Created byFuzzy Cloud

Supreme Court of India

PRAKASH ASPHALTINGS AND TOLL HIGHWAYS (INDIA) LIMITEDversusMANDEEPA ENTERPRISES AND OTHERS

Citation
2025 INSC 1108
Decided
12 September 2025
Disposal
Appeal(s) allowed

Holding

The Supreme Court held that the Division Bench erred; the prohibition on changing the BOQ template under Clause 4(g) precludes any post‑tender rectification, and the order directing such rectification is set aside and quashed.

Summary

The dispute arose from an electronic tender for a Road User Fee collection contract where the appellant, Prakash Asphaltings and Toll Highways (India) Ltd, was the highest bidder and respondent No.1, Mandeepa Enterprises, was the lowest bidder. Respondent No.1 claimed it had mistakenly quoted a per‑day rate of Rs 9,72,999 instead of the total amount for the 1,095‑day contract and sought rectification, which the tendering authority rejected. The High Court Division Bench allowed the rectification, treating the quoted figure as a per‑day amount and directing the authorities to recompute the total bid, a decision the appellant challenged. The Supreme Court held that Clause 4(g) of the notice expressly forbids any change to the BOQ template, precluding post‑tender correction, and that the Division Bench’s order violated the sanctity of the tender process and the principles of natural justice. Consequently, the Supreme Court set aside and quashed the High Court’s order, allowing the appeal.

Issues considered

  • Whether the Division Bench of the High Court erred in directing rectification of respondent No.1's financial bid by treating the quoted amount as a per‑day figure and recomputing the total for the contract period.
  • Whether Clause 4(g) of the notice inviting electronic bid, which prohibits any change in the BOQ template, bars post‑tender correction of a bid.
  • Whether the non‑impleadment and non‑hearing of the appellant violated principles of natural justice.
  • Whether judicial review under Article 226 can intervene in the tendering process in the circumstances presented.

Headnote

Issue for Consideration Whether the Division Bench of the High Court fell in error in directing respondent nos. 2 to 4 to allow rectification of the financial bid of respondent no.1 by treating the amount offered by it as the per day figure and on that basis to compute for the entire contractual period of 1095 days. Headnotes† Tender – Electronic bid – A notice inviting electronic bid was issued for engaging complete Road User Fee (RUF) collection operator for RUF collection from commercial vehicles (non- passenger) at designated locations

Subjects

TenderElectronic bidRoad User Fee (RUF)Highest bidderLowest bidderBill of Quantity (BOQ)Rectification of bona fide mistakesNon-impleadmentNon-hearing of party

Judgment

                 [2025] 9 S.C.R. 794 : 2025 INSC 1108

    Prakash Asphaltings and Toll Highways (India) Limited
                             v.
             Mandeepa Enterprises and Others
                       (Civil Appeal No. 11418 of 2025)
                              12 September 2025
                 [Manoj Misra and Ujjal Bhuyan,* JJ.]


                            Issue for Consideration
       Whether the Division Bench of the High Court fell in error in directing
       respondent nos. 2 to 4 to allow rectification of the financial bid of
       respondent no.1 by treating the amount offered by it as the per
       day figure and on that basis to compute the total amount for the
       entire contractual period of 1095 days.

                                    Headnotes†
       Tender – Electronic bid – A notice inviting electronic bid was
       issued for engaging complete Road User Fee (RUF) collection
       operator for RUF collection from commercial vehicles (non-
       passenger) at designated locations – The contract period was
       for 1095 days – On opening of financial bids, it was found
       that appellant-Prakash Asphaltings and Toll Highways (India)
       Limited was the highest bidder with the quoted amount of Rs.
       91,19,00,000/- (for 1095 days) and respondent no. 1 was the
       lowest bidder (H4) at the offered amount of Rs. 9,72,999/- –
       Respondent no. 1 made a request to respondent no. 4 to change
       the rate offered by it by treating the same as per day offer
       and on that basis, figure would stand at Rs. 106,54,33,905/- –
       Prayer was rejected – Writ petition – Single Judge of the High
       Court dismissed the writ petition – However, the Division
       Bench of the High Court allowed the appeal by directing
       respondent nos. 2 to 4 to evaluate the Bill of Quantity (BOQ)
       rate of respondent no. 1 by treating Rs. 106,54,33,905/- as
       the amount for the entire contractual period of 1095 days
       instead of Rs. 9,72,999/- which was treated to be a per day
       figure – Correctness:
       Held: Clause 4 of the notice inviting electronic bid lays down the
       eligibility criteria for participation in bid – Clause 4(g) specifically


* Author
[2025] 9 S.C.R.                                                            795

       Prakash Asphaltings and Toll Highways (India) Limited v.
                 Mandeepa Enterprises and Others

     says that any change in the template of BOQ will not be accepted
     under any circumstances – Division Bench of the High Court has
     interpreted this clause in a broad way to include rectification of
     bona fide mistakes in quoting BOQ rates by the bidders – This
     provision is meant to empower the notice inviting authority to seek
     clarification or further information regarding any document filed
     by a bidder – This cannot be interpreted so broadly as to include
     rectification of the BOQ rates which is governed by Clause 4(g)
     of the notice inviting electronic bid putting a complete embargo
     to any change in the template of BOQ; the prohibition is specific:
     change in the template of BOQ will not be accepted under any
     circumstances – The view of this Court is fortified by the item
     rate BOQ of respondent no. 1 entered into figure for 1095 days –
     Therefore, though the contention of respondent no. 1 is that it
     had made an inadvertent mistake in quoting the BOQ rate of per
     day figure instead of the total contract period of 1095 days, a
     closer scrutiny would however belie such contention – Allowing
     respondent no. 1 to rectify such mistakes after finalization of the
     financial bid would be highly improper as it would have the effect
     of unsettling the entire tender process – The Division Bench of
     the High Court clearly fell in error in directing respondent nos. 2
     to 4 to allow rectification of the financial bid of respondent No. 1
     by treating the amount offered by it as the per day figure and on
     that basis to compute the total amount for the entire contractual
     period of 1095 days – Also, non-impleadment and consequential
     non-hearing of the appellant by the High Court, has vitiated the
     impugned judgment and order – Thus, impugned judgment and
     order dated 23.02.2024 passed by the Division Bench of the High
     Court cannot be sustained and is hereby set aside and quashed.
     [Paras 29-32, 43, 45]

                              Case Law Cited
     West Bengal State Electricity Board v. Patel Engineering Company
     Limited [2001] 1 SCR 352 : (2001) 2 SCC 451; Jagdish Mandal v.
     State of Orissa [2006] Supp. 10 SCR 606 : (2007) 14 SCC 517;
     Afcons Infrastructure Limited v. Nagpur Metro Rail Corporation
     Limited [2016] 3 SCR 551 : (2016) 16 SCC 818; CIDCO v. Shishir
     Realty Private Limited [2021] 13 SCR 190 : (2012) 16 SCC 527 –
     relied on.
     Johra v. State of Haryana [2018] 14 SCR 970 : (2019) 2 SCC 324;
     M/s. ABCI Infrastructures Private Limited v. Union of India, 2025
796                                                          [2025] 9 S.C.R.

                          Supreme Court Reports


       INSC 215; [2025] 3 SCR 128;Subodh Kumar Singh Rathore v.
       Chief Executive Officer [2024] 7 SCR 532 : 2024 SCC Online
       SC 1682 – referred to.
       Supreme Infrastructure India Limited v. Rail Vikas Nigam Limited,
       2012 SCC Online Delhi 616 – referred to.

                              List of Keywords
       Tender; Electronic bid; Road User Fee (RUF); Highest bidder;
       Lowest bidder; Bill of Quantity (BOQ); Rectification of bona fide
       mistakes; Non-impleadment; Non-hearing of party.

                             Case Arising From
       CIVIL APPELLATE JURISDICTION: Civil Appeal No. 11418
       of 2025
       From the Judgment and Order dated 23.02.2024 of the High Court
       at Calcutta in MAT No. 93 of 2024

                          Appearances for Parties
       Advs. for the Appellant:
       Kavin Gulati, Sr. Adv., Monish Panda, Anmol Jassal, Jatinder Bir
       Singh, Ms. Amrita Singh, Krishna Kumar Singh.
       Advs. for the Respondents:
       Anurag Soan, Akshay Saxena, Ritu Raj, Ms. Kanika, Ayush Mishra,
       Ms. Nandini Sen Mukherjee, Tuhin, Ms. Niyati Pathak, Tuhin.

                  Judgment / Order of the Supreme Court

                                  Judgment

       Ujjal Bhuyan, J.

       This civil appeal is directed against the judgment and order dated
       23.02.2024 passed by a Division Bench of the High Court at Calcutta
       (High Court) in MAT No. 93 of 2024.
2.     Be it stated that MAT No. 93 of 2024 was filed by the respondent
       No. 1 as an intra-court appeal against the final order dated 03.01.2024
       passed by a learned Single Judge of the High Court dismissing the
       writ petition, WPA No. 29001 of 2023, filed by respondent No. 1.
[2025] 9 S.C.R.                                                          797

       Prakash Asphaltings and Toll Highways (India) Limited v.
                 Mandeepa Enterprises and Others

3.   Respondent No. 1 had filed the aforesaid writ petition assailing the
     action of respondent Nos. 2, 3 and 4 (State of West Bengal and its
     officials) refusing to treat respondent No. 1 as the highest bidder
     by permitting it to rectify its financial bid after the bidding process
     was over. After observing that there was no scope for interference,
     learned Single Judge dismissed the writ petition.
4.   Aggrieved by such dismissal, respondent No. 1 preferred an intra-
     court appeal which was registered as MAT No. 93 of 2024. According
     to the Division Bench, the error in quoting the figure by respondent
     No. 1 was inadvertent; instead of quoting the price for the entire
     contract period of 1095 days, respondent No. 1 had uploaded per
     day amount of the Bill of Quantity (BOQ) of Rs. 9,72,999.00. Division
     Bench further observed that respondent No. 1 had promptly sought
     for correction of the error immediately after reopening of the price
     bids. Therefore, the Division Bench allowed the writ appeal vide the
     judgment and order dated 23.02.2024 by setting aside the order of
     the learned Single Judge, further directing respondent Nos. 2, 3
     and 4 to evaluate the BOQ rate of respondent No. 1 by treating the
     amount offered by respondent No. 1 as the per day amount and
     then on that basis to compute the total amount for the entire contract
     period of 1095 days. However, the Division Bench was of the view
     that an opportunity should be granted by the tendering authority to
     the other bidders as well to match the price of respondent No. 1 and
     thereafter to take a final decision with regard to the award of contract.
5.   It is this judgment and order which is under impugnment in the
     present proceeding.
6.   At the outset, relevant facts may be noted.
7.   A notice inviting electronic bid No. 7 of 2023-24 dated 17.10.2023
     was issued by the Superintending Engineer and Project Director,
     Project Implementation Unit – I, Public Works (Roads) Directorate,
     Government of West Bengal for engaging complete Road User Fee
     (RUF) collection operator for RUF collection from commercial vehicles
     (non-passenger) at designated locations on few roads in the State of
     West Bengal. In this case, we are concerned with the following work:
           RUF Collection with HNETC System Integration and
           Transaction Acquiring services at Fee collection plaza
           under NETC programme through NPCI approved acquirer
           bank including engagement of required man power for
798                                                            [2025] 9 S.C.R.

                           Supreme Court Reports


            operation of Road User Fee collection plaza for Dankuni
            Chandannagar Mogra in Hooghly district SH 13.
8.     The contract period is for 1095 days. While the annual potential
       collection was pegged at Rs. 21.60 crores, the earnest money deposit/
       bid security was fixed at Rs. 25,00,000.00. As per Clause 2 of the
       notice inviting electronic bid, there would be two bids: technical bid and
       financial bid, both of which would have to be submitted concurrently
       duly digitally signed in the website of the West Bengal Government.
       Clause 3 mentioned that the rates should be quoted both in words
       and in figures in specific format i.e. BOQ. In case of any discrepancy
       between words and figures, the rate quoted in words would be treated
       as the actual rate offered. After bidding, the selected bidder will be
       the H1 bidder who will offer the highest remittance for the contract
       period and will make necessary agreement with the condition that
       the accepted bid amount over the stipulated period will have to be
       deposited in advance as per payment schedule to the government
       account in lieu of RUF collection right.
9.     Clause 4 lays down the eligibility criteria for participation in the Bid.
       Clause 4(g) is very specific. It says that any change in the template
       of BOQ will not be accepted under any circumstances. Clause 4(g)
       reads thus:
            Any change in template of BOQ will not be accepted under
            any circumstances.
10. The date and time schedule of the tender process as provided in
    Clause 9 was as follows:
            9.    Date & Time Schedule:

             Particulars                  Date & Time
             1. Date of Publishing NIT 17/10/2023
                & Tender Documents
             2. D o c u m e n t S a l e / 18/10/2023 from 10.00 a.m.
                Download Start Date
             3. Pre Bid Meeting with 03/11/2023 at 1.00 p.m.
                the intending bidders at the Conference Hall
                                      of PWD at Nabanna, 8th
                                      Floor, 325, Sarat Chatterjee
                                      Road.,Howrah- 711102.
[2025] 9 S.C.R.                                                              799

        Prakash Asphaltings and Toll Highways (India) Limited v.
                  Mandeepa Enterprises and Others


            4. B i d S u b m i s s i o n / 08/11/2023 from 3.00 p.m.
               Upload Start Date
            5. B i d S u b m i s s i o n / 22/11/2023 upto 3.00 p.m.
               Upload End Date
            6. Date of opening of 24/11/2023 at 3.00 p.m.
               Technical Proposals
            7. D a t e o f o p e n i n g To be notified at the time of
               o f F i n a n c i a l B i d / publishing List of Technically
               Proposals                     Qualified Bidders in the web
                                             portal only.

11. Instructions to Bidders is part of the notice inviting electronic bid.
    Clause 5 thereof deals with submission of bids. It clarified that the
    notice inviting bid was of two bid system: (i) technical and (ii) financial,
    both to be submitted concurrently in the portal. Bidders who would
    be technically pre-qualified in respect of technical and financial
    eligibility/capability criteria would only be permitted to participate in
    the financial bidding. Bidders were required to submit online in two
    folders for each work, one being technical proposal and the other
    being financial proposal. It was clarified that at the time of uploading
    bid, care should be taken so that during evaluation, all the documents
    required to be submitted by the bidders are found in a neat, clear and
    in a readable format, otherwise the bid might be treated as cancelled.
    The instructions to bidders also clarifies that technical proposals will
    be opened by the Bid Inviting Authority (BIA) or by the Bid Evaluation
    Committee, and thereafter to upload the summary list of technically
    qualified bidders. Heading of sub-clause B is bid evaluation. As
    per sub-clause B(v), in the course of evaluation, the notice inviting
    authority may seek clarification/information or additional supporting
    documents or original hard copies of documents already submitted
    and if these are not produced by the bidders within the stipulated
    time frame, their proposals will be liable for rejection. Clause 5B (v)
    of the Instruction to Bidders is as follows:
           v. While evaluation the Notice Inviting Authority may
           summon of the bids and seek clarification/information or
           additional supporting documents or original hard copies
           against any of the documents only, which are already
           submitted/uploaded to the web portal and if these are not
800                                                         [2025] 9 S.C.R.

                           Supreme Court Reports


            produced by the intending Bidders within the stipulated
            time frame, their proposals will be liable for rejection.
12. The following seven bidders had participated in the present tender
    process. These seven bidders are as follows:
            1.     Ainul Hoque
            2.     SK Nasir.
            3.     Mandeepa Enterprises
            4.     RMN Infrastructures Limited.
            5.     M/S GVR Infra Projects Limited.
            6.     Prakash Asphaltings and Toll Highways India Ltd
            7.     Eagle Infra India Ltd.
13. Tender evaluation was carried out by a five-member screening
    committee for bid evaluation on 06.12.2023 which was constituted
    vide G.O. No. 3410-PW/O/E-1/2M-17/2017 dated 18.09.2017. After
    evaluation of the technical bids by aforesaid committee, it was found
    that out of the aforesaid total seven bidders, only four numbers of
    bidders were found to be technically qualified. Three bidders were
    found to be non eligible and declared as disqualified. The short listed
    four bidders are as follows:
            (i)    Ainul Hoque
            (ii)   Mandeepa Enterprises
            (iii) Prakash Asphaltings and Toll Highways (India) Limited
            (iv) Eagle Infra India Limited
       It was mentioned that financial bids would be opened on 08.12.2023
       at 06:30 pm.
14. Accordingly, forty eight hours after declaration of technical evaluation,
    financial bids of the four technically qualified bidders were opened
    electronically as per the e-tender mechanism. On such opening, it
    was found that the appellant Prakash Asphaltings and Toll Highways
    (India) Limited was the highest bidder with the quoted amount
    of Rs. 91,19,00,000.00 (for 1095 days). It was also found that
    respondent No. 1 was the lowest bidder (H4) at the offered amount
    of Rs. 9,72,999.00. Details of financial bid evaluation are as under:
[2025] 9 S.C.R.                                                                                 801

        Prakash Asphaltings and Toll Highways (India) Limited v.
                  Mandeepa Enterprises and Others


                              BOQ Summary Details
                Tender Title: WBPWD/PW(R)/SEPD/PIU-I/NIB-07 OF
                                 2023-24, SI-3
                      TENDER ID: 2023_WBPWD_595358_3
      Sheet SI.                  Bidder Name                        Amount                 Bid
      Name No.                                                                            Rank
      BoQ1         1     Prakash Asphaltings and               911900000.00                 H1
                         Toll Highways India Ltd.
                   2     Eagle Infra India Ltd.                783899999.00                 H2
                   3     Ainul Hoque                           652176525.00                 H3
                   4     Mandeepa Enterprises                  972999.00                    H4

15. Since much hinges on this, we may extract the item rate BOQ of
    respondent No. 1 which is as under:
                                          Item Rate BoQ
     Tender Inviting Authority: Superintending Engineer & Project
     Director, Project Implementation Unit-I.
     Name of Work: RUF Collection with HNETC System Integration
     and Transaction Acquiring services at Fee collection plaza
     under NETC programme through NPCI approved acquirer bank
     including engagement of required man power for operation
     of Road User Fee collection plaza for Dankuni Chandannagar
     Mogra in Hooghly district SH 13.
     Contract No: SL No. 3 of eNIB No. 07 of 2023-2024 of S.E. &
     PD/PIU-I
      Name of the Bidder/Bidding Firm/Company:                          Mandeepa Enterprises
                                           PRICE SCHEDULE
      (This BOQ template must not be modified/replaced by the bidder and the same should be
      uploaded after filling the relevant columns, else the bidder is liable to be rejected for this
      tender. Bidders are allowed to enter the Bidder Name and Values only)
      NUM TEXT#               NUM TEXT# NUMBER#                      NUMBER# TEXT#
      BER#                    BER#
      SL.    Name of the   Qua        Units   Amount of Road         TOTAL        TOTAL
      No.    road on which ntity              User Fee in Figures    AMOUNT AMOUNT
             Road User                        To be entered by       (in figures) In Words
             Fee Plaza is                     the Bidder for 1095    exclusive of
             situated                         Days Rs. P             all taxes
802                                                                    [2025] 9 S.C.R.

                                 Supreme Court Reports



       1.     RUF Collection     1   Nos   972999.00           972999.00   INR Nine Lakh
              with HNETC                                                   Seventy Two
              System                                                       Thousand
              Integration and                                              Nine Hundred
              Transaction                                                  & Ninety Nine
              Acquiring                                                    Only
              services at Fee
              collection plaza
              under NETC
              progr-amme
              through NPCI
              approved
              acquirer bank
              including
              engagement
              of required
              man power
              for operation
              of Road User
              Fee collection
              plaza for
              Dankuni
              Chandannagar
              Mogra in
              Hoogly
              district SH 13.
              (Scope of work
              as per terms
              and condition
              laid down in
              the NIB)
       Total in Figures                                        972999.00   INR Nine Lakh
                                                                           Seventy Two
                                                                           Thousand
                                                                           Nine Hundred
                                                                           & Ninety Nine
                                                                           Only
       Quoted Rate in Words      INR Nine Lakh Seventy Two Thousand Nine Hundred & Ninety
                                 Nine Only

16. After the financial bids were opened and became public, respondent
    No. 1 made a request to the tender committee vide e-mail dated
    13.12.2023. The e-mail was accompanied by an affidavit stating that
    the amount offered was per day rate and that the said figure should be
    worked out for the total contract period of 1095 days in which event,
    the offer of respondent No. 1 would stand at Rs. 106,54,33,905.00
[2025] 9 S.C.R.                                                                803

          Prakash Asphaltings and Toll Highways (India) Limited v.
                    Mandeepa Enterprises and Others

     for the contract period. The tendering authority was requested to treat
     the figure of Rs. 9,72,999.00 as a typographical error and the figure
     offered by respondent No. 1 should be read as 106,54,33,905.00.
     The authority was further requested to consider the same keeping
     higher revenue in mind.
17. It appears that vide communication dated 20.12.2023, respondent No.
    4 rejected the prayer of respondent No. 1 stating that such request
    for correction of financial bid was not possible to be entertained as
    it would impeach the sanctity of the tender process.
18. Thereafter, respondent No. 1 filed a writ petition before the High
    Court seeking the following reliefs:
     a)     Leave under Rule 26 of the Rules relating to petitions
            under Article 226 of the Constitution of India to move
            the writ petition before service of copy of the petition be
            granted to the petitioner to move the writ petition before
            service of copy thereof, in view of extreme urgency as
            narrated hereinabove;
     b)     A Writ of Mandamus directing the respondents and each
            of them esp., the respondent No. 3, to rescind and/or
            cancel and/or withdraw the letter rejecting the prayer of
            the petitioner to amend the rate quoted by the petitioner
            in the bid in respect of the tender process being Annexure
            “P-1”to the petition forthwith;
     c)     A Writ of Mandamus directing the respondent No. 3 to allow
            the petitioner to amend and/or rectify the petitioner’s bid
            in respect of the tender process dated 17th October, 2023
            being Annexure “P-1” hereto by quoting the rate for 1095
            days instead or one day treating the same as bonafide and
            inadvertent mistake of the petitioner and then to consider
            the bid of the petitioner in the financial bid upon rectification
            of the same in terms of the prayers of the petitioner made
            in the letters and documents submitted by the petitioner on
            13.12.2023, 15.12.2023 and 20.12.2023 in respect of the
            tender process dated 17th October, 2023 being Annexure
            “P-5”, “P-6” and “P-7”· hereto;
     d)     A writ of Certiorari calling upon the respondents and each
            of them to certify and transmit all records in respect of
804                                                           [2025] 9 S.C.R.

                           Supreme Court Reports


            tender having Memo No. 590-R/PIU-I dated 17th October,
            2023 being notice inviting Electronic Bid No. 07-2023-24
            by the Superintending Engineer/ Project Director Unit-I
            Public Works (Roads) Directorate being Annexure “P-1”
            hereto and all subsequent letters and correspondences
            being Annexure “P-2” to “P-8” hereto to this Hon’ble Court
            so that conscionable justice may be done by quashing and/
            or setting aside the letter of rejection by the respondent
            No.3 dated 20th December, 2023 being Annexure “P-8”
            hereto and by directing the respondent No. 3 to allow the
            petitioner to rectify and/ or amend the bid for 1095 days
            and further process the bid of the petitioner upon such
            rectification in the financial bid of the said tender process
            being Annexure “P-1” hereto;
       e)   A Writ of Prohibition prohibiting the respondents and each
            of them, esp., the respondent No. 3 from indulging any
            further non-action and/or inaction in allowing the petitioner
            from rectifying the bid of the petitioner for l095 days and
            from further taking any steps for issuing the Letter of
            Acceptance (LOA) to the H-1 bidder in respect of the said
            tender process being Annexure “P-1” hereto;
       f)   Interim order directing the respondents and each of them,
            esp., the respondent No. 3 from proceeding further in the
            tender process being Annexure “P-1” hereto including
            issuing the Letter of Acceptance (LOA) to the H-1 bidder
            in respect of the tender process being Annexure “P-1”
            hereto till the disposal of the writ petition;
       g)   Ad-interim order of terms of prayer (f) above;
       h)   Rule NISI in terms of prayers (a), (b), (c), (d), (e), (f) and
            (g) above;
       i)   Costs;
       j)   Such further or other order or orders be passed and/or
            direction or directions be given as this Hon’ble Court may
            deem fit and proper.
19. The writ petition was registered as W.P.A. No. 29001 of 2023. A
    Single Bench of the High Court dismissed the writ petition vide the
    order dated 03.01.2024 by holding as under:
[2025] 9 S.C.R.                                                           805

       Prakash Asphaltings and Toll Highways (India) Limited v.
                 Mandeepa Enterprises and Others

           8.   Bona fides cannot be attributed to the petitioner;
                rather, the petitioner was grossly negligent, since the
                price schedule indicated in the BOQ, which found
                place even in the bid of the petitioner itself, clearly
                showed that the amount of Road User Fee in the
                figures was to be entered by the bidder for 1095 days.
                Even after knowing the same and being aware of the
                various amounts involved by way of annual potential
                collection and bid security, the petitioner committed
                the error which it did.
           9.   After the financial bid was opened, the petitioner
                wrote to the tender issuing authorities. If such an
                opportunity is to be given to a particular bidder, the
                same would upset the entire tender process and, as
                rightly argued by the respondents, would make the
                tender process opaque and arbitrary.
           10. The petitioner, with its eyes open, participated in
               the bid and quoted an erroneous amount. As such,
               the petitioner ought to suffer for the same and take
               responsibility therefor. Even if the petitioner’s bid, if
               taken to be for 1095 days, would far exceed the next
               highest bid, such opportunity cannot be given to the
               petitioner to rectify its error after the entire bidding
               process was over and the financial bids of all the
               bidders were opened. Such chance, if given to the
               petitioner, would be contrary to every known principle
               of fairness pertaining to tenders and would amount
               to a special favour being extended to the petitioner
               for no particular reason.
           11. Thus, there is no scope of interference in the tender
               process.
20. Aggrieved thereby, respondent No. 1 preferred a letters patent appeal
    before the Division Bench of the High Court which was registered as
    MAT No. 93 of 2024. Vide the judgment and order dated 23.02.2024,
    the Division Bench of the High Court observed as under:
           8.       *        *           *           *            *
                Thus, in the light of the above undisputed factual
                position we are of the considered view that the Tender
806                                                        [2025] 9 S.C.R.

                        Supreme Court Reports


               Inviting Authority had sufficient leverage and play in
               the joints to seek for any clarification or information
               during the entire evaluation process and sub-clause
               (b) of clause 5 of the Instruction to Bidders is not
               restricted to the stage of evaluation of the technical
               bid along but it encompasses the evaluation of the
               entire tender right from the stage of inception till the
               issuance of work order. This interpretation is proper
               interpretation that should be given to the said clause
               or else it would put shackles on the right of the Tender
               Inviting Authority. The explanation offered by the
               appellant is acceptable and the appellant’s offer is
               Rs.16 crore over and above the highest offer which
               is now come to the light after the financial bid has
               been opened.
          9.   For the above reasons, the appeal is allowed and
               order passed in the writ petition is set aside and
               the writ petition is allowed and the respondents are
               directed to evaluate the appellant’s BOQ by taking
               the amount of Rs.106,54,33,905.00 for the period
               of 1095 days as called for in the tender notification.
          10. Since admittedly the affidavit for correction of the bid
              document was submitted after opening the financial
              bid, this Court feels that an opportunity is to be
              granted to other bidders to match the price quoted
              by the writ petitioner. The Tender Inviting Authority
              shall call upon all the bidders who were found to
              be technically qualified including the petitioner and
              after evaluating the bids of all such bidders and after
              giving opportunity to the other bidders, who are found
              technically qualified, to match the corrected figures
              quoted by the writ petitioner shall take a final decision
              with regard to award of the contract in question.
21. It may be mentioned that both before the learned Single Judge as
    well as before the Division Bench, appellant was not arrayed as a
    party respondent, though on evaluation of the financial bids, it was
    found to be the highest bidder (H1).
22. Aggrieved by the aforesaid judgment and order dated 23.02.2024,
    appellant preferred the related special leave petition. By order dated
[2025] 9 S.C.R.                                                         807

       Prakash Asphaltings and Toll Highways (India) Limited v.
                 Mandeepa Enterprises and Others

     27.05.2024, this Court granted permission to the appellant to file the
     special leave petition. While issuing notice, this Court also stayed
     the impugned judgment and order dated 23.02.2024. Thereafter, the
     matter was heard on 08.08.2025 when leave was granted.
23. Mr. Kavin Gulati, learned senior counsel for the appellant submits that
    after the financial bids were opened, appellant was found to be and
    was declared as the highest (H1) bidder by the tendering authority
    on 13.12.2023. Admittedly, respondent No. 1 sought rectification/
    correction of its financial bid only after the financial bids were opened
    and only after the appellant was declared as H1. The tendering
    authority was fully justified in rejecting the request of respondent
    No. 1 for rectification/correction of its financial bid.
     23.1. Learned Single Judge was justified in observing that if the
           opportunity as sought for by respondent No. 1 is allowed,
           the same would upset the entire tender process. Learned
           Single Judge had rightly observed that respondent No. 1 had
           participated in the tender process with its eyes wide open
           and had quoted an erroneous amount. Even if its bid taken
           for the entire contract period exceeds the highest bid, such
           opportunity for rectification cannot be given to respondent
           No. 1 to rectify its error after the entire bidding process was
           over and the financial bids of all the tenderers were opened.
           If this is accepted and respondent No. 1 is given such an
           opportunity, it would be contrary to every known principle of
           fairness pertaining to tenders and would amount to a special
           favour being extended to respondent No. 1 for no particular
           reason. Learned senior counsel submits that the view taken
           by the learned Single Judge is the correct view and should not
           have been interfered with by the Division Bench in a letters
           patent appeal.
     23.2. Mr. Gulati submits that in the proceedings before the learned
           Single Judge, appellant was not made a party respondent
           though it was the highest (H1) bidder. Though the relief claimed
           by respondent No. 1, if granted, would have adversely affected
           the appellant, this issue did not arise because the learned
           Single Judge did not accept the contentions of respondent
           No. 1 and had declined to interfere with the tender process.
     23.3. However, in the intra-court appeal before the Division Bench,
           respondent No. 1 again did not array the appellant as a party
808                                                         [2025] 9 S.C.R.

                          Supreme Court Reports


             respondent. Division Bench took the view that the tendering
             authority had sufficient leverage and play in the joints to seek
             any clarification or information during the tender evaluation
             process. Learned senior counsel submits that the Division
             Bench had interpreted Clause 5B(v) of the Instructions to
             Bidders erroneously to hold that the tendering authority had
             the discretion to seek any clarification or information at any
             stage of the tender process right from the stage of inception
             till issuance of the work order and thereafter to hold that any
             other interpretation would put shackles on the functioning of
             the tendering authority. Learned senior counsel submits that
             the aforesaid view taken by the Division Bench is palpably
             erroneous having the effect of unsettling the entire tender
             process. Clause 5B(v) of the Instructions to Bidders cannot
             be given such a broad interpretation. Referring to Clause 4(g)
             of the tender conditions, he submits that it is clear therefrom
             that change of Bill of Quantity (BOQ) would not be accepted
             under any circumstances. If the view of the Division Bench
             is accepted, there would be no finality attached to a tender
             process which in turn would impeach the sanctity of the tender
             process itself.
       23.4. Learned senior counsel further submits that the final direction
             of the Division Bench directing the tendering authority to
             evaluate the BOQ of respondent No. 1 not at Rs. 9,72,999.00
             which it held to be per day figure but to accept respondent
             No. 1’s BOQ at Rs. 106,54,33,905.00 for the entire contract
             period has changed, the entire complexion of the tendering
             process thereby rendering the position of the appellant wholly
             untenable despite being declared as the highest (H1) bidder
             by the tendering authority. This direction of the Division Bench
             entails adverse civil consequences upon the appellant. Despite
             being so, the Division Bench did not deem it appropriate to
             get the appellant impleaded in the appellate proceedings.
             Consequently, no notice was issued or opportunity of hearing
             granted to the appellant by the Division Bench before disposing
             of the intra-court appeal. This is in clear violation of the
             principles of natural justice.
       23.5. According to him, the reasoning adopted by the Division
             Bench is highly questionable. Division Bench has taken the
[2025] 9 S.C.R.                                                             809

        Prakash Asphaltings and Toll Highways (India) Limited v.
                  Mandeepa Enterprises and Others

              view that if the BOQ amount of respondent No. 1 is read as
              Rs. 106,54,33,905.00, the difference between the amount
              quoted by respondent No. 1 and what is being offered by
              the H1 bidder i.e. the appellant would be about 15 crores
              and this additional amount would enure to the benefit of the
              state exchequer. He submits that collecting higher revenue
              is only one facet of public interest. The other aspect, which
              is more important, is that because of the avoidable litigation
              instituted by respondent No. 1, the State could not timely start
              the contract work. As a result, it lost considerable amount of
              revenue. However, this aspect of the matter was overlooked
              by the Division Bench. He reiterates that if the view taken by
              the Division Bench is accepted then there would be no finality
              to a tender process.
     23.6. Learned senior counsel to buttress his arguments has
           submitted a compilation of judgments. Additionally, he has
           also placed reliance on few other judgments. The decisions
           relied upon by learned counsel for the appellant are as under:
              (i)      West Bengal State Electricity Board Vs. Patel
                       Engineering Company Limited1
              (ii)     Jagdish Mandal Vs. State of Orissa2
              (iii) Afcons Infrastructure Limited Vs. Nagpur Metro Rail
                    Corporation Limited 3
              (iv) Johra Vs. State of Haryana4
              (v)      M/s. ABCI Infrastructures Private Limited Vs. Union
                       of India5
     23.7. Finally, learned senior counsel submits that whether on account
           of violation of the principles of natural justice or on the point
           of unduly interfering with a tender process, the impugned
           judgment and order of the Division Bench cannot be sustained.
           Therefore, the same is liable to be set aside and quashed.


1   (2001) 2 SCC 451
2   (2007) 14 SCC 517
3   (2016) 16 SCC 818
4   (2019) 2 SCC 324
5   2025 INSC 215
810                                                         [2025] 9 S.C.R.

                          Supreme Court Reports


24. Mr. Anurag Soan, learned counsel appearing for respondent No. 1 has
    opposed the challenge made by the appellant. He submits that the
    Division Bench has rightly observed that the tendering authority have
    the leverage to consider the clarifications as sought for by respondent
    No. 1. According to him, the mistake committed by respondent No. 1
    was a bona fide one and completely unintentional. Since ordinarily,
    the rates sought for and offered in the tenders floated in the State of
    West Bengal are on the basis of per day figures, respondent No. 1
    offered per day BOQ figure whereas the figure ought to have been
    a consolidated one for the entire contractual period of 1095 days.
    This inadvertent mistake was detected only when the financial bids
    were opened and without loss of time, respondent No. 1 promptly
    e-mailed the tendering authority pointing out the mistake and sought
    for rectification. This was supported by an affidavit. If the BOQ amount
    of respondent No. 1 for the entire contractual period is calculated
    based on the per day rate, the bid offer of respondent No. 1 would
    be by far the highest; by an amount of Rs. 15 crores over the bid
    value of the appellant. Therefore, there was no reason why the
    tendering authority should have ignored the rectification effort of
    respondent No. 1.
       24.1. Learned counsel submits that to the extent the Division Bench
             held that the tendering authority had the leverage to consider
             such clarification, the decision is in favour of respondent
             No. 1. However, the Division Bench ought to have declared
             respondent No. 1 as the highest bidder because that would
             be the natural consequence of acceptance of respondent
             No. 1’s rectification effort. But the direction of the Division
             Bench to the state authorities to provide an opportunity to the
             other bidders to match the BOQ figure of respondent No. 1 is
             completely unwarranted. Viewed in that context, though the
             intra-court appeal has been decided in favour of respondent
             No. 1, it has actually been denied the consequential relief.
       24.2. Mr. Soan submits that the BOQ figure offered by respondent
             No. 1 was highest (H1) from day one; it was an inadvertent
             mistake to declare the said amount as per day figure instead
             of computing the total amount for the entire contractual period.
             He submits that there is a material difference between a total
             revision of price by quoting a new amount and clarifying the
             existing price. The case of respondent No. 1 falls in the latter
             category.
[2025] 9 S.C.R.                                                         811

        Prakash Asphaltings and Toll Highways (India) Limited v.
                  Mandeepa Enterprises and Others

     24.3. Regarding non-joinder of appellant as a party respondent,
           learned counsel for respondent No. 1 submits that respondent
           no. 1 had approached the High Court seeking a writ of
           mandamus against respondent No. 4 to allow rectification/
           clarification of its financial bid owing to inadvertent mistake
           and also sought for quashing of the rejection letter dated
           20.12.2023 issued by respondent No. 4 whereby the request
           for rectification/clarification of financial bid by respondent No.
           1 was rejected. No relief was sought for against the appellant.
           Evidently, bid of respondent No. 1 is substantially higher than
           that of the appellant. Public at large would have benefitted
           by such rectification/clarification. Therefore, non-joinder of
           appellant as respondent to the proceedings before the High
           Court is not fatal. Consequently, it cannot be said that there
           is any violation of the principles of natural justice.
     24.4. Learned counsel has referred to Clause 5B(v) of the Instructions
           to Bidders which empowers the tendering authority to seek
           clarification of the documents submitted by the bidders.
           In terms of Clause D(ii) of the notice inviting bid, both the
           technical bid and the financial bid were required to be submitted
           simultaneously. Division Bench has correctly interpreted Clause
           5B(v) of the Instructions to Bidders and such interpretation
           warrants no interference. Learned counsel for respondent No.
           1 submits that the clarified financial bid of respondent No. 1
           should be accepted in the light of the larger public interest
           otherwise the State would lose revenue by about 15 crores.
           Public exchequer should not be made to suffer because of an
           inadvertent mistake in quoting the BOQ figure by respondent
           No. 1. In this connection, learned counsel has placed reliance
           on a decision of the Delhi High Court in the case of Supreme
           Infrastructure India Limited Vs. Rail Vikas Nigam Limited6 in
           which case, rectification/clarification was allowed by the Delhi
           High Court.
     24.5. Learned counsel further submits that matters relating to tender
           and awarding of contract are essentially commercial functions.
           In such matters, principles of equity and natural justice should
           be kept at a distance.


6   2012 SCC Online Delhi 616
812                                                            [2025] 9 S.C.R.

                           Supreme Court Reports


       24.6. Learned counsel for respondent No. 1 submits that the mistake
             committed by respondent No. 1 was so apparent when
             compared with the annual potential collection of the contract
             which is estimated in crores and the bid security is fixed at
             Rs. 25 lakhs. Therefore, there was no reason for respondent
             No. 1 to quote a figure of Rs. 9,72,000.00 as the bid price for
             the entire contractual period of 1095 days. In the absence of
             any allegation of malafides or collusion or fraud, respondent
             No. 1’s right to request for clarification was correctly allowed
             by the Division Bench.
       24.7. Clarifying the position, learned counsel submits that in an earlier
             bid process in which respondent No. 1 participated, per day
             figure was sought for. It was because of this that there was
             confusion and respondent No. 1 followed the same protocol
             in the present case. It was only when the financial bid was
             opened that respondent No. 1 realised the inadvertent mistake.
             Rectification of such apparent mistakes can in no manner be
             said to vitiate the sanctity of the tender process as respondent
             No. 1 is also a technically qualified bidder.
       24.8. In the facts and circumstances of the case, learned counsel
             submits that no case for interference in the impugned judgment
             is made out by the appellant and, therefore, the appeal is
             liable to be dismissed.
25. Ms. Nandini Sen Mukherjee, learned counsel appearing for respondent
    Nos. 2 to 4, at the outset submits that though the State has not
    challenged, the impugned judgment and order of the Division Bench,
    nonetheless it is ad idem with the appellant who has questioned the
    impugned directions of the Division Bench.
       25.1. Learned counsel submits that both on the issue of violation of
             the principles of natural justice and interference with an ongoing
             tender process by a court in a proceeding under Article 226
             of the Constitution of India, the impugned judgment and order
             cannot be sustained.
       25.2. She submits that both appellant and respondent No. 1
             alongwith two other bidders were found to be technically
             qualified. Thereafter, when the financial bids were opened, it
             was found that the bid offered by the appellant was the highest
[2025] 9 S.C.R.                                                        813

       Prakash Asphaltings and Toll Highways (India) Limited v.
                 Mandeepa Enterprises and Others

            and therefore it was declared as H1. On the other hand, bid
            of respondent No. 1 was found to be the lowest. Accordingly,
            the tendering authority had finalized the bidders. Therefore,
            when respondent No. 1 moved the High Court and the Division
            Bench had substantially granted relief to respondent No. 1
            having the potential to upset the financial bids of the bidders
            as finalized by the tendering committee, it was necessary
            that appellant should have been made a party respondent in
            the proceedings before the High Court. As the appellant was
            not put to notice and was not heard, the impugned directions
            which are prejudicial to the appellant cannot be sustained.
     25.3. Ms. Mukherjee further submits that the sanctity of the entire
           tender process would be affected in case the corrections
           suggested by the Division Bench are sustained. This would not
           only be unfair to the bidders higher in rank than respondent
           No. 1 but has unduly delayed finalisation of the contract.
     25.4. After adverting to the facts of the case, learned counsel
           representing respondent Nos. 2 to 4 submits that in the
           BOQ template contained in the tender papers, it was clearly
           mentioned that the rate was to be quoted for the entire duration
           of the contractual period i.e. for 1095 days. Therefore, the
           assertion of respondent No. 1 that it had inadvertently quoted
           rate on per day basis instead of 1095 days cannot be accepted.
           In this connection, learned counsel has also referred to Clause
           4(g) of the notice inviting bid which clearly prohibits change
           in the template of BOQ. This type of post tender modification
           of quoted rate as sought for by respondent No. 1 is not at
           all permissible. In fact, because of this attempt on the part of
           respondent No. 1, finalisation of the contract has been unduly
           delayed which in turn has affected collection of government
           revenue.
     25.5. Elaborating further, learned counsel for respondent Nos. 2 to
           4 submits that respondent No. 1 did not mention anywhere in
           its bid that the rate quoted by it was on ‘per day’ basis. It was
           only after opening of the financial bid that respondent No. 1
           claimed that the quoted rate was on per day basis. Respondent
           No. 4 had rightly rejected such request construing it to be an
           attempt to influence the bidding process.
814                                                        [2025] 9 S.C.R.

                          Supreme Court Reports


       25.6. In these circumstances, learned counsel submits that the
             Division Bench was not justified in setting aside the order of
             the learned Single Judge and by directing respondent Nos.
             2 to 4 to accept the computed bid of respondent No. 1 by
             converting the figure from per day basis to the entire contract
             period of 1095 days and thereafter to make an analysis with
             the bids offered by the other bidders. In view of a catena of
             judgments of this Court, such interference by a writ court is
             simply not permissible.
       25.7. Learned counsel therefore submits that as a matter of fact,
             following the impugned judgment and order, all the four
             technically qualified bidders were called upon to submit
             their sealed bids afresh for 1095 days keeping the rates of
             106,54,33,905.00 as the minimum. However, after this Court
             granted stay, the aforesaid process has been cancelled.
       25.8. Learned counsel finally submits that permitting an unsuccessful
             bidder to raise grievance after opening of the financial bid
             would set a bad precedent. If it is permitted, grievance of all
             kinds and of all sorts would be forthcoming and the contracts
             would never get executed.
26. Submissions made by learned counsel for the parties have received
    the due consideration of the Court.
27. Though we have adverted to the facts in the preceding paragraphs,
    nonetheless for a proper appreciation it would be apposite to briefly
    sum up the factual contours of the present controversy.
28. The contract in question relates to RUF collection at fee collection
    plaza for Dankuni Chandannagar Mogra section of SH 13 in the District
    of Hooghly, West Bengal. In terms of the notice inviting electronic
    bid dated 17.10.2023, the contract period is for 1095 days. While
    the annual potential collection was pegged at Rs. 21.60 crores, the
    earnest money deposit/bid security was fixed at Rs. 25,00,000.00.
    The tender comprised of two bid system: technical bid and financial
    bid to be submitted concurrently digitally in the website of the West
    Bengal Government. The rates should be quoted in both words and
    figures in BOQ format. In case of any discrepancy between words
    and figures, the rate quoted in words would be accepted as the
    actual rate offered. After the bidding process, the selected bidder
[2025] 9 S.C.R.                                                          815

       Prakash Asphaltings and Toll Highways (India) Limited v.
                 Mandeepa Enterprises and Others

     will be treated as H1 bidder who will offer the highest remittance for
     the contract period. The eligibility criteria made it clear that under no
     circumstances, change in template of BOQ will be accepted.
     28.1. In all, total of seven bidders had participated in the tender
           process out of which four were shortlisted by the screening
           committee on 06.12.2023 as being technically qualified. These
           four included appellant and respondent No. 1.
     28.2. Thereafter, financial bids of the four technically qualified
           bidders were opened. On such opening, it was found that
           the bid offered by the appellant at Rs. 91,19,00,000.00 for
           1095 days was found to be the highest (H1) whereas the bid
           offered by respondent No. 1 at Rs. 9,72,999.00 was found to
           be the lowest (H4).
     28.3. After the financial bids were opened and finalized, respondent
           No. 1 made a request to respondent No. 4 vide email dated
           13.12.2023 to change the rate offered by it by treating the
           same as per day offer and on that basis, to compute the
           amount for the entire contractual period of 1095 days which
           figure would stand at Rs. 106,54,33,905.00. It was contended
           that respondent No. 1 was therefore the highest bidder and its
           rate was more than Rs. 15 crores above that of the appellant.
           The mistake committed by it was an inadvertent one. Since it
           would be beneficial to the public exchequer, respondent No.
           4 was requested to correct the inadvertent mistake.
     28.4. This prayer of respondent No. 1 was rejected by respondent
           No. 4 vide the communication dated 20.12.2023.
     28.5. Thereafter, respondent No. 1 filed a writ petition before the
           High Court being WPA No. 29001/2023. A learned Single
           Judge of the High Court dismissed the writ petition vide the
           order dated 03.01.2024.
     28.6. Aggrieved thereby, respondent No. 1 preferred a letters patent
           appeal before the Division Bench of the High Court being MAT
           No. 93 of 2024. Vide the judgment and order dated 23.02.2024,
           the Division Bench allowed the appeal by directing respondent
           Nos. 2 to 4 to evaluate the BOQ rate of respondent No. 1 by
           treating Rs. 106,54,33,905.00 as the amount for the entire
           contractual period of 1095 days instead of Rs. 9,72,999.00
816                                                          [2025] 9 S.C.R.

                          Supreme Court Reports


            which was treated to be a per day figure. However, since the
            other bidders were not before the court, it was directed that
            opportunity be granted to such bidders to match the price
            quoted by respondent No. 1. After evaluating the bids of all
            such bidder, the said respondents were directed to take a
            final decision with regard to award of the contract in question.
29. Having noted the factual backdrop of the case, let us now examine
    the relevant provisions of the tender conditions. We have already
    noted that Clause 4 of the notice inviting electronic bid lays down
    the eligibility criteria for participation in bid. Clause 4(g) specifically
    says that any change in the template of BOQ will not be accepted
    under any circumstances. Clause 5 of the Instructions to Bidders
    which form part of the notice inviting electronic bid cautions the
    bidders that care should be taken so that during evaluation of the
    documents submitted by the bidders those are found to be neat
    and clear and in a readable format, otherwise the bid would be
    treated as cancelled. Clause 5B of the Instruction to Bidders deals
    with bid evaluation. Clause 5B(v) says that during the process of
    evaluation of bids, the notice inviting authority may summon and
    seek clarification/information on additional supporting documents or
    original hardcopies against any of the documents which are already
    submitted/uploaded in the web portal. In the event, these are not
    produced by the intending bidders within the stipulated time frame,
    their proposals will be liable for rejection.
30. Division Bench of the High Court has interpreted this clause in a
    broad way to include rectification of bona fide mistakes in quoting
    BOQ rates by the bidders. In our view, this will be stretching things
    a bit too far. This provision is meant to empower the notice inviting
    authority to seek clarification or further information regarding any
    document filed by a bidder. This cannot be interpreted so broadly
    as to include rectification of the BOQ rates which is governed by
    Clause 4(g) of the notice inviting electronic bid putting a complete
    embargo to any change in the template of BOQ; the prohibition is
    specific: change in the template of BOQ will not be accepted under
    any circumstances.
31. Our view is fortified by the item rate BOQ of respondent No. 1 which
    we have extracted in paragraph 15 of this judgment. In column 5, the
    heading is : amount of road user fee in figures to be entered by the
[2025] 9 S.C.R.                                                              817

       Prakash Asphaltings and Toll Highways (India) Limited v.
                 Mandeepa Enterprises and Others

     bidder for 1095 days. As against this, respondent No. 1 quoted the
     figure of Rs. 9,72,999.00. In words, i.e. in column 6, the quoted rate
     was mentioned as nine lakhs seventy two thousand nine hundered
     and ninety nine only.
32. Therefore, though the contention of respondent No. 1 is that it had
    made an inadvertent mistake in quoting the BOQ rate of per day
    figure instead of the total contract period of 1095 days, a closer
    scrutiny would however belie such contention. In columns 5, 6
    and 7, respondent No. 1 filled up the amount in figures and words
    as Rs. 9,72,999.00 and Rupees nine lakhs seventy two thousand
    nine hundred and ninety nine respectively for 1095 days. In such
    circumstances, it cannot be said to be an inadvertent or unintentional
    mistake, as is being contended on behalf of respondent No. 1.
    Therefore, allowing respondent No. 1 to rectify such mistakes after
    finalization of the financial bid would be highly improper as it would
    have the effect of unsettling the entire tender process.
33. In Patel Engineering Company Limited (supra), this Court had rejected
    a similar contention that the mistakes were unintentional and had
    occurred due to fault of the computer in the following manner:
                23. The mistakes/errors in question, it is stated,
                are unintentional and occurred due to the fault of
                computer termed as “a repetitive systematic computer
                typographical transmission failure”. It is difficult to
                accept this contention. A mistake may be unilateral or
                mutual but it is always unintentional. If it is intentional
                it ceases to be a mistake. Here the mistakes may
                be unintentional but it was not beyond the control
                of Respondents 1 to 4 to correct the same before
                submission of the bid. Had they been vigilant in
                checking the bid documents before their submission,
                the mistakes would have been avoided. Further,
                correction of such mistakes after one-and-a-half
                months of opening of the bids will also be violative
                of clauses 24.1, 24.3 and 29.1 of the ITB.
     33.1. This Court also held that tenders are invited on the basis of
           competitive bidding. On the one hand, it offers a fair opportunity
           to all those who are interested in competing for the contract and
           on the other hand it affords the authority a choice to select the
818                                                          [2025] 9 S.C.R.

                         Supreme Court Reports


            best of competitors on a competitive price without prejudice to
            the quality of the work. Above all, it eliminates favoritism and
            discrimination in allotting public works to contractors. While
            benefit to the public exchequer is certainly an important criteria
            in award of contract, it is equally in public interest to adhere
            to the rules and conditions subject to which bids are invited.
34. This Court in Jagdish Mandal (supra) after referring to earlier decisions
    of this Court succinctly summed up the scope of judicial review of
    award of contracts and held thus:
          22. Judicial review of administrative action is intended to
          prevent arbitrariness, irrationality, unreasonableness, bias
          and mala fides. Its purpose is to check whether choice
          or decision is made “lawfully” and not to check whether
          choice or decision is “sound”. When the power of judicial
          review is invoked in matters relating to tenders or award
          of contracts, certain special features should be borne in
          mind. A contract is a commercial transaction. Evaluating
          tenders and awarding contracts are essentially commercial
          functions. Principles of equity and natural justice stay at
          a distance. If the decision relating to award of contract
          is bona fide and is in public interest, courts will not, in
          exercise of power of judicial review, interfere even if a
          procedural aberration or error in assessment or prejudice
          to a tenderer, is made out. The power of judicial review will
          not be permitted to be invoked to protect private interest at
          the cost of public interest, or to decide contractual disputes.
          The tenderer or contractor with a grievance can always
          seek damages in a civil court. Attempts by unsuccessful
          tenderers with imaginary grievances, wounded pride and
          business rivalry, to make mountains out of molehills of
          some technical/procedural violation or some prejudice to
          self, and persuade courts to interfere by exercising power
          of judicial review, should be resisted. Such interferences,
          either interim or final, may hold up public works for years,
          or delay relief and succour to thousands and millions
          and may increase the project cost manifold. Therefore, a
          court before interfering in tender or contractual matters in
          exercise of power of judicial review, should pose to itself
          the following questions:
[2025] 9 S.C.R.                                                             819

       Prakash Asphaltings and Toll Highways (India) Limited v.
                 Mandeepa Enterprises and Others

                (i) Whether the process adopted or decision made
                by the authority is mala fide or intended to favour
                someone;
                or
                Whether the process adopted or decision made is
                so arbitrary and irrational that the court can say: “the
                decision is such that no responsible authority acting
                reasonably and in accordance with relevant law could
                have reached”;
                (ii) Whether public interest is affected.
           If the answers are in the negative, there should be no
           interference under Article 226. Cases involving blacklisting
           or imposition of penal consequences on a tenderer/
           contractor or distribution of State largesse (allotment of
           sites/shops, grant of licences, dealerships and franchises)
           stand on a different footing as they may require a higher
           degree of fairness in action.
35. Afcons Infrastructure Limited (supra) is a case where this Court
    reiterated the proposition that the words used in the tender documents
    cannot be ignored or treated as redundant or superfluous: they must
    be given the due meaning and their necessary significance. The owner
    or a employer of a project having authored the tender documents
    is the best person to understand and appreciate its requirements
    and interpret its documents. Constitutional courts must defer to this
    understanding and appreciation of the tender documents unless
    there is mala fides or perversity in the understanding or appreciation
    or in the application of the terms of the tender documents. It is
    possible that the view taken by the owner or the employer may not
    be acceptable to the constitutional courts but that by itself is not a
    reason for interfering with the interpretation given. This Court held
    as follows:
           13. In other words, a mere disagreement with the decision-
           making process or the decision of the administrative
           authority is no reason for a constitutional court to interfere.
           The threshold of mala fides, intention to favour someone or
           arbitrariness, irrationality or perversity must be met before
           the constitutional court interferes with the decision-making
           process or the decision.
820                                                        [2025] 9 S.C.R.

                         Supreme Court Reports


36. In the recent case of M/s. ABCI Infrastructures Private Limited (supra),
    this Court has dealt with a similar issue as in the present case. In
    that case, appellant was ranked as L-1 bidder with the bid price of
    Rs. 1,569.00 (rupees one thousand five hundred and sixty nine only).
    According to the appellant, they had quoted a bid price of Rs. 1,569
    crores but due to system error, the quoted amount appeared just
    as 1,569.00. After the financial bids were opened and announced,
    appellant stated that it had discovered the mistake and accordingly
    the mistake was informed to the respondent authority stating that its
    actual bid was Rs. 1,569 crores and not Rs. 1,569.00. Though the
    mistake was bald-faced, Border Roads Organization, the respondent
    authority, insisted on accepting the bid inspite of the letters from the
    appellant seeking to withdraw from the tender. Ultimately Border
    Roads Organization declared the appellant as a defaulter and decided
    to forfeit its bid security. Consequently, the bank guarantee was sought
    to be encashed. It was in that context, this Court though observed
    that the mistake was self evident, nonetheless it agreed with the
    Border Roads Organization that the appellant was at fault and had
    made the mistake of having failed to add the required zeroes in the
    financial bid. The plea of system glitch put forth by the appellant was
    not acceptable as the others had successfully uploaded their bids
    without any problem. In the facts of that case, this Court noted that
    there were subsequent developments leading to fresh tender and
    award of contract though at a lower price. In the circumstances, this
    Court directed the appellant to pay Rs. 1 crore to the Border Roads
    Organization as a consequence of its error and upon receipt of the
    same, Border Roads Organization was directed to return appellant’s
    original bank guarantee.
37. Reverting back to the case of Afcons Infrastructure Limited (supra),
    we find that this Court had also examined the issue regarding
    impleadment of other bidders when a challenge is made to an award
    of contract. This Court was of the view that it would be appropriate
    for the constitutional courts to insist on all eligible bidders being
    made parties to the proceedings filed by an unsuccessful or ineligible
    bidder. It has been held as under:
          18. Before we conclude, it is necessary to point out that
          the High Court was of the opinion that the eligible bidders
          were not entitled to be either impleaded in the petition
          filed in the High Court by the ineligible bidder GYT-TPL
[2025] 9 S.C.R.                                                            821

        Prakash Asphaltings and Toll Highways (India) Limited v.
                  Mandeepa Enterprises and Others

            JV or were not entitled to be heard. With respect, this is
            not the appropriate view to take in matters such as the
            present. There are several reasons for this, one of them
            being that there could be occasions (as in the present
            appeals) where an eligible bidder could bring to the
            notice of the owner or employer of the project that the
            ineligible bidder was ineligible for additional reasons or
            reasons that were not within the contemplation of the
            owner or employer of the project. It was brought to our
            notice by Afcons Infrastructure in these appeals that GYT-
            TPL JV did not have any experience in the construction
            of a viaduct by the segmental construction method and
            that the translations of documents in Mandarin language
            filed in the High Court were not true English translations.
            Submissions made by the learned counsel for Afcons
            Infrastructure in this regard are important and would have
            had a bearing on the decision in the writ petition filed in
            the High Court but since Afcons Infrastructure was not a
            party in the High Court, it could not agitate these issues
            in the writ petition but did so in the review petition which
            was not entertained. It is to avoid such a situation that it
            would be more appropriate for the constitutional courts
            to insist on all eligible bidders being made parties to the
            proceedings filed by an unsuccessful or ineligible bidder.
38. In Johra (supra), this Court reiterated the fundamental principle that
    no order can be passed by any court in any judicial proceeding
    against any party without hearing and without giving such party an
    opportunity of hearing. In the facts of that case, the impugned order
    was set aside on the ground that the same was passed without
    hearing the appellant.
39. A three-Judge Bench of this Court in CIDCO Vs. Shishir Realty
    Private Limited7, observed that when a contract is being evaluated,
    the mere possibility of more money in the public coffers does not in
    itself serve public interest. This Court held as follows:
            61. When a contract is being evaluated, the mere possibility
            of more money in the public coffers, does not in itself serve


7   (2012) 16 SCC 527
822                                                         [2025] 9 S.C.R.

                              Supreme Court Reports


            public interest. A blanket claim by the State claiming loss
            of public money cannot be used to forego contractual
            obligations, especially when it is not based on any evidence
            or examination. The larger public interest of upholding
            contracts and the fairness of public authorities is also in
            play. The courts need to have a broader understanding of
            public interest, while reviewing such contracts.
40. The above proposition has been followed by another three-Judge
    Bench of this Court in the recent case of Subodh Kumar Singh Rathore
    Vs. Chief Executive Officer8, when it examined the concept of public
    interest in administrative decisions relating to award of contracts.
    This Court held that even assuming for a moment that there was
    technical fault in the tender, which if rectified had the possibility of
    generating more revenue, the same by no stretch could be said
    to be a cogent reason for concealing an already existing tender.
    This Court highlighted the importance of maintaining the sanctity
    of tenders in governmental procurement processes. Public tenders
    are the cornerstone of governmental procurement processes, being
    competitive and ensuring fairness and transparency in the allocation
    of public resources. Public tenders are designed to provide a level
    playing field for all potential bidders, fostering an environment where
    competition thrives. The integrity of this process ensures that public
    projects and resources are delivered efficiently and effectively,
    benefiting the society at large. Therefore, sanctity of public tenders
    and contract is a fundamental principle that underpins the stability
    and predictability of legal and commercial relationships. Infact this
    Court put in a word of caution that considerations of public interest
    should not be narrowly confined to financial aspect only.
41. Applying the above legal principles to the facts of the present case,
    we are of the view that the Division Bench of the High Court clearly
    fell in error in directing respondent No. 2 to 4 to allow rectification
    of the financial bid of respondent No. 1 by treating the amount
    offered by it as the per day figure and on that basis to compute the
    total amount for the entire contractual period of 1095 days. Such
    an exercise is clearly impermissible having regard to the terms and



8   2024 SCC Online SC 1682
[2025] 9 S.C.R.                                                        823

       Prakash Asphaltings and Toll Highways (India) Limited v.
                 Mandeepa Enterprises and Others

     conditions of the contract which are required to be understood on
     the anvil of this Court’s judgments. The authority granted to the
     tendering authority by clause 5B (v) of the Instruction to Bidders
     cannot be stretched to construe the price bid of respondent No. 1 as
     the per day offer, contrary to the bid declaration of respondent No. 1
     itself, and thereafter, on that basis to work out a new bid amount for
     the entire contractual period making it the highest. In the present
     case, respondent No. 1 was not at all vigilant; rather, it displayed a
     very casual approach. In such circumstances, clause 5B(v) cannot
     be invoked to resurrect the bid of respondent No. 1 to make it H1.
     Clause 5B(v) of the Instruction to Bidders has to read conjointly with
     clause 4(g) of the notice inviting electronic bid.
42. While judicial review is not excluded to assail administrative decisions
    even in matters of tenders and contract, the long line of consistent
    judicial pronouncements tells us that the constitutional courts should
    exercise utmost restraint in interfering with a tender process unless
    the threshold of judicial review are met, as explained in Jagdish
    Mandal (supra) and in Afcons Infrastructure Limited (supra).
43. As is clearly discernible, appellant was a necessary party to the
    proceedings before the High Court instituted by respondent No.
    1 being the H1 bidder. Impugned directions of the High Court has
    adversely affected the case of the appellant, downgrading its H1
    status. The proposition that equity and natural justice should be kept
    at bay during the course of tender evaluation, while fully applicable
    to the case of respondent No. 1, cannot be applied to judicial
    proceedings where tender evaluation is under judicial scrutiny, fairness
    and natural justice being integral to the judicial process. Therefore,
    non-impleadment and consequential non-hearing of the appellant
    by the High Court, has vitiated the impugned judgment and order.
44. The expression ‘public interest’ in the arena of commercial transactions
    cannot and should not be confined to any straight jacket definition.
    While benefit or accrual of more revenue to the public exchequer
    is certainly an important aspect, equally important, if not more, is
    adherence to the rules and conditions of tender; sanctity of the tender
    process being paramount and should be maintained at all cost.
45. Thus, having regard to the above, impugned judgment and order
    dated 23.02.2024 passed by the Division Bench of the High Court
824                                                          [2025] 9 S.C.R.

                              Supreme Court Reports


       in MAT No. 93 of 2024 cannot be sustained and is hereby set aside
       and quashed. Respondent Nos. 2 to 4 would be free to proceed
       with and finalise the award of contract in terms of the notice inviting
       electronic bid dated 17.10.2023.
46. Civil appeal is accordingly allowed. However, there shall be no order
    as to cost.

       Result of the case: Appeal allowed.




       †
           Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Tender"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.