Created byFuzzy Cloud

Supreme Court of India

BSES RAJDHANI POWER LTD. & ANRversusUNION OF INDIA AND ORS

Citation
2025 INSC 937
Decided
6 August 2025
Disposal
Directions issued

Holding

A regulatory asset must not exceed 3% of the approved ARR, must be cost‑reflective, and any new asset must be liquidated within three years, with existing assets to be cleared within seven years, subject to APTEL’s oversight.

Summary

The three Delhi distribution companies (BSES Rajdhani Power Ltd., BSES Yamuna Power Ltd., and Tata Power Delhi Distribution Ltd.) challenged the Delhi Electricity Regulatory Commission’s (DERC) tariff orders that created and perpetuated a large regulatory asset to bridge revenue gaps, which had ballooned to over Rs 27,200 crore by March 2024. The Court examined the legal nature of a regulatory asset, its permissible limits, and the duties of regulatory commissions under the Electricity Act, 2003, the National Tariff Policy, and the newly introduced Rule 23 of the Electricity (Amendment) Rules, 2024. It held that tariff must be cost‑reflective, a regulatory asset may not exceed 3% of the approved Annual Revenue Requirement, and any new asset must be liquidated within three years, while existing assets must be cleared within seven years. The Court emphasized the accountability of the commissions and the extraordinary powers of the Appellate Tribunal for Electricity (APTEL) under Section 121 to enforce compliance. Accordingly, the Court issued detailed directions for the liquidation roadmap, audit of the asset, and mandated APTEL’s suo motu monitoring, disposing of the writ petitions and related civil appeals.

Issues considered

  • The legal status and definition of a regulatory asset in tariff determination
  • Whether the creation and continuation of the regulatory asset by DERC complied with the Electricity Act, National Tariff Policy and Rule 23
  • The permissible percentage and time‑frame for creation and liquidation of a regulatory asset
  • The accountability of regulatory commissions and the powers of APTEL under Section 121 to enforce compliance

Legislation cited

Headnote

Issue for Consideration Legal position and status of a regulatory asset; its position in the regulatory regime for determination of tariff; the rights and liabilities of stakeholders; consequences of regulatory failure to manage the regulatory asset as a reasonable measure; powers of the APTEL and this Court to ensure accountability and restitution. Headnotes† Electricity Law – Electricity Act, 2003 – Electricity Rules, 2005 – “Regulatory asset” – Delhi Electricity Regulatory Commission (DERC) adopted Multi Year Tariff

Subjects

Regulatory assetElectricityTariffTariff determinationTariff for retail supply of electricityCreation, continuation and liquidation of the regulatory assetElectricity is a public goodIncrease in quantum of regulatory assetLiquidation of regulatory assetNational Tariff PolicyNational Electricity PolicyElectricity RulesTariff Determination RegulationsRegulatory CommissionsGeneration, transmission, and distribution of electricityStatutory regulatorsEquitable distributionRegulatory failureRegulatory captureRegulatory functionPower distribution companiesRights and liabilities of the stakeholdersRegulatory dutiesGood governance of the electricity sectorIntangible assetUncovered revenue gap or revenue shortfallDistribution licenseeBulk procurement and bulk supply of powerDeficit Recovery SurchargeFuel price adjustment chargePower Purchase Adjustment ChargeDraft RERC (Terms and Conditions for Determination of Tariff) Regulations, 2025National Electricity Plan

Judgment

          [2025] 8 S.C.R. 1875 : 2025 INSC 937

            BSES Rajdhani Power Ltd. & Anr.
                           v.
                Union of India and Ors.
               (Writ Petition (C) No. 104 of 2014)
                          06 August 2025
           [Pamidighantam Sri Narasimha and
                  Sandeep Mehta, JJ.]


                      Issue for Consideration
Legal position and status of a regulatory asset; its position in the
regulatory regime for determination of tariff; the rights and liabilities
of stakeholders; consequences of regulatory failure to manage
the regulatory asset as a reasonable measure; the appellate and
review powers of the APTEL and this Court to ensure accountability
and restitution.

                             Headnotes†
Electricity Law – Electricity Act, 2003 – Electricity Rules,
2005 – “Regulatory asset” – Delhi Electricity Regulatory
Commission (DERC) adopted Multi Year Tariff framework
in generation, transmission, and distribution businesses
to bring certainty regarding tariff – A regulatory asset was
first created by the DERC in various tariff orders wherein it
introduced the regulatory asset as a mechanism to bridge the
revenue gap in the tariff order for FY 2004-05 – Over the years,
there was an increase in the quantum of the regulatory asset
across all three distribution companies before this Court –
DERC also provided for carrying costs on the regulatory
asset to each distribution company, which further contributed
to its ballooning – Various measures were also introduced
by DERC for liquidation of regulatory asset – Challenge by
the three distribution companies supplying electricity to
consumers in the NCT of Delhi, to the manner in which the
DERC has determined the tariff for retail supply of electricity
over the years, leading to the creation and continuation of a
“regulatory asset” – As on 31.03.2024, the regulatory asset
including carrying costs totally amounted to Rs. 27,200.37
crores across all three distribution companies – Directions
issued:
1876                                                         [2025] 8 S.C.R.

                         Supreme Court Reports


    Held: 1.1 Tariff shall be cost-reflective – Revenue gap between the
    approved Annual Revenue Requirement (ARR) and the estimated
    annual revenue from approved tariff may be in exceptional
    circumstances – The regulatory asset should not exceed a
    reasonable percentage, which percentage can be arrived on the
    basis of r.23 of the Electricity Rules that prescribes 3% of the ARR
    as the guiding principle. [Paras 71 (i)-(iii)]
    1.2 If a regulatory asset is created, it must be liquidated within
    a period of 3 years, taking r.23 as the guiding principle – The
    existing regulatory asset must be liquidated in a maximum of 4
    years starting from 01.04.2024, taking r.23 as the guiding principle.
    [Paras 71 (iv)-(v)]
    1.3 Regulatory Commissions must provide the trajectory and
    roadmap for liquidation of the existing regulatory asset, which will
    include a provision for dealing with carrying costs – They must
    also undertake strict and intensive audit of the circumstances in
    which the distribution companies have continued without recovery
    of the regulatory asset. [Para 71 (vi)]
    1.4 Regulatory Commissions shall in general follow the principles
    governing creation, continuation and liquidation of the regulatory
    asset, as laid down in paragraph 70 of the present judgment, and
    also abide by the directions of the APTEL summarised in paragraph
    69.8. [Para 71 (vii)]
    1.5 APTEL shall invoke its powers u/s.121 and issue such orders,
    instructions or directions as it may deem fit to the Regulatory
    Commissions for performance of their duties with respect to
    regulatory asset as enunciated in this judgment and as per the
    orders of the APTEL in O.P. No. 1/2011 dtd. 11.11.2011 and O.P.
    Nos. 1 and 2/2012 dtd. 14.11.2013. [Para 71 (viii)]
    1.6 APTEL shall register a suo moto petition u/s.121 of the Act to
    monitor implementation of directions (v) and (vi) till the conclusion
    of the period mentioned therein. [Para 71 (ix)]

    Electricity Law – Electricity Act, 2003 – Concept of a regulatory
    asset, explained – Principles governing creation, continuation
    and liquidation of the regulatory asset – In the context of
    creation, management and liquidation of a regulatory asset,
    the Regulatory Commissions are bound by the mandate
    of Electricity Act, National Electricity Policy, National Tariff
[2025] 8 S.C.R.                                                               1877

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


     Policy, Electricity Rules, the Tariff Determination Regulations
     applicable at the relevant period, and the precedents of the
     APTEL:
     Held: A “regulatory asset” in the context of tariff determination
     for electricity utilities is an intangible asset that is created by the
     Regulatory Commissions in recognition of an uncovered revenue
     gap or revenue shortfall when a distribution licensee could not
     fully recover the costs reasonably incurred by it through revenue
     from tariff – This portion of the revenue requirement is not included
     while determining the tariff for the particular year – Rather, the
     distribution company is entitled to receive or recover such revenue
     in the future, over a period of time. [Para 5]
     1.2 It is generally created when the projected revenue based on
     the determined tariff is significantly lower than the revenue required
     by the distribution company to recover reasonably-incurred costs
     as well as for return on investment – Another situation requiring
     the creation of a regulatory asset is at the time of truing up, if
     the actual revenue realisation from tariffs is much lesser than the
     Annual Revenue Requirement (ARR). [Para 6]
     1.3 This revenue gap can be recovered through government
     subsidies or by increasing the tariff – However, the latter may lead
     to a tariff shock to consumers in a given year – Hence, to protect
     consumer interests, the Regulatory Commission may choose to
     direct recovery of only some portion of the gap while creating a
     regulatory asset for the remaining portion, which can be recovered
     in the subsequent years. [Para 7]
     1.4 The creation and continuation of a regulatory asset is neither
     a statutory concept nor a power granted under the Electricity Act –
     Rather, it is a measure adopted by the Regulatory Commissions,
     which are statutory bodies, in exercise of their powers and functions
     under the Act. [Para 8]
     1.5 In the context of creation, management and liquidation of a
     regulatory asset, the Regulatory Commissions are bound by the
     mandate of the Electricity Act, the National Electricity Policy, the
     National Tariff Policy, the Electricity Rules, the Tariff Determination
     Regulations applicable at the relevant period, and the precedents of
     the APTEL – Law governing creation, continuation and liquidation
     of regulatory asset, summarized. [Paras 67-67.4]
1878                                                            [2025] 8 S.C.R.

                          Supreme Court Reports


    Electricity Law – Electricity Act, 2003 – Constitution of India –
    Art.39 – Position of regulatory asset in the regulatory regime
    for determination of tariff – Duties and accountability of the
    regulators- the Regulatory Commissions – Powers of the
    Appellate Tribunal for Electricity to avert a regulatory failure:
    Held: 1.1 Electricity is a public good – Its generation, transmission,
    and distribution are statutorily regulated to ensure access to supply,
    on a non-rival and non-exclusive basis – Being a material resource
    within Art.39 of the Constitution of India, Part-IV of the Constitution
    must inform the generation, transmission, and distribution of
    electricity. [Paras 70 I-II]
    1.2 The statutory regulators, i.e. the Central and State Regulatory
    Commissions alongwith Union and State Governments and other
    stakeholders are equally bound by the mandate under Part-IV of the
    Constitution for its equitable distribution – This duty is predicated
    on the independent, efficient, objective functioning of the electricity
    commissions – They must guard themselves against ‘regulatory
    failure’ and in particular ‘regulatory capture’– The interpretation
    of the powers and function of the Regulatory Commissions have
    to be such that there is no regulatory vacuum, in that there is no
    unallocated residue of power of regulation. [Para 70 III]
    1.3 Tariff determination is a regulatory function and it is the exclusive
    province of the Regulatory Commissions – Tariff determination
    involves multiple variables requiring the regulators to act with
    expertise and also with certain amount of flexibility – Creation
    of regulatory asset is a ‘measure’ that the Commission adopts
    for good governance of tariff – It is also a recognition of revenue
    recoverable by distribution companies, and as such, it is an
    enforceable right, though only through tariff determination for later
    years – This ‘measure’ gives rise to correlative obligations of the
    Regulatory Commissions to manage it efficiently and allow easy
    liquidation. [Para 70 IV]
    1.4 Disproportionate increase and long pending regulatory asset
    depict a ‘regulatory failure’ – It has serious consequences on all
    stakeholders and the ultimate burden is only on the consumer –
    Laws encompassing the creation, continuation, and liquidation of
    a ‘regulatory asset’ are located in the Act, National Tariff Plan and
    Policy, Rules, and Regulations made under the Act, as interpreted
    by the APTEL – The combined effect of this legal regime is the
    statutory obligation on the regulator(s). [Paras 70 V, VI]
[2025] 8 S.C.R.                                                               1879

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


     1.5 Ineffective and inefficient functioning of the Regulatory
     Commissions, coupled with acting under dictation can lead
     to regulatory failure – The commissions are accountable for
     their decisions, and they are subject to judicial review – Apart
     from examining the legality and propriety of the orders of the
     Commissions in appeal, the APTEL has extraordinary powers
     u/s.121 to issue orders, instructions or directions for effective
     enforcement of the regulatory regime – This is one of the
     most important powers allocated to APTEL by the Parliament.
     [Paras 70 VII, VIII]
     1.6 The limits of creation, continuation and liquidation of the
     regulatory asset have been affirmed, the obligations of the
     Regulatory Commissions have been recognised and it is directed
     that they will be accountable and subject to such orders, instructions
     or directions as the APTEL may issue in this regard u/s.121 – The
     regulatory regime under the Act is a complete code enunciating
     rights, prescribing obligations, and laying down the mechanism
     for course correction. [Paras 70 IX, X]
     Electricity Law – Electricity Act, 2003 – ss.62, 61, 79, 86, 6;
     Preamble of the Electricity Act – Tariff determination is governed
     by the Act, which entrusts this function to independent
     Regulatory Commissions – Multiple stakeholders, the Central
     Government, the State Governments, Regulatory Commissions,
     the Appellate Tribunal, statutory policy makers, and the utilities
     collaborate to ensure that the purpose of the Act is subserved
     and, in this endeavour, the Regulatory Commissions share the
     social justice obligations of the State – Tariff fixation takes into
     account multiple variables and requires flexibility – Regulatory
     asset is a measure adopted during tariff fixation that recognises
     right of recovery. [Paras 63.1-65.1]

     Electricity Law – Electricity Act, 2003 – ss.121, 111, 125 –
     Accountability of the Regulatory Commissions:
     Held: A Regulatory Commission must perform its functions as per
     the provisions of the Electricity Act, the National Electricity Policy,
     the National Tariff Policy, the relevant rules and regulations made
     under the Act, and the APTEL’s directions. [Para 68]
     Electricity Law – Electricity Act, 2003 – Factors leading to an
     unmanageable regulatory asset, and consequent ‘regulatory
     failure’, enumerated. [Paras 66-66.1]
1880                                                        [2025] 8 S.C.R.

                        Supreme Court Reports


    Electricity Act, 2003 – ss.110, 11, 121 – Powers of APTEL –
    Significance of s.121 in the context of the facts of the present
    writ petitions and civil appeals, explained – Performance of
    DERC, a classic case of ‘regulatory failure’:
    Held: Regulatory Commissions must call for ARR, ensure that
    tariffs are determined, and that truing up is conducted in a timely
    manner, by exercising suo motu powers if necessary – In case of
    non-compliance with these directions, the APTEL has the power and
    duty to call for an explanation, ensure accountability, and monitor
    compliance by the Regulatory Commissions – Similarly, the APTEL
    must exercise its powers u/s.121 to ensure that the legal principles
    on regulatory asset laid down by us in paragraph 67.3 hereinabove
    are complied with by the Regulatory Commissions, and it must
    monitor the same – In case of non-compliance, the APTEL must
    issue such orders, directions, or instructions to the Commissions
    as may be necessary to hold them accountable [Paras 69-69.9]
    Electricity Law – Electricity Act, 2003 – Salient features –
    Discussed. [Para 32]

    Words and Phrases – Electricity Law – Revenue Assets –
    Meaning of – Discussed:
    Held: ‘Revenue assets’ are costs incurred by power distribution
    companies that are recognised as recoverable from consumers
    in future tariffs but are not immediately recovered in the current
    bills. [Para 65]

                             Case Law Cited
    Tata Power Co. Ltd. v. Reliance Energy Ltd. [2009] 9 SCR 625 :
    (2009) 16 SCC 659; BSES Rajdhani Power Ltd. v. Delhi Electricity
    Regulatory Commission [2022] 14 SCR 790 : (2023) 4 SCC 788;
    PTC India Ltd. v. Central Electricity Regulatory Commission [2010]
    3 SCR 609 : (2010) 4 SCC 603; Hindustan Zinc Ltd. v. Rajasthan
    Electricity Regulatory Commission [2015] 7 SCR 1104 : (2015)
    12 SCC 611; West Bengal Electricity Regulatory Commission v.
    CESC Ltd. (2002) 8 SCC 715; Kerala State Electricity Board Ltd. v.
    Jhabua Power Ltd. [2024] 9 SCR 971 : 2024 SCC OnLine SC
    2819; Tata Power Co. Ltd. v. Maharashtra Electricity Regulatory
    Commission [2022] 19 SCR 620 : (2023) 11 SCC 1; K.C. Ninan v.
    Kerala State Electricity Board [2023] 9 SCR 637 : (2023) 14 SCC
    431; Transmission Corporation of Andhra Pradesh Ltd. v. Sai
[2025] 8 S.C.R.                                                               1881

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


     Renewable Power (P) Ltd. [2010] 8 SCR 636 : (2011) 11 SCC 34;
     Vijay Rajmohan v. CBI [2022] 19 SCR 563 : (2023) 1 SCC 329;
     SEBI v. Mega Corporation [2022] 2 SCR 546 : (2023) 12 SCC
     802; Lifecare Innovations Pvt. Ltd. v. Union of India 2025 INSC
     269 : [2025] 2 SCR 727; 7 Gulf Goans Hotels Co. Ltd v. Union of
     India [2014] 10 SCR 536 : (2014) 10 SCC 673; Bennett Coleman
     & Co. v. Union of India [1973] 2 SCR 757 : (1972) 2 SCC 788; In
     Re: T.N. Godavarman Thirumulpad v. Union of India, 2024 INSC
     78 : [2024] 1 SCR 1194 – referred to.
     Tamil Nadu Electricity Consumers’ Association v. Tamil Nadu
     Electricity Board, Appeal Nos. 192 and 206 of 2010, APTEL
     order dated 28.07.2011 – referred to.

                                 List of Acts
     Electricity Act, 2003; Delhi Electricity Reform Act, 2000 and the Delhi
     Electricity Reform (Transfer Scheme) Rules, 2001; DERC (Terms
     and Conditions for Determination of Wheeling Tariff and Retail
     Supply Tariff) Regulations, 2007; DERC (Terms and Conditions
     for Determination of Wheeling Tariff and Retail Supply Tariff)
     Regulations, 2011; Electricity (Amendment) Rules, 2024; Electricity
     Rules, 2005; CERC (Unscheduled Interchange charges and related
     matters) (Amendment) Regulations, 2010; Electricity (Late Payment
     Surcharge) Rules, 2022; Indian Electricity Act, 1910; Electricity
     (Supply) Act, 1948; Electricity Regulatory Commissions Act, 1998;
     Delhi Electricity Reforms Act, 2000; DERC (Terms and Conditions
     for Determination of Tariff) Regulations, 2017; Constitution of India.

                              List of Keywords
     Regulatory asset; Electricity; Tariff; Tariff determination; Tariff for
     retail supply of electricity; Creation, continuation and liquidation
     of the regulatory asset; Electricity is a public good; Increase in
     quantum of regulatory asset; Liquidation of regulatory asset; BSES
     Rajdhani Power Ltd., BSES Yamuna Power Ltd., and Tata Power
     Delhi Distribution Limited; Distribution companies; DISCOMS;
     National Tariff Policy, 2006; National Electricity Policy; National
     Tariff Policy; Electricity Rules; Tariff Determination Regulations;
     National Electricity Policy, 2005; National Tariff Policy, 2016;
     Bridging revenue gap; Revenue assets; Regulatory Commissions;
     Generation, transmission, and distribution of electricity; Statutory
     regulators; Equitable distribution; Regulatory failure; Regulatory
1882                                                         [2025] 8 S.C.R.

                         Supreme Court Reports


    capture; Regulatory function; Power distribution companies;
    Rights and liabilities of the stakeholders; Regulatory duties; Good
    governance of the electricity sector; Intangible asset; Uncovered
    revenue gap or revenue shortfall; Distribution licensee; Distribution
    company; Bulk procurement and bulk supply of power; Deficit
    Recovery Surcharge; Fuel price adjustment charge; Power
    Purchase Adjustment Charge; Draft RERC (Terms and Conditions
    for Determination of Tariff) Regulations, 2025; National Electricity
    Plan.

                           Case Arising From
    ORIGINAL/CIVIL APPELLATE JURISDICTION: Writ Petition (C)
    104 of 2014
    Under Article 32 of The Constitution of India
    With
    Civil Appeal No(s). 4010 and 4013 of 2014, Writ Petition (C) No.
    105 of 2014 and Writ Petition (C) No. 1005 of 2021

                        Appearances for Parties
    Advs. for the Petitioners:
    Abhishek Manu Singhvi, Kapil Sibal, Buddy A. Ranganadhan,
    Sr. Advs., Shri Venkatesh, Ms. Kanika Chugh, Asutosh Kumar
    Srivastava, Shryeshth Ramesh Sharma, Bharat Gangadhar, Nihal
    Bhardwaj, Kartikay Trivedi, Aashwyn Singh, Abhishek Nangia,
    Aadarsh Singh, Nitin Saluja, Amit Kapur, Pukhrambam Ramesh
    Kumar, Anupam Varma, Rahul Kinra, Aditya Ajay, Ms. Isnain
    Muzamil, Girdhar Gopal Khattar, Sanjay Nair S, Ms. Manisha
    Singh, Ms. Shefali Tripathi, Aditya Gupta, Karun Sharma, Ms.
    Rajkumari Divyasana, Amit Kapur, Anupam Varma, Rahul Kinra,
    Aditya Gupta, Aditya Ajay, Sanjay Nair S., Ms. Isnain Muzamil,
    Ms. Manisha Singh, Girdhar Gopal Khattar, Mrs. Shefali Tripathi,
    Sanjay Nair S, Ms. Manish Singh, Ms. Shefali Tripathi, Avinash
    Das, Sidharth Sethi.
    Advs. for the Respondent:
    R. Venkataramani, Attorney General for India, K M Nataraj, A.S.G.,
    Lokesh Sinhal, Sr. A.A.G., S. Wasim A. Qadri, Nikhil Nayyar,
    Mrs. Shirin Khajuria, Sr. Advs., Gurmeet Singh Makker, Piyush
    Beriwal, Shyam Gopal, Ms. Shradha Deshmukh, Ms. Chinmayee
    Chandra, Rajat Nair, K. V. Mohan, Satya Mitra, Vivek Singh, Ritik
[2025] 8 S.C.R.                                                          1883

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


     Dwivedi, Siddhartha Chowdhury, Anand Ganesan, Ms. Swapna
     Seshadri, Pramod Dayal, Nikunj Dayal, Utkarsh Singh, Lakshmi
     Raman Singh, Tamim Qadri, Chitvan Singhal, Saeed Qadri,
     Shraveen Kumar Verma, Saahil Gupta, B. Krishna Prasad, Ms.
     Prerna Singh, Guntur Pramod Kumar, Samarth Krishan Luthra,
     Dhruv Yadav, Ms. Pritha Srikumar Iyer, Naveen Hegde, Kshitij
     Maheshwari, Abhyudaya Shishodia, Saumya Sinha, Ms. Saumya
     Sinha, Abhishek Vikas, Adarsh Tripathi, Vikram Singh Baid, Ajitesh
     Garg, Veevak Goel, B. K. Satija, Ms. Pallavi Langar, Vishnu
     Sharma, Sujeet Kumar Chaubey, Ravi Sharma, Aryan Chanda,
     Ms. Bhavana Duhoon, Ms. Swati Tiwari, Naveen Kumar, Ms.
     Stuti Bisht, Nitesh Bhandari, Maitreya, Shourajeet Chakravarty,
     Ms. Aprajita Bhardwaj, Prabhat Kumar Rai, Aditya Goyal, Ujjawal
     Kumar Rai, Ms. Esha Kumar, Ms. Nidhi Singh, Utkarsh Chandra,
     Ms. K. Enatoli Sema, Amit Kumar Singh, Ms. Chubalemla Chang,
     Prang Newmai, Harshad V. Hameed, Dileep Poolakkot, Ms. Ashly
     Harshad, Nitin Gaur, Anshuman Ashok, Anshuman Ashok, Sagar
     Parashar, Anshul Singh, Shashank Shekhar Singh, Abhinav Singh,
     Aaditya Aniruddha Pande, Siddharth Dharmadhikari, Sourav
     Singh, Mayank Sapra, Ms. Lalima Das, Karan Sharma, Ms.
     Baani Khanna, Sameer Abhyankar, Mrs. Ayushi Bansal, Rahul
     Kumar, Ms. Yashika Sharma, Krishna Rastogi, Aakash Thakur,
     M/s. Ag Veritas Law, Gaichangpou Gangmei, Arjun D. Singh,
     Ms. Nisha Pandey, Yimyanger Longkumer, Maitreya Mahaley,
     J. Prasad, Kunal Chatterji, Ms. Maitrayee Banerjee, Rohit
     Bansal, Pashupathi Nath Razdan, Astik Gupta, Ms. Mandakini
     Ghosh, Nikilesh Ramachandran, Ms. Suparna Srivastava, Ms.
     Arshiya Sharma, Akshay Amritanshu, Nikunj Gupta, Ms. Pragya
     Upadhyay, Ms. Drishti Saraf, Ms. Aakanksha, Pradeep Misra,
     Daleep Dhyani, Suraj Singh, Aditya Singh-1, Shashi Bhushan
     Kumar, Dinesh Kumar Prasad, Ms. Advaita Bhushan, Darpan Km,
     Ms. Amrita Sharma, Rajat Jonathan Shaw, Durgha Prakash, Ms.
     Easha Chandhok, Ms. Rashi Bansal, M. T. George, C. K. Rai,
     Mrs. Anuradha Roy, Vinay Kumar Gupta, Sahil Chandra, Rutwik
     Panda, Ms. Nikhar Berrry, Ms. Anshu Malik, Ms. Nikhar Berry, Ms.
     Sunieta Ojha, Ms. Gargi Kumar, Rajeev Kumar Panday, Zoheb
     Hossain, Somanadri Goud Katam, Rajat Srivastava, Sirajuddin,
     Sriram Krishna, Ms. Anupama Dhurve, B. K. Satija, Subhash
     Chandran K.R. Ms. Krishna L.R., Ankit Roy, Chinmoy Sharma, Ms.
     Diksha Rai, Piyush Vyas, Purvat Wali, Irfan Hasieb, Krishnajyoti
     Deka, Vijay Deora.
1884                                                                                          [2025] 8 S.C.R.

                                      Supreme Court Reports


                        Judgment / Order of the Supreme Court

                                                 Judgment

                                          Table of Contents*

       1.      Introduction ...................................................................................       4

       2.      Concept of a Regulatory Asset .....................................................                    7

       3.      Facts. .............................................................................................   9

       4.      Submissions of Parties ................................................................. 11

       5.      Impleadment of the State Commissions and Governments ......... 20

       5(i). Affidavits by State Commissions ................................................... 21

       5(ii). Affidavits by State Governments ................................................... 25

       6.      Law Governing the Electricity Sector Prior to 2003 ..................... 26

       7.      Electricity Act, 2003 ...................................................................... 28

       8.      Provisions of the Electricity Act relating to determination of Tariff ... 31

       9.      Provisions of Act, Policies, Rules, Regulations, and Orders having
               a bearing on creation of a Regulatory Asset ................................. 35

       9(i). National Electricity Policy, 2005 .................................................... 35

       9(ii). National Tariff Policy, 2006 ............................................................ 36

       9(iii). DERC Tariff Determination Regulations, 2007 .............................. 37

       9(iv). DERC Statutory Advice dated 15.12.2010 .................................... 38

       9(v). Ministry of Power’s Letter to the APTEL ....................................... 40

       9(vi). APTEL’s Order dated 11.11.2011 .................................................. 40

       9(vii). DERC Tariff Determination Regulations, 2011 ............................ 41

       9(viii). DERC’s Tariff Order dated 26.08.2011 (FY 2011-12) .................. 42

       9(ix). DERC’s MYT Order dated 13.07.2012 (FY 2012-15) .................. 43


* Ed. Note: Pagination as per the original Judgment.
[2025] 8 S.C.R.                                                                                         1885

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.



     9(x). DERC’s Statutory Advice dated 01.02.2013 ................................ 43

     9(xi). DERC’s Tariff Order dated 31.07.2013 (FY 2013-14) ................. 44

     9(xii). APTEL’s Order dated 14.11.2013 ................................................ 45

     9(xiii). APTEL’s Order dated 11.03.2014 ............................................... 46

     9(xiv). National Tariff Policy, 2016 .......................................................... 47

     9(xv). DERC Tariff Determination Regulations, 2017 ............................ 48

     9(xvi). Ministry of Power’s Affidavit dated 10.08.2022 ........................... 49

     9(xvii). Ministry of Power’s Affidavit dated 12.12.2022 ........................... 51

     9(xviii). Electricity (Amendment) Rules, 2024 introducing Rule 23 ........ 52

     9(xix). DERC’s Order dated 19.07.2024 (true-up till FY 2020-21) ....... 53

     10.    Analysis ......................................................................................... 53

     10(i). Electricity is a public good and is regulated under the Act ........ 54

     10(ii). Tariff determination is governed by the Act, which entrusts this
             function to independent Regulatory Commissions ..................... 54

     10(iii). Collaborative effort of the Regulatory Commissions to balance
              social justice obligations with efficiency ...................................... 57

     10(iv). Tariff fixation takes into account multiple variables and requires
             flexibility. Regulatory asset is a measure adopted during tariff
             fixation that recognises right of recovery .................................... 58

     10(v). Factors leading to an unmanageable regulatory asset, and
            consequent ‘regulatory failure’ .................................................... 59

     10(vi). Law that governs creation, continuation and liquidation of
             regulatory asset .......................................................................... 62

     10(vii). Accountability of the Regulatory Commissions .......................... 67

     10(viii). Powers of the APTEL ................................................................. 69

     11.    Conclusions ................................................................................... 77

     12.    Directions ....................................................................................... 80
1886                                                                              [2025] 8 S.C.R.

                                      Supreme Court Reports


       1.      Introduction.
1.     We are entertaining these writ petitions1 and civil appeals2 only for
       examining a limited question as to the law that governs the creation
       of a “regulatory asset” during the process of tariff determination by
       the Electricity Regulatory Commissions, its impact on the rights and
       liabilities of the stakeholders, the limits within which it can be operated,
       and finally the regulatory duties that it invokes for the Regulatory
       Commissions. We also clarify that through these proceedings, we
       are not determining the rights and liabilities of the parties, which
       will anyways be considered in the pending civil appeals against the
       orders of the Appellate Tribunal of Electricity3.
2.     In these writ petitions and civil appeals, the three distribution companies
       that supply electricity to consumers in the National Capital Territory
       of Delhi4, namely BSES Rajdhani Power Ltd.5, BSES Yamuna Power
       Ltd.6, and Tata Power Delhi Distribution Limited7, have challenged
       the manner in which the Delhi Electricity Regulatory Commission8
       has determined the tariff for retail supply of electricity over the years,
       leading to the creation and continuation of a “regulatory asset”. The
       prayers in W.P. (C) Nos. 104 and 105/2014 by BRPL and BYPL9 are
       similar, which we may formulate as follows:
       i.      To hold and declare that the petitioners are entitled to prudently
               incurred cost and allowances in terms of Sections 61 and 62
               of the Electricity Act, 200310 and Multi Year Tariff Regulations;
       ii.     To direct the DERC to give effect to the deferred cost creating
               a regulatory asset in accordance with Para 8.2.2 of the National
               Tariff Policy;


1    W.P. (C) No. 104/2014, W.P. (C) No. 105/2014 and W.P. (C) No. 1005/2021 under Article 32 of the
     Constitution.
2    C.A. No. 4010/2014 and C.A. No. 4013/2014 against the order dated 11.03.2014 passed by the Appellate
     Tribunal for Electricity in I.A Nos. 364-365/2013 in Appeal Nos. 265-266/2013.
3    Hereinafter “APTEL”.
4    Hereinafter “NCT of Delhi”.
5    Hereinafter “BRPL”.
6    Hereinafter “BYPL”.
7    Hereinafter “TPDDL”.
8    Hereinafter “DERC”.
9    Hereinafter collectively referred to as “BSES Discoms”.
10   Hereinafter “the Electricity Act”.
[2025] 8 S.C.R.                                                                                   1887

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


      iii.    To direct the respondent-generating companies to not disconnect
              or discontinue power supply or take any other coercive steps till
              this Court determines an appropriate mechanism for adjustment
              of dues owed by the distribution companies from the amounts
              due and owed to them; and
      iv.     To protect their investment and assured return from the licensed
              business.
3.    TPDDL has also filed W.P. (C) No. 1005/2021, where it has prayed
      for the following reliefs:
      i.      To direct DERC to recognise its regulatory asset and formulate
              and implement a clear roadmap for the liquidation of the
              regulatory asset in a time-bound manner of 3 years;
      ii.     In the alternative, to direct DERC to increase the Deficit Recovery
              Surcharge to 20% to amortise the regulatory asset as per the
              National Tariff Policy;
      iii.    To direct DERC to implement various judgments of the APTEL
              in appeals against tariff orders by the DERC.
4.    In order to consider these prayers as well as the maintainability of the
      writ petitions, which has been contested by the respondents, we will
      have to examine the concept of a ‘regulatory asset’ and its creation
      and continuation in the context of the law that may govern it. Further,
      we will also examine whether the law creates any statutory duties
      and whether failure to fulfil the same gives rise to an enforceable
      legal right. For this purpose, we will commence with examining
      the Electricity Act, and the rules, regulations, and policies framed
      thereunder as well as judicial precedents and necessary practices
      for good governance of the electricity sector.

      2.      Concept of a Regulatory Asset.
5.    A “regulatory asset” in the context of tariff determination for electricity
      utilities is an intangible asset that is created by the Regulatory
      Commissions in recognition of an uncovered revenue gap or revenue
      shortfall when a distribution licensee could not fully recover the costs
      reasonably incurred by it through revenue from tariff.11 This portion of


11   See Tamil Nadu Electricity Consumers’ Association v. Tamil Nadu Electricity Board, Appeal Nos. 192 and
     206 of 2010, APTEL order dated 28.07.2011.
1888                                                         [2025] 8 S.C.R.

                          Supreme Court Reports


      the revenue requirement is not included while determining the tariff
      for the particular year. Rather, the distribution company is entitled to
      receive or recover such revenue in the future, over a period of time.
6.    There are several situations and factors leading to the creation of such
      a regulatory asset. It is generally created when the projected revenue
      based on the determined tariff is significantly lower than the revenue
      required by the distribution company to recover reasonably-incurred
      costs as well as for return on investment. When it is not feasible to
      recover this gap either by increasing tariffs or through other means
      such as government subsidy during that year, a regulatory asset
      equivalent to the uncovered expenses is created. Another situation
      requiring the creation of a regulatory asset is at the time of truing
      up, if the actual revenue realisation from tariffs is much lesser than
      the Annual Revenue Requirement12.
7.    This revenue gap can be recovered through government subsidies or
      by increasing the tariff. However, the latter may lead to a tariff shock
      to consumers in a given year. Hence, to protect consumer interests,
      the Regulatory Commission may choose to direct recovery of only
      some portion of the gap while creating a regulatory asset for the
      remaining portion, which can be recovered in the subsequent years.
      At the same time, the financial health and commercial viability of the
      distribution company must be ensured by the Regulatory Commission.
      Hence, the Regulatory Commission must ensure that if a regulatory
      asset is created, the same is recovered in a time-bound manner.
8.    The creation and continuation of a regulatory asset is neither a
      statutory concept nor a power granted under the Electricity Act.
      Rather, it is a measure adopted by the Regulatory Commissions,
      which are statutory bodies, in exercise of their powers and functions
      under the Act. It is hence guided by the legal regime of the Electricity
      Act and the rules, regulations, and policies framed thereunder, along
      with their interpretation in various judicial precedents.

      3.      Facts.
9.    Initially, the Delhi Vidyut Board was responsible for generation,
      transmission and distribution of electricity in NCT of Delhi. With the



12   Hereinafter “ARR”.
[2025] 8 S.C.R.                                                      1889

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


      Delhi Electricity Reform Act, 2000 and the Delhi Electricity Reform
      (Transfer Scheme) Rules, 2001, these functions were unbundled
      and different entities were made responsible for each function. Until
      2007, the Delhi Transco Limited13 was solely responsible for bulk
      procurement and bulk supply of power in Delhi, and all distribution
      companies were required to purchase power from it. After 31.03.2007,
      the responsibility for power purchase in Delhi was transferred to the
      distribution companies.
10. DERC adopted the Multi Year Tariff 14 framework in generation,
    transmission, and distribution businesses so as to bring certainty
    regarding tariff and its annual basis during each control period.
11. A regulatory asset was first created by the DERC in the tariff order
    dated 09.06.2004 for North Delhi Power Limited15 and orders dated
    11.06.2004 for BRPL and BYPL. In these orders, the DERC introduced
    the regulatory asset as a mechanism to bridge the revenue gap in
    the tariff order for FY 2004-05, and it amounted to a total of Rs. 696
    crores across BRPL, BYPL, NDPL and DTL.
12. Over the years, various orders of the DERC determining ARR
    for each year, MYT orders, and truing-up orders demonstrate an
    increase in the quantum of the regulatory asset across all three
    distribution companies before us. The DERC also provided for
    carrying costs on the regulatory asset to each distribution company,
    which further contributed to its ballooning. We are informed that
    as on 31.03.2024, the regulatory asset including carrying costs is
    Rs. 12,993.53 crores for BRPL, Rs. 8419.14 crores for BYPL, and
    Rs. 5,787.70 crores for TPDDL, totally amounting to Rs. 27,200.37
    crores across all three distribution companies. During this time,
    the DERC has taken note of this increase and introduced various
    measures like increasing tariffs, Deficit Recovery Surcharge16, fuel
    price adjustment charge and Power Purchase Adjustment Charge17.
    These measures are byproducts of the regulatory asset and are
    intended for its liquidation.


13   Hereinafter “DTL”.
14   Hereinafter “MYT”.
15   Hereinafter “NDPL”, which is now TPDDL.
16   Hereinafter “DRS”.
17   Hereinafter “PPAC”.
1890                                                          [2025] 8 S.C.R.

                          Supreme Court Reports


13. After setting out the submissions of the parties as well as views of
    various State Commissions and State Governments, we will examine
    framework within which the regulatory asset is created, continued, and
    liquidated. We will refer to the relevant provisions of the Electricity
    Act, National Tariff Policies, the Electricity Rules, DERC’s Tariff
    Determination Regulations, and introduction of various measures by
    the DERC, either as mitigative or alleviative to deal with the problem.
    Following this, we will determine the status of the regulatory asset
    and the consequential directions that may be passed in these writ
    petitions and civil appeals.

     4.     Submissions of Parties.
14. We have heard Mr. Kapil Sibal and Dr. Abhishek Manu Singhvi, learned
    senior counsels and Mr. Amit Kapur, learned counsel for the three
    distribution companies, who are the petitioners and appellants. On
    behalf of the respondents, we have heard Mr. Nikhil Nayyar, learned
    senior counsel for the DERC, Mr. R. Venkataramani, learned Attorney
    General of India for certain generating and transmission companies,
    Mr. K.M. Nataraj, learned ASG for the Ministry of Power, Union of
    India, and Mr. Siddharth Dave and Mr. Shadan Farasat, learned
    senior counsels for the Government of NCT of Delhi.
15. Mr. Sibal made the following submissions:
     i.     Referring to the Statement of Objects and Reasons of the
            Electricity Act, he submitted that the statute intends to distance
            the government from tariff regulation and determination by
            establishing independent regulators, and it aims to encourage
            private sector participation in the electricity sector.
     ii.    Mr. Sibal then referred us to various provisions of the Electricity
            Act, including factors guiding tariff determination under Section
            61, tariff determination for retail supply of electricity under
            Sections 62 and 64, and advance payment of government
            subsidies under Section 65. He also took us through the
            mandatory and advisory functions of the State Commission
            under Section 86, emphasising that the Commission must be
            guided by the policies and plans formulated under the Act in
            discharge of its functions.
     iii.   He then referred us to the relevant portions of the statutory
            advice issued by the DERC to the Government of NCT of Delhi
[2025] 8 S.C.R.                                                         1891

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


              by letters dated 15.12.2010 and 01.02.2013, which we will deal
              with in more detail at a later stage.
      iv.     Referring to Clause 8.2.2 of the National Tariff Policy, 2006,
              he submitted that a regulatory asset must be created only
              in exceptional circumstances that are clearly defined in the
              regulations and that only include natural causes or force
              majeure conditions. Further, that the regulatory asset must be
              recovered in a time-bound manner in 3 years, and preferably
              within the control period. These conditions are also incorporated
              in Regulation 5.42 of the DERC (Terms and Conditions for
              Determination of Wheeling Tariff and Retail Supply Tariff)
              Regulations, 200718 and Regulation 5.40 of the DERC (Terms
              and Conditions for Determination of Wheeling Tariff and Retail
              Supply Tariff) Regulations, 201119, which we will deal with at
              a later stage. Mr. Sibal submitted that these conditions for
              creation of a regulatory asset have not been complied with
              by the DERC.
      v.      He then referred us to the Electricity (Amendment) Rules, 2024
              (notified on 10.01.2024) that inserts Rule 23 in the Electricity
              Rules, 2005, which stipulates various conditions for creation,
              continuation, and recovery of a revenue gap or regulatory
              asset.
      vi.     To conclude, Mr. Sibal submitted that the creation, continuation,
              and expansion of the regulatory asset over the years can be
              attributed to the following causes: (i) assumed power purchase
              cost for tariff determination is lower than the actual cost; (ii)
              assumption of inflated revenue; (iii) tariffs determined by the
              DERC are not cost-reflective; (iv) the orders of the APTEL and
              this Court regarding tariff fixation are not implemented; (v) the
              state government has not paid the subsidy amount in advance
              as per Section 65; (vi) payment of Late Payment Surcharge20
              @ 18% on late payments to the generating companies; and
              (vii) the truing-up exercise is not carried out properly.



18   Hereinafter “Tariff Determination Regulations, 2007”.
19   Hereinafter “Tariff Determination Regulations, 2011”.
20   Hereinafter “LPS”.
1892                                                       [2025] 8 S.C.R.

                         Supreme Court Reports


16. Mr. Amit Kapur, for the BSES Discoms has submitted that currently,
    the regulatory asset is about Rs. 26,000 crores (including the carrying
    cost payable to date). The continuation of the revenue gap, without
    liquidating it in a time-bound manner undermines the very purpose
    of the Electricity Act to promote private sector participation and to
    provide for cost-reflective tariffs. He submits that there is a creeping
    acquisition of private distribution companies due to this.
17. Dr. Singhvi appearing for TPDDL then addressed us and made the
    following submissions:
     i.    To liquidate the regulatory asset, certain measures may be
           taken such as increasing the DRS, increasing tariffs payable
           by consumers, and through government support. Further, there
           must be a fixed timeline for liquidation as the quantum of the
           regulatory asset only increases with the passage of time due
           to accumulation of carrying costs.
     ii.   While the DERC’s roadmap for liquidation submitted before
           this Court estimated recovery of the entire regulatory asset by
           2022, this has not fructified. In this context, he submitted that
           DRS of 8% is wholly inadequate as it is insufficient to even
           meet the carrying cost on the regulatory asset.
18. Mr. Nikhil Nayyar, learned senior counsel appearing on behalf of the
    DERC then addressed us. He took us through the scheme of the
    Electricity Act and its provisions, and also traced the history of the
    creation and continuation of a regulatory asset by the DERC. While
    doing so, he made the following submissions:
     i.    The DERC’s tariff order dated 11.06.2004 shows that the BSES
           Discoms themselves suggested the creation of a regulatory
           asset to enable recovery of the revenue gap over a period of
           time through gradual increase in tariffs.
     ii.   Over the years, the DERC introduced various measures to
           liquidate the regulatory asset, including tariff hikes, 8% DRS,
           carrying cost, fuel purchase adjustment charge, and PPAC.
           Currently, TPDDL, BRPL, and BYPL levy 29.13%, 27.08%,
           and 31.60% PPAC respectively and between FY 2018-19
           to FY 2022-23, they have earned Rs. 3,230.48 crores, Rs.
           4,399.48 crores, and Rs. 2,210 crores through PPAC. The
           DERC also increased the tariff by 50% between FY 2011-15
[2025] 8 S.C.R.                                                          1893

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


            as follows - 22% by order dated 26.08.2011), 23% by order
            dated 13.07.2012, 5% by order dated 31.07.2013, and 8.32%
            by order dated 23.07.2014.
     iii.   However, these measures were not sufficient as between 2007
            and 2012, the power purchase cost, which constitutes 80% of
            the ARR, increased by more than 80% from Rs. 2.86 to Rs.
            5.16 per unit. The regulatory asset ballooned during this period
            due to this unprecedented increase in power purchase costs,
            which is attributable to the increase in coal and gas prices.
            Further, the introduction of CERC (Unscheduled Interchange
            charges and related matters) (Amendment) Regulations, 2010
            prevented the use of UI mechanism for sale of surplus power
            at profitable rates.
     iv.    While the roadmap submitted by the DERC before this Court
            estimated that the regulatory asset would be liquidated by
            2022, this did not materialise for several reasons such as the
            distribution companies not achieving the estimated 15% growth
            rate and carrying cost on the regulatory asset being a compound
            interest that itself amounts to Rs. 8,692 crores across BRPL,
            BYPL, and TPDDL from FY 2012-13 to FY 2019-20, while DRS
            @ 8% led to a collection Rs. 11,073 crores.
     v.     He submitted that the regulatory asset could not be liquidated
            as planned as the amount does not remain static. With each
            tariff order, some portion is recovered while other factors lead
            to an increase in the regulatory asset. Further, considering that
            the roadmap for liquidation was prepared in 2014, it needs to
            be revised.
     vi.    Mr. Nayyar also disputed the maintainability of these writ petitions
            as there is a statutory mechanism under the Electricity Act for
            tariff determination, which is a quasi-judicial exercise by an
            expert body and the scope of judicial review is limited. Further,
            the Act also provides for appealing the DERC’s decision before
            the APTEL under Section 111. Finally, there is no allegation
            regarding violation of any fundamental right for this Court to
            exercise writ jurisdiction.
     vii.   Finally, Mr. Nayyar averred to tariff determination and regulatory
            assets created by other State Commissions. He submitted that
1894                                                        [2025] 8 S.C.R.

                            Supreme Court Reports


              15 states have implemented an automatic pass-through for fuel
              costs, which means that the distribution companies in these
              states can pass on the rise in power purchase costs to the
              consumers. He also submitted that other than Delhi, regulatory
              assets have been created in Tamil Nadu, Rajasthan, Kerala,
              and Maharashtra.
19. We then heard the learned Attorney General for the generating and
    transmission companies namely Indraprastha Power Generation
    Company Limited21, Pragati Power Corporation Limited22, and DTL.
    He submitted that while the DERC has recognised a revenue gap
    for all three distribution companies, BRPL and BYPL are not making
    regular payments to IGPCL, PPCL and DTL, despite making regular
    payments to other power utilities. He also submitted that TPDDL has
    been regularly paying the bill amounts. With regard to non-payment
    by BRPL and BYPL, he submitted that these dues cannot be set-off/
    netted-off/squared off against the unrecovered tariff, which must be
    realised by the distribution companies from consumers in accordance
    with DERC orders. He also submitted that the adjustment of any
    payments against past dues is in accordance with the provisions of
    their power purchase agreements and Rule 4 of the Electricity (Late
    Payment Surcharge) Rules, 2022.
20. We then heard Mr. K.M. Nataraj, learned ASG appearing for the
    Ministry of Power, Union of India. He submitted that a regulatory
    asset is created when State Commission determines tariffs while
    ignoring the principles laid down in Section 61 of the Electricity
    Act, specifically in sub-sections (b), (c), and (d). In such situations,
    the approved tariff and revenue generated from it is lower than the
    actual ARR of the distribution company. Further, the regulatory asset
    is created without following the conditions specified in Clause 8.2.2
    of the National Tariff Policy, 2006 and without a specific time period
    for liquidation. In order to recover this amount, he submits that the
    tariffs may be increased, the state government may provide additional
    subsidies to reduce the burden on the consumers due to increased
    tariffs, and through financial support by the state government. He
    also submitted that liquidation must be in accordance with Rule 23
    of the Electricity (Amendment) Rules, 2024.


21   Hereinafter “IPGCL”.
22   Hereinafter “PPCL”.
[2025] 8 S.C.R.                                                      1895

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


21. Finally, Mr. Shadan Farasat and Mr. Siddharth Dave, learned senior
    counsels for the Government of NCT of Delhi addressed us. They
    submitted that the regulatory asset is not attributable to the subsidies
    granted by the Government and its payments under Section 65 of
    the Electricity Act.
22. By order dated 23.10.2024, this Court directed the Government of
    NCT of Delhi to respond to the subsisting regulatory asset. When
    the matters were listed on 20.11.2024, Mr. Shadan Farasat, learned
    senior counsel appeared for the Government and expressed that the
    Government has not yet taken its decision regarding subsidies and
    creation of the regulatory asset, the reasons for which we directed
    be placed in an affidavit before us. An affidavit dated 06.01.2025
    was filed by the Government of NCT of Delhi indicating that the
    Department of Power had prepared a cabinet note for circulation
    on 29.10.2024, which was circulated for comments. The same
    received concurrence from the Law Department on 01.11.2024
    but the comments of the Finance and Planning Departments are
    awaited. It was also stated that the Government of NCT of Delhi
    is releasing the subsidy amounts without default, and there is no
    relation between the grant of electricity subsidy and accumulation of
    the revenue gap. The amounts payable to the BSES Discoms are
    directly released to IPGCL, PPCL, and DTL for adjustment against
    outstanding dues, in accordance with interim orders of this Court in
    these writ petitions and civil appeals.

     5.    Impleadment of the State Commissions and Governments.
23. After hearing the learned counsels for the parties, by this Court’s
    order dated 23.10.2024 we directed the impleadment of State
    Governments and State Electricity Regulatory Commissions to
    gather their views in light of the large-scale and nation-wide
    implications of creation and continuation of regulatory assets on
    the electricity sector. Subsequently, by order dated 20.11.2024, we
    directed the State Governments and State Commissions to express
    their views through affidavits. Upon perusing these affidavits, the
    position of each state vis-à-vis regulatory assets can be captured
    as follows:

     5 (i). Affidavits by State Commissions.
24. Following is the gist of the affidavits filed by various Commissions.
1896                                                         [2025] 8 S.C.R.

                         Supreme Court Reports


    i.     The State Commissions of Andhra Pradesh, Assam, Haryana,
           Himachal Pradesh, Jharkhand, Madhya Pradesh, Odisha,
           Punjab, Sikkim, Telangana, and Uttar Pradesh have submitted
           that they have not created any regulatory asset at any point
           in time.
    ii.    The Maharashtra Electricity Regulation Commission submits
           that in compliance with Clause 8.2.2 of the National Tariff Policy,
           2016 and Rule 23 of the Electricity (Amendment) Rules, 2024, it
           has not created a regulatory asset since March 2020 in respect
           of any distribution licensee in the state.
    iii.   The Joint Electricity Regulatory Commission for UT of Jammu
           and Kashmir and UT of Ladakh also submits that it has not
           created any regulatory asset since FY 2019-2020 and tariff
           determination is such that the ARR of the distribution companies
           is met from the revenue from consumers and grant-in-aid from
           the UT Government.
    iv.    The Chhattisgarh State Electricity Regulatory Commission
           submits that there was a revenue gap of Rs. 343 crores in
           FY 2011-12, even after tariff increase by 14%, but the same
           was fully apportioned in FY 2012-13 with carrying cost. In FY
           2012-13, there was a cumulative deficit of Rs. 1752 crores
           that was partially apportioned by a 17% tariff increase and the
           remaining revenue gap of Rs. 828 crores was carried forward
           as a regulatory asset, which was subsequently apportioned in
           FY 2013-14 with carrying costs. There was no regulatory asset
           between FY 2013-14 and FY 2015-16. Then in FY 2016-17, the
           State Commission had to allow Rs. 1130.80 crores over and
           above the ARR to comply with an APTEL order. To prevent a
           tariff shock, it allowed recovery of Rs. 370 crores in that year,
           and created a regulatory asset for Rs. 760.80 crores that
           was recovered in FY 2017-18. There was no regulatory asset
           created or carried forward between FY 2017-18 to FY 2019-20.
           In FY 2020-21, considering the COVID-19 pandemic and to
           avoid increasing tariffs, the Commission created a regulatory
           asset of Rs. 213 crores that was recovered in FY 2021-22.
           Post-COVID, the Commission increased tariff by 6.19% and
           2.31%, with no regulatory assets. However, as of FY 2023-24,
           there was a cumulative revenue deficit of Rs. 2924.53 crores
[2025] 8 S.C.R.                                                       1897

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


           as the tariff hikes were insufficient to meet expenditure. The
           Commission implemented various rationalisation measures to
           reduce the regulatory asset to Rs. 2528 crores, which would be
           recovered with carrying cost during the true-up for FY 2023-24
           and tariff determination of FY 2025-26. It also submitted that
           no further regulatory asset has been crated in the tariff order
           dated 01.06.2024 for ARR of FY 2024-25.
     v.    Kerala State Electricity Regulatory Commission has submitted
           that till FY 2022-23, the regulatory asset is Rs. 7123 crores as
           per the Commission’s order dated 25.06.2022. Against this, the
           average GPF balance estimated by the Kerala State Electricity
           Board at the end of FY 2026-27 is about Rs. 3500 crores, and
           the average surplus security deposit at the end of FY 2026-
           27 is Rs. 285 crores. Considering these funds available with
           the Kerala State Electricity Board, the Commission decided to
           amortise the balance gap of about Rs. 3350 crores during the
           control period while avoiding tariff shock and financial burden
           to the consumers, in the following manner: Rs. 850 crores each
           year from FY 2022-23 to FY 2024-25, Rs. 500 crores in FY
           2025-26, and Rs. 300 crores in FY 2026-27.
     vi.   The Rajasthan Electricity Regulatory Commission has submitted
           that as per its orders dated 31.03.2023 and 26.07.2024, the
           regulatory asset across the three distribution companies in the
           state is Rs. 47,578 crores upto FY 2023-24 and Rs. 47,114
           crores upto FY 2024-25. Various measures have been taken for
           recovery of the accumulated regulatory assets including financial
           support from the state government and introduction of monthly
           fuel surcharge to account for increasing power purchase costs.
           The Commission also noted that decision regarding regulatory
           surcharge, tariff increase, and adjustment of regulatory asset
           against revenue surplus will be taken in the successive years.
           It has also submitted that under the Draft RERC (Terms and
           Conditions for Determination of Tariff) Regulations, 2025,
           Regulation 91 provides for the creation of a regulatory asset only
           in exceptional circumstances under natural calamity conditions.
           Even then, it shall not be more than 3% of the approved ARR
           and it shall be liquidated with carrying costs in maximum 3
           equal yearly instalments. Existing regulatory asset, along with
           the carrying costs, shall be liquidated in a maximum of 7 equal
1898                                                           [2025] 8 S.C.R.

                           Supreme Court Reports


            yearly instalments. In case there is surplus in any financial year,
            it shall be adjusted first against regulatory assets. This is exactly
            what is prescribed in Rule 23 of the Electricity Rules made by
            the Central Government, which we will refer to in further detail
            at a later stage.
     vii.   The Tamil Nadu Electricity Regulatory Commission submits that
            the regulatory asset in the State of Tamil Nadu till FY 2021-22,
            including carrying cost, is estimated at Rs. 89,375.09 crores.
            The Commission submits that this is more than 100% of the
            ARR, and hence a tariff-based liquidation would not be feasible
            as it would excessively burden consumers. Rather, the same
            must be recovered by upgrading transmission infrastructure,
            reducing aggregate technical and commercial (AT&C) losses,
            and sourcing low-cost renewable energy sources. Essentially,
            the cost of procurement must be lowered such that the revenue
            requirement of the distribution company is on par with the
            consumers’ paying capacity. It further submits that in the
            true-up order for FY 2022-23, the Commission directed the
            Tamil Nadu Generation and Distribution Corporation to seek
            approval from the Government of Tamil Nadu to liquidate the
            revenue gap till FY 2021-22 of Rs. 83,000 crores through
            government resources. Based on the Government’s decision,
            the Commission submits that it will finalise the strategy for
            amortisation of the regulatory asset. It also submits that it has
            endeavoured to not create any new regulatory asset from FY
            2022-23 by proposing a tariff increase in a socially balanced
            manner.

     5 (ii). Affidavits by State Governments.
25. Following is the gist of the affidavits filed by various State Governments.
     i.     The State of Nagaland has filed an affidavit stating that it is a
            bulk power customer and is allotted power by the Government
            of India from generating stations within and outside the state.
            The tariff for the same is determined by the Central Electricity
            Regulatory Commission.
     ii.    The State of Odisha submitted that as per its communication with
            the Odisha Electricity Regulatory Commission, the Commission
            has never created a regulatory asset.
[2025] 8 S.C.R.                                                                              1899

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


      iii.    The Government of Madhya Pradesh also filed its affidavit
              through the Madhya Pradesh Power Management Co. Ltd.,
              which has submitted that the State Commission has always
              followed a cost-reflective tariff and has not created any regulatory
              asset.
26. We would have expected the State Governments to take a clear
    stand on the social justice obligations of the State in the context of
    the power of the Regulatory Commissions to determine tariff. The
    Regulatory Commissions are required to balance the interplay of the
    obligations of the State to ensure access to electricity on the one
    hand, and the right of the utilities to recover cost-based expenses
    on the other. We are aware of the autonomy that the Regulatory
    Commissions exercise in the context of tariff determination, as well
    as of applicability of the National Tariff Policy and Rules formulated
    by the Central Government on regulatory asset. We were conscious
    of this aspect and the same is reflected in our consideration.

      6.      Law Governing the Electricity Sector Prior to 2003.
27. The supply and use of electricity was originally governed under the
    Indian Electricity Act, 1910, which provided the legal framework
    for laying cables and other works. With independence and
    industrialisation, the need for electricity in urban as well as rural
    areas increased, leading to enactment of the Electricity (Supply)
    Act, 1948 that mandated State Governments to constitute separate
    State Electricity Boards that would be responsible for arranging
    supply of electricity in each state and administering the grid system.
    It also provided for a Central Electricity Authority23 for planning
    and development of the national power system.24 These were the
    regulators, but the governments exercised substantial control on
    policy as well as management of the sector.
28. Over time it was noticed that these State Electricity Boards were
    unable to respond to the rapidly growing demand of electricity due
    to financial losses, low tariffs, lack of budgetary support from the




23   Hereinafter “CEA”.
24   Tata Power Co. Ltd. v. Reliance Energy Ltd., (2009) 16 SCC 659, paras 67-71; BSES Rajdhani Power
     Ltd. v. Delhi Electricity Regulatory Commission, (2023) 4 SCC 788, paras 11-13.
1900                                                                                  [2025] 8 S.C.R.

                                   Supreme Court Reports


       governments, or investments.25 Further, various problems plagued
       the power sector, namely the lack of rational retail tariffs, high
       level of cross-subsidies, poor planning and operation, inadequate
       capacity, neglect of consumer interest, limited involvement of
       the private sector’s skills and resources, and the absence of an
       independent regulatory authority.26 This led to the enactment of the
       Electricity Regulatory Commissions Act, 1998 with the objective of
       reforming the electricity sector by establishing Central and State
       Electricity Regulatory Commissions, rationalising electricity tariffs,
       transparent policies regarding subsidies, and promoting efficient and
       environmentally benign policies.27
29. In the NCT of Delhi, the Delhi Electricity Reforms Act, 2000
    was enacted to restructure the electricity industry by unbundling
    generation, transmission and distribution, to increase avenues for
    private sector participation, and to take measures conducive to the
    development and management of the electricity industry in an efficient,
    commercial, economic, and competitive manner.28

       7.     Electricity Act, 2003.
30. The Electricity Act, 2003 was enacted by the Parliament as a complete
    and comprehensive law for regulating the generation, transmission,
    distribution, and use of electricity in India. The Preamble of the Act
    reads:
              “An Act to consolidate the laws relating to generation,
              transmission, distribution, trading and use of electricity and
              generally for taking measures conducive to development


25   Statement of Objects and Reasons, Electricity Regulatory Commissions Act, 1998.
26   ibid.
27   The Preamble of this Act reads:
        “An Act to provide for the establishment of a Central Electricity Regulatory Commission
        and State Electricity Regulatory Commissions, rationalization of electricity tariff, transparent
        policies regarding subsidies, promotion of efficient and environmentally benign policies and
        matters connected therewith or incidental thereto. “
28   BSES Rajdhani Power Ltd (supra), para 15. The Preamble of the Delhi Electricity Reform Act, 2000
     reads:
        “An Act to provide for the constitution of an Electricity Regulatory Commission, restructuring
        of the electricity industry (rationalisation of generation, transmission, distribution and supply of
        electricity), increasing avenues for participation of private sector in the electricity industry and
        generally for taking measures conducive to the development and management of the electricity
        industry in an efficient, commercial, economic and competitive manner in the National Capital
        Territory of Delhi and for matters connected therewith or incidental thereto.”
[2025] 8 S.C.R.                                                             1901

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


           of electricity industry, promoting competition therein,
           protecting interest of consumers and supply of electricity
           to all areas, rationalization of electricity tariff, ensuring
           transparent policies regarding subsidies, promotion of
           efficient and environmentally benign policies, constitution
           of Central Electricity Authority, Regulatory Commissions
           and establishment of Appellate Tribunal and for matters
           connected therewith or incidental thereto.”
31. Further, the purpose of the enactment is explained in detail in its
    Statement of Objects and Reasons, the relevant portions of which
    are extracted hereinbelow:
           “3. With the policy of encouraging private sector participation
           in generation, transmission and distribution and the
           objective of distancing the regulatory responsibilities from
           the Government to the Regulatory Commissions, the need
           for harmonising and rationalising the provisions in the Indian
           Electricity Act, 1910, the Electricity (Supply) Act, 1948 and
           the Electricity Regulatory Commissions Act, 1998 in a new
           self-contained comprehensive legislation arose. Accordingly
           it became necessary to enact a new legislation for regulating
           the electricity supply industry in the country which would
           replace the existing laws, preserve its core features other
           than those relating to the mandatory existence of the
           State Electricity Board and the responsibilities of the State
           Government and the State Electricity Board with respect
           to regulating licensees. There is also need to provide for
           newer concepts like power trading and open access. There
           is also need to obviate the requirement of each State
           Government to pass its own Reforms Act. The Bill has
           progressive features and endeavours to strike the right
           balance given the current realities of the power sector in
           India. It gives the State enough flexibility to develop their
           power sector in the manner they consider appropriate.
           The Electricity Bill, 2001 has been finalised after extensive
           discussions and consultations with the States and all other
           stake holders and experts.”
32. Through reading the Statement of Objects and Reasons as well as
    the Preamble, the salient features of the Act are:
1902                                                                                [2025] 8 S.C.R.

                                    Supreme Court Reports


      i.      The Act is a comprehensive code to regulate the generation,
              transmission, distribution, trading and use of electricity and
              replaces the erstwhile 1910 Act, 1948 Act, and 1998 Act that
              governed electricity supply and use;29
      ii.     The State Electricity Boards are unbundled into separate utilities
              for electricity generation, transmission, and distribution,30 and
              private sector participation is encouraged in these activities;31
      iii.    The Act provides for development of the electricity sector
              through coordinated efforts of the Central Government, State
              Governments, and various statutory authorities and regulators
              by institutionalising electricity policies and plans;
      iv.     While generation has been delicensed, the transmission,
              distribution, and trading of electricity are licensed activities;32
      v.      The Act provides for a price discovery mechanism through
              tariff fixation;
      vi.     The Act entrusts the performance of regulatory and adjudicatory
              functions, including licensing and tariff fixation, to permanent,
              independent Regulatory Commissions that act as expert and
              specialised bodies.33 It also enables dispute resolution through
              arbitration in specified cases;
      vii.    The Act established the APTEL as a specialised appellate
              forum;34
      viii. The Act provides for offences as well as their penalties.

      8.      Provisions of the Electricity Act relating to determination
              of Tariff.
33. Section 3 of the Electricity Act provides for the preparation, publication,
    review, and revision of the National Electricity Policy and tariff policy



29   Tata Power Co Ltd (supra), para 76.
30   PTC India Ltd. v. Central Electricity Regulatory Commission, (2010) 4 SCC 603, para 17.
31   Tata Power Co Ltd (supra), para 80; Hindustan Zinc Ltd. v. Rajasthan Electricity Regulatory Commission,
     (2015) 12 SCC 611, para 29.
32   Tata Power Co. Ltd. (supra).
33   Tata Power Co Ltd (supra), para 78; PTC India Ltd (supra), para 17.
34   See West Bengal Electricity Regulatory Commission v. CESC Ltd., (2002) 8 SCC 715, para 102.
[2025] 8 S.C.R.                                                      1903

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


     by the Central Government in consultation with the State Governments
     and the CEA for development of the power sector through optimal
     utilisation of resources. Sub-section (4) also provides for the CEA
     to prepare a National Electricity Plan as per the National Electricity
     Policy.
34. A distribution licensee is defined under Section 2(17) as a licensee
    operating and maintaining a distribution system for supplying
    electricity to consumers in its area of supply. Electricity distribution
    is a licensed activity as per Section 12, and the license is granted
    by the Regulatory Commission under Section 14. Part VI of the Act
    deals with distribution of electricity – Sections 42 and 43 set out of
    the duties of a distribution licensee and open access, Sections 45
    and 46 provide for the power to recover charges and expenditure
    for supply of electricity, Section 47 provides for the power to require
    security, and Sections 48 and 49 empower the distribution licensee to
    impose restrictions and enter into agreements for supply of electricity.
35. The Electricity Act also lays down a regulatory mechanism as follows:
    Section 2(4) defines “Appropriate Commission” as meaning the
    Central, State, or Joint Electricity Regulatory Commission, as the
    case may be. The Central Commission is constituted under Section
    76, its functions are stipulated under Section 79, and its regulation-
    making powers are provided under Section 178. Sections 80 and 81
    deal with the Central Advisory Committee and its objects.
     35.1 Similarly, the State Commissions are constituted under Section
          82 and their functions are provided in Section 86, which include
          both mandatory and advisory functions. The relevant mandatory
          function for our purpose is under sub-section (1)(a), which
          provides for tariff determination for retail supply of electricity
          within the State. Sub-section (4) provides that the State
          Commission shall be guided by the National Electricity Policy,
          tariff policy, and National Electricity Plan formulated under
          Section 3. The State Commission can also make regulations
          in exercise of its powers under Section 181, including on the
          terms and conditions for determination of tariff under Section
          61 (sub-section (2)(zd)), methodologies and procedures for
          calculating expected revenue from tariff and charges under
          Section 62(5) (sub-section (2)(zf)), the manner of making an
          application and fee payable under Section 64 (sub-section
1904                                                                              [2025] 8 S.C.R.

                                  Supreme Court Reports


                (2)(zg)), and modifications or conditions under Section 64(3)
                (sub-section (zh)). Sections 87 and 88 deal with State Advisory
                Committees and their objects.
      35.2 The Joint Regulatory Commission is constituted under Section
           83, and its functions and powers are under sub-sections (4)
           and (5).
      35.3 Lastly, it is important to note that Section 142 empowers the
           Commissions to punish for non-compliance of their directions,
           or any provision of the Act or rules or regulations made
           thereunder.
36. The Central and State Governments are also given the power to
    make rules under the Act, under Sections 176 and 180 respectively.
    Beyond rule-making, the Central and State Governments can issue
    policy directions to the Central and State Commissions respectively in
    matters involving public interest under Sections 107 and 108. These
    directions “shall guide” the Regulatory Commissions, but shall not
    be binding on them.35
37. In exercise of their powers and functions, the Central and State
    Commissions are required to determine tariff as per Part VII of
    the Electricity Act. Section 61 lays down the guiding principles
    for the Commissions to specify the terms and conditions of tariff
    determination, of which the following are relevant:
              “Section 61. (Tariff regulations): The Appropriate
              Commission shall, subject to the provisions of this Act,
              specify the terms and conditions for the determination of
              tariff, and in doing so, shall be guided by the following,
              namely:-
              ***
              (b) the generation, transmission, distribution and supply of
              electricity are conducted on commercial principles;
              (c) the factors which would encourage competition,
              efficiency, economical use of the resources, good
              performance and optimum investments;



35   Kerala State Electricity Board Ltd. v. Jhabua Power Ltd., 2024 SCC OnLine SC 2819.
[2025] 8 S.C.R.                                                              1905

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


           (d) safeguarding of consumers’ interest and at the same
           time, recovery of the cost of electricity in a reasonable
           manner;
           (e) the principles rewarding efficiency in performance;
           (f) multi year tariff principles;
           (g) that the tariff progressively reflects the cost of supply of
           electricity and also, reduces cross-subsidies in the manner
           specified by the Appropriate Commission;
           ***
           (i) the National Electricity Policy and tariff policy…”
38. While these principles have a bearing on making the regulations
    for tariff determination, tariff is fixed under Section 62, inter alia,
    for retail supply of electricity. Sub-section (5) also provides for
    compliance with procedures specified for calculating expected
    revenues from tariff and charges that can be recovered. Section
    63 deals with tariff determination through bidding, and Section
    64 provides the procedure for application for tariff determination.
    Section 65 mandates that if the State Government requires the
    grant of subsidy to any class of consumers in tariff, it shall pay
    the amount of such subsidy in advance to compensate the person
    affected by the grant of subsidy.

     9.    Provisions of Act, Policies, Rules, Regulations, and Orders
           having a bearing on creation of a Regulatory Asset.

     9 (i). National Electricity Policy, 2005.
39. The Central Government notified the National Electricity Policy under
    Section 3 of the Electricity Act on 12.02.2005, which laid down
    guidelines for development of the power sector, providing electricity
    supply to all areas, and protecting consumer and other stakeholders’
    interests keeping in view availability of energy resources, technology,
    and energy security issues.
40. On 01.01.2006, the DERC issued a Public Awareness Bulletin setting
    out the major components of ARR for Delhi’s distribution companies as
    well as the approximate ratio of each component in the tariff. Power
    purchase costs are 80% of the tariff, operations and maintenance
1906                                                      [2025] 8 S.C.R.

                        Supreme Court Reports


     expenses are 9-10% of the tariff, depreciation is 3-4%, return on
     capital employed is 6-7%, and income tax is 0.5-1%.

     9 (ii). National Tariff Policy, 2006.
41. On 06.01.2006, the Central Government notified the National Tariff
    Policy, 2006 under Section 3 of the Act. Clause 8.2.2 of the Policy
    provides for the creation of a regulatory asset, as well as certain
    restrictions on time-period and circumstances. It reads:
           “8.2.2. The facility of a regulatory asset has been adopted
           by some Regulatory Commissions in the past to limit tariff
           impact in a particular year. This should be done only as
           exception, and subject to the following guidelines:
           a. The circumstances should be clearly defined through
           regulations, and should only include natural causes
           or force majeure conditions. Under business as usual
           conditions, the opening balances of uncovered gap must
           be covered through transition financing arrangement or
           capital restructuring;
           b. Carrying cost of Regulatory Asset should be allowed
           to the utilities;
           c. Recovery of Regulatory Asset should be time-bound
           and within a period not exceeding three years at the
           most and preferably within control period;
           d. The use of the facility of Regulatory Asset should not
           be repetitive.
           e. In cases where regulatory asset is proposed to be
           adopted, it should be ensured that the return on equity
           should not become unreasonably low in any year so that
           the capability of the licensee to borrow is not adversely
           affected.”
                                                (emphasis supplied)

     41.1 As stated above, Section 86(4) provides that the State
          Commission shall be guided by the National Tariff Policy in
          discharging its functions, and the Policy is also a guiding
          principle for tariff determination as per Section 61(1)(i). This
[2025] 8 S.C.R.                                                                                 1907

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


                Court has held that while the Policy does not bind the State
                Commission, it is a material consideration that must guide
                tariff determination.36
      41.2 Nothing can be clearer than the mandate under Clause 8.2.2
           of the National Tariff Policy, 2006. The real issue is to examine
           the circumstances and the compelling reasons for the creation
           and undue extension of the regulatory asset over a period of
           time, which we will undertake in our Analysis.

      9 (iii). DERC Tariff Determination Regulations, 2007.
42. On 30.05.2007, the DERC framed the Tariff Determination
    Regulations, 2007 for the first control period (FY 2007-2011), under
    which Regulation 5.42 deals with regulatory asset. It stipulates that
    at the time of truing up, if variations on account of uncontrollable
    items like energy sales and power purchase costs are large and it
    is not feasible to recover them in one year, the Commission can
    create a regulatory asset as per Clause 8.2.2 of the National Tariff
    Policy, 2006. Regulation 5.42 in fact incorporates the National Tariff
    Policy and makes it a part of the enforceable regime. The relevant
    portion is extracted below for ready reference:
              “5.42 Variations on account of uncontrollable items like
              energy sales and power purchase cost shall be trued
              up. Truing-up shall be carried out for each year based
              on the actual/audited information and prudence check by
              the Commission;
              Provided that if such variations are large, and it is not feasible
              to recover in one year alone, the Commission may take
              a view to create a regulatory asset, as per the guidelines
              provided in clause 8.2.2 of the National Tariff Policy.”
                                                                   (emphasis supplied)

      9 (iv). DERC Statutory Advice dated 15.12.2010.
43. On 15.12.2010, the DERC issued a statutory advice to the Government
    of NCT of Delhi regarding the financial position of BRPL and BYPL


36   Tata Power Co. Ltd. v. Maharashtra Electricity Regulatory Commission, (2023) 11 SCC 1, para 122.
1908                                                         [2025] 8 S.C.R.

                        Supreme Court Reports


    and whether they are able to meet expenses from tariff revenue and
    return on equity. In this letter, the DERC stated that the tariffs for FY
    2008-09 to FY 2010-11 are not cost-reflective and they do not account
    for the increase in power purchase costs during this period, which
    constituted more than 80% of the tariff. While generating companies
    recover the increase in cost from the distribution companies, the
    latter are unable to recover the same from consumers under the
    present tariff. Distribution licensees resorted to extensive borrowing
    to sustain operations, resulting in substantial interest costs and a
    precarious financial position. The DERC noted that this is against
    consumer interests as these costs must ultimately be recovered from
    consumers with carrying cost, and would burden future consumers
    with previously incurred costs. The relevant portions of the DERC’s
    letter are extracted below:
         “16. The Commission has analysed the ability of the
         distribution licensees to meet their expenses and has
         considered the revenue from retail sale of electricity at the
         tariffs determined by the Commission. These have been
         compared with various heads of expenditure i.e. power
         purchase cost, operating expenses including interest and
         depreciation, to determine the extent of surplus available
         towards the return on equity allowed by the Commission.
         18. Power purchase cost should not be exceeding 80%
         which was in the range of 73-80% in the year 2008-09,
         77-98% in the year 2009-10 and 113-135% in the first six
         months of 2010-11.
         20. Power purchase and revenue recovered from sale of
         energy are not within the control of the distribution licensees.
         Power purchase cost is mostly dependent upon the fuel
         cost which is market driven. The generating company
         recovers the increase in the fuel cost and other variable
         expenses every month from the distribution licensees, who
         in turn are not able to recover timely from the consumers
         under the present dispensation. Thus, the operations of
         the distribution companies are dependent on borrowings
         over a period of 18-24 months which entails substantial
         interest cost. This, in any case, is detrimental to consumer
         Interest as all power purchase costs whether short term
[2025] 8 S.C.R.                                                            1909

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


           or long term are passed through to the consumers (and
           recovered from the consumers along with the carrying cost).
           ***
           Conclusion
           The Commission is of the view that the tariff during previous
           years has not been cost effective. The distribution licensees
           have had to resort to extensive borrowing to sustain their
           operations.
           ***
           (3) Accumulation of Revenue gaps beyond sustainable
           levels
           Analysis of the Audited Accounts of the distribution
           licensees in Tables 1-3 would indicate that there is shortfall
           in the years 2009-10 and 2010-11 beyond sustainable
           levels. Thus, it would be quite obvious that in the absence
           of tariff revision there is a growing revenue gap which is
           to be funded out of borrowings which are increasing from
           year to year.
           ***
           (5) Power purchase cost/quantum
           Analysis carried out for the years 2008-09 and 2009-
           10 in Tables 1-4 would indicate that there has been a
           steep increase in the power purchase cost. These issues
           would get addressed while taking the ground realities into
           consideration and estimating the quantum and the cost
           based upon the current data based upon the latest bills
           available from the generating companies, power purchase
           rates in the Power Exchange, Ul and bilateral contracts.”

     9 (v). Ministry of Power’s Letter to the APTEL.
44. On 21.01.2011, the Minister of Power issued a letter to the APTEL
    to take suo motu cognisance and issue necessary directions under
    Section 121 of the Electricity Act regarding periodical tariff revisions
    for improving the long-term financial health and viability of the
    electricity sector.
1910                                                                 [2025] 8 S.C.R.

                                   Supreme Court Reports


      9 (vi). APTEL’s Order dated 11.11.2011.
45. Pursuant to this letter, the APTEL passed an order dated 11.11.201137
    wherein it issued various directions to Regulatory Commissions
    regarding timely tariff determination, truing up, and creation,
    continuation, and recovery of the regulatory asset. The directions
    issued by the APTEL are as follows:
              “65. In view of the analysis and discussion made above,
              we deem it fit to issue the following directions to the State
              Commissions:
              (i)     Every State Commission has to ensure that Annual
                      Performance Review, true-up of past expenses and
                      Annual Revenue Requirement and tariff determination
                      is conducted year to year basis as per the time
                      schedule specified in the Regulations.
              (ii)    It should be the endeavour of every State Commission
                      to ensure that the tariff for the financial year is decided
                      before 1st April of the tariff year. For example, the
                      ARR & tariff for the financial year 2011- 12 should be
                      decided before 1st April, 2011. The State Commission
                      could consider making the tariff applicable only till the
                      end of the financial year so that the licensees remain
                      vigilant to follow the time schedule for filing of the
                      application for determination of ARR/tariff.
              (iii) In the event of delay in filing of the ARR, truingup
                    and Annual Performance Review, one month beyond
                    the scheduled date of submission of the petition, the
                    State Commission must initiate suo-moto proceedings
                    for tariff determination in accordance with Section 64
                    of the Act read with clause 8.1 (7) of the Tariff Policy.
              (iv) In determination of ARR/tariff, the revenue gaps
                   ought not to be left and Regulatory Asset should
                   not be created as a matter of course except where
                   it is justifiable, in accordance with the Tariff Policy
                   and the Regulations. The recovery of the Regulatory



37   In O.P. No. 1/2011, order dated 11.11.2011.
[2025] 8 S.C.R.                                                            1911

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


                 Asset should be time bound and within a period not
                 exceeding three years at the most and preferably
                 within Control Period. Carrying cost of the Regulatory
                 Asset should be allowed to the utilities in the ARR of
                 the year in which the Regulatory Assets are created to
                 avoid problem of cash flow to the distribution licensee.
           (v)   Truing up should be carried out regularly and
                 preferably every year. For example, truing up for the
                 financial year 2009-10 should be carried out along
                 with the ARR and tariff determination for the financial
                 year 2011-12.
           (vi) Fuel and Power Purchase cost is a major expense
                of the distribution Company which is uncontrollable.
                Every State Commission must have in place a
                mechanism for Fuel and Power Purchase cost in
                terms of Section 62 (4) of the Act. The Fuel and
                Power Purchase cost adjustment should preferably
                be on monthly basis on the lines of the Central
                Commission’s Regulations for the generating
                companies but in no case exceeding a quarter. Any
                State Commission which does not already have such
                formula/mechanism in place must within 6 months of
                the date of this order must put in place such formula/
                mechanism.
           66. We direct all the State Commissions to follow these
           directions scrupulously, and send the periodical reports by
           1st June of the relevant financial year about the compliance
           of these directions to the Secretary, Forum of Regulators,
           who in turn will send the status report to this Tribunal and
           also place it on its website.”

     9 (vii). DERC Tariff Determination Regulations, 2011.
46. The DERC then issued the Tariff Determination Regulations, 2011
    for the second control period (FY 2012-2015, later extended till
    31.03.2017), under which Regulation 5.40 is relevant and deals with
    regulatory asset. Similar to Regulation 5.42 of the Tariff Determination
    Regulations, 2007, it provides for creation of a regulatory asset
    when the variations at the truing up stage are large and cannot be
1912                                                       [2025] 8 S.C.R.

                         Supreme Court Reports


     recovered in one year. Further, the regulatory asset must be created
     as per the guidelines in Clause 8.2.2 of the National Tariff Policy,
     2006. The Regulation reads:
          “5.40 Truing-up shall be carried out in accordance with
          Regulation 4.21, for each year based on the actual/audited
          information and prudence check by the Commission;
          Provided that if such variations are large, and it is not
          feasible to recover in one year alone, the Commission
          may take a view to create a regulatory asset, as per the
          guidelines provided in clause 8.2.2 of the National Tariff
          Policy.
          Provided further that under business as usual conditions,
          the Commission, to ensure tariff stability, may include the
          opening balances of uncovered gap / trued-up costs in
          the subsequent Control Period’s ARR instead of including
          in the year succeeding the relevant year of the control
          period after providing for transition financing arrangement
          or capital restructuring.”

     9 (viii). DERC’s Tariff Order dated 26.08.2011 (FY 2011-12).
47. The DERC also passed an order dated 26.08.2011 wherein it
    determined the ARR for FY 2011-12 and the true-up for FY 2008-
    2010. In this order, it increased the tariff by 22% across the board for
    all consumer categories and also introduced a fuel price adjustment
    charge.

     9 (ix). DERC’s MYT Order dated 13.07.2012 (FY 2012-15).
48. In its subsequent MYT order dated 13.07.2012 determining ARR for
    FY 2012-2015 and true-up for FY 2010-11, the DERC approved tariff
    increase of 23%, introduced the DRS @ 8%, and the PPAC. The
    fuel price adjustment charge was absorbed into these.

     9 (x). DERC’s Statutory Advice dated 01.02.2013.
49. On 01.02.2013, the DERC issued another statutory advice to the
    Government of NCT of Delhi, wherein it noted that the revenue gap
    was Rs. 19,505.04 crores, including carrying costs, across BRPL,
    BYPL, and TPDDL since FY 2009-10. The DERC also specified
[2025] 8 S.C.R.                                                              1913

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


     various measures taken to recover the revenue gap, including the
     23% tariff hike w.e.f. 01.07.2012 and the DRS of 8%, but that these
     were insufficient. In this light, the DERC recommended that the
     Government of NCT of Delhi may take steps to ensure that benefits
     of Central Government sponsored schemes, direct subsidies from
     state governments, and additional budgetary support are extended
     to the distribution licensees. The relevant recommendations of the
     DERC to the Government of NCT are extracted below:
           “14. Recommendations:-
           ***
           i) …The Commission recommends that Govt. of NCT of
           Delhi may take urgent steps so that the benefits of various
           Central Government sponsored schemes are extended to
           the Delhi distribution utilities and, in tum, to the electricity
           consumers in Delhi. Unless this is done, tariffs in Delhi
           could become unsustainable, especially when compared
           to other States in the country where State owned utilities
           not only avail the benefits of the centrally sponsored
           schemes but also avail direct subsidies from the State
           Governments as well as additional budgetary support for
           lower tariff levels.
           ii) In case of APDRP, R-APDRP and JNNURM schemes of
           the Central Govt., the view of the Govt. been that privately
           managed distribution entities should not be allowed to avail
           the benefits of these programmes. The Commission is of
           the view that denial of the benefits of these programmes
           to the distribution entities of Delhi does not affect the
           managements of these distribution companies but, in
           fact, denies the benefit of the schemes to the consumers
           of electricity of Delhi who are as a result required to pay
           higher tariffs than are paid by the electricity consumers in
           other States which avail of the benefits of these schemes.
           Thus, the Govt. of NCT of Delhi may take up with the
           Ministry of Power that these schemes are availed of by the
           Delhi distribution utilities for the benefit of the consumers
           in the NCT of Delhi.
           iii) The financial bailout package introduced by the Central
           Govt. for financial restructuring of State distribution entities
1914                                                         [2025] 8 S.C.R.

                                  Supreme Court Reports


              with certain conditions including support from the State
              Govt. is also being denied to the distribution entities in
              Delhi. Here again, this view does not impact the private
              managements of these companies but has a direct impact
              on their revenue requirements and consequently, the tariff
              required to be paid by electricity consumers in the city.
              The Govt. of NCT of Delhi may take up with the Ministry of
              Power to sanction the bail-out package for the DISCOMs
              of Delhi. This would be the single most important measure
              for deferring the incidence of high levels of past revenue
              gaps on the tariff determination process.”

       9 (xi). DERC’s Tariff Order dated 31.07.2013 (FY 2013-14).
50. In the next tariff order dated 31.07.2013 to determine ARR for FY
    2013-14 and true-up for FY 2011-12, the DERC increased the tariff
    by 5% and continued the existing DRS @ 8% over and above the
    revised tariff. It also allowed carrying cost on the regulatory asset
    to all distribution companies. At this stage, the regulatory asset
    amounted to Rs. 8060 crores across the BSES Discoms and Rs.
    3370 crores for TPDDL.

       9 (xii). APTEL’s Order dated 14.11.2013.
51. The APTEL also passed the order dated 14.11.201338, wherein it
    reiterated its direction to the DERC to provide for recovery of the
    regulatory asset in 3 years as per its order dated 11.11.2011 and
    to implement the judgments of the APTEL. The DERC has filed
    civil appeals against this order, which have been dismissed by this
    Court’s order dated 01.12.2021 as there was no substantial question
    of law.39 This Court also directed the DERC to implement the issues
    decided by the APTEL, if not already complied, within a period of 3
    months and to file a compliance report in 2 weeks thereafter.40 The
    relevant portion of the APTEL order is as follows:
              “37. As regards recovery of the Regulatory assets/
              amortization schedule and fuel and power purchase


38   In O.P. Nos. 1 and 2/2012, order dated 14.11.2013.
39   In C.A. No. 1854-1855/2014, order dated 01.12.2021.
40   ibid.
[2025] 8 S.C.R.                                                           1915

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


           adjustment mechanism, this Tribunal in OP No.1 of 2011
           dated 11.2011 has given the following directions to the
           State Commission…
           38. In view of the above, we direct the State Commission to
           take immediate steps for recovery of the admitted revenue
           gap and decide amortization schedule and also ensure
           that the Fuel and Power Purchase costs are passed on
           regularly and effectively as per the above directions of this
           Tribunal to avert the problems of cash flow experienced
           by the Petitioners which may come in the way of smooth
           operation of the distribution system and meeting the
           requirements of electricity of the consumers in the national
           capital in a reliable manner if not remedied in time.
           39. In view of the categorical stand taken by the Delhi
           Commission now, it is enough for us to direct the Delhi
           Commission to implement the directions of this Tribunal
           given in the decisions referred to above and pass an order
           in terms of those directions in future.”

     9 (xiii). APTEL’s Order dated 11.03.2014.
52. The above-referred tariff order dated 31.07.2013 was appealed before
    the APTEL by BRPL in Appeal No. 266/2013 and by BYPL in Appeal
    No. 265/2013 on the ground that the tariff order did not provide a
    roadmap for recovery of the regulatory asset. In these appeals, BRPL
    and BYPL filed IA 365/2013 and 364/2013 respectively for an order to
    increase the DRS to meet carrying costs upto 31.03.2014, to repay
    one-third of the principal component of the regulatory asset, and to
    provide a plan for completely recovery of the regulatory asset in 3
    years as per the National Tariff Policy, 2006.
53. The APTEL rejected the prayer for liquidating the regulatory asset
    in 3 years by order dated 11.03.2014, which has been appealed by
    BRPL and BYPL in the present civil appeals. However, the APTEL
    directed the DERC to prepare a roadmap for liquidation of the
    regulatory asset, both principal amount and carrying cost, keeping
    in mind the interests of consumers and the distribution licensees.
54. In the present civil appeals (C.A. No. 4010 and 4013/2014) against
    the APTEL’s order dated 11.03.2014, as well as writ petitions by
    BRPL and BYPL, this Court by order dated 26.03.2014 directed the
1916                                                     [2025] 8 S.C.R.

                        Supreme Court Reports


     DERC to submit a roadmap for liquidation of the regulatory asset
     and also directed BRPL and BYPL to pay the current dues to the
     generating and transmission companies. In compliance with this
     order, the DERC submitted a liquidation schedule on 01.05.2014
     before this Court, in which it proposed to liquidate the regulatory
     asset including carrying cost in 6-7 years (by FY 2020-21) by taking
     the average growth rate of distribution companies at 15%.

     9 (xiv). National Tariff Policy, 2016.
55. On 28.01.2016, a revised National Tariff Policy, 2016 was notified by
    the Central Government, wherein Clause 8.2.2 deals with regulatory
    asset. While the other conditions for creation of a regulatory asset
    are similar to the National Tariff Policy, 2006, the time-period for
    recovery was increased from 3 to 7 years. The relevant portion is
    extracted below:
          “8.2.2 The facility of a regulatory asset has been adopted
          by some Regulatory Commissions in the past to limit tariff
          impact in a particular year. This should be done only as
          a very rare exception in case of natural calamity or force
          majeure conditions and subject to the following:
          a. Under business as usual conditions, no creation of
          Regulatory Assets shall be allowed;
          b. Recovery of outstanding Regulatory Assets along with
          carrying cost of Regulatory Assets should be time bound
          and within a period not exceeding seven years. The State
          Commission may specify the trajectory for the same.”
                                               (emphasis supplied)

     9 (v). DERC Tariff Determination Regulations, 2017.
56. The DERC then framed the DERC (Terms and Conditions for
    Determination of Tariff) Regulations, 2017, which contains a
    separate section on regulatory asset. Regulation 154 provides that
    an accumulated revenue gap approved by the Commission in the
    relevant tariff order shall be treated as a regulatory asset, and that
    such revenue gap shall be computed on the basis of excess of
    ARR over revenue approved after truing up for the relevant year.
    Regulation 155 provides for carrying cost, and Regulation 156 deals
[2025] 8 S.C.R.                                                                1917

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


      with the how the regulatory asset must be shown in the books of
      accounts. On a perusal of these regulations, it is clear that Clause
      8.2.2 of the National Tariff Policy, 2016 has not been referred, nor
      are there any conditions on when a regulatory asset can be created,
      its quantum, and the time-period for its recovery.

      9 (vi). Ministry of Power’s Affidavit dated 10.08.2022.
57. On 10.08.2022, the Ministry of Power, Union of India submitted an
    affidavit before this Court in the present writ petitions. It submitted
    that while the DERC created the regulatory asset as an exception, it
    is now being continued in a manner inconsistent with the Electricity
    Act and its larger objective of a healthy and economical electricity
    sector. The affidavit also relied on the APTEL’s judgment dated
    11.11.201141 where it was held that the regulatory asset must be
    recovered in a time-bound manner within 3 years, and preferably
    within the control period. The Ministry of Power prayed that this
    Court direct DERC to devise a roadmap or plan for amortisation of
    the regulatory asset in a time-bound manner as per the National
    Tariff Policies, to direct the State Commissions to determine cost-
    reflective tariffs, and that no new regulatory asset be created except
    as per the National Tariff Policy, 2016. The relevant portions of the
    affidavit are extracted below:
              “10. That creation of Regulatory Asset essentially requires
              deferment of admitted cost due to a Distribution Company
              to a future period in order to avoid tariff shock. This concept
              was adopted by the Respondent No. 2 as an exception,
              however, gradually the exercise of creation of Regulatory
              Asset seems to have become a trend and is now being
              done on year to year basis. Such an approach is not only
              inconsistent with the Act but is also irreconcilable with the
              larger objective to have a healthy and economical electricity
              sector in the country.
              11. That in order to address this situation, the Answering
              Respondent in compliance with section 3 of the Act, notified
              the National Tariff Policy (“NTP, 2006”) on 06.01.2006,
              wherein the Answering Respondent had directed that


41   In O.P. No. 1/2011 (supra).
1918                                                        [2025] 8 S.C.R.

                       Supreme Court Reports


        the ‘Regulatory Asset’ should not be created under usual
        business condition and the recovery of Regulatory Asset
        should be timebound, within a period of three years.
        Following are the relevant extracts of the NTP, 2006…
        12. That despite the above mandate, it was observed that
        the SERCs have failed/or are reluctant to conduct the tariff
        determination exercise in consistency with the Act. In this
        respect, on 21.01.2011, the Answering Respondent issued
        a Letter to the Appellate Tribunal for Electricity (“Appellate
        Tribunal”), inter alia, requesting the Appellate Tribunal to
        issue necessary directions to the SERCs to revise the
        tariff periodically for improving the financial health and
        long-term viability of the electricity sector, particularly for
        distribution utilities. Basis the letter issued by the Answering
        Respondent, the Appellate Tribunal initiated a Suo- Moto
        proceeding being O.P. No. 01 of 2011 wherein, various
        issues with respect to power of SERCs to determine tariff
        were discussed…
        14. That the Answering Respondent on 28.01.2016 issued
        the National Tariff Policy, 2016 (“NTP, 2016”). Clause 8.2.2
        of NTP, 2016, provided that the SERCs cannot continue
        to delay the liquidation of Regulatory Assets and the
        recovery of outstanding Regulatory Assets along with the
        Carrying Cost should be done in a time bound manner
        not exceeding 7 years…
        15. That it is evident from the above that Answering
        Respondent has taken steps and mandated that the SERCs
        (including the Respondent No.2) cannot create Regulatory
        Asset as a matter of routine and the Regulatory Asset and
        directed the SERCs to recover the outstanding Regulatory
        Assets in a time bound manner…
        18. That in view of the above, it is submitted that the
        creation of a Regulatory Asset’ with no mechanism
        for recovery is contrary to the Act’s legislative intent,
        as it amounts to artificially keeping the tariff low while
        prejudicing the efficient recovery of the tariff. Answering
        Respondent vide the statutory policies and various
        communications have directed the Commissions to
[2025] 8 S.C.R.                                                        1919

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


           refrain from creating Regulatory Asset and to amortise the
           Regulatory Asset within a time bound manner. However,
           as evident in the present case, the Respondent No. 2
           has not acted in the compliance of the Act, Statutory
           policies issued by the Answering Respondent and the
           Judgments/Order of the Appellate Tribunal and deferred
           the recovery of recognised revenue gap for 17 years by
           creating the Regulatory Asset.
           19. That it is therefore submitted that this Hon’ble Court
           may be pleased to direct the Respondent No. 2 to devise
           a roadmap/plan to amortise the Regulatory Asset in a
           time-bound manner as mandated under the Tariff Policies
           notified by the Answering Respondent or any other
           methodology as this Hon’ble Court may deem fit in the
           present situation. Since such problem is also observed in
           other State Commissions also, Hon’ble Court may also be
           pleased to direct all State Commission for determination
           of cost reflective tariff and no new regulatory assets
           be created as stipulated in the Tariff Policy 2016. State
           Commission may also be directed to devise a roadmap/
           plan to amortise the Regulatory Asset in a time-bound
           manner as mandated under the Tariff Policies notified by
           the Answering Respondent.”

     9 (vii). Ministry of Power’s Affidavit dated 12.12.2022.
58. In another affidavit dated 12.12.2022, the Ministry of Power submitted
    that the LPS fixed by the State Commissions was 18%, which is
    “usurious” as bank lending rates are 6-7%. This higher LPS means
    that distribution companies bear a heavy burden in case of delayed
    payments, which is subsequently passed on to consumers. Hence,
    LPS must be linked to the Bank Lending Rate to make it reasonable.
    Though this issue does not directly arise for our consideration, we
    are aware that it has a bearing on the tariff, if not for the present
    but in future. Eventually, the burden is shifted on the consumer. The
    Ministry also submits that taking into account these concerns, it has
    notified the Electricity (LPS) Rules, 2022. The relevant portions of
    the affidavit are extracted below:
           “In the absence of any Rules or directions with regard
           to the specific rates for Late Payment Surcharge (LPS),
1920                                                       [2025] 8 S.C.R.

                         Supreme Court Reports


          the CERC and SERCS notified their respective Tariff
          Regulations from time to time wherein different rates of
          the LPS were specified and which were exorbitant- as high
          as 18 percent- whereas Banks are charging an interest of
          only 6 to 7 percent on their loans. The extortionate rate
          of LPS lead to higher cost of electricity for the common
          man; and a heavy burden on the distribution companies
          putting them virtually into a debt trap.”

     9 (viii). Electricity (Amendment) Rules, 2024 introducing Rule 23.
59. On 10.01.2024, the Central Government notified the Electricity
    (Amendment) Rules, 2024 by which it inserted Rule 23, which
    deals with regulatory asset, in the Electricity Rules, 2005. This
    was in exercise of its rule-making powers under Section 176 of
    the Electricity Act. Rule 23 prescribes as a first principle that tariff
    shall be cost-reflective and that there shall not be any gap between
    the ARR and the estimated revenue from approved tariff. The only
    exception to this rule is natural calamity conditions. Four conditions
    are formulated for the creation, management, and liquidation of a
    regulatory asset under Rule 23: First, the regulatory asset shall not
    be more than 3% of the ARR. Second, the revenue gap shall be
    liquidated within 3 years. Third, the existing regulatory assets shall
    be liquidated within 7 years. Fourth, the regulatory asset will have
    carrying cost as prescribed under the Rules. We will deal with Rule
    23 in more detail at a later stage.

     9 (xix). DERC’s Order dated 19.07.2024 (true-up till FY 2020-21).
60. Finally, in its orders dated 19.07.2024 for truing-up till FY 2020-21,
    the DERC implemented various decisions of the APTEL and this
    Court. Pursuant to this, the regulatory asset including carrying costs
    is as follows: Rs. 12,993.53 crores for BRPL, Rs. 8419.14 crores
    for BYPL, and Rs. 5,787.70 crores for TPDDL. This amounts to Rs.
    27,200.37 crores across all three distribution companies until the
    end of FY 2020-21.

     10. Analysis.
61. We are considering the legal position and status of a regulatory
    asset, the rights and liabilities of stakeholders, consequences of
    regulatory failure to manage the regulatory asset as a reasonable
[2025] 8 S.C.R.                                                                                      1921

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


      measure, and the appellate and review powers of the APTEL and
      this Court to ensure accountability and restitution.

      10 (i). Electricity is a public good and is regulated under the Act.
62. Since electricity is a material resource, the State has a public interest
    in ensuring that its ownership and control is so distributed as best to
    subserve the common good. Therefore, the public policy that governs
    purchase, sale and distribution of electricity is not based on market
    forces of demand and supply but by regulation through statute. The
    Electricity Act 2003, the policies and plan(s) formulated under Section
    3 of the Act, rules made by the Central and State Governments,
    and more importantly, the regulations formulated by the Regulatory
    Commissions, followed by the precedents laid down by the APTEL
    and this Court form the legal regime, by which tariff is determined,
    restructured, and reviewed from time to time.

      10 (ii). Tariff determination is governed by the Act, which entrusts
      this function to independent Regulatory Commissions.
63. The Electricity Act unbundled generation, distribution and transmission
    of electricity, and at the same time, institutionalised important
    functions such as grant of licenses and determination of tariff through
    the establishment of Regulatory Commissions. These Regulatory
    Commissions have autonomy as provided in the statute, expertise
    through human resource, continuation through seal and succession,
    plurality by composition, and accountability by transparency. With
    the powers that they are granted, coupled with autonomy that they
    enjoy, these Commissions are the primary duty bearers to implement
    the provisions of the Act.
      63.1 Tariff determination is the exclusive province of the Regulatory
           Commissions. In performance of their functions, the Central
           and State Electricity Regulatory Commissions determine tariff
           for supply of electricity by generating companies to distribution
           licensees, for transmission, wheeling, and also for retail sale
           of electricity.42 Section 61 provides the guiding principles for


42   Section 62 of the Electricity Act, which reads:
     “Section 62. (Determination of tariff): ---
     (1) The Appropriate Commission shall determine the tariff in accordance with the provisions of this
     Act for –
1922                                                                                [2025] 8 S.C.R.

                                      Supreme Court Reports


                 good governance for development, sale, and distribution
                 of power and also emphasises the overarching principle of
                 subserving the interests of consumers. The journey as well
                 as the destination of tariff determination indicates that the
                 Commissions shall adopt commercial principles, encourage
                 competition, promote efficiency, use resources economically,
                 perform efficiently and optimise investments. The purpose
                 of adopting such measures is to “safeguard and protect
                 the interest of the consumers”. Section 61 also recognises
                 the vulnerability of the electricity sector to undue political
                 posturing, and therefore emphasises that the Commission
                 shall ensure that “the tariff progressively reflects the cost of
                 supply of electricity and also, reduce cross-subsidies”.43 In
                 this endeavour the National Electricity Policy and the National
                 Tariff Policy shall also be guiding factors.44



         (a) supply of electricity by a generating company to a distribution licensee:
     Provided that the Appropriate Commission may, in case of shortage of supply of electricity, fix
     the minimum and maximum ceiling of tariff for sale or purchase of electricity in pursuance of an
     agreement, entered into between a generating company and a licensee or between licensees, for
     a period not exceeding one year to ensure reasonable prices of electricity;
         (b) transmission of electricity;
         (c) wheeling of electricity;
         (d) retail sale of electricity:
     Provided that in case of distribution of electricity in the same area by two or more distribution
     licensees, the Appropriate Commission may, for promoting competition among distribution
     licensees, fix only maximum ceiling of tariff for retail sale of electricity.”
     Sections 79 sets out the functions of the Central Commission. The relevant portion is as follows:
         “Section 79. (Functions of Central Commission): ---
         (1) The Central Commission shall discharge the following functions, namely:-
         (a) to regulate the tariff of generating companies owned or controlled by the Central
         Government;
         (b) to regulate the tariff of generating companies other than those owned or controlled by
         the Central Government specified in clause (a), if such generating companies enter into
         or otherwise have a composite scheme for generation and sale of electricity in more than
         one State;
         ***
         (d) to determine tariff for inter-State transmission of electricity;…”
     Section 86 sets out the functions of the State Commission. The relevant portion is as follows:
         “Section 86. (Functions of State Commission): ---
         (1) The State Commission shall discharge the following functions, namely:-
         (a) determine the tariff for generation, supply, transmission and wheeling of electricity,
         wholesale, bulk or retail, as the case may be, within the State:
         (b) regulate electricity purchase and procurement process of distribution licensees
         including the price at which electricity shall be procured from the generating companies or
         licensees or from other sources through agreements for purchase of power for distribution
         and supply within the State;…”
43   Section 61(1)(g) of the Electricity Act.
44   Section 61(1)(i) of the Electricity Act.
[2025] 8 S.C.R.                                                                                          1923

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


       10 (iii). Collaborative effort of the Regulatory Commissions to
       balance social justice obligations with efficiency.
64. The Electricity Act contemplates multiple stakeholders, in other
    words, a plurality of collaborators – the Central Government, the
    State Governments, Regulatory Commissions, the Appellate Tribunal,
    statutory policy makers, and the utilities. These authorities collaborate
    to ensure that the purpose of the Act is subserved and, in this
    endeavour, the Regulatory Commissions share the social justice
    obligations of the State. Since electricity is a public good,45 Regulatory
    Commissions must undertake joint and collaborative efforts with
    the other authorities to enable access to electricity across urban
    and rural areas46 and affordability through rationalisation of tariffs47.
    The statutory authorities must work in cohesion towards a common
    goal of ensuring supply of electricity across regions and terrains,
    and cheaper and affordable supply of electricity to those sections
    of society who cannot afford it.48 At the same time the Regulatory
    Commissions maintain their independence and autonomy and ensure
    that the final decision with respect to fixation of tariff will be that of
    the Regulatory Commissions alone.

       10 (iv). Tariff fixation takes into account multiple variables and
       requires flexibility. Regulatory asset is a measure adopted during
       tariff fixation that recognises right of recovery.
65. A regulatory asset is adopted as a measure by the Regulatory
    Commissions when the gap between the revenue required by the



45   See K.C. Ninan v. Kerala State Electricity Board, (2023) 14 SCC 431, para 93.
46   See Preamble of the Electricity Act; Section 6 of the Electricity Act that places the responsibility of rural
     electrification jointly on the Central and State Governments.
47   See Preamble of the Electricity Act.
48   Paul Craig, UK, EU and Global Administrative Law: Foundations and Challenges (Cambridge University
     Press, 2015), 305-306. The relevant portion is extracted hereinbelow:
        “Regulation as an enterprise conceives regulators as governments in miniature, in which
        efficiency and distributive goals are both legitimate regulatory concerns, and anyway
        are inseparable’. The regulatory goals may include social cohesion, and this function may
        be shared with government Regulatory independence is not regarded as central, because
        regulation is conceived as a collaborative project between agencies and other organs of
        government. Regulation in this mould is seen as delegation by government of its inherent
        powers to act in the public interest. The emphasis is on different actors working towards a
        common enterprise, with accountability conceived primarily in terms of public law mechanisms
        such as proceduralization, judicial review and parliamentary scrutiny. For Prosser this model
        has the virtue of rendering it easier to understand in areas where regulation has a social
        rationale, and is not driven by considerations of economic efficiency.”
1924                                                      [2025] 8 S.C.R.

                        Supreme Court Reports


     distribution company to meet its costs and expenditure and the actual
     revenue realised through immediate tariff is so high that it would not
     only prejudice the consumer but lead to what is called a tariff shock.
     By adopting such a measure, the Commission liquidates the revenue
     required by the utility through future tariff determinations. ‘Revenue
     assets’ are costs incurred by power distribution companies that are
     recognised as recoverable from consumers in future tariffs but are
     not immediately recovered in the current bills.
     65.1 The measure adopted by the Commissions in creating a
          ‘regulatory asset’ can also be seen as an accounting treatment.
          Regulatory assets are treated as assets in the balance sheet
          and are liquidated over a defined period of time through tariff
          adjustments or government subsidies. The regulatory asset is
          a cost incurred by the utility that the Regulatory Commission
          allows to be deferred on the balance sheet instead of being
          immediately expensed. It enables the distribution company to
          utilise the ‘recognition’ of a regulatory asset to obtain bridge
          funds from bankers and the financial institutions as they have
          the confirmation that the said amount will be recovered in the
          ensuing financial years.

     10 (v). Factors leading to an unmanageable regulatory asset,
     and consequent ‘regulatory failure’.
66. While determining tariff, Regulatory Commissions have to deal
    with situations where there could be a sudden increase in the fuel
    cost, infrastructure investments, or some extraordinary expenditure.
    Further, lack of discipline followed by delays in filing the ARR leads
    to uncertainties. Equally, not conducting quick and effective truing
    up multiplies the problem of ascertaining the actual cost incurred.
    The failure to file ARR in time and the Regulatory Commissions
    not invoking their suo motu powers to rectify the same are not
    addressed. There is a lack of accountability here. Further, even
    though Section 65 provisions that State Governments shall pay
    in advance the subsidy to subserve social justice obligations, it is
    alleged that such payments are not made in time. The decisions
    taken by the Regulatory Commissions, which were considered in
    appeal by the APTEL and this Court, give a clear impression that the
    Regulatory Commission is not able to take firm decisions. Instead
    of taking strong decisions on the basis of the statutory mandate,
[2025] 8 S.C.R.                                                                                1925

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


      we see instances where the Regulatory Commissions manage and
      manoeuvre to arrive at a tariff by creating regulatory assets over and
      above all permissible limits. This is where the problem lies. Though
      the Electricity Act envisages functional autonomy for Regulatory
      Commissions49 and the statutory scheme is complete in all respects,
      the decisions taken by the Commissions, many a time, have not
      inspired confidence of independence and autonomy. The reasons are
      not difficult to conceive as there is an issue about the appointment
      process. The assertion of independence, however, comes through
      individual volition and that is where the mandate of transparency
      leads to accountability. The decisions taken by the Commission,
      rather the Regulatory Commissioners, are subject to scrutiny in the
      appellate and the review jurisdiction of the APTEL and thereafter
      by the Supreme Court. We have dealt with this issue in more detail
      while considering accountability of the Regulatory Commissions and
      powers of the APTEL. All these factors give rise to a situation where
      the tariff for the subsequent years has to be substantially increased
      to meet the ARR of the previous years.
      66.1 A Regulatory Commission’s power to create a regulatory
           asset is part of the tariff fixation process, as long as it is in
           reasonable measure. However, in an egregious situation where
           the regulatory asset has grown beyond proportion and is also
           extended from time-to-time inefficiently, there is a compelling
           need to deal with it. In this context, the Regulatory Commissions
           have twin obligations: first, the Commission must enable an
           efficient and effective recovery of the regulatory asset by
           the utility, and second, more importantly, it must manage the
           regulatory asset in a manner that does not transgress the
           principles that inform and govern tariff determination. The
           regulatory asset cannot be permitted to balloon into such
           proportions or continued for such periods, year after year,
           that the governance of the sector is set in peril, affecting the
           rights of the utilities and at the same time jeopardising the
           consumer interest, who eventually end up bearing the burden.
           Creation, management and dissolution of regulatory assets
           are subject to law and regulation. In performance of these


49   See Transmission Corporation of Andhra Pradesh Ltd. v. Sai Renewable Power (P) Ltd., (2011) 11 SCC
     34, para 59; Kerala SEB Ltd. (supra), paras 16 and 17.
1926                                                           [2025] 8 S.C.R.

                         Supreme Court Reports


            duties, the orders of the Regulatory Commissions are subject
            to the orders, instructions, and directions of the APTEL issued
            in exercise of its statutory powers. When they fail to comply
            with these statutory and other requirements, one can infer
            regulatory failure.

     10 (vi). Law that governs creation, continuation and liquidation
     of regulatory asset.
67. In the context of creation, management and liquidation of a regulatory
    asset, the Regulatory Commissions are bound by the mandate of
    the Electricity Act, the National Electricity Policy, the National Tariff
    Policy, the Electricity Rules, the Tariff Determination Regulations
    applicable at the relevant period, and the precedents of the APTEL.
    We have already indicated that the Central Government recently
    notified the Electricity (Amendment) Rules, 2024 by which it inserted
    Rule 23 that deals with regulatory asset. Prior to the notification,
    the Central Government elicited comments from various statutory
    authorities, including the CEA, the Central and State Commissions,
    the State Governments, generating and distribution utilities, etc. The
    reason for introduction of this rule is evident from the circulation
    of the Draft Rules for stakeholder comments, wherein the Central
    Government has expressed the need for a statutory rule on the
    conditions for creation and management of a regulatory asset as
    follows:
          “3. In order to remove difficulties/challenges faced by
          various entities and to facilitate development of the power
          sector some more reforms are proposed. The issues and
          the reforms proposed to resolve them are mentioned below:
          ***
          iii) To ensure financial sustainability of the power sector, it is
          necessary that the tariff is cost reflective and all the prudent
          cost is pass through. However, it has been observed that
          in many States there is large gap in approved ARR and
          estimated revenue on approved tariff. To discourage such
          practice there is need to make statutory provisions to avoid
          such gap. It is also imperative that liquidation of any such
          gaps in revenue required and estimated approved tariff is
          done in a time bound manner. New rules are proposed to
[2025] 8 S.C.R.                                                         1927

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


           ensure that revenue gap/regulatory assets is not created
           except in extraordinary circumstances and to provide for
           time bound liquidation of the same.”
     67.1 In furtherance of this object and purpose, Rule 23 provides
          as follows:
            “Rule 23. Gap between approved Annual Revenue
            Requirement and estimated annual revenue from
            approved tariff.– The tariff shall be cost reflective and
            there shall not be any gap between approved Annual
            Revenue Requirement and estimated annual revenue
            from approved tariff except under natural calamity
            conditions:
            Provided that such gap, created if any, shall not be more
            than three percent of the approved Annual Revenue
            Requirement:
            Provided further that such gap along with the carrying
            costs at the base rate of Late Payment Surcharge as
            specified in the Electricity (Late Payment Surcharge and
            Related Matters) Rules, 2022, as amended from time
            to time shall be liquidated in maximum three numbers
            of equal yearly installments from the next financial
            year:
            Provided also that any gap between approved Annual
            Revenue Requirement and estimated annual revenue
            from approved tariff existing on the date of notification
            of these rules, along with the carrying costs at the
            base rate of Late Payment Surcharge as specified in
            the Electricity (Late Payment Surcharge and Related
            Matters) Rules, 2022, as amended from time to time
            shall be liquidated in maximum seven numbers of
            equal yearly installments starting from the next financial
            year.”
     67.2 The rule has come into existence after detailed consultation
          with all the stakeholders. It subserves a salutary purpose
          and sets a normative principle in motion. Rule 23 is issued
          in exercise of powers under Section 176, which enables the
          Central Government to make rules to carry out the provisions
1928                                                                                  [2025] 8 S.C.R.

                                   Supreme Court Reports


                of the Act.50 Sub-section (2)(z) of the Section 176 provides that
                without prejudice to the generality of the rule-making power,
                the Central Government may also provide for, by way of a
                rule, “any other matter which is required to be, or may be,
                prescribed”. The expression “prescribed” is defined in Section
                2(52) to mean “prescribed by rules made by the Appropriate
                Government under this Act”. It may sound tautological, but
                the correct way to examine the legal position is to look at the
                provisions with respect to which the Central Government or
                the State Governments may make rules for carrying out the
                provisions of the Act. The province or domain with respect
                to which rules can be made is based on the functions that
                have been assigned to the Government(s) and the Regulatory
                Commissions. Tariff determination is provisioned in Sections
                61 and 62 of the Act, and this must be read with the functions
                of the Regulatory Commissions under Sections 79 and 86
                and the power of the Central and State Commissions to make
                regulations under Sections 178 and 181.
      67.3 The creation of a regulatory asset, being a measure
           undertaken by the Regulatory Commissions as part of tariff
           determination, such exercise is informed by Section 61 read
           with Sections 79 and 86. It is also important to note that
           Rules made by the Central Government under Section 176
           are binding on the Regulatory Commissions when they make
           regulations because Sections 178 and 181 provide that the
           “Commission may make regulations consistent with the Act
           and the rules”. In any event of the matter, the principle that
           one must adopt is that the adverse effect of an overbearing
           regulatory asset extended beyond proportion is an anathema
           to good governance of the Electricity Act. It affects every
           stakeholder, the worst of all being the consumer who is
           burdened, rather over-burdened, from time to time because


50   The relevant portion of Section 176 of the Electricity Act reads:
        “Section 176. (Power of Central Government to make rules): ---
        (1) The Central Government may, by notification, make rules for carrying out the provisions
        of this Act.
        (2) In particular and without prejudice to the generality of the foregoing power, such rules may
        provide for all or any of the following matters, namely: -
        ***
        (z) any other matter which is required to be, or may be, prescribed.”
[2025] 8 S.C.R.                                                           1929

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


                 of the lapses of the regulators or the manipulation of the
                 utilities or the indifference of the government. Therefore, the
                 principle formulated in Rule 23, consistent with Clause 8.2.2
                 of the National Tariff Policy, 2016 and the scheme of the
                 Act, must be the normative principle which must invariably
                 be followed. Wherever Rule 23 is incorporated into the Tariff
                 Determination Regulations of the State Commission, it shall
                 be complied with.
       67.4 We have dealt with the legal regime in detail and have also
            extracted the relevant provisions, rules, regulations, policies,
            instructions and precedents. A combined effect of these can
            be restated as follows: (i) As a first principle, tariff shall be
            cost-reflective; (ii) The revenue gap between the approved
            ARR and the estimated annual revenue from approved tariff
            must be only in exceptional circumstances; (iii) The regulatory
            asset should not exceed a reasonable percentage, which can
            be arrived on the basis of Rule 23 of the Electricity Rules
            that prescribes 3% of the ARR as the guiding principle; (iv)
            If a regulatory asset is created, it must be liquidated within
            a period of 3 years from 01.04.2024, taking Rule 23 as the
            guiding principle; (v) The existing regulatory asset must be
            liquidated in a maximum of 7 years starting from 01.04.2024,
            taking Rule 23 as the guiding principle; and (vi) Regulatory
            Commissions must provide the trajectory and roadmap for
            liquidation of the regulatory asset, which will include a provision
            for dealing with carrying costs. Regulatory Commissions must
            also undertake strict and intensive audit of the circumstances
            in which the distribution companies have continued without
            recovery of the regulatory asset.

       10 (vii). Accountability of the Regulatory Commissions.
68. A Regulatory Commission must perform its functions as per the
    provisions of the Electricity Act, the National Electricity Policy,
    the National Tariff Policy, the relevant rules and regulations made
    under the Act, and the APTEL’s directions51. In performance of its
    functions, the Regulatory Commission’s decisions are subject to


51   Section 121 of the Electricity Act.
1930                                                                [2025] 8 S.C.R.

                                    Supreme Court Reports


       appeal before the APTEL as well as the Supreme Court.52 The APTEL
       has also issued directions under Section 121 from time to time for
       timely determination of tariff, regular truing up, and management
       of a regulatory asset, as indicated hereinabove53. The Regulatory
       Commissions must abide by and implement the directions of the
       APTEL. That is how accountability can be ensured. The need for
       accountability and its dimensions have been explained by this Court
       in Vijay Rajmohan v. CBI54 as follows:
               “34. Accountability in itself is an essential principle of
               administrative law. Judicial review of administrative action
               will be effective and meaningful by ensuring accountability
               of the officer or authority in charge.
               35. The principle of accountability is considered as a
               cornerstone of the human rights framework. It is a crucial
               feature that must govern the relationship between “duty
               bearers” in authority and “right holders” affected by their
               actions. Accountability of institutions is also one of the
               development goals adopted by the United Nations in 2015
               and is also recognised as one of the six principles of the
               Citizens Charter Movement.
               36. Accountability has three essential constituent
               dimensions: (i) responsibility, (ii) answerability, and (iii)
               enforceability. Responsibility requires the identification
               of duties and performance obligations of individuals in
               authority and with authorities. Answerability requires
               reasoned decision-making so that those affected by
               their decisions, including the public, are aware of the
               same. Enforceability requires appropriate corrective
               and remedial action against lack of responsibility
               and accountability to be taken. Accountability has
               a corrective function, making it possible to address
               individual or collective grievances. It enables action
               against officials or institutions for dereliction of duty. It
               also has a preventive function that helps to identify the


52   Sections 111 and 125 of the Electricity Act.
53   In O.P No. 1/2011 (supra) and O.P. Nos. 1 and 2/2012 (supra).
54   (2023) 1 SCC 329.
[2025] 8 S.C.R.                                                               1931

       BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


             procedure or policy which has become non-functional
             and to improve upon it.”

      10 (viii). Powers of the APTEL.
69. Under Section 110 of the Act, the Central Government establishes
    the Appellate Tribunal for Electricity to hear appeals against orders
    of the Adjudicating Officer or the Appropriate Commission. Section
    111 is the statutory remedy for any person aggrieved against an
    order made by the Adjudicating Officer or that of the Appropriate
    Commission as it provides for the appellate power of the Tribunal,
    which reads as follows:
               “Section 111. Appeal to Appellate Tribunal: --- (1) Any
               person aggrieved by an order made by an adjudicating
               officer under this Act (except under section 127) or an
               order made by the Appropriate Commission under this
               Act may prefer an appeal to the Appellate Tribunal for
               Electricity…”
      69.1 While exercising appellate jurisdiction, the APTEL routinely
           interprets the Act and the rules and regulations framed
           thereunder, by which process it systematically evolves legal
           principles. These very principles are applied consistently for
           a structural evolution of sectoral laws. This freedom to evolve
           and interpret laws must belong to the APTEL to subserve
           the regulatory regime for clarity and consistency. In a similar
           context, while interpreting the scope of appellate jurisdiction
           of the Securities Appellate Tribunal against orders of the
           regulator, the SEBI, this Court in SEBI v. Mega Corporation55
           held as under;
               “20. … Being a permanent body, apart from acting as an
               appellate Tribunal on fact, the Tribunal routinely interprets
               the Act, Rules and Regulations made thereunder and
               evolves a legal regime, systematically developed over
               a period of time. The advantage and benefit of this
               process is consistency and structural evolution of the
               sectorial laws.



55   (2023) 12 SCC 802.
1932                                                        [2025] 8 S.C.R.

                          Supreme Court Reports


           21. … This freedom to evolve and interpret laws must
           belong to the Tribunals to subserve the regulatory regime
           for clarity and consistency and it is with this perspective
           that the Supreme Court will consider appeals against
           judgment of the Tribunals on questions of law arising
           from its orders.
           ***
           23.2 … The Tribunal while exercising jurisdiction under
           Section 15-T, apart from acting as an appellate authority
           on fact, also interprets the Act, Rules and Regulations
           made thereunder and systematically evolves a legal
           regime. These very principles are applied consistently
           for structural evolution of the sectorial laws….”
    69.2 The power under Section 111 is that of an appeal and as
         such the decision of the APTEL shall be after re-appreciation
         of facts and by applying the law on the subject. The APTEL
         will also examine the legality, propriety or correctness of the
         orders made by the Regulatory Commissions, and it may also
         on its own motion make such orders as are appropriate for
         adjudication and determination of the case.
    69.3 Apart from Section 111 under which the APTEL is granted
         appellate jurisdiction, it is significant to note that the Parliament
         has also empowered the APTEL with important jurisdiction and
         powers under Section 121, which is reproduced hereinunder
         for ready reference.
                 “Section 121. (Power of Appellate Tribunal): ---
                 The Appellate Tribunal may, after hearing the
                 Appropriate Commission or other interested party, if
                 any, from time to time, issue such orders, instructions
                 or directions as it may deem fit, to any Appropriate
                 Commission for the performance of its statutory
                 functions under this Act.”
    69.4 We can explain the significance of Section 121 in the context
         of the facts of these very writ petitions and civil appeals. The
         facts relating to the performance of DERC present a classic
         case of ‘regulatory failure’. Typically, ‘regulatory failure’ does
[2025] 8 S.C.R.                                                                                            1933

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


                 not come under scrutiny when the APTEL considers appeals
                 from orders of the Regulatory Commissions as the focus
                 at that time is on the merits of the decision made by the
                 Commission. The institutional failures or the shortcomings of
                 the regulatory bodies are often ignored and an appellate forum
                 or even constitutional courts proceed to resolve the issue by
                 addressing the merits of the case. In Lifecare Innovations Pvt.
                 Ltd. v. Union of India56 this Court had an occasion to reflect
                 on this problem and held as follows;
                       “21. Having considered the provisions of the Act and
                       the MSE Procurement Preference Policy, 2012, we
                       are of the opinion that there is no mandatory minimum
                       procurement ‘right’ of an individual MSE. However,
                       there is certainly a statutory foundation for the
                       Procurement Preference Policy, 2012, having force
                       of law as it ‘encapsulates a mandate and discloses a
                       specific purpose’.57 Clause 3 of the policy mandating
                       procurement of 25 per cent of supply from MSEs is
                       simply the statutory duty of the bodies constituted
                       under the Act and the Policy. The significance of
                       creation and establishment of these statutory and
                       administrative bodies is not difficult to conceive. If
                       these institutions and bodies work effectively and
                       efficiently, it is but natural that the purpose and object
                       of the legislation will be achieved in a substantial
                       measure. It is, therefore, necessary to ensure that
                       in the functioning of these bodies, there is efficiency
                       in administration, expertise through composition,
                       integrity through human resources, transparency and
                       accountability, and response-ability through regular
                       review, audits and assessments.


56   2025 INSC 269.
57   Gulf Goans Hotels Co. Ltd v. Union of India, (2014) 10 SCC 673 “…a government policy may acquire
     the ‘force of ‘law’ if it conforms to a certain form possessed by other laws in force and encapsulates a
     mandate and discloses a specific purpose”; Bennett Coleman & Co. v. Union of India (1972) 2 SCC 788
     “What is termed ‘policy’ can become justiciable when it exhibits itself in the shape of even purported
     ‘law’. According to Article 13(3)(a) of the Constitution, ‘law’ includes ‘any Ordinance, order, bye-law, rule,
     regulation, notification, custom or usage having in the territory of India the force of law’. So long as policy
     remains in the realm of even rules framed for the guidance of executive and administrative authorities it
     may bind those authorities as declarations of what they are expected to do under it.”
1934                                                                             [2025] 8 S.C.R.

                                  Supreme Court Reports


                     22. While exercising judicial review of administrative
                     action in the context of Statutes, laws, rules or policies
                     establishing statutory or administrative bodies to
                     implement the provisions of the Act or its policy,
                     the first duty of constitutional courts is to ensure
                     that these bodies are in a position to effectively and
                     efficiently perform their obligations. This approach
                     towards judicial review has multiple advantages. In
                     the first place, while continually operating in the field
                     with domain experts, these bodies acquire domain
                     expertise, the consequence of which would also be
                     informed decision-making and consistency. Further,
                     the critical mass of institutional memory acquired
                     by these bodies will have a direct bearing on the
                     systematic development of the sector and this will
                     also help handling polycentric issues. Thirdly, while
                     continuously being on the field, and having acquired
                     the capability of making real-time assessments about
                     the working of the policies, these bodies will be in
                     a position to visualize course correction for future
                     policymaking.”
      69.5 In the above referred matter, this Court was considering
           the duty to ensure institutional integrity and efficiency of the
           regulators under the MSME Act. A similar approach was
           adopted by this Court in T.N. Godavarman Thirumulpad58
           for reviving and effectuating the environment regulators,
           rather than taking over or routinely reviewing their decision
           making.
      69.6 ‘Regulatory failure’ occurs due to ineffective functioning
           of the Regulatory Commissions, excessive governmental
           interference, or ‘regulatory capture’. We cannot wish away
           these real and imminent dangers that affect effective
           functioning of the Regulatory Commissions. These issues
           could have the effect of completely eclipsing regulatory
           functions, thereby losing the very purpose and object of



58   In Re: T.N. Godavarman Thirumulpad v. Union of India, 2024 INSC 78, paras 27-30.
[2025] 8 S.C.R.                                                                                          1935

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


                 restructuring the electricity sector by unbundling the functions
                 of generation, distribution, and transmission and more
                 importantly, establishing independent regulatory institutions
                 and granting them the exclusive jurisdiction over grant of
                 licenses and tariff determination. Section 121 is intended to
                 ensure that in the functioning of the Regulatory Commissions,
                 there is efficiency in administration, expertise through human
                 resource, integrity through transparency, and accountability
                 and responsibility through review audit and assessment. For
                 enforcing these values, Section 121 empowers the APTEL to
                 issue such orders, instructions or directions as it deems fit,
                 to the Commission for performance of its statutory functions
                 under the Act.
       69.7 The power of the APTEL to issue such orders and directions
            takes within its sweep the power to enforce such orders, as
            provided in Section 120(3) of the Act.59 The power under
            Section 121 is extremely important as it is intended by the
            Parliament that the APTEL must be the guiding force to ensure
            that Regulatory Commissions across the length and breadth
            of the nation perform their statutory functions with efficiency
            and integrity.
       69.8 This position is already recognized by the APTEL, as is evident
            from its order in O.P. No. 1 of 2011, relevant portion of which
            has already been reproduced in this judgment. It is necessary
            to restate the directions issued by the Appellate Tribunal in
            its orders dated 11.11.2011 and 14.11.2013, as it is relevant
            for the present purpose:
                 i.        The APTEL has the power and the duty to issue
                           directions to Regulatory Commissions when they fail to
                           comply with the Act, rules or regulations, fail to perform
                           their statutory functions and duties, or perform the same




59   Section 120(3) of the Electricity Act reads:
           “Section 120. (Procedure and powers of Appellate Tribunal): ---
           ***
           (3) An order made by the Appellate Tribunal under this Act shall be executable by the
           Appellate Tribunal as a decree of civil court and, for this purpose, the Appellate Tribunal shall
           have all the powers of a civil court.”
1936                                                                                  [2025] 8 S.C.R.

                                     Supreme Court Reports


                               negligently, improperly or poorly.60 Such directions are
                               intended to secure compliance with the letter and spirit
                               of the Electricity Act, and the APTEL can monitor the
                               same through periodical status reports and by setting
                               timelines for the Regulatory Commissions.61
                 ii.           Tariff determination is a statutory function entrusted to
                               the Regulatory Commissions, and it must be undertaken
                               on a regular, timely, and annual basis.62
                 iii.          Regulatory Commissions must undertake truing up on
                               a regular basis, immediately at the end of the financial
                               year so that any discrepancies between the ARR
                               and the revenue realised through tariffs is brought to
                               notice and can be rectified in a timely manner.63 This
                               is necessary so that the burden or benefit of present
                               years is not carried forward to future consumers, and
                               delay in truing up could lead to imposition of carrying
                               costs and cash-flow problems for the utility.64
                 iv.           The tariff determined by the Regulatory Commissions
                               must be cost-reflective as per Section 61 of the Electricity
                               Act.65
                 v.            Regulatory Commissions must not ordinarily leave
                               revenue gaps or create regulatory assets, and when it
                               does so in exceptional circumstances, it must comply
                               with the provisions of the Act, rules and regulations on
                               the issue;66
                 vi.           In case a Regulatory Commission creates a regulatory
                               asset, it must allow carrying costs to the distribution
                               utility, time-bound recovery and a liquidation schedule,
                               and ensure that neither the financial position and liquidity


60   O.P. No. 1/2011 (supra), para 47-48; O.P. Nos. 1 and 2/2012 (supra), para 15.
61   O.P. No. 1/2011 (supra), para 66.
62   O.P. No. 1/2011 (supra), paras 59, 65(i) and (ii); O.P Nos. 1 and 2/2012 (supra), para 15.
63   O.P. No. 1/2011 (supra), para 65(i) and (iii).
64   ibid, para 57.
65   ibid, para 65(iv).
66   ibid, paras 62, 65(iv).
[2025] 8 S.C.R.                                                             1937

        BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


                          of the distribution company nor consumer interests are
                          jeopardised.67
      69.9 We reiterate that the Regulatory Commissions must call for
           ARR, ensure that tariffs are determined, and that truing up
           is conducted in a timely manner, by exercising suo motu
           powers if necessary. In case of non-compliance with these
           directions, the APTEL has the power and duty to call for an
           explanation, ensure accountability, and monitor compliance
           by the Regulatory Commissions. Similarly, the APTEL must
           exercise its powers under Section 121 to ensure that the legal
           principles on regulatory asset laid down by us in paragraph 67.3
           hereinabove are complied with by the Regulatory Commissions,
           and it must monitor the same. In case of non-compliance, the
           APTEL must issue such orders, directions, or instructions to the
           Commissions as may be necessary to hold them accountable.

      11. Conclusions.
70. In the following ten sutras, we have examined the issue relating to
    regulatory asset, its position in the regulatory regime for determination
    of tariff, the duties and accountability of the regulators - the Regulatory
    Commissions and then powers of the Appellate Tribunal for Electricity
    to avert a regulatory failure.
      I.      Electricity is a public good. Its generation, transmission, and
              distribution are statutorily regulated to ensure access to supply,
              on a non-rival and non-exclusive basis.
      II.     Being a material resource within Article 39 of the Constitution
              of India, Part-IV of the Constitution must inform the generation,
              transmission, and distribution of electricity.
      III.    The statutory regulators, i.e. the Central and State Regulatory
              Commissions alongwith Union and State Governments and
              other stakeholders are equally bound by the mandate under
              Part-IV of the Constitution for its equitable distribution. This duty
              is predicated on the independent, efficient, objective functioning
              of the electricity commissions. They must guard themselves
              against ‘regulatory failure’ and in particular ‘regulatory capture’.


67   ibid, para 62(iv); O.P. Nos. 1 and 2/2012, para 38.
1938                                                         [2025] 8 S.C.R.

                         Supreme Court Reports


          The interpretation of the powers and function of the Regulatory
          Commissions have to be such that there is no regulatory
          vacuum, in that there is no unallocated residue of power of
          regulation.
    IV.   Tariff determination is a regulatory function and it is the exclusive
          province of the Regulatory Commissions. Tariff determination
          involves multiple variables requiring the regulators to act with
          expertise and also with certain amount of flexibility. Creation
          of regulatory asset is a ‘measure’ that the Commission adopts
          for good governance of tariff. It is also a recognition of revenue
          recoverable by distribution companies, and as such, it is an
          enforceable right, though only through tariff determination for
          later years. This ‘measure’ gives rise to correlative obligations
          of the Regulatory Commissions to manage it efficiently and
          allow easy liquidation.
    V.    Disproportionate increase and long pending regulatory asset
          depict a ‘regulatory failure’. It has serious consequences on all
          stakeholders and the ultimate burden is only on the consumer.
    VI.   Laws encompassing the creation, continuation, and liquidation
          of a ‘regulatory asset’ are located in the Act, National Tariff
          Plan and Policy, Rules, and Regulations made under the Act,
          as interpreted by the APTEL. The combined effect of this legal
          regime is the statutory obligation on the regulator(s).
    VII. Ineffective and inefficient functioning of the Regulatory
         Commissions, coupled with acting under dictation can lead to
         regulatory failure. The commissions are accountable for their
         decisions, and they are subject to judicial review.
    VIII. Apart from examining the legality and propriety of the orders
          of the Commissions in appeal, the APTEL has extraordinary
          powers under Section 121 to issue orders, instructions or
          directions for effective enforcement of the regulatory regime.
          This is one of the most important powers allocated to APTEL
          by the Parliament.
    IX.   We have affirmed the limits of creation, continuation and
          liquidation of the regulatory asset, recognised the obligations
          of the Regulatory Commissions, and directed that they will be
[2025] 8 S.C.R.                                                        1939

      BSES Rajdhani Power Ltd. & Anr. v. Union of India and Ors.


            accountable and subject to such orders, instructions or directions
            as the APTEL may issue in this regard under Section 121.
     X.     The regulatory regime under the Act is a complete code
            enunciating rights, prescribing obligations, and laying down the
            mechanism for course correction. The effectiveness of these
            laws will be reflected in the will to enforce them.

     12. Directions.
71. For the reasons state above, we issue the following directions:
     (i)    As a first principle, tariff shall be cost-reflective;
     (ii)   The revenue gap between the approved ARR and the estimated
            annual revenue from approved tariff may be in exceptional
            circumstances;
     (iii) The regulatory asset should not exceed a reasonable
           percentage, which percentage can be arrived on the basis of
           Rule 23 of the Electricity Rules that prescribes 3% of the ARR
           as the guiding principle;
     (iv) If a regulatory asset is created, it must be liquidated within a
          period of 3 years, taking Rule 23 as the guiding principle;
     (v)    The existing regulatory asset must be liquidated in a maximum
            of 4 years starting from 01.04.2024, taking Rule 23 as the
            guiding principle;
     (vi) Regulatory Commissions must provide the trajectory and
          roadmap for liquidation of the existing regulatory asset, which
          will include a provision for dealing with carrying costs. Regulatory
          Commissions must also undertake strict and intensive audit of
          the circumstances in which the distribution companies have
          continued without recovery of the regulatory asset;
     (vii) Regulatory Commissions shall in general follow the principles
           governing creation, continuation and liquidation of the regulatory
           asset, as laid down in paragraph 70, and also abide by the
           directions of the APTEL summarised in paragraph 69.8;
     (viii) The APTEL shall invoke its powers under Section 121 and
            issue such orders, instructions or directions as it may deem
            fit to the Regulatory Commissions for performance of their
1940                                                      [2025] 8 S.C.R.

                           Supreme Court Reports


            duties with respect to regulatory asset as enunciated by us in
            this judgment and as per the orders of the APTEL in O.P. No.
            1/2011 dated 11.11.2011 and O.P. Nos. 1 and 2/2012 dated
            14.11.2013.
    (ix) The APTEL shall register a suo moto petition under Section
         121 of the Act to monitor implementation of above directions
         (v) and (vi) till the conclusion of the period mentioned therein.
72. With these directions, the present writ petitions in W.P. (C) No.
    104/2014, W.P. (C) No. 105/2014 and W.P. (C) No. 1005/2021 and the
    present civil appeals in C.A. No. 4010/2014 and C.A. No. 4013/2014
    against the APTEL’s order dated 11.03.2014 stand disposed of.

    Result of the case: Directions issued.




    †
        Headnotes prepared by: Divya Pandey


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Regulatory asset"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.