Created byFuzzy Cloud

Supreme Court of India

M/S A.K.G. CONSTRUCTION AND DEVELOPERS PVT. LTDversusSTATE OF JHARKHAND & ORS.

Citation
2026 INSC 312
Decided
2 April 2026
Disposal
Disposed off

Holding

A blacklisting order that is not preceded by a specific, reasoned show‑cause notice and fails to demonstrate application of mind is illegal, arbitrary and must be set aside, whereas a termination order based on clear findings of negligence is valid.

Summary

M/s A.K.G. Construction and Developers Pvt. Ltd was contracted by the Jharkhand Water and Sanitation Department to build an elevated service reservoir. The reservoir's top dome collapsed on 1 June 2024, prompting a show‑cause notice alleging negligence and poor quality. The department subsequently issued a combined termination and blacklisting order on 23 August 2024, blacklisting the contractor for five years. The contractor challenged both orders; the High Court upheld them, but the Supreme Court found the termination justified while holding that the blacklisting order violated natural‑justice principles because it lacked a specific show‑cause notice and application of mind. The Court set aside the blacklisting order, directing that it cease to operate immediately, and dismissed the appeals concerning termination.

Issues considered

  • Whether the department’s blacklisting order is valid in view of the requirements of natural justice and the Contractor Registration Rules, 2012.
  • Whether the termination of the contract was lawful under the General Conditions of Contract.
  • Whether a show‑cause notice specific to blacklisting is mandatory before imposing a blacklisting order.

Legislation cited

Headnote

Issue for Consideration Whether the black listing order, in the instant case, suffers from patent infirmities; whether the blacklisting, being stigmatic and exclusionary in nature, can be imposed mechanistically. Headnotes† Contract – Termination – Blacklisting – contractor with the Water and Sanitation Department was contracted for construction of an Elevated Service Reservoir (ESR) by issuance of a Letter of Acceptance (LOA) on 06.03.2023 – During the subsistence of the contract, on 01.06.2024, the top dome of the reservoir collapsed –

Subjects

ContractTerminationBlacklistingAudi alteram partemNegligencePrinciples of natural justiceShow-cause noticeNon-application of mindReasonableness

Judgment

            [2026] 4 S.C.R. 331 : 2026 INSC 312

  M/s A.K.G. Construction and Developers Pvt. Ltd
                         v.
             State of Jharkhand & Ors.
                 (Civil Appeal No. 4152 of 2026)
                            02 April 2026
[Pamidighantam Sri Narasimha and Alok Aradhe, JJ.]


                      Issue for Consideration
 Whether the black listing order, in the instant case, suffers from
 patent infirmities; whether the blacklisting, being stigmatic and
 exclusionary in nature, can be imposed mechanistically.

                             Headnotes†
 Contract – Termination – Blacklisting – The appellant,
 a registered contractor with the Water and Sanitation
 Department was contracted for construction of an Elevated
 Service Reservoir (ESR) by issuance of a Letter of
 Acceptance (LOA) on 06.03.2023 – During the subsistence
 of the contract, on 01.06.2024, the top dome of the reservoir
 collapsed – Department issued a show cause notice dated
 04.06.2024 seeking explanation as to why action should not
 be taken for the negligence and bad quality of work – Upon
 receiving concurrent reports indicating negligence on part
 of appellant, respondent no. 3, Chief Engineer, Drinking
 Water and Sanitation Department, passed the termination
 cum blacklisting order dated 23.08.2024 – Aggrieved, the
 appellant filed an appeal, which was dismissed by the
 Appellate Authority – Appellant filed writ petition, which was
 also dismissed – Correctness:
 Held: In view of the clear findings of negligence as articulated in the
 order of termination, this Court will not interfere with the decision
 of termination – In so far as the order relating to blacklisting is
 concerned, the blacklisting order suffers from patent infirmities: it
 evinces no application of mind, disregards the mandatory precept of
 audi alteram partem, and fails to precede with a show-cause notice
 requiring the contractor to demonstrate why such drastic action
 should not be taken – Blacklisting, being stigmatic and exclusionary
332                                                              [2026] 4 S.C.R.

                            Supreme Court Reports


       in nature, cannot be imposed mechanistically but must comport with
       principles of natural justice and reasonableness – The final order
       of blacklisting, dated 23.08.2024, does not list the reasons as to
       why an order of blacklisting has become necessary – A blacklisting
       order assumes that the contractor is an incorrigible entity, at least
       for some time to come, in this case such an assumption was
       intended to operate for five years – For giving effect to such a
       premise, there has to be sufficient evidence, clear application of
       mind and stronger adherence to principles of natural justice – The
       blacklisting order dated 23.08.2004 falls short of this requirement
       and is liable to be set aside – Thus, the decision of blacklisting of
       the appellant is illegal, arbitrary and unreasonable – The declaration
       of blacklisting is set aside. [Paras 15, 16, 3, 23, 25]

       Contract – Termination – Blacklisting:
       Held: The contractual conditions governing termination on the one
       hand and those that relate to blacklisting on the other are distinct
       and will be exercised independently – A decision of blacklisting
       is not automatic and certainly not a logical consequence of a
       decision of termination – Even after the Department decides
       to terminate the contract, there is still a choice of exercising
       the power of blacklisting – These decisions operate in two
       dimensions-past and subsisting for termination and future for
       blacklisting – In other words, an order of blacklisting transcends
       the existing contract and debars the contractor from contracts that
       could probably be executed in the next five years – In view of
       the serious consequences, it is necessary for the Department to
       issue a specific notice proposing blacklisting of a contractor and
       call for an explanation as to why an order of blacklisting should
       not be passed. [Para 18]

                                Case Law Cited
       Erusian Equipment & Chemicals Ltd. v. State of West Bengal,
       [1975] 2 SCR 674 : (1975) 1 SCC 70; UMC Technologies Pvt
       Ltd v. Food Corporation of India [2020] 13 SCR 1175 : (2021) 2
       SCC 551; M/s Techno Prints v. Chhattisgarh Textbook Corporation
       & Anr., 2025 INSC 236 : [2025] 3 SCR 208 – relied on.
       Raghunath Thakur v. State of Bihar, [1988] 3 Supp. SCR 867 :
       (1989) 1 SCC 229; Gorkha Security Services v. Govt. (NCT of Delhi)
[2026] 4 S.C.R.                                                             333

            M/s A.K.G. Construction and Developers Pvt. Ltd v.
                        State of Jharkhand & Ors.

     [2014] 13 SCR 617 : (2014) 9 SCC 105; Kulja Industries Ltd. v.
     Chief General Manager, Western Telecom Project BSNL [2013]
     14 SCR 430 : (2014) 14 SCC 731; The Blue Dreamz Advertising
     Pvt Ltd. & Anr. v. Kolkata Municipal Corporation & Ors., 2024
     INSC 589 : [2024] 8 SCR 189 – referred to.

                                List of Acts
     Contractor Registration Rules, 2012.

                             List of Keywords
     Contract; Termination; Blacklisting; Audi alteram partem; Negligence;
     Principles of natural justice; Show-cause notice; Non-application
     of mind; Reasonableness.

                            Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4152 of 2026
     From the Judgment and Order dated 07.02.2025 of the High Court
     of Jharkhand at Ranchi in WPC No. 6886 of 2024.
     With
     Civil Appeal No. 4153 of 2026.

                         Appearances for Parties
     Advs. for the Appellant(s):
     M.S. Ganesh, Sr.Adv., R. Ayyam Perumal, Ms. Archana Sharma,
     Rao Raj Bahadur Singh, A. Sai Kumar.
     Advs. for the Respondent(s):
     Kumar Anurag Singh, Jayant Mohan, Ms. Meenakshi Chatterjee,
     Zain A. Khan, Ms. Adya Shree Dutta, Ms. Dorjee Ongmu Lachungpa,
     Priyanshu Teotia, Dev Aaryan, Mohd. Abran Khan.

                 Judgment / Order of the Supreme Court

                                 Judgment

1.   Leave granted.
2.   While exercising judicial review over administrative actions of the State
     and its instrumentalities in relation to contracts provisioning clauses
334                                                             [2026] 4 S.C.R.

                            Supreme Court Reports


       and rules relating to termination and/or blacklisting, Courts must apply
       distinct standards of legality, rationality and proportionality. Such an
       approach is compelling as conditions for imposing such measures,
       as also the consequences of such actions, have differing gravity.
3.     Upon careful consideration of the impugned State action, which
       terminates the contract and blacklists the appellant without meaningful
       distinction, we hold that the termination order is substantiated and
       justified. However, the blacklisting order suffers from patent infirmities:
       it evinces no application of mind, disregards the mandatory precept of
       audi alteram partem, and fails to precede with a show-cause notice
       requiring the contractor to demonstrate why such drastic action
       should not be taken. Blacklisting, being stigmatic and exclusionary
       in nature, cannot be imposed mechanistically but must comport with
       principles of natural justice and reasonableness.
4.     For the reasons detailed hereafter, we uphold the order of termination
       and the impugned judgement and review order affirming the same,
       but set aside the decision to blacklist the appellant.
5.     Having upheld the order of termination, we were of the opinion
       that the assumed logical consequence of blacklisting is neither
       supported by application of mind nor followed by a clear notice
       proposing blacklisting. For the reasons to follow, we set aside the
       order of blacklisting. However, in the facts and circumstances of the
       case, due to passage of time, we have suitably moulded the relief
       and directed that the order of blacklisting shall not continue for five
       years as directed by the Department but will cease to operate from
       the date of our judgment.

       Facts
6.     The appellant, a registered contractor with the Water and Sanitation
       Department was contracted for construction of an Elevated Service
       Reservoir (ESR) by issuance of a Letter of Acceptance (LOA) on
       06.03.2023. During the subsistence of the contract, on 01.06.2024,
       the top dome of the reservoir collapsed. Though it was justified as
       being a result of an unexpected cyclone, the appellant offered to
       reconstruct it at own expense. However, the Department issued a
       show cause notice dated 04.06.2024, seeking explanation as to why
       action should not be taken for the negligence and bad quality of work.
       The contents of the show cause notice are as follows -
[2026] 4 S.C.R.                                                          335

          M/s A.K.G. Construction and Developers Pvt. Ltd v.
                      State of Jharkhand & Ors.

                      “(PURPOTED SHOW CAUSE)
                     GOVERNMENT OF JHARKHAND
              DRINKING WATER & SANITATION DEPARTMENT
           Letter No. 4/A.V.-01-1019/2024-1311
           From,
                    Navneet Kumar
                    Under Secretary to the Government.
           To,
                    M/s. A.K.G. Construction & Developers
                    Pvt. Ltd. Ranchi.
                                                Ranchi, Date- 4/6/24
           Subject: Regarding submitting clarification.
           Context: Letter No. 727 of Executive Engineer, Drinking
           Water and Sanitation Division, Jhumritilaiya, dated
           01.06.2024.
           Sir,
           As per the directions, the department received information
           about collapse of the under-construction water tower in
           Neemadhi village under Koderma-Demchonch Jaynagar
           Mega Rural Water Supply Scheme through the relevant
           letter on the above subject.
           The collapse of the under-construction water tower proves
           that quality was not taken care of in the construction of
           the water tower.
           Due to your not doing quality work as per the agreement
           in the construction of the water tower, the water tower
           collapsed due to which the image of the department got
           tarnished.
           Therefore, it is directed by attaching a copy of the letter
           describing tire incident that why action should not be taken
           against you as per rules for negligence shown by you and
           not doing quality construction and, ensure to submit your
           explanation within 03 (three) days. In case of not receiving
           the explanation on time, it will be considered that you have
336                                                         [2026] 4 S.C.R.

                          Supreme Court Reports


            nothing to say regarding the allegation and the department
            will be free to take unilateral action.
                                           Translation- As Aforesaid
                                                     Yours sincerely,
                                                        Sd./-Illegible
                                                         04/06/2024
                                                    (Navneet Kumar)
                                Under Secretary to the Government.”
7.     Following the show cause notice, multi-level enquiries were
       conducted. Initially, a three-member committee gave its report on
       06.06.2024. Thereafter, the Superintending Engineer also examined
       the matter in detail. These enquiries drew inputs from Birsa Institute
       of Technology, Sindri and also IITs of Delhi, Madras and Bombay.
       Upon receiving concurrent reports indicating negligence on part of
       the appellant, respondent no. 3, Chief Engineer, Drinking Water and
       Sanitation Department, passed the termination cum blacklisting order
       dated 23.08.2024. The order containing the reasons for termination
       and blacklisting is reproduced below for ready reference;
                     “GOVERNMENT OF JHARKHAND
              DRINKING WATER & SANITATION DEPARTMENT
               Order No.-4/A.V.-01-102l/2024-20(CDO), Ranchi,
                              Date- 23/08/2024
                                     ORDER
            It was informed by letter no. 727 dated 01.06.2024 of
            Executive Engineer, Drinking Water and Sanitation Division,
            Jhumritilaiya that the water tower under construction in
            Neemadhi village under the work of Koderma-Domchonch
            Jaynagar Large Rural Water Supply Scheme, which is
            allotteed to the contractor M/s A.K.G. Construction &
            Developers Pvt. Ltd., Ranchi, collapsed on 01.06.2024.
            In the light of the above, the contractor was asked
            for clarification by departmental letter no. 1311 dated
            04.06.2024, in the light of which the contractor submitted
            clarification through letter no. AKG/24-25/26 dated
            06.06.2024 in which the contractor has reported that no
            laxity has been shown in the construction of the under-
            construction water tower and the under-construction water
[2026] 4 S.C.R.                                                             337

          M/s A.K.G. Construction and Developers Pvt. Ltd v.
                      State of Jharkhand & Ors.

           tower fell due to natural disaster/cyclonic storm. In the light
           of the above, by letter no. 663 (CDO) dated 21.06.2024
           of this office, the Superintending Engineer, Drinking Water
           and Sanitation Zone, Hazaribagh was directed to review
           the clarification received from the contractor point by point
           and provide a report with his clear opinion. The opinion
           was provided by letter no. 545 dated 21.06.2024 of the
           Superintending Engineer, Drinking Water and Sanitation
           Zone, Hazaribagh in which it is reported that the work
           described has not been done as per the approved Design
           & Drawing and the quality of the overall work has not been
           taken care of.
           In the matter described by the department, an inquiry was
           conducted by a three-member inquiry committee. The
           inquiry committee submitted the inquiry report through
           departmental G.S.P. No.-283 dated 06.06.2024 in which
           it is reported that negligence was shown in getting the
           construction work of the water tower completed as per the
           approved Design & Drawing and quality was not taken care
           of, due to which the incident of collapse/demolition of the
           water tower occurred. Thus, the contractor is responsible/
           guilty for negligence and negligence in getting the quality
           work done.
           The contractor informed the concerned Executive Engineer
           through his letter-AKG/24-25/23 dated-01.06.2024 that he
           is ready to construct ESR again at his own expense in
           place of the demolished ESR under construction. It was
           never appropriate for him to construct ESR again without
           departmental order. This act of his reflects an attempt to
           hide his wrongdoings.
           The department condemns this modus operandi of the
           contractor.
           It is clear from the above that the contractor got low
           quality construction work done in the work of the scheme,
           which tarnished the image of the department and created
           obstacles in achieving the objectives of the department.
           This is a clear violation of rule number-10.1.8 and 10.1.15
           of the Contractor Registration Rules 2012. Therefore,
338                                                            [2026] 4 S.C.R.

                           Supreme Court Reports


            after review by the department, the explanation of the
            contractor is rejected.
            Therefore, after due consideration by the department in
            the light of Rule No. 10.1.8 and 10.01.15 of Contractor
            Registration Rules 2012, the contractor M/s A.K.G.
            Construction & Developers Pvt. Ltd., Panna Enclave, Flat
            No-202, Kadru, Ranchi-834002, e-mail: ketan.kumar007@
            gmail.com is blacklisted for 5 (five) years with immediate
            effect and in this context, the following order is given in the
            light of Rule No. 10.3 and 10.4 of Contractor Registration
            Rules 2012:-
            2. It is decided to stop all the works being done by the
            contractor from the date of issuance of the order and
            to confiscate the security deposit of all the works. Also,
            the concerned regional Chief Engineer/Superintending
            Engineer/Executive Engineer will ensure to take appropriate
            action as per the requirement to complete the remaining
            work being done by the contractor.
            3. The registration of the contractor in all categories in the
            department is cancelled with immediate effect.
            4. The proposal has received the approval of the Hon’ble
            Departmental Minister.
                                                 (Prabhat Kumar Singh)
                                                  Chief Engineer, C.D.O
                                                      Date: 23/08/2024”
8.     Aggrieved, the appellant filed an appeal, which came to be dismissed
       vide order dated 05.12.2024 of the Appellate Authority cum Principal
       Secretary, Drinking Water and Sanitation Department. The appellant
       filed a writ petition challenging orders dated 23.08.2024 and
       05.12.2024. By impugned judgement and order dated 07.02.2025,
       the High Court dismissed the writ petition, while also imposing a cost
       of Rs. 2 lakhs on the appellant. It was held that the corroborated
       findings of the enquiries conducted, as also the appellant’s own
       admission in the form of offering to reconstruct the entire ESR at
       its own cost, leads to a logical inference of negligence in carrying
       out the construction as per the approved design and drawings. It
       was also held that the orders impugned were neither illegal nor
[2026] 4 S.C.R.                                                          339

           M/s A.K.G. Construction and Developers Pvt. Ltd v.
                       State of Jharkhand & Ors.

     arbitrary as proper opportunity was given to the appellant at every
     stage.
9.   The appellant sought a review of the decision arrived by the High
     Court on self-same grounds, which naturally came to be dismissed
     by the High Court vide impugned order dated 04.08.2025. Thus, the
     present appeals have been filed against the main judgement as well
     as the review order.

     Submissions
10. Mr. M.S. Ganesh, learned senior counsel appearing on behalf of the
    appellant, would submit that the termination as well as the blacklisting
    are illegal and arbitrary. He would submit that constitution of the three-
    member committee, followed by its report and subsequent reports,
    were without giving any opportunity to the appellant. He would also
    submit that the arbitrariness is writ large as the decision to blacklist
    had the effect of terminating all subsisting contracts.
11. Mr. Kumar Anurag Singh, learned counsel for the respondent
    Department would submit that Clause 59 of the General Conditions
    of Contract (GCC), dealing with termination of contract does not
    provide for a prior notice. He would also rely on Rule 10 of the
    Contractor Registration Rules, 2012, dealing with blacklisting, which
    mandates issuance of a show cause notice before blacklisting a
    contractor upon misconduct. He would submit that the show cause
    notice 04.06.2024 was specifically for purpose of blacklisting the
    appellant, which according to him, is further cemented by express
    use of the phrase “why action should not be taken against it as
    per the rules”. In view of the concurrent operation of GCC and
    the 2012 Rules, he submits that the common order of termination
    cum blacklisting is compliant of all conditions and therefore legal
    and valid.

     Analysis
12. The controversy revolves around a true and correct interpretation
    of Clause 59 of GCC, relating to termination, and Rule 10 of 2012
    Rules, relating to blacklisting. The Clause and the Rule is reproduced
    herein for ready reference.
13. Clause 59 of GCC is as follows -
340                                                     [2026] 4 S.C.R.

                     Supreme Court Reports


       “59.Termination
       59.1. The Employer or the Contractor may terminate the
       Contract if the other party causes a fundamental breach
       of the Contract.
       59.2. Fundamental breaches of Contract include, but shall
       not be limited to the following:
       (a) The Contractor stops work for 28 days when no
       stoppage of work is shown on the current Programme and
       the stoppage has not been authorized by the Engineer;
       (b) The Engineer instructs the Contractor to delay the
       progress of the Works and the instruction is not withdrawn
       within 28 days;
       (c) The Employer or the Contractor is made bankrupt or
       goes into liquidation other than for a reconstruction or
       amalgamation.
       (d) The Engineer gives Notice that failure to correct a
       particular Defect is a fundamental breach of Contract and
       the Contractor fails to correct it within a reasonable period
       of time determined by the Engineer.
       (e) The Contractor does not maintain a security which is
       required;
       (f) The Contractor has delayed the completion of works
       by the number of days for which the maximum amount of
       liquidated damages can be paid as defined in the Contract
       data; and
       (g) If the Contractor, in the judgment of the Employer has
       engaged in corrupt or fraudulent practices in competing
       for or in executing the Contract.
       For the purpose of this paragraph: “corrupt practice” means
       the offering, giving, receiving or soliciting of anything of
       value to influence the action of a public official in the
       procurement process or in contract execution. “Fraudulent
       practice” means a misrepresentation of facts in order to
       influence a procurement process or the execution of a
       contract to the detriment of the Borrower, and includes
[2026] 4 S.C.R.                                                           341

          M/s A.K.G. Construction and Developers Pvt. Ltd v.
                      State of Jharkhand & Ors.

           collusive practice among Bidders (prior to or after bid
           submission) designed to establish bid prices at artificial
           non-competitive levels and to deprive the Borrower of the
           benefits of free and open competition.”
           59.3. When either party to the Contract gives notice of a
           breach of contract to the Engineer for a cause other than
           those listed under Sub Clause 59.2. above, the Engineer
           shall decide whether the breach is fundamental or not.
           59.4. Notwithstanding the above, the Employer may
           terminate the Contract for convenience.
           59.5. If the Contract is terminated the Contractor shall
           stop work immediately, make the Site safe and secure and
           leave the Site as soon as reasonably possible”
14. Rule 10 of Contractor Registration Rules, 2012 is as follows -
           “10. BLACKLISTING
           10.1 A contractor in person or any partner of a registered
           firm or any director of a private public limited company or
           his technical staff or any of his authorized representatives,
           registered in any of the above categories, may be
           blacklisted for any of the following misconducts:
           10.1.1 Creating law and order problem in Government
           office while receiving tender documents, submitting tender
           documents or doing any work related thereto.
           10.1.2 Intimidating or assaulting concerned officer or
           employee.
           10.1.3 If the contractor is found selling or misusing
           Government goods such as cement, steel and pipes etc..
           10.1.4 If convicted in any criminal activity.
           10.1.5 If wrong documents are submitted for registration
           under these rules.
           10.1.6 In case of being banned or blacklisted by any
           department/undertaking of the Government of India or
           any State Government.
           10.1.7 In case of violation of Rule 6.2 of these rules.
342                                                      [2026] 4 S.C.R.

                      Supreme Court Reports


       10.1.8 Failure to execute the work as per the agreement
       and prescribed specifications.
       10.1.9 In case of the contractor handing over his work to
       another contractor or any person without departmental
       order (subletting).
       10.1.10 No improvement is reflected in the conduct of the
       suspended contractor.
       10.1.11 Corrupting or attempting to corrupt the tender
       process.
       10.1.12 indulging in malpractices likes bribery, corruption
       or fraud.
       10.1.13 any such act which obstructs the achievement of
       the objectives of the works department.
       10.1.14 applying political pressure directly or indirectly.
       10.1.15 doing work of poor quality.
       10.1.16 directly or indirectly threatening or intimidating
       departmental officers/employees.
       10.1.17 not achieving physical targets in proportion to the
       time elapsed.
       10.2 The blacklisted contractor will be debarred from
       working in any Government Department / Undertaking in
       future and his registration will be cancelled with immediate
       effect.
       10.3 If a registered contractor is blacklisted in any one
       category in the light of Rule 10.1, then the registration of
       the said contractor in all other categories, if any, will also
       be deemed to be cancelled with immediate effect.
       10.4 All the works being carried out by the blacklisted
       contractor in the Department of Drinking Water and
       Sanitation, Jharkhand will be stopped from the date of
       the order issued in the light of Rule 10.1, and the security
       deposit of all the works will be forfeited and appropriate
       action will be taken as per requirement to complete the
       remaining works.
[2026] 4 S.C.R.                                                           343

          M/s A.K.G. Construction and Developers Pvt. Ltd v.
                      State of Jharkhand & Ors.

           10.5. Before blacklisting a contractor of a particular
           category, it will be necessary to issue a show cause notice.
           10.6 The order of blacklisting can be passed by the
           registration officer of the concerned category or the officer
           under who’s supervision/under whose supervision the
           registration officer is working.
           10.7 Against the penalty imposed, the contractor may
           file an appeal before the departmental secretary within
           thirty days.
           10.8 After approval by the government, the blacklisting
           order will be issued by the concerned registration officer.”
15. Before we proceed to consider the Rules relating to blacklisting and
    its adverse consequences, we may state that it was made clear to
    Mr. M.S. Ganesh, learned senior counsel for the appellant, that in
    view of the clear findings of negligence as articulated in the order
    of termination, we will not interfere with the decision of termination.
    As regards the submission of Mr. M.S. Ganesh that the appellant
    did not have sufficient opportunity to defend himself, notwithstanding
    the submission of Mr. Kumar Anurag Singh that termination does
    not require prior notice, we are of the opinion that the appellant had
    sufficient opportunity at the common hearing for termination and
    blacklisting. Further, the appellant argued the entire case before the
    Appellate Authority. Appellant also raised and contested the case
    on merits before the Division Bench. Having examined the contest
    and its due consideration all through, we are of the opinion that the
    decision as regards termination is unimpeachable, on merits as well
    as on the grounds of due process.
16. In so far as the order relating to blacklisting is concerned, we are
    of the opinion that this issue requires close scrutiny and that will be
    undertaken by reference to Rule 10 of the 2012 Rules.
17. A cursory reading of Rule 10 makes it evident that an order of
    blacklisting has serious consequences, effecting not only the existing
    contracts but also bars future business transactions for some years.
    Under Rule 10.3, if a registered contractor is blacklisted for any one
    category as per Rule 10.1, then the registration of the said contractor
    in all other categories, if any, will be deemed to be cancelled with
    immediate effect. Upon such cancellation, under Rule 10.4, all the
344                                                                             [2026] 4 S.C.R.

                                Supreme Court Reports


       works carried out by the blacklisted contractor in the department will
       be stopped from the date of issuance of order under Rule 10.1. It also
       provides that the security deposit for all the works will be forfeited.
18. The contractual conditions governing termination on the one hand
    and those that relate to blacklisting on the other are distinct and will
    be exercised independently. A decision of blacklisting is not automatic
    and certainly not a logical consequence of a decision of termination.
    Even after the Department decides to terminate the contract, there is
    still a choice of exercising the power of blacklisting. These decisions
    operate in two dimensions - past and subsisting for termination
    and future for blacklisting. In other words, an order of blacklisting
    transcends the existing contract and debars the contractor from
    contracts that could probably be executed in the next five years. In
    view of the serious consequences, it is necessary for the Department
    to issue a specific notice proposing blacklisting of a contractor and
    call for an explanation as to why an order of blacklisting should not
    be passed. This is exactly the purpose and object behind Rule 10.5.
19. The requirement under Clause 10.5 is a clear case of legislative (in
    this case subordinate legislation) incorporation of principles of natural
    justice. This Court has time and again emphasised the need to adhere
    to principles of natural justice while passing blacklisting orders,
    given the grave consequences that follow. In Erusian Equipment &
    Chemicals Ltd. v. State of West Bengal1, it was observed that –
             “15. The blacklisting order does not pertain to any
             particular contract. The blacklisting order involves civil
             consequences. It casts a slur. It creates a barrier between
             the persons blacklisted and the Government in the matter
             of transactions. The blacklists are “instruments of
             coercion”.
             20. Blacklisting has the effect of preventing a person
             from the privilege and advantage of entering into lawful
             relationship with the Government for purposes of gains.
             The fact that a disability is created by the order of
             blacklisting indicates that the relevant authority is


1   (1975) 1 SCC 70. The principle in Eurasian Equipment has been reiterated by this Court in many
    subsequent judgements such as Raghunath Thakur v. State of Bihar (1989) 1 SCC 229, Gorkha Security
    Services v. Govt. (NCT of Delhi), (2014) 9 SCC 105, etc.
[2026] 4 S.C.R.                                                              345

             M/s A.K.G. Construction and Developers Pvt. Ltd v.
                         State of Jharkhand & Ors.

             to have an objective satisfaction. Fundamentals of fair
             play require that the person concerned should be given
             an opportunity to represent his case before he is put on
             the blacklist.”
20. In order to emphasise the requirement of a show cause notice
    preceding an order of blacklisting, this Court in UMC Technologies
    Pvt Ltd v. Food Corporation of India2 held that –
             “13. At the outset, it must be noted that it is the first
             principle of civilised jurisprudence that a person against
             whom any action is sought to be taken or whose right or
             interests are being affected should be given a reasonable
             opportunity to defend himself. The basic principle of
             natural justice is that before adjudication starts,
             the authority concerned should give to the affected
             party a notice of the case against him so that he can
             defend himself. Such notice should be adequate and
             the grounds necessitating action and the penalty/
             action proposed should be mentioned specifically and
             unambiguously. An order travelling beyond the bounds
             of notice is impermissible and without jurisdiction to that
             extent. This Court in Nasir Ahmad v. Custodian General,
             Evacuee Property3 has held that it is essential for the notice
             to specify the particular grounds on the basis of which an
             action is proposed to be taken so as to enable the noticee
             to answer the case against him. If these conditions are not
             satisfied, the person cannot be said to have been granted
             any reasonable opportunity of being heard.
             14. Specifically, in the context of blacklisting of a
             person or an entity by the State or a State Corporation,
             the requirement of a valid, particularised and
             unambiguous show-cause notice is particularly crucial
             due to the severe consequences of blacklisting and
             the stigmatisation that accrues to the person/entity
             being blacklisted. Here, it may be gainful to describe
             the concept of blacklisting and the graveness of the


2   (2021) 2 SCC 551.
3   Nasir Ahmad v. Custodian General, Evacuee Property, (1980) 3 SCC 1.
346                                                         [2026] 4 S.C.R.

                          Supreme Court Reports


            consequences occasioned by it. Blacklisting has the
            effect of denying a person or an entity the privileged
            opportunity of entering into government contracts.
            This privilege arises because it is the State who is the
            counterparty in government contracts and as such, every
            eligible person is to be afforded an equal opportunity
            to participate in such contracts, without arbitrariness
            and discrimination. Not only does blacklisting take
            away this privilege, it also tarnishes the blacklisted
            person’s reputation and brings the person’s character
            into question. Blacklisting also has long-lasting civil
            consequences for the future business prospects of
            the blacklisted person.
            21. Thus, from the above discussion, a clear legal position
            emerges that for a show-cause notice to constitute the
            valid basis of a blacklisting order, such notice must
            spell out clearly, or its contents be such that it can
            be clearly inferred therefrom, that there is intention
            on the part of the issuer of the notice to blacklist the
            noticee. Such a clear notice is essential for ensuring
            that the person against whom the penalty of blacklisting
            is intended to be imposed, has an adequate, informed
            and meaningful opportunity to show cause against his
            possible blacklisting.”
21. The judgment in M/S Techno Prints v. Chhattisgarh Textbook
    Corporation & Anr.4 underscored the need for a detailed consideration
    of the consequences of blacklisting right at the outset, that is,
    from the stage of issuing of show cause notice. The Court held as
    follows –
            “29. However, what is important for us to say is that
            when there are guiding principles explained by
            this Court as to when & in what circumstances a
            blacklisting order can be passed then, in our opinion
            such principles should also be borne in mind by the
            Authority at the time of issuing a show cause notice.
            We say so because in the facts of a given case like the


4   2025 INSC 236.
[2026] 4 S.C.R.                                                         347

          M/s A.K.G. Construction and Developers Pvt. Ltd v.
                      State of Jharkhand & Ors.

           one on hand, on the face of which it could be said that
           there was no good reason for the Authority to issue a show
           cause notice calling upon the contractor why he should
           not be blacklisted. Why ask the contractor to face the
           proceedings when applying the aforesaid principles, the
           issue of show cause notice would be an empty formality.
           We are saying all this keeping in mind the peculiar facts
           of this case.
           30. Therefore, the Authority is expected to be very careful
           before issuing a show cause notice. It is expected to
           understand the facts well and try to ascertain what sort of
           violation is said to have been committed by the contractor.
           As noted above, there is always an inherent power in
           the Authority to blacklist a contractor. But possessing
           such inherent power and exercising such power are
           two different situations and connotations. There may
           be a power but there should be reasonable ground to
           exercise such power.
           31. To put it by way of an illustration, the Police has the
           power to arrest but it is not necessary that in all cases
           arrest must be effected. The Police should know whether
           at all arrest is necessary.
           32. We may put it in a slightly different way. Take for
           instance, the show cause notice in the present case
           is the final order of blacklisting. The final order in any
           case cannot travel beyond the show cause notice.
           Therefore, we take the show cause notice as the final
           order. Whether it makes out a case for blacklisting?
           This should be the test to determine whether it is a
           genuine case to blacklist a contractor or visit him
           with any other penalty like forfeiture of EMD, recovery
           of damages etc. We say so because once an order
           of blacklisting is passed the same would put an
           end to the business of the person concerned. It is
           a drastic step. Once the final order blacklisting the
           Contractor is passed then the Contractor is left with
           no other option but to go to the High Court invoking
           writ jurisdiction under Article 226 of the Constitution
348                                                         [2026] 4 S.C.R.

                         Supreme Court Reports


          and challenge the same. If he succeeds before the
          Single Judge then it is well and good otherwise he
          may have to prefer a writ appeal or LPA as the case
          may be. This again would lead to unnecessary litigation
          in the High Courts. The endeavour should be to curtail
          the litigation and not to overburden the High Courts with
          litigations of the present type more particularly when
          the law by and large is very well settled and there is no
          further scope of any debate.”
22. Returning to the facts of the present case, at the outset, it is
    apparent that the show cause notice dated 04.06.2024 does not
    purport to be a show cause notice for blacklisting at all. It perhaps
    expects the contractor to assume that it is for termination as
    well as for blacklisting. Even if we accept the submissions of Mr.
    Kumar Anurag Singh that, as there is no provision for prior notice
    before termination, this show cause notice must be taken to be
    for blacklisting, we are of the opinion that it still falls short of the
    requirement of a proper show cause notice for blacklisting. This is
    for the reason that as the decision to blacklist is independent of the
    decision to terminate, the Department must demonstrate application
    of mind before it takes the next step of blacklisting the contractor,
    over an order of termination. Upon taking such a decision, it must
    also issue a show cause notice calling upon the contractor to explain
    why a consequential order of blacklisting should also not be passed.
    The letter must be indicative of the proposed decision to blacklist
    and the requirement of the contractor to respond to it. The show
    cause notice dated 04.06.2024 falls short of these requirements.
    Similarly, the final order of blacklisting, dated 23.08.2024, also
    does not list the reasons as to why an order of blacklisting has
    become necessary.
23. The contractual relationship between the parties is governed by two
    legal regimes. While GCC governs termination, the 2012 Rules govern
    blacklisting. Proceedings for termination should not be conflated with
    proceedings for blacklisting. In the latter action, what is at stake is
    the future of the contractor. A blacklisting order assumes that the
    contractor is an incorrigible entity, at least for some time to come, in
    this case such an assumption was intended to operate for five years.
    For giving effect to such a premise, there has to be sufficient evidence,
    clear application of mind and stronger adherence to principles of
[2026] 4 S.C.R.                                                                                  349

             M/s A.K.G. Construction and Developers Pvt. Ltd v.
                         State of Jharkhand & Ors.

     natural justice5. The blacklisting order dated 23.08.2004 falls short
     of this requirement and is liable to be set aside.
24. As a consequence of our decision to set aside the blacklisting order,
    we would have required the Department to issue a fresh show
    cause notice indicative of the reasons as to why a blacklisting order
    is felt necessary and to thereby call upon the contractor to show
    cause. However, in view of the fact that the order of termination cum
    blacklisting was passed on 23.08.2024, and since then almost more
    than one and a half year has already passed, without there being
    a stay of the said order in the meantime, we are of the opinion that
    the relief to be granted can suitably be moulded by directing that
    the order of blacklisting will cease to operate with immediate effect.
    This order will benefit the appellant more than the Department,
    because directing issuance of a fresh show cause notice will only
    lead to further litigation.
25. Having considered the matter in detail and taking into account the
    unimpeachable material about the negligence of the appellant leading
    to collapse of the top dome of the ESR, we are of the opinion that the
    order of termination of all contracts is legal and valid. Civil Appeals
    to this extent are dismissed. However, the decision of blacklisting of
    the appellant is illegal, arbitrary and unreasonable. The declaration of
    blacklisting is set aside, and shall cease to operate with immediate
    effect.


     Result of the case: Appeals disposed of.




     †
         Headnotes prepared by: Ankit Gyan




5   Kulja Industries Ltd. v. Chief General Manager, Western Telecom Project BSNL, (2014) 14 SCC 731; The
    Blue Dreamz Advertising Pvt Ltd. & Anr. v. Kolkata Municipal Corporation & Ors, 2024 INSC 589, M/s
    Techno Prints (supra).


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Contract"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.