Created byFuzzy Cloud

Supreme Court of India

M/S. FORTUNE INFRASTRUCTURE (NOW KNOWN AS M/S. HICON INFRASTRUCTURE) & ANR.versusTREVOR D’LIMA & ORS.

Citation
2018 INSC 233
Decided
12 March 2018
Disposal
Case Partly allowed

Holding

Compensation for breach of a real‑estate contract must be compensatory, based on actual loss, and the NCDRC's award of Rs. 3,65,46,000 was excessive, warranting reduction to Rs. 2,27,20,000.

Summary

The appellants, developers of the Hicon Onyx residential project, failed to deliver a flat purchased by the respondents and transferred the project to another company, prompting a consumer complaint under the Consumer Protection Act, 1986. The National Consumer Disputes Redressal Commission (NCDRC) held that the developers were guilty of deficiency in service and ordered a refund of the purchase price along with a compensation of Rs. 3,65,46,000. On appeal, the Supreme Court examined the principles of contractual damages, emphasizing that in real‑estate transactions the seller must prove bona‑fides and best efforts, and that damages should be compensatory, not a gain‑based award. The Court found the NCDRC's compensation excessive, noting that damages should be assessed based on actual loss and market rates, and that the date of breach need not be rigidly applied. Consequently, the Court reduced the compensation to Rs. 2,27,20,000, fixed a market rate of Rs. 50,000 per sq. ft. for valuation, and upheld the refund and parking compensation. The appeals were therefore partly allowed.

Issues considered

  • The existence of deficiency in service and unfair trade practice by the developers under the Consumer Protection Act, 1986.
  • Whether the compensation awarded by the NCDRC was excessive and amounted to a gain‑based remedy.
  • How contractual damages should be assessed in real‑estate transactions, including the applicable law and the appropriate date of assessment.
  • The appropriate quantum of compensation, considering market rates and actual loss.

Legislation cited

Subjects

consumer protectioncontractual damagesreal estatedeficiency of serviceunfair trade practicecompensationIndian Contract ActNCDRCprice escalationmarket ratebreach of contract

Judgment

                           [2018] 3 S.C.R. 273                            273


         M/S. FORTUNE INFRASTRUCTURE                                      A
(NOW KNOWN AS M/S. HICON INFRASTRUCTURE) & ANR.
                       v.
                     TREVOR D’LIMA & ORS.
                (Civil Appeal Nos. 3533-3534 of 2017)
                                                                          B
                          MARCH 12, 2018
        [N. V. RAMANA AND S. ABDUL NAZEER, JJ.]
      Consumer Protection Act, 1986 :
       Complaint against developer of housing project – By the            C
purchaser of a flat in the project – Alleging deficiency in service
and unfair trade practices for not having delivered the flat –
National Consumer Disputes Redressal Commission allowed the
complaint and directed the developers to refund the amount paid
by the complainants and also to pay compensation and cost of
litigation – On appeal, held: Contractual damages are usually             D
awarded to compensate an injured party to a breach of contract
for the loss of his bargain – This rule is more qualified when it
comes to real estate sector – Onus is on the seller to show his bona
fides and best efforts in discharging the obligation – Mere
unwillingness to carry out the duty could constitute bad faith            E
sufficient for purchaser to claim damages – In the facts of the present
case there is deficiency of service on part of the developer, which
entitles the complainant to damages/compensation – Generally
damages become due on the date when the breach of contract takes
place and assessed by the reference to the time of breach –
However, the rule is flexible which needs to be assessed in the facts     F
and circumstances of individual case – In the facts of the present
case the damage need not be determined from the date of breach of
contract – The compensation granted by the National Commission
has surpassed the actual-loss based damages and has entered the
domain of gain-based remedy – Since the damages for the                   G
contractual breach is compensatory, damages awarded should not
be excessive – Court needs to take a balanced approach so as to
ensure right compensation – Therefore compensation of
Rs. 3,65,46,000/- granted by National Commission is reduced to
Rs. 2,27,20,000/- – Compensation.
                                                                          H
                                 273
274            SUPREME COURT REPORTS                      [2018] 3 S.C.R.


A           Damages for commercial contracts – Under the Act –
      Determination of – Held: Under Consumer Protection Act damages
      for commercial contracts, need to be determined as per Contract
      Act – Contract Act, 1872 .
            Partly allowing the appeals, the Court
B           HELD : 1. The contractual damages are usually awarded to
      compensate an injured party to a breach of contract for the loss
      of his bargain. This rule is more qualified when it comes to the
      real estate sector. If the seller wants to limit their liability for
      breach of contract under the aforesaid rule, they have to portray
C     that they have performed their obligation in a prudent manner.
      The onus is on the seller to show his best efforts and bona fides
      in discharging the obligation. Even in the absence of fraud, mere
      unwillingness to carry out the duty could constitute bad faith
      sufficient for the purchaser to claim damages. [Paras 11 and
      12][280-F-H; 281-A]
D
             2. Whenever the builder has refused to perform the
      contract without valid justification, the buyer is entitled for
      compensation as he has been deprived of price escalation of the
      flat. Every breach of contract gives rise to an action for damages.
      Such amount of damages must be proved with reasonable
E     certainty. [Para 19] [283-D]
           3. Even under the Consumer Protection Act, 1986, the
      damages for commercial contracts need to be determined as per
      the Contract Act. [Para 16] [282-A]
             4. In the facts and circumstances of the present case, there
F
      is deficiency of service on the part of the appellants, which
      entitles the complainant to damages/compensation. The
      appellants did not give any valid reasons as to why they
      transferred the property to a third party, despite their
      contractual obligation to the respondents (complainants). The
G     obligation was on the appellants to show that he was unable to
      transfer the property to the respondent. Moreover, a person
      cannot be made to wait indefinitely for the possession of the flats
      allotted to them and they are entitled to seek the refund of the
      amount paid by them, along with compensation. Although there
      was no delivery period stipulated in the agreement, a reasonable
H
   M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR                       275
                   D’LIMA & ORS.

time has to be taken into consideration. [Paras 14 and 15] [281-      A
D-F]
       5. The damages become due on the date when the breach
of contract takes place, and are normally assessed by reference
to the time of breach. The aforesaid rule is based on the principle
that the injured party is presumed to be in knowledge of the breach   B
as soon as it is committed and at that time he can take appropriate
measures of mitigation to control the loss flowing from the breach.
The courts may deviate from the aforesaid rule and fix
appropriate date in facts and circumstance of a case if aforesaid
presumptions could not be established or it would not be
reasonable to follow the rule. [Para 21] [283-F-H; 284-A]             C
       6. Where a party sustains loss by reason of a breach of
contract, the damages are to be granted so as to place the
suffering party in the same position as if the contract had been
performed. In light of the above, the damages other than
consequential loss have to be measured at the time of the breach.     D
However, the aforesaid rule is flexible which needs to be assessed
in facts and circumstances of individual case. [Para 22] [284-C-
D]
       7. Where there is non-delivery of the flat/house, and the
developer has refused to provide alternative and equivalent           E
accommodation, and the buyer lacks means to purchase a
substitute from the market, then in such circumstances,
damages would not be reasonable to be assessed on the breach
date. [Para 21] [284-A]
       8. In the present case, the complainants (respondents) tried
                                                                      F
to execute the agreement and sought for conveyance of the
property through the NCDRC. In these circumstances, even in
the first appeal, offers were being made on behalf of appellants to
convey alternative properties, which were refused as being
insufficient. Therefore, in the facts and circumstances of the
present case, the damage need not be determined from the date         G
of breach of contract. [Para 22] [284-E]
      9. Appellants have produced circle rates of properties in
the vicinity of the disputed flats, which vary from Rs. 18,655 per
Sq. Ft. to Rs. 25,787/- per Sq. Ft. Whereas the respondents have
produced executed sale deeds in the nearby vicinity, which was        H
276            SUPREME COURT REPORTS                      [2018] 3 S.C.R.


A     Rs. 65,000 per Sq. ft., Rs. 69,342/- per Sq. ft., Rs. 75,000/- per
      Sq. Ft. and Rs. 88,050/- per Sq. Ft.. NCDRC has taken the
      minimum available market price as the reference point for
      awarding compensation at the rate of Rs. 65,000/- per Sq. Ft.
      Excessive reliance on the aforesaid sale deed may not be
      appropriate as the present property is a redevelopment of an
B
      earlier property. Usually the real estate rates for re-developed
      properties are on the lower side instead of green-field projects.
      [Para 24] [284-G-H; 285-A]
           10. Thus, the claim of the respondents (complainants) as
      granted by the NCDRC seems to surpass the actual-loss based
C     damages and enter the domain of gain-based remedy. It would
      not be appropriate to grant such damages. There is no dispute
      about the fact that damages for the contractual breach is
      generally compensatory arising out of the breach. Therefore, the
      damages awarded should not be excessive and a court/tribunal
D     needs to take a balanced approach so as to ensure right
      compensation. [Para 25] [285-B-C]
            11. It would be appropriate, just and reasonable that the
      market rate be fixed at Rs. 50,000/- per Sq. Ft. (Rupees Fifty
      Thousand per square feet) as the reference rate for determination
E     of market price prevailing in the vicinity of the disputed property.
      Hence, the estimated market price would be Rs.4,14,20,000/-
      instead of Rs.5,38,46,000/- as granted by the NCDRC. However,
      there is no reason to interfere in respect of the compensation
      granted for the parking space. [Para 26] [285-D-E]

F           Ghaziabad Development Authority v. Balbir Singh
            (2004) 5 SCC 65 : [2004] 3 SCR 68 – relied on.
            Johnson and Anr. v. Agnew [1979] 1 All ER 883 –
            referred to.
                             Case Law Reference
G
            [1979] 1 All ER 883       referred to           Para 11
            [2004] 3 SCR 68           relied on             Para 18



H
   M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR                               277
                   D’LIMA & ORS.

      CIVIL APPELLATE JURISDICTION : Civil Appeal Nos. 3533-                  A
3534 of 2017.
      From the Judgment and Order dated 08.09.2016 and final Order
dated 03.11.2016 of the National Consumer Disputes Redressal
Commission, New Delhi in Consumer Complaint No. 636 of 2015 and in
Review Application No.273 of 2016 in Consumer Complaint No.636 of             B
2015 respectively.
       Raju Ramachandran, Sachin Dutta, Sr. Advs, Rishi Agrawala,
Ms. Swati Sinha, Ms. Manisha Ambwani (for E.C. Agrawala), Advs
for the Appellants.
       Abir Phukan, Ms. Marilyn Khakha (for V. Shyamohan), Advs               C
for the Respondents.
      The Judgment of the Court was delivered by
       N. V. RAMANA, J. 1. These appeals are filed against the
impugned orders, dated 08.09.2016 and 03.11.2016, passed by the National      D
Consumer Disputes Redressal Commission [hereinafter ‘NCDRC’ for
brevity], in Consumer Complaint No. 636 of 2015 and Review Application
No. 273 of 2016 in the Consumer Complaint No. 636 of 2015.
        2. A few facts which are necessary for the disposal of this matter
are that the appellants, in the year 2011, launched a residential housing     E
project by name ‘Hicons Onyx’, renamed as Fortune Residency, which
was a re-development of Mohammadi House. The respondents booked
a flat bearing no. 202, 2nd Floor in ‘A’ wing, admeasuring 828.40 Sq. Ft.
with one unit of parking-space. The total consideration for the flat was
Rs. 1,93,00,000/-. It is alleged by the appellants, that due to increase in
the cost beyond what was expected, they transferred the project to            F
another company being M/s. Zoy Shelcon Pvt. Ltd. It is to be noted that
the respondents have paid a sale consideration of Rs. 1,87,00,000/-.
       3. In 2015, aggrieved by the fact that appellants were not willing
to deliver the flat to them, the respondents approached NCDRC through
a consumer complaint, being CC No. 636 of 2015, with following prayers-       G
      a. To hold and declare the Opposite Parties to be guilty of
          deficiency in service and unfair trade practices as per the
          provisions of the Consumer Protection Act, 1986

                                                                              H
278       SUPREME COURT REPORTS                         [2018] 3 S.C.R.


A     b. To direct the Opposite Parties 1 to 4 to comply with their
         statutory obligations and to execute and register the Agreement
         for Sale with the complainants in respect of flat No. 202 on the
         2nd floor admeasuring 828.40 Sq. Ft. with one car parking in the
         building known as Hicon Onyx and since re-named as Fortune
         residency situated at plot no. F/1116-A, Village Bandra, St.
B
         Martins Road Bandra (West), Mumbai 400 050 (Maharashtra).
      c. To direct the Opposite Parties no. 1 to 4 to complete the
          construction of the building known as ‘Hicons Onyx’ since
          renamed as ‘Fortune residency’ and to hand over to the
          complainants vacant and peaceful possession of the Flat No.
C         202 on the 2nd floor admeasuring 828.40 Sq. Ft. with one car
          parking in the building known as Hicons Onyx and since
          renamed as Fortune residency situated at plot no. F/1116-A,
          Village Bandra, St. Martins road Bandra (West), Mumbai 400
          050 (Maharashtra) on receiving the balance consideration
D         amount of Rs. 6,00,000/-from the complainants
                                  Alternatively
         In the event of the Opposite Parties no. 1 to 4 having created
         third party interests in favour of the Opposite Party no. 5, to
         direct the Opposite parties no. 1 to 4 to hand over to the
E        complainants any other flat of the same size quality and
         specifications with one car parking in the same building ‘Hicons
         Onyx’ since re-named as ‘Fortune Residency’ or any flat of the
         same size, quality and specifications with one car parking in the
         same locality of the present building Hicons Onyx or Fortune
F        Residency.
          x x x x x
          x x x x x
      f. To direct the Opposite Parties No. 1 to 4 jointly and severally
         pay to the complainants Rs.5,00,000/- (Rupees Five lakhs only)
G
         towards compensation for the inconvenience and mental agony
         suffered by the complainants due to the enormous delay in
         construction of the building, negligence and deficiency in
         service of the Opposite Parties No. 1 to 4.

H
   M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR                                279
            D’LIMA & ORS. [N.V. RAMANA, J.]

    g. To direct the opposite Parties No. 1 to 4 jointly and severally to      A
        pay to the complainants the sum of Rs. 1,00,000/- (Rupees One
        Lakh only) being the Legal and other incidental expenses
        incurred by the complainants.
    h. For such other and further relief as this Hon’ble Commission
       may deem fit and proper in the nature and circumstances of the          B
       above numbered complaint.
        4. The NCDRC has allowed the complaint and directed the
appellants: 1. To refund the amount of Rs. 1,87,00,000/- which they have
received from the complainants, within six weeks from the day of the
impugned judgment; 2. The appellants were further directed to pay a            C
sum of Rs. 3,65,46,000/- as compensation and Rs. 10,000/- as cost of
litigation to the complainants within six weeks from the day of the
impugned judgment; 3. The aforesaid amount was ordered to be paid at
10% per annum from the date of the order till the actual date of
payment. It may be noted that even the review against the aforesaid
order was dismissed by the NCDRC vide order dated 03.11.2016.                  D

    5. Having dissatisfied with the impugned orders passed by the
NCDRC, appellants approached this Court through these civil appeals.
        6. At the threshold it was brought to our notice that on 08.09.2016,
when the matter was argued, on most of the other dates the appellants          E
remained unrepresented before NCDRC. Further the counsels
representing the appellants stated that their counsel appointed for the
forum below did not file necessary pleadings except for a proforma
reply. Keeping in view of the above, they argued that this case should be
remanded back to the NCDRC for fresh consideration. However, on
careful consideration of facts of this case, we are of the opinion that a      F
remand may not be required at this stage. To put a quietus to the
litigation, the controversy can be adjudicated by this Court.
      7. Learned counsel for the appellants, primarily submitted that
the present appellants have transferred the project to a different
company thereby they should be discharged from any liability for not           G
handing over the disputed property to the answering respondents
(Complainants). He further argued that, the present circle rate of the
disputed property is pegged at approximately half the price awarded by
the NCDRC. Lastly, he urged before this Court to consider the
                                                                               H
280             SUPREME COURT REPORTS                             [2018] 3 S.C.R.


A     downward trends shown in the real estate market which mandates a
      lesser compensation, compared to the one awarded by the NCDRC.
            8. Per Contra, the learned counsel appearing on behalf of the
      answering respondents (Complainants) fully supported the reasoning of
      the NCDRC in coming to a conclusion that, the appellants herein
B     provided deficient service by delaying the handing over of the flat to the
      complainants. In all fairness, learned counsel for answering respondents
      have admitted that prices as contemplated under the impugned order of
      NCDRC are not reflective of the true market rates for similar flats
      available in the near vicinity of the disputed flats.
C            9. It would not be out of context to mention that during the
      hearing of this case, many attempts were made by both parties to
      amicably settle the issue concerning the quantum of compensation which
      could not fructify. Further we requested Shri. Raju Ramachandran,
      learned senior advocate, to use his good office to persuade parties to
      settle the matter. Such an endeavour also could not impress upon the
D     parties and therefore this court was called upon to adjudicate the matter.
            10. Having heard learned counsels on either side and perusing the
      materials available on record, the issue that fall for consideration is
      whether there is deficiency of service on the part of the appellants? If
      so, what is just and reasonable compensation?
E
             11. It is now well established that the contractual damages are
      usually awarded to compensate an injured party to a breach of contract
      for the loss of his bargain. In the case of Johnson and Anr. V. Agnew,
      [1979] 1 All ER 883, the aforesaid case has clearly held as under-

F            The general principle for the assessment of damages is
             compensatory, i.e. that the innocent party is to be placed, so far
             as money can do so, in the same position as if the contract had
             been performed.
             12. The aforesaid proposition remains to hold the field and has
      been applied consistently. This rule is more qualified when it comes to
G
      the real estate sector. If the seller wants to limit their liability for breach
      of contract under the aforesaid rule, they have to portray that they have
      performed their obligation in a prudent manner. It may be noted that the
      onus is on the seller to show his best efforts and bona fides in
      discharging the obligation. It may be noted that even in the absence of
H
   M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR                               281
            D’LIMA & ORS. [N.V. RAMANA, J.]

fraud, mere unwillingness to carry out the duty could constitute bad faith    A
sufficient for the purchaser to claim damages.
      13. To decide whether the respondent ought to be awarded
compensation because of deficiency of service, it is important to
consider the meaning of deficiency as provided under Section 2(1)(g) of
the Consumer Protection Act, 1986.                                            B
      (g) “deficiency” means any fault, imperfection, shortcoming or
inadequacy in the quality, nature and manner of performance which is
required to be maintained by or under any law for the time being in force
or has been undertaken to be performed by a person in pursuance of a
contract or otherwise in relation to any service;                             C
       In light of the above definition, we have to examine whether there
is any deficiency in service, which entitles the complainant to damages/
compensation.
       14. In the present case, the appellants did not give any valid
reasons as to why they transferred the property to a third party, despite     D
their contractual obligation to the respondents (complainants). The
obligation was on the appellants to show that he was unable to transfer
the property to the respondent.
      15. Moreover, a person cannot be made to wait indefinitely for
the possession of the flats allotted to them and they are entitled to seek    E
the refund of the amount paid by them, along with compensation.
Although we are aware of the fact that when there was no delivery
period stipulated in the agreement, a reasonable time has to be taken
into consideration. In the facts and circumstances of this case, a time
period of 3 years would have been reasonable for completion of the            F
contract i.e., the possession was required to be given by last quarter of
2014. Further there is no dispute as to the fact that until now there is no
redevelopment of the property. Hence, in view of the above discussion,
which draw us to an irresistible conclusion that there is deficiency of
service on the part of the appellants and accordingly the issue is
answered. When once this Court comes to the conclusion that, there is         G
deficiency of services, then the question is what compensation the
respondents/complainants is entitled to ?
      16. Before we come to the aspect of quantum of compensation,
it would be appropriate to look at the settled legal position concerning
                                                                              H
282             SUPREME COURT REPORTS                             [2018] 3 S.C.R.


A     the same. At the outset, we may note that even under the Consumer
      Protection Act, 1986, the damages for commercial contracts need to be
      determined as per the Indian Contract Act.
             17. It would be pertinent to note that in common law, claim for
      damages is the rule and specific performance is an exception, while in
B     civil law front, specific performance has traditionally been a prime
      remedy for the breach of contract.1
             18. This Court in Ghaziabad Development Authority v. Balbir
      Singh, (2004) 5 SCC 65, has observed that there is no fixed formula for
      fixing damages in the following manner-
C            8. However, the power and duty to award compensation does not
             mean that irrespective of facts of the case compensation can be
             awarded in all matters at a uniform rate of 18% per annum. As
             seen above, what is being awarded is compensation i.e. a
             recompense for the loss or injury. It therefore necessarily
D            has to be based on a finding of loss or injury and has to
             correlate with the amount of loss or injury. Thus, the Forum
             or the Commission must determine that there has been deficiency
             in service and/or misfeasance in public office which has resulted
             in loss or injury. No hard-and-fast rule can be laid down, however,
             a few examples would be where an allotment is made, price is
E            received/paid but possession is not given within the period set out
             in the brochure. The Commission/Forum would then need to
             determine the loss. Loss could be determined on basis of loss of
             rent which could have been earned if possession was given and
             the premises let out or if the consumer has had to stay in rented
F            premises then on basis of rent actually paid by him. Along with
             recompensing the loss the Commission/Forum may also
             compensate for harassment/injury, both mental and physical.
             Similarly, compensation can be given if after allotment is
             made there has been cancellation of scheme without any
             justifiable cause.
G
             9. That compensation cannot be uniform and can best be
             illustrated by considering cases where possession is being directed
             to be delivered and cases where only monies are directed to be
             returned. In cases where possession is being directed to be
      1
H      Apparent from the study of French Civil Code (FCC) and German Civil Code
      (BGB).
   M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR                               283
            D’LIMA & ORS. [N.V. RAMANA, J.]

      delivered the compensation for harassment will necessarily have         A
      to be less because in a way that party is being compensated by
      increase in the value of the property he is getting. But in cases
      where monies are being simply returned then the party is
      suffering a loss inasmuch as he had deposited the money in
      the hope of getting a flat/plot. He is being deprived of that
                                                                              B
      flat/plot. He has been deprived of the benefit of escalation
      of the price of that flat/plot. Therefore, the compensation
      in such cases would necessarily have to be higher.…We
      clarify that the above are mere examples. They are not
      exhaustive. The above shows that compensation cannot be
      the same in all cases irrespective of the type of loss or               C
      injury suffered by the consumer.
                                                   (emphasis supplied)
       19. It must be noted that the law is well settled in this regard.
Whenever the builder has refused to perform the contract without valid
justification, the buyer is entitled for compensation as he has been          D
deprived of price escalation of the flat. Every breach of contract gives
rise to an action for damages. Such amount of damages must be proved
with reasonable certainty.
      20. Before we assess the damages, another important issue to be
delved upon is the reckoning date for the purpose of the assessing the        E
damages. Whether should it be from the date on which the breach took
place or should it be from the date of judgment?
       21. Learned counsel for the appellants, with some vehemence,
argued that the rates of the property have considerably slumped due to
downfall in the real-estate market. Such submissions are to be tested as      F
per the established principles of law. As per the settled law, the damages
become due on the date when the breach of contract takes place, and
are normally assessed by the reference to the time of breach. The
aforesaid rule is based on the principle that the injured party is presumed
to be in knowledge of the breach as soon as it is committed and at that       G
time he can take appropriate measures of mitigation to control the loss
flowing from the breach. The courts may deviate from the aforesaid
rule and fix appropriate date in facts and circumstance of a case if
aforesaid presumptions could not be established or it would not be

                                                                              H
284             SUPREME COURT REPORTS                           [2018] 3 S.C.R.


A     reasonable to follow the rule. It may be noted that where there is non-
      delivery of the flat/house, and the developer has refused to provide
      alternative and equivalent accommodation, and the buyer lacks means
      to purchase a substitute from the market, then in such circumstances,
      damages would not be reasonable to be assessed on the breach date.
B            22. We have already noted that the appellants were to perform
      the contract within a reasonable period of three years from the date of
      the agreement i.e., by the last quarter of 2014. Aggrieved by the delay in
      handing over the possession, the respondents (complainants) approached
      the NCDRC for conveyance and in alternative prayed for damages. It
      is now settled that where a party sustains loss by reason of a breach of
C     contract, the damages are to be granted so as to place the suffering
      party in the same position as if the contract had been performed. In light
      of the above, the damages other than consequential loss have to be
      measured at the time of the breach. However, the aforesaid rule is
      flexible which needs to be assessed in facts and circumstances of
D     individual case. In this case at hand the respondents tried to execute the
      agreement and sought for conveyance of the property through the
      NCDRC. In these circumstances we may note that, even in the first
      appeal, offers were being made on behalf of appellants to convey
      alternative properties, which were refused as being insufficient.
      Therefore, in facts and circumstances of this case, the damage need not
E     be determined from the date of breach of contract.
             23. Even though the appellants raised a factual issue concerning
      the non-payment of part-consideration, we do not think it is necessary to
      go into this aspect, as the NCDRC has given a categorical finding that
      Rs. 1,87,00,000/- has been paid by the respondents (complainants).
F
              24. Appellants have produced circle rates of properties in the
      vicinity of the disputed flats. These rates vary from Rs. 18,655 per Sq.
      Ft. to Rs. 25,787/- per Sq. Ft. Whereas the respondents have produced
      executed sale deeds in the nearby vicinity, which was Rs. 65,000per Sq.
      ft., Rs. 69,342/- per Sq. ft., Rs. 75,000/- per Sq. Ft. and Rs. 88,050/- per
G     Sq. Ft. NCDRC has taken the minimum available market price as the
      reference point for awarding compensation at the rate of Rs. 65,000/-
      per Sq. Ft.We are of the opinion that excessive reliance on the aforesaid
      sale deed may not be appropriate as the present property is a
      redevelopment of an earlier property. Our attention has been drawn to
H
   M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR                               285
            D’LIMA & ORS. [N.V. RAMANA, J.]

the fact that usually the real estate rates for re-developed properties are   A
on the lower side instead of green-field projects.
       25. In light of the above, we consider that the claim of the
respondents (complainants) as granted by the NCDRC seems to
surpass the actual-loss based damages and enter the domain of
gain-based remedy. Although we do not recognize any a priopri                 B
limitations on such claim, but we do not think that it would be appropriate
to grant such damages in the case at hand. There is no dispute about the
fact that damages for the contractual breach is generally compensatory
arising out of the breach. Therefore, the damages awarded should not
be excessive and a court/tribunal needs to take a balanced approach so
as to ensure right compensation.                                              C

       26. Taking into consideration of factual aspects involved in the
matter and on consideration of the submissions of the counsels on either
side, we deem it appropriate, just and reasonable that the market rate be
fixed at Rs.50,000/- per Sq. Ft. (Rupees Fifty Thousand per square feet)
as the reference rate for determination of market price prevailing in the     D
vicinity of the disputed property. Hence, the estimated market price would
be Rs.4,14,20,000/- instead of Rs.5,38,46,000/- as granted by the
NCDRC. However, we do not see any reason to interfere in respect of
the compensation granted for the parking space.
         27. Therefore, the appellants are directed as under-                 E

    a.    To refund the amount of Rs. 1,87,00,000/- which they have
          received from the complainants.
    b.     To pay a sum of Rs. 2,27,20,000/- as compensation to the
           complainants.                                                      F
    c. To pay a sum of Rs. 20,00,000/- as compensation for one unit of
        parking lot.
    d.     The appellants shall also pay Rs. 10,000/- as the cost of
           litigation to the complainants.
    e. The aforesaid amount is required to be paid within six weeks           G
        from the day of this order. If the payment in terms of this order
        is not made within the time stipulated herein, it shall carry
        interest of 9% per annum from the date of this order.

                                                                              H
286             SUPREME COURT REPORTS                         [2018] 3 S.C.R.


A            28. It is to be noted that this Court vide order dated 23.02.2017,
      while issuing notice, directed the appellants to deposit Rs. 2,50,00,000/-
      before NCDRC as a condition precedent for hearing this case. Later it
      was represented to us that the appellants as on 31.05.2017, had
      deposited the aforesaid amountbefore NCDRC. In view of the above,
      we allow the respondents (complainants) to withdraw the aforesaid
B
      amount with accrued interest, if any and the same be adjusted to the
      appellants’ liability as indicated above.
             29. In light of the above discussions, we allow the appeals in part
      to the extent indicated above. There shall be no order as to the costs.
C
      Kalpana K. Tripathy                                   Appeals partly allowed.




D




E




F




G




H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "consumer protection"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.