Created byFuzzy Cloud

Supreme Court of India

PRAGNESH SHAHversusDR. ARUN KUMAR SHARMA & ORS.

Citation
2022 INSC 47
Decided
12 January 2022
Disposal
Dismissed

Holding

The NGT acted within its jurisdiction and the Expert Committee’s report, grounded in the precautionary principle, justifies the prohibition of construction on the appellant’s land.

Summary

The appellant, owner of land in the Mount Abu Eco‑sensitive Zone (ESZ), challenged the National Green Tribunal’s (NGT) order directing the State of Rajasthan to modify its Zonal Master Plan 2030 (ZMP 2030) to prohibit construction on his parcel. The NGT had relied on an Expert Committee report that deemed the land unsuitable for construction due to high‑slope terrain, soil erosion risk, and wildlife habitat, invoking the precautionary principle. The appellant argued that the NGT exceeded its jurisdiction under the NGT Act and that the Expert Committee’s findings were biased and based on a non‑public draft report. The Supreme Court held that the NGT acted within its statutory powers, that the Expert Committee’s conclusions were valid and consistent with the precautionary principle, and that there was no discrimination in treating the appellant’s land differently from other sites. Consequently, the Court dismissed the appeal, upholding the NGT’s direction to prevent construction on the appellant’s land.

Issues considered

  • The NGT exceeded its jurisdiction under the National Green Tribunal Act in directing modification of the ZMP 2030.
  • Whether the Expert Committee’s report, which formed the basis of the NGT’s order, is valid and can be relied upon.
  • Whether the precautionary principle mandates prohibition of construction on the appellant’s land despite scientific uncertainty.
  • Whether there is discrimination in the treatment of the appellant’s site compared with other sites in the ESZ.

Legislation cited

Subjects

Eco‑sensitive zoneZonal Master PlanPrecautionary principleNational Green TribunalEnvironmental lawSustainable developmentLand use restrictionExpert Committee reportConstruction banArticle 21

Judgment

154                      [2022]REPORTS
               SUPREME COURT    8 S.C.R. 154                [2022] 8 S.C.R.


A                             PRAGNESH SHAH
                                        v.
                   DR. ARUN KUMAR SHARMA & ORS.
                      (Civil Appeal Nos. 7724-7725 of 2021)
B
                               JANUARY 12, 2022
              [DR. DHANANJAYA Y. CHANDRACHUD AND
                        A. S. BOPANNA, JJ.]
             National Green Tribunal Act, 2010 – Environment Protection
C     Act, 1986 – Environment Protection Rules, 1986 – Eco-sensitive
      Zone Notification and Zonal Master Plan 2030 – NGT on basis of a
      report dated 08.12.2020 submitted by an Expert Committee, allowed
      an original application filed by the first respondent, which
      challenged the Zonal Master Plan 2030 prepared by the State of
D     Rajasthan, for the Mount Abu Eco-sensitive Zone – Report of the
      Expert committee had, inter-alia, declared land owned by the
      appellant to be unfit for construction – Review filed by the appellant
      was dismissed by NGT – On appeal, held: the Expert Committee has
      furnished valid reasons for determining that construction must not
      be allowed so as to preserve the eco-system of the region – Expert
E     Committee has noted that while the proposed site for residential
      buildings covers the land of low slopes which is stable, it also covers
      lands with a high slope domain which are not suitable for
      construction – Low slope domain site is a habitat for wildlife and
      footprints of sloth bear were also observed and it was in this context
F     the Expert Committee determined that construction must not be
      allowed – At places with a high slope domain, the landscape was
      noted to be fragile in terms of soil erosion – Further, the Expert
      Committee opined that the proposed tourism facility centre may
      disturb the wild life eco-system – The ESZ notification required,
      inter alia, the State of Rajasthan to prepare the ZMP 2030, so as to
G     ensure that future development activity in the region could be
      planned while accounting for potential environmental degradation,
      following the precautionary principle – The ESZ notification is
      backed by a statutory mandate of Union legislation – The
      Notification is an enforceable charter for the preservation of the
H     fragile eco-system of Mount Abu – Every authority is duty bound to

                                       154
 PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                           155


comply with its terms and any action in breach must peril invalidation   A
– NGT had correctly directed the ZMP 2030 to be modified to bring
it into conformity with the ESZ Notification and the precautionary
principle – Specifically, it correctly upheld the Expert Committee
Report’s recommendation that no construction should be allowed
to take place on the appellant’s land.
                                                                         B
      Environmental Law – Precautionary principle – Held: The
precautionary principle envisages that the State cannot refuse to
act to preserve the environment simply because all the scientific
data may not be available – If there is some data to suggest that
environmental degradation is possible, the State must step into action
                                                                         C
to prevent it from taking place.
      Dismissing the appeal, the Court
      Merits of Expert Committee Report
       HELD: 1. As regards the disputed site in question in this         D
appeal (“near STP plant”), the Expert Committee has furnished
valid reasons for determining that construction must not be
allowed so as to preserve the eco-system of the region. The
Expert Committee has noted that while the proposed site for
residential buildings covers the land of low slopes which is stable,
it also covers lands with a high slope domain which are not suitable     E
for construction. At places with a high slope domain, the landscape
was noted to be fragile in terms of soil erosion. Further, the Expert
Committee opined that the proposed tourism facility centre may
disturb the wild life eco-system. Additionally, although the low
slope domain may be suitable for construction, the site is a habitat     F
for wildlife and footprints of the sloth bear were also observed
during the field visit. It was in this context that the Expert
Committee determined that construction must not be allowed on
the site to preserve the eco-system. In comparison, the
observations contained in Table 16 with reference to the “Sunset
Road Scheme” and the “Sunrise Housing Society” sites clearly             G
indicate that there is no discrimination against the appellant since
there is a material difference in the location and suitability of the
sites for construction. [Para 24][174-A-E]

                                                                         H
156            SUPREME COURT REPORTS                      [2022] 8 S.C.R.


A           Precautionary Principle
            2. The report of the Expert Committee is consistent with
      the precautionary principle. The report has hence been correctly
      accepted by the NGT since it is mandated to follow the
      precautionary principle under Section 20 of the NGT Act. The
B     precautionary principle requires the State to act in advance to
      prevent environmental harm from taking place, rather than by
      adopting measures once the harm has taken place. In deciding
      when to adopt such action, the State cannot hide behind the veil
      of scientific uncertainty in calculating the exact scientific harm.
      [Paras 25 and 31][174-E-F; 177-G-H]
C
             3. The precautionary principle envisages that the State
      cannot refuse to act to preserve the environment simply because
      all the scientific data may not be available. If there is some data
      to suggest that environmental degradation is possible, the State
      must step into action to prevent it from taking place. Indeed, it
D     was this thought that compelled this Court in T.N. Godavarman
      to direct the State to identify ESZs across India, so that steps can
      be taken to identify areas where there is a greater possibility of
      environmental degradation and a plan is put in place to prevent
      such degradation before it actually makes the harm irreversible.
E     [Para 32][180-G-H; 181-A]
             4. Mount Abu was identified as an ESZ, under the ESZ
      Notification. The reason for doing this is because the State
      recognized that environmental degradation of the fragile eco-
      system is a real possibility in Mount Abu and the area surrounding
F     it if action is not immediately taken. A significant amount of soil
      erosion, air and water pollution has already taken place due to
      the developmental activities. The recitals in the ESZ Notification
      recognize the ecological importance of Mount Abu since it PART
      H 32 contains both tropical dry deciduous forests and evergreen
      forests; its flora and fauna comprise of several endemic and rare
G     species; and it also contains not only natural heritage such as
      Nakki lake but also man-made heritage sites such as the Dilwara
      temples. The ESZ notification required, inter alia, the State of
      Rajasthan to prepare the ZMP 2030, so as to ensure that future
      development activity in the region could be planned while
H     accounting for potential environmental degradation, following the
 PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                           157


precautionary principle. The ESZ notification is backed by a             A
statutory mandate of Union legislation. The Notification is an
enforceable charter for the preservation of the fragile eco-system
of Mount Abu. Every authority is duty bound to comply with its
terms and any action in breach must peril invalidation. [Para
33][181-A-E]
                                                                         B
      M.C. Mehta v. Union of India (2004) 12 SCC 118 :
      [2004] 3 SCR 126; Research Foundation for Science
      Technology National Resource Policy v. Union of India
      (2005) 10 SCC 510; Hospitality Assn. of Mudumalai v.
      In Defence of Environment & Animals (2020) 10 SCC
      589 : [2020] 10 SCR 273; H.P. Bus-Stand Management                 C
      & Development Authority v. Central Empowered
      Committee (2021) 4 SCC 309 : 2021 (1) JT 187 – relied
      on.
      T.N. Godavarman v. Union of India & Ors. Writ Petition
      No 202 of 1995; Mantri Techzone (P) Ltd. v. Forward                D
      Foundation (2019) 18 SCC 494; Municipal Corporation
      of Greater Mumbai v. Ankita Sinha and Others 2021
      SCC OnLine SC 897 – referred to.
                       Case Law Reference
                                                                         E
[2004] 3 SCR 126                   relied on              Para 27
[2020] 10 SCR 273                  relied on              Para 29
      CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 7724-
7725 of 2021.
                                                                         F
      From the Judgment and Order dated 10.03.2021 of the National
Green Tribunal, Principal Bench, New Delhi in Original Application
No.312 of 2016 and Order dated 29.07.2021 in Review Application No.26
of 2021 in Original Application No.312 of 2016.
      Mukul Rohatgi, Siddhartha Dave, Sr. Advs., Aditya Vaibhav Singh,
Ms. Saumya Gupta, Ms. Aarushi Singh, Ms. Vidhi Thaker, Ms. Nidhi         G
Jaswal, Advs. for the Appellant.
      Amit Sibal, Sr. Adv., Sameer Parekh, Vinay Tripathi, Sumit Goel,
Ms. Nina R. Nariman, Ms. Geetika Kapur, Tanuj Agarwal, Paritosh
Arora, M/s Parekh & Co., Advs. for the Respondents.
                                                                         H
158              SUPREME COURT REPORTS                        [2022] 8 S.C.R.


A            The Judgment of the Court was delivered by
             DR. DHANANJAYA Y CHANDRACHUD, J.
              This judgment has been divided into the following sections to
      facilitate analysis:
B            A       The Appeal
             B       Eco-sensitive Zone Notification and Zonal Master Plan
                     2030
             C       Proceedings before NGT
             D       Submissions of counsel
C
             E       Jurisdiction of NGT
             F       Merits of Expert Committee Report
             G       Precautionary Principle
D            H       Conclusion


             A The Appeal
             1. These appeals under Section 22 of the National Green Tribunal
      Act1 arise from judgments dated 10 March 2021 and 29 July 2021 of the
E
      National Green Tribunal2. By its judgment dated 10 March 2021, the
      NGT, on the basis of a report3 dated 8 December 2020 submitted by an
      Expert Committee, allowed an original application4 filed by the first
      respondent, which challenged the Zonal Master Plan 20305 prepared by
      the State of Rajasthan, for the Mount Abu Eco-sensitive Zone6. The
F     report of the Expert Committee had, inter alia, declared land owned by
      the appellant to be unfit for construction. Further, by its judgment dated
      29 July 2021, the NGT dismissed an application for review7 which had
      been filed by the appellant.

G     1
        “NGT Act”
      2
        “NGT”
      3
        “Expert Committee Report”
      4
        Original Application No 312 of 2016
      5
        “ZMP 2030”
      6
        “ESZ”
      7
H       Review Application No 26 of 2021
    PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                              159
         [DR. DHANANJAYA Y CHANDRACHUD, J.]

       B Eco-sensitive Zone Notification and Zonal Master Plan                 A
2030
      2. The appellant is the owner of a certain parcel of land situated
in Mount Abu in the State of Rajasthan. The appellant claims that the
land was earmarked as “Residential” and as a “Tourist Facility” in the
Zonal Master Plan 2025 for Mount Abu.                                          B

        3. On 25 June 2009, the Union Government in the Ministry of
Environment, Forest and Climate Change8 issued a Notification9 by which
it notified Mount Abu and the area surrounding it as an ESZ. The ESZ
Notification was issued in exercise of powers conferred by sub-Section
(1) read with Clause (v) and Clause (xiv) of Section 3(2) of the               C
Environment (Protection) Act 198610 and Rule 5(3) of the Environment
Protection Rules 1986. The preamble to the ESZ Notification contains
recitals emphasizing the ecological importance of Mount Abu:
       “S.O.1545(E) - WHEREAS, Mount Abu area has significant
       ecological importance comprising of tropical dry deciduous forests      D
       at lower altitude and evergreen forests at higher altitude and the
       flora and fauna of the region comprise of several endemic and
       rare species; besides Mount Abu has natural heritage such as
       Nakki Lake and man-made heritage like Dilwara temples and
       other heritage buildings and structures;                                E
       AND WHEREAS, considerable adverse environment impact has
       been caused due to degradation of the environment with excessive
       soil erosion and water and air pollution on account of certain
       developmental activities, thereby endangering not only the natural
       resources, but also affecting the health and very survival of living    F
       beings;
       AND WHEREAS, it is necessary to conserve and protect the
       area from ecological and environmental point of view;
       AND WHEREAS, a draft notification under sub-section (1) read            G
       with clause (v) and clause (xiv) of sub - section (2) of section 3 of
       the Environment (Protection) Act, 1986 (29 of 1986) was published
8
  “MoEF&CC”
9
  “ESZ Notification”
10
   “EP Act”                                                                    H
160                SUPREME COURT REPORTS                       [2022] 8 S.C.R.


A             in the Gazette of India, Extraordinary, vide Notification of
              Government of India in the Ministry of Environment and Forests
              vide number S.O. No. 2497 (E), dated the 22nd October, 2008, as
              required under sub-rule (3) of rule 5 of the Environment
              (Protection) Rules, 1986, inviting objections and suggestions from
              all persons likely to be affected thereby within a period of sixty
B
              days from the date on which copies of the Gazette containing the
              said notification were made available to the public;
              AND WHEREAS, copies of the Gazette containing the said
              notification were made available to the public on the 22nd October,
C             2008;
              AND WHEREAS, all objections and suggestions received in
              response to the above mentioned draft notification have been duly
              considered by the Central Government;
              Now, THEREFORE, in exercise of the powers conferred by sub-
D
              section (1) read with clause (v) and clause (xiv) of sub - section
              (2) of section 3 of the Environment (Protection) Act, 1986 (29 of
              1986) and sub-rule (3) of rule 5 of the Environment (Protection)
              Rules, 1986, the Central Government hereby notifies Mount Abu
              and surrounding region enclosed within the boundary described
E             below in the State of Rajasthan as the Mount Abu Eco-sensitive
              Zone (hereinafter called “the Eco-sensitive Zone”).”
             4. The ESZ Notification was preceded by a draft to which
      objections and suggestions were invited. The ESZ Notification outlines
      the boundaries of the ESZ in which activities are to be regulated. The
F     Notification envisages the preparation of a new Zonal Master Plan 11 for
      the restoration of denuded areas, conservation of existing water bodies
      including Nakki Lake, management of catchment areas, watershed
      management, groundwater management, soil and moisture conservation,
      preserving the needs of the local community, conservation of heritage
G     sites (both natural and cultural) and their surroundings, and such other
      aspects of the ecology and environment which may require attention.
      Clause 3(1)(i) of the ESZ Notification, in relation to the preparation of
      the ZMP, is extracted below:

      11
H          “ZMP”
     PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                              161
          [DR. DHANANJAYA Y CHANDRACHUD, J.]

        “3. The following activities are to be regulated in the Eco-            A
        sensitive Zone, namely:-
        (1) Zonal Master Plan for the Eco-sensitive Zone:-
        (i) A Zonal Master Plan for the Eco-sensitive Zone shall be
        prepared by the State Government within a period of two years           B
        from the date of publication of this notification and submitted for
        approval to the Central Government in the Ministry of Environment
        and Forests...”
        5. The ESZ Notification also envisages a Tourism Master Plan 12
to be prepared by the Department of Tourism of the Government for the           C
State of Rajasthan. The TMP would form a component of the ZMP, and
is to be based on a detailed Carrying Capacity Study of the ESZ. Further,
the Carrying Capacity Study is to be based on the existing infrastructure
and not on future projections of any project which requires environmental
or forest clearance. While adverting to the natural and man-made heritage
in Mount Abu, the ESZ Notification stipulates that:                             D

        “3. The following activities are to be regulated in the Eco-
        sensitive Zone, namely:-
        […]
                                                                                E
        (9) Man-made Heritage: Mount Abu is famous for several
        temples, the most prominent being Dilwara Temples and the main
        heritage and historical buildings are Achalgarh Fort, Dilwara Jain
        Temples, Rishav Deo Temple, Neminath Temple, Adinath Temple,
        Parshwanath Temple, Mahaveer Temple, etc., and later heritage
        buildings, structures and precincts. The plans for their conservation   F
        shall be prepared and incorporated in the Zonal and Sub-Zonal
        Master Plan and the development or construction activities at or
        around the heritage sites shall be regulated under the statutory
        provisions of the Rajasthan Monuments, Archaeological Sites and
        Antiquities Act and in accordance with the Draft Model                  G
        Regulations for Conservation of Natural and Manmade Heritage
        Sites formulated by the Central Government in the Ministry of
        Environment and Forests in 1995.

12
     “TMP”                                                                      H
162      SUPREME COURT REPORTS                            [2022] 8 S.C.R.


A     (10) Water:
      (i) All future and existing buildings, where possible, in the Municipal
      Area shall provide roof-top rain water harvesting structures
      commensurate with their plinth area and the Institutional and
      commercial buildings shall not draw water from existing water
B     supply schemes in a manner that adversely affects water supply
      especially to local villages or settlements.
      (ii) In Non-Municipal Areas rain water harvesting shall be
      undertaken through such structures as percolation tanks and
      storage tanks and only other means. Ground water aquifer
C     recharge structures shall be constructed wherever such structures
      do not lead to slope instabilities.
      (iii) The rain water collected through storm water drains shall be
      used to recharge the ground water or to clean the waste disposal
      drains and sewers.
D     (iv) The extraction of ground water shall be permitted only for the
      bona-fide agricultural and domestic consumption of the occupier
      of the plot and the extraction of ground water for industrial or
      commercial or residential estates or complexes shall require prior
      written permission, including of the amount that can be extracted,
E     from the State Ground Water Department. However, the areas
      rich in ground water may not be diverted for construction activities.
      (v) No sale of ground water shall be permitted except with the
      prior approval of the State Ground Water Department and all steps
      shall be taken to prevent contamination or pollution of water
F     including from agriculture.
      (vi) The area has three big water bodies namely Upper Kodra
      dam, Lower Kodra dam and Nakki Lake and in addition to this
      the area has around 25 water places, where water remains through
      out the year, which include natural nalla, dams, anicuts, seepage
      and baoris that are spread over entire area and must be protected.
G
      […]
      (13) Development on and protection of hill slopes:
      (i) The Zonal Master Plan shall indicate areas on hill slopes where
      development shall not be permitted.
H
 PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                                  163
      [DR. DHANANJAYA Y CHANDRACHUD, J.]

      (ii) No development shall be undertaken in areas having a steep           A
      slope or areas which fall in fault or hazard zones or areas falling
      on the spring lines and first order streams or slopes with a high
      degree of erosion as identified by the State Government on the
      basis of available scientific evidence.
      (iii) No development on existing steep hill slopes or slopes with a       B
      high degree of erosion shall be permitted.”
       6. Under Clause 4 of the ESZ Notification, the Central Government
has to constitute a Monitoring Committee. In pursuance of the ESZ
Notification, a Monitoring Committee was constituted by the Union
Government through MoEF&CC on 10 December 2009. The constitution                C
of the Monitoring Committee was revised on 24 January 2012 and 5
May 2015.
       7. The appellant has a grievance that when a draft of ZMP 2030
was published, the status of his land was incorrectly changed from
“Residential” and “Tourist Facility” to “Agricultural Zone”. The appellant      D
challenged this before the Chairman of the Monitoring Committee, the
MoEF&CC and the State of Rajasthan. Based on it, the status of the
appellant’s land was again changed back to “Residential” and “Tourist
Facility”. Thereafter, ZMP 2030 was notified by the State of Rajasthan
on 29 October 2015, following the approval of the MoEF&CC on 28
September 2015.                                                                 E

      C Proceedings before NGT
       8. The ZMP 2030 was challenged by the first respondent by his
original application on the ground that it is not in conformity with ESZ
Notification, since it fails to discourage construction activities at or near   F
the heritage sites, conserve the existing water bodies and permits change
of land use by illegal structures. Since the first respondent’s original
application mentioned the appellant’s land, the appellant was allowed to
intervene in the proceedings by the NGT in its order dated 10 April
2017.
                                                                                G
       9. On 26 November 2018, the NGT issued an order which noted
that the first respondent’s original application contended, inter alia, that
ZMP 2030 had permitted illegal change of land use, in direct contradiction
to the ESZ Notification, in thirteen locations, which included the
appellant’s land. To assess the claims made in the first respondent’s
original application, the NGT constituted an Expert Committee consisting        H
164                 SUPREME COURT REPORTS                         [2022] 8 S.C.R.


A     of two representatives of MoEF&CC, a representative of the School of
      Planning and Architecture, Delhi (since it had been engaged by the State
      of Rajasthan as a consultant), and a representative of Central Pollution
      Control Board13. The mandate of the Expert Committee was as follows:
              “21. The Committee will undertake comparison of ZMP 2030, in
B             terms of letter of MoEF&CC dated 28.09.2015 and ESZ
              Notification dated 25.06.2009 and point out the aberrations in some
              besides comparing ZMP 2030 map with reference to pre-existing
              2010 map in the light of ESZ notification. Thirteen (13) locations
              noted above must also be specifically looked into. The Expert
              Committee may also look into the suggestions relating to prohibiting
C             use of plastics, burning of garbage/or any other waste, proper
              laying of high tension lines for protecting animals and birds life
              particularly in Salim Ali Bird Sanctuary area, preventing forest
              fire, conservation of Nakki lake and water quality management,
              siting and operation of Solid Waste processing plant in accordance
D             with Solid Waste Management Rules, 2016 (with reference to
              sanctuary area), any other issues relating to environment
              management which may become a part of ZMP 2030, including
              observations of this Tribunal in Kasuali case.
              22. The Committee will also look into the points of concern raised
E             by the applicant in reference to conversion of green areas to non-
              green areas, permissibility of construction on higher degree slopes,
              conservation of rocks, water bodies and wildlife and other heritage
              sites, the issue of water scarcity, carrying-capacity of Mount Abu
              with regard to number of tourists and vehicles to be permitted
              having regard to the availability of the infrastructure without relying
F             upon future projection, as required in terms of ESZ notification.”
            10. The Expert Committee submitted a report on 4 September
      2019, which was not found to be acceptable when it was considered by
      the NGT on 7 November 2019. As a consequence, the NGT modified
      the composition of the Expert Committee, with the following observations:
G
              “8. Though the Committee was to furnish its report within three
              months from the order dated 6.11.2018 report has been filed almost
              after more than 9 months on 04.09.2019. We find from the report
              that the Committee has assumed the ZMP to be conclusive on the

      13
H          “CPCB”
     PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                               165
          [DR. DHANANJAYA Y CHANDRACHUD, J.]

          ground that suitability analysis test had already been carried out     A
          by the State Government. This approach is inconsistent with the
          directions of this Tribunal. If the analysis of the State Government
          was to be treated as final, there was no need for the Committee.”
       11. The reconstituted Committee then submitted the Expert
Committee Report. The Expert Committee enquired into the change in               B
land use through high resolution satellite images, while analysing the
data with particular reference to ten identified sites, including the
appellant’s land. The NGT then heard submissions on the Expert
Committee Report. By its impugned judgment dated 29 July 2021, the
NGT observed that the Expert Committee Report was based on authentic
data and on field visits by the Committee and is supported by adequate           C
reasons. The NGT noted that the object of notifying certain areas as
ESZs is to protect certain specified sensitive areas by restricting and
regulating development activities. Such areas may be based on species,
geomorphologic features or on the eco-system. The NGT held that it
was necessary to protect bio-diversity zones by creating regulated buffers       D
around them to protect their flora and fauna, prevent habitat destruction
and protect fragile ecology. Adverting to the backdrop of the ESZ
Notification, the NGT noted that the Supreme Court had in T.N.
Godavarman v. Union of India & Ors.14 (“T.N. Godavarman”)
appointed Expert Committees to identify ESZs across India, and when
such ESZs were eventually identified, Mount Abu was cleared as an                E
ESZ as well. The NGT further observed that the object of notifying
ESZs is to protect a specified area from the irreversible degradation of
its environment with a view to give effect to the principles of sustainable
development, inter-generational equity and the public trust doctrine in
exercise of powers conferred by Section 3(2)(v) of the EP Act.                   F
       12. The NGT then proceeded to deal with individual sites under
consideration. The subject matter of the present appeals pertains to an
entry in Table 16 of the Expert Committee Report. Table 16 is titled as
follows:
          “Suitability of 10 identified sites within Mount Abu ESZ as reviewed   G
          by the expert committee based on the site visit/ground verification
          as well as interactions with the local residents/Mount Abu
          Municipality officials/Town Planning Department officials/other
          stakeholders during 16-17 January 2020”
14
     Writ Petition No 202 of 1995                                                H
166             SUPREME COURT REPORTS                           [2022] 8 S.C.R.


A           The evaluation of the site in question, i.e., the appellant’s land, is
      tabulated in Table 16 as follows:




B




C




D




E




F


             13. The NGT noted that the above site (“near STP Plant”) has
      not been found suitable for construction on considerations based on the
      wild life eco-system. The NGT also accepted the view of the Expert
G
      Committee that the conversion of green areas into non-green areas should
      not be allowed, except in exceptional situations mentioned in the Report,
      and that the STP must be duly maintained. The NGT, while accepting
      the Expert Committee Report, thus directed that the ZMP 2030 should
      be brought in conformity within three months.
H
     PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                                167
          [DR. DHANANJAYA Y CHANDRACHUD, J.]

      14. The findings of the NGT in relation to appellant’s land were            A
challenged by the appellant in a review application, which was rejected
on 29 July 2021. This has led to the present appeals.
          D Submissions of counsel
      15. Mr Mukul Rohatgi, Senior Counsel appearing on behalf of the
appellant has urged two submissions:                                              B
          (i)    Firstly, the NGT, being an adjudicatory body constituted by
                 the NGT Act, is vested with limited jurisdiction under Section
                 14 to deal with a substantial question of environment arising
                 out of the statutes enumerated in Schedule I to the NGT
                 Act. The NGT had acted beyond its jurisdiction in directing      C
                 the amendment of the ZMP 2030; and
          (ii)   Secondly, on merits:
                 a.    The Expert Committee had prepared a draft report
                       in July 202015, which was not placed before the NGT
                       and was obtained by the appellant through a Right to       D
                       Information request on 1 February 2021. In the Draft
                       Report, Table 23 pertains to the suitability of ten
                       identified sites within the Mount Abu ESZ and it
                       contained a column containing remarks on the bio-
                       diversity at each of these locations. In this backdrop,    E
                       it was submitted that the appellant’s land was shown
                       to be encompassed by the movement of wild life,
                       more specifically, the sloth bear and panther. In this
                       context, it was urged that a similar situation existed
                       in Table 23 with respect to another site (described as
                       “Sunrise Housing Society”). However, in the Expert         F
                       Committee Report, the column on bio-diversity is
                       missing, which hides crucial information on the basis
                       of which the final recommendations were made. The
                       appellant alleges that the column on bio-diversity is
                       missing because the Expert Committee Report was
                                                                                  G
                       manipulated to favor others over the appellant; and
                 b.    Whereas other similar sites have been granted
                       clearances in the Expert Committee Report, the
                       appellant has not been cleared. In other words, the
15
     “Draft Report”                                                               H
168                   SUPREME COURT REPORTS                            [2022] 8 S.C.R.


A                              submission is that the Report has proceeded on the
                               basis of a “pick and choose” process.
            16. Opposing these submissions, Mr Amit Sibal, Senior Counsel
      appearing on behalf of the respondents urged the following submissions:
               (i)      The ESZ Notification, which has been issued in pursuance
B                       of the intervention of this Court in T.N. Godavarman
                        (supra), recognizes the ecological importance of Mount Abu,
                        which is comprised of tropical dry deciduous forests at a
                        lower altitude and evergreen forests at higher altitudes;
               (ii)     The ZMP 2030 was issued in accordance with the ESZ
C                       Notification;
               (iii)    The Expert Committee included domain experts, town
                        planners and government officials who proceeded to identify
                        the issues with the specified sites in Table 16 after careful
                        analysis and site visits;
D              (iv)     The Expert Committee Report is founded on the
                        precautionary principle and as it is based on a scientific
                        approach, it must warrant deference;
               (v)      Schedule I to the NGT Act, inter alia, refers to the Forest
                        Conservation Act 198016 and the EP Act;
E              (vi)     The ESZ notification has been issued in exercise of powers
                        conferred by the EP Act;
               (vii)    The order of the NGT dated 7 November 2019 did not
                        accept the report of the initial Expert Committee, and
                        reconstituted it. This order has attained finality since it was
F                       not challenged by the appellants;
               (viii) The appellant is relying upon the Draft Report, which was
                      not in the public domain since it was an incomplete report.
                      Moreover, the Draft Report contains endorsements as against
                      the site in question to the effect that it was not suitable. Further,
G                     there is a valid distinction between the site in question and
                      others (such as the “Sunset Road Scheme” and “Sunrise
                      Housing Society”) where construction has been allowed. In
                      the case of the “Sunset Road Scheme”, the land use was
                      for residential purposes while on the contrary, the appellant
      16
H          “FC Act”
     PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                                            169
          [DR. DHANANJAYA Y CHANDRACHUD, J.]

                has admitted to converting the site in question for tourism                   A
                and residential buildings under the ZMP 2030; and
        (ix)    While on the one hand, the Expert Committee which
                comprises, inter alia, of environmental experts had
                considered each of the sites in Table 16 of the Expert
                Committee Report, the appellant has brought on record no                      B
                evidence to establish any error or perversity in the Report
                which was accepted by the NGT.
        E Jurisdiction of NGT
        17. Sub-Section (1) of Section 1417 of the NGT Act provides that
the NGT shall have the jurisdiction over all civil cases where a substantial                  C
question relating to the environment, including the enforcement of any
legal right relating to the environment is involved and such question arises
out of the implementation of the enactments specified in Schedule I to
the NGT Act. Under sub-Section (2) of Section 14, the NGT is
empowered to hear disputes set out in sub-Section (1), and pass orders
thereon. Section 15(1) further provides for the reliefs which may be                          D
granted by the NGT, and reads as follows:
        “15. Relief, compensation and restitution.—(1) The Tribunal
        may, by an order, provide,—
        (a) relief and compensation to the victims of pollution and other
        environmental damage arising under the enactments specified in                        E
        the Schedule I (including accident occurring while handling any
        hazardous substance);
        (b) for restitution of property damaged;
        (c) for restitution of the environment for such area or areas, as
        the Tribunal may think fit.”                                                          F

17
  “14. Tribunal to settle disputes.—(1) The Tribunal shall have the jurisdiction over
all civil cases where a substantial question relating to environment (including enforcement
of any legal right relating to environment), is involved and such question arises out of
the implementation of the enactments specified in Schedule I.
(2) The Tribunal shall hear the disputes arising from the questions referred to in sub-       G
section (1) and settle such disputes and pass order thereon.
(3) No application for adjudication of dispute under this section shall be entertained by
the Tribunal unless it is made within a period of six months from the date on which the
cause of action for such dispute first arose:
Provided that the Tribunal may, if it is satisfied that the applicant was prevented by
sufficient cause from filing the application within the said period, allow it to be filed
within a further period not exceeding sixty days.”                                            H
170               SUPREME COURT REPORTS                         [2022] 8 S.C.R.


A            18. Among the statutes which are delineated in Schedule I are the
      FC Act (Entry 3) and the EP Act (Entry 5). There can be no manner of
      doubt that the original application filed by the first respondent before the
      NGT in the present case implicated a substantial question relating to the
      environment. The ‘substantial question’ arose from the provisions
      contained in the ESZ Notification in relation to the ESZ in Mount Abu.
B
      The ESZ Notification traces its origin to the EP Act, under which the
      Union Government through MoEF&CC is empowered to issue it. In the
      exercise of its jurisdiction, the NGT is empowered under Section 15(1)(c)
      to provide for the restoration of the environment in such area or areas.
      The ESZ Notification in Clause 3(1) provides for the ZMP for the ESZ
C     in this context. Assessing the conformity of the ZMP 2030 with the
      terms of the ESZ Notification is clearly within the remit of the NGT.
             19. In Mantri Techzone (P) Ltd. v. Forward Foundation18, a
      three-Judge Bench of this Court noted that Section 15(1)(c) of the NGT
      Act affords broad powers to the NGT. Speaking for the Court, Justice S
D     Abdul Nazeer held:
               “43. Section 15(1)(c) of the Act is an entire island of power and
               jurisdiction read with Section 20 of the Act. The principles of
               sustainable development, precautionary principle and polluter pays,
               propounded by this Court by way of multiple judicial
E              pronouncements, have now been embedded as a bedrock of
               environmental jurisprudence under the NGT Act. Therefore,
               wherever the environment and ecology are being compromised
               and jeopardized, the Tribunal can apply Section 20 for taking
               restorative measures in the interest of the environment.”
F            20. In another recent judgment in Municipal Corporation of
      Greater Mumbai v. Ankita Sinha and Others19, a three-Judge Bench
      of this Court held that the NGT can also exercise suo motu jurisdiction.
      While elaborating on the jurisdiction of the NGT in general, Justice
      Hrishikesh Roy held:
G              “27. The paragraph 2 of the Statement of Objects and Reasons
               [of the NGT Act] refers to the United Nations Conference on the
               Human Environment held at Stockholm in June 1972 which called
               upon governments and peoples to exert common efforts for the
      18
           (2019) 18 SCC 494
      19
H          2021 SCC OnLine SC 897
PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                           171
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

   preservation and improvement of the human environment when it        A
   involved people and for their posterity. Therefore, the municipal
   law enacted with such a laudatory objective of not only preventing
   damage to the environment but also to protect it, must be provided
   with the wherewithal to discharge its protective, preventive and
   remedial function towards protection of the environment. The
                                                                        B
   mandate and jurisdiction of the NGT is therefore conceived
   to be of the widest amplitude and it is in the nature of a sui
   generis forum.
   […]
   36. The laudatory objectives for creation of the NGT would implore   C
   us to adopt such an interpretive process which will achieve the
   legislative purpose and will eschew procedural impediment or so
   to say incapacity. The precedents of this Court, suggest a
   construction which fulfills the object of the Act [Sarah
   Mathew v. Institute of Cardio Vascular Diseases, (2014) 2 SCC
   62, New India Assurance Co. Ltd. v. Nusli Neville Wadia, (2008)      D
   3 SCC 279]. The choice for this Court would be to lean
   towards the interpretation that would allow fructification of
   the legislative intention and is forward looking. The
   provisions must be read with the intention to accentuate
   them, especially as they concern protections of rights under         E
   Article 21 and also deal with vital environmental policy and
   its regulatory aspects.
   […]
   38. While on the statutory provisions, it is seen that the Central
   Government has framed the National Green Tribunal (Practice &        F
   Procedure) Rules, 2011 (for short “the NGT Rules”). For our
   purpose, Rule 24 is important which reads thus:
   “24. Order and directions in certain cases - The Tribunal may
   make such orders or give such directions as may be necessary or
   expedient to give effect to its order or to prevent abuse of its     G
   process or to secure the ends of justice.”
   39. The said Rules make it clear that the NGT has been
   given wide discretionary powers to secure the ends of
   justice. This power is coupled with the duty to be exercised
   for achieving the objectives. The intention understandably           H
172            SUPREME COURT REPORTS                          [2022] 8 S.C.R.


A           being to preserve and protect the environment and the
            matters connected thereto.
            40. By choosing to employ a phrase of wide import, i.e. secure
            the ends of justice, the legislature has nudged towards a liberal
            interpretation. Securing justice is a term of wide amplitude and
B           does not simply mean adjudicating disputes between two rival
            entities. It also encompasses inter alia, advancing causes of
            environmental rights, granting compensation to victims of
            calamities, creating schemes for giving effect to the
            environmental principles and even hauling up authorities
            for inaction, when need be.
C
            41. Moreover, unlike the civil courts which cannot travel beyond
            the relief sought by the parties, the NGT is conferred with power
            of moulding any relief. The provisions show that the NGT is
            vested with the widest power to appropriate relief as may
            be justified in the facts and circumstances of the case, even
D           though such relief may not be specifically prayed for by the
            parties.”
                                                        (emphasis supplied)
              21. The NGT has not acted in excess of or beyond its jurisdiction
      in testing ZMP 2030 on the anvil of the ESZ Notification. Having found
E     that the report of the earlier Expert Committee appointed by it was not
      acceptable while adjudicating on the issue on 7 November 2019, the
      NGT constituted another Expert Committee. The Committee comprised
      of experts in the area of the environment as well as representatives of
      the CPCB and the Rajasthan Pollution Control Board. The Expert
      Committee was tasked with submitting a report to the NGT to aid it in
F
      discharging its functions of assessing the conformity of the ZMP 2030
      with the terms of the ESZ Notification. On the submission of the Expert
      Committee Report, the NGT heard objections to it and delivered a
      reasoned order on why it was accepting the recommendations made in
      the Report. Hence, there is no merit in the submission that the NGT has
G     acted beyond its jurisdiction.
            F Merits of Expert Committee Report
            22. The second limb of the appellant’s submission proceeds on
      merits. There has been a misconceived attempt on the part of the
      appellant to advert to the Draft Report which was prepared by the Expert
H     Committee. The Draft Report was in the realm of an internal document
 PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                                                      173
      [DR. DHANANJAYA Y CHANDRACHUD, J.]

and was not in the public domain. Evidently, the Draft Report was a                                 A
subject matter of deliberations, and it is only the final report which was
submitted to the NGT that represented the views of the Expert
Committee. Hence, there is no merit in the appellant’s plea which is
based on the Draft Report.
       23. The Expert Committee Report has carefully analyzed ten sites                             B
in Table 16. Since the appellant’s plea of discrimination is based on the
observation pertaining to the “Sunset Road Scheme” and “Sunrise
Housing Society”, it would be material to extract the observations of the
Expert Committee on the above two sites. The relevant part of Table 16
in relation to those sites is extracted below:
 Name      Location (Lat    Present land use &       Recommendation (All these construction
                                                                                                    C
 of Site     & long with        Vegetation         should comply the norm of 50 m away from
             Accuracy/       type/Cover (%)         forest boundary and from water body and
              Altitude);                                  100 m away from wetland/river
              Slope (oo)
Sunset     24o35'11.49''N Residential (Partly This site is stable with the granite as basement
Road       72o42'13.79"E  built/partly vacant); rock.
Scheme     (±3m)          Open scrub/isolated     This site is close to the forest land.
                                                                                                    D
           1169 m; Most   trees (<10%)            Therefore, the ESZ criteria of a buffer zone
           of the land at                         with forest and water stream must comply
           this site has                          before the start of any construction activity.
           slope <20°                             Already existing provision for farm house in
                                                  state of Rajasthan may be made applicable
                                                  with allowance of 1o% of total area of
                                                  construction as built up area or 5000 sq ft.      E
                                                  (whichever is less) subject to NOC from
                                                  Forest dept.
                                                  Conclusion:       Site    is    suitable    for
                                                  construction.
Sunrise    24o34'55.26''N Vacant; Open scrub The basement rock is granite and is well
Housing    72o43'38.12"E with isolated trees exposed at this location with very thin soil
Society    (±3m)          (>20%)                cover.                                              F
           1137 m; Most                           The site is near a local natural stream (Nala).
           of the land at                         Therefore, the ESZ criteria of the buffer
           this site has                          zone with water stream and forest must be
           slope <20°                             complied before any constructional activity
                                                  as per norms.
                                                  Site is surrounded by habitation so it may
                                                  cater to the residential needs of the local       G
                                                  people.
                                                  Thus, this site is stable and suitable for the
                                                  construction of the residential complex.
                                                  Construction may be allowed following
                                                  criteria laid down in ESZ.
                                                Conclusion:       Site     is    suitable     for
                                                construction.                                       H
174             SUPREME COURT REPORTS                           [2022] 8 S.C.R.


A            24. From the above extract, it is evident that the land used by the
      Sunset Road Scheme is described to be residential (partly built, partly
      vacant) and as regards the Sunrise Housing Society, the land use is
      described to be vacant. As regards the disputed site in question in this
      appeal (“near STP plant”), the Expert Committee has furnished valid
      reasons for determining that construction must not be allowed so as to
B
      preserve the eco-system of the region. The Expert Committee has noted
      that while the proposed site for residential buildings covers the land of
      low slopes which is stable, it also covers lands with a high slope domain
      which are not suitable for construction. At places with a high slope domain,
      the landscape was noted to be fragile in terms of soil erosion. Further,
C     the Expert Committee opined that the proposed tourism facility centre
      may disturb the wild life eco-system. Additionally, although the low slope
      domain may be suitable for construction, the site is a habitat for wildlife
      and footprints of the sloth bear were also observed during the field visit.
      It was in this context that the Expert Committee determined that
      construction must not be allowed on the site to preserve the eco-system.
D
      In comparison, the observations contained in Table 16 with reference to
      the “Sunset Road Scheme” and the “Sunrise Housing Society” sites
      clearly indicate that there is no discrimination against the appellant since
      there is a material difference in the location and suitability of the sites
      for construction.
E           G Precautionary Principle
            25. The report of the Expert Committee is consistent with the
      precautionary principle. The report has hence been correctly accepted
      by the NGT since it is mandated to follow the precautionary principle
      under Section 20 of the NGT Act. Section 20 of the NGT Act states
F     thus:
            “20. Tribunal to apply certain principles.—The Tribunal shall,
            while passing any order or decision or award, apply the principles
            of sustainable development, the precautionary principle and the
            polluter pays principle.”
G
            26. The precautionary principle finds its clearest elaboration in
      Principle 15 of the Rio Declaration on Environment and Development
      1992, which states:
            “In order to protect the environment, the precautionary approach
            shall be widely applied by States according to their capabilities.
H
     PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                                 175
          [DR. DHANANJAYA Y CHANDRACHUD, J.]

          Where there are threats of serious or irreversible damage, lack of       A
          full scientific certainty shall not be used as a reason for postponing
          cost-effective measures to prevent environmental degradation.”
      27. In M.C. Mehta v. Union of India20, a two-Judge Bench of
this Court noted the import of this principle in Indian jurisprudence by
highlighting that it requires the State to act for preventing actual               B
environmental harm, even in the face of scientific uncertainty. The Court
held:
          “48. Development and the protection of environment are not
          enemies. If without degrading the environment or minimising
          adverse effects thereupon by applying stringent safeguards, it is        C
          possible to carry on development activity applying the principles
          of sustainable development, in that eventuality, development has
          to go on because one cannot lose sight of the need for development
          of industries, irrigation resources and power projects etc. including
          the need to improve employment opportunities and the generation
          of revenue. A balance has to be struck…Principle 15 of the               D
          Rio Conference of 1992 [Ed.: Cited in (1999) 2 SCC 718,
          733 in para 33] relating to the applicability of precautionary
          principle, which stipulates that where there are threats of
          serious or irreversible damage, lack of full scientific
          certainty shall not be used as a reason for postponing cost-             E
          effective measures to prevent environmental degradation,
          is also required to be kept in view. In such matters, many a
          times, the option to be adopted is not very easy or in a
          straitjacket. If an activity is allowed to go ahead, there may
          be irreparable damage to the environment and if it is
          stopped, there may be irreparable damage to economic                     F
          interest. In case of doubt, however, protection of
          environment would have precedence over the economic
          interest. Precautionary principle requires anticipatory action
          to be taken to prevent harm. The harm can be prevented
          even on a reasonable suspicion. It is not always necessary               G
          that there should be direct evidence of harm to the
          environment.”
                                                       (emphasis supplied)

20
     (2004) 12 SCC 118                                                             H
176                SUPREME COURT REPORTS                          [2022] 8 S.C.R.


A            28. In Research Foundation for Science Technology National
      Resource Policy v. Union of India21, a two-Judge Bench of this Court
      noted that the precautionary principle is part of the Indian jurisprudence,
      arising from Articles 47, 48-A and 51-A(g) of the Constitution. The Court
      held:
B               “16. The legal position regarding applicability of the precautionary
                principle and polluter-pays principle which are part of the concept
                of sustainable development in our country is now well settled. In
                Vellore Citizens’ Welfare Forum v. Union of India [(1996) 5 SCC
                647] a three-Judge Bench of this Court, after referring to the
                principles evolved in various international conferences and to the
C               concept of “sustainable development”, inter alia, held that the
                precautionary principle and polluter-pays principle have now
                emerged and govern the law in our country, as is clear from Articles
                47, 48-A and 51-A(g) of our Constitution and that, in fact, in the
                various environmental statutes including the Environment
D               (Protection) Act, 1986, these concepts are already implied. These
                principles have been held to have become part of our law. Further,
                it was observed in Vellore Citizens’ Welfare Forum case [(1996)
                5 SCC 647] that these principles are accepted as part of the
                customary international law and hence there should be no difficulty
                in accepting them as part of our domestic law…”
E
            29. This position has been reiterated by a three-Judge Bench of
      this Court in Hospitality Assn. of Mudumalai v. In Defence of
      Environment & Animals22. The Court has held:
                “39…As was held by this Court in M.C. Mehta (Badkhal &
F               Surajkund Lakes Matter) v. Union of India [M.C. Mehta (Badkhal
                & Surajkund Lakes Matter) v. Union of India, (1997) 3 SCC 715]
                the “precautionary principle” has been accepted as a part
                of the law of our land. Articles 21, 47, 48-A and 51-A(g) of
                the Constitution give a clear mandate to the State to protect
                and improve the environment and to safeguard the forests
G               and wildlife of the country. It is the duty of every citizen of
                India to protect and improve the natural environment
                including forests and wildlife and to have compassion for

      21
           (2005) 10 SCC 510
      22
H          (2020) 10 SCC 589
 PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                                   177
      [DR. DHANANJAYA Y CHANDRACHUD, J.]

      living creatures. The precautionary principle makes it                     A
      mandatory for the State Government to anticipate, prevent
      and attack the causes of environmental degradation. In this
      light, we have no hesitation in holding that in order to protect the
      elephant population in the Sigur Plateau region, it was necessary
      and appropriate for the State Government to limit commercial
                                                                                 B
      activity in the areas falling within the elephant corridor.”
                                                     (emphasis supplied)
       30. In Municipal Corporation of Greater Mumbai (supra),
this Court elaborated on the precautionary principle in the following terms:
      “79. The principle set out above must apply in the widest                  C
      amplitude to ensure that it is not only resorted to for
      adjudicatory purposes but also for other ‘decisions’ or
      ‘orders’ to governmental authorities or polluters, when they
      fail to “to anticipate, prevent and attack the causes of
      environmental degradation” [Vellore Citizens (supra), S.                   D
      Jagannathan v. Union of India, (1997) 2 SCC 87, Karnataka
      Industrial Areas Development Board v. C Kenchappa, (2006)
      6 SCC 371]. Two aspects must therefore be emphasized i.e.
      that the Tribunal is itself required to carry out preventive
      and protective measures, as well as hold governmental and
      private authorities accountable for failing to uphold                      E
      environmental interests. Thus, a narrow interpretation for
      NGT’s powers should be eschewed to adopt one which allows
      for full flow of the forum’s power within the environmental domain.
      80. It is not only a matter of rhetoric that the Tribunal is to remain
      ever vigilant, but an important legal onus is cast upon it to act with     F
      promptitude to deal with environmental exigencies. The
      responsibility is not just to resolve legal ambiguities but to arrive at
      a reasoned and fair result for environmental problems which are
      adversarial as well as nonadversarial.”
                                                     (emphasis supplied)         G
       31. The precautionary principle requires the State to act in advance
to prevent environmental harm from taking place, rather than by adopting
measures once the harm has taken place. In deciding when to adopt
such action, the State cannot hide behind the veil of scientific uncertainty
in calculating the exact scientific harm. In H.P. Bus-Stand                      H
178                SUPREME COURT REPORTS                           [2022] 8 S.C.R.


A     Management & Development Authority v. Central Empowered
      Committee23, a three-Judge Bench of this Court emphasised the duty
      of the State to create conceptual, procedural and institutional structures
      to guide environmental regulation in compliance with the “environmental
      rule of law”. The Court noted that such regulation must arise out of a
      muti-disciplinary analysis between policy, regulatory and scientific
B
      perspectives. The Court held:
                “49. The environmental rule of law, at a certain level, is a facet of
                the concept of the rule of law. But it includes specific features
                that are unique to environmental governance, features which are
                sui generis. The environmental rule of law seeks to create
C               essential tools — conceptual, procedural and institutional
                to bring structure to the discourse on environmental
                protection. It does so to enhance our understanding of
                environmental challenges — of how they have been shaped
                by humanity’s interface with nature in the past, how they
D               continue to be affected by its engagement with nature in
                the present and the prospects for the future, if we were not
                to radically alter the course of destruction which humanity’s
                actions have charted. The environmental rule of law seeks
                to facilitate a multi-disciplinary analysis of the nature and
                consequences of carbon footprints and in doing so it brings
E               a shared understanding between science, regulatory
                decisions and policy perspectives in the field of
                environmental protection. It recognises that the “law”
                element in the environmental rule of law does not make
                the concept peculiarly the preserve of lawyers and Judges.
F               On the contrary, it seeks to draw within the fold all
                stakeholders in formulating strategies to deal with current
                challenges posed by environmental degradation, climate
                change and the destruction of habitats. The environmental
                rule of law seeks a unified understanding of these concepts.
                There are significant linkages between concepts such as
G               sustainable development, the polluter pays principle and
                the trust doctrine. The universe of nature is indivisible and
                integrated. The state of the environment in one part of the earth
                affects and is fundamentally affected by what occurs in another

      23
H          (2021) 4 SCC 309
PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                              179
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

   part. Every element of the environment shares a symbiotic               A
   relationship with the others. It is this inseparable bond and connect
   which the environmental rule of law seeks to explore and
   understand in order to find solutions to the pressing problems which
   threaten the existence of humanity. The environmental rule of
   law is founded on the need to understand the consequences
                                                                           B
   of our actions going beyond local, State and national
   boundaries. The rise in the oceans threatens not just
   maritime communities. The rise in temperatures, dilution
   of glaciers and growing desertification have consequences
   which go beyond the communities and creatures whose
   habitats are threatened. They affect the future survival of             C
   the entire eco-system. The environmental rule of law
   attempts to weave an understanding of the connections in
   the natural environment which make the issue of survival
   a unified challenge which confronts human societies
   everywhere. It seeks to build on experiential learnings of
                                                                           D
   the past to formulate principles which must become the
   building pillars of environmental regulation in the present
   and future. The environmental rule of law recognises the
   overlap between and seeks to amalgamate scientific
   learning, legal principle and policy intervention.
   Significantly, it brings attention to the rules, processes and          E
   norms followed by institutions which provide regulatory
   governance on the environment. In doing so, it fosters a
   regime of open, accountable and transparent decision
   making on concerns of the environment. It fosters the
   importance of participatory governance — of the value in
                                                                           F
   giving a voice to those who are most affected by
   environmental policies and public projects. The structural
   design of the environmental rule of law composes of
   substantive, procedural and institutional elements. The tools
   of analysis go beyond legal concepts. The result of the framework
   is more than just the sum total of its parts. Together, the elements    G
   which it embodies aspire to safeguard the bounties of nature against
   existential threats. For it is founded on the universal recognition
   that the future of human existence depends on how we conserve,
   protect and regenerate the environment today.”
                                                (emphasis supplied)        H
180            SUPREME COURT REPORTS                           [2022] 8 S.C.R.


A           The Court also acknowledged the difficulty faced in implementing
      such processes in the face of scientific uncertainty. However, it noted
      that Courts cannot be stupefied into inaction due to scientific uncertainty
      but must take decisions to protect the environment based on whatever
      information is available. The Court held:
B           “53. However, even while using the framework of an environmental
            rule of law, the difficulty we face is this — when adjudicating
            bodies are called on to adjudicate on environmental infractions,
            the precise harm that has taken place is often not susceptible to
            concrete quantification. While the framework provides
            valuable guidance in relation to the principles to be kept in
C
            mind while adjudicating upon environmental disputes, it
            does not provide clear pathways to determine the harm
            caused in multifarious factual situations that fall for judicial
            consideration. The determination of such harm requires
            access to scientific data which is often times difficult to come
D           by in individual situations.
            54…The point, therefore, is simply this — the environmental rule
            of law calls on us, as Judges, to marshal the knowledge emerging
            from the record, limited though it may sometimes be, to respond
            in a stern and decisive fashion to violations of environmental law.
E           We cannot be stupefied into inaction by not having access
            to complete details about the manner in which an
            environmental law violation has occurred or its full
            implications. Instead, the framework, acknowledging the
            imperfect world that we inhabit, provides a roadmap to deal
            with environmental law violations, an absence of clear
F
            evidence of consequences notwithstanding.”
                                                         (emphasis supplied)
             32. The precautionary principle envisages that the State cannot
      refuse to act to preserve the environment simply because all the scientific
G     data may not be available. If there is some data to suggest that
      environmental degradation is possible, the State must step into action to
      prevent it from taking place. Indeed, it was this thought that compelled
      this Court in T.N. Godavarman (supra) to direct the State to identify
      ESZs across India, so that steps can be taken to identify areas where
      there is a greater possibility of environmental degradation and a plan is
H
 PRAGNESH SHAH v. DR. ARUN KUMAR SHARMA & ORS.                                 181
      [DR. DHANANJAYA Y CHANDRACHUD, J.]

put in place to prevent such degradation before it actually makes the          A
harm irreversible.
       33. Mount Abu was identified as an ESZ, under the ESZ
Notification. The reason for doing this is because the State recognized
that environmental degradation of the fragile eco-system is a real
possibility in Mount Abu and the area surrounding it if action is not          B
immediately taken. A significant amount of soil erosion, air and water
pollution has already taken place due to the developmental activities.
The recitals in the ESZ Notification recognize the ecological importance
of Mount Abu since it contains both tropical dry deciduous forests and
evergreen forests; its flora and fauna comprise of several endemic and
rare species; and it also contains not only natural heritage such as Nakki     C
lake but also man-made heritage sites such as the Dilwara temples. The
ESZ notification required, inter alia, the State of Rajasthan to prepare
the ZMP 2030, so as to ensure that future development activity in the
region could be planned while accounting for potential environmental
degradation, following the precautionary principle. The ESZ notification       D
is backed by a statutory mandate of Union legislation. The Notification
is an enforceable charter for the preservation of the fragile eco-system
of Mount Abu. Every authority is duty bound to comply with its terms
and any action in breach must peril invalidation.
      H Conclusion                                                             E
      34. Therefore, we hold that the NGT’s judgment and order dated
10 March 2021 and 29 July 2021 correctly directed the ZMP 2030 to be
modified to bring it into conformity with the ESZ Notification and the
precautionary principle. Specifically, it correctly upheld the Expert
Committee Report’s recommendation that no construction should be               F
allowed to take place on the appellant’s land.
       35. For the above reasons, we have come to the conclusion that
there is no merit in the present appeal and it shall accordingly stand
dismissed.
                                                                               G
Ankit Gyan                                                 Appeal dismissed.




                                                                               H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Eco‑sensitive zone"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.