Created byFuzzy Cloud

Supreme Court of India

MAHA MINERAL MINING & BENEFICATION PVT. LTD.versusMADHYA PRADESH POWER GENERATING CO. LTD. & ANR.

Citation
2025 INSC 1085
Decided
9 September 2025
Disposal
Case Partly allowed

Holding

The Supreme Court held that the appellant’s disqualification under Clause 5(D) for non‑submission of the JV agreement was unlawful and set aside the High Court’s order, while remanding the question of spare washery capacity under Clause 5(B) for fresh consideration.

Summary

The appellant, Maha Mineral Mining & Benefication Pvt. Ltd., submitted a technical bid for a coal beneficiation tender but was disqualified by the Tender Evaluation Committee for not furnishing a Joint Venture (JV) agreement as required under Clause 5(D) of the NIT. The High Court upheld this disqualification and additionally held that the appellant would have been disqualified under Clause 5(B) for lacking spare washery capacity, despite the issue not being raised before the Committee. The Supreme Court examined whether Clause 5(D) obliges a bidder to submit the JV agreement and found that the work‑execution certificate submitted by the appellant sufficiently demonstrated its 45% share in the consortium, making the non‑submission of the JV agreement an invalid ground for disqualification. Consequently, the Court set aside the High Court’s decision on Clause 5(D) and remanded the matter to determine the appellant’s spare washery capacity under Clause 5(B). The appeal was partly allowed, with the order of the High Court overturned and the issue of washery capacity referred back for fresh consideration.

Issues considered

  • Whether the appellant’s disqualification under Clause 5(D) of the NIT for not furnishing the JV agreement is justified.
  • Whether Clause 5(D) of the NIT expressly requires submission of the JV agreement to establish proportionate share in a consortium.
  • Whether the High Court erred in additionally disqualifying the appellant under Clause 5(B) concerning spare washery capacity without giving the appellant an opportunity to contest.
  • Whether the Committee’s decision can be set aside on the ground of misinterpretation of the NIT provisions.

Headnote

Issue for Consideration Issue arose whether the decision of the High Court to uphold the appellant-bidder’s disqualification under Clause 5(D) for not furnishing Joint Venture agreement justified; and whether the appellant would have stood disqualified since exclusively committed to the State Mining Corporation. Headnotes† Tender – Notice inviting tender – Clause (5)D and Clause (5)B – Disqualification – 1st respondent invited Tender for coal beneficiation and managing logistics for Thermal Power Project –

Subjects

DisqualificationClause 5(D) of the NITNon furnishing JV agreementWasheriesTenderNotice inviting tenderClause 5(B) of the NITCoal beneficiationTechnical evaluationJoint Venture agreementState Mining Corporation

Judgment

         [2025] 9 S.C.R. 528 : 2025 INSC 1085

  Maha Mineral Mining & Benefication Pvt. Ltd.
                      v.
Madhya Pradesh Power Generating Co. Ltd. & Anr.
               (Civil Appeal No. 11726 of 2025)
                     09 September 2025
       [Surya Kant and Joymalya Bagchi, JJ.]


                    Issue for Consideration
Issue arose whether the decision of the High Court to uphold
the appellant-bidder’s disqualification under Clause 5(D) for not
furnishing Joint Venture agreement justified; and whether the
appellant would have stood disqualified since its washeries had
been exclusively committed to the State Mining Corporation.

                          Headnotes†
Tender – Notice inviting tender – Clause (5)D and Clause (5)B –
Disqualification – 1st respondent invited Tender for coal
beneficiation and managing logistics for Thermal Power
Project – Appellant and others submitted their bid – However,
the appellant-bidder was disqualified during technical
evaluation by the Committee due to non-submission of
credentials as per Clause No.(5)D of the NIT-non-filing of Joint
Venture agreement – Decision of the Committee challenged by
the appellant – High Court upheld the disqualification of the
appellant by the Committee for non-compliance of Clause 5(D)
of the NIT and also held that even if the JV agreement had
been submitted, the appellant would have stood disqualified
since its washeries had been exclusively committed to the
State Mining Corporation – Correctness:
Held: 1st respondent acted contrary to the terms of the NIT and
unfairly rejected the appellant’s bid for non-production of JV
agreement although Clause 5(D) did not prescribe production of
such agreement as mandatory to rely on past-experience of such
consortium in which the bidder had a defined proportionate share –
Decision of the Committee, upheld by the High Court as per Clause
5(D) liable to be set aside – Issue as regards washery capacity is
a contentious one and ought not to have been decided by the High
[2025] 9 S.C.R.                                                           529

            Maha Mineral Mining & Benefication Pvt. Ltd. v.
           Madhya Pradesh Power Generating Co. Ltd. & Anr.

     Court without giving opportunity to the appellant to controvert the
     same – High Court also lost sight of the fact that the Committee
     had not adverted to this issue and it was impermissible for it to
     travel beyond the reasons given by the Committee and disqualify
     the appellant – Allotment of work order to 2nd respondent has been
     made subject to the outcome of this proceeding – Matter remand
     for a fresh consideration whether appellant had requisite spare
     washing capacity as per Clause 5(B) of the NIT and the validity
     of the work order in favour of the 2nd respondent in light of such
     decision – Impugned judgment and order of the High Court set
     aside. [Paras 20, 21, 24-26]

                             List of Keywords
     Disqualification; Clause 5(D) of the NIT; Non furnishing JV
     agreement; Washeries; Tender; Notice inviting tender; Clause
     (5)B of the NIT; Coal beneficiation and managing logistics for
     Thermal Power Project; Technical evaluation by the Committee;
     Non-submission of credentials; Joint Venture agreement; State
     Mining Corporation.

                            Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 11726
     of 2025
     From the Judgment and Order dated 06.01.2025 of the High Court
     of Madhya Pradesh Principal Seat at Jabalpur in WP No. 18286
     of 2024

                         Appearances for Parties
     Advs. for the Appellants:
     Narender Hooda, Sr. Adv., Gagan Sanghi, Mrs. Farah Hashmi,
     Santosh Ghate, Rameshwar Prasad Goyal.
     Advs. for the Respondents:
     Bijender Chahar, A.S.G., Shyam Divan, Balbir Singh, Arpan Pawar,
     Sr. Advs., Kartik Seth, Ms. Ranjeeta Rohatgi, Nikhil Nasre, Raghav
     Sharma, Ms. Aditi Mishra, K.M Abish, Manan, Ms. Shrika Gautam,
     Himanshu Satija, Harsh Saxena, Chiranjeev Sharma, Pulkit Pawar,
     Mrs. Neha Mehta Satija.
530                                                                                    [2025] 9 S.C.R.

                                    Supreme Court Reports


                       Judgment / Order of the Supreme Court

                                              Judgment

1.     Leave granted.

       Factual Matrix
2.     In response to Notice Inviting Tender1 dated 17.05.2024, issued
       by the 1st respondent for the purpose of run-of-mine (ROM) coal
       beneficiation and managing logistics from Western Coalfields Ltd.2
       (Nagpur area) sources for Shree Singaji Thermal Power Project,
       Khandwa (Madhya Pradesh), the appellant and two others, namely
       the 2nd respondent3 and one M/s NN Global Mercantile Pvt. Ltd. had
       submitted their bid.
3.     As NN Global Mercantile Pvt. Ltd. could not furnish earnest money
       deposit, only the appellant and the 2nd respondent remained in
       the fray. On 04.07.2024, the Tender Evaluation Committee4 while
       referring to Clause 5(D)5 of the NIT rejected the appellant’s technical
       bid holding as follows –



1    ID 2024_MPPGC_341576_1, hereinafter referred to as “NIT”.
2    Hereinafter “WCL”.
3    Rukhmai Infrastructure Pvt. Ltd.
4    Hereinafter referred to as “The Committee”.
5    Clause 5(D): “Past Experience: Copies of successfully executed orders (including part executed) in the
     name of bidder for same or similar work {similar work means coal lifting from mines of CIL subsidiaries or
     SCCL area, coal beneficiation (through wet process), movement of washed coal by road from washery
     to railway siding and movement of washed coal through Railways with experience in liaisoning with
     Railways/ CIL subsidiaries or SCCL area, i.e., arranging rakes, dispatches coal from own or leased
     Private siding or Goods shed Railways siding by loading of washed coal into railway wagons through
     own arrangement with monitoring the rake movement etc. up to the destination Power house}. Bidder
     is allowed to use past experience of their previous Consortium or JV (proportionate to its share
     in that consortium if defined in the Consortium Agreement, otherwise, lead partner if not defined
     in the Consortium) to meet out the past experience criteria of the tender. The order copies should
     indicate the above w/ork for 4 Lakh MT (4,00,000 MT) quantity or more in stale Owned Power Generating
     Companies or Other Captive Power Utilities of PSU or NTPC or Govt. Industries / Departments or Semi
     Govt. Industries / Departments or PSUs or Nodal Agency of any PSUs in India executed in last five
     years ending with initial date of opening of bid are to be uploaded. This order execution should be within
     a period of twelve (12) months. It may be through single or multiple orders (in parallel), but in case of
     multiple orders; these should be within a single span of time period of twelve (12) months.
     1. The work execution certificate by the customers along-with self-attested un-priced copies of
     aforesaid work order(s) should be submitted.
     2. For Past performance certificates - If worked with MPEB/ MPSEB/ MPPGCL in past for similar work,
     then it is mandatory to provide Satisfactory Performance Certificate for the same. Failing this, the offer
     shall not be considered.” (emphasis supplied)
[2025] 9 S.C.R.                                                            531

                Maha Mineral Mining & Benefication Pvt. Ltd. v.
               Madhya Pradesh Power Generating Co. Ltd. & Anr.

               “As per Clause No. 5(D) “Past experience criteria” of
               NIT, bidder is allowed to use past experience of their
               previous Consortium or JV (proportionate to its share in
               that consortium if defined in the Consortium Agreement,
               otherwise, lead partner if not defined in the Consortium)
               to meet out the past experience criteria of the tender.
               The firm has used the credentials of their consortium
               M/s Hind-Maha-Mineral LLP for meeting out the past
               experience criteria. However, Agreement of the Consortium/
               JV is not submitted to substantiate the share of the
               bidder in that consortium. Bidder is disqualified due to
               non-submission of credentials as per Clause No. (5)D of
               the NIT.”
4.     Appellant challenged the decision of the Committee before the High
       Court of Madhya Pradesh.6 Appellant contended neither Clause
       5(D) nor any terms of the NIT expressly required a bidder who
       was relying on past-experience of a previous consortium or joint
       venture7 to produce the JV agreement itself to demonstrate its
       proportionate share in the consortium. In terms of Clause 5(D) it
       had submitted a work execution certificate from Maharashtra State
       Mining Corporation8 which inter alia stated that the appellant was
       45% Joint Venture/Consortium Partner of M/s. Hind Maha Mineral
       LLP vide the JV agreement dated 02.12.2019 and had executed
       similar work in respect of WCL command for the period 05.03.2021
       to 05.03.2024. It was further clarified the JV agreement had been
       submitted before MSMC.
5.     In case of doubt, 1st respondent could have verified the correctness
       of the certificate from MSMC or called upon the appellant to furnish
       the JV agreement. On the contrary, the 1st respondent arbitrarily
       rejected the technical bid on the ground the JV agreement had not
       been furnished.
6.     1st respondent contradicted such stance and contended in the event
       any bidder was seeking to rely on past-experience of a previous
       consortium/JV, submission of the JV agreement was implicit in


6    Writ Petition No. 18286/2024.
7    Hereinafter referred to as “JV”.
8    Hereinafter referred to as “MSMC”.
532                                                                                [2025] 9 S.C.R.

                                  Supreme Court Reports


       Clause 5(D) of the NIT. Further, Clause 8.1 provided that if the bidder
       did not submit the desired documents as per NIT at the time of
       submission of the bid, he shall not be allowed to submit documents
       subsequently and its bid is liable to be rejected on account of
       incomplete documents. Clause 8.1 of the NIT unequivocally states
       that –
             “Instructions regarding shortfall documents:-
             (i) The bidders not submitting all the desired documents
             as per NIT/Tender Document at the time of submitting
             bids, shall not be allowed to submit documents
             subsequently and their bids shall be rejected on
             account of incomplete documents. Thus, no “shortfall
             window” for submission of shortfall documents shall
             be created by MPPGCL in the e-tender.
             (ii) Accordingly, Clause No. 1.15 (VII) “Verification of
             credentials/PQR” of the Standard Bid Document (SBD)
             so far as it relates to “Shortfall of document” window shall
             not be applicable.
             (iii) Any condition elsewhere mentioned in the
             NIT/Tender Document for submission of Shortfall
             Document shall not be applicable.
             (iv) However, techno-commercial clarifications (if required)
             shall be obtained through e-mail/physical form from the
             bidders”
                                                                    (emphasis supplied)

       The said clause is further fortified by circular no. F-3/25/2015/13/109
       issued by the Government of Madhya Pradesh on 29.11.2023.



9   Circular dated 29.11.2023: “It has come to the notice of the department that bidders are being allowed
    to participate in the bid process with incomplete documents. Bidders are allowed to submit the balance
    documents in due course of time and meanwhile some of the bidders back out of the bidding process,
    allowing a few number of bidders to participate in the bidding process and quote non-competitive rates
    which results in financial loss to the Power Companies. It has therefore been decided that bidders not
    submitting all the desired documents as per NIT/Tender document at the time of submitting bids,
    should not be allowed to submit documents subsequently and their bids should be rejected on
    account of incomplete documents. If required, even fresh bid can be called to get competitive rates.
    As directed, it is request to please ensure the bidding process to make it more transparent and fair.”
    (emphasis supplied)
[2025] 9 S.C.R.                                                              533

            Maha Mineral Mining & Benefication Pvt. Ltd. v.
           Madhya Pradesh Power Generating Co. Ltd. & Anr.

7.   Appellant was fully aware of the requirement to furnish the JV agreement
     to demonstrate its proportionate share in the consortium in order to rely
     on the past-experience of such previous consortium/JV. In fact after
     the closing date, by email dated 05.07.2024, the appellant purportedly
     submitted a JV agreement dated 06.09.2019, which however did not
     correspond to the JV agreement dated 02.12.2019 referred to in the
     certificate issued by the MSMC. Be that as it may, such subsequent
     submission of document was impermissible as per Clause 8.1 of the
     NIT read with circular dated 29.11.2023 and the technical bid was
     rightly rejected for submission of incomplete document.
8.   During the pendency of the writ petition, 2nd respondent was declared
     as the successful bidder and was impleaded in the proceedings.
     During hearing, the JV agreement dated 02.12.2019 was placed
     on record. Written submissions were also submitted on behalf of
     the parties.

     Findings of the High Court
9.   By the impugned judgement and order, the High Court upheld the
     decision of the Committee holding as follows:-
           “22. Due to non-filing of Joint Venture agreement by the
           Petitioner, the Impugned Order rejecting the bid of the
           petitioner has to be seen wherein at the outset it has
           been stated that your bid for the above tender has been
           rejected during Technical evaluation by the duly constituted
           committee for the reason Bidder is disqualified due to
           non submission of credentials as per Clause No. (5)D of
           the NIT.” It is evident that the Petitioner has not filed the
           Joint Venture agreement. The Petitioner is disqualified
           for the reason of non compliance with the requirements
           in terms of Clause (5)D. The reason is also assigned by
           the Respondent No.1 in their reply as to why the petitioner
           was disqualified. If the petitioner is relying on the Joint
           Venture Agreement dated 02.12.2019 then it was the duty of
           Petitioner to file the same while submitting the bid. The NIT
           condition no. (8)1(i) and (8)(1)(iii), specifically prohibit the
           submission of the document/shortfall document at a later
           stage. As per the NIT conditions, a bidder is supposed to
           upload all the requisite documents at the time of submission
534                                                          [2025] 9 S.C.R.

                         Supreme Court Reports


          of the bid. It is evident that the earlier practice of allowing
          bidders to fulfil the shortfall in documents left a scope for
          unfair practices in the bidding process and therefore, the
          said practice of allowing documents at a later stage has
          been discontinued in view of the past experience, as is
          evident from the letter 29.11.2023 of the GoMP, Energy
          Department. The Petitioner in the present case relied on
          the experience certificate issued by the Maharashtra
          State Mining Corporation dated 14.06.2024 wherein
          date of the Joint Venture agreement is mentioned as
          02.12.2019. However, surprisingly the Petitioner neither
          filed the said document of JV on record at the time
          of submission of bid nor at the time of filing of the
          petition. Even the document of JV agreement, which
          the Petitioner has filed along with the Email sent to
          Respondent No.1, is dated September, 2019 and not
          02.12.2019. The Petitioner has not filed the said JV
          Agreement from its own. It is apparent that there is a
          suppression of the JV Agreement dated 02.12.2019 by
          the Petitioner and hence, on this count of concealment
          of JV agreement dated 02.12.2019 the instant petition
          fails. The Petitioner has not given any satisfactory response
          in the petition or even otherwise for not submitting the
          document in alternate. Thus, the Petitioner cannot put
          forward its claim before demonstrating its bonafides
          that could have been done by duly submitting all the
          documents and by not engaging in active suppression
          and concealment…….”
                                                  (emphasis supplied)

10. Thereafter, referring to the written submissions made by the 2nd
    respondent in light of Clauses 3.12, 3.13 and 8.5 of the JV agreement,
    the Bench further held:-
          “24. The additional submissions of the Respondent No.2
          have force and it is evident that in any case, even if
          the above-mentioned documents were provided by
          the Petitioner would have been disqualified as its
          washeries had been committed to Maharashtra State
          Mining Corporation Ltd. alone in terms with the
[2025] 9 S.C.R.                                                         535

            Maha Mineral Mining & Benefication Pvt. Ltd. v.
           Madhya Pradesh Power Generating Co. Ltd. & Anr.

           Joint Venture Agreement dated 02.12.2019. Even the
           experience Certificate issued by Maharashtra State Mining
           Corporation Ltd. to the Petitioner categorically mentions
           the Joint Venture Agreement dated 02.12.2019.”
                                                 (emphasis supplied)

11. In view of the aforesaid findings, the Division Bench dismissed the
    writ petition, giving rise to the present appeal.
12. Heard Mr. Narender Hooda, learned senior counsel for the appellant,
    Mr. Bijender Chahar, learned senior counsel for 1st respondent, and
    Mr. Shyam Divan and Mr. Balbir Singh, learned senior counsel for
    2nd respondent.

     Analysis
13. It appears the High Court had not only upheld the disqualification of
    the appellant by the Tender Evaluation Committee for non-compliance
    of Clause 5(D) of the NIT but also went a step further and held,
    even if the JV agreement had been submitted, the appellant would
    have stood disqualified since its washeries had been exclusively
    committed to MSMC.

     (I) Appellant’s disqualification under Clause 5(D) of the NIT
14. First, let us consider whether the decision of the High Court to uphold
    the appellant’s disqualification under Clause 5(D) for not furnishing
    JV agreement is justified or not?
15. Clause 5(D) of the NIT required the bidders to furnish documents
    relating to past-experience in similar work. The clause further provided
    that “bidder is allowed to use past experience of their previous
    Consortium or JV (proportionate to its share in that consortium if
    defined in the Consortium Agreement, otherwise, lead partner if not
    defined in the Consortium) to meet out the past experience criteria
    of the tender.” Sub-clause 1 and 2 of the said clause stated the
    following documents are to be submitted:-
           “1. The work execution certificate by the customers
           along-with self-attested un-priced copies of aforesaid work
           order(s) should be submitted.
           2. For Past performance certificates - If worked with
           MPEB/ MPSEB/ MPPGCL in past for similar work, then
536                                                             [2025] 9 S.C.R.

                            Supreme Court Reports


            it is mandatory to provide Satisfactory Performance
            Certificate for the same. Failing this, the offer shall not
            be considered.”
                                                     (emphasis supplied)

       Appellants had submitted a work execution certificate from MSMC
       along with its bid to support its past-experience as a 45% proportionate
       member of a consortium/JV for similar work executed at WCL in the
       last five years. The relevant portion of the certificate reads as follows:-
            “……this is to certify that as part of the aforementioned
            contract agreement, M/s Maha Mineral Mining &
            Beneficiation Private Limited being the 45% Joint
            Venture/Consortium Partner of M/s. Hind Maha Mineral
            LLP vide the JV agreement dated 02.12.2019 (submitted
            to this office by M/s Hind Maha Mineral LLP) has executed
            the said work in respect of WCL command for the period
            05.03.2021 to 05.03.2024. The details are as follows:
            a.    Quantity of RoM Coal Lifted: 1,41,55,130.40 MT
            b.    Quantity of RoM coal washed: 1,17,95,440.46 MT
            c.    Quantity of washed coal supplied to Mahagenco
                  TPSs: 1,17,47,501.99 MT
            d.    Approximate value of the work executed: Rs. 465
                  crores.”
                                                     (emphasis supplied)

16. The aforesaid certificate clearly demonstrates that the appellant had
    45% share in a JV consortium namely M/s Hind Maha Mineral LLP
    and had successfully executed work of similar nature as required
    by Clause 5(D) of the NIT.
17. The Committee refused to rely on such certificate holding as follows :-
            “(v) As per tender condition no documents other than
            Consortium/JV Agreement can be permitted to meet out
            the above criteria as per the NIT. Thus, the certificate
            submitted by M/s Maha Mineral Mining and Benefication
            Private Limited cannot be considered as valid document
            for the same.”
[2025] 9 S.C.R.                                                          537

             Maha Mineral Mining & Benefication Pvt. Ltd. v.
            Madhya Pradesh Power Generating Co. Ltd. & Anr.

18. Though the submission of a JV agreement has not been expressly
    stated in the aforesaid clause, the respondents argue that the
    proportionate share of a bidder in a consortium/JV can only be
    established through production of the JV agreement itself and
    the words used in the contract/tender document must be read in
    a purposive manner so that no part of the document is rendered
    superfluous. Respondents further contend appellant had submitted its
    bid on the last day and it was open to the appellant during the previous
    calls to seek clarification whether submission of JV agreement was
    mandatory. Appellant did not do so and intentionally suppressed the JV
    agreement while submitting its bid to avoid disclosure of inconvenient
    clauses in the JV agreement. This is evident from the appellant’s
    conduct as it had after submission of bid, emailed a purported JV
    agreement dated 06.09.2019, whereas the JV agreement mentioned
    in the certificate was a different one. Be that as it may, the subsequent
    submission of a JV agreement could not have been considered in
    light of Clause 8.1 read with circular dated 29.11.2023.
19. We are unable to accept such arguments for the following reasons:-
     (i)    Clause 5(D) merely states the appellant would be entitled to
            use the past-experience of a previous consortium/JV in the
            event its proportionate share is defined in the JV agreement
            failing which the past-experience shall be attributed to the lead
            partner. The clause does not mandate the submission of the
            JV agreement itself to satisfy such criteria. Appellant had relied
            on the work execution certificate issued by MSMC which in no
            uncertain terms states the appellant had 45% share in the JV
            consortium named M/s Hind Maha Mineral LLP and successfully
            executed similar work of a volume larger than required under
            the clause. The certificate also mentioned the JV agreement
            had been submitted and was in the custody of MSMC.
     (ii)   It is nobody’s case that the 1st respondent had doubted the
            authenticity of the certificate but had disqualified the appellant
            on the ground that Clause 5(D) mandated furnishing of the JV
            agreement alone and nothing else to prove proportionate share
            in a previous JV in order to use such experience.
     (iii) Conditions in a NIT must be clear and unambiguous. In the
           event the tendering authority insisted on furnishing of the
           JV agreement alone and no other document as proof of the
538                                                                                     [2025] 9 S.C.R.

                                    Supreme Court Reports


               proportionate share of the bidder to avail previous JV experience
               as prior qualification, it should have been spelt out clearly in the
               NIT. Having not done so, the 1st respondent cannot thrust the
               responsibility on the appellant to seek clarification and submit
               such document. As Clause 5(D) does not require submission
               of JV agreement itself to establish proportionate share in the
               JV whose past-experience the bidder is seeking to use, non-
               submission of such JV cannot be a ground to disqualify the
               bidder for submission of incomplete documents in terms of
               Clause 8.1 of NIT. Admittedly, the appellant had submitted the
               work execution certificate, as required under clause 5(D), which
               also unequivocally sets out its proportionate share in the JV
               agreement whose prior experience it had relied on.
       (iv) Though it is argued Clause 8.1 as well as circular dated
            29.11.2023 put an embargo on 1 st respondent to rely on
            documents furnished after submission of bid, nothing
            prevented 1st Respondent to seek clarification with regard to
            the proportionate share of the appellant in the previous JV as
            disclosed in the work execution certificate. It may be apposite
            to note Clause 8.810 of the NIT, couched in a non-obstante
            clause, reserved the right of the 1st respondent to seek additional
            information to satisfy itself with regard to the eligibility of any
            bidder. 1st respondent failed to exercise such discretion by
            fortifying itself through calling for the JV agreement, which, when
            placed before this Court, unequivocally endorsed the contents
            of the certificate submitted by the Appellant.
       (v)     The other argument advanced by the respondents is that the
               appellant had acted with mala fide intention by suppressing
               the JV agreement and subsequently furnishing different
               versions of the said agreement at various stages i.e., before
               the 1st Respondent, in the Special Leave Petition and finally,
               by way of additional documents respectively. This argument
               is unacceptable as neither Clause 5(D) required submission
               of JV agreement to prove proportionate share nor was the



10   Clause 8.8: “Notwithstanding anything stated above, MPPGCL reserves the right to assess the
     creditability, capability and capacity to perform the contract. Should the circumstances warrant such
     an assessment in its overall interest, bidder shall furnish additional documents to substantiate its claim.
     MPPGCL also reserves the right to seek such additional information as it may deem fit to satisfy
     itself of the eligibility of the bidder.” (emphasis supplied)
[2025] 9 S.C.R.                                                       539

            Maha Mineral Mining & Benefication Pvt. Ltd. v.
           Madhya Pradesh Power Generating Co. Ltd. & Anr.

           appellant called upon to submit such document. Moreover,
           the proportionate share of the appellant in the consortium
           as reflected in all the documents, i.e., the JV agreement
           submitted before the 1st Respondent, annexed to the SLP
           and the agreement with additional documents, is the same
           and consistent with the work execution certificate submitted
           in the bid. For these reasons, we are not in agreement with
           the argument that the appellant had intentionally suppressed
           the JV agreement or had approached the Court with unclean
           hands.
     (vi) Finally, submission of the 2nd Respondent regarding a pending
          civil dispute between the consortium partners of M/s Hind
          Maha Mineral LLP is also of little consequence. Such dispute
          has no impact on the proportionate share of the appellant in
          the JV agreement and the work executed by the appellant as
          a part of the consortium for MSMC as disclosed in the work
          execution certificate.
20. In these circumstances, we are inclined to hold the 1st respondent
    acted contrary to the terms of the NIT and unfairly rejected the
    appellant’s bid for non-production of JV agreement although Clause
    5(D) did not prescribe production of such agreement as mandatory
    to rely on past-experience of such consortium in which the bidder
    had a defined proportionate share.
21. Accordingly, decision of the Committee, upheld by the High Court
    as per Clause 5(D) is liable to be set aside.

     (II) Appellant’s disqualification under Clause 5(B) of the NIT
22. However, the High Court went a step further, traversing beyond
    the reasons given by the Committee and held the Appellant would
    otherwise be disqualified under Clause 5(B) of the NIT. Clause 5(B)
    reads as follows –
           “Details of Washery:
           Bidder should have its own Washery with wet beneficiation
           technology either of Heavy Media Cyclone or Heavy Media
           Bath or Wet Jig. The Bidder should have a minimum
           spare washing capacity using wet technology of 50%
           of annual tendered quantity, i.e., 5 Lakh Metric Tonnes
540                                                                                  [2025] 9 S.C.R.

                                   Supreme Court Reports


              (LMT), in area nearby to mines of WCL configured in
              the tender. Total distance from mine(s) to offered washery
              (ies) and offered washery (ies) to Railway siding shall not
              be more than 100 KM.”
                                                                     (emphasis supplied)

23. To arrive at such a finding the High Court relied on written arguments
    submitted by the 2nd respondent and held as per Clauses 3.12, 3.13
    and 8.5 of the JV agreement the appellant’s washeries were committed
    to MSMC and could not have been used for the present tender.
    Mr. Hooda rightly contends the issue was raised for the first time
    in the written submissions and his client did not get the opportunity
    to controvert the same. Referring to a chart placed before us,11 he
    vehemently argues the appellant’s Gondegaon washery had a spare
    capacity of 1.5 MMTPA12 which was much higher than the required
    spare capacity under Clause 5(B) of the NIT. He further contends a
    request13 had been made to MSMC to shift their operation to other
    washeries in terms of Clause 614 of the contract agreement executed
    between MSMC and the consortium, and the Gondegaon Washery
    was available for execution of the work under the present NIT.
24. We are of the considered view the aforesaid issue is a contentious
    one and ought not to have been decided by the High Court without
    giving opportunity to the appellant to controvert the same. High
    Court also lost sight of the fact that the Committee had not adverted
    to this issue and it was impermissible for it to travel beyond the
    reasons given by the Committee and disqualify the appellant. It is
    also relevant to note that allotment of work order to 2nd respondent
    has been made subject to the outcome of this proceeding.
25. For these reasons, we remand the matter for a fresh consideration
    whether appellant had requisite spare washing capacity as per
    Clause 5(B) of the NIT and the validity of the work order in favour
    of the 2nd respondent in light of such decision. The High Court shall


11   Annexure P-34 in the Appellant’s Rejoinder to the Counter Affidavit filed by the 2nd Respondent.
12   Million Metric Tonnes Per Annum.
13   Letter dated 14.06.2024, annexed as P-36 in the Appellant’s Rejoinder to the Counter Affidavit filed by
     the 2nd Respondent.
14   Clause 6: “ACCEPTED RATES:- Accepted Rates for beneficiation of raw coal as below (exclusive of
     GST). If any change in washery/railway siding is request by CONTRACTOR (LLP), then it should
     not put extra financial burden on MSMC” (emphasis supplied).
[2025] 9 S.C.R.                                                     541

               Maha Mineral Mining & Benefication Pvt. Ltd. v.
              Madhya Pradesh Power Generating Co. Ltd. & Anr.

     decide the matter as expeditiously as possible preferably within two
     months from the date of communication of this order.
26. The impugned judgment and order of the High Court is set aside
    and the appeal is partly allowed.

     Result of the case: Appeal partly allowed.




     †
         Headnotes prepared by: Nidhi Jain


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Disqualification"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

MAHA MINERAL MINING & BENEFICATION PVT. LTD. versus MADHYA PRADESH POWER GENERATING CO. LTD. & ANR. — 2025 INSC 1085 - Legal Desk AI