MIS. BLHAR CAUSTIC & CHEMICALS LTD.versusKRIPA PANDEY
- Citation
- 2008 INSC 71
- Decided
- 18 January 2008
- Disposal
- Case Partly allowed
- Bench
- ARIJIT PASAYAT
Holding
The Supreme Court partially allowed the appeal, directing payment of 50% of the back‑wages award, noting that the lower courts failed to consider the contractor‑employee relationship.
Summary
Kripa Pandey worked as a driver in the Bihar Caustic & Chemicals Ltd. factory during its construction, being engaged by a contractor under the Contract Labour (Regulation and Abolition) Act, 1970. He was terminated in September 1984 and claimed that the termination was illegal, seeking reinstatement and back wages. The Labour Court held the termination illegal, ordered his reinstatement and back wages from the date of claim, but neither the Labour Court nor the Patna High Court considered the appellant's contention that Pandey was an employee of the contractor, not of the company. The Supreme Court noted this omission and, taking into account that Pandey had already been reinstated and later superannuated, directed that only fifty percent of the back‑wages award be paid to him. The appeal was therefore partly allowed, with no order as to costs.
Issues considered
- Whether the respondent was a 'workman' within the meaning of Section 2(s) of the Industrial Disputes Act, 1947, given his engagement through a contractor.
- Whether the award of back wages by the Labour Court should stand in full despite the respondent's reinstatement and subsequent superannuation.
Legislation cited
Subjects
Judgment
[2008] 1 S.C.R. 917
A MIS. Bl'HAR CAUSTIC & CHEMICALS LTD. t
v.
KRIPA PANDEY
(Civil Appeal No. 1389 of 2001)
JANUARY 18, 2008
B
(DR. ARIJIT PASAYAT AND P. SATHASIVAM, JJ.)
Labour Laws:
Industrial Disputes Act, 1947; ss. 2(s) & 10:
c
Termination - Workman engaged by contractor serving
the appellant-company - Termination of services of workman
by the company - Held: Specific stand of appellant that
respondent was not its employee but employee of the
D contractor was neither considered by Labour Court nor by High
Court while ordering reinstatement of the workman in question
- Since workman reinstated and superannuated thereafter;
ends of justice would be best served by directing payment of
only 50% of back wages to him in terms of award of Labour
Court - Directions issued - Contract Labour (Regulation and
E
Abolition) Act, 1970 - Engagement of labour.
According to the respondent, he was working in the
appellant's factory continuously for certain period and
allegedly his services were terminated by the appellant-
F company. The dispute was referred to the Labour Court
for adjudication. The Labour Court held that termination
of the services of the workman in question was illegal and
unjustified; and that the respondent was entitled to
reinstatement and back wages from the date of the
G institution of the claim. The Writ petition filed by the
company was dismissed by the Single Judge of the High
Court. The Letters Patent Appeal was dismissed by the ..
Division Bench of the High Court. Hence the present
appeal.
H 917
M/S. BIHAR CAUSTIC & CHEMICALS LTD. v. 918
KRIPA PANDEY [PASAYAT, J.]
.,; ~ Appellant contended that during pendency of the A
appeal respondent was reinstated and superannuated on
6.3.2006; and that High Court's direction for payment of
back wages was not proper.
Partly allowing the appeal, the Court
B
HELD: Considering the facts that the specific stand
of the appellant about the respondent being employee of
the Contractor was not considered by the Labour Court
and the High Court, in normal course this Court would
have. remitted the matter to the High Court for c
consideration of that aspect. But taking into account the
fact that even after reinstatement, the respondent has
superannuated, ends of justice would be best served if
50% of the back wages in terms of the Labour Court
Court's award is paid to the respondent. If any payment
D
has already been made as back wages, the same shall be
adjusted from the amount payable in terms of this order.
(Para - 9) [921-A-C]
CIVILAPPELLATE JURISDICTION: Civil Appeal No.1389
of 2001. E
From the Judgment and final Order dated 29.6.2000 of
the High Court of Judicature at Patna, Ranchi Bench, Ranchi in
LPA No. 484 of 1999 (R).
Ashok Grover, Praveen Kumar for the Appellant. F
R.R. Dubey, Pawan Upadhyay, Santosh Mishra, Shiv
Mangal Sharma, Rohit Yadav, Shubhra Goyal and Sharmila
Upadhyay for the Respondent
The Judgment of the Court was delivered by G
Dr. ARIJIT PASAYAT, J. 1. Challenge in this appeal is to
the judgment of the Division Bench of the Patna High Court
dismissing the Letters Patent Appeal filed by the appellant.
Challenge in the Letters Patent Appeal was to the judgment of
the learned Single Judge of the said High Court. Before the H
919 SUPREME COURT REPORTS [2008] 1 S.C.R.
A High Court challenge was to the award of the Labour Court, f ~
Ranchi in Reference Case No.41/85. The respondent had raised
a dispute, inter alia, alleging illegal termination. According to
him he was working in the appellant's factory continuously from
1.8.1983 to 12.8.1984 and he was removed from service on
B 21.9.1984 without any reason. Following dispute was referred
to the Labour Court for adjudication:
"Whether the termination of services of Shri Kripa Pandey,
Driver by the management is proper and justified? If not,
whether he is entitled to reinstatement and/or any other
·c relief."
2. The aforesaid reference was made by notification dated
1.11.1985. Stand of the appellant before the Labour Court was
that during the period from 1981 to 1984 when the factory of the
appellant was under construction it had engaged several
D
contractors including one M/s Mishra Brothers for the purpose
of various works for construction of the factory. During the
aforesaid period the said Contractor who was authorized to
engage contract labour under the provisions of the Contract
Labour (Regulation and Abolition) Act, 1970 (for short' 'Contract
E Labour Act') by licence deed dated 13.3.1982 engaged the
respondent as a tractor driver. It was the case of the appellant
that at no point of time respondent was employee of the appellant
and there was no relationship of employer and employee
between them. No appointment letter was ever issued to the
F respondent by the appellant. The respondent used to get salary
from the Contractor. After construction of the work was
completed in 1984, the appellant did not require services of the
contractor and in turn the contractor did not require the services
of the employees including respondent engaged by it.
G
3. In the written statement filed before the Labour Court
the above plea was taken and it was stated that the respondent
was not a workman within the meaning of Section 2(s) of the
Industrial Disputes Act, 1947 (in short 'the Act') and, therefore,
the reference as made was maintainable in law. Before the
H
MIS. BIHAR CAUSTIC & CHEMICALS LTD. v. 920
KRIPA PANDEY [PASAYAT, J.]
r Labour Court the contractor was also examined and he stated A
" that the respondent was working under his contract and he was
employed by him and, therefore, he paid the wages to him. In
the gate pass it was clearly mentioned that he was the employee
of the Contractor.
4. The Labour Court held that the termination was illegal B
and unjustified and the respondent was entitled to reinstatement
and back wages from the date of the institution of claim i.e.
28.11.1985.
5. Writ petition was filed before the High Court and as c
noted above, it was dismissed by the learned Single Judge.
The Division Bench dismissed the Letters Patent Appeal.
6. In support of the appeal, learned counsel for the appellant
submitted that no finding on the plea taken by the appellant
regarding the respondent being employed by the contractor has D
been recorded and the plea has not been considered.
Additionally, after this Court granted leave and the stay was
restricted to payment of back wages, respondent was reinstated
on 21.3.2001 and superannuated on 6.3.2006. According to
his own case, he was getting Rs.400/- p.m. It is unbelievable E
that he was not employed elsewhere. Further, during the
pendency of the writ petition and Letters Patent Appeal, payment
in terms of Section 17-B was being made. Therefore, it is
submitted that direction of back wages is not in order.
7. Learned counsel for the respondent on the other hand F
submitted that on the plea taken by the appellant that respondent
was gainfully employed, an inquiry was conducted and it was
concluded that the respondent was not gainfully employed.
8. Few dates need to be noted.
G
Date of reference is 1.11.1985 and the case was
registered by Labour Court on 20.11.1985. The award is dated
28.7.1989. It was published on 30.10.1989. The learned Single
Judge dismissed the writ petition on 7.10.1999 and the Letters
Patent Appeal was dismissed on 29.6.2000. H
921 SUPREME COURT REPORTS [2008] 1 S.C.R.
1 •
A 9. Considering the facts that the specific stand of the
appellant about the respondent being employee of the
Contractor was not considered by the Labour Court and the
High Court, in normal course we would have remitted the matter
to the High Court for consideration of that aspect. But taking
B into account the fact that even after reinstatement, the
respondent has superannuated, ends of justice would be best
served if 50% of the back wages in terms of the Labour Court
Court's award is paid to the respondent. The payment shall be
made within three months. If any payment has already been
c made as back wages, the same shall be adjusted from the
amount payable in terms of this order.
10. The appeal is allowed to the aforesaid extent with no
order as to costs.
D S.K.S. Appeal partly allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.