Created byFuzzy Cloud

Supreme Court of India

THE HP POWER TRANSMISSION CORPORATION LTD.versusM/S BRUA HYDROWATT PVT. LTD. & ORS.

Citation
2025 INSC 680
Decided
14 May 2025
Disposal
Appeal(s) allowed

Holding

A party not privy to a contract cannot be held liable under that contract; therefore the APTEL erred and the State Commission’s order holding BHP liable for the Bay cost is restored.

Summary

The Himachal Pradesh Power Transmission Corporation Ltd (HPPTC) built a 66 kV Bay at Urni for three generating companies and sought the full construction cost from Brua Hydrowatt Pvt Ltd (BHP), the lead partner, under a Connection Agreement dated 02‑07‑2021. BHP argued that the cost should be shared proportionately with the other two generators under an internal tripartite agreement (ITA) dated 27‑12‑2019, and that it could not be made to pay the entire amount. The Himachal Pradesh Electricity Regulatory Commission held BHP liable for the full cost, but the Appellate Tribunal for Electricity (APTEL) reversed that order, exonerating BHP from the other generators' shares. HPPTC appealed, contending that the doctrine of privity prevents it from recovering from parties not privy to the Connection Agreement and that the ITA does not form part of that agreement. The Supreme Court examined the terms of the Connection Agreement, the ITA, and relevant case law on privity, concluding that only BHP, as the sole party to the Connection Agreement, can be held liable for the Bay charges. Consequently, the Court set aside the APTEL judgment and restored the State Commission’s order, allowing HPPTC’s claim against BHP alone.

Issues considered

  • Whether the Appellate Tribunal for Electricity was correct in reversing the State Commission’s order and relieving the respondents from bearing the entire construction cost of the Bay.
  • Whether the appellant can recover dues from the other generating companies despite not being a party to the internal tripartite agreement, in view of the doctrine of privity.
  • How Clause 2.4 and 2.5 of the Connection Agreement should be interpreted with respect to liability for Bay construction and O&M charges.
  • Whether the internal tripartite agreement forms part of, or can be read into, the Connection Agreement for the purpose of cost sharing.

Legislation cited

Headnote

Issue for Consideration Whether the Appellate Tribunal for Electricity was correct in reversing the Order passed by Himachal Pradesh Electricity Regulatory Commission thereby exonerating respondent from bearing the entire construction cost for the Bay. Headnotes† – Whether the appellant can recover dues and other charges despite being a stranger to the internal tripartite agreement (ITA) dated 27.12.2019 among the respondents: Held: The respondents executed an ITA wherein they agreed to pool in the power to be generated from their respective

Subjects

Doctrine of PrivityConnection AgreementTransmission LicenceHydro Electric ProcessStranger to an agreement cannot enforce

Judgment

                 [2025] 5 S.C.R. 1360 : 2025 INSC 680

            The HP Power Transmission Corporation Ltd.
                               v.
                M/s Brua Hydrowatt Pvt. Ltd. & Ors.
                       (Civil Appeal No. 3919 of 2023)
                                  14 May 2025
           [Abhay S. Oka and Augustine George Masih,* JJ.]


                            Issue for Consideration
       Whether the Appellate Tribunal for Electricity was correct in
       reversing the Order passed by Himachal Pradesh Electricity
       Regulatory Commission thereby exonerating respondent from
       bearing the entire construction cost for the Bay.

                                   Headnotes†
       Doctrine of Privity – Whether the appellant can recover dues and
       other charges despite being a stranger to the internal tripartite
       agreement (ITA) dated 27.12.2019 among the respondents:
       Held: The respondents executed an ITA wherein they agreed to
       pool in the power to be generated from their respective generative
       stations at Bay and the entire cost of the terminal, including metering
       arrangements, were to be shared between them in proportion to
       their individual generating capacities – Separately, the appellant
       executed a Connection Agreement with only respondent no. 1,
       wherein respondent no. 1 acted as lead partner of the consortium
       of the respondents, had the liability to pay for cost of construction,
       additional charges, and O&M Charges to the appellant in relation to
       the Bay – Respondent no. 1 was to ensure the payment to be made
       to the appellant and thereafter seek reimbursement in case of non-
       payment of the amount by the other generating companies within
       the time stipulated – Respondent no. 3 defaulted in its payment,
       the appellant raised a demand from the respondent no. 1 citing sole
       liability of the said respondent as per Connection Agreement dated
       02.07.2021 – Since the appellant was not a party to the ITA which
       was executed by and between the respondent no. 1, 2 and 3, thus
       appellant could not have and cannot claim proportionate shares as
       per the installed capacity of the project from Respondent No. 02 and
       Respondent No. 03 – The right, to claim and seek recovery of the
       liability from Respondent No. 02 and Respondent No. 03 would be
* Author
[2025] 5 S.C.R.                                                              1361

            The HP Power Transmission Corporation Ltd. v.
                 M/s Brua Hydrowatt Pvt. Ltd. & Ors.

     only with respondent no. 1 as per the ITA – Appellant is not privy to
     the ITA executed among the respondents, therefore does not have
     any right to claim for dues or liabilities from respondent no. 2 & 3 –
     As ITA does form part and parcel of the Connection Agreement
     executed between appellant and respondent no. 1, the exact wording
     only binds respondent no. 1 for the payment of concerned cost and
     charges – APTEL’s judgment is based upon wrong assumptions and
     misreading of the terms of agreement thereby ignoring the basic
     principle that a party not privity to the agreement or contract cannot
     be, unless the context otherwise makes it apparent, made liable for
     any term(s) and condition(s) unrelated to it.

                              Case Law Cited
     Essar Oil Limited v. Hindustan Shipyard Limited and Others [2015] 6
     SCR 924 : (2015) 10 SCC 642 – relied on.
     Jamna Das v. Pandit Ram Autar Pande and Others, 1911 SCC
     OnLine PC 35 – relied on.
     Tweddle v. Atkinson (1861) 121 ER 762 – relied on.

                                 List of Acts
     Electricity Act, 2003; The Himachal Pradesh Electricity Regulatory
     Commission (Conduct of Business) Regulations, 2005.

                              List of Keywords
     Doctrine of Privity; Connection Agreement; Transmission Licence;
     Hydro Electric Process; Stranger to an agreement cannot enforce.

                             Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3919 of 2023
     From the Judgment and Order dated 17.03.2023 of the Appellate
     Tribunal for Electricity at New Delhi at AN No. 30 of 2023

                         Appearances for Parties
     Advs. for the Appellant:
     Anand K. Ganesan, Nikunj Dayal, Pramod Dayal, Amal Nair,
     Ms. Shivani Verma.
     Advs. for the Respondents:
     Tarun Johri, Ankur Gupta, Vishwajeet Tyagi.
1362                                                       [2025] 5 S.C.R.

                        Supreme Court Reports


                Judgment / Order of the Supreme Court

                                Judgment

     Augustine George Masih, J.

1.   This Civil Appeal assails the Judgment dated 17.03.2023 in Appeal
     No. 30 of 2023 (“Impugned Judgment”) by the Appellate Tribunal for
     Electricity at New Delhi (“APTEL”) which reversed the findings returned
     vide Order dated 27.12.2022, by Himachal Pradesh Electricity
     Regulatory Commission at Shimla (State Commission) in Petition
     No. 35 of 2022, holding M/s Brua Hydrowatt Pvt. Ltd., Respondent
     No.01 herein (“BHP Ltd”) liable to bear the entire cost for Bay at the
     66kV Switching Station at Urni (“Bay”), which was constructed by
     the HP Power Transmission Corporation Limited, Appellant herein
     (“HPPTC Ltd”) as per the Connection Agreement (Revised) dated
     02.07.2021 “(CA dated 02.07.2021”).
2.   The details of the parties before us are that the HPPTC Ltd is
     a transmission licensee responsible for executing transmission
     networks, including transmission lines and sub-stations of 66kV and
     above in the State of Himachal Pradesh. The BHP Ltd, formerly
     known as M/s Contransys Pvt Ltd, is a company incorporated under
     the Companies Act, 1956, and classified as a generating company
     under Section 02 (28) of the Electricity Act, 2003. Respondent No.
     02 and Respondent No. 03, being M/s Darjeeling Power Pvt Ltd
     and M/s Roura Non-Conventional Energy Pvt Ltd respectively, are
     the other generating companies engaged in hydroelectric projects
     within the State of Himachal Pradesh. Respondent No. 04 and 05
     are proforma respondents, being the State Commission and State
     of Himachal Pradesh respectively.
3.   The facts leading to the case are that Government of Himachal
     Pradesh entered into an Implementation Agreement with the HPPTC
     Ltd on 25.07.2006 to establish the Brua Hydro Electric Project
     (“BHEP”), initially with a capacity of 05 MW. The interconnection
     was originally planned at a 33kV single circuit transmission line
     at Karcham in Kinnaur district of Himachal Pradesh. However, the
     Power Purchase Agreement dated 06.04.2009 was revised through
     a Supplementary Power Purchase Agreement on 09.07.2018 to
     increase the capacity to 09 MW at a fixed tariff of INR 2.93 per unit.
[2025] 5 S.C.R.                                                      1363

            The HP Power Transmission Corporation Ltd. v.
                 M/s Brua Hydrowatt Pvt. Ltd. & Ors.

     The connection at Karcham was approved on 03.12.2010 by the
     Himachal Pradesh State Electricity Board Ltd (HPSEBL), but stood
     modified to be connected at Urni instead of Karcham, allowing for
     the Bay in joint mode for the three generating companies i.e. BHEP,
     Shaung and Roura-II Hydro Power Project.
4.   To this effect, an application for connectivity had been submitted by
     the BHP Ltd on 04.07.2012 and stood approved by the HPPTC Ltd
     on 18.03.2013 and 23.04.2013 leading to the Connection Agreement
     dated 04.06.2014, designating Urni as the connection point. Admittedly,
     the HPPTC Ltd informed the BHP Ltd on 04.12.2015 that Bay would
     only be operational after completion of the Urni-Wangtoo 66kV line
     and the Wangtoo sub-station. In the interregnum, it allowed BHP Ltd
     to utilize the 220kV Kahshang Bhaba line circuit at 66kV. Further, in
     pursuance of direction of the HPSEBL, the HPPTC Ltd completed a
     66kV feeder Bay at Nathpa sub-station for interim power evacuation,
     leading to signing of Interim Power Transmission Agreement dated
     23.01.2016, requiring the BHP Ltd to pay INR 0.14 per unit to the
     HPPTC Ltd for providing interim arrangements.
5.   All three generating companies i.e., BHP Ltd, Respondent No.02
     and Respondent No.03 entered into an Internal Tripartite Agreement
     dated 27.12.2019 (ITA dated 27.12.2019) to allow for proportionate
     sharing of transmission charges, including the cost of Bay installed
     by the HPPTC Ltd at Urni. As per the agreement, while the BHP
     Ltd would handle claims for deemed generation and Operation and
     Maintenance Charges (O&M Charges), the other parties to the ITA
     dated 27.12.2019 i.e., Respondent No.02 and Respondent No.03
     would reimburse BHP Ltd.
6.   The HPPTC Ltd and BHP Ltd then entered the CA dated 02.07.2021
     wherein, while the HPPTC Lt d was to manage the interconnection
     to the State’s Transmission Utility System, BHP Ltd was made liable
     for all the payments concerned, including the construction cost for
     the Bay. Subsequently, request was made by BHP Ltd for connection
     to Bay, and the HPPTC Ltd raised a demand for INR 3,42,85,447
     (Rupees Three Crore Forty-Two Lakh Eighty-Five Thousand Four
     Hundred Forty-Seven only) as construction cost for the Bay vide
     Letter dated 24.01.2022.
7.   Against this demand, BHP Ltd wrote to Respondent No.02 and
     Respondent No.03 for the payment of their proportionate shares.
1364                                                           [2025] 5 S.C.R.

                          Supreme Court Reports


     While Respondent No. 02 agreed for transfer of payment, Respondent
     No. 03 responded with their inability to do so at that point in time.
     Consequently, the BHP Ltd wrote Letter dated 10.05.2022 to HPPTC
     Ltd stating that it is willing to deposit the proportionate share for itself
     and that of Respondent No.02, however, Respondent No.03 shall
     pay its proportionate share along with interest subsequently. This
     demand was rejected by the HPPTC Ltd vide Letter dated 30.05.2022,
     citing the sole liability of BHP Ltd under the CA dated 02.07.2021.
8.   This prompted the BHP Ltd to move the State Commission through
     Petition No. 35 of 2022 under Section 86(1)(f) read with Section
     158 and other enabling provisions of the Electricity Act, 2003 and
     Regulations 53, 68, and 70 of the Himachal Pradesh Electricity
     Regulatory Commission (Conduct of Business) Regulations, 2005.
     8A. While dismissing the petition of the BHP Ltd vide Order dated
         27.12.2022, the State Commission observed that BHP Ltd was
         acting as the lead partner of the consortium, while it applied
         for the connection for all three projects and agreed to pay the
         cost of construction, additional charges, and O&M Charges to
         the HPPTC Ltd, with the expectation that the amount would be
         reimbursed by the Respondent No.02 and Respondent No.03
         in their proportionate shares, which aspect of liability had been
         acknowledged by them. The HPPTC Ltd, therefore, rightfully
         issued the invoice(s) to the BHP Ltd, which is responsible and
         liable for payment as per the agreement. Recovery, if any, from
         Respondent No.02 and Respondent No.03 was an internal
         matter between them, and the HPPTC Ltd had no concern.
         While rejecting the contention that the HPPTC Ltd should issue
         separate bills or that HPPTC Ltd must enter into separate O&M
         agreements with the parties concerned, the State Commission
         observed that the BHP Ltd must fulfil its obligations under the
         agreements dated 27.12.2019 and 02.07.2021.
9.   Aggrieved by the said Order, the BHP Ltd moved the APTEL vide
     Appeal No. 30 of 2023 under Section 111 of the Electricity Act, 2003,
     which effected the pronouncement of the Impugned Judgment dated
     17.03.2023. APTEL, while considering the CA dated 02.07.2021,
     observed that the BHP Ltd was liable for construction cost and O&M
     Charges of the Bay on “mutually agreed terms”. A reference was also
     made to the ITA dated 27.12.2019 stipulating that the costs would
[2025] 5 S.C.R.                                                      1365

            The HP Power Transmission Corporation Ltd. v.
                 M/s Brua Hydrowatt Pvt. Ltd. & Ors.

     be shared by the parties in proportion to their individual capacities.
     Furthermore, the Supplementary Power Purchase Agreement dated
     09.07.2018 indicates that the interconnection facilities required for
     the project, including switching equipment, protection, control, and
     metering devices, shall be installed and maintained by the HPPTC
     Ltd at the Bay, with the costs to be shared proportionately by the
     parties. The BHP Ltd had submitted that no specific agreement for
     the payment of charges to the Appellant under Clause 2.4 of the
     CA dated 02.07.2021 was executed, holding that, in the absence
     of such an agreement, the demand for payment of the entire Bay
     charges could not be imposed on it. However, the State Commission
     concluded that the BHP Ltd, acting as the lead partner, had agreed
     to pay these charges, contrary to the assertion.
     9A. Inclined with the assertions of the BHP Ltd, APTEL further
         observed that the Clauses 2.4 and 2.5 of the CA dated
         02.07.2021 do not indicate that the BHP Ltd agreed to pay the
         entire Bay charges and O&M Charges on behalf of Respondent
         No.02 and Respondent No.03, in addition to its own liabilities.
         Furthermore, it does not address the scenario where one of the
         generating companies fails to pay the Bay charges or does not
         commission its project, leaving the lead member responsible for
         the costs and charges of such defaulting generating Company.
         Therefore, the unilateral demand for payment of Bay charges
         by the HPPTC Ltd for liability of other generating companies is
         contrary to the terms of the CA dated 02.07.2021.
     9B. Thereafter, APTEL examined the ITA dated 27.12.2019 and
         while rejecting the contentions of the HPPTC Ltd, observed that
         it cannot place reliance on the said ITA for its benefit without
         being a party therein as it does not form part and parcel of the
         CA dated 02.07.2021, nor does it govern the payment of Bay
         charges. While concluding on the liability of the BHP Ltd, APTEL
         observed that before the State Commission, the other generating
         companies, i.e. Respondent No.02 and Respondent No.03,
         had accepted their liability of the proportionate Bay charges
         and an undertaking to that effect being given by Respondent
         No. 03 should similarly apply to the BHP Ltd, so as to not hold
         it liable for share of other generating companies. The interim
         arrangement for power evacuation should cease once the
         BHP Ltd is connected through the Bay. Respondent No. 03’s
1366                                                      [2025] 5 S.C.R.

                        Supreme Court Reports


          failure to commission its project has led to complications, but
          the BHP Ltd cannot be burdened with additional costs without
          explicit contractual provisions. The Bay charges attributable to
          Respondent No. 03 may be recovered by the HPPTC Ltd after
          its project is commissioned or through other legal remedies.
     9C. Appeal No. 30 of 2023 preferred by BHP Ltd was allowed vide
         Judgment dated 17.03.2023 passed by APTEL; setting aside
         the Order dated 27.12.2022 passed by the State Commission.
         Further directions were issued to HPPTC Ltd to provide
         connection to the BHP Ltd and Respondent No.02 on payment
         of their respective share of charges for the Bay.
10. This resulted in the HPPTC Ltd moving this Court through instant
    Civil Appeal No. 3919 of 2023 assailing the Impugned Judgment
    passed by APTEL. To press their claim, the counsels on behalf of
    the HPPTC Ltd have asserted that even by virtue of the ITA dated
    27.12.2019 it was the BHP Ltd who was liable to act on behalf of
    other two generating companies and the mandate was limited to
    recovery of the proportionate charges by BHP Ltd from the other
    generating companies. It was solely BHP Ltd who was designated
    as the sole applicant in CA dated 02.07.2021 for payment of charges
    and to settle claims of deemed generation for the Bay to the HPPTC
    Ltd. Furthermore, as a stranger to the ITA dated 27.12.2019, HPPTC
    Ltd cannot seek or enforce to recover the other part of charges from
    Respondent No.02 and Respondent No.03 which APTEL failed to
    appreciate while directing HPPTC Ltd to do so.
11. Contesting the assertions by the HPPTC Ltd, the counsels for the
    BHP Ltd submitted that in pursuance of the Impugned Judgment, the
    parties entered into an agreement for the O&M of interconnection
    facilities as stipulated in Clause 2.5 of the CA dated 02.07.2021 which
    included provisions for a separate arrangement for the execution,
    operation and maintenance (O&M) of the Bay. Moreover, proportionate
    share of liability arising as against the BHP Ltd has been deposited
    and acknowledged by the HPPTC Ltd vide Letter dated 01.04.2023
    and the connection has been provided at the Bay. Having complied
    with the Impugned Judgment, the HPPTC Ltd is now precluded from
    challenging it, rendering this Civil Appeal infructuous. Moreover,
    separate bills have been raised by the HPPTC Ltd for the three
    generating companies vis-à-vis payment of provisional O&M Charges
    for April 2023 to March 2024. Therefore, it is asserted that the new
[2025] 5 S.C.R.                                                         1367

            The HP Power Transmission Corporation Ltd. v.
                 M/s Brua Hydrowatt Pvt. Ltd. & Ors.

     Agreement dated 01.04.2023 supersedes the terms of ITA dated
     27.12.2019 and reveals an acceptance on the part of the HPPTC
     Ltd to treat the three projects separately.
     11A. It was further contended on behalf of the BHP Ltd that the APTEL
          rendered its decision after thoroughly examining the relevant
          facts and circumstances and that the Order dated 27.12.2022 as
          passed by the State Commission was based on a fundamentally
          erroneous interpretation of the terms and conditions of the CA
          dated 02.07.2021 and other pertinent documents.
12. In response to these contentions, it is argued on behalf of the
    HPPTC Ltd that execution of O&M Agreement is in compliance on
    the directions by APTEL as it could not have risked contempt in case
    of non-compliance as there was no stay on the Impugned Judgment
    and same does not imply any concession on part of the HPPTC Ltd.
    Moreover, the BHP Ltd has not paid the Bay charges and while the
    Respondent No.02 attempted to pay its proportionate share, it was
    refused by the HPPTC Ltd because it had no locus to receive the
    amount owing the CA dated 02.07.2021 being only between the
    HPPTC Ltd and BHP Ltd and accordingly, such a payment does not
    impact the liability of the latter to pay charges for the Bay.
13. No submissions were made on behalf of other parties in the instant
    Civil Appeal.
14. We have heard the submissions on behalf of the parties at length.
15. Before perusing the legal conundrum of singular or shared liability
    of the BHP Ltd as against the CA dated 02.07.2021, it is pertinent to
    analyze the provisions of the terms negotiated and agreed to therein.
16. A bare perusal of the CA dated 02.07.2021 indicates that Respondent
    No.02 and Respondent No.03. are not privy to the agreement entered
    between the HPPTC Ltd and the BHP Ltd. The HPPTC is referred
    to as STU and BHP Ltd as Applicant in the CA dated 02.07.2021.
    The preamble of the said agreement reads:
           “STU and Applicant are hereinafter collectively referred to
           as “Parties” and individually as “Party”.
           WHEREAS:
           (A) The Applicant has applied to the STU for connection
           of the Brua (9.00 MW) Small Hydro Electric Project facility
1368                                                        [2025] 5 S.C.R.

                         Supreme Court Reports


          in joint mode with Shaung (3.00MW) SHP and Roura-II
          (24.00MW) SHP to the STU Transmission System and use
          of the STUs Transmission system to transmit electricity to
          and or from the Facility through the Intrastate Transmission
          system.
          (B) The STU has agreed to the connection of the Brua
          (9.00 MW) Hydro Electric Project facility in joint mode
          with Shaung (3.00MW) SHP and Roura-II (24.00MW)
          SHP to the STU’s System and Communication System
          (via the applicant’s Stie – Related Connection Equipment)
          at the Connection Point i.e. 66kV Feeder Bay at 66kV
          Switching Station, Urni through 66kV S/C Line in joint
          mode with Shaung and Roura-II SHPs using the (wave
          length) Transmission and Communication System of the
          STU, to transmit electricity as well as real time data to
          and or from the facility through the STU’s Transmission
          and Communication System.”
17. The General Conditions for Connectivity are laid down in paragraph 01
    of the CA dated 02.07.2021, and the relevant obligations are as under:
          “1.1 (b) The applicant, shall be responsible for planning,
          design, construction, and safe and reliable operation
          of its own equipments in accordance with the Central
          Electricity Authority (Technical Standards for Connectivity
          to the Grid) Regulations, 2007, Central Electricity Authority
          (Technical Standards for Construction of electrical plants
          and electric lines) Regulations, Central Electricity Authority
          (Grid Standards) Regulations, Indian Electricity Grid Code
          (IEGC) and other statutory provisions.
          (c) The applicant shall provide necessary facilities for voice
          & data communication for transfer of real time operational
          data such as voltage, frequency, real and reactive power
          flow, energy, and status of circuit breaker & isolators
          positions, transformer taps and other parameters from
          their station to Data Collection Point (DCP) of STU as
          per CGC/IEGC. STU shall provide access to applicants
          data transfer through communication network in case
          spare channels are available on mutually agreed terms.
          The location of DCP of STU shall be the nearest station
[2025] 5 S.C.R.                                                             1369

            The HP Power Transmission Corporation Ltd. v.
                 M/s Brua Hydrowatt Pvt. Ltd. & Ors.

           connected electrically where wideband communication
           capacity STU is available.
           Additional communication system from DCP to the
           HPSLDC shall be the responsibility of STU however its
           cost shall be borne by the applicant. The responsibility of
           data transfer shall be that of the applicant.”
18. On the liability to pay the charges and costs, it was agreed in Clause
    02 of the CA dated 02.07.2021 that:
           “2 Agreement to Pay Charges and Costs

           2.1 Agreement to Monthly Transmission Tariff
           The applicant declares that it shall pay the Monthly
           Tariff including HPSLDC charges, for use of Intra State
           Transmission system, as and when long term access,
           Medium-term open access or short-term open access is
           availed by the applicant, in accordance with the relevant
           regulations of HPERC in this regard.

           2.2 Agreement to additional costs
           The applicant declares that it shall pay the cost towards
           modification/alterations to the Infrastructure of STU or Intra-
           State transmission licensee/Distribution Licensee other
           than the STU, as the case may be, for accommodating
           the proposed connection as specified in the letter of STU
           furnishing connection details.

           2.3 Agreement to pay for damages
           The applicant declares that it shall pay/make good
           damages, if any, caused by the customer to the property
           of the STU or Intra-State transmission licensee/Distribution
           Licensee other than the STU, as the case may be, which
           has been notified by the STU within reasonable time of
           its occurrence, during the course of control, operation and
           maintenance of the equipment.

           2.4 Agreement to pay Charges for construction of Bays:
           The applicant will execute an agreement with STU for the
           erection of equipment of applicant or intra-state transmission
1370                                                      [2025] 5 S.C.R.

                        Supreme Court Reports


          licensee/Distribution Licensee in the substation premises
          of the STU for construction of bays, if required. For this
          purpose the applicant shall pay charges to the STU on
          mutually agreed terms.

          2.5 Agreement to pay O&M Charges:
          The applicant shall pay O&M charges to the STU on
          mutually agreed terms for the bay equipment of applicant
          being operated & maintained by the STU in their substation.
          These O&M charges will be governed time to time as per
          the mutually agreed terms.”
19. BHP Ltd has asserted that the ITA dated 27.12.2019 is relevant to
    the terms and conditions of the CA dated 02.07.2021 and also forms
    a part while interpreting the latter. On that note, the relevant terms
    of the former agreement between the three generating companies
    i.e., the BHP Ltd, Respondent No.02 and Respondent No.03 are
    as follows:
          1. That all the IPPs shall pool in the power to be generated
          from their generating stations at the common 66kV terminal
          bay at proposed 66/220kV sub-station at Urni of HPPTCL
          in District Kinnaur, Himachal Pradesh.
          2. That the entire cost of common 66kV terminal bay
          including metering arrangements required to be in place
          for metering purpose etc. shall be shared by the IPPs in
          proportionate to their individual generating capabilities.
          4. That the cost of operation & Maintenance of the
          Interconnection facilities at the HPPTCL grid as per the
          claim to be raised by HPPTCL shall be borne by the IPPs
          injecting power therein in proportionate to the installed
          capacity of project. M/s Roura Non Conventional Energy
          Private Limited and M/s Darjeeling Power Private Limited
          shall reimburse the proportionate O&M charges to M/s
          Brua Hydro Watt (P) Limited within 15 days of raising
          the bills thereof. M/s Brua Hydro Watt (P) Limited shall
          ensure that the payment of O&M charges received from
          M/s Roura Non Conventional Energy Private Limited and
          M/s Darjeeling Power Private Limited along with their own
          share of O & M charges are deposited with the HPPTCL
[2025] 5 S.C.R.                                                           1371

            The HP Power Transmission Corporation Ltd. v.
                 M/s Brua Hydrowatt Pvt. Ltd. & Ors.

           within 3 days. Any claim arising out of delayed remission
           of O&M charges after receipt of the same from M/s
           Roura Non Conventional Energy Private Limited and M/s
           Darjeeling Power Private Limited shall be to the account
           of M/s Brua Hydro Watt (P) Limited.”
           5. That the IPPs jointly nominate M/s Brua Hydro Watt (P)
           Limited to settle the claim, if any, of the deemed generation
           of the projects with the HPSEBL in line with the decision
           of HPERC in the Case no. 254/2006, M/s Sri Sai Krishna
           Hydro Energies Private Limited & Others Versus Himachal
           Pradesh State Electricity Board Shimla (Annexure-B),
           The internal settlement of the deemed generation claims
           amongst the IPPs shall be made in proportion to the
           installed capacities of the respective IPPs.”
20. A perusal of the terms of the CA dated 02.07.2021, as referred to
    above would indicate that BHP Ltd moved an application before the
    HPPTC Ltd for seeking connection to the Bay and use of the said
    system to transmit electricity. This was done not only on behalf of
    itself, but in joint mode with Respondent No.02 and Respondent
    No.03. The said request was accepted by the HPPTC Ltd, subject to
    certain conditions as had been laid down. The relevant provision, as
    far as the present issue is concerned, is covered by Clause 02 of the
    said agreement which deals with the payment of charges and costs.
21. As per this Clause 02, all the charges were to be paid by the applicant
    therein i.e. the BHP Ltd, which included not only the monthly tariff but
    the payment of costs towards modification/alteration of infrastructure,
    the other charges including the payment of damages if caused by
    the customer to the property of the HPPTC Ltd as also the charges
    of construction of the Bay. Even the payment of O&M Charges were
    to be made by the BHP Ltd. These terms make it clear that the sole
    liability was that of BHP Ltd not only in its individual capacity but
    also on behalf of the Respondent No.02 and Respondent No.03. It
    would not be out of way to mention here that CA dated 02.07.2021
    was entered into between the HPPTC Ltd and BHP Ltd only while
    Respondent No.02 and Respondent No.03 were not a party to the
    said agreement.
22. As has been insisted upon and asserted by the Counsel for the BHP
    Ltd, the ITA dated 27.12.2019, which had been entered into between
1372                                                       [2025] 5 S.C.R.

                         Supreme Court Reports


     the three generating companies i.e., BHP Ltd, Respondent No.02,
     and Respondent No.03 was an internal arrangement between them
     where the HPPTC Ltd was not a party. The relevant provisions of
     the ITA dated 27.12.2019, as have been reproduced above, leave
     no manner of doubt that as per the said agreement all three of them
     had agreed to pool in the power to be generated from their respective
     generative stations at Bay of the HPPTC Ltd. The entire cost of
     the terminal, including metering arrangements, were to be shared
     between them in proportion to their individual generating capacities.
23. Cost of operation and maintenance of the interconnection facilities
    at the grid was to be borne by all three of them as would be raised
    by the HPPTC Ltd as per their proportionate installation capacity of
    the project. BHP Ltd had taken up the responsibility to be the joint
    nominee for all three of them to settle the claim, if any, of the deemed
    generation of projects with the HPPTC Ltd. It clearly laid down that
    Respondent No.02 and Respondent No.03 would reimburse the
    proportionate amount due as per the agreement to BHP Ltd within
    15 days of raising of the bills by the HPPTC Ltd. BHP Ltd was to
    ensure the payment to be made to the HPPTC Ltd and thereafter
    seek reimbursement in case of non-payment of the amount by
    the other generating companies within the time stipulated. What,
    therefore, turns out is that the primary responsibility had been taken
    upon itself by BHP Ltd, taking the lead for the other two generating
    companies and thereafter recover the proportionate amount as
    per the respective installed capacity of the project of the other two
    generating companies i.e. Respondent No.02 and Respondent No.03.
24. Liability, if any, being therefore upon BHP Ltd as per the CA dated
    02.07.2021 with HPPTC Ltd not being a party to ITA dated 27.12.2019,
    the latter could not have and cannot claim proportionate shares as
    per the installed capacity of the project from Respondent No.02 and
    Respondent No.03. The right, if any, of the claim and recovery of
    the liability from Respondent No.02 and Respondent No.03 would
    be only with BHP Ltd. The HPPTC Ltd, therefore, has rightly put
    forth its claim to BHP Ltd.
25. Having considered the provisions of the contracts/agreements as
    above, we should ideally be considerate of the impact of the liability
    of the charges under the CA dated 02.07.2021, if so imposed on
    Respondent No.02 and Respondent No.03 through existing legal
    doctrines and decisions of the Courts.
[2025] 5 S.C.R.                                                         1373

              The HP Power Transmission Corporation Ltd. v.
                   M/s Brua Hydrowatt Pvt. Ltd. & Ors.

26. The Doctrine of Privity, as originally introduced in the decision of
    Tweddle v. Atkinson1 and acknowledged by the Privy Council in
    Jamna Das v. Pandit Ram Autar Pande and others2, still holds
    relevance when it comes to contractual rights and obligations of
    parties inter se. In a similar factual backdrop, as in this case, vis-à-vis
    relationship between the parties and their ability to sue for recovery
    thereof, a three-Judge Bench of this Court in Essar Oil Limited v.
    Hindustan Shipyard Limited and Others3 denied the Appellant
    therein, to sue ONGC for recovery of payment in its capacity as
    a sub-contractor, as it was not privy to the contract between the
    ONGC and Respondent-Contractor. Their reliance on some direct
    payments made to it by ONGC were observed to be not sufficient
    to establish privity of contract.
27. In the light of the above legal position, if the contentions of the BHP
    Ltd are accepted by this Court, HPPTC Ltd would technically have no
    legal remedy to recover its dues or other charges from Respondent
    No.02 and Respondent No.03 in event of a default as they are not
    under any contractual obligation to discharge any liability towards
    the HPPTC Ltd vis-à-vis the Bay.
28. Therefore, it is our opinion that the APTEL was incorrect in not
    considering the absence of privity of Respondent No.02 and
    Respondent No.03 to the CA dated 02.07.2021, especially when it
    went on to observe that the ITA dated 27.12.2019 cannot be relied
    upon by the HPPTC Ltd for its contentions as it does not form part
    and parcel of the CA dated 02.07.2021. An equivalence should have
    then been drawn by the APTEL to consider the fact that Respondent
    No.02 and Respondent No.03, although beneficiaries to the liability of
    the HPPTC Ltd to construct, operate and maintain the Bay through
    the CA dated 02.07.2021, could not have been held liable for the
    charges when explicit wording in the CA dated 02.07.2021 only binds
    BHP Ltd for the payment of concerned cost and charges.
29. If that be so, as per the terms of agreement, the Impugned Judgment
    of the APTEL is based upon wrong assumptions and misreading of
    the terms of agreement ignoring the basic principle that a party not


1   (1861) 121 ER 762
2   1911 SCC OnLine PC 35
3   (2015) 10 SCC 642
1374                                                             [2025] 5 S.C.R.

                             Supreme Court Reports


     privity to the agreement or contract cannot be, unless the context
     otherwise makes it apparent, made liable for any term(s) and
     condition(s) unrelated to it.
30. Accordingly, the decision rendered by the State Commission is good
    in law, and the observations herein above mandate that the Impugned
    Judgment as passed by the APTEL be set aside.
31. Therefore, the instant Appeal is allowed in favour of the HPPTC Ltd
    to the effect that the Impugned Judgment dated 17.03.2023 passed
    by the APTEL is set aside and the Order dated 27.12.2022 passed
    by the State Commission is restored.
32. There shall be no order as to costs.
33. Pending application(s), if any, stand disposed of.

     Result of the case: Appeal allowed.



     †
         Headnotes prepared by: Gaurav Upadhyay, Hony. Associate Editor
                                 (Verified by: Abhinav Mukerji, Sr. Adv.)


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Doctrine of Privity"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

THE HP POWER TRANSMISSION CORPORATION LTD. versus M/S BRUA HYDROWATT PVT. LTD. & ORS. — 2025 INSC 680 - Legal Desk AI