Created byFuzzy Cloud

Supreme Court of India

BANGALORE ELECTRICITY SUPPLY COMPANY LIMITEDversusHIREHALLI SOLAR POWER PROJECT LLP & OTHERS

Citation
2024 INSC 631
Decided
27 August 2024
Disposal
Dismissed

Holding

The delay was attributable to government authorities, invoking the force majeure clause, entitling the respondents to an extension of time and restoration of the original tariff, and no substantial question of law arose for Supreme Court intervention.

Summary

The appellant, Bangalore Electricity Supply Company Ltd., entered into a Power Purchase Agreement (PPA) with a solar project SPV and a farmer under Karnataka's solar policy, requiring commercial operation within 18 months. Delays occurred in land conversion, evacuation approvals, and other regulatory processes, leading the Karnataka Electricity Regulatory Commission (KERC) to reject the respondents' claim of force majeure and to reduce the tariff, imposing liquidated damages. The Appellate Tribunal for Electricity (APTEL) reversed KERC, finding that the delays were caused by government authorities, that the respondents acted diligently, and that the force majeure clause applied, warranting an extension of time and restoration of the original tariff with a late payment surcharge. The Supreme Court examined whether a substantial question of law existed, concluding that the dispute was factual and the APTEL's findings were reasonable. Consequently, the Court dismissed the appeals, upholding the APTEL's order restoring the tariff and rejecting the reduction and damages.

Issues considered

  • Whether the delay in commissioning the solar project falls within the force majeure clause of the PPA.
  • Whether the respondents are entitled to an extension of the Scheduled Commissioning Date under Article 2.5 of the PPA.
  • Whether the reduction of tariff under Article 5.1 of the PPA and imposition of liquidated damages are justified.
  • Whether the Supreme Court has jurisdiction to entertain the appeal under Section 125 of the Electricity Act, 2003 as a substantial question of law.

Legislation cited

Subjects

Section 125 of Electricity Act, 2003Section 32 of Contract Act, 1872Section 56 of Contract Act, 1872Power Purchase AgreementForce MajeureReduction in tariffFrustration of contractQuestion of lawSubstantial question of lawSolar Power Project

Judgment

                [2024] 8 S.C.R. 1024 : 2024 INSC 631

           Bangalore Electricity Supply Company Limited
                                  v.
            Hirehalli Solar Power Project LLP & Others
                     (Civil Appeal No. 7595 of 2021)
                             27 August 2024
   [Pamidighantam Sri Narasimha* and Pankaj Mithal, JJ.]

                         Issue for Consideration
       Whether the extension of the Scheduled Commissioning Date
       (SCD) was occasioned under the force majeure clause of the
       Power Purchase Agreement (PPA), and consequently, whether the
       reduction in tariff payable to the respondents is justified.

                                Headnotes†
       Electricity Act, 2003 – State of Karnataka introduced a
       policy dated 26.08.2014 to identify and promote solar energy
       projects by land-owning farmers – These solar power plants
       of 1-3 MW capacity would generate and sell power to the
       State Electricity (Distribution) Supply Companies at the
       tariff determined by the Karnataka Electricity Regulatory
       Commission (KERC) – Respondent no. 2-farmer applied
       under the policy – Respondent No.1 is a special purpose
       vehicle (SPV) to undertake the solar power project – In the
       year 2015, the appellant entered into a PPA with respondent
       no. 2 and the same was approved by KERC – The SPV had
       to achieve commercial operation within 18 months from the
       effective date – Several farmers, including the respondent,
       raised concerns regarding delay in the execution of the
       project on account of delay in getting land use conversion,
       delay in getting evacuation approvals, demonetisation, and
       other reasons – KERC rejected the various causes of delay
       put forth by the respondents and held that the force majeure
       clause must be strictly interpreted – KERC reduced the tariff
       payable to the respondent to Rs. 4.36 per unit for the term of
       the PPA by relying on Article 5.1 of the PPA – However, the
       APTEL found that the respondents had taken all necessary
       care and caution and acted with due diligence and held that
       respondents are entitled to the benefit of the force majeure
       clause and an extension of time – Also held that reduction in

* Author
[2024] 8 S.C.R.                                                                 1025

            Bangalore Electricity Supply Company Limited v.
              Hirehalli Solar Power Project LLP & Others

     tariff from Rs. 8.40 to Rs. 4.36 per unit would adversely affect
     them – Hence, it directed the appellant to pay the difference
     in per unit tariff along with the late payment surcharge as
     provided under Article 6.4 of the PPA – Correctness:
     Held: The KERC’s appreciation of the evidence has led it to
     the conclusion that the delay in commissioning was due to the
     respondents’ delay in making the applications, despite the approval
     of the PPA – However, the APTEL has taken note of certain
     additional factors affecting the time taken to secure the approvals
     that were not considered by the KERC – These include the time
     taken by the government to provide the PTCL that is required for
     approval of land conversion, and the delay caused by the authority
     in evacuation approval – Considering these additional factors, the
     APTEL has re-appreciated the evidence to find that the delay was
     not attributable to the respondents but to the government bodies and
     relevant authorities – There is no error in the APTEL’s approach,
     and it is reasonable in its re-appreciation of evidence – In light
     of the above findings of fact by the APTEL that the delay is not
     attributable to the respondents and that the force majeure clause is
     applicable, it rightly held that the extension of time under Article 2.5
     is warranted and the commissioning of the project on 24.08.2017
     is within the extended period of 24 months – Consequently, the
     APTEL also rightly held that there is no occasion for the imposition
     of liquidated damages under Articles 2.2 and 2.5.7 or for the
     reduction of tariff under Article 5.1 of the PPA. [Paras 10.4, 12]
     Electricity Act, 2003 – s.125 – Scope and ambit of appellate
     jurisdiction:
     Held: The position that emerges in this case, it is a little more
     restrictive as the requirement under Section 125 is not merely a
     ‘question of a law’ but a ‘substantial question of law’ – The restrictive
     scope of appellate jurisdiction is a product not only of the statutory
     preconditions, but also a necessary measure to enable freedom to
     statutory regulator and Tribunal to develop sectorial laws through
     a principled and consistent approach. [Paras 1, 7.4]
     Contract Act, 1872 – Chapter III – ss.32 and 56 – Power
     Purchase Agreement – Force Majeure:
     Held: The law on force majeure, specifically in the context of
     PPAs, has been comprehensively dealt with by this Court in
     Energy Watchdog v. Central Electricity Regulatory Commission –
     The Court delved into contractual jurisprudence on force majeure
1026                                                          [2024] 8 S.C.R.

                     Digital Supreme Court Reports


    clauses and frustration of contracts – It held that Sections 32
    and 56 of the Indian Contract Act, 1872 govern the law on force
    majeure – When the contract contains an express or implied force
    majeure clause, it is governed under Chapter III of the Contract Act,
    specifically Section 32 – In such cases, the ‘doctrine of frustration’
    in Section 56 does not apply and the court must interpret the force
    majeure clause contained in the contract – It held that a force
    majeure clause must be narrowly construed. [Para 10.1]

                             Case Law Cited
    Chennamangathihalli Solar Power Project LLP v. BESCOM, 2020
    SCC OnLine APTEL 75; SEBI v. Mega Corporation Limited [2022]
    2 SCR 546 : 2022 SCC OnLine SC 361; Energy Watchdog v.
    Central Electricity Regulatory Commission [2017] 3 SCR 153 :
    (2017) 14 SCC 80 – referred to.
                                List of Acts
    Electricity Act, 2003; Contract Act, 1872.
                             List of Keywords
    Section 125 of Electricity Act, 2003; Section 32 and section 56 of
    Contract Act, 1872; Power Purchase Agreement; Force Majeure;
    Reduction in tariff; Frustration of contract; Question of law;
    Substantial question of law; Solar Power Project.
                            Case Arising From
    CIVIL APPELLATE JURISDICTION: Civil Appeal No. 7595 of 2021
    From the Judgment and Order dated 12.08.2021 of the Appellate
    Tribunal for Electricity, New Delhi in Appeal No. 38 of 2019
    With
    Civil Appeal Nos. 7608 and 6386 of 2021
                        Appearances for Parties
    K.M. Nataraj, ASG, Yasobant Das, Sr. Adv., Ms. Garima Jain, Arnav
    Khanna, Tushar Mahindroo, Mohit Singh, Arunav Patnaik, Ms. Bhabna
    Das, Advs. for the Appellants.
    Prateek K. Chadha, A.A.G., Basava Prabhu Patil, Sr. Adv.,
    Ms. Prerna Priyadarshini, Syed Faraz Alam, Atharva Gaur, Aayushman
    Aggarwal, Ujjal Banerjee, Anmol Sehgal, V. N. Raghupathy, Sreekar
    Aechuri, Advs. for the Respondent.
[2024] 8 S.C.R.                                                                                          1027

                Bangalore Electricity Supply Company Limited v.
                  Hirehalli Solar Power Project LLP & Others

                       Judgment / Order of the Supreme Court

                                        Table of Contents*

        Facts: ........................................................................................     2
        KERC’s order: ..........................................................................            5
        APTEL’s impugned order: .........................................................                   6
        Submissions: .............................................................................. 10
        Scope of Supreme Court’s appellate jurisdiction under
        Section 125 of the Act: ................................................................ 13
        Analysis on merits: .................................................................... 16
        Clauses of the Power Purchase Agreement (PPA): ................. 17
        Re: Applicability of the force majeure clause: ............................ 21
        Conclusion ............................................................................... 26

                                              Judgment
       Pamidighantam Sri Narasimha, J.
1.     The short issue arising from these appeals is whether the extension of
       the Scheduled Commissioning Date1 was occasioned under the force
       majeure clause of the Power Purchase Agreement,2 and consequently,
       whether the reduction in tariff payable to the respondents is justified.
       While upholding the decision of the Appellate Tribunal for Electricity3
       we have examined the scope and ambit of our appellate jurisdiction
       under Section 125 of the Electricity Act, 2003.4 We have held that
       the restrictive scope of appellate jurisdiction is a product not only of
       the statutory preconditions, but also a necessary measure to enable
       freedom to statutory regulator and Tribunal to develop sectorial laws
       through a principled and consistent approach.
2.     Facts : Since the facts and the PPAs are similar in all three appeals,
       we will deal with the facts in the lead Civil Appeal No. 7595/2021,
       where the most relevant facts are as follows:


* Ed. Note: Pagination as per the original Judgment.
1     Hereinafter “SCD”.
2    Hereinafter “PPA”.
3    Hereinafter “APTEL”.
4    Hereinafter “the Act”.
1028                                                        [2024] 8 S.C.R.

                             Digital Supreme Court Reports


     2.1 State of Karnataka introduced a policy dated 26.08.2014 to
         identify and promote solar energy projects by land-owning
         farmers. These solar power plants of 1-3 MW capacity would
         generate and sell power to the State Electricity (Distribution)
         Supply Companies5 at the tariff determined by the Karnataka
         Electricity Regulatory Commission.6
     2.2 Respondent no. 2 is one of the many farmers who applied
         under the policy and is recognised as a solar power developer7
         under the policy. Respondent No.1 is a special purpose vehicle
         to undertake the solar power project in Chitradurga district in
         Karnataka.
     2.3 Pursuant to a Letter of Award dated 28.08.2015, the appellant
         entered into a PPA with respondent no. 2 on 29.08.2015. This
         PPA was approved by the KERC on 07.09.2015. The relevant
         clauses of the PPA will be discussed later, but an important
         aspect to note at this juncture is that the SPV must achieve
         commercial operation within 18 months from the effective date
         as per Article 1.1(xxviii) read with Article 4.1(c) of the PPA.
         Effective date is defined under Article 1.1(xii) as the date of
         signing the PPA. Hence, the SCD for the project was 28.02.2017
         as per these clauses.
     2.4 The SPV (respondent no. 1) was incorporated on 05.02.2016.
         The respondents then submitted an application for land
         conversion on 16.02.2016. On 10.03.2016, they paid the
         evacuation approval processing fee. On 27.12.2016, they
         paid the land conversion processing fee, and the approval
         for conversion was granted on 07.01.2017. The evacuation
         scheme was provisionally approved on 13.05.2016, and the
         final approval was on 22.08.2016.
     2.5 Several farmers, including the respondent, raised concerns
         regarding delay in the execution of the project on account of
         delay in getting land use conversion, delay in getting evacuation
         approvals, demonetisation, and other reasons. Hence, the



5   Hereinafter “DISCOMs”.
6   Hereinafter “KERC”.
7   Hereinafter “SPD”.
[2024] 8 S.C.R.                                                       1029

            Bangalore Electricity Supply Company Limited v.
              Hirehalli Solar Power Project LLP & Others

           Government of Karnataka by a letter dated 24.11.2016 directed
           all DISCOMs to set up 3-member committees to examine each
           request for extension.
     2.6 The present respondents requested a 6-month extension under
         Article 2.5 of the PPA on 03.12.2016. This was approved by
         the appellant through a letter dated 02.03.2017.
     2.7 However, by a letter dated 05.04.2017, KERC directed the
         DISCOMs that all requests for extensions must be filed before
         it. Pursuant to this letter, the respondents filed a petition before
         the KERC seeking extension of time for the commercial operation
         of the project and invoked the force majeure clause in the PPA
         (Article 8.3).
     2.8 During the pendency of the petition, the respondents’ solar
         power project was commissioned on 24.08.2017, within the
         extended period of 24 months.
3.   KERC’s order : In its order dated 18.09.2018, the KERC rejected the
     various causes of delay put forth by the respondents and held that
     the force majeure clause must be strictly interpreted. First, delay in
     approval of the PPA by KERC was held to have no bearing on the
     initial obligations of the SPD in applying for approvals, loans, etc as
     the respondents had not proved the same. Second, it found that the
     respondent had applied for conversion of land only on 18.02.2016,
     over five months after signing the PPA and paid the charges only
     on 27.12.2016, after which it was allowed on 07.01.2017. Hence, the
     delay in conversion of land use was attributed to the respondent. Third,
     the delay in disbursement of loan also did not delay the implementation
     as the respondent had commenced implementation from its own
     funds. Fourth, the respondent applied for the evacuation approval
     only on 25.02.2016, and the regular approval was finally granted
     on 22.08.2016. Hence, the respondent delayed the application and
     cannot attribute the same to the authorities. Similarly, the KERC also
     rejected delay on other grounds such as time taken for delivery of the
     breaker, and inspection of the project and grant of safety approval.
     3.1 It also found that the respondents had not submitted a notice
         as contemplated under Article 8.3(b)(i) and hence, they are
         not entitled to invoke force majeure and claim an extension of
         time under Article 2.5. Since the KERC found that the delay in
1030                                                      [2024] 8 S.C.R.

                    Digital Supreme Court Reports


          securing approvals and the consequent delay in commissioning
          was attributable to the respondents, it imposed liquidated
          damages under Articles 2.2 and 2.5.7 of the PPA.
     3.2 Lastly, the KERC reduced the tariff payable to the respondent
         to Rs. 4.36 per unit for the term of the PPA by relying on
         Article 5.1 of the PPA.
4.   APTEL’s impugned order : The respondent’s appeal against the order
     of the KERC was allowed by the APTEL by the order impugned
     before us. The APTEL dealt with each ground of delay raised by the
     respondents. First, it took note that the respondent’s application for
     land conversion was on 16.02.2016, after which it had to procure
     several documents, including a PTCL certificate, as provided under
     Rule 106A of the Karnataka Land Revenue Act. Further, these
     documents must be secured from various government departments,
     which is a laborious process. The PTCL certificate was issued by
     the government only on 04.10.2016, although the respondent had
     applied for it even before signing the PPA. Hence, it found that the
     respondent could not be blamed for the delay in getting approval
     for land use conversion.
     4.1 Further, the APTEL also took note of the State Government’s
         opinion to grant deemed conversion in such projects due to the
         number of SPDs facing similar issues. However, the APTEL
         observed, the guidelines to revenue authorities were unclear
         and hence the SPDs could not benefit from the same. The delay
         in the issuance of these guidelines and the confusion among
         authorities regarding deemed conversion had also resulted in a
         delay in obtaining land use conversion, which the respondents
         cannot be faulted for.
     4.2 Second, the APTEL found that although the application for
         grid connectivity and evacuation approval were submitted
         on 25.02.2016, the final approval was only given on 22.08.2016,
         after a lapse of 5 months. Until this approval is given, the
         authorities will not prepare the bay SLD and layout drawings
         with estimation of bay erection. The bay intimation notice was
         received by the respondents only a few days before the original
         SCD, and it was 170 days after the grant of final evacuation
         approval. Hence, there was a delay in the construction of the
         bay that was not caused by the respondents.
[2024] 8 S.C.R.                                                      1031

            Bangalore Electricity Supply Company Limited v.
              Hirehalli Solar Power Project LLP & Others

     4.3 Relying on other decisions by the APTEL, it held that the date
         of signing the PPA will not be the effective date, as provided in
         Article 1.1(xxviii). Rather, the PPA becomes effective only when it
         is approved by the KERC, which in this case was on 07.09.2015.
         Hence, 18 months must be calculated from this date.
     4.4 The APTEL observed that the appellant had itself approved
         the extension of time by 6 months after a Technical Committee
         constituted by it had scrutinised all relevant documents. Hence,
         the appellant could not take the stance that the respondents
         were not diligent. Even before the KERC, the appellant had not
         objected to the grounds raised by the respondents, and hence
         they could not take a contrary stance at this stage.
     4.5 Considering the delay in obtaining the PTCL certificate and
         approval for land conversion, the approval for evacuation, and
         construction of the bay, the APTEL found that the respondents
         had taken all necessary care and caution and acted with due
         diligence. Hence, it held that the respondents could not be
         blamed for the delay as the time taken by government authorities
         to provide approvals was not within their control and they had
         taken all the measures that they could. Consequently, the
         APTEL found that the respondents are entitled to the benefit
         of the force majeure clause and an extension of time, as was
         already approved by the appellant. The respondents were able
         to commission the project on 24.08.2017, which falls within the
         extended period of 24 months from 07.09.2015.
     4.6 With regard to the reduction in tariff by the KERC, APTEL
         considered that the government scheme, under which these
         PPAs were signed, was intended to create opportunity and
         benefit for farmers by establishing solar power plants. The
         farmers had invested huge amounts, sometimes through loans,
         in these projects and a reduction in tariff from Rs. 8.40 to Rs.
         4.36 per unit would adversely affect them. Hence, it directed
         the appellant to pay the difference in per unit tariff along with
         the late payment surcharge as provided under Article 6.4 of
         the PPA.
     4.7 Lastly, it also set aside the imposition of liquidated damages
         under the PPA as it found that there was no delay in securing
         approvals and commissioning the project.
1032                                                        [2024] 8 S.C.R.

                     Digital Supreme Court Reports


5.   Submissions: We have heard Mr. K.M. Nataraj, ASG and Mr. Yasobant
     Das, senior advocate appearing for the appellants, and Mr. Basava
     Prabhu Patil, senior advocate for the respondents. The learned
     counsels have, through the course of their submissions, emphasised
     on whether or not the delay in the present matter would be covered
     under the force majeure clause of the PPA.
     5.1 Learned ASG argued that a force majeure clause must be strictly
         interpreted. There must be a specific pleading by the party
         claiming force majeure and the burden is on him to prove the
         same. In this regard, he made two primary submissions: first,
         there was no force majeure event that warrants an extension of
         time under Article 2.5 of the PPA; and second, the respondents
         have not complied with the requirement of submitting a written
         notice invoking force majeure as required under Article 8.3(b)(i).
         Further, he has also argued that the APTEL was not justified
         in granting late payment surcharge to the respondent as the
         same was not pleaded before the KERC or in appeal.
     5.2 In regard the argument on force majeure, Mr. Nataraj has taken
         us through the various dates concerning approval for change
         in land use and the evacuation approval. He has submitted
         that the delay in securing these approvals is attributable to the
         respondents, who were required to obtain these permissions
         within the contractually stipulated period of 365 days under
         Article 2.1 of the PPA, and to finally commission the project within
         a period of 18 months. Despite being aware of these timelines,
         he submits that the respondents delayed the applications
         and payment of requisite fees. The government departments
         provided the approvals within a few days from the time when
         the respondents fulfilled all requirements. He therefore submits
         that the delay is attributable to the respondents and hence, as
         per Article 8.3(b)(iv), they cannot claim benefit of force majeure.
         Consequently, the tariff must be reduced as per Article 5.1 as
         a higher tariff increases the burden on consumers and hence,
         affects public interest.
     5.3 Mr. Das supplemented these submissions by arguing that in
         Civil Appeal No. 6386 of 2021, the respondents therein had
         also raised the ground of demonetisation as a reason for delay
         in commissioning. He submits that Article 8.3 of the PPA does
         not cover such a ground as a force majeure event.
[2024] 8 S.C.R.                                                                                     1033

                Bangalore Electricity Supply Company Limited v.
                  Hirehalli Solar Power Project LLP & Others

6.    Mr. Patil, appearing for the respondents, has submitted that there
      are three primary factors, among several others, that caused the
      delay – (i) time taken for converting the land; (ii) time taken for the
      KERC to approve the PPA; and (iii) time taken for the evacuation
      approval. He submits that these concerns have been raised by
      not only the respondents in the present case but in several other
      cases. Due to the extent to which SPDs were facing these issues,
      the government directed DISCOMs to set up committees to look
      into the same and consider the facts of each case individually. It is
      pursuant to this direction that the respondents’ case was considered
      by the appellant, who granted a 6-month extension on 02.03.2017
      by exercising its power under Article 2.5 read with Article 8.3 of the
      PPA. He submits that it was incorrect for the KERC to then require
      the respondents to file a separate petition to seek extension as the
      same is not as per the terms of the PPA. He further submits that
      the KERC had perversely appreciated the evidence regarding delay
      and that it should not have rejected the petition when the appellant
      had already granted the extension. Further, he submitted that the
      respondents were able to complete the project within the extended
      time period.
      6.1 Mr. Patil also took us through several orders of this Court8
          that dismiss appeals arising out of similar orders by the
          APTEL. He has specifically referred to the APTEL’s decision in
          Chennamangathihalli Solar Power Project LLP v. BESCOM 9 and
          has submitted that this decision has been relied on by the APTEL
          in several subsequent decisions arising out of similar facts,
          including the present impugned order. This Court has dismissed
          the appeal arising out of Chennamangathihalli (supra)10 and
          appeals from other APTEL orders relying on it. Mr. Nataraj, in
          his written submissions, has sought to differentiate these cases
          from the present matter on facts.
7.    Scope of Supreme Court’s appellate jurisdiction under Section 125 of
      the Act: Before we deal with the submissions of the learned counsels,
      we must take note of the scope of our appellate jurisdiction under
      Section 125, which reads:


8    In Civil Appeal No. 3958/2020; Civil Appeal No. 897/2022; Civil Appeal No. 5134/2021; Civil Appeal Diary
     Nos. 32980/2022, 33053/2022 and 33572/2022.
9    2020 SCC OnLine APTEL 75.
10   In Civil Appeal No. 3958/2020.
1034                                                                                [2024] 8 S.C.R.

                             Digital Supreme Court Reports


               “Section 125. (Appeal to Supreme Court):
               Any person aggrieved by any decision or order of the
               Appellate Tribunal, may, file an appeal to the Supreme
               Court within sixty days from the date of communication of
               the decision or order of the Appellate Tribunal, to him, on
               any one or more of the grounds specified in section 100
               of the Code of Civil Procedure,1908…”
       7.1 Section 100 of the CPC restricts the High Court’s jurisdiction in
           second appeals to cases that involve ‘substantial questions of
           law’. There are two components to this requirement – (i) there
           must be a ‘question of law’; and (ii) such question of law must
           be ‘substantial’.
       7.2 In SEBI v. Mega Corporation Limited,11 this Court analysed
           the meaning of ‘question of law’ to determine the scope of its
           appellate jurisdiction under Section 15Z of the SEBI Act, 1992.12
           It held that this phrase is open textured and must be interpreted
           by looking at the words in their context.13 The relevant portions
           are extracted:
                      “17. The jurisdiction of the Supreme Court under
                      Section 15Z to consider any question of law arising
                      from the orders of the Tribunal should therefore be
                      seen in the ‘context’ of the powers and jurisdiction
                      of the Tribunal under Sections 15K, 15L, 15M, 15T,
                      15U and 15Y of the Act. It is in the functioning of the
                      Tribunal to re-examine all questions of fact at the
                      appellate stage while exercising jurisdiction under
                      Section 15T of the Act. In Clariant and National
                      Securities Depository, this Court had an occasion
                      to examine the jurisdiction of the Tribunal and
                      explain that the Tribunal has wide powers. Being a
                      permanent body, apart from acting as an appellate


11   [2022] 2 SCR 546 : 2022 SCC OnLine SC 361
12   Section 15Z of the SEBI Act, 1992 reads:
      “15Z. Appeal to Supreme Court.-- Any person aggrieved by any decision or order of the Securities
      Appellate Tribunal may file an appeal to the Supreme Court within sixty days from the date of
      communication of the decision or order of the Securities Appellate Tribunal to him on any question of
      law arising out of such order…” (emphasis supplied)
13   ibid, para 16.
[2024] 8 S.C.R.                                                           1035

            Bangalore Electricity Supply Company Limited v.
              Hirehalli Solar Power Project LLP & Others

                Tribunal on fact, the Tribunal routinely interprets the
                Act, Rules and Regulations made thereunder and
                evolves a legal regime, systematically developed
                over a period of time. The advantage and benefit of
                this process is consistency and structural evolution
                of the sectorial laws.
                18. It is in the above-referred context that the Supreme
                Court while exercising appellate jurisdiction under
                Section 15Z of the Act would be measured in its
                approach while entertaining any appeal from the
                decision of the Tribunal. This freedom to evolve and
                interpret laws must belong to the Tribunals to subserve
                the regulatory regime for clarity and consistency and
                it is with this perspective that the Supreme Court will
                consider appeals against judgment of the Tribunals
                on questions of law arising from its orders.
                19. It is in this very context that the UK Supreme
                Court in the case of Jones v. First Tier Tribunal,
                formulated certain principles for appellate courts
                to interfere against the orders of Tribunals on the
                ground of existence of questions of law. The Court
                held as under:
                     “16 … It is primarily for the tribunals,
                     not the appellate courts, to develop a
                     consistent approach to these issues [of
                     law and fact], bearing in mind that they are
                     peculiarly well fitted to determine them. A
                     pragmatic approach should be taken to
                     the dividing line between law and fact, so
                     that the expertise of tribunals at the first
                     tier and that of the Upper Tribunal can be
                     used to best effect. An appeal court should
                     not venture too readily into this area by
                     classifying issues as issues of law which
                     are really best left for determination by the
                     specialist appellate tribunals.”
                20. The scope of appeal under Section 15Z may be
                formulated as under:
1036                                                                                 [2024] 8 S.C.R.

                              Digital Supreme Court Reports


                      20.1 The Supreme Court will exercise jurisdiction
                      only when there is a question of law arising for
                      consideration from the decision of the Tribunal. A
                      question of law may arise when there is an erroneous
                      construction of the legal provisions of the statute
                      or the general principles of law. In such cases, the
                      Supreme Court in exercise of its jurisdiction of Section
                      15Z may substitute its decision on any question of
                      law that it considers appropriate.
                      20.2 However, not every interpretation of the law
                      would amount to a question of law warranting
                      exercise of jurisdiction under Section 15Z. The
                      Tribunal while exercising jurisdiction under Section
                      15T, apart from acting as an appellate authority on
                      fact, also interprets the Act, Rules and Regulations
                      made thereunder and systematically evolves a legal
                      regime. These very principles are applied consistently
                      for structural evolution of the sectorial laws. This
                      freedom to evolve and interpret laws must belong
                      to the Tribunal to subserve the Regulatory regime
                      for clarity and consistency. These are policy and
                      functional considerations which the Supreme Court
                      will keep in mind while exercising its jurisdiction under
                      Section 15Z.”
      7.3 The above understanding of ‘question of law’ as a precondition
          to this Court’s exercise of appellate jurisdiction under regulatory
          statutes is extremely pertinent to the present matter. The Act
          envisages the establishment of State Electricity Regulatory
          Commissions and the Central Electricity Regulatory Commission
          as expert and specialised bodies that discharge advisory,
          regulatory, and adjudicatory functions.14 It has established the
          APTEL as an appellate body to hear appeals against orders of
          the adjudicating officers or the Appropriate Commission.15 Hence,
          while delineating the contours of this Court’s interference in


14   The functions of the Central Commission are enlisted in Section 79 of the Act. Similarly, Section 86
     provides the functions of the State Commissions.
15   Section 110 establishes the APTEL. Section 111 provides the scope of appellate jurisdiction of the APTEL
     and Section 120 sets out the procedure to be followed by the APTEL and the powers of the APTEL.
[2024] 8 S.C.R.                                                                                     1037

                Bangalore Electricity Supply Company Limited v.
                  Hirehalli Solar Power Project LLP & Others

              appeal under Section 125, we must be mindful and measured
              so as to enable a systematic and coherent development of
              electricity law by the Commissions and the APTEL.
      7.4 Having examined the scope of this Court’s exercise of appellate
          jurisdiction when there is a ‘question of law’ under Section 15Z
          of the SEBI Act, the position that emerges in this case, it is
          a little more restrictive as the requirement under Section 125
          is not merely a ‘question of a law’ but a ‘substantial question
          of law’.16
8.    Analysis on merits: The above discussion provides the context in
      which we decide the present appeals. We take note of several orders
      of this Court that have dismissed appeals arising out of similar
      orders and similar facts.17 We find it necessary to state our reasons
      for dismissing the present appeals, to finally settle this issue. We
      will therefore analyse the submissions of the learned counsels in
      light of the scope of our jurisdiction and the reasoning and findings
      of the impugned order.
      8.1 At the outset, it is necessary to state that the learned ASG and
          learned senior counsel for the appellant have not proposed a
          substantial question of law for this Court to consider. Rather,
          they have argued on facts as to whether or not the delay is
          attributable to the respondents, and consequently whether force
          majeure is applicable. We will analyse the impugned order, as
          well as the KERC’s order, to determine whether there is any
          substantial question of law that calls for our interference.
9.    Clauses of the Power Purchase Agreement (PPA): Before discussing
      the orders of the KERC and the APTEL, it is necessary to identify
      the relevant clauses of the PPA. Article 2.1 of the PPA imposes the
      obligation on the SPD to secure necessary approvals, clearances,
      and permits within 365 days. Liquidated damages can be imposed
      on the SPD under Article 2.2 in case of delay, provided that the delay
      is not attributable to the appellant or due to a force majeure event.



16   The requirement of ‘substantial question of law’ for this Court to exercise appellate jurisdiction under
     Section 125 has also been recognised in BSES Rajdhani Power Limited v. Delhi Electricity Regulatory
     Commission (2023) 4 SCC 788.
17   In Civil Appeal No. 3958/2020; Civil Appeal No. 897/2022; Civil Appeal No. 5134/2021; Civil Appeal Diary
     Nos. 32980/2022, 33053/2022 and 33572/2022.
1038                                                        [2024] 8 S.C.R.

                    Digital Supreme Court Reports


    9.1 Article 2.5.1 permits the extension of the SCD in case the SPD
        is unable to fulfil its contractual obligations due to the appellant’s
        default or there are force majeure events that affect either the
        appellant or the SPD. The list of force majeure events is set
        out in Article 8.3(a), and sub-clause (vi) is the most relevant
        for us. A party can invoke the force majeure clause subject to
        the conditions set out in Article 8.3(b).
    9.2 Article 2.5.7 provides that subject to the other provisions of
        the PPA, the SPD is liable to pay liquidated damages if it is
        unable to supply power to the appellant by the SCD. Therefore,
        the payment of damages under this clause is subject to an
        extension of time under Article 2.5.1. Article 5.1 provides for the
        tariff rate payable to the SPD as Rs. 8.40 per unit. However, in
        cases of delay, subject to extension of time under Article 2.5, it
        provides that the lower of Rs. 8.40 per unit and the varied tariff
        applicable as on the date of commercial operation will apply.
        A plain reading of Article 5.1 makes it clear that the lower tariff
        will not apply if there is an extension of time under Article 2.5.
    9.3 The relevant clauses of the PPA are reproduced for ready
        reference:
         “Article 2.1: Conditions Precedent
         The obligations of BESCOM and the SPD under this
         Agreement are conditional upon the occurrence of the
         following in full within 365 days from the effective date.
         2.1.1
         (i)The SPD shall obtain all permits, clearances and
         approvals (whether Statutory or otherwise) as required
         to execute and operate the Protect hereinafter referred
         to as “Approvals”):
         (ii) The Conditions Precedent required to be satisfied by
         the SPD shall be deemed to have been fulfilled when the
         SPD shall submit:
              a. The DPR to BESCOM and achieve financial closure
                 and provide a certificate to BESCOM from the lead
                 banker to this effect;
[2024] 8 S.C.R.                                                          1039

            Bangalore Electricity Supply Company Limited v.
              Hirehalli Solar Power Project LLP & Others

               b. All Consents, Clearances and Permits required for
                  supply of power to BESCOM as per the terms of
                  this Agreement; and
               c. Power evacuation approval from Karnataka Power
                  Transmission Company Limited or BESCOM, as
                  the case maybe.
           2.1.2 SPD shall make all reasonable endeavors to satisfy
           the Conditions Precedent within the time stipulated and
           BESCOM shall provide to the SPD all the reasonable
           cooperation as may be required to the SPD for satisfying
           the Conditions Precedent.
           2.1.3 The SPD shall notify BESCOM in writing at least once
           a month on the progress made in satisfying the Conditions
           Precedent. The date, on which the SPD fulfills any of the
           Conditions Precedent pursuant to Clause 2.1.1, it shall
           promptly notify BESCOM of the same.”
           “Article 2.2: Damages for delay by the SPD:
           “2.2.1 In the event that the SPD does not fulfill any or all
           of the Conditions Precedent set forth in Clause 2.1 within
           the period of 365 days and the delay has not occurred
           for any reasons attributable to BESCOM or due to Force
           Majeure, the SPD shall pay to BESCOM damages in an
           amount calculated at the rate of 0.2% (zero point two per
           cent) of the Performance Security for each day’s delay until
           the fulfillment of such Conditions Precedent, subject to a
           maximum period of 60 (Sixty) days. On expiry of the said
           60 (Sixty) days, BESCOM at its discretion may terminate
           this Agreement.”
           Article 2.5: Extension of Time
           “2.5.1 In the event that the SPD is prevented from
           performing its obligations under Clause 4.1 by the
           Scheduled Commissioning Date due to:
               a. Any BESCOM Event of Default; or
               b. Force Majeure Events affecting BESCOM; or
               c. Force Majeure Events affecting the SPD,
1040                                                    [2024] 8 S.C.R.

                  Digital Supreme Court Reports


        2.5.2 The Scheduled Commissioning Date and the
        Expiry Date shall be deferred, subject to the reasons and
        limits prescribed in Clause 2.5.1 and Clause 2.5.3 for a
        reasonable period but not less than ‘day for day’ basis,
        to permit the SPD or BESCOM through the use of due
        diligence, to overcome the effects of the Force Majeure
        Events affecting the SPD or BESCOM, or till such time
        such Event of Default is rectified by BESCOM.
        2.5.3. In case of extension occurring due to reasons
        specified in clause 2.5.1 (a), any of the dates specified
        therein can be extended, subject to the condition that the
        Scheduled Commissioning Date would not be extended
        by more than 6 (six) months.
        …
        2.5.6. As a result of such extension, the Scheduled
        Commissioning Date and the Expiry Date newly determined
        date shall be deemed to be the Scheduled Commissioning
        Date and the Expiry Date for the purposes of this Agreement.
        2.5.7. Liquidated damages for delay in commencement of
        supply of power to BESCOMs.
        Subject to the other provisions of this agreement, if the
        SPD is unable to commence supply of power to BESCOM
        by the scheduled commissioning date, the SPD shall pay
        to BESCOM, liquidated damages for the delay in such
        commencement of supply of power as follows:
            (a) For the delay up to one month-amount equivalent
                to 20% of the performance security.
            (b) For the delay of more than one month up to
                three months-amount equivalent to 40% of the
                performance security.
             (c) For the delay of more than three months up
                to six months-amount equivalent to 100% of the
                performance security.
        For avoidance of doubt, in the event of failure to pay the
        above mentioned damages by the SPD, the BESCOM
        entitled to encash the performance Security.”
[2024] 8 S.C.R.                                                            1041

            Bangalore Electricity Supply Company Limited v.
              Hirehalli Solar Power Project LLP & Others

           Article 5: Rates and Charges:
           “5.1 Tariff payable: The SPD shall be entitled to receive
           the Tariff of Rs. 8.40 per kwh based on the KERC tariff
           order S/03/1 dated 10.10.2013 in respect of SPD’s Solar
           PV projects in terms of this agreement for the period
           between COD and the Expiry Date. However, subject to
           Clause 2.5, if there is a delay in commissioning of the
           Project beyond the Scheduled Commissioning Date and
           during such period such period there is a variation in the
           KERC Tariff, then the applicable Tariff for the projects shall
           be the lower of the following:
           (i) Rs.8.40 per kwh
           (ii) varied tariff applicable as on the date of Commercial
           Operation…”
           Article 8: Force Majeure
           “8.3 Force Majeure Events:
           a) Neither Party shall be responsible or liable for or
           deemed in breach hereof because of any delay or failure
           in the performance of its obligations hereunder (except
           for obligations to pay money due prior to occurrence of
           Force Majeure events under this Agreement) or failure to
           meet milestone dates due to any event or circumstance
           (a “Force Majeure Event”) beyond the reasonable control
           of the Party affected by such delay or failure, including
           the occurrence of any of the following:
           i. Acts of God;
           ii. Typhoons, floods, lightning, cyclone, hurricane, drought,
           famine, epidemic, plague or other natural calamities;
           iii. Strikes, work stoppages, work slowdowns or other labor
           dispute which affects a Party’s ability to perform under
           this Agreement;
           iv. Acts of war (whether declared or undeclared), invasion
           or civil unrest;
           v. Any requirement, action or omission to act pursuant to
           any judgment or order of any court or judicial authority in
1042                                                    [2024] 8 S.C.R.

                  Digital Supreme Court Reports


        India (provided such requirement, action or omission to
        act is not due to the breach by the SPD or BESCOM, of
        any Law or any of their respective obligations under this
        Agreement);
        vi. Inability despite complying with all legal requirements
        to obtain, renew or maintain required licenses or Legal
        Approvals;
        vii. Fire, Earthquakes, explosions, accidents, landslides;
        viii. Expropriation and/or compulsory acquisition of the
        Project in whole or in part;
        ix. Chemical or radioactive contamination or ionizing
        radiation; or
        x. Damage to or breakdown of transmission facilities of
        either Party;
        b) The availability of the above item (a) to excuse a
        Party’s obligations under this Agreement due to a Force
        Majeure Event shall be subject to the following limitations
        and restrictions:
        (i) The non-performing Party gives the other Party written
        notice describing the particulars of the Force Majeure Event
        as soon as practicable after its occurrence;
        (ii) The suspension of performance is of no greater scope
        and of no longer duration than is required by the Force
        Majeure Event.
        (iii) The non-performing Party is able to resume performance
        of its obligations under this Agreement, it shall give the
        other Party written notice to that effect;
        (iv) The Force Majeure Event was not caused by the non
        performing Party’s negligent or intentional acts, errors or
        omissions, or by its negligence/failure to comply with any
        material Law, or by any material breach or default under
        this Agreement;
        (v) In no event shall a Force Majeure Event excuse the
        obligations of a Party that are required to be completely
        performed prior to the occurrence of a Force Majeure Event.”
[2024] 8 S.C.R.                                                                                  1043

                Bangalore Electricity Supply Company Limited v.
                  Hirehalli Solar Power Project LLP & Others

10. Re: Applicability of the force majeure clause: The primary issue
    for our consideration is whether the delay in this case is due to a
    force majeure event as defined under Article 8.3, and consequently
    whether the respondents were entitled to an extension of time under
    Article 2.5. If the answer to these questions is affirmative, the tariff
    cannot be lowered under Article 5.1 and liquidated damages cannot
    be imposed under Articles 2.2 and 2.5.7.
       10.1 The law on force majeure, specifically in the context of PPAs,
            has been comprehensively dealt with by this Court in Energy
            Watchdog v. Central Electricity Regulatory Commission.18 The
            Court delved into contractual jurisprudence on force majeure
            clauses and frustration of contracts. It held that Sections 32 and
            56 of the Indian Contract Act, 187219 govern the law on force
            majeure. When the contract contains an express or implied
            force majeure clause, it is governed under Chapter III of the
            Contract Act, specifically Section 32. In such cases, the ‘doctrine
            of frustration’ in Section 56 does not apply and the court must
            interpret the force majeure clause contained in the contract.20 It
            held that a force majeure clause must be narrowly construed.21
       10.2 The present case is clearly one where the PPA contains an
            explicit force majeure clause in Article 8.3, which has already
            been extracted above. The question is whether the delay in
            commissioning falls within the ambit of this clause. Article 8.3(a)
            (vi) is the most relevant force majeure event that would apply
            to the facts here. It reads:


18   [2017] 3 SCR 153 : (2017) 14 SCC 80
19   Section 32 reads:
      “32. Enforcement of contracts contingent on an event happening.—Contingent contracts to do or
      not to do anything if an uncertain future event happens, cannot be enforced by law unless and until
      that event has happened.
      If the event becomes impossible, such contracts become void.”
      Section 56 reads:
      “56. Agreement to do impossible act.—An agreement to do an act impossible in itself is void.
      Contract to do act afterwards becoming impossible or unlawful.—A contract to do an act which,
      after the contract is made, becomes impossible, or, by reason of some event which the promisor could
      not prevent, unlawful, becomes void when the act becomes impossible or unlawful.
      Compensation for loss through non-performance of act known to be impossible or unlawful.—
      Where one person has promised to do something which he knew, or, with reasonable diligence, might
      have known, and which the promisee did not know, to be impossible or unlawful, such promisor must
      make compensation to such promisee for any loss which such promisee sustains through the non-
      performance of the promise.”
20   Energy Watchdog (supra), para 47.
21   ibid, para 45.
1044                                                      [2024] 8 S.C.R.

                    Digital Supreme Court Reports


              “vi. Inability despite complying with all legal
              requirements to obtain, renew or maintain required
              licenses or Legal Approvals”
         Article 8.3(b)(iv) disentitles a party from claiming force majeure
         when the event was caused by its own negligence, intentional
         act, or omission. It reads:
              “b) The availability of the above item (a) to excuse
              a Party’s obligations under this Agreement due to a
              Force Majeure Event shall be subject to the following
              limitations and restrictions:
              …
              (iv) The Force Majeure Event was not caused by
              the non performing Party’s negligent or intentional
              acts, errors or omissions, or by its negligence/failure
              to comply with any material Law, or by any material
              breach or default under this Agreement…”
    10.3 When these clauses are read together, it is clear that the SPD
         would be entitled to the benefit of Article 8.3(a)(vi) when it is
         unable to secure the necessary approvals and licenses required
         under the PPA, provided that there is no negligence or intentional
         act or omission on its part that caused this situation.
    10.4 The entire dispute before the KERC and the APTEL revolves
         on a question of fact – whether the respondents were negligent
         or not diligent in securing approvals and hence, is the delay in
         commissioning attributable to them. The KERC’s appreciation
         of the evidence has led it to the conclusion that the delay in
         commissioning was due to the respondents’ delay in making
         the applications, despite the approval of the PPA. However,
         the APTEL has taken note of certain additional factors
         affecting the time taken to secure the approvals that were not
         considered by the KERC. These include the time taken by the
         government to provide the PTCL that is required for approval
         of land conversion, and the delay caused by the authority in
         evacuation approval. Considering these additional factors, the
         APTEL has reappreciated the evidence to find that the delay
         was not attributable to the respondents but to the government
[2024] 8 S.C.R.                                                         1045

            Bangalore Electricity Supply Company Limited v.
              Hirehalli Solar Power Project LLP & Others

           bodies and relevant authorities. We find that there is no error in
           the APTEL’s approach, and it is reasonable in its reappreciation
           of evidence.
     10.5 Further, the APTEL also correctly took note of the fact that a large
          number of SPDs have raised similar issues, and the government
          has responded to the same by requiring DISCOMs to set-up
          committees to look into these cases. The large number of cases
          that raise similar grounds and the government’s response show
          that the delay was not faced by the respondents alone, and
          hence cannot be entirely blamed on them. The government
          has itself acknowledged that the land use conversion process
          is a long and arduous one, which led it to deem conversion for
          solar power projects under the present scheme. However, due
          to lapses in the implementation of the deemed conversion, the
          SPDs were unable to avail the same. The APTEL has rightly
          appreciated these facts to hold that the respondents acted
          diligently and with care and caution to secure approvals, and
          hence their claims cannot be rejected through recourse to
          Article 8.3(b)(iv).
11. Finally, we have also considered the letter by the appellant dated
    02.03.2017 that granted a 6-month extension to the respondents
    after considering its individual facts and circumstances. This grant
    of extension must be seen in light of the government’s direction
    to DISCOMs dated 24.11.2016 to set up 3-member committees to
    consider each request for extension. This shows that the appellant,
    after considering the specific case of the respondents, has itself
    accepted that they are entitled to the benefit of Article 2.5 read with
    Article 8.3 of the PPA. Even before the KERC, the appellant did not
    challenge the respondents’ contentions. Therefore, at the appellate
    stage before the APTEL and this Court, they cannot be permitted
    to take a contrary stance and raise the plea that the delay was
    attributable to the respondents and not covered by the force majeure
    clause or that there was non-compliance with the notice requirement
    under Article 8.3(b)(i). We therefore reject the contentions of the
    appellant that force majeure does not apply in this case.
12. In light of the above findings of fact by the APTEL that the delay is
    not attributable to the respondents and that the force majeure clause
    is applicable, it rightly held that the extension of time under Article 2.5
1046                                                         [2024] 8 S.C.R.

                        Digital Supreme Court Reports


     is warranted and the commissioning of the project on 24.08.2017 is
     within the extended period of 24 months. Consequently, the APTEL
     also rightly held that there is no occasion for the imposition of
     liquidated damages under Articles 2.2 and 2.5.7 or for the reduction
     of tariff under Article 5.1 of the PPA.
13. Conclusion: After considering the learned counsels’ submissions in
    light of the above findings of the APTEL, we find that no substantial
    question of law arises in the present case. The APTEL has primarily
    decided a question of fact as to the attributability of the delay, and from
    the above, it is clear that the APTEL’s findings are neither illegal nor
    unreasonable. Hence, we find no reason to interfere with the same.
14. Lastly, we also reject the appellant’s contention that the APTEL’s
    direction to pay late payment surcharge to the respondents is
    unjustified since the same was not pleaded. As we have already
    held, the APTEL rightly restored the tariff of Rs. 8.4 per unit and
    directed the appellant to pay the difference amount. The direction to
    pay the late payment surcharge on this amount is explicitly rooted in
    the PPA, and hence, is in furtherance of the intention of the parties.
    There is no reason to set aside the same.
15. With the above reasons, we dismiss the present appeals.
16. No order as to costs.

     Result of the case: Appeals dismissed.



     †
         Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Section 125 of Electricity Act, 2003"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.