Created byFuzzy Cloud

Supreme Court of India

M/S GAYATRI PROJECT LIMITEDversusMADHYA PRADESH ROAD DEVELOPMENT CORPORATION LIMITED

Citation
2025 INSC 698
Decided
15 May 2025
Disposal
Disposed off

Holding

An arbitral award cannot be set aside solely on the ground of lack of jurisdiction where the jurisdictional objection was not raised at the appropriate stage, and the L.G. Chaudhary (II) decision is not per incuriam and coexists with Lion Engineering.

Summary

The appellant, Gayatri Project Ltd., entered into a works contract with the Madhya Pradesh Road Development Corporation and invoked arbitration under Clause 67.4 of the contract, resulting in a 2011 award in its favour. The respondent challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, alleging that the arbitral tribunal lacked jurisdiction because the dispute should have been governed by the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983. The High Court set aside the award on that ground, but the Supreme Court examined whether such a jurisdictional plea could be raised for the first time under Section 34 when it was not raised before the tribunal under Section 16(2). The Court also considered whether its earlier decision in L.G. Chaudhary (II) was per incuriam for not referring to Lion Engineering. It held that where no objection to jurisdiction was made at the appropriate stage, an award cannot be annulled solely on that ground, and L.G. Chaudhary (II) does not conflict with Lion Engineering. Consequently, the Supreme Court set aside the High Court order and restored the Section 34 proceedings to the lower court for merits determination.

Issues considered

  • Whether an arbitral award rendered under the Arbitration and Conciliation Act, 1996, where the arbitration should have been governed by the M.P. Madhyastham Adhikaran Adhiniyam, 1983, can be set aside solely on the ground of lack of jurisdiction when no objection was raised under Section 16(2) of the Act.
  • Whether the decision in M.P. Road Development Authority v. L.G. Chaudhary Engineers & Contractors (II) is per incuriam for not considering Lion Engineering Consultants v. State of Madhya Pradesh, and whether there is a conflict between the two decisions on the stage at which a jurisdictional plea may be raised.

Legislation cited

Headnote

Issue for Consideration 1. Whether an arbitral award rendered under the Arbitration and Conciliation Act, 1996 (hereinafter “Act, 1996”), where the arbitration proceedings ought to have been governed by the M.P. Madhyastham Adhikaran Adhiniyam, 1983 (hereinafter “MP set aside solely on the ground of lack of jurisdiction, even when no such plea was raised before the arbitral tribunal in terms of Section 16(2) of the Act, 1996? 2. Whether the decision of this Court in M.P. Road Development Authority & Anr v. L.G. Chaudhary Engineers & Contractors

Subjects

ArbitrationJurisdictionArbitral awardSection 34Section 16WaiverPer incuriamM.P. Madhyastham Adhikaran AdhiniyamArticle 227Article 142

Judgment

                [2025] 5 S.C.R. 2534 : 2025 INSC 698

              M/s Gayatri Project Limited
                           v.
 Madhya Pradesh Road Development Corporation Limited
                      (Civil Appeal No. 6856 of 2025)
                                15 May 2025
              [J.B. Pardiwala* and R. Mahadevan, JJ.]


                          Issue for Consideration
       1.   Whether an arbitral award rendered under the Arbitration
            and Conciliation Act, 1996 (hereinafter “Act, 1996”), where
            the arbitration proceedings ought to have been governed
            by the M.P. Madhyastham Adhikaran Adhiniyam, 1983
            (hereinafter “MP Act, 1983”), can be set aside solely on the
            ground of lack of jurisdiction, even when no such plea was
            raised before the arbitral tribunal in terms of Section 16(2)
            of the Act, 1996?
       2.   Whether the decision of this Court in M.P. Road Development
            Authority & Anr v. L.G. Chaudhary Engineers & Contractors
            reported in (2018) 10 SCC 826 can be said to be per incuriam
            for not considering the Court’s ruling in Lion Engineering?
            In other words, is there a conflict between the decisions in
            Lion Engineering and L.G. Chaudhary (II), particularly on
            when a plea of lack of jurisdiction may be raised under the
            Act, 1996?

                                 Headnotes†
       Arbitration and Conciliation Act, 1996 – M.P Madhyastham
       Adhikaran Adhiniyam, 1983 – Arbitral award cannot be set
       aside solely on the ground of jurisdiction if no objection was
       raised under Section 16(2) of the Arbitration and Conciliation
       Act, 1996:
       The appellant executed a “works contract” dated 12.12.2005 with
       the respondent for “Rehabilitation and Strengthening of Khargone-
       Barwani Road (SH-26) Project Road No.19” & “Rehabilitation and
       Strengthening of Khargone-Bistan Road (SH-31) Project Road
       No.20” in the State of Madhya Pradesh – Clause 67.3 of the


* Author
[2025] 5 S.C.R.                                                             2535

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

     “General Conditions of Contract” read with Clause 67.4 of the
     “Conditions of Particular Application” provided for arbitration as
     the means for resolution of disputes between the Parties – The
     arbitration agreement mandated that the tribunal shall comprise
     of three members, one to be appointed by each party and the
     two coarbitrators had to nominate the presiding arbitrator – The
     disputes arose between the parties from 06.08.2010 onwards in
     relation to the appellant’s right to be reimbursed additional cost
     incurred by it on account of introduction of subsequent legislation
     on increase in entry tax on High-Speed Diesel under Clause 70.8
     of the Particular Conditions of Contract – The appellant invoked
     arbitration under Clause 67.4 vide its notice dated 06.08.2010 and
     the Tribunal stood constituted on 24.09.2010 – The Tribunal passed
     a unanimous award dated 08.07.2011 in favour of the appellant
     for a sum of Rs.1,03,55,187 (i.e. Rs.1.04 Crore) – As is evident
     from Para 1.19 of the Award quoted above, the quantification of
     this amount was in-fact recommended by the Engineer and had
     been admitted by the respondent – The Tribunal also awarded
     future interest at the rate of 10% p.a. from the date of the award
     till the date of actual payment as per para 3.1 – As of 17.02.2025,
     the amount payable by the respondent to the appellant stands at
     Rs.2,44,63,775 – The respondent challenged the award before the
     Civil Court under Section 34 of the Arbitration Act vide a petition
     filed on 30.09.2011 – The same came to be allowed holding that
     the Arbitral Tribunal did not jurisdiction in view of M.P Madhyastham
     Adhikaran Adhiniyam, 1983 – The order passed by the Commercial
     Court and 19th Additional Sessions Judge, Bhopal (M.P.) came
     to be challenged by way of appeal before the High Court under
     Section 37 of the Act, 1996 – The appeal came to be dismissed –
     Hence, the present Appeal before this Court.
     Held: It was noted that the decision in M.P. Road Development
     Authority & Anr v. L.G. Chaudhary Engineers & Contractors
     (2018) 10 SCC 826 elucidated how the courts are expected to
     deal with the various issues that may arise insofar as the pending
     proceedings that were inadvertently initiated under the Arbitration
     and Conciliation Act, 1996 and any awards already passed
     thereunder are concerned – M.P. Road Development Authority v.
     L.G. Chaudhary, (2018) 10 SCC 826 was referred to wherein it was
     held that an arbitral award cannot be set aside solely on the ground
     of jurisdiction if no objection was raised under Section 16(2) of the
2536                                                         [2025] 5 S.C.R.

                         Supreme Court Reports


    Arbitration and Conciliation Act, 1996 – However, other challenges
    may be raised under Section 34 of the Act. [Paras 14, 15]

    Arbitration and Conciliation Act, 1996 – M.P Madhyastham
    Adhikaran Adhiniyam, 1983 – Stage at which plea regarding
    jurisdictional error has to be raised – Plea of jurisdiction can
    be raised under Section 34 of the Act even if no such objection
    was raised under Section 16:
    Held: In Lion Engineering Consultants v. State of Madhya Pradesh
    (2018) 16 SCC 758, it was held that any legal plea arising on
    undisputed facts can be raised in the proceedings under Section
    34 of the Act, 1996 even if they were never raised under Section
    16 – It further held that, such plea being a question of law arising
    from admitted facts, can be raised without seeking any amendment
    of the pleadings – Accordingly, it held that there is no bar to plea
    of jurisdiction being raised by way of an objection under Section
    34 of the Act even if no such objection was raised under Section
    16. [Para 16]

    Arbitration and Conciliation Act, 1996 – M.P Madhyastham
    Adhikaran Adhiniyam, 1983 – There is no conflict between
    Lion Engineering Consultants v. State of Madhya Pradesh
    (2018) 16 SCC 758 & M.P. Road Development Authority v.
    L.G. Chaudhary (2018) 10 SCC 826 if either omission in
    referring to previous decision does not amount to a non-
    consideration of the ratio of an earlier decision or where
    there is no palpable conflict or contradiction in the ratio of
    both decisions:
    Held: It was contended that there exists a conflict between the
    decisions of this Court in Lion Engineering and L.G. Chaudhary (II),
    insofar as the issue of when a plea of lack of jurisdiction on the
    basis of applicability of a State law can be raised. It was submitted
    that Lion Engineering clearly holds that an objection of lack of
    jurisdiction is a legal plea that may be raised for the first time in
    the proceedings under Section 34 of the Act, 1996, even if the
    same was never raised before the arbitral tribunal, and being
    a question of law, Section 16 sub-section (2) of the Act, 1996
    would have no application – However, in L.G. Chaudhary (II) it
    was held that no plea of lack of jurisdiction can be raised in the
    proceedings under Section 34 – This was contended to be per
[2025] 5 S.C.R.                                                              2537

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

     incurium and a contradictory view since L.G. Chaudhary (II) did not
     refer to Lion Engineering – It was held that merely because L.G.
     Chaudhary (II) does not refer to the decision of Lion Engineering,
     would not render it per incuriam, if either such omission in referring
     to previous decision does not amount to a non-consideration
     of the ratio of an earlier decision or where there is no palpable
     conflict or contradiction in the ratio of both decisions – If L.G.
     Chaudhary (II) was not conscious of the position of law laid in
     Lion Engineering, then there was no need for it to clarify that
     an award would not be annulled only on the ground of lack of
     jurisdiction – As even without the aforesaid clarification, such
     awards would not have been susceptible to annulment, if not for
     the ratio of Lion Engineering – Thus, it was held that even if L.G.
     Chaudhary (II) does not refer to the decision of Lion Engineering,
     it cannot be termed to be per incuriam, as the very factum that
     the aforesaid observations were made by L.G. Chaudhary (II) in
     paras 16, 17 and 19, shows that this Court was well aware of
     the decision of Lion Engineering, and accordingly chose to carve
     out an exception to the ratio of Lion Engineering keeping in mind
     the cleavage of judicial view that was prevailing earlier – Lion
     Engineering does not address the question whether an award may
     be annulled only on the ground of lack of jurisdiction or not – It
     does not disturb the settled position of law as regards the scope
     of Section 34 of the Act, 1996 i.e., an award may be set aside
     only if such lack of jurisdiction goes to the root of the matter and
     results in patent illegality – On the contrary, L.G. Chaudhary (II)
     specifically addresses this question in the context of the issue of
     applicability of MP Act, 1983 and explicitly states that any award
     already passed shall not be annulled only on the ground of lack
     of jurisdiction where such plea was not raised at the relevant
     stage – Thus, the aforesaid ratio of Lion Engineering by no stretch
     can be construed to mean that such a plea of jurisdiction would
     automatically result in annulment of an award, de hors the fact
     whether such lack of jurisdiction goes to the root of the award
     rendered or not – The ratio of L.G. Chaudhary (II) unlike Lion
     Engineering does not deal with whether it is permissible for such
     plea of jurisdiction to be raised under Section 34 or not, and only
     deals with the issue whether an award may be annulled only on the
     ground of jurisdiction or not, which was never an issue before Lion
     Engineering, hence there is no conflict or contradiction between
     the ratios of the aforesaid two decisions. [Para 19]
2538                                                          [2025] 5 S.C.R.

                         Supreme Court Reports


    It was held that L.G. Chaudhary (II) carved out an exception to
    the general rule that was laid in Lion Engineering, that although a
    plea of lack of jurisdiction being a question of law can be raised
    for the first time in the proceedings under Section 34 of the Act,
    1996, yet insofar as the MP Act, 1983 is concerned, particularly the
    state of flux in which the position of law regarding its applicability
    stood, in cases where either the award has already been passed
    or where the statement of defence is already been filed, and no
    plea of lack of jurisdiction or applicability of the MP Act, 1983,
    has been raised before the arbitral tribunal, then such a plea of
    jurisdiction will no longer be available, and the award cannot be
    annulled solely on such ground. [Para 20]
    Sweta Construction v. Chhattisgarh State Power Generation
    Company Ltd. (2022) SCC OnLine SC 1447 referred to where
    it was held that the law expounded in L.G. Chaudhary (II)
    insofar as those awards which have already been passed are
    concerned, should be read as one made by this Court under
    Article 142 of the Constitution to do substantive justice inter se
    the parties, keeping in mind the cleavage of judicial view earlier
    and to ensure that the objective of arbitration as an expeditious
    and effective alternative dispute resolution mechanism is not
    defeated. [Para 23]

    Arbitration and Conciliation Act, 1996 – M.P Madhyastham
    Adhikaran Adhiniyam, 1983 – The question of whether a failure
    to raise a plea of jurisdiction at the relevant stage in terms
    of Section 16 sub-section (2) of the Act, 1996 would amount
    to a ‘waiver’ or not was never examined or looked into by
    Lion Engineering – This question left to the Court exercising
    jurisdiction under Section 34:
    Held: The observations made by this Court in Lion Engineering
    that “We do not see any bar to plea of jurisdiction being raised by
    way of an objection under Section 34 of the Act even if no such
    objection was raised under Section 16” cannot be singled out and
    construed devoid of its context – The aforesaid observations have
    to be construed in light of the settled position of law by a catena
    of decisions of this Court – The decision of this Court in Pam
    Development has held that where a plea of lack of jurisdiction is
    not raised before the arbitral tribunal, such a plea cannot be raised
[2025] 5 S.C.R.                                                             2539

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

     later in the proceedings under Section 34 – Pam Development
     says this, not because such a plea is barred from being raised
     only by virtue of Section 16 sub-section (2), but rather says
     this, because such a plea is deemed to have been waived on
     account of the failure of the party in raising such a plea – Thus,
     Pam Development in no manner lays down that a plea of lack
     of jurisdiction cannot be raised in the proceedings under Section
     34 due to the bar of Section 16 sub-section (2) of the Act, 1996,
     and thus to this extent both the decisions of Pam Development
     and Lion Engineering are in tune with each other – The variance
     between the decisions of Pam Development and Lion Engineering
     is only in respect of whether a failure to raise such a plea at the
     relevant stage in terms of Section 16 sub-section (2) of the Act,
     1996 would amount to a ‘waiver’ or not, and this issue was never
     examined or looked into by Lion Engineering – The observations
     that it will be open for the respondents therein to argue that such
     an object could be raised even without a formal pleading and that
     it will be open for the appellants therein to argue the contrary,
     clearly shows that the very issue of whether such a plea can
     be allowed to be raised or not i.e., issues such as whether it is
     a purely legal plea or whether there was any waiver or not etc.
     were never decided by this Court in Lion Engineering and rather
     was left to be gone into by the court under Section 34 of the Act,
     1996. [Paras 32, 33]

     Arbitration and Conciliation Act, 1996 – M.P Madhyastham
     Adhikaran Adhiniyam, 1983 – Plea of jurisdiction cannot be
     raised for the first time in proceedings under Section 34 as
     it is deemed to have been waived, unless the party makes
     out a strong and good reason for its failure to take such a
     plea before the arbitral tribunal as per Gas Authority of India
     Ltd. v. Keti Construction (I) Ltd. reported in (2007) 5 SCC 38:
     Held: Although a plea of lack of jurisdiction, being a question of
     law, can be raised even for the first time in the proceedings under
     Section 34 as held in Lion Engineering, yet such a plea ought not
     to be allowed to be raised as it is deemed to have been waived
     in view of Section 4 of the Act, 1996 as per Pam Development,
     unless the party makes out a strong and good reason for its failure
     to take such a plea before the arbitral tribunal as per Gas Authority
     of India Ltd. v. Keti Construction (I) Ltd. reported in (2007) 5 SCC
2540                                                         [2025] 5 S.C.R.

                         Supreme Court Reports


    38, and as per the dictum of L.G. Chaudhary (II) any failure to raise
    the issue of applicability of the MP Act, 1983 before the arbitral
    tribunal is not a strong and good reason to permit raising such a
    plea in the proceedings under Section 34 of the Act, 1996. [Para 35]

    Arbitration and Conciliation Act, 1996 – M.P Madhyastham
    Adhikaran Adhiniyam, 1983 – Stage of seeking transfer to MP
    Arbitration Tribunal – Explained:
    Held: Where the arbitration proceedings are still underway, but
    no statement of defence has been filed, there it would be open
    for the parties to raise an objection of lack of jurisdiction in view
    of the applicability of MP Act, 1983 – The parties will also be
    at liberty to approach the High Court by way of a petition under
    Article 227 of the Constitution for seeking a transfer of the
    arbitration proceedings to the M.P. State Arbitration Tribunal under
    the MP Act, 1983 – Where the arbitration proceedings are still
    underway, but statement of defence has already been filed i.e.,
    the relevant stage for raising an issue of jurisdiction is already
    crossed, there it would not be open for the parties to raise an
    objection of lack of jurisdiction in view of the applicability of MP
    Act, 1983 – Furthermore, in such scenarios since the arbitration
    proceedings have already commenced and made substantial
    progress, it would not be appropriate to transfer such proceedings
    to the M.P. State Arbitration Tribunal under the MP Act, 1983,
    and the better course of action would be to let the arbitration
    proceedings conclude – As per L.G. Chaudhary (II) where the
    arbitration proceedings have concluded and an award has been
    passed, and if no objection to the jurisdiction in view of the
    applicability of MP Act, 1983 was taken at the relevant stage then
    such an award cannot be annulled only on the ground of lack of
    jurisdiction – Any award passed by an arbitral tribunal under the
    Act, 1996, where otherwise the MP Act, 1983 was applicable,
    such an award may be challenged or assailed in terms of Section
    34 and thereafter Section 37 of the Act, 1996 and other relevant
    provisions thereunder. [Para 38]

                             Case Law Cited
    M.P. Road Development Authority & Anr. v. L.G. Chaudhary
    Engineers & Contractors (2018) 10 SCC 826 – relied on.
[2025] 5 S.C.R.                                                             2541

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

     Lion Engineering Consultants v. State of Madhya Pradesh [2018] 6
     SCR 683 : (2018) 16 SCC 758; Union of India v. Pam Development
     (P) Ltd. [2014] 1 SCR 1069 : (2014) 11 SCC 366 – explained.
     VA Tech Escher Wyass Flovel Limited v. M.P. State Electricity
     Board & Anr. (2011) 13 SCC 261; MP Rural Road Development
     Authority & Anr v. L.G. Chaudhary Engineers& Contractors [2012] 2
     SCR 162 : (2012) 3 SCC 495; JMC Projects (India) Ltd v. Madhya
     Pradesh Road Development Corporation, 2020 SCC OnLine
     SC 1452; M.P. v. Anshuman Shukla [2008] 8 SCR 349 : (2008)
     7 SCC 487; Ravikant Bansal v. M.P. Rural Road Development
     Authority (2012) 3 SCC 513; MSP Infrastructure Ltd. v. M.P. Road
     Development Corpn. Ltd. [2014] 13 SCR 1331: (2015) 13 SCC
     713; Sweta Construction v. Chhattisgarh State Power Generation
     Company Ltd., 2022 SCC OnLine SC 1447; Modern Builders v.
     State of Madhya Pradesh & Anr. (2024) 10 SCC 637; Gas Authority
     of India Ltd. v. Keti Construction (I) Ltd. [2007] 6 SCR 439 : (2007)
     5 SCC 38; AC Chokshi Share Broker (P) Ltd. v. Jatin Pratap Desai
     [2025] 2 SCR 1545 : 2025 SCC OnLine SC 281 – referred to.
     Viva Highways Ltd & Ors v. M.P. Road Development Corporation
     Limited, AIR 2017 MP 103 – referred to.

                                List of Acts
     M.P. Madhyastham Adhikaran Adhiniyam, 1983; Arbitration and
     Conciliation Act, 1996; Constitution of India.
                             List of Keywords
     Arbitration; Waiver; Plea of jurisdiction; Arbitral award; Tribunal;
     Section 34.
                            Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 6856 of 2025
     From the Judgment and Order dated 07.01.2022 of the High Court
     of Madhya Pradesh Principal Seat at Jabalpur in AA No.79 of 2021

                         Appearances for Parties
     Advs. for the Appellant:
     Kaushik Laik, Ashay Kaushik, Shashank Tiwari.
     Advs. for the Respondent:
     Saurabh Mishra, Sr. Adv., Harmeet Singh Ruprah, Kanishk Sharma,
     Paras Bajpai.
2542                                                                                [2025] 5 S.C.R.

                                   Supreme Court Reports


                        Judgment / Order of the Supreme Court

                                             Judgment

       J.B. Pardiwala, J.

       For the convenience of the exposition, this judgment is divided in
       the following parts: -

                                               INDEX*

       A. FACTUAL MATRIX ................................................................                 3
       B. ISSUES FOR DETERMINATION ...........................................                          16
       C. ANALYSIS ..............................................................................       16
            i.     Can an Award passed under the Act, 1996 be annulled
                   on the ground of lack of jurisdiction where no plea of
                   applicability of MP Act, 1993 was raised before the
                   Arbitral Tribunal? ............................................................ 34
                   a.      Is there a conflict between the decisions of L.G.
                           Chaudhary (II) and Lion Engineering?...................... 37
                   b.      Whether a plea of lack of jurisdiction may be raised
                           for the first time under Section 34 of the Act, 1996
                           if no such objection was taken before the arbitral
                           tribunal? .................................................................... 51
       D. CONCLUSION ........................................................................... 58



1.     Leave Granted.
2.     This appeal arises from the judgment and order passed by the
       High Court of Madhya Pradesh, Principal Seat at Jabalpur dated
       07.01.2022 in Arbitration Appeal No. 79 of 2021 by which the appeal
       filed by the appellant herein under Section 37 of the Arbitration
       and Conciliation Act, 1996 (for short, the “Act, 1996”) came to be
       dismissed thereby affirming the order dated 20.12.2019 passed by
       the Commercial Court and 19th Additional Sessions Judge, Bhopal
       (M.P.) allowing application filed by the respondent herein under
       Section 34 of the Act, 1996.

* Ed. Note: Pagination as per the original Judgment.
[2025] 5 S.C.R.                                                           2543

                       M/s Gayatri Project Limited v.
           Madhya Pradesh Road Development Corporation Limited

3.   It appears that the respondent herein suffered an award dated
     08.07.2011 passed by the Arbitral Tribunal (for short, the “Tribunal”).
     The said award was challenged by the respondent Corporation under
     Section 34 of the Act, 1996. The appeal filed by the Corporation
     under Section 34 of the Act, 1996 came to be allowed on the ground
     that the Tribunal had no jurisdiction to pass the award in view of the
     provisions of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 (for
     short, the “MP Act, 1983”). The order passed by the Commercial
     Court and 19th Additional Sessions Judge, Bhopal (M.P.) came to be
     challenged by way of appeal before the High Court under Section 37
     of the Act, 1996. The appeal came to be dismissed.

     A.      FACTUAL MATRIX
4.   The facts giving rise to this appeal may be summarised as under:-
     (i)     The appellant executed a “works contract” dated 12.12.2005
             with the respondent for “Rehabilitation and Strengthening of
             Khargone - Barwani Road (SH-26) Project Road No. 19” &
             “Rehabilitation and Strengthening of Khargone - Bistan Road
             (SH-31) Project Road No. 20” in the State of Madhya Pradesh.
             Clause 67.3 of the “General Conditions of Contract” read with
             Clause 67.4 of the “Conditions of Particular Application” provided
             for arbitration as the means for resolution of disputes between
             the Parties.
     (ii)    The arbitration agreement mandated that the tribunal shall
             comprise of three members, one to be appointed by each
             party and the two co-arbitrators had to nominate the presiding
             arbitrator.
     (iii) Clause 67.4 of the Conditions of Particular Application – Part-II
           reads thus: -
                  “Sub-Clause 67.4 : Arbitration
                  Any dispute in respect of which:
                  a)   the decision, if any, of the Board has not become
                       final and binding pursuant to Sub-Clause 67.2,
                       and
                  b)   amicable settlement has not been reached:
2544                                              [2025] 5 S.C.R.

               Supreme Court Reports


        (i)     In the case of dispute arising between
                the Employer and a domestic Contractor
                or between the Employer and a foreign
                Contractor who opts for the application
                of the Indian Arbitration and Conciliation
                Act, 1996 related to any matter arising
                out of or connected with this Contract,
                such dispute shall be referred to the
                award of two Arbitrators (one each to be
                appointed by each party) and an Umpire
                to be appointed by the Arbitrators, or if
                there is no agreement, to be appointed
                by the Arbitration Committee of the Indian
                Council of Arbitration. The Indian Arbitration
                and Conciliation Act, 1996, the rules there
                under and any statutory modification or
                re-enactment thereof, shall apply to these
                arbitration proceedings; or (2) in the case
                of dispute arising between the Employer
                and a foreign Contractor, by application of
                the UNCITRAL Arbitration Rules related
                to any matter arising out of or connected
                with this Contract, such dispute shaft be
                referred to the award of two Arbitrators
                (one each to be appointed by each party)
                and an Umpire to be appointed by the
                Arbitrators, or if there is no agreement, to
                be appointed by the International Centre
                for Alternative Dispute Resolution (ICADR).
                The UNCITRAL Arbitration Rules shall
                apply to the arbitration proceedings.
        (ii)    Neither party shall be limited in the
                proceedings before such arbitrators to the
                evidence or arguments already put before
                the Engineer, for the purpose of obtaining
                his said decision. No such decision shall
                disqualify the Engineer from being called
                as a witness and giving evidence before
                the arbitrators or any matter whatsoever
                relevant to the dispute.
[2025] 5 S.C.R.                                                         2545

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

                    (iii) The reference to arbitration may proceed
                          notwithstanding that the Works shall not
                          then be or be alleged to be complete,
                          provided always that the obligations of the
                          Employer, the Engineer and the Contractor
                          shall not be altered by the reason of the
                          arbitration being conducted during the
                          progress of the Works. Neither party
                          shall be entitled to suspend the Works,
                          and payment to the Contractor shall be
                          continued to be made as provided by the
                          Contract.
                    (iv) If one of the parties fail to appoint its
                         arbitrators in pursuance of sub para
                         (i) and (ii) above, within 60 days after
                         receipt of the notice of the appointment
                         of its arbitrators by the other party, then
                         the Secretary General of the Permanent
                         Court of Arbitration, the Hague, in the
                         case of foreign contractors opting for the
                         application of the UNCITRAL Arbitration
                         Rules, or the Ministry of Road Transport and
                         Highways in the case of Indian contractors,
                         and the foreign contractors who opt for
                         the application of Indian Arbitration and
                         Conciliation Act 1996, as the case may
                         be, shall appoint the arbitrator. A certified
                         copy of the Secretary General’s order or
                         Ministry of Road Transport and Highways
                         order, as the case may be, making such
                         an appointment shall be furnished to both
                         the parties.
                    (v)   Arbitration proceedings shall be held at
                          Bhopal, India, and the language of the
                          arbitration proceedings and that of all
                          documents and communications between
                          the parties shall be English.
                    (vi) The decision of the majority of arbitrators
                         shall be final and binding upon both
2546                                                        [2025] 5 S.C.R.

                        Supreme Court Reports


                         parties. The expenses of the arbitrators
                         as determined by the arbitrators shall
                         be shared equally by the Employer and
                         the Contractor, However, the expenses
                         incurred by each party in connection
                         with the preparation, presentation, etc.,
                         of its case prior to, during and after the
                         arbitration proceeding shall be borne by
                         each party itself.
                    (vii) All arbitration awards shall be in writing
                          and shall state the reasons for the award.”
    (iv) This Court vide its judgment dated 14.01.2010 in the matter of
         VA Tech Escher Wyass Flovel Limited v. M.P. State Electricity
         Board & Anr. reported in (2011) 13 SCC 261, held that the
         State Act would apply only to such works contracts which did
         not have an arbitration clause.
    (v)   In VA Tech (supra), this Court held as under: -
               “1. Heard the learned counsel for the parties. This
               appeal has been filed against the impugned judgment
               of the High Court of Madhya Pradesh dated 5-3-
               2003. It appears that the appellant was awarded
               a work contract by the respondents. There was
               some dispute between the parties and there is an
               arbitration clause in the agreement. The appellant
               filed an application under Section 9 of the Arbitration
               and Conciliation Act, 1996 (for short “the 1996 Act”)
               which was rejected by the learned Additional District
               Judge and that order has been upheld by the High
               Court. Hence, this appeal.
               2. Section 7(1) of the Madhya Pradesh Madhyastham
               Adhikaran Adhiniyam, 1983 (for short “the 1983 Act”)
               provides as follows:
                    “7. Reference to Tribunal.—(1) Either party
                    to a works contract shall irrespective of
                    the fact whether the agreement contains
                    an arbitration clause or not, refer in writing
                    the dispute to the Tribunal.”
[2025] 5 S.C.R.                                                          2547

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

                3. Subsequently, Parliament enacted the 1996 Act.
                The 1996 Act only applies where there is an arbitration
                clause but it does not apply where there is none. The
                1996 Act covers all kinds of disputes including the
                dispute relating to work contracts. In our opinion, the
                1983 Act and the 1996 Act can be harmonised by
                holding that the 1983 Act only applies where there is
                no arbitration clause but it stands impliedly repealed
                by the 1996 Act where there is an arbitration clause.
                We hold accordingly. Hence, the impugned judgment
                cannot be sustained and we hold that the application
                under Section 9 of the 1996 Act was maintainable.
                4. The appeal is allowed accordingly. No costs.”
     (vi) The disputes arose between the parties from 06.08.2010
          onwards in relation to the appellant’s right to be reimbursed
          additional cost incurred by it on account of introduction of
          subsequent legislation on increase in entry tax on High-Speed
          Diesel under Clause 70.8 of the Particular Conditions of Contract.
     (vii) The appellant invoked arbitration under Clause 67.4 vide its
           notice dated 06.08.2010 and the Tribunal stood constituted on
           24.09.2010.
     (viii) The Tribunal passed a unanimous award dated 08.07.2011
            in favour of the appellant for a sum of Rs. 1,03,55,187 (i.e.
            Rs. 1.04 Crore). The relevant paras 1.19 and 3.1 respectively
            of the Arbitral Award are as follows: -
                “1.19 The valuation of the claim as assessed by the
                Engineer in its letter dt 18.03.2009 (CD - 01 pages
                20 & 21) and recommended for reimbursement is
                Rs 1,03,55,187.00. This amount is agreed to by both
                the parties as the valuation of the claim.
                3.1 The Claimant has referred two claims for
                arbitration before this AT. After careful examination
                and consideration of the written/ oral submissions
                and evidence presented by both the parties to the
                extent relevant, AT awards amounts against each
                claim as under:
2548                                                                         [2025] 5 S.C.R.

                        Supreme Court Reports



                               Amount Claimed                    Amount Awarded
               Claim No. 1     Rs. 1,03,55,187.00                Rs. 1,03,55,187.00
               Claim No. 2     Amount not specified Rs. Nil
                               ................................. ...............................
               Total Amount Rs. 1,03,55,187.00                   Rs. 1,03,55,187.00
                            plus Interest.

    (ix) As is evident from Para 1.19 of the Award quoted above, the
         quantification of this amount was in-fact recommended by the
         Engineer and had been admitted by the respondent. The Tribunal
         also awarded future interest at the rate of 10% p.a. from the
         date of the award till the date of actual payment as per para
         3.1. As of 17.02.2025, the amount payable by the respondent
         to the appellant stands at Rs. 2,44,63,775.
    (x)   The respondent challenged the award before the Civil Court
          under Section 34 of the Arbitration Act vide a petition filed on
          30.09.2011. However, the respondent in its petition admittedly
          did not challenge the jurisdiction of the Tribunal. The respondent
          has admitted this fact in Para 5 of its counter affidavit filed
          before this Court. The respondent’s grounds for challenge
          were essentially on matters of appreciation of evidence by the
          Tribunal which grounds were, in any case, untenable given the
          limited scope of Section 34 of the Arbitration Act.
    (xi) A two Judge Bench of this Court delivered a judgment in the
         matter titled MP Rural Road Development Authority & Anr v.
         L.G. Chaudhary Engineers & Contractors, reported in (2012)
         3 SCC 495, wherein it held VA Tech (supra) to be per incuriam.
         The relevant para 42 reads as under: -
               “42. Therefore, the appeal is allowed and the judgment
               of the High Court which is based on the reasoning of
               Va Tech [Va Tech Escher Wyass Flovel Ltd. v. M.P.
               SEB, Misc. Appeal No. 380 of 2003, order dated
               5-3-2003 (MP)] is set aside. This Court holds that the
               decision in Va Tech [(2011) 13 SCC 261] has been
               rendered per incuriam. In that view of the matter the
               arbitration proceeding may proceed under the M.P.
               Act of 1983 and not under the AC Act, 1996.”
[2025] 5 S.C.R.                                                        2549

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

     (xii) The Division Bench, however, differed on the point of applicability
           of the State Act to such works contracts which had been
           terminated, and this difference of opinion caused this matter
           to be referred to a larger bench in the follow terms: -
                                        “Order
                60. In view of some divergence of views expressed in
                the two judgments delivered today by us, the matter
                may be placed before the Hon’ble the Chief Justice
                of India for constituting a larger Bench to resolve
                the divergence.”
     (xiii) The appellant filed its reply dated 16.03.2012 before the Civil
            Court wherein each of the grounds raised by the respondent
            in its Section 34 petition were duly responded to.
     (xiv) Relying on the judgment of this Court in L.G. Chaudhary (I)
           (supra), the respondent moved an application dated 26.06.2012
           before the Civil Court seeking to introduce the ground of lack
           of jurisdiction in its Section 34 petition.
     (xv) A Full-Bench of the High Court delivered a judgment dated
          05.05.2017 in the matter of Viva Highways Ltd & Ors v.
          M.P. Road Development Corporation Limited, reported in
          AIR 2017 MP 103, which, in-effect, reiterated the ratio of L.G.
          Chaudhary (I) (supra) insofar as this Court had held that the
          State Act would apply to all work contracts in the State of
          Madhya Pradesh notwithstanding the existing of an arbitration
          agreement therein.
     (xvi) Relying on the Full Bench decision of the High Court, referred to
           above, the respondent moved yet one another application dated
           15.01.2018 before the Civil Court wherein it again sought to
           introduce additional grounds to its Section 34 petition contending
           lack of jurisdiction of the Tribunal.
     (xvii) A three-Judge Bench of this Court delivered a judgment on
            22.03.2018, in the matter of Lion Engineering Consultants v.
            State of Madhya Pradesh reported in (2018) 16 SCC 758,
            taking the view that objections regarding lack of jurisdiction of
            an arbitral tribunal, being a question of law, can be raised in
            Section 34 proceedings even if no such objections had been
2550                                                        [2025] 5 S.C.R.

                         Supreme Court Reports


           raised during the arbitral proceedings. Para 4 thereof is to the
           following effect: -
                “4. We find merit in the contentions raised on behalf
                of the State. We proceed on the footing that the
                amendment being beyond limitation is not to be
                allowed as the amendment is not pressed. We do
                not see any bar to plea of jurisdiction being raised by
                way of an objection under Section 34 of the Act even
                if no such objection was raised under Section 16.”
    (xviii) A three-Judge Bench of this Court passed its judgment in M.P.
            Road Development Authority & Anr v. L.G. Chaudhary
            Engineers & Contractors reported in (2018) 10 SCC 826,
            effectively stating that the State Act would prevail over the
            Arbitration Act in light of Section 2(4) of the Arbitration Act.
            The relevant para 14 is quoted below: -
                “14. In view of the above, we are of the view that the
                State law will prevail in terms of Section 2(4) of the
                Central Act. The reference under the State law was
                valid and could be decided in accordance with the
                State. Accordingly, we set aside the impugned order
                [Gammon India Ltd. v. State of M.P., WP No. 8375
                of 2010, order dated 29-11-2010 (MP)] and restore
                the proceedings before the Tribunal. The appeal is,
                accordingly, allowed in above terms.”
    (xix) In para 17 of the aforesaid judgment, however, this Court
          categorically excluded such cases where awards had already
          been made. It was held that “in such cases, if no objection to
          the jurisdiction was taken at relevant stage, the award may
          not be annulled on that ground”. It is necessary to quote para
          17 as under: -
                “17. We do not express any opinion on the applicability
                of the State Act where award has already been made.
                In such cases if no objection to the jurisdiction of the
                arbitration was taken at relevant stage, the award
                may not be annulled only on that ground.”
    (xx)    In the present case, the respondent had admittedly not raised
            the issue of jurisdiction either before the Tribunal nor in its
[2025] 5 S.C.R.                                                         2551

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

            initial petition filed under Section 34. Clearly, therefore, the
            instant case fell within the ambit of Para 17 of LG Choudhary-
            II referred to above.
     (xxi) The Civil Court passed its judgment dated 20.12.2019 allowing
           the respondent’s Section 34 petition on the ground that the
           Tribunal lacked jurisdiction to adjudicate the disputes. The Court
           observed, albeit erroneously, that para 17 of L.G. Chaudhary
           (II) (supra) did not save the instant case, inasmuch as the
           issue of jurisdiction could have been raised in the Section
           34 proceeding even though no such objection had been ever
           raised during the arbitral proceedings. The paras 12 and 13
           respectively read as follows: -
                “12. The relevant part of the Hon’ble Supreme Court’s
                precedent- “M.P. Rural Road Road Development
                Authority & Ors. Vs. M/s L.G. Chaudhary Engineering
                and Construction Civil Appeal No. 974/12 dated 13-
                03-2018” is as follows:
                     “We do not express any opinion on the
                     applicability of the State Act where award
                     has already been made. In such cases if no
                     objection to the jurisdiction of the arbitration
                     was taken at relevant stage, the award may
                     not be annulled only that ground.”
                13. It is also observable that as far as the question
                of non-objection of the Applicants on the point
                of jurisdiction of the arbitrator is concerned, the
                provisions under Section 34 (2) (B) confers special
                jurisdiction to the Courts, where it does not need
                to rely on the objections or non-objections of either
                party. Under Section 34 (2) (B) (i) if the Court is
                aware that the subject matter of the dispute is not
                arbitrable under the said act, then such an arbitral
                award can be set aside by the Court. Apart from this,
                it is also observable that Clause 28 of the Contract
                also regards such provisions as void, which confers
                jurisdiction to Courts not having jurisdiction. It has
                been clarified by the Hon’ble Supreme Court in M/s
                L.G. Choudhary with regards to the above precedent
2552                                                        [2025] 5 S.C.R.

                       Supreme Court Reports


              that wherever award has been passed, even in those
              cases, the above objection can be raised at the time
              of application under Section 34 of the Central Act.
              It is for this reason the argument made by the Non-
              Applicant in this context is not just.”
    (xxii) This Court in JMC Projects (India) Ltd v. Madhya Pradesh
           Road Development Corporation reported in (2020) SCC
           OnLine SC 1452 took note of the exception carved out in
           L.G. Chaudhary (II) (supra). In a case based on similar facts,
           this Court held that the award should not be set aside on
           the ground of jurisdiction alone. The order dated 10.01.2020
           passed by this Court is as follows: -
              “Leave granted.
              Mr. K. V. Vishwanathan, learned senior counsel
              appearing for the appellant, has shown us our order
              dated 08.03.2018 in Madhya Pradesh Rural Road
              Development Authority & Anr. v. M/s. L. G. Chaudhary
              Engineers and Contractors (Civil Appeal No. 974 of
              2012) (being the lead case) and has pointed out
              paragraph Nos. 22 to 27 thereof which are quoted
              hereinbelow:
                   “C.A. No. 2751 of 2018 @ SLP (C)No.
                   11615/2012, C.A. No. 2753 of 2018 @ SLP
                   (C)No. 11617/2012, C.A. No. 2754 of 2018
                   @ SLP (C)No. 11618/2012, C.A. No. 2755
                   of 2018 @ SLP (C)No. 11619/2012, C.A.
                   Nos. 2756-2757 of 2018 @ SLP (C)Nos.
                   11633-11634/2012, C.A. Nos. 2758-2759
                   of 2018 @ SLP (C)Nos. 11631-11632/2012
                   & C.A. Nos. 2760-2761 of 2018 @ SLP
                   (C)No. 11628- 11629/2012:
                   22. We do not express any opinion on the
                   applicability of the State Act where award
                   has already been made. In such cases if no
                   objection to the jurisdiction of the arbitration
                   was taken at relevant stage, the award
                   may not be annulled only on that ground.
[2025] 5 S.C.R.                                                       2553

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

                     23. The appeals are, accordingly, disposed
                     of.
                     C.A. No. 2616@ SLP (C)No. 35641/2011:
                     24. Leave granted.
                     25. In view of order passed in C.A. No.
                     2751 of 2018 @ SLP (C)No. 16615/2012,
                     no objection having been raised by the
                     respondents in terms of Section 16(2) of
                     the Arbitration and Conciliation Act, 1996 at
                     appropriate stage within the time stipulated,
                     the award could not have been annulled.
                     26. Accordingly, this appeal is allowed, the
                     impugned judgment is set aside and the
                     award is restored.
                     27. It is, however make it clear that
                     this order will not debar proceedings
                     under Section 34 of the Arbitration and
                     Conciliation Act, 1996.”
                It is clear that in the present case, an Award has
                already been passed which is dated 07.01.2011.
                This being the case, and following the aforesaid
                judgment of this Court, the impugned judgment dated
                24.10.2018 is set aside. The Section 34 proceedings
                will continue with all objections that may be raised
                but excluding the objection as to the applicability
                of the Madhya Pradesh Madhyastham Adhikaran
                Adhiniyam, 1983.
                The matter stands disposed of accordingly.”
     (xxiii) The High Court passed the impugned judgment dated
             07.01.2022 under Section 37 of the Act of 1996. The High
             Court held that the Tribunal lacked jurisdiction to adjudicate
             the disputes between the parties. The High Court, in effect,
             held that the exception carved out in L.G. Chaudhary (II)
             (supra), as reiterated in JMC Projects (supra), could not be
             relied upon as JMC Projects (supra) had not considered the
2554                                                    [2025] 5 S.C.R.

                    Supreme Court Reports


        law laid down by this Court in Lion Engineering (supra).
        Paras 21, 22 and 23 respectively of the impugned judgment
        dated 07.01.2022 are as under: -
           “21. Now, we shall consider the specific objection of
           the appellant regarding lack of objection on jurisdiction
           under Section 16(2) of the Act of 1996 before the
           arbitral tribunal in view of order dated 13.03.2018 in
           C.A. No. 2616 of 201810 and in M/s. JMC Projects
           (India) Ltd.
           22. It is true that the Hon’ble Supreme Court in its
           order dated 13.03.2018 in C.A.No.2616 of 2018 has
           held that award cannot be annulled on the ground
           of lack of jurisdiction if the objection under Section
           16(2) was not taken before the arbitral tribunal. This
           view was based on a decision of two judge bench
           of the Hon’ble Supreme Court in MSP Infrastructure
           Ltd. Vs. M.P. Road Development Corp. Ltd.
           23. However, a bench of three-judges of the Hon’ble
           Supreme Court in a subsequent decision in Lion Engg.
           Consultants Vs. State of M.P. partly overruled MSP
           Infrastructure Ltd and held that the objection regarding
           lack of jurisdiction can be taken under Section 34 of
           the Act of 1996, even if no objection under Section
           16(2) was taken before the arbitral tribunal. Thus, in
           view of the subsequent decision of the larger bench,
           this Court is of the view that the objection regarding
           lack of jurisdiction could have been taken before the
           learned trial Court under Section 34 of the Act of 1996,
           even though no such objection was taken before the
           arbitral tribunal under Section 16(2) of the Act. The
           Hon’ble Supreme Court in the matter of M/s. JMC
           Projects (India) Ltd. has not referred to the decision in
           the matter of Lion Engineers which was subsequent
           to the decision of C.A. No. 2616 of 2018. Hence,
           The learned trial Court acted in accordance with law
           while entertaining the objection under Section 34 of
           the 1996 Act and setting aside the arbitral award on
           the ground of lack of jurisdiction.”
[2025] 5 S.C.R.                                                         2555

                       M/s Gayatri Project Limited v.
           Madhya Pradesh Road Development Corporation Limited

     B.      ISSUES FOR DETERMINATION
5.   Having heard the learned counsels appearing for the parties and
     having gone through the materials on record, the two pivotal questions
     that fall for our consideration are as under: -
     I.      Whether an arbitral award rendered under the Act, 1996 where
             the arbitration proceedings was to be governed by the MP Act,
             1983, can be set-aside or annulled solely on the ground of lack
             of jurisdiction, even when no such plea was raised before the
             arbitral tribunal in terms of Section 16 sub-section (2) of the
             Act, 1996?
     II.     Whether the decision of this Court in LG Choudhary (II) (supra)
             could be said to be per incuriam for not having taken into
             consideration the decision of this Court in Lion Engineering
             (supra)? In other words, whether there is any conflict between
             the decisions of this Court in Lion Engineering (supra) and LG
             Choudhary (II) (supra), insofar as the observations pertaining
             to the stage at which a plea of lack of jurisdiction may be raised
             under the Act, 1996, are concerned?

     C.      ANALYSIS
6.   The MP Act, 1983 was first looked into by this Court in the case of
     State of M.P. v. Anshuman Shukla reported in (2008) 7 SCC 487.
     This Court speaking through S.B. Sinha J. (as he then was) after
     going through the various provisions of the MP Act, 1983, observed
     that the said legislation was a special Act that was enacted for
     providing compulsory arbitration on disputes to which the State
     Government or a public undertaking (wholly or substantially owned
     or controlled by the State Government), is a party, and for matters
     incidental thereto or connected therewith. It observed that the MP
     Act, 1983 postulates creation of a separate forum for the purpose of
     determination of disputes arising inter alia out of the works contract.
     The Madhya Pradesh Arbitration Tribunal established thereunder, is
     not a domestic or an ad hoc arbitral tribunal, by virtue of the unique
     scheme of provisions that govern its framework. The members of the
     MP Arbitral Tribunal are not nominated by the parties, the Tribunal
     has the power to reject a reference for arbitration; it has the power to
     suo-motu summon records; take note of evidence; award costs and
2556                                                     [2025] 5 S.C.R.

                       Supreme Court Reports


    interests. The Chairperson of the M.P. State Arbitration Tribunal has
    the power to refer disputes to another bench. It contains provisions,
    prescribing a special time-limit and procedure for the passing of an
    award and for its subsequent challenge, respectively. Accordingly,
    this Court held that the provisions of the Arbitration Act, 1940 (for
    short, the “Act, 1940”) and the Act, 1996 would have no application
    to arbitrations governed by the MP Act, 1983 or any award passed
    thereunder. The relevant observations read as under: -
         “3. Before embarking on the said question we may notice
         the statutory provisions of the Act for resolution of the
         legal issue.
         4. The Act came into force with effect from 1-3-1985. It
         was enacted to provide for the establishment of a tribunal
         to arbitrate on disputes to which the State Government
         or a public undertaking (wholly or substantially owned or
         controlled by the State Government), is a party, and for
         matters incidental thereto or connected therewith.
         5. The Arbitral Tribunal is constituted in terms of Section
         3 of the Act for resolving all disputes and differences
         pertaining to works contract or arising out of or connected
         with execution, discharge or satisfaction of any such works
         contract.
         6. Section 7 provides for reference to the Tribunal. Such
         reference may be made irrespective of the fact as to
         whether the agreement contains an arbitration clause or
         not. Section 7-A provides for the particulars on the basis
         whereof the reference petition is to be filed. Section 7-B
         provides for limitation for filing an application [...]
         7. Chapter IV of the Act contains Sections 16 to 18. Section
         16 deals with passing of an award by the Tribunal and/or
         its Benches. Section 17 gives finality to the award made
         thereunder. Such awards made, in terms of Section 18
         would be deemed to be a decree within the meaning of
         Section 2(2) of the Code of Civil Procedure, 1908. Section
         19 confers a power of revision on the High Court [...]

                 xxx                 xxx                  xxx
[2025] 5 S.C.R.                                                             2557

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

           14. The Act is a special Act. It provided for compulsory
           arbitration. It provides for a reference. The Tribunal has the
           power of rejecting the reference at the threshold. It provides
           for a special limitation. It fixes a time-limit for passing an
           award. Section 14 of the Act provides that proceeding and
           the award can be challenged under special circumstances.
           Section 17, as noticed hereinbefore, provides for finality
           of the award, notwithstanding anything to the contrary
           contained in any other law relating to arbitration.

                    xxx                  xxx                  xxx
           28. The provisions of the Act referred to hereinbefore
           clearly postulate that the State of Madhya Pradesh has
           created a separate forum for the purpose of determination
           of disputes arising inter alia out of the works contract. The
           Tribunal is not one which can be said to be a domestic
           tribunal. The Members of the Tribunal are not nominated
           by the parties. The disputants do not have any control over
           their appointment. The Tribunal may reject a reference
           at the threshold. It has the power to summon records. It
           has the power to record evidence. Its functions are not
           limited to one Bench. The Chairman of the Tribunal can
           refer the disputes to another Bench. Its decision is final. It
           can award costs. It can award interests. The finality of the
           decision is fortified by a legal fiction created by making an
           award a decree of a civil court. It is executable as a decree
           of a civil court. The award of the Arbitral Tribunal is not
           subject to the provisions of the Arbitration Act, 1940 and
           the Arbitration and Conciliation Act, 1996. The provisions
           of the said Acts have no application.
           29. We are, therefore, of the opinion that the Tribunal for all
           intent and purport is a court. The Tribunal has to determine
           a lis. There are two parties before it. Its proceedings are
           judicial proceedings subject to the revisional order which
           may be passed by the High Court.
                                                   (Emphasis supplied)

7.   In VA Tech (supra) the short point that fell for the consideration
     of this Court was whether, an application under Section 9 of the
2558                                                        [2025] 5 S.C.R.

                         Supreme Court Reports


     Act, 1996 could be said to be maintainable, where the arbitration
     proceedings were governed by the MP Act, 1983. In other words,
     where the dispute had to be resolved by way of arbitration in
     terms of the MP Act, 1983, more particularly Section 7(1), thereof,
     could the Act, 1996 be said to also be applicable simultaneously
     or alternatively for such disputes. This Court held that since both
     the MP Act, 1983 and the Act, 1996 respectively were similar in
     nature inasmuch as both provided frameworks for resolution of
     dispute by way of arbitration, any potential conflict or overlap in
     their application ought to be construed harmoniously. This Court
     observed that the gravamen of Section 7 of the MP Act, 1983 which
     provided for reference to arbitral tribunal was only to make arbitration
     compulsory for resolving disputes arising out of work contracts
     involving either the State Government or a Public Undertaking of
     Madhya Pradesh. As per VA Tech (supra) what has been conveyed
     in so many words by the plain language of Section 7 of the MP
     Act, 1983 is only to mandate arbitration in respect of such work
     contracts, and the said provision by no means in the opinion of
     this Court was intended to override any legislation enacted by the
     Parliament, be it the Act, 1996 (sic or the Arbitration Act, 1940).
     As per VA Tech (supra), Section 7 of the MP Act, 1983 cannot be
     construed to oust the application of Act, 1996 to the arbitration
     clauses which are otherwise governed by the provisions of the said
     Act. Accordingly, it held that the MP Act, 1983 would apply only to
     the disputes pertaining to work contracts as aforementioned which
     do not contain an arbitration clause i.e., where the Act, 1996 is
     otherwise inapplicable. In all other disputes, where the work contract
     contains an arbitration clause, the Act, 1996 would be applicable
     and the MP Act, 1983 inapplicable.
8.   Remarkably, the decision of this Court in VA Tech (supra) inadvertently
     failed to take into consideration and refer to its earlier decision in
     Anshuman Shukla (supra).
9.   However, interestingly in the subsequent decision of Ravikant
     Bansal v. M.P. Rural Road Development Authority reported in
     (2012) 3 SCC 513, a coordinate bench of this Court comprising of
     one of the judges (Markandey Katju J.) who had earlier delivered the
     decision of VA Tech (supra), held that the ratio of VA Tech (supra)
     would not be applicable where the arbitration clause itself expressly
     stipulates that the arbitration would take place before the Madhya
[2025] 5 S.C.R.                                                           2559

                       M/s Gayatri Project Limited v.
           Madhya Pradesh Road Development Corporation Limited

     Pradesh Arbitration Tribunal in terms of the MP Act, 1983. In other
     words, Ravikant Bansal (supra) held that where the arbitration
     clause stipulates that the arbitration proceedings have to take place
     in terms of the MP Act, 1983 or by the arbitral tribunal established
     thereunder, then the Act, 1996 would have no application. The
     relevant observations read as under: -
             “2. This petition has been filed against the judgment
             and order dated 11-3-2011 passed by the High Court of
             Madhya Pradesh at Gwalior Bench in Ravikant Bansal
             v. M.P. Rural Road Development Authority. The learned
             counsel for the petitioner has relied on a decision of this
             Court in Va Tech Escher Wyass Flovel Ltd. v. M.P. SEB2
             decided on 14-1-2010.
             3. We are of the opinion that the aforesaid decision is
             distinguishable because in the present case the arbitration
             clause itself mentions that the arbitration will be by the
             Madhya Pradesh Arbitration Tribunal. Hence, in this case
             arbitration has to be done by the Tribunal.”
10. In view of the conflict between Anshuman Shukla (supra) and VA
    Tech (supra), and that between VA Tech (supra) and Ravikant
    Bansal (supra), the issue as regards the applicability of the MP Act,
    1983 viz- à-viz the Act, 1996 once again fell for the consideration
    of this Court in L.G. Chaudhary (I) (supra). In L.G. Chaudhary
    (I) (supra) the question before this Court was whether the MP Act,
    1983 and the arbitral tribunal statutorily established thereunder,
    would continue to have jurisdiction over disputes pertaining to work
    contracts as mentioned in Section(s) 2(d) and 2(i) thereunder, in
    view of the subsequent enactment of the Act, 1996.
11. In L.G. Chaudhary (I) (supra), A.K. Ganguly J. (as he then was)
    held that the MP Act, 1983 is a special law providing for statutory
    arbitration in the State of Madhya Pradesh. The opinion of A.K.
    Ganguly J. is in two parts: -
     (i)     First, placing reliance on the decision of Anshuman Shukla
             (supra), it was held that the MP Arbitral Tribunal established
             thereunder had distinct features from an ordinary arbitral
             tribunal constituted in terms of the Act, 1996. It observed
             that the structure of the M.P. State Arbitration Tribunal, the
2560                                                    [2025] 5 S.C.R.

                      Supreme Court Reports


        manner of appointment and term of office of its members was
        significantly at variance from that under the Act, 1996. Unlike
        the Act, 1996, the MP Act, 1983 vests the MP Arbitral Tribunal
        with inherent powers that may be necessary for the ends of
        justice or to prevent abuse of the process of the Tribunal.
        Even the procedure for making a reference to arbitration, for
        passing an award thereunder, thereafter challenging it and
        the limitation period thereof, was in stark contrast to the Act,
        1996. Accordingly, it held that in view of the unique statutory
        provisions governing the framework of arbitration under the
        MP Act, 1983 that are either absent or at variance with the
        Act, 1996, shows that there is inconsistency between the
        two legislations, and that the M.P. State Arbitration Tribunal
        as held in Anshuman Shukla (supra) is akin to a statutory
        forum for adjudication of disputes in contrast to an arbitral
        tribunal under the Act, 1996 whose edifice is party autonomy.
        Accordingly, it held VA Tech (supra) to be per incuriam. The
        relevant observations read as under: -
             “18. If this Court compares the provisions of the M.P.
             Act with the AC Act, 1996 then the Court finds that
             the provisions of the M.P. Act are inconsistent with
             the provisions of the AC Act, 1996. The M.P. Act is
             a special law providing for statutory arbitration in
             the State of Madhya Pradesh even in the absence
             of arbitration agreement. Under the provisions of
             the AC Act, 1996 in the absence of an arbitration
             agreement, arbitration is not possible. There is also
             difference in the formation of the Arbitration Tribunal
             as is clear from Section 2(1)(d) of the AC Act, 1996.
             Again, under the AC Act, 1996, “Arbitral Tribunal” is
             defined under Section 2(1)(d) as a sole arbitrator or
             a panel of arbitrators. But under the M.P. Act such
             a Tribunal is created under Sections 3 and 4 of the
             Act. And under the M.P. Act “dispute” has a special
             meaning as defined under Section 2(d) of the Act
             whereas “dispute” has not been defined under the
             AC Act, 1996.

                    xxx                xxx               xxx
[2025] 5 S.C.R.                                                           2561

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

                20. The structure of the Tribunal under the M.P. Act
                is also different from the structure of a Tribunal under
                the AC Act, 1996. It is clear from Section 4 of the
                M.P. Act that the composition of the Tribunal and their
                qualification is statutorily provided [...]
                21. The term of office and salaries and allowances
                are also statutorily provided under Sections 5 and 6
                of the M.P. Act. Section 8 provides for the procedure
                to be followed by the Tribunal on receipt of reference
                and Section 9 provides for the constitution of Benches
                and the Chairman’s power of distribution of business.
                Under Section 16(2) of the M.P. Act there is a time-
                limit for giving the award which is absent in the AC
                Act, 1996.
                22. Section 17-A of the M.P. Act confers inherent
                power on the Arbitral Tribunal to make orders as may
                be necessary for the ends of justice or to prevent
                abuse of the process of the Tribunal. Section 17-B
                also provides for power conferred on the Tribunal
                for correction of clerical or arithmetical mistakes. No
                such power is given to an Arbitral Tribunal under the
                AC Act, 1996. Section 19 of the M.P. Act gives the
                High Court the suo motu power of revision. The High
                Court has also been given the power of revision to be
                exercised on an application made by an aggrieved
                party within three months of the award. While doing
                so, the High Court is to act like a Revisional Court
                under Section 115 CPC.
                23. It is clear from the aforesaid enumeration of
                the statutory provisions that under the M.P. Act the
                parties’ autonomy in the choice of Arbitral Tribunal
                is not there.
                24. In State of M.P. v. Anshuman Shukla this Court
                while referring to the M.P. Act and dealing with the
                nature of the Arbitral Tribunal constituted under the
                said Act held that the said Act is a special Act and
                provides for compulsory arbitration. It provides for
                a reference and the Tribunal has been given the
2562                                                         [2025] 5 S.C.R.

                         Supreme Court Reports


                power of rejecting the reference at the threshold.
                It also held that the M.P. Act provides for a special
                limitation and fixes a time-limit for passing an award.
                It has also been held that Section 14 of the M.P. Act
                provides that the award can be challenged under
                special circumstances and Section 17 provides for
                finality of the award, notwithstanding anything to
                the contrary contained in any other law relating to
                arbitration. All these features of the Act were pointed
                out by this Court in Anshuman Shukla to show that
                there is inconsistency between the provisions of the
                AC Act, 1996 and those of the M.P. Act.

                       xxx                xxx                xxx
                26. It is clear, therefore, that in view of the aforesaid
                finding of a coordinate Bench of this Court on the
                distinct features of an Arbitral Tribunal under the said
                M.P. Act in Anshuman Shukla case5 the provisions of
                the M.P. Act are saved under Section 2(4) of the AC
                Act, 1996. This Court while rendering the decision in
                Va Tech has not either noticed the previous decision
                of the coordinate Bench of this Court in Anshuman
                Shukla or the provisions of Section 2(4) of the AC
                Act, 1996. Therefore, we are constrained to hold that
                the decision of this Court in Va Tech was rendered
                per incuriam.”
                                                  (Emphasis supplied)

    (ii)   Secondly, A.K. Ganguly J. negativing the argument of there
           being a repugnancy between the Act, 1996 and the MP Act,
           1983, observed that since the Act, 1996, more particularly
           Section 2 sub-section (4) clearly stipulates that Part I of the
           Act, 1996 shall apply insofar as the provisions thereunder are
           not inconsistent with the other enactment or with any other
           rule made thereunder, the MP Act, 1983 respectively and its
           provisions will have precedence and continue to apply over an
           above the Act, 1996. It further observed that although the Act,
           1996 came into force after the MP Act, 1983 yet there is nothing
           to indicate that the Act, 1996 either expressly or impliedly has
[2025] 5 S.C.R.                                                          2563

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

           repealed the MP Act, 1983. The aforesaid is reinforced from
           Section 2 sub-section (5) of the Act, 1996 which contains a
           saving clause for other laws being already in force in India. On
           the contrary, Section 85 of the Act, 1996 when read with Section
           2 sub-section(s) (4) and (5) shows that the legislature had no
           such intention to repeal the MP Act, 1983. Even otherwise, the
           subject-matter of the MP Act, 1983 falls within the concurrent
           list, and the said Act had received the assent of the President
           while the erstwhile Arbitration Act, 1940 was in force. Both
           the Acts operated in view of Section 46 of the 1940 Act. The
           relevant observations read as under: -
           “16. If this Court looks at Section 2(4) of the AC Act,
           1996, it will appear that Part I of the AC Act, 1996 which
           is from Section 2 to Section 43, shall, except sub-section
           (1) of Section 40 and Sections 41 and 43, apply to every
           arbitration under any other enactment for the time being in
           force where the arbitration was pursuant to an arbitration
           agreement except insofar as the provisions of this Part i.e.
           Part I are inconsistent with the other enactment or with
           any other rule made thereunder.
           17. Similar provision relating to statutory arbitration was
           also there in Section 46 of the Arbitration Act, 1940. [...]

                    xxx                xxx                  xxx
           36. In reply the learned counsel for the respondent only
           submitted that the M.P. Act is repugnant to the AC Act,
           1996 since the same is a later Act made by Parliament.
           The learned counsel referred to the provisions of Article
           254 of the Constitution. The learned counsel also urged
           that in view of the provision of Section 85 of the AC Act,
           1996, the M.P. Act stands impliedly repealed.
           37. The said argument cannot be accepted. The provision
           for repeal under Section 85 of the AC Act, 1996 does not
           show that there is any express repeal of the M.P. Act.
           Apart from that, the provision of Section 2(4) of the AC
           Act clearly militates against the aforesaid submissions.
           38. The argument of repugnancy is also not tenable. Entry
           13 of the Concurrent List in the Seventh Schedule of the
2564                                                       [2025] 5 S.C.R.

                         Supreme Court Reports


          Constitution runs as follows [...] In view of the aforesaid
          entry, the State Government is competent to enact laws
          in relation to arbitration.
          39. The M.P. Act of 1983 was made when the previous
          Arbitration Act of 1940 was in the field. That Act of 1940
          was a Central law. Both the Acts operated in view of
          Section 46 of the 1940 Act. The M.P. Act, 1983 was
          reserved for the assent of the President and admittedly
          received the same on 17-10-1983 which was published
          in the Madhya Pradesh Gazette Extraordinary dated 12-
          10-1983. Therefore, the requirement of Article 254(2) of
          the Constitution was satisfied. Thus, the M.P. Act of 1983
          prevails in the State of Madhya Pradesh. Thereafter, the
          AC Act, 1996 was enacted by Parliament repealing the
          earlier laws of arbitration of 1940. It has also been noted
          that the AC Act, 1996 saves the provisions of the M.P.
          Act, 1983 under Sections 2(4) and 2(5) thereof. Therefore,
          there cannot be any repugnancy. [...]

                   xxx                 xxx                 xxx
          41. It is clear from the aforesaid observations that in the
          instant case the latter Act made by Parliament i.e. the AC
          Act, 1996 clearly showed an intention to the effect that the
          State law of arbitration i.e. the M.P. Act should operate in
          the State of Madhya Pradesh in respect of certain specified
          types of arbitrations which are under the M.P. Act, 1983.
          This is clear from Sections 2(4) and 2(5) of the AC Act,
          1996. Therefore, there is no substance in the argument
          of repugnancy and is accordingly rejected.”
                                                (Emphasis supplied)

12. However, Gyan Sudha Misra J. in her dissenting opinion in L.G.
    Chaudhary (I) (supra) held that where the nature of the dispute
    does not fall within the definition of work contract under Section
    2(i) of the MP Act, 1983, such disputes can be resolved by way of
    arbitration under the Act, 1996, notwithstanding the fact that such work
    contract is otherwise governed by the MP Act, 1983. She observed
    that a reference to arbitration under the MP Act, 1983 postulates
    two requirements, namely; (i) the existence of a ‘works contract’
[2025] 5 S.C.R.                                                            2565

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

     involving either the State Government or a Public Undertaking of
     Madhya Pradesh and (ii) that such contract pertains to the execution
     of any of the work enumerated in Section 2(i) thereof. Section 2(i) in
     turn lays down in explicit terms as to the nature and scope of “works
     contract” by enumerating the specific nature of disputes that would
     be covered, i.e., “work relating to construction, repair or maintenance
     ... supply of goods or material and all other matters relating to the
     execution of any of the said works”. However, since Section 2(i) of
     the MP Act, 1983 only covers specific and well-defined ‘works’ and is
     applicable only in respect of disputes pertaining to its execution, and
     does not include disputes of repudiation, cancellation or termination
     of such works, the legal and logical consequence of the aforesaid
     would be that, insofar as the dispute is not of the nature enumerated
     in Section 2(i) of the MP Act, 1983, such dispute would be outside
     the jurisdiction of the M.P. State Arbitration Tribunal, and can be
     decided by an arbitral tribunal in terms of the Act, 1996, irrespective
     of whether arbitration clause requires the dispute to be referred to
     arbitration under the MP Act, 1983. The relevant observations read
     as under: -
           “46. On perusal of the aforesaid provision enumerated
           under Section 7, it is explicitly clear that the matter in the
           event of existence of a dispute between the parties in
           certain categories of cases where the State of Madhya
           Pradesh is a contracting party, the dispute shall be referred
           in writing to the Tribunal irrespective of the fact whether
           the agreement contains an arbitration clause or not. From
           this provision it is clearly apparent that reference of any
           dispute to the Tribunal postulates an existence of a works
           contract and in the definition of “works contract” under
           Section 2(i) of the M.P. Arbitration Tribunal Act, 1983, it
           has clearly and unequivocally been specified as to what
           is a “works contract” in relation to which the dispute is
           required to be referred in writing to the Tribunal.

                    xxx                xxx                  xxx
           48. Thus, on a perusal of the definition of “works contract”,
           it is manifestly clear that while the “works contract” means
           an agreement pertaining to matters relating to the execution
           of any of the work enumerated in the definition of “works
2566                                                     [2025] 5 S.C.R.

                      Supreme Court Reports


        contract”, the same does not include the dispute pertaining
        to termination, cancellation or repudiation of works contract
        and the entire nature of transaction laid down therein
        relates to disputes which arise out of execution of the
        nature of work specified in the “works contract”. However,
        the question whether the “works contract” has been legally
        repudiated and rightly cancelled or not is the question or
        dispute pertaining to termination of works contract and has
        not been incorporated even remotely within the definition
        of “works contract”.
        49. In view of this, the legal and logical consequence
        which can be reasonably drawn from the definition of
        “works contract” would be, that if there is a dispute
        between the contracting parties for any reason relating
        to works contract which include execution of any work
        relating to construction, repair or maintenance of any
        building or superstructure, dam, weir, canal, reservoir,
        tank, lake, road, well, bridge, culvert, factory, workshop,
        powerhouse, transformers or such other works of the
        State Government or public undertaking including an
        agreement for the supply of goods or material and all other
        matters relating to the execution of any of the said works,
        the same would fall within the ambit of the definition of
        “works contract” and hence all disputes pertaining to or
        arising out of execution of the works contract will have
        to be referred to the M.P. State Arbitration Tribunal as
        envisaged under Section 7 of the 1983 Act. Hence, in
        addition to the reasons assigned in the judgment and
        order of learned Brother Ganguly, J. disputes arising
        out of execution of works contract have to be referred
        to the M.P. State Arbitration Tribunal and not under the
        Arbitration and Conciliation Act, 1996.

                xxx                  xxx                 xxx
        51. [...] But the same cannot be allowed to be raised
        under the M.P. Act of 1983 since the definition of “works
        contract” unambiguously lays down in explicit terms as
        to what is the nature and scope of “works contract” and
        further enumerates the specific nature of disputes arising
[2025] 5 S.C.R.                                                             2567

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

           out of the execution of works contract which would come
           within the definition of a “works contract”. However, the
           same does not even vaguely include the issue or dispute
           arising out of cancellation and termination of contract due
           to which this question, in my considered opinion, would
           not fall within the jurisdiction of the M.P. State Arbitration
           Tribunal so as to be referred for adjudication arising out
           of its termination.
           52. As already stated, fallout certainly would be otherwise
           if the matter were to be adjudicated by an arbitrator
           appointed under the Arbitration and Conciliation Act, 1996
           and that would be in view of the ratio of the decisions of
           the Supreme Court referred to hereinbefore which has
           held it permissible for the arbitrator to adjudicate even
           the dispute arising out of cancellation or termination of an
           agreement or contract. This however, cannot be allowed
           to broaden or expand the ambit and scope of the M.P.
           Act of 1983 where the State Legislature has passed a
           specific legislation in respect of certain specified types of
           arbitration determining as to what is the nature of disputes
           to be referred to the M.P. State Arbitration Tribunal and
           that specifically permits the reference of dispute arising out
           of execution of contract but clearly leaves out any dispute
           arising out of termination, cancellation or repudiation of
           “works contract”.
           53. In order to clarify the point further, what needs to be
           emphasised is that if the nature of dispute referred to
           the arbitrator like the instant matter, related to a dispute
           pertaining to construction, repair, maintenance of any
           building or superstructure, dam or for the reasons stated
           within the definition of “works contract”, the matter may be
           referred to the M.P. Tribunal in view of the fact that if there
           is a dispute in relation to execution of a works contract,
           then irrespective of the fact whether the agreement
           contains an arbitration clause or not, the dispute is
           required to be referred to the M.P. State Arbitration Tribunal
           for adjudication. But when the contract itself has been
           terminated, cancelled or repudiated as it has happened
           in the instant case, then the nature of dispute does not
2568                                                    [2025] 5 S.C.R.

                      Supreme Court Reports


        fall within the definition of “works contract” for the sole
        reason that it does not include any dispute pertaining to
        cancellation of a works contract implying that when the
        works contract itself is not in existence by virtue of its
        cancellation, the dispute cannot be referred to the M.P.
        State Arbitration Tribunal but may have to be decided by an
        arbitrator appointed under the Arbitration and Conciliation
        Act, 1996.
        54. Hence, if the nature of the dispute is such which falls
        within the definition of “works contract” under Section 2(i)
        of the M.P. Act, 1983 and one of the contracting parties to
        the agreement is the State of M.P., then irrespective of an
        arbitration agreement the dispute will have to be referred
        to the Tribunal in terms of Section 7 of the Act of 1983.
        But if the works contract itself has been repudiated and
        hence not in existence at all by virtue of its cancellation/
        termination, then in my considered view, the dispute will
        have to be referred to an independent arbitrator to be
        appointed under the Arbitration and Conciliation Act, 1996
        since the M.P. Act, 1983 envisages reference of a dispute
        to the State Tribunal only in respect of certain specified
        types of arbitration enumerated under Section 2(i) of the
        M.P. Act, 1983.

                xxx                 xxx                xxx
        57. Thus, the sum and substance of what I wish to
        emphasise is that the question as to whether the dispute
        would be referred to the M.P. Tribunal in terms of Section
        7 of the M.P. Act of 1983 or to an independent arbitrator
        under the Arbitration and Conciliation Act, 1996 will
        depend upon the factum whether the works contract is
        existing between the parties or not out of which the dispute
        has arisen. In case, the works contract itself has been
        repudiated/cancelled, then, in view of its non-existence,
        Section 7 of the M.P. Act pertaining to reference of dispute
        to the Tribunal would not come into play at all by virtue
        of the fact that the dispute relating to execution of works
        contract alone can be referred to the Tribunal in view of
        the specific nature of works contract enumerated within
[2025] 5 S.C.R.                                                          2569

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

           the definition of works contract under the Act of 1983.
           However, when the works contract itself becomes non-
           existent as a consequence of its cancellation, the matter
           will have to be referred to an independent arbitrator under
           the Arbitration and Conciliation Act, 1996 and not to the
           M.P. State Arbitration Tribunal.
           58. Thus, while holding that the M.P. Act, 1983 should
           operate in the State of M.P. in respect of certain specified
           types of arbitration, the appointment of an independent
           arbitrator by the High Court under the Arbitration and
           Conciliation Act, 1996 needs to be sustained since the
           works contract itself is not in existence by virtue of its
           cancellation and hence this part of the dispute could not
           have been referred to the M.P. State Tribunal.”
                                                 (Emphasis supplied)

13. In view of the cleavage of opinion expressed by this Court in L.G.
    Chaudhary (I) (supra), the issue of applicability of the MP Act, 1983
    viz- à-viz the Act, 1996 came to be referred to a three-Judge Bench
    of this Court, culminating into the decision of L.G. Chaudhary (II)
    (supra). Answering the aforesaid reference, L.G. Chaudhary (II)
    (supra) held that the definition of “dispute” under Section 2(d) of
    the sic Act, 1996 (which due to an inadvertent typographical error in
    para 5 of L.G. Chaudhary (II) (supra) was written as the Act, 1996
    instead of MP Act, 1983) would cover and include any dispute that
    arises after the termination, repudiation or cancellation of the contract
    or pertains thereto. It observed that the dissenting opinion of Gyan
    Sudha Misra J. in L.G. Chaudhary (I) (supra) failed to notice the said
    provision i.e. Section 2(d) of the MP Act, 1983, and accordingly, it
    held that the view expressed by A.K. Ganguly J. in L.G. Chaudhary
    (I) (supra) that reference to arbitration for disputes covered under the
    MP Act, 1983 would mandatorily lie before the M.P. State Arbitration
    Tribunal in terms of the said Act and would not be governed the
    provisions of the Act, 1996, is the correct interpretation, and the
    law laid down by VA Tech (supra) was held to be per incuriam. The
    relevant observations read as under: -
           “4. When the matter was considered by a Bench of this
           Court on 24-1-2012 (order in M.P. Rural Road Development
2570                                                       [2025] 5 S.C.R.

                        Supreme Court Reports


          Authority v. L.G. Chaudhary Engineers and Contractors),
          this Court held that the judgment in VA Tech Escher Wyass
          Flovel Ltd. was per incuriam insofar as it held that the M.P.
          Act stands impliedly repealed by the Central Act. While
          Hon’ble Ganguly, J., held that the State Act will cover a
          dispute even after termination of the “works contract”,
          Hon’ble Gyan Sudha Mishra, J. took a different view [...]
          5. We find from the definition under Section 2(d) of the
          Arbitration and Conciliation Act, 1996 that even after a
          contract is terminated, the subject-matter of dispute is
          covered by the said definition. The said provision has not
          been even referred to in the judgment rendered by Hon’ble
          Gyan Sudha Mishra, J.
          6. In view of the above, we are of the opinion that the
          view expressed by Hon’ble Ganguly, J. is the correct
          interpretation and not the contra view of Hon’ble Gyan
          Sudha Mishra, J. Reference stands answered accordingly.
          7. Taking up appeal on merits, we find that the High Court
          proceeded on the basis of the judgment of this Court in
          VA Tech Escher Wyass Flovel Ltd. which has been held
          to be per incuriam. The M.P. Act cannot be held to be
          impliedly repealed.
          8. We are, thus, in agreement with the proposed opinion
          of Hon’ble Ganguly, J. [...]”
                                                (Emphasis supplied)

     i.   Can an Award passed under the Act, 1996 be annulled on the
          ground of lack of jurisdiction where no plea of applicability
          of MP Act, 1993 was raised before the Arbitral Tribunal?
14. It is worthwhile to note, that the decision of L.G. Chaudhary (II)
    (supra) did not merely decide the aforesaid reference arising from
    L.G. Chaudhary (I) (supra), but also elucidated how, the courts are
    expected to deal with the various issues that may arise therefrom
    insofar as the pending proceedings that were inadvertently initiated
    under the Act, 1996 and any awards already passed thereunder
    are concerned.
[2025] 5 S.C.R.                                                          2571

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

15. In the entire batch of matters that had been referred to this Court in
    L.G. Chaudhary (II) (supra), this Court in few of the civil appeals
    where the reference to arbitration under the Act, 1996 had been
    challenged, while the matters were still at the pre-award stage,
    however the statement of defence had already been filed without
    raising a plea of lack of jurisdiction, held that in such instances, the
    plea of lack of jurisdiction cannot be allowed to be now raised in
    terms of Section 16 sub-section (2) of the Act, 1996 and as such the
    award cannot be annulled only on such ground. Similarly, in a batch
    of matters where the award had already been passed but no objection
    of jurisdiction was raised in terms of Section 16(2) of the Act, 1996,
    there L.G. Chaudhary (II) (supra) whilst restoring the award again
    reiterated that the award could not have been annulled only on the
    ground of jurisdiction, but clarified that, all other challenges to the
    award may be made in appropriate proceedings under Section 34 of
    the Act, 1996. Lastly, in one of the civil appeals, where the execution
    proceedings for the award passed were pending, this Court in view
    of the prolonged nature of the litigation, directed that the award be
    treated to have been rendered under the MP Act, 1983 and transferred
    the execution proceedings to the High Court of Madhya Pradesh at
    Jabalpur. The relevant observations read as under: -
           “CA No. 2751 of 2018 arising out of SLP (C) No. 11615
           of 2012, CA No. 2753 of 2018 arising out of SLP (C) No.
           11617 of 2012, CA No. 2754 of 2018 arising out of SLP
           (C) No. 11618 of 2012, CA No. 2755 of 2018 arising out
           of SLP (C) No. 11619 of 2012, CAs Nos. 2756-57 of 2018
           arising out of SLPs (C) Nos. 11633-34 of 2012, CAs Nos.
           2758-59 of 2018 arising out of SLPs (C) Nos. 11631-32
           of 2012 & CAs Nos. 2760-61 of 2018 arising out of SLPs
           (C) Nos. 11628-29 of 2012
           15. Leave granted. In view of order passed in Civil Appeal
           No. 2615 of 2018 [arising out of SLP (C) No. 16889 of 2012],
           the impugned order is set aside and the application(s) filed
           by the respondent(s) under Section 11 of the Arbitration
           and Conciliation Act, 1996 are dismissed.
           16. However, since it is stated that proceedings are pending
           before the arbitrator in pursuance of the impugned order,
           the same will stand transferred to the State Tribunal and
2572                                                      [2025] 5 S.C.R.

                       Supreme Court Reports


        the State Tribunal may proceed further taking into account
        the proceedings which have already been taken. The
        learned counsel for the respondent(s) pointed out that in
        view of Section 16(2), the objection to the jurisdiction could
        not be raised after statement of defence was filed. This
        contention cannot be accepted in view of the fact that the
        SLP was filed prior to the filing of statement of defence
        wherein this objection was raised.
        17. We do not express any opinion on the applicability
        of the State Act where award has already been made.
        In such cases if no objection to the jurisdiction of the
        arbitration was taken at relevant stage, the award may
        not be annulled only on that ground.

                xxx                 xxx                  xxx
        CA No. 2616 arising out of SLP (C) No. 35641 of 2011
        19. Leave granted. In view of the order passed in CA No.
        2751 of 2018 arising out of SLP (C) No. 16615 of 2012,
        no objection having been raised by the respondents in
        terms of Section 16(2) of the Arbitration and Conciliation
        Act, 1996 at appropriate stage within the time stipulated,
        the award could not have been annulled.
        20. Accordingly, this appeal is allowed, the impugned
        judgment is set aside and the award is restored. It
        is, however, made clear that this order will not debar
        proceedings under Section 34 of the Arbitration and
        Conciliation Act, 1996.

                xxx                  xxx                  xxx
        Civil Appeal No. 4261 of 2018
        34. The Division Bench vide order dated 5-7-2012 directed
        that the enforceability of the decree will depend upon the
        fate of another appeal which was pending between the
        parties. The said appeal, FAO (OS) No. 23 of 1998, is still
        pending but the High Court has deferred the same pending
        decision of the larger Bench of this Court in pursuance of
        the judgment of this Court in M.P. Rural Road Development
[2025] 5 S.C.R.                                                           2573

                      M/s Gayatri Project Limited v.
          Madhya Pradesh Road Development Corporation Limited

            Authority v. L.G. Chaudhary Engineers and Contractors. It
            may be noted that the larger Bench has decided the matter
            on 8-3-2018. In terms of the said decision, the dispute
            between the parties has to be settled in accordance with the
            provisions of the M.P. Madhyastham Adhikaran Adhiniyam,
            1983 (the M.P. Act). However, since in the present case
            the award has been rendered long back which was not
            challenged by the respondents and the matter is pending
            at the stage of execution, we direct that the award to be
            treated to have been rendered under the M.P. Act.
            35. In view of the above, we transfer pending proceedings
            before the Delhi High Court being FAO (OS) No. 23 of
            1998 and connected matters to the High Court of Madhya
            Pradesh at Jabalpur to be treated as revision petition
            under the M.P. Act.
                                                  (Emphasis supplied)

     a.     Is there a conflict between the decisions of L.G. Chaudhary
            (II) and Lion Engineering?
16. At this stage, it is apposite to note, that prior to the decision of
    L.G. Chaudhary (II) (supra), this Court in one another decision of
    Lion Engineering (supra) had looked into the issue as to at what
    stage a plea of lack of jurisdiction or applicability of any State Act
    may be raised. The facts of Lion Engineering (supra) were that
    the respondent State therein had sought to amend its pleadings
    in the proceedings under Section 34 of the Act, 1996 to raise the
    objection of a lack of jurisdiction on the ground of applicability of
    the MP Act, 1983. The said amendment application was rejected
    by the trial court as being barred by limitation. The High Court
    however, in exercise of its supervisory jurisdiction under Article 227
    of the Constitution allowed the said amendment. In appeal, before
    this Court it was inter-alia contended by the appellant therein,
    that the amendment ought not to have been allowed, since the
    objection of lack of jurisdiction had never been raised before the
    arbitral tribunal and hence was barred by Section 16 sub-section
    (2) of the Act, 1996. This Court held that any legal plea arising on
    undisputed facts can be raised in the proceedings under Section
    34 of the Act, 1996 even if they were never raised under Section
2574                                                      [2025] 5 S.C.R.

                        Supreme Court Reports


     16. It further held that, such plea being a question of law arising
     from admitted facts, can be raised without seeking any amendment
     of the pleadings. Accordingly, it held that there is no bar to plea of
     jurisdiction being raised by way of an objection under Section 34
     of the Act even if no such objection was raised under Section 16.
     The relevant observations read as under: -
          “3. The learned Advocate General for the State of M.P.
          submitted that the amendment sought is formal. Legal plea
          arising on undisputed facts is not precluded by Section
          34(2)(b) of the Act. Even if an objection to jurisdiction is
          not raised under Section 16 of the Act, the same can be
          raised under Section 34 of the Act. It is not even necessary
          to consider the application for amendment as it is a legal
          plea, on admitted facts, which can be raised in any case.
          He thus submits the amendment being unnecessary is not
          pressed. The learned Advocate General also submitted
          that observations in MSP Infrastructure Ltd., particularly
          in paras 16 and 17 do not lay down correct law.
          4. We find merit in the contentions raised on behalf of the
          State. We proceed on the footing that the amendment being
          beyond limitation is not to be allowed as the amendment is
          not pressed. We do not see any bar to plea of jurisdiction
          being raised by way of an objection under Section 34 of the
          Act even if no such objection was raised under Section 16.
                                                (Emphasis supplied)

17. Lion Engineering (supra) expressing disagreement with the view
    taken in MSP Infrastructure Ltd. v. M.P. Road Development Corpn.
    Ltd., reported in (2015) 13 SCC 713, further held that the ground of
    ‘public policy of India’ in Section 34 of the Act, 1996 would include
    violation of not only a Central law but also a State law, and hence,
    it would be open for the parties to argue the aspect of applicability
    of the MP Act, 1983 even without a formal pleading, being purely
    a legal plea in the proceedings under Section 34 of the Act, 1996.
    The relevant observations read as under: -
          “6. Both stages are independent. Observations in paras
          16 and 17 in MSP Infrastructure Ltd. do not, in our view,
          lay down correct law. We also do not agree with the
[2025] 5 S.C.R.                                                          2575

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

           observation that the public policy of India does not refer
           to a State law and refers only to an all-India law.
           7. In our considered view, the public policy of India refers
           to law in force in India whether State law or Central law.
           Accordingly, we overrule the observations to the contrary in
           paras 16 and 17 of the judgment in MSP Infrastructure Ltd.
           9. The matter may now be taken up by the trial court
           for consideration of objections under Section 34 of the
           Central Act. It will be open for the respondents to argue
           that its objection that the Act stands excluded by the
           M.P. Madhyastham Adhikaran Adhiniyam, 1983 could
           be raised even without a formal pleading, being purely a
           legal plea. It will also be open to the appellant to argue
           to the contrary. We leave the question to be gone into by
           the court concerned.
                                                 (Emphasis supplied)

18. It is in this aforesaid context, that the respondent herein has contended
    before us that there exists a conflict between the decisions of this
    Court in Lion Engineering (supra) and L.G. Chaudhary (II) (supra),
    insofar as the issue of when a plea of lack of jurisdiction on the basis
    of applicability of a State law can be raised. It was submitted that
    Lion Engineering (supra) clearly holds that an objection of lack of
    jurisdiction is a legal plea that may be raised for the first time in the
    proceedings under Section 34 of the Act, 1996, even if the same
    was never raised before the arbitral tribunal, and being a question
    of law, Section 16 sub-section (2) of the Act, 1996 would have no
    application. It was further canvassed on behalf of the respondents
    herein that the decision of L.G. Chaudhary (II) (supra) to the extent
    that it holds that no plea of lack of jurisdiction can be raised in the
    proceedings under Section 34, if it was never raised before the arbitral
    tribunal, could be said to be per incuriam, as it failed to refer and
    advert to the earlier binding decision of Lion Engineering (supra),
    which as per the respondents herein, lays down a contradictory view.
19. We are however, not impressed by the aforesaid submission that
    has been canvassed on behalf of the respondents herein, primarily
    for the following three reasons: -
2576                                                        [2025] 5 S.C.R.

                         Supreme Court Reports


    (i)    First, that merely because L.G. Chaudhary (II) (supra) does
           not refer to the decision of Lion Engineering (supra), would
           not render it per incuriam, if either such omission in referring
           does not amount to a non-consideration of the ratio of an earlier
           decision or where there is no palpable conflict or contradiction
           in the ratio of both decisions. Lion Engineering (supra) holds
           that a plea of lack of jurisdiction being a question of law may
           be raised for the first time under Section 34 of the Act, 1996
           even if it was never raised before the arbitral tribunal. Whereas,
           L.G. Chaudhary (II) (supra) holds that where such plea of
           lack of jurisdiction was not taken before the arbitral tribunal,
           then an award that has been so passed by the tribunal will not
           be annulled only on the ground of lack of jurisdiction. If L.G.
           Chaudhary (II) (supra) was not conscious of the position of
           law laid in Lion Engineering (supra), then there was no need
           for it to clarify that an award would not be annulled only on
           the ground of lack of jurisdiction. As even without the aforesaid
           clarification, such awards would not have been susceptible to
           annulment, if not for the ratio of Lion Engineering (supra).
           Thus, in our opinion, even if L.G. Chaudhary (II) (supra)
           does not refer to the decision of Lion Engineering (supra), it
           cannot be termed to be per incuriam, as the very factum that
           the aforesaid observations were made by L.G. Chaudhary
           (II) (supra) in paras 16, 17 and 19, shows that this Court was
           well aware of the decision of Lion Engineering (supra), and
           accordingly chose to carve out an exception to the ratio of Lion
           Engineering (supra) keeping in mind the cleavage of judicial
           view that was prevailing earlier.
    (ii)   Secondly, the decision of Lion Engineering (supra) only dealt
           with the question whether an amendment of pleadings was
           required or not, to raise a plea of jurisdiction. It was in this
           aforesaid context, that this Court held that such objection being
           a question of law can be raised by way of an objection in the
           proceedings under Section 34 of the Act, 1996 even if no such
           objection was raised under Section 16 of the Act, 1996. Thus,
           the aforesaid observations could be said to be confined only
           to the issue of requirement to amend the pleadings for raising
           such an objection, and cannot be stretched to apply blanketly
           in all cases.
[2025] 5 S.C.R.                                                        2577

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

     (iii) Thirdly, even otherwise, the ratio of Lion Engineering (supra)
           in paras 6 to 9 only goes so far as to hold that where a plea
           of jurisdiction involves purely a question of law and is based
           on undisputed facts, then such a plea may be raised for the
           first time in the proceedings under Section 34 of the Act, 1996,
           notwithstanding the bar of Section 16 sub-section (2) or whether,
           such plea was taken before the arbitral tribunal or not. However,
           Lion Engineering (supra) does not address the question
           whether an award may be annulled only on the ground of lack
           of jurisdiction or not. It does not disturb the settled position of
           law as regards the scope of Section 34 of the Act, 1996 i.e., an
           award may be set aside only if such lack of jurisdiction goes to
           the root of the matter and results in a patent illegality. On the
           contrary, L.G. Chaudhary (II) (supra) specifically addresses
           this question in the context of the issue of applicability of MP
           Act, 1983 and explicitly states that any award already passed
           shall not be annulled only on the ground of lack of jurisdiction
           where such plea was not raised at the relevant stage. Thus,
           the aforesaid ratio of Lion Engineering (supra) by no stretch
           can be construed to mean that such a plea of jurisdiction would
           automatically result in annulment of an award, de hors the fact
           whether such lack of jurisdiction goes to the root of the award
           rendered or not. The ratio of L.G. Chaudhary (II) (supra)
           unlike Lion Engineering (supra) does not deal with whether
           it is permissible for such plea of jurisdiction to be raised under
           Section 34 or not, and only deals with the issue whether an
           award may be annulled only on the ground of jurisdiction or not,
           which was never an issue before Lion Engineering (supra),
           hence there is no conflict or contradiction between the ratios
           of the aforesaid two decisions.
20. What can be discerned from the aforesaid is that L.G. Chaudhary
    (II) (supra) carved out an exception to the general rule that was
    laid in Lion Engineering (supra), that although a plea of lack of
    jurisdiction being a question of law can be raised for the first time
    in the proceedings under Section 34 of the Act, 1996, yet insofar as
    the MP Act, 1983 is concerned, particularly the state of flux in which
    the position of law regarding its applicability stood, in cases where
    either the award has already been passed or where the statement
    of defence is already been filed, and no plea of lack of jurisdiction or
2578                                                         [2025] 5 S.C.R.

                          Supreme Court Reports


     applicability of the MP Act, 1983, has been raised before the arbitral
     tribunal, then such a plea of jurisdiction will no longer be available,
     and the award cannot be annulled solely on such ground.
21. In JMC Projects (supra) this Court reiterated the aforesaid exception
    carved out in L.G. Chaudhary (II) (supra) and held that since the
    award had already been passed, all objections except the plea of
    lack of jurisdiction and the applicability of the MP Act, 1983 may be
    raised in the proceedings under Section 34 of the Act, 1996.
22. In Sweta Construction v. Chhattisgarh State Power Generation
    Company Ltd. reported in (2022) SCC OnLine SC 1447, while
    dealing with an issue pertaining to the applicability of the Chhattisgarh
    Madhyastham Adhikaran Adhiniyam, 1983, which is pari materia to
    the MP Act, 1983, this Court followed the ratio laid down in L.G.
    Chaudhary (II) (supra), and reiterated that where awards have
    already been made and if no objection to the jurisdiction was taken
    at the relevant stage, then the award may not be annulled “only” on
    that ground. The relevant observations read as under: -
           12. [...] Thus what was opined was that where awards have
           already been made and if no objection to the jurisdiction
           was taken at the relevant stage, the award may not be
           annulled “only” on that ground and the appeals dealing with
           those aspects were granted a favourable consideration.
           13. [...] It was however, clarified in the very next paragraph
           that the order would not debar proceedings under Section
           34 of the 1996 Act.
23. Furthermore, this Court in Sweta Construction (supra), taking note
    of the ostensible conflict between the decisions of L.G. Chaudhary
    (II) (supra) and Lion Engineering (supra), made the following
    pertinent observations: -
     (i)   First, that, in Lion Engineering (supra) the controversy before
           the court was different inasmuch as it was dealing with the issue
           of an amendment in pleadings being sought beyond the period
           of limitation. This Court observed that, it was in this context that
           Lion Engineering (supra) held that no amendment of pleadings
           was required to raise a plea of jurisdiction, and such objection
           being a question of law can be raised by way of an objection
           in the proceedings under Section 34 of the Act, 1996 even if no
[2025] 5 S.C.R.                                                               2579

                    M/s Gayatri Project Limited v.
        Madhya Pradesh Road Development Corporation Limited

            such objection was raised under Section 16 of the Act, 1996.
            The relevant observations read as under: -
                 “15. However, as pointed by the learned counsel for
                 the respondent, there appears to be some lack of
                 clarity on the issue raised in the present petition on
                 account of the same three-Judge Bench having opined
                 in another order passed in Lion Engg. Consultants v.
                 State of M.P. on 22-3-2018 i.e. about three weeks after
                 that. The issue however, raised was whether there
                 was any bar to the plea of jurisdiction being raised
                 by way of an objection under Section 34 of the 1996
                 Act even if no objection was raised under Section 16
                 of that Act. It was opined that public policy of India
                 refers to law enforced in India i.e. both Central law as
                 well as the State law. The respondent State was given
                 liberty to argue before the trial court its objections that
                 the 1996 Act stood excluded by the State Adhiniyam
                 even without formal pleadings being a pure legal plea.
                 This was in the context of an amendment sought being
                 beyond limitation. In that context there is an observation
                 in one sentence, “we do not see any bar to plea of
                 jurisdiction being raised by way of an objection under
                 Section 34 of the Act even if no objection was raised
                 under Section 16 of that Act”.”
                                                    (Emphasis supplied)

     (ii)   Secondly, that the decision of Lion Engineering (supra) was
            only an order unlike the decision of L.G. Chaudhary (II) (supra)
            which was a substantive judgment, and thus, the observations
            of Lion Engineering (supra) would by no means detract or
            take away the law laid down in L.G. Chaudhary (II) (supra)
            as regards the maintainability of the plea of jurisdiction where
            awards have already been passed, and no such objection was
            raised before the arbitral tribunal at the relevant stage. The
            relevant observations read as under: -
                 “16. If we appreciate the aforesaid observation in
                 Lion Engg. Consultants and that too emerging from
                 identical Bench in the two matters, we would have to
2580                                                       [2025] 5 S.C.R.

                        Supreme Court Reports


               construe as what is meant by this sentence extracted
               aforesaid. We take note of the fact that this is an
               order and not a judgment. The controversy before
               the Court was something different as noticed by us
               aforesaid. In that context, this sentence has been
               inserted, but that does not take away the law laid
               down in the substantive judgment (in M.P. Rural
               Road Development Authority) dealing with the issue
               at hand in respect of awards already made where
               petitions were pending before the competent Court
               under Section 34 of the said Act.”
                                                (Emphasis supplied)

    (iii) Thirdly, that the law expounded in L.G. Chaudhary (II) (supra)
          insofar as those awards which have already been passed are
          concerned, should be read as one made by this Court under
          Article 142 of the Constitution to do substantive justice inter se
          the parties, keeping in mind the cleavage of judicial view earlier
          and to ensure that the objective of arbitration as an expeditious
          and effective alternative dispute resolution mechanism is not
          defeated. The relevant observations read as under: -
               “17. This Court (in M.P. Rural Road Development
               Authority) in the context of the 1996 Act and the
               1983 Adhiniyam, keeping in mind the cleavage of
               judicial view earlier and expounding on the law in
               that judgment has in succinct terms set out that the
               objections under Section 34 of the said Act, where
               no such plea of jurisdiction was raised in proceedings
               before the arbitrator, should not be dealt with “alone”
               on the plea of jurisdiction i.e. it should be considered
               on merits. One can say that possibly this part of the
               order can also be read as one made under Article
               142 of the Constitution of India to do substantive
               justice inter se the parties, more so, when arbitration
               as an alternative dispute resolution mechanism
               presupposes an expeditious disposal of commercial
               disputes and that objective would stand nullified if a
               contrary view was taken.”
                                                (Emphasis supplied)
[2025] 5 S.C.R.                                                          2581

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

     (iv) Lastly, it observed that even otherwise, the conduct of the
          respondent therein of accepting the notice of invocation and
          commencing arbitration under the Act, 1996 on their own volition
          amounts to a waiver of their right to claim initiation of arbitration
          under the State Act. In such circumstances it was held that the
          respondent therein cannot be now permitted to approbate and
          reprobate a right it failed to exercise on it own, and that too in
          a manner which would defeat the entire object of arbitration.
          The relevant observations read as under: -
                “18. We are also of the view that in particular facts
                of the present case, the position is even more gross
                because when the appellant claimed arbitration,
                the respondent accepted invocation of arbitration,
                suggested a panel of arbitrators, the appellant chose
                one of the arbitrators out of the two suggested and
                the arbitrator was so appointed as the sole arbitrator.
                Thus, the arbitration proceedings commenced in
                pursuance to the acts of the respondent and it cannot
                be permitted to get away to say that the whole process
                was gone through because of some misconception or
                inappropriate legal advice. Arbitration by consent is
                always possible. The mode and manner of conduct
                of arbitration is possible and how those arbitration
                proceedings would be governed is also a matter
                of consent. If at all there were any rights of the
                respondent to have claimed arbitration under the 1983
                Adhiniyam, that right was never exercised or waived.
                The respondent cannot be permitted to approbate
                and reprobate and that too in arbitration proceedings
                and that too in dispute or resolution through the
                method of arbitration defeating the very purpose of
                an alternative dispute resolution to arbitration as an
                expeditious remedy.”
                                                  (Emphasis supplied)

24. In yet another decision of this Court in Modern Builders v. State
    of Madhya Pradesh & Anr. reported in (2024) 10 SCC 637, the
    appellant contractor therein had approached the M.P. State Arbitration
    Tribunal for initiation of arbitration in respect of certain disputes,
2582                                                         [2025] 5 S.C.R.

                         Supreme Court Reports


    however the reference was rejected by the State Tribunal in view
    of the law laid down by VA Tech (supra) that held field at that time.
    Accordingly, the appellant therein initiated arbitration under the Act,
    1996, and consequently an award was passed. The aforesaid award
    came to be challenged, wherein the High Court under Section 37
    of the Act, 1996 set-aside the award only on the ground that the
    arbitral tribunal had no jurisdiction in view of the MP Act, 1983. In
    appeal, this Court setting aside the order of the High Court, held
    that even though the objection based on applicability of the MP
    Act, 1983 had been raised by the respondent therein in its written
    statement filed before the arbitrator, nevertheless, in view of the
    fact that the respondents therein neither raised this objection when
    the Section 11 petition was filed by the appellant, nor did it take
    recourse of Section 16 of the Act, 1996 to challenge the jurisdiction
    of the arbitral tribunal, it would be unjust to set aside the award
    only on the ground of the failure of the appellant to take recourse
    to the MP Act, 1983. Furthermore, in light of the fact that the only
    reason the appellant took recourse to the Act, 1996 was because
    its earlier reference to the M.P. State Arbitration Tribunal had been
    rejected in terms of the decision of VA Tech (supra), this Court held
    that it is a fit case to exercise its jurisdiction under Article 142 of the
    Constitution and restore the award to ensure complete justice. The
    relevant observations read as under: -
         “6. A few factual aspects will have to be noted. After
         the contract granted to the appellant was rescinded, the
         appellant invoked Section 7 of the 1983 Act by approaching
         the Arbitration Tribunal. By the order dated 19-4-2010, the
         Arbitration Tribunal held that in view of the arbitration clause
         in the contract, the 1983 Act will have no application and the
         appellant will have to take recourse to the Arbitration Act.
         In view of this order, the appellant invoked the jurisdiction
         of the High Court under Section 11(6) of the Arbitration
         Act by filing a petition for the appointment of an arbitrator.
         7. The order dated 22-7-2011 passed by the High Court
         on the said petition shows that the respondents’ opposition
         was only on the merits of the claim. The objection based
         on the applicability of the 1983 Act was not raised. The
         respondents did not challenge the order of appointment of
         the arbitrator passed by the High Court under Section 11(6)
[2025] 5 S.C.R.                                                             2583

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

           of the Arbitration Act. Even before the learned arbitrator,
           Section 16(1) of the Arbitration Act was not invoked to raise
           the jurisdiction issue. However, in the written statement
           filed before the arbitrator, the contention regarding the
           applicability of the 1983 Act was raised.
           9. As noted earlier, in the facts of the case, before taking
           recourse to the Arbitration Act, the appellant had taken
           recourse to Section 7 of the 1983 Act. The order of the
           Arbitration Tribunal, holding that the Arbitration Act will
           apply, led the appellant to file a petition under Section 11(6)
           of the Arbitration Act, which was not objected to on the
           grounds of the applicability of the 1983 Act. The objection
           of the State Government was confined to the merits of the
           claim. The award is only in the sum of Rs 6,52,235 with
           interest. The award was made on 25-4-2014. Therefore,
           in the facts of the case, it will be unjust to set aside the
           award only on the ground of the failure of the appellant
           to take recourse to the 1983 Act. In fact, the appellant
           had taken recourse to the 1983 Act before seeking the
           appointment of an arbitrator.
           10. In this case, as can be seen from the impugned
           judgment, the award has been set aside only on the ground
           that the appellant ought to have invoked the provisions
           of the 1983 Act. Even assuming that the observations in
           para 17 of the decision in M.P. Rural Road Development
           Authority, are not applicable, this is a fit case to exercise
           jurisdiction under Article 142 of the Constitution of India to
           ensure that complete justice is done. Therefore, by setting
           aside the impugned judgment, the appeal under Section
           37 of the Arbitration Act will have to be restored with a
           request to the High Court to decide the same on merits.
                                                   (Emphasis supplied)

25. What can be discerned from the above is that, this Court has
    consistently held that an exception has been carved out in L.G.
    Chaudhary (II) (supra) whereby any awards that have already been
    made and if no objection to the jurisdiction was taken at the relevant
    stage, then the award may not be annulled “only” on that ground.
2584                                                        [2025] 5 S.C.R.

                         Supreme Court Reports


     b.   Whether a plea of lack of jurisdiction may be raised for
          the first time under Section 34 of the Act, 1996 if no such
          objection was taken before the arbitral tribunal?
26. The aforesaid may be looked at from one another angle, with a
    view to obviate the possibility of any confusion. The respondent
    herein placed much emphasis on the observations made in Lion
    Engineering (supra) to canvass that a plea of lack of jurisdiction
    being a question of law may be raised at any stage. Even where
    no such plea was raised at the time of filing of written submissions,
    the same can be validly raised for the first time in the proceedings
    under Section 34 of the Act, 1996, and the bar under Section 16
    sub-section (2), would not come in the way.
27. Before adverting to the aforesaid submission, it would be apposite
    to first look into the interplay between Section(s) 16 and 34 of the
    Act, 1996, respectively. These two provisions, although distinct in
    form and function, yet are intrinsically linked in the broader scheme
    of the Act, insofar as the stage at which issues pertaining to the
    jurisdiction of the arbitral tribunal may be validly raised.
28. In Union of India v. Pam Development (P) Ltd. reported in (2014)
    11 SCC 366 this Court held that where a party does not raise a
    plea of jurisdiction before the arbitral tribunal, then such a plea is
    deemed to have been waived in view of the provisions contained in
    Section 4 read with Section 16 of the Arbitration Act, 1996, and in
    consequence cannot be raised for the first time in the proceedings
    under Section 34. The relevant observations read as under: -
          “16. As noticed above, the appellant not only filed the
          statement of defence but also raised a counterclaim
          against the respondent. Since the appellant has not raised
          the objection with regard to the competence/jurisdiction
          of the Arbitral Tribunal before the learned arbitrator, the
          same is deemed to have been waived in view of the
          provisions contained in Section 4 read with Section 16 of
          the Arbitration Act, 1996.
          17. Section 16 of the Arbitration Act, 1996 provides that the
          Arbitral Tribunal may rule on its own jurisdiction. Section 16
          clearly recognises the principle of kompetenz-kompetenz.
          Section 16(2) mandates that a plea that the Arbitral Tribunal
[2025] 5 S.C.R.                                                          2585

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

           does not have jurisdiction shall be raised not later than
           the submission of the statement of defence. Section 4
           provides that a party who knows that any requirement
           under the arbitration agreement has not been complied
           with and yet proceeds with the arbitration without stating
           his objection to such non-compliance without undue delay
           shall be deemed to have waived his right to so object.
           8. In our opinion, the High Court has correctly come to
           the conclusion that the appellant having failed to raise the
           plea of jurisdiction before the Arbitral Tribunal cannot be
           permitted to raise for the first time in the Court. [...]
                                                 (Emphasis supplied)

29. In Gas Authority of India Ltd. v. Keti Construction (I) Ltd. reported
    in (2007) 5 SCC 38 this Court held that where a party does not raise
    a plea of lack of jurisdiction before the arbitral tribunal, he must
    make out a strong case why he did not do so if he chooses to move
    a petition for setting aside the award under Section 34 of the Act,
    1996 on such ground. The relevant observations read as under: -
           “25. Where a party has received notice and he does
           not raise a plea of lack of jurisdiction before the Arbitral
           Tribunal, he must make out a strong case why he did not
           do so if he chooses to move a petition for setting aside
           the award under Section 34(2)(a)(v) of the Act on the
           ground that the composition of the Arbitral Tribunal was
           not in accordance with the agreement of the parties. If
           plea of jurisdiction is not taken before the arbitrator as
           provided in Section 16 of the Act, such a plea cannot
           be permitted to be raised in proceedings under Section
           34 of the Act for setting aside the award, unless good
           reasons are shown.”
                                                 (Emphasis supplied)

30. A similar view was reiterated in AC Chokshi Share Broker (P) Ltd. v.
    Jatin Pratap Desai reported in (2025) SCC OnLine SC 281 wherein
    it was held that when the jurisdictional issue has not been raised in
    accordance with Section 16 of the Act, 1996, it is deemed that the
    objecting party has waived his right, in terms of Section 4, and the
2586                                                          [2025] 5 S.C.R.

                         Supreme Court Reports


     same cannot be raised at a later stage such as under Section 34 or
     37 of the Act. The relevant observations read as under: -
          “20. The High Court in the impugned order relied on this
          rationale of a “private” transaction to hold that the arbitral
          tribunal lacked inherent jurisdiction to decide the claim
          against respondent no. 1, and such a jurisdictional plea
          could be raised at any stage even if it was not raised before
          the arbitral tribunal. From the above reasons, it is clear
          that there is no inherent lack of jurisdiction. Consequently,
          any issue regarding the scope of Bye-law 248(a) ought to
          have been raised in accordance with Section 16 of the Act,
          i.e. during the arbitration, not later than the submission
          of statement of defence. Neither respondent has, in their
          statements of defence or Section 34 petitions, raised an
          objection to the arbitral tribunal›s jurisdiction in clear terms
          beyond stating that there is a misjoinder of parties as they
          are not jointly and severally liable. A clear jurisdictional
          issue was only raised at the Section 37 appeal stage, as
          has also been noted by the High Court in the impugned
          order.
          21. This Court has held, in several judgments, that when
          the jurisdictional issue has not been raised in accordance
          with Section 16, it is deemed that the objecting party
          has waived his right, in terms of Section 4 of the Act to
          raise the same at a later stage. Such objection cannot
          be raised for the first time when the party is challenging
          the award under Section 34. Here, respondent no. 1 not
          only filed his statement of defence and participated in
          the arbitral proceedings but also filed a counter-claim,
          thereby submitting to the arbitral tribunal’s jurisdiction.
          Hence, any jurisdictional objection must be rejected on
          this ground as well.”
                                                  (Emphasis supplied)

31. The fallacy of the aforesaid argument of the respondent herein lies in
    the very fact, that it has misconstrued the observations of this Court
    in Lion Engineering (supra) by ignoring the very settled position of
    law as regards the interplay between Section(s) 16 and 34 of the
    Act, 1996, respectively.
[2025] 5 S.C.R.                                                       2587

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

32. The observations made by this Court in Lion Engineering (supra)
    that “We do not see any bar to plea of jurisdiction being raised by way
    of an objection under Section 34 of the Act even if no such objection
    was raised under Section 16” cannot be singled out and construed
    devoid of its context. The aforesaid observations have to be construed
    in light of the settled position of law by a catena of decisions of this
    Court. The decision of this Court in Pam Development (supra) has
    held that where a plea of lack of jurisdiction is not raised before the
    arbitral tribunal, such a plea cannot be raised later in the proceedings
    under Section 34. Pam Development (supra) says this, not because
    such a plea is barred from being raised only by virtue of Section
    16 sub-section (2), but rather says this, because such a plea is
    deemed to have been waived on account of the failure of the party in
    raising such a plea. Thus, Pam Development (supra) in no manner
    lays down that a plea of lack of jurisdiction cannot be raised in the
    proceedings under Section 34 due to the bar of Section 16 sub-
    section (2) of the Act, 1996, and thus to this extent both the decisions
    of Pam Development (supra) and Lion Engineering (supra) are
    in tune with each other. The variance between the decisions of
    Pam Development (supra) and Lion Engineering (supra) is only
    in respect of whether a failure to raise such a plea at the relevant
    stage in terms of Section 16 sub-section (2) of the Act, 1996 would
    amount to a ‘waiver’ or not, and this issue was never examined or
    looked into by Lion Engineering (supra).
33. On the contrary Lion Engineering (supra) specifically observed in para
    9 that “It will be open for the respondents to argue that its objection
    that the Act stands excluded by the M.P. Madhyastham Adhikaran
    Adhiniyam, 1983 could be raised even without a formal pleading,
    being purely a legal plea. It will also be open to the appellant to argue
    to the contrary. We leave the question to be gone into by the court
    concerned.” The observations that it will be open for the respondents
    therein to argue that such an object could be raised even without a
    formal pleading AND that it will be open for the appellants therein to
    argue the contrary, clearly shows that the very issue of whether such
    a plea can be allowed to be raised or not i.e., issues such as whether
    it is a purely legal plea or whether there was any waiver or not etc.
    were never decided by this Court in Lion Engineering (supra) and
    rather was left to be gone into by the court under Section 34 of the
    Act, 1996. The aforesaid observations clearly show, that although
2588                                                         [2025] 5 S.C.R.

                         Supreme Court Reports


     such a plea may be raised for the first time in the proceedings under
     Section 34 of the Act, 1996, it may still nevertheless be rejected if it
     is found that such a plea is not purely a question of law or that the
     party raising the plea had waived it in terms of Pam Development
     (supra). Whereas Gas Authority of India (supra) goes one step
     ahead of Pam Development (supra) and lays down that where a
     party makes out a strong and good reason for its failure to take a plea
     of lack of jurisdiction before the arbitral tribunal, then there would be
     no deemed waiver of such a plea, and the same may then be looked
     into by the courts under Section 34 of the Act, 1996.
34. Thus, insofar as the manner in which the question of whether a plea
    of lack of jurisdiction being raised for the first time under Section
    34 of the Act, 1996 has to be decided, the decision of this Court
    in Pam Development (supra) and Gas Authority of India (supra)
    would be applicable, as Lion Engineering (supra) only decided
    the limited issue of whether the bar under Section 16 sub-section
    (2) would preclude raising of such a plea i.e., whether such a plea
    is maintainable or not, and never decided or laid down when the
    courts would entertain such a plea. It is in this aforesaid context that
    the observations of this Court in L.G. Chaudhary (II) (supra), more
    particularly at para 17 that “We do not express any opinion on the
    applicability of the State Act where award has already been made.
    In such cases if no objection to the jurisdiction of the arbitration
    was taken at relevant stage, the award may not be annulled only
    on that ground” assumes significance. What has been conveyed,
    in so many words, by this Court in L.G. Chaudhary (II) (supra) is
    that any failure to raise the issue of applicability of the MP Act, 1983
    before the arbitral tribunal is not a strong and good reason in terms
    of Gas Authority of India (supra) to permit raising such a plea in
    the proceedings under Section 34 of the Act, 1996.
35. Thus, what can be discerned from the aforesaid is that although a
    plea of lack of jurisdiction, being a question of law, can be raised
    even for the first time in the proceedings under Section 34 as held in
    Lion Engineering (supra), yet such a plea ought not to be allowed
    to be raised as it is deemed to have been waived in view of Section
    4 of the Act, 1996 as per Pam Development (supra), unless the
    party makes out a strong and good reason for its failure to take such
    a plea before the arbitral tribunal as per Gas Authority of India
    (supra), and as per the dictum of L.G. Chaudhary (II) (supra) any
[2025] 5 S.C.R.                                                      2589

                   M/s Gayatri Project Limited v.
       Madhya Pradesh Road Development Corporation Limited

     failure to raise the issue of applicability of the MP Act, 1983 before
     the arbitral tribunal is not a strong and good reason to permit raising
     such a plea in the proceedings under Section 34 of the Act, 1996.

     D.    CONCLUSION
36. What emerges from the foregoing is that although Lion Engineering
    (supra) affirms that a plea of lack of jurisdiction, being a question
    of law, may be raised for the first time under Section 34 of the Act,
    1996, yet such a plea is nevertheless subject to the waiver as held
    in Pam Development (supra). Furthermore, as per Gas Authority
    of India (supra), such a plea may only be entertained if the party
    demonstrates a strong and sufficient reason for not raising it before
    the arbitral tribunal. However, L.G. Chaudhary (II) (supra) makes it
    clear that a failure to raise the issue of applicability of the MP Act,
    1983 at the appropriate stage cannot be regarded as a sufficient
    reason, and therefore the plea cannot be permitted at the stage of
    Section 34 proceedings.
37. L.G. Chaudhary (II) (supra) carved out the aforesaid limited exception
    to the general rule laid down in Lion Engineering (supra) that a plea
    of lack of jurisdiction, being a pure question of law, may be raised for
    the first time under Section 34 of the Act, 1996. The failure of L.G.
    Chaudhary (II) (supra) to take into consideration the decision of this
    Court in Lion Engineering (supra) does not render the former per
    incuriam, as there exists no direct conflict between the two. While
    Lion Engineering (supra) permits a jurisdictional plea to be raised
    under Section 34 of the Act, 1996 even if not urged under Section
    16, L.G. Chaudhary (II) (supra) merely clarifies that an arbitral award
    will not be annulled solely on that ground, particularly where the issue
    was not raised before the tribunal. On the contrary, the aforesaid
    observations of L.G. Chaudhary (II) (supra) had been consciously
    made by this Court keeping in mind the ratio of Lion Engineering
    (supra), even though the latter was never explicitly referred to.
    L.G. Chaudhary (II) (supra) cannot be termed to be per incuriam,
    as the very factum that the aforesaid observations were made by
    L.G. Chaudhary (II) (supra) in paras 16, 17 and 19 respectively
    shows that this Court was well aware of the decision of this Court
    in Lion Engineering (supra), and accordingly chose to carve out an
    exception to the ratio of Lion Engineering (supra) keeping in mind
    the cleavage of judicial view that was prevailing earlier.
2590                                                           [2025] 5 S.C.R.

                           Supreme Court Reports


38. In view of the above exposition of law, what has been conveyed by
    this Court in L.G. Chaudhary (II) (supra) in so many words is that: -
     i.     Where the arbitration proceedings are still underway, but no
            statement of defence has been filed, there it would be open
            for the parties to raise an objection of lack of jurisdiction in
            view of the applicability of MP Act, 1983. The parties will also
            be at liberty to approach the High Court by way of a petition
            under Article 227 of the Constitution for seeking a transfer of
            the arbitration proceedings to the M.P. State Arbitration Tribunal
            under the MP Act, 1983.
     ii.    Where the arbitration proceedings are still underway, but
            statement of defence has already been filed i.e., the relevant
            stage for raising an issue of jurisdiction is already crossed,
            there it would not be open for the parties to raise an objection
            of lack of jurisdiction in view of the applicability of MP Act, 1983.
            Furthermore, in such scenarios since the arbitration proceedings
            have already commenced and made substantial progress,
            it would not be appropriate to transfer such proceedings to
            the M.P. State Arbitration Tribunal under the MP Act, 1983,
            and the better course of action would be to let the arbitration
            proceedings conclude.
     iii.   As per L.G. Chaudhary (II) (supra) where the arbitration
            proceedings have concluded and an award has been passed,
            and if no objection to the jurisdiction in view of the applicability
            of MP Act, 1983 was taken at the relevant stage then such
            an award cannot be annulled only on the ground of lack of
            jurisdiction.
     iv.    Any award passed by an arbitral tribunal under the Act, 1996,
            where otherwise the MP Act, 1983 was applicable, such an
            award may be challenged or assailed in terms of Section 34
            and thereafter Section 37 of the Act, 1996 and other relevant
            provisions thereunder.
     v.     Any award passed by an arbitral tribunal under the Act, 1996,
            where otherwise the MP Act, 1983 was applicable, such an
            award must be executed in terms of the MP Act, 1983 and the
            relevant provisions thereunder.
[2025] 5 S.C.R.                                                             2591

                      M/s Gayatri Project Limited v.
          Madhya Pradesh Road Development Corporation Limited

     vi.    Where the objection based on applicability of the MP Act,
            1983 had been raised in the written statement or statement of
            defence, but the parties never took steps towards challenging
            the jurisdiction of the arbitral tribunal under Section 16 of the
            Act, 1996 or where such plea of jurisdiction was turned down
            in view of the position of law that was prevailing prior to L.G.
            Chaudhary (II) (supra) i.e., such challenge to the jurisdiction was
            decided prior to the date of pronouncement of L.G. Chaudhary
            (II) (supra), then even in such cases, as per the decision of this
            Court in Modern Builders (supra), the award should not be
            disturbed or set-aside only on the ground of lack of jurisdiction.
39. In the present case at hand, we take note of the following
    circumstances emerging from the facts on record: -
     a.     It is an admitted fact that at the time of constitution of the arbitral
            tribunal, the respondent never objected to the invocation of
            arbitration under the Act, 1996 and both the parties proceeded
            to nominated their respective co-arbitrators.
     b.     On the date of invocation of the Act, 1996, and commencement
            of arbitration proceedings, as well as of the date when the
            arbitration proceeding concluded and the award in question
            passed, the erstwhile decision of this Court in VA Tech (supra)
            held the field.
     c.     The respondent herein never raised any objection to the arbitral
            tribunal’s lack of jurisdiction during the arbitration proceedings
            either in its statement of defence or by way of an application
            under Section 16 of the Act, 1996.
     d.     Even when the award was challenged by the respondents,
            the initial petition filed by them under Section 34 of the Act,
            1996 also did not contain any objection as regards the lack of
            jurisdiction of the arbitral tribunal.
     e.     The ground of lack of jurisdiction was introduced by the
            respondents herein only after the decision of L.G. Chaudhary
            (II) (supra) by way of an application for amending the grounds
            of its petition under Section 34 of the Act, 1996, i.e., after the
            award had been passed.
2592                                                     [2025] 5 S.C.R.

                         Supreme Court Reports


40. Thus, the present case is squarely covered by the decision of
    this Court in L.G. Chaudhary (II) (supra), more particularly the
    observations made in paras 6 to 9 thereunder, and as such once
    the award had been passed and no objection as to the jurisdiction
    of the arbitral tribunal had been taken at the relevant stage, then
    the award could not have been annulled by the High Court only on
    the ground of lack of jurisdiction.
41. For all the foregoing reasons, we have reached the conclusion
    that the High Court committed an egregious error in passing the
    impugned judgment. We are left with no other option but to set aside
    the impugned judgment and order passed by the High Court, and
    restore the proceedings in Arbitration Case No. 48 of 2011 to the
    court of Commercial Court and 19th Upper District Judge, Bhopal
    (M.P.), for deciding all other issues on merit that may have been
    raised by the respondent in its petition under Section 34 of the Act,
    1996. We accordingly pass such order. Thus, the appeal is disposed
    of in the above terms.
42. Pending application(s) if any, also stand disposed of.
43. We direct the Registry to circulate a copy of this judgment to all
    High Courts.
     Result of the case: Appeal disposed of.


     †
         Headnotes prepared by: Mukund P. Unny, Hony. Associate Editor
                                 (Verified by: Liz Mathew, Sr. Adv.)


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.