Created byFuzzy Cloud

Supreme Court of India

YASH DEVELOPERSversusHARIHAR KRUPA CO-OPERATIVE HOUSING SOCIETY LIMITED & ORS.

Citation
2024 INSC 559
Decided
30 July 2024
Disposal
Dismissed

Holding

Section 13(2) of the Maharashtra Slum Areas Act, 1971 grants the SRA a power coupled with a duty to ensure timely completion of slum rehabilitation projects, and the termination order was valid.

Summary

The Supreme Court examined the termination of a development agreement between Yash Developers (appellant) and Harihar Krupa Co‑Operative Housing Society (respondent) under Section 13 of the Maharashtra Slum Areas (Improvement, Clearance and Redevelopment) Act, 1971, which had been upheld by the Bombay High Court. The Court considered whether the Apex Grievance Redressal Committee (AGRC) had lawfully exercised its power to cancel the agreement due to inordinate delay in project implementation spanning over 16 years. It held that Section 13(2) confers a power coupled with a duty on the Slum Rehabilitation Authority (SRA) and its CEO to ensure timely completion, and that the developer could not rely on litigation, environmental clearances, or non‑cooperation of some slum dwellers as justifications. The Court found the appellant’s explanations untenable, affirmed the accountability of the SRA and CEO, and dismissed the appeal. Additionally, the Court directed the Bombay High Court to initiate a performance audit of the Act to address systemic deficiencies.

Issues considered

  • The scope of judicial review under Article 226 of the Constitution against an order passed under Section 13 of the Maharashtra Slum Areas Act, 1971.
  • Whether the power conferred on the SRA under Section 13(2) is coupled with a statutory duty to ensure timely completion of slum rehabilitation projects.
  • Whether the delays attributed to litigation with a competing builder, environmental clearances, and non‑cooperation of slum dwellers justify termination of the development agreement.
  • Accountability of the CEO and SRA for dereliction of duty under the Act.
  • Maintainability of the appeal before the AGRC and the locus of respondent No.6.

Legislation cited

Subjects

Section 13 of the Maharashtra Slum Areas ActJudicial review under Article 226Development agreementDeveloper accountabilityPerformance audit of statuteOrder of terminationComprehensive statutory auditRehabilitation of slum dwellersDelay in implementationEnvironmental clearanceRight to life under Article 21Slum Rehabilitation Scheme

Judgment

                 [2024] 7 S.C.R. 1443 : 2024 INSC 559

                        Yash Developers
                               v.
           Harihar Krupa Co-Operative Housing Society
                         Limited & Ors.
                       (Civil Appeal No. 8127 of 2024)
                                  30 July 2024
  [Pamidighantam Sri Narasimha* and Aravind Kumar, JJ.]

                            Issue for Consideration
       Development agreement in favour of the appellant was terminated
       by the Apex Grievance Redressal Committee (AGRC) exercising
       its power under Section 13 of the Maharashtra Slum Areas
       (Improvement, Clearance and Redevelopment) Act, 1971. Order
       of termination upheld by the High Court. Issue as regards scope
       of judicial review under Article 226 of the Constitution against
       an order passed under Section 13; accountability of officers
       exercising power coupled with duty under Section 13; Performance
       audit of Maharashtra Slum Areas (Improvement, Clearance and
       Redevelopment) Act, 1971.

                                   Headnotes†
       Maharashtra Slum Areas (Improvement, Clearance and
       Redevelopment) Act, 1971 – s.13 – Constitution of India – Article
       226 – Rehabilitation of slum dwellers – Appellant was appointed
       as a developer by respondent no. 1 – However, development
       was prolonged for over two decades – Development agreement
       terminated by the statutory authority – Apex Grievance
       Redressal Committee (AGRC) – Validity of the said power
       exercised by the AGRC – Order of termination upheld by
       the High Court – Plea of the appellant that the delay in
       implementation of the project was in various phases between
       2003 to 2011, 2011 to 2014 and 2014 to 2019 due to various
       reasons inter alia long-drawn litigation with a competing
       builder, delay in obtaining the environmental clearances or the
       delay due to non-cooperation of certain slum dwellers, in which
       the appellant had no role and was not at all responsible for:
       Held: Under s.13(2), Slum Rehabilitation Authority (SRA) has the
       power to redevelop the project if it is satisfied that the development
       is not proceeding within the time specified – This power of SRA
* Author
1444                                                         [2024] 7 S.C.R.

                     Digital Supreme Court Reports


    is coupled with a duty to ensure that the project is completed
    within time – The provision is a statutory incorporation of time
    integrity in the performance of the duty – SRA is accountable
    for the performance of this duty – The primary responsibility to
    implement s.13 and allied provisions and to monitor compliances
    of schemes and agreements vests with the CEO – If the actions
    of CEO are based on the directions of the SRA, then the SRA
    must equally bear the responsibility – A writ of mandamus would
    lie against the concerned authorities if they do not perform the
    statutory duty of ensuring that the project is completed within
    the time prescribed – Delay of 8 years in resolving disputes
    with a competing builder cannot be a justification under any
    circumstance – Appellant being a developer fully understands
    the process of obtaining environmental clearances while other
    sanctions and permissions are pending, and it was for him to
    make all the necessary arrangements – Non-cooperation of some
    of the members cannot be a ground for delaying the project from
    2014 to 2019 – AGRC and High Court correctly held that the delay
    caused due to the sanction of the draft development plan for the
    construction of the road cannot be a justification for delaying the
    project from 2015 to 2019 – Justifications given by the appellant
    for delaying the project, rejected – No merit in the present appeal,
    costs imposed – Though the justifications for delay are rejected, but
    there was dereliction of the statutory duty of the SRA in ensuring
    that the project is completed within time – There was negligence
    on the part of CEO and the SRA and they are accountable for
    their actions. [Paras 13, 14.1, 24, 26, 27]
    Constitution of India – Article 21 – Right to life – Slum
    Rehabilitation Scheme – Rehabilitation of slum dwellers:
    Held: Execution of the project under the Slum Rehabilitation
    Scheme cannot be viewed as a real estate development project –
    There is a public purpose involved inextricably connected to the
    right to life of some of our brother and sister citizens living in
    pathetic conditions. [Para 27]
    Maharashtra Slum Areas (Improvement, Clearance and
    Redevelopment) Act, 1971 – Performance audit of – Litigation
    under the Act, worrisome – Directions for comprehensive
    statutory audit issued – Problem with the statutory scheme
    w.r.t issues such as identification and declaration of land as a
    slum; identification of slum dwellers; selection of a developer;
[2024] 7 S.C.R.                                                              1445

                         Yash Developers v.
      Harihar Krupa Co-Operative Housing Society Limited & Ors.

     apportionment of the slum land between redevelopment area
     and sale area; obligation to provide transit accommodation for
     the slum dwellers pending redevelopment; issues of lack of
     independence and objectivity in the functioning of statutory
     authorities; effectiveness of statutory remedies; judicial review
     proceedings under Art. 226 cannot be a long-term solution:
     Held: The problems arising out of the statutory scheme and
     policy framework should have come under review by the State
     of Maharashtra – Assessment of the working of the statute to
     realise if its purpose and objective achieved or not is the implied
     duty of the executive government – Reviewing and assessing the
     implementation of a statute is an integral part of Rule of Law – It
     is in recognition of this obligation of the executive government
     that the constitutional courts have directed governments to carry
     performance audit of statutes – Role of judiciary elaborated – Chief
     Justice of the Bombay High Court requested to constitute a bench
     to initiate suo motu proceedings for reviewing the working of the
     statute to identify the cause of the problems indicated. [Para 35, 42]
     Judicial review – Directions for review and assessment of the
     implementation of a Statute – Justification:
     Held: Constitutional courts are fully justified in giving such
     directions as they are in a unique position of perceiving the
     working of a statute while exercising judicial review, during
     which they could identify the fault-lines in the implementation of
     a statute. [Para 37]

                              Case Law Cited
     Susme Builders Pvt. Ltd. v. CEO, Slum Rehabilitation Authority
     & Ors. [2018] 1 SCR 1 : (2018) 2 SCC 230; Vijay Rajmohan v.
     CBI [2022] 19 SCR 563 : (2023) 1 SCC 329; State of Haryana v.
     Mukesh Kumar [2011] 14 SCR 211 : (2011) 10 SCC 404; Pravin
     Electricals (P) Ltd. v. Galaxy Infra & Engineering (P) Ltd. [2021] 1
     SCR 1162 : (2021) 5 SCC 671; Preeti Gupta v. State of Jharkhand
     [2010] 9 SCR 1168 : (2010) 7 SCC 667; Arif Azim Co. Ltd. v.
     Aptech Ltd. [2024] 3 SCR 73 : (2024) 5 SCC 313; Public Interest
     Foundation v. Union of India [2018] 10 SCR 141 : (2019) 3 SCC
     224 – referred to.
     Galaxy Enterprises v. State of Maharashtra (2019) SCC OnLine
     Bom 897; Tulsiwadi Navnirman Co-op Housing Society Ltd. & Anr.
1446                                                      [2024] 7 S.C.R.

                    Digital Supreme Court Reports


    v. State of Maharashtra & Ors., 2008 (1) Bom.C.R.1; New Janta
    SRA CHS Ltd. v. State of Maharashtra (2019) SCC Online Bom
    3896 – referred to.

                     Books and Periodicals Cited
    Justice in Adapting to Change, in R.W.M. Dias, JURISPRUDENCE,
    305-327 (5th edn., 2013).
                              List of Acts
    Maharashtra Slum Areas (Improvement, Clearance and
    Redevelopment) Act, 1971; Constitution of India.
                           List of Keywords
    Section 13 of the Maharashtra Slum Areas (Improvement, Clearance
    and Redevelopment) Act, 1971; Judicial review under Article 226 of
    the Constitution; Development agreement; Developer; Performance
    audit of statute; Order of termination; Comprehensive statutory
    audit; Rehabilitation of slum dwellers; Delay in implementation of
    the project; Development agreement terminated; Redevelopment
    of the project; Rehabilitation building; Environmental clearance;
    Development plan; Builders; Slum Rehabilitation Scheme; Right
    to life.
                          Case Arising From
    CIVIL APPELLATE/INHERENT JURISDICTION: Civil Appeal No.
    8127 of 2024
    From the Judgment and Order dated 14.10.2022 of the High Court
    of Judicature at Bombay in WPL No.18022 of 2021
    With
    Contempt Petition (Civil) No. 217 of 2024 In SLP (C) No. 20844 of 2022
                       Appearances for Parties
    Kapil Sibal, Sr. Adv., C.U. Singh, Vikas Mehta, Adit Nair, Prakash
    Shah, Ranbir Singh, Abhik Chimni, Ms. Rupali Samuel, Kartik, Advs.
    for the Appellant.
    Sanjay Kharde, Shekhar Naphade, C.A. Sunderam, Dama
    Seshadri Naidu, Dhruv Mehta, Huzeifa Ahmadi, Vinay Navare,
    Sr. Advs., Satyajeet Kharde, Sunil Kumar Verma, Anirudha Joshi,
    Shashibhushan P. Adgaonkar, Ms. Pradnya S. Adgaonkar, Aaditya
[2024] 7 S.C.R.                                                                             1447

                           Yash Developers v.
        Harihar Krupa Co-Operative Housing Society Limited & Ors.

       Aniruddha Pande, Ms. Rukmini Bobde, Siddharth Dharmadhikari,
       Bharat Bagla, Sourav Singh, Aditya Krishna, Ms. Preet S. Phanse,
       Adarsh Dubey, Ms. Soumya Priyadarshinee, Ankit Ambasta, Amit
       Srivastava, Amlaan Kumar, Saket Sikri, Aman Vachher, Dhiraj,
       Ashutosh Dubey, Ms. Anshu Vachher, Ms. Abhiti Vachher, Akshat
       Vachher, Ms. Smriti Puri, Amit Kumar, P. N. Puri, Anil Nag, Zulfikar
       Ali, Mrs. Jaya, Ms. Monica Saini, Amit Agnihotri, Ms. Priyanka Midha,
       Ms. Priya Misra, M. Yogesh Kanna, Ms. Anshula Vijay Kumar Grover,
       Ms. Rucha Deshpande, Rajeev Maheshwaranand Roy, Nilesh Kumar,
       Advs. for the Respondents.
                       Judgment / Order of the Supreme Court

                                             Judgment
       Pamidighantam Sri Narasimha, J.

                                          Table of Contents*

        I. Introduction :...................................................................... 2
        II. Scope of Judicial Review against an order under Section
        13 of the Act:........................................................................ 4
        III. Accountability of officers exercising power coupled
        with duty under Section 13:................................................. 11
        IV. Submissions and Analysis:.............................................. 13
                (i) The first phase of delay is between 2003 and 2011..... 14
                (ii) The second phase relates to the delay in obtaining
                necessary permissions, approvals and environmental
                clearances from 2011 to 2014......................................... 17
                (iii) The third phase of delay relates to the alleged
                non-cooperation of certain slum dwellers leading to
                the stalling of the project from 2014 to 2019................. 18
                (iv) The next period of inaction is from 2015 to 2017.
                This is sought to be justified on the ground that the
                Municipal Corporation sanctioned a road that may
                pass through the property and published the draft
                development plan (DP) on 25.02.2015........................... 20
                (v) Re: Appellant did not have the financial resources..... 21

* Ed. Note: Pagination as per the original Judgment.
1448                                                                            [2024] 7 S.C.R.

                               Digital Supreme Court Reports



                (vi) Re: Submission on maintainability of proceedings
                before AGRC................................................................... 25
                (vii) Re: Locus or conflict of respondent no.6.............. 27
        V.      Findings:......................................................................... 28
        VI.     Conclusion:...................................................................... 32
        VII. Re : Performance audit of statute:.................................. 32


1.     Leave granted.
       I.      Introduction:
2.     The present controversy is a manifestation of common battles between
       competing real estate developers under the pretext of rehabilitating
       slum dwellers under the Maharashtra Slum Areas (Improvement,
       Clearance and Redevelopment) Act, 1971.1 In the year 2003, the
       appellant was appointed as a developer by respondent no. 1, a co-
       operative Housing Society of slum dwellers having their hutments on
       the subject land in Borivali, Mumbai which was declared as a ‘slum
       area’ under the Act. As the development was unduly prolonged for over
       two decades, the development agreement in favour of the appellant
       was terminated by the Apex Grievance Redressal Committee2 by its
       order dated 04.08.2021. The order of termination was challenged
       by the appellant before the Bombay High Court.3
3.     The Bombay High Court formulated the following issues:
               “(i) A developer being removed on the non-fulfillment of
               the basic requirement to commence construction of a slum
               rehabilitation building for a long period of 18 years, whether
               is not fatal to the object and intention of a statutory intent
               behind a Slum Rehabilitation Scheme.
               (ii) Another question would be as to whether the right to
               shelter which is part of the slum dwellers’ right to livelihood
               guaranteed under Article 21 of the Constitution, can be



1    Hereinafter, referred to as the “Act”.
2    For short, the ‘AGRC’.
3    Writ Petition (L) No. 18022 of 2021.
[2024] 7 S.C.R.                                                                                1449

                          Yash Developers v.
       Harihar Krupa Co-Operative Housing Society Limited & Ors.

              continued to be nullified by such actions of unconscionable
              delay on the part of the developer, in not commencing
              construction of the slum project even by an inch more
              particularly when the nature of such work awarded to a
              developer for him is purely a commercial venture, for profit.”
4.    Apart from the above two issues, the High Court highlighted the
      limited scope of judicial review under Article 226 of the Constitution
      against the decision of the statutory authority-AGRC. The High Court,
      however, proceeded to examine the facts in full detail and dismissed
      the writ petition on facts, as well as on law.4 Thus, the present appeal.
5.    Even before us, the appellant argued the case only on facts, to the
      extent that we were under an illusion that we were hearing suit for
      specific performance involving an issue of ready and willingness.
      Having heard the learned counsels for the parties at length on
      facts, we will certainly deal with their submissions, but before that
      we must reiterate the limited scope of inquiry under Article 226 of
      the Constitution.
      II.     Scope of Judicial Review against an order under Section
              13 of the Act:
6.    In this case, as in any other public law proceedings, we are concerned
      with the legality and validity of the power exercised by the AGRC
      in terminating the development agreement with the appellant by its
      order dated 04.08.2021. This order is in exercise of power under
      Section 13 of the Act which is as under:
              “13. Power of Competent Authority to redevelop
              clearance area:
              (1)    Notwithstanding anything contained in sub-section (1)
                     of Section 12 the Competent Authority may, at any
                     time, after the land has been cleared of buildings in
                     accordance with a clearance order, but before the work
                     of redevelopment of that land has been commenced
                     by the owner, by order, determine to redevelop the
                     land at its own cost, if that Authority is satisfied that
                     it is necessary in the public interest to do so.


4    By judgment dated 14.10.2022, reported as 2022 SCC Online Bom 3712, hereinafter referred to as the
     impugned Judgment.
1450                                                              [2024] 7 S.C.R.

                            Digital Supreme Court Reports


             (2)     Where land has been cleared of the buildings in
                     accordance with a clearance order, the Competent
                     Authority, if it is satisfied that the land has been,
                     or is being, redeveloped by the owner thereof in
                     contravention of plans duly approved, or any restrictions
                     or conditions imposed under sub-section (10) of Section
                     12, or has not been redeveloped within the time, if
                     any, specified under such conditions, may, by order,
                     determine to redevelop the land at its own cost.
             Provided that, before passing such order, the owner
             shall be given a reasonable opportunity of showing
             cause why the order should not be passed.”
                                                      (emphasis supplied)
7.    Section 13(2) of the Act specifically empowers the competent
      authority to re-determine the agreement if it is satisfied that the
      re-development has not been done within the time specified. The
      provision is certainly a statutory incorporation of time integrity in
      the performance of the duty. We recognise this as a statutory duty
      of the competent authority to ensure that the project is completed
      within the prescribed time. We have no hesitation even in holding
      that a writ of mandamus would lie against the concerned authorities
      if they do not perform the statutory duty of ensuring that the project
      is completed within the time prescribed.
8.    In Susme Builders Pvt. Ltd. v. CEO, Slum Rehabilitation Authority
      & Ors.,5 this Court held that Section 13(2) of the Act empowers the
      statutory authorities to take action and hand over the project to some
      other agency if the development is being delayed. The relevant
      portions of the judgment are as under:-
             “49. Otherwise, there would be an anomalous situation
             where the Society would have terminated its contract
             with Susme but the letter of intent issued by the SRA
             would continue to hold the field and it would be entitled
             to develop the land. The Society approached the SRA,
             in fact, asking it to take action against Susme. Since the
             SRA is the authority which issued the letter of intent, it will
             definitely have the power to cancel the letter of intent...


5    [2018] 1 SCR 1 : (2018) 2 SCC 230
[2024] 7 S.C.R.                                                            1451

                          Yash Developers v.
       Harihar Krupa Co-Operative Housing Society Limited & Ors.

             …
             52. A bare reading of these provisions shows that in
             terms of clauses (c) and (d) of sub-section (3) of Section
             3-A of the Slum Act, the SRA not only has the power,
             but it is duty-bound to get the slum rehabilitation scheme
             implemented and to do all such other acts and things as
             will be necessary for achieving the object of rehabilitation
             of slums. In this case, the SRA was faced with a situation
             where the slum-dwellers were suffering for more than 25
             years and, therefore the action taken by SRA to remove
             Susme for the unjustified delay was totally justified.”
9.    Case after case, the Bombay High Court has been ruling that, a) the
      developer is duty-bound to complete the project within the stipulated
      time and that b) the Slum Rehabilitation Authority (SRA) has not
      merely the power but a broader duty to ensure that the developer
      completes the project within time. We will refer to those judgments,
      not so much to certify that the issue is no more res-integra, but to
      emphasise that the rulings have not had the desired impact, much
      less compliance. The reason is that, neither the developer nor the
      authority is asked to face the consequences of their derelictions.
      That Section 13(2) is a power coupled with duty is clear from the
      judgments of this Court and many other judgments of the High
      Courts, however experience tells us that this recognition of a statutory
      duty in itself is not sufficient. Until and unless duty is identified with
      accountability, judicial review is ineffective.
10. In Galaxy Enterprises v. State of Maharashtra,6 the Bombay High
    Court observed:
             “53. The record reveals that what M/s Saral could do in
             eight years of its appointment, was to get the Annexure II,
             namely the list of the 73 eligible occupants certified from
             the MHADA. It was, thus, expected from the petitioner
             that the revalidation of Annexure II, which was possibly
             not a complex formality be undertaken at the earliest.
             However this certainly did not happen and citing various
             reasons, which cannot be believed to be not attributable


6    2019 SCC OnLine Bom 897.
1452                                                       [2024] 7 S.C.R.

                   Digital Supreme Court Reports


        to the petitioner, ultimately, the petitioner could not get the
        Annexure II certified only on 23 December 2013, which is
        after about eight years of the petitioner’s appointment. This
        fact itself raises a serious doubt as to the real intentions
        of the petitioner to undertake the scheme. The petitioner
        could not have simply blamed the authorities for the
        delay, as there is complete lack of concrete and/or any
        real steps which were to be taken by the petitioner to
        effectively seek different approvals, once the society had
        put the petitioner in the driver’s seat, in complete control
        of the project as rightly commented, in the impugned
        orders. Thus, the case of the petitioner, that from time to
        time steps were taken to implement the slum scheme as
        entrusted to it be the society cannot be accepted. These
        are the contentions of the petitioner, merely pointing out
        some movement of the files with the authorities. This
        was certainly not sufficient and what was required and
        expected by the petitioner was to take real effective steps
        to progress the slum redevelopment. The petitioner was
        expected to expeditiously obtain an Annexure II, as certified
        by the MHADA, thereafter obtain a LOI and then obtain a
        Commencement Certificate to start with the constructions
        and before that make a provision for temporary alternate
        accommodation for the slum dwellers to reside till
        completion of the scheme. There is not an iota of material
        to show that any such steps much less expeditiously were
        taken by the petitioner which will show the real bonafides
        of the petitioner to undertake the scheme.
        54. In fact the petitioner kept the slum dwellers/society
        in dark on any of the steps alleged to be taken by the
        petitioner. There was no transparency in the petitioner’s
        approach with the slum-dwellers whose anxious, impatient
        and painful wait of so many years for the slum scheme to
        start was continuously staring at the petitioner’s right from
        the word go. This was not what was expected of a diligent
        developer. The slum schemes are expected to be taken and
        pursued by the developers for genuine and bonafide object
        and purpose to redevelop the slums as reflected in the
        rules which is for the mutual benefit namely the benefit of
[2024] 7 S.C.R.                                                            1453

                         Yash Developers v.
      Harihar Krupa Co-Operative Housing Society Limited & Ors.

           the slum dwellers of being provided a permanent alternate
           accommodation and so far as the developer, to exploit
           the free sale component, which is nothing but a business
           consideration for the developer. If this be the long and short
           of a slum scheme what can be the intention of a developer
           to sit tight on a slum scheme and not take expeditious
           measures to undertake and complete the scheme. The
           reasons can be innumerable, if the reasons are attributable
           to the authorities, the developer has certainly remedies in
           law to be immediately resorted. No forum competent to
           entertain such complaints would refuse to look into such
           grievances when the very right to livelihood of the slum
           dwellers who are living in inhuman conditions, being a
           concomitant of Article 21 of the Constitution, is involved
           and which becomes a matter of urgent concern and of
           utmost priority. A developer cannot shut his eyes to all
           these factors and attributes, once appointed by the society.
           For the developer, there has be relentless action on day
           to day basis as any delay in not implementing the slum
           scheme is not only detrimental to the slum dwellers, but
           to the society at large. Delay in effective implementation
           of the slum scheme would defeat the very goal, the ideals
           and the purpose of the slum redevelopment scheme.
           55. A perusal of the record indicates that the society is
           correct in contending that during the period from 2006 to
           2016 i.e. for about 10 years the petitioner did not take
           any concrete steps towards implementation of the slum
           rehabilitation scheme and the petitioner had clearly failed
           to obtain a LOI for such a long period. The society, thus,
           was constrained to file the application dated 15 March
           2016, under Section 13(2) of the Slums Act, praying for
           change of the petitioner as the developer. It is correct
           that Annexure-II was originally issued by MHADA on 16
           April 1998. The petitioner was appointed as developer
           in the month of June 2006 and it clearly took about
           seven to eight years for the petitioner to obtain revised
           Annexure-II which was obtained on 23 December 2013.
           Before the Chief Executive Officer and even before the
           appellate authority the petitioner has failed to show any
1454                                                         [2024] 7 S.C.R.

                   Digital Supreme Court Reports


        justifiable reason as to why it took these many years for
        the petitioner to simply obtain a revised Annexure-II when
        as per norms issued by the Slum Rehabilitation Authority
        Annexure-II is required to be finalised within a period of
        four months when the hutment dwellers are below 500 in
        number. Further the record clearly indicates that even after
        obtaining the revised Annexure II, on 23 December 2013,
        the petitioner did not initiate immediate steps to obtain LOI
        for the next three years. There is, thus, much substance
        in the contention of the society that only after the society
        initiated proceedings under Section 13(2) of the Slums
        Act, the petitioner initiated steps to obtain a LOI.
        ...
        57. There cannot be a myopic approach to these issues
        of a delay in implementation of a slum rehabilitation
        scheme. Things as they stand are required to be seen in
        their entirety. The only mantra for the slum schemes to be
        implemented is it’s time bound completion and a machinery
        to be evolved by the authorities, to have effective measures
        in that direction to monitor the schemes as a part of their
        statutory obligation to avoid delays. Non-commencement
        of the slum scheme for long years and substantial delay
        in completion of the slum schemes should be a thing of
        the past. In the present case, looked from any angle there
        is no plausible explanation forthcoming for the delay of
        so many years at the hands of the petitioner to take bare
        minimum steps to commence construction.
        58. The authorities should weed away and reprimand
        persons who are not genuine developers and who are
        merely agents and dealers in slum schemes. These
        persons after get themselves appointed as developers,
        to ultimately deal/sell the slum schemes, as if it is a
        commodity. Any loopholes in the rules to this effect,
        therefore, are required to be sealed.
        ...
        64. Thus, it is quite clear that inordinate delay is a sufficient
        ground for removal of a developer. There is neither any
[2024] 7 S.C.R.                                                                1455

                         Yash Developers v.
      Harihar Krupa Co-Operative Housing Society Limited & Ors.

            perversity nor any illegality in the findings as recorded by
            both authorities below, in observing that the petitioner had
            grossly delayed the implementation of the slum scheme in
            question. The findings as recorded in the impugned order
            passed by the Apex Grievance Redressal Committee are
            also sufficiently borne out by the files produced before
            this Court…”
                                                     (emphasis supplied)
11. A Full Bench of the Bombay High Court in Tulsiwadi Navnirman Co-
    op Housing Society Ltd. & Anr. v. State of Maharashtra & Ors.,7 held
    that the SRA has been conferred with certain powers and each one
    of them is coupled with a duty. If the slum dwellers are eligible to be
    rehabilitated at the site and within a reasonable period, they cannot
    be left at the mercy of developers and builders. The slum dwellers
    cannot be expected to occupy a transit accommodation endlessly,
    without proper maintenance, and hygiene. An independent and
    impartial implementation, supervision and monitoring of the projects
    is the purpose for which the authority has been set up under the Act.
12. In New Janta SRA CHS Ltd. v. State of Maharashtra,8 the High Court
    considered the dispute between two rival societies claiming rights
    over a slum scheme. The Court observed as under:-
            “187. It thus cannot be accepted more particularly
            considering the provisions of Section 13(2) of the Slums Act
            that a slum society at its sole discretion and/or without any
            control and regulations by SRA can change the developer.
            If such a course of action is made permissible, considering
            the hard realities and the hundreds of developers being
            available to take over such schemes, it would create a
            chaos and it is likely that a situation is created, that the slum
            rehabilitation scheme never takes off and it is entangled
            into fights between two factions within the society and/or
            two rival developers. This is certainly not the object of the
            legislation. It would be too farfetched to read such draconian
            rights available to the Managing Committee or to general



7   2008(1) Bom.C.R.1.
8   2019 SCC Online Bom 3896.
1456                                                            [2024] 7 S.C.R.

                          Digital Supreme Court Reports


            body of a society without any regulation, supervision and
            control of the SRA to change the developer. The SRA
            has all the powers not only to regulate and control such
            situations but to take a decision as to what is in the best
            interest of the slum dwellers and intended to achieve the
            object of the legislation.
            188. Secondly it is not in dispute that the application of the
            petitioner for change of respondent no.5-developer was
            under Section 13(2) of the Slums Act. Having noted this
            provision in the foregoing paragraphs, Section 13(2) of the
            Slums Act would come into play only when the developer
            fails to adhere to the provisions of the development
            permissions granted by the SRA and a change of developer
            can be sought only when there is an inordinate delay or
            the construction carried on, is contrary to the sanctioned
            plans and/or the permissions. Considering this clear position
            falling under Section 13(2), in the context of this factual
            controversy as raised by the petitioner in regard to the
            consent of 70% of the slum dwellers being not available
            to respondent no.5, 1 am of the clear opinion that the view
            taken by both the authorities, in not accepting the petitioner’s
            contention, is required to be held to be correct and valid. “
     III.   Accountability of officers exercising power coupled with
            duty under Section 13:
13. Two facets of Section 13 (2) of the Act are that; a) the SRA
    has the power to redevelop the project if it is satisfied that the
    development is not proceeding within the time specified, and
    b) that power of SRA is coupled with a duty to ensure that the project
    is completed within time. We hold that the SRA is accountable for the
    performance of this duty. Accountability need not be superimposed by
    the text of a statute, it exists wherever power is granted to accomplish
    statutory purpose. In Vijay Rajmohan v. CBI,9 this Court held:-
            “34. Accountability in itself is an essential principle of
            administrative law. Judicial review of administrative action
            will be effective and meaningful by ensuring accountability
            of the officer or authority in charge.


9   [2022] 19 SCR 563 : (2023) 1 SCC 329
[2024] 7 S.C.R.                                                                                        1457

                          Yash Developers v.
       Harihar Krupa Co-Operative Housing Society Limited & Ors.

               35. The principle of accountability is considered as a
               cornerstone of the human rights framework. It is a crucial
               feature that must govern the relationship between “duty
               bearers” in authority and “right holders” affected by their
               actions. Accountability of institutions is also one of the
               development goals adopted by the United Nations in 201510
               and is also recognised as one of the six principles of the
               Citizens Charter Movement.11
               36. Accountability has three essential constituent
               dimensions: (i) responsibility, (ii) answerability, and (iii)
               enforceability. Responsibility requires the identification
               of duties and performance obligations of individuals in
               authority and with authorities. Answerability requires
               reasoned decision-making so that those affected by their
               decisions, including the public, are aware of the same.
               Enforceability requires appropriate corrective and remedial
               action against lack of responsibility and accountability to be
               taken.12 Accountability has a corrective function, making it
               possible to address individual or collective grievances. It
               enables action against officials or institutions for dereliction
               of duty. It also has a preventive function that helps to
               identify the procedure or policy which has become non-
               functional and to improve upon it.”
14. For effective implementation of the principle of accountability of power
    under the Act, we identify the duties and performance obligations of
    the CEO. It is evident from the statutory scheme that the responsibility
    vests in the CEO, defined under Section 2 (b+a) read with Section
    3A(2) of the Act. The CEO reports to the SRA, the duty of which
    is defined under Section 3B of the Act. One of the most important
    duties of the SRA is to ensure that the Slum Rehabilitation Scheme
    is implemented.



10   United Nations General Assembly Resolution 70/1 dated 25-9-2015.
11   Citizens Charter adopted by the Government in the “Conference of Chief Ministers of various States and
     Union Territories” held in May 1997 in New Delhi, available from https://goicharters.nic.in/public/website/
     home.
12   See Office of United Nations High Commissioner for Human Rights, Who will be Accountable? Human
     Rights and the Post-2015 Development Agenda, available from http://www.ohchr.org/Documents/
     Publications/WhoWillBeAccountable.pdf
1458                                                         [2024] 7 S.C.R.

                              Digital Supreme Court Reports


       14.1. The primary responsibility to implement Section 13 of the Act
             and allied provisions and to monitor compliances of schemes
             and agreements vests with the CEO. If the actions of CEO are
             based on the directions of the SRA, then the SRA must equally
             bear the responsibility. The CEO and/or the SRA must explain
             the delay in implementation, failing which, the consequences
             as determined by the court will follow.
                                                    PART-II
       IV.     Submissions and Analysis:
15. Returning to facts of the case, Mr. Kapil Sibal, learned senior counsel,
    appearing on behalf of the appellant, articulated the allegation of delay
    into six parts and in his inimitable style proceeded to explain how in
    each part, the appellant had no role and not at all responsible. We
    will deal with each phase of delay in the same manner as Mr. Sibal
    has presented the case before us.
16. (i) The first phase of delay is between 2003 and 2011. The relevant
    facts are as follows.
       16.1. The appellant was appointed by respondent no.1 to develop
             the Project under a development agreement dated 20.08.2003,
             following which the appellant made a proposal for development
             on 11.12.2003. The Municipal Corporation of Greater Mumbai,
             however, assigned the re-development to a rival society,
             namely Omkareshwar Co-Operative Housing Society13 and a
             developer, namely Siddhivinayak Developers14 on 06.05.2004.
             Pursuant to this, on 07.09.2004, the SRA accepted the
             proposal given by Omkareshwar and Siddhivinayak for the
             development of the Property. After a long-drawn litigation
             between the appellant and respondent no. 1 on one side,
             and Omkareshwar and Siddhivinayak on the other, the CEO,
             SRA finally settled the dispute by its order dated 07.06.2011
             and held that the appellant had the required 70% consent of
             individual slum dwellers to implement the project and also
             that the proposal of Omkareshwar was not valid as it was



13   Hereinafter, referred to as “Omkareshwar”.
14   Hereinafter, referred to as “Siddhivinayak”.
[2024] 7 S.C.R.                                                          1459

                          Yash Developers v.
       Harihar Krupa Co-Operative Housing Society Limited & Ors.

                made after the proposal of respondent no.1. Dealing with
                the period, Mr. Sibal has submitted that multiple proceedings
                between the appellant and respondent no. 1 on one side and
                Omkareshwar and Siddhivinayak on the other consumed lot of
                time. While the High Court initially disposed of a writ petition
                recording a settlement that appellant and respondent no.1 are
                entitled to develop the Property, Omkareshwar challenged it
                leading to several rounds of litigation before the High-Powered
                Committee15 and the High Court. The issue was laid to rest
                only on 07.06.2011 by an order of the CEO, SRA holding that
                the appellant enjoyed the consent of 70% of eligible slum
                dwellers and hence was qualified to be the developer. Mr.
                Sibal has submitted that the consequence of this litigation is
                that the LOI could be issued in favour of the appellant only
                on 29.06.2011, i.e. after this dispute was settled. The eight
                years’ delay in obtaining the LOI was inevitable and was not
                due to any fault of the appellant.
      16.2. Per contra, Mr. C A Sundaram, learned senior counsel,
            appearing for the respondent no.6-Veena Developers, has
            submitted that the appellant did not have the financial capacity
            or the technical expertise to complete the project within the
            prescribed time of 3 years. It is due to this reason that the
            appellant was unable to commence construction even when
            all the requisite permissions and approvals had been obtained.
            Further, Mr. Huzefa Ahmadi, learned senior counsel,
            appearing for respondent nos.8-48, who are some of the slum
            dwellers, has submitted that the delay in the construction is
            entirely attributable to the appellant. He submitted that the
            appellant did not take any action to obtain the LOI anytime
            between 2003-2011.
      16.3. While adjudicating on the delay in implementation of the
            project during 2003-2011, the AGRC relied on clause 11
            of the development agreement dated 20.08.2003 requiring
            the appellant to complete the development of the project
            within three years from the issuance of the Commencement
            Certificate dated 14.07.2014.


15   Hereinafter, referred to as the “HPC”.
1460                                                          [2024] 7 S.C.R.

                               Digital Supreme Court Reports


       16.4. On the issue of delay from 2003 to 2011, the High Court
             examined the facts independently and upheld the findings of
             the AGRC. The High Court held that a delay cannot be viewed
             as reasonable. Further, the High Court held that the litigation
             with Omkareshwar did not prevent the appellant from starting
             the project, especially when the appellant had the consent of
             more than 70% of the slum dwellers at all material times. The
             High Court also observed that the appellant was not diligent
             in procuring the LOI.
17. (ii) The second phase relates to the delay in obtaining necessary
    permissions, approvals and environmental clearances from 2011 to
    2014. The SRA issued Annexure-III, certifying the financial capability
    of a developer on 21.06.2011 and this was followed by issuance
    of LOI dated 29.06.2011. The appellant applied for Environmental
    Clearance16 on 15.12.2011 and obtained it only on 28.04.2014. The
    Commencement Certificate for the construction of the rehabilitation
    building and the high-rise clearance by the Municipal Corporation
    of Greater Mumbai were issued to the appellant on 14.07.2014 and
    09.10.2014, respectively.
       17.1. In the above referred background, Mr. Sibal submitted that the
             EC had to be obtained before the Commencement Certificate
             could be issued for the construction of the rehabilitation
             building. For on-site construction of more than 20,000 square
             meters, EC is required and for this, he relied on condition no.
             51 of the LOI dated 29.06.2011 and condition no. 38 of the
             intimation of approval dated 21.04.2012. While the appellant
             made an application for EC in the year 2011, it was granted
             only on 28.04.2014. He has submitted that the delay between
             2011-2014 was again unavoidable as certain mandatory
             permissions were required. Per contra, Mr. Ahmadi submitted
             that an EC was not required to commence construction of
             the rehabilitation building as the on-site construction did not
             exceed 20,000 square meters.
       17.2. Upon perusing the record, the AGRC found that the delay was
             indeed attributable to the appellant. The High Court also noticed
             that the appellant did not commence the construction after


16   Hereinafter, referred to as “EC”.
[2024] 7 S.C.R.                                                       1461

                         Yash Developers v.
      Harihar Krupa Co-Operative Housing Society Limited & Ors.

           getting the necessary approvals but waited for the EC. The
           High Court also noted that some parts of the project like the
           rehabilitation building did not require an EC for commencing
           construction.
18. (iii) The third phase of delay relates to the alleged non-cooperation
    of certain slum dwellers leading to the stalling of the project from
    2014 to 2019. Mr. Sibal submitted that as some of the slum dwellers
    were not cooperative, applications under Sections 33 and 38 of the
    Act for eviction were made to the Assistant Municipal Commissioner,
    MCGM. Initially, the Deputy Collector passed orders on 05.11.2020
    observing that the eviction proceedings can be taken forward only
    after directions from the High Court and in the meanwhile directed the
    appellant to deposit 11 months rent concerning 30 non-cooperating
    slum dwellers. These applications under Sections 33 and 38 of the Act
    came to be decided only in 2021, and that is how, it is submitted, the
    project got delayed for reasons beyond the control of the appellant.
     18.1. Mr. Ahmadi submitted that the pendency of the eviction
           applications does not justify the extraordinary delay of 5
           years on the part of the appellant. Mr. Sundaram submitted
           that the mere filing of applications under Sections 33 and 38
           of the Act is not sufficient to justify the delay. It is submitted
           that the appellant has failed to take active steps in getting the
           applications disposed of. This inaction suited the appellant as
           it did not have the capacity or the capability to complete the
           project.
     18.2. Affirming the findings of the AGRC, the High Court observed that
           the appellant went into deep slumber after filing applications for
           eviction of non-cooperating slum dwellers between 2014-2015.
     18.3. The fact that the appellant had to initiate proceedings against
           certain non-cooperating members and that the proceedings
           were pending for a long time, whether justified or not, should not
           have a bearing on the obligations of the appellant to complete
           and handover the project as per the development agreement.
           Under no circumstance, litigation of this nature would justify
           inaction from 2014 to 2019.
19. (iv) The next period of inaction is from 2015 to 2017. This is sought to
    be justified on the ground that the Municipal Corporation sanctioned
1462                                                      [2024] 7 S.C.R.

                    Digital Supreme Court Reports


     a road that may pass through the property and published the draft
     development plan (DP) on 25.02.2015.
     19.1. The objections filed by the appellant on 03.04.2015 eventually
           came to be disposed of only on 12.11.2018 when the said road
           was deleted from the development plan. This period, Mr. Sibal
           submits, must be excluded as no development, much less any
           construction, is permissible once the draft plan is published.
     19.2. Mr. Sundaram submitted that if the appellant had commenced
           the construction after the commencement certificate dated
           14.07.2014, the draft development plan published in 2015
           could never have affected the re-development at all. He
           further submitted that as LOI and IOA were issued in 2011 and
           2012, the so-called draft DP published in 2015 cannot be a
           justification. Mr. Ahmadi has submitted that except for 2 months
           between 25.02.2015 and 23.04.2015, there was no proposed
           development plan road in any of the plans. He would submit
           that the proposed DP road affected only the proposed sale
           building, not the entire project. In any event, he would submit
           that the sale building could not have commenced till substantial
           progress in rehabilitation building was made.
     19.3. The observations of AGRC also go to show that draft DP could
           justify 2 years’ delay and no more. The High Court observed
           that the notification dated 25.02.2015 under no circumstances
           precluded the appellant from starting construction of other
           parts of the Property.
20. (v) Re: Appellant did not have the financial resources. Dealing with
    the findings of the AGRC and the High Court that the appellant did
    not have the financial resources as evidenced by the agreements
    that they have executed in favour of third parties, Mr. Sibal
    submitted that this issue was never raised in the show-cause notice
    dated 04.12.2020, which initiated the proceedings leading to the
    termination of the development agreement of the appellant. The
    factual background is that from 2017 onwards, the appellant executed
    certain financial agreements with third parties. On 17.02.2017, an
    agreement with M/s Rajesh Habitat Private Limited was executed as
    per which the saleable rights under the project were transferred in
    favour of Rajesh Habitat in lieu of finance of Rs. 30 crores. Further,
    Rajesh Habitat mortgaged their rights in favour of M/s Vistra ITCL
[2024] 7 S.C.R.                                                             1463

                         Yash Developers v.
      Harihar Krupa Co-Operative Housing Society Limited & Ors.

     by a deed dated 22.03.2017, which later came to be cancelled on
     08.02.2019 and a deed of reconveyance between the appellant and
     Vistra was entered into. Later, one M/s Sanghvi Associates provided
     financial assistance of Rs. 50 crores to the appellant by way of a
     mortgage deed. In pursuance of these financing arrangements,
     Sanghvi Associates gave no objection to the appellant entering into
     an agreement with respondent no.6-Veena Developers. Following
     this, a joint development agreement dated 18.10.2019 was entered
     into between the appellant and respondent no. 6.
     20.1. Mr. Sibal contended that the appellant has the requisite financial
           capacity of technical expertise to complete the project. He
           would submit that these agreements do not establish that the
           appellant does not have the financial capacity or the technical
           expertise to undertake and complete the project. That the
           appellant had the capacity is evidenced by the deposit of rents
           due to the slum dwellers and in fact, the SRA has certified the
           appellant’s financial capacity on 21.12.2019.
     20.2. Mr. Sundaram submitted that all the documents were before
           the SRA and that the parties have made submissions on all
           aspects of the matter. He has taken us through the various
           findings of the High Court on the finances and the clauses in
           the agreements entered into with the third parties. The following
           findings of the High Court were referred to:
                “57. In any case, the petitioner struggled to avail
                finance and was facing severe financial crisis, this
                itself was material for the Chief Executive Officer of
                the SRA to come to a conclusion that it may not be
                possible for the petitioner to execute the scheme. The
                Chief Executive Officer however did not call upon the
                petitioner to satisfy that it had the appropriate finances
                to undertake the “entire scheme”. The Chief Executive
                Officer merely asking the petitioner to deposit the
                arrears of rent, can in no manner, whatsoever, be
                accepted as a certificate to the petitioner possessing
                a financial capacity to complete the project.
                58. It is crystal clear from the petitioner’s own
                showing that the petitioner was required to take the
                crutches/financial assistance initially from Rajesh
1464                                                         [2024] 7 S.C.R.

                    Digital Supreme Court Reports


              Habitat Pvt. Ltd., who in turn looked at Vistra ITCL
              India Ltd. and thereafter having failed with both these
              entities, with one M/s Sanghvi Associates, which is
              not for a small amount but for a substantial amount
              of Rs. 50 crores. Things however would not stop at
              this and subsequently it appears that now respondent
              no.6-Veena Developers was roped in, to provide
              working capital for the entire project described to be
              the business partners/joint developers of the petitioner
              as in para 1 of the petition.”
    20.3. Mr. Sundaram also brought to our notice certain clauses in
          agreements with third parties and submitted that this amounts
          to complete subversion of the scheme. High Court has reflected
          on these clauses. The following findings of the High Court are
          important:
         “73. Certainly, the period of two years as contractually
         agreed, under the development agreement cannot be
         stretched to such a long period of almost 17 to 18 years
         as in the present case, despite these circumstances, an
         attempt on the part of the petitioner to justify that such delay
         was not attributable to the petitioner, at least in the facts
         of the case, is wholly untenable. The AGRC examined the
         case of the petitioner and of the society and the situation
         persisting at the ground level. The AGRC however not
         agreeing with the findings of the Chief Executive Officer-
         SRA, has reached a conclusion that the petitioner could
         not take the project forward for reasons which were borne
         out by the record.
         74. In these circumstances to upset the decision of the
         AGRC would amount to rewarding the petitioner of its
         defaults and the breaches committed by it, not only of the
         very terms and conditions of the Development Agreement,
         but also, the clear statutory mandate in undertaking Slums
         Rehabilitation Schemes. In fact, the petitioner has betrayed
         the trust of the society/slum dwellers. Even otherwise, a
         closer scrutiny of the petitioner’s actions clearly hint of the
         petitioner’s interest not in the rehabilitation of the slum
         dwellers but in its own private interest, solely in relation
[2024] 7 S.C.R.                                                      1465

                         Yash Developers v.
      Harihar Krupa Co-Operative Housing Society Limited & Ors.

           to the sale component. There cannot be a space for a
           pure commercial greed in taking up such projects which
           involves the basic rights of the slum dwellers.”
21. (vi) Re: Submission on maintainability of proceedings before
    AGRC. Finally, Mr. Sibal submitted that the complaints filed by
    the 12 members of the managing committee of respondent no.1 on
    18.11.2019 were withdrawn by 8 members on 31.12.2019 and by
    another member on 14.01.2020. Consequently, the show-cause notice
    dated 04.12.2020, based on these complaints, was rightly withdrawn
    on 16.03.2021. Secondly, although the managing committee of
    respondent no. 1 had initially terminated the development agreement
    on 02.02.2020, this termination was revoked on 28.02.2021. The
    revocation of termination was because the agreement was terminated
    by Mr. Rai, who did not have the requisite authorisation. Mr. Sibal has
    relied on the above to submit that respondent no.1 did not object to
    the withdrawal of the termination of the development agreement of
    the appellant, and in fact, wanted the appellant to continue as the
    developer. He would further submit that Mr. Rai was acting without
    the authorisation of the other members, and hence, he also could
    not have filed an appeal before the AGRC on behalf of respondent
    no.1 against the order of the respondent no. 3 – CEO, SRA dated
    16.03.2021 that dropped the proceedings against the appellant.
    Mr. Navare, learned senior counsel, appearing for some of the
    slum dwellers, supported the submissions put forth by Mr. Sibal
    regarding the lack of authorisation of Mr. Rai to act on behalf of
    respondent no. 1.
     21.1. Mr. Sundaram submitted that the appeal before the AGRC
           against the order dated 16.03.2021 was maintainable even if
           some of the complaints filed on 18.11.2019 were withdrawn.
           He submits that Mr. Rai, who filed the appeal, had the requisite
           locus because he, along with some others, had also filed
           complaints that were not withdrawn. It is submitted that Mr.
           Rai was still a slum dweller and a member of respondent
           no.1 and hence, was an ‘aggrieved person’ against the
           order dated 16.03.2021. There were also, as many as 132
           complaints against the appellant by other slum dwellers who
           filed complaints in January and February, 2021 before the SRA
           under Section 13(2) of the Act alleging non-payment of rent.
           Lastly, he submits that in any case, the SRA has the power to
1466                                                     [2024] 7 S.C.R.

                      Digital Supreme Court Reports


           suo moto proceed against the appellant under Section 13(2) of
           the Act and therefore the withdrawal of complaints is not fatal
           to proceeding against the appellant and does not preclude the
           AGRC from deciding the appeal. Mr. Ahmadi made a submission
           along the same lines and to the same effect.
     21.2. Answering the question regarding the maintainability of the
           proceedings after the complaints dated 18.11.2019 were
           withdrawn, the High Court held that even if many complaints
           before the SRA were withdrawn, the complaint filed by Mr.
           Rai survived to be adjudicated. Further, the High Court
           rejected the contention of the appellant that Mr. Rai was not
           authorised by respondent no. 1 to take any action against the
           appellant. In order to reach this conclusion, the High Court
           observed that if the contention of the appellant was true,
           then respondent no. 1 would have supported the appellant
           before the High Court; however, this was not the case. The
           High Court also held that in any case, the SRA and the
           AGRC have the requisite power under Section 13(2) of the
           Act to suo moto examine the delay caused by the appellant
           in implementing the project.
22. (vii) Re: Locus or conflict of respondent no.6: Mr. Sibal concluded
    his submissions by arguing that respondent no.6 does not have the
    locus to take a stand contrary to that of the appellant as it has been
    involved with the venture from the time of the joint development
    agreement dated 18.10.2019. For this reason, he would submit that
    the findings of AGRC and the High Court must apply to respondent
    no. 6 as well.
     22.1. Mr. Dhruv Mehta, learned senior counsel, appearing for the
           administrator of respondent no.1 has argued that Section 13(2)
           of the Act empowers and places an obligation upon the SRA
           to take action against the developer when the project is not
           being implemented. Therefore, he submits that even if some
           of the complaints have been withdrawn, the termination of the
           development agreement is valid.
     V.   Findings:
23. Having considered the findings of the AGRC and the High Court in
    detail, we have found them to be correct on law and fact. Further,
    having independently considered the detailed submissions of the
[2024] 7 S.C.R.                                                       1467

                         Yash Developers v.
      Harihar Krupa Co-Operative Housing Society Limited & Ors.

      appellant and the respondents, on delay as well as on lack of
      financial and technical capabilities and maintainability of the appeal,
      we proceed to analyse and discuss them as follows.
24. Admittedly, the delay in executing the project, by the time of the
    termination order is more than 16 years. This period is sought to
    be explained by fragmenting it into bits and pieces falling between
    2003 to 2011, 2011 to 2014 and 2014 to 2019.
25. What amuses us is that we are called upon to hold that the order of
    termination for delaying the project for 16 years must be held to be
    bad by examining each episode of delay as independent and stand
    alone. Judicial Review Courts enquiring into these allegations would
    only examine whether it would be arbitrary and/or unreasonable to
    exclude the delay caused because of the incidents that occurred from
    2003 to 2019. In other words, the inquiry must be to see whether it
    would be unjust if we do not account for the long-drawn litigation with
    a competing builder between 2003 to 2011, the delay in obtaining the
    environmental clearances from 2011 to 2014, or the delay caused
    due to non-cooperation of certain slum dwellers.
26.    Having examined the matter, we are of the opinion that the delay of
      8 years in resolving disputes with a competing builder cannot be a
      justification under any circumstance. The appellant is a developer and
      fully understands the process of obtaining environmental clearances
      while other sanctions and permissions are pending, and it is for him
      to make all the necessary arrangements. To say the least, the non-
      cooperation of some of the members cannot be a ground for delaying
      the project from 2014 to 2019. The findings of the AGRC and the High
      Court are very clear, they have correctly held that the delay caused
      due to the sanction of the draft DP for the construction of the road
      cannot be a justification for delaying the project from 2015 to 2019.
27. In any event, execution of the project under the Slum Rehabilitation
    Scheme cannot be viewed as a real estate development project.
    There is a public purpose involved, and that is inextricably connected
    to the right to life of some of our brother and sister citizens who are
    living in pathetic conditions. While we reject the justifications given
    by the appellant for delaying the project, we are fully conscious of
    the dereliction of the statutory duty of the SRA in ensuring that the
    project is completed within time. We have already expressed our
    opinion that the CEO and the SRA are accountable for their actions.
1468                                                         [2024] 7 S.C.R.

                     Digital Supreme Court Reports


     While we reject the justification for delay, we record our dissatisfaction
     about the indifference, amounting to negligence on the part of CEO
     and the SRA.
28. So far as the submissions relating to the financial resources are
    concerned, we have seen the number of agreements that the
    appellants have entered into. We need not examine this aspect
    independently as the findings are concurrent and thorough. The
    following findings of the High Court are sufficient for disposing of
    this issue:
          “59. The petitioner time and again having approached
          third parties for financial requirements in the manner
          as discussed above, in fact was quite fatal and counter
          productive to the implementation of the slum scheme, for
          the reason that if any of the financers were to withdraw
          from their financial support and the commitments as made
          to the petitioner, the same would leave the petitioner with
          no remedy but to wander further hunting for fresh finance.
          Such financial instability of a developer certainly would
          have a devastating effect on the implementation of the
          slum scheme which could also result in the total collapse
          of the slum scheme being implemented and in fact a death
          knell for the slum scheme. It is for such reason, the real
          wherewithal and financial stability of a developer plays an
          extremely pivotal role, as finance is the very lifeline for
          successful implementation and completion of the slum
          scheme. The present case is a classic case of how the
          petitioner is running helter-skelter to secure finance, that
          too without taking the society into confidence much less
          the authorities. This on the basis of a solitary clause in
          the Development Agreement which is being discussed
          hereafter.”
29. We will now deal with the submission on the maintainability of the
    appeal before the AGRC and that respondent no. 6 who was the
    collaborator of the appellant must face the same consequence as
    that of the appellant. This submission proceeds on the assumption
    that the statutory power under Section 13(2) of the Act is to be
    exercised only upon an application made to the authority. This is a
    complete misconception. We have already dealt with the scope and
[2024] 7 S.C.R.                                                      1469

                         Yash Developers v.
      Harihar Krupa Co-Operative Housing Society Limited & Ors.

     ambit of Section 13 of the Act, and in particular the duty followed
     by accountability of the SRA under the said provision. Irrespective
     of whether anybody applied or not, the authority is bound to ensure
     that the project is completed within the time stipulated. In any event,
     as the dispute before us is confined to the legality and propriety of
     the termination order, we are not concerned about the relationship
     of the appellant with respondent no. 6.
     VI.   Conclusion:
30. For the reasons stated above, there is no merit in this appeal, and we
    dismiss the Civil Appeal arising out of SLP (C) No. 20844 of 2022
    with costs quantified at Rs. 1,00,000/- (Rupees One Lakh) payable
    to Supreme Court Mediation and Conciliation Project Committee.
    In view of our decision, no further orders are necessary in the
    Contempt Petition (Civil) No. 217 of 2024.
31. Pending applications, if any, stand disposed of.
     VII. Re : Performance audit of statute:
32. Though we have disposed of this Civil Appeal by dismissing it, we
    must record that this case has provoked us to reflect on the working
    of this Act.
33. The Act came into being in 1971 and since then, for over five decades,
    the High Court has been exercising judicial review jurisdiction,
    disposing of Writ Petitions raising claims or challenges to the exercise
    of powers or dereliction of duties by Authorities under the Act. Data
    fetched from National Judicial Data Grid (NJDG) reveals that a total
    of 1612 cases involving disputes arising under the Act are pending
    before the Bombay High Court. Of these, 135 cases are more than
    10 years old. In the last 20 years, 4488 cases have been filed and
    disposed of under the said Act. Latest data from the Bombay High
    Court reveal that about 923 cases on the Appellate side and 738 on
    the Original Side are pending adjudication. The Act is a beneficial
    legislation, intended to materialize the Constitutional assurance of
    dignity of the individual by providing basic housing, so integral to
    human life. However, the propensity and the proclivity of the statute
    to generate litigation are worrisome. There seems to be a problem
    with the statutory framework for realizing the purpose and object
    of the statute. In M/s. Galaxy Enterprises v. State of Maharashtra
    (supra) the Bombay High Court has remarked that:
1470                                                         [2024] 7 S.C.R.

                    Digital Supreme Court Reports


         “3. …Nonetheless, considering the volumes of disputes
         still reaching the Courts, it can certainly be said that
         time is ripe, if not too late, to ponder, whether things are
         realistically working in the right direction, to eradicate slums
         and rehabilitate the slum dwellers, with the desired efficacy
         and expedition. This not only at the hands of the authorities
         but also at the hands of the other stake holders. The vital
         issue which has often led to controversy and disputes, is
         on the rules permitting, the selection and appointment of
         developers to undertake a Slum Rehabilitation Scheme,
         being conferred on the slum dwellers, who are hardly
         expected to know the nitty-gritty of the slum redevelopment
         schemes. It is seen that the so called leaders of the slum
         dwellers who are themselves in need to be rehabilitated,
         are often lured by developers and their agents, and once
         a developer is appointed, what normally prevails is a
         constant fear of incertitude and scepticism amongst the
         slum dwellers, leading to disputes on variety of issues
         affecting their final rehabilitation. Such issues not only
         frustrate the very object of a speedy slum redevelopment
         but completely derail the slum schemes. It can be seen
         that scores of slum schemes have remained incomplete for
         years together and are languishing on such issues, either
         in litigation before Courts and/or before the authorities.
         These schemes need not face such ordeal, including
         of an unending litigation. To change the developer is no
         answer as even this process involves dispute resolution
         and ultimately lengthy litigation from one forum to another.”
    33.1. Further, referring to the statutory scheme, as per which
          development is possible only when the slum dwellers feel the
          need and seek development, the High Court pointed out yet
          another problem about the statutory framework in the following
          terms;
         “…It cannot be countenanced that the slums be
         redeveloped only when the slum dwellers feel the need
         of a redevelopment and the Government Authorities cannot
         initiate redevelopment and cannot initiate a suo motu action
         in that behalf. It is hence, for the Government and the
         Slum Authority to give its anxious consideration to these
[2024] 7 S.C.R.                                                          1471

                         Yash Developers v.
      Harihar Krupa Co-Operative Housing Society Limited & Ors.

           issues and in its wisdom to device a substantial, nay a
           full proof mechanism, by undertaking a study and identify
           these grey areas, so that the helping hand as extended by
           the legislature in providing this beneficial law as far back
           in 1971 that is almost 50 years back is held strongly and
           firmly by all concerned. It is never too late.”
34. The exasperation of the High Court about working of the Act is
    understandable. The present appeal is a classic example of why the
    High Court’s concern is genuine. It has been noticed that the statutory
    scheme is problematic with respect to: i) Identification and declaration
    of land as a slum. This problem involves an examination of the role of
    authorities in giving such recognition, insidious intervention of builders
    in the said process cast doubts on the independence and integrity in
    the decision-making process; ii) Identification of slum dwellers: This
    involves a complicated process of proof of such a status, the attendant
    problem of groupism, giving rise to competing claims inevitably leading
    to litigation; iii) Selection of a developer: The Act leaves this decision
    to the cooperative society of slum dwellers and the majority decision
    is manipulated by competing and rival developers; iv) Apportionment
    of the slum land between redevelopment area and sale area: This
    is yet another area where court has witnessed developers seeking
    to increase the proportion of the sale area, leading to contestation;
    v) Obligation to provide transit accommodation for the slum dwellers
    pending redevelopment: Invariably, we see instances where the
    developer does not provide transit accommodation within time or
    provides an inadequate alternative in the form of a quantified amount
    towards rent, On the other hand, there are instances where some
    slum dwellers refuse to vacate the premises on the ground that the
    transit accommodation is either inconvenient or the amount offered
    is insufficient; vi) There are also issues of lack of independence and
    objectivity in the functioning of statutory authorities: This is a matter
    of serious concern. Courts have witnesses that the authorities have
    no independence and, their tenure is also short. Additionally, the
    functioning of these statutory authorities gives an indication that there
    could be a regulatory capture; vii) Another concern which exists is
    about the effectiveness of statutory remedies: Statutory remedies
    are ineffective and at the same time, lacking in accountability and
    vii) Judicial review proceedings under Art. 226 cannot be a long-
    term solution: We have given details of the number of writ petitions
    pending before the High Court in Para 33.
1472                                                                                 [2024] 7 S.C.R.

                              Digital Supreme Court Reports


35. The above-referred problems arising out of the statutory scheme and
    policy framework should have come under review by the State of
    Maharashtra. Assessment of the working of the statute to realise if
    its purpose and objective achieved or not is the implied duty of the
    executive government. Reviewing and assessing the implementation
    of a statute is an integral part of Rule of Law. It is in recognition of
    this obligation of the executive government that the constitutional
    courts have directed governments to carry performance audit of
    statutes.
36. Four aspects for achieving justice are well founded and articulated as,
    i) distribution of advantages and disadvantages of society, ii) curbing
    the abuse of power and liberty, iii) deciding disputes and, iv) adapting
    to change.17 Adapting to change is important for achieving justice,
    as failure to adapt produces injustice and is, in a sense, an abuse
    of power. Thus, failure to use power to adapt to change is in its own
    way an abuse of power. In fact, the issue is not one of change or not
    to change, but of the direction and the speed of change and such
    a change may come in various ways, and most effectively through
    legislation. Legal reform through legislative correction improves the
    legal system and it would require assessment of the working of
    the law, its accessibility, utility and abuse as well. The Executive
    branch has a constitutional duty to ensure that the purpose and
    object of a statute is accomplished while implementing it. It has the
    additional duty to closely monitor the working of a statute and must
    have a continuous and a real time assessment of the impact that
    the statute is having. As stated above, reviewing and assessing
    the implementation of a statute is an integral part of Rule of Law.
    The purpose of such review is to ensure that a law is working out
    in practice as it was intended. If not, to understand the reason and
    address it quickly. It is in this perspective that this court has, in a
    number of cases, directed the Executive to carry a performance/
    assessment audit of a statute or has suggested amendments to
    the provisions of a particular enactment so as to remove perceived
    infirmities in its working.18



17   See: Justice in Adapting to Change, in R.W.M. Dias, Jurisprudence, 305-327 (5th edn., 2013).
18   State of Haryana v. Mukesh Kumar (2011) 10 SCC 404; Pravin Electricals (P) Ltd. v. Galaxy Infra &
     Engineering (P) Ltd. (2021) 5 SCC 671; Preeti Gupta v. State of Jharkhand (2010) 7 SCC 667; Arif Azim
     Co. Ltd. v. Aptech Ltd. (2024) 5 SCC 313; Public Interest Foundation v. Union of India (2019) 3 SCC 224.
[2024] 7 S.C.R.                                                                                          1473

                          Yash Developers v.
       Harihar Krupa Co-Operative Housing Society Limited & Ors.

37. Constitutional courts are fully justified in giving such directions as
    they are in a unique position of perceiving the working of a statute
    while exercising judicial review, during which they could identify
    the fault-lines in the implementation of a statute. This extraordinary
    capacity to assess the working of a statute is available to the
    judicial institution because of its unique position where, i) disputes,
    based on the statutory provisions unfold before it, ii) claims of rights
    or allegations of dereliction of duties are raised with varied, and
    sometimes, contradictory interpretations of the same text of the
    statute, iii) submissions of lawyers opens up a debate and as officers
    of the Court experienced lawyers would lay bare the fault-lines in
    the statutory scheme, iv) many a times court silently witnesses the
    play of statutory power relegating the deserving to the backseat,
    and the undeserving taking away all the benefits.
38. Laws that are made by Parliament or the legislative assemblies
    create rights, entitlements, duties or liabilities. Application of such
    empowerments or disabilities gives rise to competing claims or
    conflicting interests. For resolution of these disputes, constitutional
    courts provide public law remedies19 where claims and contestations
    are decided by High Courts on a case by case basis. Judicial review
    is generally episodic, and is intended to resolve the lis on a case-
    to-case basis. Though cases are decided on their own merit and
    the lis disposed of, what is left behind is the institutional memory
    of the Court about the working of the statute and its interpretation
    preserved as precedents. Over a period of time, a critical mass of
    adjudicatory determinations on the working of the statute is built.
    This critical mass, coupled with the experiences gained by the
    Judges and the Court on the working of the statute, is of immense
    value for auditing the working of the legislation. It enables the
    court to assess whether the purpose and object of the Act is being
    achieved or not.



19   Judicial control of administrative action in our country, the effective and the most prolific, has evolved
     from its classical scrutiny of ultra vires exercise of power, to a whole set of procedural and substantive
     principles, such as: legality, procedural propriety, reasonableness, legitimate expectation, proportionality,
     transparency, legal certainty, accountability, level playing field, consultation or participation etc. These
     principles are now well entrenched in our judicial review processes and are part of our administrative law.
     In fact, bulk of judicial review proceedings initiate before the High Courts examine if the power exercised
     is with its bounds.
1474                                                         [2024] 7 S.C.R.

                      Digital Supreme Court Reports


39. The traditional perception of the constitutional role of writ courts
    was confined to judicial review of executive and legislative action.
    In that role, the courts were to decide the vires of the legislative
    and executive actions based on constitutional parameters. Not only
    have the tools of judicial review been reinvented (the rise of the
    proportionality and arbitrariness doctrines) but also the breadth of the
    judicial power has substantially expanded to areas that were hitherto
    forbidden (review of policy decisions, constitutional amendments and
    continuing mandamus being prime examples). However, even this
    expansive reading of judicial review does not capture the essence
    of the judicial branch in its entirety.
40. There is yet another role which the judiciary can and ought to
    perform- that of facilitator of access to justice and effective functioning
    of constitutional bodies. In this role, the judiciary does not review
    executive and legislative actions, but only nudges and provides
    impetus to systemic reforms. The statute in question is one which
    was intended to benefit the marginalised and the impoverished. It
    is not easy for the intended beneficiaries of this legislation to carry
    their voice to legislative branch for effective reform. The exercise
    that this Court intends to direct presently is aimed at facilitating their
    access to legislative and executive reform, which this court believes
    is an essential component of constitutional justice. That all justice
    is to be achieved only through courtroom debates is too myopic an
    understanding of constitutional justice. The facilitative role is not
    just inspired from the institutional role that the judiciary perceives
    for itself, but is also a directive of many of the fundamental rights
    in Part III and the cherished preambular vision of justice- social,
    economic and political.
41. A peculiar feature of how our legislative system works is that an
    overwhelming majority of legislations are introduced and carried
    through by the Government, with very few private member bills being
    introduced and debated. In such circumstances, the judicial role does
    encompass, in this court’s understanding, the power, nay the duty
    to direct the executive branch to review the working of statutes and
    audit the statutory impact. It is not possible to exhaustively enlist
    the circumstances and standards that will trigger such a judicial
    direction. One can only state that this direction must be predicated
    on a finding that the statute has through demonstrable judicial data
    or other cogent material failed to ameliorate the conditions of the
[2024] 7 S.C.R.                                                         1475

                         Yash Developers v.
      Harihar Krupa Co-Operative Housing Society Limited & Ors.

     beneficiaries. The courts will also do well, to arrive the very least, at
     a prima facie finding that much statutory schemes and procedures
     are gridlocked in bureaucratic or judicial quagmires that impede or
     delay statutory objectives. This facilitative role the judiciary compels
     audit of the legislation, promote debate and discussion but does not
     and cannot compel legislative reforms.
42. In light of the foregoing, considering that the Act is a state-legislation,
    implementation of which lies with the State of Maharashtra, and
    till date no comprehensive statutory audit has been undertaken,
    we request the Ld. Chief Justice of the Bombay High Court to
    constitute a bench to initiate suo motu proceedings for reviewing
    the working of the statute to identify the cause of the problems
    indicated in Paragraph 34. The concerned bench will hear the
    government, the statutory authorities, the necessary stakeholders
    including intended beneficiaries and perhaps take the assistance of
    some senior members of the bar specialising in this area as amici
    curae. We leave it to the High Court to devise such methods as it
    deems fit and appropriate. Having examined the matter, the bench
    may consider directing the government to constitute a committee for
    performance audit of the Act. The court’s jurisdiction extends only to
    that extent, and no further. The law-making, including amendments,
    is the exclusive domain of the legislature.

     Result of the case: Civil Appeal dismissed.



     †
         Headnotes prepared by: Divya Pandey


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Section 13 of the Maharashtra Slum Areas Act"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.