Created byFuzzy Cloud

Supreme Court of India

M/S FERRO CONCRETE CONSTRUCTION (INDIA) PVT. LTD.versusTHE STATE OF RAJASTHAN

Citation
2025 INSC 429
Decided
1 April 2025
Disposal
Appeal(s) allowed

Holding

Clause 22 does not expressly bar the arbitrator from awarding pendente lite interest, so the arbitrator's power remains and the appeal is allowed with 9% interest.

Summary

M/s Ferro Concrete Construction (India) Pvt. Ltd. entered into a works contract with the State of Rajasthan that contained Clause 22 prohibiting the contractor from claiming any interest on payments, arrears or balances. Disputes led to arbitration under the Arbitration Act, 1940, where the arbitrator awarded the contractor a sum with 15% pendente lite interest. The District Judge and the Rajasthan High Court reduced the interest to 9% simple interest, holding that Clause 22 barred the arbitrator's power to award interest. The Supreme Court examined the interpretation of contractual clauses under the 1940 Act and the 1996 Act, emphasizing that an express bar must be clear and specific to exclude pendente lite interest. It held that Clause 22, being a general prohibition on the contractor's claim, does not expressly bar the arbitrator from granting pendente lite interest. Consequently, the Court set aside the High Court's decision and allowed the appeal, directing that 9% pendente lite interest be awarded from the date of reference to the date of the award. The appeal was allowed and costs were left to the parties.

Issues considered

  • Whether Clause 22, which bars the contractor from claiming interest on any payment, constitutes an express bar on the arbitrator's power to award pendente lite interest under the Arbitration Act, 1940.
  • How contractual clauses barring interest are to be interpreted under the Arbitration Act, 1940 versus the Arbitration and Conciliation Act, 1996.

Legislation cited

Subjects

Grant of interest under Arbitration Act, 1940Contractual clausesPayment of interestPendente lite interest on arbitral sumPhraseology of the agreementClauses conferring powers relating to arbitrationPower to award interestExpress contractual bar on payment of pendente lite interest

Judgment

                  [2025] 4 S.C.R. 529 : 2025 INSC 429

           M/s Ferro Concrete Construction (India) Pvt. Ltd.
                                 v.
                       The State of Rajasthan
                       (Civil Appeal No. 4723 of 2025)
                                  02 April 2025
[Pamidighantam Sri Narasimha* and Joymalya Bagchi, JJ.]


                            Issue for Consideration
       Whether the contractual clause that bars the appellant/contractor
       from claiming any interest on any payment, arrears or balance due
       to it amounts to an express bar on the arbitrator’s power to grant
       pendente lite interest as per the law under the Arbitration Act, 1940.

                                   Headnotes†
       Arbitration Act, 1940 – Appellant was awarded a works
       contract by the respondent – A Clause 22 of the agreement
       barred the appellant from claiming interest on any payment
       or arrears or balance due to him – Disputes arose between
       the parties – Arbitration invoked – Arbitral award came out
       in favour of appellant – Arbitrator granted 15% pendente lite
       interest – However, the District Judge granted 9% simple
       interest on the Principal sum – Same was upheld by the High
       Court – Correctness:
       Held: Both the decisions in Reliance Cellulose and the First
       Ambica case emphasise the need for an express contractual bar
       on the payment of pendente lite interest to create a bar on the
       arbitrator from awarding interest – They also emphasise that a
       bar on the arbitrator’s power would depend on the phraseology
       of the contractual clause in that case – In the instant case, the
       Clause 22 prohibits the appellant (contractor) from claiming interest
       on any payment, arrears or balance, which may be found due to
       him at any time – Applying the above-stated law, this Court finds
       that this clause does not expressly bar the award of pendente lite
       interest in the event of disputes, differences, or misunderstandings
       between the parties, or on delayed payment, or in any other respect
       whatsoever – Under the 1940 Act, this Court has not readily
       inferred a bar on the arbitrator from clauses that merely bar the

* Author
530                                                             [2025] 4 S.C.R.

                        Digital Supreme Court Reports


       contractor from claiming interest, and the same will apply to this
       case as well – In view thereof, the judgment of the High Court is set
       aside – However, considering that the arbitrator entered reference
       in 1991 and the award was made in 1995, along with the passage
       of time in litigation as well as the amounts already paid by the
       respondent including post-award interest @ 9%, this Court deems
       it appropriate to grant 9% pendente lite interest, instead of 15%
       as granted by the arbitral tribunal, from 18.12.1991 till 07.03.1995
       (date of the arbitral award). [Paras 14, 15, 16]
       Arbitration Act, 1940 – Arbitration and Conciliation Act, 1996 –
       Position of law on the grant of interest – Discussed.

                                Case Law Cited
       Secretary, Irrigation Department, Government of Orissa v. G.C.
       Roy [1991] Supp. 3 SCR 417 : (1992) 1 SCC 508; Executive
       Engineer, Dhenkanal Minor Irrigation Division v. N.C. Budharaj
       [2001] 1 SCR 264 : (2001) 2 SCC 721 – followed.
       Reliance Cellulose Products Ltd v. Oil and Natural Gas Corporation
       Limited [2018] 6 SCR 618 : (2018) 9 SCC 266; Union of
       India v. Ambica Construction [2016] 2 SCR 810 : (2016) 6 SCC
       36 – relied on.
       Pam Developments Private Limited v. State of West Bengal [2024]
       8 SCR 615 : (2024) 10 SCC 715; M.B. Patel & Co. v. ONGC [2008]
       8 SCR 35 : (2008) 8 SCC 251; Union of India v. Krafters Engg.
       & Leasing (P) Ltd. [2011] 8 SCR 196 : (2011) 7 SCC 279; Board
       of Trustees For The Port of Calcutta v. Engineers-De-Space-Age
       [1995] Supp. 6 SCR 327 : (1996) 1 SCC 516; Sayeed Ahmed
       & Co. v. State of U.P. [2009] 10 SCR 841 : (2009) 12 SCC 26;
       Sree Kamatchi Amman Constructions v. Railways [2010] 10 SCR
       487 : (2010) 8 SCC 767; Union of India v. Bright Power Projects
       (India) (P) Ltd. [2015] 6 SCR 488 : (2015) 9 SCC 695; Chittaranjan
       Maity v. Union of India [2017] 11 SCR 722 : (2017) 9 SCC 611;
       Garg Builders v. BHEL (2022) 11 SCC 697; Madnani Construction
       Corpn. (P) Ltd. v. Union of India [2009] 16 SCR 216 : (2010) 1
       SCC 549; Tehri Hydro Development Corpn. Ltd. v. Jai Prakash
       Associates Ltd. [2012] 8 SCR 813 : (2012) 12 SCC 10 – referred to.

                                  List of Acts
       Arbitration Act, 1940; Arbitration and Conciliation Act, 1996.
[2025] 4 S.C.R.                                                            531

               M/s Ferro Concrete Construction (India) Pvt. Ltd. v.
                            The State of Rajasthan

                                  List of Keywords
      Grant of interest under Arbitration Act, 1940; Contractual clauses;
      Payment of interest; Pendente lite interest on arbitral sum;
      Phraseology of the agreement; Clauses conferring powers relating
      to arbitration; Power to award interest; Express contractual bar on
      payment of pendente lite interest.

                                 Case Arising From
      CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4723 of 2025
      From the Judgment and Order dated 06.01.2023 of the High Court
      of Judicature for Rajasthan at Jaipur in SBCMA No. 3175 of 2006

                               Appearances for Parties
      Advs. for the Appellant:
      Vinayak Mehrotra, Ms. Sonali Jain, Ms. Nandini.
      Advs. for the Respondent:
      Ms. Sansriti Pathak, AAG, Aman Prasad, Milind Kumar.

                      Judgment / Order of the Supreme Court

                                     Judgment

      Pamidighantam Sri Narasimha, J.

1.    Leave granted.
2.    It is just as necessary to follow a precedent as it is to make a
      precedent.
3.    The short issue arising for consideration in this appeal is whether the
      contractual clause that bars the appellant/contractor from claiming any
      interest on any payment, arrears or balance due to it amounts to an
      express bar on the arbitrator’s power to grant pendente lite interest
      as per the law under the Arbitration Act, 19401. While the arbitrator
      granted 15% pendente lite interest, the same was set aside by the
      District Judge while deciding objections against the award, and upheld
      by the High Court by order dated 06.01.2023, which is impugned


1    Hereinafter “1940 Act”.
532                                                            [2025] 4 S.C.R.

                        Digital Supreme Court Reports


       herein. By relying on settled case-law on the grant of interest under
       the 1940 Act and the interpretation of contractual clauses barring
       payment of interest, we have allowed the present appeal and have
       directed payment of pendente lite interest on the arbitral sum.
4.     The relevant facts are that the appellant was awarded a works
       contract by the respondent, and they entered into an agreement dated
       06.02.1988 that contains the following clause barring the appellant
       from claiming interest on any payment or arrears or balance due to
       him at any time:
            “22. Payments :-
            (i)    Payments will be made to the contractor within one
                   month of the issuing of the corresponding bills. The
                   contractor shall comply with the procedure that may
                   be prescribed for all operations from the recording
                   of progress measurements upto payment of bills.
            (ii)   All materials and work for which payment is made in
                   part or full shall become the sole property of the Govt,
                   but this provision shall not relieve the contractor of
                   his responsibility for the care and protection of the
                   materials and works at his own cost nor his liability
                   to make good the damage if any unless and until the
                   whole work has been deemed to have been completed
                   and handed over to the Government.
            The contractor shall not be entitled to claim any interest
            upon any payment, any arrears or upon any balance,
            which may be found due to him at any time.”
                                                     (emphasis supplied)

5.     When disputes arose under the contract, the appellant invoked
       arbitration and filed its claim, resulting in arbitral award dated
       07.03.1995 for a sum of Rs. 1,78,17,146 in its favour. The arbitrator
       also directed payment of 15% interest p.a. on all dues payable from
       18.12.1991 (when the arbitrator entered reference) till payment or
       the date of decree, whichever is earlier. The respondent filed an
       application to set aside the award, which was decided by the District
       Judge’s order dated 16.08.2005 that only set aside the interest
       awarded by the arbitrator, and instead granted 9% simple interest
[2025] 4 S.C.R.                                                          533

             M/s Ferro Concrete Construction (India) Pvt. Ltd. v.
                          The State of Rajasthan

      on the principal sum from that date till the date of payment. The
      other objections against the award were rejected and the rest of the
      award was upheld. It was held that the arbitrator did not consider
      that Clause 22 of the contract is widely worded and prohibits the
      appellant from claiming interest at any time. Both parties preferred
      appeals against this order, which were dismissed by the High Court
      by order dated 06.01.2023, impugned herein.
6.    While issuing notice on 24.04.2023 in the present special leave petition
      converted to a civil appeal, this Court passed the following order:
             “1. Learned counsel appearing on behalf of the petitioner
             relies upon paragraph 24 of the decision of this Court in
             Reliance Cellulose Products Ltd Vs Oil and Natural
             Gas Corporation Limited.2 He urges that Clause 22 of
             the agreement does not specifically exclude either the
             power of the arbitrator to grant pendente lite interest or
             rule out the claimant from claiming interest pendente lite
             in the course of arbitration.
             2. Issue notice returnable in four weeks.”
7.    We have heard Mr. Vinayak Mehrotra, learned counsel for the
      appellant, and Ms. Sansriti Pathak, learned Additional Advocate
      General for the respondent State on the issue of whether Clause
      22 amounts to a bar on the arbitrator from awarding pendente lite
      interest under the 1940 Act.
      7.1 Mr. Mehrotra submits that the present issue is covered by this
          Court’s decision in Reliance Cellulose (supra). He submits that
          the contractual clause in the present case does not clearly
          and expressly bar the arbitrator from awarding interest on the
          arbitral sum. He has also referred to this Court’s decision in
          Pam Developments Private Limited v. State of West Bengal3
          in support of his argument.
      7.2 On the other hand, Ms. Pathak has made detailed submissions
          regarding the interpretation of the contractual clause, which are
          as follows: First, the interpretation of an ouster clause is the



2    (2018) 9 SCC 266.
3    (2024) 10 SCC 715, para 23.
534                                                                                [2025] 4 S.C.R.

                               Digital Supreme Court Reports


              same under the 1940 Act and the Arbitration and Conciliation
              Act, 19964. Under both statutes, the arbitrator can award interest
              unless the agreement provides otherwise. The key difference
              between the statutes is that the 1996 Act contains an express
              statutory provision for the grant of interest in Section 31(7), but
              this is based on the principle in G.C. Roy 5 that recognised the
              arbitrator’s power to award interest under the 1940 Act. Further,
              that Section 31(7)(a) of the 1996 Act does not differentiate pre-
              reference and pendente lite interest. However, these differences
              do not have any bearing on the interpretation of contractual
              clauses. Second, by referring to various decisions of this Court,
              she submits that narrower contractual clauses have been
              treated as ouster clauses that bar the arbitrator from awarding
              pendente-lite interest.6 Third, she submits that paragraph 24 of
              Reliance Cellulose (supra), which is relied on by the appellant,
              is based on this Court’s decision in Board of Trustees For The
              Port of Calcutta v. Engineers-De-Space-Age,7 which has been
              doubted in several cases. A 3-judge bench of this Court in Union
              of India v. Ambica Construction 8 (First Ambica case) held that
              the observations in Engineers-De-Space-Age (supra) cannot
              be considered as general observations and each contractual
              clause barring payment of interest must be interpreted by the
              words used therein. Fourth, in the facts of the present case, the
              respondent has already paid a sum of Rs. 4.65 crores to the
              appellant, of which Rs. 2.83 crores is the interest component.
              Hence, a further award of pendente lite interest is not warranted
              in the present case.
8.     The position of law on the grant of interest under the 1940 Act and
       the 1996 Act is well-settled. The constitution bench decisions of this
       Court in GC Roy (supra) and NC Budharaj 9 recognised the arbitrator’s
       power to grant pre-reference, pendente lite, and post-award interest
       on an arbitral award made under the 1940 Act unless there is a


4    Hereinafter “1996 Act”.
5    Secretary, Irrigation Department, Government of Orissa v. G.C. Roy, (1992) 1 SCC 508.
6    Relied on M.B. Patel & Co. v. ONGC, (2008) 8 SCC 251; Union of India v. Krafters Engg. & Leasing (P)
     Ltd., (2011) 7 SCC 279 under the 1940 Act.
7    (1996) 1 SCC 516.
8    (2016) 6 SCC 36.
9    Executive Engineer, Dhenkanal Minor Irrigation Division v. N.C. Budharaj, (2001) 2 SCC 721.
[2025] 4 S.C.R.                                                                                   535

              M/s Ferro Concrete Construction (India) Pvt. Ltd. v.
                           The State of Rajasthan

      contractual bar.10 The question that falls for our consideration is
      whether the contractual bar in the present case prohibits the arbitrator
      from granting pendente lite interest, which necessarily entails an
      interpretation of the clause.
9.    This Court has, on multiple occasions, noted that a contractual clause
      which bars the payment of interest is interpreted differently under
      the 1940 Act and the 1996 Act. In fact, while deciding cases under
      the 1996 Act, this Court has been slow to rely on the principles laid
      down under the 1940 Act, considering the legislative incorporation of
      the arbitrator’s power to grant interest through Section 31(7) of the
      1996 Act.11 The difference in the interpretative approach has been
      expounded by this Court in Reliance Cellulose (supra) as follows:
              “24. A conspectus of the decisions that have been
              referred to above would show that under the 1940 Act,
              an arbitrator has power to grant pre-reference interest
              under the Interest Act, 1978 as well as pendente lite and
              future interest. However, he is constricted only by the
              fact that an agreement between the parties may contain
              an express bar to the award of pre-reference and/or
              pendente lite interest. Since interest is compensatory in
              nature and is parasitic upon a principal sum not having
              been paid in time, this Court has frowned upon clauses
              that bar the payment of interest. It has therefore evolved
              the test of strict construction of such clauses, and has
              gone on to state that unless there is a clear and express
              bar to the payment of interest that can be awarded by
              an arbitrator, clauses which do not refer to claims before
              the arbitrators or disputes between parties and clearly
              bar payment of interest, cannot stand in the way of an
              arbitrator awarding pre-reference or pendente lite interest.
              Thus, when one contrasts a clause such as the clause in
              Second Ambica Construction case with the clause in Tehri
              Hydro Development Corpn. Ltd., it becomes clear that



10   GC Roy (supra), para 45.
11   Sayeed Ahmed & Co. v. State of U.P., (2009) 12 SCC 26, para 24; Sree Kamatchi Amman Constructions v.
     Railways, (2010) 8 SCC 767, paras 18-19; Union of India v. Bright Power Projects (India) (P) Ltd.,
     (2015) 9 SCC 695, paras 17-19; Chittaranjan Maity v. Union of India, (2017) 9 SCC 611, para 16; Garg
     Builders v. BHEL, (2022) 11 SCC 697, para 17.
536                                                       [2025] 4 S.C.R.

                     Digital Supreme Court Reports


          unless a contractor agrees that no claim for interest will
          either be entertained or payable by the other party owing
          to dispute, difference, or misunderstandings between the
          parties or in respect of delay on the part of the engineer
          or in any other respect whatsoever, leading the Court to
          find an express bar against payment of interest, a clause
          which merely states that no interest will be payable upon
          amounts payable to the contractor under the contract
          would not be sufficient to bar an arbitrator from awarding
          pendente lite interest under the 1940 Act. As has been
          held in First Ambica Construction case, the grant of
          pendente lite interest depends upon the phraseology used
          in the agreement, clauses conferring power relating to
          arbitration, the nature of claim and dispute referred to the
          arbitrator, and on what items the power to award interest
          has been taken away and for which period. We hasten
          to add that the position as has been explained in some
          of the judgments above under Section 31(7) of the 1996
          Act, is wholly different, inasmuch as Section 31(7) of the
          1996 Act sanctifies agreements between the parties and
          states that the moment the agreement says otherwise, no
          interest becomes payable right from the date of the cause
          of action until the award is delivered.”
                                                (emphasis supplied)

10. The difference in the interpretative approach can be stated as follows.
    Under the 1940 Act, a stricter approach is followed that requires a
    clear and express clause against the payment of interest in case of
    difference, dispute, or misunderstanding, in case of delay of payment,
    or any other case whatsoever, to constitute a bar on the arbitrator
    from granting interest. A clause that only provides that interest shall
    not be granted on amounts payable under the contract would not be
    sufficient. On the other hand, under the 1996 Act wherein Section
    31(7)(a) sanctifies party autonomy, interest is not payable the moment
    the contract provides otherwise. This distinction has been reiterated
    by us in a recent decision in Pam Developments (supra), which
    summarised the position of law as follows:
          “23. The power of the arbitrator to grant pre-reference
          interest, pendente lite interest, and post-award interest
[2025] 4 S.C.R.                                                            537

           M/s Ferro Concrete Construction (India) Pvt. Ltd. v.
                        The State of Rajasthan

           under Section 31(7) of the Act is fairly well-settled. The
           judicial determinations also highlight the difference in
           the position of law under the Arbitration Act, 1940. The
           following propositions can be summarised from a survey
           of these cases:
           23.1. Under the Arbitration Act, 1940, there was no specific
           provision that empowered an arbitrator to grant interest.
           However, through judicial pronouncements, this Court
           has affirmed the power of the arbitrator to grant pre-
           reference, pendente lite, and post-award interest on the
           rationale that a person who has been deprived of the use
           of money to which he is legitimately entitled has a right
           to be compensated for the same. When the agreement
           does not prohibit the grant of interest and a party claims
           interest, it is presumed that interest is an implied term of
           the agreement, and therefore, the arbitrator has the power
           to decide the same.
           23.2. Under the 1940 Act, this Court has adopted a strict
           construction of contractual clauses that prohibit the grant
           of interest and has held that the arbitrator has the power
           to award interest unless there is an express, specific
           provision that excludes the jurisdiction of the arbitrator.
           23.3. Under the 1996 Act, the power of the arbitrator to grant
           interest is governed by the statutory provision in Section
           31(7). This provision has two parts. Under clause (a), the
           arbitrator can award interest for the period between the
           date of cause of action to the date of the award, unless
           otherwise agreed by the parties. Clause (b) provides that
           unless the award directs otherwise, the sum directed to
           be paid by an arbitral award shall carry interest @ 2%
           higher than the current rate of interest, from the date of
           the award to the date of payment.
           23.4. The wording of Section 31(7)(a) marks a departure
           from the Arbitration Act, 1940 in two ways : first, it does
           not make an explicit distinction between pre-reference and
           pendente lite interest as both of them are provided for under
           this sub-section; second, it sanctifies party autonomy and
           restricts the power to grant pre-reference and pendente
538                                                                             [2025] 4 S.C.R.

                              Digital Supreme Court Reports


              lite interest the moment the agreement bars payment of
              interest, even if it is not a specific bar against the arbitrator.
              23.5. The power of the arbitrator to award pre-reference and
              pendente lite interest is not restricted when the agreement
              is silent on whether interest can be awarded or does not
              contain a specific term that prohibits the same.
              23.6. While pendente lite interest is a matter of procedural
              law, pre-reference interest is governed by substantive law.
              Therefore, the grant of pre-reference interest cannot be
              sourced solely in Section 31(7)(a) (which is a procedural
              law), but must be based on an agreement between the
              parties (express or implied), statutory provision (such as
              Section 3 of the Interest Act, 1978), or proof of mercantile
              usage.”
                                                                    (emphasis supplied)

11. At this stage, we find it necessary to deal with Ms. Pathak’s submission
    that Reliance Cellulose (supra) relies on Engineers-De-Space-Age
    (supra), which was later read down and clarified by a 3-judge bench
    in the First Ambica case. Upon reading Reliance Cellulose (supra),
    it is clear that this Court undertook a comprehensive survey of the
    case-law on the issue of payment of interest on arbitral awards,
    including a detailed discussion of the First Ambica case,12 before
    formulating the legal position extracted hereinabove.
12. In the First Ambica case (supra), the issue before this Court was
    whether Engineers-De-Space-Age (supra) and Madnani Construction13
    were correctly decided.14 After taking note of the interpretation of
    various contractual clauses barring payment of interest in this Court’s
    decisions under the 1940 Act and the 1996 Act, it summarised their
    rulings as follows:
              “28. It is apparent from various decisions referred to above
              that in G.C. Roy the Constitution Bench of this Court has
              laid down that where the agreement expressly provides


12   Reliance Cellulose (supra), paras 19-21.
13   Madnani Construction Corpn. (P) Ltd. v. Union of India, (2010) 1 SCC 549.
14   First Ambica case (supra), para 1.
[2025] 4 S.C.R.                                                                539

           M/s Ferro Concrete Construction (India) Pvt. Ltd. v.
                        The State of Rajasthan

           that no interest pendente lite shall be payable on amount
           due, the arbitrator has no power to award interest. In N.C.
           Budharaj a Constitution Bench has observed that in case
           there is nothing in the arbitration agreement to exclude
           jurisdiction of the arbitrator to entertaining claim for interest,
           the jurisdiction of the arbitrator to consider and award
           interest in respect to all periods is subject to Section 29 of
           the Act. In Hindustan Construction Co. Ltd. this Court has
           followed the decision in G.C. Roy and laid down that on
           the basis of principles of Section 34 the arbitrator would
           have the power to award pendente lite interest also. In
           B.N. Agarwalla, this Court has again followed G.C. Roy and
           Hindustan Construction Co. Ltd. with respect to the power
           of the arbitrator to award pendente lite interest and it was
           held that the arbitrator has the power to award interest. In
           Harish Chandra this Court interpreted Clause 1.9 which
           provided that no claim for interest or damages will be
           entertained by the Government in respect to any monies
           or balances which may be lying with the Government. It
           was held that there was no provision which could be culled
           out against the contractor not to claim interest by way of
           damages before the arbitrator on the relevant items placed
           for adjudication. In Ferro Concrete Construction (P) Ltd.
           this Court considered Clause 4 containing a stipulation
           that no interest was payable on amount withheld under
           the agreement. It was held that Clause 4, which dealt
           with rates, material and workmanship, did not bar award
           of interest by the arbitrator on claims of the contractor
           made in the said case. In Sayeed Ahmed this Court has
           emphasised that award of interest would depend upon
           nature of the clause in the agreement. In Bright Power
           Projects (India) (P) Ltd. this Court has considered the
           expression “unless otherwise agreed by parties” employed
           in Section 31(7)(a) of the 1996 Act and laid down that in
           case contract bars claim of interest the contractor could
           not have claimed interest. The provision of Section 31(7)
           (a) of the 1996 Act is binding upon the arbitrator. In Sree
           Kamatchi Amman Constructions similar view has been
           taken.”
540                                                             [2025] 4 S.C.R.

                             Digital Supreme Court Reports


       The Court then took note of the doubts expressed regarding the
       correctness of Engineers-De-Space-Age (supra) and Madnani
       Construction (supra) in Sayeed Ahmed (supra) and Tehri Hydro
       Development Corpn. Ltd. v. Jai Prakash Associates Ltd.15, on the
       ground that they allow the arbitrator to grant interest by ignoring an
       express bar in the contract.16 In order to resolve the discordant note,
       this Court in the First Ambica case (supra) held as follows:
              “32. In para 4 in Engineers-De-Space-Age this Court has
              observed that bar under the contract will not be applicable
              to the arbitrator cannot be said to be observation of general
              application. In our opinion, it would depend upon the
              stipulation in the contract in each case whether the power
              of the arbitrator to grant pendente lite interest is expressly
              taken away. If answer is “yes” then the arbitrator would
              have no power to award pendente lite interest.
              33. The decision in Madnani Construction Corpn. has
              followed the decision in Engineers-De-Space-Age. The
              same is also required to be diluted to the extent that
              express stipulation under contract may debar the arbitrator
              from awarding interest pendente lite. Grant of pendente
              lite interest may depend upon several factors such as
              phraseology used in the agreement, clauses conferring
              power relating to arbitration, nature of claim and dispute
              referred to arbitrator and on what items power to award
              interest has been taken away and for which period.
              34. Thus, our answer to the reference is that if the contract
              expressly bars the award of interest pendente lite, the same
              cannot be awarded by the arbitrator. We also make it clear
              that the bar to award interest on delayed payment by itself
              will not be readily inferred as express bar to award interest
              pendente lite by the Arbitral Tribunal, as ouster of power
              of the arbitrator has to be considered on various relevant
              aspects referred to in the decisions of this Court, it would
              be for the Division Bench to consider the case on merits.”
                                                     (emphasis supplied)


15   (2012) 12 SCC 10.
16   First Ambica case (supra), paras 29-31.
[2025] 4 S.C.R.                                                         541

           M/s Ferro Concrete Construction (India) Pvt. Ltd. v.
                        The State of Rajasthan

13. From the above extracted paragraphs, the decision of the 3-judge
    bench in the First Ambica case (supra) can be stated as follows. The
    arbitrator’s power to grant interest would depend on the contractual
    clause in each case, and whether it expressly takes away the
    arbitrator’s power to grant pendente lite interest. This would have to
    be determined based on the phraseology of the agreement, clauses
    conferring powers relating to arbitration, the nature of claim and
    dispute referred to the arbitrator, and on what items the power to
    award interest is contractually barred and for which period. Further,
    a bar on award of interest for delayed payment would not be readily
    inferred as an express bar to the award of pendente lite interest by
    the arbitrator.
14. We find that the position of law laid down in paragraph 24 of Reliance
    Cellulose (supra) is in line with the position of law laid down in
    the First Ambica case. Both decisions emphasise the need for an
    express contractual bar on the payment of pendente lite interest
    to create a bar on the arbitrator from awarding interest. They also
    emphasise that a bar on the arbitrator’s power would depend on the
    phraseology of the contractual clause in that case. In this light, Ms.
    Pathak’s submission regarding the correctness of Reliance Cellulose
    (supra) ought to be rejected. We do not find any reason to unsettle
    the position of law, when it has been clearly enunciated and followed.
    It is not sufficient to lay down a precedent, but it is equally important
    to follow and apply them as well.
15. Now that we have stated the law applicable to this case, we will
    consider the terms of Clause 22 of the contract to determine whether
    it bars the arbitrator from awarding pendente lite interest on the
    arbitral award. Clause 22 prohibits the appellant (contractor) from
    claiming interest on any payment, arrears or balance, which may be
    found due to him at any time. Applying the above-stated law, we find
    that this clause does not expressly bar the award of pendente lite
    interest in the event of disputes, differences, or misunderstandings
    between the parties, or on delayed payment, or in any other respect
    whatsoever. Under the 1940 Act, this Court has not readily inferred
    a bar on the arbitrator from clauses that merely bar the contractor
    from claiming interest, and the same will apply to this case as well.
16. In view of the above discussion, we allow the present appeal and
    set aside the impugned judgment of the High Court in SBCMA No.
542                                                                                  [2025] 4 S.C.R.

                              Digital Supreme Court Reports


       3175/2006 dated 06.01.2023. Considering that the arbitrator entered
       reference in 1991 and the award was made in 1995, along with the
       passage of time in litigation as well as the amounts already paid
       by the respondent including post-award interest @ 9%, we deem
       it appropriate to grant 9% pendente lite interest, instead of 15% as
       granted by the arbitral tribunal, from 18.12.1991 till 07.03.1995 (date
       of the arbitral award) within a period of 60 days.17
17. No order as to costs.
18. Pending applications, if any, stand disposed of.

       Result of the case: Appeal allowed.



       †
           Headnotes prepared by: Ankit Gyan




17   As these proceedings arise under the 1940 Act, the scope and jurisdiction of the Court to modify or vary
     the award is larger than that of the court exercising jurisdiction under Section 34 of the 1996 Act.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Grant of interest under Arbitration Act, 1940"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

M/S FERRO CONCRETE CONSTRUCTION (INDIA) PVT. LTD. versus THE STATE OF RAJASTHAN — 2025 INSC 429 - Legal Desk AI