Created byFuzzy Cloud

Supreme Court of India

POWER GRID CORPORATION OF INDIA LIMITEDversusMADHYA PRADESH POWER TRANSMISSION COMPANY

Citation
2025 INSC 697
Decided
15 May 2025
Disposal
Appeal(s) allowed

Holding

The CERC’s powers under section 79(1) are not limited by the existence of regulations under section 178; its ad‑hoc regulatory orders, including compensation for delay, are within its jurisdiction, and the High Court erred in admitting the writ petitions.

Summary

Power Grid Corporation of India Ltd (the appellant) sought CERC orders to approve the commercial operation date of its inter‑state transmission assets and to recover compensation for delays caused by Madhya Pradesh Power Transmission Company Ltd (respondent No.1). CERC, exercising powers under s.79(1) of the Electricity Act, 2003, imposed liability on the respondent for transmission charges despite the absence of a specific regulation under s.178. The respondent challenged the CERC orders by filing writ petitions, arguing that CERC exceeded its jurisdiction and that an alternative remedy under s.111 was available. The Supreme Court held that CERC’s regulatory functions under s.79 are distinct from its legislative power under s.178, and that in the absence of a specific regulation the Commission may fill regulatory gaps by ad‑hoc orders, including compensation for delay. The Court found no breach of natural‑justice principles and ruled that the High Court erred in admitting the writ petitions. Consequently, the appeals were allowed and the writ petitions dismissed.

Issues considered

  • Whether the CERC, while exercising its functions under section 79(1) of the Electricity Act, 2003, is circumscribed by statutory regulations enacted under section 178 of the Act.
  • Whether the CERC exercises regulatory or adjudicatory functions under section 79 of the Act, and the scope of its power to regulate inter‑state transmission and determine tariff under clauses (c) and (d) of s.79(1).
  • Whether the grant of compensation by the CERC for delay, via orders dated 21.01.2020 and 27.01.2020, is a regulatory or adjudicatory function and the extent to which principles of natural justice apply.
  • Whether the High Court was justified in admitting the writ petition challenging the CERC order when an alternative remedy under section 111 of the Act, 2003 existed.

Legislation cited

Headnote

Issue for Consideration (i) Whether the CERC, while exercising its functions u/s.79(1) of the Electricity Act, 2003, is circumscribed by statutory regulations enacted u/s.178 of the Act, 2003; (ii) Whether the CERC exercises regulatory or adjudicatory Act, 2003. In other words, what is the scope of the CERC’s power to regulate inter-state transmission of electricity and determine tariff for the same under clauses (c) and (d) of s.79(1); (iii) Whether the grant of compensation by the CERC for the delay vide the orders dated 21.01.2020 and

Subjects

Section 79 of the Electricity Act, 2003Section 178 of the Electricity Act, 2003Determination of tariffRegulatory and adjudicatory functionsTariff RegulationsCommercial Operation DateCompensatory transmission chargesPrinciples of natural justiceAlternative remedyInter‑state transmissionIntra‑state transmissionTime‑overrun/DelayQuasi‑judicial bodyDelegated legislationAd hoc power

Judgment

                 [2025] 5 S.C.R. 2062 : 2025 INSC 697

              Power Grid Corporation of India Limited
                                v.
           Madhya Pradesh Power Transmission Company
                          Limited & Ors.
                       (Civil Appeal No. 6847 of 2025)
                                  15 May 2025
              [J.B. Pardiwala* and R. Mahadevan, JJ.]


                            Issue for Consideration
       (i) Whether the CERC, while exercising its functions u/s.79(1) of
       the Electricity Act, 2003, is circumscribed by statutory regulations
       enacted u/s.178 of the Act, 2003; (ii) Whether the CERC exercises
       regulatory or adjudicatory functions u/s.79 of the Act, 2003. In
       other words, what is the scope of the CERC’s power to regulate
       inter-state transmission of electricity and determine tariff for the
       same under clauses (c) and (d) of s.79(1); (iii) Whether the grant
       of compensation by the CERC for the delay vide the orders
       dated 21.01.2020 and 27.01.2020 respectively, is a regulatory
       or adjudicatory function and to what extent are the principles
       of natural justice applicable to the exercise of such functions;
       (iv) Whether the High Court was justified in admitting the writ
       petition filed by the respondent no. 1 herein challenging the order
       dated 21.01.2020 of the CERC when there existed an alternative
       remedy u/s.111 of the Act, 2003.

                                   Headnotes†
       Electricity Act, 2003 – ss.79, 178 – Relationship between ss.79
       and 178 of the Act, 2003:
       Held: A perusal of the provisions laying down the functions of the
       CERC indicates that the statutory authority is enjoined with the
       task of regulation as well as adjudication of several aspects of the
       generation, transmission and distribution of electricity – S.79 of the
       Act, 2003 enumerates the functions of the CERC which includes
       the dual functions of regulation and adjudication – S.178, on the
       other hand, empowers the CERC to enact regulations by notification
       thereby delegating to the body, the power of legislating statutory
       regulations under the Act, 2003 – The aforesaid two provisions


* Author
[2025] 5 S.C.R.                                                                 2063

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

     indicate that the CERC functions as both, decision-making and
     regulation-making authority u/ss.79 and 178 respectively – However,
     while the authority exercising both these functions is one and the
     same, it is a settled position of law that the functions by themselves
     are separate and distinct – The functions u/s.79 are administrative
     or adjudicatory whereas those u/s.178 are legislative – A regulation
     u/s.178 is of general application to the entirety of a particular subject
     matter as opposed to regulation on a case-to-case basis which may
     be done by the CERC u/s.79 – Therefore, making of a regulation
     u/s.178 has the effect of interfering with and overriding existing
     contractual relationships between the regulated entities – On the
     other hand, the orders u/s.79 have to be confined to the existing
     statutory regulations and do not have the effect of altering the
     terms of contract between the specific parties before the CERC.
     [Paras 37, 38, 40]

     Electricity Act, 2003 – ss.79, 178 – The CERC vide its orders
     dated 21.01.2020 and 27.01.2020 respectively imposed the
     liability of payment of compensation for delay onto the
     respondent no. 1 – Correctness:
     Held: It is the case of the respondent no. 1 that by doing so, the
     CERC did not act in conformity with the 2014 Tariff Regulations
     which do not provide for payment of transmission charges by a
     party to whom the delay is attributable – In considered view of this
     Court, the said argument does not hold any water – This Court’s
     dictum in PTC and Energy Watchdog respectively settles the law
     in this regard and the absence of a regulation u/s.178 does not
     preclude the CERC from exercising its powers u/s.79(1) to make
     specific regulations or pass orders between the parties before
     it.[Para 43]

     Electricity Act, 2003 – s.79 – Regulatory and adjudicatory
     functions of the CERC:
     Held: The regulatory powers provided to the CERC u/s.79 are of
     ad hoc nature and are required to be exercised by the CERC in
     context of the specific circumstances of the parties before it – The
     rationale for provision of such ad hoc powers by the Act, 2003 is
     to ensure that regulatory gaps, if any, that may be discovered on a
     case-to-case basis, are filled or removed – Therefore, there is no
     doubt that the CERC is enabled to exercise its regulatory powers
     by way of orders u/s. 79 and the purview of s.79 is not limited to
2064                                                           [2025] 5 S.C.R.

                         Supreme Court Reports


    only adjudicatory orders but includes within its scope administrative
    functions as well. [Para 48]

    Electricity Act, 2003 – Whether the grant of compensation by
    the CERC was a decision taken by the authority in its regulatory
    or adjudicatory capacity and whether it goes a step beyond
    the function of determination of tariff:
    Held: A reading of the Act, 2003 would indicate that it makes
    no distinction between the regulatory and adjudicatory functions
    vested in and conferred upon the CERC, which is a quasi-judicial
    body enjoined to regulate and administer the subject of electricity
    generation, transmission and distribution – In such a situation, it
    becomes necessary to undertake a harmonious reading of ss.61
    and 79 respectively to determine whether the CERC granted
    the liberty to claim compensation in exercise of its regulatory or
    adjudicatory function – The CERC granted liberty to the appellant
    herein to claim compensation from the respondent no. 1 to deal with
    a situation caused due to an unprecedented event not covered by
    any guidelines, regulations or contractual provisions between the
    parties – The dictum of this Court in Energy Watchdog, indicates
    that in such a situation where there is an absence of regulations and
    guidelines, the Act, 2003 mandates the CERC to strike a judicious
    balance between the parties keeping in mind commercial principles
    and consumers’ interest, in exercise of its general regulatory powers
    u/s.79(1) – The aforesaid leaves no manner of doubt that though
    the CERC’s orders dated 21.01.2020 and 27.01.2020 respectively
    were for determination of tariff, yet the order granting liberty to the
    aggrieved appellant to claim compensation from the defaulting
    party is a consequence of a regulatory lacuna in the 2014 Tariff
    Regulations and therefore, is an instance of regulation of tariff
    between the parties. [Paras 53, 59, 60]

    Electricity Act, 2003 – Whether there was a contravention of
    the principles of natural justice by the CERC:
    Held: The CERC was not adjudicating the issue of delay between
    the parties but was only regulating the consequences of the
    delay to the commissioning of the transmission elements – There
    was also no occasion for the respondent no. 1 to be afforded an
    opportunity to be heard at that stage – In considered view of this
    Court, any dispute pertaining to the levy of transmission charges
    incurred before the concerned transmission assets were put to use,
[2025] 5 S.C.R.                                                                2065

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

     would arise only upon the appellant raising bills to the respondent
     no. 1 in this regard – In such a scenario, it cannot be said that
     there was a contravention of the principles of natural justice by
     the CERC. [Para 61]

     Electricity Act, 2003 – Whether the CERC is empowered to
     order for imposition of transmission charges on the party to
     whom delay is attributable.
     Held: The CERC is empowered to order for imposition of
     transmission charges on the party to whom delay is attributable –
     This Court has, however, have not considered the question
     whether such liability of payment of transmission charges could
     be imposed on the respondent no. 1 in the specific facts of the
     case on hand – This Court is of the opinion that APTEL is the
     appropriate authority to look into the merits of the matter should
     the respondent no. 1 choose to prefer an appeal before APTEL
     u/s.111 of the Act, 2003. [Para 66]

     Electricity Act, 2003 – Writ Petition – Maintainability of a writ
     petition before the High Court in the presence of the alternative
     remedy – Conditions of:
     Held: This Court’s dictum in Whirlpool Corporation v. Registrar of
     Trademarks wherein it has been held that despite the availability
     of an alternative remedy, a writ petition can be entertained in the
     following cases: a) Where principles of natural justice are breached;
     b) Where fundamental rights are sought to be enforced or breach
     thereof is complained of; c) Where the impugned order is passed by
     an authority without jurisdiction; d) Where the constitutionality of any
     provision is called in question – However, this Court’s observations
     in Whirlpool are of no avail to the respondent no. 1 as the present
     matter falls in none of the cases enumerated therein – Therefore,
     there was no occasion for the High Court to admit the writ petition
     of the respondent no. 1. [Paras 11, 64]

                               Case Law Cited
     PTC India Limited v. Central Electricity Regulatory Commission
     [2010] 3 SCR 609 : (2010) 4 SCC 603; Airports Economic
     Regulatory Authority of India v. Delhi International Airport Ltd. [2024]
     10 SCR 1404 : 2024 SCC OnLine SC 2923; Energy Watchdog v.
     CERC [2017] 3 SCR 153 : (2017) 14 SCC 80 – relied on.
2066                                                      [2025] 5 S.C.R.

                        Supreme Court Reports


    Whirlpool Corporation v. Registrar of Trademarks [1998] Supp.
    2 SCR 359 : (1998) 8 SCC 1: Power Grid Corpn. of India Ltd. v.
    Punjab State Power Corpn. Ltd. [2016] 2 SCR 116 : (2016) 4 SCC
    797; Sitaram Sugar Co. Ltd. v. Union of India [1990] 1 SCR 909 :
    (1990) 3 SCC 223 – referred to.
    Nuclear Power Corporation of India Limited. v. Central Electricity
    Regulatory Commission & Ors., 2019 SCC OnLine APTEL
    83 – referred to.

                              List of Acts
    Electricity Act, 2003; Central Electricity Regulatory Commission
    (Terms and Conditions of Tariff) Regulations, 2014.

                           List of Keywords
    Section 79 of the Electricity Act, 2003; Section 178 of the
    Electricity Act, 2003; Determination of tariff; Regulatory and
    adjudicatory functions; Tariff Regulations; Commercial Operation
    Date; Compensatory transmission charges; Principles of natural
    justice; Alternative remedy; Inter-state transmission; Intra-state
    transmission; Time-overrun/Delay; Quasi-judicial body; Delegated
    legislation; Ad hoc power.

                          Case Arising From
    CIVIL APPELLATE JURISDICTION: Civil Appeal No. 6847 of 2025
    From the Judgment and Order dated 25.02.2021 of the High Court
    of Madhya Pradesh at Indore in WP No. 10845 of 2020
    With
    Civil Appeal No. 6848 of 2025

                       Appearances for Parties
    Advs. for the Appellant:
    M.G. Ramachandran, Sr. Adv., Shubham Arya, Ms. Poorva Saigal,
    Pramod Dayal, Nikunj Dayal, Ms. Reeha Singh, Ms. Pallavi Saigal,
    Ms. Shirin Gupta, Aneesh Bajaj, Ms. Srishti Khindaria.
    Advs. for the Respondents:
    Prashant Singh. A.G. (MP), Amit Seth, Arjun Garg, Ms. Kriti Gupta,
    Ms. Sagun Srivastava, Brahma Prakash Soni, Anup Jain, Udit
[2025] 5 S.C.R.                                                                              2067

         Power Grid Corporation of India Limited v. Madhya Pradesh
               Power Transmission Company Limited & Ors.

       Gupta, Vyom Chaturvedi, Ms. Pragya Gupta, Amrnath Sahoo,
       Ms. Nishtha Goel, Ms. Deep Shikha Kumar (for M/s. Udit Kishan
       And Associates), Shirish K. Deshpande, Ms. Rucha Pravin Mandlik,
       Mohit Gautam, Apoorv Sharma, Sudhanshu S. Choudhari.

                       Judgment / Order of the Supreme Court

                                             Judgment

       J.B. Pardiwala, J.

       For the convenience of exposition, this judgment is divided into the
       following parts:

                                               INDEX*

       A.     FACTUAL MATRIX .............................................................         2

       B.     IMPUGNED ORDER ...........................................................           8

       C.     SUBMISSIONS ON BEHALF OF THE APPELLANT ........ 12

       D.     SUBMISSIONS ON BEHALF OF THE RESPONDENTS ... 16

       E.     ISSUES FOR DETERMINATION ........................................ 20

       F.     ANALYSIS ........................................................................... 21

              i.    Relevant Provisions of the Act, 2003 ........................ 21

              ii. Relationship between Sections 79 and 178 of the 31
                  Act, 2003 respectively .................................................

              iii. Regulatory and adjudicatory functions of the CERC 38
                   under Section 79 .........................................................

              iv. Grant of compensation for delay on the part of a 41
                  party is a regulatory function .....................................

       G. CONCLUSION ...................................................................... 55


* Ed. Note: Pagination as per the original Judgment.
2068                                                       [2025] 5 S.C.R.

                        Supreme Court Reports


1.   Leave granted.
2.   Since the issues raised in both the captioned appeals are the same,
     those were taken up for hearing analogously and are being disposed
     by this common judgment and order.
3.   These appeals arise from the Judgment and Order passed by the
     High Court of Madhya Pradesh, Indore Bench dated 25.02.2021, in
     Writ Petition No. 10845 of 2020 and Writ Petition No. 9136 of 2020
     respectively, by which the High Court admitted the writ petitions
     filed by the Madhya Pradesh Power Transmission Company Limited
     (“MPPTCL”) on the ground that the Central Electricity Regulatory
     Commission (the “CERC”) had exercised powers beyond those vested
     in it as per the regulations under the Electricity Act, 2003 (the “Act,
     2003”) in passing the orders dated 21.01.2020 and 27.01.2020 in
     Petition No. 311/TT/2018 and Petition No. 266/TT/2018 respectively.

     A.   FACTUAL MATRIX
4.   The appellant herein is a Government of India Undertaking constituted
     for the purpose of undertaking inter-state transmission of electricity.
     In other words, the scope of work of the appellant includes inter
     alia, establishing and operating transmission lines, sub-stations and
     other transmission assets associated with inter-State transmission
     of power. These include ‘bays’ and inter-connecting ‘transformers’ at
     sub-stations to provide inter-connection facilities. By virtue of being
     a central transmission utility, the appellant is a deemed transmission
     licensee in terms of Section 38 of the Act, 2003. The respondent no.
     1 herein is the State Transmission Utility and intra-state transmission
     licensee in the State of Madhya Pradesh.
5.   The case on hand pertains to a dispute between the appellant and
     respondent no. 1 in respect of the implementation of the “Western
     Region System Strengthening Scheme XIV (WRSS-XIV) and Western
     Region Strengthening Scheme XVI (WRSS-XVI)” respectively by
     the appellant. The transmission assets were implemented by the
     appellant at the Indore sub-station upon the specific request of the
     respondent no. 1. In this regard, the parties planned and approved
     the WRSS-XIV in its 37th Standing Committee Meeting on Power
     System Planning of Western Region held on 05.09.2014 and WRSS-
     XVI in the 38th Standing Committee Meeting for the Western Region
     on 17.07.2015.
[2025] 5 S.C.R.                                                         2069

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

6.   According to the agreement between the parties, the respondent
     no. 1 was required to construct and commission the intra-state
     transmission line from Indore sub-station coinciding with the timeline
     of completion of works which were within the scope of the appellant.
     However, the construction and commissioning of the intra-state
     transmission line by respondent no. 1 was delayed. Such delay
     constrained the appellant to file Petition No. 311/TT/2018 and Petition
     No. 266/TT/2018 corresponding to WRSS-XIV and WRSS-XVI
     respectively, before the CERC for (i) approval of the Commercial
     Operation Date (the “COD”) of its transmission system, under
     Regulation 4(3) of the Central Electricity Regulatory Commission
     (Terms and Conditions of Tariff) Regulations, 2014 (the “2014 Tariff
     Regulations”), and (ii) determination of transmission charges and
     billing of the tariff for the transmission facilities established by it at
     the Indore sub-station.
7.   The CERC vide its order dated 21.01.2020, observed, inter alia,
     that as per the investment approval accorded to the transmission
     scheme on 27.01.2016, the assets were scheduled to be
     commissioned within 30 months from the date of investment
     approval. Accordingly, the scheduled COD came to be 27.07.2018.
     However, the commissioning of such assets was delayed thereby
     compelling the appellant to file a petition for approval of COD under
     Regulation 4(3) of the 2014 Tariff Regulations. The details of the
     transmission assets are as follow:

                                            Proposed
                                                          Date of
                                               COD                    Time-
                                  Scheduled               active
       Asset        Description               as per                 overrun/
                                    COD                   power
                                            Regulation                Delay
                                                           flow
                                              4(3)(ii)
              1 x 500 MVA,
              400/220 kV
              ICT-2 along
              with associated
      Asset-1 transformer        27.07.2018 02.09.2018 10.12.2018 37 days
              bays and 2 no.
              220kV line bays
              at 400/220 kV
              Indore substation.
2070                                                             [2025] 5 S.C.R.

                            Supreme Court Reports



                2 no. 220 kV line
                bays at 400/220
        Asset-2                     27.07.2018 02.09.2018 12.12.2018 37 days
                kV Indore
                substation.
                1 x 500 MVA,
                400/220 kV
                ICT-1 along
        Asset-3 with associated    27.07.2018 14.10.2018 10.12.2018 79 days
                transformer bays
                at 400/220 kV
                Indore substation.
                1 no. 220 kV line
                bays at 400/220
        Asset-4                     27.07.2018 14.10.2018     -        79 days
                kV Indore
                substation.
                1 no. 220 kV line
                bay at 400/220
        Asset-5                     27.07.2018 05.12.2018     -        131 days
                kV Indore
                substation.

8.   As regards the specific issue of time-overrun, the order dated
     21.01.2020 passed by the CERC noted that the appellant herein
     had attributed the entire time-overrun in case of the instant assets
     to the respondent no. 1 who delayed the commissioning of the
     downstream intra-state assets that were supposed to be operational
     at the same time as the transmission assets to be commissioned by
     the appellant. Even though the CERC approved the COD proposed
     by the appellant under Regulation 4(3)(ii), yet it did not condone
     the time-overrun on account of matching the commissioning of the
     inter-state transmission assets in question with the downstream
     network of respondent no. 1, on the ground that it was the decision
     of the appellant to coordinate and match the commissioning dates
     of both categories of assets. However, the CERC allowed the
     appellant to claim compensation for the period prior to the COD as
     determined under Regulation 4(3)(ii), by way of liquidated damages,
     interest during construction and incidental expenses incurred during
     construction. It was held that the transmission charges in case of all
     the assets as enumerated above would be borne by the respondent
     no. 1 from the COD determined under Regulation 4(3)(ii) upto one
     day before actual charging of downstream system. It is pertinent to
[2025] 5 S.C.R.                                                        2071

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

     note that the CERC did not allow compensation from the Scheduled
     COD upto the newly determined COD as the delay in that case was
     not condoned.
9.   Aggrieved by the aforesaid order of the CERC, the respondent no. 1
     challenged the same by way of a writ petition before the High Court
     on the following grounds:
     (i)    There is no provision in the 2014 Tariff Regulations under
            which compensatory transmission charges could be levied on
            the respondent no. 1 by the CERC and therefore, the CERC
            fell into grave jurisdictional error by holding that the appellant
            could claim compensation from the respondent no. 1.
     (ii)   Further, the agreement between the parties was recorded
            in the minutes of the 37th and 38th meetings of the Standing
            Committee held on 05.09.2014 and 17.07.2015 respectively.
            Such agreement contains no terms and conditions as regards
            the recovery of compensation from the respondent no. 1.
            Therefore, the CERC, by granting liberty to the appellant to
            claim compensation from the respondent no. 1 has effectively
            re-written the terms and conditions of the agreement between
            the parties.
     (iii) The bill dated 08.06.2020 raised by the appellant for the payment
           of Rs. 6.18 crore, in consequence of the order of the CERC
           dated 21.01.2020 and 27.01.2020 respectively, is illegal and
           not in accordance with either the 2014 Tariff Regulations or the
           terms of agreement between the parties.
10. On the other hand, the appellant claimed before the High Court
    that the issue raised by the respondent no. 1 by way of the writ
    petition was not that the CERC did not have jurisdiction at all. The
    challenge was to the exercise of jurisdiction by the CERC which
    was not permissible in light of the alternative remedy available to
    the respondent no. 1 in terms of Section 111 of the Act, 2003.

     B.     IMPUGNED ORDER
11. The High Court vide its judgment and order dated 25.02.2021,
    recorded the following submissions of the respondent no. 1:
     i.     The respondent no. 1 herein relied on this Court’s decision
            in PTC India Limited v. Central Electricity Regulatory
2072                                                        [2025] 5 S.C.R.

                         Supreme Court Reports


           Commission reported in (2010) 4 SCC 603 to submit that the
           decision of the CERC must be in conformity with the Regulations
           enacted under Section 178 of the Act, 2003 wherever such
           regulations are applicable. Therefore, the measures taken by
           the CERC under Section 79(1) are required to be in conformity
           with the Regulations under Section 178.
    ii.    It was further submitted that a regulation under Section 178
           is made under the authority of delegated legislation and
           consequently, its validity can be tested only in judicial review
           proceedings before the courts and not by way of appeal before
           the Appellate Tribunal for Electricity (the “APTEL”) under Section
           111 of the Act, 2003.
    iii.   It was submitted that the order of the CERC levying compensatory
           transmission charges on the respondent no. 1 was not in
           conformity with the 2014 Tariff Regulations enacted under
           Section 178 of the Act, 2003 and was beyond the scope of the
           said Regulations. Therefore, the said order was passed without
           any jurisdiction and hence, was being assailed before the High
           Court without availing the statutory alternative remedy.
    iv.    Further, the APTEL had already addressed a similar question
           in Nuclear Power Corporation of India Limited. v. Central
           Electricity Regulatory Commission & Ors. reported in 2019
           SCC OnLine APTEL 83 wherein it was held as under:
                “10.5 Accordingly, in absence of specific provisions
                in the Sharing Regulations/Tariff Regulations, 2014
                to deal with the situation under question the Central
                Commission through exercise of its regulatory
                powers has prescribed a principle for sharing of
                transmission charges of the Transmission System of
                the Respondent No.2 in the Impugned Order. Thus,
                it is observed that by way of exercising its regulatory
                power by a way of judicial order(s) the Central
                Commission has laid down the principles of payment
                of transmission charges in such an eventuality.
                However, it is felt that the Central Commission in
                the impugned Order has abruptly concluded the
                payment liability on the Appellant just by referring
[2025] 5 S.C.R.                                                          2073

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

                 to its earlier orders and not establishing the linkage
                 with the present case explicitly. This Tribunal would
                 like to clarify the same.”
           The respondent no. 1 submitted that the APTEL had taken a
           peculiar view of the matter. Although the CERC exercises twin
           powers of adjudication and regulation, yet the fact remains that
           the regulatory power cannot be exercised by way of a judicial
           order. Since APTEL took a contrary view on the issues at hand,
           the respondent no. 1 was of the view that no useful purpose
           would be served by filing an appeal under Section 111.
     v.    Since the orders of the CERC were in the nature of regulations
           as per the averments of the appellant, the vires of the same
           could only be questioned before the High Court and not
           before the APTEL in terms of this Court’s dictum in Whirlpool
           Corporation v. Registrar of Trademarks reported in (1998)
           8 SCC 1 wherein it has been held that despite the availability
           of an alternative remedy, a writ petition can be entertained in
           the following cases:
           (a)   Where principles of natural justice are breached,
           (b)   Where fundamental rights are sought to be enforced or
                 breach thereof is complained of,
           (c)   Where the impugned order is passed by an authority
                 without jurisdiction,
           (d)   Where the constitutionality of any provision is called in
                 question.
12. Having heard the parties, the High Court affirmed that despite
    the availability of an alternative remedy, a writ petition can be
    entertained if any of the factors mentioned in Whirlpool (supra)
    are satisfied. Since the respondent no. 1 had challenged the
    constitutionality of the orders of the CERC dated 21.01.2020 and
    27.01.2020 respectively, on the grounds that the power exercised by
    the CERC was beyond the powers vested in it as per the relevant
    regulation and that the relief granted to the appellant was beyond
    the reliefs prayed for, the High Court was of the opinion that the
    principles of natural justice were breached. Therefore, despite the
    availability of an alternative remedy, the writ petition deserved to
2074                                                       [2025] 5 S.C.R.

                        Supreme Court Reports


     be entertained. Having held so, the High Court admitted the writ
     petition for hearing on merits. The relevant portion of the impugned
     order is reproduced below:
          “[13] This is trite that despite availability of alternative
          remedy, a writ petition can be entertained if any of the
          factors mentioned in the judgment of Whirlpool (supra) are
          satisfied. In the instant case, the petitioner has challenged
          the constitutionality of the orders. Even if it is challenged
          by way of amendment, once amendment is allowed it will
          relate back to the original date of filing of writ petitions.
          Petitioner has also challenged the orders by contending
          that power exercised by the Commission was beyond the
          powers vested in it as per relevant regulation. The relief
          granted was beyond the relief prayed for. Hence, principles
          of natural justice were breached. In our view, in a case of
          this nature despite availability of alternative remedy, the
          writ petition can be entertained.
          [14] Resultantly, the objection regarding alternative remedy
          is over ruled. The petition is admitted for hearing.”

     C.   SUBMISSIONS ON BEHALF OF THE APPELLANT
13. Mr. M.G. Ramachandran, the learned senior counsel appearing on
    behalf of the appellant, submitted that the orders dated 21.01.2020
    and 27.01.2020 respectively were passed by the CERC under
    Sections 62 and 79 of the Act, 2003 respectively. Section 111 of the
    Act, 2003 provides for regular first appeal on both questions of fact
    and law to the APTEL which is an expert body specially constituted
    as per the recommendations of this Court in West Bengal Electricity
    Regulatory Commission v. CESC Limited reported in (2002) 8
    SCC 715. A second appeal to this Court is allowed under Section
    125 of the Act, 2003 for the purpose of adjudication of substantial
    questions of law.
14. He submitted that the Act, 2003 is an exhaustive and self-contained
    complete code on all matters concerning electricity including
    generation, distribution, trading and transmission of electricity. The
    Act, 2003 provides for tariff fixation by the CERC under Section 62.
    Since determination of tariff is a quasi-judicial function, the same
    has been made appealable to the APTEL. The learned counsel
[2025] 5 S.C.R.                                                     2075

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

     relied upon this Court’s decision in PTC India (supra) to submit that
     the only exclusion to the scope of the appellate remedies provided
     under the Act, 2003 is that the statutory regulations notified by the
     CERC under Section 178 cannot be challenged in appeal before
     the APTEL. The APTEL, therefore, cannot rule on the vires of a
     regulation formulated by the CERC but there is no bar on it to
     interpret such regulations.
15. Therefore, a writ petition before the High Court cannot be maintained
    when an efficacious alternative remedy was available to the
    respondent. The learned counsel relied on this Court’s judgment
    in Jaipur Vidyut Vitran Nigam Limited v. MB Power (Madhya
    Pradesh) Limited reported in (2024) 8 SCC 513 and GRIDCO v.
    Western Electricity Supply Co. of Orissa Ltd. reported in (2024) 2
    SCC 500 to fortify his submission in this regard. He also contended
    that as per this Court’s dictum in Titaghur Paper Mills Co. Ltd. v.
    State of Orissa reported in (1983) 2 SCC 433, Nivedita Sharma
    v. Cellular Operators Association of India reported in (2011) 14
    SCC 337 and U.P. Jal Nigam & Anr. v. Nareshwar Sahai Mathur
    & Anr. reported in (1995) 1 SCC 21, where statutory tribunal or
    statutory remedies are in place, a writ petition should not ordinarily
    be entertained at other fora.
16. It is the case of the appellant that the respondent has not challenged
    any regulation or provision of the Act, 2003 and has only challenged
    the orders dated 21.01.2020 and 27.01.2020 respectively passed by
    the CERC which in ordinary circumstances may be appealed under
    Section 111 of the Act, 2003.
17. In the case on hand, no issue of constitutionality of the order arises
    as the conditions prescribed in this Court’s judgment in Whirlpool
    (supra), for exercise of writ jurisdiction are fulfilled. The learned
    counsel submitted that there is no violation of principles of natural
    justice as the respondent was duly served. Further, no issue as
    regards the defect in jurisdiction of the CERC was raised before
    that forum in the first instance.
18. Mr. Ramachandran submitted that it was not the case of the
    respondent that the CERC had acted wholly without jurisdiction.
    The respondent has admitted that in terms of Section 62 and
    Section 79(1)(c) and (d) of the Act, 2003, the CERC undoubtedly
    and undisputedly has the function and the jurisdiction to deal with
2076                                                       [2025] 5 S.C.R.

                         Supreme Court Reports


     inter-state transmission, determination of transmission charges and
     the sharing thereof. The orders dated 21.01.2020 and 27.01.2020
     respectively passed by the CERC had been challenged by the
     respondent only on one consideration that is, the correctness of the
     decision holding the respondent liable for transmission charges. It
     is the case of the appellant that the APTEL is competent to decide
     such issues.
19. The learned counsel further submitted that the respondent had
    intentionally not approached the APTEL with a view to escape the
    decision rendered by it in a similar set of facts wherein the liability
    of payment of transmission charges was imposed on the generating
    company in the event of delay in commissioning of downstream
    assets by it. It was submitted that the writ petition was filed by the
    respondent to avoid the binding decision of the APTEL in Nuclear
    Power Corporation (supra).
20. Mr. Ramachandran also highlighted the consequences of entertaining
    writ petitions against the orders of the CERC. He submitted that
    there are multiple beneficiaries in an inter-state transmission system.
    Owing to the nature of electricity transmission systems that span
    across states, it is possible that an identical issue relating to the
    same transmission system may be challenged before multiple High
    Courts resulting in multiplicity of decisions as well as a higher chance
    of conflict between different decisions for the same transmission
    assets. He brought to our notice that the respondent no. 4 herein that
    is, Maharashtra State Electricity Transmission Corporation Limited
    (“MSETCL”), who is one another beneficiary of the transmission
    system established by the appellant, has filed an appeal under
    Section 111 of the Act, 2003 before the APTEL bearing DFR No.
    414 of 2024 challenging the order dated 27.01.2020 passed by the
    CERC, which is the very same order that has been challenged by the
    respondent no. 1 herein before the High Court of Madhya Pradesh
    by way of a writ petition.
21. The learned counsel submitted that the delay on the part of the
    respondent no. 1 in bringing up the intra-state system cannot lead
    to deprive the appellant of the charges for its inter-state system. We
    were informed that as on 23.11.2024, the principal amount due and
    outstanding was approximately Rs. 16.86 crore along with the late
    payment surcharge.
[2025] 5 S.C.R.                                                         2077

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

     D.     SUBMISSIONS ON BEHALF OF THE RESPONDENTS
22. Mr. Prashant Singh, the learned Advocate General of the State
    of Madhya Pradesh appearing on behalf of the respondent no. 1,
    submitted that the present appeal is directed against an interim order
    of admission of the writ petition passed by the High Court and the
    same does not warrant any interference by this Court.
23. The learned counsel submitted that the orders dated 21.01.2020 and
    27.01.2020 respectively passed by the CERC, wherein the liability of
    payment of transmission charges from 11.01.2019 till the downstream
    transmission assets achieve their Commercial Operation Date, are
    beyond its jurisdiction and violative of the rights of the respondents.
    It was submitted that no statutory authority or tribunal can assume
    jurisdiction in respect of a subject matter which the statute does not
    confer on such authority/tribunal. In the circumstance that a tribunal
    erroneously decides a fact in which the question of the jurisdiction
    depends, then in that case, the order passed thereby stands vitiated.
24. Mr. Singh further submitted that the powers of the High Court are wide
    and unlimited, therefore, the availability of an alternate remedy is not
    an absolute bar under Article 226. It is the case of the respondents
    that as per the dictum of this Court in Southern Electricity Supply
    Co. of Orissa Ltd. v. Sri Seetaram Rice Mill reported in (2012) 2
    SCC 108, if the exercise of jurisdiction by a tribunal ex facie appears
    to be in futility, then the High Court would be justified to interfere with
    the order of the tribunal under Article 226. He also relied upon this
    Court’s decision in Maharashtra Chess Assn. v. Union of India
    reported in (2020) 13 SCC 285, to submit that the availability of an
    alternative remedy does not alter the discretionary nature of the High
    Court under its writ jurisdiction.
25. The learned counsel submitted that the grounds set out in the
    writ petition before the High Court clearly meet the parameters
    laid down by this Court in Whirlpool (supra) and The Asssistant
    Commissioner of State Tax and Ors. v. M/s Commercial Steel
    Limited reported in (2022) 16 SCC 447, which are as follow:
     (i)    An excess of jurisdiction,
     (ii)   A breach of fundamental rights,
     (iii) A violation of the principles of natural justice, and
     (iv) A challenge to the vires of the statute or delegated legislation.
2078                                                         [2025] 5 S.C.R.

                         Supreme Court Reports


     It is the case of the respondent that no statutory authority or tribunal
     can assume jurisdiction in respect of subject matter which the statute
     does not confer on it and an error of jurisdictional facts renders the
     order erroneous in law.
26. Mr. Singh submitted that the CERC exceeded its jurisdiction while
    ordering for recovery of transmission charges as the provisions for
    determination of tariff under the Act, 2003 do not confer power on the
    CERC to act arbitrarily and levy unilateral charges. He vehemently
    submitted that doing so is violative of the principles of natural justice.
    He argued that there is no provision either in the agreement between
    the parties or in the 2014 Tariff Regulations for claiming compensation
    or damages. He further submitted that the conditions governing the
    commissioning of the transmission assets in question were approved
    in the 38th Standing Committee meeting held on 17.07.2015 and the
    same include no provision as regards claiming of compensation or
    damages from the respondent.
27. The learned counsel brought to our notice the order dated 18.01.2019
    passed by APTEL in Nuclear Power Corporation (supra) wherein,
    in a similar set of facts, the liability to pay compensation or damages
    was imposed on the generating entity for delaying the commissioning
    of transmission assets. It is the case of the respondent that since the
    APTEL has already passed an adverse order previously, the concerns
    of the respondent may not be addressed by filing an appeal under
    Section 111 of the Act, 2003.
28. Mr. Singh informed us that the transmission line is now functional
    and fully charged. The dispute regarding payment of compensation
    or damages is with respect to a limited period of time in which
    there was admittedly, a delay in commissioning the line due to
    force majeure.
29. It was submitted that no error or illegality could be said to have
    been committed by the High Court while exercising its discretion to
    entertain the writ petition and the impugned orders passed thereby
    are neither perverse nor contrary to law.

     E.    ISSUES FOR DETERMINATION
30. Having heard the learned counsel appearing for the parties and
    having gone through the materials on record, the following questions
    fall for our consideration:
[2025] 5 S.C.R.                                                            2079

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

     i.     Whether the CERC, while exercising its functions under Section
            79(1) of the Act, 2003, is circumscribed by statutory regulations
            enacted under Section 178 of the Act, 2003?
     ii.    Whether the CERC exercises regulatory or adjudicatory
            functions under Section 79 of the Act, 2003? In other words,
            what is the scope of the CERC’s power to regulate inter-state
            transmission of electricity and determine tariff for the same
            under clauses (c) and (d) of Section 79(1)?
     iii.   Whether the grant of compensation by the CERC for the delay
            vide the orders dated 21.01.2020 and 27.01.2020 respectively,
            is a regulatory or adjudicatory function and to what extent are
            the principles of natural justice applicable to the exercise of
            such functions?
     iv.    Whether the High Court was justified in admitting the writ petition
            filed by the respondent no. 1 herein challenging the order dated
            21.01.2020 of the CERC when there existed an alternative
            remedy under Section 111 of the Act, 2003?

     F.     ANALYSIS

     i.     Relevant Provisions of the Act, 2003
31. Section 61 reads thus:
            “61. Tariff regulations.
            The Appropriate Commission shall, subject to the provisions
            of this Act, specify the terms and conditions for the
            determination of tariff, and in doing so, shall be guided
            by the following, namely:--
            (a) the principles and methodologies specified by the
            Central Commission for determination of the tariff applicable
            to generating companies and transmission licensees;
            (b) the generation, transmission, distribution and supply of
            electricity are conducted on commercial principles;
            (c) the factors which would encourage competition,
            efficiency, economical use of the resources, good
            performance and optimum investments;
2080                                                         [2025] 5 S.C.R.

                        Supreme Court Reports


         (d) safeguarding of consumers’ interest and at the same
         time, recovery of the cost of electricity in a reasonable
         manner;
         (e) the principles rewarding efficiency in performance;
         (f) multi year tariff principles;
         (g) that the tariff progressively reflects the cost of supply of
         electricity and also, reduces cross-subsidies in the manner
         specified by the Appropriate Commission;
         (h) the promotion of co-generation and generation of
         electricity from renewable sources of energy;
         (i) the National Electricity Policy and tariff policy:
         Provided that the terms and conditions for determination of
         tariff under the Electricity (Supply) Act, 1948 (54 of 1948),
         the Electricity Regulatory Commission Act, 1998 (14 of
         1998) and the enactments specified in the Schedule as
         they stood immediately before the appointed date, shall
         continue to apply for a period of one year or until the terms
         and conditions for tariff are specified under this section,
         whichever is earlier.”
32. Section 62 reads thus:
         “62. Determination of tariff.
         (1) The Appropriate Commission shall determine the tariff
         in accordance with the provisions of this Act for--
         (a) supply of electricity by a generating company to a
         distribution licensee:
         Provided that the Appropriate Commission may, in case
         of shortage of supply of electricity, fix the minimum and
         maximum ceiling of tariff for sale or purchase of electricity
         in pursuance of an agreement, entered into between a
         generating company and a licensee or between licensees,
         for a period not exceeding one year to ensure reasonable
         prices of electricity;
         (b) transmission of electricity;
         (c) wheeling of electricity;
[2025] 5 S.C.R.                                                             2081

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

           (d) retail sale of electricity:
           Provided that in case of distribution of electricity in the
           same area by two or more distribution licensees, the
           Appropriate Commission may, for promoting competition
           among distribution licensees, fix only maximum ceiling of
           tariff for retail sale of electricity.
           (2) The Appropriate Commission may require a licensee
           or a generating company to furnish separate details, as
           may be specified in respect of generation, transmission
           and distribution for determination of tariff.
           (3) The Appropriate Commission shall not, while determining
           the tariff under this Act, show undue preference to any
           consumer of electricity but may differentiate according to
           the consumer’s load factor, power factor, voltage, total
           consumption of electricity during any specified period or
           the time at which the supply is required or the geographical
           position of any area, the nature of supply and the purpose
           for which the supply is required.
           (4) No tariff or part of any tariff may ordinarily be amended,
           more frequently than once in any financial year, except
           in respect of any changes expressly permitted under the
           terms of any fuel surcharge formula as may be specified.
           (5) The Commission may require a licensee or a generating
           company to comply with such procedures as may be
           specified for calculating the expected revenues from the
           tariff and charges which he or it is permitted to recover.
           (6) If any licensee or a generating company recovers a
           price or charge exceeding the tariff determined under
           this section, the excess amount shall be recoverable by
           the person who has paid such price or charge along with
           interest equivalent to the bank rate without prejudice to
           any other liability incurred by the licensee.”
33. Section 64 reads thus:
           “64. Procedure for tariff order.
           (1) An application for determination of tariff under section 62
           shall be made by a generating company or licensee in
2082                                                     [2025] 5 S.C.R.

                      Supreme Court Reports


        such manner and accompanied by such fee, as may be
        determined by regulations.
        (2) Every applicant shall publish the application, in such
        abridged form and manner, as may be specified by the
        Appropriate Commission.
        (3) The Appropriate Commission shall, within one hundred
        and twenty days from receipt of an application under
        sub-section (1) and after considering all suggestions and
        objections received from the public,--
        (a) issue a tariff order accepting the application with such
        modifications or such conditions as may be specified in
        that order;
        (b) reject the application for reasons to be recorded in
        writing if such application is not in accordance with the
        provisions of this Act and the rules and regulations made
        thereunder or the provisions of any other law for the time
        being in force:
        Provided that an applicant shall be given a reasonable
        opportunity of being heard before rejecting his application.
        (4) The Appropriate Commission shall, within seven days
        of making the order, send a copy of the order to the
        Appropriate Government, the Authority, and the concerned
        licensees and to the person concerned.
        (5) Notwithstanding anything contained in Part X, the
        tariff for any inter-State supply, transmission or wheeling
        of electricity, as the case may be, involving the territories
        of two States may, upon application made to it by the
        parties intending to undertake such supply, transmission
        or wheeling, be determined under this section by the State
        Commission having jurisdiction in respect of the licensee
        who intends to distribute electricity and make payment
        therefor.
        (6) A tariff order shall, unless amended or revoked, continue
        to be in force for such period as may be specified in the
        tariff order.”
[2025] 5 S.C.R.                                                               2083

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

34. Section 79 reads thus:
           “79. Functions of Central Commission.
           (1) The Central Commission shall discharge the following
           functions, namely:-
           (a) to regulate the tariff of generating companies owned
           or controlled by the Central Government;
           (b) to regulate the tariff of generating companies other
           than those owned or controlled by the Central Government
           specified in clause (a), if such generating companies enter
           into or otherwise have a composite scheme for generation
           and sale of electricity in more than one State;
           (c) to regulate the inter-State transmission of electricity;
           (d) to determine tariff for inter-State transmission of
           electricity;
           (e) to issue licences to persons to function as transmission
           licensee and electricity trader with respect to their inter-
           State operations;
           (f) to adjudicate upon disputes involving generating
           companies or transmission licensee in regard to matters
           connected with clauses (a) to (d) above and to refer any
           dispute for arbitration;
           (g) to levy fees for the purposes of this Act;
           (h) to specify Grid Code having regard to Grid Standards;
           (i) to specify and enforce the standards with respect to
           quality, continuity and reliability of service by licensees;
           (j) to fix the trading margin in the inter-State trading of
           electricity, if considered, necessary;
           (k) to discharge such other functions as may be assigned
           under this Act.
           (2) The Central Commission shall advise the Central
           Government on all or any of the following matters, namely:-
           (i) formulation of National electricity Policy and tariff policy;
2084                                                         [2025] 5 S.C.R.

                        Supreme Court Reports


         (ii) promotion of competition, efficiency and economy in
         activities of the electricity industry;
         (iii) promotion of investment in electricity industry;
         (iv) any other matter referred to the Central Commission
         by that Government.
         (3) The Central Commission shall ensure transparency
         while exercising its powers and discharging its functions.
         (4) In discharge of its functions, the Central Commission
         shall be guided by the National Electricity Policy, National
         Electricity Plan and tariff policy published under section 3.”
35. Section 111 reads thus:
         “111. Appeal to Appellate Tribunal.
         (1) Any person aggrieved by an order made by an
         adjudicating officer under this Act (except under section
         127) or an order made by the Appropriate Commission
         under this Act may prefer an appeal to the Appellate
         Tribunal for Electricity:
         Provided that any person appealing against the order of
         the adjudicating officer levying any penalty shall, while filing
         the appeal, deposit the amount of such penalty:
         Provided further that where in any particular case, the
         Appellate Tribunal is of the opinion that the deposit of such
         penalty would cause undue hardship to such person, it may
         dispense with such deposit subject to such conditions as it
         may deem fit to impose so as to safeguard the realisation
         of penalty.
         (2) Every appeal under sub-section (1) shall be filed
         within a period of forty-five days from the date on which
         a copy of the order made by the adjudicating officer or
         the Appropriate Commission is received by the aggrieved
         person and it shall be in such form, verified in such
         manner and be accompanied by such fee as may be
         prescribed:
         Provided that the Appellate Tribunal may entertain an
         appeal after the expiry of the said period of forty-five days
[2025] 5 S.C.R.                                                               2085

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

           if it is satisfied that there was sufficient cause for not filing
           it within that period.
           (3) On receipt of an appeal under sub-section (1), the
           Appellate Tribunal may, after giving the parties to the
           appeal an opportunity of being heard, pass such orders
           thereon as it thinks fit, confirming, modifying or setting
           aside the order appealed against.
           (4) The Appellate Tribunal shall send a copy of every order
           made by it to the parties to the appeal and to the concerned
           adjudicating officer or the Appropriate Commission, as the
           case may be.
           (5) The appeal filed before the Appellate Tribunal under
           sub-section (1) shall be dealt with by it as expeditiously
           as possible and endeavour shall be made by it to dispose
           of the appeal finally within one hundred and eighty days
           from the date of receipt of the appeal:
           Provided that where any appeal could not be disposed of
           within the said period of one hundred and eighty days, the
           Appellate Tribunal shall record its reasons in writing for
           not disposing of the appeal within the said period.
           (6) The Appellate Tribunal may, for the purpose of
           examining the legality, propriety or correctness of any
           order made by the adjudicating officer or the Appropriate
           Commission under this Act, as the case may be, in relation
           to any proceeding, on its own motion or otherwise, call for
           the records of such proceedings and make such order in
           the case as it thinks fit.”
36. Section 178 reads thus:
           “178. Powers of Central Commission to make
           regulations.
           (1) The Central Commission may, by notification make
           regulations consistent with this Act and the rules generally
           to carry out the provisions of this Act.
           (2) In particular and without prejudice to the generality of
           the power contained in sub-section (1), such regulations
           may provide for all or any of following matters, namely:-
2086                                                      [2025] 5 S.C.R.

                       Supreme Court Reports


        (a) period to be specified under the first proviso to
        section 14;
        (b) the form and the manner of the application under sub-
        section (1) of section 15;
        (c) the manner and particulars of notice under sub-section
        (2) of section 15;
        (d) the conditions of licence under section 16;
        (e) the manner and particulars of notice under clause (a)
        of sub-section (2) of section 18;
        (f) publication of alterations or amendments to be made in
        the licence under clause (c) of sub-section (2) of section 18;
        (g) Grid Code under sub-section (2) of section 28;
        (h) levy and collection of fees and charge from generating
        companies or transmission utilities or licensees under
        sub-section (4) of section 28;
        (i) rates, charges and terms and conditions in respect of
        intervening transmission facilities under proviso to section
        36;
        (j) payment of the transmission charges and a surcharge
        under sub-clause (ii) of clause (d) of sub-section (2) of
        section 38;
        (k) reduction of surcharge and cross subsidies under
        second proviso to sub-clause (ii) of clause (d) of sub-
        section (2) of section 38;
        (l) payment of transmission charges and a surcharge under
        sub-clause (ii) of clause (c) of section 40;
        (m) reduction of surcharge and cross-subsidies under the
        second proviso to sub-clause (ii) of clause (c) of section 40;
        (n) proportion of revenues from other business to be utilised
        for reducing the transmission and wheeling charges under
        proviso to section 41;
        (o) duties of electricity trader under sub-section (2) of
        section 52;
[2025] 5 S.C.R.                                                          2087

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

           (p) standards of performance of a licensee or class of
           licensees under sub-section (1) of section 57;
           (q) the period within which information to be furnished by
           the licensee under sub-section (1) of section 59;
           (r) the manner of reduction of cross-subsidies under clause
           (g) of section 61;
           (s) the terms and conditions for the determination of tariff
           under section 61;
           (t) details to be furnished by licensee or generating
           company under sub-section (2) of section 62;
           (u) the procedures for calculating the expected revenue
           from tariff and charges under sub-section (5) of section 62;
           (v) the manner of making an application before the Central
           Commission and the fee payable therefor under sub-section
           (1) of section 64;
           (w) the manner of publication of application under sub-
           section (2) of section 64;
           (x) issue of tariff order with modifications or conditions
           under sub-section (3) of section 64;
           (y) the manner by which development of market in power
           including trading specified under section 66;
           (z) the powers and duties of the Secretary of the Central
           Commission under sub-section (1) of section 91;
           (za) the terms and conditions of service of the Secretary,
           officers and other employees of Central Commission under
           sub-section (3) of section 91;
           (zb) the rules of procedure for transaction of business
           under sub-section (1) of section 92;
           (zc) minimum information to be maintained by a licensee
           or the generating company and the manner of such
           information to be maintained under sub-section (8) of
           section 128;
           (zd) the manner of service and publication of notice under
           section 130;
2088                                                       [2025] 5 S.C.R.

                         Supreme Court Reports


           (ze) any other matter which is to be, or may be, specified
           by regulations.
           (3) All regulations made by the Central Commission under
           this Act shall be subject to the conditions of previous
           publication.”

     ii.   Relationship between Sections 79 and 178 of the Act, 2003
           respectively
37. A perusal of the provisions laying down the functions of the CERC
    indicates that the statutory authority is enjoined with the task of
    regulation as well as adjudication of several aspects of the generation,
    transmission and distribution of electricity. Section 79 of the Act,
    2003 enumerates the functions of the CERC which includes the
    dual functions of regulation and adjudication. Section 178, on the
    other hand, empowers the CERC to enact regulations by notification
    thereby delegating to the body, the power of legislating statutory
    regulations under the Act, 2003.
38. The aforesaid two provisions indicate that the CERC functions as
    both, decision-making and regulation-making authority under Sections
    79 and 178 respectively. However, while the authority exercising
    both these functions is one and the same, it is a settled position
    of law that the functions by themselves are separate and distinct.
    The functions under Section 79 are administrative or adjudicatory
    whereas those under Section 178 are legislative.
39. This Court in PTC (supra) has succinctly explained that the powers
    under Section 79 of the Act, 2003 are supposed to be exercised in
    conformity with the statutory regulations under Section 178 wherever
    such regulations are applicable. However, there is no bar on the
    exercise of powers under Section 79 in a situation where a regulation
    under Section 178 has not been enacted in respect of a particular
    subject matter. The relevant portion of the judgment reads thus:
           “53. Applying the abovementioned tests to the scheme
           of the 2003 Act, we find that under the Act, the Central
           Commission is a decision-making as well as regulation-
           making authority, simultaneously. Section 79 delineates
           the functions of the Central Commission broadly into two
           categories —mandatory functions and advisory functions.
[2025] 5 S.C.R.                                                              2089

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

           Tariff regulation, licensing (including inter-State trading
           licensing), adjudication upon disputes involving generating
           companies or transmission licensees fall under the head
           “mandatory functions” whereas advising the Central
           Government on formulation of National Electricity Policy
           and tariff policy would fall under the head “advisory
           functions”. In this sense, the Central Commission is the
           decision-making authority. Such decision-making under
           Section 79(1) is not dependent upon making of regulations
           under Section 178 by the Central Commission. Therefore,
           functions of the Central Commission enumerated in
           Section 79 are separate and distinct from functions of the
           Central Commission under Section 178. The former are
           administrative/adjudicatory functions whereas the latter
           are legislative.
           54. As stated above, the 2003 Act has been enacted in
           furtherance of the policy envisaged under the Electricity
           Regulatory Commissions Act, 1998 as it mandates
           establishment of an independent and transparent
           Regulatory Commission entrusted with wide-ranging
           responsibilities and objectives inter alia including protection
           of the consumers of electricity. Accordingly, the Central
           Commission is set up under Section 76(1) to exercise the
           powers conferred on, and in discharge of the functions
           assigned to, it under the Act. On reading Sections 76(1)
           and 79(1) one finds that the Central Commission is
           empowered to take measures/steps in discharge of the
           functions enumerated in Section 79(1) like to regulate the
           tariff of generating companies, to regulate the inter-State
           transmission of electricity, to determine tariff for inter-State
           transmission of electricity, to issue licences, to adjudicate
           upon disputes, to levy fees, to specify the Grid Code, to
           fix the trading margin in inter-State trading of electricity,
           if considered necessary, etc. These measures, which the
           Central Commission is empowered to take, have got to
           be in conformity with the regulations under Section 178,
           wherever such regulations are applicable. Measures under
           Section 79(1), therefore, have got to be in conformity with
           the regulations under Section 178.
2090                                                       [2025] 5 S.C.R.

                         Supreme Court Reports


          55. To regulate is an exercise which is different from making
          of the regulations. However, making of a regulation under
          Section 178 is not a precondition to the Central Commission
          taking any steps/measures under Section 79(1). As stated,
          if there is a regulation, then the measure under Section
          79(1) has to be in conformity with such regulation under
          Section 178. This principle flows from various judgments
          of this Court which we have discussed hereinafter. For
          example, under Section 79(1)(g) the Central Commission
          is required to levy fees for the purpose of the 2003 Act.
          An order imposing regulatory fees could be passed even
          in the absence of a regulation under Section 178. If the
          levy is unreasonable, it could be the subject-matter of
          challenge before the appellate authority under Section
          111 as the levy is imposed by an order/decision-making
          process. Making of a regulation under Section 178 is not
          a precondition to passing of an order levying a regulatory
          fee under Section 79(1)(g). However, if there is a regulation
          under Section 178 in that regard then the order levying
          fees under Section 79(1)(g) has to be in consonance with
          such regulation.
          56. Similarly, while exercising the power to frame the terms
          and conditions for determination of tariff under Section 178,
          the Commission has to be guided by the factors specified in
          Section 61. It is open to the Central Commission to specify
          terms and conditions for determination of tariff even in the
          absence of the regulations under Section 178. However,
          if a regulation is made under Section 178, then, in that
          event, framing of terms and conditions for determination
          of tariff under Section 61 has to be in consonance with
          the regulations under Section 178.”
                                                 (Emphasis supplied)

40. What is discernible from the aforesaid exposition of law is that there
    is a dichotomy between the power to make a regulation under Section
    178 and the power to regulate or adjudicate on the various areas
    enumerated under Section 79(1). A regulation under Section 178 is
    of general application to the entirety of a particular subject matter as
    opposed to regulation on a case-to-case basis which may be done
[2025] 5 S.C.R.                                                            2091

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

     by the CERC under Section 79. Therefore, making of a regulation
     under Section 178 has the effect of interfering with and overriding
     existing contractual relationships between the regulated entities. On
     the other hand, the orders under Section 79 have to be confined to
     the existing statutory regulations and do not have the effect of altering
     the terms of contract between the specific parties before the CERC.
41. This Court in PTC (supra) also held that though the validity of a
    delegated legislation under Section 178 can be tested by way of
    judicial review of the courts and not by way of an appeal under
    Section 111, yet a dispute as regards the interpretation of a regulation
    enacted under Section 178 is entertainable before the APTEL by
    way of an appeal.
42. In Energy Watchdog v. CERC, reported in (2017) 14 SCC 80, this
    Court has further held that Section 79(1) is the repository of the
    regulatory powers of the CERC and such powers must be exercised
    in consonance with the guidelines or regulations under Section 178.
    However, if there are no such guidelines or regulations in place, it
    cannot be said that the hands of the CERC are tied when it encounters
    a regulatory lacuna. The relevant portion of the judgment reads thus:
           “20. It is important to note that the regulatory powers of
           the Central Commission, so far as tariff is concerned, are
           specifically mentioned in Section 79(1). This regulatory
           power is a general one, and it is very difficult to state
           that when the Commission adopts tariff under Section
           63, it functions dehors its general regulatory power under
           Section 79(1)(b). For one thing, such regulation takes
           place under the Central Government’s guidelines. For
           another, in a situation where there are no guidelines or in
           a situation which is not covered by the guidelines, can it
           be said that the Commission’s power to “regulate” tariff is
           completely done away with? According to us, this is not a
           correct way of reading the aforesaid statutory provisions.
           The first rule of statutory interpretation is that the statute
           must be read as a whole. As a concomitant of that rule,
           it is also clear that all the discordant notes struck by the
           various sections must be harmonised. Considering the
           fact that the non obstante clause advisedly restricts itself
           to Section 62, we see no good reason to put Section 79
           out of the way altogether. The reason why Section 62
2092                                                       [2025] 5 S.C.R.

                        Supreme Court Reports


          alone has been put out of the way is that determination
          of tariff can take place in one of two ways — either under
          Section 62, where the Commission itself determines the
          tariff in accordance with the provisions of the Act (after
          laying down the terms and conditions for determination of
          tariff mentioned in Section 61) or under Section 63 where
          the Commission adopts tariff that is already determined
          by a transparent process of bidding. In either case,
          the general regulatory power of the Commission under
          Section 79(1)(b) is the source of the power to regulate,
          which includes the power to determine or adopt tariff. In
          fact, Sections 62 and 63 deal with “determination” of tariff,
          which is part of “regulating” tariff. Whereas “determining”
          tariff for inter-State transmission of electricity is dealt
          with by Section 79(1)(d), Section 79(1)(b) is a wider
          source of power to “regulate” tariff. It is clear that in
          a situation where the guidelines issued by the Central
          Government under Section 63 cover the situation, the
          Central Commission is bound by those guidelines and
          must exercise its regulatory functions, albeit under Section
          79(1)(b), only in accordance with those guidelines. As has
          been stated above, it is only in a situation where there
          are no guidelines framed at all or where the guidelines
          do not deal with a given situation that the Commission’s
          general regulatory powers under Section 79(1)(b) can
          then be used.”
                                                (Emphasis supplied)

43. In the case on hand, the CERC vide its orders dated 21.01.2020
    and 27.01.2020 respectively imposed the liability of payment of
    compensation for delay onto the respondent no. 1. It is the case
    of the respondent no. 1 that by doing so, the CERC did not act in
    conformity with the 2014 Tariff Regulations which do not provide
    for payment of transmission charges by a party to whom the delay
    is attributable. In our considered view, the said argument does not
    hold any water. This Court’s dictum in PTC (supra) and Energy
    Watchdog (supra) respectively settles the law in this regard and
    the absence of a regulation under Section 178 does not preclude
    the CERC from exercising its powers under Section 79(1) to make
    specific regulations or pass orders between the parties before it.
[2025] 5 S.C.R.                                                               2093

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

     iii.   Regulatory and adjudicatory functions of the CERC under
            Section 79
44. The CERC vide its orders dated 21.01.2020 and 27.01.2020
    respectively determined and approved the transmission tariff for the
    assets commissioned by the appellant at the Indore substation under
    Section 79 wherein the specific prayer for condonation of delay in
    commissioning of the said assets was taken by the appellant in terms
    of the Regulation 4(3)(ii) of 2014 Tariff Regulations.
            “4. Date of Commercial Operation:
            The date of commercial operation of a generating station or
            unit or block thereof or a transmission system or element
            thereof shall be determined as under:
            […]
            (3) Date of commercial operation in relation to a
            transmission system shall mean the date declared by the
            transmission licensee from 0000 hour of which an element
            of the transmission system is in regular service after
            successful trial operation for transmitting electricity and
            communication signal from sending end to receiving end:
            Provided that:
            (i)    where the transmission line or substation is dedicated
                   for evacuation of power from a particular generating
                   station, the generating company and transmission
                   licensee shall endeavour to commission the generating
                   station and the transmission system simultaneously as
                   far as practicable and shall ensure the same through
                   appropriate Implementation Agreement in accordance
                   with Regulation 12(2) of these Regulations :
            (ii)   in case a transmission system or an element thereof
                   is prevented from regular service for reasons not
                   attributable to the transmission licensee or its supplier
                   or its contractors but is on account of the delay in
                   commissioning of the concerned generating station
                   or in commissioning of the upstream or downstream
                   transmission system, the transmission licensee shall
                   approach the Commission through an appropriate
2094                                                       [2025] 5 S.C.R.

                         Supreme Court Reports


                application for approval of the date of commercial
                operation of such transmission system or an element
                thereof. […]”
                                                 (Emphasis supplied)

45. The appellant in its petition before the CERC had submitted that
    the delay was due to the delay in commissioning of the associated
    transmission lines which were in scope of the respondent no. 1
    herein. It is in consequence to this prayer that the CERC, though
    did not condone the delay, yet granted the liberty to the appellant
    to claim compensation from the respondent no. 1.
46. It is the submission of the respondent no. 1 that the CERC does
    not possess any regulatory or legislative power while adjudicating a
    petition and it functions as a purely quasi-judicial body, therefore, it
    does not have the jurisdiction to impose a charge on the respondent
    no. 1. In our considered view, the said argument must fail for the
    reason that Section 79 of the Act, 2003 envisages dual function
    of regulation and adjudication to be performed by the CERC. The
    expressions “to regulate”, “to determine” and “to adjudicate” are
    used for different purposes in the list of matters enumerated under
    Section 79(1) and cannot be incorporated within the umbrella term
    of “adjudication”.
47. The exposition of law in PTC (supra) clarifies the scheme of
    regulatory powers and functions under the Act, 2003. It was held
    therein that Section 178 that deals with making of regulations by
    way of subordinate legislation by the CERC, is wider than Section
    79(1) which enumerates specified areas where the CERC exercises
    regulatory functions to be discharged by orders or decisions.
    Therefore, unlike the regulations enacted under Section 178 that
    have a general application, the CERC, under Section 79, has both
    regulatory and adjudicatory functions which it exercises in respect of
    specific issues arising between specific parties. The relevant portion
    of the judgment reads thus:
          “92. (i) In the hierarchy of regulatory powers and functions
          under the 2003 Act, Section 178, which deals with making
          of regulations by the Central Commission, under the
          authority of subordinate legislation, is wider than Section
          79(1) of the 2003 Act, which enumerates the regulatory
[2025] 5 S.C.R.                                                       2095

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

           functions of the Central Commission, in specified areas,
           to be discharged by orders (decisions).”
                                                 (Emphasis supplied)

48. The regulatory powers provided to the CERC under Section 79 are
    of ad hoc nature and are required to be exercised by the CERC in
    context of the specific circumstances of the parties before it. The
    rationale for provision of such ad hoc powers by the Act, 2003 is to
    ensure that regulatory gaps, if any, that may be discovered on a case-
    to-case basis, are filled or removed. Therefore, there is no doubt in
    our mind that the CERC is enabled to exercise its regulatory powers
    by way of orders under Section 79 and the purview of Section 79 is
    not limited to only adjudicatory orders but includes within its scope
    administrative functions as well.

     iv.   Grant of compensation for delay on the part of a party is
           a regulatory function
49. The respondent no. 1 would submit that the CERC exhibits the
    trappings of an adjudicatory authority when it determines tariff and
    therefore, was required to confine itself to the reliefs as prayed for
    by the appellant before the CERC. By providing the appellant with
    the liberty to claim compensation from the respondent no. 1, CERC
    could be said to have granted a relief that was not sought for and the
    proper opportunity to defend against such claims was not afforded
    to respondent no. 1. In order to address this submission, we must
    first look into the nature of the power exercised by the CERC while
    determining tariff under Section 79(1).
50. This Court in PTC (supra) has held that the determination of tariff
    under Section 79(1) is an adjudicatory function of the CERC for the
    following reasons:
     (i)   First, the actual determination/fixation of tariff is done by
           the appropriate commission between the parties before it
           under Section 62 of the Act, 2003. Although Section 61 is the
           enabling provision for framing of regulations while keeping in
           mind the generic propositions provided thereunder, yet the
           determination of tariff in respect of a specific generation unit,
           asset, transmission line, etc, is done by virtue of the power
           emanating from Section 62. Therefore, the determination of
2096                                                         [2025] 5 S.C.R.

                         Supreme Court Reports


           tariff is specific to an individual case and is not of general
           application under the Act, 2003. This is in consonance with the
           test laid down in Sitaram Sugar Co. Ltd. v. Union of India,
           reported in (1990) 3 SCC 223 wherein it was held that one of
           the factors to determine if an order was issued in exercise of
           an adjudicatory function, is to ascertain whether it was specific
           to an individual or of general application.
    (ii)   Secondly, even though determination of tariff like price fixation
           is a legislative act, yet such determination has been made
           appealable to the APTEL under Section 111. The terms of the
           Act, 2003, therefore, clearly indicate that determination of tariff
           is an adjudicatory function. The relevant observations of this
           Court in PTC (supra) are reproduced below:
                “26. The term “tariff” is not defined in the 2003 Act.
                The term “tariff” includes within its ambit not only the
                fixation of rates but also the rules and regulations
                relating to it. If one reads Section 61 with Section 62
                of the 2003 Act, it becomes clear that the appropriate
                Commission shall determine the actual tariff in
                accordance with the provisions of the Act, including
                the terms and conditions which may be specified by
                the appropriate Commission under Section 61 of the
                said Act. Under the 2003 Act, if one reads Section 62
                with Section 64, it becomes clear that although tariff
                fixation like price fixation is legislative in character,
                the same under the Act is made appealable vide
                Section 111. These provisions, namely, Sections
                61, 62 and 64 indicate the dual nature of functions
                performed by the Regulatory Commissions viz.
                decision-making and specifying terms and conditions
                for tariff determination.
                49. On the above analysis of various sections of
                the 2003 Act, we find that the decision-making
                and regulation-making functions are both assigned
                to CERC. Law comes into existence not only
                through legislation but also by regulation and
                litigation. Laws from all three sources are binding.
                According to Professor Wade, “between legislative
[2025] 5 S.C.R.                                                          2097

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

                and administrative functions we have regulatory
                functions”. A statutory instrument, such as a rule or
                regulation, emanates from the exercise of delegated
                legislative power which is a part of administrative
                process resembling enactment of law by the
                legislature whereas a quasi-judicial order comes from
                adjudication which is also a part of administrative
                process resembling a judicial decision by a court of
                law. (See Shri Sitaram Sugar Co. Ltd. v. Union of
                India [(1990) 3 SCC 223].)
                50. Applying the above test, price fixation exercise
                is really legislative in character, unless by the terms
                of a particular statute it is made quasi-judicial as
                in the case of tariff fixation under Section 62 made
                appealable under Section 111 of the 2003 Act,
                though Section 61 is an enabling provision for the
                framing of regulations by CERC. If one takes “tariff”
                as a subject-matter, one finds that under Part VII of
                the 2003 Act actual determination/fixation of tariff is
                done by the appropriate Commission under Section
                62 whereas Section 61 is the enabling provision for
                framing of regulations containing generic propositions
                in accordance with which the appropriate Commission
                has to fix the tariff. This basic scheme equally
                applies to the subject-matter “trading margin” in a
                different statutory context as will be demonstrated
                by discussion hereinbelow.”
                                                 (Emphasis supplied)

51. While we are in complete agreement with the observations in PTC
    (supra), we are of the opinion that the bench therein had no occasion
    to consider the issue of other kinds of reliefs that may be given by
    the CERC under Section 79(1) read with Section 61 of the Act, 2003.
52. The question that falls for our consideration is whether the grant of
    compensation by the CERC was a decision taken by the authority
    in its regulatory or adjudicatory capacity and whether it goes a
    step beyond the function of determination of tariff. To answer this
    question, we may refer to this Court’s decision in Airports Economic
2098                                                         [2025] 5 S.C.R.

                          Supreme Court Reports


    Regulatory Authority of India v. Delhi International Airport Ltd.,
    reported in 2024 SCC OnLine SC 2923 (“AERA”) wherein one of
    us, J.B. Pardiwala, J., was a part of the bench. We may refer to the
    following observations in AERA (supra) with profit:
    (i)    First, it was observed that while the distinction between ‘general’
           or ‘specific’ as laid down in Sitaram Sugar (supra) is a crucial
           test consistently applied by this Court for identifying adjudicatory
           functions, it cannot be the sole litmus test for distinguishing
           between regulatory and adjudicatory functions, especially
           where the statute in question does not draw a clear distinction
           between the adjudication and regulatory functions. A function,
           however specific, cannot be considered de hors the context in
           which it is being exercised.
    (ii)   Secondly, an examination of the broad factors that are required
           to be considered while exercising a function is important to
           ascertain the nature of such function. The relevant portion of
           the judgment reads thus:
                57. It may be argued by relying on the judgment
                in PTC (supra) that the 2011 Guidelines issued in
                exercise of the power under Section 15 is a regulatory
                function while the determination of tariff under Section
                13(1)(a) is adjudicatory by relying on the distinction
                between ‘general’ and ‘specific’ as highlighted above.
                In PTC (supra), this Court drew a distinction between
                Section 61 of the Electricity Act which grants the
                Appropriate Commission the power to issue specific
                terms and conditions for determination of tariff and
                Section 62 which grants the power to determine tariff.
                The crucial test that has been consistently applied by
                this Court in drawing the distinction is to determine
                if the function is discharged in the capacity of a
                regulator or an adjudicator. Now, it may be possible
                that certain statutes create a clear distinction between
                the regulatory and adjudicatory roles with respect to
                the same function. When such a distinction is created,
                the Authority does not put on the hat of a regulator
                while undertaking the adjudicatory function. On the
                other hand, certain other statutes may require the
[2025] 5 S.C.R.                                                              2099

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

                Authority to ‘determine’ something in its capacity
                as a regulator. In such cases, a clear distinction
                between the adjudication and regulatory functions
                cannot be drawn.
                                        ---xxx---
                59. The respondents have relied on two clauses
                of Section 13 to argue that tariff determination is
                an adjudicatory function. The first is the proviso
                to Section 13(1)(a) which provides that different
                tariff structures may be determined for different
                airports. This, it is argued, is a specific/individualistic
                component which is an indicator of the adjudicatory
                function. It is true that this Court in Sitaram Sugar
                (supra) held that one of the factors to assess if a
                function is adjudicatory is by determining if it has
                a specific or a general application. However, the
                observations cannot be interpreted to mean that it
                is an overarching consideration in the determination
                of whether the function is adjudicatory. Neither can
                it be interpreted to mean that the factor must be
                considered de hors the context. The consideration of
                the factors while exercising the function is equally and
                if not more important as a factor. As the judgment in
                Sitaram Sugar (supra) notes, “judicial decisions are
                made according to law while administrative decisions
                emanate from administrative policy.” As held above,
                the factors to be considered by AERA in terms of
                Section 13(1)(a) are purely ‘policy’ factors. Further, the
                function of AERA to determine tariff must be read in
                the context of the role of the Authority as a ‘regulator’
                as has been highlighted above. Modern constitutional
                governance requires that legislation is not general
                but context specific. Over-emphasising the distinction
                between general and specific provisions to determine
                if a function is regulatory or adjudicatory would be to
                completely ignore the jurisprudential developments
                governing both the regulatory domain and Article 14.
                                                    (Emphasis supplied)
2100                                                         [2025] 5 S.C.R.

                          Supreme Court Reports


53. A reading of the Act, 2003 would indicate that it makes no distinction
    between the regulatory and adjudicatory functions vested in and
    conferred upon the CERC, which is a quasi-judicial body enjoined
    to regulate and administer the subject of electricity generation,
    transmission and distribution. In such a situation, it becomes
    necessary for us to undertake a harmonious reading of Sections
    61 and 79 respectively to determine whether the CERC granted
    the liberty to claim compensation in exercise of its regulatory or
    adjudicatory function.
54. Section 61 of the Act, 2003 lays down the guidelines that the
    CERC must adhere to while specifying the terms and conditions
    for determination of tariff, which inter alia includes that: (i) the
    generation, transmission, distribution and supply of electricity are to be
    conducted on commercial principles; and (ii) the consumers’ interest
    is to be safeguarded while also recovering the cost of electricity in
    a reasonable manner.
55. This Court in Power Grid Corpn. of India Ltd. v. Punjab State Power
    Corpn. Ltd., reported in (2016) 4 SCC 797 (“Barh-Balia”) has held
    that beneficiaries cannot be made liable to pay for the delay in any
    transmission element, which in turn prevents the entire transmission
    system form being operationalized. This is in consonance with the
    principle of safeguarding consumers’ interest. We affirm that in a
    situation where transmission charges accrue before the assets are
    operationalized due to a non-condonable delay on part of one of the
    utilities in charge of putting the transmission element into use, the
    cost of transmission cannot be put on the beneficiaries or consumers
    through the Point of Connection (POC) mechanism. The relevant
    portion of the Barh-Balia judgment is reproduced below:
           “10. […] In our opinion, Regulation 3(12) of the 2009
           Regulations cannot be interpreted against the spirit of the
           definition of “transmission lines” given in the statute. It is
           evident from the record that it is not a disputed fact that
           switchgear at Barh end of Barh-Balia line for protection
           and metering were to be installed by NTPC and the same
           was not done by it when transmission line was completed
           by the appellant. As such the appellant might have
           suffered due to delay on the part of NTPC in completing
           the transmission lines for some period. But beneficiaries,
[2025] 5 S.C.R.                                                         2101

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

           including Respondent 1, cannot be made liable to pay for
           this delay w.e.f. 1-7-2010 as the energy supply line had
           not started on the said date.
           12. Since we are in agreement with the Tribunal that in
           the present case, Respondent 1 and the beneficiaries
           could not have been made liable to pay the tariff before
           transmission line was operational, we find no infirmity in
           the impugned order. Therefore, the appeals are liable to
           be dismissed. Accordingly, both the appeals are dismissed
           without prejudice to the right of the appellant, if any,
           available to it under law, against NTPC. There shall be
           no order as to costs.”
                                                 (Emphasis supplied)

56. In the case on hand, there is no contractual clause between the parties
    for establishing the risks of delay in commissioning of a transmission
    asset. There is also no uniform settled position as regards the liability
    of transmission charges payable before a particular transmission
    element is put in operation, in the form of regulations under Section
    178. These circumstances, considered together with the prohibition
    on imposing liability of delayed payments on beneficiaries, leave a
    regulatory gap. This lacuna was recognized by APTEL in Nuclear
    Power Corporation (supra) wherein the correctness of the CERC’s
    order was questioned. The CERC, therein, had imposed the liability
    of transmission charges on the defaulting party on account of a
    transmission element not having been put to use by it, in the absence
    of a contractual arrangement between the parties. It was held that in
    the absence of any specific provisions dealing with the situation in
    the 2014 Tariff Regulations or any other concurrent regulations under
    Section 178, the CERC has prescribed a principle that the party to
    which the delay is attributable would be responsible for payment of
    the transmission charges for the period of delay not condoned. The
    relevant portion of the order is reproduced below:
           “10.2 […] Similarly, in the facts of the instant Appeal,
           there is no inter se contractual arrangement between
           the Respondent No. 2 and the defaulting party, i.e. the
           Appellant. However, similar to the factual situation in the
           case of the Patran Judgment, the Respondent No. 2 had
           entered into the TSA dated 24.07.2013 with the various
2102                                                         [2025] 5 S.C.R.

                         Supreme Court Reports


          LTTCs, who were the beneficiaries of the Project being
          established by it.
          10.3 We further observe that these type of major issues
          ought to have been covered under Regulations by the
          Central Commission to plug the gaps, which would avoid
          litigations. The importance of the same was considered
          by the Central Commission at one point of time in its
          order dated 5.8.2015 and directed its staff for appropriate
          amendments in the Tariff Regulations, 2014. Till date no
          such modifications have been carried out by it in the
          Regulations. It is however, observed that there are many
          regulatory/judicial orders of the Central Commission to
          deal with the situations like in the present case.
                                     ---xxx---
          10.5 Accordingly, in absence of specific provisions in the
          Sharing Regulations/Tariff Regulations, 2014 to deal with
          the situation under question the Central Commission
          through exercise of its regulatory powers has prescribed
          a principle for sharing of transmission charges of the
          Transmission System of the Respondent No. 2 in the
          Impugned Order. Thus, it is observed that by way of
          exercising its regulatory power by a way of judicial order
          (s) the Central Commission has laid down the principles
          of payment of transmission charges in such an eventuality.
          However, it is felt that the Central Commission in the
          Impugned Order has abruptly concluded the payment
          liability on the Appellant just by referring to its earlier
          orders and not establishing the linkage with the present
          case explicitly. This Tribunal would like to clarify the same.”
                                                  (Emphasis supplied)

57. The respondent no. 1 has averred that the CERC cannot conflate its
    powers of regulation with its adjudicatory functions and a regulation
    cannot be brought into force by way of a judicial order. In the specific
    case of Nuclear Power Corporation (supra), we are inclined to
    agree with the submission of the respondent no. 1 to the extent that
    a regulation cannot be done through the process of adjudication.
    However, could it be said that there is a blanket ban on the CERC
[2025] 5 S.C.R.                                                        2103

      Power Grid Corporation of India Limited v. Madhya Pradesh
            Power Transmission Company Limited & Ors.

     to exercise its regulatory functions by way of orders under Section
     79(1)? In light of this Court’s dictum in AERA (supra), our answer
     to this question must be an emphatic ‘No’.
58. We are of the view that even though the orders under Section 79
    may not always be limpid as regards the matters where CERC is
    exercising its regulatory functions yet this cannot be the reason
    to conclude that the CERC passes all orders in its capacity as an
    adjudicator. The nomenclature “judicial order(s)” as used in Nuclear
    Power Corporation (supra) does not change the nature of a specific
    order that the CERC gives in its capacity as a regulator and the
    courts must understand the true import of an order to determine
    the nature thereof.
59. The CERC granted liberty to the appellant herein to claim compensation
    from the respondent no. 1 to deal with a situation caused due to
    an unprecedented event not covered by any guidelines, regulations
    or contractual provisions between the parties. The dictum of this
    Court in paragraph 20 of Energy Watchdog (supra), indicates that
    in such a situation where there is an absence of regulations and
    guidelines, the Act, 2003 mandates the CERC to strike a judicious
    balance between the parties keeping in mind commercial principles
    and consumers’ interest, in exercise of its general regulatory powers
    under Section 79(1).
60. The aforesaid leaves no manner of doubt in our mind that though
    the CERC’s orders dated 21.01.2020 and 27.01.2020 respectively
    were for determination of tariff, yet the order granting liberty to the
    aggrieved appellant to claim compensation from the defaulting party
    is a consequence of a regulatory lacuna in the 2014 Tariff Regulations
    and therefore, is an instance of regulation of tariff between the parties.
61. Since the CERC was not adjudicating the issue of delay between
    the parties but was only regulating the consequences of the delay
    to the commissioning of the transmission elements, we are of the
    view that there was no requirement for a specific prayer in this
    regard. As a natural corollary, there was also no occasion for the
    respondent no. 1 to be afforded an opportunity to be heard at that
    stage. In our considered view, any dispute pertaining to the levy of
    transmission charges incurred before the concerned transmission
    assets were put to use, would arise only upon the appellant raising
    bills to the respondent no. 1 in this regard. In such a scenario, it
2104                                                        [2025] 5 S.C.R.

                         Supreme Court Reports


     cannot be said that there was a contravention of the principles of
     natural justice by the CERC.
62. As regards the contention of the respondent no. 1 that the validity
    of a regulation cannot be looked into by the statutory authorities
    under the Act, 2003, we are of the view that the said submission
    was made without considering the general regulatory power under
    Section 79(1). While we are in agreement with the submission of the
    respondent no. 1 that the vires of a regulation under Section 178
    cannot be challenged before an authority that is the creation of the
    parent statute, the same cannot be said so for a specific regulation
    effected under Section 79(1).
63. It is apposite to mention that the sources of power for enactment of
    a regulation under Section 178 and regulatory order under Section
    79(1) are different. The former emanates from the power of delegated
    legislation whereas the latter is an ad hoc power which is limited
    to the specific parties and situation in context of which the order is
    given. Since the regulatory powers under Section 79(1) are of an ad
    hoc nature and are not of general application, the orders thereunder
    are made appealable under Section 111.
64. In view of the aforesaid exposition of law, we find that this Court’s
    observations in Whirlpool (supra) are of no avail to the respondent
    no. 1 as the present matter falls in none of the cases enumerated
    therein. Therefore, there was no occasion for the High Court to admit
    the writ petition of the respondent no. 1.

     G.   CONCLUSION
65. For all the foregoing reasons, we have reached the conclusion
    that the High Court committed an egregious error in passing the
    impugned judgment. We are left with no other option but to set
    aside the impugned judgment and order dated 25.02.2021 passed
    by the High Court and dismiss both the writ petitions. In the result,
    the appeals succeed and are hereby allowed.
66. Before we close this judgment, we must clarify something important
    with a view to obviate the possibility of any confusion. The matter
    before us pertained to the maintainability of the writ petitions filed by
    the respondent no. 1 on the grounds that CERC had no jurisdiction
    to grant liberty to the appellant herein to claim compensation. As
    already discussed by us in the foregoing paragraphs, the CERC is
[2025] 5 S.C.R.                                                      2105

         Power Grid Corporation of India Limited v. Madhya Pradesh
               Power Transmission Company Limited & Ors.

     empowered to order for imposition of transmission charges on the
     party to whom delay is attributable. We, however, have not considered
     the question whether such liability of payment of transmission charges
     could be imposed on the respondent no. 1 in the specific facts of the
     case on hand. We are of the opinion that APTEL is the appropriate
     authority to look into the merits of the matter should the respondent
     no. 1 choose to prefer an appeal before APTEL under Section 111
     of the Act, 2003.
67. Pending application(s), if any, are disposed of.
68. We direct the Registry to circulate a copy of this judgment to all
    High Courts.

     Result of the case: Appeals allowed.




     †
         Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Section 79 of the Electricity Act, 2003"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.