M/S. SURYACHAKRA POWER CORPORATION LIMITEDversusELECTRICITY DEPARTMENT, REP. BY ITS SUPERINTENDING ENGINEER, PORT BLAIR AND OTHERS
- Citation
- 2016 INSC 899
- Decided
- 22 September 2016
- Disposal
- Dismissed
- Bench
- KURIAN JOSEPH
Holding
The appeal is dismissed; the Supreme Court cannot condone delay beyond the 60‑day discretionary period under Section 125, and Section 5 and Section 14 of the Limitation Act are inapplicable due to lack of due diligence and good faith.
Summary
M/s Suryachakra Power Corporation Ltd filed an appeal to the Supreme Court under Section 125 of the Electricity Act, 2003 against a decision of the Appellate Tribunal for Electricity. The appeal was filed 161 days after the Tribunal's order, exceeding the 60‑day statutory period and the additional 60‑day discretionary period permitted under the Act. The appellant sought condonation of the delay, invoking Section 5 of the Limitation Act, 1963 and the principles of Section 14, arguing that the delay was caused by a pending review petition and the Court’s summer vacations. The Court held that Section 125 imposes a strict 120‑day ceiling and that the Supreme Court cannot condone delay beyond the discretionary 60 days, nor can Section 5 be invoked to override this special limitation. It further found that the appellant failed to demonstrate due diligence and good faith, so the Section 14 exclusion did not apply. Consequently, the order condoning the delay was recalled and the appeal was dismissed for being filed out of time.
Issues considered
- Whether Section 5 of the Limitation Act, 1963 can be invoked to condone delay beyond the 120‑day period prescribed under Section 125 of the Electricity Act, 2003.
- Whether the Supreme Court may extend the discretionary condonation period beyond 60 days under Section 125 of the Electricity Act, 2003.
- Whether the principles of Section 14 of the Limitation Act, 1963 apply where the appellant alleges delay due to a pending review petition and court vacations.
- Whether the period of court closure can be excluded from the limitation period under the Limitation Act.
Legislation cited
- Electricity Act, 2003s. 125
- Limitation Act, 1963s. 14, s. 2(h), s. 5
Subjects
Judgment
[2016) 8 S.C.R. 108
A MIS. SURYACHAKRA POWER CORPORATION LIMITED
v.
ELECTRICITY DEPARTMENT, REP. BY ITS
SUPERINTENDING ENGINEER, PORT BLAIR AND OTHERS
B (Civil Appeal No. 5958of2015)
SEPTEMBER 22, 2016
[KUIUAN JOSEPH AND R. F. NARIMAN, JJ.]
Electricity Act, 2003 - s.125 - Special limitation period -
Applicability of s.5, Limitation Act, 1963 - Appeal before Supreme
c Court. beyond 120 days' limitation period uls. 125, Electricity Act -
Condonation ojdelay sought 011 the ground that the delay ll'as
mai11ly on account of time taken in prosecuti11g review petition before
the Appellate Tribunal for Electricity and also because <?[vacations
in Supreme Court - Held: Appeal u!s. 125 has to be .filed ll'ithi11 60
D days ji-0111 the date of com111z111icatio11 <~f decisio11 or order of the
Appellate Tribunal - A further period of 60 days may be allowed by
the Supreme Court, if sati.1fied that appellant wa.1· prevented by
szif}icient cause from filing the appeal - Thus, the maximum period
ll'ithin irhich an appeal can be filed uls. 125 is 120 days, including
discretion granted to the Supreme Court to condone the delay limited
E
to 60 days - Therefore, Supreme Court cannot condone the delay
beyond 60 days by invoking s.5 <d' Limitation Act, ignoring the
special limitation prescribed u11der the Electricity Act. 2003 -
Furthe1; Ihere ll'ere fe11• days leji be.fore tlw d11si11g o/ thi.1· Court .for
swnmer vacations, for the appellant to jile the appeal, therej(1re
F appellant not entitled even to be11ejit of pri11ciples uls ../. Limitation
Act, 1963 j(1r exclusio11 ~f the period il'hen court is closed -
Limitation Act, 1963.
Limitation Act, 1963:
s.l./ - Exclusio11 of time o.f prosecuting the case bonatide in
G Court 1101 having j11risdictio11 - E111itleme111 - Held: The lll'o main
ingredients j(1r al/racting s.1-1 are (i) prosecution of another civil
proceedings with due diligence (ii) such prosecutio11 has to be in
good faith - In the .facts of the present case there was lack of good
faith and 110 due diligence 011 the part ~f appellant in conducting
H
108
MIS. SURYACHAKRAPOWERCORP. LTD. v. 109
ELECTRICITY DEPT., REP. BY ITS S.E., PORT BLAIR
its case - Therefore, appellant 11ot entitled to benefit u/s.14 - Delay/ A
!aches.
Applicability of s.14 when s.5 1101 applicable - Held: Principles
under s.14 can be applied even whe11 s.5 is 1101 applicable.
Dismissing the appeal on the ground of delay, the Court
B
HELD:l.1 The review petition was filed on 25.02.2015
beyond the period of limitation of 30 days. After the dismissal of
the review petition on 07.05.2015, the instant appeal was filed
b1<fore this Court on 07.07.2015. It is stated in the application
that the delay mainly occurred on account of time taken by the
appellant in prosecuting a review petition before the Appellate c
Tribunal for Electricity and also because of the summer vacations,
and thus, there is a total delay of 161 days. [Paras 2, 3][41-D,E)
1.2 The appeal under Section 125 of the Electricity Act,
· 2003 in Supreme Court has to be filed within 60 days from the
date of communication of the decision or order of the Appellate D
Tribunal. llowevei·, the Supreme Court, if it is satisfied that the
appellant was prevented by sufficient cause from filing an appeal
within the said period of 60 days, may allow it to be filed within a
further period not exceeding 60 days. Thus, the maximum period
within which an appeal can be filed under Section 125 is 120 days E
which includes the discretion granted to the Supreme Court to
condone the delay limited to 60 days. The Supreme Court cannot
condone the delay beyond 60 days by invoking Section 5 of the
Limitation Act, 1963 and ignoring the special limitation prescribed
under the Electricity Act, 2003. [Para 5)[112-D-C]
F
Chhattisgarh State Electricity Board v. Ce11tral
Electricity Regulatory Commissio11 and others (2010) 5
SCC 23 : 2010 (4) SCR 680 - relied on.
2.1 As regards the prayer that the application may be
considered in terms of the principles under Section 14 of the G
Limitation Act, 1963. The two main ingredients required for
attracting the principles under Section 14 of the Limitation Act,
1963 are that the party should be prosecutin.g another civil
proceedings with due diligence and that the prosecution should
be in good faith. It is not enough that one part is satisfied. Both
H
110 SUPREME COURT REPORTS [2016] 8 S.C.R.
A due diligence and good faith must be established. (Paras 6, 8)(112-
F; 113-G-H]
M.P. Steel Corporation v. Commissioner of Central
Excise (2015) 7 SCC 58 - relied on.
2.2 In the present case, after obtaining the certified copy
B of the order on 17.12.2014, the review petition was filed only on
25.02.2015, delayed by 37 days. Even after withdrawal of the
review petition on 07.05.2015, the appeal was filed before this
Court only on 07.07.2015. This Court closed for summer
vacations in the year 2015 only on 16.05.2015 and reopened on
c 01.07.2015. Thus, there were few days left, before the closing of
the Court for summer vacations, for the appellant to file the appeal
after withdrawal of the review petition. The appeal was filed only
after a few days of the reopening of the Court on 01.07.2015.
Therefore, the appellant is not entitled even to the benefit of the
principles under Section 4 of' the Limitation Act, 1963 for exclusion
D of the period when court is closed. Merely because the Tribunal
condoned the delay in filing the review petition, for the purpose
of application of Section 14 before this Court for exclusion of the
period, in the facts of the present case, it cannot be said that
there was due diligence. Under Section 2(h) of the Limitation
E Act, 1963, nothing shall be deemed to be done in good faith which
is not done with due care and attention. The facts of the present
case would also show lack of good faith on the part of the appellant
in conducting its case. Thus, the appellant having not prosecuted
his case with due diligence and good faith is not entitled for the
application of the principles under Section 14 of the Limitation
F Act, 1963. (Para 9] [114-A-D]
Case Law Reference
2010 (4) SCR 680 relied on Para5
(2015) 1 sec 58 relied on Para 7
G
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 5958
of2015.
From the Judgment and Order dated 28.11.2014 of the Appellate
Tribunal for Electricity at New Delhi in Appeal No. 200of2013.
H Rakesh Khanna, Sr. Adv., Ms. Ruchi Singhwani, Mohit Paul,
MIS. SURYACHAKRAPOWERCORP. LTD. v. 111
ELECTRICITY DEPT., REP. BY ITS S.E., PORT BLAIR
Ms. Megha Bharara, Vikash Arora, Ms. Diksha Jhingan, Advs. for the A
Appellants.
Gurukrishna Kumar, Sr. Adv., Rohit Rao N., Mukund P. Unny,
Ananga Bhattacharyya, Advs. for the Respondent.
The Judgment of the Court was delivered by
B
KURIAN, J. I. This appeal is filed under Section I 25 of the
Electricity Act, 2003. Interlocutory Application No. I of 20 I 5 is for
con donation of 161 days' delay in filing the appeal. The main ground in
the application is that the delay occurred on account of the time taken by
the appellant in prosecuting a review petition before the Appellate Tribunal
for Electricity. c
2. lt is seen from the application for condonation of delay that the
original order of the Appellate Tribunal was passed on 28.11.2014. A
certified copy of the order was obtained on 17.12.2014. Review petition
was filed on 25.02.2015 beyond the period oflimitation of30 days. We
are informed that the Appellate Tribunal had condoned the delay and D
entertained the review petition.
3. Be that as it may, on 07.05.2015, the review petition was
dismissed as withdrawn. According to the appellant and as stated in the
application for condonation of delay before this Court, the review petition
was withdrawn with a view to filing the present appeal before this Court. E
After the dismissal of the review petition on 07.05.2015, the present
appeal is filed before this Court on 07.07.2015. It is stated in the application
that the delay occurred on account of the summer vacatio'ns, and thus,
there is a total delay of 161 days.
4. Section 125 of the Electricity Act, 2003 provides for appeals to F
the Supreme Court of India. The provision reads as follows:
"125. Appeal to Su11reme Court.-Any person aggrieved
by any decision or order of the Appellate Tribunal, may,
file an appeal to the Supreme Court within sixty days from
the date of communication of the decision or order of the G
Appellate Tribunal, to him, on any one or more of the
grounds specified in section 100 of the Code of Civil
Procedure, 1908 (5 of 1908):
Provided that the Supreme Court may, if it is satisfied that
the appellant was prevented by sufficient cause from filing
H
112 SUPREME COURT REPORTS [2016] 8 S.C.R.
A the appeal within the said period, allow it to be filed within
a further period not exceeding sixty days."
5. The appeal under Section 125 of the Electricity Act, 2003 in
Supreme Court has to be filed within 60 days from the date of
communication of the decision or order of the Appellate Tribunal.
B However, the Supreme Court, if it is satisfied that the appellant was
prevented by sufficient cause from filing an appeal within the said period
of 60 days, may allow it to be filed within a further period not exceeding
60 days. Thus, the maximum period within which an appeal can be filed
under Section 125 is 120 days which includes the discretion granted to
the Supreme Court to condone the delay limited to 60 days. The Supreme
c Court cannot condone the delay beyond 60 days by invoking Section 5
of the Limitation Act, 1963 and ignoring the special limitation prescribed
under the Electricity Act, 2003. This Court, in Chhattisgarh State
Electricity Board v. Central Electricity Regulatory Commission
and others', at paragraph-32, has settled this issue:
D "32. In view of the above discussion, we hold that Section
5 of the Limitation Act cannot be invoked by this Court for
entertaining an appeal filed against the decision or order of
the Tribunal beyond the period of 120 days specified in
Section 125 of the Electricity Act and its proviso. Any
interpretation of Section 125 of the Electricity Act which
E may attract the applicability of Section 5 of the Limitation
Act read with Section 29(2) thereof will defeat the object
of the legislation, namely, to provide special limitation for
filing an appeal against the decision or order of the Tribunal
and proviso to Section 125 will become nugatory."
F 6. Learned Senior Counsel at this juncture prays that the
application may be considered in terms of the principles under Section
14 of the Limitation Act, 1963. Section 14 of the Limitation Act, 1963
reads as follows:
"14. Exclusion of time of proceeding bona fide in court
without jurisdiction.- (1) In computing the period of
G
limitation for any suit the time during which the plaintiff has
been prosecuting with due diligence another civil proceeding,
whether in a court of first instance or of appeal or revision,
against the defendant shall be excluded, where the
proceeding relates to the same matter in issue and is
H 1
(2010) s sec 23
MIS. SURYACHAKRAPOWERCORP. LTD. v. 113
ELECTRICITY DEPT., REP. BY ITS S.E., PORT BLAIR [KURIAN, J.)
prosecuted in good faith in a court which, from defect of A
jurisdiction or other cause of a like nature, is unable to
entertain it.
(2) In computing the period oflimitation for any application,
the time during which the applicant has been prosecuting
with due diligence another civil proceeding, whether in a
B
co mt of first instance or of app'eal or revision, against the
same party for the same relief shall be excluded, where
such proceeding is prosecuted in good faith in a court which,
from defect ofjurisdiction or other cause of a like nature, is
unable to entertain it.
(3) Notwithstanding anything contained in rule 2 of Order c
XXIII of the Code of Civil Procedure, 1908 (5of1908), the
provisions of sub-section (I) shall apply in relation to a fresh
suit instituted on pennission granted by the court under rule
I of that Order where such permission is granted on the
ground that the first suit must fail by reason of a defect in
D
the jurisdiction of the court or other cause of a like nature.
Explanation.- For the purposes of this section,-
(a) in excluding the time during which a former civil
proceeding was pending, the day on which that proceeding
was instituted and the day on which it ended shall both be E
counted;
(b) a plaintiff or an applicant resisting an appeal shall be
deemed to be prosecuting a proceeding;
(c) misjoinder of parties or of causes of action shall be
deemed to be a cause of a like nature with defect of
F
jurisdiction."
7. That the principles under Section 14 of the Limitation Act, 1963
can be applied even when Section 5 of the Act is not applicable, is no
more res integra, in view ofM.P. Steel Corporation v. Commissioner
of Central Excise 2 •
G
8. The two main ingredients required for attracting the principles
under Section 14 of the Limitation Act, 1963 are that the paity should be
prosecuting another civil proceedings with due diligence and that the
prosecution should be in good faith. It is not enough that one part is
satisfied. Both due diligence and good faith must be established.
' (20I5J 1 sec 58 H
114 SUPREME COURT REPORTS [2016] 8 S.C.R.
A 9. In the case before us, after obtaining the certified copy of the
order on 17.12.2014, the review petition was filed only on 25.02.2015,
delayed by 37 days. Even after withdrawal of the review petition on
07.05.2015, the appeal was filed before this Court only on 07.07.2015.
This Court closed for summer vacations in the year 2015 only on
16.05.2015 and reopened on 01.07.2015. Thus, there were few days
B
left, before the closing of the Court for summer vacations, for the
appellant to file the appeal after withdrawal of the review petition. The
appeal was filed only after a few days of the reopening of the Court on
01.07.2015. Therefore, the appellant is not entitled even to the benefit of
the principles under Section 4 of the Limitation Act, 1963 for exclusion
c of the period when court is closed. Merely because the Tribunal condoned
the delay in filing the review petition, for the purpose of application of
Section 14 before this Court for exclusion of the period, in the facts of
the present case, it cannot be said that there was due diligence. Under
Section 2(h) of the Limitation Act, 1963, nothing shall be deemed to be
done in good faith which is not done with due care and attention. The
0
facts as narrated above would also show lack of good faith on the pa11
of the appellant in conducting its case. Thus, the appellant having not
prosecuted his case with due diligence and good faith is not entitled for
the application of the principles under Section 14 of the Limitation Act,
1963.
E 10. By order dated 03.08.2015, it is seen that this Cou11 had
condoned the delay without noticing the bar under Section 125 of the
Electricity Act, 2003 for condoning delay beyond 60 days after expiry of
the limitation period. Therefore, the order dated 03.08.2015 condoning
the delay of 161 days in filing the appeal is recalled.Since, the Supreme
F Court cannot condone the delay beyond 60 days under Section 125 of
the Electricity Act, 2003, and in the facts of the present case, since the
principles of Section 14 of the Limitation Act, 1963 are not attracted,
Interlocutory Application No. I of 2015 for con donation of delay is
dismissed. Consequently, the appeal is also dismissed on the ground of
delay.
G
11. There shall be no order as to costs.
Divya Pandey Appeal dismissed.
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.