Created byFuzzy Cloud

Supreme Court of India

RELIANCE INFRASTRUCTURE LIMITEDversusSTATE OF MAHARASHTRA AND ORS.

Citation
2019 INSC 63
Decided
21 January 2019
Disposal
Disposed off

Holding

Regulation 44.2(d) of the MERC (Multi Year Tariff) Regulations, 2011 does not suffer from any constitutional or statutory infirmity, and the writ petition is maintainable, but the High Court’s dismissal of the petition on its merits is affirmed.

Summary

Reliance Infrastructure Ltd (RInfra) challenged Regulation 44.2(d) of the MERC (Multi Year Tariff) Regulations, 2011, which imposed a stricter Station Heat Rate (SHR) on its Dahanu thermal power station than on other units. RInfra filed a writ petition under Article 226 of the Constitution while an appeal against MERC’s order was pending before the Appellate Tribunal for Electricity (APTEL). The Bombay High Court dismissed the petition and imposed costs, holding the writ was an abuse of process. The Supreme Court held that the validity of regulations framed by a State Electricity Regulatory Commission can be tested only before a court, not before APTEL, and therefore the High Court was wrong to deem the writ non‑maintainable and to award costs. However, the Court found no constitutional or statutory infirmity in Regulation 44.2(d) and affirmed the High Court’s dismissal of the writ on its merits.

Issues considered

  • The maintainability of a writ petition under Article 226 challenging the validity of MERC Regulation 44.2(d) while an appeal was pending before APTEL.
  • Whether Regulation 44.2(d) is ultra vires, discriminatory, or violative of the National Tariff Policy and Article 14 of the Constitution.
  • Whether the Appellate Tribunal for Electricity has jurisdiction to decide on the validity of regulations framed under Section 181 of the Electricity Act, 2003.
  • Whether the regulation suffers from manifest unreasonableness or arbitrariness warranting judicial intervention.

Legislation cited

Subjects

Regulation validityElectricity lawStation Heat RateDiscriminationArticle 226Appellate Tribunal jurisdictionMulti‑Year TariffMERCManifest unreasonablenessStatutory interpretation

Judgment

886                      [2019]REPORTS
               SUPREME COURT    1 S.C.R. 886               [2019] 1 S.C.R.


A                RELIANCE INFRASTRUCTURE LIMITED
                                        v.
                   STATE OF MAHARASHTRA AND ORS.
                         (Civil Appeal No. 879 of 2019)
B                               JANUARY 21, 2019
                  [DR. DHANANJAYA Y CHANDRACHUD
                          AND HEMANT GUPTA, JJ.]
             MERC (Multi Year Tariff) Regulations, 2011 – Regn. 44.2(d) –
      Jurisdiction to decide validity of regulations – The grievance of the
C     appellant arises from the fact that regn. 44.2(d) prescribed a tighter
      standard for its thermal generating station Dahanu TPS as compared
      to other generating stations in the State – Petition filed by the
      appellant before Maharashtra Electricity Regulatory Commission
      (MERC) – Appellant requested for relaxation of the norms and to
D     bring it in the line with the normative Station Heat Rate (SHR) –
      MERC held that it had considered the norms for SHR based on the
      MYT regulations and it did not find any merit in altering the MYT
      norms for SHR – The appellant filed an appeal u/s.111 of the
      Electricity Act 2003 before the Appellate Tribunal for Electricity
      (APTEL) – Also, appellant instituted a Writ petition u/Art.226 of the
E     Constitution before the Bombay High Court for the purpose of
      challenging regn 44.2(d) which specifies a separate SHR for the
      Dahanu TPS as compared to other generating stations in the State
      – The High Court dismissed the Writ petition and imposed costs of
      Rs. 1 lakh on the appellant, and held that having approached the
F     Appellate Tribunal for Electricity, the appellant was not justified in
      moving the High Court u/Art.226 “on the same issue” when the
      Tribunal was in a position to provide adequate relief – On appeal,
      held: The position in law is established by the judgment of
      Constitution Bench in PTC India Limited case that while the Tribunal
      may decide upon a dispute involving the interpretation of a
G     regulation, for which an appeal under Section 111 of the Act would
      be maintainable, no appeal can lie before the Tribunal on the validity
      of a regulation – Thus, High Court was not right in holding that the
      Writ petition u/Art.226 was not maintainable – Indeed, a challenge
      to the validity of the regulations framed by the MERC could lie only
      before the High Court – Thus, the imposition of costs for having
H
                                         886
    RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                           887
                  MAHARASHTRA

adopted the remedy u/Art.226 was unjustified – However, there is          A
no infirmity in the impugned regulation and accordingly ultimate
conclusion of the High Court to dismiss the Writ petition u/Art.226
affirmed – Electricity Act, 2003 – ss.61, 82, 111 and 181 – MERC
(Terms and Conditions of Tariff) Regulations, 2005 – National Tariff
Policy, 2006 – Constitution of India – Art.226 – Jurisdiction.
                                                                          B
       MERC (Multi Year Tariff) Regulations, 2011 – Regn. 44.2(d)
– Validity of – Plea of discrimination by the appellant – The grievance
of the appellant arises from the fact that a tighter standard or norm
has been prescribed for its thermal generating station Dahanu TPS
as compared to other generating stations in the State – The
discrimination, according to the appellant, lied in a statutory           C
regulations determining the Station Heat Rate (SHR) – Held: The
power to frame regulations is of a legislative nature – The Central
Power Research Institute (CPRI) report was an input before the
Maharashtra Electricity Regulatory Commission (MERC) in carrying
out that exercise – MERC followed the statutory procedures laid           D
down for the determination of tariffs – It took into account factors
which it is mandated by the statute to consider – The National Tariff
Policy, suggestions of stakeholders as well as the assessment carried
out by the CPRI were duly considered – Thus, the present case does
not fall in the paradigm of manifest unreasonableness or
arbitrariness to warrant the interference of the Supreme Court –          E
Regulation 44.2(d) of the MERC (Multi Year Tariff) Regulations,
2011 does not suffer from any constitutional or statutory infirmity –
National Tariff Policy, 2006.
      On 04.02.2011, the MERC (Multi Year Tariff) Regulations,
2011 were notified. Regulation 44 provides norms for the                  F
operation of thermal generating stations. Regulation 44.2
stipulates gross station heat rates for existing generating stations.
The above regulation indicated that save and except for the
excluded categories set out in clauses (b), (c) and (d), the Station
Heat Rate (SHR) for existing coal based thermal generating                G
stations is pegged at a uniform level of 2450 kCal/kWh (for 200/
210/250 MW sets) and 2425 kCal/kWh (for 500 MW sets and
above). As opposed to the uniform criterion of 2450 kCal/kWh in
Regulation 44.2(a), the SHR for the Dahanu TPS was varied
between 2350 in financial year 2011-12 to 2370 in financial year
                                                                          H
888           SUPREME COURT REPORTS                      [2019] 1 S.C.R.


A     2015-16. It was this prescription of a more stringent SHR in the
      case of R-Infra’s Dahanu TPS which forms the focus of dispute in
      the present case.
            Disposing of the appeal, the Court
            HELD: 1. On the maintainability of the petition under Article
B     226 of the Constitution, the High Court, has overlooked the
      position in law established by the judgment of a Constitution
      Bench of this Court in PTC India Limited v Central Electricity
      Regulatory Commission. The Constitution Bench considered
      whether the Appellate Tribunal for Electricity has jurisdiction to
      decide upon the validity of the regulations framed by the Central
C
      Electricity Regulatory Commission (CERC). CERC has been
      entrusted with the power to frame regulations under Section 178
      of the Electricity Act 2003. The Constitution Bench held that the
      validity of a regulation framed under Section 178 can be tested
      only before the court exercising judicial review. While the
D     Tribunal may decide upon a dispute involving the interpretation
      of a regulation, for which an appeal under Section 111 of the Act
      would be maintainable, no appeal can lie before the Tribunal on
      the validity of a regulation. [Para 18][905-E-H]
            2. In view of the legal position settled by the Constitution
E     Bench, the High Court was not justified in disparaging the
      appellant for taking recourse to a constitutional remedy under
      Article 226. Indeed, a challenge to the validity of the regulations
      framed by the Maharashtra Electricity Regulatory Commission
      (MERC) could only lie before the High Court. Hence, the
      imposition of costs for having adopted the remedy under Article
F     226 was unjustified. There was no suppression of fact on the
      part of the appellant which had indicated the recourse it had taken
      in the appeal before the Tribunal, arising from its prayer for
      relaxation of the Station Heat Rate (SHR) norms before MERC.
      The plea before the Appellate Tribunal was for relaxation of the
G     SHR norms. The plea before the High Court was that the SHR
      fixed was discriminatory and ultra vires. Undoubtedly, if the
      appellant were to succeed before the Tribunal, it would perhaps
      obviate the challenge in the High Court. The appellant, did not
      press ahead with its plea before the Tribunal. Hence, the writ
      petition could not have been held not to be maintainable.
H     [Para 18][906-G-H; 907-A-B]
    RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                          889
                  MAHARASHTRA

       3. The substratum of the case of the appellant is founded         A
on a plea of discrimination. Simply put, the plea is founded on
the hypothesis that the Central Power Research Institute (CPRI)
report regarded the units of Dahanu TPS (DTPS) as identical to
Parli Unit 6 and Paras Unit 3 (of MSPGCL) and Trombay Unit 8
(of TPC-G). The observations contained in the Central Power
                                                                         B
Research Institute (CPRI) report must be read in their entirety.
The fact that the manufacturing specifications of the units may be
similar (assuming they are so) is only one aspect of the total range
of considerations which are required to be borne in mind under
the terms of the National Tariff Policy notified u/s. 3 of the
Electricity Act 2003. The tariff policy requires that the operating      C
norms should be efficient, relatable to past performance, capable
of achievement and progressively reflect increased efficiencies.
They may also take into consideration technical advancements,
fuel, vintage of equipment, nature of operations and the level of
service among other factors. Appellant laid emphasis on clause
                                                                         D
5.3(f) of the National Tariff Policy where it prescribes that the
operating parameters and tariffs should be at “normative levels”
only and not at the “lower of normative and actuals” except in
the case of those units governed by para 5.3(h)(2). This
submission will not, however, carry the case of the appellant any
further. Normative levels are those which are fixed by the               E
application of the standards guided by the terms of the tariff policy
while actual levels are those which have been achieved as a matter
of fact, in the past. The emphasis in the tariff policy is on creating
incentives for achieving higher efficiency in order to enable the
ultimate consumer to have the benefit of efficient operations.
                                                                         F
[Para 29][915-G-H; 916-A-D]
      4. MERC is an expert body which is entrusted with the
duty and function to frame regulations, including the terms and
conditions for the determination of tariff. The Court, while
exercising its power of judicial review, can step in where a case
of manifest unreasonableness or arbitrariness is made out.               G
Similarly, where the delegate of the legislature has failed to follow
statutory procedures or to take into account factors which it is
mandated by the statute to consider or has founded its
determination of tariffs on extraneous considerations, the Court
                                                                         H
890            SUPREME COURT REPORTS                       [2019] 1 S.C.R.


A     in the exercise of its power of judicial review will ensure that the
      statute is not breached. However, it is no part of the function of
      the Court to substitute its own determination for a determination
      which was made by an expert body after due consideration of
      material circumstances. [Para 30][917-F-G]
B            5. The power to frame regulations is of a legislative nature.
      The CPRI report was an input before the MERC in carrying out
      that exercise. MERC followed the statutory procedures laid down
      for the determination of tariffs. It took into account factors which
      it is mandated by the statute to consider. The national tariff policy,
      suggestions of stakeholders as well as the assessment carried
C     out by the CPRI were duly considered. Hence, the present case
      does not fall in the paradigm of manifest unreasonableness or
      arbitrariness to warrant the interference of this Court. It would
      be rather formulaic for the Court to accept that merely because
      DTPS was placed at par in the immediately previous period (2006-
D     07) and the period immediately succeeding (2016-20), that this
      must necessarily be extrapolated to the intervening period
      governed by the MYT Regulations 2011. A body which is
      entrusted with the task of framing subordinate legislation has a
      range of options including policy options. If on an appraisal of all
      the guiding principles, it has chosen a particular line of logic or
E     rationale, this Court ought not to interfere. [Para 31][918-D-F]
            5. Thus, this Court has come to the conclusion that
      regulation 44.2(d) of the MERC (Multi Year Tariff) Regulations,
      2011 does not suffer from any constitutional or statutory infirmity.
      However, the ultimate decision of the High Court to dismiss the
F     writ petition is affirmed. The High Court was not right in holding
      that the writ petition under Article 226 was not maintainable and
      accordingly the direction on the imposition of costs is set aside.
      However, this Court holds that there is no infirmity in the
      impugned regulation and accordingly affirm the ultimate
G     conclusion of the High Court to dismiss the writ petition under
      Article 226. [Para 32][918-F-H]
            PTC India Limited v. Central Electricity Regulatory
            Commission (2010) 4 SCC 603 : [2010] 3 SCR 609 –
            followed.
H
     RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                  891
                   MAHARASHTRA

        Transmission Corporation of Andhra Pradesh Ltd. v.                        A
        Sai Renewable Power Pvt. Ltd. (2011) 11 SCC 34 :
        [2010] 8 SCR 636; Association of Industrial Electricity
        Users v. State of Andhra Pradesh (2002) 3 SCC 711 :
        [2002] 2 SCR 273 – relied on.
                           Case Law Reference                                     B
        [2010] 3 SCR 609                     followed          Para 18
        [2010] 8 SCR 636                     relied on         Para 30
        [2002] 2 SCR 273                     relied on         Para 30
        CIVIL APPELLATE JURISDICTION: Civil Appeal No. 879 of                     C
2019.
      From the Judgment and Order dated 18.04.2016 of the High Court
of Judicature at Bombay in Writ Petition No. 2474 of 2013.
      P. Chidambaram, S. K. Rungta, Sr. Advs., Ms. Anjali Chandurkar,
                                                                                  D
Hasan Murtaza, Ms. Divya Anand, Kartik Anand, Alok Kumar, Ankur
Kashyap, Rajesh Kumar, A. V. Rangam, Buddy A. Ranganadhan,
Ms. Stuti Krishn, Ms. Deepa M. Kulkarni, Nishant R. Katneshwarkar,
Advs. for the appearing parties.
        The Judgment of the Court was delivered by
                                                                                  E
      DR. DHANANJAYA Y CHANDRACHUD, J. 1. Leave
granted.
       2. The validity of a tariff regulation framed by the Maharashtra
Electricity Regulatory Commission (MERC) was questioned before the
High Court of Judicature at Bombay. Bereft of jargon – both legal and             F
scientific – the plea of the appellant is of discrimination. The
discrimination, according to the appellant, lies in a statutory regulation
determining the Station Heat Rate. According to the appellant, its thermal
power station at Dahanu has been subjected to a more stringent norm
than other comparable units. MERC, it is asserted, breached the National
Tariff Policy 2006. The High Court held against the appellant both on             G
the maintainability of its writ petition under Article 226 of the Constitution
and on the merits of the challenge to the validity of the statutory regulation.
The case has thus travelled to this Court.

                                                                                  H
892                SUPREME COURT REPORTS                           [2019] 1 S.C.R.


A            3. The Electricity Act 2003 came into force on 10 June 2003.
      Electricity Regulatory Commissions constituted under Section 82 are
      empowered to frame regulations under Section 181, including the terms
      and conditions for determination of tariff under Section 611. The MERC
      framed the MERC (Terms and Conditions of Tariff) Regulations 20052
      for a period of five years, upto financial year 2010-11. The regulations,
B
      in so far as the appellant is concerned were extended for a further period
      of one year upto financial year 2011-12.
              4. Regulation 33.1.3 prescribed the Station Heat Rate (SHR).
      The SHR is the heat energy required to generate one unit of electrical
      energy. The SHR is significant because it represents the ratio between
C     heat input and the energy output. SHR has a co-relationship with
      efficiency: a higher SHR reflects comparative inefficiency while a
      reduction in the SHR is associated with increasing levels of efficiency.
      In the Tariff Regulations 2005, the gross SHR was defined in the following
      terms:
D               “33.1.3. Gross station heat rate
                (a) Gross station heat rate for coal-based generating stations
                                        200/210/250 MWsets   500 MWand above sets
                 During stabilization     2600 kCal/kWh         2550 kCal/kWh
E                Period
                 Subsequent period        2500 kCal/kWh         2450 kCal/kWh

             Note 1:
             In respect of 500 MW and above units where the boiler feed
F     pumps are electrically operated, the gross station heat rate shall be 40
      kCal/kWh lower than the station heat rate indicated above.
             Note 2:
             For generating stations having combination of 200/210/250 MW
      seats and 500 MW and above sets, the normative gross station heat rate
G     shall be the weighted average station heat rate.”
             In the above regulations, uniform norms were fixed for all coal
      based thermal generating stations, without any distinction between
      individual generating stations. The norm applicable to the Dahanu Thermal
      1
          Section 181(2)(zd)
      2
H         Tariff Regulations 2005
            RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                 893
          MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

          Power Station of the appellant was 2500 kCal/kWh. This norm also              A
          applied to other generating stations in the State of Maharashtra.
                 5. On 6 January 2006 the Union of India in the Ministry of Power
          notified the National Tariff Policy under Section 3 of the Electricity Act
          2003. The policy, inter alia, spelt out the general approach to be followed
          for the purpose of determining tariffs including operating norms for          B
          generating stations. Clause 4 of the policy laid out its objectives in the
          following terms:
                “(a) Ensure availability of electricity to consumers at reasonable
                and competitive rates;
                (b) Ensure financial viability of the sector and attract investments;   C
                (c) Promote transparency, consistency and predictability in
                regulatory approaches across jurisdictions and minimise
                perceptions of regulatory risks;
                (d) Promote competition, efficiency in operation and improvement
                                                                                        D
                in quality of supply.”
                 Clause 5.0 spells out the “general approach to tariff”. Clause 5(f)
          stipulates operating norms:
ve sets
                “(f) Operating Norms
Wh
                Suitable performance norms of operations together with incentives       E
                and dis-incentives would need be evolved along with appropriate
Wh
                arrangement for sharing the gains of efficient operations with the
                consumers. Except for the cases referred to in para 5.3 (h)(2),
                the operating parameters in tariffs should be at “normative levels”
                only and not at “lower of normative and actuals”. This is essential
                                                                                        F
                to encourage better operating performance. The norms should be
                efficient, relatable to past performance, capable of achievement
                and progressively reflecting increased efficiencies and may also
                take into consideration the latest technological advancements, fuel,
                vintage of equipments, nature of operations, level of service to be
                provided to consumers etc. Continued and proven inefficiency            G
                must be controlled and penalized. The Central Commission would,
                in consultation with the Central Electricity Authority, notify
                operating norms from time to time for generation and transmission.
                The SERC would adopt these norms. In case where operations
                have been much below the norms for many previous years, the
                                                                                        H
894            SUPREME COURT REPORTS                             [2019] 1 S.C.R.


A           SERCs may fix relaxed norms suitably and draw a transition path
            over the time for achieving the norms notified by the Central
            Commission.
            Operating norms for distribution networks would be notified by
            the concerned SERCs. For uniformity of approach in determining
B           such norms for distribution, the Forum of Regulators should evolve
            the approach including the guidelines for treatment of state specific
            distinctive features.”
            Clause 5 (h) adverts to the Multi Year Tariff:
            “(h) Multi Year Tariff
C
            (1) Section 61 of the Act states that the Appropriate Commission,
            for determining the terms and conditions for the determination of
            tariff, shall be guided inter-alia, by multi-year tariff principles. The
            MYT framework is to be adopted for any tariffs to be determined
            from April 1, 2006. The framework should feature a five-year
D           control period. The initial control period may however be of 3
            year duration for transmission and distribution if deemed necessary
            by the Regulatory Commission on account of data uncertainties
            and other practical considerations. In cases of lack of reliable
            data, the Appropriate Commission may state assumptions in MYT
E           for first control period and a fresh control period may be started
            as and when more reliable data becomes available.
            (2) In cases where operations have been much below the norms
            for many previous years, the initial starting point in determining
            the revenue requirement and the improvement trajectories should
            be recognised at “relaxed” levels and not the “desired” levels.
F
            Suitable benchmarking studies may be conducted to establish the
            “desired” performance standards. Separate studies may be
            required for each utility to assess the capital expenditure necessary
            to meet the minimum service standards…”
            6. In August 2009, MERC published a ‘draft approach paper’ for
G
      the purpose of enacting multi year tariff regulations for financial years
      2010-11 to 2014-15. On 23 October 2009, the appellant furnished its
      suggestions. In 2010, MERC commissioned a report from the Central
      Power Research Institute (CPRI) for ascertaining achievable
      performance parameters for thermal power plants in Maharashtra and
H
  RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                   895
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

to suggest improvements. CPRI carried out an independent assessment             A
in respect of the plant of the appellant (DTPS), Tata Power (Generation)
– TPCG, and Maharashtra State Power Generation Company Limited
(MSPGCL). According to the appellant, no recommendation was made
in respect of their plant since it was performing better than the prescribed
SHR.
                                                                                B
       7. In July 2010, MERC published another draft approach paper in
regard to the proposed multi year tariff regulations for financial years
2011-12 to 2015-16 together with draft regulations. On 26 October 2010,
the appellant made submissions on the draft approach paper. On 4
February 2011, the MERC (Multi Year Tariff) Regulations, 20113 were
notified. Regulation 2(32) defines the Gross Station Heat Rate thus:            C

          “(32) “Gross Station Heat Rate” means the heat energy input in
          kcal required to generate one kWh of electrical energy at generator
          terminals.”
       Regulation 44 provides norms for the operation of thermal                D
generating stations. Regulation 44.2 stipulates gross station heat rates
for existing generating stations in the following terms:
          “44.2 Gross Station Heat Rate - For existing Generating Stations:
          a) Existing Coal-based Thermal Generating Stations, other than
             those covered under clauses (b), (c) and (d), below:               E

                 200/210/250 MW sets        500 MW and above sets

                      2450 kcal/kW h              2425 kcal/kW h

          Note 1                                                                F

          In respect of 500 MW and above Units, where the boiler feed
          pumps are electrically operated, the gross Station Heat Rate shall
          be 40 kcal/kWh lower than the gross Station Heat Rate indicated
          above.
                                                                                G
          Note 2
          For Generating Stations having combination of 200/210/250 MW
          sets and 500 MW and above sets, the normative gross Station
          Heat Rate shall be the weighted average station heat rate.
3
    Tariff Regulations 2011                                                     H
896             SUPREME COURT REPORTS                        [2019] 1 S.C.R.


A            b) Thermal Generating Stations of Maharashtra State Power
                Generation Company Ltd. (MSPGCL):
                                                     K cal/kWh
      Year     Koradi Khaperkheda Chandrapur Nasik Bhusawal Paras     Parli
                                                            excluding excluding
B                                                           Unit      Unit
                                                            No.3      No.6
      FY 2010- 2965      2560        2617    2722    2734     3186      2745
      11
      FY 2011- 2975      2568        2626    2731    2742     3199      2753
      12
C     FY 2012- 2985      2575        2635    2740    2751     3212      2762
      13
      FY 2013- 2873      2424        2539    2664    2671     3225      2679
      14
      FY 2014- 2881      2429        2544    2670    2677     3237      2684
      15
      FY 2015- 2889      2433        2549    2677    2683     3250      2690
D     16
             Provided that the Commission may revise the norms for heat rate
             for the above mentioned Generating Stations in case of Renovation
             & Modernisation undertaken for the Generating Station.
             c) Thermal Generating Units of the Tata Power Company Ltd.
E
                Generation Business (TPC-G):
                                                              K cal/kWh
              Year               Unit-4     Unit-5     Unit-6
                                                       With Oil & Gas
F                                                      mix.i n
                                                       proportion  of
                                                       50:50*
                  FY 2011-12       2570      2575             2519
                  FY 2012-13       2576      2583             2524
                  FY 2013-14       2581      2591             2529
G                 FY 2014-15       2586      2573             2534
                  FY 2015-16       2591      2581             2539
             * In case variation in Oil and Gas mix is more than +/- 5%, the
             Heat Rate for Unit 6 shall be approved considering the actual Oil
             and Gas Mix.
H
        RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                    897
      MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

                d) Thermal Generating Station of Reliance Infrastructure Ltd.-         A
                   Generation Business (RInfra-G):
                                                   K cal/kWh

                               Year              Dahanu TPS
                          FY 2011-12                 2350                              B
                          FY 2012-13                 2355
                          FY 2013-14                 2360
                          FY 2014-15                 2365
                          FY 2015-16                 2370
                                                                                       C
                                                                          ”
             8. The above regulation indicates that save and except for the
      excluded categories set out in clauses (b), (c) and (d), the SHR for
      existing coal based thermal generating stations is pegged at a uniform
      level of 2450 kCal/kWh (for 200/210/250 MW sets) and 2425 kCal/kWh
                                                                                       D
      (for 500 MW sets and above). The excluded categories are the generating
      stations of (i) MSPGCL; (ii) TPC – G; and (iii) RInfra-G. As the table in
      clause (b) of Regulation 44.2 indicates, a relaxed standard for the SHR
      has been prescribed for the units of MSPGCL. However, there is an
      exclusion within the exclusion for Unit 3 at Paras and Unit 6 at Parli,
      since these units are governed by the uniform criterion prescribed in            E
      clause (a). The dispensation for Units 4, 5 and 6 of TPC-G is prescribed
      in clause (c). For Unit 8 of TPC-G, the applicable SHR is in terms of the
      uniform rate of 2450 kCal/kWh, since this unit is not specified in clause (c).
Gas          9. The grievance of the appellant arises from the fact that a tighter
      standard or norm has been prescribed for its Dahanu TPS. As opposed              F
 of   to the uniform criterion of 2450 kCal/kWh in Regulation 44.2(a), the
      SHR for the Dahanu TPS varies between 2350 in financial year 2011-12
      to 2370 in financial year 2015-16. Essentially, it is this prescription of a
      more stringent SHR in the case of R-Infra’s Dahanu TPS which forms
      the focus of dispute in the present case.
                                                                                       G
             10. In order to buttress its grievance of discrimination, the appellant
      has relied upon the Multi Year Tariff regulations notified by MERC for
      the previous period (2005-10) and for the subsequent period (2016-21).
      The MERC (Multi Year Tariff) Regulations 20154 which govern the
      4
          Tariff Regulations 2015
                                                                                       H
898            SUPREME COURT REPORTS                          [2019] 1 S.C.R.


A     period 1 April 2016 to 31 March 2020 place the Dahanu TPS of RInfra-
      G at par with other coal-based thermal generating stations. Regulation
      44.4 is in the following terms:
            “44.4 Gross Station Heat Rate for existing coal-based thermal
            Generating Stations, other than those covered under Regulation
B           44.5 and 44.6 shall be:

           200/210/250 MW            300 MW sets         500 MW sets (sub-
                 sets                                     critical boilers)
            2450 kcal/kWh           2400 kcal/kWh          2375 kcal/kWh

C           Note 1
            In respect of 500 MW Units, where the boiler feed pumps are
            electrically operated, the Gross Station Heat Rate shall be 40 kcal/
            kWh lower than the gross Station Heat Rate specified above.
            Note 2
D
            For Generating Stations having combination of 200/210/250 MW
            sets and 300 MW and 500 MW sets, the normative gross Station
            Heat Rate shall be weighted average Station Heat Rate.”
            Regulation 44.5 contains the SHR for the coal based thermal
E     generating stations of MSPGCL. Regulation 44.6 specifies the SHR for
      TPC-G. Regulations 44.5 and 44.6 are extracted below:
            “44.5 Gross Station Heat Rate for existing coal-based thermal
            Generating Stations of Maharashtra State Power Generation
            Company Ltd. (MSPGCL) shall be:
F




G

            Provided that the Commission may revise the Gross Station Heat
            Rate norms for these Generating Stations in case any Renovation
            & Modernization is undertaken.

H
            RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                 899
          MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

                44.6 Gross Station Heat Rate for existing thermal Generating            A
                Stations of The Tata Power Company Ltd- Generation Business
                (TPC-G) shall be:



                                                                                        B
s (sub-
ilers)
kWh

                                                                                        C
                *In case variation in Oil and Gas mix is more than +/- 5%,
                the Gross Station Heat Rate for Unit 6 shall be approved
                considering the actual Oil and Gas Mix.”
                 In Regulation 44.5, Units 4 and 5 at Bhusawal and Units 6 and 7
          at Parli have been excluded. Similarly, Unit 8 for TPC-G is excluded          D
          from the SHR in Regulation 44.6.
                 11. In order to complete the narration, it may be noted that on 2
          September 2011, MERC passed an order on a petition filed by the
          appellant for deferring the implementation of the MYT regulations. On
          5 May 2012, the appellant submitted a petition for approval of its business   E
          plan for financial years 2010-11 to 2015-16. The appellant requested
          that the norm should be relaxed and brought in line with the normative
          SHR. On 25 October 2012, MERC passed an order on the MYT
          Business Plan for RInfra-G stating that it had considered the norms for
          SHR based on the MYT regulations. MERC held thus:
                                                                                        F
                “Station heat rate
                4.5.2
                RInfra-G submitted that MYT Regulations, 2011 framed the norms
                for DTPS based on the plant’s historical performance. RInfra-G
                submitted that it believes that all operating parameters, “norms”       G
                including the secondary oil consumption, auxiliary energy
                consumption, station heat rate and transit loss should be specified
                to create a level playing field and bring discipline for regulated
                entities for the benefit of beneficiaries of the state. RInfra-G
                submitted that the essence of the norms should be to create
                                                                                        H
900      SUPREME COURT REPORTS                          [2019] 1 S.C.R.


A     benchmarks based on industry-wide performance and let the
      market to reward or penalize the performance of the utilities vis-
      à-vis those benchmarks. RInfra-G further submitted that such
      mechanism will not only force underperforming utilities to perform
      but also bring the competitive price of power in the market in
      overall benefit of consumers.
B
      4.5.3
      In its Petition under Case No.45 of 2011, RInfra-G had raised the
      issue of specifying separate norms for SHR of DTPS in the MYT
      Regulations, 2011 and argued that any norm for generating stations
C     should be made based on performance of the industry as a whole
      and should not be specific to a plant based on its historical
      performance.
      4.5.4
      RInfra-G submitted that specific relaxations from the norms can,
D     however, be provided considering the specific issues of any given
      plant. In the said Petition, RInfra-G also highlighted the SHR norms
      adopted by other Regulatory Commissions to bring out its point
      that the SHR norms should be linked with unit size and ageing and
      not driven by the performance of the generating company. RInfra-
E     G further added that the tightening of the norms for efficient
      generating plant is against the principle of equality and rewarding
      efficiency.
      4.5.5
      Accordingly, RInfra-G has requested the Commission not to tighten
F     the norms for DTPS and retain it at industrial normative level of
      2450 kCal/kWh. RInfra-G submitted that the Commission, in its
      Order in Case No.45 of 2011 dated 2 September, 2011 on the said
      Petition did not provide any specific ruling on the said contention
      of RInfra-G; however stated that the Commission could invoke
      its powers alter the MYT norms for SHR and OEM cost, if
G
      required.
      4.5.6
      The Commission is of the view that norms can be fixed station
      wise based on the historical performance of the plant. The SHR
H
  RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                 901
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

      of the plant is dependent on the age of the plant, the technology       A
      used, the capital expenditure incurred overhauling the plant, regular
      repair and maintenance expenditure incurred and various other
      factors. Hence, there could be wide variations on SHR across
      plants. Further, if the Commission derives the benchmark
      considering only the industry-wide performance capital and
                                                                              B
      operating expenditures incurred, the generating company may not
      have sufficient motivation to continue to operate as efficiently as
      it had been in the past. Therefore, a balanced approach is to provide
      a target which will adequately motivate the generating plant to
      perform at existing levels or better and still have room for earning
      incentives. Moreover, the MYT Regulations, 2011 have been               C
      finalised after following appropriate regulatory process after
      considering and deliberating on the views of all stakeholders on
      various issue. Considering all the facts discussed above, the
      Commission does not find any merit in altering the MYT norms
      for SHR. Therefore, though RInfra-G has proposed a SHR of
                                                                              D
      2,450 kCal/kWh, the Commission has considered the SHR as per
      the MYT Regulations, 2011.
      4.5.7
      For FY 2011-12, the Commission has considered the SHR as
      approved in the ARR Order in Case No.163 of 2011. The SHR               E
      approved by the Commission for RInfra-G for the second control
      period is as below:
      Table 5: Approved station heat rate for the second control
      period
                                                                              F
                                                                       “




                                                                              G


      12. On 7 December 2012, the appellant filed an appeal under
Section 111 of the Electricity Act 2003 before the Appellate Tribunal for
Electricity (APTEL) against the order dated 25 October 2012. The
                                                                              H
902             SUPREME COURT REPORTS                            [2019] 1 S.C.R.


A     appellant submitted that the MERC ought to have exercised its power
      under Regulations 99 and 100 of the Tariff Regulations 2011 to amend
      and remove difficulties since the SHR which was prescribed for Dahanu
      TPS was not the same as for similarly situated generating units.
             13. On 3 October 2013, the appellant instituted a writ petition
B     under Article 226 of the Constitution before the Bombay High Court for
      the purpose of challenging Regulation 44.2(d) which specifies a separate
      SHR for the Dahanu TPS as compared to other generating stations in
      the State of Maharashtra. The appellant disclosed the pendency of the
      appeal before the Tribunal against MERC’s order dated 25 October
      2012 disallowing the prayer for relaxing the norms.
C
             14. MERC opposed the writ petition. MERC submitted that the
      appellant had filed a substantive petition seeking approval of its business
      plan for the financial years 2010-11 to 2015-16 and an SHR of 2450
      kCal/kWh for 2012-13 to 2015-16. MERC in the course of its adjudication
      on the business plan had adopted the same SHR as under the tariff
D     regulations. MERC contended that since the appeal before the Tribunal
      was pending, the appellant was not entitled to pursue a remedy under
      Article 226 of the Constitution.
             15. The Appellate Tribunal for Electricity disposed of the appeal
      on 8 April 2015, recording that it did not survive in view of the institution
E     of the writ proceedings before the Bombay High Court. The appellant
      asserts that it drew the attention of the High Court, when the writ petition
      was being heard, to the fact that the appeal before the Tribunal was not
      pending and had been disposed of.
             16. The High Court by its judgment dated 18 April 2016 dismissed
F     the writ petition. In coming to the conclusion that the petition was lacking
      in merit, the High Court came to the following conclusions:
             (i) MERC in framing statutory regulations in exercise of the power
      conferred by Section 181 had followed the procedure by granting an
      opportunity to stake holders including the appellant to make their
G     suggestions on the draft approach paper which was published on the
      basis of the CPRI report;
            (ii) CPRI was commissioned to undertake a study in order to fix
      norms for SHR for different power stations in the State of Maharashtra
      and it was only after the technical material collated by CPRI was
H
  RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                     903
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

considered and reviewed that the tariff regulations were notified                 A
prescribing SHR norms for various power stations;
       (iii) MERC has applied the principles evolved in the tariff policy
which stipulates that the operating norms should be “efficient, relatable
to past performance, capable of achievement and progressively reflect
increased efficiencies”. The past performance of the Dahanu TPS of                B
the appellant was also taken into consideration;
      (iv) The submissions urged by the appellant was not accepted for
two reasons which were formulated by the High Court as follows:
      “Firstly, if this submission is accepted then the whole exercise of
      undertaking an expert analysis, the working of each of the thermal          C
      power station to determine the SHR by studying various factors
      including the past performance would be rendered nugatory.
      Secondly the tariff standards are required to be fixed on realistic
      data and its consideration, as public interest is directly involved in
      fixation of the electricity tariff. The contention of the petitioner if     D
      accepted it would also result in a situation that the realistic standards
      are deviated to fix unrealistic or a camouflage norms. This is surely
      not permissible and is fundamentally against public interest being
      against the interest of the consumers of electricity. The submission
      of the petitioner is only from the sole consideration of profits of
      the petitioner, while disregarding the norms and standards required         E
      to be followed by the 2nd Respondent in determination of the
      electricity tariff.”
      (v) In the exercise of its jurisdiction under Article 226 of the
Constitution, the High Court cannot decide on technical parameters or
come to the conclusion that the norms fixed by MERC are inappropriate;            F
       (vi) The power to frame tariff regulations under Section 181 of
the Electricity Act 2003 is of a legislative character. The regulations
constitute subordinate legislation. Once MERC has followed appropriate
procedures mandated by the Electricity Act, the Court will not interfere
with the regulations merely on the ground that the SHR prescribed for             G
the power station of the appellant was fixed at a rate below its peers;
      (vii) Profitability of the producer is not the only consideration in
determining the SHR. The regulations are also framed in the interest of
the consumers of electricity; and
                                                                                  H
904            SUPREME COURT REPORTS                            [2019] 1 S.C.R.


A            (viii) Having approached the Appellate Tribunal for Electricity,
      the appellant was not justified in moving the High Court under Article
      226 “on the same issue” when the Tribunal was in a position to provide
      adequate relief. Entertaining a writ petition of this nature, when an
      alternate remedy is provided by the statute would render the statutory
      machinery under the Electricity Act nugatory. The petition under Article
B
      226 was held to be an abuse of process.
             While dismissing the petition, the High Court imposed costs of
      Rs 1 lakh on the appellant.
             17. While assailing the decision of the High Court,
C     Mr P Chidambaram, learned Senior Counsel, urged that the High Court
      was not justified in coming to the conclusion that in view of the pendency
      of the appeal before APTEL, recourse to the jurisdiction under Article
      226 constituted an abuse of process. Learned Senior Counsel submits
      that the pendency of the appeal before APTEL was disclosed in paragraph
      27 of the writ petition before the High Court:
D
            “27. As stated hereinabove, the Petitioners have preferred Appeal
            No.4 of 2013 before the Appellate Tribunal for Electricity
            challenging the Order dated 25 th October 2012 insofar as
            Respondent No.1 disallows the Petitioners prayer for relaxation
            of the norms under Regulations 99 and 100 of the MYT
E           Regulations. The present Petition challenges the vires, legality
            and validity of Regulation 44.2 (d) of the MYT Regulations that
            fixes SHR norms for the 1st Petitioners. Save as aforesaid, the
            Petitioners have not filed any other Petition in respect of the subject
            matter of the present Petition either before this Hon’ble Court or
F           any other High Court or the Supreme Court of India.”
             In response to the objection raised by MERC, the following assertion
      was contained in the rejoinder filed by the appellant before the High
      Court:
            “2.3. The Petitioners in the Petition have, inter alia, in paragraph
G           27 thereof disclosed to this Hon’ble Court that they have preferred
            Appeal No. 4 of 2013 before the Appellate Tribunal for Electricity
            challenging the order dated 25th October 2012 passed in Case
            No. 156 of 2011 which disallowed the Petitioners’ prayer for
            relaxation of the norms under Regulations 99 and 100 of the MYT
H
  RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                       905
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

         Regulations. It is settled law of the Hon’ble Supreme Court of             A
         India that the Appellate Tribunal for Electricity has no power,
         authority or jurisdiction to go into validity or legality of Regulations
         framed by a Regulatory Commission. Regulation 44.2 (d) has been
         challenged in the present Writ Petition and is not the subject matter
         of any other Petition or Appeal in any other Court as stated, inter
                                                                                    B
         alia, in paragraph 27 of the Petition. In fact, the Petitioners have
         enclosed at Exhibit-K to the Petition a copy of the Memorandum
         of Appeal without annexures. It is denied that there is any forum
         shopping. The said Appeal has since been heard by the Appellate
         Tribunal, in any event, was not pressed by the Petitioners at the
         final hearing of the Appeal. The grievance of Respondent No. 2,            C
         in any event, does not survive.”
       The submission of the appellant on the maintainability of the
proceedings under Article 226 is that the scope of the appeal before the
Tribunal was entirely different from the ambit of the writ petition. The
appellant moved the Tribunal against the order of MERC dated 25 October             D
2012 which disallowed the prayer for relaxation of the norms under
Regulations 99 and 100 of the Tariff Regulations 2011. The petition
challenged the vires of the regulations before the High Court and the
remedy before the High Court was the only remedy available to challenge
the validity of the regulations.
                                                                                    E
       18. On the maintainability of the petition under Article 226, the
High Court, in our view, has overlooked the position in law established
by the judgment of a Constitution Bench of this Court in PTC India
Limited v Central Electricity Regulatory Commission 5. The
Constitution Bench considered whether the Appellate Tribunal for
Electricity has jurisdiction to decide upon the validity of the regulations         F
framed by the Central Electricity Regulatory Commission. CERC has
been entrusted with the power to frame regulations under Section 178
of the Electricity Act 2003. The Constitution Bench held that the validity
of a regulation framed under Section 178 can be tested only before the
court exercising judicial review. While the Tribunal may decide upon a              G
dispute involving the interpretation of a regulation, for which an appeal
under Section 111 would be maintainable, no appeal can lie before the
Tribunal on the validity of a regulation. The summary of the findings in
the judgment includes, inter alia, the following:
5
    (2010) 4 SCC 603
                                                                                    H
906             SUPREME COURT REPORTS                             [2019] 1 S.C.R.


A           “(iii) A regulation under Section 178 is made under the authority
            of delegated legislation and consequently its validity can be tested
            only in judicial review proceedings before the courts and not by
            way of appeal before the Appellate Tribunal for Electricity under
            Section 111 of the said Act.
B           (iv) Section 121 of the 2003 Act does not confer the power of
            judicial review on the Appellate Tribunal. The words “orders”,
            “instructions” or “directions” in Section 121 do not confer the
            power of judicial review in the Appellate Tribunal for Electricity.
            In this judgment, we do not wish to analyse the English authorities
            as we find from those authorities that in certain cases in England
C           the power of judicial review is expressly conferred on the tribunals
            constituted under the Act. In the present 2003 Act, the power of
            judicial review of the validity of the regulations made under Section
            178 is not conferred on the Appellate Tribunal for Electricity.
            (v) If a dispute arises in adjudication on interpretation of a regulation
D           made under Section 178, an appeal would certainly lie before the
            Appellate Tribunal under Section 111, however, no appeal to the
            Appellate Tribunal shall lie on the validity of a regulation made
            under Section 178.”
      Hence the conclusion of the Court is in the following terms:
E
            “The Appellate Tribunal for Electricity has no jurisdiction to decide
            the validity of the Regulations framed by the Central Electricity
            Regulatory Commission under Section 178 of the Electricity Act,
            2003. The validity of the Regulations may, however, be challenged
            by seeking judicial review under Article 226 of the Constitution of
F           India.”
             Though the above principles emerge in the context of regulations
      framed under Section 178 by the CERC, the logic of the judgment extends
      to the regulations framed under Section 181 by the State Electricity
      Regulatory Commissions. In view of the legal position settled by the
G     Constitution Bench, we are of the clear view that the High Court was
      not justified in disparaging the appellant for taking recourse to a
      constitutional remedy under Article 226. Indeed, a challenge to the validity
      of the regulations framed by the MERC could only lie before the High
      Court. Hence, the imposition of costs for having adopted the remedy
      under Article 226 was unjustified. There was no suppression of fact on
H
  RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                     907
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

the part of the appellant which had indicated the recourse it had taken in        A
the appeal before the Tribunal, arising from its prayer for relaxation of
the SHR norms before MERC. The plea before the Appellate Tribunal
was for relaxation of the SHR norms. The plea before the High Court
was that the SHR fixed was discriminatory and ultra vires. Undoubtedly,
if the appellant were to succeed before the Tribunal, it would perhaps
                                                                                  B
obviate the challenge in the High Court. The appellant, as learned Senior
Counsel informed the court, did not press ahead with its plea before the
Tribunal. Hence, the writ petition could not have been held not to be
maintainable.
       19. The High Court has dealt with the merits of the challenge to
the validity of the regulations. The constitutional validity of Regulation        C
44.2(d) of the Tariff Regulations 2011 is the subject of the challenge in
these proceedings. The basic challenge which has been addressed before
the Court is founded on a plea of discrimination. Elaborating on this
challenge, Mr P. Chidambaram, learned Senior Counsel urged the
following submissions:                                                            D
        (i) Regulation 44.2(d) is contrary to the national tariff policy. While
framing regulations under Section 181, MERC is required by Section
61(i) to be guided by the “National Electricity Policy and tariff policy”.
Clause 5.3(f) of the national tariff policy notified on 6 January 2006 by
the Union Ministry of Power requires that operating parameters and                E
tariffs should be at “normative levels” only and not at “lower of normative
and actuals”. Regulation 44.2(d) lays down a more stringent SHR for
the appellant, based on its energy efficient performance by disregarding
the normative levels;
       (ii) The CPRI report, which was commissioned by MERC contains              F
the following conclusions on the comparability of RInfra’s Dahanu TPS
with Paras Unit 3 and Parli Unit 6 (of MSPGCL) and TPC-G Unit 8:
       “ii. DTPS units are identical to units installed at Parli Unit 6, Paras
       Unit 3 & Tata Trombay Unit 8. They are of the general or standard
       design of 250 MW duplicated by BHEL in nearly 25 units in India.           G
       iii. Both DTPS units have operating margins of 8% steam flow in
       the boiler side (BMCR flow), 5% power output on the turbine
       side (VWO flow) and 16% on the generator side (capability curve)
       and 23% on the generator transformer side. These margins are
       provided in all 250 BHEL supplied units, including those at Paras
                                                                                  H
908            SUPREME COURT REPORTS                          [2019] 1 S.C.R.


A           Unit 3, Parli Unit 6 and Tata Trombay Unit 8 as elaborated in the
            text.”
      Moreover, the CPRI report observes that:
            “vii. Combining all the margins provided by the OEM, R-Infra has
            been able to load the unit to 268 MW against the design value of
B           250 MW. Maintaining this load is not harming the life of the unit
            as the DTPS has ensured that all parameters are kept within OEM
            limits. High loadability is made possible by high energy efficiency
            or low unit heart rate of the unit. When the deviation of the unit
            heat rate from the design heart rate is low, heat generation in the
C           equipment is low which enables the parameters not to exceed
            their limits. As many as 66 units in India have clocked average
            annual plant loading in excess of 100% UMCR in 2007-08.”
             R Infra’s Dahanu TPS unit has been found to be identical to Parli
      Unit 6, Paras unit 3 (MSPGCL) and Trombay unit 8 (of Tata power).
D     The units have the same design, standard and OEM. Therefore, merely
      because the appellant has performed better, this would not be a ground
      to subject it to more stringent norms;
             (iii) In any event, for the next control period – 2016-20, the
      appellant has been equated with other thermal power stations. There
E     exists no justifiable reason for making a distinction for the period 2011-
      16 and for imposing more stringent norms for SHR in the case of DTPS.
      In imposing more stringent norms on the appellant for its DTPS unit for
      2011-16, MERC has acted in an arbitrary exercise of power which violates
      Article 14 of the Constitution; and

F           (iv) As a matter of fact, CPRI did not furnish a “trajectory” for
      the appellant’s DTPS unit, as assumed by the High Court. A trajectory
      was furnished for less efficient plants.
             20. On the other hand, contesting the submissions which were
      urged on behalf of the appellant, Mr SK Rungta, learned Senior Counsel
      for the respondents urged the following submissions:
G
            (i) The SHR represents heat energy required to generate one unit
      of electrical energy. The norm determines the cost of coal and
      corresponding gas that will be allowed to be recovered. Fixation of the
      SHR has an important bearing on the cost of energy which will be
      recovered from the consumer;
H
  RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                  909
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

       (ii) There is a fundamental error in the submission that the CPRI       A
report found an equivalence between the appellant’s Dahanu TPS with
Parli Unit 3 and Paras Unit 6 (of MSPGCL) and Trombay Unit 8 (of
Tata Power). CPRI found an equivalence of specifications and not of
performance. The dates on which the above three units commenced
operations were:
                                                                               B
      • Paras 3     31 March 2008;
      • Parli 6      1 November 2007;
      • TPC 8       31 March 2008.
      The appellant’s unit at Dahanu commenced operations in 1995.             C
CPRI has not, as a matter of fact, come to the conclusion that the
performance of DTPS was equivalent to Parli Unit 6, Paras Unit 3 and
Trombay Unit 8;
       (iii) The CPRI report has separately evaluated DTPS and the
units of Tata Power and MSPGCL. It is factually incorrect to posit that        D
the CPRI study was for Parli Unit 6, Paras Unit 3 and Trombay Unit 8;
      (iv) After the enactment of the Electricity Act 2003, the first MYT
regulations were promulgated in 2005. All units were placed at par in the
absence of a base line study at that stage;
       (v) Section 61(i) requires that the appropriate commission “shall       E
be guided by” the principles set out in the tariff policy. The tariff policy
enunciates the factors which have to be taken into account while framing
the tariff regulations;
       (vi) In the MYT regulations which governed the period 2011-16,
the sharing of gains occasioned by the SHR, between the producer and           F
the consumer, was in the ratio of 2/3:1/3. In the 2015 regulations, the
ratio of sharing has been altered and 2/3rd enures to the benefit of the
consumer; and
      (vii) The SHR delivered by the appellant for 2006-07 to 2009-10
would sufficiently explain the basis of fixation. The same principle has       G
been applied in the case of Tata power;
      (viii) Unless a subordinate legislation is found to suffer from
manifest unreasonableness or from a breach of the principle of
proportionality, it would not be regarded as ultra vires.
                                                                               H
910             SUPREME COURT REPORTS                             [2019] 1 S.C.R.


A            21. These submissions fall for our consideration.
              22. The power to determine tariffs is of a legislative nature. Section
      61 is borne in Part VII of the Electricity Act 2003 which deals with
      tariffs. Section 61 provides thus:
             “Section 61. Tariff regulations: The Appropriate Commission
B            shall, subject to the provisions of this Act, specify the terms and
             conditions for the determination of tariff, and in doing so, shall be
             guided by the following, namely:-
             (a) the principles and methodologies specified by the Central
             Commission for determination of the tariff applicable to generating
C            companies and transmission licensees;
             (b) the generation, transmission, distribution and supply of electricity
             are conducted on commercial principles;
             (c) the factors which would encourage competition, efficiency,
D            economical use of the resources, good performance and optimum
             investments;
             (d) safeguarding of consumer’s interest and at the same time,
             recovery of the cost of electricity in a reasonable manner;
             (e) the principles rewarding efficiency in performance;
E            (f) multi year tariff principles;
             (g) that the tariff progressively reflects the cost of supply of
             electricity and also reduces cross-subsidies in the manner specified
             by the Appropriate Commission;

F            (h) the promotion of co-generation and generation of electricity
             from renewable sources of energy;
             (i) the National Electricity Policy and tariff policy:
             Provided that the terms and conditions for determination of tariff
             under the Electricity (Supply) Act, 1948, the Electricity Regulatory
G            Commission Act, 1998 and the enactments specified in the
             Schedule as they stood immediately before the appointed date,
             shall continue to apply for a period of one year or until the terms
             and conditions for tariff are specified under this section, whichever
             is earlier.”
H
  RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                   911
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

       Section 61 provides that the appropriate commission shall, subject       A
to the provisions of the Act, specify the terms and conditions for the
determination of tariff. In doing so, it has to be guided by the
considerations which are stipulated in clauses (a) to (i). Among them, in
clause (i) is the national electricity policy and tariff policy.
        23. Section 181 empowers the state commissions to make                  B
regulations consistent with the Act and the rules to carry out the provisions
of the Act. Among the matters for which the regulations may provide
are “the terms and conditions for the determination of tariff under Section
61”6. In specifying the terms and conditions for the determination of
tariff, the appropriate commission (as Section 61 provides) “shall be
guided” by the factors which are set out in clauses (a) to (i). The             C
expression “shall be guided” comprises of two elements: the ‘shall’ and,
the ‘guidance’. Clauses (a) to (i) provide guidance to the commission in
specifying the terms and conditions for the determination of tariff. The
expression “shall” indicates that the factors which are specified in clauses
(a) to (i) have to be borne in mind by the appropriate commission. As           D
guiding factors, they provide considerations which are material to the
determination of tariffs by the appropriate commission.
       24. The national tariff policy has multi-faceted objectives.
Significant among them is the need to ensure to consumers the availability
of electricity at reasonable and competitive rates. The policy also seeks       E
to ensure the financial viability of the sector and underlines the need to
attract investments. A financially sustainable electricity sector is an
important facet of the overall regulatory framework. The objectives of
the policy emphasise the need to promote transparency, consistency and
predictability in regulatory approaches across jurisdictions. The policy
emphasises the need to minimise perceptions of regulatory risk. Finally,        F
the policy recognises the need to promote competition, efficiency in
operations and improvements in the quality of supply. In designing and
formulating the regulatory framework for tariffs, the delegate of the
legislature has to bring about a balance between the competing goals
which the tariff policy incorporates.                                           G
       25. As part of the process, the delegate has to bear in mind the
interests of diverse stake holders including consumers and producers.
The process of framing tariffs is of equal significance, for it is through
the procedural framework that norms of consistency, transparency and
6
    Section 181 (2)(zd)                                                         H
912            SUPREME COURT REPORTS                           [2019] 1 S.C.R.


A     predictability can be enforced. Competition, efficiency and quality of
      supply are key components of the policy framework in designing tariffs.
      Clause 5.3(f) of the tariff policy speaks of the need to evolve performance
      norms which incorporate incentives and disincentives and provide an
      appropriate arrangement that fosters the sharing of gains of efficiency
      in operations with consumers. Operating parameters in tariffs are
B
      required to be pegged only on a “normative level” and not at the “lower
      of normative and actuals”, save and except in those cases referred to in
      paragraph 5.3(h)(2). Paragraph 5.3(h)(2) deals with those cases where
      operations have been much below the norm for several previous years.
      In those cases, the initial starting point in determining the revenue
C     requirement and the trajectories are fixed at a relaxed level and not at
      desired levels. Under clause 5.3(f), the operating norms must fulfil
      several parameters. They must be (i) efficient; (ii) relatable to past
      performance; (iii) capable of achievement; and must progressively reflect
      increased efficiencies. They may also take into consideration latest
      technological advances, fuel, vintage of equipment, nature of operations,
D
      level of service to be provided to consumers, among other factors.
      Continuous and proven inefficiency has to be controlled and penalised.
      The operating norms must be designed to promote efficiency and to
      ensure that the gains which accrue on account of efficient operations
      are shared with the consumers of electricity. The operating norms will,
E     therefore, have due regard to the performance in the past as well as
      capacities for future achievement. These must be dovetailed with all
      relevant considerations, bearing on the requirements of the policy.
              26. The Tariff policy provides guidance to the appropriate
      commission when it frames regulations. The power to frame regulations
F     is legislative in nature. It is conferred upon the appropriate commission.
      The commission weighs numerous factors. Its discretion in carrying out
      a complex exercise cannot be constrained. The delegate of the legislature
      is therefore under a mandate to bring about a fair and equitable balance
      between competing considerations. Standing at the forefront of those
      considerations is above all the need to ensure efficiency and to protect
G     the interests of consumers. The submission which has been urged on
      behalf of the appellant would reduce tariff fixation to a rather simplistic
      process of bringing about equality between generating units which have
      the same design and manufacturing origin. Such an approach overlooks
      the complex factors which have to be borne in mind in the determination
H
  RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                913
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

of tariffs. The submission which has been urged on behalf of the appellant   A
is based on the hypothesis that the CPRI report underlined the similarity
of Parli Unit 6, Paras Unit 3, Tata Trombay Unit 8 and the DTPS unit of
the appellant. At the highest, the CPRI study would indicate a similarity
of specifications but not a similarity of performance. Performance, as
we have seen, is a critical element in designing an appropriate SHR.
                                                                             B
The SHR has an important co-relationship with efficiency. The CPRI
report indicates a detailed analysis of RInfra’s DTPS. Specifically, in
the context of DTPS, it observed:
      “vii. Combining all the margins provided by the OEM, R-Infra has
      been able to load the unit to 268 MW against the design value of
      250 MW. Maintaining this load is not harming the life of the unit      C
      as the DTPS has ensured that all parameters are kept within OEM
      limits. High loadability is made possible by high energy efficiency
      or low unit heart rate of the unit. When the deviation of the unit
      heat rate from the design heart rate is low, heat generation in the
      equipment is low which enables the parameters not to exceed            D
      their limits. As many as 66 units in India have clocked an average
      annual plant loading in excess of 100% UMCR in 2007-08.”
      The CPRI report similarly contained an analysis of Units 5 and 6
of TPC-G and of MSPGCL units. CPRI conducted studies on Units 1
and 2 of R Infra’s DTPS. In its counter affidavit, MERC has tabulated        E
the SHR achieved by DTPS for financial years 2006-07 to 2009-10 as
follows:
     “Table No: 2 SHR achieved by DTPS from FY 2006-07 to
FY 2009-10
     Year                Station Heat Rate (SHR) (kcal /kWh)                 F
                RInfra’s Submission    MERC Approved         DTPS
                    in Petition                            Achieved
  FY 2006-07           2315                   2500           2278
  FY 2007-08           2500                   2500           2279
  FY 2008-09           2500                   2500           2300
                                                                             G
  FY 2009-10           2500                   2500           2293
                                                                        “
      It has been explained that to anticipate the SHR for financial year
2011-12 till financial year 2015-16, the actual heat rate achieved during
the previous years and predicted deviation due to factors such as            H
914            SUPREME COURT REPORTS                           [2019] 1 S.C.R.


A     reduction in boiler efficiency due to coal energy degradation and average
      annual aging loss were considered. The anticipated SHR for DTPS for
      financial years 2011-12 to 2015-16 was computed in the following manner:
            “SHR = 2292* + (Reduction in Boiler Efficiency + Coal Quality
            Degradation + Annual Ageing Loss) = 2350 kCal/kWh.
B           (* Station Heat Rate of 2292 kCal/kWh was taken from CPRI
            Test Reports of March, 2010.)”
             On a similar basis, CPRI carried out technical studies for Units 5
      and 6 of TPC-G. The SHR achieved by TPC-G Unit 5 (coal fired) from
      2006-07 and 2008-09 was computed. On this basis, the SHR, projected
C     as an achievable heat rate, was computed and an approved trajectory
      for Unit 5 for financial years 2011-12 to 2015-16 was laid down. Similarly,
      in respect of Unit 6 of TPC-G, CPRI studies indicated the SHR achieved
      for financial years 2006-07 to 2009-10. CPRI projected a heat rate on
      the basis of fuel oil firing and fuel gas firing. On the basis of the CPRI
D     report, MERC arrived at its findings for TPC-G Units 5 and 6. In this
      regard, it has been demonstrated in the counter affidavit that there was
      no discrimination in the methodology followed and the same principle
      was uniformly applied.
             27. The attention of the Court has also been drawn to the fact
E     that the Tariff Regulations 2011 contained a stipulation in clause 14 for
      the sharing of gains or losses on account of controllable factors. Clause
      14 provides as follows:
            “14 Mechanism for sharing of gains or losses on account of
            controllable factors:
F           14.1 The approved aggregate gain to the Generating Company or
            Transmission License or Distribution License on account of
            controllable factors shall be dealt with in the following manner:
            (a) One-third of the amount of such gain shall be passed on as a
            rebate in tariff over such period as may be stipulated in the Order
G           of the Commission under Regulation 11.6;
            (b) The balance amount, which will amount to two-third of such
            gain, may be utilised at the discretion of the Generating Company
            or Transmission License or Distribution License.”

H
  RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                915
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

       [The expression ‘controllable factors’ is explained in clause 12.2    A
of the regulations.]
       28. Under the Tariff Regulations 2011, the approved aggregate
gain to the generating company was to be shared: one-third was required
to be passed on as a rebate in tariff while the balance of two-thirds
would be utilised at the discretion of the generating company. On the        B
other hand, in the Tariff Regulations 2015, Regulation 11 contains a
corresponding mechanism for the sharing of gains on account of
controllable factors. Regulation 11 is in the following terms:
      “11 Mechanism for sharing of gains or losses on account of
      controllable factors:                                                  C
      11.1 The approved aggregate gain to the Generating Company or
      Licensee or MSLDC on account of controllable factors shall be
      dealt with in the following manner:
      (a) Two-third of the amount of such gain shall be passed on as a
      rebate in Tariff over such period as may be stipulated in the Order    D
      of the Commission under Regulation 8.4;
      (b) The balance amount of such gain shall be retained by the
      Generating Company or Licensee or MSLDC.”
       While in the Regulations of 2011, one-third of the aggregate gain
                                                                             E
was to be passed on in the form of a rebate in tariff and the balance
two-thirds was to be utilised by the generating company at its discretion,
in the 2015 regulations, the proportion has been reversed. In the 2015
regulations, two-thirds of the amount of the gain is required to be passed
on as a rebate in tariff while the balance shall be retained by the
generating company. The interests of the consumer are required to be         F
borne in mind under the terms of the tariff policy consistent with Section
61. In its expert judgment, the Commission, while formulating the 2015
regulations mandated that an enhanced ratio of the aggregate gain would
be passed on in the form of a rebate on the tariff. This could have
legitimately been borne in mind as a relevant consideration in evaluating
                                                                             G
what should be appropriately fixed as the SHR for the period in question.
       29. The substratum of the case of the appellant is founded on a
plea of discrimination. Simply put, the plea is founded on the hypothesis
that the CPRI report regarded the units of DTPS as identical to Parli
Unit 6 and Paras Unit 3 (of MSPGCL) and Trombay Unit 8 (of TPC-
                                                                             H
916               SUPREME COURT REPORTS                           [2019] 1 S.C.R.


A     G). The observations contained in the CPRI report must be read in their
      entirety. The fact that the manufacturing specifications of the units may
      be similar (assuming they are so) is only one aspect of the total range of
      considerations which are required to be borne in mind under the terms
      of the tariff policy. The tariff policy requires that the operating norms
      should be efficient, relatable to past performance, capable of achievement
B
      and progressively reflect increased efficiencies. They may also take
      into consideration technical advancements, fuel, vintage of equipment,
      nature of operations and the level of service among other factors. Mr
      Chidambaram laid emphasis on clause 5.3(f) of the tariff policy where it
      prescribes that the operating parameters and tariffs should be at
C     “normative levels” only and not at the “lower of normative and actuals”
      except in the case of those units governed by para 5.3(h)(2). This
      submission will not, however, carry the case of the appellant any further.
      Normative levels are those which are fixed by the application of the
      standards guided by the terms of the tariff policy while actual levels are
      those which have been achieved as a matter of fact, in the past. The
D
      emphasis in the tariff policy is on creating incentives for achieving higher
      efficiency in order to enable the ultimate consumer to have the benefit
      of efficient operations.
             30. Tariff fixation is a complex exercise involving a careful balance
      between numerous considerations. The “shall be guided” prescription
E     under Section 61 requires the appropriate commission to bear those
      considerations in mind. Deducing past performance on the basis of
      historical data, balancing diverse policy objectives and evaluating the
      comparative weight to be ascribed to the interests of stakeholders is a
      scientific exercise which is carried out by the commission. The nature
F     of judicial review that is exercisable in a given subject area depends in a
      significant measure on the nature of the area and the body which is
      entrusted with the task of framing subordinate legislation. In
      Transmission Corporation of Andhra Pradesh Ltd. v Sai
      Renewable Power Pvt. Ltd.,7 a two judge Bench of this Court held
      thus:
G            “17. Fixation of tariff is, primarily, a function to be performed by
             the statutory authority in furtherance to the provisions of the relevant
             laws. We have already noticed that fixation of tariff is a statutory
             function as specified under the provisions of the Reform Act, 1998,
             Electricity Regulatory Commissions Act, 1998 and the Electricity
      7
H         (2011) 11 SCC 34
  RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                                     917
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

       Act, 2003. These functions are required to be performed by the             A
       expert bodies to whom the job is assigned under the law… The
       functions assigned to the Regulatory Commission are wide enough
       to specifically impose an obligation on the Regulatory Commission
       to determine the tariff. The specialized performance of functions
       that are assigned to Regulatory Commission can hardly be assumed
                                                                                  B
       by any other authority and particularly, the Courts in exercise of
       their judicial discretion. The Tribunal constituted under the
       provisions of the Electricity Act, 2003, again being a specialized
       body, is expected to examine such issues, but this Court in exercise
       of its powers under Article 136 of the Constitution would not sit
       as an appellate authority over the formation of opinion and                C
       determination of tariff by the specialized bodies.
       18. …This Court has consistently taken the view that it would not
       be proper for the Court to examine the fixation of tariff rates or
       its revision as these matters are policy matters outside the purview
       of judicial intervention. The only explanation for judicial intervention   D
       in tariff fixation/revision is where the person aggrieved can show
       that the tariff fixation was illegal, arbitrary or ultra vires the Act.
       It would be termed as illegal if statutorily prescribed procedure is
       not followed or it is so perverse and arbitrary that it hurts the
       judicial ‘conscience’ of the Court making it necessary for the Court
       to intervene. Even in these cases the scope of jurisdiction is a           E
       very limited one.”
       MERC is an expert body which is entrusted with the duty and
function to frame regulations, including the terms and conditions for the
determination of tariff. The Court, while exercising its power of judicial
review, can step in where a case of manifest unreasonableness or                  F
arbitrariness is made out. Similarly, where the delegate of the legislature
has failed to follow statutory procedures or to take into account factors
which it is mandated by the statute to consider or has founded its
determination of tariffs on extraneous considerations, the Court in the
exercise of its power of judicial review will ensure that the statute is not
breached. However, it is no part of the function of the Court to substitute       G
its own determination for a determination which was made by an expert
body after due consideration of material circumstances. In Association
of Industrial Electricity Users v State of Andhra Pradesh,8 a three
judge Bench of this Court dealt with the fixation of tariffs and held thus:
8
    (2002) 3 SCC 711                                                              H
918             SUPREME COURT REPORTS                            [2019] 1 S.C.R.


A           “11. We also agree with the High Court that the judicial review in
            a matter with regard to fixation of tariff has not to be as that of an
            Appellate Authority in exercise of its jurisdiction under Article
            226 of the Constitution. All that the High Court has to be satisfied
            with is that the Commission has followed the proper procedure
            and unless it can be demonstrated that its decision is on the face
B
            of it arbitrary or illegal or contrary to the Act, the court will not
            interfere. Fixing a tariff and providing for cross-subsidy is
            essentially a matter of policy and normally a court would refrain
            from interfering with a policy decision unless the power exercised
            is arbitrary or ex facie bad in law.”
C            31. We commenced our discussion by emphasising, in our prefatory
      observations, that the power to frame regulations is of a legislative nature.
      The CPRI report was an input before the MERC in carrying out that
      exercise. MERC followed the statutory procedures laid down for the
      determination of tariffs. It took into account factors which it is mandated
D     by the statute to consider. The national tariff policy, suggestions of
      stakeholders as well as the assessment carried out by the CPRI were
      duly considered. Hence, the present case does not fall in the paradigm
      of manifest unreasonableness or arbitrariness to warrant the interference
      of this Court. It would be rather formulaic for the Court to accept that
      merely because DTPS was placed at par in the immediately previous
E     period (2006-07) and the period immediately succeeding (2016-20), that
      this must necessarily be extrapolated to the intervening period governed
      by the MYT Regulations 2011. A body which is entrusted with the task
      of framing subordinate legislation has a range of options including policy
      options. If on an appraisal of all the guiding principles, it has chosen a
F     particular line of logic or rationale, this Court ought not to interfere.
             32. For the reasons which we have recorded in this judgment, we
      have come to the conclusion that regulation 44.2(d) of the MERC (Multi
      Year Tariff) Regulations, 2011 does not suffer from any constitutional or
      statutory infirmity. We have, however, furnished reasons of our own for
G     affirming the ultimate decision of the High Court to dismiss the writ
      petition. We have disapproved of the view of the High Court that the
      writ petition under Article 226 was not maintainable and accordingly set
      aside the direction on the imposition of costs. However, we hold that
      there is no infirmity in the impugned regulation and accordingly affirm
      the ultimate conclusion of the High Court to dismiss the writ petition
H     under Article 226.
  RELIANCE INFRASTRUCTURE LIMITED v. STATE OF                               919
MAHARASHTRA [DR. DHANANJAYA Y CHANDRACHUD, J.]

      The Civil Appeal is, accordingly, disposed of. There shall be no      A
order as to costs.


Ankit Gyan                                            Appeal disposed of.

                                                                            B




                                                                            C




                                                                            D




                                                                            E




                                                                            F




                                                                            G




                                                                            H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Regulation validity"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.