Created byFuzzy Cloud

Supreme Court of India

PAM DEVELOPMENTS PRIVATE LIMITEDversusTHE STATE OF WEST BENGAL & ANR.

Citation
2024 INSC 628
Decided
23 August 2024

Holding

The High Court correctly set aside the labour‑charges award as it violated the contract’s special terms, but it erred in interfering with the arbitrator’s award of interest, since s.31(7) empowers the tribunal to grant pre‑reference, pendente lite and post‑award interest unless the contract expressly prohibits it.

Summary

Pam Developments Private Ltd entered into a work contract with the State of West Bengal for road widening, which was completed after a five‑month delay. The contractor claimed several sums, including labour charges for uneconomical stoppage, interest on delayed payment of running‑account bills, and pre‑reference interest, which were awarded by an arbitrator. The State challenged the award; the District Judge set aside some claims, and the Calcutta High Court further set aside the labour‑charges claim and modified the interest awards. The Supreme Court examined whether the High Court correctly interfered with the arbitral award, focusing on the contractual prohibition of idle‑labour claims and the arbitrator’s statutory power to award interest under s.31(7) of the Arbitration and Conciliation Act, 1996. It held that the High Court was right to reject the labour‑charges claim but was wrong to disturb the interest awards, as the contract did not forbid pre‑reference interest. Consequently, the Court set aside the High Court’s judgment on the interest claims while upholding its decision on the labour‑charges claim, allowing the appeal in part.

Issues considered

  • The arbitral award for labour charges for uneconomical stoppage of work contravened the contract's special terms and conditions.
  • Whether the arbitrator had the authority under s.31(7) of the Arbitration and Conciliation Act, 1996 to award pre‑reference, pendente lite and post‑award interest absent an express contractual bar.
  • Whether the High Court was justified in setting aside the arbitral award for interest on delayed payment of running‑account bills.
  • Whether the High Court erred in modifying the award by removing pre‑reference interest.

Legislation cited

Subjects

Arbitral awardLabour charges for uneconomical stoppage of workInterest on delayed paymentInterestWork contractLoss of businessUneconomic utilization of plant and machineryEscalation billCostsContractual provisionsPre-reference interestSpecial Terms and Conditions of the ContractPublic policyPendente lite interestPost award interest

Judgment

                  [2024] 8 S.C.R. 615 : 2024 INSC 628

                 Pam Developments Private Limited
                                 v.
                  The State of West Bengal & Anr.
                   (Civil Appeal Nos. 9781-9782 of 2024)
                                23 August 2024
   [Pamidighantam Sri Narasimha* and Pankaj Mithal, JJ.]

                            Issue for Consideration
       Matter pertains to the arbitral award in favour of the contractor
       as regards labour charges for uneconomical stoppage of work,
       interest on delayed payment, and interest, upheld by the District
       Judge but set aside/modified by the High Court.

                                   Headnotes†
       Arbitration and Conciliation Act, 1996 – ss. 34 and 37 – Arbitral
       awards – Work contract – Claims raised by the contractor under
       different heads alleging delays on the part of the State, referred
       to the arbitrator – Arbitral award in favour of the contractor
       under heads-loss of business, uneconomic utilization of plant
       and machinery, labour charges for uneconomical stoppage of
       work, interest on delayed payment, escalation bill, interest and
       costs – Award challenged by the State, whereby the District
       Judge set aside few of the claims – High Court modified the
       award – Interference with:
       Held: Decision of the High Court setting aside the award with
       respect to claim as regards labour charges for uneconomical
       stoppage of workup held since the arbitrator did not even refer to
       the contractual provisions which prohibited such claim – Judgment
       of the High Court setting aside claim of interest on delayed payment
       awarded by the Arbitrator, as upheld by the District Judge u/s. 34 is
       set aside since nothing perverse in the reasoning of the Arbitrator
       and nor such conclusion against public policy – Judgment of
       the High Court in so far as it modified claim as regards interest,
       to the extent of rejecting pre-reference interest awarded by the
       arbitrator, as upheld by the District Judge u/s. 34 is set aside since
       the High Court had no reason to interfere with the Arbitral Award
       with respect to grant of pre-reference interest, since the contract

* Author
616                                                             [2024] 8 S.C.R.

                        Digital Supreme Court Reports


       between parties does not prohibit the same – Award as regards
       labour charges for uneconomical stoppage of work set aside and
       award as regards interest on delayed payment is upheld – As
       regards the claim of interest, the appellant entitled to claim pre-
       reference interest. [Para 10]
       Arbitration and Conciliation Act, 1996 – Work contract –
       Arbitration proceedings – Contractual clauses – Interpretation
       of – Claim relating to loss caused due to idle labour, machinery –
       High Court held that the said claim is impermissible under
       the contractual provisions – Correctness:
       Held: Contract clauses speak for themselves – High Court did
       what the Arbitrator should have done and examined what the
       contract provides – This is not even a matter of interpretation – It
       is the duty of every arbitral tribunal and court alike and without
       exception, for contract is the foundation of the legal relationship –
       High Court came to the conclusion that awarding any amount
       towards idle, machinery, etc. is prohibited under the ‘Special Terms
       and Conditions’ of the Contract – Arbitrator did not even refer to
       the contractual provisions and the District Court dismissed the
       objections u/s. 34 with a standard phrase – High Court exercising
       jurisdiction u/s 37 did its duty and the conclusions of the High
       Court are correct and cannot be interfered with. [Paras 7, 7.3-7.5]
       Arbitration and Conciliation Act, 1996 – ss. 34, 37 – Dispute
       relating to work contract – Arbitral award – Arbitrator awarded
       interest on delayed payment of running account bills – Upheld
       by the District Court – However, the High Court set aside the
       award – Challenge to:
       Held: Conclusion of the High Court, that it appears that the bills
       were paid soon after they were prepared or that, in that case
       there could not have been any claim for interest cannot qualify
       as grounds for interference u/s 37 – Equally, the approach of
       the High Court in holding that the Arbitrator neither established
       nor discussed the questions posed by it, not a ground to set
       aside the Award – Reasoning of the Arbitrator is reflected in that
       portion of the Award and nothing perverse is seen in it – Nor
       such conclusion is against the public policy – Judgment of the
       High Court in relation to the said claim set aside and the Award
       is restored. [Paras 8.5, 8.6]
[2024] 8 S.C.R.                                                              617

Pam Developments Private Limited v. The State of West Bengal & Anr.


     Arbitration and Conciliation Act, 1996 – ss. 34, 37 – Dispute
     relating to work contract – Arbitral award – As regards claim
     relating to Interest, Arbitrator awarded interest @12% on
     sum awarded from the date when appellant claimed breach
     of contract, to the date of the Award, and further interest @
     9.25% p.a. from date of Award till actual payment – District
     Judge upheld the same – However, the High Court held that
     pre-reference interest could not have been granted for this
     period, and that as the Arbitrator could have granted interest
     only for pendent lite and post award, the Award was modified
     directing pendente lite interest along with post award interest –
     Correctness:
     Held: s. 31(7) determines the grant of interest – Power of the
     Arbitrator to grant pre-reference interest, pendente lite interest,
     and post-award interest u/s 31(7) of the Act is fairly well-settled –
     High Court had no reason to interfere with the Arbitral Award with
     respect to grant of pre-reference interest, since the contract between
     parties does not prohibit the same. [Paras 9.4-9.6]
     Arbitration and Conciliation Act, 1996 – s 37(1) – Power of the
     Arbitrator to grant pre-reference interest, pendente lite interest,
     and post-award interest under – Difference in the position of
     law under the Arbitration Act, 1940 – Encapsulated. [Para 9.5]

                              Case Law Cited
     Secretary, Irrigation Department, Government of Orissa v. G.C.
     Roy [1991] Supp. 3 SCR 417 : (1992) 1 SCC 508; Executive
     Engineer, Dhenkanal Minor Irrigation Division, Orissa v. N.C.
     Budharaj [2001] 1 SCR 264 : (2001) 2 SCC 721; Union of
     India v. Krafters Engg. and Leasing (P) Ltd. [2011] 8 SCR 196 :
     (2011) 7 SCC 279; Board of Trustees for the Port of Calcutta
     v. Engineers-de-Space-Age [1995] Supp. 6 SCR 327 : (1996)
     1 SCC 516; Madnani Construction Corporation Private Limited
     v. Union of India [2009] 16 SCR 216 : (2010) 1 SCC 549; Tehri
     Hydro Development Corporation Ltd. v. Jai Prakash Associates
     Ltd. [2012] 8 SCR 813 : (2012) 12 SCC 10; Union of India v.
     Ambica Construction [2016] 2 SCR 810 : (2016) 6 SCC 36;
     Ambica Construction v. Union of India (2017) 14 SCC 323;
     Raveechee and Company v. Union of India [2018] 5 SCR 138 :
     (2018) 7 SCC 664; Reliance Cellulose Products Ltd. v. ONGC Ltd.
     [2018] 6 SCR 618 : (2018) 9 SCC 266; State of U.P. v. Harish
618                                                               [2024] 8 S.C.R.

                        Digital Supreme Court Reports


       Chandra and Co. [1998] Supp. 2 SCR 660 : (1999) 1 SCC 63;
       Sayeed Ahmed and Company v. State of Uttar Pradesh [2009]
       10 SCR 841 : (2009) 12 SCC 26; Union of India v. Saraswat
       Trading Agency [2009] 10 SCR 1063 : (2009) 16 SCC 504;
       Sree Kamatchi Amman Constructions v. The Divisional Railway
       Manager (Works), Palghat [2010] 10 SCR 487 : (2010) 8 SCC
       767; Union of India v. Bright Power Projects (India) Pvt Ltd. [2015]
       6 SCR 488 : (2015) 9 SCC 695; Jaiprakash Associates Limited
       v. Tehri Hydro Development Corporation India Limited [2019] 2
       SCR 41 : (2019) 17 SCC 786; Delhi Airport Metro Express Private
       Limited v. Delhi Metro Rail Corporation [2022] 3 SCR 716 : (2022)
       9 SCC 286; Oriental Structural Engineers Private Limited v. State
       of Kerala [2021] 4 SCR 137 : (2021) 6 SCC 150; Central Bank of
       India v. Ravindra [2001] Supp. 4 SCR 323 : (2002) 1 SCC 367;
       Secy./GM, Chennai, Central Coop. Bank Ltd. v. S. Kamalaveni
       Sundaram [2011] 1 SCR 66 : (2011) 1 SCC 790 – referred to.

                                   List of Acts
       Arbitration and Conciliation Act, 1996; Arbitration Act, 1940; Interest
       Act, 1978.

                                List of Keywords
       Arbitral award; Labour charges for uneconomical stoppage of
       work; Interest on delayed payment; Interest; Work contract; Loss of
       business; Uneconomic utilization of plant and machinery; Escalation
       bill; Costs; Contractual provisions; Pre-reference interest; Special
       Terms and Conditions of the Contract; Public policy; Pendente lite
       interest; Post award interest.

                               Case Arising From
       CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 9781-9782 of
       2024
       From the Judgment and Order dated 03.06.2021 of the High Court at
       Calcutta in FMAT No.376 of 2019 and COT No. 54 of 2019
                            Appearances for Parties
       Saurav Agarwal, Priyankar Saha, Sarad Kumar Singhania, Ms.
       Rashmi Singhania, Anshuman Choudhry, Advs. for the Appellant.
       Ms. Madhumita Bhattacharjee, Ms. Srija Choudhury, Anant, Ms. Sajal
       Bhrdwaj, Advs. for the Respondents.
[2024] 8 S.C.R.                                                         619

Pam Developments Private Limited v. The State of West Bengal & Anr.


                       Judgment / Order of the Supreme Court

                                             Judgment
       Pamidighantam Sri Narasimha, J.
1.     Leave granted.
2.     State of West Bengal, respondent herein, issued a notice inviting
       tenders on 08.09.2010, for the widening and strengthening of Egra
       Bajkul road under the Tamluk Highway Division in Purbo Medinipur
       District and accepted appellant’s offer, leading to grant of a Work
       Order for the project to be completed within 18 months from
       23.12.2010. The project got delayed by about five months, but the
       work was completed by 09.11.2012.
3.     The appellant raised a bill for Rs. 77,85,290 and that was in addition
       to seven other claims under different heads, owing to alleged delays
       on part of the Respondent. As the respondent denied any liability,
       the dispute was referred to Arbitration for resolution.
4.     The Arbitrator gave his award on 30.01.2018, holding the respondents
       are liable to the tune of Rs.1,37,25,252, with interest. There
       were seven claims. Claim no. 1 related to loss of business, with
       respect to which Rs. 3,87,530 was awarded; claim no. 2 related
       to uneconomic utilization of plant and machinery, with respect to
       which Rs. 61,22,000 was awarded and claim no. 3 related to labour
       charges for uneconomical stoppage of work, with respect to which
       Rs.5,80,500 was awarded; claim no. 4 related to interest on delayed
       payment of running account bills and escalation bill for which the
       Arbitrator awarded Rs. 54,84,024; claim no. 5 related to escalation
       with respect to which Rs.11,51,198 was granted; and claim 6 related
       to interest on the sum awarded, with respect to which interest @12%
       p.a. was awarded from 12.04.2016 to 30.01.2018 and @ 9.25%
       p.a. post award interest till date of actual payment. Finally claim
       no.7 pertained to costs and the Arbitrator awarded 4 lakhs to the
       appellant, being the successful party.
       4.1 The Respondents challenged the award under Section 34 of
           the Arbitration and Conciliation Act, 19961 and it was allowed


1    Hereinafter referred to as the ‘Act’.
620                                                          [2024] 8 S.C.R.

                        Digital Supreme Court Reports


            in part by the District Judge setting aside claim no. 1 for loss
            of business, since the same had never been claimed by the
            appellant and was thus beyond the Arbitrator’s jurisdiction. Claim
            no. 2 for uneconomic utilization of plant and machinery was also
            set aside because the Arbitrator didn’t account for the loss of
            135 days at the behest of the appellant while determining the
            alleged 200 days of ‘wasted machine’.
       4.2 Aggrieved by the decision of the District Judge, the appellant
           filed an appeal under Section 37 of the Act against the order
           setting aside the award on claims 1 and 2. On the other hand,
           the Respondent filed a cross appeal seeking setting aside of
           the rest of the claims as well. By the order impugned before
           us, the Calcutta High Court exercising jurisdiction under
           Section 37 of the Act set aside claim no.1 as well as claim
           nos. 3 and 4, but restored the Award with respect to claim
           no.2. However, while retaining claim no. 5 as it is, the High
           Court slightly modified claim no. 6 relating to pre-reference
           interest.
5.     A comprehensive table of the claims and the decision in the Award,
       Section 34 and Section 37 jurisdiction is as follows –

       Claim no.        Arbitral Award    Section 34            Section 37
       1. Loss of       Awarded           Award Set aside,      Affirmed
       business         Rs.3,87,530.      because it was        the decision
                                          never claimed by      of District
                                          the appellant and     judge.
                                          was the basis for
                                          granting of-site
                                          expenses.
       2.               Awarded Rs.       Award set aside, as Awarded
       Uneconomic       61,22,000 for     Arbitrator did not  claim no.
       utilization of   deploying plant   account for wastage 2, thereby
       plant and        and machinery     of 135 days by the reversing
       machinery        on all 200 wasted appellant itself.   decision by
                        days as required                      the District
                        under the                             Judge.
                        Contract.
[2024] 8 S.C.R.                                                       621

Pam Developments Private Limited v. The State of West Bengal & Anr.



      3. Labour       Arbitrator granted Award upheld by the Set aside,
      Charges for     3% of the          District Court.     because it is
      uneconomical    contract amount                        contrary to
      stoppage of     Rs.5,80,500/- as                       the Special
      work            per the Hudson’s                       Terms and
                      formula.                               Conditions
                                                             of the
                                                             Contract.
      4. Interest    Awarded Rs.     Award upheld by the Set aside
      on delayed     54,84,024/- on  District Court.     because
      payment        the ground                          monthly bills
      of Running     of interest on                      raised by
      Account Bills blocked capital                      appellants
      and Escalation (when amount                        were paid
      Bills          exceeded Rs.1                       without
                     crore) @12% pa.                     delay. As per
                                                         clauses 7-9,
                                                         no claim
                                                         for interest
                                                         arises.
      5. Escalation   Awarded           Award upheld by the Affirmed the
      Bill            Rs.11,51,198/- as District Court.     Award and
                      respondent has                        decision of
                      already paid part                     the District
                      of such amount.                       Judge.
                      The claimant is
                      entitled to the
                      balance.
      6. Interest     Arbitrator        Award upheld by      Modified.
                      awarded interest the District Judge.   Only interest
                      @12% on                                pendent
                      amount of claims                       lite and
                      w.e.f 12.04.2016                       post award
                      to the date of                         payable.
                      Award and further                      No interest
                      interest @9.25%                        for pre-
                      p.a. from date of                      reference
                      award till actual                      period.
                      payment.
622                                                         [2024] 8 S.C.R.

                      Digital Supreme Court Reports



       7. Cost         Awarded Rs.4
                       Lakhs towards
                       legal and
                       administrative
                       expenses.

6.     Mr. Saurav Agarwal, counsel for the appellant, confined his
       submissions to claim no. 3, 4 and 6 awarded by the Arbitrator and
       upheld by the District Judge but set aside/modified by the High Court.
       We will deal with each of these claims.
7.     Re claim no. 3: This claim relating to loss caused due to idle labour,
       machinery, etc.
       7.1 On this count, the Arbitrator accepted the claim of loss on the
           ground of on-site establishment ‘as permissible’ to the extent
           of 3% of the contract amount by the Hudson’s formula for
           expenses of engineers, supervisors, etc. It was his considered
           view that the appellant maintained such an establishment to
           execute the work and the same has not been disputed by the
           Respondent. Therefore, he awarded claim no. 3 in favour of
           the appellant for Rs.5,80,500.
       7.2 The challenge to the Award made by the Respondent was
           dismissed by the District Judge under Section 34, holding that
           the findings of the Arbitrator cannot be held to be irrational,
           insensible or unrealistic and also that they are not in conflict
           with public policy. We may state at this very stage that this
           common reasoning of the District Court while upholding the
           Award for claim nos. 3, 4, 5 and 6. The standard reasoning of
           the District Court for these claims is as follows:
                 “I have gone through the observation of the learned
                 Arbitrator in respect of claim Nos. 3, 4, 5 and 6.
                 On meticulous scrutiny of the award with reference
                 to the documents produced by the parties to the
                 ease, I find that the reasons and findings given
                 by the learned Arbitrator cannot be said to be
                 irrational, insensible or unrealistic. In fact, award
                 in respect of claim Nos. 3, 4, 5 & 6 cannot be said
[2024] 8 S.C.R.                                                           623

Pam Developments Private Limited v. The State of West Bengal & Anr.


                to be.in conflict with the public policy of India even
                by stretch of Imagination. On the other hand, it is
                apparent that cogent and acceptable reasons have
                been furnished by the learned Arbitrator in respect
                of these four heads of claims (claim Nos. 3 to 6).
                The award in respect of such four claims does not
                call for any interference.”
     7.3 While exercising jurisdiction under Section 37, the High Court
         examined the relevant clauses of the contract and held the
         claim is impermissible under the contractual provisions. They
         are extracted herein below for ready reference.
                ‘’SPECIAL TERMS AND CONDITIONS
                CONDITION IN EXTENDED PERIOD
                As Clause 4 of W.B.F. 2908 or Clause 5 of W.B.F.
                No.2911 (ii) as the case may be when an extension
                of time for completion of work is authorised by the
                Engineer-In-Charge, it will be taken for granted that
                the validity of the contract is extended automatically
                upon the extended period with all terms and conditions
                rates, etc. remaining unaltered, i.e. the tender is
                revalidated upon the extended period.
                EXTENSION OF TIME
                For cogent reasons over which the contractor will
                have no control and which will retard the· progress,
                extension of time for the period lost will be granted
                on receipt of application from the contractor before
                the expiry date of contract. No claim whatsoever for
                idle labour, additional establishment, cost of materials
                and labour and hire charges of tools & Plants etc.
                would be entertained under any circumstances. The
                contractor should consider the above factor while
                quoting this rate. Applications for such extension of
                time should be submitted by the contractor in the
                manner indicated in Clause 5 of the printed form of
                W.B.F. No. 2911 (ii).
                IDLE LABOUR Whatever the reasons may be no claim
                or idle labour, enhancement of labour rate additional
624                                                         [2024] 8 S.C.R.

                      Digital Supreme Court Reports


                 establishment cost, cost of TOLL and hire and labour
                 charges of tools and plants Railway freight etc. would
                 be entertained under any circumstances.”
       7.4 Mr. Saurav Agarwal submitted that the High Court under Section
           37 ignored the plausible view of the Arbitrator, as upheld under
           Section 34, and substituted it with its own reasoning.
       7.5 This submission is persuasive, but the contract clauses speak
           for themselves. In fact, High Court did what the Arbitrator
           should have done. Examine what the contract provides. This
           is not even a matter of interpretation. It is the duty of every
           Arbitral Tribunal and Court alike and without exception, for
           contract is the foundation of the legal relationship. Having
           considered the above referred clauses in the Contract the
           High Court came to the conclusion that awarding any amount
           towards idle, machinery, etc. is prohibited under the ‘Special
           Terms and Conditions’ of the Contract. The Arbitrator did not
           even refer to the contractual provisions and the District Court
           dismissed the objections under Section 34 with a standard
           phrase as extracted hereinabove. High Court exercising
           jurisdiction under Section 37 did its duty and we are of the
           opinion that the conclusions of the High Court are correct and
           cannot be interfered with.
8.     Re claim no. 4: This claim relates to interest on delayed payment
       of running account bills.
       8.1 The Arbitrator held that the Claimant is entitled to receive
           compensation for any loss and/or damage of capital which
           arose naturally from breach or which parties knew to be likely
           to arise from breach. Payments on running account bills is
           guided by clause 7 of the Contract and there is no prohibition
           in the contract regarding payment of interest on the ‘blocked
           capital’. Therefore, holding that the injured party ought to be
           placed in the same financial position he would have been but
           for the other party’s fault, the Arbitrator awarded interest on
           delayed payments at the rate of 12% p.a., which was quantified
           to Rs. 54,84,024. As indicated above, the District Court upheld
           the Award.
[2024] 8 S.C.R.                                                             625

Pam Developments Private Limited v. The State of West Bengal & Anr.


     8.2 The relevant portion of the Award is as follows:-
           “23.1… As the claimant is entitled to payment of R/A
           bills when the amount is Rs. 1 crore and above, I accept
           the statements/calculation made by the claimant vide
           Statement submitted before the arbitral tribunal for Rs.
           82,26,036/-. In compliance of direction issued by MOM no.
           21 dated 24.7.2017, based on work value of Rs. one crore.
           Such statement giving all details covering the criteria of bill
           value of Rs. 1 crore was served to respondent and there
           was no comment on such statement whatsoever. Payment
           of R/A bills is guided only by the provision under clause
           7 with amendment thereon. Claimant claimed interest @
           18% p.a. which is not allowed. I restrict rate of interest @
           12% p.a. only and thereby the admissible amount of the
           claim stands at Rs. 54,84,024/- [Rs. 82,26,036 ÷ 18 X 12]
           23.2 The claimant notified loss of interest during the
           execution period under Interest Act (vide annexure-K,
           page 109, Annexure-m page-112, annexure-O, page 115,
           annex.-R1, page-119 & 122 with claimant’s document).
           Moreover, such payment is out of the written contract for
           executed quantities. There is no prohibition in the contract
           for payment of interest on blocked capital. The claimant is
           otherwise entitled to receive payment on account of interest
           on blocked capital. Such principle of law is laid down in
           the case of Secretary, Irrigation Department Government
           of Orissa Vs. G.C. Ray reported in (1992) 1 SCC 508. The
           claimant is entitled to receive compensation for any loss or
           damage and/or blockage of capital which arose naturally
           from the breach or which the parties knew to be likely to
           arrive from such breach. The injured party is to be placed
           in the same financial position, as he would have been in,
           if the other party had duly carried out the contract, i.e., to
           place the injured party in the same position if the contract
           has been performed. I award Rs. 54,84,024/- only.”
     8.3 Mr. Saurav Agarwal submitted that the payments became due
         when the gross amount of work done exceeded Rs.1 crore,
         therefore the delay was to be accounted for from this date.
626                                                           [2024] 8 S.C.R.

                       Digital Supreme Court Reports


            The error, he submits is because the High Court relied on
            chart submitted by the respondents, unlike the Arbitrator and
            the District judge who relied on appellant’s chart.
       8.4 High Court exercising jurisdiction under Section 37 merely
           recounted the dates on which the bills were raised, and the
           payments made. Thereafter High Court formulated certain
           questions, which it felt that the Arbitrator and the District Judge
           should have answered, but failed to hold any discussion on such
           questions. In this view of the matter, the High Court proceeded
           to set aside Award of claim no. 4. The relevant portion of the
           High Court Judgment is as follows:-
                 “The learned Arbitrator proceeded on the basis of the
                 statement submitted by the appellant that there was
                 delay in the payment of these bills. The unpaid running
                 account bills were described as “blocked capital”. He
                 viewed the delay in receiving “this blocked capital” as
                 “loss and damage” to the appellant and granted Rs.
                 54,84,024/- on that reasoning, as “interest”.
                 The learned Judge upheld this award. It is challenged
                 by the respondent. The respondent relies on Clauses
                 7, 8 and 9 of the contract by which monthly bills had
                 to be raised by the appellant on the measurement
                 made. These payments against the monthly running
                 account bills were to be treated as advance under
                 Clause 7. Payment could have been made only when
                 the gross amount exceeded Rs. 1 crore. According
                 to the respondent no bill was raised by the appellant.
                 According to the statement of claim of the appellant,
                 the first bill for Rs. 1,32,91,180/- was prepared on 29th
                 August, 2011 and paid on or about 30th August 2011.
                 Similarly, the second was prepared on 7th February,
                 2012 and paid on 9th February, 2012. The third and
                 fourth bills for Rs. 1,28,23,488/- and Rs. 1,30,90,000/-
                 respectively were prepared on 5th March, 2012 and
                 paid between 30th March, 2012 and 20th June, 2012.
                 The fifth bill for Rs. 3,14,82,214/- was prepared on 6th
                 July, 2012 and paid between 24th July, 2012 and 1st
[2024] 8 S.C.R.                                                          627

Pam Developments Private Limited v. The State of West Bengal & Anr.


                October, 2012. The sixth bill was raised on 5th July,
                2012 and paid between 6th July, 2012 and 1st October,
                2012. The work was completed on 9th November, 2012.
                What the learned Arbitrator did not determine were
                the following:
           a)   Who was responsible for non-preparation of the RA
                bill within time?
           b)   Which of the RA bill claims of the appellant were to
                be treated as advance under the above clause of
                the contract?
           c)   Was any notice under the Interest Act, 1978 issued
                by the appellant and to what effect?
           d)   For what amount and for which period the claim for
                interest was being entertained and granted by him?
                From the above narration of facts it appears that
                the bills were paid soon after they were prepared.
                In that case there could not have been any claim
                for interest. If a claim for interest has been made
                for running account bill below one crore, under the
                said terms it is to be treated as a claim for interest
                for unpaid advance. No right to claim interest arose.
                Now, unless these facts were established by the
                appellant and discussed by the learned Arbitrator to
                show that there was delay in the preparation of the
                bills by the respondent, that those bills were over
                one crore and not be treated as advance and that
                the right to obtain payment thereof arose on their
                due submission and service of a notice under the
                Interest Act, 1978, the award of interest could not be
                justified. Total absence of discussion of these facts
                signifies that the learned Arbitrator completely failed
                to exercise its jurisdiction….”
     8.5 The conclusion of the High Court, “that it appears that the bills
         were paid soon after they were prepared” or that, “in that case
         there could not have been any claim for interest” cannot qualify
         as grounds for interference under Section 37. Equally, the
         approach of the High Court in holding that the Arbitrator neither
628                                                         [2024] 8 S.C.R.

                      Digital Supreme Court Reports


            established nor discussed the questions posed by it is not a
            ground to set aside the Award. The reasoning of the Arbitrator is
            reflected in that portion of the Award extracted hereinabove and
            we see nothing perverse in it. Nor such conclusion is against
            our public policy. The scope of Section 37 is enunciated in
            many decisions of this Court, and we apply the principles laid
            down therein to the facts of the present case.
       8.6 For these reasons, we set aside the judgment of the High Court
           in relation to claim no. 4 and restore the Award and thereby the
           judgment of the District Court upholding the Award.
9.     Re claim no. 6: This claim relates to Interest
       9.1 Arbitrator awarded interest @12% on sum awarded from
           12.04.2016, which is the date when appellant claimed breach
           of contract, to 30.01.2018, which is the date of the Award, and
           further interest @ 9.25% p.a. from date of Award till actual
           payment. This was confirmed by the District Judge under
           Section 34.
       9.2 High Court held that the contract between the parties prohibits
           grant of pre-reference interest and therefore interest could not
           have been granted for this period. As per the High Court, as
           the Arbitrator could have granted interest only for pendent lite
           and post award, the Award was modified directing - pendente
           lite interest @12% p.a. from 03.08.2016 till date of award i.e.
           30.01.2018, along with post award interest @ 9.25% p.a.
       9.3 The learned counsel for the appellants has submitted that the
           award for interest is within the domain of the Arbitrator under
           Section 31(7) and ought not to be substituted by courts under
           Section 34 or 37.
       9.4 Section 31(7) of the Act determines the grant of interest. The
           relevant provision is extracted hereunder for ready reference.
                 “31. Form and contents of arbitral award.—
                 (7) (a) Unless otherwise agreed by the parties, where
                 and in so far as an arbitral award is for the payment
                 of money, the arbitral tribunal may include in the sum
                 for which the award is made interest, at such rate
[2024] 8 S.C.R.                                                                                   629

Pam Developments Private Limited v. The State of West Bengal & Anr.


                     as it deems reasonable, on the whole or any part of
                     the money, for the whole or any part of the period
                     between the date on which the cause of action arose
                     and the date on which the award is made.
                     (b) A sum directed to be paid by an arbitral award shall,
                     unless the award otherwise directs, carry interest at
                     the rate of two per cent higher than the current rate
                     of interest prevalent on the date of award, from the
                     date of award to the date of payment.
                     Explanation.—The expression “current rate of
                     interest” shall have the same meaning as assigned
                     to it under clause (b) of section 2 of the Interest Act,
                     1978 (14 of 1978).”
     9.5 The power of the Arbitrator to grant pre-reference interest,
         pendente lite interest, and post-award interest under Section
         31(7) of the Act is fairly well-settled. The judicial determinations
         also highlight the difference in the position of law under
         the Arbitration Act, 1940. The following propositions can be
         summarised from a survey of these cases:
             I.      Under the Arbitration Act, 1940, there was no specific
                     provision that empowered an Arbitrator to grant interest.
                     However, through judicial pronouncements, this Court
                     has affirmed the power of the Arbitrator to grant pre-
                     reference, pendente lite, and post-award interest on the
                     rationale that a person who has been deprived of the use
                     of money to which he is legitimately entitled has a right
                     to be compensated for the same.2 When the agreement
                     does not prohibit the grant of interest and a party claims
                     interest, it is presumed that interest is an implied term of
                     the agreement, and therefore, the Arbitrator has the power
                     to decide the same.3
             II.     Under the 1940 Act, this Court has adopted a strict


2   Secretary, Irrigation Department, Government of Orissa v. G.C. Roy (1992) 1 SCC 508, para 43(i). Also
    see Executive Engineer, Dhenkanal Minor Irrigation Division, Orissa v. N.C. Budharaj, (2001) 2 SCC
    721; Union of India v. Krafters Engg. and Leasing (P) Ltd. (2011) 7 SCC 279
3   G.C. Roy (supra), paras 43(iv) and 44.
630                                                                                [2024] 8 S.C.R.

                            Digital Supreme Court Reports


                     construction of contractual clauses that prohibit the grant
                     of interest and has held that the Arbitrator has the power
                     to award interest unless there is an express, specific
                     provision that excludes the jurisdiction of the Arbitrator4
                     from awarding interest for the dispute in question.5
             III.    Under the 1996 Act, the power of the Arbitrator to grant
                     interest is governed by the statutory provision in Section
                     31(7). This provision has two parts. Under sub-section (a),
                     the Arbitrator can award interest for the period between the
                     date of cause of action to the date of the award, unless
                     otherwise agreed by the parties. Sub-section (b) provides
                     that unless the award directs otherwise, the sum directed
                     to be paid by an arbitral award shall carry interest at the
                     rate of 2% higher than the current rate of interest, from
                     the date of the award to the date of payment.
             IV.     The wording of Section 31(7)(a) marks a departure from
                     Arbitration Act, 1940 in two ways: first, it does not make an
                     explicit distinction between pre-reference and pendente lite
                     interest as both of them are provided for under this sub-
                     section; second, it sanctifies party autonomy and restricts
                     the power to grant pre-reference and pendente lite interest
                     the moment the agreement bars payment of interest, even
                     if it is not a specific bar against the Arbitrator.6
             V.      The power of the Arbitrator to award pre-reference and
                     pendente lite interest is not restricted when the agreement



4   Board of Trustees for the Port of Calcutta v. Engineers-de-Space-Age (1996) 1 SCC 516, paras 4 and
    5; Madnani Construction Corporation Private Limited v. Union of India (2010) 1 SCC 549; Tehri Hydro
    Development Corporation Ltd. v. Jai Prakash Associates Ltd. (2012) 12 SCC 10, paras 18-20; Union of
    India v. Ambica Construction (2016) 6 SCC 36 (First Ambica Construction Case); Ambica Construction
    v. Union of India (2017) 14 SCC 323 (Second Ambica Construction Case); Raveechee and Company v.
    Union of India (2018) 7 SCC 664; Reliance Cellulose Products Ltd. v. ONGC Ltd. (2018) 9 SCC 266
5   State of U.P. v. Harish Chandra and Co. (1999) 1 SCC 63
6   Sayeed Ahmed and Company v. State of Uttar Pradesh (2009) 12 SCC 26, paras 14, 23, 24; Union of
    India v. Saraswat Trading Agency (2009) 16 SCC 504; Sree Kamatchi Amman Constructions v. The
    Divisional Railway Manager (Works), Palghat (2010) 8 SCC 767, para 19; Union of India v. Bright Power
    Projects (India) Pvt Ltd. (2015) 9 SCC 695, para 13; Reliance Cellulose Products Ltd (supra), para 24;
    Jaiprakash Associates Limited v. Tehri Hydro Development Corporation India Limited (2019) 17 SCC
    786, paras 13-15; Delhi Airport Metro Express Private Limited v. Delhi Metro Rail Corporation (2022) 9
    SCC 286, paras 16-20, 24
[2024] 8 S.C.R.                                                                                      631

Pam Developments Private Limited v. The State of West Bengal & Anr.


                      is silent on whether interest can be awarded7 or does not
                      contain a specific term that prohibits the same.8
              VI.     While pendente lite interest is a matter of procedural law,
                      pre-reference interest is governed by substantive law.9
                      Therefore, the grant of pre-reference interest cannot be
                      sourced solely in Section 31(7)(a) (which is a procedural
                      law), but must be based on an agreement between the
                      parties (express or implied), statutory provision (such as
                      Section 3 of the Interest Act, 1978), or proof of mercantile
                      usage.10
      9.6 In view of the above, the High Court had no reason to interfere
          with the Arbitral Award with respect to grant of pre-reference
          interest, since the Contract between parties does not prohibit
          the same.
10. Having analysed the reasoning in the Award and the judgment of
    the District Judge under Section 34 of the Act and of the High Court
    under Section 37 with respect to claim nos. 3, 4 and 6, we;
      (a)     Uphold the decision of the High Court in setting aside the
              Award with respect to claim no. 3 and dismiss the Civil Appeal
              to this extent.
      (b)     Allow the appeal and set aside the judgment of the High Court
              in so far as it rejected and set aside claim no. 4 awarded by
              the Arbitrator, as upheld by the District Judge under Section 34.
      (c)     Allow the appeal and set aside the judgment of the High Court
              in so far as it modified claim no. 6, to the extent of rejecting
              pre-reference interest awarded by the Arbitrator, as upheld by
              the District Judge under Section 34.
      (d)     In conclusion, Award of claim no. 3 is set aside and Award of
              claim no. 4 is upheld. Under claim no.6, the appellant will also
              be entitled to claim pre-reference interest.


7    Jaiprakash Associates Limited v. Tehri Hydro Development Corporation India Limited (2019) 17 SCC
     786, para 13.2
8    Oriental Structural Engineers Private Limited v. State of Kerala (2021) 6 SCC 150, paras 15-18
9    Central Bank of India v. Ravindra (2002) 1 SCC 367, para 39 following G.C. Roy (supra), para 43(v)
10   Central Bank of India (supra), para 39; Secy./GM, Chennai, Central Coop. Bank Ltd. v. S. Kamalaveni
     Sundaram (2011) 1 SCC 790, para 13
632                                                        [2024] 8 S.C.R.

                           Digital Supreme Court Reports


11. The Civil Appeal arising out of SLP (C) No. 8128 of 2021 is allowed
    in part as indicated hereinabove and Civil Appeal arising out of SLP
    (C) No. 8129/2021 stands disposed of accordingly. Parties shall bear
    their own costs.


       Result of the case: Civil Appeal arising out of SLP (C) No. 8128 of
                            2021 partly allowed.
                            Civil Appeal arising out of SLP (C) No. 8129 of
                            2021 disposed of.



       †
           Headnotes prepared by: Nidhi Jain


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitral award"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.