M/S SUNDEW PROPERTIES LIMITEDversusTELANGANA STATE ELECTRICITY REGULATORY COMMISSION & ANR.
- Citation
- 2024 INSC 439
- Decided
- 17 May 2024
- Disposal
- Case Partly allowed
- Bench
- SANJIV KHANNA
Holding
A SEZ developer, even after being recognised as a deemed distribution licensee, is exempt from regulation 12 and the capital‑adequacy condition of rule 3(2) of the 2005 Rules; thus the condition imposed by TSERC is invalid.
Summary
The appellant, Sundew Properties Ltd., was notified by the Ministry of Commerce & Industry as a developer of a Special Economic Zone (SEZ) and claimed that, under the 2010 Notification inserting a proviso to section 14(b) of the Electricity Act, it automatically became a deemed distribution licensee without needing to apply for a licence. The Telangana State Electricity Regulatory Commission (TSERC) granted deemed licence status but conditioned it on the appellant complying with rule 3(2) of the 2005 Capital Adequacy Rules, i.e., infusing additional capital of Rs 26.90 crore, invoking regulation 12 of the 2013 Regulations. The appellant challenged this condition before the Appellate Tribunal for Electricity and the Supreme Court, arguing that SEZ developers are exempt from such requirements and that regulation 12 applies only to regular applicants, not deemed licensees. The Court held that SEZ developer status does not ipso facto confer deemed licence without an application, but once recognised as a deemed licence, the entity is exempt from regulation 12 and the capital‑infusion condition is ultra vires. Consequently, the Court set aside the TSERC and APTEL orders to the extent they imposed the additional capital condition, modifying the TSERC order to remove that condition. The appeal was partly allowed and no costs were awarded.
Issues considered
- Whether the designation of an entity as a SEZ developer ipso facto qualifies it to be a deemed distribution licensee, obviating the need for an application under section 14 of the Electricity Act.
- Whether regulation 12 of the 2013 Regulations, and by implication rule 3(2) of the 2005 Rules, are applicable to a SEZ developer recognised as a deemed distribution licensee.
Legislation cited
- Andhra Pradesh Electricity Regulatory Commission (Distribution Licence) Regulations, 2013s. Regulation 12, s. Regulation 13, s. Regulation 2(i)(h), s. Regulation 49
- Andhra Pradesh Reorganisation Act, 2014
- Distribution of Electricity Licence (Additional Requirements of Capital Adequacy, Creditworthiness and Code of Conduct) Rules, 2005s. Rule 3(2)
- Electricity Act, 2003s. 14, s. 14(b) proviso, s. 15, s. 16, s. 175, s. 176, s. 177, s. 181, s. 49
- Special Economic Zones Act, 2005s. 3, s. 4, s. 49(1)
Subjects
Judgment
[2024] 5 S.C.R. 739 : 2024 INSC 439
M/s Sundew Properties Limited
v.
Telangana State Electricity Regulatory Commission & Anr.
(Civil Appeal No. 8978 of 2019)
17 May 2024
[Sanjiv Khanna and Dipankar Datta,* JJ.]
Issue for Consideration
Whether the designation of an entity as a Special Economic Zone-
developer ipso facto qualifies the entity to be a deemed distribution
licensee, obviating the need for an application u/s. 14 of the
Electricity Act; whether Regn 12 of the Andhra Pradesh Electricity
Regulatory Commission (Distribution Licence) Regulations, 2013,
and by implication r. 3(2) of the Distribution of Electricity Licence
(Additional Requirements of Capital Adequacy, Creditworthiness and
Code of Conduct) Rules, 2005 are applicable to a SEZ developer
recognised as a deemed distribution licensee under the proviso to s.
14(b) read with Regn 13 of the 2013 Regulations; and whether the
condition imposed by the State Electricity Regulatory Commission
to infuse additional capital as per r. 3(2) of the 2005 Rules read
with Regn 12 of the 2013 Regulations, justifiable or extraneous.
Headnotes†
Electricity Act, 2003 – s. 14(b) proviso – Distribution of
Electricity Licence (Additional Requirements of Capital
Adequacy, Creditworthiness and Code of Conduct) Rules,
2005 – r. 3(2) – Andhra Pradesh Electricity Regulatory
Commission (Distribution Licence) Regulations, 2013 – Regns
12, 13 – Application for grant of Distribution Licence in the
area of supply of an existing Distribution Licensee – Procedure
to get identified as deemed distribution licensee – On facts,
designation of an entity-appellant as a Special Economic
Zone-SEZ developer by the Ministry – Appellant, if ipso facto
qualifies the entity to be a deemed distribution licensee,
obviating the need for an application u/s. 14 – Regn 12 of the
2013 Regulations and by implication r. 3(2) of the 2005 Rules,
if applicable to a SEZ developer recognised as a deemed
distribution licensee under the proviso to s. 14(b) read with
Regn 13 of the 2013 Regulations – Condition imposed by the
* Author
740 [2024] 5 S.C.R.
Digital Supreme Court Reports
State Electricity Regulatory Commission to infuse additional
capital as per r. 3(2) of the 2005 Rules read with Regn 12 of
the 2013 Regulations, if justifiable or extraneous:
Held: Being a SEZ developer in terms of the 2010 Notification
does not ipso facto confer upon the appellant the status of a
deemed licensee without any scrutiny and without being under
any requirement to apply – It is required to make an application in
accordance with the 2013 Regulations – This condition has been
fulfilled as the status of the appellant as a deemed licensee was
upheld pursuant to the application made in accordance with r. 13
of the 2013 Regulations – As regards the applicability of Regn 12
of the 2013 Regulations and r. 3(2) of the 2005 Rules, none of the
nine provisos to s. 14, apply to the appellant – Sixth proviso to s.
14 does not pertain to deemed licensees and, thus, the 2005 Rules
not applicable to the appellant – Furthermore, it cannot be said that
Regn 12 applies implicitly to a deemed licensee as well – Regn
12 pertains solely to regular distribution licensees not to deemed
licensees – ‘Reading up’ Regn 12 so as to expand its ambit to include
within it deemed licensees, especially when the Electricity Act does
not stipulate any such inclusion, runs counter to proviso to clause
(b) of s. 14 of the Electricity Act, which is impermissible and cannot
be approved – Thus, the recognition of the status of a deemed
distribution licensee cannot hinge on compliance with r. 3(2) of the
2005 Rules read with Regn 12 of the 2013 Regulations – Having
been statutorily exempted from complying with Regns 4 to 11, the
appellant, being a deemed licensee, would also be exempt from
the concomitant obligation of complying with Regn 12 – Condition
imposed on appellant to infuse an additional capital, not justified
and contrary to the statutory scheme – Judgments and orders of
the State Electricity Regulatory Commission and the Appellate
Tribunal for Electricity set aside to this extent – Order of the State
Electricity Regulatory Commission granting the status of a deemed
licensee to the appellant, subject to the condition that its promoters
infuse additional capital modified to the extent of excluding such
condition. [Paras 25, 37, 28, 29, 34, 35, 37]
Interpretation of statutes – Principles of statutory interpretation –
Reading down and reading up:
Held: Reading down and reading up are two principles in the
realm of statutory interpretation – Reading down refers to the
practice of interpreting a statute narrowly, limiting its scope or
[2024] 5 S.C.R. 741
M/s Sundew Properties Limited v. Telangana State
Electricity Regulatory Commission & Anr.
application to specific situations or individuals – This approach is
commonly employed when the language of a statute is ambiguous
or when there is a need to avoid potential conflicts with other laws
or constitutional provisions – If a law is unclear about whether
it applies to certain types of businesses, a court may choose to
read down the statute to only include those businesses explicitly
mentioned in the text – Reading up involves interpreting a
statute broadly, extending its scope or application beyond what
is expressly stated in the text – Reading up is a concept that is
invoked with great caution within the legal framework because
it can lead to judicial activism or judicial overreach – Practice of
reading up a provision can only be justified when it aligns with
legislative intent, maintains the fundamental character of the law,
and ensures that the resulting interpretation remains consistent
with the original context to which the law applies – This holds
especially true for subordinate legislation, which require greater
scrutiny – Reading up a provision of subordinate legislation in
a manner that it militates against the primary legislation not
permissible. [Paras 30, 32]
Legislation – Enabling/primary legislation and subordinate
legislation – Harmonization between – Requirement:
Held: Authority to enact subordinate legislation is derived from the
enabling/primary legislation and it is imperative that such legislation
harmonizes with the provisions outlined in the primary legislation –
Electricity Act has conferred power on the Central Government to
make Rules and on the Central Electricity Authority and the Central
Commission to make Regulations – All such rules/regulations are
to be made consistent with the Electricity Act – Rules/Regulations
are enacted to supplement the main provision, not to supplant
it – They serve the crucial role of bridging potential gaps within
the primary legislation, yet, their function is not to create webs
and voids merely to clog and hamper their implementation – Any
gaps addressed by Rules/Regulations must be discernible within
the framework of primary legislation. [Para 33]
Case Law Cited
Sesa Sterlite Limited. v. Orissa Electricity Regulatory Commission
and Others [2014] 13 SCR 426 : (2014) 8 SCC 444; State of
Bombay v. Pandurang Vinayak Chaphalkar [1953] 1 SCR 773 :
(1953) 1 SCC 425; B.R. Kapur v. State of Tamil Nadu [2001] Supp.
3 SCR 191 : (2001) 7 SCC 231 – referred to.
742 [2024] 5 S.C.R.
Digital Supreme Court Reports
List of Acts
Electricity Act, 2003; Special Economic Zones Act, 2005; Andhra
Pradesh Electricity Regulatory Commission (Distribution Licence)
Regulations, 2013; Andhra Pradesh Reorganisation Act, 2014;
Distribution of Electricity Licence (Additional Requirements of Capital
Adequacy, Creditworthiness and Code of Conduct) Rules, 2005.
List of Keywords
Designation of entity; SEZ developer; Deemed distribution licensee;
Condition to infuse additional capital; 2010 Notification; Deemed
licensee status; Lack of specificity; Legislative intent; Deemed
licence; Reading up’; Reading down; Statutory interpretation;
Primary legislation; Subordinate legislation.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 8978 of 2019
From the Judgment and Order dated 27.09.2019 of the Appellate
Tribunal for Electricity, New Delhi in Appeal No. 03 of 2017
Appearances for Parties
Maninder Singh, Sr. Adv., Mahesh Agarwal, Rishi Agrawala,, Ms.
S. Lakshim Iyer, Ms. Anwesha Padhi, Abhishek Munot, Kunal Kaul,
Samikrith Rao Puskuri, Ms. Ashita Chawla, Amarpal Singh Dua, E.C.
Agrawala, Advs. for the Appellant.
C.S. Vaidyanathan, Sr. Adv., Somanadri Goud Katam, Sirajuddin,
D. Abhinav Rao, Vinayak Goel, Gunnalan, Nitish Raj, Rahul Jajoo,
Devadipta Das, Ms. Prerna Robin, Advs. for the Respondents.
Judgment / Order of the Supreme Court
Judgment
Dipankar Datta, J.
THE CHALLENGE
1. This is a statutory appeal before us under section 125 of the Indian
Electricity Act, 20031. It registers a challenge to the judgment and
1 Electricity Act
[2024] 5 S.C.R. 743
M/s Sundew Properties Limited v. Telangana State
Electricity Regulatory Commission & Anr.
order dated 27th September, 2019 passed by the Appellate Tribunal
for Electricity2 dismissing an appeal carried under section 111 of the
Electricity Act by the appellant from the judgment and order dated 15th
February, 2016 passed by the Telangana State Electricity Regulatory
Commission3. Consequently, the impugned judgment and order of
the TSERC was upheld.
BRIEF FACTS
2. The basic facts giving rise to this appeal are not disputed. A brief
overview of the facts and the trajectory of proceedings, relevant for
a decision on the present appeal, are set out hereunder:
a) The appellant was notified by the Ministry of Commerce &
Industry (Department of Commerce), Government of India4 as a
‘Developer’, in terms of sections 3 and 4 of the Special Economic
Zones Act, 20055, to establish a sector-specific Special Economic
Zone6 unit for Information Technology/Information Technology
Enabled Services sector in Madhapur, Ranga Reddy District,
Hyderabad, in the former State of Andhra Pradesh.
b) MoCI, vide a Notification bearing No.SO 528(E) dated 3rd March,
20107 introduced a proviso to section 14(b) of the Electricity
Act. The proviso accords upon the developer of a SEZ, the
status of a deemed distribution licensee under the provisions
of the Electricity Act.
c) Pursuant to the 2010 Notification, the appellant filed an
application8 before the erstwhile Andhra Pradesh Electricity
Regulatory Commission seeking identification as a deemed
distribution licensee, in terms of the proviso to section 14(b) of
the Electricity Act read with regulation 13 and Schedule-2 of the
Andhra Pradesh Electricity Regulatory Commission (Distribution
Licence) Regulations, 20139 and section 49 of the SEZ Act.
2 APTEL
3 TSERC
4 MoCI
5 SEZ Act
6 SEZ
7 2010 Notification
8 O.P. No. 10 of 2015
9 2013 Regulations
744 [2024] 5 S.C.R.
Digital Supreme Court Reports
Upon the Andhra Pradesh Reorganisation Act, 2014 coming
into force, the application was transferred to the TSERC.
d) By its aforesaid judgment and order dated 15th February, 2016,
the TSERC identified and accorded the status of a deemed
licensee to the appellant. However, this grant of status was
made conditional upon the appellant satisfying the requirements
stipulated in rule 3 of the Distribution of Electricity Licence
(Additional Requirements of Capital Adequacy, Creditworthiness
and Code of Conduct) Rules, 200510, compliance whereof was
mandatory per regulation 12 [which stipulates that an applicant
for grant of distribution licence shall, in addition to regulations
4 to 11, comply with the 2005 Rules] read with regulation 49
of the 2013 Regulations [which stipulates that all the general
conditions applicable to a distribution licensee are also equally
applicable to a deemed licensee]. The appellant was, therefore,
directed to infuse an additional capital of Rs. 26.90 crore as
equity share capital, contributed by its promoters, into its power
distribution business via account payee cheques by 31st March,
2016. The relevant part of the judgment and order of the TSERC
is extracted hereunder:
“16. […] On a close reading of the provisions of
section 14, we are of the view that the ‘provisos’ to
section 14 are not applicable to a deemed licensee.
The status of a deemed licence to a person under
Section 14(b) of the Electricity Act, 2003 emanates
from the Notification given under Section 49(1) of the
SEZ Act to a developer of SEZ provided the deemed
Licensee satisfies the other provisions of the Act.
[…]
18. We are of the view that the provisions contained
in sub-section (2), (3), (4), (5) & (6) of Section 15
of the Act are not applicable to a deemed licensee.
Moreover, [A.P. Distribution Licence Regulations]
contains the Rules relating to procedure for granting
of a distribution licensee from Rules 4 to 11 […]
10 2005 Rules
[2024] 5 S.C.R. 745
M/s Sundew Properties Limited v. Telangana State
Electricity Regulatory Commission & Anr.
The Rule 13 of the Regulation stipulates that Rules
contained in 4 to 11 are not applicable to a deemed
licensee and these Rules contain the procedure for
granting of a distribution licence to a person. […]
19. The Rule 13 of the [A.P. Distribution Licence
Regulations] stipulates that a deemed licensee shall
make an application in the form specified in Schedule
- 2 to the Commission to get identified as a deemed
licensee and rules 4 to 11 in the Regulations are not
applicable to a deemed licensee, Thus, the Rule
13 […] has excluded the application of Rules laid
down from Rules 4 to 11 […] As observed earlier, the
Rules 4 to 11 basically deal with the procedure to be
followed by a person for obtaining a licence from the
Commission. By implication, Rule 12 is applicable to
a deemed licensee also […]
20. We are not able to appreciate the argument
of the petitioner that Rule 12 is not applicable to a
deemed licensee. In our view, Rule 49 stipulates that
all the general conditions applicable to a distribution
licensee are also equally applicable to a deemed
licensee. Thus, in our view, the Rule 12 is applicable
to the petitioner.
21. The next issue that arises is whether the petitioner
has complied with the provisions of Rule 12? […] As
a stand-alone entity the petitioner does riot fulfil the.
conditions laid down in Rule 3 of the Capital Adequacy
Rules. However, the Rule 3(2) also stipulates that
the net worth of the promoters of the petitioner can
be considered for the purpose of computation of the
Debt Equity ratio of 30:70 […].
26(A). The [Commission], in exercise of the powers
conferred under Section 14 (b) of the Electricity
Act, hereby identifies and recognises M/s. Sundew
Properties Ltd. […] as a deemed licensee.
26(D). […] the promoters have to contribute 30% of
the total anticipated investment of Rs. 89.53 Crores
746 [2024] 5 S.C.R.
Digital Supreme Court Reports
which works out to Rs.26.9 Crores on or before
31.03.2016.”
e) Aggrieved, the appellant carried an appeal11 from the aforesaid
order of the TSERC to the APTEL. According to the appellant,
the directions of the TSERC were in excess of jurisdiction.
APTEL dismissed the appeal, as noticed above. It held that the
TSERC was justified in ordering infusion of additional equity
by the appellant to the tune of Rs.26.90 crore (being 30% of
the total anticipated investment of Rs.89.53 crore) as a pre-
condition for being identified as a deemed distribution licence.
The operative part of the judgment and order passed by the
APTEL reads as follows:
“8.14 […] while the Appellant is not required to apply
for grant of license but being a deemed distribution
licensee has to fulfil other technical and financial
requirements as per prevailing rules and regulations of
the State Commission which is mandated to regulate
the Electricity business in the state whether it is a
DISCOM or any other deemed distribution licensee
as in the present case. Accordingly, we are of the
opinion that the State Commission has passed the
impugned order with careful consideration and proper
interpretation of the statute and also considering the
judgments passed by Hon’ble Supreme Court in Sesa
Sterilite [sic] case (supra) […]”
f) It is this judgment and final order that the appellant has subjected
to challenge in this statutory appeal by invoking the appellate
jurisdiction of this Court under section 125 of the Electricity Act.
SUBMISSIONS
3. Mr. Singh, learned senior counsel appearing for the appellant,
challenged the validity of the orders of the TSERC and the APTEL
by advancing the following submissions:
a) The TSERC and the APTEL erred in failing to recognize that
under section 14(b) of the Electricity Act, a developer of an SEZ
is ipso facto and unconditionally deemed to be a distribution
11 Appeal No.3 of 2017
[2024] 5 S.C.R. 747
M/s Sundew Properties Limited v. Telangana State
Electricity Regulatory Commission & Anr.
licensee, thus eliminating the need for a separate licence
application. Recognition of the status of a deemed distribution
licensee is a ministerial act, effected automatically upon
fulfilment of conditions laid down in the SEZ Act, independent
of rule 3(2) of the 2005 Rules read with regulation 12 of the
2013 Regulations.
b) The status of deemed distribution licensee stands bestowed
upon the appellant by virtue of the 2010 Notification, requiring no
further action. This position has been recognized and approved
by both the TSERC and the APTEL.
c) Under the 2013 Regulations, there are two types of licensees:
first, those who apply for a distribution licence under regulations
2(d) and 12, and secondly, those already deemed licensees,
seeking recognition of their status as such, under regulations
2(h) and 13. The appellant belongs to the latter category.
d) Regulation 12 of the 2013 Regulations applies to general
applicants seeking a distribution licence, mandating compliance
with both the 2005 Rules and the procedures prescribed in
regulations 4 to 11. It cannot apply to a deemed licensee under
regulation 13. The TSERC’s finding, as approved by the APTEL,
that the 2005 Rules are in-built into the 2013 Regulations and
therefore have to be satisfied by the appellant because of implied
application of regulation 12 to deemed licensees, is contrary
to the provisions of the Electricity Act and the very scheme of
the 2013 Regulations.
e) APTEL erred by agreeing with the TSERC’s reasoning that the
requirement to infuse Rs. 26.90 crore in equity was imposed
on the appellant under section 16 of the Electricity Act, despite
recognising the appellant as a deemed distribution licensee.
Conditions under section 16, whether general or specific, must
be ‘specified’ by the Appropriate Commission through regulations
according to section 2(62) of the Electricity Act.
4. Resting on the aforesaid submissions, learned senior counsel urged
this Court to allow the appeal and set-aside the orders of the TSERC
and the APTEL to the extent requiring the appellant to comply with
the conditions stipulated in rule 3 of the 2005 Rules and infuse
additional capital to gain the status of a deemed licensee.
748 [2024] 5 S.C.R.
Digital Supreme Court Reports
5. Per contra, Mr. Vaidyanathan, learned senior counsel appearing for
the second respondent (Southern Power Distribution Company of
Telangana Limited), joined by Mr. Goud, learned counsel appearing
for respondent no. 1 (TSERC), supported the impugned judgment
and order and advanced the following submissions:
a) No doubt, the appellant, a SEZ developer, may be granted the
status of a deemed licensee; however, the 2005 Rules and the
2013 Regulations will be applicable to the appellant as per the
law laid down by this Court in Sesa Sterlite Limited. v. Orissa
Electricity Regulatory Commission and others12.
b) The appellant cannot be deemed to be a distribution licensee
on its own without making an application under regulation 13.
c) There is a necessity to harmoniously interpret the SEZ Act and
the Electricity Act to uphold the provisions of both enactments.
The appellant cannot argue that the 2005 Rules and the 2013
Regulations do not apply to it, being a SEZ developer.
d) TSERC is empowered to impose general and specific conditions
at its discretion. The purpose of requiring the appellant to infuse
an additional capital under the 2005 Rules was to assess the
credit-worthiness of the appellant as it had accumulated losses
at the end of the financial year 2013-2014 and more than 50%
of its net-worth has been wiped-out, a fact which is reflected
from the Statutory Auditor’s report.
6. No case for interference having been set up by the appellant, learned
counsel for respondents prayed for dismissal of the appeal.
STATUTORY FRAMEWORK
7. Before proceeding further, it is imperative to refer to certain statutory
provisions.
8. Section 14 of the Electricity Act deals with the grant of a licence:
“14. Grant of Licence – The Appropriate Commission
may, on an application made to it under section 15, grant
a licence to any person –
12 [2014] 13 SCR 426 : (2014) 8 SCC 444
[2024] 5 S.C.R. 749
M/s Sundew Properties Limited v. Telangana State
Electricity Regulatory Commission & Anr.
(a) to transmit electricity as a transmission licensee; or
(b) to distribute electricity as a distribution licensee; or
(c) to undertake trading in electricity as an electricity trader,
in any area as may be specified in the licence:
Provided that any person engaged in the business of
transmission or supply of electricity under the provisions
of the repealed laws or any Act specified in the Schedule
on or before the appointed date shall be deemed to be
a licensee under this Act for such period as may be
stipulated in the licence, clearance or approval granted
to him under the repealed laws or such Act specified in
the Schedule, and the provisions of the repealed laws
or such Act specified in the Schedule in respect of such
licence shall apply for a period of one year from the date
of commencement of this Act or such earlier period as
may be specified, at the request of the licensee, by the
Appropriate Commission and thereafter the provisions of
this Act shall apply to such business:
Provided further that the Central Transmission Utility or
the State Transmission Utility shall be deemed to be a
transmission licensee under this Act:
Provided also that in case an Appropriate Government
transmits electricity or distributes electricity or undertakes
trading in electricity, whether before or after the
commencement of this Act, such Government shall be
deemed to be a licensee under this Act, but shall not be
required to obtain a licence under this Act:
Provided also that the Damodar Valley Corporation,
established under sub-section (1) of section 3 of the
Damodar Valley Corporation Act, 1948, shall be deemed
to be a licensee under this Act but shall not be required
to obtain a licence under this Act and the provisions of the
Damodar Valley Corporation Act, 1948, in so far as they
are not inconsistent with the provisions of this Act, shall
continue to apply to that Corporation:
750 [2024] 5 S.C.R.
Digital Supreme Court Reports
Provided also that the Government company or the
company referred to in sub-section (2) of section 131 of this
Act and the company or companies created in pursuance
of the Acts specified in the Schedule, shall be deemed to
be a licensee under this Act:
Provided also that the Appropriate Commission may grant a
licence to two or more persons for distribution of electricity
through their own distribution system within the same
area, subject to the conditions that the applicant for grant
of licence within the same area shall, without prejudice
to the other conditions or requirements under this Act,
comply with the additional requirements [relating to the
capital adequacy, credit-worthiness, or code of conduct]
as may be prescribed by the Central Government, and no
such applicant, who complies with all the requirements for
grant of licence, shall be refused grant of licence on the
ground that there already exists a licensee in the same
area for the same purpose:
Provided also that in a case where a distribution licensee
proposes to undertake distribution of electricity for a
specified area within his area of supply through another
person, that person shall not be required to obtain any
separate licence from the concerned State Commission
and such distribution licensee shall be responsible for
distribution of electricity in his area of supply:
Provided also that where a person intends to generate
and distribute electricity in a rural area to be notified by
the State Government, such person shall not require any
licence for such generation and distribution of electricity,
but he shall comply with the measures which may be
specified by the Authority under section 53:
Provided also that a distribution licensee shall not require
a licence to undertake trading in electricity.”
9. To determine who qualifies as a deemed licensee under the Electricity
Act, we may refer to the 2013 Regulations.
10. Regulation 2(i)(h) of the 2013 Regulations defines “deemed licensee”
as follows:
[2024] 5 S.C.R. 751
M/s Sundew Properties Limited v. Telangana State
Electricity Regulatory Commission & Anr.
“(h) ‘Deemed Licensee’ means a person authorised under
sub-section (b) of Section 14 and also under the first,
second, third, and fifth provisos to section 14 of the Act
to operate and maintain a distribution system for supply
of electricity to the consumers in his area of supply.”
11. Regulation 13 of the 2013 Regulations stipulates the procedure to
get identified as a deemed distribution licensee. It reads:
“13. The deemed licensees shall make application in the
form specified in Schedule- 2 to the Commission to get
identified as the deemed Licensee. Provided that nothing
in Regulations 4 to 11 shall apply to deemed licensees.”
12. Insofar as a developer under the SEZ Act is concerned, a reference
may be made to the scheme of the SEZ Act to ascertain its status
as deemed distribution licensee.
13. The policy for SEZs was introduced with an objective to create a
competitive export environment and to attract foreign investment. It
levels the playing field for domestic businesses globally and introduces
favourable policies in investment, taxation, trade, customs, and labour
regulations. In line with this, for the purpose of ensuring consistent
and high-quality power supply to these SEZ units, the MoCI, vide
the 2010 Notification [under clause (b) of sub-section (1) of section
49 of the SEZ Act] has specified that the ‘developer’ of the SEZ
shall be deemed to be a ‘distribution licensee’ under the provisions
of the Electricity Act. The proviso inserted in clause (b) of section
14 of the Electricity Act, vide the 2010 Notification, reads as follows:
“Provided that the Developer of a Special Economic Zone
notified under sub-section (1) of Section 4 of the Special
Economic Zones Act, 2005, shall be deemed to be a
licensee for the purpose of this clause, with effect from
the date of notification of such Special Economic Zone.”
14. With the inclusion of the aforementioned proviso to section 14(b) of
the Electricity Act, it is evident that a SEZ developer is deemed to
be a distribution licensee.
15. The main contention of the parties that whether the TSERC imposed
condition to infuse additional capital per rule 3(2) of the 2005 Rules
read with regulation 12 of the 2013 Regulations is justifiable or
752 [2024] 5 S.C.R.
Digital Supreme Court Reports
extraneous is deliberated at length in a later part of this judgment.
Regulation 12 provides that a person applying for a grant of a
distribution licence shall, in addition to regulations 4 to 11, comply
with the 2005 Rules. Regulation 12 is extracted below:
“12. Application for grant of Distribution Licence in the
area of supply of an existing Distribution Licensee – A
person applying for grant of a licence for distribution of
electricity through his own distribution system within the
same area of supply of an existing Distribution Licensee
shall, in addition to the provisions of Regulation 4 to 11,
comply with “Distribution of Electricity Licence (additional
requirements of Capital Adequacy, Creditworthiness and
Code of Conduct) Rules, 2005” issued by the Central
Government.”
16. Rule 3 is extracted hereunder:
“3. Requirements of capital adequacy and
creditworthiness. –
(1) The Appropriate Commission shall, upon receipt of an
application for grant of licence for distribution of electricity
under sub-section (1) of section 15 of the Electricity Act,
2003, decide the requirement of capital investment for
distribution network after hearing the applicant and keeping
in view the size of the area of supply and the service
obligation within that area in terms of section 43.
(2) The applicant for grant of licence shall be required to
satisfy the Appropriate Commission that on a norm of 30%
equity on cost of investment as determined under sub-
rule (1), he including the promoters, in case the applicant
is a company, would be in a position to make available
resources for such equity of the project on the basis of net
worth and generation of internal resources of his business
including of promoters in the preceding three years after
excluding his other committed investments.”
ISSUES
17. Having noticed the relevant statutory framework, we are now tasked
with deciding two short issues:
[2024] 5 S.C.R. 753
M/s Sundew Properties Limited v. Telangana State
Electricity Regulatory Commission & Anr.
a) Whether the designation of an entity as a SEZ developer by the
MoCI ipso facto qualifies the entity to be a deemed distribution
licensee, obviating the need for an application under section
14 of the Electricity Act?
b) Whether regulation 12 of the 2013 Regulations, and by
implication rule 3(2) of the 2005 Rules, are applicable to a
SEZ developer recognised as a deemed distribution licensee
under the proviso to section 14(b) of the Electricity Act read
with regulation 13 of the 2013 Regulations?
ANALYSIS
18. We have considered the submissions advanced by learned counsel
for the parties and have also perused the materials on record.
Issue (a)
19. It would not be inapt to be reminded of what was stated by a Bench of
two Hon’ble Judges of this Court in State of Bombay v. Pandurang
Vinayak Chaphalkar13 nearly seventy years ago:
“11. […] When a statute enacts that something shall be
deemed to have been done, which in fact and truth was
not done, the court is entitled and bound to ascertain for
what purposes and between what persons the statutory
fiction is to be resorted to and full effect must be given to
the statutory fiction and it should be carried to its logical
conclusion.”
20. In view of the existing facts, we are inclined to the view that the
very purpose of the deeming fiction in the proviso to section 14(b)
of the Electricity Act is to confer upon an entity like the appellant a
status which is otherwise available in accordance with the Electricity
Act. In other words, as an effect of the 2010 Notification inserting
the proviso to section 14(b), the appellant is entitled to the privilege
of being acknowledged as a (deemed) distribution licensee under
the Electricity Act for supply of power within its SEZ area. Once the
appellant is a (deemed) distribution licensee, certain benefits and/
or privileges do enure in its favour.
13 [1953] 1 SCR 773 : (1953) 1 SCC 425
754 [2024] 5 S.C.R.
Digital Supreme Court Reports
21. The respondents have heavily relied on Sesa Sterlite Limited (supra)
to assert that there has to be a harmonious construction of both the
SEZ Act and the Electricity Act to give effect to the provisions of both
the enactments, so long as they are not inconsistent with each other.
22. A Bench of two Hon’ble Judges of this Court in Sesa Sterlite Limited
(supra) held:
“43. The reading of Section 49 of the SEZ Act would reveal
that the Central Government has got the authority to direct
that any of the provisions of a Central Act and the rules
and regulations made thereunder would not apply or to
declare that some of the provisions of the Central Acts
shall apply with exceptions, modifications and adaptation
to the special economic zone. So, under the scheme of
the Special Economic Zones Act, the Central Government
has to first notify as to what extent the provision of the
other Acts are to be made applicable or applicable with
modification or not applicable for the special economic zone
area. It is in furtherance thereto, the Government of India,
Ministry of Commerce and Industry through its Notification
dated 21-3-2012, with regard to power generation in special
economic zone, has declared that all the provisions of
the Electricity Act, 2003 and the Electricity Rules, 2005
shall be applicable to the generation, transmission and
distribution of power, whether stand-alone or captive power.
This notification would clarify that there is no inconsistency
between the Special Economic Zones Act, 2005 and the
Electricity Act, 2003.
[…]
46. To recapitulate briefly, in the present case no doubt
by virtue of the status of a developer in the SEZ area, the
appellant is also treated as deemed distribution licensee.
However with this, it only gets exemption from specifically
applying for licence under Section 14 of the Act.”
23. The question in Sesa Sterlite Limited (supra), was whether the
appellant - a deemed distribution licensee, being a developer of
Special Economic Zone (SEZ) and having a unit in the SEZ, is liable
to pay Cross-Subsidy Surcharge (CSS). It was held that the appellant
[2024] 5 S.C.R. 755
M/s Sundew Properties Limited v. Telangana State
Electricity Regulatory Commission & Anr.
would be liable to pay CSS for several reasons, including on the
facts that it was using dedicated transmission lines belonging to the
distribution licensee for the area in question. This Court interpreted
the expression ‘open access’ and the rationale behind CSS and
additional surcharge to observe that the former was payable by a
distribution licensee and the latter was to meet the fixed cost of the
distribution licensee of the area. The provision of open access, it is
observed, balances the right of the consumers to purchase from a
source of their choice. The rationale and the ratio of the decision,
therefore, is that a deemed distribution licensee is treated at par
and not different from a distribution licensee. Accordingly, if CSS is
payable by a distribution licensee, the deemed distribution licensee
is equally liable to pay the same. This decision, in other words,
equates deemed distribution licensee with the distribution licensee
for the purpose of supply of electricity to the consumers. Sesa
Sterlite Limited (supra) is not a decision for the proposition that
deemed distribution licensee, to qualify as a deemed distribution
licensee, must meet the criteria, including the capital requirements
as applicable by regulations to a distribution licensee.
24. Further, the provisos to section 14 of the Electricity Act distinguish
between entities that are ipso facto deemed distribution licensees and
those that are merely declared as deemed licensees without clarity
on the necessity of making an application to obtain a licence. For
instance, the third and fourth provisos to section 14 not only confer
the status of deemed licensees to the State Government and the
Damodar Valley Corporation, respectively, but also explicitly exempt
them from the requirement to obtain a licence. Entities not covered
by these specific provisos would, therefore, be required to obtain a
licence. The requirement of obtaining a license has to be read into
the other provisos to section 14 since, for instance, the second and
fifth provisos to section 14 grant deemed licensee status to Central/
State Transmission Utility and a government company, respectively,
but neither specifies the requirement to obtain a license nor exempts
them from obtaining license.
25. As far as the 2010 Notification is concerned, the proviso to section
14(b) introduced by the said Notification, confers deemed licensee
status on SEZ developers. However, such conferment does not
explicitly exclude the requirement of obtaining a licence. This lack
of specificity, especially when compared with the clear provisions for
756 [2024] 5 S.C.R.
Digital Supreme Court Reports
other entities, suggests that the legislative intent was not to ipso facto
grant SEZ developers the status of deemed distribution licensees,
thereby obliging them to obtain a licence by making an application in
terms of regulation 13. TSERC is, therefore, empowered to scrutinise
such applications in accordance with law, however, only limited to
the provisions which are applicable to deemed licensees. Verification
and acceptance recognise their status as deemed licensees.
Issue (b):
26. Issue (b) revolves around rule 3(2) of the 2005 Rules, which per
the TSERC and the APTEL, the appellant is bound to adhere by
infusing additional capital in order to qualify as a deemed licensee.
While the appellant contends that the 2010 Notification, by necessary
consequence, grants upon the appellant the status of a deemed
licensee, the respondents submit that the identification of the appellant
as a deemed distribution licensee is conditional upon the appellant
satisfying the other requirements of the Electricity Act, specifically
the sixth proviso to section 14 of the Electricity Act which provides
for compliance with additional requirements like capital adequacy
which as per the respondents includes rule 3 of the 2005 Rules read
with regulation 12 of the 2013 Regulations.
27. It is contended by the respondents that the application of 2005 Rules
to the appellant, a SEZ developer, stems from the sixth proviso to
section 14 read with regulation 12 of the 2013 Regulations.
28. Let us now deal with the provisos to section 14. Upon a bare reading
of the provision, it becomes crystal clear that not only does the sixth
proviso, but none of the nine provisos to section 14, apply to the
appellant, a SEZ developer. Even the TSERC and the APTEL are
ad idem with this view. The status of a SEZ developer as a deemed
licensee emanates from the 2010 Notification, which introduced the
proviso to section 14(b), conferring deemed licensee status to SEZ
developers. Reading anything beyond this would defeat the very
purpose of the proviso and the concept of the deemed licence. The
sixth proviso does not pertain to deemed licensees and, therefore,
the 2005 Rules are not applicable to the appellant.
29. Upon closer examination of regulation 12, it becomes apparent
that its application does not extend to applicants who are otherwise
deemed licensees. The interpretation of regulation 12 as requiring
[2024] 5 S.C.R. 757
M/s Sundew Properties Limited v. Telangana State
Electricity Regulatory Commission & Anr.
additional capital infusion for an applicant for acceptance of a deemed
licensee status appears to be at odds with the language and intent
of the 2013 Regulations itself. TSERC has, in essence, interpreted
regulation 12 by reading it up to mean that it also applies to a person
who is a deemed licensee, and in doing so, the TSERC has aimed
to achieve indirectly what it could not directly.
30. Reading down and reading up are two principles often discussed
in legal contexts, particularly in the realm of statutory interpretation.
Reading down, which has been firmly ingrained in our jurisprudence,
refers to the practice of interpreting a statute narrowly, limiting
its scope or application to specific situations or individuals. This
approach is commonly employed when the language of a statute
is ambiguous or when there is a need to avoid potential conflicts
with other laws or constitutional provisions. For example, if a law
is unclear about whether it applies to certain types of businesses,
a court may choose to read down the statute to only include those
businesses explicitly mentioned in the text. On the other hand,
reading up involves interpreting a statute broadly, extending its
scope or application beyond what is expressly stated in the text.
Reading up is a concept that is invoked with great caution within our
legal framework because it can lead to judicial activism or judicial
overreach, where courts expand the reach of laws beyond what the
legislature intended.
31. A Constitution Bench of this Court in B.R. Kapur v. State of Tamil
Nadu14, while stating that reading up of a statute is not permissible,
held thus:
“39. Section 8(4) opens with the words ‘notwithstanding
anything in sub-section (1), sub-section (2) or sub-section
(3)’, and it applies only to sitting members of Legislatures.
There is no challenge to it on the basis that it violates
Article 14. If there were, it might be tenable to contend
that legislators stand in a class apart from non-legislators,
but we need to express no final opinion. In any case, if it
were found to be violative of Article 14, it would be struck
down in its entirety. There would be, and is no question
of so reading it that its provisions apply to all, legislators
14 [2001] Supp. 3 SCR 191 : (2001) 7 SCC 231
758 [2024] 5 S.C.R.
Digital Supreme Court Reports
and non-legislators, and that, therefore, in all cases the
disqualification must await affirmation of the conviction
and sentence by a final court. That would be ‘reading up’
the provision, not ‘reading down’, and that is not known
to the law.”
32. The literal rule of interpreting a statute empowers courts to iron out
the creases within legislation but without altering the very fabric
of which it is made. The practice of reading up a provision can
only be justified when it aligns with legislative intent, maintains the
fundamental character of the law, and ensures that the resulting
interpretation remains consistent with the original context to which
the law applies. This holds especially true for subordinate legislation,
which require greater scrutiny in this regard. Reading up a provision
of subordinate legislation in a manner that it militates against the
primary legislation is not permissible.
33. The authority to craft subordinate legislation is derived from the
enabling/primary legislation and it is imperative that such legislation
harmonizes with the provisions outlined in the enabling/primary
legislation. The Electricity Act has conferred power on the Central
Government to make Rules [see section 175], and on the Central
Electricity Authority and the Central Commission to make Regulations
[see sections 176 and 177, respectively]. All such rules/regulations
are to be made consistent with the Electricity Act. Section 181 of
the Electricity Act confers power on the State Commissions to make
Regulations but such regulations too must be consistent with the
provisions of the primary enactment and the rules framed thereunder
generally. Rules and Regulations are enacted to supplement the
main provision, not to supplant it. They serve the crucial role of
bridging potential gaps within the primary legislation, yet, their
function is not to create webs and voids merely to clog and hamper
their implementation. Any gaps addressed by Rules and Regulations
must be discernible within the framework of the primary legislation.
34. In the present case, the TSERC, in paragraph 19, asserted that
regulation 12 applies implicitly to a deemed licensee as well. We
do not agree with this reasoning, mainly for two reasons. First,
the primary legislation, the Electricity Act, through the proviso
inserted in section 14(b), confers deemed licensee status upon SEZ
developers without imposing any specific conditions. Secondly, the
[2024] 5 S.C.R. 759
M/s Sundew Properties Limited v. Telangana State
Electricity Regulatory Commission & Anr.
2013 Regulations make a clear distinction between an applicant
seeking a licence [as defined under regulation 2(d)] and a deemed
distribution licensee seeking recognition as such [as defined under
regulation 2(h)]. Regulation 2(d) defines an “applicant” as “a person
who has submitted an application to the Commission for the grant of
a distribution licence”. In contrast, regulation 2(h) defines a “deemed
licensee” as “a person authorized under sub-section (b) of Section
14, and also under the first, second, third, and fifth provisos to
section 14 of the Act, to operate and maintain a distribution system
for supplying electricity to consumers in their area of supply”. The
2013 Regulations clearly delineate distinct categories of licensees.
Regulation 12 pertains solely to regular distribution licensees as
defined under regulation 2(h), not to deemed licensees. ‘Reading up’
regulation 12 so as to expand its ambit to include within it deemed
licensees, especially when the Electricity Act does not stipulate any
such inclusion, runs counter to the subsequently inserted proviso
to clause (b) of section 14 of the Electricity Act—an exercise which
is impermissible and which we cannot approve. Therefore, the
recognition of the status of a deemed distribution licensee cannot
hinge on compliance with rule 3(2) of the 2005 Rules read with
regulation 12 of the 2013 Regulations.
35. The language of regulation 12 merits careful scrutiny. It states that
an applicant shall, “in addition to the provisions of Regulation 4 to
11”, comply with the provisions of the 2005 Rules. It is evident that
it is a normal applicant [as defined under regulation 2(d)], which is
tasked with complying with regulations 4 to 11, that has to comply
with the 2005 Rules. However, the appellant herein, as discussed
previously, is not a regular applicant but a deemed distribution
licensee [as defined under regulation 2(h)], and is governed by
regulation 13, the proviso to which specifically states that nothing in
regulations 4 to 11 would apply to deemed licensees. Having thus
been statutorily exempted from complying with regulations 4 to 11,
we are of the opinion that the appellant, being a deemed licensee,
would also be exempt from the concomitant obligation of complying
with regulation 12, in view of the language of the provision, which
imposes the burden of complying with regulation 12 only on those
applicants who come within the purview of regulations 4 to 11. The
appellant falling outside the scope of the latter, would thus necessarily
fall outside the scope of the former too.
760 [2024] 5 S.C.R.
Digital Supreme Court Reports
36. TSERC’s reliance on regulation 49 of the 2013 Regulations to
enforce the applicability of regulation 12 also appears to be flawed.
Regulation 49, situated within Chapter-4 [General Conditions of
Distribution Licence] of the 2013 Regulations, specifies that “these
general conditions shall apply to distribution licensees and to all
deemed distribution licensees”. A straightforward reading reveals
that the term ‘general conditions’ in regulation 49 pertains exclusively
to the general conditions outlined in Chapter-4. By no stretch of
imagination could the scope of this provision be widened so as to
include within its ambit regulation 12, which forms part of Chapter-3
[Procedure for Grant of Distribution Licence] of the 2013 Regulations.
CONCLUSION
37. To sum up, being a SEZ developer in terms of the 2010 Notification
does not ipso facto confer upon the appellant the status of a deemed
licensee without any scrutiny and without being under any requirement
to apply; it is required to make an application in accordance with the
2013 Regulations. We have been apprised that this condition has
been fulfilled as the status of the appellant as a deemed licensee has
already been upheld pursuant to the application made in accordance
with rule 13 of the 2013 Regulations. The first issue is answered
accordingly. As far as the second issue is concerned, the condition
stipulated in rule 3(2) of the 2005 Rules, as imposed by the TSERC
with a direction to infuse an additional capital of Rs. 26.90 crore
is not justified and contrary to the statutory scheme as discussed
aforesaid. The judgments and orders of the TSERC and the APTEL
are set aside to this extent. The order of the TSERC, which grants
the status of a deemed licensee to the appellant, however, subject to
the condition that its promoters infuse additional capital is accordingly
modified to the extent of excluding such condition.
38. The appeal is partly allowed in the aforesaid terms. No costs.
Result of the case: Appeal partly allowed.
†
Headnotes prepared by: Nidhi Jain
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.