Created byFuzzy Cloud

Supreme Court of India

PUNE MUNICIPAL CORPORATIONversusSUS ROAD BANER VIKAS MANCH AND OTHERS

Citation
2024 INSC 682
Decided
12 September 2024
Disposal
Appeal(s) allowed

Holding

The GPP, having been authorized and commenced before the 2016 Rules came into force, is governed by the 2000 Rules, rendering the NGT’s order to close it erroneous and therefore quashed.

Summary

The Pune Municipal Corporation (PMC) and its concessionaire Noble Exchange set up a Garbage Processing Plant (GPP) at Baner, Pune under a 2005 development plan that reserved the land for such a facility. The plant was authorized under the Municipal Solid Waste (Management and Handling) Rules, 2000 and received environmental clearance in early 2016, before the Solid Waste Management Rules, 2016 came into force. The National Green Tribunal (NGT) ordered the plant’s closure, invoking the 2016 Rules, buffer‑zone requirements and alleging procedural violations. On appeal, the Supreme Court held that because the authorization, clearance and commencement occurred before 8 April 2016, the 2000 Rules, not the 2016 Rules, govern the plant; the NGT had erred in applying the newer regime, in finding a required 500‑metre buffer zone, and in treating the land as a biodiversity park. The Court quashed the NGT orders, dismissed the original application, and directed the PMC and the concessionaire to comply with specific environmental safeguards while allowing the plant to continue operating.

Issues considered

  • The applicability of the Municipal Solid Waste (Management and Handling) Rules, 2000 versus the Solid Waste Management Rules, 2016 to the GPP.
  • Whether the NGT correctly applied the buffer‑zone requirement of the 2000 Rules to a waste‑processing plant.
  • Whether the land earmarked for the GPP was lawfully reserved for that purpose and not for a biodiversity park.
  • Whether the closure of the GPP would be contrary to public interest.
  • Whether the original application filed by Sus Road Baner Vikas Manch is barred by the limitation provision of Section 16 of the NGT Act, 2010.
  • Whether the Maharashtra Pollution Control Board’s authorization prior to 2021 sufficed as consent under the Water Act, 1974 and the Air Act, 1981.

Legislation cited

Subjects

Garbage Processing PlantSolid Waste ManagementEnvironmental ClearancePublic InterestBuffer ZoneNational Green TribunalMunicipal Solid Waste RulesRight to Clean EnvironmentOdour ControlDecentralised Waste Processing

Judgment

                 [2024] 9 S.C.R. 374 : 2024 INSC 682

                  Pune Municipal Corporation
                               v.
             Sus Road Baner Vikas Manch and Others
                    (Civil Appeal Nos. 258-259 of 2021)
                             12 September 2024
             [B.R. Gavai,* Prashant Kumar Mishra and
                      K.V. Viswanathan, JJ.]

                           Issue for Consideration
       National Green Tribunal, Principal Bench, New Delhi disposed of
       the OA preferred by the Sus Road Baner Vikas Manch, respondent
       No. 1 herein, by directing the Pune Municipal Corporation to close
       the Garbage Processing Plant (GPP) operated by Noble Exchange
       Environment Solution Pune LLP, at Baner, Pune and to shift the
       same to an alternate location in terms of the guidelines issued by
       the Central Pollution Control Board.

                                  Headnotes†
       Municipal Solid Waste (Management and Handling) Rules,
       2000 – Solid Waste Management Rules, 2016 – Sus Road
       Baner Vikas Manch, respondent No. 1 sought to restrain the
       respondent-Concessionaire from operating the GPP at Survey
       No. 48/2/1 at Baner, Pune since the same had been established
       without following the procedure prescribed by law.
       Held: A perusal of the proposed Land Use Map for village Balewadi,
       Baner which was notified on 31.12.2002 would reveal that in the said
       Plan, Plot No. 48/2/1 was reserved for GPP – The commencement
       certificates insofar as all other buildings are also after the Draft
       Development Plan was sanctioned by the State Government – It
       is clear that the commencement certificates in respect of all the
       buildings are after the date on which the Plot was reserved for
       GPP – In the instant case, the application for authorization, the
       grant of authorization, the grant of Environment Clearance by the
       SEIAA and the commencement of the GPP all have taken place
       prior to 08.04.2016 i.e. the date on which the 2016 Rules came into
       force – As such, the Tribunal has grossly erred in observing that
       the GPP in question was covered by the 2016 Rules – A perusal
       of the Minutes of the 11th Consent Committee Meeting of 2015-

* Author
[2024] 9 S.C.R.                                                               375

                     Pune Municipal Corporation v.
                Sus Road Baner Vikas Manch and Others

     16 held on 09.11.2015 would clearly reveal that the MPCB was
     following the practice of granting authorization under the 2000 Rules
     which covers all the aspects of the consent – The MPCB started
     granting Consent only after 06.09.2021 and prior to that, it was
     only issuing a composite authorization – The Tribunal has failed to
     take this into consideration – Also, a perusal of the Checklist issued
     by the MPCB which was published in 2003 would reveal that the
     requirement of no-development zone or a buffer zone is only with
     regards to landfill sites – The contention of the respondent No. 1 that
     under the 2000 Rules, a buffer zone is required to be maintained
     for GPP is without substance – The finding of the Tribunal that
     initially the plot where GPP was constructed was reserved for
     Bio-diversity Park is also erroneous and factually incorrect – As
     discussed, the plot in question has been reserved for the GPP
     since inception and it is only the adjoining plot which was reserved
     for the Bio-diversity Park – Apart from that, the closure of the GPP
     in question rather than subserving the public interest, would be
     detrimental to public interest – If the GPP in question is closed, the
     organic waste generated in the western part of Pune city would be
     required to be taken all the way throughout the city to Hadapsar
     which is in the eastern part of the city – This will undoubtedly
     lead to foul odour and nuisance to the public – Therefore of
     the considered view that the impugned judgment and order of
     the Tribunal deserves to be quashed and set aside – However,
     the appellant-Corporation as well as the respondent-Concessionaire
     is cautioned that they should take necessary steps so that the
     residents residing in the nearby buildings do not have to suffer
     on account of foul odour – The appellant-Corporation and the
     respondent-Concessionaire are directed to ensure that all the
     suggestions/recommendations made by NEERI should be strictly
     complied with. [Paras 26, 34, 35, 38, 39, 40, 41, 42, 47, 50]

                               Case Law Cited
     State of Punjab v. Harnek Singh [2002] 1 SCR 1060 : (2002) 3
     SCC 481 : (2002) INSC 84 – relied on.
     Bhavya Height Co-operative Housing Society Ltd. v. Mumbai
     Metropolitan Region Development Authority and Others (2019)
     SCC OnLine Bom 1075 – referred to.

                                 List of Acts
     Municipal Solid Waste (Management and Handling) Rules, 2000;
     Solid Waste Management Rules, 2016.
376                                                         [2024] 9 S.C.R.

                        Digital Supreme Court Reports


                              List of Keywords
       Garbage Processing Plant (GPP); Public interest; Organic waste;
       Foul odour; Nuisance to public; Odour control system; Slurry
       sampling; Waste processing; Recycling; Treatment; Right to clean
       environment.

                             Case Arising From
       CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 258-259 of
       2021
       From the Judgment and Order dated 27.10.2020 and 22.12.2020 of
       the National Green Tribunal, Principal Bench at New Delhi in Original
       Application No.210 of 2020 and Review Application No.49 of 2020 in
       Original Application No. 210 of 2020 respectively
       With
       Civil Appeal Nos. 265-266 of 2021
                          Appearances for Parties
       Ms. Aishwarya Bhati, A.S.G., K. Parameshwar, A. N. S. Nadkarni,
       Rahul Kaushik, Sr. Advs., Aman Varma, Dhaval Mehrotra, Rahul
       Garg, Adith Deshmukh, Ms. Aditi Desai, Ms. Riya Wasade, Ms.
       Nishtha Kumar, Shrom Sethi, Ms. Pallavi Mohan, S. S. Rebello,
       Ms. Deepti Arya, Ms. Arzu Paul, Ninad Laud, Saurabh Kulkarni, Ivo
       D’Costa, Guru Prasad Naik, Ms. Ishani Shekhar, Ms. Anshula Vijay
       Kumar Grover, Mukesh Verma, Pankaj Kumar Singh, Kamal Kumar
       Pandey, Ms. Vatsala Tripathi, Pawan Kumar Shukla, Shashank Singh,
       Devanshu Gupta, Krishna Prakash Dubey, Avijit Roy, Gurmeet Singh
       Makker, Ms. Swarupma Chaturvedi, Piyush Beriwal, Mohdd. Akhil,
       Ishaan Sharma, Ms. Ruchi Kohli, Rohan Gupta, Aaditya Aniruddha
       Pande, Siddharth Dharmadhikari, Shrirang B. Varma, Bharat Bagla,
       Sourav Singh, Aditya Krishna, Ms. Preet S. Phanse, Adarsh Dubey,
       Advs. for the appearing parties.
                 Judgment / Order of the Supreme Court

                                 Judgment
       B.R. Gavai, J.
1.     These Civil Appeals challenge the judgment and order dated 27th
       October 2020 passed by the National Green Tribunal, Principal Bench,
[2024] 9 S.C.R.                                                                                    377

                            Pune Municipal Corporation v.
                       Sus Road Baner Vikas Manch and Others

       New Delhi1 in Original Application2 No. 210 of 20203 wherein the
       Tribunal disposed of the OA preferred by the Sus Road Baner Vikas
       Manch, Respondent No. 1 herein, by directing the Pune Municipal
       Corporation4 to close the Garbage Processing Plant5 operated by
       Noble Exchange Environment Solution Pune LLP,6 at Baner, Pune and
       to shift the same to an alternate location in terms of the guidelines
       issued by the Central Pollution Control Board,7 within 4 months from
       the date of the order. Having directed the closure of the GPP, the
       Tribunal further granted liberty to the Maharashtra Pollution Control
       Board8 to recover environmental compensation on the basis of ‘polluter
       pays’ principle from the GPP for the entirety of the period during
       which the environmental norms were violated by the GPP. Seeking
       a review of the aforesaid order, the respondent-Concessionaire,
       the operator of the aforementioned GPP, filed a Review Application
       being No. 49 of 2020 which came to be dismissed by the Tribunal
       vide order dated 22nd December 2020. The said order is also under
       challenge in these present appeals.
2.     We have two Civil Appeals before us. The first set of Civil Appeals
       being CA Nos. 258-259 of 2021 have been filed by the Pune Municipal
       Corporation. The second set of Civil Appeals being CA Nos. 265-66
       of 2021 have been filed by Noble Exchange Environment Solution
       Pune LLP. For the sake of clarity and to avoid confusion, the parties
       will be referred to according to their positions in the first set of civil
       appeals.
3.     The facts which give rise to the present appeals are as under:
       3.1. Upon the municipal limits of the appellant-Corporation being
            extended to include Baner Balewadi, a Development Plan
            was drawn up in 2002 wherein land situated at Survey No.
            48/2/1 in Baner Balewadi, Pune was reserved for the purpose


1    Hereinafter referred to as the ‘Tribunal’.
2    Hereinafter referred to as OA
3    Earlier OA No. 34 of 2019 (WZ). Initially the OA was preferred before the Tribunal, Western Zone, and
     was subsequently transferred to the Principal Bench, New Delhi.
4    Hereinafter referred to as the ‘appellant-Corporation’.
5    Hereinafter referred to as the ‘GPP’.
6    Hereinafter referred to as the ‘respondent-Concessionaire’.
7    Hereinafter referred to as the “CPCB”.
8    Hereinafter referred to as the “MPCB”.
378                                                        [2024] 9 S.C.R.

                      Digital Supreme Court Reports


             of a GPP. In 2004, a public hearing was conducted for the
             purpose of drawing up a new development plan, subsequent
             to which, the Planning Committee of the appellant-Corporation
             submitted its report on 30th December 2004 to the General
             Body of the appellant-Corporation earmarking the aforesaid
             land for a GPP in the Draft Development Plan of 2005. The
             said Plan was submitted to the Government of Maharashtra
             on 29th November 2005 whereafter the Plan came to be
             sanctioned by the State Government vide Notification dated
             18th September, 2008.
       3.2. In the interregnum, while the aforesaid Plan was pending
            approval, in 2005, permission was sought for constructing a
            residential building being Tarai Heights at a site which was
            approximately 100 metres away from the earmarked land in
            Survey No. 48/2/1 and subsequently, in 2008, permission was
            sought for constructing another residential building being 52
            Green Woods at a site which was approximately 140 metres
            away from the aforesaid earmarked land. In said fashion,
            over the years, permission for construction of similar such
            residential projects were sought in and around the earmarked
            portion of land. The last such permission was sought in 2019
            for the construction of a residential building being Platinum 9.
       3.3. Subsequent to the Development Plan of 2005 being sanctioned,
            the appellant-Corporation and the respondent-Concessionaire,
            Respondent No. 7 in the first appeal, entered into a Concession
            Agreement on 30th March 2015 for setting up an Organic Waste
            Processing Plant at the land situated at Survey No. 48/2/1.
            The purpose of the Concession Agreement was to set up an
            operational waste-processing facility where pre-segregated,
            non-compacted organic waste received from the appellant-
            Corporation would be crushed into a slurry, after removing
            any non-biodegradable material, and the said slurry would be
            transported to a facility in Talegaon where raw biogas would
            be generated from the slurry. The Concession Agreement was
            for a period of 30 years.
       3.4. Subsequently, in compliance of the notification dated 14th
            August 2006, for the setting up of GPP, the respondent-
            Concessionaire sought Environment Clearance from the State
[2024] 9 S.C.R.                                                            379

                           Pune Municipal Corporation v.
                      Sus Road Baner Vikas Manch and Others

                Level Environment Impact Assessment Authority9 on 13th August
                2015. Thereafter, pursuant to a public hearing the SEIAA granted
                Environment Clearance to the respondent-Concessionaire for
                establishment of Organic Waste Management Plant on 1st
                February 2016. The Environment Clearance accorded was to
                be valid for a period of 7 years.
      3.5. In the meanwhile, on 2 nd December 2015, the MPCB,
           Respondent No. 2 herein, granted authorization to the
           respondent-Concessionaire to set up and operate a solid waste
           processing/disposal plant in accordance with the Municipal
           Solid Waste (Management and Handling) Rules, 2000.10 The
           said authorization was valid till 31st December 2016.
      3.6. The authorization granted by the MPCB was subsequently
           renewed on two occasions. On 4th May 2017, the MPCB further
           granted authorization to the appellant-Corporation to set up and
           operate waste processing/recycling/treatment/disposal facilities
           at various sites, 48 in total, including at the concerned site
           i.e. Survey No. 48/2/1, at Baner, Pune. The said authorization
           was to be valid till 31st December 2021. The authorization was
           renewed once again on 3rd August 2022 and the same is valid
           up till 31st July 2027.
      3.7.      In 2019, Respondent No.1-Sus Road Baner Vikas Manch,
                a registered Trust that had been established to protect the
                interests of the citizens residing at the Sus Road and Baner
                areas in Pune, preferred an OA being No. 34 of 2019 before the
                National Green Tribunal, Western Zone, seeking to restrain the
                respondent-Concessionaire from operating the aforementioned
                GPP at Survey No. 48/2/1 at Baner, Pune since the same had
                been established without following the procedure prescribed
                by law.
      3.8. Deeming it appropriate to verify the factual details set out in
           the OA, the Tribunal vide its order dated 5th September 2019
           constituted an expert committee comprising of the CPCB and
           the MPCB to inspect the GPP and the area in question, and
           to submit a report within a month.


9    Hereinafter referred to as ‘SEIAA’.
10   Hereinafter referred to as the ‘2000 Rules’.
380                                                          [2024] 9 S.C.R.

                              Digital Supreme Court Reports


       3.9. In compliance of the aforesaid order, the CPCB and the
            MPCB conducted a joint inspection of the GPP and area in
            question. Subsequently, a report was submitted before the
            Tribunal wherein the joint inspection team had made several
            observations about the operational capacity of the GPP, its
            authorization status and certain procedural shortcomings.
       3.10. Based on the Joint Inspection Report, the Tribunal vide the first
             impugned order dated 27th October 2020 held that the GPP was
             in violation of the right to clean environment of the inhabitants
             and was against the statutory norms. In that view of the matter,
             the Tribunal disposed of the OA in the aforementioned terms.
             While directing a shut-down of the plant, the Tribunal further
             directed that the site in question might be used for the purpose
             of developing a bio-diversity park, for which purpose the site
             had been originally designated. The Tribunal further constituted
             a Joint Committee comprising of the CPCB, the MPCB, District
             Magistrate of Pune and the Municipal Corporation of Pune
             to monitor the subsequent course of action in light of the
             aforesaid decision.
       3.11. Aggrieved thereby, the respondent-Concessionaire filed a
             Review Application before the Tribunal being Review Application
             No. 49 of 2020 which came to be dismissed vide second
             impugned order dated 22nd December 2020.
       3.12. Being aggrieved thereby, the present statutory appeals have
             been filed under Section 22 of the National Green Tribunal
             Act, 2010.11
4.     We have heard Shri A.N.S. Nadkarni, learned Senior Counsel
       appearing on behalf of the appellant in CA Nos. 258-259 of 2021, Shri
       K. Parameshwar, learned Senior Counsel appearing on behalf of the
       appellant in CA Nos. 265-266 of 2021 and on behalf of respondent
       No.7 in CA Nos.258-259 of 2021, Shri Ninad Laud, learned counsel
       appearing on behalf of respondent No.1 in both the matters and
       Shri Rahul Kaushik, learned Senior Counsel appearing on behalf
       of respondent No.2-MPCB in both the appeals.



11   Hereinafter referred to as the “NGT Act”.
[2024] 9 S.C.R.                                                          381

                           Pune Municipal Corporation v.
                      Sus Road Baner Vikas Manch and Others

5.    Shri Nadkarni submitted that the Draft Development Plan 2002 for
      Pune city was sanctioned on 18th September 2008. He submitted
      that this was done after inviting and hearing objections under Section
      28 of the Maharashtra Regional and Town Planning Act, 1966.12 He
      submitted that, at that stage, no objection was raised by anyone.
      He further submitted that the advertisement inviting Expression of
      Interest for setting up Waste Segregation and Processing Unit was
      published on 4th March 2014. He submitted that the Concession
      Agreement was entered into on 30th March 2015. It is submitted
      that the Waste Segregation Unit is set up within Pune city limits and
      the Processing Plant is situated at Talegaon that is outside the city
      limits. It is further submitted that the MPCB granted its authorization
      to set up and operate on 2nd December 2015 and the Environmental
      Clearance was also issued on 1st February 2016.
6.    Shri Nadkarni submitted that the respondent No. 1 herein despite
      having knowledge of the reservation in the Development Plan, EC
      and grant of authorization for the Waste Segregation and Processing
      Unit, filed an OA seeking cancellation and revocation of EC only
      on 2nd March 2019. It is therefore submitted that the OA was filed
      belatedly almost after a period of three years from the date of grant
      of EC. It is therefore submitted that the OA was filed much beyond
      the period prescribed under Section 16 of the NGT Act. As such, the
      OA ought to be dismissed on the ground of limitation alone.
7.    Shri Nadkarni further submitted that the learned Tribunal had mixed
      up the facts. Whereas the GPP reservation is in Plot No. 48/2/1 under
      the Development Plan, the Bio-diversity Park is in Plot No. 49 which
      is an adjoining plot. As such, the direction issued by the learned
      Tribunal to use Plot No. 48/2/1 for Bio-diversity Park is unsustainable.
8.    Shri Nadkarni further submitted that the reservation for the GPP in
      the Draft Development Plan is since 2002 which was subsequently
      sanctioned in 2008. The residential buildings had come up at a
      much later point in time. He submitted that only one project was
      commenced on 27th December 2005 whereas the second project
      was commenced on 25th March 2008 and all other projects that is 17
      in number were commenced only from 2010 onwards that is much
      after sanction of the Development Plan.


12   Hereinafter referred to as the “MRTP Act”.
382                                                          [2024] 9 S.C.R.

                              Digital Supreme Court Reports


9.     Shri Nadkarni further submitted that the Environmental Clearance
       for the GPP was received on 1st February 2016 and the Plant was
       set up and commenced in the same year. He submitted that, at the
       relevant time, the 2000 Rules were in force. It is submitted that the
       Solid Waste Management Rules, 201613 granted two years period
       for the migration and upgrading of the existing Plant to the 2016
       Rules and as such, the provisions pertaining to the waste disposal
       came into force on 8th April 2018 i.e. after two years from the date
       of notification of the 2016 Rules.
10. Shri Nadkarni further submitted that the provisions as regards the
    buffer zones around waste processing and disposal facility came into
    force in 2017 and as such, would not apply to a plant which was
    conceived, set up and became functional in 2016. It is submitted
    that, even the 2016 Rules envisage decentralization of the process
    i.e. segregation at source. It is submitted that the present location of
    the GPP conforms to the requirement of the 2016 Rules inasmuch as
    only the waste generated from surrounding areas alone is segregated
    and crushed at the Baner Plant.
11. Shri Nadkarni further submitted that in pursuance of the observations
    made by this Court, the appellant-Corporation took steps to look
    for an alternative site, but it has not been possible to find out an
    alternative site on account of variety of reasons.
12. Shri Nadkarni further submitted that the reasoning given by the learned
    Tribunal that there was no consent of MPCB for establishment of
    the GPP is also unsustainable. It is submitted that, at the relevant
    time, the MPCB was not issuing a separate “consent to establish”
    under the Water Act, 1974 or the Air Act, 1981 but was issuing a
    composite authorization to “set up and operate” across the State. It is
    submitted that the circular issued by the MPCB dated 6th September
    2021 would clarify this position. It is further submitted that the said
    practice was followed throughout the State. Shri Nadkarni relies on
    the proceedings of the Minutes of the Consent Committee Meeting
    dated 9th November 2015.
13. Shri Nadkarni submitted that, since initially the authorization granted
    by MPCB on 2nd December 2015 was valid till 31st December 2016,
    the appellant-Corporation and the respondent-Concessionaire applied


13   Hereinafter referred to as the “2016 Rules”.
[2024] 9 S.C.R.                                                          383

                     Pune Municipal Corporation v.
                Sus Road Baner Vikas Manch and Others

     for renewal and the authorization, vide communication of the MPCB
     dated 4th May 2017, was renewed for a period of five years i.e. till 31st
     December 2021. It is submitted that, before the expiry of five years
     period which was to expire on 31st December 2021, the appellant-
     Corporation and the respondent-Concessionaire again applied for
     renewal of the authorization to set up and operate on 26th October
     2021 and vide communication dated 3rd August 2022, the authorization
     to set up and operate was renewed till 31st July 2027. Not only that,
     but on 1st November 2022, consent to operate was also obtained as
     per notification dated 6th September 2021. The consent to operate
     has been further renewed till 30th September 2025.
14. Shri Nadkarni further submitted that the Joint Inspection Committee
    appointed by the learned Tribunal erroneously applied the 2016 Rules
    which did not apply to the GPP which was conceived and became
    functional prior to 2016.
15. Insofar as the finding of the learned Tribunal regarding buffer zone
    is concerned, Shri Nadkarni submitted that the said buffer zone of
    500 meters is to be maintained from land fill sites and does not
    apply to Waste Segregation Plant. Shri Nadkarni further submitted
    that the continuation of the Project was in the larger public interest.
    It is submitted that the GPP processes the organic waste generated
    in the western part of the city i.e., Aundh, Baner, Kothrud, Sinhagad
    road and Katraj. It is submitted that, prior to commencement of the
    said Plant, the organic waste generated in the western part of the
    city was taken all the way to Hadapsar which is in the eastern part
    of the city. It is submitted that this led to foul odour and nuisance
    to public. It is therefore submitted that the impugned order of the
    learned Tribunal rather than subserving in public interest, would be
    detrimental to the public interest.
16. Shri Nadkarni submitted that, in any case, in order to address the
    concern of the respondents, the appellant-Corporation is in the process
    of installing portable compactors with hook lifting mechanism to ensure
    that the reject waste generated does not touch the ground. It is
    submitted that the tenders for the same have already awarded to one
    M/s Global Waste Management and the installation of the machinery
    would be completed by December 2024. He further submitted that
    the construction of shed to cover the reject area would also be
    completed by December 2024. Shri Nadkarni further submitted that
    the appellant-Corporation would construct bitumen road to the Waste
384                                                           [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       Segregation Plant and concrete the Reject Area immediately. This will
       in turn enhance the clean transfer of waste and avoid accumulation
       of water around the Waste Segregation Plant. He submitted that
       though the appellant-Corporation desired to do it earlier, it could not
       be done since the appellant-Corporation was facing objections from
       protestors due to pendency of the present proceedings.
17. Shri Parameshwar, learned Senior Counsel appearing on behalf
    of the respondent-Concessionaire also supported the submissions
    made on behalf of the appellant-Corporation. He submitted that the
    respondent-Concessionaire specializes in processing food waste with
    cutting edge anaerobic digestion technology – a process in which
    microorganisms break down biodegradable waste to produce biogas
    and organic manure. He submitted that, when cleaned and purified
    to 96% purity, Bio CNG/CBG can replace fossil fuels such as LPG,
    diesel, petrol, etc. It is further submitted that the anaerobic digestion is
    an efficient and controlled biological process that productively utilises
    waste in an enclosed space, rather than dumping it in a landfill,
    which causes environmental harm through leaching, contamination
    of groundwater, risk of fires, etc. It is further submitted that Indian
    food waste is unique in its composition, with a high concentration of
    antibacterial ingredients like turmeric and spices, and greases such
    as ghee that cannot be broken down using conventional enzymes
    and cultures. He submitted that the respondent-Concessionaire,
    through years of research and experience, has successfully developed
    enzymes, cultures, and processes to biologically break down Indian
    food. It is submitted that the Project commissioned by the respondent-
    Concessionaire, as a matter of fact, is environment friendly inasmuch
    as it converts the food waste into biogas which has also been used
    to run public transport buses in Pune City.
18. Shri Parameshwar submitted that, in order to carry out the conversion
    of food waste into biogas, the respondent-Concessionaire has
    established two plants – one in Baner and one in Talegaon. He
    submitted that the site at Baner is a waste processing facility where
    pre-segregated, non-compacted organic waste is received from the
    appellant-Corporation. The waste is segregated again to remove
    any non-biodegradable materials, and the residual organic waste is
    crushed to make a slurry. The slurry produced is then transported to
    a different site in Talegaon, which is about 34 kms away from Pune
    City, where raw biogas is generated from the slurry.
[2024] 9 S.C.R.                                                         385

                           Pune Municipal Corporation v.
                      Sus Road Baner Vikas Manch and Others

19. Shri Parameshwar submitted that though the reservation in the
    Draft Development Plan is of 2002 which was sanctioned in 2008,
    no challenge has been made in the OA challenging the reservation
    of this Plot as GPP. He therefore joins Shri Nadkarni in submitting
    that the impugned order passed by the learned Tribunal is not
    sustainable in law.
20. Shri Ninad Laud, learned counsel appearing on behalf of respondent
    No.1 in both the matters submitted that the checklist prescribed by
    the MPCB in 2003 would also apply to waste processing facility and
    the same is not restricted to landfill sites. He submitted that, as per
    the said checklist, no development zone of 500 meters is prescribed
    for Municipal Solid Waste Processing Plants and Landfill sites. He
    further submitted that a mere reservation in the municipal land will
    not absolve the appellant-Corporation of the environmental obligation.
    He submitted that the appellant-Corporation itself has sanctioned the
    plans of the buildings where the residents of respondent No.1 reside.
    Having sanctioned the Plans, the appellant-Corporation cannot run
    away from its duty of preventing pollution in the area on account of GPP.
21. Insofar as the contention that the MPCB was only granting authorization
    and not consent, Shri Laud submitted that merely because the MPCB
    was following a particular practice, it cannot absolve the appellant-
    Corporation of obtaining consent under the Water Act, 1974 or the
    Air Act, 1981 which are statutory requirements. Shri Laud submitted
    that the 2003 checklist is traceable to 2000 Rules.
22. Shri Laud further submitted that, a perusal of the Joint Inspection
    Committee Report itself would reveal that the Joint Inspection officials
    felt prevalence of odour in and around the plant premises. He further
    submitted that the Joint Inspection Committee also found that the
    segregation rejects has been transported in open truck without any
    cover. He has submitted that the said Report also suggests that
    such open carriage would cause nuisance during transportation.
    He therefore submitted that it is clear that the GPP was causing
    pollution in the area thereby making the life of the residents of
    respondent No. 1 miserable. He submitted that, not only that even
    the suggestions which are given by the National Engineering and
    Environment Research Institute14 have also not been implemented.


14   Hereinafter referred to as the “NEERI”.
386                                                        [2024] 9 S.C.R.

                     Digital Supreme Court Reports


23. Shri Laud, in the alternative, submitted that, in the event this Court
    is inclined to hold that the GPP is entitled to continue its operations,
    the Court should issue stringent directions so that the residents are
    not compelled to suffer the pollution.
24. Shri Kaushik, learned Senior Counsel appearing on behalf of the
    MPCB also accepts the position that, at the relevant time i.e. when
    the GPP commenced, the MPCB was following the practice of only
    granting authorization and only after its circular dated 6th September
    2021, it has started granting consent. He therefore submitted that
    accordingly, the first consent was granted on 1st November 2022 and
    the second consent has been granted on 16th March 2024.
25. We have heard the learned counsel for the parties and also perused
    the materials placed on record.
26. A perusal of the proposed Land Use Map for village Balewadi,
    Baner which was notified on 31st December 2002 would reveal that
    in the said Plan, Plot No. 48/2/1 has been reserved for GPP. Plot
    Nos. 49/289/50 and 7 have been shown in Green Belt. The Draft
    Development Plan was published under Section 28(4) of the MRTP
    Act on 30th November 2005. In the said Plan also, Plot No. 48/2/1
    has been shown as reserved for GPP. Plot Nos. 49/289/50 and 7
    have been reserved for Bio-diversity Park (BDP). The Government of
    Maharashtra vide notification dated 18th September 2008 sanctioned
    the said Draft Development Plan. It could thus clearly be seen that
    right from 2002, the Plot in question has been reserved for GPP.
    As already observed hereinabove, the first building was granted
    commencement certificate on 27th December 2005 whereas the
    second was granted commencement certificate on 25th March 2008
    and all other, that is 17 buildings, have been granted commencement
    certificate only after 2008. It is thus clear that the commencement
    certificate insofar as the first building is concerned is also after the
    Draft Development Plan was statutorily notified. The commencement
    certificates insofar as all other buildings are also after the Draft
    Development Plan was sanctioned by the State Government. It is
    thus clear that the commencement certificates in respect of all the
    buildings are after the date on which the Plot was reserved for GPP.
27. The learned Tribunal while allowing OA of respondent No.1 has also
    come to a conclusion that the GPP is also in violation of Rule 20
    of 2016 Rules. For considering the correctness of the said finding
[2024] 9 S.C.R.                                                        387

                     Pune Municipal Corporation v.
                Sus Road Baner Vikas Manch and Others

     of the learned Tribunal, we will have to first consider as to which of
     the Rules are to be applicable to the said GPP.
28. It is the contention of the appellant-Corporation that the GPP would
    be covered by the 2000 Rules whereas it is the contention of the
    respondent No. 1 that the same would be covered by the 2016 Rules.
29. As per sub-rule (2) of Rule 1 of the 2016 Rules, the Rules were to be
    given effect from the date of their publication in the Official Gazette.
    The 2016 Rules were notified on 8th April 2016. As per Entry No. 7
    under Rule 22 of the 2016 Rules, the time frame for establishment of
    necessary infrastructure for implementation of these Rules was to be
    created by the local bodies and other concerned authorities within a
    period of two years from the date of the said Rules coming into force.
    It is further to be noted that the application for authorization as per
    sub-rule (2) of Rule 4 of the 2000 Rules was made by the appellant-
    Corporation on 10th August 2015 in Form-I and the authorization was
    granted in Form-III of the 2000 Rules on 2nd December 2015. The
    processing plant also became operational on 17th December 2015.
    It is also to be noted that the SEIAA granted Environment Clearance
    in respect of the Organic Waste Management Plant at Talegaon,
    Dabhade after public hearing on 1st February 2016. The GPP and the
    Organic Waste Management Plant at Talegoan, Dabhade are part of
    the same Concession Agreement which was entered into between
    the appellant-Corporation and the respondent-Concessionaire on
    30th March 2015. It could thus clearly be seen that the application for
    grant of authorization, grant of authorization, grant of Environment
    Clearance by the SEIAA and the commencement of the project
    was all prior to 8th April 2016 i.e. the date on which the 2016 Rules
    came into force.
30. It will also be relevant to refer to the Preamble of the said 2016
    Rules, which reads thus:
           “Now, therefore, in exercise of the powers conferred by
           sections 3, 6 and 25 of the Environment (Protection) Act,
           1986 (29 of 1986) and in supersession of the Municipal
           Solid Waste (Management and Handling) Rules, 2000,
           except as respect things done or omitted to be done
           before such supersession, the Central Government hereby
           makes the following rules for management of Solid Waste,
           namely:-”
388                                                            [2024] 9 S.C.R.

                            Digital Supreme Court Reports


31. It could thus clearly be seen that the Preamble itself states that
    though the 2016 Rules are in supersession of the 2000 Rules, they
    will apply except as respect things done or omitted to be done before
    such supersession.
32. It will be relevant to refer to the following observations of this Court
    in the case of State of Punjab v. Harnek Singh,15 wherein this Court
    after considering the earlier decisions has observed thus:
             “16. The words “anything duly done or suffered thereunder”
             used in clause (b) of Section 6 are often used by the
             legislature in saving clause which is intended to provide that
             unless a different intention appears, the repeal of an Act
             would not affect anything duly done or suffered thereunder.
             This Court in Hasan Nurani Malak v. S.M. Ismail, Asstt.
             Charity Commr., Nagpur [AIR 1967 SC 1742] has held
             that the object of such a saving clause is to save what
             has been previously done under the statute repealed. The
             result of such a saving clause is that the pre-existing law
             continues to govern the things done before a particular
             date from which the repeal of such a pre-existing law takes
             effect. In Universal Imports Agency v. Chief Controller of
             Imports and Exports [AIR 1961 SC 41 : (1961) 1 SCR
             305] this Court while construing the words “things done”
             held that a proper interpretation of the expression “things
             done” was comprehensive enough to take in not only the
             things done but also the effect of the legal consequence
             flowing therefrom.”
33. It can thus be seen that this Court has in unequivocal terms held
    that the term “things done” was comprehensive enough to take in not
    only the things done but also the effect of the legal consequences
    flowing therefrom.
34. In the present case, as already discussed hereinabove, the application
    for authorization, the grant of authorization, the grant of Environment
    Clearance by the SEIAA and the commencement of the GPP all have
    taken place prior to 8th April 2016 i.e. the date on which the 2016
    Rules came into force. As such, we hold that the learned Tribunal
    has grossly erred in observing that the GPP in question was covered
    by the 2016 Rules.


15   [2002] 1 SCR 1060 : (2002) 3 SCC 481 : 2002 INSC 84
[2024] 9 S.C.R.                                                            389

                     Pune Municipal Corporation v.
                Sus Road Baner Vikas Manch and Others

35. The next finding of the learned Tribunal is with regard to the consent
    under the Water Act or the Air Act. A perusal of the Minutes of the
    11th Consent Committee Meeting of 2015-16 held on 9th November
    2015 would clearly reveal that the MPCB was following the practice
    of granting authorization under the 2000 Rules which covers all the
    aspects of the consent. As such, MPCB did not find it necessary to
    cover such processing plant for the consent management.
36. It will be relevant to refer to the Circular issued by the MPCB dated
    6th September 2021, which reads thus:
           “Board is receiving applications from solid waste
           Management Facilities and ULBs for grant of consent
           for installation and operation of the facility. As there is no
           comprehensive categorization of all Solid waste processing
           operations/activities in modified CPCB categorization for
           Solid Waste Management, Board is not granting the consent
           for Solid Waste Management Facility/operations/activities.
           Presently, Board is granting authorization under The
           Solid Waste Management rules, 2016, for setting up and
           operation of solid waste management facilities.
           The Board in its 176 th meeting held on 25/O2/2O2I
           passed resolution on consent management for solid waste
           processing plants / facilities and decided to grant Consent
           to Establish/Operate for Solid Waste Management facilities.
           The Consent fees is charged as per Env. Dept. GoM
           GR dated 25.8.2011 to individual/Integrated Solid Waste
           Management facility depending upon type of ULB. The
           term of consent for Red, Orange, and Green category of
           Industry is one, two and three years respectively”.
           Local Bodies to pay the consent fees to the Board as per
           the statement given below.
           •    Urban Local Bodies-
            Sr. No.       Urban Local Body                 Fees
               1.     Municipal Corporation         Rs.1,00,000/-
               2.     Municipal Council Class-A     Rs.50,000/-
               3.     Municipal Council Class-B     Rs.5,000/-
               4.     Municipal Council Class-C     Rs.2,000/-
390                                                      [2024] 9 S.C.R.

                    Digital Supreme Court Reports


          •    Other than Local Body-

           Individual Operator/       Based on gross capital
           Industry installing MSW    investment as per prevailing
           based processing plant.    rules for industries.
          Delegation of powers to various authorities for grant of
          consent will be as per “revised delegation of powers for
          consent Management” issued vide Office Order No. 12,
          Dated- 23/12/2O2O.
          Therefore, all Ros and SROs are hereby directed to
          communicate all local Bodies/Cantonment Boards of
          Concern area of jurisdiction for submission of application
          to obtain Consent to Establish/Operate for setting up and
          operation of existing as well as proposed solid waste
          management facilities.”
37. It could thus be seen that prior to 6th September 2021, the MPCB
    was not granting Consent for Solid Waste Management facility/
    operations/activities. The MPCB was granting authorization for
    setting up and operation of solid waste management facilities. Only
    in the meeting dated 25th February 2021, a Resolution was passed
    on consent management and it was decided to grant Consent
    to operate for Solid Waste Management Facilities. Vide the said
    communication, all ROs and SROs were directed to communicate
    to all local Bodies/Cantonment Boards of concerned areas for
    submission of applications to obtain Consent to establish/operate
    for setting up and operation of existing as well as proposed Solid
    Waste Management Facilities.
38. Admittedly, after the said date i.e. 6th September 2021, the Consent
    to Operate was granted by the MPCB on 1st November 2022. The
    said Consent to Operate has been further renewed till 30th September
    2025 and authorization to set up and operate has been granted till
    31st July 2027. It can thus clearly be seen that the MPCB started
    granting Consent only after 6th September 2021 and prior to that, it
    was only issuing a composite authorization. We find that the learned
    Tribunal has failed to take this into consideration and as such, the
    finding in that regard also deserves to be set aside.
39. The next contention is that the Checklist issued by the MPCB which
    was published in 2003 would also apply to the GPP. The learned
[2024] 9 S.C.R.                                                           391

                     Pune Municipal Corporation v.
                Sus Road Baner Vikas Manch and Others

     counsel for respondent No. 1 submitted that the said Checklist
     specifically prescribes that no development zone of 500 metres was
     required to be kept from the boundary of the landfill site. Further
     relying on the Checklist, the learned counsel submitted that the buffer
     zone of 500 metres was required to be kept from the Solid Waste
     Processing Plant as well. A perusal of the said Checklist would
     reveal that the requirement of no-development zone or a buffer zone
     is only with regards to landfill sites. It can further be seen that the
     Schedules framed under Rules 6 (1)(3) and 7 (2) of the 2000 Rules
     prescribe separate Schedules for landfill sites on one hand and
     Composting, Treated Leachates and Incineration by waste processing
     or disposal facilities on the other hand. From the said Schedule-III
     which is applicable to landfill sites, it can be seen that under clause
     9, a buffer zone of no-development is required to be maintained
     around the landfill site and the same shall be incorporated in the
     Town Planning Department’s land use plans. However, insofar as
     the Standards for Composting, Treated Leachates and Incineration
     are concerned, the same read as under:
           “3. In order to prevent pollution problems from compost
           plant and other processing facilities, the following shall be
           complied with, namely :-
                i. The incoming wastes at site shall be maintained
                prior to further processing. To the extent possible,
                the waste storage area should be covered. If,
                such storage is done in an open area, it shall be
                provided with impermeable base with facility for
                collection of leachate and surface water run-off
                into lined drains leading to a leachate treatment
                and disposal facility;
                ii. Necessary precautions shall be taken to
                minimise nuisance of odour, flies, rodents, bird
                menace and fire hazard;
                iii. In case of breakdown or maintenance of plant,
                waste intake shall be stopped and arrangements
                be worked out for diversion of wastes to the
                landfill site;
                iv. Pre-process and post-process rejects shall be
392                                                          [2024] 9 S.C.R.

                      Digital Supreme Court Reports


                removed from the processing facility on regular
                basis and shall not be allowed to pile at the site.
                Recyclables shall be routed through appropriate
                vendors. The non-recyclables shall be sent for
                well designed landfill site(s).
                v. In case of compost plant, the windrow area
                shall be provided with impermeable base. Such
                a base shall be made of concrete or compacted
                clay, 50 cm thick, having permeability coefficient
                less than 10 –7 cm/sec. The base shall be
                provided with 1 to 2 per cent slope and circled
                by lined drains for collection of leachate or
                surface run-off;
                vi. Ambient air quality monitoring shall be
                regularly carried out particularly for checking
                odour nuisance at down-wind direction on the
                boundary of processing plant.”
40. We are therefore of the considered view that the contention of the
    learned counsel for respondent No. 1 that under the 2000 Rules,
    a buffer zone is required to be maintained insofar as the GPP is
    concerned is without substance.
41. We further find that the finding of the learned Tribunal that initially the
    plot where GPP was constructed was reserved for Bio-diversity Park
    is also erroneous and factually incorrect. As discussed hereinabove,
    the plot in question has been reserved for the GPP since inception
    and it is only the adjoining plot which was reserved for the Bio-
    diversity Park.
42. We are therefore of the considered view that the learned Tribunal
    has erred in allowing the OA of the respondent No. 1 and directing
    closure of the GPP. Apart from that, we find that the closure of the
    GPP in question rather than subserving the public interest, would
    be detrimental to public interest. If the GPP in question is closed,
    the organic waste generated in the western part of Pune city would
    be required to be taken all the way throughout the city to Hadapsar
    which is in the eastern part of the city. This will undoubtedly lead to
    foul odour and nuisance to the public.
43. It will be relevant to refer to clauses (q) and (v) of Rule 15 of the
    2016 Rules, which read thus:
[2024] 9 S.C.R.                                                              393

                     Pune Municipal Corporation v.
                Sus Road Baner Vikas Manch and Others

           “15. Duties and responsibilities of local authorities
           and village Panchayats of census towns and urban
           agglomerations.- The local authorities and Panchayats
           shall,-
           …………..
           (q) transport segregated bio-degradable waste to the
           processing facilities like compost plant, bio-methanation
           plant or any such facility. Preference shall be given for on
           site processing of such waste;
           ……………
           (v) facilitate construction, operation and maintenance
           of solid waste processing facilities and associated
           infrastructure on their own or with private sector participation
           or through any agency for optimum utilization or various
           components of solid waste adopting suitable technology
           including the following technologies and adhering to the
           guidelines issued by the Ministry of Urban Development
           from time to time and standards prescribed by the Central
           Pollution Control Board. Preference shall be given to
           decentralized processing to minimize transportation cost
           and environmental impacts such as-
                a) bio-methanation, microbial composting,
                vermi-composting, anaerobic digestion or any
                other appropriate processing for bio-stabilisation
                of biodegradable waste;
                b) waste to energy processes including refused
                derived fuel for combustible fraction of waste or
                supply as feedstock to solid waste based power
                plants or cement kilns;”
44. It can thus be seen that the 2016 Rules also give preference to the
    on-site processing of the waste. It also emphasizes preference to
    be given to decentralized processing to minimize transportation cost
    and environmental impact. It has been submitted on behalf of the
    appellant-Corporation that 48 such GPPs have been commissioned
    throughout the city of Pune wherein the non-compacted, organic
    waste is segregated to remove any non-biodegradable materials
    and the residual organic waste is crushed to make a slurry. The said
394                                                         [2024] 9 S.C.R.

                         Digital Supreme Court Reports


       slurry is then transported to a site in Talegaon where raw biogas is
       generated from the slurry. At the Talegaon plant, biogas is produced
       which is used for providing fuel to the public transport buses. As
       such, the entire Project is environmentally friendly.
45. The approach of respondent No. 1 appears to be that such
    a Facility though could be established in the vicinity of the
    other buildings, it should not be established in their backyard.
    The Division Bench of the Bombay High Court in the case of
    Bhavya Height Co-operative Housing Society Ltd. v. Mumbai
    Metropolitan Region Development Authority and Others 16
    had an occasion to consider a similar situation, wherein the High
    Court observed thus:
            “36. …….. To this affidavit there are sketch plans annexed
            prepared by the Petitioner’s architects. These propose that
            the Monorail Station staircase be shifted to a point to the
            south, directly in front of Rehab Building No. 5. In other
            words, it would prima facie seem that this is the classic
            NIMBY principle — Not In My Back Yard. For what the
            Petitioner seems to be suggesting is that it is perfectly
            all right if the lives of the residents of the seven-storey
            slum rehab building (all previously slum dwellers) are
            endangered by the same staircase, but the Petitioner’s
            members’ interest must remain paramount. We cannot
            and do not countenance any such submission.”
46. We agree with the said observations of the High Court.
47. We are therefore of the considered view that the impugned judgment
    and order of the learned Tribunal deserves to be quashed and set
    aside and the OA of the respondent No. 1 is to be dismissed.
48. In the result, the appeals are allowed. The impugned judgments
    and orders dated 27th October 2020 passed by the learned Tribunal
    in OA No. 210 of 2020 and dated 22nd December 2020 in Review
    Application being No. 49 of 2020 are quashed and set aside. OA
    No. 210 of 2020 filed by respondent No. 1 is also dismissed.
49. However, before we part with the judgment, we find it necessary
    to caution the appellant-Corporation as well as the respondent-


16   2019 SCC OnLine Bom 1075
[2024] 9 S.C.R.                                                          395

                     Pune Municipal Corporation v.
                Sus Road Baner Vikas Manch and Others

     Concessionaire that they should take necessary steps so that the
     residents residing in the nearby buildings do not have to suffer on
     account of foul odour. The NEERI, in its Report, had made the
     following recommendations:
           “Recommendations:
           Based on the observations and good engineering practices,
           following suggestions are offered:
           Plant A:
           •    The slurry making area needs proper cover in the
                hopper area to reduce odour / foul smell,
           •    A suitable odour control system / misting system (e.g
                carbon filters, etc) needs to be installed immediately,
           •    Better material of construction and design could be
                employed to avoid corrosion problems and frequent
                shut downs,
           •    The space is too congested for capacity enhancement.
                PMC may think of additional/alternative space,
           •    The food bags need to be stored properly before
                using them.
           •    Slurry sampling and analysis needs to be done
                frequently to understand the decomposition of food
                waste and control it to the level so that maximum
                methane can be produced in the Talegaon plant.
           •    The technology provider must also look into reducing
                the transporting cost between slurry making facility
                at Baner and Talegaon plant by finding an optimum
                slurry density.”
50. We direct the appellant-Corporation and the respondent-
    Concessionaire to ensure that all the aforesaid suggestions made
    by NEERI should be strictly complied with. We further direct the
    appellant-Corporation to install the portable compactors with hook
    mechanisms so as to ensure that the reject waste does not touch
    the ground by 31st December 2024.
51. The appellant-Corporation is further directed to construct bitumen
    road to the Waste Segregation Plant and concrete the reject area
396                                                      [2024] 9 S.C.R.

                          Digital Supreme Court Reports


       which will enhance clean transfer of waste and avoid accumulation
       of water around the Waste Segregation Plant.
52. We further direct the appellant-Corporation as well as the respondent-
    Concessionaire to construct a shed so as to cover the reject area
    by 31st December 2024.
53. We further direct the appellant-Corporation/respondent-Concessionaire
    to carry out plantation with thick density so that there would be a
    green cover on all the sides of the GPP.
54. A perusal of the sanctioned plan would reveal that, on one side, there
    is a reservation for the Bio-diversity Park. As such, the plantation
    would be required to be done to cover the three sides.
55. Insofar as the Bio-diversity Park is concerned, we direct the State
    Government to consider the possibility of growing Miyawaki forests
    so as to provide green lungs to the nearby areas.
56. We further direct the NEERI to conduct an environmental audit of
    the GPP every six months and in turn, the appellant-Corporation
    and the respondent-Concessionaire are directed to ensure that the
    suggestions made in the said audit are strictly complied with.
57. Pending application(s), if any, shall stand disposed of.

       Result of the Case: Appeals allowed.



       †
           Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Garbage Processing Plant"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.