towards transportation of coal from the         H
668             SUPREME COURT REPORTS                            [2023] 7 S.C.R.


A           Lohara Coal Blocks to Tiroda TPS is concerned the same may be
            considered based on applicable Railway Freight with applicable
            taxes and duties, while determining the landed cost of coal from
            the Lohara Coal Blocks. We are in agreement with this contention.
            It is no longer res integra that landed cost of coal includes
            transportation costs. Supreme Court’s judgment in Nabha Power
B
            Ltd. vs. Punjab State Power Corp. Ltd. (2018) 11 SCC 508 is
            locus classicus on the subject wherein it was held that landed
            costs cannot exclude transportation costs viz.:-
                “64. We fail to appreciate as to how these costs can be
                excluded, as the transportation costs to the project site have to
C               be compensated to the appellant. It is not qualified by the
                methodology of transfer, i.e., railways or road. It is also a matter
                of necessity, since the railway siding had not reached the project
                site due to some complications in acquisition of land. It is really
                the transportation cost from point to point which would be
D               involved and the mere mention in the RFP under project related
                activity/milestone about Railway siding and the Railway lines
                from nearby station to site cannot imply that the Railways is
                the only mode of transportation when the siding has not been
                made, albeit on account of land acquisition problems.”
E           8.16 We, therefore, hold that MSEDCL ought to pay Lohara coal
            cost as base (including transportation costs) while compensating
            Adani for the change in law events. This issue is decided
            accordingly and the Impugned Order on this issue is set aside.”
              50. It could thus be seen that the finding of APTEL is based on
F     the report of the Expert Committee, which was ignored by MERC. The
      Expert Committee had found that APML had entered into a PPA based
      on the assurance of an instrumentality of the Government of India that
      coal would be provided to it from the Lohara Coal Blocks. However, on
      account of the reasons that have been elaborately discussed, Lohara
      Coal Blocks, which was allocated to APML, came to be deallocated for
G     no fault on the part of APML. It is to be noted that the Expert Committee,
      while arriving at its finding, had also appointed external industry experts,
      i.e. legal consultant, financial experts and independent auditors. It is
      worthwhile to mention that one of the Members of the said Expert
      Committee was a representative of MSEDCL. What has been granted
H     under the said methodology is the additional cost of transport which
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v.                            669
   ADANI POWER MAHARASHTRA LTD. [B. R. GAVAI, J. ]

APML would be required to incur for transporting the coal from other              A
locations on account of deallocation of Lohara Coal Blocks. We, therefore,
find no reason to interfere with the said finding with regard to
methodology of arriving at the compensation payable on account of
‘Change in Law’ event.
       51. The appeals are, therefore found to be without merit and, as           B
such, are dismissed.
       52. Pending application(s), if any, shall stand disposed of. No costs.

Divya Pandey                                                 Appeals dismissed.
(Assisted by : Roopanshi Virang, LCRA)                                            C




                                                                                  D




                                                                                  E




                                                                                  F




                                                                                  G




                                                                                  H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Change in Law"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.