Created byFuzzy Cloud

Supreme Court of India

KALPATARU POWER TRANSMISSION LTD. (NOW KNOWN AS KALPATARU PROJECTS INTERNATIONAL LTD.)versusVINOD AND ORS. ETC.

Citation
2025 INSC 1004
Decided
19 August 2025
Disposal
Disposed off

Holding

The High Court’s uniform compensation assessment is unsustainable; compensation must be determined on a district‑specific basis, and the statutory scheme lacks a proper appellate remedy, warranting remand for fresh consideration.

Summary

The case concerned compensation disputes arising from the erection of transmission towers and power lines under a 400 kV project that traversed four districts in Haryana. Landowners claimed that the compensation awarded by the District Judges and upheld by the High Court was inadequate, while the contractor sought to limit the compensation. The High Court had applied a uniform compensation rate based on the collector's valuation for land in Sonepat to all lands, including those in Jhajjar, without considering district‑specific differences. The Supreme Court held that this methodology was legally untenable, that the High Court erred by treating the writ petitions as original trials, and that the statutory scheme under the Telegraph Act, 1885 provides no appeal against the District Judge’s order, creating a procedural gap. Consequently, the Court set aside the High Court’s order, remitted the matters for fresh consideration with appropriate methodology, and disposed of the civil appeals. The judgment also directed the High Court and the Ministry of Law and Justice to examine the need for a statutory appeal mechanism and uniform nomenclature for such proceedings.

Issues considered

  • The adequacy and methodology of compensation assessment for land used as tower base area and right‑of‑way under the Telegraph Act, 1885.
  • Whether a uniform compensation rate can be applied to lands situated in different districts with varying characteristics.
  • The existence of a statutory appeal remedy against orders of the District Judge under Sections 16(3) and 16(4) of the Telegraph Act, 1885.
  • The applicability of Ministry of Power guidelines issued after the relevant transactions.
  • The need for uniform nomenclature and procedural consistency for proceedings under the 1885 Act and similar statutes.

Legislation cited

Headnote

Issue for Consideration Issue arose as regards the landowners seeking further enhancement of compensation on account of damages suffered by erection of transmission lines and towers, whereas the Contractor challenging the amount and whether there should be some remedy of appeal against order passed by the District Judge. Headnotes† Telegraph Act, 1885 – s.16(3), (4) – Disputes as to compensation – Assessment of compensation for the Tower Base Area (land beneath four legs of the tower) and the

Subjects

LandownersEnhancement of compensationDamages suffered by erection of transmission lines and towersRemedy of appealDistrict JudgeTower Base AreaRight of Way corridorCollector rateSonepat districtJhajjar districtUniform compensation methodologyStatutory appeal gapUniform nomenclature

Judgment

               [2025] 8 S.C.R. 1053 : 2025 INSC 1004

            Kalpataru Power Transmission Ltd.
     (Now Known as Kalpataru Projects International Ltd.)
                            v.
                   Vinod and Ors. Etc.
                (Civil Appeal No(s). 10882-10888 of 2025)
                               19 August 2025
             [M.M. Sundresh and Rajesh Bindal,* JJ.]


                           Issue for Consideration
       Issue arose as regards the landowners seeking further
       enhancement of compensation on account of damages suffered by
       erection of transmission lines and towers, whereas the Contractor
       challenging the amount of compensation awarded; and whether
       there should be some remedy of appeal against order passed by
       the District Judge.

                                 Headnotes†
       Telegraph Act, 1885 – s.16(3), (4) – Disputes as to compensation –
       Assessment of compensation for the Tower Base Area (land
       beneath four legs of the tower) and the Right of Way-ROW
       Corridor – Utilization of land owned by the landowners for
       erection of tower or drawing power lines in four districts,
       however ownership of the land not transferred – Damages
       suffered by the landowners – Petition u/s.16(3) before the
       District Judge by the landowners – Award of compensation
       by District Judge of Sonepat and Jhajjar respectively – High
       Court decided bunch of petitions, and awarded uniform
       compensation to the landowners @ 85% of the collector rate
       beneath the tower area, determined at ₹1.50 crores per acre,
       and for diminishing the value of land across the width of
       ROW, 15% of the value of land, on account of imposition of
       restrictions on utilization thereof – High Court assessed the
       compensation in all cases on basis of the facts pertaining
       to land in district Sonepat only, without touching the facts
       pertaining to district Jhajjar – Sustainability:
       Held: Order passed by the High Court cannot be legally sustained –
       High Court failed to appreciate the fundamental fact that land

* Author
1054                                                          [2025] 8 S.C.R.

                         Supreme Court Reports


    pertaining to different villages falling in different districts, which
    may be the subject matter of consideration for assessment of
    compensation, would have been assessed differently by the
    Collector based on their respective locations and characteristics –
    Facts only pertaining to district Sonepat have been discussed –
    Applying a uniform rate for the entire transmission corridor would
    not be a proper methodology for assessing fair compensation to
    which the landowners are entitled to – Thus, the manner adopted
    by the High Court for assessment of compensation not approved –
    Some parties invoked Art. 226, whereas others filed petitions
    invoking Art. 227 challenging the judgments of the trial court,
    which were delivered on appreciation of evidence – This is solely
    because no proper appellate remedy has been provided against
    the order passed by the District Judge – There are other gaps as
    well in the statutory scheme-limited determination of compensation,
    no timelines regarding payment of compensation to the affected
    parties after the right u/s.10(d) is exercised by the competent
    authority – This being an Act of Parliament, its application has
    to be uniform throughout the country – In the absence of defined
    parameters, it will depend on different courts, how they interpret
    the provisions – Unless statutory remedy of appeal is provided
    where all issues of law and facts can be re-examined, any other
    remedy may be illusionary – Remedies availed by different parties
    were different – Reappriciation of evidence in those proceedings
    may be an issue – Anomalies with reference to various timelines
    as well, the matter to be examined – Issues to be examined by
    the Law Commission of India and the Ministry of Law and Justice,
    Government of India, to determine whether a statutory remedy
    of appeal should be provided against judgments/orders passed
    u/s.16(3) and 16(4), the Petroleum Act or any other similar statute –
    In district Sonepat, application for dispute related to compensation
    was registered and numbered as a Civil Suit where a judgment
    and decree was passed, whereas in district Jhajjar, the same was
    registered as a Civil Miscellaneous Application and only judgment
    was passed – Need to bring uniformity in the nomenclature to be
    assigned to these kind of proceedings, which may come to the
    court under the 1885 Act and also the proceedings under the
    Petroleum and Minerals Pipelines (Acquisition of Right of User in
    Land) Act, 1962 – Order passed by the High Court set aside –
    Matters remitted back to the High Court for fresh consideration –
    Electricity Act, 2003.
[2025] 8 S.C.R.                                                              1055

         Kalpataru Power Transmission Ltd. (Now Known as
      Kalpataru Projects International Ltd.) v. Vinod and Ors. Etc.

                              Case Law Cited
     Janardhan Reddy and Others v. State, 1950 INSC 37 : [1950] 1
     SCR 940 : AIR 1951 SC 124; The Kerala State Electricity Board,
     Trivandrum v. T.P. Kunhaliumma, 1976 INSC 272 : [1977] 1 SCR
     996 : AIR 1977 SC 282; Suhas H. Pophale v. Oriental Insurance
     Company Limited and Its Estate Officer, 2014 INSC 92 : [2014] 2
     SCR 480 : AIR 2014 SC 1509; State of Haryana and Another v.
     Pala Ram and Others, 2012 SCC Online P&H 24551; Kerala SEB v.
     Livisha, 2007 INSC 638 : [2007] 7 SCR 356 : (2007) 6 SCC 792;
     M.L. Jaggi v. Mahanagar Telephones Nigam Ltd. and Ors., 1996
     INSC 6 : [1996] 1 SCR 25 : (1996) 3 SCC 119 – referred to.

                                 List of Acts
     Telegraph Act, 1885; Electricity Act, 2003; Land Acquisition
     Act, 1894; Right to Fair Compensation and Transparency in
     Land Acquisition, Rehabilitation and Resettlement Act, 2013;
     Requisitioning and Acquisition of Immovable Property Act, 1952;
     Arbitration and Conciliation Act, 1996; National Highways Act,
     1956; Railways Act, 1989; Coal Bearing Areas (Acquisition and
     Development) Act, 1957; Petroleum and Minerals Pipelines
     (Acquisition of Right of User in Land) Act, 1962.

                              List of Keywords
     Landowners; Enhancement of compensation; Damages suffered
     by erection of transmission lines and towers; Remedy of appeal;
     District Judge; Tower Base Area (land beneath four legs of the
     tower) and the Right of Way corridor; Collector rate beneath the
     tower area; District of Sonepat; District of Jhajjar; Land pertaining
     to different villages falling in different districts; Uniform rate for
     the entire transmission corridor; Methodology for assessing fair
     compensation; Anomalies with reference to various timelines; Law
     Commission of India; Ministry of Law and Justice, Government of
     India; Uniformity in the nomenclature.

                             Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No(s).
     10882-10888 of 2025
     From the Judgment and Order dated 24.02.2023 of the High
     Court of Punjab & Haryana at Chandigarh in CWP No(s). 21878,
1056                                                          [2025] 8 S.C.R.

                                   Supreme Court Reports


       26406, 9495, and 28540 of 2017 in CR No(s). 3502, 3503 and
       3830 of 2017
       With
       Civil Appeal No(s).10889-10890 and 10891-10892 of 2025

                                   Appearances for Parties
       Advs. for the Appellant:
       Nidhesh Gupta, Sr. Adv., Arvind Gupta, Mahesh Agarwal, Rishi
       Agrawala, Manu Krishnan, Sunil Mittal, Ms. Madhavi Agarwal, Amit
       Sagar, Amit Kumar, Jimut Mohapatra, E. C. Agrawala.
       Advs. for the Respondents:
       Lokesh Sinhal, Sr. A.A.G., Mahabir Singh, Sr. Adv, Rakesh Dahiya,
       Karan Singh, Akshat Jain, Praveen Kumar, Rn Mahlawat, Rajeev
       Sharma, Arvind Gupta, Samar Vijay Singh, Nikunj Gupta, Ms.
       Akanksha, Ms. Sabarni Som, Fateh Singh, Aman Dev Sharma,
       Ms. Ishika Gupta, Sarthak Arya, Vaibhav Saini.

                       Judgment / Order of the Supreme Court

                                             Judgment

       Rajesh Bindal, J.

                                      Table of Contents*

          S.                           Particulars           Paras       Page
          No.

           1.      Factual background                         2–7        2–7

                   Civil Appeal No(s). 10882-10888 of 2025   5 – 5.1     4–5
                   [@SLP (C) No(s). 14936-14942/2023]

                   Civil Appeal No(s).10891-10892 of 2025    6 – 6.1        6
                   [@SLP (C) No(s).18246-18247 of 2025]

                   Civil Appeal No(s). 10889-10890 of 2025   7 – 7.1     6–7
                   [@SLP (C) No(s). 14926-14927/2023]

           2.      Regarding ‘Impugned Order’                        8      8


* Ed. Note: Pagination as per the original Judgment.
[2025] 8 S.C.R.                                                                     1057

           Kalpataru Power Transmission Ltd. (Now Known as
        Kalpataru Projects International Ltd.) v. Vinod and Ors. Etc.


          3.      Arguments of the contractor                        9 – 9.3      8 – 10
          4.      Arguments of the landowners                       9.4 – 10           11
          5.      Discussion                                         11 – 20     11 – 20
          6.      Re-right of appeal                                 21 – 35     21 – 32
          7.      Need for uniformity in nomenclature of                   36          32
                  cases
          8.      Relief on merits                                 37 – 37.1     32 – 33
          9.      Directions                                         38 – 39           33




1.    Leave granted.

      FACTUAL BACKGROUND
2.    The present judgment shall dispose of a batch of appeals arising out
      of a common judgment dated 24.02.2023 passed by the High Court1
      whereby a bunch of nine matters2 were decided. The landowners
      before this Court are seeking further enhancement of compensation
      on account of damages suffered by erection of transmission lines
      and towers, whereas the Contractor is before this Court, challenging
      the amount of compensation awarded.
3.    Briefly, basic facts of the case as are evident from the record are
      that Haryana Vidyut Prasaran Nigam Limited (hereinafter, “HVPNL”),
      a public company owned by the State Government initiated a power
      transmission project, titled “400 KV Jhajjar Power Transmission
      System-PPP-1,” by issuing a Request for Quotation (RFQ) on
      13.01.2009. Jhajjar KT Transco Private Limited (hereinafter,
      “JKTPL”) was selected as the lowest bidder for the transmission
      project and was awarded the project under an Agreement dated
      28.05.2010. Subsequently, JKTPL entered into a sub-contract for
      erection, commissioning & other services with Kalpataru Power


1    High Court of Punjab and Haryana at Chandigarh.
2    CWP No. 21878 of 2017; CWP No. 26406 of 2017; CR-3502-2017; CR-3503-2017; CR-1280-2020;
     CR-2873-2021; CWP No. 9495 of 2017; CR-3830-2017; CWP No. 28570 of 2017.
1058                                                                              [2025] 8 S.C.R.

                                    Supreme Court Reports


       Transmission Ltd. on 29.10.2010, the present appellant in some
       of the appeals.
       3.1 As is evident from the aforesaid contract executed between the
           JKTPL and Kalpataru Power Transmission Ltd., total length of
           transmission line is 100 km. The details thereof are as under:
               •       Jharli (Jhajjar) - Kabulpur (Rohtak) 400 KV D/C line
                       (Length: 35 km).
               •       Kabulpur (Rohtak) - Dipalpur (Sonepat) 400 KV D/C line
                       (Length: 64 km).
               •       Loop-in-Loop-out (LILO) of one circuit of Abdallapur -
                       Bawana 400 KV D/C line at Dipalpur (Sonipat)
                       (Length: 1 km).
       3.2 The transmission line has passed through 4 districts in different
           villages as is mentioned in the public notice dated 12.07.2010.3
           The districts are Bhiwani, Jhajjar, Rohtak and Sonepat. The issue
           arose regarding compensation to which the landowners may
           be entitled to for the damages suffered on account of erection
           of towers and drawing the power lines. The fact remains that
           ownership of land is not transferred.
4.     As there are certain glaring errors in the judgment of the High Court
       deciding bunch of petitions pertaining to land falling in different
       districts, to put the record straight we wish to narrate brief facts of
       all the appeals.

       Civil Appeal No(s).10882-10888 of 2025 (@SLP (C) No(s). 14936-
       14942/2023)
5.     These appeals arise out of common judgment of the High Court
       wherein challenge was made to different judgments and decrees
       passed by the Ld. Additional District Judge, Sonepat in 3 different
       applications filed by landowners under Section 16(3) of the Indian
       Telegraph Act, 1885.4 These three applications were registered as
       Civil Suits bearing CIS No. CS/5/2016, titled as “Tara Chand and
       Ors. versus Kalpa-Taru and Ors.”, CIS No. CS/6/2016 titled as “Vinod


3    Available in the record of the Trial Court in CS No. 6 of 2017 at page 267.
4    Hereinafter referred to as “the 1885 Act”.
[2025] 8 S.C.R.                                                      1059

         Kalpataru Power Transmission Ltd. (Now Known as
      Kalpataru Projects International Ltd.) v. Vinod and Ors. Etc.

     and Another versus Kalpa-Taru and Ors.” and CIS No. CS/7/2016
     titled as “Pramod Kumar etc. versus Ministry of Power etc.”. The Ld.
     Additional District Judge, Sonepat awarded compensation @ 85% of
     collector rate i.e., ₹85,00,000/- per acre along with interest @ 8%,
     for the tower base area (land beneath the four legs of the tower).
     5.1 Both the parties being aggrieved by the judgment and decree
         of the Trial Court, challenged the same before the High Court.
         Two Civil Writ Petitions were filed by the landowners under
         Article 226 of the Constitution of India (CWP-9495-2017 and
         CWP-21878-2017) seeking enhancement of compensation.
         Whereas the contractor filed three Civil Revision Petitions
         under Article 227 of the Constitution of India (CR-3502-2017,
         CR-3503-2017 and CR-3830-2017). Two Civil Writ Petitions
         (CWP-26406-2017 and CWP-28570-2017) were filed by
         HVPNL, Panipat challenging the quantum of compensation
         awarded.

     Civil Appeal No(s). 10891-10892 of 2025 (SLP (C) No.18246-
     18247 of 2025)
6.   The aforesaid appeals have been filed against the judgment of the
     High Court in CWP-21878-2017 and CWP-9495-2017 and the same
     judgment is under challenged in Civil Appeals arising out of S.L.P.(C)
     No.14936/2023 and 14940/2023 (@ S.L.P.(C) Nos.14936-14942 of
     2023) seeking further enhancement of the compensation awarded.
     The land pertains to the District Sonepat.
     6.1 Since the parties in the aforesaid appeals are common and
         are being represented, we do not consider it appropriate to
         issue formal notice in these appeals and the same are being
         disposed of along with the bunch of appeals.

     Civil Appeal No(s).10889-10890 of 2025 (@SLP (C) No. 14926-
     14927/2023)
7.   Challenge in present appeals is also to the same common judgment of
     the High Court dated 24.02.2023. Land involved forms part of district
     Jhajjar. Before the High Court, two Civil Revision Petitions bearing
     CR-1280-2020 and CR-2873-2021 were filed by the contractor and
     the landowner, respectively. The issue again pertained to assessment
     of fair compensation on account of utilization of land owned by
1060                                                       [2025] 8 S.C.R.

                        Supreme Court Reports


     the landowners for erection of tower or drawing power lines. An
     application was filed by the landowner under Section 16(3) of the
     1885 Act bearing CM No. 516 of 2013 titled “Rati Ram versus State
     of Haryana and Ors.” before the Additional District Judge, Jhajjar.
     The Trial Court initially vide order dated 07.11.2016 awarded total
     compensation of ₹30,00,000/- under various heads. The aforesaid
     order was challenged by the contractor before the High Court by filing
     CR No. 3420 of 2017. The High Court vide order dated 19.08.2019
     set aside the order of the Trial Court and remanded the case back
     for determination of compensation afresh. On remand, the Trial Court
     vide order dated 20.12.2019 assessed the total compensation at
     ₹26,12,000/- to be paid along with interest @ 18% per annum from
     April 2011 till realization. The compensation was awarded under
     various heads.
     7.1 The order passed by the Trial Court in CM No. 516 of 2013
         seems to be erroneous on the face of it. In paragraph 6 of the
         order, documentary evidence led by the landowners has been
         referred to. There are five exhibits and three documents which
         have been marked. In paragraph 18 of the order passed by the
         Trial Court, reference has been made to Exhibits P-5 to P-8 as
         sale deeds, which are not mentioned in paragraph 6 as such.
         Further Exhibit P-5 is stated to be an attested copy of the Notice
         dated 07.12.2011 of HVPNL. Further, the manner in which the
         compensation has been assessed cannot be made out. The
         High Court has failed to notice this aspect of the matter.

     REGARDING IMPUGNED ORDER
8.   Aggrieved by the aforesaid judgments/orders of the Trial Court,
     at Sonepat and Jhajjar both parties filed petitions before the High
     Court. While deciding the bunch of petitions, the High Court noticed
     the facts pertaining to land in district Sonepat only and assessed
     the compensation in all cases. The facts pertaining to district Jhajjar
     were not even touched. May be counsels did not argue. A uniform
     compensation @ 85% of the collector rate beneath the tower area,
     which was determined at ₹1.50 crores per acre was awarded to the
     landowners. Besides this, for diminishing the value of land across the
     width of Right of Way (ROW), 15% of the value of land was awarded
     as compensation. It was on account of imposition of restrictions on
     utilization thereof.
[2025] 8 S.C.R.                                                        1061

         Kalpataru Power Transmission Ltd. (Now Known as
      Kalpataru Projects International Ltd.) v. Vinod and Ors. Etc.

     ARGUMENTS OF THE CONTRACTOR
9.   Mr. Nidhesh Gupta, learned senior counsel appearing for the
     Contractor challenged the judgment of the High Court, whereby
     the damages payable to the landowners were further enhanced.
     He submitted that there was no basis for assessment of huge
     compensation on account of use of the land for erection of towers
     and drawing of the power lines. The area beneath the transmission
     lines could be utilized by the landowners, however, subject to certain
     restrictions. The ownership of the land is not transferred. Section 10 of
     the 1885 Act authorizes the authority concerned to erect towers and
     draw power lines, for which only right to use is acquired, warranting
     compensation to that extent only. The assessment of compensation
     by the Additional District Judge, Sonepat, which was further enhanced
     by the High Court, was totally on erroneous grounds and without any
     basis. Some studies related to effects of electromagnetic waves on
     the yield of crops, which may be available on internet, have been
     relied upon by the Additional District Judge, Sonepat, which in fact,
     have no basis and was not even confronted to any of the parties,
     before the same were relied upon. It was not even the case of the
     landowners as the same was not part of the evidence led.
     9.1 It was further argued that the towers were erected and the power
         lines were drawn, running into about 100 kms falling in Jhajjar,
         Sonipat and other districts. In the case in hand, the value of
         land was equivalized for the stretch of the land passing under
         the transmission lines falling in different districts, regardless of
         the fact whether the towers and lines were situated close to
         some National Highway or State Highways or running through
         agricultural areas having no road connectivity as such. Thus,
         the assessment of compensation at uniform rate for the entire
         land cannot be legally justified.
     9.2 Reliance on the guidelines issued by the Ministry of Power,
         Government of India bearing No.3/7/2015-Trans (“MOP
         Guidelines”) dated 15.10.2015 is totally misplaced in these
         cases for the reason that these were issued much after the
         transmission line in question had already been drawn and
         further these were required to be adopted by the concerned
         State/UTs. It is the case of State of Haryana, that the aforesaid
         guidelines had not been adopted, hence, invocation of those
1062                                                      [2025] 8 S.C.R.

                               Supreme Court Reports


            guidelines for the purpose of assessment of compensation was
            totally uncalled for.
     9.3 In support of the argument, reliance was placed upon judgments
         of this Court in Janardhan Reddy and others vs. State,5 The
         Kerala State Electricity Board, Trivandrum vs. T.P. Kunhaliumma6
         and Suhas H. Pophale vs. Oriental Insurance Company Limited
         and Its Estate Officer.7

     ARGUMENTS OF THE LANDOWNERS
     9.4 On the other hand, learned counsel for the landowners submitted
         that there is no error in the assessment of compensation by the
         High Court on account of damages suffered by them. Hence,
         the appeals filed by the contractor deserve to be dismissed.
         As far as the appeals filed by the landowners are concerned,
         the compensation awarded by the High Court, deserves to be
         enhanced further. For the land beneath the legs of the towers, the
         landowners are entitled to 100% compensation and not @ 85%
         of the value of the land since such area is rendered completely
         non-utilizable. Further, even for the land areas falling under the
         overhead power lines (Right of Way Corridor), lot of restrictions
         are imposed on the use of land, hence, compensation on that
         account also deserves to be enhanced.
10. Heard learned counsel for the parties and perused the relevant
    records.

     DISCUSSION
11. The facts of the cases in brief have already been referred to in
    paragraph 3 to 7 of the judgment, hence, are not being repeated.
    The land was acquired for execution of the project titled, “400 KV
    Jhajjar Power Transmission System-PPP-1”. Transmission line has
    the total length of 100 km passing through four districts, namely,
    Jhajjar, Rohtak, Bhiwani and Sonepat. We have matters before
    this Court pertaining to portions of the land utilized for the project
    which fall in districts Sonepat and Jhajjar. The first error committed


5   1950 INSC 37 : AIR 1951 SC 124
6   1976 INSC 272 : AIR 1977 SC 282.
7   2014 INSC 92 : AIR 2014 SC 1509.
[2025] 8 S.C.R.                                                         1063

         Kalpataru Power Transmission Ltd. (Now Known as
      Kalpataru Projects International Ltd.) v. Vinod and Ors. Etc.

     by the High Court, which is apparent on the face of it is that cases
     pertaining to areas falling in two different districts have been decided
     by a common judgment while referring to the material with reference
     to district Sonepat only.
12. Another error committed by the High Court in the impugned judgment
    is that the matter was dealt with as if it was a writ petition filed on the
    original side dealing with an issue raised for the first time. Rather,
    challenge before the High Court in the writ petition filed under Article
    226 and some petitions filed under Article 227 was to the judgments
    of the Trial Court, which were delivered on appreciation of evidence.
    The High Court, merely on the basis of pleadings in the High Court
    stating that the same has not been denied, has recorded findings.
13. A perusal of the impugned judgment reveals that the High Court
    solely and heavily relied on the findings of the Trial Court in the
    case of district Sonepat. The High Court while quoting paragraph
    23 of the Trial Court’s judgment in Sonepat matter, observed that
    the contractor had installed towers and high-tension wires on the
    landowners’ land but had not paid any compensation for the land
    covered under the poles of the towers or for the diminution of value
    of such land, although some compensation was paid for damage
    to the crops at the time of erection. The Trial Court had opined that
    this action of erecting towers and high-tension wires without paying
    compensation for the land covered or its diminished value was in
    violation of Articles 21, 39A, and 41 of the Constitution of India.
14. The High Court noticed the location of the land, to be part of the
    National Capital Region and is stated to be situated merely 6 acres/
    killas from the G.T. Road, in an area where land prices had already
    doubled. While holding that this was not a case of land acquisition
    stricto senso, but merely the right of way is taken, the High Court
    proceeded to examine the fair amount of compensation to which the
    landowners were entitled to. The Court relied on the guidelines issued
    by the Ministry of Power, Government of India on 15.10.2015. As far
    as the consent of the State was concerned, it was deemed to have
    been given since the State had not objected against the guidelines
    or submitted any representative comments against the same when
    these were circulated by the Ministry of Power to all the States/UTs.
15. We are not approving the manner adopted by the High Court
    for assessment of compensation. The fact remains that the
1064                                                       [2025] 8 S.C.R.

                        Supreme Court Reports


     compensation has been calculated on the basis of collector’s rate,
     which will be a matter of evidence pertaining to each area where
     the land is situated. The collector rate which has been referred to
     in the impugned judgment passed by the High Court pertained to
     only district Sonepat. Apparently, there was no evidence on record
     produced by the landowners to that extent. As is evident from the
     impugned order passed by the High Court, three sale deeds, Exhibits
     P-9, P-11 and P-12 were produced by the landowners pertaining to
     district Sonepat. These however, pertained to village Livaspur and
     Rathdhana and not to village Rai to which the land belonged to.
     The High Court considered the matter as if it was dealing with the
     same on original side as a writ petition. While observing that the
     allegations made by the landowners in the writ petitions had not been
     denied, the High Court relied upon the collector’s rate as pleaded
     by the landowners. Finally, rejecting the valuation shown in various
     sale deeds produced by the landowners, the High Court referred to
     the collector’s rate fixed for village Rai at ₹1.50 crores per acre and
     awarded compensation @ 85% thereof for the Tower Base Area and
     compensation @15% towards diminution of land value in the width
     of ROW Corridor. The aforementioned compensation was ordered to
     carry interest @ 8% per annum. Although the Collector’s award was
     not part of the formal evidence, the Court relied upon it, noting that
     the pleading to that effect had not been denied by the contractors.
16. No doubt, the landowners whose land is utilized for right of way by
    the contractor for drawing the high-tension lines and for erection
    of towers are entitled to be compensated adequately, but how that
    compensation is to be assessed is the moot question, which the
    Trial Court as well as the High Court have failed to appreciate. The
    basic issue which lost sight of was that it was not a chunk of land
    located at one place for which compensation could be assessed
    by considering the value of the land in the vicinity. It was a belt of
    land running into 100 kms. While referring to the facts of one case
    that the suit land forms part of the National Capital Region and is
    located at a distance of 6 acres/killas from G.T. Road, compensation
    for the land question, which is located in two different districts, was
    assessed at the same rate. However, this locational advantage
    cannot be uniformly applied to the entire transmission corridor, as
    the transmission line is running through 100 kms in different districts
    and villages with vastly different characteristics. Some portion of
[2025] 8 S.C.R.                                                             1065

          Kalpataru Power Transmission Ltd. (Now Known as
       Kalpataru Projects International Ltd.) v. Vinod and Ors. Etc.

     land may be close to a National Highway or State Highway or some
     other roads; some may be close to Abadi, whereas some portion of
     land may be falling within rural areas where the land is used only
     for agricultural purpose and with no connectivity by roads as such.
     Applying a uniform rate for the entire transmission corridor would not
     be a proper methodology for assessing fair compensation to which
     the landowners are entitled to. Nothing was pointed out at the time of
     hearing regarding status of any other petition filed by the landowners
     at any other place seeking compensation. In the absence thereof
     we are unable to examine as to what method was adopted therein.
     16.1 A somewhat similar issue came before the High Court in State
          of Haryana and Another vs. Pala Ram and Others.8 That case
          concerned acquisition of land for the construction of BML Hansi
          Butana Multipurpose Link Channel, however, the principles laid
          down therein may be relevant to the present matter. In that
          case, the entire channel length was 108 km, with land forming
          part of 52 villages across four districts. The High Court laid
          down the methodology for assessing compensation in such
          cases. It may be relevant for the reason that correct method
          is to firstly assess the value of land and thereafter determine
          the compensation payable to the landowners.
17. This Court observed in the case of Kerala SEB v. Livisha,9 that
    although there cannot be any hard and fast rule to determine
    compensation in cases of telegraph lines and electrical lines, certain
    factors should be looked into. The observations of the court in the
    aforesaid case are extracted hereinbelow:
            “7. We may, however, notice that in one of the impugned
            judgments, a learned Single Judge of the High Court held:
                   “The court below has fixed the land value at Rs 20,000
                   per cent and the rate of diminution at 40%. Taking
                   Exhibits A-1 and A-2 produced, the lower court is
                   correct in fixing the land value at Rs 20,000 per cent,
                   (sic which) cannot be the reasonable land value in
                   this case. Hence I fix the land value in this case at
                   Rs 30,000 per cent. So also the rate of diminution


8   2012 SCC Online P&H 24551.
9   (2007) 6 SCC 792 : 2007 INSC 638.
1066                                                       [2025] 8 S.C.R.

                       Supreme Court Reports


             in land value is fixed at 50% instead of 40% fixed
             by the court below. The order passed by the court
             below is modified accordingly.”
        No reason has been assigned in support of the above
        view. The materials placed on record were not analysed.
        Why such a view was taken also does not appear from
        the records of the case. The amount of compensation is
        required to be determined keeping in view the purpose and
        object of the statute. There cannot be any fixed formula
        therefor or the other. Although undoubtedly one formula laid
        down may assist the Board and/or the Reference Court to
        apply the same, but there cannot be a hard-and-fast rule
        in this behalf. A fixed formula for determining the amount
        of compensation although may make the task of the Land
        Acquisition Officer or the Reference Court easier but in
        our opinion each case is required to be taken on its own
        merit. We may hasten to add that the purpose and object
        of the Act and the methodology laid down therein for the
        purpose thereof should be the guiding factor.
                                                (emphasis supplied)

                            x         x          x
        9. Both telegraph lines and electrical lines are required to
        be drawn over the agricultural lands and/or other properties
        belonging to third parties. In drawing such lines, the entire
        land cannot be acquired but the effect thereof would be
        diminution of value of the property over which such line
        is drawn.
        10. The situs of the land, the distance between the high
        voltage electricity line laid thereover, the extent of the line
        thereon as also the fact as to whether the high voltage line
        passes over a small tract of land or through the middle of
        the land and other similar relevant factors in our opinion
        would be determinative. The value of the land would also
        be a relevant factor. The owner of the land furthermore, in
        a given situation may lose his substantive right to use the
        property for the purpose for which the same was meant
        to be used.”
[2025] 8 S.C.R.                                                           1067

         Kalpataru Power Transmission Ltd. (Now Known as
      Kalpataru Projects International Ltd.) v. Vinod and Ors. Etc.

18. Certain other arguments have also been noticed by the High Court
    regarding adoption of MOP Guidelines dated 15.10.2015 regarding
    assessment of compensation for the Tower Base Area (land beneath
    four legs of the tower) and the ROW Corridor. In the case in hand,
    sole reliance of the landowners is on the MOP Guidelines dated
    15.10.2015. The question arises as to whether these guidelines
    are applicable, even assuming the deemed consent was there, as
    opined by the High Court. The notification in the present case was
    published on 12.07.2010. Even the notice regarding erection of
    towers and drawing of power lines was issued to the landowners
    on 27.12.2011 and they had filed petition under Section 16(3) of the
    1885 Act before the District Judge on 06.04.2012. Meaning thereby,
    everything happened much before the aforesaid guidelines were
    issued. Paragraph 4 of the guidelines clearly provides that States
    and Union Territories were requested to take suitable decisions
    regarding adoption of the guidelines, considering that acquisition of
    land is a State subject. According to these guidelines, compensation
    for the area beneath the four legs of a tower is fixed at 85% of
    the circle rate to be determined by the District Magistrate or any
    other competent authority. For the Right of Way (ROW) corridor
    falling under the transmission lines, the maximum compensation
    provided is 15% of the land value. The use of the word “maximum”
    is of relevance. Further, whether administrative instructions could
    control the judicial power of the Court ? The question needs to be
    addressed.
19. The High Court failed to appreciate the fundamental fact that land
    pertaining to different villages falling in different districts, which may be
    the subject matter of consideration for assessment of compensation,
    would have been assessed differently by the Collector based on
    their respective locations and characteristics. Even in the case in
    hand, facts only pertaining to district Sonepat have been discussed.
    From Page 24 of the impugned judgment, it is evident that the land
    involved even in those cases, is located at different places, some
    close to Highway, whereas some at a distance.
20. For the reasons mentioned above, in our view, the order passed by
    the High Court cannot be legally sustained, hence, the same is set
    aside and the matters are remitted back to the High Court for fresh
    consideration in accordance with law.
1068                                                      [2025] 8 S.C.R.

                        Supreme Court Reports


     Re-RIGHT OF APPEAL
21. During the course of arguments before this Court, learned counsel for
    the parties referred to various factual matrix, pointing out errors not
    only in the judgment of the Trial Court but also of the High Court. It
    was also submitted that the factual aspects and the evidence led by
    the parties was not properly appreciated by the High Court. When the
    matter was examined, this Court also noticed these facts and found
    it appropriate to give opportunity to the counsel for the appellant to
    assist the court on the issue as to whether there should be some
    remedy of appeal against order passed by the District Judge, so that
    the facts of the case could be examined in detail. The appellants
    have submitted a note.
22. The case in hand pertains to erection of towers and drawing the
    power lines, for which right of way was taken. There being no
    independent provision available for the same in the Electricity Act,
    2003, the provisions of the 1885 Act have been adopted in terms
    of Section 164 of the 2003 Act.
23. Section 10 of the 1885 Act confers powers on the Telegraph Authority
    to place and maintain the telegraph lines and posts. Proviso (b) to
    the aforesaid section provides that the Central Government shall not
    acquire any right other than the right of user in the property upon
    which the authority places any telegraph line or post. Clause (d) of
    the proviso provides for payment of compensation. Relevant part of
    Section 10 of the 1885 Act is extracted below:
          “10. Power for telegraph authority to place and maintain
          telegraph lines and posts.—The telegraph authority may,
          from time to time, place and maintain a telegraph line
          under, over, along or across, and posts in or upon, any
          immovable property:
          Provided that—

          (a)                           xxx
          (b) the Central Government shall not acquire any right
          other than that of user only in the property under, over,
          along, across, in or upon which the telegraph authority
          places any telegraph line or post;

          (c)                           xxx
[2025] 8 S.C.R.                                                             1069

         Kalpataru Power Transmission Ltd. (Now Known as
      Kalpataru Projects International Ltd.) v. Vinod and Ors. Etc.

            (d) in the exercise of the powers conferred by this
            section, the telegraph authority shall do as little damage
            as possible, and, when it has exercised those powers
            in respect of any property other than that referred to in
            clause (c), shall pay full compensation to all persons
            interested for any damage sustained by them by reason
            of the exercise of those powers.”
     23.1 Section 16 of the 1885 Act deals with assessment and payment
          of compensation. Relevant portion of the aforesaid section is
          extracted below:
            “16. Exercise of powers conferred by section 10, and
            disputes as to compensation, in case of property other
            than that of a local authority.—

            (1) & (2)                      xxx
            (3) If any dispute arises concerning the sufficiency of
            the compensation to be paid under section 10, clause
            (d), it shall, on application for that purpose by either of
            the disputing parties to the District Judge within whose
            jurisdiction the property is situate, be determined by him.
            (4) If any dispute arises as to the persons entitled to
            receive compensation, or as to the proportions in which
            the persons interested arc entitled to share in it, the
            telegraph authority may pay into the Court of the District
            Judge such amount as he deems sufficient or, where
            all the disputing parties have in writing admitted the
            amount tendered to be sufficient or the amount has been
            determined under sub-section (3), that amount; and the
            District Judge, after giving notice to the parties and hearing
            such of them as desire to be heard, shall determine
            the persons entitled to receive the compensation or, as
            the case may be, the proportions in which the persons
            interested are entitled to share in it.
            (5) Every determination of a dispute by a District Judge
            under sub section (3) or sub-section (4) shall be final:
            Provided that nothing in this sub-section shall affect the
            right of any person to recover by suit the whole or any
1070                                                         [2025] 8 S.C.R.

                                Supreme Court Reports


               part of any compensation paid by the telegraph authority,
               from the person who has received the same.”
      23.2 On a perusal of Section 16(3) of the 1885 Act, it is evident
           that in case of dispute regarding sufficiency of compensation,
           application can be filed before the District Judge, within whose
           jurisdiction the property is situated. However, the 1885 Act
           does not provide any timeline within which such an application
           can be filed, nor does it specify the starting point of limitation
           for the purpose.
      23.3 Similarly, Section 16(4) of the aforementioned Act provides
           for resolution of disputes inter se the parties with reference
           to their entitlement to compensation. In such situation, the
           authority is required to deposit the amount of compensation
           with the District Judge, who will finally determine the rights
           of the parties.
      23.4 Section 16(5) provides that any order passed by the District
           Judge under sub-sections (3) or (4) shall be final, thereby
           precluding any appeal. The same cannot be challenged before
           Civil Court. Only extraordinary jurisdiction of the High Court
           can be invoked, wherein normally the findings of facts are
           not disturbed, and evidence is not reappreciated. The High
           Court proceeds only on undisputed facts under its power of
           judicial review.
24. Section 7-B of the 1885 Act talks of arbitration of disputes and sub-
    section (2) provides that the award of the arbitrator appointed under
    sub-section (1) thereof shall be conclusive between the parties to the
    dispute and shall not be questioned in any court. Meaning thereby,
    there is finality attached to the same. While dealing with the scope
    of challenge to an award passed under section 7-B of the 1885 Act,
    to which finality has been attached, this Court in M.L. Jaggi Versus
    Mahanagar Telephones Nigam Ltd. and Ors.,10 opined that in such
    circumstances, the only available remedy to a party aggrieved by such
    an award is to seek judicial review by way of writ petition. The High
    Court will not sit in appeal over the award but will only examine its
    correctness and legality within the limited confines of judicial review.


10   1996 INSC 6 : (1996) 3 SCC 119
[2025] 8 S.C.R.                                                      1071

         Kalpataru Power Transmission Ltd. (Now Known as
      Kalpataru Projects International Ltd.) v. Vinod and Ors. Etc.

25. To complete the narration with reference to the scheme of the 1885
    Act, we may add that Section 15 of the aforesaid Act provides for
    resolution of disputes between the telegraph authority and a local
    authority. An appeal from such resolution by a designated officer,
    has been provided to the Central Government.
26. As evident from the facts of the case and is a matter of common
    knowledge, assessment of fair value of land requires evidence to
    be led by both parties. Based on such evidence, value of land is
    determined. This factor is equally relevant for assessing compensation
    for the land coming beneath four legs of the towers or under the
    power lines as ROW is taken. If crops are standing on the land, for
    assessment of value thereof, or the quantum of damages suffered,
    evidence will be required. Even if the MOP guidelines issued by
    the Ministry of Power, Government of India are to be considered,
    there may still be issues regarding the rates fixed by the Collector
    for a particular area. This can also be subject matter of dispute.
    Furthermore, for determining the rights of various parties to receive
    compensation in case there is inter se dispute, certain amount of
    evidence would be required.
27. In the present case as well, some parties invoked Article 226 of the
    Constitution, whereas others filed petitions invoking Article 227 of
    the Constitution. This is solely because no proper appellate remedy
    has been provided. The only scope of interference in exercise of
    extra-ordinary jurisdiction of the High Court would be within the
    parameters of judicial review.
28. If we examine the scope of first appeal under any statute, entire case
    is open for re-hearing, both on questions of facts and on law. The
    First Appellate Court is required to address all the issues considered
    in the order impugned and decide the same by giving reasons. It
    is in fact continuation of the original proceedings. The power of
    the First Appellate Court is co-extensive with that of the trial court,
    unless the scope thereof is limited by the statute which provides for
    the appellate jurisdiction.
29.     As is evident from the provisions of the 1885 Act, there is no
      amendment in Sections 10 and 16, ever since the same was enacted.
      It may be noted that when the 1885 Act was enacted, there was
      limited development and there may have been few cases requiring
      determination of compensation under the aforementioned Act. The
1072                                                         [2025] 8 S.C.R.

                         Supreme Court Reports


     value of the land was also in peanuts. However, with the rapid pace
     of development in the electrical and power sector, the volume of
     litigation has increased significantly, necessitating assessment of
     compensation under the 1885 Act.
30. Besides there being no appellate remedy, we find that there are
    other gaps as well in the statutory scheme.
     30.1 A reading of the provisions of Sections 10 and 16 of 1885 Act
          reveals that in addition to no remedy of appeal being provided
          against the order passed by the District Judge, no timelines have
          been provided regarding payment of compensation to the affected
          parties after the right under Section 10(d) is exercised by the
          competent authority; the time during which any party can raise
          grievance about sufficiency of compensation so assessed. The
          provisions are also silent about the time during which a landowner
          can file an application before the District Judge in case sufficiency
          of compensation is disputed. The Act also does not provide the
          rate at which interest is to be paid to the landowners in case
          there is any delay in payment of compensation. This being an
          Act of Parliament, its application has to be uniform throughout
          the country. In the absence of defined parameters, it will depend
          on different courts, how they interpret the provisions.
31. In the case in hand, certain rights were taken by the authority
    concerned for the erection of electric towers and drawing the power
    lines and not the ownership of the land. There are many different
    statutes under which the ownership of the land is acquired by the
    competent authority in exercise of powers conferred under those
    statutes. Wherever such a power is exercised, the natural corollary is,
    the landowner is to be adequately compensated. Detailed procedure
    and timelines for different actions have been provided under those
    statutes.
     31.1 If we consider the provisions of erstwhile Land Acquisition
          Act, 1894, procedure as well as timelines had been provided
          for various actions to be taken in case there is acquisition of
          land, even remedy of appeal against the award of the District
          Judge/Additional District Judge had also been provided. Rate
          of interest was also prescribed.
     31.2 Similar is the position under the Right to Fair Compensation
          and Transparency in Land Acquisition, Rehabilitation and
[2025] 8 S.C.R.                                                           1073

           Kalpataru Power Transmission Ltd. (Now Known as
        Kalpataru Projects International Ltd.) v. Vinod and Ors. Etc.

                Resettlement Act, 2013. Detailed procedures have been
                provided in case any party is not satisfied with the compensation
                awarded. Matter can be referred to the Authority as established
                under Section 51 of the aforesaid Act. Against an order passed
                by the Authority, an appeal is provided to the High Court. The
                rate of interest on account of delay in payment of compensation
                has also been prescribed.
      31.3 Further, in the Requisitioning and Acquisition of Immovable
           Property Act, 1952, the adequacy of compensation is assessed
           through the process of arbitration. Though provisions of the
           Arbitration and Conciliation Act, 199611 have not been made
           applicable, remedy of appeal to the High Court has been
           provided.
      31.4 Under the National Highways Act, 1956, the dispute regarding
           adequacy of compensation is referred to arbitration and the
           provisions of the 1996 Act have been made applicable, hence,
           the remedies available thereunder could be availed of.
      31.5 Similar provisions are present in the Railways Act, 1989.
           Reference can also be made to the provisions of Coal Bearing
           Areas (Acquisition and Development) Act, 1957.
32. It is noticed that under the Petroleum and Minerals Pipelines
    (Acquisition of Right of User in Land) Act, 196212, the provisions are
    similar to the case in hand. In fact, Section 10 of the aforesaid Act
    is pari-materia to Section 16 of the 1885 Act. District Judge of the
    concerned district is the competent Court, whose jurisdiction can be
    invoked to challenge the sufficiency of compensation. As per Section
    10(6) of the aforesaid Act, order of the District Judge is final.
33. Needless to add here that, in the process of determination of
    compensation, evidence will have to be led by the parties. Unless
    statutory remedy of appeal is provided where all issues of law and
    facts can be re-examined, any other remedy may be illusionary. As
    is noticed in the facts of the present case, the remedies availed by
    different parties were different. In some of the cases, writ petitions
    were filed by the landowners under Article 226 of the Constitution


11   Hereinafter, “1996 Act”
12   Hereinafter referred to as “the Petroleum Act”.
1074                                                        [2025] 8 S.C.R.

                         Supreme Court Reports


     of India, impugning the judgment and decree of the civil court and
     in some of the cases, the contractor as well as the landowners filed
     petitions under Article 227 of the Constitution of India. Reappreciation
     of evidence in those proceedings may be an issue. Remedy may
     not be effective and can become illusionary.
34. Not only this, but the anomalies as have been referred to in the
    paragraph 30 with reference to various timelines as well, the matter
    needs to be examined.
35. In the aforesaid background, we are of the opinion that these issues
    need to be examined by the Law Commission of India and the Ministry
    of Law and Justice, Government of India, so as to determine whether
    a statutory remedy of appeal should be provided against judgments/
    orders passed under Sections 16(3) and 16(4) of the 1885 Act, the
    Petroleum Act or any other similar statute.

     NEED FOR UNIFORMITY IN NOMENCLATURE OF CASES
36. Section 16(3) of 1885 Act, provides that an application can be
    filed before the District Judge in case of a dispute related to
    compensation. In district Sonepat, such an application was registered
    and numbered as a Civil Suit where a judgment and decree has
    been passed. Whereas in district Jhajjar, the same was registered
    as a Civil Miscellaneous Application and only judgment has been
    passed. There is need to bring uniformity in the nomenclature to
    be assigned to these kinds of proceedings, which may come to
    the court under the 1885 Act and also the proceedings under the
    Petroleum and Minerals Pipelines (Acquisition of Right of User in
    Land) Act, 1962.

     RELIEF ON MERITS
37. For the reasons mentioned above, in our view, the order passed
    by the High Court cannot be legally sustained, hence, the same is
    set aside and the matters are remitted back to the High Court for
    fresh consideration in accordance with law. The civil appeals are
    accordingly disposed of. Keeping in view the issues involved, we
    request the High Court to make an effort to take up the matters
    expeditiously.
     37.1 Pending application(s), if any, are accordingly disposed of.
[2025] 8 S.C.R.                                                         1075

            Kalpataru Power Transmission Ltd. (Now Known as
         Kalpataru Projects International Ltd.) v. Vinod and Ors. Etc.

     DIRECTIONS
38. A copy of this order be sent to the Registrar General of the High
    Court of Punjab and Haryana for placing the same before Hon’ble
    Chief Justice for taking the appropriate steps in terms of observations
    made in paragraph 36 above.
39. The Registry of this Court shall forthwith send a copy of this order to
    the Secretary, Legislative Department, Ministry of Law and Justice,
    Government of India to examine the issue and take appropriate steps.

     Result of the case: Appeals disposed of.




     †
         Headnotes prepared by: Nidhi Jain


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Landowners"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

KALPATARU POWER TRANSMISSION LTD. (NOW KNOWN AS KALPATARU PROJECTS INTERNATIONAL LTD.) versus VINOD AND ORS. ETC. — 2025 INSC 1004 - Legal Desk AI