Created byFuzzy Cloud

Supreme Court of India

STATE OF ODISHA & ORS.versusM/S PANDA INFRAPROJECT LIMITED

Citation
2022 INSC 232
Decided
24 February 2022
Disposal
Disposed off

Holding

The blacklisting order, issued after a valid show‑cause notice and consideration of the inquiry report, did not breach natural justice, and while a permanent ban is excessive, the debarment may be limited to five years.

Summary

The State of Odisha blacklisted M/s Panda Infraproject Ltd. after a high‑level inquiry found the contractor responsible for the collapse of a ten‑metre flyover slab that killed one person and injured eleven. The contractor was served a detailed show‑cause notice, replied, and was subsequently debarred under the Orissa Public Works Department Code. The contractor challenged the blacklisting in the High Court, which set aside the order on the ground that it violated natural justice and was pre‑determined. On appeal, the Supreme Court held that the show‑cause process and consideration of the inquiry report satisfied the principles of natural justice, and that the State was within its authority to debar. However, the Court found a permanent ban excessive and limited the debarment period to five years. Consequently, the appeal was allowed in part, restoring the blacklisting order with a five‑year term and dismissing the related second appeal.

Issues considered

  • Whether the blacklisting order violated the principles of natural justice.
  • Whether the High Court erred in quashing the blacklisting order on the ground of pre‑determination.
  • Whether the State may impose a permanent debarment or must limit its duration.
  • Whether the procedure prescribed under the OPWD Code satisfied due process requirements.

Legislation cited

Subjects

administrative lawgovernment contractsblacklistingdebarmentnatural justicejudicial reviewpublic procurementsafety standardsshow-cause notice

Judgment

                         [2022] 2 S.C.R. 183                              183


                    STATE OF ODISHA & ORS.                                A
                                  v.
             M/S PANDA INFRAPROJECT LIMITED
                   (Civil Appeal No. 1083 of 2022)
                        FEBRUARY 24, 2022                                 B
         [M. R. SHAH AND B. V. NAGARATHNA, JJ.]
       Administrative Law: Government contracts – Blacklisting of
contractor – Principle of natural justice – Judicial review –
Respondent was awarded contract to construct a flyover over the
                                                                          C
railway level crossing – Post construction, a ten meter slab of flyover
collapsed which resulted in loss of life and property – A high level
inquiry was conducted which submitted a comprehensive report and
found respondent guilty – On the basis of such report, state
government issued a show cause notice to respondent and on
considering its reply thereto, permanently banned it from                 D
participating or bidding for any work to be undertaken by the
government – Respondent filed writ petition before High Court –
High Court set aside the order of blacklisting on the ground of
violation of principles of natural justice – On appeal, held:
Blacklisting order was passed after considering the allegations in
                                                                          E
the show cause notice, considering the reply and also by considering
the material available on record and after following the procedure
as per the Orissa Public Works Department Code – Thus, decision
of state government of blacklisting the respondent was not in breach
of principles of natural justice – “Debarment” is recognised and
often used as an effective method for disciplining deviant suppliers/     F
contractors who may have committed acts of omission and
commission – It is for the State or appropriate authority to pass an
order of blacklisting/debarment in the facts and circumstances of
the case – It was specifically found that the safety arrangements
were lacking severely in the construction work zone and quality
                                                                          G
assurance was not emphasised as stipulated in the codes – High
Court erred and exceeded its jurisdiction in exercise of powers under
Art.226 of the Constitution of India in setting aside the blacklisting
order, that too, without adverting to the serious allegations and the
act of omission and commission on the part of the contractor which
led to a serious incident of collapse of ten meter slab while concrete    H
                                 183
184            SUPREME COURT REPORTS                      [2022] 2 S.C.R.


A     work of the deck was going on and due to which one person died
      and eleven others were injured – However, to debar him permanently
      can be said to be too harsh a punishment – Blacklisting restricted
      to five years.
            Disposing of the appeals, the Court
B           HELD: 1. A detailed show cause notice was issued with
      specific allegations to which the respondent-contractor submitted
      a detailed reply. After considering the allegations in the show
      cause notice, considering the reply and also by considering the
      material available on record the order of blacklisting was passed.
C     [Para 8.3][192-D]
            2. As per the law laid down by this Court in a catena of
      decisions “debarment” is recognised and often used as an
      effective method for disciplining deviant suppliers/contractors
      who may have committed acts of omission and commission. It is
D     for the State or appropriate authority to pass an order of
      blacklisting/debarment in the facts and circumstances of the case.
      Therefore, the High Court has erred and has exceeded its
      jurisdiction in exercise of powers under Article 226 of the
      Constitution of India by quashing and setting aside the blacklisting
      order, that too, without adverting to the serious allegations and
E     the act of omission and commission on the part of the contractor
      which led to a serious incident of collapse of ten meter slab while
      concrete work of the deck was going on and due to which one
      person died and eleven others were injured. It was specifically
      found that the safety arrangements were lacking severely in the
F     construction work zone. It was also found that quality assurance
      was not emphasised as stipulated in the codes and manuals and
      as per the Agreement. Therefore, the High Court ought to have
      considered the seriousness of the incident in which due to
      omission and commission on the part of the contractor in
      constructing the flyover one person died and eleven others were
G     injured. [Para 8.7][193-C-F]
            3. In the instant case, it might be true that the offence was
      the first offence committed by the contractor. However,
      considering the seriousness of the matter that due to the omission

H
 STATE OF ODISHA & ORS. v. M/S PANDA INFRAPROJECT LTD.                 185


and commission on the part of the contractor a serious incident        A
had occurred as there was a collapse of a ten meter slab while
constructing a flyover in which one person died and eleven others
injured, as such the contractor does not deserve any leniency.
However, to debar him permanently can be said to be too harsh a
punishment. Blacklisting is restricted to five years in the fitness
                                                                       B
of things. [Para 9.1][194-F-H]
      Kulja Industries Limited v. Chief General Manager,
      Western Telecom Project Bharat Sanchar Nigam Limited
      and Ors. (2014) 14 SCC 731 : [2013] 14 SCR 430;
      Grosons Pharmaceuticals (P) Ltd. & Anr. v. State of U.P.
      (2001) 8 SCC 604 : [2001] 2 Suppl. SCR 567; Gorkha               C
      Security Services v. Govt. (NCT of Delhi) & Ors. (2014)
      9 SCC 105 : [2014] 13 SCR 617 – relied on.
      Erusian Equipment & Chemicals Ltd. v. State of West
      Bengal and Anr. (1975) 1 SCC 70 : [1975] 2 SCR 674;
      M/s. Daffodills Pharmaceuticals Ltd. & Anr. v. State of          D
      U.P. & Anr. 2019 (17) Scale 758 – referred to.
                      Case Law Reference
[1975] 2 SCR 674               referred to             Para 6.7
[2013] 14 SCR 430              relied on               Para 6.7        E
[2001] 2 Suppl. SCR 567        relied on               Para 8.4
[2014] 13 SCR 617              relied on               Para 8.6
      CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1083
of 2022.                                                               F
      From the Judgment and Order dated 23.03.2021 of the High Court
of Orissa at Cuttack in Writ Petition (C) No.26408 of 2017.
      With
      Civil Appeal No.1084 of 2022.                                    G
      Ashok Kr. Parija, AG, Ravi Prakash Mehrotra, Sr. Adv., Arnav
Behera, Ramendra Mohan Patnaik, Ms. Deepti R. Mehrotra, Apoorv
Srivastava, Prasenjit K. Chakravarti, Jogy Scaria, Advs. for the
Appellants.
                                                                       H
186            SUPREME COURT REPORTS                          [2022] 2 S.C.R.


A          Sibo Sankar Misra, Gaurav Puri, Smarhar Singh, Sarthak Gupta,
      Ms. Yashika Verma, Advs. for the Respondent.
            The Judgment of the Court was delivered by
            M. R. SHAH, J.
B             1. Feeling aggrieved and dissatisfied with the impugned judgment
      and order dated 23.03.2021 passed by the High Court of Orissa at
      Cuttack in W.P. (C) No.26408 of 2017, by which the High Court has
      allowed the said writ petition and has quashed and set aside the order
      passed by the State, banning the respondent herein from participating
      or bidding for any work to be undertaken by Government of Odisha
C     and transacting any business with Government of Odisha, either directly
      in the name of propriety bidder or indirectly under any different name
      or title, the State of Odisha has preferred the present C.A. No.1083 of
      2022.
             2. Feeling aggrieved and dissatisfied with the subsequent
D     consequential order passed by the High Court vide order dated 04.06.2021
      in W.P. (C) No.16723 of 2021 by which the High Court, in consequence
      of the earlier order dated 23.03.2021 passed in W.P. (C) No.26408 of
      2017, directed the State of Odisha to remove the name of the contractor
      – respondent herein from the list of blacklisted contractors, the State of
E     Odisha has preferred the present C.A. No.1084 of 2022.
             3. That the respondent – contractor was awarded a contract for
      construction of a flyover over the railway level crossing at Bomikhal
      Junction in Bhubaneswar. That in pursuance of the said contract the
      respondent – contractor constructed the said flyover. In the year 2017,
F     a ten meter slab of the flyover collapsed during concreting of the railway
      over bridge at the level crossing, which resulted in loss of life and
      property. One person died and eleven others were injured. A high-
      level inquiry was conducted by the Chief Engineer (Design) and Chief
      Engineer (DPI and Roads). The committee submitted a comprehensive
      report after a detailed inquiry and found the contractor – respondent
G     herein guilty. It was found that the contractor did not submit the
      formwork design and adopted his own arrangement leading to collapse
      of such a huge structure during construction. It was also found that
      the contractor had not ensured adequate safety measures during the
      period of construction; otherwise such an unfortunate fatal accident
      could have been avoided. It was found that the quality assurance had
H
 STATE OF ODISHA & ORS. v. M/S PANDA INFRAPROJECT LTD.                             187
                    [M. R. SHAH, J.]

not been maintained as stipulated in the codes and manuals and as per              A
the agreement. It was found that there were a lot many deficiencies in
workmanship that could affect the quality of work, as found in other
formwork assemblies. Therefore, the committee found the contractor
responsible for such a serious accident.
        3.1 On the basis of such report the State Government took the              B
matter very seriously and directed that immediate necessary action be
taken for blacklisting the contractor following the procedure as per the
Orissa Public Works Department (OPWD) Code. Thereafter, a show
cause notice was issued to the contractor and the contractor was asked
to show cause as to why it be not blacklisted for intentionally violating
the relevant clauses of the Agreement No.15-P1/2011-12. The respondent             C
filed a detailed reply. That on considering the allegations in the said show
cause notice and reply thereto, the Chief Engineer (DPI & Roads) Odisha
issued an order dated 12.12.2017, whereby the respondent – contractor
was blacklisted with immediate effect, for intentional violation of condition
of the contract leading to injuries and loss of life. The respondent –             D
contractor was banned from participating or bidding for any work to be
undertaken by the Government of Odisha and the contractor was also
banned from transacting business with Government of Odisha, either
directly or indirectly.
       3.2 Aggrieved by the order of blacklisting dated 12.12.2017, the            E
contractor filed Writ Petition (C) No.26408 of 2017 seeking quashing of
the order of blacklisting and by the impugned judgment and order, the
High Court has set aside the order of blacklisting mainly on the ground
that the order of blacklisting is in violation of principles of natural justice.
The impugned judgment and order passed by the High Court quashing
and setting aside the order of blacklisting is the subject matter of Civil         F
Appeal No.1083 of 2022.
       3.3 That thereafter the contractor filed another Writ Petition (C)
No.16723 of 2021, making a grievance that despite the order of blacklisting
set aside by the High Court in Writ Petition (C) No.26408 of 2017, the
contractor’s name continues to be shown as the blacklisted in the official         G
portal of the Government of Odisha. By the order dated 04.06.2021, the
High Court has disposed of the said writ petition by directing the State to
pass appropriate orders to stop showing on the official portal of the
Government of Odisha the name of the contractor – respondent herein
as a blacklisted company to enable the contractor to seek renewal of its           H
188             SUPREME COURT REPORTS                              [2022] 2 S.C.R.


A     licence as well participate in future tenders. The order dated 04.06.2021
      passed by the High Court in Writ Petition (C) No.16723 of 2021 is the
      subject matter of Civil Appeal No.1084 of 2022.
            4. Shri Ashok Kumar Parija, learned Advocate General has
      appeared on behalf of the State of Odisha and Shri Sibo Sankar Misra,
B     learned Advocate has appeared on behalf of the respondent – contractor.
             5. Shri Ashok Kumar Parija, learned Advocate General appearing
      on behalf of the State of Odisha has vehemently submitted that in the
      facts and circumstances of the case, the High Court has materially erred
      in quashing and setting aside the order passed by the State of Odisha
C     blacklisting the respondent – contractor.
             5.1 It is contended that the High Court has erred in holding that
      the order of blacklisting was in violation of the principles of natural justice.
            5.2 It is submitted that as such before blacklisting the respondent
      – contractor a show cause notice was issued and served upon the
D     respondent. The procedure as required as far as Appendix-XXXIV of
      OPWD Code was followed and thereafter, after considering the reply
      submitted by the contractor, the order of blacklisting was passed. It is
      submitted that therefore, the High Court has erred in holding that the
      order of blacklisting was in breach of principles of natural justice.
E             5.3 It is further submitted by Shri Parija, learned Advocate General
      appearing on behalf of the State that the High Court has also erred in
      concluding that the blacklisting order was pre-decided as the same was
      passed on the basis of the recommendations made in the inquiry report.
      It is urged that in fact the findings recorded by the inquiry committee
F     can be said to be the basis for initiating the action of blacklisting against
      the contractor. It is submitted that therefore, the findings recorded by
      the inquiry committee can be said to be a prima facie opinion while
      initiating the proceedings for blacklisting. It is submitted that merely
      because show cause notice was issued and the blacklisting order was
      passed on consideration of the inquiry report, that by itself it cannot be
G     said that the blacklisting order was pre-decided.
             5.4 It is further submitted by Shri Parija, learned Advocate General,
      appearing on behalf of the State that even otherwise, while passing the
      impugned judgment and order quashing and setting aside the blacklisting
      order, the High Court has not at all considered the seriousness of the
H     allegations against the contractor. It is submitted that it was a case of
 STATE OF ODISHA & ORS. v. M/S PANDA INFRAPROJECT LTD.                           189
                    [M. R. SHAH, J.]

grave lapse and omission and commission on the part of the contractor;           A
a serious incident occurred in which one person died and eleven others
were injured. It is submitted that therefore, the High Court ought not to
have interfered with the order passed by the State Government
blacklisting the respondent – contractor
      6. The present appeals are vehemently opposed by Shri Sibo                 B
Sankar Misra, learned counsel appearing on behalf of the respondent –
contractor.
       6.1 It is submitted that in the facts and circumstances of the case
the High Court has rightly observed and held that the order of blacklisting
was pre-determined and the same was in breach of principles of natural           C
justice.
        6.2 It is submitted that before a show cause notice was issued
to the respondent – contractor, a communication/letter dated 10.10.2017
was written by the Under Secretary in the Works Department to the
Chief Engineer which shows that the Government had already ordered               D
blacklisting of the contractor and the Engineer-in-Chief was directed
to take immediate action for blacklisting the contractor. It is submitted
that as rightly observed that the action of blacklisting the contractor
was pre-determined. It is submitted that it is rightly observed by the
High Court that giving a show cause notice was an empty formality
which was not going to change the decision already taken to blacklist            E
the contractor.
       6.3 It is further submitted that even in the show cause notice
there was no reference to the letter dated 10.10.2017 and/or to the report
of the committee.
                                                                                 F
       6.4 It is further submitted that even after the show cause notice
containing serious allegations of violations by the contractor, the contractor
was asked to execute the balance work, on a revised design, which the
contractor – respondent admittedly completed to the satisfaction of the
Department by 31.03.2018. It is submitted that therefore, the High Court
has rightly quashed the order of blacklisting the respondent – contractor.       G
      6.5 In the alternative, it is contended by learned counsel appearing
on behalf of the respondent – contractor that in the facts and circumstances
of the case, the order of blacklisting the respondent – contractor
permanently can be said to be too harsh and/or disproportionate to the
charge/misconduct proved against the respondent – contractor.                    H
190                SUPREME COURT REPORTS                         [2022] 2 S.C.R.


A            6.6 It is urged that it was the first offence by the respondent –
      contractor. That after the impugned order passed by the Government,
      the Government of Odisha, Works Department passed an office
      memorandum dated 26.11.2021, which provides that the blacklisting period
      per offence shall be limited to three years subject to an overall maximum
      cumulative period of ten years for multiple offences. It is submitted that
B
      the respondent has completed a period of 4 ½ years of its blacklisting. It
      is submitted that therefore the order of blacklisting respondent –
      contractor permanently also deserves to be quashed and set aside.
            6.7 Making the above submissions and relying on the decisions of
      this Court in the cases of Erusian Equipment & Chemicals Ltd. Vs.
C     State of West Bengal and Anr. (1975) 1 SCC 70, Kulja Industries
      Limited Vs. Chief General Manager, Western Telecom Project
      Bharat Sanchar Nigam Limited and Ors. (2014) 14 SCC 731 and
      M/s. Daffodills Pharmaceuticals Ltd. & Anr. Vs. State of U.P. &
      Anr. 2019 (17) Scale 758, it is prayed to dismiss the present appeals
D     and/or in the alternative to reduce the period of blacklisting.
            7. We have heard learned counsel appearing on behalf of the
      respective parties at length.
             8. By the impugned judgment and order, the High Court has set
      aside the order passed by the Government of Odisha blacklisting the
E     respondent contractor mainly on the ground that the same was pre-
      determined and in breach of principles of natural justice.
             8.1 However, it is required to be noted that the action of blacklisting
      followed a high-level inquiry conducted by two members committee,
      Chief Engineer (Designs) and Chief Engineer (DPI & Roads). After
F     studying the contract provisions and drawings, as also inquiry on the
      spot and after a detailed consideration of the general behaviour and
      collapse of the formwork, a comprehensive report was submitted and
      the following observations were made in respect of the respondent –
      contractor: -
G            “(b) In respect of the Contractor
             (i)     The Contractor has not submitted the formwork design and
                     has adopted his own arrangement leading to such
                     occurrence of collapse of such huge structure during
                     construction. Design of the formwork is the responsibility
H                    of the Contractor and the Contractor shall also be entirely
 STATE OF ODISHA & ORS. v. M/S PANDA INFRAPROJECT LTD.                          191
                    [M. R. SHAH, J.]

              responsible for adequacy and safety of formwork,                  A
              notwithstanding any approval or review of drawing and
              design by the Engineer.
      (ii)    The Contractor has not ensured adequate safety measures
              during construction activities with which such unfortunate
              fatal accident could have been avoided, even in case of           B
              failure.
      (iii)   Quality assurance has not been emphasized as stipulated in
              the codes and manuals and as per the Agreement.
      (iv)    There are lot many deficiencies in workmanship that may
              affect the quality of work, as found in other formwork            C
              assemblies.”
       8.2 Thereafter, the State Government studied the report submitted
by a high-level committee and having considered the case of lapse on
the part of the contractor, a serious incident had taken place of collapse
of a ten meter slab and in the said incident, one person died and eleven        D
others were injured. Hence, a decision was taken to blacklist the
contractor after following the proceedings as per the OPWD Code.
Thereafter, a show cause notice was issued upon the respondent –
contractor and the respondent – contractor was called upon to show
cause as to why he be not blacklisted. The said show cause notice was           E
issued in terms of the provisions and the procedures in the OPWD Code.
The respondent – contractor replied to the same. After considering the
allegations in the show cause notice and the reply submitted by the
contractor, thereafter the Government passed an order of blacklisting.
Merely because the show cause notice was issued after the inquiry
committee report was considered and thereafter the State Government             F
took the decision to initiate proceedings for blacklisting, that by itself it
cannot be said that the order of blacklisting was pre-determined as
observed by the High Court. The communication dated 10.10.2017 by
the State Government to the Chief Engineer can be said to be a proposed
decision to initiate the proceedings for blacklisting. In the communication     G
dated 10.10.2017, it has been specifically mentioned that the action be
taken for blacklisting after following the procedure as per the OPWD
Code. Before any show cause notice is issued for any action when a
tentative decision is taken, it cannot be said that subsequent decision
followed by a show cause notice and the proceedings as per the OPWD
Code can be said to be pre-determined. Before initiation of any                 H
192             SUPREME COURT REPORTS                            [2022] 2 S.C.R.


A     proceedings for blacklisting, there can be a tentative decision on the
      basis of the material available forming a tentative/prima facie opinion
      that action is required. In the instant case a committee submitted a detailed
      report which was the basis for issuance of the show cause notice to the
      respondent. The action initiated against the respondent was not in a
      vacuum but after considering the committee’s report and after following
B
      the due procedure as required. Therefore, the High Court has erred in
      holding that the blacklisting order was pre-determined.
             8.3 So far as the findings recorded by the High Court that the
      blacklisting order was in breach of principles of natural justice is
      concerned, it is to be noted that the blacklisting order was passed after
C     issuing a show cause notice to which the contractor – respondent was
      called upon to reply and show cause as to why he be not blacklisted. A
      detailed show cause notice was issued with specific allegations to which
      the respondent – contractor submitted a detailed reply. After considering
      the allegations in the show cause notice, considering the reply and also
D     by considering the material available on record the order of blacklisting
      was passed. We fail to appreciate, how in such a case the blacklisting
      order can be said to be in breach of principles of natural justice.
              8.4 In the case of Grosons Pharmaceuticals (P) Ltd. & Anr.
      v. State of U.P., (2001) 8 SCC 604, the order of blacklisting was
E     challenged by the contractor on the ground that the contractor was not
      supplied with all the materials on the basis of which charges against him
      were based. It was the case on behalf of the contractor that non-supply
      of such material resulted in violation of principles of natural justice. To
      that, this Court observed that it was sufficient requirement of law that
      an opportunity of show cause was given to the appellant before it was
F     blacklisted. This Court observed that the contractor was given an
      opportunity to show cause and it did reply to the show-cause to the State
      Government and therefore the procedure adopted by the Government
      while blacklisting the contractor was in conformity with the principles of
      natural justice.
G            8.5 In the present case as observed hereinabove, show cause
      notice was issued upon the contractor by which the contractor was called
      upon to show cause why he be not blacklisted; the show cause notice
      was replied to by the contractor and thereafter, after considering the
      material on record and the reply submitted by the contractor and having
H     found the serious lapses which led to a serious incident in which one
 STATE OF ODISHA & ORS. v. M/S PANDA INFRAPROJECT LTD.                         193
                    [M. R. SHAH, J.]

person died and eleven others were injured, the State Government took          A
a conscious decision to blacklist the contractor. Therefore, it cannot be
said the order blacklisting the contractor was in violation of principles of
natural justice.
       8.6 As observed by this Court in the case of Gorkha Security
Services v. Govt. (NCT of Delhi) & Ors., (2014) 9 SCC 105, the                 B
fundamental purpose behind the serving of a show-cause notice is to
make the noticee understand the precise case set up against him which
he has to meet. This would require the statement of imputations detailing
out the alleged breaches and defaults he has committed, so that he gets
an opportunity to rebut the same. Another requirement is the nature of
action which is proposed to be taken for such a breach.                        C

       8.7 As per the law laid down by this Court in a catena of decisions
“debarment” is recognised and often used as an effective method for
disciplining deviant suppliers/contractors who may have committed acts
of omission and commission. It is for the State or appropriate authority
to pass an order of blacklisting/debarment in the facts and circumstances      D
of the case. Therefore, the High Court has erred and has exceeded its
jurisdiction in exercise of powers under Article 226 of the Constitution
of India by quashing and setting aside the blacklisting order, that too,
without adverting to the serious allegations and the act of omission and
commission on the part of the contractor which led to a serious incident       E
of collapse of ten meter slab while concrete work of the deck was going
on and due to which one person died and eleven others were injured. It
was specifically found that the safety arrangements were lacking severely
in the construction work zone. It was also found that quality assurance
was not emphasised as stipulated in the codes and manuals and as per
the Agreement. Therefore, the High Court ought to have considered the          F
seriousness of the incident in which due to omission and commission on
the part of the contractor in constructing the flyover one person died and
eleven others were injured.
      9. The next question which is posed for consideration of this Court
is, whether, in the facts and circumstances of the case the contractor         G
was required to be debarred/blacklisted permanently?
      9.1 In the case of Kulja Industries Limited (supra), this Court
has observed that “debarment” is never permanent and the period of
debarment would invariably depend upon the nature of the offence
committed by the erring contractor.                                            H
194             SUPREME COURT REPORTS                            [2022] 2 S.C.R.


A             In the said decision this Court emphasised on prescribing guidelines
      by determining the period for which the blacklisting should be effective.
      It is observed and held by this Court that while determining the period
      for which the blacklisting should be effective, for the sake of objectivity
      and transparency it is required to formulate broad guidelines to be
      followed. It is further observed that different periods of debarment
B
      depending upon the gravity of the offences, violations and breaches may
      be prescribed by such guidelines. In the present case, after the order of
      blacklisting was passed, the State Government has formulated guidelines
      by O.M. dated 26.11.2021 which provides as under:-
            “The blacklisting period per offence shall be limited to 03 (Three)
C           years subject to an overall maximum cumulative period of 10 (Ten)
            years for multiple offences”
             However, we may observe that we do not approve of the guidelines
      issued by the State Government by O.M. dated 26.11.2021. Duration of
      blacklisting cannot be solely per offence. Seriousness of the lapse and
D     the incident and/or gravity of commission and omission on the part of the
      contractor which led to the incident should be the relevant considerations.
      In a given case, it may happen that the commission and omission is very
      grave and because of the serious lapse and/or negligence, a major incident
      would have taken place. In such a case, it may be the contractor’s first
E     offence, in such a case, the period/duration of the blacklisting/banning
      can be more than three years. However, as the said guidelines are not
      under challenge, we rest the matter there and leave it to the State
      Government to suitably amend and/or modify the said office
      memorandum. However, what we have observed above can be a guide
      while determining the period of debarment/blacklisting.
F
             In the instant case, it might be true that the offence was the first
      offence committed by the contractor. However, considering the
      seriousness of the matter that due to the omission and commission on
      the part of the contractor a serious incident had occurred as there was a
      collapse of a ten meter slab while constructing a flyover in which one
G     person died and eleven others injured, as such the contractor does not
      deserve any leniency. However, to debar him permanently can be said
      to be too harsh a punishment. But considering the subsequent O.M.
      dated 26.11.2021 reproduced hereinabove (to which as such we do not
      agree as observed hereinabove), we are of the opinion that if the
H     blacklisting is restricted to five years, it may be in the fitness of things.
 STATE OF ODISHA & ORS. v. M/S PANDA INFRAPROJECT LTD.                         195
                    [M. R. SHAH, J.]

       10. In view of the above discussion and for the reasons stated          A
above, present appeal, i.e., C. A.No. 1083 of 2022 is allowed in part.
The impugned judgment and order passed by the High Court quashing
and setting aside the order dated 12.12.2017 blacklisting the respondent
herein – contractor is hereby quashed and set aside. However, the period
of blacklisting is ordered to be restricted to five years from the date of
                                                                               B
passing of the order of blacklisting. Civil Appeal No.1083 of 2022 is
allowed to the aforesaid extent.
       In view of the order passed in Civil Appeal No.1083 of 2022, Civil
Appeal No.1084 of 2022 stands dismissed. In the facts and circumstances
of the case, there shall be no order as to costs.
                                                                               C

Devika Gujral                                           Appeals disposed of.




                                                                               D




                                                                               E




                                                                               F




                                                                               G




                                                                               H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "administrative law"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

STATE OF ODISHA & ORS. versus M/S PANDA INFRAPROJECT LIMITED — 2022 INSC 232 - Legal Desk AI