M/S S.S. ENGINEERSversusHINDUSTAN PETROLEUM CORPORATION LTD. & ORS.
- Citation
- 2022 INSC 1309
- Decided
- 15 July 2022
- Disposal
- Dismissed
- Bench
- INDIRA BANERJEE
Holding
An operational creditor cannot invoke Section 9 of the IBC to commence a CIRP where the debt is disputed; such applications must be rejected, and the NCLT erred in admitting the petition.
Summary
M/S S.S. Engineers, an operational creditor, filed a petition under Section 9 of the Insolvency and Bankruptcy Code (IBC) to initiate a Corporate Insolvency Resolution Process (CIRP) against Hindustan Petroleum Corporation Ltd.'s subsidiary, HPCL Biofuels Ltd (HBL). The National Company Law Tribunal (NCLT) admitted the petition despite a pre‑existing dispute over the claim, a decision later set aside by the National Company Law Appellate Tribunal (NCLAT). The Supreme Court examined whether an operational creditor can trigger CIRP when the debt is contested, emphasizing that Sections 8 and 9 of the IBC require an undisputed debt exceeding Rs 1 lakh and no pending dispute. Relying on precedents, the Court held that the NCLT erred in treating the matter as a debt‑collection forum and that the application must be rejected. Consequently, the appeal by the operational creditor was dismissed, affirming the NCLAT order and directing the parties to pursue other remedies such as arbitration.
Issues considered
- Can an operational creditor initiate a CIRP under Section 9 of the IBC when the debt is disputed?
- Whether the NCLT functions as a debt‑collection forum for operational creditors under the IBC.
- Interpretation of Sections 8 and 9 of the IBC regarding the existence of a dispute, the Rs 1 lakh threshold, and the requirement of an undisputed default.
- Whether the presence of pending arbitration or litigation bars admission of a Section 9 application.
Legislation cited
- Central Sales Tax Act, 1956s. 8
- Insolvency and Bankruptcy Code, 2016s. 7, s. 8, s. 9
Subjects
Judgment
[2022] 18 S.C.R. 391 391
M/S S.S. ENGINEERS A
v.
HINDUSTAN PETROLEUM CORPORATION LTD. & ORS.
(Civil Appeal No. 4583 of 2022)
B
JULY 15, 2022
[INDIRA BANERJEE AND V. RAMASUBRAMANIAN, JJ.]
Insolvency and Bankruptcy Code, 2016 – ss.7-9 – Held: NCLT,
exercising powers u/s.7 or s.9, is not a debt collection forum – IBC
tackles and/or deals with insolvency and bankruptcy – It is not the C
object of the IBC that Corporate Insolvency Resolution Process
(CIRP) should be initiated to penalize solvent companies for non-
payment of disputed dues claimed by an operational creditor – There
are noticeable differences in the IBC between the procedure of
initiation of CIRP by a financial creditor and initiation of CIRP by D
an operational creditor – On a reading of ss.8 and 9, it is patently
clear that an Operational Creditor can only trigger the CIRP process,
when there is an undisputed debt and a default in payment thereof
– If the claim of an operational creditor is undisputed and the
operational debt remains unpaid, CIRP must commence, for IBC
does not countenance dishonesty or deliberate failure to repay the E
dues of an Operational Creditor – However, if the debt is disputed,
the application of the Operational Creditor for initiation of CIRP
must be dismissed – In the present case, there was a pre-existing
dispute with regard to the alleged claim of the appellant-Operational
Creditor against HPCL (respondent no.1) or its wholly owned F
subsidiary HBL – Adjudicating Authority (NCLT) clearly fell in error
in admitting the application filed by the appellant u/s.9 as
Operational Creditor, for initiation of the CIRP against HBL – NCLAT
rightly allowed the appeal filed on behalf of HBL – No grounds to
interfere with the impugned judgment of the NCLAT.
G
Mobilox Innovations Private Limited v. Kirusa Software
Private Limited (2018) 1 SCC 353 : [2017] 10 SCR
1006; K Kishan vs. Vijay Nirman Co. (P) Ltd. (2018)
17 SCC 662 : [2018] 10 SCR 959 – relied on.
H
391
392 SUPREME COURT REPORTS [2022] 18 S.C.R.
A Case Law Reference
[2017] 10 SCR 1006 relied on Para 16
[2018] 10 SCR 959 relied on Para 18
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4583
B of 2022.
From the Judgment and Order dated 10.01.2022 of the National
Company Law Appellate Tribunal, New Delhi in Company Appeal (AT)
(Insolvency) No. 332 of 2020.
Ratnanko Banerjee, Sanjeev Sen, Sr. Advs., Ms. Poonam Verma,
C Sidharth Sethi, Ms. Sakshi Kapoor, Avinash Das, Advs. for the Appellant.
Tushar Mehta, SG, Sanjay Kapur, Ms. Megha Karnwal, Arjun
Bhatia, Advs. for the Respondents.
The following Order of the Court was passed:
D ORDER
This appeal is against a judgment and order dated 10th January,
2022 passed by the National Company Law Appellate Tribunal, Principal
Bench, New Delhi allowing Company Appeal (AT)(Insolvency) No. 332
of 2020 filed by the Respondent No.1 Hindustan Petroleum Corporation
E Limited (HPCL) and setting aside the order dated 12.02.2020 passed by
the National Company Law Tribunal (NCLT), Kolkata, admitting an
application filed by the appellant under Section 9 of the Insolvency and
Bankruptcy Code (IBC) as Operational Creditor, for initiation of the
Corporate Insolvency Resolution Process (CIRP) against HPCL Biofuels
Ltd. (HBL), a wholly owned subsidiary of HPCL. The NCLAT directed
F the Adjudicating Authority NCLT to close the proceedings for CIRP
initiated against HBL.
2. On or about 15.11.2018, the appellant filed an application for
initiation of CIRP against HBL under Section 9 of the IBC in the Kolkata
Bench of the NCLT. On 07.03.2019, HBL filed its reply to the said
G application made by the appellant and the appellant also filed a rejoinder
thereto.
3. By an order dated 12.02.2020, the Adjudicating Authority
(NCLT) admitted the application for initiation of CIRP filed by the
appellant, rejecting the contention raised by HBL that there were pre-
H
M/S S.S. ENGINEERS v. HINDUSTAN PETROLEUM 393
CORPORATION LTD. & ORS.
existing disputes between the parties in respect of the claim of the A
appellant.
4. From the List of Dates filed by the appellant, it appears that
between 27.06.2012 to 30.08.2012, various tenders were floated by HBL
for enhancing the capacity of the Boiling Houses of HBL at Lauryia and
Sugauli from 1750 TCD to 3500 TCD. B
5. The appellant submitted its offer pursuant to the tenders. On or
about 15.10.2012, four purchase orders were issued to the appellant in
relation to the tender work of enhancing the capacity of the Boiler Houses.
On 01.11.2012, Purchase Orders were issued by HBL for enhancing
the Juice Heater and Evaporator Section and Pan and Crystallization C
Section at Sugauli Plant on a turnkey basis.
6. Between 21.11.2012 to 25.03.2013, the appellant raised invoices
in respect of the purchase orders. It is not necessary for this Court to go
into the details of what transpired between 21.11.2012 when the appellant
started raising invoices of HBL and 29.12.2013. D
7. Suffice it to mention that on 29.12.2013, HBL sent an email to
the appellant pointing out that the appellant had been violating the terms
of the purchase order and backing out from its commitments thereunder,
thereby causing huge losses to HBL. HBL contended that because of
the failure of the appellant to honour its commitments in terms of the E
Tenders/Purchase Orders it had to procure materials from other vendors.
8. On 02.01.2014, HBL sent a letter to the appellant stating that
the appellant had acted in violation of the General Terms and Conditions,
inter alia, by raising improper invoices for materials not supplied, not
renewing bank guarantees, failing to effect supplies and complete work F
within the stipulated period. It was alleged that the service rendered
and/or materials supplied by the appellant were of poor quality.
9. On 03.01.2014, HBL raised a debit note in respect of
consumption by the appellant of spares and consumables from the
warehouse of HBL. A series of correspondence followed. By a letter
G
dated 11.4.2014 addressed to the appellant, HBL made allegations with
regard to the service rendered and/or goods supplied by the appellants
and contended that there was no payment outstanding from HBL to the
appellant. On the other hand, HBL claimed that an amount of Rs.1.49
crores was due from the appellant, which amount excluded consequential
losses. H
394 SUPREME COURT REPORTS [2022] 18 S.C.R.
A 10. On 07.5.2014, HBL sent an email to the appellant stating that
HBL would not release money to the appellant as the quality of work
done by the Appellant was poor and the Appellant had breached the
terms and conditions of the Purchase Orders. Further correspondence
ensued.
B 11. Between 11.03.2015 to 27.03.2018 C-forms were issued by
HBL to the appellant under Section 8 of the Central Sales Tax Act read
with Rules 12(1) of the Central Sales Tax (Registration and Turnover)
Rules, 1957. The statutory duty of issuance of C-forms under the Central
Sales Tax, do not and cannot constitute acknowledgment of any liability
of HBL to the appellant, to make payment. On 09.7.2016, the appellant
C sent legal notice to HBL through its advocate, demanding payment or
alternatively reference of the disputes to arbitration.
12. On 30.08.2017, the appellant sent a demand notice under
Section 8 of the IBC to HBL claiming that a sum of Rs. 18,12,21,452/-
(Rupees eighteen crores twelve lakhs, twenty one thousand four hundred
D and fifty two) along with interest, was due from HBL to the Appellant
from 30.12.2013. A second demand notice was sent by the appellant to
HBL on 07.08.2018. HBL replied to the demand notice dated 25.07.2018
received on 01.08.2018 disputing the claim. It is apparent from the records
that there were pre-existing disputes between the parties and on
E 09.07.2016, a request had been made by the Operational Creditor to
HBL to refer the disputes to Arbitration.
13. Sections 8 and 9 of the IBC read :-
“8. Insolvency resolution by operational creditor.—(1) An
operational creditor may, on the occurrence of a default, deliver
F a demand notice of unpaid operational debt or copy of an invoice
demanding payment of the amount involved in the default to
the corporate debtor in such form and manner as may be
prescribed.
(2) The corporate debtor shall, within a period of ten days of the
G receipt of the demand notice or copy of the invoice mentioned in
sub-section (1) bring to the notice of the operational creditor—
(a) existence of a dispute, 1[if any, or] record of the pendency
of the suit or arbitration proceedings filed before the receipt of
such notice or invoice in relation to such dispute;
H
M/S S.S. ENGINEERS v. HINDUSTAN PETROLEUM 395
CORPORATION LTD. & ORS.
(b) the payment of unpaid operational debt— A
(i) by sending an attested copy of the record of electronic
transfer of the unpaid amount from the bank account of the
corporate debtor; or
(ii) by sending an attested copy of record that the operational
B
creditor has encashed a cheque issued by the corporate
debtor.
Explanation.—For the purposes of this section, a “demand notice”
means a notice served by an operational creditor to the corporate
debtor demanding payment of the operational debt in respect of C
which the default has occurred.
9. Application for initiation of corporate insolvency resolution
process by operational creditor.—(1) After the expiry of the period
of ten days from the date of delivery of the notice or invoice
demanding payment under sub-section (1) of section 8, if the D
operational creditor does not receive payment from the corporate
debtor or notice of the dispute under sub-section (2) of section 8,
the operational creditor may file an application before the
Adjudicating Authority for initiating a corporate insolvency
resolution process.
E
(2) The application under sub-section (1) shall be filed in such
form and manner and accompanied with such fee as may be
prescribed.
(3) The operational creditor shall, along with the application
furnish— F
(a) a copy of the invoice demanding payment or demand notice
delivered by the operational creditor to the corporate debtor;
(b) an affidavit to the effect that there is no notice given by the
corporate debtor relating to a dispute of the unpaid operational
debt; G
(c) a copy of the certificate from the financial institutions
maintaining accounts of the operational creditor confirming that
there is no payment of an unpaid operational debt by the
corporate debtor, if available;
H
396 SUPREME COURT REPORTS [2022] 18 S.C.R.
A (d) a copy of any record with information utility confirming
that there is no payment of an unpaid operational debt by the
corporate debtor, if available; and
(e) any other proof confirming that there is no payment of any
unpaid operational debt by the corporate debtor or such other
B information, as may be prescribed.
(4) An operational creditor initiating a corporate insolvency
resolution process under this section, may propose a resolution
professional to act as an interim resolution professional.
(5) The Adjudicating Authority shall, within fourteen days of the
C receipt of the application under sub-section (2), by an order—
(i) admit the application and communicate such decision to the
operational creditor and the corporate debtor if,—
(a) the application made under sub-section (2) is complete;
D (b) there is no payment of the unpaid operational debt;
(c) the invoice or notice for payment to the corporate debtor
has been delivered by the operational creditor;
(d) no notice of dispute has been received by the operational
E creditor or there is no record of dispute in the information
utility; and
(e) there is no disciplinary proceeding pending against any
resolution professional proposed under sub-section (4), if
any.
F (ii) reject the application and communicate such decision to
the operational creditor and the corporate debtor, if—
(a) the application made under sub-section (2) is incomplete;
(b) there has been payment of the unpaid operational debt;
G (c) the creditor has not delivered the invoice or notice for
payment to the corporate debtor;
(d) notice of dispute has been received by the operational
creditor or there is a record of dispute in the information
utility; or
H
M/S S.S. ENGINEERS v. HINDUSTAN PETROLEUM 397
CORPORATION LTD. & ORS.
(e) any disciplinary proceeding is pending4 against any A
proposed resolution professional:
Provided that Adjudicating Authority, shall before rejecting an
application under sub-clause (a) of clause (ii) give a notice to the
applicant to rectify the defect in his application within seven days
of the date of receipt of such notice from the adjudicating B
Authority.
(6) The corporate insolvency resolution process shall commence
from the date of admission of the application under sub-section
(5) of this section.”
14. On 15.02.2018, the appellant filed its application under Section C
9 of the IBC for initiation of CIRP against HBL, as stated above. By the
order dated 12.02.2020, the Adjudicating Authority (NCLT) admitted
the said application of the Appellant. The Adjudicating Authority, inter
alia, held:
“17. As regards the pre-existing dispute, we have gone through D
all the facts stated by the Corporate Debtor but having regard to
the quantum of claim in respect of supplies order, in our considered
view, the amount of disputed claim due and payable will be more
than Rs. One lakh in any case. Hence, such claims do not help
the case of Corporate Debtor in substantial manner. Having said E
so, we would further refer to the provisional statement attached
with the letter of the Corporate Debtor dated June 25, 2014 copy
of which has been placed at Page 1779 of Vol.10 of the paper
book to find as to what is the factual position as per the stand of
Corporate Debtor on various issues. As per this provisional
statement, the total purchase order value has been shown as F
Rs.3818.72 lakhs. There have been several deductions including
for service provided by Corporate Debtor to the Operational
Creditor in the execution of the contract, entry tax, TDS, WCD,
payment to parties/payment to Operational Creditor by the
Corporate Debtor/sub-vendors and subcontractors/vendors of the G
Operational Creditor. These are normal deductions as per business
practice and terms of contract. However, it is noteworthy that
Liquidated Damage @ 5% amount to Rs.190.94 lakhs,
Performance Bank Guarantee to the tune of 673.6 lakhs, work
claim of Rs.352.00 lakhs for boiler house extension P.O. finalization
H
398 SUPREME COURT REPORTS [2022] 18 S.C.R.
A and additional work 71 lakh have also been considered. The net
effect has been worked out by Corporate Debtor as Rs.500 lakhs
receivable from the Operational Creditor. If the boiler house
extension and additional work are ignored, the amount recoverable
from the Operational Creditor gets reduced to 63.13 lakhs. Further,
if the amount retained for Performance Bank Guarantee is taken
B
into consideration, then the amount payable to Operational Creditor
works out at Rs.610.23 lakhs (i.e. 673-63.13). As noted earlier,
L.D. is applicable @ 5% amounting to Rs.190,94 lakhs has already
been deducted. Further, amount of Rs.400.55 lakhs in respect of
Purchase Orders issued at the risk and cost of the vendor have
C also been deducted. Thus, all recoveries for non-performance/
default has been considered and therefore, amount of
Performance Bank Guarantee minus recovery i.e., 610.23 lakhs
at least becomes payable by Corporate Debtor to the Operational
Creditor. As an adjudication authority in the proceedings, we are
not suppose to do this kind of working, but to find out the
D
genuineness of the claim of pre-existing dispute, and amount of
outstanding debt, it was necessary in the facts and circumstances
of the case, hence, it has been so analysed on the basis of the
provisional statement prepared and filed by the Corporate Debtor
itself. At the cost of repetition, we again state that this statement
E takes into consideration all these disputes raised by the Corporate
Debtor, hence, the amount payable by the Corporate Debtor
remains in positive which is more than one lakh ultimately that too
when we have considered the project as a whole against the claim
of Operational Creditor of undisputed dues of supply portion only.
We have also gone through the emails which have been taken
F
into consideration. While preparing this provisional statement.
Hence, on the basis of material on record, it cannot be said that
any other dispute remains to be considered. Apart from this, the
fact which is crucial to note is that the Corporate Debtor has
awarded new work orders to the Operational Creditor
G subsequently which means that all the disputes relating to this
contract had been considered/resolved and this fact has remained
undisputed. Further, Form “C”s have been issued as late as up to
March 2018. We further make it clear that we have analysed the
provisional statement with limited objective of admissibility of this
application and this analysis cannot be considered as expression
H
M/S S.S. ENGINEERS v. HINDUSTAN PETROLEUM 399
CORPORATION LTD. & ORS.
of opinion on the amount of claim in any manner which may be A
actually due and payable.”
15. In our considered view, the Adjudicating Authority (NCLT)
committed a grave error of law by admitting the application of the
Operational Creditor, even though there was a pre-existing dispute as
noted by the Adjudicating Authority. B
16. When examining an application under Section 9 of the IBC,
the Adjudicating Authority would have to examine (i) whether there was
an operational debt exceeding Rupees 1,00,000/- (Rupees One Lac); (ii)
whether the evidence furnished with the application showed that debt
exceeding Rupees one lac was due and payable and had not till then C
been paid; and (ii) whether there was existence of any dispute between
the parties or the record of pendency of a suit or arbitration proceedings
filed before the receipt of demand notice in relation to such dispute. If
any one of the aforesaid conditions was not fulfilled, the application of
the Operational Creditor would have to be rejected
D
17. In Mobilox Innovations Private Limited v. Kirusa Software
Private Limited1, this Court held:-
“34. Therefore, the adjudicating authority, when examining
an application under Section 9 of the Act will have to
determine: E
(i) Whether there is an “operational debt” as defined
exceeding Rs 1 lakh? (See Section 4 of the Act)
(ii) Whether the documentary evidence furnished with the
application shows that the aforesaid debt is due and
payable and has not yet been paid? and F
(iii) Whether there is existence of a dispute between the
parties or the record of the pendency of a suit or
arbitration proceeding filed before the receipt of the
demand notice of the unpaid operational debt in relation
to such dispute? G
If any one of the aforesaid conditions is lacking, the
application would have to be rejected. Apart from the above,
the adjudicating authority must follow the mandate of Section
1
(2018) 1 SCC 353 H
400 SUPREME COURT REPORTS [2022] 18 S.C.R.
A 9, as outlined above, and in particular the mandate of Section
9(5) of the Act, and admit or reject the application, as the
case may be, depending upon the factors mentioned in Section
9(5) of the Act.
***
B 51. It is clear, therefore, that once the operational creditor
has filed an application, which is otherwise complete, the
adjudicating authority must reject the application under
Section 9(5)(2)(d) if notice of dispute has been received by
the operational creditor or there is a record of dispute in the
C information utility. It is clear that such notice must bring to
the notice of the operational creditor the “existence” of a
dispute or the fact that a suit or arbitration proceeding
relating to a dispute is pending between the parties. Therefore,
all that the adjudicating authority is to see at this stage is
whether there is a plausible contention which requires further
D investigation and that the “dispute” is not a patently feeble
legal argument or an assertion of fact unsupported by
evidence. It is important to separate the grain from the chaff
and to reject a spurious defence which is mere bluster.
However, in doing so, the Court does not need to be satisfied
E that the defence is likely to succeed. The Court does not at
this stage examine the merits of the dispute except to the extent
indicated above. So long as a dispute truly exists in fact and
is not spurious, hypothetical or illusory, the adjudicating
authority has to reject the application.”
F 18. In K Kishan vs. Vijay Nirman Co. (P) Ltd.2, cited by the
NCLAT in its impugned judgment, this Court held:-
“22. Following this judgment, it becomes clear that operational
creditors cannot use the Insolvency Code either prematurely or
for extraneous considerations or as a substitute for debt
G enforcement procedures. The alarming result of an operational
debt contained in an arbitral award for a small amount of say, two
lakhs of rupees, cannot possibly jeopardise an otherwise solvent
company worth several crores of rupees. Such a company would
be well within its rights to state that it is challenging the arbitral
2
H (2018) 17 SCC 662
M/S S.S. ENGINEERS v. HINDUSTAN PETROLEUM 401
CORPORATION LTD. & ORS.
award passed against it, and the mere factum of challenge would A
be sufficient to state that it disputes the award. Such a case would
clearly come within para 38 of Mobilox Innovations [Mobilox
Innovations (P) Ltd. v. Kirusa Software (P) Ltd., (2018) 1 SCC
353 : (2018) 1 SCC (Civ) 311], being a case of a pre-existing
ongoing dispute between the parties. The Code cannot be used in
B
terrorem to extract this sum of money of rupees two lakhs even
though it may not be finally payable as adjudication proceedings
in respect thereto are still pending. We repeat that the object of
the Code, at least insofar as operational creditors are concerned,
is to put the insolvency process against a corporate debtor only in
clear cases where a real dispute between the parties as to the C
debt owed does not exist……………………………
27. We repeat with emphasis that under our Code, insofar as an
operational debt is concerned, all that has to be seen is whether
the said debt can be said to be disputed, and we have no doubt in
stating that the filing of a Section 34 petition against an arbitral D
award shows that a pre-existing dispute which culminates at the
first stage of the proceedings in an award, continues even after
the award, at least till the final adjudicatory process under Sections
34 and 37 has taken place.”
19. In this Case, the correspondence between the parties would E
show that HBL had been disputing the claims of the Appellant on the
contention that the appellant had not been adhering to the time schedules
for completion of the contract work, had been violating the terms of
Tender documents and the Purchase Orders, and backing out from its
commitments thereunder, thereby causing losses to HBL. HBL was
constrained to procure materials from other vendors incurring losses. F
20. The correspondence between the parties evince the existence
of real dispute, particularly the letter dated 02.01.2014 from HBL to the
appellant stating that the appellant had inter alia raised improper invoices
for materials not supplied and had failed to effect supplies and complete
work within a stipulated period; debit note dated 03.01.2014 raised by G
HBL in respect of consumption by the appellant of spares and
consumables from the warehouse of HBL; letter dated 11.04.2014 from
HBL to the Appellant, inter alia, contending there was no payment
outstanding from HBL to the appellant and claiming that a sum of Rs.1.49
Crores was due from appellant to the HBL excluding consequential H
402 SUPREME COURT REPORTS [2022] 18 S.C.R.
A losses; an email dated 07.05.2014 from HBL to the appellant declining
to release money claimed by the appellant on the ground of poor quality
of work and breaches of the terms and conditions of the Purchase Order.
21. Going by the test of existence of a dispute, it is clear that HBL
had raised a plausible defence. It was not for the Adjudicating Authority
B to make a detailed examination of the respective contentions and
adjudicate the merits of the dispute at this stage.
22. As held by the NCLAT :-
“The facts of the present case are being examined in the light of
the law laid down by the Hon’ble Supreme Court, though the
C Learned Counsel for the ‘Operational Creditor’ has strenuously
contended that the issuance of further work orders and the Notice
issued by the ‘Operational Creditor’ invoking Arbitration does not
amount to Existence of a Dispute’, the nature of communication
on record with rival contentions clarify the ‘Existence of a Dispute’
D between the parties prior to issuance of the Demand Notice. It
has been time and again held that ‘it is enough that a ‘dispute
exists’ between the parties.
The communication between the parties as noted in para 10 read
together with the Arbitration invoked by the ‘Operational Creditor’,
E we are of the considered view that there is an ‘Existence of a
Dispute’ between the parties which is a genuine dispute and not a
spurious, patently feeble legal argument or an assertion of fact
unsupported by evidence.”
23. The learned NCLAT rightly observed that a perusal of the
F “Tender Enquiry dated 27.06.2012”, “Instructions to Bidders”, “General
Conditions of Contract” and “Special Conditions of Contract”, showed
that the tender was for ‘design, engineering, manufacture,
procurement, supply, transportation to site, transit and storage,
insurance storing at site, project management, civil work,
mechanical works, electrical works, instrumentation work,
G mechanical works, electrical works, instrumentation work, erection,
installation interfacing, testing, commissioning, performance testing,
putting into successful commercial operation and handing over
additional equipment goods, and material centrifugal section
including civil foundation for enhancing the boiling house capacity
from 1750 TCD to 3750 TCD on Lumpsum Turnkey Basis including
H
M/S S.S. ENGINEERS v. HINDUSTAN PETROLEUM 403
CORPORATION LTD. & ORS.
civil foundation work’. It was also not in dispute that the appellants A
had been issued further work on 13.06.2013 and 08.8.2013 all on Lumpsum
Turnkey Basis.
24. The NCLAT held that the execution of the contract work
being on a lumpsum turnkey basis, the Appellant contractor was
responsible for the entire execution of the work, as per specifications B
and to the satisfaction of HBL. On completion of the work, the Appellant
contractor was to give notice of such completion to the site in charge,
who would inspect the work and furnish the Appellant contractor with a
Completion Certificate indicating defects, if any, in the contract work
and the date of completion of the contract work.
C
25. Referring to the letter dated 11.08.2013 of HBL to the Appellant,
the NCLAT found that it was the case of HBL that the Appellant, as
contractor, had delayed the performance of its obligations in terms of
the contract. In the aforesaid letter, HBL enumerated the lacuna and
lapses of the Appellant in the performance of the contract and the various
D
breaches of contract committed by the Appellant and also made a
categorical assertion that till 31.07.2013, there was no amount outstanding
from HBL to the Appellant. Rather there was a recovery from the
Appellant.
26. In the impugned order, NCLAT set out a communication dated
E
02.01.2014 from HBL to the Appellant giving details of the acts and
omissions of the Appellant, which tantamounted to breaches of contract
on the part of the Appellant. Several other letters were also set out in the
impugned order.
27. The impugned order takes note of the averment in the Appellant F
Operational Creditor’s Reply before the NCLT that despite several
requests and reminder letters from 2013 to 2017, the Corporate Debtor
HBL did not pay the amounts due, but raised baseless allegations and
disputes.
28. The NCLAT found: G
“13. ………. It is the case of the ‘Operational Creditor’ that there
is no ‘Existence of Dispute’ prior to the issuance of Demand
Notice. In their email dated 08.04.2013, in relation to the Minutes
of the Meeting, the ‘Operational Creditor’ had clarified that work
progress is subject to prompt payments. July 31, 2013 was decided H
404 SUPREME COURT REPORTS [2022] 18 S.C.R.
A as the commissioning date subject to immediate and prompt
payment made by the ‘Corporate Debtor’. The ‘Operational
Creditor’ had always shown their willingness to commission and
perform their obligations and their senior personnel were stationed
at the site of the ‘Corporate Debtor’ and additional staff always
visited from time to time. It was only because of pendency of
B
payment of the dues that the ‘Operational Creditor’ had faced
difficulties in executing the ongoing Project. The ‘Corporate
Debtor’ was making ad hoc payments but not as per the bills
raised.
C 14. It is strenuously contended by the Learned Counsel that the
conduct of the ‘Corporate Debtor’ in awarding fresh Purchase
Order in August 2013 at the fag end of the completion of the
previous 6 orders, while at the same time, complaining against
their performance, is self-contradictory and goes to show the
malafide intention of the ‘Corporate Debtor’. It is the case of the
D ‘Operational Creditor’ that all equipment supplied was of good
quality and all the valves which were procured were from a vendor
mandated by the ‘Corporate Debtor’ only. If the ‘Corporate
Debtor’ was dissatisfied with the quality of work or substandard
material supplied, there are no substantial reasons as to why new
E contracts were awarded at the fag end of the previous 6 contracts.
87% of the material and services were already completed as per
the billing breakup and therefore the question of short supply or
purchase of additional material by the ‘Corporate Debtor’ does
not arise. It is also vehemently contended that the ‘Operational
Creditor’ was constrained to stop supply to the ‘Corporate Debtor’
F only on account of failure of payments of pending principal dues
which amounts to more than Rs.13 Crores. The ‘Corporate
Debtor’ continued to raise various debit notes unilaterally without
any supporting documentation, for which the ‘Operational Creditor’
cannot be held responsible.
G 15. The ‘Operational Creditor’ vide email dated 02.02.2014 i.e.
one month after the aforenoted letter sought for release of payment.
Once again the ‘Corporate Debtor’ on 04.02.2014 and on
28.02.2014 reiterated the poor performance of the ‘Operational
Creditor’ on account of which huge losses were incurred.
H
M/S S.S. ENGINEERS v. HINDUSTAN PETROLEUM 405
CORPORATION LTD. & ORS.
16. On 29.03.2014, it is the case of the ‘Corporate Debtor’ that A
the ‘Operational Creditor’ had abandoned the site and therefore,
the ‘Corporate Debtor’ had to take over the Project and make all
the relevant payments to the vendor.
19. It is pertinent to note that on 09.07.2016, ‘prior to the issuance
of the Demand Notice under Section 8 of the Code’, the B
‘Operational Creditor’ invoked Arbitration pursuant to the 8 project
orders issued by the ‘Corporate Debtor’, which itself substantiates
the ‘Existence of a Dispute’. In the ‘Notice’ invoking Arbitration,
the ‘Operational Creditor’ has stated that there is an outstanding
of Rs.18,12,21,452/- and has further stated that they are ready to
settle the disputes through Arbitration. C
22. The communication between the parties as noted in para 10
read together with the Arbitration invoked by the ‘Operational
Creditor’, we are of the considered view that there is an ‘Existence
of a Dispute’ between the parties which is a genuine dispute and
not a spurious, patently feeble legal argument or an assertion of D
fact unsupported by evidence”.
29. The HBL raised serious allegations against the appellant of
breach of its contractual commitments. From the letter of HBL dated
02.01.2014, it is evident that HBL had been contending inter alia that
work of erection and commissioning of electric power had not been E
done, the dead line of completion of the contract work had not been
adhered to and the quality of the equipment supplied and/or work done
was of poor quality.
30. This Court finds that there was a pre-existing dispute with
regard to the alleged claim of the appellant against HPCL or its subsidiary F
HBL. The NCLAT rightly allowed the appeal filed on behalf of HBL. It
is not for this Court to adjudicate the disputes between the parties and
determine whether, in fact, any amount was due from the appellant to
the HPCL/HBL or vice-versa. The question is, whether the application
of the Operational Creditor under Section 9 of the IBC, should have G
been admitted by the Adjudicating Authority. The answer to the aforesaid
question has to be in the negative. The Adjudicating Authority (NCLT)
clearly fell in error in admitting the application.
31. The NCLT, exercising powers under Section 7 or Section 9 of
IBC, is not a debt collection forum. The IBC tackles and/or deals with
H
406 SUPREME COURT REPORTS [2022] 18 S.C.R.
A insolvency and bankruptcy. It is not the object of the IBC that CIRP
should be initiated to penalize solvent companies for non-payment of
disputed dues claimed by an operational creditor.
32. There are noticeable differences in the IBC between the
procedure of initiation of CIRP by a financial creditor and initiation of
B CIRP by an operational creditor. On a reading of Sections 8 and 9 of the
IBC, it is patently clear that an Operational Creditor can only trigger the
CIRP process, when there is an undisputed debt and a default in payment
thereof. If the claim of an operational creditor is undisputed and the
operational debt remains unpaid, CIRP must commence, for IBC does
C not countenance dishonesty or deliberate failure to repay the dues of an
Operational Creditor. However, if the debt is disputed, the application of
the Operational Creditor for initiation of CIRP must be dismissed.
33. We find no grounds to interfere with the judgment and order
of the NCLAT impugned in this appeal.
D 34. The appeal is dismissed.
35. Needles to mention that the appellant may avail such other
remedies as may be available in accordance with law including arbitration
to realise its dues, if any.
E 36. Pending applications, if any, stand disposed of accordingly.
Divya Pandey Appeal dismissed.
(Assisted by : Roopanshi Virang, LCRA)
F
G
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.