Created byFuzzy Cloud

Supreme Court of India

TRANSMISSION CORPN. OF A.P. LTD. & ANR.versusSAI RENEWABLE POWER PVT. LTD. & ORS.

Citation
2010 INSC 391
Decided
8 July 2010
Disposal
Disposed off

Holding

The Andhra Pradesh Electricity Regulatory Commission is vested with the statutory power to determine tariff, including the purchase price, and to impose restrictions on third‑party sales, and the Tribunal’s order is set aside.

Summary

The Supreme Court examined a dispute between the Andhra Pradesh Transmission Corporation and several non‑conventional energy developers over the purchase price of electricity and the restriction on third‑party sales imposed by the Andhra Pradesh Electricity Regulatory Commission (APERC). The developers had entered into Power Purchase Agreements (PPAs) based on an earlier APERC order of 20 June 2001, which fixed a base price of Rs 2.25 per unit with 5% annual escalation and prohibited sales to third parties. The developers later challenged the APERC’s subsequent orders that revised the tariff and maintained the sales restriction, invoking promissory estoppel, legitimate expectation, and duress. The Court held that APERC has statutory jurisdiction to determine tariffs, including the purchase price, and to impose such restrictions, and that the principles of estoppel and duress did not apply because the contracts were clear, reviewed, and not indefeasibly promised. Consequently, the Tribunal’s order was set aside and the matter remitted to APERC for fresh tariff determination and consideration of third‑party sales, with the State of Andhra Pradesh added as a party.

Issues considered

  • Whether the Andhra Pradesh Electricity Regulatory Commission has jurisdiction to fix the tariff and purchase price for non‑conventional energy generators
  • Whether the Commission can impose a restriction on sale of generated electricity to third parties
  • Correctness of the tariff fixation by the Commission
  • Whether the doctrine of promissory estoppel or legitimate expectation applies to the developers
  • Whether the developers’ contracts were entered into under duress
  • Effect of the APERC order dated 20 June 2001, which had attained finality

Legislation cited

Subjects

electricitytariff fixationregulatory commissionpromissory estoppelduressnon‑conventional energypower purchase agreementthird‑party salejurisdiction

Judgment

                         [2010] 8 S.C.R. 636


A         TRANSMISSION CORPN. OF A.P. LTD. & ANR.
                                  v.
          SAi RENEWABLE POVVER PVT. LTD. & ORS.
               (Civil Appeal No. 2926 of 2006 etc.)

                            JULY 8, 2010
B
     [DR. B.S. CHAUHAN AND SWATANTER KUMAR, JJ.]

       Electricity - Promotion of generation of grid quality power
  from non-conventional sources -- Guidelines issued by
c Central Government indicating the purchase price of such
  electricity - State Government granting uniform incentives
  to all the projects based on renewable sources of energy -
  Order reviewing the tariff and imposing restriction on sale to
  third party - Non-conventional energy developers/generators
D accepted and acted upon the order by entering into Power
  Purchase Agreements - Thereafter State Electricity
  Regulatory Commission determining the purchase price for
  procurement of such electricity and also imposing restriction
  with regard to sale thereof to third party- Propriety of the order
E of the Regulatory Commission - Held: It is within the power
  and jurisdiction of the Regulatory Commission to determine
  the 'purchase price' and to impose restriction on sale to third
  party - The Commission was not estopped from altering the
  purchase rates or imposing restriction on the sale - The
  incentives initially provided by the authorities under the
F
  guidelines issued by the Central Government and the Power
  Purchase Agreements were not for indefinite period, but were
  subject to review - The contracts entered into by the parties
  provided for review and the restriction for sale to third party -
  Parties are bound by contractual obligation and such
G obligation cannot be frustrated by aid of promissory estoppel
  - Agreements cannot be said to be result of duress - Duress
  not proved, so as to render the contract voidable - Conditions
  of a contract cannot be altered/avoided on presumptions or

H                                636
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 637
               POWER PVT. LTD.

assumptions - Determination of tariff is a function assigned      A
legislatively to Regulatory Commission - Supreme Court in
exercise of powers under Article 136 of the Constitution would
not sit as an appellate authority over the formation of opinion
and determination of tariff by the specialized bodies - Matters
remanded to the Regulatory Commission to fix/determine the        B
tariff for purchase of electricity - Electricity Regulatory
Commission Act, 1998 - s. 17 - Andhra Pradesh Electricity
Reform Act, 1998 - s. 11 - Electricity Act, 2003 - ss. 61 and
62 r/w. s. 86(1)(a) and (b) - Contract - Promissory Estoppel
- Constitution of India, 1950 - Article 136.                      c
    Administrative Law:

     Principle of promissory estoppel -          Nature and
applicability of - Discussed.
                                                                  D
    Principle of legitimate expectation - Applicability of

    Judicial Review - Scope of, in policy matters.

     Maxim - 'Al/egans contraria non est audiendus' -
Applicability of.                                                 E

   Words and Phrases - 'Tariff' and 'Purchase price' -
Meaning of

     Ministry of Non-Conventional Energy Sources of
Central Government wrote letter dated 7.9.1993 to                 F
different States informing that under new strategy and
action plan of the Ministry, special emphasis would be
given to generation of grici quality power from non-
conventional sources. Guidelines drawn up by the
Ministry were also enclosed with the letter, whereby a            G
minimum buy back price of Rs. 2.25 per unit was
proposed. The transmission of electricity was required to
be undertaken by State Electricity Board.

     In furtherance of the decision of the Central                H
    638    SUPREME COURT REPORTS              (2010] 8 S.C.R.


A Government and the Guidelines, State of Andhra Pradesh
  issued two different Government Orders dated 18.11.1997
  and 22.11.1998 granting uniform incentives to all the
  projects based on renewable sources of energy. The
  Power Purchase Agreement (PPA) between the appellant-
s Corporation (APTRANSCO) and non-conventional power
  project developers were executed. The A.P. Regulatory
  Commission passed an order on 20.6.2001 determining
  the tariff as well as defining other rights and obligations
  between the parties including that the generators of
c electricity were not permitted to make sale in favour of
  third party. After passing of this order, developers
  entered into PPAs and confirmed the acceptance and
  implementation of the order dated 20.6.2001. The PPAs
  as well as the order dated 20.6.2001 specifically provided
  for review/revision of purchase price. The order dated
0
  20.6.2001 was never challenged.

      Thereafter, pursuant to suo motu proceedings,
  Andhra Pradesh Electricity Regulatory Commission
  (which was constituted under Andhra Pradesh Electricity
E Reform Act, 1998) by its order dated 20.3.2004 fixed the
  energy purchase rates at base unit price of Rs. 2.25 as
  on 1.4.1994 and the escalation index of 5% p.a .. Thus, the
  base price as on 1.4.2004 was 3.37 per kwh. The tariff was
  frozen for five years. The Regulatory Commission also
F restricted the sale, procurement and distribution of
  electricity by the developers to any other party except
  APTRANSCO. This order was further clarified by order
  dated 7.7.2004. The developers filed appeals against both
  the orders. The Appellate Tribunal for Electricity held that
G there was some element of duress in execution of the
  PPAs; that the PPA being a statutory document, the
  Regulatory Commission had no authority to interfere with
  the same; that the Regulatory Commission had neither
  the power nor the jurisdiction to compel the developers
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 639
               POWER PVT. LTD.

to sell the power generated by them to APTRANSCO and/          A
or DISCOM.

    The instant appeals were filed against the orders of
the appellate tribunal. The questions, broadly, for
consideration before the Supreme Court pertained to the
                                                               8
issues as under:

     (i)     Jurisdiction of the Regulatory Commission for
             fixation of tariff and sale of generated
             electricity to third party;
                                                               c
     (ii)    Correctness of tariff fixation;

     (iii)   Applicability of principle of estoppel and the
             extent of its applicability;

     (iv)    Applicability of plea of duress;                  D

     (v)     Effect of order dated 20.6.2001 in view of its
             having attained finality and for the same not
             being questioned in the instant proceedings.

    Disposing of the appeals and remanding the matters         E
to Andhra Pradesh Electricity Regulatory Commission,
the Court

      HELD: 1.1. The Andhra Pradesh Electricity
Regulatory Commission has the jurisdiction to determine        F
tariff which takes within its ambit the 'purchase price' for
procurement of the electricity generated by the non-
conventional energy developers/ generators, in the facts
and circumstances of the instant cases. (Para 52] [717-
8]                                                             G
    1.2. The Tribunal was not correct in holding that since
no independent notification was issued u/s. 17 of the
Regulatory Commission Act, 1998, therefore, the A.P.
Electricity Regulatory Commission could not exercise the
                                                               H
    640    SUPREME COURT REPORTS               [2010] 8 S.C.R.


A   powers vested in the Regulatory Commission under that
    Act. The Regulatory Commission was constituted under
    the Andhra Pradesh Electricity Reform Act, 1998 and an
    appropriate notification in that behalf was issued. The
    Electricity Regulatory Commission Act, 1998 stood
B   repealed by the Electricity Act, 2003. The Electricity Act,
    2003 specifically recognized and accepted the
    Commissions constituted under the enactments specified
    in the Schedule to the Act as appropriate Commission.
    In entry 3 of the said Schedule, Reform Act, 1998 has
c   been specifically noticed. Thus, the Regulatory
    Commission constituted under the Reform Act, 1998
    became the appropriate Ccmmission under the Electricity
    Act, 2003 as well. [Para 3] [665-F-H; 666-A-B]

       1.3. Fixation of tariff is, primarily, a function to be
D performed by the statutory authority in furtherance to the
  provisions of the relevant laws.      Fixation of tariff is a
  statutory function as specified under thQ provisions of
  the Reform Act, 1998, Electricity Regulatory Commissions
  Act, 1998 and the Electricity Act, 2003. These functions
E are required to be performed by the expert bodies as to
  whom the job is assigned under the law. The Regulatory
  Commission constituted by the notification dated
  3.4.1999 would be the appropriate Commission under the
  Reform Act, 1998, Electricity Regulatory Commissions
F Act, 1998 and the Electricity Act, 2003 and is required to
  perform the functions as contemplated u/ss. 11, 17 and
  82 of the respective Acts. The functions assigned to the
  Regulatory Commission are wide enough to specifically
  impose an obligation on the Regulatory Commission to
G determine the tariff. [Para 17] [678-F-H; 679-A-F]

        1.4. The Regulatory Commission is vested with very
    vast powers and functions. Section 11 of the Reform Act,
    1998 declares fixation of tariff as one of the primary
    functions of the Regulatory Commission in general more
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 641
               POWER PVT. LTD.

particularly, to the specified consumers u/s. 26 of the A
Reform Act, 1998. While under the Electricity Act, 2003,
Sections 61 and 62 r/w Section 86(1)(a) and (b) deal with
fixation of tariffs in relation to production, distribution and
sale of generated power to the end consumer. These
provisions clearly demonstrate that the Regulatory B
Commission is vested with the function for determining
the tariff for generation, supply, transmission and billing
of electricity etc., as well as regulation of electricity
purchase and procurement process of distribution
licensees, including price at which electricity shall be     c
procured from the generating companies. With these
specific powers in the statute book itself, it cannot be said
that procurement of power from the generating
companies will not fall within the ambit of powers and
functions of the Regulatory Commission. It is a common D
body performing functions, duties and exercising powers
under all these three Acts. [Para 30] [694-F-H; 695-A]

   PTC India Ltd. v. Central Electricity Regulatory
Commission (201 O) 4 sec 603, relied on.
                                                             E
     Tata Power Company Ltd. v. Reliance Energy Ltd. 2009
(7) SCALE 513, referred to.                             '

    1.5. All the Power Purchase Agreements (PPAs)
entered into by the generating companies with the F
appropriate body, as well as the orders issued by the
State in GO Ms. Nos. 93 and 112, in turn, had provided
for review of tariff and the conditions. The Tribunal
appears to have fallen in error of law in coming to the
conclusion that the Regulatory Commission had no
powers either in law or otherwise of reviewing the tariff G
and so called incentives. From various provisions and
the documents on record it is clear that the Regulatory
Commission is vested with the power to revise tariff and
conditions in relation to procurement of power from
generating companies. It is also clear from the record that H
    642     SUPREME COURT REPORTS              [2010] 8 S.C.R.


A   in terms of the contract between the parties, the
    APTRANSCO had reserved the right to revise tariff etc.
    with the approval of the Regulatory Commission. [Para
    33) [698-D-G]

       1.6. The Tribunal has taken a narrower view of the
8
  jurisdiction vested in the Regulatory Commission which
  is discharging its statutory functions under all the three
  Acts in accordance with law. The power available to the
  Government to issue policy directions has two
C restrictions. Firstly, the policy direction has to be on the
  matters related to electricity in the State including overall
  planning and coordination. Secondly, all such policy
  directions have to be issued by the State Government in
  consonance with the object sought to be achieved by this
  Act and accordingly shall not adversely affect or interfere
D with the functions and powers of the Regulatory
  Commission including, but not limited to, determination
  of the structure of tariff for supply of electricity to the
  consumers.        Powers vested in the Regulatory
  Commission to frame regulations under Section 54 also
E intend that regulations are to be framed with an object to
  ensure proper performance of its functions under the Act.
  Both the State and the Regulatory Commission are
  supposed to exercise their respective powers only for the
  purposes of furthering the cause of the Reform Act. The
F Commission discharging its statutory functions within
  the ambit of Sections 11, 12 and 26 of the Reform Act,
  1998 as well as Sections 61, 62 and 86(1 )(b) of the
  Electricity Act, 2003 renders advisory functions to the
  State. [Para 46] [711-G-H; 712-A-D]
G
        1.7. It is not correct to say that the Regulatory
    Commission acted in contradiction or conflict with the
    State policy. The State was certainly not intending to
    provide incentives and concessions with assurance of
    buy-back to enable the Non-Conventional Energy
H   developers/generators to sell generated powers to third
TRANSMISSION CORPN. OF AP. LTD v. SAi RENEWABLE 643
               POWER PVT. LTD.

parties. It must be kept in mind that the policy of the A
Government of India as well as the State of Andhra
Pradesh was for encouraging the developers/generators
of Non-conventional Energy to generate electricity for the
benefit of public at large with buy back of power being
one of the basic features of this policy. Such parameters B
are subject to change in larger public interest. All these
issues, in fact, loose much significance because of the
fact that parties have, by and large, entered into the field
of contract simpliciter and their rights are controlled by
the contracts executed between them. There is no c
challenge to ,these contracts and, therefore, it may be
hardly permissible for the Court to go behind these
contracts and permit questioning of the statutory
jurisdiction vested in the Regulatory Commission. [Para
46] [712-F-H; 713-A-B]                                       D

    1.8. After creation of the Regulatory Commissions
under the provisions of the Electricity Regulatory
Commission Act, 1998, the Commission has clear power
and jurisdiction to fix tariff. The Court should not adopt
an interpretation which should neither be strict nor         E
narrower so as to oust the jurisdiction of the Regulatory
Commission, as it would defeat the very object of
enacting the said Act. [Para 47] [713-C-D]

     1.9. The basic policy of both the Central as well as F
the State Government was to encourage private sector
participation in generation, transmission and distribution
of electricity on the one hand and to further the objective
of distancing the regulatory responsibilities of the
Regulatory Commission from the Government and of G
harmonizing and rationalizing the provisions of the
existing laws relating to electricity in India, on the other
hand. The object and reasons of Electricity Act, 2003 as
well as the Reform Act, 1998 are definite indicators of
such legislative intent. The objects and reasons clearly H
    644    SUPREME COURT REPORTS               [2010] 8 S.C.R.


A   postulated the need for introduction of private sector into
    the field of generation and distribution of energy in the
    State. Efficiency in performance and economic utilization
    of resources to ensure satisfactory supply to the public
    at large is the paramount concern of the State as well as
B   the Regulatory Commission. The policy decisions of
    these constituents are to be in conformity with the object
    of the Act. Thus, it is necessary that the Regulatory
    Commission, in view of this object, take practical
    decisions which would heli- in ensuring existence of
c   these units rather than their extinguishment as alleged.
    [Para 51] [716-A-G]

       1.10. The restriction with regard to third party sales
  was not only creation of a directive issued or approval
  granted by the Regulatory Commission, but was actually
D in furtherance of the contract entered into between the
  parties. Rights and liabilities arising from a binding
  contract cannot be escaped on the basis of some
  presumptions or inferences in relation to the facts leading
  to the execution of the contract between the parties. The
E jurisdiction of the Regulatory Commission, in the facts of
  the case, arises not only from the statutory provisions
  under the different Acts but also in terms of the contract
  executed between the parties which has binding force.
  [Para 49] [714-G-H; 715-A-B]
F
       1.11. However, the grievance of the respondents that
  enforcement of the purchase price at the rate determined
  by the Regulatory Commission along with complete
  prohibition on the right of the Non-conventional Energy
G Generator/Developers to sell generated power to the third
  parties would compel them to shut down their projects,
  is a matter of concern, even for the State Government. All
  these projects, admittedly, were established in
  furtherance of the scheme and the guidelines provided
H by the Central Government which, in turn, were adopted
TRANSMISSION CORPN. OF AP. LTD v. SAi RENEWABLE 645
               POWER PVT. LTD.
with some modification by the State Government. The A
State Electricity Board implemented the said scheme and
initially had permitted sale of generated electricity to third
parties, however, subsequently and after formation of the
Regulatory Commission which, in turn, took over the
functions of the State Electricity Board, the incentives B
were modified and certain restrictions were placed. The
reasons for these restrictions have been stated in the
affidavit filed on behalf of the appellants which is not a
matter to be examined by this Court in exercise of its
extra-ordinary jurisdiction. These matters, essentially, c
must be examined by expert ~odies particularly, when
such bodies are constituted ~nder the provisions of a
special statute. [Paras 49 and 50] [715-B-C-E-H]

     2.1. It is not correct to say that the developers have
legitimate right to expect that the incentives as provided     D
to them in furtherance of the letters and orders of the
Central as well as the State Government were to be
continued indefinitely and the authorities concerned
were estopped from altering the rates and I or imposing
the condition of no sale to third parties. For the principle   E
of estoppel to be attracted, there has to be a definite and
unambiguous representation to a party which then
should act thereupon and then alone the consequences
in law can follow. The Tribunal has erred in law in
treating the inter-se letters and guidelines between the       F
Government of India, State Government and the
Commission/the State Electricity Board as unequivocal
commitments to the respondent/purchasers/generators/
developers so as to bind the State for all times to come.
In the instant cases, the policy guidelines issued by the      G
Central Government were the proposals sent to the State
Government, which the State Government accepted to
consider, amend or alter as per their        ' needs and
conditions and then make efforts to achieve the objects
of encouraging non-conventional energy generators and          H
    646     SUPREME COURT REPORTS               [2010) 8 S.C.R.


A   purchasers to enter into this field. These are the matters,
    which will squarely fall within the competence of the
    Regulatory Commission/the State Electricity Board at the
    relevant points of time. Besides that, there was no definite
    and clear promi5-~ made by the authorities to the
s   developers that would invoke t\e principle of promissory
    estoppel:"Undoubtedly,
                ,          . to encourage participation in the
    field of generation of energy through non-conventional
    methods, some incentives were provided but these
    incentives ,u_nder the guidelines as well as under the
c   PPAs signed between the parties from time to time were
    subject to review. In any case, the matter was completely
    put at rest by the order of 20th June, 2001 and the PPAs
    voluntarily signed by the parties at that time, which had
    also provided such stipulations. If such stipulations were
    not acceptable to the parties they ought to have raised
0
    objections at that time or at least within a reasonable time
    thereafter. The agreements have not only been signed
    by the parties but they have been fully acted upon for a
    substantial period. [Para 36] [702-F-H; 703-A-F]

E       2.2. The principle of promissory estoppel, even if, it
    was applicable as such, the Government can still show
    that equity lies in favour of the Government and can
    discharge the heavy burden placed on it. In such
    circumstances, the principle of promissory estoppel
F   would not be enforced against the Government as it is
    primarily a principle of equity. [Para 37] [703-H; 704-A-B]

      2.3. It is a settled canon of law that doctrine of
  promissory estoppel is not really based on principle of
G estoppel but is a doctrine evolved by equity in order to
  prevent injustice. There is no reason why it should be
  given only a limited application by way of defence. It can
  also be the basis of a cause of action. Once the
  ingredients of promissory estoppel are satisfied then it
  could be enforced against the authorities including the
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 647
               POWER PVT. LTD.

State with very few extra ordinary exceptions to such      A
enforcement. [Para 37] [704-A-B]

    2.4. Even if it is assumed that there was a kind of
unequivocal promise or representation to the
respondents, the reviews have taken place only after the
                                                            8
period specified under the guidelines and/or in the PPAs
was over. This is a matter which, primarily, falls in the
rea!m of contract and the parties would be governed by
the agreements that they have signed. Once these
agreements are signed and are enforceable in law then
the contractual obligations cannot be frustrated by the aid C
of promissory estoppel. [Para 37] [704-D-F]

     2.5. If the Promise is made in regard to a present or
existing facts, the principle of estoppel can be enforced
against the Government. But a promise in relation to a D
future transaction or act may not fall within the ambit of
promissory estoppel. [Para 38] [705-G]

     Union of India v. Mis. Inda-Afghan Agencies Ltd. (1968)
2 SCR 366; Century Spinning and Manufacturing Company
Ltd. v. The Ulhasnagar Municipal Council (1970) 1 SCC 582; E
Motilal Padampat Sugar Mills. Co. Ltd. v. State of Uttar
Pradesh (1979) 2 SCC 409, relied on.

     2.6. In our country, the law of promissory estoppel
has attained certainty . It is only an unambiguous and F
definite promise, which is otherwise enforceable in law
upon which, the parties have acted, comes within the
ambit and scope of enforcement of this principle and
binding on the parties for their promise and
representation. In the instant case, the guidelines cannot G
take the colour of a definite promise which in the letters
of the Central Government itself was proposals to the
State Government. Besides that, even if the State letters/
circulars are treated as promise or representations to the
private parties like the respondents even then, they lead H
    648    SUPREME COURT REPORTS              [2010] 8 S.C.R.

A to the execution of a definite contract between the parties
  which will purely fall io the domain of contractual law.
  These contracts specifically provided for review and
  when reviewed in the year 2001 parties not only accepted
  the order but executed contracts (PPAs) in furtherance
B of it. In these circumstances, it is not correct to say that
  the State or the Regulatory Commission or erstwhile
  State Electricity Board were bound to allow same tariff
  and permit third party sales for an indefinite period. To
  this extent, authorities, in any case, would not be bound
C by the principle of estoppel. [Para 41] [707-F-H; 708-A-B]

      2.7. Besides, the State of Andhra Pradesh was neither
  impleaded as a party to the proceedings before the
  Regulatory Commission nor before the Tribunal. In fact,
  the Tribunal has referred to various acts and deeds of the
D State and consequences thereof, but did not consider it
  appropriate to implead the State Government as a party
  to the proceedings. The presence of the State
  Government before the Tribunal could have certainly
  been appropriate, inasmuch as the State would have
E placed before the Appellate Authority and the Regulatory
  authorities, its views in regard to revision of incentives
  as well as the purchase price. The State of Andhra
  Pradesh was a necessary, in any case, a proper party in
  these proceedings. [Para 48] [714-C-F]
F
      BSES Ltd. v. Tata Power Co. Ltd. (2004) 1 SCC 195;
  Andhra Pradesh Electricity Regulatory Commission v. R. V.K.
  Energy Private Limited (2008) 17 SCC 769, relied on.

      3.1. To frustrate a contract on the ground of duress
G or coercion, there has to be definite pleadings which
  have to be substantiated normally by leading cogent and
  proper evidence. However, in the case where summary
  procedure is adopted like in the instant case, at least
  some documentary evidence or affidavit ought to have
H been filed raising this plea of duress specifically. Nothing
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 649
               POWER PVT. LTD.

was brought to the notice of the Court to state the plea      A
of duress and to prove the alleged facts which
constituted duress, so as to vitiate and/or even partially
reduce, the effect of the PPAs. On the one hand, the
Tribunal appears to have doubted the binding nature of
the contracts stating that it contained unilateral            B
conditions introduced by virtue of Order and approval of
the Regulatory Commission, while on the other hand, it
proceeded on the presumption that PPAs are final and
binding and still drew the conclusion that the Regulatory
Commission could not revise the tariff. Even in the order,    c
no facts have been pointed out which, in the opinion of
the Tribunal, constituted duress within the meaning of the
Contract Act so as to render the contract voidable. In the
instant case, it is significant to note that the PPAs were
executed prior and subsequent to the issuance of the          0
order dated 20th June, 2001. Different persons executed
the contracts at different times in full awareness of the
terms and conditions of such PPA. Therefore, the Tribunal
was not right in recording the findings that the PPAs
executed by the parties, were result of some duress and,
                                                              E
thus, it will not vest the authorities with the power to
review the tariff and other granted incentives. [Para 42]
[708-C-H]

    3.2. Besides, none of the generators had challenged
the agreements and, in fact, except in arguments before       F
the Tribunal no case was made out for the purposes of
vitality of the contract or any part thereof. On the
contrary, all the generators under all the branches of non-
conventional energies, have accepted the contract and
proceeded on the basis that the said contracts are            G
binding and still the Regulatory Commission does not
have any power or jurisdiction to revise the tariff or deal
with the concessions. Even otherwise, firstly, there are
no facts on record, much less, supported by any
documentary or any other evidence to sustain the plea         H
    650      SUPREME COURT REPORTS               (2010] 8 S.C.R.


A that the contracts (PPAs) are a result of undue influence
  or duress by the State or its agencies upon the
  generators. Secondly, the generators have already taken
  benefit of that contract which was based on the policy
  of the State as well as the order of the Regulatory
B Commission. Having attained those benefits, it will
  hardly be of any help to the generators particularly, in the
  facts and circumstances of the case, to substantiate,
  justify or argue the plea of duress. [Para 42] [709-A-G]

C         Bir/a Jute Manufacturing Co. v. State of M.P. (2002) 9
    sec 667, relied on.
       3.3. The finding of the Tribunal that "out of
  compulsion some of the developers entered into Power
  Purchase Agreement with APTRANSCO accepting the
D terms and conditions set out in order dated 20th June,
  2001" is not substantiated by any material on record.
  What was the compulsion and what were the facts which
  persuaded the Tribunal to take such a view are
  conspicuous by their very absence. A compulsion
E leading to execution of a contract is a matter entirely
  based upon facts. It is difficult for this Court, originally,
  to infer duress or compulsion in absence of specific
  pleadings and materials in that behalf. [Para 44] [710-D-
  F]
F
       4. In the instant case, the order dated 20th June, 2001
  was fully accepted by the parties without any reservation.
  After the lapse of more than reasonable time of their own
  accord they voluntarily signed the PPA which contained
  a specific stipulation prohibiting sale of generated power
G by them to third parties. The agreement also had renewal
  clause empowering TRANSCO/APTRANSCO/ Board to
  revise the tariff. Thus, the documents executed by these
  parties and their conduct of acting upon such
  agreements over a long period, bind them to the rights
H and obligations stated in the contract. The parties can
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 651
               POWER PVT. LTD.
hardly deny the facts as they existed at the relevant time,   A
just because it may not be convenient now to adhere to
those terms. Conditions of a contract cannot be altered/
avoided on presumptions or assumptions or the parties
having a second thought that a term of contract may not
be beneficial to them at a subsequent stage. They would       B
have to abide by the existing facts, correctness of which,
they can hardly deny. Such conduct, would be hit by
allegans contraria non est audiendus. [Para 39] [705-F-H;
706-A-B]

    Kusumam Hotels (P) Ltd. v. Kera/a Seb (2008) 13 SCC       C
213, relied on.

    Pawan Alloys v. UPSEB (1997) 7 SCC 251, referred to.

     5.1. The expression 'tariff' as explained in the Law     D
Lexicon* is a "determinatiorl,, ascertainment, a table of
rates of export and import duties, in which sense the word
has been adopted in English and other European
languages and as defined by the law dictionaries the
word 'tariff' is a cartel of commerce; a book of rates; a     E
table or catalogue, drawn usually in alphabetical order,
containing the names of several kind of merchandise,
with the duties or customs to b~ paid for the same as
settled by the authcyity or agreeti between the several
princes and States that hold com"1erce together." It has
also been explained as a scheduil:!, system, or scheme        F
of duties imposed by the Government of a country upon
goods imported or exported; published volume of rate
schedules and general terms and conditions under which
a product or service will be supplied; a document
approved by the responsible regulatory agency listing the     G
terms and conditions including a schedule of prices,
under which utility services will be provided. [ Paras 28
and 29] [693-F-H; 694-A-C]

     *Law Lexicon with legal Maxims, L[atin terms and Words   H
   652     SUPREME COURT REPORTS               [2010] 8 S.C.R.

A and Phrases (Second Edition 1997) - referred to.

        5.2. The expression 'purchase price' has to be given
  its limited meaning, i.e. the price paid for purchasing a
  good and in the context of the instant case, price at which
  generated electricity will be sold to the specified
8
  agencies. The term 'purchase price' indicated in the
  PPAs, as such, would be a matter within the realm of
  contract but this is subject to the changes which are
  contractually and/or even statutorily permissible.
  Purchase price ultimately would form part of the tariff, as
C tariff relatable to a licensee or a consumer would have
  essentially taken into account, the purchase price. The
  purchase price may not include tariff but tariff would
  always or is expected to include purchase price. [Para 29]
  (694-B-D]
D
        6. The order dated 20th June, 2001 passed by the
  Andhra Pradesh Electricity Regulatory Commission has
  attained finality and was not challenged in any
  proceedings so far. This judgment shall not, therefore,
E be in detriment to that order which will operate
  independently and in accordance with law. [Para 52] [717-
  H; 718-A-B]

       7.1 The specialized performance of functions that are
  assigned to Regulatory Commission can hardly be
F assumed by any other authority and particularly, the
  courts in exercise of their judicial discretion. The Tribunal
  constituted under the provisions of the Electricity Act,
  2003, again being a specialized body, is expected to
  examine such issues, but this Court in exercise of its
G powers under Article 136 of the Constitution would not
  sit as an appellate authority over the formation of opinion
  and determination of tariff by the specialized bodies. This
  question is itself open to be considered by the
  appropriate authority at the appropriate stage.
H Determination of tariff is a function assigned legislatively
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 653
               POWER PVT. LTD.

to a competent forum/authority. Whether it is by exercise         A
of legislative or subordinate legislative power or a policy
decision, if the Act so requires, but it generally falls in the
domain of legislative activity and the courts refrain from
adverting into this arena. It would be termed as illegal if
statutorily prescribed procedure is not followed or it is so      B
perverse and arbitrary that it hurts the judicial conscience
of the court making it necessary for the court to
intervene. Even in the instant case the scope of
jurisdiction is a very limited one. [Para 17, 18] [679-F-H;
680-A-B; D-E]                                                     C

     Association of Industrial Electricity Users v. State of
Andhra Pradesh (2002) 3 SCC 711; West Bengal Electricity
Regulatory Commission v. CESC Ltd. (2002) 8 SCC 715,
relied on.
                                                                  D
     7.2. The matters are remanded to the Andhra Pradesh
Electricity Regulatory Commission with a direction that
it shall hear the Non-conventional energy generators
afresh and fix/ determine the tariff for purchase of
electricity in accordance with law, expeditiously. It shall       E
also re-examine that in addition to the above or in the
alternative, whether it would be in the larger interest of
the public and the State, to permit sale of generated
electricity to third parties, if otherwise feasible. The
Andhra Pradesh Electricity Regulatory Commission shall            F
consider and pronounce upon all the objections that may
be raised by the parties appearing before it, except
objections in relation to its jurisdiction, plea of estoppel
and legitimate expectancy against the State and/or
APTRANSCO and the plea in regard to PPAs being result             G
of duress as these issues stand concluded by this
judgment. It is directed that State of Andhra Pradesh shall
be added as a party respondent in the proceedings and
the Andhra Pradesh Electricity Regulatory Commission
shall grant hearing to the State during pendency of
proceeding before it. [Para 52] [717-C-H; 718-A-C]                H
    654      SUPREME COURT REPORTS                  [2010] 8 S.C.R.


A                         Case Law Reference:

          (2002) 3 sec 111         Relied on.             Para 18

          (2002) 8 sec 115         Relied on.             Para 19
          (2010) 4 sec so3         Relied on.             Para 30
B
          2009 (7) SCALE 513       Referred to.           Para 31

          (1968) 2 SCR 366         Relied on.             Para 38

          (1970) 1 sec 582         Relied on.             Para 38
c
          (1979) 2 sec 409         Relied on.             Para 38

          (1997) 1 sec 251         Referred to.           Para 38

          (2008) 13 sec 213        Relied on.             Para 40
D         (2002) 9 sec 667         Relied on.             Para 43

          (2004) 1 sec 195         Relied on.             Para 47

          (2008) 11 sec 769        Relied on.             Para 47

E       CIVIL APPELLATE JURISDICTION : Civil Appeal No.
    2926 of 2006.

         From the Judgment and Order dated 02.06.2006 of the
    Appellate Tribunal for Electricity, New Delhi in Appeals No. 1,
    2, 5, 6, 7, 8, 9, 10, 12, 15, 16, 17, 18, 19, 20, 21, 22, 34, 47,
F
    52, 58, 67 and 80 of 2005.

                                    With

          C.A. No. 5940/2006
G         C.A. No. 5941/2006

          C.A. No. 5942/2006

          C.A. No. 5943/2006

H         C.A. No. 5944/2006
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 655
               POWER PVT LTD.

    C.A. No. 5945/2006                                 A
    C.A. No. 5946/2006

    C.A. No. 5947/2006

    C.A. No. 5948/2006
                                                       B
    C.A. No. 5949/2006

    C.A. No. 5950/2006

    C.A. No. 5951/2006
                                                       c
    C.A. No. 5952/2006

    C.A. No. 5953/2006

    C.A. No. 5954/2006

    C.A. No. 5955/2006                                 D

    C.A. No. 5956/2006
    C.A. No. 5957/2006

    C.A. No. 5958/2006                                 E
    C.A. No. 5959/2006

    C.A. No. 5960/2006

    C.A. No. 5961/2006
                                                       F
    C.A. No. 3091/2006

    C.A. No. 5962/2006

    C.A. No. 5963/2006
                                                       G
    C.A. No. 5964/2006
    C.A. No. 3884/2006
    C.A. No. 5966/2006
                                                       H
    656      SUPREME COURT REPORTS   (2010] 8 S.C.R.


A         C.A. No. 5967/2006

          C.A. No. 5968/2006

          C.A. No. 5969/2006

          C.A. No. 5970/2006
8
          C.A. No. 5971/2006

          C.A. No. 5972/2006

          C.A. No. 5973/2006
c         C.A. No. 5974/2006

          C.A. No. 5975/2006

          C.A. No. 5976/2006
D         C.A. No. 5977/2006

          C.A. No. 5978/2006

          C.A. No. 5979/2006

E         C.A. No. 5980/2006

          C.A. No. 5981/2006

          C.A. No. 5982/2006

          C.A. No. 5983/2006
F
          C.A. No. 5984/2006

          C.A. No. 5985/2006

          C.A. No .. 5986/2006
G
          C.A. No. 5987/2006

          C.A. No. 3910/2006

          C.A. No. 5988/2006

H
TRANSMISSION CORPN. OF AP. LTD v. SAi RENEWABLE 657
               POWER PVT. LTD.

    C.A. No. 5989/2006                                           A
    C.A. No. 5990/2006

    C.A. No. 5991/2006

    C.A. No. 4106/2009                                           B
     Gopal Subramanium S.G., L.N. Rao, Challa Kodandaram,
Raju Ramachandran, Shiva Rao P., A. Subba Rao, A.T. Rao,
K.V. Mohan, Suyodhan Byrapaneni, G Ramakrishna Prasad,
T.V. Ratnam, K Subba Rao, P. Ramesh Babu, T.V. George, Y
Vismai Rao, Y Raja Gopala Rao, K Parameshwar,                    C
Khwairakpam Nobin Singh, Rohit Rao, Kamal Bhudhiraja,
Siddharth Bawa, (for Dua Associates), B Kanta Rao, Sudha
Gupta, M Srinivas R Rao, S Chandra Shekhar, B Gopal Reddy,
Manoj Kumar, R.V. Kameshwaran, Ravi Shastri, Vinita
Sasidharan, S. Udaya Kumar Sagar, Bina Madhavan, (for            D
Lawyers' Knit & Co.), Anil Kumat Tandale, V.G. Pragasam,
Anagha S. Desai, John Mathew Guntur Prabhakar, Rohit Rao
M., Ariban Guneshwar Sharma for the appearing parties.
    The Judgment of the Court was delivered by
                                                                 E
      SWATANTER KUMAR, J. 1. Andhra Pradesh Electricity
Regulatory Commission (for short 'Regulatory Commission')
was created in furtherance to the provisions of the Andhra
Pradesh Electricity Reform Act, 1998 (hereinafter referred to
as the 'Reform Act, 1998') enacted by the State legislature      F
which received the assent of the President on 21st December,
1998 and became effective w.e.f. 1st February, 1999. The
Commission initiated suo motu proceedings for determination
of tariff applicable to the Non-Conventional Energy generation
projects of Andhra Pradesh, which was to take effect from 1st    G
April, 2004 onwards. After hearing the Non-Conventional Power
Project Developers, the Non-Conventional Energy
Development Corporation of Andhra Pradesh Ltd. and
Transmission Corporation of Andhra Pradesh Ltd. (for short
referred to as 'NEDCAP' and 'APTRANSCO' respectively), the       H
    658      SUPREME COURT REPORTS                   [2010] 8 S.C.R.


A   Regulatory Commission, vide its detailed order dated 20th
    March, 2004, arrived at certain conclusions and fixed the energy
    purchnse rates at base unit price of Rs. 2.25 as on 1st
    April,1994 and the escalation index of 5% p.a., but the
    escalation would be simple and not to be compounded every
B   year. In other words, the base price as on 1st April, 2004 will
    be Rs.3.37 per kwh. As these projects have no variable
    expenses and negligible increase in maintenance cost, the tariff
    will be frozen for a period of five year, which however, is to be
    reviewed thereafter. The Regulatory Commission also issued
c   certain instructions to restrict and regulate various operations
    and other aspects. It restricted the sale, procurement and
    distribution of electricity by the Developers to any other party
    except APTRANSCO. After passing of the order dated 20th
    March, 2004 an application for review was filed by the
D   Developers before the Regulatory Commission. The order was
    clarified to some extent on this review application vide order
    dated 7th July, 2004. Aggrieved from both these orders the
    Developers filed independent appeals under Section 111 (1) of
    the Electricity Act, 2003 collectively against the order dated 2oth
    March, 2004 as modified by order dated 7th July, 2004. These
E   appeals came up for hearing before the Appellate Tribunal for
    Electricity (for short the 'Tribunal') which decided all these
    appeals by a common order dated 2nd June, 2006. The
    Tribunal granted certain relief to the appellants before it, who
    are the respondents in the present appeals, holding that there
F   was some element of duress in execution of the purchase price
    agreements. The Power Purchase Agreement (for short 'PPA')
    was a statutory document and the Regulatory Commission had
    no authority to interfere with the same. It could not even be
    altered by the Regulatory Commission. One of the most
G   important finding recorded by the Tribunal was that the
    Regulatory Commission has neither the power nor jurisdiction
    to compel the Developers to sell the power generated by them
    to APTRANSCO and/or DISCOM. Feeling seriously aggrieved
    from the order of the Tribunal the Transmission Corporation of
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 659
     _POWER PVT. LTD. [SWATANTER KUMAR, J.)

Andhra Pradesh Ltd. as well as Eastern Power Distribution           A
Company of Andhra Pradesh Ltd. have come up in appeal
before this Court under Section 125 of the Electricity Act, 2003.
Though the controversy, in the present case, appears to be a
narrow one but on examination it is clear that there are various
ancillary questions, which need to be decided by the Court,         B
prior to answering the main controversy relating to the
jurisdiction and fixation of tariff by the Regulatory Commission.
Arguments at great length were addressed by different learned
counsel appearing for the parties. Before we notice the facts
in detail or even refer to the contentions raised, it will be       c
appropriate to refer to the issues involved in the case as the
entire matter revolves around these questions and answers
thereto and the relief granted. For better understanding of the
same, let us refer to these questions and answers. The
comparative table of the points at issue, that were raised, and
                                                                    D
the answers thereto are as under:
A. Whether a Regulatory          On the point 'A', we hold that
Commission has the power,        the Regulatory Commission
authority and jurisdiction       has neither the power nor the
either under the Electricity     authority nor jurisdiction to      E
Act, 2003 or under the A         compel the Developers to sell
Electricity Reform Act, 1998     the power generated by them
to compel the Developers to      TO      APTRANSCO           or
sell the power generated by      DISCOMS.
them       to   the    State                                        F
Transmission Utility or
Distribution Company?
B. Whether the A.P.              On the point 'B'. we hold that
Regulatory Commission            the Regulatory Commission
having approved and              having approved the regulated      G
regulated the purchase price     the purchase price agreed to
of power in terms of             between the Developer and
arrangement and PPA              the TRANSCO in terms of
entered            between       Section 21 (4)(b) and 11
                                                                    H
    660    SUPREME COURT REPORTS                   (2010] 8 S.C.R.


A                           an     (1 )(e) of the Andhra Prades
    Developers i'n terms of Sec.   Electricity Reform Act, 199
    21 (4)(B) and 11 (1)(e) of     read with Section 86 (1 )(b) o
    A.P. Reform Act read with      2003 Act cannot re-fix th
    Sec. 86( 1)(b) of 2003 Act     regulatory purchase price b
B   could re-fix the regulatory    resorting to tariff fixation unde
    purchase price by resorting    Section 62; 64 read wit
    to tariff fixation under       Section 86(1 )(a) of 2003 Act
    Section 62; 64 read with       as Section 86( 1)(b) being
    Sec. 86(1 )(a) of 2003 Act?    sµecial provision excludes th
c                                  applicability of Section 86(1 )(a
                                   of the 2003 Act to privat
                                   Generators.
    C. Whether the A.P.            On the point 'C' and 'F', w
    Regulatory Commission has      hold that the Andhra Prades
D   the power or authority to      Regulatory Commission has n
    alter the policy directions    power or authority to alter th
    issued by the State            policy direction issued by th
    Government with respect to     State Government and the sai
    NCE Developers? Whether        Commission has no executiv
E   the Commission could claim     power nor a plenary power a
    executive power with           claimed by it.
    respect to NCE Developers
    and fixation of price for
    power generated by NCE
F   Developers and sold to
    APTRANSCO/DISCOM?
    D. Whether the plea of         The points 'D' & 'E' ar
    estoppel advanced by           answered in favour of th
    Developers is sustainable      appellants and they ar
G   on facts and law?              substantiated by the appellants
    E. Whether the plea of         The points 'D' & 'E' ar
    legitimate  expectation        answered in favour of th
    advanced by Developers is      appellants and they ar
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE661
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

sustainable?                     substantiated       by     the    A
                                 appellants.
F. Whether- the          A.P.    On the point 'C' and 'F', we
Electricity      Regulatory      hold that the Andhra Pradesh
Commission is possessed          Regulatory Commission has
                                                                   B
of Executive Powers to           no power or authority to alter
issue policy arid executive      the policy direction issued by
directions in respect of NCE     the State Government and the
Developers in the State?         said Commission. has no
                                 executive power nor a plenary
                                 power as claimed by it.           c
G. Is not the Commission         On the point 'G', we hold that
bound by directions already      the Andhra Pradesh Electricity
issued by the State in           Regulatory Commission is
respect of NCE Developers        bound by policy directions
as well as incentives            already issued by the State       D
directed by the given to         Government so long as they
encourage them?                  are not modified or altered.
H. Whether Regulatory             On the point 'H', we hold that
Commission could alter or        the Regulatory Commission
                                                                   E
change the PPAs entered          has no authority to alter or
between     the     NCE          change the PPAs entered
Developers and Electricity       between the NCE Developers
Board/APTRANSCO?                 and     Electricity    Board/
                                 APTRANSCO
                                                                   F
I. Whether the procurement       On the point 'I', we hold that
arrangement/ PPA entered         the procurement arrangemenU
is a statutory contract and if   PPA is statutory and the
so, wh-ether it could be         Commission has no authority
interfered       by       the    to interfere with the same.
                                                                   G
Commission?

J. Whether the Commission · On the point 'J', we hold that
is just a regulator to approve the Commission is just a
the PPA entered or whether regulator or approve the PPA
                                                                   H
    SQ.2    SUPREME COURT REPORTS                     [2010] 8 S.C.R.


A   it could determine tariff with   entered between the appella11t
    respect        to        NCE     generator       and         the
    Developers?                      APTRANSCO by examining
                                     as to whether the purchase is
                                     economical and it is in terms of
B                                    State Policy.
    K. Having approved PPA by        In the result on the 'K', we hold
    exercise of Regulatory           that the appeals preferred by
    Power, is it open to             the      NCE       Developers-
    commission to undertake          Appellants in appeal Nos.
c   determination of tariff in       1,2,5,6,7,8,9, 10, 12, 15, 16, 17, 1
    respect     of     private       8,19,20,21,22,3
                                     4,46,47,52,58, 67 & 80 of
                                     2005 are allowed and the
                                     impugned proceedings of the
D                                    Regulatory Commission are
                                     set aside and there will be a
                                     direction to the APTRANSCO,
                                     the Transmission Corporation
                                     of AP, the Central Power
E                                    Distributing Company of AP
                                     Ltd., the Southern Power
                                     Distributing Company of AP
                                     Ltd., the Northern Power
                                     Distributing Company of AP
F                                    Ltd. and the Eastern Power
                                     Distributing Company Limited
                                     of AP Ltd. to continue the
                                     Power Purchase and at the
                                     same rate at which the power
                                     generated           by        NCE
G
                                     Developers supplied to them
                                     are being paid before passing
                                     of the impugned order of the
                                     Commission                  dated
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 663
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

generation       by     NCE 20.03.2004 and 07.07.2004              A
Developers?                 made in R.P. No.84/2003 and
                            O.P. No.1075/2000 with all
                            differences and arrears thereof,
                            up to date and continue to pay
                            at the same rate, until a new          B
                            PPA is entered by agreement
                            between them in terms of State
                            Government Policy direction,
                            that may be made hereafter
                            and       approved      by     the     C
                            Regulatory Commission. This
                            Judgment shall be given effect
                            from         the     date        of
                            communication. For payment of
                            tariff difference and arrears, the     o
                            respondents shall have six
                            weeks from the date of this
                            Judgment, failing which the
                            respondents shall be liable to
                            pay interest at 9% per annum           E
                            with effect from the month on
                            which the difference in tariff rate
                            remains to be paid ant till date
                            of payment.
                                                                   F
L. To what relief, if any?     Consequently, the Appeal Nos.
                               46,48,49 and 50 of 2005
                               preferred      by    the     AP
                               Transmission Corporation and
                               the four Discoms will stand
                               dismissed as there are no           G
                               merits in them. The parties shall
                               bear the respective cost
                               throughout.

                                                                   H
    664     SUPREME COURT REPORTS                  [2010] 8 S.C.R.


A       2. The above conclusions arrived at by the Tribunal on the
  factual matrix that the Government of Andhra Pradesh on 18th
  January, 1997 by GO Ms. No. 93, with the object of encouraging
  generation of electricity from renewable sources of energy,
  allowed uniform charges to all such projects. After issuance of
B the above GO Ms. 93 certain ambiguities were noticed by the
  concerned parties. This resulted in issuance of GO Ms. No. 112
  dated 22nd December, 1998 and vide this GO clarifications
  were issued to the earlier Government order and it clearly
  provided for uniform implementation of the proposed scheme
c to all non-conventional energy developers/generators of power.
  The Andhra Pradesh Electricity Regulatory Commission was
  constituted under the said Reform Act, 1998 vide notification
  dated 3rd April, 1999 and the same Commission performing
  the duties and functions under the above Act continued to be
  a Commission under and within the meaning of Electricity Act,
0
  2003 as well. This was done by virtue of Section 185 of the
  Electricity Act, 2003. State Government of Andhra Pradesh
  notified the Transmission Corporation of Andhra Pradesh to be
  the State Transmission utility. We may also notice here that the
  Electricity Regulatory Commissions Act, 1998 also
E contemplated under Section 3, constitution of a Central
  Electricity Regulatory Commission to exercise the powers
  conferred and functions assigned to it under the Act. In terms
  of Section 17 of this Act the State Government was also to notify
  in the official gazette and establish, for the purposes of this Act
F a Commission for the State to be known as the State Electricity
  Regulatory Commission. In terms of Section 22 of this Act the
  functions of the State Commission were defined, which included
  determination of tariff for electricity, wholesale, bulk, grid or
  retail, as the case may be. Under Section 11 of the Reform Act,
G 1998 it has been spelt out as to what are the functions of the
  Regulatory Commission, inter alia, it provides to aid and advise
  to the State Government, in matters concerning electricity
  generation, transmission, distribution and supply in the State,
  to issue licences in accordance with the provisions of this Act
H and determine the conditions to be included in the licences, to
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 665
     POWER PVT. LTD. [SWATANTER KUMAR, J.]
regulate the purchase, distribution, supply and utilization of        A
electricity, the quality of service, the tariff and charges payable
keeping in view both the interest of the consumer as well as
the consideration that the supply and distribution cannot be
maintained unless the charges for the electricity supplied are
adequately levied and duly collected, to require licensees to         B
formulate prospective plans and schemes in cooperation with
others for the promotion of generation, transmission, distribution
and supply of electricity. Besides these powers, which have
been noticed by us, inter alia, the residue clause has been
worded very widely to permit the Regulatory Commission to             c
undertake all incidental or ancillary things. Under Section. 15,
the Regulatory Commission is vested with the power to issue
licences and to enter into agreements on specified terms and
also to determine the charges and establish tariff in terms of
clause (5) of Section 15 of the Reform Act, 1998. It needs to
                                                                      D
be noticed that the State of Andhra Pradesh was vested with
the powers and intact the duty to constitute the Regulatory
Commission in terms of Section 11 afore noticed.

      3. The Regulatory Commission was constituted as per the
provisions of Reform Act, 1998 vide notification dated 3rd April,     E
1999 and it was to perform all regulatory functions pertaining
to the electricity industry in the State of Andhra Pradesh. It was
commonly agreed before us during the course of argument that
it is the Electricity Regulatory Commission for the State of
Andhra Pradesh for all intent and purposes under the Reform           F
Act, 1998 as well as the Electricity Act, 2003. We must notice,
at this stage itself, that the Tribunal has entertained the doubt
that since no independent notification was issued under Section
17 of Electricity Regulatory Commission Act, 1998, therefore,
it could not exercise the powers vested in the Regulatory             G
Commission under that Act. This may not be the correct
position in law. The Regulatory Commission was constituted
under the Reform Act, 1998 and an appropriate notification in
that behalf was issued. The Electricity Regulatory Commission
Act, 1998 stood repealed by the Electricity Act, 2003. The            H
    666      SUPREME COURT REPORTS                  [201 O] 8 S.C.R.


A Electricity Act. 2003 specifically recognized and accepted the
  Commissions constituted under the enactments specified in the
  schedule to the Act as appropriate Commission. In entry 3 of
  the said schedule, Reform Act, 1998 has been specifically
  noticed. In other words, the Regulatory Commission constituted
B under the Reform Act, 1998 became the appropriate
  commission under the Electricity Act, 2003 as well.

         4. In exercise of its powers, the Regulatory Commission
    claims to have issued licences to Transmission Corporation as
C   well as DISCOM for bulk and retail supply of electricity w.e.f.
    1st April, 2001. Vide order dated 20th June, 2001 made in OP
    No. 1075 of 2000, the Regulatory Commission directed
    generators of Non-Conventional Energy to supply power
    exclusively to APTRANSCO. The Non-Conventional Energy
    Developers were not permitted to sell the energy generated by
D   them to 3rd parties. By the same order the Regulatory
    Commission also approved the rate which was prevailing earlier
    for such supply at Rs. 2.25 per unit with 5% escalation per
    annum from 1994-95 being the base year. After coming into
    force of the Electricity Act, 2003, Regulatory Commission
E   issued notice on 23rd October, 2003 inviting objections from
    various Developers and Generators to the proposals of
    APTRANSCO and NEDCAP in regard to fixation of price to
    be paid by APTRANSCO for the quantum of electricity
    purchas.ed from non-conventional energy projects w.e.f. 1st
F   April, 2004. The objections, if any, were to be filed on or before
    5th November, 2003. NEDCAP and DISCOM were to submit
    proposals for review of incentives. The proposal had been
    received for review by the Regulatory Commission from
    APTRANSCO. Within the extended time the Developers,
G   individually as well as acting through their Association, filed
    various objections in response to the notice dated 23rd
    October, 2003. All the parties were granted hearing by the
    Regulatory Commission which, then, passed the order dated
    20th March, 2004, reducing the price payable by APTRANSCO
H   to Non-Conventional Energy Developers towards the supply of
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 667
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

electricity. Some of the Developers moved to the Andhra             A
Pradesh High Court by filing a Writ Petition No. 7222 of 2004
in which interim order dated 15th April, 2004 came to be
passed directing APTRANSCO to continue to pay to NCE
Developers for the power that may be supplied by them as per
the earlier rates prevalent on 1st April, 2004. By order dated      B
27th April, 2004, the High Court disposed of the batch of the
Writ Petitions while issuing the direction to the Developers to
approach the Regulatory Commission and seek review of its
order dated 20th March, 2004. The Regulatory Commission
was also directed to take up the review petition and dispose        c
of the same within 8 weeks. Till then, the interim order dated
15th April, 2004 was to remain in force. This resulted in filing
of the Review Petitions before the Regulatory Commission. In
the meanwhile the Govt. of Andhra Pradesh ordered that
APTRANSCO shall cease to engage in trading relating                 D
functions and that the PPAs entered with the Developers shall
vest in DISCOM(s) w.e.f. 10th June, 2004 in terms of Section
 39 read with Section 172(b) of the Electricity Act, 2003. The
 Review Petitions filed by the Developers before the Regulatory
 Commission came to be dismissed by different orders passed         E
 on 5th July, 2004 and 10th July, 2004 respectively. The Review
 Petition filed by APTRANSCO also came to be dismissed on
 11th July, 2004. This resulted in approaching the High Court
 again, by nine of the developers, filing Writ Petition No. 16621
of 2004. The High Court, vide its order dated 16th September,
2004, permitted the implementation of the revised tariff by         F
 APTRANSCO. It further directed that 50% of the differential
 amount between the old and the revised tariff shall also be paid
for the actual power supplied. By GO 58 dated 7th June, 2005,
 an approval scheme came to be framed under the Reform Act,
 1998 to transfer and distribute the assets and contracts of bulk   G
 supply and trading business of APTRANSCO to DISCOM
which was in furtherance to the earlier decision of the State of
 Andhra Pradesh. Ultimately these Writ Petitions came to be
 disposed of with the direction that the Developers shall
 approach the Tribunal and the interim order shall continue to      H
    668     SUPREME COURT REPORTS                  (2010] 8 S.C.R.


A   be in force for a period of 8 weeks from 15th June, 2005 or till
    the Tribunal passes order on the interim application, whichever
    is earlier. Same interim order was passed by the Tribunal
    during the pendency of the appeal which, were filed before it.

        5. As is obvious from the above narrated facts and again,
8
  it is not in dispute that the Regulatory Comrr»sston passed an
  order dated 20th June, 2001 which, in faet, attained finality and
  its correctness was never been questiorned by any of the parties
  including the present appellants. Thu$, the order dated 20th
  June, 2001 is of some significance and certainly of some
C definite relevancy. The proceedings were initiated suo motu by
  the Regulatory Commission against all the Developers of Non-
  Conventional Energy including mi~i hydro projects. The
  Regulatory Commission noticed, in its order dated 20th June,
  2001 that Govt. of India issued guidelines regarding
D promotional and fiscal incentives to be given by the State
  Governments for power generation through Non-Conventional
  Energy sources. The Govt. of Andhra Pradesh issued order No.
  19 dated 16th March, 1996 under which it accorded certain
  incentives in respect of the Developers with whom NEDCAP
E had entered into the memorandum of 1.:mderstanding. A review
  of these incentives was taken after whiqh GO Ms. 93 dated 18th
  November, 1997 was issued, as alre13dy noticed and it was
  decided to provide uniformity to all the projects based on
  renewable sources of energy like Waste, Wind, Bio-mass, Co-
F generation, Municipal Waste and Mini Hydro projects.

       6. The Regulatory Commission had passed an order
  dated 6th March, 2000 giving certain (:lirections including that
  the Developers could sell the power g€1nerated by them to third
  party upto 17th November, 2000. The rates were indicated, as
G we have already noticed, and that there would be reviewed with
  regard to purchase price with referenae to each Developer on
  completion of 10 years from the date of the commission of the
  project. After noticirTg various objections that had been raised
  by the Developers it was stated 'that the Regulatory
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 669
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

Commission was not attempting to stop any incentive while           A
referring to the statistics and the· market conditions. It was
specifically noticed that permitting Non-Conventional Energy
Developers to make third party sales would not, at all, be in the
interest of organized growth of electricity industry and it would
create discrimination between the industrial consumer drawing       8
power from Non-Conventional Energy Developers and the
industrial consumers drawing power from APTRANSCO and
these two would have to pay two different rates. It also noticed
that there will be undue enrichment of the Developers as they
were permitted to establish their generation plants with definite   C
benefits which were carried out for. years together. While
holding that the Regulatory Commission had jurisdiction, it also
noticed that the rate approved by the Regulatory Commission
on the basis of guidelines issued by the Ministry of Non-
Conventional Energy Sources are much higher than the rate
permitted by the State Government and in comparison to other        D
States they were favourable to the NCE developers. This
reasoning persuaded the Regulatory Commission to pass the
following directions:

     "29. The existing incentives under G.O. Ms. No. 93, dated      E
     18.11.1997, which are continued. under the orders of the
     Commission from time to time till 24.06.2001 under our
     letter No. 2473, Dated 24-04-2001 -are extended for the
     time being till 24-07-2001. The temporary extension has
     been given to enable the developers to finalise                F
     agreements'/arrangements relating to supply of power to
     APTRANSCO prior to 24-07-2001 ). With effect from the
     billing month pf August 2001, all generators of non-
     conventional energy shall supply power to APTRANSCO
     only as per the following terms:                               G

             (i)    Power generated by non-conventional energy
                    developers is not permitted for sale to third
                    parties.

             (ii)   Developers of non-conventional energy shall     H
    670       SUPREME COURT REPORTS                  [2010] 8 S.C.R.


A                       supply power generated to APTRANSCO/
                        DISCOMS of A.P. only.

          (iii) Price applicable for the purchase by the supply
          licensee should be Rs. 2.25 per unit with 5% escalation
          per annum with 1994-95 as the base year.
8
          APTRANSCO is simultaneously directed to arrange
          payment for the supply of power purchased from
          developers of non-conventional energy by opening a Letter
          of Credit in favour of the suppliers of power.
c
          30. A suo motu review of the incentives to take effect
          from 1st April, 2004, will be undertaken by the Commission
          after discussions with all the concerned parties. There will
          also be a review of the purchase price with specific
          reference to each developer on completion of 10 years
D
          from the date of commissioning of the project (by which
          time the loans from financial institutions would have been
          repaid) when the purchase price will be reworked on the
          basis of return on enquity. O&M expenses and the variable
          cost.
E
          31. However, if any developer wishes to raise any
          specific issue with reference to this order, he will be
          entitled to apply to the Commission in the manner provided
          in the regulations."
F
       7. After passing of this order by the Regulatory
  Commission the parties executed PPAs. These agreements
  were signed on the lines of the directives given in the order of
  Regulatory Commission. In fact, it was stated that the
  agreements were required to be and were actually approved
G by the Regulatory Commission. In terms of Clause 5 of the PPA
  these agreements were enforceable subject to obtaining
  consent of the Regulatory Commission as per Section 21 of
  the Reform Aot, 1998. Obviously, the rates and conditions
  specified in the earlier proceedings of 11th November, 1999,
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 671
     POWER PVT. LTD. [SWATANTER KUMAR, J.]
1st April, 2000, 27th January, 2001 and 13th July, 2001 were A
accepted by the parties. Some of the clauses of the PPA, which
have also been heavily relied upon by the learned counsel for
the parties, read as under:

                            "ARTICLE 2                               B
     PURCHASE OF DELIVERED ENERGY AND TARIFF

            2.1   All the Delivered Energy at the
                  interconnection point for sale to
                  APTRANSCO will be purchased at the tariff C
                  provided for in Article 2.2 from and after the
                  date of Commercial Operation of the Project.
                  Title to Delivered Energy purchased shall
                  pass from the Company to the APTRANSCO
                  at the Interconnection Point.                  D

            2.2    The Company shall be paid the tariff for the
                   energy delivered at the interconnection point
                   for sale to APTRANSCO at Rs. 2.25 paise
                   per unit with escalation at 5% per annum with
                   1994-95 as base year and to be revised on         E
                   1st April of every year upto the year 2003-
                   2004. Beyond the year 2003-2004, the
                   purchase price by APTRANSCO will be
                   decided by Andhra Pradesh Electricity
                   Regulatory Commission. There will be further      F
                   review of purchase price on completion of ten
                   years from the date of commissioning of the
                   project, when the purchase price will be
                   reworked on the basis of Return on Equity,
                   0 & M expenses and the Variable Cost."            G

     8. Besides the above clauses it also provided other terms
and conditions under different articles, which are not necessary
for us to be noticed at this stage. It required to be noticed with
some significance that no disputes of any kind were raised by        H
    672      SUPREME COURT REPORTS                     [2010] 8 S.C.R.


A   the Developers till and after passing of the order dated 2oth
    March, 2004. The order of 20th June, 2001 read in conjunction
    with the PPAs executed by the parties controlled the entire field
    and all the persons including the Regulatory Commission as
    well as the State therein.
B
          9. This period of nearly three years, thus, was free of
    grievances and objections and the order of 2001 appears to
    have been implemented willingly by the parties. There was
    execution of the PPAs completely bringing the matter between
    the parties into the realm of contract. Thereafter, the Regulatory
C   Commission in terms of its 2001 order appears to have initiated
    suo motu proceedings for determination of tariff for non-
    conventional energy projects of Andhra Pradesh with effect from
    1st April, 2004. The Regulatory Commission, in its order dated
    2oth March, 2004 has also noticed the background facts of the
D   case and the determination of rates earlier. It had given notice
    to all the developers and other shareholders to submit their
    views and objections on the above issues. After hearing the
    parties, the Regulatory Commission considered the proposal
    for tariff. The proposal submitted by APTRANSCO and
E   NEDCAP were as under :

          "APTRANSCO's Tariff Proposals

    Particulars Unit Tariff (Levelised Tariff        Year-on-year
F               over the life of the project)         escalation
                  Existing       New            Existing     New
                   Plants        Plants
                  Rs/kWhr.       Rs/kWhr.
    Mini Hyde!        2.42         2.31          -            -
G
    Bagasse           2.23         2.25          2%           2%
    Biomass           2.27         2.27          2%           2%
    Waste to          Nil          2.66          -            1%
    Energy
H   Wind              2.52         2.55          -            -
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 673
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

                                                                      A
NEDCAP Tariff proposals:
Bagasse                              Rs. 2.62 - 1st year
                                     Rs. 2.48 - 10th year
Biomass                              Rs. 3.27 - 1st year
                                     Rs. 3.77 - 10th year             B
Mini Hydel                           Rs. 2.96 - 1st year
                                     Rs. 2.26 - 10th year
Wind Farm                            Rs. 4.54 - 1st year
                                     Rs. 3.19 - 10th year
Waste to Energy                      Rs. 2.99 - 1st year              c
                                     Rs. 3.19 - 10th vear
     10. Objections to the above proposals were also received.
Interestingly and rightly so, the Regulatory Commission before
analyzing the proposal and objections, noticed:
                                                                      D
    "20 .... as mentioned herein above, the Commission, in this
    order is not examining any issues concerning the direction
    contained in the order dated 20.6.2001 that the NCE
    Developers shall not sell electricity to third parties and they
    are required to sell electricity only to APTRANSCO. The           E
    Commission, in this order, is dealing with only those NCE
    Developers who had accepted the order dated 20.6.2001
    and voluntarily agreed to sell electricity to APTRANSCO
    on the terms and conditions contained in the order dated
    20.6.2001"                                                        F

      11. While the Regulatory Commission undertook the review
of prices in relation to sale of electricity by Non-Conventional
Energy developers, it specifically referred to order in O.P. No.
1075 of 2000, which, in turn, provided for review of sale price       G
and incentives given earlier to the said developers with effect
from 1st April, 2004. It also noticed that the PPAs signed by
the APTRANSCO and NCE Developers include provisions for
such review by the Regulatory Commission with effect from 1st
April, 2004. It took the view that review of the price at which
    674        SUPREME COURT REPORTS                 [2010] 8 S.C.R.


A APTRANSCO shall purchase power from the NCE developers
  is within the jurisdiction of the Regulatory Commission under
  Section 21 (4) of the Reform Act, 1998 and also under Section
  86(1) of the Electricity Act, 2003. Referring to Section 61 of the
  Electricity Act, 2003 which cast obligation upon the Regulatory
B Commission to frame tariff regulations specifying the terms and
  conditions for determination of tariff, in para 21 of that order,
  the Regulatory Commission framed the following issues:

                     "Issues for consideration on merits:

C         The Commission has considered inter alia, the following
          issues:

       (i)     Whether the tariffs and incentives should be uniform
               for all the categories of NCE projects as provided
D              earlier in MNES guidelines, GoAP orders and
               APERC's order OP. No. 1075/2000 dated 20.6.2001
               or should they be different for different categories of
               NCE projects.

       (ii)    Whether the tariff should be a single part tariff or a
E              two part tariff.

       (iii)   Whether the tariff should be project specific or uniform
               for all project falling in a category.

       (iv)    Whether there should be a cap on tariff when a project
F
               exceeds the expected minimum performance.

       (v)     Social and environmental considerations.

       (vi)    Control period."
G
         12. The Regulatory Commission decided tariff fixation in
    relation to Bagasse based co-generation plants, Bio-mass
    power generation and Mini hydel projects separately. The
    specific issue raised by the objectors was that the
    benchmarking of capital cost should be based on market
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 675
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

trends, confirmed through competitive bidding from time to A
time. Though APTRANSCO accepted this in principle, but
stated that they expect a detailed procedure from the Regulatory
Commission for an effective competent bidding. The tariff basis
was questioned as well as it was submitted that tariff beyond
threshold limit should be limited to the variable cost and B
incentives only and not the full tariff. This was opposed by
APTRANSCO which preferred a single time tariff in entire
energy purchase. While taking into consideration the
applicability of depreciation and its extent the tariff was fixed
and the Regulatory Commission drew the following conclusion:          c
           "81. The tariffs arrived at along with escalation under
    each category will be applicable as detailed in the
    respective paragraphs under each category. The
    aforementioned tariffs are, however, also subject to the
    following:                                                     D
         Iii.   In regard to tariff for Bagasse based co-
                generation projects, where the Plant Load Factor
                during a settlement period exceeds 55% (the level
                at which the fixed cost is expected to be             E
                recovered), only incentive of 21.5 paise/unit and
                variable cost as indicated in para (47) above shall
                be paid for every unit delivered in excess of the
                55% PLF.

         ii.                                                        F
                As regards to tariff for Biomass based power
                projects, where the Plant Load Factor ·during a
                settlement period exceeds 80% (the level at
                which the fixed cost is expected to be recovered},
                only incentive of 21.5 paise/unit and variable cost
                as indicated in para (63) above shall be paid for G
                every unit delivered in excess of 80% PLF.

         iii.   The tariff for mini-hydel power projects is
                exclusive of Royalty.
                                                                      H
    676   SUPREME COURT REPORTS                   [201 O] 8 S.C.R.

A         iv.   In the case of tariff for mini-hydel power projects,
                where the PLF during settlement period exceeds
                35%, only an incentive of 21.5 paise/kwh shall be
                paid for every unit delivered in excess of 35%.

          v.    The tariffs authorized above will be applicable
8
                w.e.f. 1.4.2004 to all NCE power plants of
                respective categories for sale to APTRANSCO.

          vi.   The above tariff structure is valid for control
                period of five years with effect from 1.4.2004.
c               Thereafter, the Commission will review the prices
                and incentives after consultation with the
                Developers and licensees.

          vii. A further review of the individual projects will be
D              undertaken on completion of 10 years from the
               date of commissioning of the project, by which
               time the loan is expected to have been
               substantially repaid, and the purchase price will
               be based on 0 & M expenditure, return on equity,
               variable cost and residual depreciation, if any.
E
          viii. For those developers' having captive
                consumption who supply excess energy to
                APTRANSCO after meeting their internal
                consumption, the current practice of meter
F               reading at the interconnection point and grossing
                up for auxiliary consumption in order to arrive at
                PLF will be misleading as it will not take into
                consideration the captive consumption. The
                incentive payments begin after threshold PLF. In
G               order to ascertain the PLF levels, APTRANSCO
                should make arrangements for authenticated
                meter reading at the generator terminals so that
                the two-tier tariff is properly implemented.

          ix.   Developers will be entitled to dispatch 100% of
H
TRANSMISSION CORPN. OF AP. LTD v. SAi RENEWABLE 677
     POWER PVT. LTD. [SWATANTER KUMAR, J.]
              the available capacity without reference to Merit       A
              Order Dispatch subject, however, to any system
              constrains."

     13. After arriving at this conclusion the Regulatory
Commission also specifically clarified that as and when,              B
however, trading function of APTRANSCO is segregated and
vested in new entity pursuant to the Electricity Act, 2003, the
terms and conditions contained therein shall be binding on the
new entity in the same manner as was applicable to
APTRANSCO.
                                                                      c
      14. As is clear from the order itself that it dealt with,
primarily, the question of refund/fixation of tariff in relation to
various generation projects. It decided no other matter and even
these findings were subsequently questioned by the Developers
before the High Court and in furtherance to the order of the High     D
Court dated 15th July, 2004, Review Petitions were filed, which
finally resulted in filing of the appeals before the Tribunal.

     15. We may notice here that vide notification dated 28th
May, 2004, the State Government ordered that APTRANSCO                E
shall cease to engage in trading relating functions and that the
PPAs entered with the Developers shall vest inDISCOM w.e.f.
10th June, 2004 in terms of Section 39 read with Section 172(b)
of the Electricity Act, 2003. On 9th June, 2004, the Central
Government also authorized the State Transmission Utility to
                                                                      F
engage in bulk purchase and sell it to DISCOM for a period of
one year from 10th June, 2004. With this background, the
appeals which were filed before the Appellate Tribunal came
up for hearing and some appeals were also filed by DISCOM
with APTRANSCO as a party. Appeals from both sides came
up, heard and decided by the order dated 2nd June, 2006               G
impugned in the present case.

    16. Now with this factual background, we shall proceed to
examine the issues of law raised in the present appeals before
                                                                      H
    678          SUPREME COURT REPORTS                  [2010] 8 S.C.R.


A   this Court. As already not~ed, in paragraph 40 of the impugned
    judgment, the Tribunal had framed as many as 12 points for
    determination which were answered by it in paragraph 114. The
    points formulated by the Tribunal, in fact, can be categorized
    in the following principal heads:
B
          (i)     Matters relating to jurisdiction of the Commission
                  for fixation of tariff and sale of generated electricity
                  to third party;

          (ii)    Correctness of tariff fixation on merits of the case;
c
          (iii)   Is the principle of estoppel attracted in the present
                  case, if so, to what extent?

          (iv)    Does the plea of duress need to be accepted as
                  per settled principles and with reference to the facts
D
                  of the case?

          (v)     What is the effect of order dated 20.6.2001 having
                  attained finality and even not being questioned in
                  the present proceedings?
E
          (vi)    What orders can be made by this Court to deal with
                  these appeals to do complete justice between the
                  parties?

       17. Fixation of tariff is, primarily, a function to be performed
F by the statutory authority in furtherance to the provisions of the
  relevant laws. We have already noticed that fixation of tariff is
  a statutory function as specified under the provisions of the
  Reform Act, 1998, Electricity Regulatory Commissions Act,
  1998 and the Electricity Act, 2003. These functions are required
G to be performed by the expert bodies to whom the job is
  assigned under the law. For example, Section 62 of the
  Electricity Act, 2003 requires an appropriate Commission to
  determine the tariff in accordance with the provisions of the Act.
  The Regulatory Commission has been constituted and notified
H
                                                                          '




TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 679
     POWER PVT. LTD. [SWATANTER KUMAR, J.)

under the provisions of Section 3 read with Section 11 of the         A
Reform Act, 1998 which in terms of Section 11 (1 )(c)&(e) is
expected to fix the tariff as well as the terms of licence. There
are three different legislations in course and the Regulatory
Commission has been constituted under the Reform Act, 1998
which in turn would be the Commission as contemplated under           B
the Electricity Regulatory Commission Act, 1998 and the
Electricity Act, 2003. In terms of first proviso to Section 82(1)
of the Electricity Act, 2003 the State Electricity Regulatory
Commission established by the State Government under
Section 17 of the Electricity Regulatory Commission Act, 1998         c
and the enactment specified in the schedule shall be the State
Commission for the purposes of this Act. Even in terms of
Section 185(3) of the Electricity Act, 2003 the said authority
would be deemed to be an appropriate Commission for all
purposes and intent as the Reform Act, 1998 has been
                                                                      D
specifically mentioned in entry 3 of the Schedule to the
Electricity Act, 2003. In other words, as already noticed the
 Regulatory Commission constituted by the said notification
would be the appropriate Commission under all these Acts and
is required to perform the functions as contemplated under
 Sections 11, 17 and 82 of the respective Acts. The functions         E
assigned to the Regulatory Commission are wide enough to
specifically impose an obligation on the Regulatory
Commission to determine the tariff. The specialized
 performance of functions that are assigned to Regulatory
 Commission can hardly be assumed by any other authority and          F
 particularly, the Courts in exercise of their judicial discretion.
 The Tribunal constituted under the provisions of the Electricity
 Act, 2003, again being a specialized body, is expected to
examine such issues, but this Court in exercise of its powers
 under Article 136 of the Constitution would not sit as an            G
 appellate authority over the formation of opinion and
 determination of tariff by the specialized bodies. We would
 prefer to leave this question open to be considered by the
 appropriate authority at the appropriate stage. We do not
                                                                      H
    680      SUPREME COURT REPORTS                    (2010] 8 S.C.R.


A consider it appropriate to go into the merit or de-merit of
  determination of tariff rates in the appeals. Determination of
  tariff is a function assigned legislatively to a competent forum/
  authority. Whether it is by exercise of legislative or subordinate
  legislative power or a policy decision, if the Act so requires,
B but it generally falls in the domain of legislative activity and the
  Courts refrain from adverting into this arena.

          18. We have to further examine the legality of this issue in
    the light of the findings that we have recorded on the issues in
    relation to jurisdiction of the Regulatory Commission to
C   determine/review the tariff. The jurisdiction of this Court is
    limited in this aspect. This Court has consistently taken the view
    that it would not be proper for the Court to examine the fixation
    of tariff rates or its revision as these matters are policy matters
    outside the preview of judicial intervention. The only explanation
D   for judicial intervention in tariff fixation/revision is where the
    person aggrieved can show that the tariff fixation was illegal,
    arbitrary or ultra virus the Act. It would be termed as illegal if
    statutorily prescribed procedure is not followed or it is so
    perverse and arbitrary that it hurts the judicial conscious of the
E   Court making it necessary for the Court to intervene. Even in
    these cases the scope of jurisdiction is a very limited one. This
    Court in the case of Association of Industrial Electricity Users
    v. State of Andhra Pradesh ((2002) 3 SCC 711], while dealing
    with the provisions of tariff fixation in terms of the provisions of
F   the Reform Act, 1998, observed that even where the Act did
    not envisage classification of consumers according to the
    purpose for which electricity is used, Sub-Section(9) of Section
    26 of that Act does state that the tariff rate relatable to
    classification of consumers would be permissible, of course,
G   depending upon various factors stipulated in Section 26(7) of
    the Act. The Court finally held as under:

          "11. We also agree with the High Court that the judicial
          review in a matter with regard to fixation of tariff has not
          to be as that of an Appellate Authority in exercise of its
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 681
     POWER PVT. LTD. [SWATANTER KUMAR, J.]
    jurisdiction under Article 226 of the Constitution. All that the   A
    High Court has to be satisfied with is that the Commission
    has followed the proper procedure and unless it can be
    demonstrated that its decision is on the face of it arbitrary
    or illegal or contrary to the Act, the court will not interfere.
    Fixing a tariff and providing for cross-subsidy is essentially     B
    a matter of policy and normally a court would refrain from
    interfering with a policy decision unless the power
    exercised is arbitrary or ex facie bad in law."

      19.' Similarly, in the case of West Bengal Electricity C
Regulatory Commission v. CESC Ltd. [(2002) 8 SCC 715],
this Court was concerned with determination of tariff by the
State Commission, the applicability of principles of natural
justice and the scope of interference by the High Court in
distinction to the power exercisable by the appellate authority.
Stating it to be a function in the nature of legislative power, the · D
Court felt that the principles of natural justice were not attracted
and the power of judicial review could hardly be invoked. The
Court held as under:

     "39. Having considered the finding of the High Court, we          E
     are of the opinion that though generally it is true that the
     price fixation is in the nature of a legislative action and no
     rule of natural justice is applicable (see Shri Sitaram
     Sugar Co. Ltd. v. Union of India SCC, para 45), the said
     principle cannot be applied where the statute itself has          F
     provided a right of representation to the party concerned.
     Therefore, it will be our endeavour to find out whether, as
     contended by learned counsel for the appellants, the
     statute has provided such a right to the consumers or not.

     xxx   xxx                     xxx                xxx              G

     44. Having held on merits that the Regulations are not
     arbitrary and are in conformity with the provisions of the
     Act, we will now consider whether the High Court could
                                                                       H
    682       SUPREME COURT REPORTS                   (2010] 8 S.C.R.


A         have gone into this issue at all in an appeal filed by the
          respondent Company. First of all, we notice that the High
          Court has proceeded to declare the Regulations contrary
          to the Act in a proceeding which was initiated before it in
          its appellate power under Section 27 of the Act. The
B         appellate power of the High Court in the instant case is
          derived from the 1998 Act. The Regulations framed by the
          Commission are under the authority of subordinate
          legislation conferred on the Commission in Section 58 of
          the 1998 Act. The Regulations so framed have been
c         placed before the West Bengal Legislature, therefore they
          have become a part of the statute. That being so, in our
          opinion the High Court sitting as an appellate court under
          the 1998 Act could not have gone into the validity of the
          said Regulations in exercise of its appellate power."
D         20. In view of the above settled position of law we are of
    the considered opinion that the present case is one where this
    Court should examine determination of tariff on merits and
    particularly, in view of the directions that we propose to pass
    finally in this case.
E
        21. The issue relating to jurisdiction, again, would have to
  be divided into two different parts. Firstly, whether the
  Regulatory Commission could exercise the powers for
  determination and/or re-fixing the price by resorting to tariff
F fixation powers under the Act and secondly, with regard to sale
  of generated electricity by the Generators to parties other than
  State Transmission Utility or Distribution Company. In regard
  to first part of this issue the Tribunal in its order, while answering
  issue B, held that Regulatory Commission has no jurisdiction
G to re-fix the regulatory purchase price by resorting to tariff
  fixation methods specified under the provisions of law.
  Similarly, it also answered issue A in the negative and against
  the Regulatory Commission. The primary reason recorded by
  the Tribunal is that the original fixation of purchase price for
  energy generated by NCE Developers is in terms of the policy
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 683
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

directions issued by the State and it was not within the                A
jurisdiction and scope of the powers conferred upon the
Regulatory Commission under the Reform Act, 1998. It was
considered by the Tribunal that policy decision of the State
could not have been set at naught on the assumption that the
Regulatory Commission is vested with executive powers. Also             B
that Regulatory Commission had proceeded on the basis that
it has power to review the rate/incentives given to developers
or it has power to issue executive directions. The Tribunal also
felt that PPAs are final and binding and there is assumption of
power on the part of the Regulatory Commission that they have           c
authority to fix tariff with respect to power generators by taking
recourse to provisions of Sections 62, 64 read with Section
86(1) of Electricity Act, 2003.

     22. Before we proceed to examine the various provisions
under different Acts afore referred, let us once again refer, in        D
precise form, the necessary facts. From the record it appears
that on 7th September, 1993 the Ministry of Non-Conventional
Energy Sources, New Delhi had written a letter to the Chief
Secretary of the different States informing them that under the
new strategy and action plan of the ministry special emphasis           E
is sought to be given to generation of grid quality power from
non-conventional energy sources, noticing that the average cost
of power generation from non-conventional energy sources
compares quite favourably with new coal thermal/gas based
projects and captive diesel generating sets. While in future the        F
costs of the former are expected to drop, costs of conventional
electricity generation will only increase. Referring to the fact that
Central Government has introduced several fiscal and other
promotional incentives to attract private sector participation in
the generation and supply of ·energy from non-conventional              G
energy sources and consequently the States had also
introduced measures such as wheeling and banking, buy back,
third party sale, capital subsidies, industry status, sales tax
exemption etc., it had also been noticed that they were to vary
                                                                        H
    684     SUPREME COURT REPORTS                   [2010] 8 S.C.R.


A   in operation from State to State. In this background the Ministry
    had drawn up guidelines which was enclosed to that letter and
    asked all States to work towards a uniform policy pertaining to
    the non-conventional energy sources. A minimum buy back
    price of Rs. 2.25 per unit had been proposed and it required
B   the States to consider that these guidelines were not exhaustive.
    Other matters, including additional incentives, attractive
    packages could be formulated by the State and accordingly the
    States were required to take further steps. The very opening
    part of the guidelines dealt with the operative period and it was
c   stated that "The Scheme of promotional and fiscal incentives
    will come into operation with immediate effect and will remain
    in force for a period of five years." Besides this eligibility,
    facilities and tax relief etc. were also indicated. The
    transmission of Electricity was to be undertaken by the State
    Electricity Board and even the third party must be HT consumer
0
    of the Board unless the stipulation was specifically relaxed.
    SEB was to purchase the electricity from the producer at the
    minimum specified rate without any restriction on time or
    quantum of electricity. Importantly, Clause 3(iii) of the policy
    guidelines suggested that the producer will have the option to
E   sell the electricity generated by him to a third party at mutually
    agreed rates but within the State as per clause 1(i). On or
    before 14th February 1994 two projects, namely wind farm and
    mini hydel projects were transferred from Andhra Pradesh State
    Electricity Board to NEDCAP by the Government of Andhra
F   Pradesh. Later, vide letter dated 25th November, 1994 the
    guidelines as indicated in the letter of 7th September, 1993
    were further clarified by the Government of India, in relation to
    fixation of purchase price for power produced from non-
    conventional energy. As per the guidelines commenting or
G   clarifying the earlier guidelines it was stated that the base price
    applicable to non-conventional energy based power projects
    based on solar, wind small hydro, biomass etc. shall be equal
    to the base price of the year in which the PPAs are signed,
    clause 2 of the guidelines reads as under:
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 685
     POWER PVT. LTD. [SWATANlER KUMAR, J.]

     "A promoter I developer shall be entitled to receive the         A
     base price set out in PPA for all electrical energy delivered
     from his project to the State grid for the duration of the
     Power Purchase Agreement. The rate shall be equal to
     base price in the year of signing of PPA, escalated at a
     rate of 5% per year for a period of 10 years, from the date      B
     of signing of the Power Purchase Agreement. From the
     end of the 10 years, and for the remaining duration of the
     Power Purchase Agreement, the new purchase price shall
     be equal to the purchase price at the end of the 10th year,
     or the High Tension (HT) tariff prevalent in the State at that   c
     time which is higher."

     23. In furtherance of the decision of the Govt. of India and
the guidelines published, the Govt. of Andhra Pradesh issued
two different GOs on which, the Tribunal as well as all the parties
before us have placed heavy reliance. They read as under:             D

                  ENERGY(RES) DEPARTMENT

     G.O.MS. NO: 93                 DATED: 18-11-1997

     ORDER:-                                                          E

      "In the reference 1st read above, the Ministry of Non-
     Conventional Energy Sources, Government of India have
     issued guidelines for promotional and Fiscal incentives to
     be given by State Government for power generation from F
     Non-Conventional Energy Sources. The incentives are
     envisaged to encourage power generation in the Non-
     C o nve ntio n a I Sector which are renewable and
     encouragement from the Government for this Sector is
     necessary in view of the fact depletion of fossilfuels. G
     Further, the Renewable/ Non-Conventional Energy
     Sources are least pollution-effecting.

     In the G.O. third read above, the Government have
     accorded certain revised incentives in respect of the
                                                                      H
    686       SUPREME COURT REPORTS                  [2010] 8 S.C.R.


A         Developers with whom Non-Conventional Energy
          Development Corporation of Andhra Pradesh had already
          entered into Memoranda of Understanding based on the
          guidelines existing prior to 15th November, 1995.

          While reviewing the incentives made available to the
B
          sectors, certain representations were received from some
          of the Non-Conventional Energy Developers, and they
          have requested for extending the benefits available to other
          sectors.

c         A review of the incentives made available to various
          sectors of non-conventional energy was made in the
          presence of official from Non-Conventional Energy
          Development Corporation of Andhra Pradesh and Andhra
          Pradesh State Electricity Board, duly keeping in view the
D         guidelines of Ministry of Non-Conventional Energy
          Sources, Government of India, dated: 13-9-1993, a view
          was taken to make available the incentives to all the Non-
          Conventional Energy Sources uniformly.

          The Government after careful examination of the
E
          recommendations and with a view to encourage
          generation of electricity from renewable sources of energy
          hereby allow the following uniform incentives to all the
          projects based on renewable sources of energy viz. Wind,
          Biomass, Co-generation, Municipal Waste and Mini Hyde!:
F


    S.No. Description
     1.      Power Purchase price               Rs. 2.25
G
     2.      Escalation                         5% per annum with
                                                1997-98 as base
                                                year and to be
                                                revised on 1st April
H                                           I   of every year upto the
TRANSMISSION CORPN. OF AP LTD v. SAi RENEWABLE 687
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

                                          year 2000 A.O.            A

 3.       Wheeling Charges                2%

 4.       Third party sales               Allowed at a tariff not
                                          lower than H.T. tariff
                                          of A.P.S.E. Board.        B

 5.       Banking                          Allowed    up to   12
                                           months

 (a)      Captive consumption              Allowed throughout
                                           the year on 2%
                                                                    c
                                           banking charges.

 (b)      Third party sale                 Allowed on 2%
                                           banking charges
                                           from August to           D
                                           March.

       This order issues with the concurrence of Finance &
       Planning (Fin.) Department vide their U.O. No. 46291/351/
       EBS-EFES&T/97, dated: 18.11.1997.
                                                                    E
       (BY ORDER AND IN THE NAME OF THE GOVERNOR
       OF ANDHRA PRADESH)

                                                V.S. SAMPATH

                              SECRETARY TO GOVERNMENT               F

                    ENERGY(RES) DEPARTMENT

       G.O. Ms. No.112             Dated: 22.12.1998
                                                                    G
       ORDER:

       "In the Government Order cited, certain uniform incentives
       were extended to the Developers of Power Projects using
       wind, biomass co-generation, Municipal wastes and mini
                                                                    H
    688      SUPREME COURT REPORTS                 [2010] 8 S.C.R.


A         hydel for promotion of and to encourage generation of
          electricity from renewable sources of energy. In order to
          remove certain ambiguities in the implementation of
          uniform incentives scheme and also to ensure that the
          incentives contemplated are channelled for promotion and
B         development of non-conventional energy sources, in
          keeping with the spirit of Government Order cited, the
          following amendments are issued:

          In the Government Order cited, certain uniform incentives
          were extended to the Developers of Power Projects using
c         wind, biomass co-generation, Municipal wastes and mini
          hydel for promotion of and to encourage generation of
          electricity from renewable sources of energy. In order to
          remove certain ambiguities in the implementation of
          uniform incentives scheme and also to ensure that the
D         incentives contemplated are channelled for promotion and
          development of non-conventional energy sources, in
          keeping with the spirit of Government Order cited, the
          following amendments are issued:

E                1.    The uniform incentives specified in G.O. Ms.
                       No.93, dated 18.11.1997 shall be available
                       only to the power projects where fuel used is
                       from non-conventional energy sources which
                       are on the nature of renewable sources of
                       energy.
F
                 2.    The operation of the incentives scheme shall
                       be watched for a period of 3 years and at the
                       end of 3 years period from the date of G.O.
                       Ms. No.93 the Andhra Pradesh State
G                      Electricity Board shall come up with suitable
                       proposals for review for further continuance
                       of the incentives in the present form or in a
                       suitable modified manner to achieve the
                       objectives of promotion of power generation
H
TRANSMISSION CORPN. OF AP. LTD v. SAi RENEWABLE 689
     POWER PVT. LTD. [SWATANTER KUMAR, J.]
                   through non-conventional sources.                  A

            3.     Though there is a provision for banking and
                   third party sale, in the absence of conferring
                   the status of licences under Section 3 of the
                   Indian Electricity Act, the Entrepreneurs/         B
                   Developers of non-conventional energy
                   power may be handicapped in effecting third
                   party sales to the needy and contracted
                   consumers. Therefore, it is hereby ordered
                   that the Entrepreneurs/Developers covered          C
                   by G.O.Ms. No.93, dated 18.11.1997 who
                   made the third party sale of energy shall be
                   deemed to be licencees for the purpose
                    under Section 3 of the Electricity Duty Act,
                    1930 read with Sedion 28 of Indian
                    Electricity Act."                                 D

                   (BY ORDER AND IN THE NAME OF
                   GOVERNOR OF ANDHRA PRADESH)

                                                   S. SAMPATH
                                                                      E
                             SECRETARY TO GOVERNMENT

     24. These were the declarations or representations stated
to have been made by the State to the Developers. The PPAs
between Transmission Corporation of Andhra Pradesh Ltd.               F
and the Developers were executed somewhere in May 1999
and some of the agreements even prior thereto. However,
despite all the above guidelines and GOs, the Regulatory
Commission passed an order on 20th June, 2001 determining
the tariff as well as defining other rights and obligations between   G
the parties including that the generators were not permitted to
make sale in favour of third party. After the passing of this order
the Developers entered into PPAs between the period August
2001 to 2002 and confirmed the acceptance and
implementation of the order of 20th June, 2001. While providing
                                                                      H
    690      SUPREME COURT REPORTS                   [2010) 8 S.C.R.


A different clauses relating to various facets of sale and
   distribution of generated power, PPAs under Articles 2.1 and
   2.2, which we have already reproduced, contemplate
   specifically that the purchase of energy by APTRANSCO will
   be at the tariff provided under Article 2.2. Article 2.2 determines
B the rate at Rs. 2.25 per unit with escalation at 5% per annum
  with 1994-1995 as base year which is to be revised on 1st
  April of every year upto the year 2003-2004, beyond which the
  purchase price by APTRANSCO will be decided by the
  Regulatory Commission. Still a further review of purchase price
c is contemplated on completion of 10 years from the date of
  commissioning of the project when it will be reworked. In other
  words, there are specific stipulations provided under the PPAs,
  as well as in the order dated 20th June, 2001, for revision/
  review of purchase price. Clause 2.3 further clearly says that
0 tariff is inclusive of all taxes, duties and levies. In other words,
  all the documents afore stated provide for a review including
  the guidelines issued by the Govt. of India.

       25. At this stage, we may notice that these guidelines are
  general guidelines and every State was required to act as per
E its own needs, convenience and by taking a general view, as
  to, which are the most practical and affordable projects and
  how they should be carried on by the State. To give meaning
  to the guidelines that they were 'absolutely mandatory', will not
  be in conformity with the law relating to interpretation of
F documents as well as according to the canons of exercise of
  executive and administrative powers. These guidelines were
  certainly required to be moulded by the State to meet their
  requirements depending on various factors prevailing in the
  State.
G
       26. Now we will proceed to refer to the various legal
  provisions relating to purchase price and/or tariff regulations.
  The principal central legislation in this regard is the Indian
  Electricity Act, 2003. Under Section 3, a national electricity
  policy and plan has to be prepared by the Central Government
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 691
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

which has to be notified. This plan itself can be reviewed or          A
revised by the appropriate authority under the Act. Section 8
of the Electricity Act, 20031 requires every State to notify and
constitute, for.the purposes of this Act, a Commission for the
State to be known as Electricity Regulatory Commission of that
State. Section 86 of this Act spells out the functions of the State    8
Commission. Under Section 86(1 )(a) it is to determine the tariff
for generation, supply, transmission and wheeling of electricity,
wholesale, bulk and retail, as the case may be. It is also to
regulate electricity purchase and procurement process of
distribution licencees including the price at which electricity        C
shall be procured from the generating companies or licensees
or from other sources through agreements for purchase of
power for distribution and supply within the State as per Section
86(1)(b). Section 86(1)(d) empowers this Commission to issue
 licer.c@s to persons seeking to act as transmission licensees,
distribBtion licensees and electricity traders with respect to their   D
operations within the State. Besides its advisory functions it has
also been given the general /residue powers to do all other
 functions in terms of Section 86(1 )(k). Sections 61 to 64 of the
 Electricity Act, 2003 place an obligation upon the appropriate
 Commission to determine the tariff in accordance with the             E
 provisions of this Act. An application .for determination of tariff
 shall be made by the generating company under Section 64
 and the tariff has to be determined by the appropriate
 Commission and it is also required to specify the terms and
 conditions for determination of the tariff as per the factors and     F
 the guidelines specified under Section 61 of th~ Act.

     27. The Reform Act, 1998 was enacted, primarily, with the
object of constituting two separate corporations; one for
generation and other for transmission and distribution of              G
electrical energy. The essence was restructuring, so as to
achieve the balance required to be maintained in regard to
competitiveness and efficiency on the one part and the social
objective of ensuring a fair deal to the consumer on the other.
This Act is also intended for creation of a statutory regulatory       H
    692      SUPREME COURT REPORTS                    (2010] 8 S.C.R.


A   authority. Section 3 of the Act requires the State Govt. to
    establish by notification a Commission to be known as Andhra
    Pradesh Electricity Regulatory Commission. This was done by
    notification dated 3rd April, 1999. As already noticed, section
    11 detailed the functions of the Regulatory Commission and
    primarily it had advisory as well as regulatory functions. In terms
8
    of Section 11 (1 )(c) it was required to issue licenses in
    accordance with the provisions of the Act and determine the
    conditions to be included in the license. However, 11 (1 )(e) gave
    it much wider power and duty LO regulate the purchase,
C   distribution, supply and utilization of electricity, the quality of
    service, the tariff and charges payable keeping in view both the
    interest of the consumer as well as the consideration that the
    supply and distribution cannot be maintained unless the charges
    for the electricity supplied are adequately levied and duly
    collected. In terms of Section ·11 (1 )(I) it was to undertake all
D   incidental or ancillary things to the functions assigned to it under
    the provisions of the Act. Section 12 of the Act vests the State
    Govt. with the power to issue policy directions on matters
    concerning electricity in the State including the overall planning
    and co-ordination. All policy directions shall be issued by the
E   State Govt. consistent with the objects sought to be achieved
    by this Act and, accordingly, shall not adversely affect or
    interfere with the functions and powers of the Regulatory
    Commission including, but not limited to, determination of the
    structure of tariffs for supply of electricity to various classes of
F   consumers. The State Govt. is further expected to consult the
    Regulatory Commission in regard to the proposed legislation
    or rules concerning any policy direction and shall duly take into
    account the recommendation by the Regulatory Commission
    on all such matters. Thus the scheme of these provisions is to
G   grant supremacy to the Regulatory Commission and the State
    is not expected to take any policy decision or planning which
    would adversely affect the functioning of the Regulatory
    Commission or interfere with its functions. This provision also
    clearly implies that fixation of tariff is the function of the
H   Regulatory Commission and the State Govt. has a minimum
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 693.
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

role in that regard. Chapter VII of this Act deals with tariff. In     A
terms of Section 26(2), the Regulatory Commission, in addition
to its power of issuing licence, is entitled to fix terms      and
conditions for determination of the licensee's revenue and tariffs
by regulations which are to be duly published. The expression
'tariff' has not been defined in any of the Acts, with which we        B
are concerned in the present appeals, despite the fact that the
expression 'tariff' has been used repeatedly in both the Acts.
Under the Electricity Act, 2003 'tariff' has neither been defined
nor explained in any of the provisions of the Act. Explanation
(b) to Section 26 of the Reform Act, 1998 states-what is meant         c
by 'tariff'. This provision states that 'tariff' means a schedule of
standard price or charges or specified services which are
applicable to all such specified services provided to the type
 or types of customers specified in the 'tariff' notification. This
 is an explanation to Section 26 which deals with licenses,            D
 revenues and tariffs. In other words, this explanation may not
 be of greater help to the Court in dealing with the case of
 generating companies. Similarly, the expression 'purchase
 price' has neither been defined nor explained in any of the
 afore-stated Acts.
                                                                       E
     28. Therefore, in the absence of any specific definition in
any of these Acts we will have to depend upon the meaning
attached to these expressions under the !iJeneral law or in
common parlance. The expression 'tariff' has been explained
in the Law Lexicon with legal Maxims, Latin terms and Words            F
& Phrases (Second Edition 1997) as "determination,
ascertainment, a table of rates of export and import duties, in
which sense the word has been adopted in English and other
European languages and as defined by the law dictionaries the
word 'tariff' is a cartel of commerce; a book of rates; a table        G
or catalogue, drawn usually in alphabetical order, containing the
names of several kind of merchandise, with the duties or
customs to be paid for the same as settled by the authority or
agreed between the several princes and States that hold
commerce together."                                                    H
    694      SUPREME COURT REPORTS                   (2010] 8 S.C.R.


A        29. It has also been explained as a schedule, system, or
    scheme of duties imposed by the Government of a country
    upon goods imported or exported; published volume of rate
    schedules and general terms and conditions under which a
    product or service will be supplied; a document approved by
s   the responsible regulatory agency listing the terms and
    conditions including a schedule of prices, under which utility
    services will be provided. The expression 'purchase price' has
    to be given its limited meaning, i.e. the price paid for
    purchasing a good and in the context of the present case, price
c   at which generated electricity will be sold to the specified
    agencies. The term 'purchase price' indicated in the PPAs, as
    such, would be a matter within the realm of contract but this is
    subject to the changes which are contractually and/or even
    statutorily permissible. Purchase price ultimately would form
    part of the tariff, as tariff relatable to a licensee or a consumer
0
    would have essentially taken into account, the purchase price.
    The purchase price may not include tariff but tariff would always
    or is expected to include purchase price.

        30. The Regulatory Commission is vested with very vast
E powers and functions. Section 11 of the Reform Act, 1998
   declares fixation of tariff as one of the primary functions of the
   Regulatory Commission in general more particularly, to the
   specified consumers under Section 26 of the Reform Act, 1998.
   While under the Electricity Act, 2003, Sections 61 and 62 read
'= with Section 86 (1 )(a)(b) deal with fixation of tariffs in relation
   to production, distribution and sale of generated power to the
   end consumer. These provisions clearly demonstrate that the
   Regulatory Commission is vested with the function for
   determining the tariff for generation, supply, transmission and
G billing of electricity etc., as well as regulation of electricity
   purchase and procurement process of distribution licensees,
   including price at which electricity shall be procured from the
   generating companies. With these specific powers in the
   statute book itself, it cannot be said that procurement of power
H from the generating companies will not fall within the ambit of
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 695
     POWER PVT LTD. [SWATANTER KUMAR, J.]
powers and functions of the Regulatory Commission. It, as A
already noted, is a common body performing functions, duties
and exercising powers under all these three Acts. This Court
had the occasion to deal with somewhat similar issues in the
case of PTC India Ltd. v. Central Electricity Regulatory
Commission [(2010) 4 SCC 603]. The Court was, amongst B
others, dealing with the provisions of Sections 61 to 63 of the
Electricity Act, 2003 and regulation making power of the
Regulatory Commission. The Court was concerned with other
issues as well including the powers of the Tribunal in relation
to judicial review etc. but it will be of assistance to us to notice c
that the Court referred to different kinds of delegated legislations
under the provisions of Electricity Act, 2003 and with regard to
the power of the Regulatory Commission and the scope of the
term 'tariff the Court held as under:

     "23. Section 52 of the 2003 Act deals with trading of D
     electricity activity. Under Section 52(1 ), the appropriate
     Commission may specify the technical requirement, capital
     adequacy requirement and creditworthiness for being an
     electricity trader. Under Section 52(2), every trader is
     required to discharge its duties, in relation to supply and E
     trading in electricity, as may be specified by the
     appropriate Commission.

     24. The standards of performance of licensee(s) may be
     specified by the appropriate Commission under Section          F
     57 of the Act.

     25. The 2003 Act contains separate provisions for the
     performance of dual functions by the Commission. Section
     61 is the enabling provision for framing of regulations by
     the Central Commission; the determination of terms and G
     conditions of tariff has been left to the domain of the
     Regulatory Commissions under Section 61 of the Act
     whereas actual tariff determination by the Regulatory
     Commissions is covered by Section 62 of the Act. This
     aspect is very important for deciding the present case. H
    696       SUPREME COURT REPORTS                     [2010] 8 S.C.R.


A         Specifying the terms and conditions for determination of
          tariff is an exercise which is different and distinct from
          actual tariff determination in accordance with the ·
          provisions of the Act for supply of electricity by a
          generating company to a distribution licensee or for
B         transmission of electricity or for wheeling of electricity or
          for retail sale of electricity.

          26. The term "tariff' is not defined in the 2003 Act. The term
          "tariff' includes within its ambit not only the fixation of rates
          but also the rules and regulations relating to it. If one reads
c         Section 61 with Section 62 of the 2003 Act, it becomes
          clear that the appropriate Commission shall determine the
          actual tariff in accordance with the provisions of the Act,
          including the terms and conditions which may be specified
          by the appropriate Commission under Section 61 of the
D         said Act. Under the 2003 Act, if one reads Section 62 with
          Section 64, it becomes clear that although tariff fixation like
          price fixation is legislative in character, the same under the
          Act is made appealable vide Section 111. These
          provisions, namely, Section 61, 62 and 64 indicate the dual
E         nature of functions performed by the Regulatory
          Commissions viz. decision-making and specifying terms
          and conditions for tariff determination.

          27. Section 66 confers substantial powers on the
          appropriate Commission to develop the relevant market
F
          in accordance with the principles of competition, fair
          participation as well as protection of consumers' interests.
          Under Sections 111 (1) and 111 (6) respectively, the
          Tribunal has appellate and revisional powers. In addition,
          there are powers given to the Tribunal under Section 121
G
          of the 2003 Act to issue orders, instructions or directions,
          as it may deem fit, to the appropriate Commission for the
          performance of statutory functions under the 2003 Act."

          31. Similarly, another Bench of this Court in the case of
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 697
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

Tata Power Company Ltd. v. Reliance Energy Ltd., [2009 (7) A
SCALE 513], was primarily, concerned with the role of the
generating companies and their right to make choice to sell
power to any person or licensee and while referring to the
concept of open access, the Court in para 59 of the judgment
referred to the issues arising in the case which read as under: B

    "Although before us a large number of contentions had
    been raised, the core questions, which arise for our
    consideration, are:-

    (A) Whether recourse to Section 23 of the Act can be C
    taken for issuance of any direction to the generating
    company?

    (B) Whether the Commission while applying the
    provisions of Section 86(1 )(b) of the Act could also take      D
    recourse to Sections 23 and 60 thereof?

    (C) Whether equitable allocation of power generated by
    a generating company is permissible?"

     32. In the present case we are, primarily, concerned with      E
the answers given by the Court to questions (A) and (B) framed
therein, the discussion on the subject and finally the relevant
conclusions drawn by the Court in para 140 to 142. The Court
elaborately discussed the matter including the fact that some
generating c9mpanies had entered into PPAs while other had          F
not. The Court, amongst others, declare the following
conclusions (of which we refer only the relevant portions):

    ''7) if regulatory clause is sought to be applied in relation
    to allocation of power, the same would defeat the de-           G
    licensing provisions. Generating companies have the
    freedom to enter into contract and in particular long term
    contracts with a distribution company subject to the
    regulatory provisions contained in the 2003 Act.

     8) PPA for a long term is essential for increasing and         H
    698       SUPREME COURT REPORTS                   [2010] 8 S.C.R.


A         decreasing the capacity of generation of electricity by the
          generating company, which purpose by the 2003 Act must
          be allowed to achieve.

          13) Section 86(1 )(b) of the 2003 Act clearly shows that the
          generating company indirectly comes within the purview of
B
          regulatory jurisdiction as and when directions are issued
          to the distributing companies by the appropriate
          Commission but the s::ime would not mean that while
          exercising the said jurisdiction, the Commission will bring
          within its umbrage the generating company also for the
c         purpose of issuance separate direction."

          33. In addition to the statutory provisions and the judgments
    afore referred, we must notice that all the PPAs entered into
    by the generating companies with the appropriate body, as well
D   as the orders issued by the State in GO Ms. Nos. 93 and 112,
    in turn, had provided for review of tariff and the conditions. The
    Tribunal appears to have fallen in error of law in coming to the
    conclusion that the Regulatory Commission had no powers
    either in law or otherwise of reviewing the tariff and so called
E   incentives. Every document on record refers to the power of the
    authority/Commission to take a review on all aspects including
    that of the tariff. One of the relevant consideration for
    determining the question in controversy is to examine whether
    the matter falls within the statutory or contractual domain. From
F   various provisions and the documents on record it is clear that
    Regulatory Commission is vested with the power to revise tariff
    and conditions in relation to procurement of power from
    generating companies. It is also clear from the record that in
    terms of the contract between the parties, the APTRANSCO
G   had reserved the right to revise tariff etc. with the approval of
    the Regulatory Commission.

         34. With some emphasis, the parties had argued the
    question relating to 'estoppel' and 'legitimate expectation' with
    reference to the facts of the present case. The contention is
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 699
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

raised that by the GOs issued by the State Government as well           A
as the letters of the ministry a representation was made by the
Government to the generating companies and they, having
altered their positions, have a right to compel the State
Government and the Regulatory Commission to abide by those
terms for ever and it is their legitimate expectation thatState         B
is required to comply with those conditions and no other.

     35. For proper analysis of the submissions made by the
parties, it is necessary for us to examine on what premises the
appellants had claimed and the Tribunal has accepted the plea
of estoppel. Admittedly, this all begins with the letter dated 7th      C
September, 1993 issued by the Government of India, Ministry
of Non-Conventional Energy Sources, New Delhi to the Chief
Secretary of the respective States. In this letter, the new strategy
action plan of the Ministry in relation to generation of grid quality
power from non-conventional energy sources was mentioned                D
in some elaboration and the Ministry had referred to the fact
that it had drawn certain guidelines and also indicated the
minimum buy-back price of Rs. 2.25 per unit which was
proposed by the Ministry and it was based upon the average
cost of generation, as noticed by the authorities, at the relevant      E
point of time. These guidelines were to constitute an attractive
package to encourage private sector and the respective States
were required to examine and alter or amend the same as
conducive to a particular State. Hereafter, a letter dated 25th
November, 1994 was again issued by the Ministry to the                  F
Managing Director of the Non-Conventional Energy
Development Corporation, Andhra Pradesh annexing the
guidelines which were subject to be amended. These
guidelines itself showed that Electricity Board, which was the
competent authority at that relevant point of time, to announce         G
a 'base purchase price' every year for electrical energy
purchased by the Board from the non-conventional energy
based projects. These guidelines contemplated that the base
price shall be escalated at a minimum rate of 5% every year.
Clause 2 of the Guidelines stipulated that the promoter or a            H
    700     SUPREME COURT REPORTS                 (2010] 8 S.C.R.


A developer shall be entitled to receive the base price set out in
  the PPA for all electrical energy delivered for the duration of
  the PPA. The rate shall be equal to the base price in the year
  of signing of PPA, escalated at the rate of 5% per year for a
  period of ten years from the date of signing. Thereafter new
8 purchase price will be fixed as per the tariff prevalent in the
  State at the relevant time. Thereafter, the Andhra Pradesh
  Government has issued GO Ms. No. 93 dated 18th November,
  1997 referring to certain incentives required to be given to the
  projects. These incentives only referred to the power purchase
C price, escalation of 5% with base year 1997-98, wheeling
  charges, third party sales allowed to a limited extent. These,
  again, were the guidelines which, in fact, we have referred to
  in great detail above and were primarily intended to guide the
  States in taking the respective decisions in that behalf. Again
D vide GO. Ms. No. 112 dated 22nd December, 1998 referring
  to the extension of all these uniform incentives, certain
  amendments were carried out to GO Ms. No. 93 dated 18th
  November, 1997. Clause 2 of this order referred that the
  operation of the incentive scheme shall be watched for a period
  of three years and at the end of three years the Electricity Board
E shall come up with suitable proposals for review for further
  continuance of the incentives in that form, or to be modified
  suitably. Keeping these guidelines in mind, the State of Andhra
  Pradesh vide GO Ms. No. 93 dated 18th November, 1997,
  while referring to the guidelines issued by the Government of
F India for promotional and fiscal incentives, noticed the various
  representations which were received from Non-conventional
  Energy Developers for extension of benefits as afore-referred
  in relation to all non-conventional energy resources uniformly.
  Thereafter, the parties took up the matter for annual
G consideration, which exercise was undertaken by them in terms
  of the guidelines issued by the State and the Central
  Government. State of Andhra Pradesh reiterated the incentives
  and directed that the same would continue for a period of three
  years in terms of GO Ms. No. 93, whereafter it will be reviewed.
H The incentives relied upon, on the basis of the guidelines and
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 701
     POWER PVT. LTD. [SWATANTER KUMAR, J.]
the issued Government orders are primarily, related to fixation       A
of purchase price of the generated power from Non-
Conventional developer/generators and sale of such energy to
third parties. In the meanwhile, Regulatory Commission had
been established under the provisions of the Reform Act, 1998.
This Regulatory Commission was to take over all the functions         B
of the said Electricity Board as well as other authorities for
generation, distribution and other matters relating to electricity
in the State. This resulted in initiation of suo motu proceedings
by the Regulatory Commission for determination and fixation
of tariff, which after hearing the parties finally passed the order   c
dated 20th June, 2001. This order as we have already noticed
was accepted by all the parties and has not been questioned
till date. This order provided for certain variations in the
 incentives, which as already noticed, are related to the fixation
of tariff or purchase price and as stipulated, the Commission         D
considered all objections at some length and ordered that
 power generated by Non-conventional Energy Developers is not
 permitted to be sold to third parties and price was kept at Rs.
 2.25 per unit price with 5% escalation per annum with 1994-
 95 as the base year. The parties had entered into agreements
                                                                      E
 i.e. PPAs at different times after passing of this order between
 June, 2001 to August, 2001 and even thereafter. Thus, at that
 time, the entire matter between the parties was controlled by
 the PPAs which fully contemplated that all the delivered energy
 at the interconnection point for sale to TRANSCO will be
 purchased at the tariff provided under Article 2.2 which in turn     F
 confirmed the order of 20th June, 2001 in that regard and it was
 stated that the matter will be reviewed in April, 2004 and it
 could also be reviewed after 10 years from the date of
 commissioning of the project. This PPA as well as the order
 passed by the Regulatory Commission in the year 2001                 G
 remained in force without being questioned in any manner
 whatsoever before any competent forum and in any case, not
 to any benefit of respondents. Then came the order dated 20th
 March, 2004 passed by the Regulatory Commission again, by
                                                                      H
    702       SUPREME COURT REPORTS                   [2010] 8 S.C.R.


A initiating suo motu proceedings. In this order, the Commission
  had retained the basic unit price of 2.25 as on 1st April, 1994
  and the escalation index of 5% per annum which was to be
  simple and not compounded every year. In other words, on 1st
  April, 2001 the price was 3.37/kwh in relation to Wind Power
B Purchasers. Except varying this price, the order of 2004, in turn,
  had reiterated the contents of the order of 2001 which, as
  already noticed, has attained finality. Another factor which we
  may notice is that in its order dated 7th July, 2004, while
  clarifying its order dated 20th March 2004, the Commission has
c clearly observed:

          "12. It is relevant to clarify that by the order dated 20-03-
          2004, the Commission is not mandating in any manner
          those NCE developers who have not accepted the earlier
          order dated 20-06-2001 passed by the Commission,
D         while their challenge to the order is pending the decision
          by the High Court. However, such of the NCE developers
          who had accepted the earlier order dated 20-06-2001 and
          have been selling electricity generated by them to
          APTRANSCO cannot challenge the jurisdiction of the
E         Commission to review the terms as per the stipulation
          contained in the order dated 20-6-2001."

       36. On the basis of this factual matrix, the respondents
  claimed that the State Government and the Regulatory
F Commission both were bound to continue the incentives as
  were provided to them in furtherance to the letters and orders
  of Central as well as the State Governments discussed above.
  They have a legitimate right to expect that these incentives were
  to be· continued indefinitely in the same manner and the
G authorities concerned are estopped from altering the rates and/
  or imposing the condition of no sale to third parties. We are
  unable to find any merit in this contention. In our view, the
  Tribunal has erred in law in treating these inter-se letters and
  guidelines between the Government of India, State Government
  and the Commission/the State Electricity Board as unequivocal
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 703
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

commitments to the respondent/purchasers/generators/                   A
developers so as to bind the State for all times to come. For
the principle of estoppel to be attracted, there has to be a
definite and unambiguous representation to a party which then
should act thereupon and then alone the consequences in law
can follow. In the present case, the policy guidelines issued by       B
the Central Government were the proposals sent to the State
Government, which the State Government accepted to
consider, amend or alter as per their needs and conditions and
then make efforts to achieve the objects of encouraging Non-
conventional Energy Generator and Purchasers to enter into this        c
field. These are the matters, which will squarely fall within the
competence of the Regulatory Commission/the State Electricity
Board at the relevant points of time. Besides that, there was
no definite and clear promise made by the authorities to the
developers that would invoke the principle of promissory
                                                                       0
estoppel. Undoubtedly, to encourage participation in the field
of generation of energy through non-conventional methods,
some incentives were provided but these ·incentives under the
guidelines as well as under the PPAs signed between the
parties from time to time were subject to review. In any case,
                                                                       E
the matter was completely put at rest by the order of 20th June,
2001 and the PPAs voluntarily signed by the parties at that time,
which had also provided such stipulations. If such stipulations
were not acceptable to the parties they ought to have raised
objections at that time or at least within a reasonable time
thereafter. The agreements have not only been signed by the            F
parties but they have been fully acted upon for a substantial
 period. We have already referred to various statutory provisions
where the Regulatory Commission is entitled to determine the
tariff. In this situation we are unable to agree with the view taken
 by the Tribunal that Regulatory Commission had no jurisdiction        G
 and that fixation of tariff does not include purchase price for buy
 back of the generated power.

     37. The principle of promissory estoppel, even if, it was
applicable as such, the Government can still show that equity          H
    704      SUPREME COURT REPORTS                   [2010] 8 S.C.R.


A  lies in favour of the Government and can discharge the heavy
   burden placed on it. In such circumstances, the principle of
  promissory estoppel would not be enforced against the
  Government as it is primarily a principle of equity. Once the
  ingredients of promissory estoppel are satisfied then it could
B be enforced against the authorities including the State with very
  few extra ordinary exceptions to such enforcement. In the United
  States the doctrine of Promissory Estoppel displayed
  remarkable vigor and vitality but it is still developing and
  expanding. In India, the law is more or less settled that where
c the Government makes a promise knowing or intending that it
  would be acted upon by the promissory and in fact the
  promissory has acted in reliance of it, the Government may be
  held to be bound by such promise. It is a settled canon of law
  that doctrine of promissory estoppel is not really based on
  principle of estoppel but is a doctrine evolved by equity in order
0
  to prevent injustice. There is no reason why it should be given
  only a limited application by way of defence. It can also be the
  basis of a cause of action. Even if we assume that there was
  a kind of unequivocal promise or representation to the
E respondents, the reviews have taken place only after the period
  specified under the guidelines and/or in the PPAs was over.
  This is a matter which, primarily, falls in the realm of contract
  and the parties would be governed by the agreements that they
  have signed. Once these agreements are singed and are
  enforceable in law then the contractual obligations cannot be
F frustrated by the aid of promissory estoppel.

        38. Following the judgment of this Court in the case of
  Union of India v. Mis. Inda-Afghan Agencies Ltd. ((1968) 2
  SCR 366], this Court in the case of Century Spinning and
G Manufacturing Company Ltd. v. The Ulhasnagar Municipal
  Council ((1970) 1 SCC 582] held that if the promise is made
  in regard to a present or existing fact, the principle of estoppel
  can be enforced against the Government. But a promise in
  relation to a future transaction or act may not fall within the ambit
H of promissory estoppel. This law was further discussed with
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 705
     POWER PVT. LTD. [SWATANTER KUMAR, J.]
some elaboration by the Court in the case of Motila/ Padampat       A
Sugar Mills. Co. Ltd. v. State of Uttar Pradesh [(1979) 2 SCC
409], where the Court after considering the position of law in
England and United States and comparing the same to the
Indian Law, laid down the basic concept of promissory estoppel
that would determine its enforceability. In the case of Pawan       B
Alloys v. UPSEB [(1997) 7 SCC 251], the Court, though had
enforced the principle of promissory estoppel against the
Board, but certain basic facts of that case needs to be noticed
by us. The appellants in that case had neither expressly nor
impliedly stated that it has the power to withdraw the incentives   c
and rebate at a time prior to the expiry of three years for which
it was granted. Secondly, none of the private parties had
voluntarily or even by remotest choice agreed to give up the
benefits given to them by clear representation held out by the
 Board. As is obvious, the power of the Board to increase the
                                                                    0
general tariff was accepted, but the incentive of rebate was de
horse the tariff and thus, promissory estoppel was enforceable
against the Board.

     39. Another very important dictum of the Court in this
judgment was that the power of the Board to fix general tariff      E
as well as discharge of other related functions was held to be
quasi-judicial in character. This power of the Board is exercised
under the statute as a power-cum-duty and is independent of
granting or declining any rebate. In the present case the order
dated 20th June, 2001 was fully accepted by the parties without     F
any reservation. After the lapse of more than reasonable time
of their own accord they voluntarily signed the PPA which
contained a specific stipulation prohibiting sale of generated
power by them to third parties. The agreement also had renewal
clause empowering TRANSCO/APTRANSCO/Board to revise                 G
the tariff. Thus, the documents executed by these parties and
their conduct of acting upon such agreements over a long
period, in our view, bind them to the rights and obligations
stated in the contract. The parties can hardly deny the facts as
 they existed at the relevant time, just because it may not be      H
    706       SUPREME COURT REPORTS                   [2010] 8 S.S.?


A   convenient now to adhere to those terms. Conditions of a
    contract cannot be altered/avoided on presumptions or
    assumptions or the parties having a second thought that a term
    of contract may not be beneficial to them at a subsequent
    stage. They would have to abide by the existing facts,
8   correctness of which, they can hardly deny. Such conduct, would
    be hit by a/legans contraria non est audiendus.

       40. Lastly, we may refer to a more recent judgment of this
  Court. In the case of Kusumam Hotels (P) Ltd. v. Kera/a Seb
  [(2008) 13 SCC 213], where the Court discussed in some
C elaboration the different judgments of this Court on the subject
  and then declined to enforce the principle of promissory
  estoppel as there was no foundational facts and also indicated
  that the Government can alter, amend or rescind its policy
  decision in public interest, the Court held as under:
D
                "27. Yet again in UP. Power Corpn. Ltd. v. Sant
          Steels & Alloys (P) Ltd., it was held: (SCC p.800, para
          27)

                "27. In this background, in view of various decisions
E         noticed above, it will appear that the Court's approach in
          the matter of invoking the principle of promissory estoppel
          depends on the facts of each case. But the general
          principle that emerges is that once a representation has
          been made by one party and the other party acts on that
F         representation and makes investment and thereafter the
          other party resiles, such act cannot be stated to be fair and
          reasonable. When the State Government makes a
          representation and invites the entrepreneurs by showing
          various benefits for encouraging to make investment by
G         way of industrial development of the backward areas or
          the hill areas, and thereafter the entrepreneurs on the
          representations so made bona fide make investment and
          thereafter if the State Government resiles from such
          benefits, then it certainly is an act of unfairness and
H
TRANSMISSION CORPN. OF AP. LTD v. SAi RENEWABLE 707
     POWER PVT. LTD. [SWATANTER KUMAR, J.)
    arbitrariness. Consideration of public interest and the fact       A
    that there cannot be any estoppel against a statute are
    exceptions."

    xxx xxx                        xxx
    36. The law which emerges from the above discussion is             B
    that the doctrine of promissory estoppel would not be
    applicable as no foundational fact therefor has been laid
    down in a case of this nature. The State, however, would
    be entitled to alter, amend or rescind its policy decision.
    Such a policy decision, if taken in public interest, should        c
    be given effect to. In certain situations, it may have an
    impact from a retrospective effect but the same by itself
    would not be sufficient to be struck down on the ground of
    unreasonableness if the source of power is referable to a
    statute or statutory provisions. In our constitutional scheme,     D
    however, the statute and/or any direction issued thereunder
    must be presumed to be prospective unless the
    retrospectivity is indicated either expressly or by necessary
    implication. It is a principle of the rule of law. A
    presumption can be raised that a statute or statutory rule         E
    has prospective operation only."

     41. In our country, the law of promissory estoppel has
attained certainty. It is only an Unambiguous and definite
promise,. which is otherwise enforceable in law upon which, the
parties· have acted, comes within the ambit and scope of
                                                                       F
enforcement of this principle and binding on the parties for their
promise and representation. It will be difficult for the Court to
hold that the guidelines can take the colour of a definite promise
which in the letters of the Central Government itself were
proposals to the State Government. Besides that, if for the sake       G
of argument, we treat the State letters/circulars as promise or
representations to the private parties like the respondents, even
then, they led to the execution of a definite contract between
the parties which will purely fall in the domain of contractual law.
                                                                       H
    708      SUPREME COURT REPORTS                     [2010] 8 S.C.R.


A These contracts specifically provided for review and when
  reviewed in the year 2001 parties not only accepted the order
  but executed contracts (PPAs) in furtherance of it. In these
  circumstances, we are unable to accept the argument that the
  State or the Regulatory Commission or erstwhile State
s Electricity Board were bound to allow same tariff and permit
  third party sales for an indefinite period. To this extent,
  authorities, in any case, would not be bound by the principle of
  estoppel.

            42. Now, we will proceed to examine the merits or
C   otherwise of the findings recorded by the Tribunal that the PPAs
    executed by the parties, were result of some duress and thus,
     it will not vest the authorities with the power to review the tariff
    and other granted incentives. PPAs were executed prior and
    subsequent to the issuance of the order dated 20th June, 2001.
D   Different persons executed the contracts at different times in
    full awareness of the terms and conditions of such PPA. To
    frustrate a contract on the ground of duress or coercion, there
    has to be definite pleadings which have to be substantiated
    normally by leading cogent and proper evidence. However, in
E   the case where summary procedure is adopted like the present
    one, at least some documentary evidence or affidavit ought to
    have been filed raising this plea of duress specifically. From
    the record before us, nothing was brought to our notice to state
    the plea of duress and to prove the alleged facts which
F   constituted duress, so as to vitiate and/or even partially reduce,
    the effect of the PPAs. On the one hand, the Tribunal appears
    to have doubted the binding nature of the contracts stating that
    it contained unilateral conditions introduced by virtue of Order
    and approval of the Regulatory Commission", while on the other
G   hand, in para 53 of the Order, it proceeded on the presumption
    that PPAs are final and binding and still drew the conclusion
    that the Regulatory Commission could not revise the tariff. Even
    in the order, no facts have been pointed out which, in the
    opinion of the Tribunal, constituted duress within the meaning
H   of the Contract Act so as to render the contract voidable.
TRANSMISSION CORPN. OF AP. LTD v. SAi RENEWABLE 709
     POWER PVT. LTD. [SWATANTER KUMAR, J.)

Another aspect of the entire controversy is that none of the         A
generators had challenged the agreements and in fact, except
in arguments before the Tribunal no case was made out for the
purposes of vitality of the contract or any part thereof. On the
contrary, all the generators under all the branches of Non-
Conventional Energies, have accepted the contract and                B
proceeded on the basis that the said contracts are binding and
still the Regulatory Commission does not have any power or
jurisdiction to revise the tariff or deal with the concessions. If
the contracts are a result of duress and cannot be given effect,
the results could be disastrous for both the sides. If a contract    c
suffers from the defect of undue influence or duress, as the
case may be then the consequences in law should follow. It is
a settled canon of law that when the consent to agreement is
caused by undue influence the agreement is a contract voidable
at the option of the parties whose consent was so caused. Even       D
 if such party had received any benefit under the terms of the
 contract the Court could still pass orders as to the voidability
 or otherwise of the contract but upon such terms and conditions
 as the Court may deem just. Undue influence or duress is said
 to be subtle of the fraud whereby mysteries burden over the
                                                                     E
 mind of a victim by insidious approaches. Firstly, there are no
 facts on record, much less, supported by any documentary or
 any other evidence to sustain the plea that the contracts (PPAs)
 are a result of undue influence or duress by the State or its
 agencies upon the generators. Secondly, the generators have
 already taken benefit of that contract which was based on the       F
 policy of the State as well as the order of the Regulatory
 Commission. Having attained those benefits, it will hardly be
 of any help to the appellants, particularly, in the facts and
 circumstances of the case, to substantiate, justify or argue the
 plea of duress.                                                     G

    43. In the case of Bir/a Jute Manufacturing Co. v. State
of M.P. [(2002) 9 SCC 667], the Supreme Court was
concerned with a case where validity of undertaking given
under duress was the plea taken by the appellant. This pleading      H
    710       SUPREME COURT REPORTS                    [2010] 8 S.C.R.


A   on the same ments and noticing the material, like the present
    case, the Court held as under:

          "2. Learned counsel, appearing for the appellant urged that
          the undertaking given by the appellant Company was under
          duress and, therefore, it is not an undertaking in the eyes
B
          of law and the appellant is not liable to pay the water
          charges under such circumstances. There is no material
          before us to come to this conclusion that the undertaking
          given by the appellant was t•rider duress. On the contrary
          we find that the appellant had given the solemn
c         undertaking voluntarily. We, therefore, find no merit in the
          appeal."

       44. The Tribunal in paras 45-47 of its order has used the
  expression "out of compulsion some of the developers entered
D into Power Purchase Agreement with APTRANSCO accepting
  the terms and conditions set out in order dated 20th June,
  2001". We are afraid that there is hardly any material on record
  to substantiate such a finding. What was the compulsion and
  what were the facts which persuaded the Tribunal to take such
E a view are conspicuous by their very absence. A compulsion
  leading to execution of a contract is a matter entirely based
  upon facts. It is difficult for this Court, originally, to infer duress
  or compulsion in absence of specific pleadings and materials
  in that behalf. It may also be noticed at the cost of repetition
F that the order dated 20th June, 2001 was never questioned by
  any ofthe parties to any favourable results. Even in these
  proceedings there is no challenge to the said order which,
  admittedly, has been acted upon and has attained finality. The
  power generators/Non-Conventional Energy developers have
G executed the PPAs without any protest and, in fact, did nothing
  to challenge such agreements or any part thereof, till passing
  of the impugned order of 2004. There were some proceedings,
  without questioning the validity and effectiveness of the order
  dated 20th June, 2001, carried out by some of the generators
  before the Andhra Pradesh High Court. Certain interim
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 711
     POWER PVT. LTD. [SWATANTER KUMAR, J.]

directions were passed in those proceedings, as already               A
noticed, but finally all proceedings culminated into dismissal of
the Writ Petitions and/or reference back to the Regulatory
Commission for grant of a hearing as per the directions
contained in the order of the High Court.
                                                                      B
      45. Another important aspect of the case is that the learned
counsel appearing for the respondents, particularly, in Appeal
No. 2926 of 2006 had stated that they are not arguing in support
of the plea of estoppel and duress as decided by the Tribunal
in their favour. They had mainly concentrated their submissions       C
on jurisdiction of the Regulatory Commission with respect to
withdrawal of incentives and fixation of tariff. These are the
contracts which have been executed prior and after the
issuance of the order dated 20th June, 2001 and have been
acted upon by the parties without any reservation. In view of the
fact that no challenge was made to the order dated 20th June,         D
2001, execution of PPAs and the conduct of the respondents
 over the long period and particularly, while keeping in mind the
 statutory provisions we are unable to sustain the plea of duress
 in favour of the respondents.
                                                                      E
      46. The main emphasis of the judgment of the Tribunal is
that the Government had framed the policy under which,
incentives were given and as such, the Regulatory Commission
had no power and authority to fix tariffs or amend or alter the
policy decision of the State. We have already held that in law        F
and in face of the contract between the parties the Regulatory
Commission is the Authority to fix the tariff which includes within
its ambit the purchase price of the Non-conventional Energy
under the policy of the State. It appears that the Tribunal has
taken a narrower view of the jurisdiction vested in the Regulatory    G
Commission which is discharging its statutory functions under
all the three Acts in accordance with law. In terms of Section
 12 of the Reform Act, 1998, which has been referred to by the
Tribunal, the power of the Government had been stated. The
 power available to the Government to issue policy directions
                                                                      H
    712       SUPREME COURT REPORTS                     [2010] 8 S.C.R.


A    has two restrictions. Firstly, the policy direction has to be on
     the matters related to electricity in State including overall
     planning and coordination. Secondly, all such policy directions
     have to be issued by the State Government in consonance with
     the object sought to be achieved by this Act and accordingly
B    shall not adversely affect or interfere with the functions and
     powers of the Regulatory Commission including, but not limited
     to, determination of the structure of tariff for supply of electricity
     to the consumers. Powers vested in the Regulatory
     Commission to frame regulations under Section 54 also intend
c    that regulations are to be framed with an object to ensure proper
     performance of its functions under the Act. In other words, both
     the State and the Regulatory Commission, are supposed to
     exercise their respective powers only for the purposes of
    furthering the cause of the Act. The Commission discharging
    its statutory functions within the ambit of Sections 11, 12 and
0
    26 of the Reform Act, 1998 as well as Sections 61, 62 and
    86(1 )(b) of the Electricity Act, 2003 renders advisory functions
    to the State. All these provisions, examined and analyzed
    cumulatively, do not support the approach adopted by the
    Tribunal that the functions of the Regulatory Commission in
E   fixing tariff/purchase price was contrary to or distinctive of the
    said policy. This cannot be supported either on the basis of the
    statutory provisions of the various Acts as well as with reference
    to the various documents on record including the order dated
    20th June, 2001 and the PPAs signed by the parties at different
F   stages. We are also unable to contribute to the view of the
    Tribunal that the Regulatory Commission has acted in
    contradiction or conflict with the State policy. The State was
    certainly not intending to provide incentives and concessions
    with assurance of buy-back to enable the Non-Conventional
G   Energy developers/generators to sell generated powers to third
    parties. It must be kept in mind that the policy of the Government
    of India as well as the State of Andhra Pradesh was for
    encouraging the developers/generators of Non-conventional
    Energy to generate electricity for the benefit of public at large
H
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 713
     POWER PVT. LTD. [SWATANTER KUMAR, J.]
with buy back of power being one of the basic features of this        A
policy. Such parameters are obviously subject to change in
larger public interest. All these issues, in fact, loose much
significanee because of the fact that parties have, by and large,
entered into the field of contract simpliciter and their rights are
controlled by the contracts executed between them. There is           B
no challenge to these contracts and, therefore, it may be hardly
permissible for the Court to go behind these contracts and
permit questioning of the statutory jurisdiction vested in the
Regulatory Commission.

     47. In the case of BSES Ltd. v. Tata Power Co. Ltd. [(2004)
                                                                      c
1 SCC 195], the Court clearly held that after creation of the
Regulatory Commissions under the provisions of the Electricity
Regulatory Commission Act, 1998, the Commission has clear
power and jurisdiction to fix tariff. The Court should not adopt
an interpretation which should neither be strict nor narrower so      D
as to oust the jurisdiction of the Regulatory Commission, as it
would defeat the very object of enacting the said Act. The
reliance placed by the respondents upon the judgment of this
Court in the case of Andhra Pradesh Electricity Regulatory
Commission v. R. V. K. Energy Private Limited [(2008) 17 SCC          E
769] is, again, of not much help to them. In that case also, the
Court had upheld the exercise of statutory power by the
Regulatory Commission. Of course, the Court held that the
regulatory power u/s 11 (1 )(e) of the Reform Act, 1998 does not
ordinarily extend to prohibition or positive direction for entire     F
supply to APTRANSCO alone. Such prohibition may be
resorted to in exceptional situations. It reiterated the principle
that the Government policy as well as the Regulatory
Commission should act in consonance with the object of the
Aci.                                                                  G

     48. The appellants have referred and relied upon the policy
directions and guidelines framed by the Central Government
while the respondents have relied upon these documents as
well as the circulars issued by the State of Andhra Pradesh.
                                                                      1-i
    714      SUPREME COURT REPORTS                   [2010] 8 S.C.R.


A   The respondents have raised the plea of estoppel against the
    Regulatory Commission on the basis of the averment that the
    State had framed policies, which the Regulatory Commission
    instead of implementing, has acted contrary thereto. There is
    no doubt that before the formation of the Regulatory
B   Commission it was the State Electricity Board which was
    performing all the functions in relation to generation as well as
    distribution of electricity. The Board was directly under the
    control of the State and the State, in exercise of its general
    executive powers, had framed policies to encourage Non-
e   conventional Energy developers and producers to come into
    the field of generation of electricity and had issued the
    Government orders which we have discussed in some detail
    above. Strange enough, the State of Andhra Pradesh was
    neither impleaded a~ a party to the proceedings before the
    Regulatory Commission nor before the Tribunal. In fact, the
0
    Tribunal has referred to various acts and deeds of the State
    and consequences thereof, but did not consider it appropriate
    to implead the State Government as a party to the proceedings.
    We are of the considered view that presence of the State
    Government before the Tribunal could have certainly been
E   appropriate, inasmuch as the State would have placed before
    the Appellate Authority and the Regulatory authorities, its views
    in regard to revision of incentives as well as the purchase price.
    We are also constrained to observe that the State of Andhra
    Pradesh was a necessary, in any case, a proper party in these
F   proceedings. This itself would be a ground for this Court to
    remit the matter to the Competent Authority, in addition to the
    other reasons recorded in this judgment.

       49. In the present case, the restriction with regard to third
G party sales was not only creation of a directive issued or
  approval granted by the Regulatory Commission, but was
  actually in furtherance to the contract entered into between the
  parties. Rights and liabilities arising from a binding contract
  cannot be escaped on the basis of some presumptions or
H inferences in relation to the facts leading to the execution of the
TRANSMISSION CORPN. OF A.P. LTD v. SAi RENEWABLE 715
     POWER PVT. LTD. [SWATANTER KUMAR, J.]
contract between the parties. The jurisdiction of the Regulatory      A
Commission, in the facts of the case, arises not only from the
statutory provisions under the different Acts but also in terms
of the contract executed between the parties which has binding
force. Lastly, but with great emphasis, it was argued on behalf
of the respondents that enforcement of the purchase price at          B
the rate determined by the Regulatory Commission along with
complete prohibition on the right of the Non-conventional Energy
Generator/Developers to sell generated power to t~e third
parties would compel them to shut down their projects. The rates
are so unfair that it would result in extinguishment of the power     c
generating units from the State of Andhra Pradesh on the one
hand, while on the other, it is bound to prejudicially affect the
larger public interest. According to the respondents they have
invested large sums of money in developing these generating
 units and it will be unfair to compel their closure, particularly,
                                                                      D
when for all these years they have supplied electricity generated
 by them solely to APTRANSCO or its predecessors.

      50. We find some substance in this submission and are
of the view that it is a matter of some concern, even for the
State Government. All these projects, admittedly, were                E
established in furtherance to the scheme and the guidelines
provided by the Central Government which, in turn, were
adopted with some modification by the State Government. The
State Electricity Board implemented the said scheme and
initially had permitted sale of generated electricity to third        F
parties, however, subsequently and after formation of the
Regulatory Commission which, in turn, took over the functions
of the State Electricity Board, the incentives were modified and
certain restrictions were placed. The reasons for these
restrictions have been stated in the affidavit filed on behalf of     G
the appellants which, as already noticed by us, is not a matter
to be examined by this Court in exercise of its extra-ordinary
jurisdiction. These matters, essentially, must be examined by
expert bodies particularly, when such bodies are constituted
 under the provisions of a special statute.                           H
    716      SUPREME COURT REPORTS                   [2010] 8 S.C.R.


A         51. The basic policy of both the Central as well as the State
     Government was to encourage private sector participation in
    generation, transmission and distribution of electricity on the
    one hand and to further the objective of distancing the regulatory
     responsibilities of the Regulatory Commission from the
B   Government and of harmonizing and rationalizing the provisions
    of the existing laws relating to electricity in India, on the other
    hand. The object and reasons of Electricity Act, 2003 as well
    as the Reform Act, 1998 are definite indicators of such
    legislative intent. The basic objects of these enactments were
c   that the said Regulatory Commission may permit open access
    in distribution of energy as well as to decentralize management
    of power distribution through different bodies. The Reform Act,
    1998 stated in its objects and reasons that the set-up of power
    sector in force, at that time, was virtually integrated and
    functional priorities were getting distorted due to resource-
0
    cru nch. This has resulted in inadequate investment in
    transmission and distribution which has adversely affected the
    quality and reliability of supply. The two corporations proposed
    thereunder were to be constituted to perform various functions
    and to ensure efficiency and social object of ensuring a fair deal
E   to the customer. These objects and reasons clearly postulated
    the need for introduction of private sector into the field of
    generation and distribution of energy in the State. Efficiency in
    performance and economic utilization of resources to ensure
    satisfactory supply to the public at large is the paramount
F   concern of the State as well as the Regulatory Commission.
    The policy decisions of these constituents are to be in
    conformity with the object of the Act. Thus, it is necessary that
    the Regulatory Commission, in view of this object, take practical
    decisions which would help in ensuring existence of these units
G   rather than their extinguishment as alleged.

         52. In view of our above detailed discussion, we dispose
    of these appeals with the following order:

                 (a)   The order of the Tribunal dated 2nd June,
H
TRANSMISSION CORPN. OFAP LTD v. SAi RENEWABLE717
     POWER PVT. LTD. [SWATANTER KUMAR, J.]
               2006 is hereby set aside.                           A

        (b)    We hold that the Andhra Pradesh Electricity
               Regulatory Commission has the jurisdiction
               to determine tariff which takes within its
               ambit the 'purchase price' for procurement of       8
               the electricity generated by the Non-
               conventional energy developers/ generators,
               in the facts and circumstances of these
               cases.

         (c)   We hereby remand the matters to the Andhra          C
               Pradesh Electricity Regulatory Commission
               with a direction that it shall hear the Non-
               conventional energy generators afresh and
               fix/ determine the tariff for purchase of
               electricity in accordance with law,                 D
               expeditiously.

         (d)   It shall also re-examine that in addition to the
               above or in the alternative, whether it would
               be in the larger interest of the public and the
                                                                   E
               State, to permit sale of generated electricity
               to third parties, if otherwise feasible.

         (e)    The Andhra Pradesh Electricity Regulatory
                Commission shall consider and pronounce
                upon all the objections that may be raised by      F
                the parties appearing before it, except
                objections in relation to its jurisdiction, plea
                of estoppel and legitimate expectancy
                against the State and/or APTRANSCO and
               'the plea in regard to PPAs being result of         G
                duress as these issues stand concluded by
                this judgment.

         (f)   We make it clear that the order dated 2oth
               June, 2001 passed by the Andhra Pradesh             H
    718      SUPREME COURT REPORTS                  [2010J 8 S.C.R.


A                     Electricity Regulatory Commission has
                      attained finality and was not challenged in any
                      proceedings so far. This judgment shall not,
                      therefore, be in detriment to that order which
                      will ope.rate independently and in accordance
B                     with law.

                (g)   We also hereby direct that State of Andhra
                      Pradesh shall be added as a party
                      respondent in the proceedings and the
                      Andhra Pradesh Electricity Regulatory
c                     Commission shall grant hearing to the State
                      during pendency of proceeding before it.

          53. In the facts and circumstances of the case parties are
    left to bear their own costs.
D
    K.K.T.                                   AppealR disposed of.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "electricity"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.