POWERGRID CORPORATION OF INDIA LIMITEDversusCENTRAL ELECTRICITY REGULATORY COMMISSION & ORS.
- Citation
- 2025 INSC 626
- Decided
- 4 May 2025
- Disposal
- Dismissed
- Bench
- ABHAY S OKA
Holding
Regulation 53 of the Tariff Regulations does not allow additional capitalisation for replacement of damaged transformers, and the self‑insurance policy covers the loss, rendering the Tribunal's orders proper.
Summary
Powergrid Corporation of India Ltd., a central transmission utility, suffered failure of three inter‑connecting transformers (ICTs) in its Rihand I system in 2006 and temporarily replaced them with transformers from its Rihand II system. Powergrid sought de‑capitalisation of the removed ICTs and additional capitalisation for the new/repaired transformers, invoking Regulation 53 of the CERC Tariff Regulations, and also claimed that its self‑insurance policy covered the loss. The Central Electricity Regulatory Commission (CERC) rejected both claims, directing Powergrid to fund the net cost from its self‑insurance reserve, and the Appellate Tribunal affirmed CERC’s order. Powergrid appealed to the Supreme Court, raising three questions: (1) whether the Tribunal and CERC were justified in rejecting the additional capitalisation claim, (2) whether the self‑insurance policy covered the replacement cost, and (3) whether a revised availability certificate should be directed. The Court held that Regulation 53 does not permit additional capitalisation for replacement of damaged ICTs and that the self‑insurance policy does cover fire‑related losses, making the Tribunal’s directions proper. Consequently, the Court found the third question moot and dismissed both appeals.
Issues considered
- Whether the Appellate Tribunal and CERC were justified in rejecting Powergrid's claim of additional capitalisation for replacement of damaged inter‑connecting transformers.
- Whether Powergrid's self‑insurance policy covered the cost of replacement of the damaged transformers.
- Whether the Member Secretary of the Northern Regional Power Committee should be directed to issue a revised availability certificate for the transmission assets.
Legislation cited
Headnote
Issue for Consideration The questions arose for consideration whether the appellate tribunal and Central Electricity Regulatory Commission justified in rejecting the appellant’s claim of additional capitalization due to replacement of the damaged the self-insurance policy of the appellant covered the cost of replacement of the damaged ICTs; and whether the Member Secretary of NRPC should have been directed by the appellate tribunal to issue revised availability certificate for the transmission assets. Headnotes† Central Electricity
Subjects
Judgment
[2025] 6 S.C.R. 123 : 2025 INSC 626
Powergrid Corporation of India Limited
v.
Central Electricity Regulatory Commission & Ors.
(Civil Appeal No(s). 5857-5858 of 2011)
05 May 2025
[Abhay S. Oka and Ujjal Bhuyan,* JJ.]
Issue for Consideration
The questions arose for consideration whether the appellate tribunal
and Central Electricity Regulatory Commission justified in rejecting
the appellant’s claim of additional capitalization due to replacement
of the damaged Inter-connecting Transformers-ICTs; whether the
self-insurance policy of the appellant covered the cost of replacement
of the damaged ICTs; and whether the Member Secretary of NRPC
should have been directed by the appellate tribunal to issue revised
availability certificate for the transmission assets.
Headnotes†
Central Electricity Regulatory Commission (Terms and
Conditions of Tariff) Regulations, 2004 – Reg. 53 – Additional
capitalisation – Claim of – Appellant owned and operated
transmission systems in the northern region-R I and R II –
Inter-connecting transformers in the R I transmission system
got burnt and damaged due to internal faults – Transformers
from R II temporarily taken out and diverted to R I – Appellant
restored the transformers at R-1 and ICTs taken out from
R II were restored by new/repaired transformers – Petition
by the appellant before the respondent-CERC claiming de-
capitalization for the transformers taken out from R II and
additional capitalization for the new/repaired transformer
installed at R I – Claim not allowed by CERC holding that the
net cost for such replacement has to be met out from the
insurance fund reserve maintained by the appellant under
the internal insurance policy; and also did not accede to the
prayer of the appellant for giving directions to the Northern
Regional Power Committee for issuance of revised availability
certificate – Appeal thereagainst, dismissed by the appellate
tribunal – Interference:
* Author
124 [2025] 6 S.C.R.
Supreme Court Reports
Held: Not called for – Appellate tribunal and CERC justified in rejecting
the appellant’s claim of additional capitalization due to replacement
of the damaged ICTs – Reg. 53 provides that additional capital
expenditure incurred after the commercial operation date and upto
the cut-off-date may be admitted by the CERC if such expenditure
relates to deferred liabilities, deferred works, procurement of initial
spares, etc. – Reg. 53 does not include within its scope replacement
of transformers due to damage or failure – As per Reg. 53(2)(iv)
any additional work/services which becomes necessary for the
efficient and successful operation of the project but not included in
the original project cost may be admitted by CERC as additional
capital expenditure – All that the appellant had done was diversion
and replacement of transformers which cannot be construed as
doing any additional work/services u/Reg.53(2)(iv) – Nothing on
record to show that prior to the breakdown of transformers the
transmission systems were in bad shape or had started wearing
out – As regards the self-insurance policy, the loss caused to the
appellant by fire would be covered by the policy as it covered all fires
which caused loss without any exception and as all the ICTs were
operating until those got burnt – Proximate cause for the damage
to the transformers is the implosion/explosion in the internal/external
machinery of the transformers which caused fire – Self-insurance
policy of the appellant covered the cost of replacement of the
damaged ICTs – Appellate tribunal justified in directing the appellant
to finance the net cost from the self-insurance fund reserve as part
of the operation and maintenance charges – As decapitalization and
additional capitalization of the replaced ICTs have not been allowed,
issuance of direction to NRPC for revised availability certificate for
the transmission assets does not arise. [Paras 28-35, 37-39]
Case Law Cited
New India Assurance Company Limited v. Zuari Industries Limited
[2009] 13 SCR 1101 : (2009) 9 SCC 70 – relied on.
Gujarat Urja Vikas Nigam Limited v. Renew Wind Energy (Rajkot)
Private Limited [2023] 7 SCR 670 : 2023 SCC OnLine SC 411 –
held inapplicable.
List of Acts
Electricity Act, 2003; Electricity Regulatory Commission Act, 1998;
Central Electricity Regulatory Commission (Terms and Conditions
of Tariff) Regulations, 2004.
[2025] 6 S.C.R. 125
Powergrid Corporation of India Limited v.
Central Electricity Regulatory Commission & Ors.
List of Keywords
Electricity; Central transmission utility; Transmission systems; Inter-
State Transmission Systems; De-capitalization of transformers;
Additional capitalization; Replacement for damaged transformers;
Northern Regional Power Committee; Inter-connecting Transformers;
Revision tariff; Self-insurance reserve policy; Fire risk; Machinery
breakdown; Self-insurance reserve; Proximate cause; Revised
availability certificate; Central Electricity Regulatory Commission;
Cost of replacement of the damaged ICTs; Certificate for transmission
assets; New/repaired transformers; Approval of transmission charges;
Additional capital expenditure.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No(s). 5857-5858
of 2011
From the Judgment and Order dated 23.03.2011 of the Appellate
Tribunal for Electricity in Appeal Nos. 91-92 of 2009
Appearances for Parties
Advs. for the Appellant:
Ms. Swapna Seshadri, Pramod Dayal, Nikunj Dayal, Utkarsh Singh,
Ms. Sneha Singh Baghel.
Advs. for the Respondents:
Pradeep Misra, Daleep Dhyani, Manoj Kumar Sharma.
Judgment / Order of the Supreme Court
Judgment
Ujjal Bhuyan, J.
This order will dispose of both Civil Appeal Nos. 5857 and 5858 of
2011.
2. Since both the civil appeals filed by the appellant under Section
125 of the Electricity Act, 2003 arise out of the common order dated
23.03.2011 passed by the Appellate Tribunal for Electricity in Appeal
Nos. 91-92 of 2009 with the issue being inter-related and between
the same parties, both the appeals were heard together and are
being disposed of by this common order.
126 [2025] 6 S.C.R.
Supreme Court Reports
3. Appellant in this case is Powergrid Corporation of India Limited.
4. In Appeal No. 91 of 2009, the challenge made was to the order
dated 03.02.2009 passed by the Central Electricity Regulatory
Commission in Petition No. 68 of 2008. In Appeal No. 92 of 2009,
challenge made was to the order dated 03.02.2009 passed by the
Central Electricity Regulatory Commission in Petition No. 80/2008.
Both Appeal Nos. 91 and 92 of 2009 were dismissed by the Central
Electricity Regulatory Commission vide the order dated 23.03.2011
(impugned order).
5. Hence, the two appeals.
6. This Court by order dated 01.08.2011 had issued notice.
7. Relevant facts may be briefly noted.
8. Appellant Powergrid Corporation of India Limited (for short
‘Powergrid’) is a public sector undertaking of the Government
of India. It is mainly engaged in the business of transmission of
power through its transmission network. It discharges its statutory
functions under the Electricity Act, 2003 and transmits electricity
throughout the country. On the other hand, respondent No. 1 is
the Central Electricity Regulatory Commission. It is a statutory
body established under the provisions of the erstwhile Electricity
Regulatory Commission Act, 1998 (since repealed). After coming into
force of the Electricity Act, 2003, the Central Electricity Regulatory
Commission (‘CERC’ for short) began to exercise its functions
under the said statute.
9. At the relevant point of time, appellant was a central transmission
utility responsible for establishing transmission assets of Inter-
State Transmission Systems (‘ISTS’ for short) dealing with
planning and transmission of electricity. Amongst others, appellant
owned and operated two transmission systems in the northern
region: Rihand I and Rihand II. Rihand I comprises of Mandola
and Ballabgarh sub-stations whereas Rihand II comprises of
Kaithal, Mainpuri and Abdullapur sub-stations. Rihand I had three
Inter-connecting Transformers (‘ICT’ for short): one at Ballabgarh
and two at Mandola. Rihand II had four ICTs: two at Kaithal and
two at Mainpuri.
10. Between 28.04.2006 and 09.05.2006, all the three transformers in the
Rihand I transmission system failed and broke down. In fact, those
[2025] 6 S.C.R. 127
Powergrid Corporation of India Limited v.
Central Electricity Regulatory Commission & Ors.
were burnt and damaged due to internal faults. Considering that it
was peak summer season with high anticipated load demand in the
National Capital Territory of Delhi, the transformers were required to
be replaced immediately. According to the appellant, procurement of
new transformers would have taken a long time. Therefore, it was
decided to temporarily take out one transformer each from Mainpuri
and Kaithal sub-stations and to divert the same to Ballabgarh and
Mandola. It was also decided to divert one transformer which was
procured for Bahadurgarh sub-station to Mandola as commissioning
at Bahadurgarh was scheduled later.
11. Accordingly, appellant restored the transformers at Ballabgarh and
Mandola during the period from 29.05.2006 to 19.06.2006. The ICTs
that were taken out from Mainpuri and Kaithal were restored by
January and February, 2007 by new/repaired transformers.
12. Thereafter, appellant filed a petition before the CERC for approval
of the transmission charges for the three replaced ICTs in Rihand I
based on the Central Electricity Regulatory Commission (Terms and
Conditions of Tariff) Regulations, 2004 (referred to hereinafter as ‘the
Tariff Regulations’). The said petition was registered as Petition No.
68 of 2008. Appellant claimed de-capitalization for the transformers
taken out from Mainpuri and Kaithal and additional capitalization for
the new/repaired transformer originally procured for Bahadurgarh
sub-station and installed at the two sub-stations of Mandola and
Ballabgarh.
13. By order dated 03.02.2009, CERC did not allow the claim of the
appellant and dismissed Petition No. 68 of 2008.
14. Aggrieved thereby, appellant preferred Appeal No. 91 of 2009
before the Appellate Tribunal for Electricity (‘Appellate Tribunal’
for short).
15. On 09.05.2006, the tariff for the Rihand transmission systems
were determined by the CERC for the period from 01.04.2004 to
02.04.2009. On 04.09.2008, appellant filed a petition before the
CERC for revision of tariff in respect of the Rihand transmission
system for the period upto 02.04.2009 considering the net additional
capitalization on account of replacement of the three burnt ICTs at
Mandola and Ballabgarh. Appellant also sought for a direction to
the Northern Regional Power Committee for issuance of revised
128 [2025] 6 S.C.R.
Supreme Court Reports
availability certificate excluding the period when the three ICTs were
decapitalized and not in use. According to the appellant, an availability
certificate was required for claiming full transmission charges and
incentives. It was registered as Petition No. 80 of 2008.
16. CERC vide the order dated 03.02.2009 disallowed the claim of the
appellant for decapitalization of the damaged transformers and
recapitalization of the installed transformers as replacement for the
damaged transformers. CERC further held that the net cost for such
replacement has to be met out from the insurance fund reserve
maintained by the appellant under the internal insurance policy for
which contribution was being paid by the beneficiaries in the form
of operations and maintenance expenses. Further, CERC also did
not accede to the prayer of the appellant for giving directions to
the Northern Regional Power Committee for issuance of revised
availability certificate. Accordingly, vide the aforesaid order dated
03.02.2009, Petition No. 80 of 2008 filed by the appellant was
dismissed.
17. This led to filing of Appeal No. 92 of 2009 by the appellant before
the Appellate Tribunal. Both the appeals were heard together
by the Appellate Tribunal; and vide the impugned order dated
23.03.2011 dismissed the two appeals as being devoid of merit.
18. Learned counsel for the appellant submits that Appellate Tribunal
had virtually rubber stamped the findings arrived at by the
CERC. That apart it had interpreted Regulation 53(2)(iv) and
Note 2 of the Tariff Regulations in a most illogical manner. If
this is the interpretation, then no transmission licensee will ever
get additional capitalization on restoration and replacement of
the ICTs. He also submits that interpretation of the Appellate
Tribunal viz-a-viz the self-insurance policy is wholly illogical
without appreciating that the fire had occurred as a result of
the machinery breakdown and hence it is not covered under the
self-insurance policy.
18.1. Because of such erroneous decision, appellant has been
denied Rs. 15.63 crores on account of capitalization and Rs.
4.58 crores on account of tariff qua Rihand I transmission
system and Rs. 3.54 crores on account of capitalization qua
Rihand II transmission system.
[2025] 6 S.C.R. 129
Powergrid Corporation of India Limited v.
Central Electricity Regulatory Commission & Ors.
18.2. He submits that in April-May, 2006, the three ICTs at Mandola
and Ballabhgarh were damaged due to internal faults i.e.
machinery breakdown which resulted in the burning of the ICTs.
19. Learned counsel again referred to Regulation 53(2) of the Tariff
Regulations and submits that any work that may be required to
be done by a transmission licensee for successfully operating the
transmission system is permissible expenditure for capitalization,
whether it is a new work or a replacement. Any other interpretation
would render the aforesaid provision particularly Note 2 meaningless.
Contrary to this Appellate Tribunal has returned a finding that
replacement of ICTs/transformers is neither an additional work
necessary for efficient and successful operation nor an old asset
requiring replacement. Such a finding is unsustainable.
19.1. It is further submitted that Appellate Tribunal was not justified
in denying decapitalization and additional capitalization
of the ICTs on the ground that it was the responsibility of
the appellant for maintenance of the transmission system.
Appellant’s decapitalization and capitalization were under the
terms of accepted accounting practice. By not factoring in the
said expenditure as additional capitalization for the value of
the ICTs has led to a non-cost reflective tariff being paid to
the appellant. Finding rendered by the Appellate Tribunal that
provisions of Regulation 53 of the Tariff Regulations does not
cover replacement of damaged ICTs/transformers is incorrect
for the reason that any additional expenditure is contemplated
to be an additional capitalization if it relates to the efficient and
successful operation of the project. Regulation 53 cannot be
interpreted in a narrow and pedantic manner.
19.2. Referring to the self-insurance policy of the appellant,
learned counsel submits that the same covers losses from
fire, whether it is internal or external or even if it is due to
machinery breakdown. Fire was not the direct cause of the
damage to the ICTs/transformers; rather it was machinery
failure that possibly led to the fire. Learned counsel submits
that if the fire had caused the machinery breakdown, the
coverage will be available under the self-insurance policy
as the proximate cause in such a case would be the fire.
In this connection he has placed reliance on a decision of
130 [2025] 6 S.C.R.
Supreme Court Reports
this Court in New India Assurance Company Limited Vs.
Zuari Industries Limited1. He has also placed reliance on
another decision of this Court in Gujarat Urja Vikas Nigam
Limited Vs. Renew Wind Energy (Rajkot) Private Limited 2to
contend that Appellate Tribunal virtually rubber stamped
the decision of CERC.
20. On the other hand, learned counsel for some of the respondents i.e.
respondent Nos.2 to 5 and 10, who are the beneficiaries, supported
the order of CERC as well as that of the Appellate Tribunal.
20.1. It is submitted that appellant under the statute is under an
obligation to maintain a healthy transmission system. For
maintenance of the transmission system, the beneficiaries
are not required to pay additional amount. The very concept
of additional capitalization is based on the premise that in
case any additional benefit is given to the beneficiaries, the
amount can be capitalized. It is contended that by replacement
of the failed transformers no additional benefit is given to the
beneficiaries. Hence, the amount claimed for replacement of
the transformers cannot be capitalized.
20.2. Appellant had also shown a huge figure as cost of the installed
transformers though such transformers were not new ones.
Actual cost of the transformers would be much less. The
differential amount cannot be capitalized.
20.3. Adverting to Regulation 53 of the Tariff Regulations, it is
submitted that additional capitalization can be claimed only in
respect of the works in the original scope of the project. That
apart, additional capitalization can be claimed due to change
in law or on account of any award passed in arbitration, decree
of court, etc. Replacement of transformers does not fall in any
of such categories. Hence, the amounts claimed in both the
appeals cannot be capitalized.
20.4. The self-insurance reserve policy of the appellant covers
unsecured risks. The policy does not say that it will not cover
the risk regarding failure of transformers. If the appellant had
1 (2009) 9 SCC 70
2 2023 SCC OnLine SC 411
[2025] 6 S.C.R. 131
Powergrid Corporation of India Limited v.
Central Electricity Regulatory Commission & Ors.
not secured that risk in the policy, it cannot be allowed to
penalise the beneficiaries.
20.5. Learned counsel has also justified the decision of the Appellate
Tribunal declining to issue directions to Northern Regional
Power Committee (NRPC).
20.6. It is therefore submitted that there is no merit in the appeals
which should be dismissed.
21. Submissions made by learned counsel for the parties have received
the due consideration of the Court.
22. Upon perusal of the materials on record and after hearing learned
counsel for the parties, we are of the view that the following questions
arise for our consideration in this case:
1. Whether the Appellate Tribunal and respondent No.1 were
justified in rejecting the claim made by the appellant of additional
capitalization due to replacement of the damaged ICTs?
2. Whether the self-insurance policy of the appellant covered the
cost of replacement of the damaged ICTs?
3. Whether the Member Secretary of NRPC should have been
directed by the Appellate Tribunal to issue revised availability
certificate for the transmission assets?
23. To consolidate all the laws relating to generation, transmission,
distribution, trading and use of electricity and generally for taking
measures conducive to development of the electricity industry,
promoting competition therein, protecting the interest of consumers
and supply of electricity to all areas, rationalization of electricity
tariff, ensuring transparent policies regarding subsidies, promotion of
efficient and environmentally benign policies, constitution of Central
Electricity Authority, Regulatory Commissions and establishment
of Appellate Tribunal and for such related matters, the Electricity
Act has been enacted. Whether it is Appellate Tribunal traceable
to Section 110 or the Central Electricity Regulatory Commission
(CERC) referred to in Section 76(1) or Central Transmission Utility
meaning any government company which the Central Government
may notify under sub-section (1) of Section 38, such as the appellant,
all are covered by provisions of the Electricity Act. It also provides
for appeal to the Supreme Court, as in the present case, under
132 [2025] 6 S.C.R.
Supreme Court Reports
Section 125 against any decision or order of the Appellate Tribunal
on a substantial question of law.
24. In exercise of the powers conferred under Section 178 of the Electricity
Act and all other powers enabling in this behalf and after previous
publication, CERC has made the Tariff Regulations which came into
force on 01.04.2004.
25. The scope and extent of application of the Tariff Regulations is
provided in Regulation 2. As per clause (1), where tariff is determined
through a transparent process of bidding in accordance with the
guidelines issued by the Central Government, CERC shall adopt
such tariff in accordance with the provisions of the Electricity Act.
Clause (2) says that the Tariff Regulations shall apply in all such
cases where tariff is to be determined by the CERC based on capital
cost. Ofcourse, the CERC has the authority to prescribe relaxed
norms of application for determination of tariff.
26. Chapter - 2 of the Tariff Regulations deals with thermal power
generating stations. Regulations 14 and 18 are included in Chapter - 2.
26.1. Regulation 14(xviii) defines ‘Operation and Maintenance
Expenses’ or O&M expenses to mean the expenditure
incurred on operation and maintenance of the generating
station including part thereof and includes the expenditure
on manpower, repairs, spares, consumables, insurance and
overhead.
26.2. Regulation 18 deals with additional capitalization. Regulation
18 is extracted hereunder:
18. Additional capitalisation: (1) The following
capital expenditure within the original scope of
work actually incurred after the date of commercial
operation and up to the cut off date may be admitted
by the Commission, subject to prudence check:
(i) Deferred liabilities;
(ii) Works deferred for execution;
(iii) Procurement of initial capital spares in
the original scope of work, subject to ceiling
specified in regulation 17;
[2025] 6 S.C.R. 133
Powergrid Corporation of India Limited v.
Central Electricity Regulatory Commission & Ors.
(iv) Liabilities to meet award of arbitration or for
compliance of the order or decree of a court; and
(v) On account of change in law.
Provided that original scope of work along with
estimates of expenditure shall be submitted along
with the application for provisional tariff.
Provided further that a list of the deferred liabilities
and works deferred for execution shall be submitted
along with the application for final tariff after the date
of commercial operation of the generating station.
(2) Subject to the provisions of clause (3) of this
regulation, the capital expenditure of the following
nature actually incurred after the cut off date may
be admitted by the Commission, subject to prudence
check:
(i) Deferred liabilities relating to works/services
within the original scope of work;
(ii) Liabilities to meet award of arbitration or for
compliance of the order or decree of a court;
(iii) On account of change in law;
(iv) Any additional works/services which have
become necessary for efficient and successful
operation of the generating station, but not
included in the original project cost; and
(v) Deferred works relating to ash pond or ash
handling system in the original scope of work.
(3) Any expenditure on minor items/assets like normal
tools and tackles, personal computers, furniture,
air-conditioners, voltage stabilizers, refrigerators,
fans, coolers, TV, washing machines, heat-
convectors, carpets, mattresses etc. brought after
the cut off date shall not be considered for additional
capitalisation for determination of tariff with effect
from 1.4.2004.
134 [2025] 6 S.C.R.
Supreme Court Reports
Note
The list of items is illustrative and not exhaustive.
(4) Impact of additional capitalisation in tariff
revision may be considered by the Commission
twice in a tariff period, including revision of tariff
after the cut off date.
Note 1
Any expenditure admitted on account of
committed liabilities within the original scope
of work and the expenditure deferred on
techno-economic grounds but falling within
the original scope of work shall be serviced
in the normative debt-equity ratio specified in
regulation 20.
Note 2
Any expenditure on replacement of old assets
shall be considered after writing off the gross
value of the original assets from the original
project cost, except such items as are listed in
clause (3) of this regulation.
Note 3
Any expenditure admitted by the Commission
for determination of tariff on account of new
works not in the original scope of work shall
be serviced in the normative debt-equity ratio
specified in regulation 20.
Note 4
Any expenditure admitted by the Commission
for determination of tariff on renovation and
modernization and life extension shall be
serviced on normative debt-equity ratio specified
in regulation 20 after writing off the original
amount of the replaced assets from the original
project cost.
[2025] 6 S.C.R. 135
Powergrid Corporation of India Limited v.
Central Electricity Regulatory Commission & Ors.
27. To answer question No.1, it is necessary to advert to Regulation 53
of the Tariff Regulations which is included in Chapter - 4, the
heading of which is Inter-State Transmission. Regulation 53 reads
thus:
53. Additional capitalisation: (1) The following capital
expenditure within the original scope of work actually
incurred after the date of commercial operation and up
to the cut off date may be admitted by the Commission,
subject to prudence check:
(i) Deferred liabilities;
(ii) Works deferred for execution;
(iii) Procurement of initial capital spares in the original
scope of works subject to the ceiling norm specified in
regulation 52;
(iv) Liabilities to meet award of arbitration or compliance
of the order or decree of a court; and
(v) On account of change in law.
Provided that original scope of work along with estimates
of expenditure shall be submitted along with the application
for provisional tariff.
Provided further that a list of the deferred liabilities and
works deferred for execution shall be submitted along with
the application for final tariff after the date of commercial
operation of the transmission system.
(2) Subject to the provisions of clause (3) of this regulation,
the capital expenditure of the following nature actually
incurred after the cut off date may be admitted by the
Commission, subject to prudence check:
(i) Deferred liabilities relating to works/services within the
original scope of work;
(ii) Liabilities to meet award of arbitration or compliance
of the order or decree of a court;
(iii) On account of change in law; and
136 [2025] 6 S.C.R.
Supreme Court Reports
(iv) Any additional works/services which have become
necessary for efficient and successful operation of the
project, but not included in the original project cost.
(3) Any expenditure on minor items/assets brought after
the cut off date like tools and tackles, personal computers,
furniture, air-conditioners, voltage stabilizers, refrigerators,
coolers, fans, T.V., washing machine, heat-convectors,
mattresses, carpets, etc shall not be considered for
additional capitalisation for determination of tariff with
effect from 1.4.2004.
Note
The list of items is illustrative and not exhaustive.
(4) Impact of additional capitalisation in tariff revision may
be considered by the Commission twice in a tariff period,
including revision of tariff after the cut off date.
Note 1
Any expenditure admitted on account of committed liabilities
within the original scope of work and the expenditure
deferred on techno-economic grounds but falling within the
original scope of work shall be serviced in the normative
debt-equity ratio specified in regulation 54.
Note 2
Any expenditure on replacement of old assets shall be
considered after writing off the entire value of the original
assets from the original capital cost.
28. From a perusal of the above, it is seen that Regulation 53 provides
for additional capital expenditure incurred after the commercial
operation date. It says that additional capital expenditure incurred
after the commercial operation date and upto the cut-off-date may
be admitted by the CERC if such expenditure relates to deferred
liabilities, deferred works, procurement of initial spares (within
specified norms), compliance with arbitral award or court order or
change in law subject to submission of necessary documents and
a prudent check. Post cut-off date, additional capitalization may
still be allowed for similar liabilities and more importantly essential
new works or services necessary for efficient project operation but
[2025] 6 S.C.R. 137
Powergrid Corporation of India Limited v.
Central Electricity Regulatory Commission & Ors.
minor assets like furniture, computers or appliances are excluded.
It also provides that expenditure on replacement of old assets shall
be considered after the full value of the old asset is written off and
the impact of additional capitalization on tariff can be considered
by the CERC twice in a tariff period, including revision of tariff after
the cut off date.
29. Thus, it is evident that Regulation 53 does not include within its scope
replacement of ICTs due to damage or failure. Regulation 53(2)(iv)
says that any additional work/services which have become necessary
for the efficient and successful operation of the project but not included
in the original project cost may be admitted by the CERC as additional
capital expenditure. Contention of the appellant that such a provision
would apply to it also does not appeal to the Court as all that the
appellant had done was diversion and replacement of ICTs. This
cannot be construed as doing any additional work/services. On the
contrary, we concur with the contention of some of the respondents
that as a central transmission utility, it was the duty of the appellant
to maintain a healthy transmission system; replacement of damaged
equipment(s) is part of operation and maintenance.
30. Insofar Note 2 to Regulation 53 is concerned, it says that any
expenditure on replacement of old assets shall be considered
after writing off the entire value of the original assets from the
original capital cost. In this case, the transmission systems were in
normal operational condition since those were commissioned. Both
Rihand I and Rihand II cannot be considered as old assets as these
were fairly new. There is nothing on record to show that prior to the
breakdown of ICTs, the transmission systems were in bad shape or
had started wearing out.
31. That being the position, the answer to question No.1 can only be in
the affirmative, in favour of the respondents and against the appellant.
32. This brings us to the second question which is as to whether the
self-insurance policy of the appellant covered the cost of replacement
of the damaged ICTs.
33. In the fiscal year 1994-1995, appellant opted to adopt a self-insurance
reserve policy based on its past experience and in alignment with
industry practices. The decision was taken to allocate estimated
appropriations in the accounts for future losses potentially arising
138 [2025] 6 S.C.R.
Supreme Court Reports
out of uninsured risks, such as, machinery breakdown and fire risk
of equipments in operational sub-stations. Consequently, a self-
insurance account was created. The reserve was created at the
rate of 0.1 percent of the gross value of the fixed assets at the
close of each year covering potential future losses from uninsured
risks with the exception of those related to high voltage direct
current valve halls and sub-stations. The insurance reserve covered
losses caused by events such as fire including by way of lightning,
explosion/implosion, bush fires etc. with such losses being adjusted
against the insurance reserve as per CERC’s guidelines upon actual
occurrence. We thus find that there are no inclusions or exclusions
with regard to loss caused by ‘fire’ nor does it include any exception
to loss caused by fire.
34. It is the contention of the appellant that it could not take finance
from the self-insurance reserve as the cause of the loss to the ICTs
was damage due to machinery breakdown leading to fire. It is not
the fire itself which damaged the ICTs. We find such contention of
the appellant to be contradictory.
35. Considering the above we are of the view that the loss caused to
the appellant by fire, whether by way of implosion or by way of
explosion, would be covered by the policy as it covered all fires
which caused loss without any exception and as all the three ICTs
were operating until those got burnt. Therefore, the loss was caused
due to fire because of which the ICTs became damaged beyond
immediate repair.
36. In Zuari Industries Limited (supra), this Court analyzed the expression
‘proximate cause’. In that case there was a short-circuit in the main
switchboard installed in the sub-station receiving electricity from
the State Electricity Board. This resulted in a flashover producing
overcurrents. The flashover and overcurrents generated excessive
heat. The paint on the panel board was charred by the excessive
heat producing smoke because of which the partition of the adjoining
feeder developed a hole. The smoke travelled to the generator
compartment where also there was short-circuit because of which
the power tripped. As a result, the entire electricity supply to the plant
stopped. Due to the stoppage of electric supply, supply of water/
stream to the waste heat boiler by the flue gases at high temperature
continued to be fed into the boiler which resulted in damage to the
[2025] 6 S.C.R. 139
Powergrid Corporation of India Limited v.
Central Electricity Regulatory Commission & Ors.
boiler. It was in that context that the court considered the question
as to whether the flashover or the fire was the proximate cause of
the damage in question. After a thorough analysis of the chain or
sequence of events, this Court took the view that the proximate
cause is not the cause which is nearest in point of time or place but
the active and efficient cause that sets in motion a train or chain of
event which brings about the ultimate result without the intervention
of any other force working from an independent source. On that
basis this Court held that the fire was the efficient and active cause
of the damage. Had the fire not occurred, the damage also would
not have occurred. There was no intervening agency which was an
independent source of the damage. Therefore, this Court did not
agree with the conclusion of the Surveyor that the fire was not the
cause of the damage to the machinery of the claimant.
37. Applying the above principle to the facts of the present case, it can
be seen that the proximate cause for the damage to the ICTs is the
implosion/explosion in the internal/external machinery of the ICTs
which caused fire. All the three ICTs became unserviceable due
to the fire and had to be replaced by the appellant. Appellant has
admitted that preventive maintenance and checks were done from
time to time prior to the incident and everything was going fine. It
was only when the fire broke out and damaged the ICTs did the
authorities concerned diverted other transformers for replacement
of the damaged transformers. Thus, our answer to question No.
2 would be that the self-insurance policy of the appellant covered
the cost of replacement of the damaged ICTs. Therefore, Appellate
Tribunal was justified in directing the appellant to finance the net cost
from the self-insurance fund reserve as part of the operation and
maintenance charges. Accordingly, question No. 2 stands answered
in the affirmative and against the appellant.
38. Since we have decided question Nos.1 and 2 against the appellant,
question No.3 has become redundant as decapitalization and
additional capitalization of the replaced ICTs have not been
allowed. Therefore, question of issuing direction to the Member-
Secretary, NRPC for issuance of revised availability certificate for
the transmission assets does not arise.
39. Before parting with the record, we may refer to the decision of this
Court in Gujarat Ujra Vikas Nigam Limited (supra) in which case
140 [2025] 6 S.C.R.
Supreme Court Reports
this Court agreed with the appellant that there was not a shred of
evidence adduced by the respondent beyond the bare allegation
of coercion made against the appellant. It was in that context this
Court expressed surprise as to how such a sweeping allegation of
coercion was accepted by the Appellate Tribunal de hors adequate
pleadings. Therefore, this Court opined that Appellate Tribunal had
virtually rubber stamped the findings of Gujarat Electricity Regulatory
Commission on coercion. Evidently, the above decision would have
no application to the facts of the present case. That apart, Appellate
Tribunal has given cogent and valid reasons while rejecting the
appeals of the appellant. We, therefore, do not find any ground to
interfere with the impugned order.
40. That being the position, we are of the considered opinion that the
two appeals are devoid of any merit. Accordingly, the appeals are
dismissed. No Cost.
Result of the case: Appeals dismissed.
†
Headnotes prepared by: Nidhi Jain
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.