Created byFuzzy Cloud

Supreme Court of India

NATIONAL INSURANCE CO. LTD.versusM/S. BOGHARA POLYFAB PVT. LTD.

Citation
2008 INSC 1057
Decided
18 September 2008
Disposal
Dismissed

Holding

A claim for arbitration is not barred merely because a full and final discharge voucher has been executed; if the voucher’s validity is disputed on grounds of fraud, coercion or undue influence, the dispute remains arbitrable and must be referred to arbitration.

Summary

The Supreme Court examined whether an insurance dispute could be referred to arbitration after the insured had executed an undated full‑and‑final discharge voucher. The insured claimed the voucher was signed under coercion and that the insurer had conditioned payment on its execution. The Court held that the existence of a discharge voucher does not automatically bar arbitration; if the voucher’s validity is contested on grounds of fraud, duress or undue influence, the dispute remains arbitrable. It outlined the categories of preliminary issues a Chief Justice must decide under Section 11 of the Arbitration and Conciliation Act, 1996, and clarified that an arbitration clause survives unless the contract is genuinely discharged by performance or accord and satisfaction. Applying these principles, the Court found no accord and satisfaction in the present case and ordered that the matter be referred to arbitration. The appeal was dismissed.

Issues considered

  • Whether a dispute raised after execution of a full‑and‑final discharge voucher can be referred to arbitration under Section 11 of the Arbitration and Conciliation Act, 1996.
  • Whether a discharge voucher obtained by fraud, coercion or undue influence renders the contract not discharged and the dispute arbitrable.
  • Which preliminary questions the Chief Justice or his designate must decide when exercising power under Section 11.
  • Whether an arbitration clause perishes when the contract is discharged by performance, accord and satisfaction, or mutual agreement.
  • Whether the practice of obtaining undated discharge vouchers as a condition precedent to payment is lawful.

Legislation cited

Subjects

ArbitrationSection 11Discharge voucherAccord and satisfactionInsurance contractCoercionUndue influenceFull and final settlementArbitration clauseCompetence-competence

Judgment

                        [2008] 13 S.C.R. 638


A               NATIONAL INSURANCE CO. LTO.
                                 v
              M/S. BOGHARA POLYFAB PVT. LTD.
                 (Civil Appeal No. 5733 of 2008)
                      SEPTEMBER 18, 2008
B
        [R.V. RAVEENDRAN AND LOKESHWAR SINGH
                       PANTA, JJ.]

         Contract - Insurance contract - Reference to arbitration
c - After issuance of final discharge voucher by the insured -
  Propriety of - Insured alleging coersion for issuance of dis-
  charge voucher - Held: A claim for arbitration cannot be re-
  ;ected merely/solely on the ground that final discharge voucher
  had been executed by the claimant, if its validity is disputed
  by the claimant - If the claimant is able to prove that the dis-
0
  charge voucher was executed on account of fraud/coersion/
  undue influence, such voucher would be rendered void - Dis-
  charge of contract on account of performance, or accord and
  satisfaction or mutual agreement which is reduced to writing
E cannot be referred to arbitration - In the instant case, prima
  facie it appears that voucher was not issued on account of
  accord and satisfaction - Hence reference to arbitration -
  General practice by Government Departments and Corporate
  sectors of obtaining undated receipts of final settlement vouch-
  ers/No dues in advance for a sum which is smaller than the
F claim in full and final settlement of all claims, as a condition
  precedent for releasing even the admitted dues, is unfair, ir-
  regular and illegal and hence deprecated - Arbitration and
  Conciliation Act, 1996 - s. 11.
G         The question for consideration in the present appeal
    was whether a dispute raised by an insured, after giving
    full and final discharge voucher to the insurer, could be
    referred to arbitration. Contention of the insured was that
    it had given the discharge voucher under coercion and

H                               638
                NATIONAL INSURANCE CO. LTD. v. M/S. BOGHARA 639
                             POLYFAB PVT. LTD.

           pressure of the insurer in as much the insurer wanted A
           that unless and until the insurer would sign an undated
           discharge voucher in advance, it would not release even
           the admitted claim amount.
                Dismissing the appeal, the Court
                                                                         B
                 HELD: 1.1 Where the intervention of the court is
           sought for appointment of an Arbitral Tribunal under sec-
           tion 11 of Arbitration and Conciliation Act, 1996, the pre-
            liminary issues that may arise for consideration in such
           application falls into three categories, that is (i) issues c
           which the Chief Justice or his Designate is bound to de-
           cide; viz. (a) whether the party making the application has
           approached the appropriate High Court; (b) whether there
            is an arbitration agreement and whether the party who
.     ~·
            has applied u/s. 11 is a party to such an agreement. (ii)
                                                                         D
            issues which he can also decide, that is issues which he
           .may choose to decide; viz. (a) whether the claim is a dead
            (long barred) claim or a live claim (b) whether the parties
            have concluded the contract/transaction by recording
           satisfaction of their mutual rights and obligation~~or by
            receiving the final payment without objection; and (iii) is- E
           sues which should be left to the Arbitral Tribunal to de-
           cide. viz. (a) whether a claim made fails within the arbitra-
           tion clause (as for example, a matter which is reserved
. i        for final decision of a departmental authority and excepted
           or excluded from arbitration); (b) merits or any claim in- F
           volved in the arbitration. [Para 17] [656-H; 657-A-G]
                1.2 With regard to issues which the Chief Justice or
           his Designate may choose to decide if raised in any ap-
           plication under Section 11 of the Act, the chief Justice/his
                                                                        G
           designate may decide them, if necessary by taking evi-
           dence or may leave those issues open with a direction to
           the Arbitral Tribunal to decide the same. If the Chief Jus-
           tice or his Designate chooses to examine the issue and
           decide it, the Arbitral Tribunal cannot re-examine the same
                                                                        H
    640      SUPREME COURT REPORTS              [2008] 13 S.C.R.


A issue. Where allegations of forgery/fabrication are made
  in regard to the document recording discharge of con-
  tract by full and final settlement, it would be appropriate if
  the Chief Justice/his Designate decides the issue. [Para
  17] (657-H; 658-A-C]
B       1.3. A claim for arbitration cannot be rejected merely
  or solely on the ground that a settlement agreement or
  discharge voucher had been executed by the claimant, if
  its validity is disputed by the claimant. When it is con-
  tended that the dispute is not arbitrable on account of
C discharge of the contract under a settlement agreement
  or discharge voucher or no-claim certificate, and the
  claimant contends that it was obtained by fraud, coercion
  or under influence, the issue will have to be decided ei-
  ther by the Chief Justice/his designate in the proceed-
D ings under Section 11 or by the Arbitral Tribunal as di-
  rected by the order u/s. 11 of the Act. [Para 18] (658-D-E]
       1.4 The arbitration agreement contained in a contract
  cann.tt be invoked to seek reference of any dispute to
  arbitration, in the circumstances, when the contract is
E discharged on account of performance, or accord and
  satisfaction, or mutual agreement, and the same is re-
  duced to writing (and signed by both parties or by the
  party seeking arbitration. [Para 21] (660-E-F]
F       1.5 In such a case, a civil court would have consid-
  ered the evidence as to whether there was any fraud, co-
  ercion or undue influence. If it found that there was none,
  it will accept the voucher as being in discharge of the
  contract and reject the claim without examining the claim
G on merits. On the other hand, if it found that the discharge
  voucher had been obtained by fraud/undue influence/
  coercion, it will ignore the same, examine whether plain-
  tiff had made out the claim on merits and decide the mat-
  ter accordingly. The position will be the same even when
H there is a provision for arbitration. The Chief Justiceihis
         1        NATIONAL INSURANCE CO. LTD. v. MIS. BOGHARA        641
                               POLYFAB PVT. LTD.

             designate exercising jurisdiction under Section 11 of the A
             Act will consider whether there was really accord and sat-
             isfaction or discharge of contract by performance. If the
             answer is in the affirmative, he will refuse to refer the dis-
             pute to arbitration. On the other hand, if the Chief Justice/
             his designate comes to the conclusion that the full and B
             final settlement receipt or discharge voucher was the re-
             suit of any fraud/coercion/undue influence, he will have
             to hold that there was no discharge of the contract and
             consequently refer the dispute to arbitration. Alternatively,
             where the Chief Justice/his designate is satisfied prima c
             facie that the discharge voucher was not issued volun-
             tarily and the claimant was under some compulsion or
             coercion, and that the matter deserved detailed consid-
             eration, he may instead of deciding the issue himself, re-

 -       ~
             fer the matter to the arbitral tribunal with a specific direc-
             tion that the said question should be decided in the first
                                                                            D
             instance. [Para 27] [672-A-F]
                  1.6 In the present case, on the date when the dis-
             charge voucher was signed and given by the respondent,
             the payment of admitted amount for the claim had not been E
             made. It was made after receiving the voucher. Therefore,
             at the time of signing the voucher by the respondent and
             at the time of delivery of voucher by the respondent to
             the appellant, the contents of the voucher that the said
~    i       amount had been received, that such amount had been F
             received in full and final settlement of all claims, and that
             in consideration of such payment, the company was ab-
             solved from any further liability, are all false and not sup-
             ported by consideration. [Para 30] [675-C-E]
                   1.7 On the facts and circumstances and the settled G
             position of law, the court is prima facie of the view that
·-   ~       there is no accord and satisfaction in this case, and hence,
             the dispute is arbitrable. But it is still open to the appel-
             lant to lead evidence before the arbitrator, to establish that
                                                                            H
    642      SUPREME COURT REPORTS               [2008] 13 S.C.R.


A there is a valid and binding discharge of the contract by
  way of accord and satisfaction. It is clarified that nothing
  stated by the High Court or this Court should be construed
  as expression of any final opinion on the issue whether
  there was accord and satisfaction nor as expression of
8 any views on merits of any claim or contentions of the
  parties. [Paras 31 and 32] [675-F-G; 676-A-B]
         SBP and Co. vs. Patel Engineering Ltd. 2005 (8) SCC
    618 - held inapplicable.

c         State of Maharashtra v. Nav Bharat Builders 1994 Supp
    (3) SCC 83; Mis. P K. Ramaiah and Co. v. Chairman and
    Managing Director, National Thermal Power Corpn. 1994
    Supp (3) SCC 126; Nathani Steels Ltd. v. Associated Con-
    structions 1995 Supp (3) SCC 324 - distinguished.
D        Damodar Valley Corporation v. K. K.Kar 1974 (1) SCC
                                                                    )'
                                                                              -
  141; Mis. Bharat Heavy Electricals Ltd., Ranipur v. Mis. Amar
  Nath Bhan Prakash 1982 (1) SCC 625; Union of India vs. L.
  K. Ahuja and Co. 1988 (3) SCC 76; Jayesh Engineering Works
  v. New India Assurance Co. Ltd. 2000 (10) SCC 178; Chair-
E man and Managing Director, NTPC Ltd. v. Reshmi Construe-
  tions, Builders and Contractors 2004 (2) SCC 663; Ambica
  Construction v. Union of India 2006 (13) SCC 475; Union of
  India v. Kishorilal Gupta and Bros. 1960 (1) SCR 493; Payana
  Reena Saminathan vs. Pana Lana Palaniappa 41 IA 142;
F United India Insurance Co. Ltd. vs. Ajmer Singh Cotton and
                                                                         ~    -
  General Mills 1999 (6) SCC 400; National Insurance Co. Ltd.
  'IS. Nipha Exports (P) Ltd. 2006 (8) SCC 156; National Insur-
  ance Co. Ltd., vs. Sehtia Shoes 2008 (5) sec 400; Central
  Inland Water Transport Corporation Ltd. vs. Brojo Nath
  Ganguly 1986 (3) SCC 156; Indian Drugs and Pharmaceuti-
G
  cal.s Ltd. vs. lndo Swiss Synthetic Can Manufacturing Ltd. 1996
  (1) sec 54 - referred to.                                              ..
       2. Obtaining of undated receipts-in-advance in regiud
  to regular/routine payments by government departments
H and corporate sector is an accepted practice which has
               NATIONAL INSURANCE 00. LTD. v. M/S. BOGHARA 643
                            POLYFAB PVT. LTD.

          come to stay due to administrative exigencies and ac- · A
          counting necessities. The routine insistence by some
          Government Departments, statutory Corporations and
          Government Companies for issue of undated 'no due
          certificates' or a 'full and final settlements vouchers' ac-
          knowledging receipt of a sum which is smaller than the 8
          claim in full and final settlement of all claims, as a condi-
          tion precedent for releasing even the admitted dues, is
          unfair, irregular and illegal and requires to be deprecated.
          [Para 26) (671 C-D; 671 F-H]
                              Case Law Reference                     c
              1960 (1) SCR 493         Referred to.       Para 13
              1996 (1) sec 54          Referred to.       Para 14
              2005 (8) sec 618         Held inapplicable. Para 15
,   ..,                                                              D
              41 IA 142                Referred to.       Para 20
              1994 Supp (3) sqc 83     Distinguished.     Para 22
              1994 Supp (3) SCC 126 Distinguished.        Para 22
              1995 Supp (3) SCC 324 Distinguished.        Para 22
                                                                     E
              1974 (1) sec 141         Referred to.       Para 23
              19s2 (1 J sec 625        Referred to.       Para 23
              1988 (3) sec 76          Referred to.       Para 23
?)            2000 (10) sec 178        Referred to.       Para 23    F
              2004 (2) sec 663         Referred to.       Para 23
              2006 (13) sec 475        Referred to.       Para 23
              1999 (6) sec 400         Referred to.       Para 25
              2006 (8) sec 156         Referred to.       Para 25    G
              2008 (5) sec 400         Referred to.       Para 25
    ~
              1986 (3) sec 156         Referred to.       Para 25
               CIVILAPPELLATE JURISDCTION: Civil Appeal No. 5733
          of 2008                                                H
    644        SUPREME COURT REPORn                    (2008] 13 S.C.R.


A        From the Judgment and Order date :l 19.4.2007 of the High
    Court of Judicature at Bombay in A.A.~ :>. 182/2006
         Parag P. TripathiASG, Vishnu Meh a, Sakshi Mittal, Varun
    Sarin and Pramod Dayal for the Appell< nt.

B         T.R. Andhyarujina, Atul Chitale, SL chitra Atul Chitale and
    Sunina Dutta for the Resµondent.
          The Judgment of the Court was de livered by
         R.V.RAVEENDRAN, J. 1. Leave granted. Heard both
c   counsel. The question involved in this a 1peal is whether a dis-
    pute raised by an insured, after giving a ull and final discharge
    voucher to the insurer, can be referred ti: arbitration.
          The brief facts :
        2. The res:')ondent (Insured) obtain !d a standard Fire and         ,.,.
D                                                                                     '
  Special Perils (with a floater) Policy from I !1e appellant ('Insurer')
  to cover its goods in its godowns situat1 d at Surat for the pe-
  riod 4.8.2003 to 3.8.2004. The sum in rnred was Rs. Three
  crores, subsequently increased to Rs. Si:: crores. On 27.5.2004
  the respondent requested the insurer tc increase the sum in-
E
  sured by another Rs. six crores for a per :id of two months. Ac-
  cordingly, the appellant issued an addit onal endorsement in-
  creasing the sum insured by another Rt pees six crores, in all
  Rupees twelve crores. The respondent alleges that the addi-
  tional endorsement cover issued by the appellant was for 69                  .._,   ~


F days, that is from 27.5.2004 to 3.8.2004. The appellant alleges
  that the additional endorsement cover~ ,as for a period of 60
  days from 27.5.2004 to 26.7.2004. (Nota The appellant claims
  that during subsequent investigations, i came to light that its
  AAO (Dilip Godbole) had delivered to th'! respondent, a com-
G puter generated Additional Endorsement i unauthorisedly altered
  by hand) showing the period of addition< cover as 69 days up
  to 3.8.2004. and departmental proceedin is have been initiated               ~
  against the said officer).
          3. On 5.8.2004, the respondent re~ orted loss/damage to
H
-f          NATIONAL INSURANCE CO. LTD. v MIS. BOGHARA             645
              POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

      their stocks on account of heavy rains and flooding which took A
      place on 2/3.8.2004 and made a claim in that behalf. The sur-
      veyor submitted a preliminary report dated 14.8.2004 followed
      by a final survey report dated 6.12.2004 according to which the
.._   net assessed loss (payable to respondent) was Rs.3, 18,26,025/
      -. The said sum was arrived at on the basis that the sum insured    s
      was Rs.12 crores, the actual value of stocks in the godowns at
      risk was Rs.8,15,99,149/-, value of damaged goods was
      Rs.5,22,81,001/-, and the recoverable salvage value was
      Rs.1,87,79,922/-. The appellant informed the surveyor by letter
      dated 1.3.2005 that there was an error in the net assessed loss     c
      arrived at by the surveyor as it assumed the sum insured as
      Rs.12 crores up to 3.8.2004 whereas the sum insured was only
      Rs.6 crores after 26.7.2004 till 3.8.2004, and therefore in-
      structed the surveyor to prepare the final report regarding net
      assessed loss by taking the sum insured as only Rupees six
                                                                       0
      crores. The surveyor therefore gave an addendum to the final
      survey report on 22.3.2005 reassessing the net loss by taking
      the sum insured as only Rupees six crores. The value of goods
      at risk, the value of damaged goods and the value of recover-
      able salvage remained unaltered. By modifying the percentage
      of insurance at 75.53%, the 'Net Assessed Loss' was re-worked E
      as Rs.2,34,01,740/-. The respondent protested against the loss
      being assessed by taking the sum insured as only Rupees six
      crores. The claim and the dispute were pending consideration
      for a considerable time.
                                                                          F
            4. The respondent alleged that the appellant forced the
      respondent to accept a lower settlement; that the appellant in-
      formed the respondent that unless and until the respondent is-
      sued an undated 'Discharge voucher-in-advance' (in the pre-
      scribed form) acknowledging receipt of Rs.2,33,94,964/- in full     G
      and final settlement, no amount would be released towards the
      claim; that in that behalf, the appellant sent the format of the
      discharge voucher to be signed by respondent on 21.3.2006;
      that on account of the non-release of the claim, it was in a dire
      financial condition and it had no alternative but to yield to the   H
      646        SUPREME COURT REPOF TS                     [2008] 13 S.C.R


 A    coercion and pressure applied by thi · appellant; that therefore
      the respondent signed and gave thE said discharge voucher,
      undated, as required by the insurer du1 ng the last week of March,
      2006. The payment was released b ,' the appellant only after
      receiving the said discharge-vouche . It is extracted below:
 B                  "NATIONAL INSURANC:: COMPANY LTD.
                   REGO. OFFICE: 3, MIDJLETON STREET,
                     POST BOX N0.9229, ::OLKATA 700071
                                                       FORM ACL - 10(1)
 c                                        Loss voucher Non Motor & PA
            Received from National lnsuranc ':Company Limited through
            its policy issuing office (herein af :r called the Company) the
            sum of Rs.2,33,94,964.00 (Rupe =s two crore thirty three lakh
. D         ninety four thousand nine hundn 'd sixty four only) in full and
            final settlement of all my/our clair ·1s in respect of the property
            lost or damaged due to others or or about 03/08/2004 under
            Policy No.250501/11/03/310000( 145.
            In consideration of such payme 11t I/we hereby absolve the
 E          Company from all liability preser 1: or future arising directly or
            indirectly out of the said loss or d 1mage under the said policy.
            Further I/We hereby assign to tt : company my/our rights to
            the affected property stolen whi :h shall in the event of their
            recovery be the property of the :ompany. I/We even agree
            that the sum insured under the i aid policy stand reduced by
 F          the amount paid under the next ·enewal."
                                                                          Sd/-
        5. Simultaneously, the respo 1dent lodged a complaint
   dated 24.3.2006 with the lnsuranci: Regulatory and Develop-
 G mentAuthority wherein, after settin~ out the facts, it alleged:
            "We lodged a claim with our insu :rs immediately and pursued
            the matter with them. Even after ·:he Surveyor Mr. Mehernosh
            Todiwala of M/s. Bhatawadekar I : Co. had submitted his report
            on 22nct March, 2005, the insure 1·s refused to settle our claim
 H          on various counts. We had varic .is meetings at the Divisional,
                  NATIONAL INSURANCE CO. LTD. v. M/S. BOGHARA 647
    -+              POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

                  Regional and even the Head Office of the insurers, but to no         A
                  avail.
                  In March, 2005, the insurer company forced us to accept a
                  lower settlement and we were told that we would have to
                  agree to a lower settlement to ensure expeditious settlement
                  of the claim. Accordingly on and around the 15th of March,           B
                  2005 nearly 8 months after the loss we gave our forced consent
                  to the lower settlement offered in the hope that the claim
                  amount would be received immediately.
                  Thereafter for the next 1 year, the insurers failed to settle our
                  claim and made us run from pillar to post for the settlement.        c
                  Finally on March 21st 2006 the insurers have sent us a voucher
                  for the sum of Rs.2,33,94,94 which considering our dire
                  financial condition, and the continuous failed promises from
                  the insurers, we have had no choice but to accept.
                                                                                       D
                  Sir, subsequent to the loss, since we could not pay our
                  international suppliers on time they almost completely stopped
                  all our shipments. This has resulted in tremendous financial
                  loss to us. We have lost our long hard earned reputation in
                  the market by becoming defaulters. The insurers have
                  deliberately starved our unit of funds to ruin us financially.       E

                  You will appreciate that we are how faced with a situation
                  where we have no choice but to accept the payment being
                  released to us unconditionally as the insurers have made it
~    ~            very clear that the payment will not be released if there is any
                  conditional discharge of the vouchers. In order to safeguard         F
                  our right to claim the difference amount and any other claims
                  arising out of the financial losses incurred by us a direct result
                  of the deliberate delay in settlement of our claim by the
                  insurers, we make a humble request to the l.R.D.A. to take up
                  the matter with the insurers to ensure that justice prevails and     G
                  we are ~id the entire compensation due to us."
         •          6. The respondent also issued a !egal notice dated
             27.5.2006 wherein it was alleged that the amount due by the
             insurer was Rs.3, 18,26,025/-, and that under duress and im-
             plicit coercion, it had accepted the payment of Rs.2,33,94.!;164/         H
    648        SUPREME COURT REPORTE                   [2008] 13 S.C.R.


A -, by signing and handing over a 'full and f nal discharge voucher'.
  By the said notice, the respondent demanded the difference
  amount with interest at the rate of ·12% per annum from
  6.12.2004 (date of final survey report) till the date of payment.
  The respondent also informed the appellant that if payment was
B not so made within 15 days, the notic~ should be treated as
  notice invoking arbitration. The appellant by its reply dated
  2.8.2006, rejected the said demand. Tl1e appellant contended
  that the respondent had unconditionally cccepted the claim settle-
  mentamount fully and finally; that respo 1dent had not registered
c any protest while accepting the claim cheque; that the amount
  payable was arrived at amicably after cliscussing all aspects of
  the claim with the insured and at no juncture any protest was
  expressed; and that therefore the que~.tion of invoking the pro-
  vision for arbitration did not arise.
D       7. In view of appellant's refusal to agree for arbitr:ation, the   ..,.
  respondent filed an application under :;ection 11 of the Arbitra-
  tion & Conciliation Act, 1996 ('Act' for s 1ort) in the Bombay High
  Court. The said petition was resisted ty the appellant by reiter-
  ating that the respondent had accepted the payment of
E Rs.233,94,964/- in full and final settlement and therefore, the
  respondent could not invoke the arbitration clause.
        8. The learned Chief Justice of the Bombay High Court
  exercising power under section 11 of the Act, allowed the peti-
  tion by order dated 19.4.2007. Afte; 1:onsidering the fa:::ts, he
F was of the view that there was a serious dispute between the              >- '
  parties as to whether 'discharge voucher' was given voluntarily
  or under pressure or coercion, and tllat required to be settled
  by the Arbitral Tribunal. He therefo;e appointed Sri Justice
  S.N.Variava as the sole arbitrator. The learned Chief Justice
G left open the question whether there was any coercion/undue
  influence in regard to issue of full and final settlement discharge
  voucher by the respondent, and permitted the parties to lead
  evidence before the arbitrator on that question. The said order          '
  is challenged by the insurer in this appeal by special leave.
H
-t         NAllONAL INSURANCE CO. LTD. v. M/S. BOGHARA 649
             POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

          The rival contentions :                                         A
           9. Learned counsel for the appellant contended that once
     the insurance claim was settled and the insured received pay-
     ment and issued a full and final discharge voucher, there was
     discharge of the contract by accord and satisfaction. As a re-
     sult, neither the contract nor any claim survived. It is submitted   B
     that when a discharge voucher was issued by the respondent,
     acknowledging receipt of the amount paid by the appellant, in
     full and final settlement and confirming that there are no pend-
     ing claims against the appellant, such discharge voucher should
     be accepted on its face value as a discharge of contract by full     C
     and final settlement. Consequently, it should entail ipso jure,
     rejection in limine of any subsequent claim or any request for
     reference of any dispute regarding any claim to arbitration. It
     was also contended that having received the payment under
     the said discharge voucher, the respondent cannot, while re-         D
     taining and enjoying the benefit of the full and final payment,
     challenge the validity or correctness of the discharge voucher.
     The appellant contends that the subsequent claim of the respon-
     dent ought not to have been referred to arbitration. In support of
     its contentions, reliance was placed on three decisions of this      E
     Court in State of Maharashtra v. Nav Bharat Builders [1994
     Supp (3) SCC 83], M/s. P K. Ramaiah & Co. v. Chairman &
     Managing Director, National Thermal Power Corpn. [1994
     Supp (3) SCC 126] and Nathani Steels Ltd. v. Associated Con-
     structions [1995 Supp (3) SCC 324].                                  F
            10. On the other hand the respondent contended that the
     scope of proceeding under section 11 of the Act was limited. It
     is submitted that once the petitioner establishes that the con-
     tract between the parties contains an arbitration agreement, and ·
     that the dispute raised is in respect of a claim arising out of G
     such contract, the dispute has to be referred to arbitration; that
     any contention by the appellant that there is discharge of the
     contract by issue of full and final discharge voucher is a matter
     for the arbitral tribunal to examine and decide, and cannot be
     held out as a threshold bar to arbitration; and that the question H
    650       SUPREME COURT REPORTS                  [2008] 13 S.C.R.


A whether there was accord and satis ..action, or whether there
  was discharge of a contract by perforrnance, is itself a question
  that is clearly arbitrable. It is alternatively submitted that when
  the Chief Justice or his designate is required to consider whether
  the claimant has issued a full and fi ial discharge voucher in
B settlement of all claims, any objection to the validity of such dis-
  charge voucher should also be consic ered. It is pointed out that
  where the discharge voucher is given under threat or coercion,
  resulting in economic duress and compulsion, such discharge
  voucher is not valid nor binding on the claimant, and the dispute
C relating to the claim survives for consideration and is arbitrable.
  According to respondent, where the person on whom the claim
  is made, withholds the admitted amount to coerce and compel
  the claimant to accept a smaller payment in full and final settle-
  ment and give a discharge voucher, t1ere is no accord and sat-
  isfaction in the eye of law; and the c ischarge voucher will not
D come in the way of a genuine and bona fide dispute being raised
  regarding the balance of the claim and seeking reference of
  such claim to arbitration. In support of the said contentions, re-
  liance was placed on the decisions of this Court in Damodar
  Valley Corporation v. K. K.Kar [1974 (1) SCC 141], M/s. Bharat
E Heavy Electricfils Ltd., Ranipur ~·. Mis. Amar Nath Bhan
  Prakash [1982 (1) SCC 625], Union oflndia vs. L. K. Ahuja &
  Co. [1988 (3) SCC 76], Jayesh Eng'neering Works v. New In-
  dia Assurance Co. Ltd. [2000 (10) SCC 178], Chairman & Man-
  aging Director, NTPC Ltd. v. Reshr1i Constructions, Builders
F & Contractors [2004 (2) SCC 663], and Ambica Construction              ~   •
  v. Union of India [2006 (13) SCC 4~'5].
         11. In reply, the learned counsel for the appellant submit-
  ted that the decisions relied on by the respondent were all ren-
  dered by two-Judge Benches of thii; Court, whereas the deci-
G sion in Nathani Steels relied on by the appellant, was rendered
  'uy a three-Judge Bench; and therefore the principle laid down
  in Nathani Steels that there can be no reference to arbitration
  wherever there is a full and final sett ement, resulting in the dis-
  charge of the contract, holds the field and will have to be fol-
H lowed in preference to the other decisions.
                    NATIONAL INSURANCE CO. LTD. v. M/S. BOGHARA              651
                      POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

                   The questions for consideration :                                 A
                    12. In this case existence of an arbitration clause in the
              contract of insurance is not in dispute. It provides that "if any
..
~
              dispute or difference shall arise as to the quantum to be paid
          •   under this. policy (liability being otherwise admitted) such differ-
              ence shall, independently to all other questions be referred to        B
              the decision of a sole Arbitrator." The rival contentions give rise
              to the following question for our consideration :
                   In what circumstances, a court will refuse to refer a dispute
                   relating to quantum to arbitration, when the contract             c
                   specifically provides for reference of disputes and
                   differences relating to the quantum to arbitration? In
                   particular, what is the position when a respondent in an
                   application under section 11 of the Act, resists reference
                   to arbitration on the ground that petitioner has issued a full
          ¥                                                                          D
                   and final settlement discharge voucher and the petitioner
                   contends that he was constrained to issue it due to
                   coercion, undue influence and economic compulsion?
                    13. In Union of India v. Kishorilal Gupta & Bros. [1960 (1)
              SCR 493), this Court considered the question whether the arbi-         E
              tration clause in the contract will cease to have effect, when the
              contract stood discharged as a result of settlement. While an-
              swering the question in the affirmative, a three Judge Bench of
              this Court culled out the following general principles as to when
    - -c
    '         arbitration agreements operate and when they do not operate:           F
                   (i)    An arbitration clause is a collateral term of a contract
                          distinguished from its substantive terms; but none
                          the less it is an integral part of it.
                   (ii)   Howsoever comprehensive the terms of an arbitration
                                                                                     G
                          clause may be, the existence of the contract is a
                          necessary condition for its operation; and the
        ...               arbitration clause perishes with the contract.
                   (iii) A contract may be non est in the sense that it never
                         came legally into existence or it was void ab initio.       H
    652          SUPREME COURT REPORTS                  [2008] 13 S.C.R.


A                In that event, as the original contract has no legal
                 existence, the arbitration clause also cannot operate,
                 for along with the original contract, it is also void.
          (iv)   Though the contract was validly executed, the parties             •·
B
                 may put an end to it as if it had never existed and
                 substitute a new contract for it, solely governing their
                                                                             •
                 rights and liabilities. In such an event, as the original
                 contract is extinguished by the substituted one, the
                 arbitration clause of the original contract perishes
                 with it.
c         (v)    Between the two extremes referred to in paras (c)
                 and (d), are the cases where the contract may come
                 to an end, on account of repudiation, frustration,
                 breach etc. In these cases, it is the performance of
                 the contract that has come to an end, but the contract
D                                                                            v
                 is still in existence for certain limited purposes, in
                 respect of disputes arising under it or in connection
                 with it. When the contracts subsist for certain
                 purposes, the arbitration clauses in those contracts
                 operate in respect of those purposes.
E
        The principle stated in para (i) is now given statutory rec-
  ognition in section 16(1 )(a) of the Act. The principle in para (iii)
  has to be now read subject to section 16( 1)(b) of the Act. The
  principles in paras (iv) and (v) are clear and continue to be ap-
F plicable. The principle stated in para (ii) requires further eluci-        )>-   ~

  dation with reference to contracts discharged by performance
  or accord and satisfaction.
        14. The decision in Kishori/al Gupta was followed and re-
  iterated in several decisions including Naithani Jute Mills Ltd.
G vs. Khya/iram Jagannath (AIR 1968 SC 522), Oamodar Val-
  fey Corporation vs. K. K. Kar [1974 (1) SCC 141] and Indian
  Drugs & Pharmaceuticals Ltd. vs. Inda Swiss Synthetic Gem                  r
  Manufacturing Co. Ltd. (1996 (1) SCC 54). In Oamodar Valley
  Co1poration, this Court observed :
H
                           NATIONAL INSURANCE CO. LTD. v. IVl/S. BOGHARA                653
           -1                POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

                          "A contract is the creature of an agreement between the parties A
                          and where the parties under the terms of the contract agree
                          to incorporate an arbitration clause, that clause stands apart
                          from the rights and obligations under that contract, as it has
                          been incorporated with the object of providing a machinery for
               )-         the settlement of disputes arising in relation to or in connection
                                                                                                B
                          with that contract. The questions of unilateral repudiation of
                          the rights and obligations under the contract or of a full and
                          final settlement of the contract relate to the performance or
                          discharge of the contract. Far from putting an end to the
                          arbitration clause, they fall within the purview of it. A repudiation
                          by one party alone does not terminate the contract. It takes .C
                          two to end it, and hence it follows that as the contract subsists
                          for the determination of the rights and obligations of the parties,
                          the arbitration clause also survives. This is not a case where
                          the plea is that the contract is void, illegal or fraudulent etc.,
                          in which case, the entire contract along with the arbitration
               "!'                                                                              D
                          clause is non est, or voidable. As the contract is an outcome
                          of the agreement between the parties it is equally open to the
                          parties thereto to agree to bring it to an end or to treat it us if
                          it never existed. It may also be open to the parties to terminate
                          the previous contract and substitute in its place a new contract
                          or alter the original contract in such a way that it cannot E
                          subsist. In all these cases, since the entire contract is put an
                          end to the arbitration clause, which is a part of it, also perishes
                          along with it."

                           15. Section 16 of the Act bestows upon the arbitral tribu-
    ,#   ...

                     nal, the competence to rule on its own jurisdiction. Sub-section          F
                     (1) of the section reads thus :
4
    .                     "16. Competence of arbitral tribunal to rule on its
                          jurisdiction. - (1) The arbitral tribunal may rule on its own
                          jurisdiction, including ruling on any objections with respect
                                                                                              G
                          to the existence or validity of the arbitration agreement,
                          and for that purpose, -
'        ...
                          (a)   an arbitration clause which forms part of a contract
                                shall be treated as an agreement independent of the
                                other terms of the contract; and                               H
    654         SUPREME COURT REPORTS                    [2008] 13 S.C.R


A         (b)   a decision by the arbitral tribunal that the contract is
                null and void shall not entail ipso Jure the invalidity of
                the arbitration clause.

           In SBP & Co. vs. Patel Engineering Ltd. - 2005 (8) SCC
    618, a seven Judge Bench of this Court considered the scope
B   of section 11 of the Act and held that the scheme of section 11
    of the Act required the Chief Justice or his designate to decide
    whether there is an arbitration agreement in terms of Section 7
    of the Act before exercising his power under Section 11 (6) of
    the Act and its implications. It was of the view that sub-sections
C   (4), (5) and (6) of section 11 of the new Act, combined the power
    vested in the court under sections 8 and 20 of the old Act (Arbi-
    tration Act, 1940). This Court held :

          "It is necessary to define what exactly the Chief Justice,
          approached with an application under Section 11 of the Act,
D         is to decide at that stage. Obviously, he has to decide his own
          jurisdiction in the sense, whether the party making the motion
          has approached the right High Court. He has to decide whether
          there is an arbitration agreement, as defined in the Act and
          whether the person who has made the request before him, is
E         a party to such an agreement. It is necessary to indicate that
          he can also decide the question whether the claim was a dead
          one; or a long barred claim that was sought to be resurrected
          and whether the parties have concluded the transaction by
          recording satisfaction of their mutual rights and obligations or
          by receiving the final payment without objection. It may not be
F         possible at that stage, to decide whether a live claim made,
          is one which comes within the purview of the arbitration clause.
          It will be appropriate to leave that question to be decided by
          the arbitral tribunal on taking evidence, along with the merits
          of the claims involved in the arbitration. The Chief Justice has
G         to decide whether the applicant has satisfied the conditions
          for appointing an arbitrator under Section 11 (6) of the Act. For
          the purpose of taking a decision on these aspects, the Chief
          Justice can either proceed on the basis of affidavits and the
          cfocuments produced or take such evidence or get such
          evidence recorded, as may be necessary. We think that
H
              NATIONAL INSURANCE CO. LTD. v. M/S. BOGHARA .655
   ~            POLYFAB PVT LTD. [RVRAVEENDRAN, J]

             adoption of this procedure in the context of the Act would best       A
             serve the purpose sought to be achieved by the Act of
             expediting the process of arbitration, without too many
             approaches to the court at various stages of the proceedings
             before the Arbitral tribunal."
             "47.(iv) The Chief Justice or the designated judge will have          B
             the right to decide the preliminary aspects as indicated in the
             earlier part of this judgment. These will be, his own jurisdiction,
             to entertain the request, the existence of a valid arbitration
             agreement, the existence or otherwise of a live ciaim, .the
             existence of the condition for the exercise of his power and
             on the qualifications of the arbitrator or arbitrators."
                                                                                   c
                                                : Ii
                                                       {emphasis supplied)
              This Court also examined the 'competence' of the arbitral
        tribunal to rule upon its own jurisdiction and about the existence
                                                                                   D
        of the arbitration clause, when the Chief Justice or his desig-
   "'   nate had appointed the Arbitral Tribunal under section 11 of the
        Act, after deciding upon such jurisdictional issue. This Court
        held:

             "We are inclined to the view that the decision of the Chief           E
             Justice on the issue of jurisdiction and the existence of a .vaiid
             arbitration agreement would be binding on the parties when
             the matter goes to the arbitral tribunal".
             "Section 16 is said to be the recognition of the principle of
, -1         Kompetenz - Kompetenz. The fact that the arbitral tribunal F
             has the competence to rule on its own jurisdiction and to
             define the contours of its jurisdiction, only means that when
             such issues arise before it, the Tribunal can and possibly,
             ought to decide them. This can happen when the parties have
             gone to the arbitral tribunal without recourse to Section 8 or
             11 of the Act. But where the jurisdictional issues are decided G
             under these Sections, before a reference is made, Section
             16 cannot be held to empower the arbitral tribunal to ignore
             the decision given by the judicial authority or the Chief Justice
             before the reference to it was made. The competence to
             decide does not enable the arbitral tribunal to get over the H
•



        656        SUPREME COURT REPORTS                      [2008) 13 S.C.R.


    A         finality conferred on an order passed prior to its entering upon
              the reference by the very statute that creates it. That is the
              position arising out of Section 11 (7) of the Act read with Section
              16 thereof. The finality given to the order of the Chief Justice
              on the matters within his competence under Section 11 of the
              Act, are incapable of being reopened before the arbitral
    B         tribunal."

              16. It is thus clear that when a contract contains an arbitra-
      tion clause and any dispute in respect of the said contract is
      referred to arbitration without the intervention of the court, the
    c Arbitral Tribunal can decide the following questions affecting its
      jurisdiction: (a) whether there is an arbitration agreement; (b)
      whether the arbitration agreement is valid; (c) whether the con-
      tract in which the arbitration clause is found is null and void and
      if so whether the invalidity extends to the Arbitration clause also.
    0 It follows therefore that if the respondent before the Arbitral Tri-
      bunal contends that the contract has been discharged by rea-
      son of the claimant accepting payment made by the respon-
      dent in full and final settlement, and if the claimant counters it by
      contending that the discharge voucher was extracted from him
    E by practicing fraud, undue influence, or coercion, the arbitral
      tribunal will have to decide whether the discharge of contract
      was vitiated by any circumstance which rendered the discharge ·
      voidable at the instance of the claimant. If the arbitral tribunal
      comes to the conclusion that there was a valid discharge by
      voluntary execution of a discharge voucher, it will refuse to ex-
    F amine the claim on merits, and reject the claim as not maintain-
      able. On the other hand, ifthe arbitral tribunal comes to the con-
      clusion that such discharge of contract was vitiated by any cir-
      cumstance which rendered it void, it will ignore th.e same and
      proceed to decide the claim on merits.
    G
            17. Where the intervention of the court is sought for ap-
      pointment of an Arbitral Tribunal under section 11, the duty of
      the Chief Justice or his designate is defined in SBP & Co. This
      Court identified and segregated the preliminary issues that may
    H arise for consideration in an application under section 11 of the
      NATIONAL INSURANCE CO. LTD. v. MIS. BOGHARA               657
        POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

Act into three categories, that is (i) issues which the Chief Jus-     A
tice or his Designate is bound to decide; (ii) issues which he
can also decide, that is issues which he may choose to decide;
and (iii) issues which should be left to the Arbitral Tribunal to
decide.
     17 .1) The issues (first category) which Chief Justice/his        8
     designate will have to decide are:
     (a)     Whether the party making the application has
             approached the appropriate High Court.
     (b)     Whether there is an arbitration agreement and             C
             whether the party who has applied under section 11
             of the Act, is a party to such an agreement.
     17.2) The issues (second category) which the Chief
     Justice/his designate may choose to decide (or leave
                                                          0
     them to the decision of the arbitral tribunal) are:
     (a)     Whether the claim is a dead (long barred} claim or
             a live claim.
     (b)     Wheth_er the parties have concluded the contract/
             transaction by recording satisfaction of their mutual     E
             rights and obligation or by receiving the final payment
             without objection.
     17.3) The issues (third category) which the Chief Justice/
     his designate should leave exclusively to the arbitral tribunal   F
     are:
     (i}      Whether a claim made falls within the arbitration
              clause (as for example, a matter which is reserved
            · for final decision of a departmental authority and·
              excepted or excluded from arbitration).             G
     (ii)    Merits or any claim involved in the arbitration.
     It is clear from the scheme of the Act as explained by this
Court in SBP & Co., that in regard to issues falling under the
second category, if raised in any application under section 11         H
    658       SUPREME COURT REPORTS                  [2008] 13 S.C.R.


A   of the Act, the Chief Justice/his designate may decide them, if
    necessary by taking evidence. Alternatively, he may leave those
    issues open with a direction to the Arbitral Tribunal to decide
    the same. If the Chief Justice or his Designate chooses to ex-
    amine the issue and decides it, the Arbitral Tribunal cannot re-
8   examine the same issue. The Chief Justice/his designate will,
    in choosing whether he will decide such issue or leave it to the
    Arbitral Tribunal, be guided by the object of the Act (that is ex-
    pediting the arbitration process with minimum judicial interven-
    tion). Where allegations of forgery/fabrication are made in re-
c   gard to the document recording discharge of contract by full
    and final settlement, it would be appropriate if the Chief Jus-
    tice/his designate decides the issue.

        18. What is however clear is when a respondent contends
  that the dispute is not arbitrable on account of discharge of the
D contract under a settlement agreement or discharge voucher or
  no-claim certificate, and the claimant contends that it was ob-
  tained by fraud, coercion or under influence, the issue will have
  to be decided either by the Chief Justice/his designate in the
  proceedings under section 11 of the Act or by the arbitral Tribu-
E nal as directed by the order under section 11 of the Act. A claim
  for arbitration cannot be rejected merely or solely on the ground
  that a settlement agreement or discharge voucher had been
  executed by the claimant, if its validity is disputed by the claim-
  ant.
F       19. We may next examine some related and incidental
  issues. Firstly, we may refer to the consequences of discharge
  of a contract. When a contract has been fully performed, there
  is a discharge of the contract by performance, and the contract
  comes to an end. In regard to such a discharged contract, noth-
G ing remains - neither any right to seek performance nor any
  obligation to perform. In short, tllere cannot be any dispute.
  Consequently, there cannot obviously be reference to arbitra-
  tion of any dispute arising from a discharged contract Whet~:er
  the contract has been discharged by performance or not is a
H mixed question of fact and law, and if there is a dispute in re-
      NATIONAL INSURANCE CO. LTD. v. MIS. BOGHARA             659
        POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

gard to that question, that is arbitrable. But there is an excep-    A
tion. Where both parties to a contract confirm in writing that the
contract has been fully and finally discharged by performance
of all obligations and there are no outstanding claims or dis-
putes, courts will not refer any subsequent claim or dispute to
arbitration. Similarly, where one of the parties to the contract     B
issues a full and final discharge voucher (or no due certificate
as the case may be) confirming that he has received the pay-
ment in full and final satisfaction of all claims, and he has no
outstanding claim, that amounts to discharge of the contract by
acceptance of performance and the party issuing the discharge        c
voucher/certificate cannot thereafter make any fresh claim or
revive any settled claim. Nor can he seek reference to arbitra-
tion in respect of any claim. When we refer to a discharge of
contract by an agreement signed by both parties or by execu-
tion of a full and final discharge voucher/receipt by one of the
                                                                     0
parties, we refer to an agreement or discharge voucher which
is validly and voluntarily executed. If the party who has executed
the discharge agreement or discharge voucher, alleges that the
execution of such discharge agreement or voucher was on ac-
count of fraud/coercion/undue influence practiced by the other
party and is able to establish the same, then obviously the dis-     E
charge of the contract by such agreement/voucher is rendered
void and cannot be acted upon. Consequently, any dispute raised
by such party would be arbitrable.
     20. While discharge of contract by performance refers to        F
fulfillment of the contract by performance of all the obligations in
terms of the original contract, discharge by 'accord and satis-
faction' refers to the contract being discharged by reason of
performance of certain substituted obligations. The agreement
by which the original obligation is discharged is the accord, and G
the discharge of the substituted obligation is the satisfaction. A
contract can be discharged by the same process which cre-
ated it, that is by mutual agreement. A contract may be dis-
charged by the parties to the original contract either by entering
into a new contract in substitution of the original contract; or by H
    660         SUPREME COURT REPORTS                   [20C8j 13 S.C.R.


A   acceptance of performance of modified obligations in lieu of
    the obligations stipulated in the contract. The classic definition
    of the term 'accord and satisfaction' given by the Privy Council
    in Payana Reena Saminathan vs. Pana Lana Palaniappa -
    41 IA 142 (reiterated in Kishorilal Gupta) is as under:
B         "The 'receipt' given by the appellants and accepted by the
          respondent, and acted on by both parties proves conclusively
          that all the parties agreed to a settlement of all their existing
          disputes by the arrangement formulated in the 'receipt'. It is
          a clear example of what used to be well known as common
c         law pleading as 'accord and satisfaction by a substituted
          agreement'. No matter what were the respective rights of the
          parties inter se they are abandoned in consideration of the
          acceptance by all of a new agreement. The consequence is
          that when such an accord and satisfaction takes place the
          prior rights of the parties are extinguished. They have in fact     y
D         been exchanged for the new rights; and the new agreement
          becomes a new departure, and the rights of all the parties are
          ful!y represented by it."

                                                  [Emphasis supplied]

E         21. It is thus clear that the arbitration agreement contained
    in a contract cannot be invoked to seek reference of any dis-
    pute to arbitration, in the following circumstances, when the con-
    tract is discharged on account of performance, or accord and
    satisfaction, or mutual agreement. and the same is reduced to
F   writing (and signed by both parties or by the party seeking arbi-
    tration) :
          (a)   Where the obligations under a contract are fully
                performed and discharge of the contract by
                performance is acknowledged by a full and final
G               discharge voucher/receipt. Nothing survives in regard
                to such discharged contract.
          (b)   VVhere the parties to the contract, by mutual
                agreement, accept performance of altered, modified
                and substituted obligations and confirm in writing
H
          NATIONAL INSURANCE CO. LTD. v. M/S. BOGHARA 661
            POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

               the discharge of contract by performance of the            A
               altered, modified or substituted obligations.

         (c)   Where the parties to a contract, by mutual
               agreement, absolve each other from performance of
               their respective obligations (either on account of
               frustration or otherwise) and consequently cancel the      8
               agreement and confirm that there is no outstanding
               claims or disputes.

          22. We may next consider whether the decisions relied on
    by the appellant and the decisions relied on by the respondent        c
    express divergent views, as contended by the learned counsel
    for the appellant. We will first consider the three cases relied on
    by the appellant.
          22.1) In PK. Ramaiah, the appellant contractor made cer-
    tain claims in regard to a construction contract. The employer D
    rejected the claims, as also the request for reference to arbitra-
    tion. On an application by the contractor, under the Arbitration
    Act, 1940 for appointment of an Arbitrator, the Civil Court ap-
    pointed an Arbitrator. The said order of appointment was chal-
    lenged by the employer. The High Court found that the contrac- E
    tor had unconditionally acknowledged the final measurement
    and accepted the payment in full and final settlement of the con-
    tract on 19.5.1981; that thereafter he had made a fresh claim
    on 1.6.1981 which was rejected on 12.8.1981; and that the con-
    tractor did not take action and sought reference to arbitration F
    only several years thereafter. The High Court therefore held that
    there was no subsisting contract to enable reference to arbitra-
    tion and consequently, set aside the reference to arbitration.
    On appeal by the contractor, this Court held that in view of the
    finding recorded by the High Court that the contractor had ac- G
    cepted the measurements and payment and had uncondition-
    ally acknowledged full and final settlement and satisfaction by
i
    issuing a receipt in writing, no arbitrable dispute arose for be-
    ing referred to Arbitration. This Court further held that there was
    accord and satisfaction by final settlement of the claims and the H.
    662       SUPREME COURT REPORTS                      [2008) 13 s c R.


A   subsequent allegation of coercion was an afterthought and only
    a ploy to get over the settlement of the dispute.

          22 2) In Nav Bharat Builders, a dispute arose in regard to
  labour escalation charges. As the employer did not agree for
  escalation, the contractor made an application under section
B 20 of the Arbitration Act, 1940 for filing the agreement and for
  reference of the dispute to arbitration. Pending the said appli-
  cation, the contractor made a representation to the employer
  for settlement of the claim. The government constituted a Com-
  mittee to examine the labour escalation. The said Committee
c suggested acceptance of the claim subject to certain terms.
  The contractor by his letter dated 3.3.1989 agreed to receive
  the price escalation on account of the labour component, as
  worked out by the Committee. Thereafter, the recommended
  amount was paid to the contractor, who accepted the payment
  and agreed to withdraw the application under section 20 in re-
0
  gard to the claim for labour escalation. He subsequently con-
  tended that the said letter was obtained by coercion and he
  was not bound by it. The trial court and the High Court held that
  there was an arbitrable dispute which was challenged before
  this Court. It is in this background this Court following P K.
E Ramaiah held :
          "............ the respondent contended that the appellant had
          accepted the principle on which the escalation charges are to
          be paid but in its working the amount was not calculated
          correctly and he expressly referred the same in his letter of         r .
F         acceptance and that, therefore, it is open to the respondent to
          contend before the arbitrator that in working the principle on
          wh.ich the amount offered by the Government the arbitrator has
          to decide as to what amount had been arrived at and if the
          working in principle is not acceptable any alternative principle
G         would be applicable. If the arbitrator finds that the respondent
          is entitled to any claim it is still an arbitrable dispute. We find
          no substance in the contention. Whatever be the principle or
          method or manner of working it out, a particular figure was
          arrived at by the Government. The respondent was then asked
          to consider its willingness to accept the offer and having
H
         -~         NATIONAL INSURANCE CO. LTD. v. MIS. BOGHARA 663
                      POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

                   accepted the same and received the amount, it is no longer A
                   open to the respondent to dispute the claim on any count or
                   ground. The dispute was concluded and the respondent fully
                   and finally accepted the (settlement of the) claim and thereafter
                   received the amount. Thus there is accord and satisfaction of
                   the claim relating to labour escalation charges. Thereby there
                                                                                     B
                   is no further arbitrable dispute in that behalf."
                                                            [emphasis supplied]
                   22.3) Nathani Steels related to a dispute on account of
              non-completion of the contract. The Court found that the said
              dispute was settled by and between the parties as per deed               c
              dated 20.12.1980 signed by both parties. The deed referred to
              the prior discussions between the parties and recorded the
              amicable settlement of the disputes and differences between
              the parties in the presence of the Architect on the terms and
              conditions set out in clauses 1 to 8 thereof. In view of it, the
        "'    Court rejected the contention of the contractor that the settle-
                                                                                        D
              ment was liable to be set aside on the ground of mistake. A
              three-Judge Bench of this Court, after referring to the decisions
              in P K. Ramaiah and Nav Bharat Builders, held thus :
                   ".... that once the parties have arrived at a settlement in respect
                                                                                         E
                   of any dispute or difference arising under a contract and that
                   dispute or the difference is amicable settled by way of a final
                   settlement by and between the parties, unless that settlement
                   is set aside in proper proceedings, it cannot lie in the mouth of
. -1               one of the parties to the settlement to spurn it on the ground
                   that it was a mistake and proceed to invoke the Arbitration F
                   clause. If this is permitted the sanctity of contract, the settlement
                   also being a contract, would be wholly lost and it would be open
                   to one party to take the benefit under the settlement and then
                   to question the same on the ground of mistake without having
                   the settlement set aside. In the circumstances, we think that in
                                                                                         G
                   the instant case since the dispute or difference was finally
  ..,              settled and payments were made as per the settlement, it was
                   not open to the respondent unilaterally to treat the settlement
                   as non est and proceed to invoxe the Arbitration clause."
                                                            [emphasis supplied]        H
    664       SUPREME COURT REPORTS                    [2008] 13 S.C.R


A         22.4) What requires to be noticed is that in Nav Bharat
    Builders and Nathani Steels, this court on examination of facts,
    was satisfied that there were negotiations and voluntary settle-
    ment of all pending disputes, and the contract was discharged
    by accord and satisfaction. In P K. Ramaiah, the Court was
B   satisfied that there was a voluntary acceptance of the measure-
    ments and full and final payment of the amount found due, re-
    sulting in discharge of the contract, leaving no outstanding claim
    or pending dispute. In those circumstances, this Court held that
    after such voluntary accord and satisfaction or discharge of the
c   contract, there could be no arbitrable disputes.

         23. We may next refer to the decisions relied on by the
    respondent:

         23.1) In Damodar Valley Corporation, the question that
    arose for consideration of this Court was as follows:                   y
0
          "where one of the parties refers a dispute or disputes to
          arbitration and the other party takes a plea that there was a
          final settlement of all claims, is the Court, on an application
          under Sections 9(b) and 33 of the Act, entitled to enquire into
          the truth and validity of the averment as to whether there was
E
          or was not a final settlement on the ground that if that was
          proved it would bar a reference to the arbitration inasmuch as
          the arbitration clause itself would perish."

         In that case the question arose with reference to a claim
F by the supplier. The purchaser required the supplier to furnish a
  full and final receipt But the supplier did not give such a receipt
  Even though there was no discharge voucher, the purchaser
  contended that the payments made by it were in full and final
  settlement of the bills. This Court rejected that contention and
G held that the question whether there has been a settlement of all
  the claims arising in connection with the contract also postu-
  lates the existence of the contract which would mean that the
  arbitration clause operates. This Court held that the question
  whether there has been a full and final settlement of a claim
H under the contract is itself a dispute arising 'upon' or 'in relation
'

                     NATIONAL INSURANCE CO. LTD. v. MIS. BOGHARA 665
          ~
                       POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

               to' or 'in connection with' the contract; and where there is an A
               arbitration clause in a contract, notwithstanding the plea that
               there was a full and final settlement between the parties, that
               dispute can be referred to arbitration. It was also observed that
               mere claim of accord and satisfaction may not put an end to the
          ).
               arbitration clause. It is significant that neither PK. Ramaiah nor B
               Nathani Steels disagreed with the decision in Damodar Val-
               fey Corporation but only distinguished it on the ground that there
               was no full and final discharge voucher showing accord and
               satisfaction in that case.
                     23.2) In Bharat Heavy Electricals Ltd., this Court observed c
               that the question whether there was discharge of the contract
               by accord and satisfaction or not, is a dispute arising out of the
               contract, which requires to be referred to arbitration. It was held
               that the Arbitrator shall first determine whether there was ac-
        '(     cord and, satisfaction between parties and/or whether the con- D
               tract wa$ discharged; that if the decision was in favour of the
               employer, the Arbitrator will not proceed further in the matter but
               dismiss the claim of the contractor; and that if he finds that the
               contract was not discharged by accord and satisfaction or oth-
               erwise, he should proceed to determine the claim of the con- E
               tractor on merits. In this case also, there was no acknowledg-
               ment of full and final settlement not any discharge voucher.
                   23.3) In Union of India vs. L.K. Ahuja & Co. - 1988 (3)
               SCC 76, this Court observed :
    --1                                                                                F
                    "In order to be entitled to ask for a reference under section 20
                    of the Act, there must be an entitlement to money and a
                    difference or dispute in respect of the same. It is true that.on
                    completion of the work, right to get payment would normally
                    arise and it is also true that on settlement of theJinal bill, the
                    right to get further payment gets weakened but the claim G
                    subsists and whether it does subsist, is a matter which is
    i
                    arbitrable."
                     There was no full and final discharge or accord and satis-
'              faction in that case. In Jayesh Engineering Works, These was
                                                                                      H
    666       SUPREME COURT REPORTS                      [2008] 13 S.C.R.


A an acknowledgment by the contractor that he had received the
  amount in full and final settlement and he has no further claim.
  This Court following L. K. Ahuja held that whether the contract
  has been fully worked out and whether the payments have been
  made in full and final settlement are questions to be considered
B by the arbitrator when there is a dispute regarding the validity of
  such acknowledgement and that the arbitrator will consider
  whether any amount is due to be paid and how far the claim
  made by the contractor is tenable. Jayesh Engineering Works
  did not refer to Kishorilal Gupta, Nav Bharat Builders, PK.
c Ramaiah or Nathani Steels ..
         23.4) In Reshmi Constructions, the employer prepared a
  final bill and forwarded the same along with a 'No-Demand
  Certificate' in printed format confirming that it had no claims.
  The contractor signed the no-demand certificate and submit-
D ted it. But on the same day, the contractor also wrote a letter to
  the employer stating that it had issued the said certificate in
  view of a threat that until the said document was executed, pay-
  ment of the bill will not be released. In those circumstances,
  after considering P K. Ramaiah and Nathani Steels, this Court
E held:
          "26 .... The conduct of the parties as evidenced in their letters,
          as noticed hereinbefore, clearly goes to show that not only
          the final bill submitted by the respondent was rejected but
          another final bill was prepared with a printed format that a
F         "No-Demand Certificate" has been executed as otherwise
          the final bill would not be paid. The respondent herein, as
          noticed hereinbefore, categorically stated in its letter dated
          20.12.1990 as to under what circumstances they were
          compelled to sign the said printed letter. It appears from the
          appendix appended to the judgment of the learned trial Judge
G         that the said letter was filed even before the trial court. It is,
          therefore, not a case whether the respondent's assertion of
          "under influence or coercion" can be said to have been taken
          by way of an afterthought.

          27. Even when rights and obligations of the parties are worked
H
      NATIONAL INSURANCE CO. LTD. v. MIS. BOGHARA 667
        POLYFAB PVT. LTD. [RVRAVEENDRAN, J.]

     out, the contract does not come to an end inter alia for the     A
     purpose of determination of the disputes arising thereunder,
     and, thus, the arbitration agreement can be invoked. Although
     it may not be strictly in place but we cannot shut our eyes to
     the ground reality that in a case where a contractor has made
     huge investments, he cannot afford not to take from the
                                                                      B
     employer the amount under the bills, for.various reasons which
     may include discharge of his liability towards the banks,
     financial institutions and other persons. In such a situation,
     the public sector undertakings would have an upper hand.
     They would not ordinarily release the money unless a "No-
     Demand Certificate" is signed. Each case, therefore, is          C
     required to be considered on its own facts.
     28. Further, necessitas non habet legem is an age-old maxim
     which means necessity knows no law. A person may
     sometimes have to succumb to the pressure of the other
     party to the bargain who is in a stronger position.              D
     29. We may, however, hasten to add that such a case has to
     be made out and proved before the arbitrator for obtaining an
     award."

       This decision dealt with a case where there was some jus-      E
tification for the contention of the contractor that the 'No-demand
Certificate' was not given voluntarily butunder coercion, and on
facts, this Court felt that the question required to be examined.

      23.5) In Ambica Constructions (supra) this Court consid-
ered a clause in the contract which required the contractor to F
give a no claim certificate in the form required by Railways after
the final measurement is taken and provided that the contractor
shall be debarred from disputing the correctness of the_items
covered by 'No claim certificate' or demanding a reference to
arbitration in respect thereof. There was some material to show G
that the certificate was given under coercion and duress. This
Court following Reshmi Constructions, observed that such a
clause in contract would not be an absolute bar to a contractor
raising claims which were genuine, even after submission of a
no-claim certificate.                                              H
    668       SUPREME COURT REPORTS                   [2008] 13 S.C.R.


A          24. We thus find that the cases referred fall under two cat-
    egories. The cases relied on by the appellant are of one cat-
    egorywhere the court after considering the facts, found that there
    was a full and final settlement resulting in accord and satisfac-
    tion, and there was no substance in the allegations of coercion/
    undue influence. Consequently, this Court held that there could
8
    be no reference of any dispute to arbitration. The decisions in
    Nav Bharat and Nathani Steels are cases falling under this
    category where there were bilateral negotiated settlements of
    pending disputes, such settlements having been reduced to
    writing either in the presence of witnesses or otherwise. PK.
C   Ramaiah is a case where the contract was performed and there
    was a full and final settlement and satisfaction resulting in dis-
    charge of the contract. It also falls under this catego1y. The cases
    relied on by the respondent fall under a different category where
    the court found some substance in the contention of the claim-
0   ants that 'no due/claim certificates', or 'full and final settlement
    Discharge Vouchers' were insisted and taken (either in a printed
    format or otherwise) as a condition precedent for release of the
    admitted dues. Alternatively, they were cases where full and fi-
    nal discharge was alleged, but there were no documents con-
E   firming such discharge. Consequently, this Court held that the
    disputes were arbitrable. None of the three cases relied on by
    the appellant lay down a proposition that mere execution of a
    full and final settlement receipt or a discharge voucher is a bar
    to arbitration, even when the validity thereof is challenged by
     the claimant on the ground of fraud, coercion or undue influ-
F   ence. Nor do they lay down a proposition that even if the dis-         t   ·
     charge of contract is not genuine or legal, the claims cannot be
     referred to arbitration. In all the three cases, the court examined
     the facts and satisfied itse!f that there was accord and satisfac-
     tion or ·complete discharge of the contract and that there was
G    no evidence to support the allegation of coercion/undue influ-
     ence. It is true that in Nathani Steels, there is an observation
     that "unless that settlement is set aside in proper proceedings,
     it cannot lie in the mouth of one of the parties to the settlement    t
     to spurn it on the ground that it was a mistake and proceed to
     invoke the arbitration clause". But that was an observation made
H
                      NATIONAL INSURANCE CO. LTD. v, MIS. BOGHARA 669
                        POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

                with reference to a plea of 'mistake' and not with reference to A
                allegation of fraud, undue influence or coercion. It is also true
                that the observations in Damodar Valley Corporation and
                Jayesh Engineering Works, that whether contract has been fully
                worked out and whether payment has been made in full and
                final settlement are questions to be considered by the Arbitra- 8
                tor when there is a dispute regarding the same, even if there is
                a full and final settlement discharge voucher, seem to reflect a
                view at the other end of the spectrum. Though it is possible to
                read them harmoniously, such an exercise may not be neces-
                sary. All those decisions were rendered in the context of the
                provisions of the Arbitration Act, 1940. The perspective of the        c
                new Act is different from the old Act. The issue is not covered by
                the decision in SBP & Co.
                      25. In several insurance claim cases arising under Con-
          -.\   sumer Protection Act, 1986, this Court has held that if a com-
                                                                                  D
                plainant/ claimant satisfies the consumer forum that discharge
                vouchers were obtained by fraud, coercion, undue influence etc.,
                they should be ignored, but if they were found to be voluntary,
 ,•             the claimant will be bound by it resulting in rejection of com- ·
                plaint. In United India Insurance Co. Ltd., vs. Ajmer Singh Cot-
                ton & General Mills - 1999 (6) SCC 400, this Court held :         E

                     "The mere execution of the discharge voucher would not
                     always deprive the consumer from preferring claim with

- ...                respect to the deficiency in service or consequential benefits
                     arising out of the amount paid in default of the service rendered.
                     Despite execution of the discharge voucher, the consumer F
                     may be in a position to satisfy the Tribunal or the Commission
                     under the Act that such discharge voucher or receipt had
                     been obtained from him under the circumstances which can
                     be termed as fraudulent or exercise of undue influence or by
                     misrepresentation or the like. If in a given case the consumer G
                    satisfies the authority under the Act that the discharge voucher
      i             was obtained by fraud, misrepresentation, undue influence or
                    the like, coercive bargaining compelled by circumstances,
                    the authority before whom the complaint is made would be
                    justified in granting appropriate relief.
                                                                                        H
    670       SUPREME COURT REPORTS                     [2008] 13 S.C.R.


A         In the instant cases the discharge vouchers were admittedly
          executed voluntarily and the complainants had not alleged
          their execution under fraud, undue influence, misrepresentation
          or the like. In the absence of pleadings and evidence the State
          Commission was justified in dismissing their complaints."

B       The above principle was followed and reiterated in Na-
  tional Insurance Co. Ltd. vs. Nipha Exports (P) Ltd. - 2006 (8)
  SCC 156 and National Insurance Co. Ltd., vs. Sehtia Shoes -
  2008 (5) sec 400. It will also not be out of place to refer to what
  this Court had said in Central Inland Water Transport Corpo-
C ration Ltd. vs. Brojo Nath Ganguly - 1986 (3) SCC 156 in a
  different context (not intended to.apply to commercial transac-
  tions):

          "(This) principle is that the courts will not enforce and will,
          when called upon to do so, strike down an unfair and
D         unreasonable contract, or an unfair and unreasonable clause
          in a contract, entered into between parties who are not equal
          in bargaining power. It is difficult to give an exhaustive list of
          all bargains of this type. No court can visualize the different
          situations which can arise in the affairs of men. One can only
E         attempt to give some illustrations. For instance, the above
          principle will apply where the inequality of bargaining power is
          the result of the great disparity in the economic strength of the
          contractinQ parties. It will apply where the inequality is the
           result of circumstances, whether of the creation of the parties
           or not. It will apply to situations in which the weaker party is
F          in a position in which he can obtain goods or services or
           means of livelihood only upon the terms imposed by the
           stronger party or go without them. It will also apply where a
           man has no choice, or rather no meaningful choice, but to
           give his assent to a contract or to sign on the dotted line in
G          a prescribed or standard form or to accept a set of rules as
            part of the contract, however unfair, unreasonable and
            unconscionable a clause in that contract or form or rules may
            be. This principle, however, will not apply where the bargaining
            power of the contracting parties is equal or almost equal. This
            principle may not apply where both parties are businessmen
H
                      NATIONAL INSURANCE CO. LTD. v. M/S. BOGHARA              671
                        POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

                      and the contract is a commercial transaction. In today's       A
                      complex world of giant corporations with their vast infra-
                      structural organizations and with the State through its
                      instrumentalities and agencies entering into almost every
                      branch of industry and commerce, there can be myriad
                      situations which result in unfair and unreasonable bargains    B
                      between parties possessing wholly disproportionate and
                      unequal bargaining power. These cases can neither be
                      enumerated nor fully illustrated. The court must judge each
                      case on its own facts and circumstances."
                                                            [emphasis supplied]      c
                        26. Obtaining of undated receipts-in-advance in regard to·
                 regular/routine payments by government departments and cor-
                 porate sector is an accepted practice which has come to stay
                due to administrative exigencies and accounting necessities.
           'I   The reason for insisting upon undated voucher/receipt is that D
                as on the date of execution of such voucher/receipt, payment is
                 not made. The payment is made only on a future date long after
                obtaining the receipt. If the date of execution of the receipt is
                mentioned in the receipt and the payment is released long there-
                after, the receipt acknowledging the amount as having been E
                received on a much earlier date will be absurd and meaning-
                less. Therefore, undated receipts are taken so that it can be
                used in respect of subsequent payments by incorporating the
                appropriate date. But many a time, matters are dealt with so
      '1        casually, that the date is not filled even when payment is made.
                                                                                      F
                Be that as it may. But what is of sor;ne concern is the routine
                insistence by some government Departments, statutory Cor-
                porations and government Companies for issue of undated 'no
                due certificates' or a 'full and final settlements vouchers' acknowl-
                edging receipt of a sum which is smaller than the claim in full
                and final settlement of all claims, as a condition precedent for G
                releasing even the admitted dues. Such a procedure requiring
     -1'        the claimant to issue an undated receipt (acknowledging re-
                ceipt of a sum smaller than his claim) in full and final settlement,
_,
 ~

                as a condition for releasing an admitted lesser amount, is un-
                fair, irregular and illegal and requires to be deprecated.            H
    672         SUPREME COURT REPORTS                  [2008] 13 S.C.R.


A         27. Let us consider what a civil court would have done in a
    case where the defendant puts forth the defence of accord and
    satisfaction on the basis of a full and final discharge voucher
    issued by plaintiff, and the plaintiff alleges that it was obtained
    by fraud/coercion/undue influence and therefore not valid. It
B   would consider the evidence as to whether there was any fraud,
    coercion or undue influence. If it found that there was none, it
    will accept the voucher as being in discharge of the contract
    and reject the claim without examining the claim on merits. On
    the other hand, if it found that the discharge voucher had been
C   obtained by fraud/undue influence/coercion, it will ignore the
    same, examine whether plaintiff had made out the claim on
    merits and decide the matter accordingly. The position will be
    the same even when there is a provision for arbitration. The
    Chief Justice/his designate exercising jurisdiction under sec-
D   tion 11 of the Act will consider whether there was really accord
    and satisfaction or discharge of contract by performance. If the
    answer is in the affirmative, he will refuse to referthe dispute to
    arbitration. On the other hand, ifthe Chief Justice/his designate
    comes to the conclusion that the full and final settlement receipt
    or discharge voucher was the result of any fraud/coercion/un-
E   due influence, he will have to hold that there was no discharge
    of the contract and consequently refer the dispute to arbitration.
    Alternatively, where the Chief Justice/his designate is satisfied
    prima facie that the discharge voucher was not issued voluntar-
    ily and the claimant was under some compulsion or coercion,             'r .
F   and that the matter deserved detailed consideration, he may
    instead of deciding the issue himself, refer the matter to the
    arbitral tribunal with a specific direction that the said question
    should be decided in the first instance.
G         28. Some illustrations (not exhaustive) as to when claims
    are arbitrable and when they are not, when discharge of con-
    tract by accord and satisfaction are disputed, to round up the
    discussion on this subject :
          (i)   A claim is referred to a conciliation or a pre-iitigation
H               Lok Adalat. The parties negotiate and arrive at a
r



              NATIONAL INSURANCE CO. LTD. v. MIS. BOGHARA 673
                POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]

                     settlement. The terms of settlement are drawn up, A
                     and signed by both the parties and attested by the
                     Conciliator or the members of the Lok Adalat. After
                     settlement by way of accord and satisfaction, there
                     can be no reference to arbitration.

              (ii)   A claimant makes several claims. The admitted or           B
                     undisputed claims are paid. Thereafter negotiations
                     are held for settlement of the disputed claims resulting
                     in an agreement in writing settling all the pending
                     claims and disputes. On such settlement, the amount
                     agreed is paid and the contractor also issues a            c
                     discharge voucher/no claim certificate/full and final
                     receipt. After the contract is discharged by such
                     accord and satisfaction, neither the contract nor any
                     dispute survives for consideration. There cannot be
                     any reference of any dispute to arbitration thereafter.    D
              (iii) A contractor executes the work and claims payment
                    of say Rupees Ten lakhs as due in terms of the
                    contract. The employer admits the claim only for
                    Rupees six lakhs and informs the contractor either in
                    writing or orally that unless the contractor gives a E
                    discharge voucher in the prescribed format
                    acknowledging receipt of Rupees Six Lakhs in full
                    and final satisfaction of the contract, payment of the
    . .....         admitted amount will not be released. The contractor
                    who is hard pressed for funds and keen to get the F
                    admitted amount released, signs on the dotted line
                    either in a printed form or otherwise, stating that the
                    amount is received in full and final settlement. In such
                    a case, the discharge is under economic duress on
                    account of coercion employed by the employer. G
                    Obviously, the discharge voucher cannot be
                    considered to be voluntary or as having resulted in
                    discharge of the contract by accord and satisfaction.
                    It will not be a bar to arbitration.
                                                                                H
    674          SUPREME COURT REPORTS                [2008] 13 S.C.R     't


A         (iv)   An insured makes a claim for loss suffered. The claim
                 is neither admitted nor rejected. But the insured is
                 informed during discussions that unless the claimant
                 gives a full and final voucher for a specified amount
                 (far lesser than the amount claimed by the insured},
8                the entire claim will be rejected. Being in financial
                 difficulties, the claimant agrees to the demand and
                 issues an undated discharge voucher in full and final
                 settlement. Only a few days thereafter, the admitted
                 amount mentioned in the voucher is paid. The accord
c                and satisfaction in such a case is not voluntary but
                 under duress, compulsion and coercion. The coercion
                 is subtle, but very much real. The 'accord' is not by
                 free consent. The arbitration agreement can thus be
                 invoked to refer the disputes to arbitration.
D         (v)    A claimant makes a claim for a huge sum, by way of
                 damages. The respondent disputes the claim. The
                 claimant who is keen to have a settlement and avoid
                 litigation, voluntarily reduces the claim and requests
                 for settlement. The respondent agrees and settles
E                the claim and obtains a full and final discharge
                 voucher. Here even if the claimant might have agreed
                 for settlement due to financial compulsions and
                 commercial pressure or economic duress, the
                 decision was his free choice. There was no threat,
                 coercion or compulsion by the respondent. Therefore,
                                                                           ., .
F
                 the accord and satisfaction is binding and valid and
                 there cannot be any subsequent claim or reference
                 to arbitration.
          29. Let us now examine the receipt that has been taken in
G this case. It is undated and is in a pro forma furnishu(: by the
  appellant containing irrelevant and inappropriate statements. It
  states : "/!we hereby assign to the company, my/our right to             'i·
  the affected property stolen which shall, in the event of their
  recovery, be the property of the company". The claim was not
H in regard to theft of any property nor was the r.Jaim being settled
     -+         NATIONAL INSURANCE CO. LTD. v. M/S. BOGHARA 675
                  POLYFAB PVT. LTD. [R.V.RAVEENDRAN, J.]
          in respect of a theft claim. We are referring to this aspect only to A
          show how claimants are required to sign on the dotted line, and
          how such vouchers are insisted and taken mechanically without
          application of mind.
                 30. The discharge voucher form was handed over to the
          respondent on 21.3.2006. It was signed and delivered to the B
          appellant immediately thereafter acknowledging that a sum of
          Rs.2,33,94,964/- had been received from the insurer (appel-
          !ant) in full and final settlement, and that in consideration of such
          payment, the respondent absolved the appellant from all liabili-
          ties, present and future, arising directly or indirectly, out of saidc
          loss or damage under the policy. Admittedly, on the date when
          such discharge voucher was signed and given by the respon-
          dent, the payment of Rs.233,94,964/- had not been made. It
          was made after receiving the voucher. Therefore, at the time of
          signing the voucher by the respondent and at the time of deliv- D
  "       ery of voucher by the respondent to the appellant, the contents
          of the voucher that the said amount had been received, that
          such amount had been received in full and final settlement of all
          claims, and that in consideration of such payment, the company
          was absolved from any further liability, are all false and not sup- E
          ported by consideration.
                31. In this case the High Court examined the issue and
          found that prima facie there was no accord and satisfaction or
...,      discharge of the contract. It held that the appellant is still entitled
          to raise this issue before an arbitrator and the arbitrator has to F
          decide it. On the facts and circumstances and the settled posi- ·
          tion of law referred by us above, we are also prima facie of the
          view that there is no accord and satisfaction in this case and
          the dispute is arbitrable. But it is still open to the appellant to
          lead evidence before the arbitrator, to establish that there is a G
          valid and binding discharge of the contract by way of accord
-f        and satisfaction.
               32. We therefore find no reason to interfere with the order
          of the High court. The appeal is accordingly dismissed. We
                                                                               H
    676       SUPREME COURT REPORTS                [2008) 13 S.C.R.


A   make it clear nothing stated by the High Court or by us shall be
    construed as expression of any final opinion on the issue
    whether there was accord and satisfaction nor as expression
    of any views on merits of any claim or contentions of the par-
    ties.
B K.K.T.                                        Appeal dismissed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.