Created byFuzzy Cloud

Supreme Court of India

WEST INTERNATIONAL CITY PVT LTDversusDEVASIS RUDRA

Citation
2019 INSC 395
Decided
25 March 2019
Disposal
Disposed off

Holding

A one‑sided contract clause limiting the developer’s interest liability does not preclude the buyer from claiming reasonable interest and a refund when the developer’s delay in delivering possession is unreasonable.

Summary

The appellant, a real‑estate developer, entered into a buyer's agreement with the respondent to deliver possession of a row house by 31 December 2008 with a six‑month grace period. The respondent paid Rs 39,29,280 but the developer failed to hand over possession, and the respondent filed a consumer complaint in 2011 seeking possession or, alternatively, a refund with interest and compensation. The State Consumer Disputes Redressal Commission ordered a refund with 12% interest and Rs 5 lakhs compensation, which the National Consumer Disputes Redressal Commission later reduced the compensation to Rs 2 lakhs. The Supreme Court held that the contract clause limiting the developer’s interest liability to the prevailing savings‑bank rate did not bar the buyer from claiming reasonable interest or compensation, especially given the unreasonable seven‑year delay. It affirmed the lower forums' refund orders but modified the interest rate payable by the developer to 9% per annum. The appeal was disposed of, with the Supreme Court directing the developer to pay the modified interest and confirming the refund.

Issues considered

  • Whether the buyer is entitled to a refund of the amount paid despite the contract’s clause on interest and compensation.
  • Whether the one‑sided interest clause in the buyer's agreement precludes the buyer from claiming reasonable interest or compensation.
  • Whether the developer’s delay of nearly seven years constitutes a reasonable period for awaiting possession.
  • Whether the interest rate awarded by the NCDRC (12% p.a.) should be modified.

Legislation cited

Subjects

Consumer Protection ActHousingPossessionRefundInterestCompensationDeveloper‑buyer contractOne‑sided contractDelayNCDRCSCDRC

Judgment

1070                SUPREME[2019]
                            COURT   REPORTS
                                  2 S.C.R. 1070             [2019] 2 S.C.R.


 A           KOLKATA WEST INTERNATIONAL CITY PVT LTD
                                         v.
                               DEVASIS RUDRA
                          (Civil Appeal No. 3182 of 2019)
 B                              MARCH 25, 2019
              [DR. DHANANJAYA Y CHANDRACHUD AND
                         HEMANT GUPTA, JJ.]
             Consumer Protection Act, 1986:
              Housing – Failure to deliver possession – Buyer having
 C     claimed compensation from the developer, entitled to seek refund
       amount or estopped from doing so – On facts, in terms of the buyer’s
       agreement, developer was to handover possession to the buyer by
       the stipulated date with a grace period of further six months –
       However, failure of developer to deliver the possession of houses –
 D     Complaint by the buyer seeking possession of houses and in
       alternate for refund of the amount paid to developer with 12%
       interest p.a. and compensation of Rs.20 lakhs – Order by the State
       Commission directing the developer to refund the amount with 12%
       interest p.a. and compensation of Rs 5 lakhs – However,
       compensation amount reduced to Rs. 2 lakhs by the National
 E     Commission – On appeal, held: In the buyer’s agreement, for default
       on the part of the buyer, the buyer liable to pay interest at the rate
       of 18% p.a., however, for default on the part of the developer, the
       developer liable to pay interest only at the savings bank rate
       prescribed by the SBI – Agreement being one sided, would not
 F     preclude the right and remedy available to the buyer to claim
       reasonable interest or compensation – Buyer can be expected to
       wait for possession for a reasonable period – It would be
       unreasonable to construe the contract between the parties as
       requiring the buyer to wait indefinitely for possession – Completion
       certificate was received nearly seven years after the extended date
 G     for the handing over of possession which was not at all reasonable
       – Thus, the orders passed by the forum below for refund justified –
       Rate of interest payable by the developer to the buyer modified to
       9% p.a. instead of 12% p.a. – Interest.

 H
                                       1070
    KOLKATA WEST INTERNATIONAL CITY PVT LTD v.                        1071
                 DEVASIS RUDRA

      Disposing of the appeal, the Court                              A
      HELD: 1.1 Under the Agreement clause, any delay beyond
30 June 2009 would result in the developer being required to
pay interest at the prevailing savings bank interest of the State
Bank of India. Interestingly, where the buyer is in default, the
agreement stipulates that interest at the rate of 18 per cent from    B
the date of default until the date of payment would be charged for
a period of two months, failing which the allotment would be
cancelled by deducting 5% of the entire value of the property.
The agreement was evidently one sided. The clause will not
preclude the right and remedy available to the buyer to claim
reasonable interest or, as the case may be, compensation.             C
[Para 10][1074-A-D]
       1.2 In terms of the Buyer’s agreement, the date for handing
over possession was 31 December 2008, with a grace period of
six months. Even in 2011, when the buyer filed a consumer
complaint, he was ready and willing to accept possession. It would
be manifestly unreasonable to construe the contract between the       D
parties as requiring the buyer to wait indefinitely for possession.
By 2016, nearly seven years had elapsed from the date of the
agreement. Even according to the developer, the completion
certificate was received on 29 March 2016. This was nearly seven
years after the extended date for the handing over of possession
prescribed by the agreement. A buyer can be expected to wait          E
for possession for a reasonable period. A period of seven years
is beyond what is reasonable. Hence, it would have been
manifestly unfair to non-suit the buyer merely on the basis of the
first prayer in the reliefs sought before the SCDRC. There was
in any event a prayer for refund. [Para 11][1074-E-G]
                                                                      F
     1.3 In the circumstances, the orders passed by the SCDRC
and by the NCDRC for refund of moneys were justified. Having
regard to all the facts and circumstances of the case, the order of
the NCDRC is modified by directing that the appellant would pay
interest at the rate of 9% per annum to the respondent
instead and in place of 12% as directed by the NCDRC.                 G
[Para 12, 13][1075-A]
      CIVIL APPELLATE JURISDICTION : Civil Appeal No. 3182
of 2019.
      From the Judgment and Order dated 21.11.2016 of the National
Consumer Disputes Redressal Commission, New Delhi in First Appeal     H
No. 958 of 2016.
1072                 SUPREME COURT REPORTS                    [2019] 2 S.C.R.


 A           Ravinder Narain, Siddharth Banthia, Rajat Gava, Rajan Narain,
       Advs. for the Appellant.
            Supriya Bose, Sr. Adv., Debajyoti Deb, Subhasish Bhowmick,
       Ms. Goldy Goyel, Advs. for the Respondent.
            The Judgment of the Court was delivered by
 B          DR. DHANANJAYA Y CHANDRACHUD, J.
               1. Leave granted.
              2. This appeal arises from the judgment dated 21 November 2016
       of the National Consumer Disputes Redressal Commission1.
 C          3. A Buyer’s Agreement dated 2 July 2007 was entered into
       between the appellant and the respondent.
               The respondent paid an amount of Rs 39,29,280 in 2006 in terms
       of a letter of allotment dated 20 September 2006. The agreement between
       the parties envisaged that the appellant would hand over possession of a
 D     Row House to the respondent by 31 December 2008 with a grace period
       of a further six months ending on 30 June 2009.
             4. The respondent filed a consumer complaint before the West
       Bengal State Consumer Disputes Redressal Commission2 in 2011 praying
       for possession of the Row House and in the alternative for the refund of
 E     the amount paid to the developer together with interest at 12% per annum.
       Compensation of Rs 20 lakhs was also claimed.
              5. The SCDRC allowed the complaint by directing the appellant
       to refund the moneys paid by the respondent together with interest at
       12% per annum and compensation of Rs 5 lakhs. The NCDRC has
 F     modified this order by reducing the compensation from Rs 5 lakhs to Rs
       2 lakhs.
              6. Mr. Ravinder Narain, learned counsel appearing on behalf of
       the appellant submits that the primary relief which was sought in the
       consumer complaint was for delivery of possession. According to
 G     the appellant, the completion certificate was received on 29 March
       2016, which was intimated to the respondent on 11 April 2016. Moreover,
       before the SCDRC, in its written submissions, the appellant had offered
       possession of the Row House to the respondent. It has also been stated
       that in a complaint which was filed by an association representing
       1
           ”NCDRC”
 H     2
           ”SCDRC”
   KOLKATA WEST INTERNATIONAL CITY PVT LTD v.    1073
DEVASIS RUDRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

the allottees of 161 Row houses, a settlement was arrived on 11 September     A
2018 before the NCDRC specifying the date on which possession
would be handed over together with interest at 6% per annum instead
of 4% as mentioned in the Buyers’ Agreement. It was urged that the
developer having made a substantial investment in terms of the agreement,
a direction for refund is not warranted. It has also been urged that the
                                                                              B
SCDRC in the course of its decision erroneously observed that the
developer was unable to fulfill its obligation to complete the construction
within the agreed period and it was not certain when the Row house
would be handed over. It was urged that this observation by the SCDRC
is contrary to the record since before it, a specific offer of possession
was made.                                                                     C
        7. It has been urged on behalf of the respondent by Mr.
Supriya Bose, learned senior counsel that a consumer complaint was
filed in the year 2011. At that stage, the respondent was bonafide ready
and willing to accept possession. However, nearly seven years have
elapsed after the extended date for the delivery of possession which          D
expired on 30 June 2009. In spite of this, no offer of possession was
forthcoming. Learned senior counsel submitted that the letter dated 22
March 2016 of the developer was conditional and despite the subsequent
letter dated 11 April 2016, no formal offer of possession was ever made
by the appellant. Moreover, it was urged that the interest awarded by
the NCDRC at the rate of 12% is just having regard to the economic            E
loss and hardship suffered by the respondent.
      8. While considering the rival submissions, we must at the outset
advert to the following clause which was contained in the Buyer’s
Agreement:
                                                                              F
      “Unless prevented by circumstances beyond the control of the
      company and subject to Force Majeure, KWIC shall ensure to
      complete the said unit in all respect within 31st December 2008
      only for the Cluster D. Further there will be a grace period of 6
      months (up to 30th June, 2009) from the date of completion. In
      case the possession is not transferred after expiry of the said         G
      grace period, KWIC will be liable to pay prevailing saving Bank
      interest of the State Bank of India for each month of delay on the
      money given by the allottee as compensation but no compensation
      will be paid on account of force majeure reasons.”
                                                                              H
1074                 SUPREME COURT REPORTS                      [2019] 2 S.C.R.


 A            9. It is the above clause which is pressed in aid by the developer.
       Under the aforesaid clause, any delay beyond 30 June 2009 would result
       in the developer being required to pay interest at the prevailing savings
       bank interest of the State Bank of India. Interestingly, where the buyer
       is in default, the agreement stipulates that interest at the rate of 18 per
       cent from the date of default until the date of payment would be charged
 B
       for a period of two months, failing which the allotment would be
       cancelled by deducting 5% of the entire value of the property. The
       agreement was evidently one sided. For a default on the part of the
       buyer, interest at the rate of 18% was liable to be charged. However, a
       default on the part of the developer in handing over possession would
 C     make him liable to pay interest only at the savings bank rate prescribed
       by the SBI. There is merit in the submission which has been urged by
       the buyer that the agreement was one sided. The clause which has been
       extracted in the earlier part of this order will not preclude the right and
       remedy available to the buyer to claim reasonable interest or, as the
       case may be, compensation.
 D
              10. The essential aspect of the case which is required to be analysed
       is whether the buyer was entitled to seek a refund or was estopped from
       doing so, having claimed compensation as the primary relief in the
       consumer complaint. The Buyer’s Agreement is dated 2 July 2007. In
       terms of the agreement, the date for handing over possession was 31
 E     December 2008, with a grace period of six months. Even in 2011, when
       the buyer filed a consumer complaint, he was ready and willing to
       accept possession. It would be manifestly unreasonable to construe the
       contract between the parties as requiring the buyer to wait indefinitely
       for possession. By 2016, nearly seven years had elapsed from the date
 F     of the agreement. Even according to the developer, the completion
       certificate was received on 29 March 2016. This was nearly seven
       years after the extended date for the handing over of possession
       prescribed by the agreement. A buyer can be expected to wait for
       possession for a reasonable period. A period of seven years is beyond
       what is reasonable. Hence, it would have been manifestly unfair to non-
 G     suit the buyer merely on the basis of the first prayer in the reliefs sought
       before the SCDRC. There was in any event a prayer for refund.
              11. In the circumstances, we are of the view that the orders passed
       by the SCDRC and by the NCDRC for refund of moneys were justified.

 H
   KOLKATA WEST INTERNATIONAL CITY PVT LTD v.    1075
DEVASIS RUDRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

      12. Having regard to all the facts and circumstances of the case,          A
we modify the order of the NCDRC by directing that the appellant shall
pay interest at the rate of 9% per annum to the respondent instead and
in place of 12% as directed by the NCDRC. Save and except for the
above modification, we affirm the directions of the NCDRC.
      13. The amount outstanding in terms of the directions of this              B
Court shall be released out of the moneys which have been deposited by
the appellant. The balance, if any, that remains shall be refunded to the
appellant.
      14. The appeal is, accordingly, disposed of. There shall be no
order as to costs.                                                               C
        15. Pending application(s), if any, shall stand disposed of.

Nidhi Jain                                                 Appeal disposed of.


                                                                                 D




                                                                                 E




                                                                                 F




                                                                                 G




                                                                                 H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Consumer Protection Act"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.