Created byFuzzy Cloud

Supreme Court of India

HARYANA POWER PURCHASE CENTREversusSASAN POWER LTD. & ORS

Citation
2023 INSC 326
Decided
6 April 2023
Disposal
Appeal(s) allowed

Holding

The Tribunal and Commission cannot disregard the express terms of the PPA or create a new bargain; the claimed cost escalations are not "change in law" events and therefore no compensation is payable.

Summary

The case concerned an Ultra Mega Power Project where the seller (Sasan Power Ltd.) claimed compensation for increased costs of a water‑intake system and customs duty on mining equipment, alleging these were "change in law" events under Article 13 of the Power Purchase Agreement (PPA). The seller argued that the Appellate Tribunal for Electricity (APTEL) and the Central Electricity Regulatory Commission (CERC) could override the express terms of the PPA and award compensation, relying on disclaimer clauses and the principle of contra proferentem. The Supreme Court examined the definitions of "change in law" in the PPA, the statutory framework of the Electricity Act, 2003, and the contractual disclaimer provisions, concluding that the alleged cost escalations did not fall within the defined change‑in‑law categories. It held that neither the Tribunal nor the Commission could rewrite the contract or disregard its express terms, and that the seller had a duty to conduct independent enquiries. Consequently, the Court set aside the Tribunal’s order and allowed the appeals, denying the seller’s compensation claims.

Issues considered

  • The increase in water‑intake system cost qualifies as a "change in law" under Article 13.1.1 of the PPA.
  • The customs duty imposed on mining equipment constitutes a "change in law" under the same provision.
  • Whether APTEL and CERC can override or rewrite the express terms of a PPA under their regulatory powers.
  • The effect of disclaimer clauses in the RFP/RFA on liability for erroneous information.
  • The applicability of the principle of contra proferentem in interpreting the PPA.

Legislation cited

Subjects

Electricity Act 2003Power Purchase AgreementChange in lawTariff regulationAppellate Tribunal for ElectricityCentral Electricity Regulatory CommissionContract interpretationContra proferentemCustoms duty exemptionUltra Mega Power Project

Judgment

                           [2023] 8 S.C.R. 1                               1


            HARYANA POWER PURCHASE CENTRE                                  A
                                   v.
                   SASAN POWER LTD. & ORS.
                   (Civil Appeal No. 11826 of 2018)
                           APRIL 06, 2023                                  B
       [K. M. JOSEPH AND B. V. NAGARATHNA, JJ.]
      Electricity Laws – Appellate Tribunal for Electricity (APTEL)
and Central Electricity Regulatory Commission (CERC), if
empowered to disregard the express words of a contract and create
                                                                           C
a new bargain – Held: In a case where the matter is governed by
express terms of the contract, it may not be open to the Central
Electricity Regulatory Commission even donning the garb of a
regulatory body to go beyond the express terms of the contract –
While it may be open for a regulation to extricate a party from its
contractual obligations, in the course of its adjudicatory power it        D
may not be open to the Commission by using the nomenclature
regulation to usurp this power to disregard the terms of the contract
– The Appellate Tribunal for Electricity cannot indeed make a new
bargain for the parties – The Tribunal cannot rewrite a contract
solemnly entered into – It cannot ink a new agreement – Such
                                                                           E
residuary powers to act which varies the written contract cannot be
located in the power to regulate – The power cannot, at any rate,
be exercised in the teeth of express provisions of the contract – In a
matter where the parties have entered into a contract with express
provisions, it cannot be said that the Tribunal would have power to
disregard the express provisions of the contract on the score that as      F
it turns out that with passage of time and even change in
circumstances, it is found that the contract cannot be worked except
at a loss for the contractor – Contract.
      Electricity Act, 2003: s.79 – Power Plant Project – Special
Purpose Vehicle – Power Purchase Agreement (PPA) – Compensation            G
due to ‘change in law’ – Special purpose vehicle formed to set up
an Ultra Mega Power Project – Power generated by the successful
bidder was to be supplied through procurers/distribution licensees
(appellant) – Petition u/s.79 of Electricity Act read with the statutory
framework governing procurement of power through competitive
                                                                           H
                                   1
2            SUPREME COURT REPORTS                       [2023] 8 S.C.R.


A   bidding and Articles 13 and 17 of the PPA for compensation due to
    change in law ‘during the construction period’ – Held: The matter
    must be viewed from the prism of the specific provisions defining
    the change in law and the actual change in law – On facts, the PPA
    contemplates that if the seller is affected by change in law and
    wishes to claim change in law, it has to notify the procurers of the
B
    change in law as soon as is reasonably practicable after becoming
    aware of the same – There is no material made available indicating
    that the procurers have held out that they will be liable – It could
    not be a change in law as contemplated in the agreement as it was
    not a change in initial consent which was the only case which was
C   argued in this regard – Parties were clear about how the change in
    law had to be compensated and methodology has been set out clearly
    – Therefore, any appeal made to the general part in Article 13.2
    which speaks about the affected party being restored to the same
    economic condition as if such change in law had not occurred cannot
    result in departing from the specific formula which has been set in
D
    place – If a certain timelimit is crossed by the procurers in the
    performance of its obligations in this regard, the seller (the first
    respondent) has been given the right to repudiate the contract – It
    is not the case of the first respondent that it purported to repudiate
    the contract – On the other hand, it is the common case that the
E   contract continued to be alive and it has survived subject to the
    claims which have been raised thereunder – This would mean that
    as the consequences of failure to perform the task having been
    provided in the contract in the manner provided, one should not
    ordinarily tarry further to ask as to whether this would provide the
    premise for a change in law as contemplated under Article 13.1.1 –
F
    Even in terms of the case built around Part II of Schedule 2 to the
    PPA under which the performing of the task mentioned in Article
    3.1.2A within the time provided was to be treated as a deemed initial
    consent, the consequence of failure to do that have been expressly
    spelt out – At best or at worst, it could have empowered the first
G   respondent to rescind the contract – The first respondent has not
    been able to demonstrate that there was a change in law.
           Doctrines / Principles – Principle of contra proferentem –
    Explained – Held: The principle of contra proferentem is ordinarily
    utilised in contracts of insurance and standard form contracts –
H   The principle apparently in substance is that in case of any doubt
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                      3
                  LTD. & ORS.

in its terms, the doubt should be resolved against the party who   A
drafted the contract.
     PTC India Limited v. Central Electricity Regulatory
     Commission (2010) 4 SCC 603 : [2010] 3 SCR 609 –
     held inapplicable.
     Energy Watchdog v. Central Electricity Regulatory             B
     Commission and Others (2017) 14 SCC 80 : [2017]
     3 SCR 153 and Uttar Haryana Bijli Vitran Nigam Ltd.
     & Anr. v. Adani Power Limited & Ors. (2019) 5 SCC
     325 : [2019] 4 SCR 487 – relied on.
     Gujarat Urja Vikas Nigam Ltd. v. Essar Power (2008)           C
     4 SCC 755 : [2008] 4 SCR 822; Skandia Insurance
     Co. Ltd. v. Kokilaben Chandravan & Ors. (1987) 2 SCC
     654 : [1987] 2 SCR 752; DLF Universal Limited v.
     Director, Town and Country Planning Department,
     Haryana (2010) 14 SCC 1 : [2010] 15 SCR 85;                   D
     Sumitomo Heavy Industries v. Oil and Natural Gas
     Commission of India (2010) 11 SCC 296 : [2010] 9
     SCR 176; Nabha Power Limited v. PSPCL (2018) 11
     SCC 508 : [2017] 14 SCR 301; Prahlad & Ors. v. State
     of Maharashtra & Anr. (2010) 10 SCC 458 : [2010]
     11 SCR 916; State of Punjab & Ors. v. Bakshish Singh          E
     (1998) 8 SCC 222 : [1998] 1 Suppl. SCR 478; Mahant
     Dhangir & Anr. v. Madan Mohan & Ors. (1987) (Supp)
     SCC 528 : [1988] 1 SCR 679; Uttar Pradesh Power
     Corporation Limited v. National Thermal Power
     Corporation Limited and Others (2009) 6 SCC 235 :             F
     [2009] 3 SCR 1060; Gujarat Urja Vikas Nigam Limited
     v. Tarini Infrastructure Limited and Others (2016) 8 SCC
     743 : [2016] 5 SCR 990 and Manohar Lal Sharma v.
     Principal Secretary & Ors. (2014) 9 SCC 614 : [2014]
     12 SCR 110 – referred to.
                                                                   G
                     Case Law Reference
[2017] 3 SCR 153              relied on               Para 28
[2019] 4 SCR 487              relied on               Para 28
[2008] 4 SCR 822              referred to             Para 28
                                                                   H
4           SUPREME COURT REPORTS                      [2023] 8 S.C.R.


A   [1987] 2 SCR 752               referred to            Para 28
    [2010] 15 SCR 85               referred to            Para 28
    [2010] 9 SCR 176               referred to            Para 28
    [2017] 14 SCR 301              referred to            Para 28
B   [2010] 11 SCR 916              referred to            Para 29
    [1998] 1 Suppl. SCR 478        referred to            Para 29
    [1988] 1 SCR 679               referred to            Para 29
    [2009] 3 SCR 1060              referred to            Para 37
C
    [2016] 5 SCR 990               referred to            Para 39
    [2019] 4 SCR 487               referred to            Para 84
    [2017] 3 SCR 153               referred to            Para 86
    [2010] 3 SCR 609               held inapplicable      Para 94
D
    [2014] 8 SCR 446               referred to            Para 118
    [2014] 12 SCR 110              referred to            Para118
          CIVIL APPELLATE JURISDICTION : Civil Appeal No.11826
    Of 2018.
E
          From the Judgment and Order dated 20.11.2018 of the Appellate
    Tribunal for Electricity, New Delhi in Appeal No.121 of 2015.
          With
          Civil Appeal Nos.11927, 12190 of 2018, 1670 Of 2019, 12232 of
F   2018 and 1742 of 2019
          G. Umapathy, P. Chidambaram, M.G. Ramachandran, Rana
    Mukherjee, Sajan Povayya, Sr. Advs., Rohit K. Singh, Anand K.
    Ganesan, Ms. Poorva Saigal, Nikunj Dayal, Shubham Arya, Amal Nair,
    Ms. Kritika Khanna, Ms. Pallavi Saigal, Ms. Reeha Singh, Ms. Shikha
G   Sood, Ms. Anumeha Smiti, K. V. Mohan, K.V. Balakrishnan, Ravi Nair,
    Rahul Kumar Sharma, Rakesh K. Sharma, Rajiv Srivastava, Nishant
    Sharma, Ms. Gargi Srivastava, Ms. Adviteeya, Ms. Aparna Bhat, Amit
    Kapur, Pukhrambam Ramesh Kumar, Rahul Kinra, Aditya Ajay, Karun
    Shrama, Girdhar Gopal Khattar, Ms. Aliva Ahmed, Ms. Raksha Agrawal,
    Ms. Divyya Kaul, Hasan Murtaza, Advs. for the appearing parties.
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                   5
                  LTD. & ORS.

      The Judgment of the Court was delivered by                                A
      K. M. JOSEPH, J.
       (1) The six appeals with which we are concerned have been filed
under Section 125 of the Electricity Act, 2003 (hereinafter referred to as
‘Act’ for brevity). The appeals are directed against the order passed by
the Appellate Tribunal for Electricity (hereinafter referred to as ‘Tribunal’   B
for brevity) in an appeal carried by the first respondent under Section
111 of the Act.
      (2) The appeal before the Tribunal, in turn, was lodged against the
order passed by the Central Electricity Regulatory Commission
(hereinafter referred to as ‘Commission’ for brevity). The Commission           C
passed the order purporting to be one under Section 79(b) inter alia of
the Act in a petition filed by the first respondent.
      FACTS
        (3) It was decided to set up an Ultra Mega Power Project. Towards
this end, the Power Finance Corporation Limited of India was to be the          D
nodal agency. It incorporated a Special Purpose Vehicle, which is the
first respondent. The idea was to set up the Ultra Mega Power Project
which would be operated by the successful bidder selected through an
international competitive bidding. The power generated by the successful
bidder was to be supplied through procurers (the appellants before us),
                                                                                E
who can be described also as the distribution licensees under the Act.
The appellants were to supply the power so procured finally to the
consumers.
        (4) Since what was contemplated was seeking shelter under
Section 63 of the Act, we must refer to the guidelines which have been
issued by the Central Government purporting to act under Section 63.            F
Guidelines were issued on 19.01.2005. We deem it appropriate to set out
the following guidelines:
      “2.1 These guidelines are being issued under the provisions of
      Section 63 of the Electricity Act, 2003 for procurement of electricity
      by distribution licensees (Procurer) for:                                 G
      (a) long-term procurement of electricity for a period of 7 years
      and above;
      (b) Medium term procurement for a period of upto 7 years but
      exceeding 1 year.
                                                                                H
6            SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A         2.2 The guidelines shall apply for procurement of base-load and
          seasonal power requirements through competitive bidding, through
          the following mechanisms:
          i. Where the location, technology, or fuel is not specified by the
          procurer (Case 1);
B         ii. For hydro-power projects, load center projects or other location
          specific projects with specific fuel allocation such as captive mines
          available, which the procurer intends to set up under tariff based
          bidding process (Case 2).”
          (5) The guidelines are binding on the procurers. Guideline 3.2
C   which is related to preparation for the invitation of bids would assume
    relevance. It reads as follows:
          “3.2 For long-term procurement from hydro electric projects or
          for projects for which pre-identified sites are to be utilized (Case
          2), the following activities should be completed by the procurer or
D         authorized representative of the procurer, before commencing the
          bid process:
          - Site identification and land acquisition required for the project
          - Environmental clearance
E         - Fuel linkage, if required (may also be asked from bidder)
          - Water linkage
          - Requisite Hydrological, geological, meteorological and
          seismological data necessary for preparation of Detailed Project
          Report (DPR), where applicable.
F
          The bidder shall be free to verify geological data through his own
          sources, as the geological risk would lie with the project developer.
          The project site shall be transferred to the successful bidder at a
          declared price.
G         Provided that for the projects from which more than one distribution
          licensees located in different States intend to procure power and
          if the preparations for such projects are being facilitated by the
          Central Government, the activities referred to above shall be
          initiated before the bidding process and should be completed before
          signing the power purchase agreement with the selected bidder.
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                 7
           LTD. & ORS. [K. M. JOSEPH, J.]

       (6) Under the guidelines, tariff structure is contemplated which       A
consists of capacity charges and energy charges which are dealt with in
detail. It also deals with bidding process. The bidding process itself is
divided into two stages, viz., a determination of the qualification by a
pre-qualification system and thereafter submission and consideration of
essentially what consists of the financial bid. There is a guideline which
                                                                              B
deals with arbitration and it was contained in guideline 5.17:
      “5.17 The procurer will establish an Amicable Dispute Resolution
      (ADR) mechanism in accordance with the provisions of the Indian
      Arbitration and Conciliation Act, 1996. The ADR shall be
      mandatory and time-bound to minimize disputes regarding the bid
      process and the documentation thereof.                                  C

      If the ADR fails to resolve the dispute, the same will be subject to
      jurisdiction of the appropriate Regulatory Commission under the
      provisions of the Electricity Act 2003.”
       (7) It is, accordingly, purporting to act in terms of the guidelineS   D
that a Request for Qualification (for short RFQ) came to be issued on
31.03.2006. Reliance Power Limited was one of the bidders which was
pre-qualified in terms of the RFQ. On 18.08.2006, there was a change
notified in the guidelines. It brought about the following changes in the
guidelines 5.17 besides guideline No. 4.7. The unamended and the
amended guidelines 4.7 and 5.17 read as follows:                              E




                                                                              F




                                                                              G




                                                                              H
8            SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A          (8) On 21.08.2006, a Request for Proposal, for short RFP, came
    to be issued. We deem it appropriate to refer to the following provisions
    of the RFP.
          “4. While this RFP has been prepared in good faith, neither the
          Procurers, Authorised Representative and Power Finance
B         Corporation Limited (PFC) nor their directors or employees or
          advisors/consultants make any representation or warranty, express
          or implied, or accept any responsibility or liability, whatsoever, in
          respect of any statements or omissions herein, or the accuracy,
          completeness or reliability of information contained herein, and
          shall incur no liability under any law, statute, rules or regualations
C         as to the accuracy, reliability or completeness of this RFP, even if
          any loss or damage is caused to the Bidder by any act or omission
          on their part.
          1.3 The objective of the bidding process is to select a
          SuccessfulBidder for development of the Project as per the terms
D         of the RFP. The Project will have a Contracted Capactiy of
          minimum of 3500 MW and maximum of 3800 MW in accordance
          witht he terms of the PPA. The Selected Bidder shall purchase
          the entire shareholding of the Authorised Representative from
          PFC and its nominees in accordance with Share Purchase
E         Agreement and cause the Seller to enter into the RFP Project
          Documents. The Selected Bidder shall be responsible for ensuring
          that the Seller undertakes development, finance, ownership, design,
          engineering procurement, construction, commissioning, operation
          and maintenance of the Project as per the terms of the RFP Project
          Documents. The Selected Bidder shall also ensure:
F
          (i) All equipment and auxiliaries shall be suitable for continuous
          operation in the frequency range of 47.5 to 51.5 Hz (-5% to +3%
          of rated frequency of 50.0 Hz).
          (ii)The plant shall be capable of delivering contracted capacity
G         continously at 47.5 Hz grid frequency.
          1.4 The Procurers through the Authorised Representative, have
          initiated development of the Project at Sasan, District Sidhi,
          Madhya Pradesh and shall complete the following tasks in this
          regard by such time as specified hereunder:
H
HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                 9
          LTD. & ORS. [K. M. JOSEPH, J.]

   iv. Allocation of main Captive Coal Mine(s) and providing                 A
   geological report (GR) for the same; at least ninety (90) days
   prior to Bid Deadline. Allocation of other Captive Coal Mine(s)
   and available information regarding quality and quantity of coal
   (GR related information) would be made available at least thirty
   (30) days prior to Bid Deadline. The Seller shall pay the final cost
                                                                             B
   of geological reports (Grs). The Indicative Cost of geological
   reports (Grs), would be made available at least thirty (30) days
   prior to bid Deadline;
   v. Tying up water linkage for the Project requirement along with
   approval of Central Water Commission, at least thirty (30) days
   prior to Bid Deadline;                                                    C

   Water intake study report and Project Report including geo-
   technical study, topographical survey, area drainage study, socio-
   economic study and EIA study (rapid) would be made available
   at least ninety (90) days prior to Bid Deadline;
                                                                             D
   vi. issue of certificate by Ministry of Power, Government of India
   extending the benefits to power generation projects under Mega
   Power Policy upto the Scheduled COD of the Power Station by
   Government of India at least thrity (30) days prior to Bid Deadline;
   It may be noted that noe of the Procurers, Authorised                     E
   Representative and PfC, nor their directors, employees or advisors/
   consultants make any representation or warranty, express or
   implied, or accept any responsibility or liability, whatsoever, in
   respect of any statements or omissions made in the water intake
   study report and Project Report, or the accuracy, completeness
   or reliablility of information contained therein, and shal incur no       F
   liability under any law, statute, rules or regualtions as to the
   accuracy, reliability or completeness of such water intake study
   report and Project Report, even if any loss or damage is caused
   to the Selected Bidder by any act or omission on their part. The
   Ministry of Power and the State Government of Madhya Pradesh              G
   have expressed their support to the Seller, on best endeavour basis,
   in enabling the Seller to develop the Project.
   2.7.2.1 The Bidder shall make independent enquiry and satisfy
   itself with respect to all the required information, inputs, conditions
   and cirumstances and factors that may have any effect on his
                                                                             H
10      SUPREME COURT REPORTS                              [2023] 8 S.C.R.


A    Bid. In assessing the Bid, it is deemed that the Bidder has inspected
     and examined the site conditions and its surroundings, examined
     the laws and regulations in force in India, the transportation facilities
     available in India, the grid conditions, the conditions of roads,
     bridges, ports, etc. For unloading and/or transporting heavy pieces
     of material and has based its design, equipment size and fixed its
B
     price taking into account all such relevant conditions and also the
     risks, contingencies and other circumstances which mayh influence
     or affect the supply of power.
     2.7.2.2 In their own interest, the Bidders are requested to
     familiarize themselves with the Electricity Act, 2003, the Income
C    Tax Act 1961, the Companies Act, 1956, the Customs Act, the
     Foreign Exchange Management Act, IEGC, the regulations
     framed by regulatory commissions and all other related acts, laws,
     rules and regulations prevalent in India. The procuers shall not
     entertain any request for clarifications from the Bidders regarding
D    the same. Non-awareness of these laws or such information shall
     not be a reason for the Bidder to request for extension of the Bid
     Deadline. The Bidder undertakes and agrees that before
     submission of its Bid all such factors, as generally brought out
     above, have been fully investigated and considered while submitting
     the Bid.
E
                                ANNEXURE 5
               SITE DETAILS ALONG WITH SITE MAP
     The Site is located near Sasan village in Singrauli Tehsil in District
     Sidhi of Madhya Pradesh. The nearest Railway Station is Shakti
F    Nagar (18km) and nearest Airport is Varanasi (250 km). The site
     is situated at 23°58’30"N latitude and 82°37’03"E longtitue.
     About 3500 acres of land has been identified for the project
     covering villages of Sidhikala, Harhawa, Tiara, Jhanjitola and
     Sidhikhud. Out of this, about 2000 acres of land has been identified
G    for main plant, about 1100 acres for ash disposal/dyke and 400
     acres for colony.
     Water source for the project is Govind Ballabh Pant Sagar (Rihand
     Reservoir), which is about 6-7 km from the main plant site. Water
     will be brought to site by suitable pumping arrangement and
H    pipelines.
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                11
           LTD. & ORS. [K. M. JOSEPH, J.]

      Coal blocks (mines) in Singrauli area with reserves of about 700-      A
      800 million tons will be allocated as Captive Coal Blocks (mines)
      for this Project. The Project will require the development of a
      coalmine with production of 18-20 million tons per annum (MTPA)
      Vicinity map of Site is enclosed.
      Further details are provided in the Project Report.”                   B
      (9) We may, at this juncture, notice also that the Special Purpose
Vehicle which was put in place for carrying out the activities also,
commissioned a study by WAPCOS (a public sector body of the Central
Government). It was tasked with the project to ascertain about the
availability of water inter alia. Water is an indispensable factor for the   C
successful running of the power plant which was contemplated.
WAPCOS made available its report on 03.08.2006.
        (10) Reliance Power Limited applied pursuant to the RFP. Though,
initially, its bid was not the lowest, but on account of the fact that the
lowest bidder was found to be not eligible, Reliance Power Limited           D
emerged as the lowest bidder. In keeping with the conditions, Reliance
Power Limited acquired 100 per cent share holding of the first respondent
and it was favoured with the Letter of Intent on 01.08.2007. It entered
into a Power Purchase Agreement (hereinafter referred to as ‘PPA’)
on 07.08.2007. In the second week of December, 2007, it would appear
that the first respondent which now stood transformed as a fully owned       E
company of the successful bidder Reliance Power Limited, commissioned
a new Study by WAPCOS. WAPCOS submitted its report on 04.04.2008.
We must at this juncture notice that ‘21.07.2007’ has been determined
as the cut off date, the relevance of which will be unfolded in the later
part of the judgment.                                                        F
        (11) The PPA contemplated two phases. The first phase was the
construction of the power plant. The second was the operation of the
power plant. The PPA was to be enforced for a period of 25 years.
Therefore, we can safely characterise it as along term agreement to
purchase power. Since this was a case of competitive bidding, leading to     G
the finding out of the lowest bidder, but faced with the regime under
Section 63 of the Act which stood attracted, after the PPA was entered
into, a petition was moved before the Commission for adopting the rates
as contemplated in the PPA. By order dated 17.10.2007, the Commission
after considering the relevant matters, adopted the rates in accordance
with the PPA. It is, thereafter, that the present petition was moved by      H
12            SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A    the first respondent on 19.02.2013. It is relevant at this stage to set out
     certain portions of the petition. The petition has been filed under Section
     79 of the Act read with the statutory framework governing procurement
     of power through competitive bidding and articles 13 and 17 of the PPA
     between the parties for compensation due to change in law ‘during the
     construction period’. After setting out the facts which we do not consider
B
     relevant to advert to, the following is noticed.
           “5. It is submitted that the following Changes in Law have occurred
           during the Construction Period of the Project which have caused
           the Capital Cost of the Project to increase substantially:
C          a) Increase in Declared price of Land for the Project which
           includes the land for the Power Station, the Moher, Moher-Amlohri
           Extension and Chhatrasal captive coal blocks;
           b) Increase in cost of implementation of the Resettlement and
           Rehabilitation Plan (“R&R Plan”) for the Moher, Moher-Amlohri
D          Extension and Chhatrasal captive coal blocks;
           c) Increase in cost of Geological Reports for the Moher, Moher-
           Amlohri Extension and Chhatrasal captive coal blocks;
           d) Increase in cost of compensatory afforestation for the Moher,
           Moher-Amlohri Extension and Chhatrasal captive coal blocks;
E
           e) Increase in cost of Water Intake system due to an incorrect
           assessment of conditions in the original report supplied to the
           bidders at the RFP stage;
           f) Levy of excise duty on cement and steel used in the Project;
           and
F
           g) Levy of Customs Duty on mining equipment imported for the
           Project.”
           (12) Since, in this case, we are concerned only with two aspects,
     namely claims under clause(e) and clause(g) we deem it appropriate
G    only to refer to the pleadings of the first respondent in regard to the
     same.
           Increase in cost of Water Intake System
           “65. As per Clause 1.4(v) of RFP for Sasan UMPP, the Procurers
           through the Authorized Representative had to provide water intake
H
HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                13
          LTD. & ORS. [K. M. JOSEPH, J.]

   study report. WAPCOS (a premier Government of India agency)              A
   was appointed to conduct the water intake study. WAPCOS, as
   the expert agency identified the water intake pump house location
   and the pipeline route from the intake pump house to the power
   plant in its Report. This report was made available to all the bidders
   before bid submission so that the bidders could factor in the cost
                                                                            B
   of the water intake system in preparation of their financial bid i.e.,
   the tariff at which power would be supplied to the Procurers. The
   total estimated cost for the construction of water intake system
   for the location and route indicated in the report by WAPCOS
   was estimated to be approximately Rs.92 Crores. The WAPCOS
   Report along with the estimated cost are annexed herewith and            C
   marked as Annexure P-24 (Colly).”
   “66. After RPower acquired the Petitioner, WAPCOS was
   appointed to confirm the technical feasibility as part of detailed
   engineering exercise. During this process, it was discovered that
   the water intake location as finalized by WAPCOS before the              D
   bidding was not an appropriate location and does not ensure reliable
   supply of water to the power plant. It was also found that the
   water intake at the original location indicated by WAPCOS in the
   pre-bid report would have resulted in shutdown of power plant
   for a considerable period during the lean season.”
                                                                            E
   “67. Thereafter, WAPCOS conducted detailed bathymetric studies
   and recommended a new location for water intake, which was 23
   km from the power plant as against 12.5 km initially indicated at
   the time of bidding (original location). It was highlighted that new
   location would ensure reliable water supply to the power plant.
   Due to increase in distance, submergence area along the route            F
   and construction time, there has been considerable increase in
   the cost of the water intake system as detailed below. The report
   of WAPCOS recommending the revised location is annexed
   herewith and marked as Annexure p-25.”
   “68. The cost for the construction of water system for the new           G
   location is Rs. 244 Cr. Out of the aforesaid amount, a sum of
   Rs.185 Crores has already been incurred and balance of Rs.
   59Crores is to be spent. The estimated increase in cost of the
   water intake system due to the change in location of the water
   intake system is Rs.152 Crores. Since this increase is directly          H
14      SUPREME COURT REPORTS                         [2023] 8 S.C.R.


A    attributable to the error in the WAPCOS report provided to the
     bidders at the pre-bid stage, the Petitioner is required to be
     compensated for the same. The cost break up for the new/
     appropriate location which will ensure reliable water supply is
     annexed herewith and marked as Annexure P-26.”
B    “75. It is submitted that the UMPP Policy envisages domestic
     coal based UMPPs as integrated projects where the power station
     and the captive coal mines are treated as an integrated unit. This
     is also recognized in the PPA as well as other project documents
     like the RFQ and the RFP.”
C    “76.As per Notification 21 of 2002-Customs dated 01.03.2002
     issued by the Ministry of Finance, Government of India, the
     customs duty on goods required for setting up mega power projects
     has been prescribed as nil meaning thereby that no customs duty
     will be levied on goods imported for setting up a mega power
     project. A copy of Notification 21 of 2002-Customs is annexed
D    herewith and marked as Annexure P-32.”
     “77.Sasan UMPP was accorded in-principle mega power project
     status as per Ministry of Power’s letter no. F.No. 12/18/2006-
     P&P dated 20.10.2006. The final certificate was issued on
     21.09.2007.”
E
     “78.Sasan UMPP is an integrated power project with captive coal
     mines viz. Moher, Moher Amlohri Extension and Chhatrasal Coal
     Blocks. The captive coal mines allocated for Sasan UMPP form
     an integral and essential part of the Project and any equipment
     imported in relation to the captive coal mines would therefore be
F    treated as goods imported for setting up the Project.”
     “79.The Petitioner was required to import mining equipment for
     setting up the captive coal mines from which coal will be sourced
     for the Project since the required mining equipments were not
     available in India.”
G
     “80.On 05.05.2011, the Petitioner applied to the Energy
     Department, Government of Madhya Pradesh for
     recommendation letter to import mining equipments for Sasan
     UMPP under nil custom duty as is applicable for the other
     equipment such as power plants of the Project. This application
H
HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                  15
          LTD. & ORS. [K. M. JOSEPH, J.]

   was premised on Notification 21 of 2002-Customs. However, vide             A
   an Office Memorandum dated 17.06.2011, the Ministry of Power
   has intimated that the exemption for customs duty for UMPPs is
   given only with respect to power equipment, which was forwarded
   to Petitioner by Government of Madhya Pradesh on 20.06.2011.
   Copies of letters dated 05.05.2011 and 17.06.2011 are annexed
                                                                              B
   herewith and marked as Annexure P-33(Colly)”
   “81.Based on Ministry of Power’s Office Memorandum’s, the
   Energy Department, Government of Madhya Pradesh declined
   to issue the recommendation letter which was required by the
   Petitioner to claim nil customs duty. In view of the refusal by
   Energy Department, Government of Madhya Pradesh and in the                 C
   interest of the Project and power consumers, Petitioner had to
   seek recommendation letter from Energy Department, Government
   of Madhya Pradesh to import mining equipments at project import
   rate of 20.94%, which is now reduced to 16.85% with effect
   from 17.03.2012.”                                                          D
   “82.The decision of the Ministry of Power detailed in its office
   memorandum dated 17.06.2011 and refusal by Energy
   Department, Goverment of Madhya Pradesh to provide
   recommendation letter to import mining equipments for Sasan
   UMPP under nil custom duty amounts to a Change in Law under                E
   Article 13.1 of the PPA and Petitioner is entitled to be compensated
   for the same.”
   “83.The total amount of customs duty paid by the Petitioner on
   mining equipments imported for Sasan UMPP is Rs. 361.47 Crores
   till date. The total custom duty for mining equipments is estimated        F
   to be about Rs. 531 Crores. The details of the custom duty paid
   on mining equipments and estimated to be paid in future are
   annexed herewith in Annexure P-34 (Colly).”
   “84.It is submitted that the Petitioner has already surpassed the
   indicative costs provided by the Procurers and in certain instances        G
   as indicated hereinabove, the Petitioner will be required to pay
   the increased Capital Cost in the future. In this regard, the Petitioner
   is claiming the following reliefs:
   (a) In relation to the Changes in Law where the additional Capital
   Cost has already been incurred, this Hon’ble Commission may
                                                                              H
16      SUPREME COURT REPORTS                          [2023] 8 S.C.R.


A    direct the Procurers to compensate the Petitioner for such increase
     in Capital Cost; and
     (b) In relation to the Changes in Law for which the liability is yet
     to be incurred, the Petitioner is seeking a declaration from this
     Hon’ble Commission that the increased expenditure amounts to
B    Change in Law. The actual payment will be claimed as and when
     it falls due.”
     “89.From the above discussions and facts, it is clear that:-
     (a) One of the objectives of the National Electricity Policy and
     the Tariff Policy is to secure commercial viability of electricity
C    sector while ensuring fair pricing and quality of supply.
     (b) Power procurement under Section 63 of the Act is governed
     by the statutory framework comprising (i) Section 63 of the Act,
     (ii) Government of India’s Guidelines and (iii) standard documents
     being RFP and PPA.
D
     (c) In terms of Section 63 of the Act the successful bid must be
     selected consistent with the guiding principles under Section 61 of
     the Act meaning thereby that while adoption of tariff under Section
     63 of the Act, the principles as laid down under Section 61 need to
     be complied.
E
     (d) Power procurement pursuant to the statutory framework
     constitutes a statutory contract in terms of the pre-approved and
     finalized PPA governed by provisions of the Act as well as the
     Guidelines.
     (e) The PPA envisages the adjustment of tariff by this Hon’ble
F
     Commission to restore/restitute the party adversely affected (the
     Petitioner in the present case).”
     “90. It is also pertinent to note that under Section 79(1)(b) of the
     Act, this Hon’ble Commission has been given the power to regulate
     the tariff of generating companies like the Petitioner which have
G    a composite scheme for generation and sale of electricity in more
     than one state.”
     “91.The present Petition has been filed for compensation on
     account of Changes in Law which have impacted the Capital
     Cost of the Project as well as for compensation for costs incurred
H
HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                 17
          LTD. & ORS. [K. M. JOSEPH, J.]

   in excess of the indicative costs provided by the Procurers, which        A
   were the basis for formulation of the financial bid of Rpower.”
   “92.The Petitioner had approached the Procurers for an amicable
   resolution. However, all efforts made by the Petitioner to seek an
   amicable resolution to the unforeseen and undeserved commercial
   implication with the Procurers have proved fruitless. In this             B
   backdrop, it has become imperative and necessary for the
   Petitioner to invoke jurisdiction of this Hon’ble Commission to
   issue appropriate orders as prayed for in the Petition.”
   “93.It is submitted that the present Petition has been filed invoking:-
   (a) Section 79(1)b) of the Act under which this Hon’ble                   C
   Commission has the power to regulate the tariff of the Petitioner.
   (b) Section 79(1)(f) of the Act which gives this Hon’ble
   Commission the power to adjudicate upon disputes involving the
   Petitioner.
                                                                             D
   (c) Regulations 82, 92 and 113 of the Central Electricity Regulatory
   Commission (Conduct of Business) Regulations, 1999.
   (d) Article 13 of the PPA read with Article 17 and Paragraph 5.17
   of the Competitive Bidding Guidelines in terms of which this
   Hon’ble Commission has the power to adjudicate upon any dispute
                                                                             E
   that arises claiming any change in or regarding determination of
   the tariff or any tariff related matters, or which partly or wholly
   could result in change in tariff.”
   “104. As detailed in Paragraphs 75-83 above, Notification 21 of
   2002-Customs issued by the Ministry of Finance, Government of
                                                                             F
   India granted 100% exemption from Customs duty to goods required
   for setting up mega power projects. The Petitioner was required
   to import equipment for operation of the coal mine which is an
   integral part of the Project.”
   “105. It is submitted that as per the said Notification, any entity
   which intended to claim the customs duty exemption was required           G
   to apply to the Sponsoring Authority for an exemption certificate.
   This was essential to claim the customs duty exemption. In this
   regard, the Petitioner wrote to the Government of Madhya Pradesh
   to recommend the Petitioner’s case to the Commissioner of
   Customs on 5.5.2011 for nil custom duty on mining equipments.”            H
18      SUPREME COURT REPORTS                          [2023] 8 S.C.R.


A    “106.It is submitted that vide an Office Memorandum dated
     17.06.2011, the Ministry of Power intimated Government of
     Madhya Pradesh that the exemption for customs duty for UMPPs
     is given only with respect to power equipment. The total amount
     of customs duty paid by the Petitioner on mining equipments
     imported for Sasan UMPP is Rs.361.47 Crores till date. Total
B
     custom duty for mining equipments is estimated to be about Rs.
     531 Crores.”
     “107. It is submitted that the decision of the Ministry of Power
     amounts to a Change in Law under Article 13.1 of the PPA and
     the Petitioner is entitled to be compensated for the same. It is
C    further submitted that the Petitioner not being allowed to import
     mining equipment under nil customs duty as is granted for the
     other equipment such as power plants of the Project qualifies as
     Change in Law under Article 13.1 of the PPA.”
     “108. It is submitted that as per RFP for Sasan UMPP, the
D    Procurers had to provide water intake study report. This study
     was conducted by WAPCOS and the report was made available
     to all the bidders before bid submission. The cost of the water
     intake system as per the report was approximately Rs.92 Crores.
     This estimation was factored into the bid at the time of submission
E    of the financial bid.”
     “109. It is submitted that after Rpower acquired the Petitioner,
     WAPCOS was tasked with confirming the technical feasibility
     during the detailed engineering exercise. During this process, it
     was discovered that the water intake location as intimated in the
F    pre-bid report was not appropriate. After, conducting another
     detailed study, WAPCOS determined that a new location would
     be suitable. The new location is 23 km from the power plant as
     against 12.5 km initially indicated at the time of bidding (original
     location).”

G    “110. It is submitted that due to the increase in distance,
     submergence area along the route and construction time there
     has been considerable increase in cost of the water intake system.
     The cost for the construction of water system for the new location
     is Rs. 244 Cr. The estimated increase in cost of the water intake
     system due to the change in location of the water intake system is
H    Rs.152 Crores.”
HARYANA POWER PURCHASE CENTRE v. SASAN POWER                               19
          LTD. & ORS. [K. M. JOSEPH, J.]

   “111.It is submitted that the increase in cost of the water intake      A
   system is on account of the errors in the report provided by the
   Procurers and therefore, the Procurers are obligated for
   compensating the Petitioner for the difference in cost. It is further
   submitted that since the water pipeline corridor is part of the Power
   Station Land and the water intake pipeline is an integral part of
                                                                           B
   the Power Station, any change in the indicative cost of the water
   intake system will be covered under Change in Law.”
   “120.Section 79 of the Act, inter alia, empowers the Hon’ble
   Commission to:-
   (a) Regulate the tariff of generating companies other than those        C
   owned or controlled by the Central Government if such generating
   companies entered into or otherwise have a composite scheme
   for generation and sale of electricity in more than one State; and
   (b) To adjudicate upon the disputes involving the distribution
   companies or transmission licensees with regard to the matters          D
   connected with regulation of tariff of generating companies.”
   “128. It is submitted that the present case involves a situation
   where the compensatory mechanism under the PPA for
   compensation for Change in Law has failed. It does not meet the
   objective of restoring an affected party to the same economic           E
   condition as if the change in law had not occurred. Therefore, this
   is a fit case for this Hon’ble Commission to exercise its powers
   under Section 79 and devise a mechanism to uphold the objective
   and purpose of Article 13 – to provide economic restitution.”
   “129. It is further submitted that PPA envisages a scenario where       F
   this Hon’ble Commission can interfere with the issues relating to
   the claim made by a party for any change and/or determination of
   the tariff or any matter relating to the tariff or claims made by any
   party which partly or wholly related to any change in the tariff or
   determination of any such claim which can result in change in the
   tariff. In this context, Articles 13 and 17 are noteworthy. While       G
   Article 13 of the PPA envisages tariff adjustment in the event of
   “Change in Law”, Article 17 of the PPA provides for dispute
   resolution, by the Hon’ble Commission in case of claim made by
   any party for any change in or determination of tariff or any matter
   related to tariff or claims made by any party, which partly or wholly
                                                                           H
20            SUPREME COURT REPORTS                          [2023] 8 S.C.R.


A          relate to any change in the tariff or determination of any of such
           claims could result in change in tariff.”
           “142.The Petitioner therefore most humbly and respectfully prays
           that this Hon’ble Commission be pleased to adjudicate upon the
           present Petition to:-
B          (a) Declare that the items set out in Paragraph 5 above as Change
           in Law during Construction Period and/or changes which has led
           to an increase in the Capital Cost of the Project;
           (b) Restitute the Petitioner to the same economic condition as if
           the said Changes in Law had not occurred and devise a mechanism
C          by which the Petitioner is compensated for the aggregate financial
           impact and increase in capital cost of account of the Changes in
           Law, the details of which are set out in Paragraph 113 above; and
           (c) Pass any such other and further reliefs as this Hon’ble
           Commission deems just and proper in the nature and circumstances
D          of the present case.”
           (13) After exchange of pleadings, the Commission passed the
     order dated 04.02.2015. Since we are in these appeals to be detained
     only by two aspects, we notice the following findings:
           “30. The petitioner has submitted that as per Clause 1.4(V) of
E
           RFP for Sasan UMPP, the Procurers through the Authorized
           Representative had to provide water intake study report. WAPCOS
           (a premier Government of India agency) was appointed to conduct
           the water intake study. WAPCOS, as the expert agency identified
           the water intake pump house location and the pipeline route from
F          the intake pump house to the power plant in its Report. This report
           was made available to all the bidders before bid submission so
           that the bidders could factor in the cost of the water intake system
           in preparation of their financial bid i.e. the tariff at which power
           would be supplied to the Procurers. The total estimated cost for
           the construction of water intake system for the location and route
G
           indicated in the report by WAPCOS was estimated to be
           approximately 92 Crore. After RPower acquired the project,
           WAPCOS was appointed to confirm the technical feasibility as
           part of detailed engineering exercise. During this process, it was
           discovered that the water intake location as finalized by WAPCOS
H          before the bidding was not an appropriate location and does not
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                 21
           LTD. & ORS. [K. M. JOSEPH, J.]

      ensure reliable supply of water to the power plant. It was also         A
      found that the water intake at the original location indicated by
      WAPCOS in the pre-bid report would have resulted in shutdown
      of power plant for a considerable period during the lean season.
      Thereafter, WAPCOS conducted detailed bathymetric studies and
      recommended a new location for water intake, which was 23 km
                                                                              B
      from the power plant as against 12.5 km initially indicated at the
      time of bidding (original location). It was highlighted that new
      location would ensure reliable water supply to the power plant.
      Due to increase in distance, submergence area along the route
      and construction time, there has been considerable increase in
      cost of the water intake system as per following details (Annexure      C
      P-26 of the petition) and as per the earlier report of WAPCOS:-




                                                                              D




                                                                              E


       31. MPPMCL has submitted that it is an expense incurred by the
petitioner but is not covered under “Change in Law” under Article 13.1.1
of the PPA. However, it is concluded that the cost has been incurred by       F
the petitioner and exceeds the estimates given by the procurer’s authorized
representative prior to bid submission. HPCC has submitted that the
price and other details given in the bidding document were by way of
information and it was for the bidders to conduct independent enquiry
and verify the information and details. There is no misrepresentation by
the procurers or by the Bid Process Coordinators at the time of bidding       G
in relation to water intake for the project. In view of the specific
disclaimer and the requirement to conduct independent enquiry, the
petitioner was required to make appropriate enquiries into the matter
before bidding and the bidders were not entitled to proceed only on the
basis indicative information given by the Bid Process Coordinator.
                                                                              H
22      SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A    32. We have considered the submission of the petitioner and
     respondent. As against the indicative cost of 92.40 crore, the
     cost for the construction of water system for the new location is
        244 crore out of the aforesaid amount, a sum of 185 crore
     has already been incurred and balance of 59 crore is to be
     spent. The estimated increase in cost of the water intake system
B
     due to the change in location of the water intake system is 152
     crore. The petitioner has submitted that since this increase is
     directly attributable to the error in the WAPCOS report provided
     to the bidders at the pre-bid stage, the petitioner is required to be
     compensated for the same.
C    33. In our view, the claim is not covered under any of the provisions
     of Article 13.1.1 of the PPA. The petitioner being aware that the
     cost of water intake system being indicative in nature and being
     not covered under the “Change in Law” under Article 13 should
     have informed itself fully with the actual site conditions before
D    preparing the bid and accordingly factored the possible estimates
     of water intake system while quoting the bid instead of relying on
     the indicative cost. In this connection, para 2.7.2.1 of the RfP
     document provides as under:
        “2.7.2.1 The Bidder shall make independent enquiry and satisfy
E       itself with respect to all the required information, inputs,
        conditions and circumstances and factors that may have any
        effect on his Bid. In assessing the Bid, it is deemed that the
        Bidder has inspected and examined the site conditions of roads,
        bridges, ports etc. for unloading and/or transporting heavy pieces
        of material and has based its design, equipment size and fixed
F       its price taking into account all such relevant conditions and
        also the risks, contingencies and other circumstances which
        may influence or affect supply of power.”
     Further para 4 of the RfP document provides that the pricing and
     other details given in the bidding documents are by way of
G    information only and it was for the bidders to conduct independent
     enquiry and verify the details and information. Para 4 are extracted
     as under:
        “4. While the RFP has been prepared in good faith, neither the
        Procurers, Authorised Representative and Power Finance
H       Corporation (PFC) nor their directors or employees or advisors/
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                    23
           LTD. & ORS. [K. M. JOSEPH, J.]

         consultants make any representation or warranty, express or             A
         implied, or accept any responsibility or liability, whatsoever, in
         respect of any statements or omission herein, or the accuracy,
         completeness or reliability of information contained herein, and
         shall incur no liability under any law, statute, rules or regulations
         as to the accuracy, reliability or completeness of this RFP, even
                                                                                 B
         if any loss or damage is caused to the Bidder by any act or
         omission on their part.”
      Therefore, it is the responsibility of the petitioner to verify the
      suitability of the location of water intake and ensure reliable water
      supply for the power plant and workout the relevant approximate
      cost of water intake system independently and factor in the                C
      estimates in the bid so that a realistic cost is reflected in the bid.
      The petitioner having failed to do so, the increase in cost on account
      of this head is not admissible.”
      (14) As far as the question relating to imposition of customs duty
on mining equipment is concerned, the same is dealt with in paragraphs           D
40 and 41.
      “40. We have considered the submission of the petitioner and
      respondents. The Notification No.49/2006 provides as under:
                      Notification No. 49/2006-Customs                           E
      In exercise of the powers conferred by sub-section (1) of Section
      25 of the Customs Act, 1962 (52 of 1962), the Central Government,
      on being satisfied that it is necessary in the public interest so to
      do, hereby makes the following further amendments in the
      notification of the Government of India in the Ministry of Finance         F
      (Department of Revenue) No. 21/2002- Customs, dated the 1st
      March, 2002, which was published in the Gazette of India,
      Extraordinary vide number G.S.R. 118(E), dated the 1st March,
      2002, namely:-
      In the said notification,-
                                                                                 G
         (I) in the Table, against S.No.400, for the entry in column (3),
         the following entry shall be substituted, namely:-
         “Goods required for setting up of any Mega Power Project, so
         certified by an officer not below the rank of a Joint Secretary
                                                                                 H
24      SUPREME COURT REPORTS                               [2023] 8 S.C.R.


A         to the Government of India in the Ministry of Power, that is to
          say-
          (a) an inter-state thermal power plant of a capacity of 700MW
          or more, located in the States of Jammu and Kashmir, Sikkim,
          Arunachal Pradesh, Assam, Meghalaya, Manipur, Mizoram,
B         Nagaland and Tripura; or
          (b) an inter-state thermal power plant of a capacity of 1000MW
          or more, located in States other than those specified in clause
          (a) above; or
          (c) an inter-state hydel power plant of a capacity of 350MW
C         or more, located in the States of Jammu and Kashmir, Sikkim,
          Arunachal Pradesh, Assam, Meghalaya, Manipur, Mizoram,
          Nagaland and Tripura; or
          (d) an inter-state hydel power plant of a capacity of 500MW
          or more, located in States other than those specified in clause
          (c) above”;
D
          (II) in the Annexure, in Condition No. 86, for sub-clauses (ii)
          and (iii) of clause (a), the following shall be substituted, namely:-
          “(ii) the power purchasing State undertakes, in principle, to
          privatize distribution in all cities, in that State, each of which
          has a population of more than one million, within a period to be
E         fixed by the Ministry of Power.”.
                               [F.No.354/104/2003-TRU]
     It is noticed that the revised policy guidelines issued by Government
     of India, Ministry of Power vide its letter No. A-118/2003-IPC
     dated 2.8.2006 has stated that an inter-State thermal power plant
F    of a capacity of 1000 MW or more is eligible for grant of mega
     power status. It further states as under:
          “Zero Customs Duty: In terms of the notification of the
          Government of India in the Ministry of Finance (Department
          of Revenue) No. 21/2002-Customs dated 1.3.2002 read
G         together with No. 49/2006-Customs dated 26.5.2006, the import
          of capital equipment would be free of customs duty for these
          projects.”
     41. It is to be considered whether under the notification as stated
     above, mining equipments were exempted from customs duty.
     General Exemption No.122 under the Customs Notification No.21/
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                  25
           LTD. & ORS. [K. M. JOSEPH, J.]

      2002 as amended from time to time contains the list of items which       A
      are exempted from customs duty. It is observed that Notification
      21 of 2002-Customs clearly demarcates the power projects and
      mining projects separately. It is seen that at Ser No.399 of the list,
      coal mining projects are liable to pay customs duty. Ser No. 400
      only exempts the mega power project from payment of customs
                                                                               B
      duty and there is no mention that it includes captive power plants.
      Therefore, it cannot be said that as on the cut-off date, there was
      exemption on mining equipment and the petitioner had taken into
      consideration such exemption while quoting the bids. Nothing has
      been produced in the petition which could indicate that any such
      impression was given by the procurers or their representative prior      C
      to bidding. In view of the foregoing discussion, the submission of
      the petitioner that the decision of the Ministry of Power detailed
      in its office memorandum dated 17.06.2011 and refusal by Energy
      Department, Government of Madhya Pradesh to provide
      recommendation letter to import mining equipments for Sasan
                                                                               D
      UMPP under nil custom duty amounts to a “Change in Law”
      under Article 13.1 of the PPA and the petitioner is entitled to be
      compensated for the same is not acceptable and hence no
      compensation would be available in this regard.”
      THE APPEAL BEFORE THE TRIBUNAL
      (15) This led to the appeal being filed by the first respondent under    E
Section 111 of the Act. It is apposite that we set out the exact case
which has been set up by the first respondent before the Tribunal.
      “9.5 The Report identified the water intake pump house location
      and pipeline route from the intake pump house to the power plant
      in its report. This report was made available to all the bidders         F
      before bid submission so that the bidders could factor in the cost
      of water intake system in preparation of their financial bids i.e.,
      the tariff at which power be supplied to the Procurers. The total
      cost for the construction of water intake system for the location
      and route of indicated in the report by WAPCOS was estimated
                                                                               G
      to be Rs.92 Crores. The water intake system is an integral part of
      the Project without with it is not possible to set up and operate the
      Project. The WAPCOS report along with estimated cost are
      annexed herewith and marked as Annexure A-14.
      9.6 After RPower was declared the successful bidder and the
      Appellant Company was transferred to RPower, WAPCOS was                  H
26      SUPREME COURT REPORTS                             [2023] 8 S.C.R.


A    re-appointed to confirm the technical feasibility as part of the
     detailed engineering exercise. During this process, it emerged that
     the water intake location as finalized by WAPCOS vide its earlier
     report prepared for PFC/ Procurers and made available to all
     bidders prior to bid submission was not an appropriate location
     and does not ensure reliable supply of water to the power plant. It
B
     also emerged that the water intake at the original location indicated
     by WAPCOS in the pre-bid report would have resulted in
     shutdown of the power plant for a considerable period in a year
     during the lean season. Therefore, WAPCOS recommended a
     new location for water intake, which was 23 km from the power
C    plant as against the 12.5 kms initially indicated at the time of bidding
     (original location). It was highlighted that the new location would
     ensure reliable water supply to the power plant. Due to increase
     in the distance, submergence area along the route and construction
     time, there has been considerable increase in the cost of water
     intake system due to change in location as detailed below. The
D
     report of WAPCOS recommending the revised location is annexed
     herewith and marked as Annexure A-15.
     9.7 It is submitted that due to the change in location, cost for
     water intake system has increased on following counts:
     (a) While the route length itself increased to 23 kms, the increase
E    in piping length increased from 24 km (2 Pipe Lines each of 12
     Kms) to 59.5 km (2 Pipe Lines each of 8 km & 3 Pipes each of
     14.5 km)
     (b) Increased cost due to deeper Pump House.
     (c) Additional dredging for creation of intake channel for the
F    offshore pump house.
     (d) Additional cost due to HT transmission line.
     There has been considerable increase of approximately Rs.176
     Crores in cost of the water intake system, which now is estimated
     to be approximately Rs.268 Crores. The cost break-up for the
G    new location for the water intake system is annexed herewith
     and marked as Annexure A-16.
     9.8 It is submitted that the increase in cost of the water intake
     system is on account of the errors in the report provided by the
     Procurers and therefore, the Procurers are required to compensate
H    the Appellant for the difference in cost.
HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                27
          LTD. & ORS. [K. M. JOSEPH, J.]

   9.9 It is further submitted that since the water pipeline corridor is    A
   part of the Land for the Power Station and the water intake pipeline
   is an integral part of the Power Station, any change in the indicative
   cost of the water intake system is covered under Change in Law
   in terms of Article 13 of the PPA since it amounts to change in
   cost of land of the Project. In fact, the Ld. General Commission
                                                                            B
   has noted in the impugned Order that the estimate for Declared
   Price of Land for the Power Station includes the Water Intake
   System. The operative part of the Impugned Order is reproduced
   below:
   “19. Change in the declared price of land is covered under “Change
   in Law”. The procurers have also agreed that this item of                C
   expenditure is admissible under “Change in Law”. The declared
   price of land for the Power Station was stated to be 190.677
   crore. This has been verified from the communication dated
   23.10.2006 from the representative of the procurers to the bidders.
   This included the power plant area, the fuel transport system land,      D
   the water pipeline corridor and the ash pipeline corridor.”
   9.11 It is submitted that pre-bid site visit and project reports were
   prepared and made available by Authorized Representative
   (Power Finance Corporation) to all bidders. The disclaimer, if at
   all applicable, will only apply to such instances where the bidders
   were able to identify any issues or liability with reasonable            E
   diligence. Based on the information and material provided, there
   was no indication that the water intake system proposed in the
   WAPCOS Report was unfeasible. Therefore, the disclaimer does
   not absolve the Procurers of their liability to compensate the
   Appellant for the increase in cost. It is submitted that due to the      F
   error in WAPCOS’s report, the Appellant is faced with an additional
   burden of Rs.176 Crore which has adversely impacted the project
   economics. It is submitted that the disclaimers contained in Para
   2.7.2.1 and Para 4 of the RFQ ought not to be considered absolute
   in nature so as to prevent loading of costs which are incurred by
   the Appellant as a direct result of omission or error on part of the     G
   Procurers in providing information during the pre-bid stage. This
   approach is counter-intuitive to ensuring that the Appellants Project
   is able to supply cheap and affordable power to over 42 million
   consumers in the Procurer States. It is further submitted that the
   disclaimers cannot act as an absolute bar to the liability of the        H
28             SUPREME COURT REPORTS                          [2023] 8 S.C.R.


A           Procurers. Any duty to independently verify inputs, information
            factors etc. require only a reasonable duty of care. The grave
            technical deficiencies and huge differences between actual cost
            and estimates provided to the bidders defeat the fundamental
            objective of providing information to the bidders especially when
            the nature of expense in this case was of buying a report from a
B
            Government Company which had carried out a detailed study.
            The Appellant had no other option but to rely on the information
            provided by the authorized representative of the Procurers.
            Therefore, Ld. Commission’s reliance on the disclaimers contained
            in the bid documents to reject the claim of the Appellant is not
C           sustainable.”
            (16) In regard to the complaint about the notification issued by the
     Joint Secretary in the Ministry of Power having brought about a change
     in law, we find the following complaint, inter alia:
            “9.20. It is submitted that as per Notification 21 of 2022- Customs
D           dated 01.03.2002 issued by the Ministry of Finance, Government
            of India, the customs duty on goods required for setting up mega
            projects has been prescribed as nil meaning thereby that no customs
            duty will be levied on goods imported for setting up a mega power
            project. Notification 21/2022- Customs which provides as under:
E          “




F




G

           9.22 It is submitted that captive Coal Blocks being an integral part
           of the Project, the mining equipment would be covered under this
           provision as well. It is submitted that RFP clearly stated that
           Procurers through the Appellant (which was a wholly-owned
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                   29
           LTD. & ORS. [K. M. JOSEPH, J.]

      subsidiary of PFC at that time) will procure a certificate from the       A
      Ministry of Power that the benefits of the Mega Power Policy
      would be extended to the Project till scheduled Commercial
      Operations Date of the Power Station. As per definition, Project
      includes captive mine and hence, it was Procurer’s obligation to
      provide for the exemption to the coal mining equipment.
                                                                                B
      9.24 It may also noted that:-
                    Xxx                xxx                xxx
      (b) PPA defines Project as power plant along with captive coal
      mines.
                                                                                C
      9.35 It is submitted that the Appellant has set up an ultra-mega
      power project which comprises of captive coal mines. It is not
      separately indulging in mining activities. Moreover, the coal from
      the Project is being used only for the Project. The entire capital
      cost of the power project includes the cost of the coal mines. This
      is also evident from Article 13 of the PPA where increase in cost         D
      of land and R&R expenditure for the coal mines is included as
      change in law. Therefore, the finding that the captive coal mines
      are a separate activity and will fall under Serial No. 399 is incorrect
      and ought to be set aside.
      FINDINGS OF THE TRIBUNAL                                                  E
      (17) As far as the complaint about the increased costs on account
of change in water intake system, the following is the finding of the
Tribunal.
      “12.4 After due consideration of the rival contentions of both the
                                                                                F
      parties, what emerges is that after being declared as the successful
      bidder, the SPL with a view to affirm the technical suitability of
      the preliminary report of the WAPCOS on Water Intake System,
      re-engaged the same agency for finalization of the said report. It
      is not in dispute that the Consultant, WAPCOS reviewed its earlier
      report and came to a conclusion that the earlier location of Water        G
      Intake was not at proper place and would result in non-availability
      of water for the plant during lean period. It is relevant to note that
      based on the recommendations of WAPCOS, SPL decided to go
      ahead for selection of new location as recommended and got
      carried out the requisite design and engineering of the entire Water
                                                                                H
30      SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A    Intake System which resulted into longer piping system, increased
     submergence area along the route, additional construction period
     etc.. On account of these factors, the cost of Water Intake System
     went up by over Rs.176 crores. The learned counsel appearing
     for the Appellant pointed out that the judgment of this Tribunal in
     Nabha Power case is not applicable to the present case since no
B
     cost relating to seismic zone data was provided to Nabha whereas
     in the instant case, costs were provided to the bidders. The
     Appellant has further reiterated that para 2.7.2.1 and para 4 of
     RFP which were relied upon by the Respondent procurers cannot
     be taken as obsolute in nature so as to absolve procurers of their
C    responsibility for providing grossly incorrect information leading
     to substantial increase in cost of Water Intake System.
     12.5 After thoughtful consideration of the submissions made by
     the learned counsel for the Appellant and the Respondents and
     the findings of the Central Commission, we find that while the
D    responsibility of carrying out due diligence before bidding and
     verifying the correctness of information provided in the bid
     documents rested with the bidders, at the same time, Respondent
     procurers cannot justify providing grossly erroneous report on
     Water Intake System taking shelter under the disclaimer in the
     bid document. As a matter of fact, the water availability for a
E    thermal power station of this magnitude on regular, reliable and
     uninterrupted basis is essential and is a vital input for successful
     operation of the plant. It is noticed that the report of WAPCOS
     supplied to bidders at the time of bidding was deficient in ensuring
     adequate water supplies throughout the year uninterrupted and if
F    the same would have been taken for construction and
     implementation, the same could have resulted into huge loss to
     the Respondent procurers being deprived of power supply for
     some period of the year due to less/ non-availability of water during
     the lean period. It is not in dispute that Sasan UMPP is supplying
     power to the Respondent procurer at one of the most competitive
G    tariff in the country. It is noted from the contentions of the
     Respondent procurers that such an issue has not been dealt with
     either in the PPA or in the competitive bidding guidelines issued
     by Ministry of Power under Section 63 of the Act, however, in
     view of the criticality of such situation, we opine that the matter
H    needs afresh re-look for suitable redressal. While the Central
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                31
           LTD. & ORS. [K. M. JOSEPH, J.]

     Commission has correctly concluded that it does not qualify as          A
     change in law under Articles 13.1.1 of the PPA, it, however, needs
     to be addressed on the basis of settled principles of law and equity
     also, in the light of the Hon’ble Supreme Court findings in its
     judgment at Para 19 in Energy Watchdog vs. CERC dated
     11.04.2017. Thus, we are of the considered view that this issue
                                                                             B
     involving substantial additional expenditure basically arising out of
     erroneous report of the consultants needs to be re-examined afresh
     by the Central Commission. Hence, this issue is answered in favour
     of the Appellant.”
      (18) In regard to the complaint relating to the O.M. dated
17.06.2011 forming change in law, we note the following findings:            C

     “14.5 We have considered the submissions of the learned counsel
     for the Appellant and learned counsel for the Respondents along
     with the consideration of the Central Commission on this issue
     pertaining to the claims of the Appellant regarding compensation
     on account of additional payment towards custom duty on mining          D
     equipment. After careful consideration and critical evaluation of
     the same, the key question arises for consideration, whether the
     equipment required for captive coal mines allocated to UMPP
     should be considered at par with the equipment required for setting
     up the power plants as far as exemption from the custom duty is         E
     concerned. The contention of the Appellant that the captive coal
     mines allocated to Sasan UMPP are integral & essential part of
     the project as a whole and as such, the exemption of custom duty
     was applicable to all equipments being imported for the entire
     project i.e. captive coal mines as well as power plants. It is not in
     dispute that the captive coal mines were allotted for UMPP for its      F
     exclusive use for power generation and in no way, meant for
     commercial utilization elsewhere.
     14.6 In this regard, we also take the note of Hon’ble Supreme
     Court directions in judgment dated 24.08.2014 in Manohar Lal
     Sharma Vs. Principal Secy., in W.P.(CRL) 120 of 2012 (Para              G
     158) that coal from captive coal mines is to be used for UMPP
     alone and no diversion of coal for commercial exploitation would
     be permitted. Keeping these facts in view, we notice the glowing
     difference between an independent coal mines up for exploitation
     and selling coal on commercial lines and a captive coal mine set        H
32            SUPREME COURT REPORTS                          [2023] 8 S.C.R.


A          up to meet requirement of UMPP only to generate power for the
           ultimate benefit of the Respondent procurers and in turn, consumers
           for obtaining electricity at cheaper rates. The actual positions
           purported the assumption made by the Appellant that the customs
           duty exemptions will be available for import of the equipment for
           the entire project including captive mines and power plants. We
B
           find force in the argument of the learned counsel for the Appellant
           that being the integral and inseparable part of the UMPP, the
           custom duty rates applicable for stand alone coal mining projects
           would not be applicable in the present case and the exemption
           would need to be given effect to. We, thus opine that the Central
C          Commission appears to have been mechanically guided by the
           mere description of the relevant entry (Sl.No.399 & 400) in the
           said custom duty notifications and has not appreciated that the
           captive coal mines being integral part of the UMPP cannot be
           equated to a stand alone coal mines, having commercial line of
           utilization. The Appellant was thus right in assuming that Custom
D
           Duty exemption will be available for the coal mining equipments.
           As such, this issue needs to be examined afresh in accordance
           with law and various provisions of the RFQ/RFP/PPA. Therefore,
           we answer this issue in favour of the Appellant.”
            (19) On the basis of the aforesaid findings, the Tribunal remanded
E    the matter back to the Commission. We may also notice the sequel to
     the impugned judgment. Pursuant to the remand, the Commission
     reconsidered the matter in regard to the water intake. The Commission
     ordered payment of sum of Rs.176 crores. As far as the claim for
     compensation on the basis that the issuance of the office memorandum
F    by the Joint Secretary in the Ministry of Power having brought about a
     change in law, it was found that the goods in question had been imported
     not by the first respondent but by its parent company. This, in turn, has
     triggered two sets of appeals again before the Tribunal and they are still
     pending. Their fate, undoubtedly, will depend upon the decision which
     we will be rendering in these cases.
G
           (20) We have heard Mr. P. Chidambaram, Mr. Dhruv Mehta, Mr.
     Rana Mukherjee, Mr. M. G. Ramachandran, Mr. G. Umapathy, learned
     senior counsel, assisted by Mr. Nikunj Dayal and Ms. Pallavi Sehgal.
     We have also heard Mr. Shubham Arya, learned counsel appearing on
     behalf of the appellant in one of the appeals. On the other hand, we also
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                    33
           LTD. & ORS. [K. M. JOSEPH, J.]

heard Mr. Sajjan Poovayya, learned senior counsel assisted by Mr. Rahul          A
Kinra, learned counsel and Mr. Amit Kapoor, learned counsel.
       SUBMISSION OF APPELLANTS
       (21) Shri P. Chidambaram, learned senior counsel appearing for
the appellant, would submit that the Tribunal has clearly acted in error
and illegally in passing the impugned order.                                     B

        (22) He would submit that as far as the finding given by the Tribunal
in regard to the water intake system being located at a different place, is
concerned, the Tribunal agreed with the Commission that there was no
change in law. Once, it was found that there was no change in law, there
is no power with the Tribunal to do what it did. The PPA signifies an            C
agreement between the parties. The PPA goes into meticulous details.
It follows an internationally competitive bidding and the obligations of
the parties have been carved out and articulated with great care. Once
the party, viz., the first respondent went to the Commission complaining
that there is a change in law and it was found that there is no change in        D
law, there ended the jurisdiction of the Tribunal. Instead of terminating
the lis, the Tribunal has clearly strayed outside its jurisdiction in granting
relief on the basis that report of WAPCOS was grossly erroneous. In
this regard, he enlisted in support of his contention, various clauses which
unambiguously disclaimed any liability with the procurers on account of
any inaccuracies which may be reflected in the WAPCOS report. A                  E
report submitted by WAPCOS which is a public sector body was only
by way of providing information. The bidders were provided with the
report well before they decided to put in their bids. Having regard to the
various disclaimer clauses, it did not lie in their mouth to thereafter seek
to construct a case based on the report being erroneous. In this regard,         F
it is pointed out that the clauses clearly indicate that the bidder was to
satisfy itself by conducting a study of the site. Nothing prevented the
first respondent from carrying out inspection of the site and verifying for
itself the information which was provided through the report of the
WAPCOS.
                                                                                 G
       (23) Mr. P. Chidambaram, learned senior counsel, further pointed
out that a perusal of the second WAPCOS report, which is the sole basis
for the huge claim raised by the first respondent, would show that the
second report does not, in any manner, rubbish the first report. It is not in
dispute, it is pointed out, that the procurers were in no way associated
                                                                                 H
34             SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A    with the carrying out of the second WAPCOS report. Unilaterally, the
     first respondent without any basis gets the second report commissioned
     and it is on the said basis alone that the claim was made and what is
     more, allowed by the Tribunal. This is clearly impermissible. As regards
     the claim for compensation alleging change in law brought about by the
     Office Memorandum issued by the Joint Secretary is concerned, in the
B
     first place, it is pointed out that the proper thing for the first respondent
     to do would have been to take up the matter with the Department and
     claim a refund and he would submit it is strange instead of doing that the
     burden is sought to be passed on to the procurers and which, in turn,
     would necessarily be passed on to the ultimate consumers.
C           (24) Further, it is pointed out that the Tribunal has actually
     proceeded to take into consideration the earlier notifications which
     prevailed at the time of the cut off date with reference to which alone
     change in law is projected. Thereafter, it has come to the conclusion that
     for the goods imported from abroad for the purpose of the captive mines,
D    there was an exemption. Such an inquiry itself could not have been
     done. In other words, it is not a case where the first respondent had
     indisputable material on hand which established unambiguously that there
     was a change in law. This is for the reason that there is no material to
     establish that prior to the cut off date, the goods which are the subject
     matter of dispute, were exempt under the notification. On the other hand,
E    our attention is drawn to the decision of the Advance ruling authority
     which has gone into the issue and found that goods in question were not
     exempt. In fact, it is the contention of the appellants that the office
     memorandum issued by the Joint Secretary, Ministry of Power, merely
     follows the advance ruling.
F           (25) Another argument which is raised in this regard is that the
     Joint Secretary in the Ministry of Power is not the final Governmental
     authority within the meaning of clause 13.1.1. What we are concerned
     with is notification issued under Section 25 of the Customs Act. It is not
     as if any authority which is competent within the meaning of Article
G    13.1.1 has issued a notification or even an interpretation within the
     meaning of the said article which has resulted in a change in law within
     the meaning of Article 13.1.1.
            (26) We have also heard Shri Dhruv Mehta, as we have already
     stated. We have heard the other senior counsel who have essentially
H    adopted the arguments which have been addressed by Mr.
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                    35
           LTD. & ORS. [K. M. JOSEPH, J.]

P.Chidambaram, learned senior counsel, and they are one in contending            A
that the Tribunal has strayed outside the contours of its jurisdiction and
this has resulted in an order which is clearly illegal and erroneous.
       SUBMISSIONS OF THE FIRST RESPONDENT
        (27) Per contra, Mr. Sajjan Poovayya, learned senior counsel
for the first respondent, took us through the other side of the picture and      B
projected a totally different scenario. He would point out, in the first
place, that the Court may not view the PPA in question as an ordinary
contract. He pointed out that what is at stake is the interpretation to be
placed on a long term power procurement contract. It is not as if in such
a contract, the matters are fixed with reference to the point of time            C
when the contract is entered into. It is not cast in stone, in other words.
It is open to change. More appropriately, it is open to regulation. We are
invited to consider that the Act represents a paradigm shift from the
previous regime under which the price of power was fixed essentially at
the whims and caprice of the State Electricity Boards. There was a
stagnation in the production and supply of power. It is realising the need       D
for increasing private participation in the generation of power that the
Act was enacted in the year 2003. Being the subject matter of regulations
means that tariff was open to be revisited from time to time. It is precisely
this regime which is reflected by Section 79 of the Act. It is further
pointed out that the complaint of the appellants regarding the Tribunal in       E
regard to the water intake system despite agreeing with the Commission
that there was no change in law rendering the findings it did and therefore,
being unsustainable, the Court may consider that in fact there was a
change in law. This argument is sought to be buttressed with reference
to the provisions of clause (iii) of Article 13.1.1. It is contended, in other
words, that a perusal of the various clauses of the PPA would show that          F
the procurers (the appellants) were obliged under the contract to provide
initial consent. One of the initial consents related to the water linkage for
the project. He would submit that in view of the provisions of Schedule
II to the PPA the initial consent also consisted of carrying out the task of
making available land for the power plant and for the laying of the pipeline.    G
Since as it turned out and as supported by the second report of the
WAPCOS, there was clearly insufficient availability of water at the site
supported by the first report, the first respondent was compelled to take
water from a distant point of the reservoir in question. This led to the
colossal increase in the expenditure towards laying of the pipeline inter
alia. This constituted, therefore, a change in law.                              H
36            SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A           (28) As far as the contention based on the disclaimer clauses
     which are relied upon by the appellant is concerned, it is pointed out that
     the width of the disclaimer clause could not be stretched to the point that
     is canvassed by the appellants. We are dealing with a case where a
     public sector unit viz., WAPCOS has given its report. Not unnaturally,
     the first respondent relied upon the same. It is factored in its price and
B
     once it is found that the report was entirely fallacious, no shelter can be
     sought by the appellants under the disclaimer clauses. Our attention was
     drawn to various judgments. They include Energy Watchdog v. Central
     Electricity Regulatory Commission and Others (2017) 14 SCC 80,
     Uttar Haryana Bijli Vitran Nigam Ltd. &Anr. v. Adani Power Limited
C    &Ors. (2019) 5 SCC 325, Gujarat Urja Vikas Nigam Ltd. v. Essar
     Power (2008) 4 SCC 755, Skandia Insurance Co. Ltd. v. Kokilaben
     Chandravan & Ors. (1987) 2 SCC 654, DLF Universal Limited v.
     Director, Town and Country Planning Department, Haryana (2010)
     14 SCC 1 and Sumitomo Heavy Industries v. Oil and Natural Gas
     Commission of India (2010) 11 SCC 296, Nabha Power Limited v.
D
     PSPCL (2018) 11 SCC 508.
            (29) The respondents have also relied upon the judgments of this
     Court which are detailed hereinafter essentially for the proposition that
     there is power under Order XLI Rule 22 and Rule 33:Prahlad&Ors. v.
     State of Maharashtra &Anr. (2010) 10 SCC 458, State of Punjab
E    &Ors. v. Bakshish Singh (1998) 8 SCC 222, Mahant Dhangir & Anr.
     v. Madan Mohan &Ors. (1987) (Supp) SCC 528.
            (30) It is contended by Mr. Sajjan Povayya, learned senior counsel
     that there is indeed power, at any rate, under the provisions of Section
     79(1)(b) of the Act to revisit the fixation of tariff de hors even the
F    specific relief which is contemplated under the contract. In this regard,
     emphasis is laid on the fact that clauses 4.7 and 5.1.17 of the guidelines
     came to be amended and it is the amended guidelines which apply to the
     facts of the case. That it is the amended guidelines which were applied
     can be perceived from the fact that the amended guidelines are seen
G    reflected in the PPA. The amended provisions are found in 17.3.1 and
     13.1.1
          (31) Amended Guideline 4.7 is reflected in 13.1.1 whereas
     amended guideline 5.17 is reflected in Article 17.3.1.
           (32) With regard to 17.3.1, it is pointed out that a reading of the
H    same, in particular, the opening limb of the provision would show that
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                    37
           LTD. & ORS. [K. M. JOSEPH, J.]

there is clearly general power for the purpose of changing determiningor         A
increasing the tariff. It is sought to be contrasted with specific instances
which would notify the jurisdiction of the Commission which included
Article 13.1 which deals with change in law. In other words, the contention
is that de hors a change in law, it becomes the duty of the Commission
and the Tribunal and of this Court to factor in the need to arm the Tribunal
                                                                                 B
and the Commission with ample power in the interest of justice, to deal
with situations which call out for a fair and equitable treatment to be
meted out to the private player as well in a long term contract.
       (33) Mr. Amit Kapoor, learned counsel, who supplemented the
submissions of Mr. Sajjan Poovayya, learned senior counsel, would draw
our attention to Section 61 of the Act. He would submit that Section 61          C
read with Sections 63 to 79(b) provided a statutory framework which
enabled the Commission to devise an equitable tariff even in a PPA
governed scenario having regard to the very nature of the services
involved and the changed system evolved under the Act.
        (34) Mr. Amit Kapoor, learned counsel, laid stress on the principle      D
of contra proferentem. He would point out along with Mr. Sajjan Poovyya,
learned senior counsel, that the Court must not be oblivious of the fact
that this case represents a case 2 scenario under the RFP. This means
that unlike a situation where the contractor is free to choose the site and
the other facilities, in a case 2 situation which is the situation prevailing    E
in this case,everything is dictated to by the employer viz., SPV. Expatiating
the said point, it is pointed out that the bidders did not have a control over
the water source from which water had to be taken. In other words, the
water could not have been sourced from any other water body. This
aspect is relevant for the purpose of considering the free play with the
Commission in the matter of fixing tariff based on a situation which was         F
created as are exemplified by two grounds which have been made out
and which are the subject matter of the appeals. Another point which is
projected is that in regard to geological matters, the bidders were warned
that they would have to on their own make an assessment. But such a
caveat was not entered with regard to pertinently the hydrological               G
conditions. Since water intake system related to hydrology, it is not open
to the appellants to ward off a just fixation of tariff based on the discovery
of the fact that the first WAPCOS report was highly flawed. We are
reminded that it was of the greatest importance for the first respondent
that it ran the power plant on a yearly basis. The second report of the
WAPCOS would clearly indicate that if the appellant had to take water            H
38             SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A    in terms of the first WAPCOS report, during the lean months, the first
     respondent would not get sufficient water supply to operate the plant. If
     such an eventuality had taken place, the result would be that the procurers
     would end up paying the charges towards capacity charge even though,
     it would not get power. The appellants would be compelled to buy power
     from outside and finally the end consumer would have to bear the brunt
B
     of the loss. It is to avoid all this that the first respondent has acted in a
     manner which was not only in tune with its best interest but also ensuring
     that the procurers and finally the consumers were best protected. It is
     further pointed out by the learned counsel that the Court must bear in
     mind that the contract in question permits the passing of the benefit not
C    only to the contractor but also to the employer viz., the appellants. In
     other words, if it was a case where the first respondent were to be
     found to be making an unjust enrichment under the regulatory mechanism,
     the appellants could have moved the Commission for bringing down the
     rates. Therefore, the regulatory mechanism is meant to work both ways,
     in both directions and the Court must bear in mind the unique nature of a
D
     regulated contract.
             (35) Shri Amit Kapoor also referred to the theory of incomplete
     contracts. This is explained as meaning that being a long term contact,
     the parties may not expect and factor in all possible developments which
     may take place. This also necessitates the Commission being endowed
E    with sufficient power to reach the contractor as also the employer a just
     tariff bearing in mind the regime under Section 61 of the Act.
            (36) Upon being queried as to what would be the position at law
     outside of the PPA and of the jurisdiction of the Commission and if the
     matter were to be considered with reference to the law of contract, Shri
F    Amit Kapoor drew our attention to Sections 18 and 19 of the Indian
     Contract Act, 1872. He would point out that even an innocent
     representation within the meaning of Section 18 can result in the contact
     becoming voidable under Section 19. Section 19 contemplates that the
     party whose consent is obtained by misrepresentation within the meaning
G    of Section 18 can insist upon the other side to perform the contact. But
     the wronged party retained the right to insist that it shall be put in the
     same position it would have occupied if there was no misrepresentation.
     Therefore, it is pointed out that there is foundation even in the law of
     contract for contending that the Commission armed with its powers under
     Section 79(b) could compensate the contractor in the situation we are
H    concerned with.
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                 39
           LTD. & ORS. [K. M. JOSEPH, J.]

       (37) The judgment of this Court reported in Uttar Pradesh Power        A
Corporation Limited v. National Thermal Power Corporation Limited
and Others (2009) 6 SCC 235 rendered by a Bench of three learned
judges with Justice S. B. Sinha speaking for the Court had occasion to
consider the impact of regulations made purporting to act under the
Electricity Regulatory Commission Act, 1998. In the said judgment, it
                                                                              B
has been inter alia held that there is power under regulation 92, in
particular, to revise the tariff (see para 35 read with 38 and 40)
       (38) Noticing this aspect, when we sought assistance from the
learned counsel. We heard the following submissions. Mr. M. G.
Ramachandran, learned senior counsel, would point out that the
observations relating to the power under Section 92 must be understood        C
as confined to the situation obtaining under Section 61 read with Section
62 of the Act. The said power may not be available when the tariff is
fixed under Section 63 of the Act. When we queried as to whether the
provisions of Section 61 are totally unconnected with Section 63, Mr. M.
G. Ramachandran, learned senior counsel, would submit that Section 61         D
may not be entirely inapplicable. He would submit that particular
provisions of Section 61 may, in fact, apply. They include Section 61(b).
He would submit that even the guidelines issued under Section 63 have
their echo in Section 61 and, therefore, it cannot be said that Section 61
and 63 are strange bedfellows.
                                                                              E
        (39) He would, however, contend that in no circumstances can
the power under regulation 92 of 1999 regulations apply when parties
have after competitive bidding and approval of the tariff under Section
63 become bound by a long term contract under the PPA. In a case
where there is a determination of tariff within the meaning of Section
62, on the other hand, Regulations of 1999 may apply. He would further        F
point out that the power under regulation 92 which provides for reviewing
of tariff and which has been understood as power of revision of tariff as
a whole must be subject to the rider that the revision of tariff can be
done only strictly in accordance with the tariff regulations brought in the
year 2001 and as subsequently, amended from time to time. In fact, he         G
would draw our attention to the Regulations of 2014 which expressly
excludes tariff determination done under Section 63 of the Act from the
ambit of the said regulation. In this regard, Shri Sajjan Povayya, learned
senior counsel, on the other hand, drew our attention to the judgment of
this Court Gujarat Urja Vikas Nigam Limited v. Tarini Infrastructure
                                                                              H
40             SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A    Limited and Others (2016) 8 SCC 743 2022 SCC Online SC 1615 2023
     SCC Online SC 233. He would on the strength of these judgments point
     out that there is regulatory power available even in a case covered by
     Section 63 of the Act.
           ANALYSIS
B           (40) We, in these cases, are concerned only with two issues. As
     we have noticed, the first respondent filed a petition before the
     Commission invoking its power inter alia under Section 79(b). The matter
     relates expressly to the construction period. It is at this point apposite to
     notice the relevant provisions under the PPA.
C          (41) Article 13 deals with change in law. Article 13.1.1. defines
     what a change in law is. It reads as follows:
           “ARTICLE 13: CHANGE IN LAW
                   13.1 Definitions
D                In this Article 13, the following terms shall have the following
           meanings:
                  13.1.1 “Change in Law” means the occurrence of any of
           the following events after the date, which is seven(7) days prior
           to the Bid Deadline:
E          (i) the enactment, bringing into effect, adoption, promulgation,
           amendment, modification or repeal, of any Law or (ii) a change
           in the interpretation of any Law by a Competent Court of Law,
           tribunal or Indian Governmental Instrumentality provided such
           Court of Law, tribunal or Indian Governmental Instrumentality is
F          final authority under law of such interpretation or (iii) change in
           any consents, approvals or licenses available or obtained for the
           Project, otherwise than for default of the Seller, which results in
           any change in any cost of or revenue from the business of selling
           electricity by the Seller to the Procurers under the terms of this
           Agreement, or (iv) any change in the (a) Declared Price of Land
G          for the Project or (b) the cost of implementation of the resettlement
           and rehabilitation package of the land for the Project mentioned
           in RFP or (c) the cost of implementing Environmental Management
           Plan for the Power Station mentioned in the RFP or (d) the cost
           of implementing compensatory afforestation for the Coal Mine,
H          indicated under the RFP and the PPA; but shall not include (i) any
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                    41
           LTD. & ORS. [K. M. JOSEPH, J.]

       change in any withholding tax on income or dividends distributed          A
       to the shareholders of the Seller, or (ii) change in respect of UI
       Charges or frequency intervals by an Appropriate Commission.
             Provided that if Government of India does not extend the
       income tax holiday for power generation projects under Section
       80 IA of the Income Tax Act, upto the Scheduled Commercial                B
       Operation Date of the Power Station, such non-extension shall be
       deemed to be a Change in Law.”
       (42) Article 13.1.2 declares that the Supreme Court or High Court
or a Tribunal or in similar judicial or quasi judicial body in India that has
jurisdiction to adjudicate upon issues relating to the project will be treated   C
as competent Court.
      (43) Article 13.2 provides for the actual application and the
principles for computing the impact of change in law. It reads as follows:
       “13.2 Application and Principles for computing impact of Change
       in Law.                                                                   D
              While determining the consequence of Change in Law under
       this Article 13, the Parties shall have due regard to the principle
       that the purpose of compensating the Party affected by such
       Change in Law, is to restore through Monthly Tariff Payments,
       to the extent contemplated in this Article 13, the affected Party         E
       to the same economic position as if such Change in Law has not
       occurred.
          a) Construction Period
          As a result of any Change in Law, the impact of increase/
                                                                                 F
          decrease of Capital Cost of the Project in the Tariff shall be
          governed by the formula given below:
          For every cumulative increase/decrease of each Rupees Fifty
          crores (Rs.50 crores) in the Capital Cost over the term of this
          Agreement, the increase/decrease in Non Escalable Capacity
          Charges shall be an amount equal to zero point two six seven           G
          (0.267%) of the Non Escalable Capacity Charges.
          Provided that the Seller provides to the Procurers documentary
          proof of such increase/decrease in Capital cost for establishing
          the impact of such Change in Law. In case of Dispute, Article
          17 shall apply.                                                        H
42            SUPREME COURT REPORTS                               [2023] 8 S.C.R.


A             It is clarified that the above mentioned compensation shall be
              payable to either Party, only with effect from the date on
              which the total increase/decrease exceeds amount of Rs. Fifty
              (50)crores.
              b) Operation Period
B              As a result of Change in Law, the compensation for any
              increase/decrease in revenues or cost to the Seller shall be
              determined and effect from such date, as decided by the Central
              Electricity Regulatory Commission whose decision shall be final
              and binding on both the Parties, subject to rights of appeal
C             provided under applicable Law.
              Provided that the above mentioned compensation shall be
              payable only if and for increase/decrease in revenues or cost
              to the seller is in excess of an amount equivalent to 1% of
              Letter of Credit in aggregate for a Contact Year.
D          (44) Article 13.4.2 provides for the manner in which the payment
     for changes in law is to be effected. It reads as follows:
           “13.4.2 The payment for Changes in Law shall be through
           Supplementary Bill as mentioned in Article 11.8. However, in case
           of any change in Tariff by reason of Change in Law, as determined
E          in accordance with this Agreement, the Monthly Invoice to be
           raised by the Seller after such change in Tariff shall appropriately
           reflect the changed Tariff.”
            (45) We may notice the other foundational articles relied upon by
     the first respondent. Article 17 relates to Governing law and Dispute
F    resolution. Article 17.2.1 reads as follows:
           “17.2.1 Either Party is entitled to raise any claim, dispute or
           difference of whatever nature arising under, out of or in connection
           with this Agreement including its existence or validity or termination
           (collectively “Dispute”) by giving a written notice to the other
G          Party, which shall contain:
           (i) a description of the Dispute;
           (ii) the grounds for such Dispute; and
           (iii) all written material in support of its claim.”
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                  43
           LTD. & ORS. [K. M. JOSEPH, J.]

       (46) The further articles which we need not capture contemplate         A
that the claim may be met even with a counter claim and an attempt
should be made to settle the dispute amicably (see Article 17.2.3). Failure
to arrive at a settlement opens the doors of Article 17.3. It is justifiable
as the caption is ‘Dispute Resolution’.
      (47) Article 17.3.1 is the crucial article. It reads: -                  B
      “Where any Dispute arises from a claim made by any Party for
      any change in or determination of the Tariff or any matter related
      to Tariff or claims made by any Partywhich partly or wholly
      relateto any change in the Tariff or determination of any of such
      claims could result in change in the Tariff or (ii) relates to any       C
      matter agreed to be referred to the Appropriate Commission under
      Articles 4.7.1, 13.2, 18.1 or clause 10.1.3 of Schedule l 7 hereof,
      such Dispute shall be submitted to adjudication by the Appropriate
      Commission. Appeal against the decisions of the Appropriate
      Commission shall be made only as per the provisions of the
      Electricity Act, 2003, as amended from time to time.                     D

      The obligations of the Procurers under this Agreement towards
      theSeller shall not be affected in any manner by reason of inter-
      se disputes amongst the Procurers.”
      (48) It is thereafter that as we have noticed, Article 17.3.2 appears    E
which we are not setting out, deals with the settlement of disputes which
are outside the ambit of Article 17.3.1.
       (49) We may at the very beginning notice the change that is brought
about in the guideline. True it is that as we have noticed that the earlier
guidelines which were formulated on 19.01.2005 contemplated a different        F
regime both as regards change in law and also dispute resolution. The
question would however be the extent to which the first respondent can
derive benefit out of the same. As far as Article 13.1.1 is concerned,
clauses 1 and 2 are clearly an inapplicable in regard to the claim based
on the change brought about in the water intake system.
                                                                               G
      (50) It is clause (iii) which is referred to and relied upon by Mr.
Sajjan Povayya. It reads as follows:
      “(iii) change in any consents, approvals or licenses available or
      obtained for the Project, otherwise than for default of the Seller,
      which results in any change in any cost of or revenue from the
                                                                               H
44             SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A          business of selling electricity by the Seller to the Procurersunder
           theterms of this Agreement.”
            (51) It is the case of the first respondent that since in the schedule
     the initial consent which was, in fact, a deemed initial consent consisting
     of performing of the task of making available land for the power plant
B    and for the pipeline and there is a change in the same in view of what
     transpired pursuant to the second report of the WAPCOS, the first
     respondent was entitled to relief. In regard to the said argument, we
     must notice the following obstacles which are indisputable. We notice
     that the pleadings which we have set out, position before the Commission
     and what is more, even before the Tribunal, do not reveal that the first
C    respondent has taken such a stand. No express reference is found to
     Schedule 2 containing the alleged deemed initial consent being overridden
     by the subsequent consent as a foundation for the claim based on change
     in law.
             (52) The second obstacle which we must notice is that we are
D    dealing with an appeal under Section 125 which is based on the existence
     of a substantial question of law. In this regard, indisputably both the
     Commission and the Tribunal have rendered the concurrent finding that
     the first respondent has failed to establish any change in law. Thus, the
     first respondent is up against concurrent findings which we cannot lightly
E    disregard.
            (53) Thirdly, we may notice that the first respondent has not
     independently challenged the finding rendered by the Tribunal holding
     that there is no change in law. We have noticed that the Tribunal has
     proceeded to premise the grant of relief to the first respondent and
F    remanding the matter on a totally different basis. Here, we may notice
     no doubt that treating it as a part of the power of appellate Court to
     correct errors in the findings in the impugned order passed may extend
     in appropriate cases by the principle of Order XLI Rule 22. However,
     objection is seen raised by the Appellants to permitting of the principle in
     Order XLI Rule 22 CPC to govern in the situation such as in an appeal
G    under Section 125 of the Act. We proceed on the basis that there is
     power to permit the respondent to impugn a finding given by the Tribunal
     against the respondent even without filing any appeal or cross petition.
          (54) Examining the claim on merits, we find that the first respondent
     would fail. It is categorically stated in para 68 of the petition that the
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                   45
           LTD. & ORS. [K. M. JOSEPH, J.]

increase in the cost is directly attributable to the error in the WAPCOS        A
report provided to the bidders at the pre-bid stage. It is contended that
the first respondent is required to be compensated for the same.
       (55) In para 108, it is stated that as per the RFP, the procurers had
to provide the water intake study report. As per the said report, the cost
of water intake system was approximately Rs.92 crores. It is further            B
stated in para 110 that there was considerable increase in the cost of
water due to the water intake system. It is stated that it is on account of
errors in the report. It is, however, no doubt, in para 111 stated that since
water pipeline is part of the power station land and the water intake
pipeline is an integral part of the power station, the indicative cost of the
water intake system will be covered by change in law. In the appeal             C
also, we have noticed the stand elaborately.
      (56) Initial consent, has been defined in the PPA as meaning the
consents listed in Schedule 2. Article 5.5 of the PPA reads as follows:
       “5.5 Consents                                                            D
       The Seller shall be responsible for obtaining all Consents (other
       than those required for the Interconnection and Transmission
       Facilities and the Initial Consents) required for developing,
       financing, constructing, operating and maintenance of the Project
       and maintaining/renewing all such Consents in order to carry out         E
       its obligations under this Agreement in general and this Article 5
       in particular and shall supply to the Lead Procurer promptly with
       copies of each application that it submits, and copy/ies of each
       consent/approval/license which it obtains. For the avoidance of
       doubt, it is clarified that the Seller shall also be responsible for
       maintaining/renewing the Initial Consents and for fulfilling all         F
       conditions specified therein.”
        (57) It is true that the procurers were to secure certain initial
consents whereas the vast majority of the consents were to be procured
by the seller. Whatever was to be procured by the procurers apparently
has been described as initial consents. It is also not in dispute that though   G
the word consent is used in Article 13.1.1, the initial consent would also
qualify as consent. The contention of the appellants is that as far as the
initial consent contemplated which was to be performed by the procurers
it was to provide the water linkage. The water linkage consisted of
making available the source of water which consisted of the Govind
                                                                                H
46             SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A    Ballabh Pant Sagar (Rihand Reservoir). There has been no change in
     the said consent. It is not a case of the first respondent, in other words,
     that the first respondent has been forced to take water from any other
     water source. In this regard by communication dated 23.10.2006, we
     find the following:
B          “6. Reference Clause: RFP 1.4(v) – regarding tying up water
           linkage for the Project requirement alongwith approval of Central
           Water Commissioner
           (i) This has already been provided on 12th October, 2006.
           (ii) The water intake study report and Project Report including
C          geo-technical study, topographical survey, area drainage study,
           socio-economic study and EIA (rapid), were provided on 3rd
           August, 2006.”
           (58) While on this document, we may also notice the following in
     regard to the declared price of land contemplated in the RFP under
D    clause 1.4 (ii):
           “2. Reference Clause: RFP 1.4(ii) – regarding Declared Price of
           Land for Power Station
           Indicative Declared Price of Land for Power Station is as follows:
E          (i) Power Plant Area – Rs.110 Crores
           (ii) MGR Land – Rs.80 Crores.
           (iii) Water Pipeline Corridor– Rs.0.63 Crores
           (iv) Ash Pipeline Corridor – Rs.0.047 Crores”
F          (59) There is no dispute regarding this aspect. In this regard, we
     notice that under Schedule 1A to the PPA it has been clearly indicated
     that water source in the project is Govind Ballabh Pant Sagar(Rihand
     Reservoir).
            (60) It is, thereafter, we must notice that under the caption initial
G    consent in Schedule 2, on behalf of the procurers, the SPV was expected
     to issue the notification under Section 6 of the Land Acquisition Act,
     obtain necessarily environmental and forest clearance for the power
     stations, allocate captive coal mines and finally, give the water linkage
     for the reasonable project requirements. It is this water linkage for the
     reasonable project requirements which was contemplated to be fulfilled
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                 47
           LTD. & ORS. [K. M. JOSEPH, J.]

from the water source Govind Ballabh Pant Sagar(Rihand Reservoir).            A
The communication dated 23.10.2006 would indicate that the Central
Water Commission had given its approval for sourcing the water need
from the water body in question. In the said sense, the procurers had
fulfilled their obligation as contemplated in RFP.
        (61) The RFP which preceded the PPA provided for certain              B
conditions which we have already indicated. Clause 1.4 inter alia
contained undertaking for providing the water linkage for the project
with the requisite approval of the Central Water Commission at least 30
days prior to Bid deadline. In the PPA, it is indicated that the procurers
have completed the initial studies as contained in the project report and
obtained initial consent required for the project which are set out in Part   C
I of Schedule 2 and have been made available to the seller on the date of
the PPA except two matters: (1) Forest clearance and the declaration
under Section 6 of the Land Acquisition Act. It is in Part I Schedule 2 of
the PPA stated that the notification under Section 6 of the Land
Acquisition Act was an act to be performed by the procurers. It is this       D
act which was not done initially at the stage of the PPA. Also forest
clearance is mentioned in the Part I of Schedule 2. Even the said
clearance was also apparently not obtained as is indicated at the beginning
of the PPA. Thereafter, Part II of Schedule 2 contains the clause which
is the fountainhead of the argument based on initial consent.
                                                                              E
       (62) It contemplated performing of the task mentioned in Article
3.1.2A also shall be part of the initial consent on their completion within
the time provided. Article 3.1.2A contemplated performance of the task
with which we are concerned viz., making available the land for the
power plant and for the water intake pipeline. This task was to be
performed within a period of eight months from the date of the letter of      F
intent being issued or six months from the PPA whichever is later. It is
true that the task which was to be performed by the procurers in terms
of Article 3.1.2A was performed belatedly by the procurers. In other
words, the time limit was overshot by nearly 18 months. But this delay is
not the basis for the claim based on change in law.                           G
      (63) The question would then arise as to whether the delay in the
performance of the task which has been characterised on its performance
within the time as a deemed initial consent would lead to a change in law
within the meaning of Article 13.1.1. We find that Article 3.3.3 of the
PPA reads as follows:                                                         H
48      SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A    “3.3.3 In case of inability of the Seller to fulfil the conditions
     specified in Article 3.1.2 due to any Force Majeure event, the
     time period for fulfilment of the Condition Subsequent as mentioned
     in Article 3.1.2 and Article 3.1.2A, shall be extended for the period
     of such Force Majeure event, subject to a maximum extension
     period of ten (10) Months, continuous or non-continuous in
B
     aggregate. Thereafter, this Agreement may be terminated by either
     the Procurers (jointly) or the Seller by giving a notice of at least
     seven (7) days, in writing to the other Party.
        Similarly, in case of inability of the Procurers to fulfil the
        conditions specified in Article 3.1.2A due to any Force Majeure
C       event, the time period for fulfillment of the Condition subsequent
        as mentioned in Article 3.1.2 and Article 3.1.2A, shall be
        extended period of ten (10) Months, continuous or non-
        continuous in aggregate. Thereafter, this Agreement may be
        terminated by either the Procurers (jointly) or the Seller by
D       giving a notice of at least seven (7) days, in writing to the other
        Party.”
     (64) We must next notice Article 3.3.3A which follows:
     “3.3.3A In case of inability of the Procurers to perform the activities
     specified in Article 3.1.2A within the time period specified therein,
E    otherwise than for the reasons directly attributable to the Seller or
     Force Majeure event, the Condition Subsequent as mentioned in
     Article 3.1.2 would be extended on a ‘day for day’ basis, equal to
     the additional time which may be required by the Procurers to
     complete the activities mentioned in Article 3.1.2A, subject to a
F    maximum additional time of six (6) Months. Thereafter, this
     Agreement may be terminated by the Seller at its option, by giving
     a notice of at least seven (7) days, in writing to the Procurers. If
     the Seller elects to terminate this Agreement, the Procurers shall,
     within a period of thirty days, purchase the entire shareholding in
     the Seller for the following amount. Provided such purchase of
G    shares shall be undertaken by the Procurers in the ratio of their
     then existing Allocated Contracted Capacity:
        a) total amount of purchase price paid by the Successful Bidder
        to the shareholders of the Seller acquire the equity shares of
        the Seller as per the RFP; plus
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                      49
           LTD. & ORS. [K. M. JOSEPH, J.]

          b) total amount of the Declared Price of Land and Geological             A
          Report (GR) to the extent already paid by the Seller after the
          acquisition of its 100% shareholding by the Selected Bidder;
          plus
          c) an additional sum equal to ten percent (10%) of the sum
          total of the amounts mentioned in sub-clauses (a) and (b).               B
          In addition, the Performance Guarantee of the Seller shall also
          be released forthwith.”
        (65) A perusal of the aforesaid articles would reveal that the parties
have provided for the consequences of failure on the part of the procurers
to make available land as contemplated in Article 3.1.2A. The long and             C
short of it is that if a certain timelimit is crossed by the procurers in the
performance of its obligations in this regard, the seller (the first respondent)
has been given the right to repudiate the contract. What is more, it could
insist on the procurers purchasing the entire share capital of the company
viz., the first respondent as provided therein. It is not the case of the first    D
respondent that by invoking the aforesaid articles, the first respondent
purported to repudiate the contract. On the other hand, it is the common
case that the contract continued to be alive and it has survived subject to
the claims which have been raised thereunder. This would mean that as
the consequences of failure to perform the task having been provided in
the contract in the manner provided, we should not ordinarily tarry further        E
to ask as to whether this would provide the premise for a change in law
as contemplated under Article 13.1.1. We necessarily pose the question
still, whether this would be change in law. Not that we are unmindful of
the fact that the two bodies have concurrently found that there is no
change in law and the attempt is to dislodge such a finding by a side              F
wind in the manner of speaking by an attack lodged by the respondent in
the appeal.This is not a case where the first respondent has made use of
the land for the purpose of laying the pipeline through the corridor as
contemplated and found that drawing water from the water intake system
as contemplated would have resulted in water not being available in
sufficient quantity through the length of the year. There is no such case.         G
      (66) The case of the first respondent, on the other hand, is that
the PPA having been signed on 07.08.2007, in the second week of
December of the very same year-2007, in order to confirm the availability
of water through water intake system as contemplated in the first
                                                                                   H
50             SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A    WAPCOS report, the second report was commissioned ironically through
     the very same consultant. There is no case, whatsoever, that having
     made attempts to draw water in terms of the first WAPCOS report and
     having found that such an effort failed, they were compelled to seek
     recourse to a second study albeit by the same body. No reasons are
     forthcoming as to what inspired the first respondent to commission the
B
     second study. Secondly, this is not a case where the procurers brought
     about any change in law in the study on their own or they persuaded or
     compelled the first respondent to change the corridor for the route for
     laying of the pipeline. The first respondent did not even involve the
     procurers in the second study. There is no intimation given that the first
C    respondent was commissioning a new study. There is no basis forthcoming
     as to what prompted the first respondent to commission a fresh study.
     What is stated is only that it wished to confirm the availability of water in
     terms of the first water intake study. In other words, we must sum up as
     follows:
D           (67) Even in terms of the case built around Part II of Schedule 2
     to the PPA under which the performing of the task mentioned in Article
     3.1.2A within the time provided was to be treated as a deemed initial
     consent, the consequence of failure to do that have been expressly spelt
     out as we have already noticed. At best or at worst, it could have
     empowered the first respondent to rescind the contract. That apart, we
E    are not in a position, for the reasons which we have indicated already, to
     come to the conclusion that it would amount to change in law. While on
     change in law, we may notice another aspect of the matter.
           (68) Article 13.3.1 reads as follows:

F          “13.3.1 If the Seller is affected by a Change in Law in accordance
           with Article 13.2 and wishes to claim a Change in Law under this
           Article, it shall give notice to the Procurers of such Change in
           Law as soon as reasonably practicable after becoming aware of
           the same or should reasonably have known of the Change in Law.”

G          (69) Thus, the PPA contemplates that if the seller is affected by
     change in law and wishes to claim change in law, it has to notify the
     procurers of the change in law as soon as is reasonably practicable after
     becoming aware of the same. It may be true that on the basis of the
     request made by the first respondent apparently based on the second
     WAPCOS report that the first respondent has taken steps for acquiring
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                   51
           LTD. & ORS. [K. M. JOSEPH, J.]

the land needed for laying the pipeline. It may be true that the said           A
pipeline had to cross a greater distance. It is not as if it was on the basis
that the procurers rendered themselves liable in law or held themselves
liable in law to make good the escalation in cost. There is no such material
made available indicating that the procurers have held out that they will
be liable. It is not in dispute that the first unit from the power plant was
                                                                                B
in fact commissioned in August, 2012. In fact, when we asked as to
whether a notice was given in terms of Article 13.3.1, Shri Amit Kapur,
learned counsel, could not point out to any such notice except the notice
which was given on 15.12.2012. In this regard also, we may notice the
contents of the said notice:
       “5.2 Additional expenditure incurred due to change in Declared           C
       Price of Land, cost of implementation of resettlement and
       rehabilitation package of land, change in customs duty on mining
       equipment, water intake system etc.
       (a) the actual expenditure incurred by SPL towards land,
       implementation of resettlement and rehabilitation package of land        D
       for the project, water intakes system, customs duty on mining
       equipment and excise duty on cement and steel.”
      (70) Therein all that is indicated is that for the water intake the
original cost was put Rs.92 crores whereas the estimated cost has been
Rs.238 crores Contemporaneous with the change in law alleged and in             E
keeping with Article 13.3.1, there is no notice brought to our notice.
      (71) No doubt, Shri Amit Kapur, learned counsel for the first
respondent, did attempt to draw inspiration from the Minutes of the
Meeting which took place on 20.03.2013 as per which the lead procurer
appears to have agreed to the change. The case of Mr. Amit Kapur,               F
learned counsel, that the lead procurer can bind the other procurers is
contested by Shri M. G. Ramachandran, learned senior counsel.
       (72) We have noticed that a notice in terms of Article 13.3.1
notifying the change in law as claimed today before the Court was not
given at the relevant time.                                                     G
       (73) The argument that the procurers agreed to the acquisition of
the land through which the new route had to travel also does not appeal
to us as firmly founding the claim of the first respondent in law. The
matter must be viewed from the prism of the specific provisions defining
the change in law and the actual change in law which is as we have              H
52            SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A    explained above. In short, being awarded a contract and having entered
     into the PPA and without any basis as such in facts, the first respondent
     ventured to commission a new study and acting on the same, a new
     pipeline corridor came on the scene. Necessarily the cost may go up.
     But the question we are to decide is as to whether it is change in law and
     we are of the view that it could not be a change in law as contemplated
B
     in the agreement as it is not a change in initial consent which is the only
     case which has been argued in this regard.
            (74) The argument further is only that the estimated cost was
     Rs.92 crores and a further sum in excess of the same had to be spent. In
     this regard, we may notice the following clause in the PPA:
C
           “5.2 The Site
           The Seller acknowledges that, before entering into this Agreement,
           it has had sufficient opportunity to investigate the Site and accepts
           full responsibility for its condition (including but not limited to its
D          geological condition, on the Site, the adequacy of the road and rail
           links to the Site and the availability of adequate supplies of water)
           and agrees that it shall not be relieved from any of its obligations
           under this Agreement or be entitled to any extension of time or
           financial compensation by reason of the unsuitability of the Site
           for whatever reason.
E
           The State Government authorities would be implementing the
           resettlement and rehabilitation package (“R&R”) in respect of
           the Site for the Project, for which the costs is to be borne by the
           Seller. The Procurers shall endeavour to ensure that the State
           Government implements such R&R ensuring that land for different
F          construction activities becomes available in time so as to ensure
           that the Power Station and each Unit is commissioned in a timely
           manner. Assistance of the Seller may be sought, which he will
           provide on best endeavour basis, in execution of those activities
           of the R&R package and as per estimated costs, if execution of
G          such activities is in the interest of expeditious implementation of
           the package and is beneficial to the Project affected persons.”
             (75) Moving on to the findings actually which have been rendered
     by the Tribunal, the Tribunal has, in the impugned order, found that the
     first report of the WAPCOS is grossly erroneous. We are at a loss to
     understand as to what was the basis for rendering such a finding. Without
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                  53
           LTD. & ORS. [K. M. JOSEPH, J.]

any material, it is a little inexplicable as to how the Tribunal could have    A
rendered such a finding which has serious consequences as we have
noticed. This is after finding undoubtedly that there is no change in law.
Virtually, the Tribunal has brushed aside the disclaimer clauses. Before
we go to the disclaimer clauses, we may also indicate that a perusal of
the first WAPCOS report indicates that it is a fairly elaborate report.
                                                                               B
The second WAPCOS report apart from it being prepared without
reference to the procurers as we have noticed does not appear to say
anything which is critical of the first WAPCOS report. At least, there is,
in fact, no express whisper about the first report. All that the second
WAPCOS report seems to indicate is upon being awarded the work,
WAPCOS has gone about preparing another report. At least we are                C
unable to find as to how the Tribunal could on the basis of the second
report find that the first WAPCOS report was grossly erroneous. The
Tribunal has not undertaken a comparative study of the two reports.
There is no discussion whatsoever of the two reports. Nor is there any
other material provided to render such a finding. The only area where
                                                                               D
we find what could perhaps be understood as a reference to the first
report is clause 4.2.2. It reads as follows:
      “4.2.2. As intimated by project authority that and acquisition of
      pipeline corridor on the right side of Vallabhh Pant Sagar is in the
      final stages and other information gathered during site visit by
      WAPCOS/CWPRS team by local enquiry survey area ‘A’ was                   E
      identified for detailed survey during detailed survey it is found
      that sufficient depth is not available for intake well as bed level of
      the reservoir is around 252.5 and this was also in a small patches.
      So, this area is discarded.”
       (76) It would appear that the word ‘project authority’ according        F
to Shri M.G. Ramachandran is to be understood as the first respondent.
All that even clause 4.2.2 indicates is that the first respondent intimated
that the acquisition for the pipeline corridor was in its final stages and
thereafter it is indicated that during the detailed survey, it was found
sufficient depth is not available.                                             G
      (77) We do not think this can be the basis for acting upon the
second report after describing the first report as grossly erroneous.
      (78) Now we may consider the disclaimer clauses. The disclaimers
have their genesis in the guidelines. Note 4 of the RFP indicates that the
procurers apart from their Directors, employees must not be treated as         H
54             SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A    having made any representation or warranting whatsoever in respect of
     any statements or omissions or the accuracy, completeness or reliability
     of information contained therein. They were not to incur any liability
     under any law inter alia even if any loss or damage is caused to the
     bidder by any act or omission on their part. Again clause 1.4 of the RFP
     clearly indicated to the bidders that the procurers inter alia do not make
B
     any representation or accept any responsibility or liability in respect of
     any statements or omissions made in the water intake study report and
     the project report. There is a specific disclaimer also about the accuracy,
     completeness or reliability of information contained therein. This is even
     if any loss or damage is caused to the selected bidder by any act or
C    omission on their part. Thus, in respect of the water intake study report,
     the prospective seller or the bidders were specifically told in no uncertain
     terms that any statements or omissions in water intake study report would
     not result in the procurers being visited with liability even if there was
     loss or damage caused to the selected bidder. This must be borne in
     mind at this juncture for the following reasons.
D
           (79) The first respondent has a case that water intake system
     goes to hydrology whereas in relation to geology, the first respondent
     was duty bound to make its own inquiries. Since the connect between
     hydrology and water intake system is real and since in regard to conditions
     about hydrology, the first respondent relied on the procurers or the report
E    prepared by a public sector unit, in particular, they should stand relieved
     of any obligation to conduct any further inquiry on their own, runs the
     argument.
             (80) We are afraid that this argument cannot hold water as the
     need for making more inquiry in relation to geology cannot relieve the
F    bidder from the operation of other clauses. A just result in the matter of
     what a contract produces by way of a legal relationship must be viewed
     holistically on a harmonious survey of all the relevant clauses. In any
     other approach, the result would have the effect of rendering specific
     clauses dealing with the topic in question dead letter. In view of clause
G    1.4 of the RFP, in other words, the bidder was duty bound if it felt advised
     to check the correctness of the report made by the WAPCOS. It could
     have undertaken its own study. What it did four months after it was
     granted the contract and entered into the PPA, it could have done before
     it decided to make the bid and enter into the PPA. At least we are not
     shown anything which stood in the way of the bidder conducting its own
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                  55
           LTD. & ORS. [K. M. JOSEPH, J.]

study and being convinced by the correctness of the report. We say this        A
for the reason that what is involved is an international competitive bid.
The bidding process is the foundation for the determination of the price
in terms of section 63 of the Act. The Commission approves the rates on
being convinced that the rates are fair and competitive and arrived at on
the basis of a fair bidding process. The provisions of the RFP must,
                                                                               B
therefore, be viewed from the perspective of it placing on alert the bidders
about the imponderables which are inevitably involved in pricing process.
This means that having regard to clause 1.4 of the RFP, no bidder could
possibly come forward with the claim that the contents of the WAPCOS
report must be treated as sacrosanct and infallible and that it should not
be taken without a generous pinch of salt as it stands. At least this was      C
the message which is writ large in the said clause. He who acted
disregarding the caveat about the report acted at his own peril.
       (81) Again, we do notice clause 2.7.2 of the RFP which we have
indicated already. It contemplates the duty on the part of the bidder to
make independent inquiry and to satisfy itself with regard to the required     D
information, inputs, conditions, circumstances, which may affect the bid.
This is apart from the site as referred to in the PPA in clause 5.2 which
we have already referred to.
        (82) With the wealth of disclaimer clauses which we have noticed,
we are unable to subscribe to the reasoning adopted by the Tribunal. We        E
are of the view that the Tribunal was wrong in brushing aside the specific
and unambiguous disclaimers under which the procurers stood exonerated
from liability.
       (83) One argument which we must notice at this stage is the
effect of Article 13.2. We have already adverted to Article 13.2. Article      F
13.2, no doubt, indicates that while determining the consequence of change
in law, the parties shall have due regard to the principle that the purpose
of compensating the party affected by any change in law is to restore
through monthly tariff payments the affected party to the same economic
position as if such change has not occurred. We have tested the hypothesis
by deliberately omitting a crucial part in Article 13.2 which are the words    G
‘to the extent contemplated in this Article 13’. When we read the words
‘to the extent contemplated in this Article 13’ as part of the Article 13.2,
it necessarily brings in clause (a) and (b) of Article 13.2. In other words,
what the parties have contemplated is that consequence of change in
law would result in it being addressed through the mechanism of monthly
                                                                               H
56             SUPREME COURT REPORTS                               [2023] 8 S.C.R.


A    tariff payments through supplementary bills (see Article 13.4.2). But it is
     to the extent as contemplated in Article 13. The question would arise as
     to whether the parties contemplated that it gave authority to the competent
     body viz., the Commission to discard the formula which is provided in
     Article 13.2(a) and (b). We are of the view that what the parties
     contemplated under Article 13.2 was that change in law must be viewed
B
     through the specific provisions of clauses (a) and (b). In other words, a
     change in law may occur during the period of construction. Then it is to
     be treated as falling under Article 13.2(a). A change in law may occur
     during the period of its operation. It would then appear to be dealt with
     under clause (b). If a change in law takes place during the period of
C    construction then its impact is to be measured with reference to the
     capital cost of the project. The word ‘capital cost’ understandably has
     been defined in PPA. A formula has been engrafted. The formula
     contemplates that for every increase/decrease of each Rs.50 crores in
     the capital cost as a result of the change in law, the increase/decrease in
     the non-escalable capacity charges is to be 0.267 per cent of the non-
D
     escalable capacity charges. No doubt, this is if the seller provides to the
     procurers documentary proof of such increase/decrease in establishing
     the impact of such change.
            (84) In other words, the effect of change in law during the
     construction period is captured by 13.2(a). We must understand that this
E    is a meticulously thought through contract which emerged after a long
     rigorous process. Parties were clear about how the change in law had to
     be compensated and methodology has been set out clearly. Therefore,
     any appeal made to the general part in Article 13.2 which speaks about
     the affected party being restored to the same economic condition as if
F    such change in law had not occurred cannot result in departing from the
     specific formula which has been set in place. This meaning is inevitable
     from the words “to the extent contemplated in this Article 13, which
     precedes the general words. In this regard, we may refer to the judgment
     of this Court in Uttar Haryana Bijli Vitran Nigam Ltd. &Anr.1. In the
     said judgment, it has been relied upon understandably by the first
G    respondent also and which also arose under the same clause (Article
     13.2), this Court has held inter alia as follows:
            “10. Article 13.2 is an in-built restitutionary principle which
            compensates the party affected by such change in law and which
     1
      Uttar Haryana Bijli Vitran Nigam Ltd. & Anr. v. Adani Power Limited & Ors. (2019)
H    5 SCC 325
HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                 57
          LTD. & ORS. [K. M. JOSEPH, J.]

   must restore, through monthly tariff payments, the affected party         A
   to the same economic position as if such change in law has not
   occurred. This would mean that by this clause a fiction is created,
   and the party has to be put in the same economic position as if
   such change in law has not occurred i.e. the party must be given
   the benefit of restitution as understood in civil law. Article 13.2,
                                                                             B
   however, goes on to divide such restitution into two separate
   periods. The first period is the “construction period” in which
   increase/decrease of capital cost of the project in the tariff is to
   be governed by a certain formula. However, the seller has to
   provide to the procurer documentary proof of such increase/
   decrease in capital cost for establishing the impact of such change       C
   in law and in the case of dispute as to the same, a dispute resolution
   mechanism as per Article 17 of the PPA is to be resorted to. It is
   also made clear that compensation is only payable to either party
   only with effect from the date on which the total increase/decrease
   exceeds the amount stated therein.
                                                                             D
   13. A reading of Article 13 as a whole, therefore, leads to the
   position that subject to restitutionary principles contained in Article
   13.2, the adjustment in monthly tariff payment, in the facts of the
   present case, has to be from the date of the withdrawal of
   exemption which was done by administrative orders dated 6-4-
   2015 and 16-2-2016. The present case, therefore, falls within Article     E
   13.4.1(i). This being the case, it is clear that the adjustment in
   monthly tariff payment has to be effected from the date on which
   the exemptions given were withdrawn. This being the case,
   monthly invoices to be raised by the seller after such change in
   tariff are to appropriately reflect the changed tariff. On the facts      F
   of the present case, it is clear that the respondents were entitled
   to adjustment in their monthly tariff payment from the date on
   which the exemption notifications became effective. This being
   the case, the restitutionary principle contained in Article 13.2 would
   kick in for the simple reason that it is only after the order dated 4-
   5-2017 [Adani Power Ltd. v. Uttar Haryana Bijli Vitran Nigam              G
   Ltd., 2017 SCC OnLine CERC 66] that CERC held that the
   respondents were entitled to claim added costs on account of
   change in law w.e.f. 1-4-2015. This being the case, it would be
   fallacious to say that the respondents would be claiming this
   restitutionary amount on some general principle of equity outside         H
58             SUPREME COURT REPORTS                             [2023] 8 S.C.R.


A           the PPA. Since it is clear that this amount of carrying cost is only
            relatable to Article 13 of the PPA, we find no reason to interfere
            with the judgment of the Appellate Tribunal.
            19. Lastly, the judgment of this Court in Energy Watchdog v.
            CERC [Energy Watchdog v. CERC, (2017) 14 SCC 80 : (2018) 1
B           SCC (Civ) 133] was also relied upon. In this judgment, three issues
            were set out and decided, one of which was concerned with a
            change in law provision of a PPA. In holding that change in
            Indonesian law would not qualify as a change in law under the
            guidelines read with the PPAs, this Court referred to Clause 13.2
            as follows : (SCC p. 131, para 57)
C
            “57. … This being so, it is clear that so far as the procurement of
            Indian coal is concerned, to the extent that the supply from Coal
            India and other Indian sources is cut down, the PPA read with
            these documents provides in Clause 13.2 that while determining
            the consequences of change in law, parties shall have due regard
D           to the principle that the purpose of compensating the party affected
            by such change in law is to restore, through monthly tariff
            payments, the affected party to the economic position as if such
            change in law has not occurred.”
            There can be no doubt from this judgment that the restitutionary
E           principle contained in Clause 13.2 must always be kept in mind
            even when compensation for increase/decrease in cost is
            determined by CERC.”
                                                             (Emphasis supplied)

F           (85) We are of the view that the view which we have taken does
     not in any way conflict with the view which has been laid down by this
     Court.
            (86) No doubt, in Energy Watchdog2again a judgment which is
     relied upon by both the sides, the Court was dealing with a case under
     the Act and has expressed the following view:
G
            “19. The construction of Section 63, when read with the other
            provisions of this Act, is what comes up for decision in the present
            appeals. It may be noticed that Section 63 begins with a non
     2
      Energy Watchdog v. Central Electricity Regulatory Commission and Others (2017)
H    14 SCC 80
HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                59
          LTD. & ORS. [K. M. JOSEPH, J.]

   obstante clause, but it is a non obstante clause covering only Section   A
   62. Secondly, unlike Section 62 read with Sections 61 and 64, the
   appropriate Commission does not “determine” tariff but only
   “adopts” tariff already determined under Section 63. Thirdly, such
   “adoption” is only if such tariff has been determined through a
   transparent process of bidding, and, fourthly, this transparent
                                                                            B
   process of bidding must be in accordance with the guidelines issued
   by the Central Government. What has been argued before us is
   that Section 63 is a standalone provision and has to be construed
   on its own terms, and that, therefore, in the case of transparent
   bidding nothing can be looked at except the bid itself which must
   accord with guidelines issued by the Central Government. One             C
   thing is immediately clear, that the appropriate Commission does
   not act as a mere post office under Section 63. It must adopt the
   tariff which has been determined through a transparent process
   of bidding, but this can only be done in accordance with the
   guidelines issued by the Central Government. Guidelines have been
                                                                            D
   issued under this section on 19-1-2005, which guidelines have been
   amended from time to time. Clause 4, in particular, deals with
   tariff and the appropriate Commission certainly has the jurisdiction
   to look into whether the tariff determined through the process of
   bidding accords with Clause 4.
   20. It is important to note that the regulatory powers of the Central    E
   Commission, so far as tariff is concerned, are specifically
   mentioned in Section 79(1). This regulatory power is a general
   one, and it is very difficult to state that when the Commission
   adopts tariff under Section 63, it functions dehors its general
   regulatory power under Section 79(1)(b). For one thing, such             F
   regulation takes place under the Central Government’s guidelines.
   For another, in a situation where there are no guidelines or in a
   situation which is not covered by the guidelines, can it be said that
   the Commission’s power to “regulate” tariff is completely done
   away with? According to us, this is not a correct way of reading
   the aforesaid statutory provisions. The first rule of statutory          G
   interpretation is that the statute must be read as a whole. As a
   concomitant of that rule, it is also clear that all the discordant
   notes struck by the various sections must be harmonised.
   Considering the fact that the non obstante clause advisedly restricts
   itself to Section 62, we see no good reason to put Section 79 out        H
60            SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A          of the way altogether. The reason why Section 62 alone has been
           put out of the way is that determination of tariff can take place in
           one of two ways — either under Section 62, where the Commission
           itself determines the tariff in accordance with the provisions of
           the Act (after laying down the terms and conditions for
           determination of tariff mentioned in Section 61) or under Section
B
           63 where the Commission adopts tariff that is already determined
           by a transparent process of bidding. In either case, the general
           regulatory power of the Commission under Section 79(1)(b) is
           the source of the power to regulate, which includes the power to
           determine or adopt tariff. In fact, Sections 62 and 63 deal with
C          “determination” of tariff, which is part of “regulating” tariff.
           Whereas “determining” tariff for inter-State transmission of
           electricity is dealt with by Section 79(1)(d), Section 79(1)(b) is a
           wider source of power to “regulate” tariff. It is clear that in a
           situation where the guidelines issued by the Central Government
           under Section 63 cover the situation, the Central Commission is
D
           bound by those guidelines and must exercise its regulatory functions,
           albeit under Section 79(1)(b), only in accordance with those
           guidelines. As has been stated above, it is only in a situation where
           there are no guidelines framed at all or where the guidelines do
           not deal with a given situation that the Commission’s general
E          regulatory powers under Section 79(1)(b) can then be used.”
           (87) It is true that as far as the said case is concerned, the case
     arose from claims which were made under the PPA on the basis that
     there were changes in law apart from the argument that a case of Force
     Majeure was made out. It is not a case which actually on facts involved
F    the Court dealing with a case arising from the fixation of tariff under
     Section 63. In fact, it arose after a PPA was approved and the rates
     were fixed already under Section 63. However, if we notice the contents
     of para 19 and 20, the principle which the first respondent seeks to
     canvas before us does not appear to emerge. The argument of the first
     respondent is that even de hors the terms of the contract, there is general
G    regulatory power available under Section 79 of the Act. There is an
     overarching authority with the Commission exercising power under
     Section 79 which would enable it and which would empower it to grant
     compensation even de hors the terms of the contract it is contended.
     The argument appears to be that unlike generality of contracts, a regulated
H    contract which is a long term contract or an incomplete contract generates
    HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                     61
              LTD. & ORS. [K. M. JOSEPH, J.]

space for power with the appropriate regulatory body to revisit the rates            A
and thereby vouchsafe a fair deal to both sides, be it a seller or the
procurer.
     (88) What this Court has laid down in para 19 and 20 in Energy
Watchdog3may be summarized as follows:
       (89) In the case of fixation of tariff under Section 63 of the Act,           B
what is contemplated is to begin with guidelines which have been issued
under Section 63. When the Commission is asked to exercise power
under Section 63, it is beholden to the guidelines as it cannot depart from
the same. In a area where the guidelines do not occupy the field,
undoubtedly, the Commission is clothed with power as a regulatory body               C
to act in the best interest of all sides and to fix the tariff in a manner
which is fair in the sense bearing in mind the paramount interest of
increased generation of power, the interest of the consumer, as also
ensuring of a fair return to the seller. So far so good. When the Commission
exercises the power under Section 63, this power is not abridged when
there are no guidelines holding the field.                                           D

        (90) We are not dealing with a case where the exercise of power
of the Commission under Section 63 is under review. In a case where,
however, the rates are approved under Section 63 and PPA is entered
into, the question would undoubtedly arise as to whether there is a power
which can be described in a manner of speaking to be plenary power                   E
with the Commission under Section 79? Can there be a power which
can be christened as omnibus? Can the Tribunal, in other words, disregard
the express words of the contract? Can it discover a new change in law
which the parties have not contemplated as change in law? In short, can
the Tribunal rewrite the contract and create a new bargain?                          F
       (91) We are of the view that the Tribunal cannot indeed make a
new bargain for the parties. The Tribunal cannot rewrite a contract
solemnly entered into. It cannot ink a new agreement. Such residuary
powers to act which varies the written contract cannot be located in the
power to regulate. The power cannot, at any rate, be exercised in the                G
teeth of express provisions of the contract.
       (92) We notice this for the reason that the first respondent has a
case that what is provided in Article 13.2(a) (since we are dealing with
3
 Energy Watchdog v. Central Electricity Regulatory Commission and Others (2017) 14
SCC 80                                                                               H
62                SUPREME COURT REPORTS                              [2023] 8 S.C.R.


A    the case of alleged change in law during the construction period) does
     not do justice to the parties or that it is incapable of producing a fair
     result and therefore, the Tribunal would necessarily be clothed with power
     bearing in mind its regulatory nature. In a matter where the parties have
     entered into a contract with express provisions, we are unable to agree
     with the first respondent that the Tribunal would have power to disregard
B
     the express provisions of the contract on the score that as it turns out
     that with passage of time and even change in circumstances, it is found
     that the contract cannot be worked except at a loss for the contractor.
             (93) We may, at this juncture, also notice an argument which has
     been raised by Shri Amit Kapur, learned counsel for the first respondent,
C    when queried as to what would be the position if a claim of the nature
     were canvassed in a civil suit. The answer came that Section 18 and 19
     of the Indian Contract Act, 1872 (hereinafter referred to as ‘Contract
     Act’ for brevity), provided the gateway. Section 18 of the Contract Act
     deals with the effect of representation or rather misrepresentation by a
D    party made to another party to the contract. It, undoubtedly, includes a
     representation, however, innocent it may be. In other words, an innocent
     representation made to one party by another party which forms the basis
     for consent of the person can lead to the contract becoming voidable
     under Section 19. It is undoubtedly true that Section 19 also contemplates
     that the wronged party can insist upon the contract being performed and
E    further, however, persevere in requiring that he be placed in the same
     position if he had not been led astray by the misrepresentation. There
     may be no dispute about this principle. However, we have noticed the
     various clauses as contained in the disclaimer clauses. When a party to
     the contract states that what is contained in the first WAPCOS report
F    and anything else as contemplated in the RFP and the PPA does not
     amount to a representation, we are unable to agree with the contention
     that it would still be considered as a representation within the meaning
     of Section 18 and thereby leading to a claim under Section 19 of the
     Contract Act. Therefore, we find that the contentions which the first
     respondent seeks to raise under the provisions of Section 18 and 19
G    untenable.
           (94) Reliance was placed on the judgment of this Court PTC India
     Limited v. Central Electricity Regulatory Commission (2010) 4 SCC
     603. In PTC India Limited4, the actual question which arose was as to
     4
         PTC India Limited v. Central Electricity Regulatory Commission (2010) 4 SCC 603
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                  63
           LTD. & ORS. [K. M. JOSEPH, J.]

whether the appellate Tribunal under the Act has jurisdiction under Section    A
111 to examine the validity of regulations framed in exercise of power
under Section 178 of the Act. The further question which arose was
whether Parliament has conferred power of judicial review on the
Tribunal under Section 121 of the Act. In the course of this judgment,
the Court inter alia held as follows:
                                                                               B
      “53. Applying the abovementioned tests to the scheme of the 2003
      Act, we find that under the Act, the Central Commission is a
      decision-making as well as regulation-making authority,
      simultaneously. Section 79 delineates the functions of the Central
      Commission broadly into two categories —mandatory functions
      and advisory functions. Tariff regulation, licensing (including inter-   C
      State trading licensing), adjudication upon disputes involving
      generating companies or transmission licensees fall under the head
      “mandatory functions” whereas advising the Central Government
      on formulation of National Electricity Policy and tariff policy would
      fall under the head “advisory functions”. In this sense, the Central     D
      Commission is the decision-making authority. Such decision-making
      under Section 79(1) is not dependent upon making of regulations
      under Section 178 by the Central Commission. Therefore, functions
      of the Central Commission enumerated in Section 79 are separate
      and distinct from functions of the Central Commission under
      Section 178. The former are administrative/adjudicatory functions        E
      whereas the latter are legislative.
      55. To regulate is an exercise which is different from making of
      the regulations. However, making of a regulation under Section
      178 is not a precondition to the Central Commission taking any
      steps/measures under Section 79(1). As stated, if there is a             F
      regulation, then the measure under Section 79(1) has to be in
      conformity with such regulation under Section 178. This principle
      flows from various judgments of this Court which we have
      discussed hereinafter. For example, under Section 79(1)(g) the
      Central Commission is required to levy fees for the purpose of           G
      the 2003 Act. An order imposing regulatory fees could be passed
      even in the absence of a regulation under Section 178. If the levy
      is unreasonable, it could be the subject-matter of challenge before
      the appellate authority under Section 111 as the levy is imposed
      by an order/decision-making process. Making of a regulation under
      Section 178 is not a precondition to passing of an order levying a       H
64             SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A           regulatory fee under Section 79(1)(g). However, if there is a
            regulation under Section 178 in that regard then the order levying
            fees under Section 79(1)(g) has to be in consonance with such
            regulation.”
            (95) We are unable to see how the said judgment can advance
B    the case of the first respondent. The question which fell for consideration
     and the opinion which has been rendered do not in any way detract from
     the view which we have taken. Substantially, it was held that the making
     of regulation was not a pre condition for levying a regulatory fee under
     Section 79(1)(g). It is no doubt true that Commission has an adjudicatory
     function. It is also empowered to give opinions. Power to frame regulations
C    indicates that it also has legislative powers. The point is that since in this
     case we are concerned with the adjudicatory function of the Commission,
     we are concerned with the trammels to which it is subject in the form of
     the express terms of the contract. All that we are holding is that in a
     case where the matter is governed by express terms of the contract, it
D    may not be open to the Commission even donning the garb of a regulatory
     body to go beyond the express terms of the contract. It is apposite that
     we notice para 58 reads as follows:
            “58. One must understand the reason why a regulation has been
            made in the matter of capping the trading margin under Section
E           178 of the Act. Instead of fixing a trading margin (including capping)
            on a case-to-case basis, the Central Commission thought it fit to
            make a regulation which has a general application to the entire
            trading activity which has been recognised, for the first time, under
            the 2003 Act. Further, it is important to bear in mind that making
            of a regulation under Section 178 became necessary because a
F           regulation made under Section 178 has the effect of interfering
            and overriding the existing contractual relationship between the
            regulated entities. A regulation under Section 178 is in the nature
            of a subordinate legislation. Such subordinate legislation can even
            override the existing contracts including power purchase
G           agreements which have got to be aligned with the regulations
            under Section 178 and which could not have been done across
            the board by an order of the Central Commission under Section
            79(1)(j).”
            (96) While it may be open as indicated therein for a regulation to
     extricate a party from its contractual obligations, in the course of its
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                 65
           LTD. & ORS. [K. M. JOSEPH, J.]

adjudicatory power it may not be open to the Commission by using the          A
nomenclature regulation to usurp this power to disregard the terms of
the contract.
        (97) Another argument which has been raised on behalf of the
first respondent is that the guidelines were framed on 19.01.2005. Clauses
4.7 and 5.17 came to be, however, modified before the PPA was entered         B
into and even prior to the RFP and therefore, the PPA and Article 17.3
therein has been cast in the widest terms.
       (98) We have already perused Article 17.3.1. Article 17.3 to begin
with, speaks of specific instances which can trigger the dispute resolution
mechanism. A case in point and close to facts is a dispute arising from a
                                                                              C
change in law, after a claim is denied and a resolution through settlement
not being arrived at. There are other specific clauses which are part of
the PPA which are adverted to in the later part of Article 17.3.1.
Therefore, the argument is raised on behalf of the first respondent that
the opening words of Article 17.3.1 are designedly broad to cater to
situations such as are represented by the facts of this case. In other        D
words, even irrespective of a situation being not governed by Article
13.1 in order that the restitutionary principle or the principle of an
incomplete contract leading to a lifelong regulation assuring a fair return
to the seller is observed, the power of revisiting of the rates is what is
contemplated in the amended guideline which finds enshrinement in
Article 17.3.1., it is contended.                                             E
        (99) In fact, when we notice the PPA, we find that apart from
matters which are expressly referred to in Article 17.3.1, viz., Articles
4.7.1, Article 13.2, Article 18.1 or clause 10.1.3 of Schedule 17, there
are other Articles in the PPA with which Article 17.3.1 can bear nexus
with. They include apparently, Articles 4.5.2, 11.6.6 and 11.6.7. This is     F
besides 12.7(e) which relates to enforcement of claims under Force
Majeure. Therefore, it is not as if Article 17.3.1 is not to be understood
without reference to the other parts of the contract. No Court should
attempt to read a part of the contract in isolation. The draftsman of a
contract of the nature we are dealing with would have not left any stone
unturned in making the contract one to be construed with a great sense        G
of harmony and care. Therefore, we do not accept the contention of the
first respondent that the Commission, Tribunal and this Court must pour
in meaning into the opening words of Article 17.3.1 so that in the facts,
the first respondent can claim compensation on the basis that it has
incurred expenditure acting on the first WAPCOS report.                       H
66             SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A           (100) Here, we must notice finally, that substantially, the claim in
     regard to the water intake system was founded on the reliance placed
     on the first WAPCOS report and on the strength of the second WAPCOS
     report.
           (101) We also find reinforcement in our view from the following
B    clauses 1.2.12:
           “1.2.12 Different parts of this Agreement are to be taken as
           mutually explanatory and supplementary to each other and if there
           is any inconsistency between or among the parts of this
           Agreement, they shall be interpreted in a harmonious manner so
           as to give effect to each part.”
C
                                                            (Emphasis supplied)
             (102) An argument was raised by Shri Amit Kapur that the contract
     in the case calls for the application of the principle of contra proferentem
     rule.
D           (103) We are of the view that the principle of contra proferentem
     is ordinarily utilised in contracts of insurance and standard form contracts.
            (104) The principle of contra proferentem apparently in substance
     is that in case of any doubt in its terms, the doubt should be resolved
     against the party who drafted the contract. We would not think in the
     facts of this case that the first respondent has been able to plant any
E    serious doubt in regard to the clauses with which we are concerned with
     on a true understanding of the same.
           (105) The second complaint- The Office Memorandum dated
     17.06.2011.
           As far as the question relating to the OM dated 17.06.2011
F
           providing the premise for change in law claim is concerned, we
           are of the view that the claim may not have merit in it. It is true
           that Article 13.1.1 inter alia provides that a change can be brought
           about by the issuance of a notification by an Indian Governmental
           authority. Also a change in interpretation of any law by an Indian
G          Governmental instrumentality inter alia provided that it is final
           authority under law for such interpretation would constitute a
           change in law.
           Indian Governmental Instrumentality is defined as follow: -
           “Indian Governmental Instrumentality” means the GOI,
H          Government of States where the Procurers and Project are located
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                   67
           LTD. & ORS. [K. M. JOSEPH, J.]

      and any ministry or department of or board, agency or other               A
      regulatory or quasi-judicial authority controlled by GOI or
      Government of States where the Procurers and Project are located
      and includes the Appropriate Commission;”
      (106) Law as defined in the PPA is as follows:
      “Law” means, in relation to this Agreement, all laws including            B
      Electricity Laws in force in India and any statute, ordinance,
      regulation, notification or code, rule, or any interpretation of any
      of them by any Indian Governmental Instrumentality and having
      force of law and shall further include all applicable rules,
      regulations, orders, notifications by an Indian                           C
      GovermentalInstrumentatlity pursuant to or under any of them
      and shall include all rules, regulations, decisions and orders of the
      Appropriate Commission;
       (107) While the word ‘competent Court’ which can also be the
source of a change in interpretation of any law is expressly defined in
                                                                                D
Article 13.1.1., when it comes to the Indian Governmental instrumentality
which is the final authority, is concerned, there is no definition in the
PPA. The controversy is this.
      (108) The first respondent allegedly imported goods for the purpose
of construction of the captive mining plant. It is its case that the goods so
imported were being used for construction of the mining plant which             E
was in turn was utilised for the construction and operation of the ultra
mega power plant project. Such goods according to the first respondent
was expressly exempted from customs duty by virtue of the notification
holding the field. The notifications holding the field it must be understood
were the notifications holding the field before the cut off date. The cut       F
off date admittedly is 21.07.2007. In other words, the said date is the
date which is seven days before the bid deadline. The OM which is the
premise for the argument has been issued by the Director no doubt with
the approval of the Joint Secretary in the Ministry of Power. It reads as
follows:
                                                                                G
                            “No. 12/20/2009-UMPP
                              Government of India
                                Ministry of Power
                       Shram Shakti Bhawan, Rafi marg,
                                                                                H
68             SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A                            New Delhi, the 17th June, 2011
                               OFFICE MEMORANDUM
           Sub: 3960 MW Sasan Ultra Mega Power Project, Distt. Singrauli
           - Exemption from Custom Duty under project Import - reg.
           The undersigned is directed to refer to Govt. of Madhya Pradesh’s
B
           letter No. 4468/13/2011/01 dated 24.05.2011 on the subject
           mentioned above and to say that under Mega Power Policy, the
           Custom/Excise Duty exemption is given in respect of power
           equipment only.
           This issues with the approval of JS (Thermal), Ministry of Power
C
                                                                    (A.A. Tazir)
                                                                        Director


           Shri Mohd. Suleman
D          Secretary (Energy)
           Govt. of Madhya Pradesh,
           Bhopal”
            (109) It is the contention of the first respondent that when it
E    imported the goods it had to pay customs duty on the same and it
     constituted a change in law as the OM issued by the Joint Secretary
     placing the interpretation constituted a change in interpretation.
            (110) In other words, in contrast with the law as it stood before
     the cut off date, by the issuance of the OM by the Joint Secretary in the
F    Ministry of Power, a change in interpretation of the law is brought about.
     This sufficed to found a claim of change in law within the meaning of
     Article 13.1.1
           (111) The argument of the procurers, on the other hand, is as we
     have noticed is that the OM cannot be found to be issued by a
     Governmental instrumentality which can be treated as the final authority
G
     under law for such interpretation. It is for the reason that the notification
     granting exemption has been issued by the authority under the Customs
     Act and the Joint Secretary in the Ministry of Power is not such an
     authority. Secondly, it is the contention of the procurers that the matter
     should have been taken before the appropriate forum by the first
H    respondent on the basis that in law, actually, the import of goods was
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                 69
           LTD. & ORS. [K. M. JOSEPH, J.]

exempt if it was exempt and it was not open to the first respondent to        A
pass on the burden without taking recourse to law. Thirdly, it is contended
that the fact of the matter is that the position even before the cut off
date was that goods in question were not exempt.
       (112) Since we are dealing with the notifications, we notice that
the authority on Advance Ruling has gone into the history of the              B
notifications and dealt with the same though in the context of the right to
exemption in a mega power plant but not for an ultra mega power project.
But we are of the view that as far as the history of the notifications go,
it would continue to be relevant:
      “7.1 The Entry corresponding to the present Entry was introduced        C
      for the first time in 1999. As pointed out by the learned Sr. counsel
      for the applicant, the introduction of this Entry in the Customs
      notification seems to be a follow up to the policy decision taken
      by the Central Government as set out in the communication dated
      10.11.1995 addressed by the Secretary, Ministry of Power,
      Government of India and the revised policy/guidelines relating to       D
      Mega power projects issued in 1998. The policy formulated in
      1995 was in relation to the “setting up of power plants of capacity
      of 1000 MW or more supplying power to more than one state”. In
      that policy document, it is stated that the “project of capacity of
      1000 MW and more and catering power to more than one state              E
      should be considered as a mega project. Projects which cater
      power to a single State, irrespective of size, would not come under
      this category”. In the policy which has been recast in 1998, it was
      decided that inter-state and inter-regional mega power projects
      were to be set up both in the public and private sectors. The re-
      organization of the public sector corporations was also envisaged       F
      by the policy. The policy contemplates the beneficiary States
      constituting Regulatory Commissions with powers to fix tariff.
      Paragraph 5 of the guidelines is important. It says “the import of
      capital equipment would be free of custom duty for these projects”.
      In order to ensure that domestic bidders were not adversely             G
      affected, certain safeguards were spelt out.”
      7.2 Entry/ Sl.No. 288A of Ch. 98.01 inserted by Notification No.
      63/1999 substantially gives effect to the 1995 policy read with
      revised policy of 1998. The same concept of mega power project
      is to be found in that Entry. The Entry reads:
                                                                              H
70      SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A




B




C    Condition No. 82 is as follows: -
     82. (a) If an officer not below the rank of a Joint Secretary to the
     Government of India in the Ministry of Power certifies that-
     (i) the power purchasing state undertakes, in principle, to privatize
     distribution in all cities, in that State, each of which having a
D    population of more than one million within a period to be fixed by
     the Ministry of Power; and
     (ii) In the case of imports by a Central Public Sector Undertaking,
     the quantity, total value, description and specifications of the
     imported goods are certified by the Chairman and Managing
E    Director of the said Central Public Sector Undertaking; and
     (c) In the case of imports by a Private Sector Project, the quantity,
     total value, description and specifications of the imported goods
     are certified by the Chief Executive Officer of such project”.
     “7.3 List 33 specifies by name the thermal projects and hydel
F    projects in respect of which exemption is made applicable. Then,
     under Customs Notification No. 100 of 99 dated 28/7/99, the
     capacity of thermal power project specified in the earlier notification
     was altered from 1500 to 1000 MW. As a result of this notification,
     7 more thermal projects were added to the list.”
     “7.4 Then, the next notifications in succession are Customs
G
     Notification No. 16 of 2000 and 17 of 2001 which are substantially
     the same excepting that the number of thermal and hydel projects
     specified in List 33 has gone down.”
     “7.5 Then comes the Customs Notification No. 21 of 2002 dated
     01.03.2002 which is material for our purpose. It reads as follows:-
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                               71
           LTD. & ORS. [K. M. JOSEPH, J.]

                                                                            A




                                                                            B




                                                                            C

      “7.6 Entry 400 was amended by the Notification No. 26/2003.
The said amendment was necessitated by reason of the policy decision
taken by the Government as reflected in the Union budget speech of
203-04. The following extract from the budged speech is relevant:           D
      “Simultaneous to the emphasis on improvement in power
      distribution, our attention on capacity addition remains. The
      Government had earlier, in 1999, notified 18 power projected as
      mega projects, conferring upon them various duty and licensing
      benefits. The Government now proposes to liberalise the mega
                                                                            E
      power project policy further by extending all these benefits to any
      power project that fulfills the conditions already prescribed for
      mega power projects”.
      Pursuant to the above policy, Notification No. 26/2003-Cus. Was
      issued amending the notification no. 21/2002-Cus. Entry 400 as
      amended reads:                                                        F




                                                                            G




                                                                            H
72             SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A           “7.7 The amended notification no. 21 of 2002 is almost in the
            same language as it stands now (vide para 3 supra). Thus, w.e.f.
            1/4/2003, the list of specified power projects has been deleted in
            tune with the liberalized policy of the Government. Further, it is to
            be mentioned that Entry 400 of notification no.21 of 2002 was
            further amended keeping in view the revised policy guidelines
B
            issued in order to cater to the special requirements of power
            projects in Jammu and Kashmir and NE States. Entry 399
            substantially remained the same from 1999 onwards excepting
            that there was change in the Sl. No. and the rate.”
            (113) The order of the Advance Ruling Authority is dated
C    19.12.2008. No doubt, it is after the cut off date. The case of the first
     respondent is not based on the order of the Advance Ruling Authority.
     The case of the first respondent is specifically based only on the OM
     issued by the Joint Secretary in the Ministry of Power. We may notice
     that Joint Secretary in the Ministry of Power has a role in terms of the
D    notification. The role assigned to him is contained in condition 82 to the
     notification 63/1999 and this condition has continued thereafter also. The
     condition as we have noticed is that it is stated that an officer not below
     the rank of a Joint Secretary is to certify the aspects which are mentioned
     in condition 82.
E            (114) It is difficult, in fact, to describe the Joint Secretary in the
     Ministry of Power as the Governmental authority which is the final
     authority under the law. The final authority under the law would be the
     authority under the Customs Act which issues the exemption notification.
     But we would not wish to rest our findings on the said basis as we feel
     that the objection of the procurers can rest on surer foundations. The
F    first respondent also relies upon no doubt, the notification dated 26.05.2006
     wherein it is indicated as follows:
                            “Notification No.49/2006-Customs
            In exercise of the poowers conferred by sub-section (1) of Section
G           25 of the Customs Act, 1962 (52 of 1962), the Central Government,
            on being satisfied that it is necessary in the public interest to do
            so, hereby makes the following further amendments in the
            notification of the Government of India in the Ministry of finance
            (Department of Revenue) No.21/2002- Customs, dated the 1st
            March, 2002, which was published in the Gazette of India,
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                    73
           LTD. & ORS. [K. M. JOSEPH, J.]

       Extraordinary vide number G.S.R. 118(E), dated the 1st March,             A
       2002, namely:-
          (I) in the Table, against S.No.400, for the entry in column (3),
          the following entry shall be substituted,namely:-
          “Goods required for setting up of any Mega Power Project, so
          certified by an officer not below the rank of Joint Secretary to       B
          the Government of India in the Ministry of Power, that is to
          say-
          (a) an inter-state thermal power plant of a capacit of 700MW
          or more, located in the States of Jammu and Kashmir, Sikkim,
          Arunachal Pradesh, Assam, Meghalaya, Manipur, Mizoram,                 C
          Nagaland and Tripura,or
          (b) an inter-state thermal power plant of a capacity of 1000MW
          or more, located in States other than those specified in clause(a)
          above; or
                                                                                 D
          (c) an inter-state hydel power plant of a capacity of 350MW
          or more, located in the States of Jammu and Kashmir, Sikkim,
          Arunachal Pradesh, Assam, Meghalaya, Manipur, Mizoram,
          Nagaland and Tripura,or
          (d) an inter-state hydel power plant of a capacity of 500MW
                                                                                 E
          or more, located in States other than those specified in Clause
          (C) above”,
          (II) in the Annexure, in Condition No.86, for sub-clauses (ii)
          and (iii) of clause(A), the following shall be substituted, namely:-
          “(ii) the power purchasing State undertakes, in principle,             F
          privatize distribution in all cities, in that State, each of which
          has a population of more than one million, within a period to be
          fixed by the Ministry of Power.”
       (115) The Tribunal has, in fact, proceeded on the basis that the
goods in question would fall under Entry 400 relating to power projects          G
and therefore, they were exempted. The Tribunal proceeded further on
the basis that the notification dated 17.06.2011 issued by the Joint Secretary
amounted to an interpretation which constitutes a change in law.
      (116) We are of the view that the approach of the Tribunal cannot
be upheld. There is no material, whatsoever, apart from the notifications        H
74             SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A    to indicate that the goods in question were being treated as exempt before
     the cut off date. In other words, it was incumbent upon the first respondent
     to produce incontestable material establishing that the goods were exempt
     and were being treated so before the cut off date. The best material
     would have been examples of similar cases where goods were being
     treated as exempt. Even though, it is pointed out that the first respondent
B
     was the only ultra mega power plant, even then power plants including
     mega power plants were operational. It is difficult to conceive that there
     would not be a single case where similar inputs by way of examples of
     other power projects even if it is not ultra mega power projects would
     not have operated for the first respondent to draw from.
C           (117) The word law has been defined as we have noticed. While
     the expression ‘Indian Governmental Instrumentality’ is used in the
     definition of the word law in Article 13.1.1, the change in interpretation
     of any law by an Indian governmental authority must be the final authority
     under the law for such interpretation. It may be difficult to attribute to
D    the Joint Secretary in the Ministry of Power the position of an Indian
     Governmental Authority who has the final authority under the law. But
     as we have indicated this must not be treated as the basis on which we
     disagree with the Tribunal.
             (118) The perusal of the OM does not advance the case of the
E    first respondent for yet another good reason. He does not in the OM
     indicate that the goods in question had been exempted before the cut off
     date and that the goods becoming exigible to duty on the date after the
     cut off date. The Authority for Advance Ruling has categorically affirmed
     that the goods of the type with which we are concerned may not qualify
     for exemption. The appellants have a case that, in fact, the Joint Secretary
F    was essentially following the Advance Ruling. While it is true that the
     Advance Ruling may not bind the first respondent as it is not a party, and
     the respondent could not have sought a ruling under the law, it is
     undoubtedly an aspect which otherwise adds strength to the case of the
     appellants. There may be cases where placing the notification holding
G    the field before the cut off date side by side to the subsequent notification
     or an interpretation issued after the said cut off date, the Commission or
     a Tribunal could find that there is change in law, which added to the cost
     to the seller. On the other hand, when the case of the first respondent
     involves interpretation of the terms of the notification then particularly
     when two views are fairly competing for acceptance before the body, at
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                75
           LTD. & ORS. [K. M. JOSEPH, J.]

best, we would think that the Tribunal has hazarded taking a perilous        A
route in venturing to find that the OM issued by the Joint Secretary
constituted the change in law. Though reliance has been placed on the
judgment of this Court reported in Manohar Lal Sharma v. Principal
Secretary &Ors. (2014) 9 SCC 516 and Manohar Lal Sharma v.
Principal Secretary &Ors. (2014) 9 SCC 614 which decisions purported
                                                                             B
to exempt the mining leases which were captive leases operating for the
purpose of the power projects including the power projects specifically
in question from the purview of its decision, we do not think that that by
itself can determine the question as to whether the goods which were
imported for the purpose of the captive mining plant was ever exempt.
What was exempt has been goods imported for the purpose of the Power         C
project. In other words, as to whether the goods in question were goods
which fell within one entry or the other is in this case a matter which is
highly disputed and the premise of the first respondent viz., the OM of
the Joint Secretary cannot be treated as being a sound foundation for
making such a claim.
                                                                             D
       (119) The parties indeed contemplated a project to be constructed
and operated. The word ‘project’ we find has been used in many clauses
in the contract. The word ‘project’ has been defined as follows:
      “”Project” means the Power Station and the Captive Coal Mine(s)
      undertaken for design, financing, engineering, procurement,            E
      construction, operation, maintenance, repair, refurbishment,
      development and insurance by the Seller in accordance with the
      terms and conditions of this Agreement;”
      (120) Since the word ‘power station’ has been used in word
‘project’, it is apposite that we advert to the definition of the words      F
‘power station’:
      “Power Station” means the:
      (a) coal fired power generation facility comprising of any or all
      the Units;
                                                                             G
      (b) any associated fuel handling, treatment or storage facilities of
      the power generation facility referred to above;
      (c) any water supply, treatment or storage facilities required for
      the operation of the power generation facility referred to above;
      (d) the ash disposal system including ash dyke;                        H
76             SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A          (e) township area for the staff colony; and
           (f) bay/s for transmission system in the switchyard of the power
           station,
           (g) all the other assets, buildings/structures, equipments, plant and
           machinery, facilities and related assets require for the efficient
B          and economic operation of the power generation facility;
           whether completed or at any stage of development and
           construction or intended to be developed and constructed as per
           the provisions of this Agreement.”

C           (121) Since the word ‘captive coal mine’ has also been referred
     to as part of the definition of the word ‘project’, it is only right that we
     advert to the definition:
           “Captive Coal Mine(s) means the captive coal mines as described
           in Schedule 1A and associated fuel transport system up to the
D          Power Station;”
           (122) ‘Project Documents” again has been defined. We may
     also notice the definition of the words ‘Prudent Utility Practices’:
           “Project documents Mean
           a) Construction Contracts;
E
           b) Fuel mining agreements, including the Fuel Transportation
           Agreement, if any;
           c) O&M contracts;
           d) RFP and RFP Project Documents; and
F
           e) any other agreements designated in writing as such, from time
           to time, jointly by the Procurers and the Seller;
           “Prudent Utility Practices means the practices, methods and
           standards that are generally accepted internationally from time to
           time by electric utilities or coal mining entities for the purpose of
G
           ensuring the safe, efficient and economic design, construction,
           commissioning, operation and maintenance of coal mines and power
           generation equipment and mine of the type specified in this
           Agreement and which practices, methods and standards shall be
           adjusted as necessary, to take account of:
H
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                77
           LTD. & ORS. [K. M. JOSEPH, J.]

      a) operation and maintenance guidelines recommended by the             A
      manufacturers of the plant and equipment to be incorporated in
      the Project;
      b) the requirements of Indian Law; and
      c) the physical conditions at the Site;”
                                                                             B
       (123) We have set out the history of the notifications relating to
grant of exemption for power projects. All of it began with the policy
issued in the year 1995. The exemptions had their origin with the
notification issued in the year 1999. Thereafter there is Notification 21/
2002 which was issued on 01.03.2002. Entry 400 in the said notification
reads as follows:                                                            C




                                                                             D




                                                                             E




                                                                             F




                                                                             G




                                                                             H
78            SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A          (124) Thereafter another notificationnamely Notification No. 26/
     03 which has given a final shape to it came to be issued which has been
     noticed also by the Authority of Advance Ruling. It reads as follows:



B




C



                                                          (Emphasis supplied)
D          (125) We may notice that with the issuance of the said notification
     what stands out is the following:
            (126) While in the opening words of the Entry, there is reference
     to power project, it is conditioned by the words ‘that is to say’. We can
     quite safely proceed on the basis that Entry 400 in the Notification No.
E    21/2002 which came into effect on 01.03.2002 as amended by Notification
     No. 46/2008 is the Entry which must be treated as holding the field as on
     the cut off date. It is thereafter, no doubt, that the first respondent has
     invoked the change in law clause by seeking to draw inspiration from
     the OM issued on 17.06.2011.
F           (127) Change in law clause is sought to be invoked apparently
     contending that there has been a change in interpretation by Indian
     Governmental Authority which has the final say in terms of the law. The
     question which looms large before the Court is whether there has been
     a change in law in terms of ‘change in interpretation’ placed by the
     Governmental authority with reference to the position obtaining under
G    the notifications issued under the Customs Act. Even the clauses in the
     PPA which we have referred to maintain a distinction between a power
     plant and a captive mine. A power plant cannot be treated as the same
     as captive mine. In fact, Schedule 1A which defines the site refers to
     the captive mines in terms of the coal blocks which are allotted. The
H    definition of captive mine also indicates that it is the coal mines as
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                  79
           LTD. & ORS. [K. M. JOSEPH, J.]

described in Schedule 1A and the associated fuel transport system up to        A
the power station. No doubt, the word ‘site’ has also been defined as the
land over which the Project will be developed as provided in Annexure
1A.
       (128) Undoubtedly, in view of the very purpose of having a coal
mine which is to supply the requisite fuel for the operation of the power      B
plant, there would be a certain measure of geographical contiguity. But
the question for the consideration before this Court is whether that would
decide the fate of the contents of a notification issued under the Customs
Act.
       (129) We must notice that it is not as if the first respondent is the   C
only person which had a right to claim the benefit of exemption on the
basis that the goods which have been imported for the purpose of their
captive mine must be treated as goods used in the power project. As the
history of the notifications as captured in order of the Advance Ruling
Authority would show over a period of time, there have been a number
of power plants which have sprung up. All of them would also be using          D
captive mines for the purpose of generating power. It is not as if there
would be a dearth of examples of exemption being extended to imports
made by them and claiming the benefit of exemption under the
notification. Not a single instance of an exemption granted to any other
project where goods imported for use in the captive mine has been              E
produced before the Commission, the Tribunal or even this Court. This
goes a long way to negate the claim of the first respondent that what
was once exempt has ceased to be exempt only by virtue of the issuance
of the OM dated 17.06.2011.
       (130) There is another very important circumstance which strikes        F
us. The material which appeals to us is to be found undoubtedly in the
order of the Advance Ruling Authority relied upon by the appellant. The
application, no doubt, is filed in the year 2008. What impresses the Court
the most is the stand of the customs authorities before the Advance
Ruling Authority. We cannot proceed on the basis that the controversy
which led to the seeking of the ruling and far more importantly the            G
persistent stand of the customs authority before the Advance Ruling
Authority would not shed light on how the Department viewed the matter.
This is important as it is the customs department which has issued the
exemption notification. Being the authors of the notification, they would
be best placed to understand the width and purport of a notification           H
80            SUPREME COURT REPORTS                            [2023] 8 S.C.R.


A    granting exemption. They have stoutly opposed the application and laid
     out various grounds which, no doubt, has appealed also to the Advance
     Ruling Authority. This is an aspect which goes a long way to show that
     the view of the customs authority which in a manner of speaking can
     also be viewed as forming contemporaneaexpositio should not be
     ignored by this Court.
B
            (131) The first respondent also sought considerable reliance in
     this regard from the Mega Power Projects: Revised Policy Guidelines.
     The relevant portions reads as follows:
                 “MEGA POWER PROJECTS: REVISED POLICY
C                            GUIDELINES
           The following conditions are required to be fulfilled by the developer
           for grant of mega project status:-
           a) an inter-state thermal power plant of a capacity of 700 MW or
           more, located in the States of Jammu and Kashmir, Sikkim,
D          Arunachal Pradesh, Assam, Meghalaya, Manipur, Mizoram,
           Nagaland and Tripura; or
           b) an inter-state thermal power plant of a capacity of 1000 MW
           or more, located in States other than those specified in clause (a)
           above; or
E
           c) an inter-state hydel power plant of a capacity of 350 MW or
           more. located in the States of Jammu and Kashmir. Sikkim,
           Arunachal Pradesh, Assam, Meghalaya. Manipur, Mizoram,
           Nagaland and Tripura: or
           d) an inter-state hydel power plant of a capacity of 500 MW or
F
           more, located in States other than those specified in clause (c)
           above’
           Fiscal concessions/benefits available to the Mega Power Projects
           Zero Customs Duty: In terms of the notification of the Government
G          of India in the Ministry of Finance(Department of Revenue) No.
           21/2002-Customs dated 18 March, 2002 read together with No.
           49/2006-Customs dated 26 May, 2006. the import of capital
           equipment would be free of customs duty for these projects.”
           (132) The understanding of the Authority for Advance Ruling
H    appears to be that as far as the entitlement to exemption under the
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                   81
           LTD. & ORS. [K. M. JOSEPH, J.]

notification is concerned a mega power project has to be understood as          A
confined to what follows after the words ‘that is to say’. In other words,
though the use of the words power project in entry 400 would appear to
suggest that it is capable of embracing within its scope a captive mine
from which the fuel is generated to run the power plant, when it came to
the actual beneficiary of entry 400, the maker of the notification has
                                                                                B
confined the exemption to the goods for the purpose of the power plant.
In other words, the word power project has been conflated with the
power plant. This appears to be the soul of the reasoning of the Advance
Ruling Authority. While we are aware that the first respondent is not
bound by the said Ruling as it is not a party, we do not find it erroneous
on our part in finding merit in the logic of the same or adopting the same      C
for the purpose of deciding the question which squarely arises before
this Court viz., whether there is a change in law.
        (133) There is also merit in the contention of the appellant that for
article 13.1.1 to be successfully invoked by the seller, it must demonstrate
that there was an interpretation earlier to or as on the date of the cut off    D
date which was advantageous to the seller and there has been a change
in the said interpretation after the cut off date.
        (134) In other words, the OM issued with the approval of the
Joint Secretary in the Ministry of Power does not indicate that it is a
case of a change in interpretation. He does not say that the position           E
adumbrated in the OM represents a shift or a change from what the
position was prior to the cut off date. This is apart from any material
being available to show that there was an interpretation in favour of the
first respondent prior to the cut off date.
        (135) We reiterate that no instance of exemption to goods of            F
similar nature being imported by any person for the captive mine as part
of a power project be it mega or ultra mega plant is placed before the
Commission. It is one thing to say that in a popular sense and it could be
urged and it may be true that the word project has been defined in the
PPA as power plant and the captive coal mine, but as we have noticed
this is a matter to be determined on what was intended by the author of         G
the notification under Section 25 of the Customs Act and the matter is to
be further determined with reference to the express terms of the
Notification. Even more importantly, the question must fall to be decided
with reference to the interpretation available prior to the cut off date and
after cut off date. The communication, which is the OM dated 17.06.2011         H
82             SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A    relied upon by the first respondent appears to have been issued on the
     basis of the request made by the first respondent to the State of Madhya
     Pradesh.
           (136) Shri Amit Kapur, learned counsel on behalf of the first
     respondent drew our attention to Entry 78 of notification No. 21/02 dated
B    1.3.2002. Entry 78 reads as follows:




C

             (137) Shri Ramchandran, learned senior counsel, would point out
     that the said Entry relates to inputs for power generation. The case of
     the first respondent is also that Entry 399 actually specifically deals with
     the goods required for coal mining project under which the first respondent
D
     has been visited with customs duty.
            (138) The argument of Shri Amit Kapur is that first of all, Entry
     78 if contrasted with Entry 400 would show that all goods needed for a
     power project understood in a larger sense as including a captive coal
     mine would also come within four walls of Entry 400.
E
             (139) Shri Amit Kapur, learned counsel, would point out that captive
     coal mine envisaged as such is one where the entire production of coal
     is to be utilised for the power plant in question which also would indicate
     that it is part of the power project. It is not in dispute that whatever may
     be the distinction which may exist between a mega power project, an
F    ultra mega power project (we are concerned with latter), there is no
     separate notification under the Customs Act which deals with ultra mega
     power project.
            (140) The upshot of the above discussion is that we are of the
     view that the first respondent has not been able to demonstrate that
G    there was a change in law as contemplated in Article 13.1.1 by issuance
     of the OM dated 17.06.2011.
           RELIEF
           (141) The three procurers who were respondents before the
H    Tribunal have not chosen to file appearance before this Court. The lead
 HARYANA POWER PURCHASE CENTRE v. SASAN POWER                                   83
           LTD. & ORS. [K. M. JOSEPH, J.]

procurer has filed an appeal before this Court. Further, there is only one      A
PPA. Ironically, decisions relating to Order XLI Rule 21 and Rule 33
have been placed before this Court by the first respondent reminding
this Court of the power available to it. No doubt, they placed this position
in an attempt at salvaging the situation arising from no appeal have been
filed by it challenging the finding relating to there being no change in law
                                                                                B
in regard to the water intake system.
       (142) In the facts of this case, we also notice that the three non-
filing parties are respondents in the appeals filed by the appellants. We
also cannot be unmindful of the argument of Shri P. Chidambaram and
others that if the first respondent had a case that they were entitled to an
exemption under the situation extant prior to the cut off date then proper      C
remedy would be to seek refund on the basis that they have been illegally
visited with customs duty.
        (143) In the facts of this case, we feel that the interest of justice
do require that the impugned order be set aside not only as against the
appellants but also as against the three non-appellants. In the nature of       D
the litigation, we would think that the benefit of this order should be
vouchsafed to the three respondents also, viz., (1) respondent No.
12(BSES Rajdhani Power Limited); (2) respondent No. 13 (BSES
Yamuna Power Limited); and (3) respondent No. 15(Uttarakhand Power
Corporation Limited). Apparently, these respondents have not contested          E
the appeals.
       (144) As we have noticed in the beginning as a sequel to the
impugned order, the Commission has passed orders allowing the claim
relating to the water intake system whereas it has rejected the prayer
relating to change in law flowing from OM dated 17.06.2011. The affected        F
parties have carried the matter to the Tribunal in appeals. It is brought to
our notice that this Court passed an order of stay dated 25.11.2019.
Since the appellants have challenged the order of the Tribunal, the
subsequent order by the Commission can only be treated as a
consequential order and therefore, it may not have any independent legs
to stand on. The appellants must be given the fruits of the decision which      G
ultimately is rendered in their favour, as we are rendering this judgment.
       (145) Accordingly, the appeals are allowed. The impugned order
is set aside. The order will enure to the benefit also of the three
respondents also, viz., (1) respondent No. 12(BSES Rajdhani Power
                                                                                H
84              SUPREME COURT REPORTS                           [2023] 8 S.C.R.


A    Limited); (2) respondent No. 13 (BSES Yamuna Power Limited); and
     (3) respondent No. 15(Uttrakhand Power Corporation Limited). Equally,
     the order passed by the Commission consequent upon the remand under
     the impugned order cannot survive. The appeals filed will also lose their
     force and it is for the appellants to do the needful to bring it to an end in
     the light of this judgment.
B
            The parties will suffer their own costs.

     Bibhuti Bhushan Bose                                          Appeals allowed.
     (Assisted by : Rahul Rathi, LCRA)
C




D




E




F




G




H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Electricity Act 2003"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

HARYANA POWER PURCHASE CENTRE versus SASAN POWER LTD. & ORS — 2023 INSC 326 - Legal Desk AI