Created byFuzzy Cloud

Supreme Court of India

BERNARD FRANCIS JOSEPH VAZ AND OTHERSversusGOVERNMENT OF KARNATAKA AND OTHERS

Citation
2025 INSC 3
Decided
1 January 2025
Disposal
Disposed off

Holding

The Supreme Court directed that compensation be determined based on the market value prevailing on 22 April 2019, as the SLAO’s earlier shift of the valuation date was beyond its jurisdiction and the delay warranted equitable relief under Article 300‑A.

Summary

The appellants purchased residential plots in Bengaluru between 1995 and 1997, which were later acquired by the Karnataka Industrial Areas Development Board (KIADB) under a preliminary notification dated 29 January 2003. Although possession was taken in 2005, no compensation award was made until a Special Land Acquisition Officer (SLAO) issued an award on 22 April 2019, using guideline values from 2011 and shifting the valuation date from the preliminary notification. The High Court quashed the award for lack of jurisdiction and directed the SLAO to determine compensation as of the preliminary notification date, dismissing the appellants' plea to shift the valuation date. The Supreme Court held that, given the inordinate delay and deprivation of compensation, it was appropriate to direct the SLAO to determine compensation based on the market value as of 22 April 2019, invoking its powers under Article 142. The Court set aside the High Court’s order, allowed the appellants’ writ petition, and ordered a fresh award reflecting the 2019 market value along with all statutory benefits.

Issues considered

  • The appropriate date for determining market value of land for compensation – whether it should be the date of the preliminary notification or the date of the award.
  • Whether the SLAO had jurisdiction to shift the valuation date to a later year.
  • The applicability of Article 300‑A of the Constitution in cases of prolonged delay in compensation.
  • The scope of the Supreme Court’s powers under Article 142 to direct a fresh award.

Legislation cited

Subjects

Article 300-ARight to propertyLand acquisitionPreliminary notificationCompensationAdequate compensationDeprivation of compensationDisbursal of compensationMarket value of landShifting valuation dateInordinate delayWelfare StateArticle 142Article 226

Judgment

                   [2025] 1 S.C.R. 190 : 2025 INSC 3

              Bernard Francis Joseph Vaz and Others
                                v.
               Government of Karnataka and Others
                        (Civil Appeal No. 17 of 2025)
                                02 January 2025
                 [B.R. Gavai* and K.V. Viswanathan, JJ.]


                            Issue for Consideration
       The Lands of appellants herein were acquired and they were
       deprived of their property without paying any compensation for
       twenty-two years. For payment of compensation, the appellants
       pleaded to shift the date for considering the market value of land as
       on the date of the award and not as on the date of the Preliminary
       Notification. Whether this Court should direct shifting of the date
       for determination of the market value of the land in question of
       the appellants.

                                  Headnotes†
       Constitution of India – Art.300-A – Land Acquisition Act, 1894 –
       Karnataka Industrial Areas Development Act, 1966 – From
       1995 to 1997, appellants herein purchased various residential
       sites – On 29.01.2003, a preliminary notification was issued
       by Respondent No. 2 (KIADB) for acquiring the said lands –
       The possession of the appellants’ land was taken over by
       Respondent No. 2 (KIADB), however, no award was passed
       immediately for such acquisitions – On 22.04.2019, Special
       Land Acquisition Officer (SLAO) passed an award for payment
       of compensation in respect of lands belonging to the erstwhile
       land-owners – The Single Judge of the High Court quashed the
       award dated 22.04.2019 passed by SLAO – Division Bench of
       the High Court dismissed the writ Appeal filed by the appellants
       herein – Appellants’ plea to shift the date for considering the
       market value of land as on the date of the award and not as
       on the date of the Preliminary Notification:
       Held: The appellants had purchased the plots in question for
       construction of residential houses – Not only have they not been
       able to construct, but they have also not been even paid any

* Author
[2025] 1 S.C.R.                                                                191

                Bernard Francis Joseph Vaz and Others v.
                  Government of Karnataka and Others

     compensation for the same – The appellants have been deprived
     of their property without paying any compensation for the same
     in the said period of last twenty-two years – Though Right to
     Property is no more a fundamental right, in view of the provisions
     of Article 300-A of the Constitution of India, it is a constitutional
     right – A person cannot be deprived of his property without him
     being paid adequate compensation in accordance with law for the
     same – In the instant case, it can clearly be seen that there is
     no delay which can be attributed to the appellants in not getting
     compensation, but it was on account of the lethargic attitude of
     the officers of the State/KIADB that the appellants were deprived
     of compensation – Only after the notices were issued in the
     contempt proceedings, the compensation was determined by
     the SLAO on 22.04.2019 taking guideline values prevailing in
     the year 2011 for determining the market value of the acquired
     land – The Single Judge of the High Court also does not say that
     the determination of compensation to be awarded by shifting of
     the date by the SLAO to that of 2011 was unjust but only sets
     aside the award on the ground that SLAO had no jurisdiction
     to do so – If on account of the inordinate delay in paying the
     compensation and thereby depriving the constitutional right to the
     appellants under Article 300-A, the land acquisition proceedings
     are quashed, the only recourse available to the State/KIADB in
     order to save the project will be to now issue a fresh acquisition
     notification by invoking the provisions as applicable under the
     Right to Fair Compensation and Transparency in Land Acquisition,
     Rehabilitation and Resettlement Act, 2013 which would entail huge
     expenditure to the public exchequer – Therefore, in exercise of
     power of this Court under Article 142 of the Constitution of India,
     this Court finds it appropriate in the interest of justice that the SLAO
     be directed to determine the compensation to be awarded to the
     appellants herein on the basis of the market value prevailing as
     on 22.04.2019 – The appellants shall also be entitled to all the
     statutory benefits as are available to them under the 1894 LA Act.
     [Paras 49, 50, 54, 55, 57]

     Land Acquisition – Compensation – Value of money – Disbursal
     of compensation with promptitude:
     Held: It cannot be controverted that money is what money buys –
     The value of money is based on the idea that money can be
     invested to earn a return, and that the purchasing power of money
192                                                              [2025] 1 S.C.R.

                        Digital Supreme Court Reports


       decreases over time due to inflation – What the appellants herein
       could have bought with the compensation in 2003 cannot do in
       2025 – It is, therefore, of utmost importance that the determination
       of the award and disbursal of compensation in case of acquisition
       of land should be made with promptitude. [Para 48]

                                Case Law Cited
       Ram Chand and Others v. Union of India and Others, 1993
       INSC 315 : [1993] Supp. 2 SCR 558 : (1994) 1 SCC 44; Vidya
       Devi v. State of Himachal Pradesh and Others, 2020 INSC 23 :
       [2020] 1 SCR 749 : (2020) 2 SCC 569; Ultra-Tech Cement Ltd.
       v. Mast Ram and Others, 2024 INSC 709 : [2024] 9 SCR 443 :
       2024 SCC OnLine 2598 – relied on.
       Tukaram Kana Joshi and Others Through Power-of-Attorney
       Holder v. Maharashtra Industrial Development Corporation and
       Others, 2012 INSC 503 : [2012] 13 SCR 29 : (2013) 1 SCC 353;
       Maharashtra State Road Transport Corporation v. State of
       Maharashtra and Others, 2003 INSC 137 : [2003] 2 SCR 530 :
       (2003) 4 SCC 200; Competent Authority v. Barangore Jute Factory
       and Others, 2005 INSC 585 : [2005] Supp. 5 SCR 421 : (2005)
       13 SCC 477; Haji Saeed Khan and Others v. State of U.P. and
       Others (2001) 9 SCC 513; K. Krishna Reddy and Others v. Special
       Deputy Collector, Land Acquisition Unit II, LMD Karimnagar, Andhra
       Pradesh, 1988 INSC 265 : [1988] Supp. 2 SCR 853 : (1988)
       4 SCC 163 – referred to.

                                   List of Acts
       Karnataka Industrial Areas Development Act, 1966; Right to Fair
       Compensation and Transparency in Land Acquisition, Rehabilitation
       and Resettlement Act, 2013; Land Acquisition Act 1894; National
       Highways Act, 1956; Constitution (Forty-Fourth Amendment)
       Act, 1978; Constitution of India.

                                List of Keywords
       Article 300-A of Constitution; Right to property; Constitutional
       right; Acquisition of land; Preliminary notification; Payment
       of compensation; Adequate compensation; Deprivation of
       compensation; Disbursal of compensation; Market value of land;
       Shifting the date for considering the market value of land; Inordinate
       delay in paying the compensation; Welfare State.
[2025] 1 S.C.R.                                                              193

               Bernard Francis Joseph Vaz and Others v.
                 Government of Karnataka and Others

                             Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 17 of 2025
     From the Judgment and Order dated 22.11.2022 of the High Court
     of Karnataka at Bengaluru in WA No. 678 of 2022

                         Appearances for Parties
     R. Chandrachud, Dhuli Ventaka Krishna, Advs. for the Appellant.
     Avishkar Singhvi, A.A.G., Atmaram N.S. Nadkarni, Sr. Adv.,
     Sharanagouda Patil, Mrs. Supreeta Patil, Jyotish Pandey,
     S.S. Rebello, Ms. Deepti Arya, Arzu Paul, Vidur Nair (for M/s. S-legal
     Associates), V.N. Raghupathy, Purushottam Sharma Tripathi, S.J.
     Amith, Mrs. Vani Vyas, Prakhar Singh, Advs. for the Respondents.

                Judgment / Order of the Supreme Court

                                 Judgment

     B.R. Gavai, J.

1.   Leave granted.
2.   This appeal takes exception to the final judgment and order dated
     22nd November 2022 in Writ Appeal No. 678 of 2022 (LA-KIADB)
     passed by the High Court of Karnataka at Bengaluru, whereby the
     Division Bench of the High Court dismissed the writ appeal filed by
     the appellants herein against the judgment and order dated 18th April
     2022 in Writ Petition No. 1627 of 2021 passed by the learned Single
     Judge of the High Court dismissing their writ petition.

     FACTS:
3.   The facts, in brief, giving rise to the present appeal are as follows:
     3.1. From 1995 to 1997, the appellants herein purchased various
          residential sites at Gottigere Village, Uttarahalli Hobli, Bengaluru
          South Taluk, Karnataka vide registered sale deeds and became
          absolute owners of their respective sites.
     3.2. On 3 rd April 1997, a Framework Agreement (hereinafter,
          “FWA”) was executed between Government of Karnataka
          (Respondent No. 1) and Nandi Infrastructure Corridor Enterprise
          Ltd. (hereinafter, “NICE”) (Respondent No. 6) envisaging the
194                                                              [2025] 1 S.C.R.

                        Digital Supreme Court Reports


             Infrastructure Corridor Project connecting Bengaluru-Mysuru
             (hereinafter, “Bengaluru-Mysuru Infrastructure Corridor Project”
             or “BMICP”). As per the FWA, the State Government undertook
             to acquire about 13,237 acres of land from private persons and
             about 6,956 acres of Government land. In all 20,193 acres of
             land was agreed to be conveyed and transferred in favour of
             Respondent No. 6 (NICE) for implementation of the BMICP.
       3.3. On 14th October 1998, Respondent No. 6 applied to Karnataka
            Industrial Areas Development Board (hereinafter, “KIADB”)
            (Respondent No. 2) to make available the lands for the project.
       3.4. On 29th January 2003, a preliminary notification was issued by
            Respondent No. 2 (KIADB) under sub-section (1) of Section 28
            of the Karnataka Industrial Areas Development Act, 1966
            (hereinafter, “KIAD Act”) for acquiring lands for the BMICP.
            Notices were issued under sub-section (2) of Section 28 of KIAD
            Act seeking objections from the land-owners. The appellants
            also submitted their objections.
       3.5. On 5th July 2003, upon consideration of the objections to the
            Preliminary Notification, the Final Notification was issued by
            Special Deputy Commissioner KIADB (Respondent No. 3).
       3.6. On 22nd November 2005, the possession of the appellants’
            land was taken over by Respondent No. 2 (KIADB) and
            subsequently handed over to Respondent No. 6 (NICE) and
            its sister concern Nandi Economic Corridor Enterprises Ltd.
            (NECE) (Respondent No. 7). However, no Award was passed
            immediately for such acquisitions.
       3.7. In 2009-10, the land-owners filed Writ Petitions before the
            High Court of Karnataka with a prayer to quash the acquisition
            notifications insofar as it relates to their lands. In the alternative,
            the land-owners sought a direction to the concerned authorities
            to allot residential sites of equal dimension.
       3.8. Vide judgment and order dated 15th June 2011, a Division
            Bench of the High Court held that the acquisition notifications
            cannot be quashed at such a belated stage and that there
            cannot be any direction for allotment of alternative sites to
            the land-owners. In the result, the batch of Writ Petitions
            filed by the land-owners were dismissed, however, liberty
[2025] 1 S.C.R.                                                      195

               Bernard Francis Joseph Vaz and Others v.
                 Government of Karnataka and Others

           was reserved to approach the concerned authorities if any
           rehabilitation programme is specifically worked out or if any
           welfare programme is generally available.
     3.9. On 12th February 2016, in terms of the judgment and order of
          the High Court dated 15th June 2011, some of the land-owners
          submitted a representation inter-alia to the Government of
          Karnataka, KIADB and NICE to frame a rehabilitation scheme
          as mandatorily required under the FWA and to allot alternative
          sites along with benefits under the scheme at the earliest.
     3.10. On non-consideration of their representation, the landowners
           filed Writ Petitions before the High Court being W.P. Nos.
           49812-49863 of 2016 (LA-KIADB), with a prayer to direct the
           State of Karnataka and KIADB to implement the request made
           in the representation dated 12th February 2016 at the earliest
     3.11. Vide order dated 24th March 2017, a learned Single Judge
           of the High Court disposed of the Writ Petitions filed by the
           land-owners by directing the State of Karnataka and KIADB
           to consider their representation and pass appropriate orders,
           in accordance with law, as expeditiously as possible.
     3.12. Alleging non-compliance of the order of the learned Single
           Judge dated 24th March 2017, Contempt Petitions being C.C.C.
           No. 2434 of 2018 and C.C.C. No. 18-65 of 2019 came to be
           filed by the land-owners.
     3.13. During the pendency of the Contempt Petitions, the Special
           Land Acquisition Officer-1, KIADB (BMICP), Bengaluru
           (hereinafter, “SLAO”) (Respondent No. 4), on 22nd April 2019,
           passed an Award for payment of compensation in respect of
           lands belonging to the erstwhile land-owners. In terms of the
           legal opinion given by the Advocate General, Respondent No. 4
           decided to postpone the date of Preliminary Notification from
           29th January 2003 to the year 2011 and decided to consider
           the guideline rates prevailing in the said year and formulate
           an award. An amount of Rs. 32,69,45,789/- was, accordingly,
           awarded for 11 Acre 1.25 Guntas of land.
     3.14. In view of the Award dated 22nd April 2019, a compliance report
           along with an endorsement came to be filed by the KIADB in
           the contempt proceedings initiated by the land-owners before
196                                                           [2025] 1 S.C.R.

                       Digital Supreme Court Reports


             the High Court. Therefore, a Division Bench of the High Court,
             vide order dated 27th November 2019, dismissed as withdrawn
             the Contempt Petitions with liberty to challenge the endorsement
             in accordance with law.
       3.15. On 19th June 2019, Respondents No. 6 and 7 (hereinafter
             collectively referred to as “Project Proponents”) filed Writ
             Petitions being W.P. No. 26085 of 2019 and W.P. No. 31407
             of 2019 before the Karnataka High Court challenging several
             Awards passed by the SLAO, including the Award dated 22nd
             April 2019. The Project Proponents were aggrieved by the
             Award dated 22nd April 2019 inasmuch as, on account of delay
             not attributable to them, they are being called upon to pay higher
             compensation. It was their contention that the compensation
             should be determined on the basis of the market value of land
             as on the date of the Preliminary Notification and that the date
             could not have been shifted.
       3.16. On 5 th January 2021, the erstwhile land-owners filed
             impleadment application in the Writ Petitions filed by the
             Project Proponents. The appellants herein, thereafter, filed a
             substantive Writ Petition being W.P. No. 1627 of 2021 on 1st
             June 2021. The appellants were aggrieved by the Award dated
             22nd April 2019 inasmuch as, even though their lands were
             acquired in the year 2003, no compensation for such acquisition
             has been disbursed to the appellants despite a lapse of 18
             years. It was their contention that the compensation should
             be determined as per the current market value of the lands.
       3.17. Vide common judgment and order dated 18th April 2022, a
             learned Single Judge of the Karnataka High Court at Bengaluru
             allowed the Writ Petitions filed by the Project Proponents. The
             High Court quashed the Award dated 22nd April 2019 passed
             by Respondent No. 4 (SLAO). In view of the decision in the
             Writ Petitions filed by the Project Proponents, the Writ Petition
             filed by the appellants herein was disposed of as the same did
             not survive for consideration inasmuch as the Award dated 22nd
             April 2019 was quashed. Ultimately, the High Court directed the
             concerned authorities to pass fresh awards in accordance with
             law and after providing sufficient and reasonable opportunity to
             the parties as expeditiously as possible and at any rate within
             a period of three months.
[2025] 1 S.C.R.                                                           197

                    Bernard Francis Joseph Vaz and Others v.
                      Government of Karnataka and Others

      3.18. Aggrieved thereby, the appellants herein filed a Writ Appeal
            being W.A. No. 678 of 2022 (LA-KIADB). Vide impugned
            judgment and order dated 22nd November 2022, the Division
            Bench of the High Court dismissed the Writ Appeal filed by
            the appellants herein. Hence, the present appeal by way of
            special leave.
4.    We have heard Shri R. Chandrachud, learned counsel appearing on
      behalf of the appellants, Shri Atmaram N. S. Nadkarni, learned Senior
      Counsel for Respondents No. 6 and 7, Shri Avishkar Singhvi, learned
      Additional Advocate General appearing for the State of Karnataka
      and Shri Purushottam Sharma Tripathi for Respondents Nos. 2 to 5.

      SUBMISSIONS:
5.    Shri Chandrachud submitted that the Division Bench of the High Court
      erroneously dismissed the Writ Appeal against the judgment and order
      of the learned Single Judge of the High Court as “premature”. It is
      submitted that the Writ Appeal was not premature as the appellants’
      plea to shift the date for considering the market value of land as
      on the date of the Award and not as on the date of the Preliminary
      Notification was rejected by the learned Single Judge and thus the
      issue stood decided against the appellants. It is further submitted that
      more than 21 years have passed since the Preliminary Notification
      was passed acquiring the appellants lands and they have not received
      any compensation yet for the same. Relying on the judgments of this
      Court in Ram Chand and Others v. Union of India and Others1
      and Tukaram Kana Joshiand Others Through Power-of-Attorney
      Holder v. Maharashtra Industrial Development Corporation and
      Others,2 it is submitted that in exceptional cases, the authorities
      must be directed to determine compensation on the basis of market
      value of the land as on the date of the Award by notionally shifting
      the date of the Preliminary Notification. It is lastly submitted that the
      compensation be determined as per the provisions contained in the
      Right to Fair Compensation and Transparency in Land Acquisition,
      Rehabilitation and Resettlement Act, 2013 (hereinafter, “2013 LA Act”)
      inasmuch as in terms of Section 30 of the KIAD Act, the provisions of



1    1993 INSC 315 : [1993] Supp. 2 SCR 558 : (1994) 1 SCC 44
2    2012 INSC 503 : [2012] 13 SCR 29 : (2013) 1 SCC 353
198                                                              [2025] 1 S.C.R.

                            Digital Supreme Court Reports


       the Land Acquisition Act 1894 (hereinafter, “1894 LA Act”) have been
       made applicable mutatis mutandis for the purposes of determination
       and award of compensation. Reliance in this regard was placed by
       the learned counsel for the appellants on the judgment of this Court
       in Maharashtra State Road Transport Corporation v. State of
       Maharashtra and Others.3
6.     Per contra, Shri Nadkarni for Respondents No. 6 and 7 submitted
       that between 2009 and 2012, the Project Proponents wrote several
       letters to Respondent No. 2 (KIADB) requesting for awards to be
       passed. It is further submitted that as no awards were passed by
       the SLAOs, the Project Proponents were constrained to file Writ
       Petition before the High Court seeking direction to pass awards
       which was allowed in 2013, thereafter, on non-compliance the Project
       Proponents initiated contempt proceedings in 2015 as no awards
       were still passed. It was, therefore, submitted that if this Court is
       inclined to grant any relief in the form of additional compensation
       or direct shifting of date as sought for, it may be seen that there
       was no error or delay on part of the Project Proponents, who have
       deposited compensation with Respondent No.2 (KIADB) as per the
       agreement and therefore any additional liability should fall on the
       State Government and/or the KIADB. Relying on the judgment of
       this Court in Competent Authority v. Barangore Jute Factory
       and Others,4 it is submitted that shifting of date can only take place
       in very rare circumstances. It is further submitted that there is no
       question of awarding compensation under the 2013 LA Act and a
       completely new case has been sought to be made out before this
       Court, which was not contended before the learned Single Judge
       or Division Bench of the High Court. It is lastly submitted that the
       appellants never sought directions to the State Government/SLAO
       to pass awards and that steps in that regard were taken only in the
       year 2021 which was pursuant to the various proceedings initiated
       by the Project Proponents.
7.     Shri Singhvi for Respondent No. 1 submitted that the appellants’
       claims are premature and speculative, as they have yet to exhaust
       remedies available under the ongoing award proceedings. It is further


3    2003 INSC 137 : [2003] 2 SCR 530 : (2003) 4 SCC 200
4    2005 INSC 585 : [2005] Supp. 5 SCR 421 : (2005) 13 SCC 477
[2025] 1 S.C.R.                                                           199

                Bernard Francis Joseph Vaz and Others v.
                  Government of Karnataka and Others

     submitted that the Division Bench of the High Court in the impugned
     judgment and order, expressly held that the issue of shifting the date
     of acquisition notification can only be examined after the award has
     been passed by the SLAO. It was, therefore, submitted that present
     appeal is untenable at this stage.
8.   Shri Purushottam Sharma Tripathi for Respondent Nos. 2 to 5
     submitted that the SLAO passed the Award dated 22nd April 2019,
     on the basis of specific opinion tendered by the learned Advocate
     General with regard to shifting of the date. It is submitted that the
     learned Single Judge of the High Court, upon consideration of the
     material placed before it, has quashed the Award and directed
     the SLAO to pass fresh awards within a stipulated timeframe. It
     is further submitted that pursuant to the directions by the learned
     Single Judge of the High Court, the SLAO has now passed fresh
     awards for the acquired lands and if the appellants are aggrieved
     by the compensation awarded, they may take such steps as are
     permissible in law. It is, therefore, submitted that this Court should
     not interfere with the concurrent findings of the learned Single Judge
     and the Division Bench of the High Court.

     DISCUSSION AND ANALYSIS:
9.   To consider the case of the appellants, it would be appropriate to
     refer to the prayer clause of their Writ Petition before the High Court.
     The appellants herein had filed Writ Petition being W.P. No. 1627
     of 2021 (LA-KIADB) with the following prayers:
           “WHEREFORE, the Petitioners most respectfully prays
           that this Hon’ble Court be pleased to:
           a.   Issue a writ of certiorari or any other writ of the same
                nature to quash and setting aside the Impugned Award
                dated 22.04.2019 passed by the Respondent No. 4
                bearing No. LAQ, SR/39 (26B, 10, 13, 14)/1998-99,
                39 (30, 31, 37, 38, 40)/2002-03 SLAO-1, produced
                at ANNEXURE – A;
           b.   Consequent to prayer (a) issue a writ of mandamus
                or any other writ of the same nature to direct the
                Respondents to issue notice to Petitioners for
                determining compensation and pass the Award as
200                                                        [2025] 1 S.C.R.

                     Digital Supreme Court Reports


                per market value of land closest to date of passing
                the Award;
          c.    Grant such other reliefs as this Hon’ble Court deems
                fit in the above circumstances of the case, in the
                interests of justice and equity.”
10. It is relevant to note that prior to the appellants herein Respondents
    No. 6 and 7 (Project Proponents) had also filed Writ Petitions before
    the High Court. From a perusal of the judgment and order of the
    learned Single Judge dated 18th April 2022, it is clear that the Project
    Proponents by way of Writ Petitions being W.P. No. 26085 of 2019 and
    W.P. No. 31407 of 2019 had also challenged the awards. Therefore,
    in the three writ petitions before the learned Single Judge, a common
    question with regard to the legality, validity and correctness of the
    Award dated 22nd April 2019 was raised.
11. Before adverting to the findings of the learned Single Judge on the
    legality of the Award dated 22nd April 2019, it would be appropriate
    to reproduce certain extracts from the Award, as under:
          “14. Valuation of land:
          In the notification dated: 29/01/2003 issued under
          Section 28(1) of the Survey number lands, based on the
          above sales figures, the value is Rs. 2,90,532/- per acre
          and the guidance value is Rs. 6.00 lakhs. Therefore, if
          the guidance value is Rs. 6.00 lakhs including all other
          allowances, this rate will be found to be real and fair.
          Accordingly, it was decided and declared the award on
          05/07/2018 and submitted for approval.
          Chief Executive Officer and Executive Member wrote
          a letter vide No. KIADB/CEO&EM/16/2019-20 dated
          16/04/2019. Along with the said letter, Government’s
          letter and Advocate General’s opinion are attached, it is
          suggested to prepare the revised award as per the opinion
          given by the Advocate General and submit it for approval.
          In this regard, this office letter No. KIADB/BMICP/LAQ(1)/
          G.I/01/2019-20 dated 22/04/2019 has been written to the
          Special Deputy Commissioner, KIADB (BMICP) seeking
          clarification on other issues that there is no scope for
          revising the current decision. On 22/04/2019 as per the
[2025] 1 S.C.R.                                                          201

                Bernard Francis Joseph Vaz and Others v.
                  Government of Karnataka and Others

           Chief Executive Officer and Executive Member’s letter No.
           KIADB/BMICP/LAQ/CR/31/2013-14 dated 22/04/2019, it
           is said that it has been suggested to submit again as per
           the Advocate General’s opinion and based on the previous
           judgments of the Hon’ble Supreme Court in several cases
           regarding framing of compensatory rate/award in land
           acquisition cases that even for the lands acquired for
           BMICP scheme, it has been again instructed to prepare a
           revised decision immediately as per the rules and submit it
           for the approval of the government. For revising the award
           and not considering the preliminary notification, the
           Advocate General in his legal opinion dated 16/04/2019
           has given the following legal opinion:
                “KIADB and the State do not have any choice
                but to pass the award which may be passed
                taking into account and consideration the
                market value of the property as on date.”
           As per the opinion given by the present Advocate General,
           the award has to be made at current market rate equal to
           the current market rate. In this regard, the Hon’ble Supreme
           Court in several cases has issued preliminary notification,
           final notification and handed over the assets to the Claims
           Department, but in the case where no award has been
           made for ten years, it is appropriate to pay real and fair
           land compensation to the land owners to avoid injustice,
           in such cases, the date of preliminary notification should
           be changed to the date of handing over the assets to the
           Claims Department, which was prevailing on that date. The
           order is to create a judgment considering the market rate.
           The following civil appeal cases of the Hon’ble Supreme
           Court have been perused to form a award in this regard.
           1.   CA No. 7015-7018/2005 (Competent Authority V/s
                Barangore Jute Factory and Others)
           2.   SLP (Civil) No. 1787473/2004 (State of M.P. V/s
                Onkar Prasad Patel)
           3.   CA No. 965/1979 with CA No. 3325/1984,
                2185-87/1980, 2381/1980, SLP No. 12352-53/1984,
202                                                        [2025] 1 S.C.R.

                     Digital Supreme Court Reports


                10572-74/1984 and others (Gauri Shankar Gaur and
                others V/s State of U.P. and others)
          4.    CA No. 2739/2000 with Nos. 2737/2000, 2738/2000,
                2736/2000 Contempt Petition (C) No. 62/1999
                (Haji Saeed Khan and others V/s State of U.P. and
                others).
          In the above cases the Hon’ble Supreme Court has
          ordered to change the preliminary notification to the date
          of handing over of the asset or to an appropriate date
          conducive to giving equitable relief in cases where there
          is severe delay in adjudication.
          Based on the above judgments of the Hon’ble Supreme
          Court, in the present case, the possession of the land was
          handed over on 05/04/2004, 22/11/2005 and 25/11/2005,
          if the award is framed considering the guideline rates
          of 2011 (sic), it is not possible to give real and fair
          compensation to the land owner.
          Therefore, with a view to providing real and fair land
          compensation to the landowners, it was decided to
          postpone the date of preliminary notification to the
          year 2011 and decided to consider the guideline rates
          prevailing in the said year and formulate an award as
          per the legal opinion given by the Advocate General.”
                                                 (emphasis supplied)
12. It can thus be seen that the learned Advocate General rendered an
    opinion on 16th April 2019, wherein it was stated that while passing the
    awards, the market value as on date has to be taken on account of
    enormous delay in passing the awards. KIADB forwarded the opinion
    to the Special Deputy Commissioner (BMICP) and SLAO directing
    them to pass the awards as per the opinion. On 22nd April 2019, the
    SLAO wrote letters to the Special Deputy Commissioner (BMICP)
    raising certain queries with regard to passing of fresh awards and
    the compensation to be calculated in view of awards already passed
    by them and sent for approval on 3rd November 2018. In response
    to the said letters, the CEO of KIADB once again addressed a letter
    dated 22nd April 2019, to the Special Deputy Commissioner (BMICP)
    and the SLAO instructing them to pass the awards as directed in
    the opinion of the learned Advocate General.
[2025] 1 S.C.R.                                                           203

                Bernard Francis Joseph Vaz and Others v.
                  Government of Karnataka and Others

13. It can further be seen that the opinion of the learned Advocate
    General as well as the judgments of this Court referred to in the
    Award were the only two factors that were taken into account for the
    purpose of passing the Award dated 22nd April 2019, by Respondent
    No. 4 (SLAO) by shifting/postponing the date of the Preliminary
    Notification to the year 2011 and by considering the guideline rates
    prevailing in the said year.
14. Aggrieved by the suo-motu shifting/postponing of the date of the
    Preliminary Notification, the Project Proponents, who as a result were
    called upon to pay higher compensation, had filed a Writ Petition
    before the High Court. The appellants herein filed an impleadment
    application in the Writ Petition filed by the Project Proponents so
    also a substantive Writ Petition with prayers referred to hereinbefore.
    Their grievance was two-fold to quash the Award and to direct
    passing of an Award as per market value of land closest to date of
    passing the Award.
15. For the common prayer qua quashing of the Award dated
    22nd April 2019, it will be profitable to refer to the following paragraphs
    of the judgment and order dated 18th April 2022, passed by the
    learned Single Judge of the High Court:
           “17.8 A perusal of the impugned awards will indicate that
           the opinion of the learned Advocate General as well as
           the judgments of the Apex Court referred to in the awards
           were the only two factors that were taken into account
           for the purpose of passing the awards by the SLAOs. As
           stated supra, in so far as the opinion of the learned
           Advocate General is concerned, the same with regard
           to shifting of the date to reckon the market value of
           the land from the date of the preliminary notification
           to a later date is concerned, the said opinion was
           beyond the scope and ambit of the query put forth
           to him and consequently, the said opinion could not
           have been made the basis by the SLAOs to pass the
           impugned awards.
                           X—X —X —X —X —X —X
           17.10 The second factor/circumstance that has been taken
           into account by the SLAOs to shift the date to reckon the
           market value of the lands from the date of the preliminary
204                                                     [2025] 1 S.C.R.

                 Digital Supreme Court Reports


       notification to a later/subsequent dates is by placing
       reliance upon the following decisions of the Apex Court viz.,
            a.    Competent Authority Vs. Barangor Jute Factory
                  C/w State of Madhya Pradesh Vs. Onkar Prasad
                  Patel – (2005) 13 SCC 47
            b.    Gaurishankar Gaur Vs. State of Uttar Pradesh –
                  (1994) 1 SCC 92; and
            c.    Haji Saeed Khan Vs. State of Uttar Pradesh –
                  (2001) 9 SCC 513.
       17.11 In this context, it is relevant to state that as can
       be seen from the aforesaid decisions as well as various
       decisions of the Apex Court as well as this Court referred to
       supra by both sides, that the market value of the acquired
       lands has to be taken as on the date of the preliminary
       notification as contemplated under Section 11 of the
       L.A. Act, 1894; it has been held that under exceptional
       circumstances, where either the Apex Court or High
       Courts came to the conclusion that the acquisition
       proceedings themselves were liable to be quashed
       on account of certain illegalities or infirmities in the
       acquisition process/procedure, it was permissible only
       for the Apex Court in exercise of its powers under
       Article 32/142 or the High Courts under Article 226 of
       the Constitution of India to shift the date to a later/
       subsequent date; however,this power to shift the date
       is available only to either the Apex Court or the High
       Courts and not definitely/certainly to the SLAOs or
       the State Government; in other words, a perusal of
       the decisions referred to supra, will indicate that in
       cases, where the Apex Court as well as this Court
       deemed it necessary to shift the date in order to do
       complete and substantial justice, inherent powers of
       the Courts were invoked and the dates were shifted in
       order to ensure no hardship, loss or prejudice would
       be caused to the land losers.
       17.12 A perusal of the decisions relied upon by the
       SLAOs in the impugned awards referred to supra, will
[2025] 1 S.C.R.                                                             205

               Bernard Francis Joseph Vaz and Others v.
                 Government of Karnataka and Others

           clearly indicate that in the said cases, the Apex Court has
           invoked its extraordinary jurisdiction and powers under
           Article 142 of the Constitution of India and in the peculiar/
           special facts and circumstances obtaining in the said
           cases, the Apex Court had shifted the date to reckon the
           market value. The SLAOs clearly fell in error in placing
           reliance upon the said decisions of the Apex Court for
           the purpose of shifting the date from the date of the
           preliminary notification without appreciating that the
           said shifting of the date by the SLAOs or the State
           Government is not legally permissible in law either
           under the provisions of the L.A. Act, 1894 or the
           KIAD Act or the Rules or by any judicial precedent.
           It is also relevant to state that even as per the aforesaid
           judgments, shifting of the date from the date of the
           preliminary notification to any later/subsequent date has
           been done only up to the date of taking possession from
           the land losers. In the instant case, the impugned awards
           disclose that the SLAOs have shifted the date to a date
           subsequent/later to the date of taking possession. Under
           these circumstances, it is clear that the impugned awards
           purporting to shift the date suffers from several legal and
           factual infirmities and illegalities which vitiate the impugned
           awards, which deserve to be quashed on this ground also.”
                                                   (emphasis supplied)
16. It can thus be seen that the learned Single Judge of the High Court,
    upon appreciation of the material placed on record, was of the
    view that insofar as the opinion of the learned Advocate General
    with regard to shifting of the date of the preliminary notification to
    a later date is concerned, the said opinion was beyond the scope
    and ambit of the query put forth to him and consequently, the said
    opinion could not have been made the basis by the SLAO to pass
    the Award. It is further to be seen that the learned Single Judge
    of the High Court after considering the provisions of 1894 LA Act,
    KIAD Act and various decisions of this Court, observed that the
    market value of the acquired land has to be taken as on the date
    of the preliminary notification as contemplated under Section 11 of
    the 1894 LA Act. Further, the learned Single Judge of the High Court
    observed that only in exceptional circumstances, where either this
206                                                            [2025] 1 S.C.R.

                       Digital Supreme Court Reports


       Court or the High Court comes to the conclusion that the acquisition
       proceedings themselves were liable to be quashed on account of
       certain illegalities or infirmities in the acquisition process/procedure,
       it was permissible only for this Court in exercise of its powers under
       Article 32/142 or the High Courts under Article 226 of the Constitution
       of India to shift the date to a later/subsequent date. It was further
       observed that this power to shift the date is available only to either
       this Court or the High Courts and not definitely/certainly to the SLAOs
       or the State Government.
17. We are in agreement with the findings of the learned Single Judge
    of the High Court, inasmuch as the SLAO cannot shift/postpone
    the date of preliminary notification. In case, upon appreciation of
    the material placed on record if this Court or the High Court, in
    exceptional circumstances, came to the conclusion that the acquisition
    proceedings themselves were liable to be quashed only then by
    exercising inherent powers this Court under Article 32/142 or the
    High Courts under Article 226 of the Constitution of India respectively
    can shift/postpone the date of preliminary notification to a later date.
    In our considered opinion, therefore, the learned Single Judge of
    the High Court rightly came to the conclusion that the Award dated
    22nd April 2019 be quashed and set aside and ordered accordingly.
18. Having decided thus, in the Writ Petitions filed by the Project
    Proponents, the learned Single Judge of the High Court came to
    the conclusion that the Writ Petition filed by the appellants herein
    before the High Court does not survive for consideration and the
    same was, accordingly, disposed of.
19. Aggrieved thereby, the appellants herein filed an intra-court appeal
    being Writ Appeal No. 678 of 2022 (LA-KIADB) before the Division
    Bench of the High Court.
20. The Division Bench of the High Court vide impugned judgment and
    order dated 22nd November 2022 upon consideration of the material
    placed before it, in paragraph 9, observed thus:
            “9. Further, the learned Single Judge held that the SLAO has
            to determine the compensation as on the date of issuing the
            preliminary notification as contemplated under Section 11
            of the Land Acquisition Act, 1894, and not to shift the date
            to a later/subsequent date. The learned Single Judge has
[2025] 1 S.C.R.                                                           207

               Bernard Francis Joseph Vaz and Others v.
                 Government of Karnataka and Others

           set aside the award passed by the SLAO and directed the
           SLAO to reconsider and pass award. The grievance of
           the petitioner regarding shifting the date at any later
           or subsequent date could be considered only if award
           is passed by the SLAO. The SLAO is yet to pass an
           award. The grievance raised by the petitioner in this
           writ appeal is premature. If the petitioner is dissatisfied
           with the award to be passed by the SLAO, liberty is
           reserved to the petitioner to raise the grounds urged
           in this appeal in the appropriate proceedings before
           the appropriate forum. The question of considering the
           shifting of date from the date of preliminary notification to
           any other date would arise only when the award is passed.
           The cause of action arose for the petitioner to raise the
           said issue only after the award is passed. The shifting of
           the date to a later/subsequent date is available only to the
           Hon’ble Apex Court and this Court, but not to the SLAO
           or State Government…”
                                                  (emphasis supplied)
21. It can thus be seen that the Division Bench of the High Court dismissed
    the Writ Appeal on the ground that the learned Single Judge has
    set aside the award passed by the SLAO and directed the SLAO to
    reconsider and pass award and so the grievance regarding shifting
    the date at any later or subsequent date could be considered only
    if an award is passed by the SLAO. The Division Bench of the High
    Court was, therefore, of the opinion that the grievance sought to
    be raised in the writ appeal is premature and that the question of
    considering the shifting of date of preliminary notification to any other
    date would arise only when the award is passed.
22. In the present appeal, it was sought to be contended by the learned
    counsel for the appellants that the Writ Appeal was not pre-mature
    inasmuch as the prayer to shift the date for considering the market
    value of the land as on the date of the award and not as on the date
    of the preliminary notification was rejected by the learned Single
    Judge of the High Court and thus the issue stood decided against the
    appellants, as a consequence of which the cause of action remained.
23. We are of the opinion that the contention of the learned counsel for
    the appellants is liable to be accepted. We say so because upon
208                                                           [2025] 1 S.C.R.

                       Digital Supreme Court Reports


       adjudication of the Writ Petitions filed by the Project Proponents,
       the learned Single Judge of the High Court came to the conclusion
       that the Award dated 22nd April 2019, is liable to be quashed and
       set aside and ordered accordingly. However, upon consideration of
       the extant position of law, the learned Single Judge further directed
       that the SLAO has to determine the compensation as on the date
       of issuance of the preliminary notification and not to shift the date to
       a later/subsequent date. Therefore, the learned Single Judge of the
       High Court while exercising inherent powers under Article 226 of the
       Constitution quashed and set aside the Award dated 22nd April 2019,
       but decided against granting relief to the appellants by shifting/
       postponing the date of the preliminary notification to a later/
       subsequent date. In our opinion, therefore, the cause of action with
       regard to prayer clause (b) of the Writ Petition filed by the appellants
       herein still survives for consideration. The Division Bench of the High
       Court should have, especially taking into consideration the facts and
       circumstances of the present case, at least considered the case of
       the appellants herein with regard to said prayer. We are, therefore,
       of the opinion that the impugned judgment and order dated 22nd
       November 2022, passed by the Division Bench of the High Court is
       liable to be quashed and set aside on this short ground alone. We
       order accordingly.
24. Having set aside the impugned judgment and order passed by the
    Division Bench of the High Court on the aforesaid ground, we shall
    now proceed to examine if the relief sought by the appellants herein
    in prayer clause (b) of the Writ Petition referred to hereinbefore is
    liable to be granted or not.
25. For the purpose of consideration of the relief sought by the appellants
    herein, it will be appropriate to refer to a few judgements of this
    Court on which reliance has been placed by the learned counsel
    for the parties.
26. In the case of Ram Chand (supra), proceedings were instituted for
    quashing the land acquisition proceedings, which had been initiated
    between the years 1959 and 1965 by issuance of notifications under
    Section 4 of the 1894 LA Act but in which no awards were made
    upto the years 1979-80, although the declarations under Section 6
    of the 1894 LA Act had been made in the years 1966 and 1969. The
    question sought to be answered by this Court in the aforesaid case
    was as to if a person is paid compensation in the year 1980/81 at the
[2025] 1 S.C.R.                                                         209

               Bernard Francis Joseph Vaz and Others v.
                 Government of Karnataka and Others

     market rate prevailing twenty years back, will that be in compliance
     of the constitutional and statutory mandate. In this regard, this Court
     observed thus:
           “14. … Ignoring the escalation of the market value of
           the lands, especially near the urban agglomeration
           or metropolitan cities, will amount to ignoring an
           earthquake and courts can certainly take judicial notice
           of the said fact. The interest and the solatium, which have
           to be paid under the provisions of the Act, are linked with
           the market value of the land with reference to the date of
           the notification under sub-section (1) of Section 4 of the
           Act. If a decision had been taken as early as in the year
           1966, by issuance of declarations under Section 6, that
           the lands belonging to the different cultivators, who
           held those lands within the ceiling limit for cultivation,
           were needed for public purpose, respondents should
           have taken steps for completion of the acquisition
           proceedings and payment of compensation at an
           early date. In the present cases, unless a justification is
           furnished on behalf of the respondents, can it be said that
           the statutory power of making an award under Section 11
           has been exercised within a reasonable time from the date
           of the declaration under Section 6? Due to escalation
           in prices of land, more so in this area, during the
           preceding two decades, in reality, the market rate,
           on the date of the notification under Section 4(1) is a
           mere fraction, of the rate prevailing at the time of its
           determination in the Award.”
                                                 (emphasis supplied)
27. It can thus be seen that this Court in the aforesaid case has observed
    that the respondents therein should have taken steps for completion
    of the acquisition proceedings and payment of compensation at an
    early date. It was further observed that due to escalation in prices
    of land, more so in the area in question, during the preceding two
    decades, in reality, the market rate, on the date of the notification
    under Section 4(1) of the 1894 LA Act is a mere fraction of the rate
    prevailing at the time of its determination in the Award. This Court,
    however, in the aforesaid case was also dealing with a challenge to
210                                                          [2025] 1 S.C.R.

                       Digital Supreme Court Reports


       the acquisition proceedings itself. In this regard, this Court observed
       thus:
            “16. On behalf of the respondents, it was pointed out
            that the petitioners have approached this Court only
            after making of the awards, or when awards were to
            be made, having waited for more than fourteen years,
            without invoking the jurisdiction of the High Court under
            Article 226 or of this Court under Article 32. It is true
            that this Court has taken note of delay on the part of
            the petitioners concerned in invoking the jurisdiction
            of the High Court or of this Court for quashing the
            land acquisition proceedings on the ground that the
            proceedings for acquisition of the lands in question
            have remained pending for more than a decade,
            in the cases of Aflatoon v. Lt. Governor of Delhi
            [(1975) 4 SCC 285] and Ramjas Foundation v. Union
            of India [1993 Supp (2) SCC 20 : AIR 1993 SC 852].
            According to us, the question of delay in invoking the writ
            jurisdiction of the High Court under Article 226 or of this
            Court under Article 32, has to be considered along with the
            inaction on the part of the authorities, who had to perform
            their statutory duties. Can the statutory authority take a
            plea that although it has not performed its duty within a
            reasonable time, but it is of no consequence because the
            person, who has been wronged or deprived of his right,
            has also not invoked the jurisdiction of the High Court or
            of this Court for a suitable writ or direction to grant the
            relief considered appropriate in the circumstances? The
            authorities are enjoined by the statute concerned to perform
            their duties within a reasonable time, and as such they are
            answerable to the Court why such duties have not been
            performed by them, which has caused injury to claimants.
            By not questioning, the validity of the acquisition
            proceedings for a long time since the declarations
            were made under Section 6, the relief of quashing the
            acquisition proceedings has become inappropriate,
            because in the meantime, the lands notified have
            been developed and put to public use. The lands are
            being utilised to provide shelter to thousands and to
[2025] 1 S.C.R.                                                          211

                  Bernard Francis Joseph Vaz and Others v.
                    Government of Karnataka and Others

            implement the scheme of a planned city, which is a
            must in the present set-up. The outweighing public
            interest has to be given due weight. That is why this
            Court has been resisting attempts on the part of the
            landholders, seeking quashing of the acquisition
            proceedings on ground of delay in completion of such
            proceedings. But, can the respondents be not directed
            to compensate the petitioners, who were small cultivators
            holding lands within the ceiling limit in and around Delhi,
            for the injury caused to them, not by the provisions of the
            Act, but because of the non-exercise of the power by the
            authorities under the Act within a reasonable time?”
                                                 (emphasis supplied)
28. It can thus be seen that this Court in the aforesaid case observed
    that by not questioning the validity of the acquisition proceedings
    for a long time since the declarations were made under Section 6 of
    the 1894 LA Act, the relief of quashing the acquisition proceedings has
    become inappropriate, because in the meantime, the lands notified
    have been developed and put to public use. It was further observed
    that the lands are being utilized to provide shelter to thousands and
    to implement the scheme of a planned city, which is a must in the
    present set-up and that the outweighing public interest has to be
    given due weight.
29. Ultimately, this Court in paragraph 27 of the aforesaid case, taking
    into consideration the interest of the public, instead of quashing the
    proceedings for acquisition, directed that the petitioners therein shall
    be paid an additional amount of compensation to be calculated at the
    rate of 12% per annum, after expiry of two years from August 23, 1974,
    till the date of the making of the awards by the Collector, to be
    calculated with reference to the market value of the lands in question
    on the date of the notifications under sub-section (1) of Section 4
    of the 1894 LA Act.
30. In the case of Haji Saeed Khan and Others v. State of U.P. and
    Others,5 land was acquired for the purposes of construction of a
    housing colony under the “Planned Development Scheme” in Village


5   (2001) 9 SCC 513
212                                                          [2025] 1 S.C.R.

                       Digital Supreme Court Reports


       Dhimri Pargana, District Moradabad by the Moradabad Development
       Authority. The challenge to the land acquisition proceedings before
       the High Court in the aforesaid case was dismissed. Aggrieved
       thereby, this Court was called upon to adjudicate the lis. This Court,
       having regard to the peculiar facts of the aforesaid case, instead
       of deciding the matter on merits, suggested to the counsel on both
       sides that it would be reasonable in the interests of justice if they
       agreed that the market value of the property could be fixed by treating
       15th June, 1998, i.e., the date of taking possession as the date of
       notification under Section 4(1) of the 1894 LA Act instead of the
       actual date of notification under Section 4(1) of the 1894 LA Act i.e.,
       30th March, 1995. When the suggestion came from the Bench, the
       counsel appearing on both sides accepted the suggestion from the
       Court. Accordingly, this Court upheld the judgment and order of the
       High Court, thereby the land acquisition proceedings were upheld
       with modification to the limited extent qua the date of notification
       under Section 4(1) of the 1894 LA Act shifted to the date of taking
       possession.
31. In the case of Barangore Jute Factory (supra), the subject matter
    of the appeals before this Court was the compulsory acquisition of
    certain lands by the Central Government by a notification dated 11th
    June 1998 under Section 3-A of the National Highways Act, 1956
    (hereinafter, “NH Act”). The landowners challenged the acquisition
    of their land on various grounds before the Calcutta High Court. The
    Division Bench of the High Court by a judgment and order dated
    7th April 2004, disposed of the writ-petition holding the impugned
    notification regarding compulsory acquisition of land to be bad in law,
    however, keeping in view the fact that possession of the acquired
    land had already been taken by the authorities, the High Court felt
    that no useful purpose would be served by quashing the notification.
    The High Court also took note of the power of the acquiring authority
    to issue a fresh notification for acquisition of the land which could
    only lead to possible increase in the amount of compensation
    payable to the owners. Keeping these aspects in view, it ordered
    that an additional amount of compensation (calculated at 30% over
    and above the above the compensation already determined) be
    awarded to the landowners. Aggrieved by the judgment and order
    of the Calcutta High Court, three appeals by way of special leave
    were filed before this Court. The first by the competent authority qua
[2025] 1 S.C.R.                                                              213

               Bernard Francis Joseph Vaz and Others v.
                 Government of Karnataka and Others

     validity of acquisition notification, second by the National Highways
     Authority of India (hereinafter, “NHAI”) qua award of additional
     compensation to the landowners and third by the landowners qua
     the acquisition notification not being quashed in spite of having been
     declared as illegal.
32. The acquisition of land in the aforesaid case was under the NH Act.
    The power to acquire land is contained in Section 3-A of the NH Act.
    According to sub-section (1) of Section 3-A of the NH Act, where the
    Central Government is satisfied that for a public purpose any land is
    required for building, maintenance, management or operation of a
    national highway or part thereof, it may, by notification in the Official
    Gazette, declare its intention to acquire such land. Sub-section (2)
    of Section 3-A of the NH Act provides that every notification under
    sub-section (1) thereof shall give a brief description of land. Under
    sub-section (3) of Section 3-A of the NH Act, the competent authority
    is required to cause the substance of the notification to be published in
    two local newspapers, one of which will be in a vernacular language.
    The acquisition notification in the aforesaid case was challenged on
    the ground that it does not give a brief description of the land sought
    to be compulsorily acquired. This Court, upon consideration of the
    acquisition notification, observed thus:
           “5. …So far as the question whether the impugned
           notification meets the requirement of Section 3-A(1) of the
           Act regarding giving brief description of land is concerned,
           we have already shown that even though plot numbers of
           lands in respect of each mouza are given, different pieces
           of land are acquired either as whole or in part. Wherever
           the acquisition is of a portion of a bigger piece of land, there
           is no description as to which portion was being acquired.
           Unless it is known as to which portion was to be acquired,
           the petitioners would be unable to understand the impact
           of acquisition or to raise any objection about user of the
           acquired land for the purposes specified under the Act or
           to make a claim for compensation. It is settled law that
           where a statute requires a particular act to be done in a
           particular manner, the act has to be done in that manner
           alone. Every word of the statute has to be given its due
           meaning. In our view, the impugned notification fails to
           meet the statutory mandate. It is vague. The least that is
214                                                           [2025] 1 S.C.R.

                     Digital Supreme Court Reports


          required in such cases is that the acquisition notification
          should let the person whose land is sought to be acquired
          know what he is going to lose. The impugned notification
          in this case is, therefore, not in accordance with the law.”
33. It can thus be seen that this Court in the aforesaid case observed
    that it is settled law that where a statute requires a particular act to
    be done in a particular manner, the act has to be done in that manner
    alone. It can further be seen that this Court held that the acquisition
    notification therein failed to meet the statutory mandate and that it
    was vague. It was further held that the least that was required was
    that the acquisition notification therein should have let the person
    whose land was sought to be acquired know what he was going to
    lose. It was, therefore, held that the acquisition notification was not
    in accordance with law.
34. Having held that the notification regarding acquisition of land was
    invalid because it failed to meet the statutory requirements and also
    having found that taking possession of the land of the landowners in
    the aforesaid case in pursuance to the acquisition notification was not
    in accordance with law, the question that arose for the consideration
    of this Court was as to what relief can be granted to the landowners.
    In that regard, this Court observed thus:
          “14. … The High Court rightly observed that the acquisition
          of land in the present case was for a project of great
          national importance i.e. the construction of a national
          highway. The construction of a national highway on the
          acquired land has already been completed as informed
          to us during the course of hearing. No useful purpose will
          be served by quashing the impugned notification at this
          stage. We cannot be unmindful of the legal position that
          the acquiring authority can always issue a fresh notification
          for acquisition of the land in the event of the impugned
          notification being quashed. The consequence of this will
          only be that keeping in view the rising trend in prices of land,
          the amount of compensation payable to the landowners
          may be more. Therefore, the ultimate question will be about
          the quantum of compensation payable to the landowners.
          Quashing of the notification at this stage will give rise to
          several difficulties and practical problems. Balancing the
[2025] 1 S.C.R.                                                            215

                 Bernard Francis Joseph Vaz and Others v.
                   Government of Karnataka and Others

           rights of the petitioners as against the problems involved
           in quashing the impugned notification, we are of the view
           that a better course will be to compensate the landowners,
           that is, the writ petitioners appropriately for what they have
           been deprived of. Interests of justice persuade us to adopt
           this course of action.”
35. It can thus be seen that this Court in the aforesaid case observed
    that the Calcutta High Court rightly observed that the acquisition
    of land was for a project of great national importance i.e., the
    construction of a national highway. This Court further observed
    that the construction of a national highway on the acquired land
    had already been completed. It was further observed that no useful
    purpose would be served by quashing the acquisition notification at
    this stage. Pertinently, this Court observed that the acquiring authority
    could always issue a fresh notification for acquisition of the land in
    the event the acquisition notification therein was quashed and that the
    consequence of that would only be that the amount of compensation
    payable to the landowners may be more. Therefore, this Court
    observed that the ultimate question would be about the quantum
    of compensation payable to the landowners. Having observed so,
    this Court held that the better course would be to compensate the
    landowners appropriately for what they have been deprived of and
    that the interests of justice persuade this Court to adopt that course
    of action. The relief, therefore, granted by this Court in the aforesaid
    case was molded in the form of paragraph 15, which reads as under:
           “15. Normally, compensation is determined as per
           the market price of land on the date of issuance of
           the notification regarding acquisition of land. There
           are precedents by way of judgments of this Court
           where in similar situations instead of quashing the
           impugned notification, this Court shifted the date of
           the notification so that the landowners are adequately
           compensated. Reference may be made to:
           (a)   Ujjain Vikas Pradhikaran v. Raj Kumar Johri [(1992)
                 1 SCC 328]
           (b)   Gauri Shankar Gaur v. State of U.P. [(1994) 1 SCC 92]
           (c)   Haji Saeed Khan v. State of U.P. [(2001) 9 SCC 513]
216                                                       [2025] 1 S.C.R.

                    Digital Supreme Court Reports


          In that direction the next step is what should be
          the crucial date in the facts of the present case for
          determining the quantum of compensation. We feel
          that the relevant date in the present case ought to
          be the date when possession of the land was taken
          by the respondents from the writ petitioners. This
          date admittedly is 19-2-2003. We, therefore, direct
          that compensation payable to the writ petitioners
          be determined as on 19-2-2003, the date on which
          they were deprived of possession of their lands.
          We do not quash the impugned notification in order
          not to disturb what has already taken place by way
          of use of the acquired land for construction of the
          national highway. We direct that the compensation
          for the acquired land be determined as on 19-2-2003
          expeditiously and within ten weeks from today and the
          amount of compensation so determined, be paid to the
          writ petitioners after adjusting the amount already paid by
          way of compensation within eight weeks thereafter. The
          claim of interest on the amount of compensation so
          determined is to be decided in accordance with law
          by the appropriate authority. We express no opinion
          about other statutory rights, if any, available to the
          parties in this behalf and the parties will be free to
          exercise the same, if available. The compensation as
          determined by us under this order along with other
          benefits, which the respondents give to parties whose
          lands are acquired under the Act, should be given to
          the writ petitioners along with what has been directed
          by us in this judgment.”
                                               (emphasis supplied)
36. It can thus be seen that this Court in the aforesaid case observed
    that normally, compensation is determined as per the market
    price of land on the date of issuance of the notification regarding
    acquisition of land but there are judgments of this Court where in
    similar situations instead of quashing the impugned notification, this
    Court shifted the date of the notification so that the landowners are
    adequately compensated. This Court directed that compensation
    payable to the landowners be determined as on the date when
[2025] 1 S.C.R.                                                         217

               Bernard Francis Joseph Vaz and Others v.
                 Government of Karnataka and Others

     possession of land was taken by the respondents therein i.e.,
     19th February 2003.
37. In the case of Tukaram Kana Joshi (supra), the land situated in
    Village Shirwame, Taluka and District Thane, stood notified under
    Section 4 of the 1894 LA Act on 6th June 1964 for establishment
    of Ulhas Khore Project i.e., a project for industrial development.
    However, no subsequent proceedings were taken up thereafter,
    and the acquisition proceedings lapsed. The respondent-authorities
    therein realised, in 1981, that grave injustice had been done to the
    appellants therein and so a fresh notification under Section 4 of
    the 1894 LA Act was issued on 14th May 1981. However, no further
    proceedings were initiated and therefore, such proceedings also
    died a natural death. In the aforesaid case, when the appellants
    therein reached this Court, this Court in unequivocal terms observed
    that even after the right to property ceased to be a fundamental
    right, taking possession of or acquiring the property of a citizen
    most certainly tantamounts to deprivation and such deprivation
    can take place only in accordance with “law”, as the said word
    has specifically been used in Article 300-A of the Constitution. In
    paragraph 22 of the aforesaid case, this Court observed that the
    concerned-State therein came forward with a welcome suggestion
    stating that in order to redress the grievances of the appellants
    therein, the respondent authorities would notify the land in dispute
    under Section 4 of the 1894 LA Act and that the market value of
    the land in dispute would be assessed as it prevails on the date
    on which Section 4 notification is again published in the Official
    Gazette.
38. In the aforesaid case of Tukaram Kana Joshi (supra), this Court
    observed that the right to property is now considered to be not only
    a constitutional or a statutory right but also a “human right”. It was
    further observed that human rights are considered in the realm of
    individual rights, such as right to health, right to livelihood, right to
    shelter and employment, etc. This Court further observed that now,
    however, human rights are gaining an even greater multifaceted
    dimension and that the right to property is considered very much to
    be a part of such new dimension.
39. It would be appropriate to refer to two recent pronouncements of
    this Court on the right to property.
218                                                             [2025] 1 S.C.R.

                           Digital Supreme Court Reports


40. This Court, in the case of Vidya Devi v. State of Himachal Pradesh
    and Others,6 while surveying the earlier judgments on the issue,
    has observed thus:
            “12.1. The appellant was forcibly expropriated of her
            property in 1967, when the right to property was a
            fundamental right guaranteed by Article 31 in Part III
            of the Constitution. Article 31 guaranteed the right to
            private property [State of W.B. v. Subodh Gopal Bose
            (1953) 2 SCC 688 : AIR 1954 SC 92], which could not be
            deprived without due process of law and upon just and
            fair compensation.
            12.2. The right to property ceased to be a fundamental
            right by the Constitution (Forty-Fourth Amendment) Act,
            1978, however, it continued to be a human right [Tukaram
            Kana Joshi v. MIDC (2013) 1 SCC 353 : (2013) 1 SCC
            (Civ) 491] in a welfare State, and a constitutional right
            under Article 300-A of the Constitution. Article 300-A
            provides that no person shall be deprived of his property
            save by authority of law. The State cannot dispossess
            a citizen of his property except in accordance with the
            procedure established by law. The obligation to pay
            compensation, though not expressly included in Article
            300-A, can be inferred in that Article. [K.T. Plantation
            (P) Ltd. v. State of Karnataka (2011) 9 SCC 1 : (2011)
            4 SCC (Civ) 414]
            12.3. To forcibly dispossess a person of his private
            property, without following due process of law, would be
            violative of a human right, as also the constitutional right
            under Article 300-A of the Constitution. Reliance is placed
            on the judgment in Hindustan Petroleum Corpn. Ltd. v.
            Darius Shapur Chenai [Hindustan Petroleum Corpn. Ltd.
            v. Darius Shapur Chenai (2005) 7 SCC 627], wherein this
            Court held that: (SCC p. 634, para 6)
                    “6. … Having regard to the provisions contained
                    in Article 300-A of the Constitution, the State in


6   2020 INSC 23 : [2020] 1 SCR 749 : (2020) 2 SCC 569
[2025] 1 S.C.R.                                                        219

               Bernard Francis Joseph Vaz and Others v.
                 Government of Karnataka and Others

                exercise of its power of “eminent domain” may
                interfere with the right of property of a person
                by acquiring the same but the same must be for
                a public purpose and reasonable compensation
                therefor must be paid.”
                                                  (emphasis supplied)
           12.4. In N. Padmamma v. S. Ramakrishna Reddy
           [N. Padmamma v. S. Ramakrishna Reddy (2008) 15 SCC
           517], this Court held that: (SCC p. 526, para 21)
                “21. If the right of property is a human right
                as also a constitutional right, the same cannot
                be taken away except in accordance with law.
                Article 300-A of the Constitution protects such
                right. The provisions of the Act seeking to divest
                such right, keeping in view of the provisions of
                Article 300-A of the Constitution of India, must
                be strictly construed.”
                                                  (emphasis supplied)
           12.5. In Delhi Airtech Services (P) Ltd. v. State of
           U.P. [Delhi Airtech Services (P) Ltd. v. State of U.P.
           (2011) 9 SCC 354 : (2011) 4 SCC (Civ) 673], this Court
           recognised the right to property as a basic human right in
           the following words: (SCC p. 379, para 30)
                “30. It is accepted in every jurisprudence and
                by different political thinkers that some amount
                of property right is an indispensable safeguard
                against tyranny and economic oppression of
                the Government. Jefferson was of the view that
                liberty cannot long subsist without the support
                of property. “Property must be secured, else
                liberty cannot subsist” was the opinion of John
                Adams. Indeed the view that property itself
                is the seed-bed which must be conserved if
                other constitutional values are to flourish, is the
                consensus among political thinkers and jurists.”
                                                  (emphasis supplied)
220                                                      [2025] 1 S.C.R.

                  Digital Supreme Court Reports


       12.6. In Jilubhai Nanbhai Khachar v. State of Gujarat
       [Jilubhai Nanbhai Khachar v. State of Gujarat, 1995 Supp
       (1) SCC 596], this Court held as follows: (SCC p. 627,
       para 48)
            “48. … In other words, Article 300-A only limits
            the powers of the State that no person shall
            be deprived of his property save by authority
            of law. There has to be no deprivation without
            any sanction of law. Deprivation by any other
            mode is not acquisition or taking possession
            under Article 300-A. In other words, if there is
            no law, there is no deprivation.”
                                              (emphasis supplied)
       12.7. In this case, the appellant could not have been forcibly
       dispossessed of her property without any legal sanction,
       and without following due process of law, and depriving
       her payment of just compensation, being a fundamental
       right on the date of forcible dispossession in 1967.
       12.8. The contention of the State that the appellant or her
       predecessors had “orally” consented to the acquisition is
       completely baseless. We find complete lack of authority
       and legal sanction in compulsorily divesting the appellant
       of her property by the State.
       12.9. In a democratic polity governed by the rule of law,
       the State could not have deprived a citizen of their property
       without the sanction of law. Reliance is placed on the
       judgment of this Court in Tukaram Kana Joshi v. MIDC
       [Tukaram Kana Joshi v. MIDC (2013) 1 SCC 353 : (2013)
       1 SCC (Civ) 491] wherein it was held that the State must
       comply with the procedure for acquisition, requisition, or
       any other permissible statutory mode. The State being a
       welfare State governed by the rule of law cannot arrogate to
       itself a status beyond what is provided by the Constitution.
       12.10. This Court in State of Haryana v. Mukesh Kumar
       [State of Haryana v. Mukesh Kumar (2011) 10 SCC 404 :
       (2012) 3 SCC (Civ) 769] held that the right to property is
       now considered to be not only a constitutional or statutory
[2025] 1 S.C.R.                                                              221

                  Bernard Francis Joseph Vaz and Others v.
                    Government of Karnataka and Others

            right, but also a human right. Human rights have been
            considered in the realm of individual rights such as right to
            shelter, livelihood, health, employment, etc. Human rights
            have gained a multi-faceted dimension.
            ………………
            12.13. In a case where the demand for justice is so
            compelling, a constitutional court would exercise its
            jurisdiction with a view to promote justice, and not defeat it.
            [P.S. Sadasivaswamy v. State of T.N. (1975) 1 SCC 152 :
            1975 SCC (L&S) 22]”
41. In the case of Ultra-Tech Cement Ltd. v. Mast Ram and Others,7
    this Court observed thus:
            “D. Role of the State under Article 300-A of the
            Constitution
            43. The Right to Property in our country is a net of
            intersecting rights which has been explained by this Court
            in Kolkata Municipal Corporation v. Bimal Kumar Shah,
            2024 SCC OnLine SC 968. A division bench of this Court
            identified seven non-exhaustive sub-rights that accrue to
            a landowner when the State intends to acquire his/her
            property. The relevant observations of this Court under
            the said judgment are reproduced below:
                   “…27.
                   … Seven such sub-rights can be identified, albeit
                   non-exhaustive. These are : i) duty of the State
                   to inform the person that it intends to acquire
                   his property - the right to notice, ii) the duty of
                   the State to hear objections to the acquisition -
                   the right to be heard, iii) the duty of the State
                   to inform the person of its decision to acquire -
                   the right to a reasoned decision, iv) the duty of
                   the State to demonstrate that the acquisition
                   is for public purpose - the duty to acquire only
                   for public purpose, v) the duty of the State


7   2024 INSC 709 : [2024] 9 SCR 443 : 2024 SCC OnLine 2598
222                                                    [2025] 1 S.C.R.

                 Digital Supreme Court Reports


            to restitute and rehabilitate - the right of
            restitution or fair compensation, vi) the
            duty of the State to conduct the process of
            acquisition efficiently and within prescribed
            timelines of the proceedings - the right to
            an efficient and expeditious process, and
            vii) final conclusion of the proceedings leading
            to vesting - the right of conclusion…”
                                            [Emphasis Supplied]
       This Court held that a fair and reasonable compensation
       is the sine qua non for any acquisition process.
       44. In Roy Estate v. State of Jharkhand (2009) 12 SCC 194;
       Union of India v. Mahendra Girji (2010) 15 SCC 682
       and Mansaram v. S.P. Pathak (1984) 1 SCC 125, this
       Court underscored the importance of following timelines
       prescribed by the statutes as well as determining and
       disbursing compensation amount expeditiously within
       reasonable time.
       45. The subject land came to be acquired by invoking
       special powers in cases of urgency under Section 17(4) of
       the 1894 Act. The invocation of Section 17(4) extinguishes
       the statutory avenue for the landowners under Section 5A
       to raise objections to the acquisition proceedings. These
       circumstances impose onerous duty on the State to
       facilitate justice to the landowners by providing them with
       fair and reasonable compensation expeditiously. The seven
       sub-rights of the landowners identified by this Court in
       Kolkata Municipal Corporation (supra) are corresponding
       duties of the State. We regret to note that the amount of
       Rs. 3,05,31,095/- determined as compensation under the
       Supplementary Award has not been paid to the landowners
       for a period of more than two years and the State of
       Himachal Pradesh as a welfare State has made no effort
       to get the same paid at the earliest.
       46. This Court has held in Dharnidhar Mishra (D) v. State
       of Bihar, 2024 SCC OnLine SC 932 and State of Haryana
       v. Mukesh Kumar (2011) 10 SCC 404 that the right to
[2025] 1 S.C.R.                                                          223

               Bernard Francis Joseph Vaz and Others v.
                 Government of Karnataka and Others

           property is now considered to be not only a constitutional
           or statutory right, but also a human right. This Court held
           in Tukaram Kana Joshi thr. Power of Attorney Holder v.
           M.I.D.C. (2013) 1 SCC 353 that in a welfare State, the
           statutory authorities are legally bound to pay adequate
           compensation and rehabilitate the persons whose lands
           are being acquired. The non-fulfilment of such obligations
           under the garb of industrial development, is not permissible
           for any welfare State as that would tantamount to uprooting
           a person and depriving them of their constitutional/human
           right.
           47. That time is of the essence in determination and
           payment of compensation is also evident from this Court’s
           judgment in Kukreja Construction Company v. State of
           Maharashtra, 2024 SCC OnLine SC 2547 wherein it
           has been held that once the compensation has been
           determined, the same is payable immediately without
           any requirement of a representation or request by the
           landowners and a duty is cast on the State to pay such
           compensation to the land losers, otherwise there would
           be a breach of Article 300-A of the Constitution.
           48. In the present case, the Government of Himachal
           Pradesh as a welfare State ought to have proactively
           intervened in the matter with a view to ensure that the
           requisite amount towards compensation is paid at the
           earliest. The State cannot abdicate its constitutional and
           statutory responsibility of payment of compensation by
           arguing that its role was limited to initiating acquisition
           proceedings under the MOU signed between the Appellant,
           JAL and itself. We find that the delay in the payment
           of compensation to the landowners after taking away
           ownership of the subject land from them is in contravention
           to the spirit of the constitutional scheme of Article 300A
           and the idea of a welfare State.
           49. Acquisition of land for public purpose is undertaken
           under the power of eminent domain of the government
           much against the wishes of the owners of the land which
           gets acquired. When such a power is exercised, it is
224                                                      [2025] 1 S.C.R.

                    Digital Supreme Court Reports


          coupled with a bounden duty and obligation on the part
          of the government body to ensure that the owners whose
          lands get acquired are paid compensation/awarded amount
          as declared by the statutory award at the earliest.
          50. The State Government, in peculiar circumstances,
          was expected to make the requisite payment towards
          compensation to the landowners from its own treasury and
          should have thereafter proceeded to recover the same from
          JAL. Instead of making the poor landowners to run after
          the powerful corporate houses, it should have compelled
          JAL to make the necessary payment.”
42. Right to Property ceased to be a Fundamental Right by the Constitution
    (Forty-Fourth Amendment) Act, 1978, however, it continues to be a
    human right in a welfare State, and a constitutional right under
    Article 300-A of the Constitution.
43. Article 300-A of the Constitution provides that no person shall be
    deprived of his property save by authority of law. The State cannot
    dispossess a citizen of his property except in accordance with the
    procedure established by law.
44. This Court in the aforesaid case of Vidya Devi (supra) observed that
    in a democratic polity governed by the rule of law, the State could
    not have deprived a citizen of their property without the sanction
    of law. It was further observed that the State being a welfare State
    governed by the rule of law cannot arrogate to itself a status beyond
    what is provided by the Constitution.
45. Recently, this Court in the aforesaid case of Ultra-Tech Cement
    Ltd. (supra) observed that the Government as a welfare State
    ought to have proactively intervened in the matter with a view
    to ensure that the requisite amount towards compensation is
    paid at the earliest. It was further observed that the State cannot
    abdicate its constitutional and statutory responsibility of payment
    of compensation by arguing that its role was limited to initiating
    acquisition proceedings. It was, therefore, observed that the delay
    in the payment of compensation, in accordance with law, to the
    landowners after taking away ownership of the subject land from
    them is in contravention to the spirit of the constitutional scheme
    of Article 300-A and the idea of a welfare State.
[2025] 1 S.C.R.                                                         225

                   Bernard Francis Joseph Vaz and Others v.
                     Government of Karnataka and Others

46. In the aforesaid case of Ultra-Tech Cement Ltd. (supra), this
    Court further observed that acquisition of land for public purpose is
    undertaken under the power of eminent domain of the government
    much against the wishes of the owners of the land which gets
    acquired. It was, therefore, observed that when such a power is
    exercised, it is coupled with a bounden duty and obligation on the
    part of the government body to ensure that the owners whose lands
    get acquired are paid compensation/awarded amount as declared
    by the statutory award at the earliest.
47. It will also be appropriate for the purpose of the present discussion to
    refer to the judgment of this Court, in the case of K. Krishna Reddy
    and Others v. Special Deputy Collector, Land Acquisition Unit II,
    LMD Karimnagar, Andhra Pradesh,8 specifically in paragraph 12,
    observed thus:
            “12. We can very well appreciate the anxiety and need
            of claimants to get compensation here and now. No
            matter what it is. The lands were acquired as far back in
            1977. One decade has already passed. Now the remand
            means another round of litigation. There would be further
            delay in getting the compensation. After all money is what
            money buys. What the claimants could have bought with
            the compensation in 1977 cannot do in 1988. Perhaps,
            not even one half of it. It is a common experience that
            the purchasing power of rupee is dwindling. With rising
            inflation, the delayed payment may lose all charms and
            utility of the compensation. In some cases, the delay may
            be detrimental to the interests of claimants. The Indian
            agriculturists generally have no avocation. They totally
            depend upon land. If uprooted, they will find themselves
            nowhere. They are left high and dry. They have no
            savings to draw. They have nothing to fall back upon.
            They know no other work. They may even face starvation
            unless rehabilitated. In all such cases, it is of utmost
            importance that the award should be made without delay.
            The enhanced compensation must be determined without
            loss of time. The appellate power of remand, at any rate


8   1988 INSC 265 : [1988] Supp. 2 SCR 853 : (1988) 4 SCC 163
226                                                        [2025] 1 S.C.R.

                    Digital Supreme Court Reports


          ought not to be exercised lightly. It shall not be resorted
          to unless the award is wholly unintelligible. It shall not be
          exercised unless there is total lack of evidence. If remand
          is imperative, and if the claim for enhanced compensation
          is tenable, it would be proper for the appellate court to
          do modest best to mitigate hardships. The appellate court
          may direct some interim payment to claimants subject to
          adjustment in the eventual award.”
48. It cannot be gainsaid that the appellants herein have been deprived
    of their legitimate dues for almost 22 years ago. It can also not be
    controverted that money is what money buys. The value of money
    is based on the idea that money can be invested to earn a return,
    and that the purchasing power of money decreases over time due
    to inflation. What the appellants herein could have bought with the
    compensation in 2003 cannot do in 2025. It is, therefore, of utmost
    importance that the determination of the award and disbursal of
    compensation in case of acquisition of land should be made with
    promptitude.
49. We find that in the present case, the appellants were required to
    knock at the doors of the courts on number of occasions during
    the period of last twenty-two years. The appellants have been
    deprived of their property without paying any compensation for
    the same in the said period of last twenty-two years. As already
    discussed hereinabove, the appellants had purchased the plots
    in question for construction of residential houses. Not only have
    they not been able to construct, but they have also not been even
    paid any compensation for the same. As discussed hereinabove,
    though Right to Property is no more a fundamental right, in view
    of the provisions of Article 300-A of the Constitution of India, it is
    a constitutional right. A person cannot be deprived of his property
    without him being paid adequate compensation in accordance with
    law for the same.
50. In the present case, it can clearly be seen that there is no delay
    which can be attributed to the appellants in not getting compensation,
    but it was on account of the lethargic attitude of the officers of the
    State/KIADB that the appellants were deprived of compensation.
51. Only after the notices were issued in the contempt proceedings,
    the compensation was determined by the SLAO on 22nd April 2019
[2025] 1 S.C.R.                                                       227

               Bernard Francis Joseph Vaz and Others v.
                 Government of Karnataka and Others

     taking guideline values prevailing in the year 2011 for determining
     the market value of the acquired land.
52. No doubt that as already observed by us hereinabove, we do not
    find any error in the approach adopted by the learned Single Judge
    of the High Court in holding that the SLAO could not have shifted
    the date and it could have been done only by this Court in exercise
    of powers under Article 32/142 of the Constitution of India or by the
    High Court under Article 226 of the Constitution of India. However,
    the learned Single Judge of the High Court instead of relegating the
    appellants to again go through the rigors of determination by SLAO,
    ought to have exercised powers under Article 226 of the Constitution
    to do complete justice. Even the Division Bench of the High Court
    on a hyper technical ground has non-suited the appellants.
53. In that view of the matter, we find that it is a fit case wherein this
    Court in exercise of its powers under Article 142 of the Constitution
    should direct shifting of the date for determination of the market
    value of the land in question of the appellants.
54. If the compensation to be awarded at the market value as of the
    year 2003 is permitted, it would amount to permitting a travesty of
    justice and making the constitutional provisions under Article 300-A
    a mockery.
55. Since the State/KIADB was in deep slumber from 2003 to 2019 and
    acted for the first time only after the notices were issued in contempt
    proceedings, we find that though SLAO had no power to shift the
    date for determination of market value, he had rightly done so. The
    learned Single Judge of the High Court also does not say that the
    determination of compensation to be awarded by shifting of the date
    by the SLAO to that of 2011 was unjust but only sets aside the award
    on the ground that SLAO had no jurisdiction to do so.
56. There is another reason for doing so. If on account of the inordinate
    delay in paying the compensation and thereby depriving the
    constitutional right to the appellants under Article 300-A, the land
    acquisition proceedings are quashed, the only recourse available to
    the State/KIADB in order to save the project will be to now issue a
    fresh acquisition notification by invoking the provisions as applicable
    under the 2013 LA Act which would entail huge expenditure to the
    public exchequer.
228                                                             [2025] 1 S.C.R.

                        Digital Supreme Court Reports


57. We, therefore, in exercise of power of this Court under Article 142 of
    the Constitution of India, find it appropriate in the interest of justice that
    the SLAO be directed to determine the compensation to be awarded
    to the appellants herein on the basis of the market value prevailing
    as on 22nd April 2019. The appellants shall also be entitled to all the
    statutory benefits as are available to them under the 1894 LA Act.
    This shall be without prejudice to the rights/contentions of either
    party, in case they make a reference before an appellate authority,
    if they are so aggrieved by the fresh determination of compensation
    by the SLAO. We further clarify that, any other award which may
    have been passed pursuant to the directions of the learned Single
    Judge of the High Court shall stand nullified by this judgment.
58. Respondent Nos.6 and 7 contend that they cannot be imposed with
    a liability for this huge additional expenditure. It is their contention
    that the delay in determination of compensation and payment of the
    same is not attributable to them but is on account of inaction on the
    part of the State and KIADB. We clarify that we are not observing
    anything about the inter se dispute between the State and KIADB
    on the one hand and Respondent Nos.6 and 7 on the other hand,
    inasmuch as the same shall be governed by the FWA and/or any
    other agreement between them. We only say that Respondent Nos.6
    and 7, will be at liberty to take recourse to such remedies as are
    available to them in law for redressal of their inter se dispute.
59. In the result, the appeal is disposed of in the following terms:
       (i)    The judgment and order passed by the Division Bench of the
              High Court dated 22nd November 2022 in Writ Appeal No. 678
              of 2022 (LA-KIADB) is quashed and set aside;
       (ii)   The writ petition filed by the appellants herein before the High
              Court being W.P. No. 1627 of 2021 is allowed;
       (iii) The SLAO shall pass a fresh award taking the market value
             prevailing as on 22nd April 2019 within a period of two months
             from today after hearing the parties;
       (iv) The appellants herein shall be entitled to all statutory benefits
            as are available to them in law;
       (v)    The rights of parties to challenge the award in reference, if they
              are aggrieved by it, shall remain open; and
[2025] 1 S.C.R.                                                   229

                  Bernard Francis Joseph Vaz and Others v.
                    Government of Karnataka and Others

     (vi) As we have not expressed our opinion on the claims, if any,
          of Respondent Nos.6 and 7 against the State/KIADB qua the
          delay in passing the award by the SLAO, Respondent Nos. 6
          and 7 are at liberty to take such steps as are permissible in
          law in case they are aggrieved by the award to be passed by
          the SLAO.
60. Pending application, if any, shall stand disposed of.

     Result of the case: Appeal disposed of.



     †
         Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Article 300-A"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.