Created byFuzzy Cloud

Supreme Court of India

LARSEN AND TOUBRO LIMITEDversusPURI CONSTRUCTION PVT. LTD. AND OTHERS

Citation
2025 INSC 523
Decided
21 April 2025
Disposal
Dismissed

Holding

A court cannot modify an arbitral award; it may only set aside or confirm it under Sections 34 and 37 of the Arbitration Act, and thus the Division Bench did not modify the award.

Summary

Larsen & Toubro (L&T) and Puri Construction Ltd (PCL) entered into a Development Agreement for land development, later supplemented by a Supplementary Agreement and a Tripartite Agreement involving a bank. Disputes arose over alleged economic duress, non‑fulfilment of conditions precedent, and L&T's abandonment of the project, leading to an arbitral award that imposed monetary liability on L&T. A Single Judge set aside the award under s.34 of the Arbitration Act, but the Delhi High Court Division Bench partially restored findings, upheld the award’s cost order, and left the quantification of damages open. L&T and PCL appealed, raising the question whether the court could modify an award by partially setting it aside. The Supreme Court held that under s.34 and s.37 the court's power is limited to setting aside or confirming an award, not modifying it, and therefore the Division Bench did not modify the award. Consequently, the appeals were dismissed, the award’s monetary liability remains set aside, costs to PCL are upheld, and the parties must pursue appropriate legal remedies.

Issues considered

  • The scope of power of a court under Section 34 of the Arbitration and Conciliation Act, 1996 to partly set aside an arbitral award
  • Whether the appellate court under Section 37 can modify an award in a manner not permitted under Section 34
  • Whether the Supplementary Agreement is a non‑starter and vitiated by economic duress
  • Whether L&T committed a fundamental breach of the Development Agreement
  • Whether the quantification of damages (Rs.35 crores) and other monetary awards can be set aside
  • Whether the court can remand the matter to the arbitral tribunal for quantification of the monetary claim
  • Whether the award’s cost order can be confirmed

Legislation cited

Headnote

Issue for Consideration In petition u/s.34, Arbitration and Conciliation Act, 1996, Single Judge had set aside the Arbitral Award. Division Bench in appeal thereagainst u/s.37, Arbitration Act by way of the impugned judgment, inter alia upheld the dismissal of L&T’s counter-claim findings of the Arbitral Tribunal that the Supplementary Agreement was a non-starter as it was vitiated by economic duress; that the Development Agreement was not novated by the Supplementary Agreement; that L&T committed fundamental breach of the Development Agreement. The operative part of

Subjects

Power of court under s.34 Arbitration ActPower of appellate court under s.37 Arbitration ActArbitral award modificationEconomic duressSupplementary Agreement non‑starterFundamental breachSection 73 Contract Act damagesCost of arbitrationLimited jurisdiction of courts in arbitration

Judgment

                 [2025] 4 S.C.R. 2811 : 2025 INSC 523

                     Larsen and Toubro Limited
                                 v.
               Puri Construction Pvt. Ltd. and Others
                  (Civil Appeal No(s). 2575-2578 of 2016)
                                 21 April 2025
               [Abhay S. Oka* and Pankaj Mithal, JJ.]


                           Issue for Consideration
       In petition u/s.34, Arbitration and Conciliation Act, 1996, Single
       Judge had set aside the Arbitral Award. Division Bench in appeal
       thereagainst u/s.37, Arbitration Act by way of the impugned
       judgment, inter alia upheld the dismissal of L&T’s counter-claim
       and agreed with the findings of the Arbitral Tribunal that the
       Supplementary Agreement was a non-starter as it was vitiated
       by economic duress; that the Development Agreement was not
       novated by the Supplementary Agreement; that L&T committed
       fundamental breach of the Development Agreement. The operative
       part of the award fixing the monetary liability of L&T was set aside
       while leaving open the remedy of PCL for the quantification of
       the monetary claim. The award regarding costs was confirmed
       however, the Division Bench did not restore any part of the arbitral
       award and the parties were left to pursue the appropriate course of
       action. Issue as regards the correctness of the impugned judgment,
       challenged by both, L&T and PCL; power of the court u/s.34,
       Arbitration Act of partly setting aside the award; whether in the
       facts and circumstances of the present case, the Division Bench
       modified the Award by partly setting aside the judgment u/s.34.

                                  Headnotes†
       Arbitration and Conciliation Act, 1996 – ss.34, 37 – Puri
       Construction Limited and its sister concerns (‘PCL’) were in
       possession of certain lands as the owner – PCL had entered
       into a joint venture with ITC Classic Real Estate Finance Limited
       (ITCREF) for the development of lands, however, ultimately,
       ITCREF exited from the business – L&T and PCL entered into an
       agreement for land development (Development Agreement) –
       Later, a supplementary agreement was entered into between
       them on the basis of which a Tripartite Agreement was entered

* Author
2812                                                         [2025] 4 S.C.R.

                         Supreme Court Reports


    into between PCL, L&T and the Bank – Disputes arose – Arbitral
    Award was passed holding inter alia that L&T jeopardised
    PCL’s obligations towards ITCREF; it resiled from and went
    back upon its original contractual obligations and tried to
    effect sales without sanction under the revised development
    plan and without making any provision for the responsibility
    towards ITCREF; L&T abandoned the Development Agreement;
    Supplementary Agreement was tainted by economic coercion
    and the signatures of PCL were obtained by fraud – In petition
    u/s.34, Single Judge set aside the award – By the impugned
    judgment, Division Bench disagreed with certain findings of
    the Single Judge, allowing the appeals preferred by PCL to that
    extent and the appeal by L&T was dismissed – However, the
    parties were left to pursue the appropriate course of actions
    under law – Challenge to, by both PCL and L&T:
    Held: 1.1 Powers of the Appellate Court u/s.37 of the Arbitration
    Act are not broader than those of the Court u/s.34 of the Arbitration
    Act – Therefore, what cannot be done in the exercise of the powers
    u/s.34 cannot be done in an Appeal u/s.37 – An Arbitral Award
    cannot be modified – In the present case, the Division Bench
    has not modified the award by partly setting aside the Judgment
    u/s.34 – The remedy of PCL was kept open to pursue appropriate
    course of action under law as there cannot be a remand to the
    Arbitral Tribunal for quantification of monetary claim – As the
    finding of the Arbitral Tribunal regarding breaches committed by
    L&T was affirmed, the Division Bench rightly segregated that part
    of the award by which, cost of arbitration was ordered to be paid
    to PCL by L&T – As documents of title were deposited with the
    Registrar, the direction to hand over the same to PCL cannot be
    faulted with. [Para 56]
    1.2 In view of the clauses in the Supplementary Agreement, the
    finding recorded by the Tribunal that, as the conditions precedent
    in the relevant clauses were not complied with by L&T, the
    Supplementary Agreement was a non-starter is a possible finding
    which could not have been interfered with u/s.34 of the Arbitration
    Act – Moreover, it is a finding of fact. [Para 46]
    1.3 Further, after examining the evidence, the Division Bench
    held that there was no patent illegality in the findings recorded by
    the Arbitral Tribunal that the Supplementary Agreement and the
    Tripartite Agreement were tainted by coercion – On facts, such a
[2025] 4 S.C.R.                                                                2813

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


     view by the Arbitral Tribunal is not contrary to justice and morality –
     View taken by the Division Bench, agreed with. [Para 48]
     1.4 The finding recorded by the Tribunal that L&T committed
     fundamental breaches of the agreement cannot be interfered
     within the limited jurisdiction u/s.34 of the Arbitration Act. [Para 49]
     1.5 Division Bench accepted the correctness of the finding recorded
     by the Tribunal that there was an abandonment of the project on
     the part of L&T – It rightly declined to find fault with the findings
     recorded by the Tribunal on this aspect based on evidence – Such
     conduct on the part of L&T caused loss to PCL, which ultimately
     resulted in the termination of the Development Agreement – The
     issues based on the rejection of the counter-claim of L&T were rightly
     addressed by the Division Bench on the ground that there were no
     submissions made on the rejection of the counter claim before the
     Single Judge in a petition u/s.34 of the Arbitration Act. [Para 50]
     1.6 Division Bench dealt with the Tribunal’s direction to L&T to pay
     Rs. 50 crores to PCL on crystallization of ITCREF’s claims – It
     held that the type and kind of losses incurred by ITCREF would
     not be reasonably foreseeable for PCL to be indemnified against –
     Therefore, the Division Bench rightly observed that while granting
     a sum of Rs. 50 crores to PCL, the Tribunal went overboard – Said
     finding of the Division Bench cannot be faulted with. [Para 51]
     1.7 As regards the damages of the sum of Rs. 35 crores to be
     paid by L&T to PCL on account of breach of the Development
     Agreement, the basis taken by the Tribunal was the figures given
     by L&T in its counter-claim – Division Bench held that instead of
     basing the findings on the figures set out by L&T in its counter-
     claim, the correct approach would have been to determine the
     prevailing market rate for sale of built-up area at the time of the
     breach and thereupon determine the proceeds that PCL would
     have received from the sale of its 25 per cent share under the
     Development Agreement – Therefore, the award of Rs.35 crores
     as damages was fundamentally contrary to s.73 of the Contract
     Act – Such an approach was completely contrary to substantive
     law in the form of s.73 – This finding cannot be disturbed – As the
     termination of the Development Agreement is upheld, L&T cannot
     deal with the property in any manner and PCL can always deal
     with the same. [Paras 52, 54]
     Practice and Procedure – Arbitration and Conciliation Act,
     1996 – ss.34, 37 – Limited jurisdiction of Courts in proceedings
2814                                                         [2025] 4 S.C.R.

                         Supreme Court Reports


    under – Unnecessary long oral submissions or bulky written
    submission in arbitration matters, matter of concern –
    Observation as regards the need for imposing time limit on
    oral submissions. [Para 58]

                             Case Law Cited
    Project Director, National Highways No. 45 E and 220, National
    Highways Authority of India v. M. Hakeem and Another [2021] 5
    SCR 368 : (2021) 9 SCC 1 – relied on.
    Dyna Technologies Private Limited v. Crompton Greaves Limited
    [2019] 15 SCR 295 : (2019) 20 SCC 1; Associate Builders v. Delhi
    Development Authority [2014] 13 SCR 895 : (2015) 3 SCC 49;
    S.V. Samudram v. State of Karnataka and Another [2024] 1 SCR
    281 : (2024) 3 SCC 623; McDermott International Inc. v. Burn
    Standard Co. Ltd. & Ors. [2006] Supp. 2 SCR 409 : (2006) 11
    SCC 181 – referred to.

                               List of Acts
    Arbitration and Conciliation Act, 1996; Code of Civil Procedure,
    1908; Contract Act, 1872; Income Tax Act, 1961.

                            List of Keywords
    Power of the court u/s.34, Arbitration and Conciliation Act, 1996
    of partly setting aside the award; Power of court to modify award
    u/s.34, Arbitration and Conciliation Act, 1996; Powers of the
    Appellate Court u/s.37, Arbitration and Conciliation Act, 1996;
    Arbitral Award cannot be modified; Supplementary Agreement;
    Tripartite Agreement; Development Agreement; Supplementary
    Agreement was a non-starter; Supplementary Agreement and
    Tripartite Agreement tainted by coercion; Coercion; Economic
    duress; Abandonment of the project; Termination of Development
    Agreement upheld; Rejection of counter claim; Fundamental breach
    of Development Agreement; Puri Construction Limited (‘PCL’);
    Larsen and Toubro Limited (‘L&T’); Limited jurisdiction under Section
    34, Arbitration and Conciliation Act, 1996; Limited jurisdiction of
    Courts under Sections 34 and 37, Arbitration and Conciliation Act,
    1996; Bulky written submissions; Long oral arguments; Lengthy
    judgments; Time limit on oral submissions; External Development
    Charges; Non-payment of External Development Charges;
    Unilaterally abandoning the project; Development of lands; Novated;
    Agreement of indemnity; Rejection of counter-claim.
[2025] 4 S.C.R.                                                          2815

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


                           Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No(s). 2575-2578
     of 2016
     From the Judgment and Order dated 30.04.2015 of the High Court
     of Delhi at New Delhi in FAO No. 194, 21, 22, and 23 of 2009
     With
     Civil Appeal No(s). 2580-2581 and 2579 of 2016

                        Appearances for Parties
     Advs. for the Appellant:
     Akhil Sibal, C. A. Sundaram, Krishnan Venugopal, Sr. Advs., Saheer
     Parekh, Sumit Goel, Ms. Sreeparna Basak, Ms. Abhishek Thakral,
     Jayant Bajaj, Ishaan Nagar, Ms. Deboshree Mukherjee, Ms. Aditi
     Phatak, M/s. Parekh & Co., M. R. Shamshad, Aditya Samaddar,
     Arijit Sarkar, Ms. Nabeela Jamil, Abhimanyu Bhandari, Ms. Rooh-
     e-hina Dua, Zafar Inayat, Ms. Shreya Arora, J. Rajesh, Krishnan
     Agarwal, Avinash Mathur.
     Advs. for the Respondents:
     C. A. Sundaram, Akhil Sibal, Sr. Advs., M. R. Shamshad, Aditya
     Samaddar, Arijit Sarkar, Ms. Nabeela Jamil, Ms. Rohini Musa,
     Zaffar Inayat, Mohd. Ajmal, Shashank Singh, Saheer Parekh,
     Sumit Goel, Ms. Sreeparna Basak, Ms. Abhishek Thakral, Jayant
     Bajaj, Ishaan Nagar, Ms. Deboshree Mukherjee, Ms. Aditi Phatak,
     M/s. Parekh & Co.

                Judgment / Order of the Supreme Court

                                Judgment

     Abhay S. Oka, J.

     FACTUAL ASPECTS
1.   These appeals arise out of the judgment and order dated 30th April,
     2015, passed by the Division Bench of Delhi High Court on the appeals
     preferred under Section 37 of the Arbitration and Conciliation Act,
     1996 (for short, ‘the Arbitration Act’). The appeals before the Division
     Bench were preferred against the judgment dated 26th November,
     2008 of the learned Single Judge in a petition under Section 34 of
2816                                                      [2025] 4 S.C.R.

                        Supreme Court Reports


     the Arbitration Act by which the award of the Arbitral Tribunal was
     set aside. The Division Bench, by the impugned judgment, has
     disagreed with some of the findings recorded by the learned Single
     Judge. To that extent, the appeals preferred by Puri Construction
     Private Limited and Mohinder Puri have been allowed. The appeal
     by Larsen and Toubro Limited was dismissed. However, the Division
     Bench observed that the parties are left to pursue the appropriate
     course of actions under law.
2.   In these appeals, we are concerned with a company, Puri Construction
     Limited and its sister concerns (collectively referred to as ‘PCL’).
     We are also concerned with another company, Larsen and Toubro
     Limited (hereafter referred to as ‘L&T’). PCL was in possession
     of lands in the Gurgaon District, Haryana, as the owner thereof.
     PCL had obtained licenses from the Director Town and Country
     Planning, Haryana (for short, ‘the DTCP’) to develop the lands for
     residential group housing schemes. Earlier, PCL had entered into
     a joint venture with ITC Classic Real Estate Finance Limited (for
     short, ‘ITCREF’) under the name Florentine Estates of India Limited
     for the development of the lands. Ultimately, ITCREF exited from
     the business. An Exit Agreement dated 30th July, 1997 was made,
     which, inter alia, stipulated that PCL would transfer to ITCREF the
     built-up space of 1,95,000 sq. ft. in the project. Thereafter, L&T was
     introduced to complete the project.
3.   L&T and PCL entered into an agreement for land development (for
     short ‘the Development Agreement’) on 19th January, 1998, but the
     date mentioned therein was 10th March, 1998. Subsequently, since
     L&T was of the opinion that there was a recessionary trend in the real
     estate market due to which the project was required to be down-sized,
     a supplementary agreement was entered into between L&T and PCL
     on 30th December, 1999 (for short ‘the Supplementary Agreement’).
     Based on the Supplementary Agreement, a Tripartite Agreement
     dated 10th January, 2000 (for short, ‘the Tripartite Agreement’) was
     entered into between PCL, L&T and Lord Krishna Bank (for short
     ‘the Bank’).
4.   Broadly, in the Development Agreement, it was provided as under:
     (a)   L&T will develop the entire property mentioned in Schedule
           ‘A’ of the Agreement, including the part allocated to PCL, at
           its own cost;
[2025] 4 S.C.R.                                                       2817

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


     (b)   In phase-I of development, L&T will develop a portion of
           Schedule ‘A’ property as described in Schedule ‘B’. An area
           of 18.025 acres will be developed by L&T within 60 months in
           phase-I. In phase-II of the development, L&T was to develop
           the remaining portion as mutually acceptable to the parties in
           view of the prevailing market conditions;
     (c)   The ratio of division in the developed property between PCL
           and L&T was agreed to be 25% and 75% respectively;
     (d)   ITCREF was to get an area of 2,20,416 sq. ft. from the property
           allocated to PCL;
     (e)   PCL agreed to pay all External Development Charges (for
           short, ‘EDC’) up to the date of the development agreement.
           The liability to pay EDC was to be of L&T after receiving No
           Objection Certificate (for short ‘NOC’);
     (f)   L&T was to complete the construction of Phase-I in 60 months,
           which was subject to extension in view of prevailing market
           conditions; and
     (g)   L&T will not be deemed to be in default if performance of its
           obligations under the development agreement is delayed, inter
           alia, due to the prevailing market conditions.
5.   The Supplementary Agreement incorporated the following clauses:
     (a)   The terms of the Development Agreement will continue to bind
           the parties unless otherwise agreed in the in the Supplementary
           Agreement, which shall come into effect after happening of the
           following events:
           i.     L&T taking over or replacing bank guarantees furnished
                  by PCL to DTCP;
           ii.    The bank paying EDC amounting to Rs. 6 crores to DTCP;
           iii.   Reimbursement of expenses incurred by PCL by L&T; and
           iv.    Compliance with the terms and conditions of the Tripartite
                  Agreement made by L&T by paying Rs.5.14 crores to the
                  Lord Krishna Bank (“the Bank”).
     (b)   L&T will furnish bank guarantees to DTCP after approval of the
           term loan by the bank to PCL;
2818                                                      [2025] 4 S.C.R.

                        Supreme Court Reports


     (c)   L&T will pay the EDC of Rs. 6 crores paid by PCL through the
           bank and the remaining EDC Charges within 18 months;
     (d)   L&T agreed to commence construction work for 3.84 lac sq.ft.
           of the development, subject to achieving a confirmed booking/
           selling target of 75% in phase-I area; and
     (e)   The Agreement would not be construed as a waiver of any
           right that has accrued for the extension or termination under
           the Development Agreement.
6.   In the Tripartite Agreement, it was provided as under:
     (a)   The Bank will pay a sum of Rs. 6 crores towards EDC to DTCP
           on behalf of PCL, which will constitute a term loan to PCL. The
           loan will be secured by 15 acres of land already mortgaged by
           PCL to the Bank;
     (b)   The Bank will issue a bank guarantee of Rs. 4.66 crores to
           DTCP on behalf of L&T; and
     (c)   L&T will pay the Bank a sum of Rs. 5.19 crores on behalf of
           PCL to discharge the loan availed for payment of EDC on or
           before 19th January, 2000.
7.   We may note here that there was an arbitration to which ITCREF and
     PCL were parties. A consent award was passed on 13th May, 2000,
     in favour of ITCREF requiring PCL to allot 1,06,200 sq. ft. to ITCREF.
8.   PCL by letter dated 18th December, 2000, terminated the Development
     Agreement with L&T inter alia, on the grounds of:
     (a)   Failure to allocate area to ITCREF;
     (b)   Non-sanctioning of funds towards the development; and
     (c)   Non-payment of EDC; and
     (d)   Other breaches in relation of non-commencement of work.
9.   Delhi High Court referred the dispute between PCL and L&T to a
     Sole Arbitrator. Broadly, the following were the prayers made by PCL
     before the Arbitral Tribunal:
     (a)   Direct L&T to satisfy the loan availed from the Bank and to
           obtain the release of the title-deeds in respect of 15 acres of
           land placed by PCL with the Bank as security;
[2025] 4 S.C.R.                                                       2819

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


     (b)   Direct L&T to return the title-deeds of the rest of the lands to
           PCL;
     (c)   Direct L&T to return the sanctioned development plans and
           other documents, including licences, permits, permissions etc;
     (d)   Issue a permanent injunction against L&T restraining it from
           interfering with any of PCL’s rights to develop the property; and
     (e)   For grant of compensation and damages to the tune of Rs. 300
           crores and Rs. 100 crores respectively.
10. L&T filed a counter-claim before the Arbitral Tribunal, making the
    following prayers:
     (a)   Declare that PCL has no authority to rescind the contract;
     (b)   Grant compensation and damages to L&T to the tune of
           Rs. 280 crores due to the wrongful rescission of the agreement
           by PCL. Rs. 280 crores were claimed as the reimbursement
           amount of profit which L&T would have received by developing
           75% of the area; and
     (c)   Grant reimbursement to L&T of Rs. 8,31,53,968/- as the
           amount spent by it towards fulfilling the obligations under the
           Development Agreement.
11. The Arbitral Award was made on 28th December, 2002. The Arbitral
    Tribunal held that:
     (a)   L&T jeopardised PCL’s obligations towards ITCREF;
     (b)   L&T resiled from and went back upon its original contractual
           obligations and tried to effect sales without sanction under the
           revised development plan and without making any provision
           for the responsibility towards ITCREF;
     (c)   L&T had consciously decided to abandon the Development
           Agreement and omitted to pay EDC and also defaulted in the
           fulfilment of its obligation to the statutory authorities, ITCREF,
           as well as the Bank;
     (d)   The object of the Supplementary Agreement was unlawful as it
           sought to defeat the beneficial interest of ITCREF, which was
           a signing party to the Development Agreement; and
     (e)   The Supplementary Agreement was tainted by economic
           coercion, and the signatures of PCL were obtained by fraud.
2820                                                      [2025] 4 S.C.R.

                       Supreme Court Reports


12. The operative award is as follows:
         “ I. An Award in favour of the Claimants directing the
         Respondent to pay Rs. 35 Crores to the Claimants on
         account of damages suffered by the Claimants within four
         weeks from the date of the award;
         II. An Award in favour of the Claimants, directing the
         Respondent to settle the claim of Lord Krishna Bank
         within 4 weeks of the Award by repayment of loan of
         Rs. 6 Crores with such interest that may be due and payable
         to Lord Krishna Bank and further directing the Respondent
         to secure the release of title deeds from the said bank
         and to reimburse the claimant’s interest charges paid by
         Puri Construction Ltd. to Lord Krishna Bank in interregnum;
         within a period of four weeks from the date of this award.
         In default thereof, the Respondent will pay to the Claimants
         a sum of Rs. 75 Crores for loss of saleable area in respect
         of 15 acres of land placed in mortgage with the said bank
         within a period of four weeks from the date of this Award.;
         III. An Award in favour of the claimants directing the
         Respondent to return licences permits and permissions
         obtained by the Claimants from the statutory authorities
         in respect of the lands covered by the Development
         Agreement dated 10.3.1998 within 4 weeks of this Award to
         the Managing Director of Puri Construction Ltd. and obtain
         a certificate of discharge to that effect granted by the said
         Puri Construction Ltd. or in lieu thereof the Respondent
         will pay to the Claimants a sum of Rs. 5 Crores by way
         of damages within a period of four weeks from the date
         of this Award;
         IV. An Award in favour of the Claimants directing that the
         Respondent or anybody claiming under the Respondent is
         permanently injuncted by restraining them from interfering
         in any way or manner with the rights of the claimants to
         develop the property covered under the said Agreement
         dated 10.3.1998;
         V. An Award in favour of the Claimants, directing the
         Respondent to indemnify the Claimants in terms of
[2025] 4 S.C.R.                                                        2821

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


           Clauses 4(b) and 25 of the Development Agreement
           dated 10.3.1998 for any action or decree or settlement to
           be enforced by ITCREF against the Claimants or in lieu
           thereof shall pay to the Claimants a sum of Rs. 50 Crores
           on such date as such action or decree or settlement to
           be enforced by ITCREF against the Claimants becomes
           crystallized;
           VI. An Award in favour of the Claimants, directing the
           Respondent to pay cost of the Arbitration proceedings
           quantified at Rs. 30 lakhs within a period of four weeks
           from the date of the Award;
           VII. An Award in favour of the Claimants, directing the
           Respondent to pay interest to the Claimants @ 12% p.a.
           on the sums awarded hereinabove commencing on four
           weeks from the date of this Award till actual payment made
           by the Respondent.”
13. The learned Single Judge in a petition under Section 34 of the
    Arbitration Act had set aside the Arbitral Award. The Division Bench by
    the impugned judgment upheld the dismissal of L&T’s counter-claim.
    The Division Bench upheld the findings of the Arbitral Tribunal that
    the Supplementary Agreement was a non-starter as it was vitiated
    by economic duress. The Division Bench also upheld the Arbitral
    Tribunal’s finding that the Development Agreement was not novated
    by the Supplementary Agreement. Division Bench also upheld the
    Tribunal’s finding that conditions to be fulfilled by L&T, subject to
    which the Supplementary Agreement was to come into force, were not
    fulfilled. However, the Tribunal’s quantification of damages for breach
    of contract, amounting to a sum of Rs. 35 crores, and compensation
    in lieu of securing title deeds with respect to 15 acres of land,
    amounting to Rs. 75 crores, as well as compensation for default in
    returning licences and permits, amounting to Rs. 5 crores, was set
    aside. The permanent injunction granted in favour of PCL, restraining
    L&T from interfering with PCL’s development of the Schedule ‘A’
    property under the Development Agreement, was upheld. Even the
    relief granted of indemnification in favour of PCL for ITCREF’s claim
    was set aside without prejudice to the indemnification for ITCREF’s
    claim relating to the transfer of 2,20,416 sq. ft of land to the extent
    envisaged under the Development Agreement. The Division Bench
2822                                                     [2025] 4 S.C.R.

                        Supreme Court Reports


     upheld the Arbitral Tribunal’s order to the extent that it awarded
     the cost of arbitration to PCL. The title deeds deposited with the
     Registrar of the High Court were ordered to be released to PCL. In
     the light of the above directions and conclusions, the parties were
     allowed to pursue their appropriate course of action. The Division
     Bench allowed three appeals preferred by PCL in part and dismissed
     the appeal preferred by L&T. Both PCL and L&T, aggrieved by the
     Division Bench’s decision, preferred the present Civil Appeals.

     SUBMISSIONS
14. Very detailed submissions have been made on behalf of both parties.
    We are reproducing the gist of the submissions made by the counsel
    appearing for the parties.
15. Learned senior counsel appearing on behalf of L&T has made detailed
    submissions after inviting our attention to the findings recorded by
    the Arbitral Tribunal and by the courts under Sections 34 and 37 of
    the Arbitration Act. The learned senior counsel submitted that though
    Division Bench of the High Court has referred to the decision of this
    court in the case of Project Director, National Highways No. 45 E
    and 220, National Highways Authority of India v. M. Hakeem and
    Another1, which holds that the court dealing with a petition under
    Section 34 cannot modify the award, the Division Bench purported
    to modify the award. He submitted that it is not permissible for the
    court to uphold a part of the award and remand the remaining part
    back to the Tribunal. He submitted that the decision of the Division
    Bench is akin to setting aside the decree for upholding judgment.
    He submitted that the reasoning in the award and its operative part
    are intrinsically linked and the same cannot be severed. Moreover,
    this is not a case where there are distinct and severable claims. He
    submitted that the effect of the impugned judgment of the Division
    Bench is that PCL would get a chance to improve upon the pleadings
    by initiating fresh arbitration before the Tribunal. But, L&T’s doors
    would be closed for a fresh adjudication in view of the findings
    rendered in the award.
16. According to the learned senior counsel, the Division Bench has set
    aside the award directing payment of Rs. 35 crores as damages


1   (2021) 9 SCC 1
[2025] 4 S.C.R.                                                       2823

    Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


       to PCL. He pointed out that the award contains a direction to L&T
       to settle the claim of the Bank by repayment of the loan of Rs. 6
       crores and to secure release of the title deeds from the Bank; in
       default, L&T was directed to pay PCL a sum of Rs. 75 crores. The
       first part of the relief for payment of Rs. 6 crores has been upheld
       by the Division Bench, but the portion of the award in respect of
       Rs. 75 crores has been set aside. The award contains a direction
       against L&T to return licences, permits and permissions obtained by
       PCL from statutory authorities in respect of the lands. On failure to
       return the documents, L&T was directed to pay Rs. 5 crores to PCL.
       However, the Division Bench has upheld the award directing return of
       the documents, but has rejected the award to the extent of payment
       of Rs. 5 crores. Moreover, an award-granting injunction against L&T
       from interfering in any manner with the rights of PCL to develop the
       property has been upheld. The award directed L&T to indemnify PCL
       for any action, decree, or settlement to be enforced by ITCREF or,
       in lieu thereof, to pay to PCL Rs. 50 crores. The Division Bench has
       set aside this part of the award in its entirety. There was an order
       of costs of arbitration to the tune of Rs. 30 lakhs in favour of PCL,
       which has been confirmed. He submitted that, in fact, no licences,
       permits, or permissions obtained from statutory authorities were in
       possession of L&T. Moreover, the award in favour of the Bank is
       perverse as L&T has sought specific performance of the contract;
       there was no need to grant an injunction.
17. Now, coming to the interplay between the Development Agreement,
    Supplementary Agreement and the Tripartite Agreement, he submitted
    that the rights and obligations of the parties under the said agreements
    have been decided by the Arbitral Tribunal without recording reasons.
    He submitted that even PCL admitted that the conditions contained in
    Sub-clauses (a) to (d) of Clause I of the Supplementary Agreement
    were conditions precedent. However, the Tribunal misread the plain
    terms of the Supplementary Agreement contrary to the pleadings and
    without assigning any reason, has held that conditions precedent in
    Clauses (I), (II) and (III) of the Supplementary Agreement have not
    been fulfilled and therefore, the Supplementary Agreement was a
    non-starter. He relied upon the decision of this Court in the case of
    Dyna Technologies Private Limited v. Crompton Greaves Limited2.


2    (2019) 20 SCC 1
2824                                                        [2025] 4 S.C.R.

                         Supreme Court Reports


18. The learned senior counsel further submitted that in Section 34
    proceedings, reasons cannot be supplanted to the reasons recorded
    in the award. He invited our attention to sub-clauses (a) to (d) of
    Clause I of the Supplementary Agreement. His submission is that
    the terms of the Supplementary Agreement were totally disregarded
    by the Tribunal and relied on the original terms of the Development
    Agreement. He submitted that the award is vitiated due to lack of
    reasons. He submitted that the award made was contrary to the
    pleadings. The learned senior counsel invited our attention to the
    findings of the learned Single Judge in a petition under Section 34.
    He submitted that the Division Bench supplanted its own reasons
    to uphold the award. Further, the Division Bench tried to rewrite the
    contract by including other clauses as conditions precedent. His
    submission is that the Tribunal mixed up various unrelated issues with
    issue no. 2 which pertains to economic coercion. He submitted that
    the entire focus was on the alleged breach committed by L&T of the
    Development Agreement and abandonment of the site. Unreasoned
    finding has been given that the Supplementary Agreement and the
    Tripartite Agreement were entered under compulsion. The Tribunal
    failed to note that in the Statement of Claim as well as in the rejoinder
    filed by PCL, there was assertion regarding the binding nature of
    the Supplementary Agreement. One Mr. Mohinder Puri on behalf of
    PCL filed an affidavit which was not only beyond the pleadings, but
    also contrary to the same as he, for the first time, alleges exercise
    of coercion to enter into Supplementary Agreement. Learned counsel
    relied upon several documents to show that there was no coercion
    and submitted that the Tribunal ignored the documents. He would,
    therefore, submit that the award was vitiated in view of Section 28(1)
    (a) of the Arbitration Act. He relied upon a decision of this Court in
    the case of Associate Builders v. Delhi Development Authority3.
    Learned counsel submitted that the view taken by the Tribunal is
    not even a plausible view.
19. Learned senior counsel submitted that a finding was recorded by
    the learned Single Judge in the Section 34 petition that the Arbitral
    Tribunal could not have ignored all the correspondence and evidence
    showing why the Supplementary Agreement was signed. The learned
    Single Judge held that the award was self-contradictory and the


3   (2015) 3 SCC 49
[2025] 4 S.C.R.                                                        2825

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


     findings were mutually destructive inasmuch as while holding that
     the Supplementary Agreement was entered into by compulsion, the
     Tribunal, thereafter, purported to enforce the Tripartite Agreement.
     Learned senior counsel pointed out that the Division Bench rejected
     the objection of L&T that the plea of coercion was not taken by
     holding that the Statement of Claim is not specific on the point of
     coercion, but the plea taken in paragraph 136(5)(a) of the Statement
     of Claim can be deemed sufficient. In fact, what is quoted was part
     of PCL’s letter dated 18th December, 2000, in response to L&T’s
     letter dated 10th July, 2000. It was urged that the above allegation
     has nothing to do with economic coercion to compel PCL to enter
     into Supplementary Agreement. It is submitted that Division Bench
     has supplied reasons to justify the award which reasons were not
     there in the award itself. In fact, the Division Bench went to the extent
     of converting the plea of coercion into undue influence even when
     there was no pleading to that effect.
20. The Arbitral Tribunal has rendered a contradictory finding that the
    Supplementary Agreement was not operative, but, L&T cannot
    be relieved of its obligations under the Tripartite Agreement and
    thus, is bound to pay the Bank. Learned counsel reiterated that
    the Tripartite Agreement flows from the Supplementary Agreement.
    He pointed out that the Arbitral Tribunal held that L&T was bound
    by the Tripartite Agreement and at the same time observed that
    the Supplementary Agreement and the Tripartite Agreement were
    signed by PCL under compulsion and in dire need of funding of EDC
    payment. He submitted that the learned Single Judge has rightly held
    that when the Supplementary Agreement was a non-starter, as per
    the Tribunal, no relief could have been granted under the Tripartite
    Agreement. Unfortunately, this argument has not been dealt with by
    the Division Bench.
21. He invited our attention to Clause 26 of the Development Agreement
    which provided that L&T was entitled to extension of time for
    completing the construction in case of adverse market conditions. As
    per Clause 34, L&T could not be treated in default of performance
    of its obligation if it is delayed or prevented due to adverse market
    conditions. He submitted that there were enough documents on
    record to show that land prices were falling and prevailing market
    conditions did not encourage development of land. He submitted
    that though there was a specific pleading to that effect, the Arbitral
2826                                                       [2025] 4 S.C.R.

                         Supreme Court Reports


     Tribunal did not record any finding in the award with regard to the
     market conditions and in fact, Clauses 26 and 34 of the Development
     Agreement have been completely ignored. However, the learned
     Single Judge noticed that there was material on record with respect
     to the fall in real estate market and held that Arbitrator could not
     have ignored all those correspondences and evidence showing why
     the Supplementary Agreement was signed. The Division Bench
     recorded the submission that the Tribunal has ignored Clauses 26
     and 34 of the Development Agreement, but, has not dealt with the
     submission and tried to supply its own reasons which were not found
     in the award. Thus, the Division Bench acted beyond the scope of
     Section 37 of the Arbitration Act.
22. The Arbitral Tribunal committed an error by directing L&T to make
    payment to the Bank on the ground that L&T cannot be relieved of its
    obligation to the Bank under the Tripartite Agreement. It is submitted
    that the Bank was not a party to the proceedings and therefore, the
    claim by the Bank was not before the Arbitral Tribunal. In fact, in the
    affidavit in lieu of evidence filed by PCL, it was contended that the
    Bank is a third party and any action by the Bank can be tried only
    by the Debt Recovery Tribunal. Therefore, the submission is that the
    award in favour of the Bank is vitiated under Section 28(1)(a)(iv).
    He submitted that the said argument of L&T was accepted by the
    learned Single Judge on the ground that the Bank was not a party
    before the Tribunal and the Tripartite Agreement did not have an
    arbitration clause. On this aspect, he pointed out the finding of the
    Division Bench that the principal amount of Rs. 6 crores with interest
    was an amount payable by L&T to the bank under the Development
    Agreement. He submitted that, in fact, the said obligation can be
    read only in the Tripartite Agreement.
23. Learned senior counsel submitted that L&T has suffered a loss of
    Rs. 5.44 crores towards EDC. Though, the Tribunal had noted that
    the EDC payment would normally be reimbursed, but it failed to offset
    the same. Learned counsel pointed out that the sum of Rs. 8.10
    crores was deposited under an interim order dated 24th January, 2003
    passed by the learned Single Judge in Section 34 petition subject to
    the outcome of the proceedings. An application for restitution was filed
    by L&T in Section 34 proceedings. By order dated 8th January, 2011,
    it was directed to be listed along with the appeal before the Division
    Bench. However, the Division Bench has not dealt with the same. A
[2025] 4 S.C.R.                                                         2827

    Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


       prayer was made that L&T may be permitted to file an appropriate
       application for restitution before the High Court.
24. The submission of the learned senior counsel is that the order of the
    learned Single Judge in the Section 34 petition deserves to be upheld.
25. The learned senior counsel appearing for PCL pointed out that
    basically two issues arise for consideration. The first is whether there
    was a breach committed by L&T as held by the Arbitral Tribunal, and
    the second question is whether, if the finding of breach committed by
    L&T is upheld, the finding of the Arbitral Tribunal regarding damages
    can be revived.
26. The learned senior counsel submitted that the scope of interference
    in a petition under Section 34 of the Arbitration Act is now well
    settled. He relied upon a decision of this Court in the case of
    S.V. Samudram v. State of Karnataka and Another4. If the Arbitral
    Tribunal’s view is a plausible view, it ought not be interfered with. To
    arrive at a decision as to whether a plausible view has been taken,
    the court would consider whether the Arbitrator has considered the
    material forming part of the record and arrived at a plausible view in
    an overall sense and not expect the Arbitrator to deal with the matter
    and render a judgment with the detailed reasoning as is normally
    found in decisions of the civil courts.
27. Learned senior counsel submitted that to examine the award in
    supervisory jurisdiction under Section 34 of the Arbitration Act, the
    court must be cautious and should defer to the view taken by the
    Arbitral Tribunal even if the reasoning provided in the award is
    implied. If the reasons recorded by the Arbitral Tribunal are intelligible,
    the award cannot be set aside just because there were gaps in
    the reasoning of conclusions reached by the Arbitral Tribunal. The
    submission is that the award of the Arbitral Tribunal in the present
    case is intelligible and contains adequate reasons. He pointed out
    several findings recorded by the Arbitral Tribunal with reasons.
28. He submitted that L&T’s submission that Clause 26 read with Clause
    34 of the Development Agreement permitted it to seek extension of
    time is wholly misplaced considering the fact that L&T abandoned
    the project because a decision was taken by L&T to do so. Only in


4    (2024) 3 SCC 623
2828                                                       [2025] 4 S.C.R.

                        Supreme Court Reports


     case L&T had paid EDC and there was no risk of losing the licences,
     L&T could have invoked Clauses 26 and 34 of the Development
     Agreement for delayed completion of construction. Admittedly, no
     request was made by L&T for the grant of extension of time for
     completing the construction with the undertaking of making payment of
     EDC in terms of Clauses 19 and 25 of the Development Agreement,
     which were never modified. Learned senior counsel submitted that
     L&T was holding title deeds in relation to 25 acres of land and did
     not return the title deeds. The title deeds in respect of the remaining
     15 acres of land were with the Bank for securing the loan availed
     for payment of EDC. The payment of EDC was the liability of L&T
     as per the Development Agreement. He also pointed out that L&T
     did not lead any of the evidence. The stand of L&T in considerations
     of the overall findings of the learned Tribunal on breach of contract,
     abandonment etc. is completely out of place and without any basis.
     In fact, no issues were framed on the basis of Clauses 26 and 34
     of the Development Agreement.
29. The conditions precedent in the Supplementary Agreement may be
    read with their true intent and purport. Condition precedent no.1
    also contains the binding nature of the Development Agreement,
    except as agreed otherwise. Under the Supplementary Agreement,
    payment of EDC, as per Clause 19 read with Clause 27 of the
    Development Agreement, was continued. The developer was liable
    to pay EDC over a period of 18 months in terms of the licence.
    Condition precedent no. 1(a) expressly requisited the ‘replacing or
    taking over’ of the bank guarantee furnished by PCL. He pointed out
    the letter dated 15th March, 2000, addressed by PCL to the Bank,
    where the request was made to continue with the bank guarantee
    of PCL. However, at the same time, the request was made to
    the bank to forthwith release the margin money of PCL. Learned
    counsel submitted that L&T has made a false statement on oath
    that the bank guarantee of PCL, with margin money and interest,
    was released. Altogether, a new case was made out by L&T before
    this court, as it was not pleaded before the Tribunal that the margin
    money had been refunded and bank guarantees had been released.
    In fact, PCL by letter dated 12th April, 2000 reminded L&T that fresh
    bank guarantees were to be served as PCL’s guarantee was not
    released. According to the specific pleading of PCL in the Statement
    of Claims, a condition precedent for the coming into effect of the said
[2025] 4 S.C.R.                                                      2829

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


     agreement was replacing and taking over the bank guarantee. In the
     Statement of defence-cum-counterclaim of L&T, it was claimed that
     L&T had executed a counter bank guarantee. It was submitted that
     attributing insufficient reasons in relation to non-satisfaction of the
     condition precedent of the Supplementary Agreement is incorrect.
     On 07th October, 1999, L&T had taken a clear stand that the report
     submitted by the consultant was not favourable to pursue the project
     and hence, they shall not pay EDC. Reliance was placed by learned
     counsel on the Statement of Claims of L&T. He invited our attention
     to the fact that on 26th October, 1999, PCL was again constrained
     to put L&T on notice that there were serious defaults of the terms of
     licences and the Development Agreement. It was submitted that L&T
     was in possession of title deeds of area of 25 acres from 15th and
     16th October, 1998. A submission was made that there were sufficient
     facts pleaded in the pleadings to show coercion. He submitted
     that non-payment of EDC as per Clause 19(b) of the Development
     Agreement led to issuance of notice for cancellation of licences of
     PCL. In the letter dated 07th October, 1999, L&T had taken a clear
     stand that they will not pay EDC. Initially, on 8th December, 1998,
     L&T’s stand was that it was their responsibility to pay EDC from
     01st July, 1998. Thereafter, a stand was taken on 02nd April, 1999
     that they will pay EDC only after launch of the project. L&T did not
     pay Rs. 5 crores refundable advance to PCL. L&T instructed PCL
     not to collect any cheque and on 08th April, 1999, L&T internally
     instructed to demobilize resources from the site. The title deeds were
     in possession of L&T and the same was pleaded in the Statement
     of Claims. Learned counsel submitted that these all facts constituted
     coercion. He also pointed out that with the consent of the parties,
     the issue was framed on the plea of coercion being an issue no. 2,
     and in fact, L&T accepted that there could be no grievance with the
     procedure followed by the Arbitral Tribunal in framing issues. In fact,
     in the final submission before the Arbitral Tribunal, L&T admitted
     that the plea of economic duress was pleaded by PCL by pointing
     out that the Supplementary Agreement was signed out of economic
     duress and coercion.
30. He submitted that on the question whether the condition precedent
    for the Supplementary Agreement was satisfied, L&T did not lead
    evidence and evidence of PCL remained uncontroverted.
2830                                                           [2025] 4 S.C.R.

                          Supreme Court Reports


31. As regards the contention that the relief granted in the award was
    beyond the jurisdiction, learned counsel submitted that the arbitration
    clause in the Development Agreement even covered disputes in
    connection with the agreement. In fact, the Supplementary Agreement
    refers to the fact that parties to the Development Agreement have
    agreed to enter into a tripartite agreement with the Bank. In turn,
    the tripartite agreement records that L&T and PCL had entered into
    Development Agreement on 10th March 1998. The notice invoking
    the arbitration clause refers to the three agreements, and even in
    the petition filed under Section 11 of the Arbitration Act, the disputes
    were set out in relation to the three agreements. By consent of the
    parties, vide order dated 14th February, 2001, the disputes in relation
    to all three agreements, including the determination of the liability of
    ITCREF and the Bank, were referred to the Arbitral Tribunal. Before
    the Arbitral Tribunal, L&T took the stand that it was its liability to ensure
    payment to the Bank. Also, L&T took a stand through its counsel
    that the obligation was cast upon L&T with respect to the liability of
    ITCREF. Moreover, L&T did not take recourse to Section 16 of the
    Arbitration Act for challenging the jurisdiction of the Arbitral Tribunal.
32. Learned senior counsel pointed out the issues framed by the Tribunal
    concerning damages and compensation. He submitted that perusal
    of L&T’s Statement of Defence shows that the parties were ad
    idem on the question of valuation at which sales could be made
    as L&T had itself based the claim for damages on such valuation.
    As regards valuation, the Tribunal considered the evidence of Shri
    Mohinder Puri adduced on behalf of PCL. Therefore, the Tribunal
    relied upon agreed valuation based on L&T’s demands in its counter-
    claim as a reasonable estimate of the loss suffered by PCL. L&T
    had pleaded that they were entitled to 75% of the total constructed
    area while PCL was entitled to 25%. In fact, the Arbitral Tribunal
    used L&T’s computation of loss of profit made by L&T at Rs. 280
    crores as the basis to arrive at PCL’s loss of profit as Rs. 93 crores.
    In fact, the estimate of loss caused to PCL was taken at Rs. 93
    crores, which is on the lower side. After considering the fact that
    ITCREF had initiated action to forfeit licenses, the Tribunal reduced
    the amount awarded as damages to Rs. 35 crores. Therefore, the
    findings recorded by the Tribunal on this behalf are reasonable.
    Learned counsel submitted that the Division Bench ought not to
    have set aside the Tribunal’s findings on damages awarded to
[2025] 4 S.C.R.                                                      2831

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


     PCL. This was not a case of no evidence before the Tribunal. The
     basis of damages was L&T’s own valuation of the built-up space.
     Evidence of Shri Mahendra Puri had gone unchallenged. As the
     damages granted to PCL were based on evidence on record, the
     said finding should not have been interfered with in a petition under
     Section 34 or in an appeal under Section 37 of the Arbitration Act.
     He submitted that in view of the decision of this Court in the case
     of Associate Builders v. Delhi Development Authority3, incorrect
     quantification of damages by the Arbitral Tribunal will not be covered
     by either “patent illegality” or “violation of public policy”. Even as
     regards the indemnity in favour of ITCREF, the concerned issue
     was issue no. 10 before the Tribunal on which detailed statements
     were made and findings were recorded by the Arbitral Tribunal
     based on the appreciation of the evidence on record. The finding
     of the Division Bench that L&T’s obligation to indemnify was only
     in terms of the built-up space is wholly incorrect. Learned senior
     counsel pointed out that on one hand, there was non-payment
     of EDC by L&T, on the other hand, there were repeated notices
     sent by DTCP for cancellation of licences. Moreover, ITCREF had
     filed a civil suit in the District Court seeking recovery of rupees
     73 crores plus interest against PCL and also against L&T. In addition
     to all this, L&T was holding title deeds of 25 acres of licensed land
     of PCL and 15 acres of PCL’s licensed land with the Bank for which
     the Bank had invoked securitization laws and also filed proceedings
     before the Debt Recovery Tribunal. During the Arbitral proceedings,
     L&T always resisted returning the title deeds in respect of 25 acres
     of land. Therefore, the argument that the land remained with PCL
     has no relevance at all.
33. Lastly, it was submitted that the dispute between the parties was of the
    year 2000. The award was made on 28th December, 2002, after a very
    detailed hearing before the Tribunal. Thereafter, the dispute remained
    sub-judice continuously before the courts. Therefore, considering
    the findings of the Tribunal, as upheld by the Division Bench, this
    court will consider exercising extraordinary powers to do complete
    justice. Therefore, appeals preferred by L&T may be dismissed, and
    PCL may be compensated for the huge legal expenditure incurred
    during the last 21 years. It was submitted that the appeal preferred
    by PCL be allowed while upholding the damages and compensation
    awarded by the Arbitral Tribunal in terms of the award.
2832                                                     [2025] 4 S.C.R.

                       Supreme Court Reports


    ISSUES FRAMED BY THE ARBITRAL TRIBUNAL
34. The Arbitral Tribunal framed 14 issues which read thus:
    Issue No. 1: Whether the Development Agreement dated 10.03.1998
    entered into between the Respondent and the Claimants is binding
    on the parties or the same stand novated by the Supplementary
    Agreement dated 30.12.1999?
    Issue No. 2: Whether the Supplementary Agreement dated 30.12.1999
    and the Tripartite Agreement dated 10.01.2000 were tainted by
    coercion and economic duress on the claimants? If not, whether
    the claimants and the Respondent performed respective obligations
    according to tenor and terms of the Supplementary Agreement dated
    30.12.1999 and the Tripartite Agreement dated 10.01.2000?
    Issue No. 3: Whether the Claimants committed breaches of
    the fundamental terms of the Development Agreement dated
    10.03.1998 to enable the Respondent to resile from the agreement
    of development?
    Issue No. 4: Whether the respondent’s Board of directors in
    pursuance of reports of Boston Consulting Group (for short ‘BCG’).
    Richard Ellis and Jones Lang La Salle decide to down-size/exit
    the business of real estate development and not to pay EDC or
    commence development work?
    Issue No. 5: Whether there had been non provisions of security of
    the development site and unprovoked unilateral abandonment of the
    site by L&T. If so whether such actions had resulted in encroachments
    causing monetary loss to the Claimants and in the event of such
    monetary loss caused to the Claimants what is the extent of such loss?
    Issue No. 6: Whether the Claimants entitled to terminate the
    development agreement for the reasons stated in the letter of
    termination dated 16.12.2000 or even otherwise?
    Issue No. 7: Was the Respondent under any obligation to commence
    construction in phase I for development of 3.84 Lac sq. ft. before
    the Claimants had confirmed booking/selling targets as per the
    Supplementary Agreement dated 30.12.1999?
    Issue No. 8: Whether termination of the contract by the Claimants
    amounts to wrongful repudiation and entitles Respondent to rescind
[2025] 4 S.C.R.                                                        2833

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


     the contract and claim damages under Section 73 and 75 of the
     Indian Contracts Act?
     Issue No. 9: Whether the Respondent is entitled to be relieved
     of its obligations under the Tripartite Agreement dated 10.01.2000
     and be put in the same position as if such agreement had not been
     entered into?
     Issue No. 10: Is the Respondent liable to compensate the Claimants
     under the agreement of indemnity and if so what effect?
     Issue No. 11: Is the Respondent liable to be compensated
     by Claimants by a sum of Rs.8,31,53,968/- including a sum of
     Rs.5.19 Crores paid by the LKB as claimed by the respondent?
     Issue No. 12: Is the Respondent entitled to be compensated by the
     Claimants a sum of Rs.280 Crores as net profit being difference in
     the cost of construction estimated at Rs.800/- per sq. ft. with the total
     cost being Rs. 320 Crores as claimed by the respondent?
     Issue No. 13: Are the Claimants entitled to compensation from the
     Respondent and damages of a total values of Rs. 300 crores and
     are the Claimants entitled to a further sum of Rs. 100 crores as
     punitive damages?
     Issue No. 14: Whether Mr. Mohinder Puri has the authority to
     institute the instant claim petition and to carry out acts necessary
     to prosecute the instant claim petition on behalf of Claimants other
     than Puri Construction Limited? If not whether the claim petition for
     other Claimants is maintainable?

     ARBITRAL TRIBUNAL’S AWARD
35. The Arbitral Tribunal recorded detailed findings. The findings recorded
    by the Arbitral Tribunal can be summarised as under:
     Issue No. 1: The conditions precedent in Clauses (I), (II), and
     (III) of the Supplementary Agreement were not fulfilled. Therefore,
     the Supplementary Agreement was a non-starter, hence, only the
     Development Agreement was binding on the parties which was not
     novated by the Supplementary Agreement.
     Issue No. 2: The Supplementary Agreement and the Tripartite
     Agreement were tainted by coercion. These agreements were
2834                                                        [2025] 4 S.C.R.

                        Supreme Court Reports


    executed as PCL was in dire need of money for making EDC
    payments. It was the obligation of L&T to provide funds for payment
    of EDC and the Tripartite Agreement was signed since L&T failed
    to provide the requisite funds.
    Issue No. 3: PCL substantially discharged its obligation under the
    Development Agreement. However, by unilaterally abandoning the
    project, L&T committed fundamental breach in its obligation under
    the Development Agreement.
    Issue No. 4: The site inspection conducted by the Arbitral Tribunal
    revealed that L&T had not commenced the development work. L&T
    did not lead any oral evidence and failed to produce the relevant
    documents that were called upon to be produced by the Tribunal.
    Thus, L&T took a conscious decision to abandon the development,
    not to pay EDC or fulfil its obligations towards statutory authorities,
    ITCREF and the Bank. Therefore, monetary loss was caused to PCL.
    Issue No. 5: L&T did not fulfil its obligations under the development
    agreement. L&T failed to fund the project. It also failed to provide
    sufficient security arrangements at the site, resulting in encroachment
    of some sites.
    Issue No. 6: PCL was entitled to terminate the Development
    Agreement in view of the breaches committed by L&T as recorded
    in issue No. 5.
    Issue No. 7: Before PCL had confirmed bookings/selling targets as
    per the Supplementary Agreement, L&T was not under an obligation
    to commence construction in phase 1. The reason was that the
    Supplementary Agreement was not operative and binding, and no
    responsibility contrary to the Development Agreement could be
    fastened on L&T.
    Issue No. 8: The termination of the contract by PCL does not amount to
    wrongful repudiation, and it does not entitle L&T to rescind the contract
    and claim damages under Sections 73 and 75 of the Contract Act.
    Issue No. 9: As the Tripartite Agreement was negated due to L&T’s
    default, and since it imposes liability on L&T, it cannot be relieved
    of its obligation under the Tripartite Agreement.
    Issue No. 10: L&T had complete knowledge of PCL’s obligation to
    ITCREF. Under Clause 25 of the Development Agreement, L&T was
[2025] 4 S.C.R.                                                           2835

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


     responsible for indemnifying PCL against any loss, liability, cost, or
     claim that may arise against PCL due to L&T’s failure to discharge
     its obligations. The obligations under Clause 25 shall subsist even
     after the termination of the Development Agreement.
     Issue No. 11: As L&T had abandoned the project, it cannot take
     advantage of its own wrong. Therefore, L&T is not entitled to
     compensation from PCL.
     Issue No. 12: The claim of Rs. 240 crores made by L&T was
     negatived on the ground that L&T itself had abandoned the project
     and therefore, it cannot take advantage of its own wrong.
     Issue No. 13: PCL was entitled to compensation from L&T amounting
     to Rs. 93 crores in relation to its 25 percent share. It was based
     on L&T’s calculation of profit for its 75 percent share. The Tribunal
     observed that PCL was entitled to damages of Rs. 35 crores in lieu
     of L&T’s failure to pay EDC in a timely manner. However, it was held
     that PCL was not entitled to any punitive damages.
     Issue No. 14: The authority of Mr. Mohinder Puri to institute a claim
     on behalf of PCL was acquiesced by L&T, as it did not object to the
     affidavit filed by Mr. Puri. Moreover, Mr. Puri supplied copies of the
     board resolutions of the respective companies granting him power
     of attorney.
36. We have already reproduced the operative part of the Award in
    paragraph 12 above.

     FINDINGS RECORDED BY LEARNED SINGLE JUDGE IN
     SECTION 34 PETITION
37. Now, coming to the findings recorded in a petition under Section 34,
    the findings can be summarised as under:
     Issue No. 1: The conditions precedent for the Supplementary
     Agreement were satisfied substantially. Clause (I) was the only
     condition required to be fulfilled, and Clauses (II) and (III) were not
     required to be fulfilled by L&T. It was held that the Arbitral Tribunal gave
     inconsistent findings by holding that the Supplementary Agreement
     was a non-starter and void. However, the Tripartite Agreement was
     not found to be void, though it was entered into as a result of the
     Supplementary Agreement.
2836                                                    [2025] 4 S.C.R.

                       Supreme Court Reports


    Issue No. 2: Both the Supplementary Agreement and the Tripartite
    Agreement were not tainted by coercion as parties to it recognized
    that the market prices had gone down and it was not advisable to
    launch the project. In fact, Clause 26 of the Development Agreement
    stipulated that construction was contingent upon prevailing market
    conditions, and parties were permitted to rescind the contract in the
    event of adverse market conditions.
    Issue No. 3: It seems that no submissions were canvassed in the
    petition under Section 34.
    Issue No. 4: The Tribunal’s conclusion could not be based solely
    on the reports of BCG; instead, the inference was to be drawn by
    the Tribunal based on the actions.
    Issue No. 5: The learned Single Judge did not record a finding on
    this issue.
    Issue No. 6: PCL was not entitled to terminate the Development
    Agreement. Although PCL made a commitment to ITCREF to provide
    an area of 153,500 sq. ft., it allocated only 88,320 sq. ft. itself.
    Issue Nos. 7 and 8: It appears that no submissions were made
    before the learned Single Judge on these issues.
    Issue No. 9: The Tribunal exceeded its jurisdiction by directing L&T
    to fulfil its obligations towards the Bank. It was held that the Bank
    was not a party to the proceedings and the Tripartite Agreement did
    not contain any arbitration clause.
    Issue Nos. 10, 11 and 12: There were no specific findings recorded
    by the learned Single Judge.
    Issue No. 13: PCL was not entitled to any compensation from L&T
    as it had already paid the price of the land to ITCREF. Moreover,
    PCL committed an area to ITCREF, which was more than its share.
    PCL’s losses would arise only when ITCREF files a suit for recovering
    damages for non-fulfilment of the commitment and failing to hand
    over the land in due time.

    FINDINGS RECORDED BY DIVISION BENCH IN SECTION 37
    APPEALS
38. Now, we must consider the findings recorded by the Division Bench
    in appeals under Section 37 of the Arbitration Act.
[2025] 4 S.C.R.                                                      2837

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


     Issue No. 1: The Division Bench relied upon the conditions included
     in Clause II of the Supplementary Agreement. The Division Bench
     observed that PCL had spent 17.28 crores towards EDC out of which
     payment of Rs. 6 crores was made by PCL by mortgaging 15 acres of
     its land. Under Clause II, L&T was required to make good a plurality
     of bank guarantees and assume responsibility for payment of EDC.
     However, there was complete failure on the part of L&T to do so.
     Issue No. 2: The Division Bench found that the finding of the Tribunal
     that the Supplementary Agreement and the Tripartite Agreement
     were tainted by coercion was correct. It was observed that the
     Arbitral Tribunal rightly found that economic duress has vitiated the
     Development Agreement.
     Issue No. 3: The Division Bench observed that L&T has not urged
     any ground with respect to rejection of its counter-claim before the
     learned Single Judge.
     Issue No. 4: The Division Bench agreed with the finding of the Tribunal
     that L&T decided to abandon the project on the basis of the BCG
     Report. The Division Bench held that the award was well supported
     by evidence. Inspection conducted by the Arbitral Tribunal showed
     that L&T had not even commenced the development work. Though,
     PCL handed over the title deeds to L&T on 16th October, 1998, no
     progress was made in construction by L&T. Moreover, L&T delayed
     the project and was planning it till 18th December, 1999. L&T was
     fully aware about PCL’s obligation to ITCREF which was expressly
     set out in the Development Agreement.
     Issue No. 6: There may not be separate findings recorded by the
     Division Bench, but the Division Bench, as stated earlier, agreed that
     the Tribunal accepted the breaches committed by L&T.
     Issue No. 7: There is no specific finding recorded by the Division
     Bench.
     Issue No. 8 and 9: The Division Bench held that L&T did not urge
     any ground with respect to the rejection of its counter-claim before
     the learned Single Judge.
     Issue No. 10: The Division Bench held that the Tribunal’s direction
     to L&T to pay Rs. 50 crores to PCL on crystallization of ITCREF’s
     claim deserves to be set aside. The loss suffered by ITCREF would
2838                                                        [2025] 4 S.C.R.

                         Supreme Court Reports


     not be reasonably foreseeable for PCL to be indemnified against. It
     was held that L&T’s failure to transfer the built-up area would have
     to be accounted for under the heading damages for the breach of
     the Development Agreement by L&T.
     Issue Nos. 11 and 12: The Division Bench held that L&T did not
     raise any ground with respect to the rejection of its counter-claim
     before the learned Single Judge.
     Issue No. 13: The Division Bench held that actual loss was not
     established by PCL. It was observed that after the rejection of L&T’s
     counterclaim, it would be an illegality to rely on L&T’s calculation of
     profit. However, the Tribunal’s finding regarding L&T’s failure to pay
     EDC timely was affirmed.
     Issue No. 14: It is evident that the Tribunal’s findings were not
     seriously challenged.
39. We now turn to the conclusions recorded in paragraph 119 of the
    impugned judgment. In substance, the Division Bench agreed with
    the findings recorded by the Arbitral Tribunal that the Supplementary
    Agreement was a non-starter, it was vitiated by economic duress,
    and that the Development Agreement was not novated by the
    Supplementary Agreement. The Division Bench also approved the
    finding of the Arbitral Tribunal that L&T committed a fundamental
    breach of the Development Agreement. The Division Bench also
    upheld the dismissal of L&T’s counterclaim. Furthermore, the Division
    Bench concluded that the permanent injunction granted in favour of
    PCL was also justified. However, the quantification of damages and
    compensation, as well as indemnification for ITCREF’s claim, was
    found to be contrary to the record. The net effect was that the operative
    part of the award fixing the monetary liability of L&T was set aside
    while leaving open the remedy of PCL for the quantification of the
    monetary claim. In view of the confirmation of findings on merits, the
    award regarding costs was confirmed. But, in view of the legal position
    that the award cannot be varied or modified, the Division Bench did
    not restore any part of the arbitral award and held in paragraph no.
    120 that the parties are left to pursue the appropriate course of action.

     CONSIDERATION
40. Firstly, we will deal with the issue of the power of the Court under
    Section 34 of partly setting aside the award. This issue was dealt with
[2025] 4 S.C.R.                                                            2839

    Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


       by this Court in the case of Project Director, National Highways
       No. 45 E and 220, National Highways Authority of India v. M.
       Hakeem and Another1. This Court, in the said decision, considered
       its earlier decision in the case of McDermott International Inc. v
       Burn Standard Co. Ltd. & Ors.5 Ultimately, in paragraph 42, this
       Court held thus:
             “42. It can therefore be said that this question has now
             been settled finally by at least 3 decisions [McDermott
             International Inc. v. Burn Standard Co. Ltd., (2006) 11 SCC
             181] , [Kinnari Mullick v. Ghanshyam Das Damani, (2018)
             11 SCC 328 : (2018) 5 SCC (Civ) 106] , [Dakshin Haryana
             Bijli Vitran Nigam Ltd. v. Navigant Technologies (P) Ltd.,
             (2021) 7 SCC 657] of this Court. Even otherwise, to state
             that the judicial trend appears to favour an interpretation
             that would read into Section 34 a power to modify, revise
             or vary the award would be to ignore the previous law
             contained in the 1940 Act; as also to ignore the fact that
             the 1996 Act was enacted based on the Uncitral Model Law
             on International Commercial Arbitration, 1985 which, as has
             been pointed out in Redfern and Hunter on International
             Arbitration, makes it clear that, given the limited judicial
             interference on extremely limited grounds not dealing with
             the merits of an award, the “limited remedy” under Section
             34 is coterminous with the “limited right”, namely, either
             to set aside an award or remand the matter under the
             circumstances mentioned in Section 34 of the Arbitration
             Act, 1996.”
41. We are conscious of the fact that a larger bench is seized with the
    issue of the power of the Court to modify the award under Section
    34. However, we are respectfully bound by the decision in the case
    of Project Director, National Highways No. 45 E and 220, National
    Highway Authority of India v. M. Hakeem and Another1. As we
    have noted, after recording its conclusions in paragraph 119, the
    Division bench, in the last paragraph of the impugned Judgment,
    has not modified the award.



5    (2006) 11 SCC 181
2840                                                        [2025] 4 S.C.R.

                         Supreme Court Reports


42. We have perused the three agreements subject matter of controversy.
    The Development Agreement is a contract between PCL and L&T.
    Clause 4 of the Development Agreement refers to the obligations
    of PCL under the agreement entered into by it on 30th July, 1997
    with ITCREF. It refers to the fact that PCL had agreed to hand over
    1,95,000 sq. ft. of built-up area in the Schedule ‘A’ property, after its
    development, comprising high-rise and low-rise buildings, inclusive
    of a car park, to ITCREF. It also refers to the fact that the extent of
    the built-up area to be allocated to ITCREF was 2,20,416 sq. ft.,
    which formed part of the allocation made under the Development
    Agreement to PCL. The Development Agreement also provides
    that PCL had agreed that 15 acres of land mortgaged to the Bank
    would be in the remaining portion of Schedule ‘A’ property and
    that PCL would get the mortgage discharged on this 15 acres of
    land comprised in Schedule ‘A’ property before commencement
    of development work in the remaining portion of Schedule ‘A’
    property. The Agreement also provides for the deposit of original
    documents in relation to Schedule ‘A’ property (except to the
    extent of 15 acres of land mortgaged with the Bank). Paragraph 19
    records L&T’s obligation to pay the EDC after receiving the NOC
    from the appropriate authority. The Agreement provides that L&T
    shall complete the construction of the building on the Schedule ‘B’
    property within 60 months or such mutually extended period from
    the date of obtaining sanction for the building plan, or tax clearance
    under Section 37-I of the Income Tax Act, and making the said
    property available for development, whichever is later. It has also
    stipulated that construction shall be carried out in phases. After
    completion of phase of 3,00,000 sq. ft. on Schedule ‘B’ property,
    L&T, in consultation with PCL, by mutual consent, shall have the
    option and liberty to renew and revise the specifications/amenities
    and built-up area of the balance development and extend the period
    of completion by a further period of 12 months, depending upon
    the prevalent market conditions.
43. Now, we refer to the Supplementary Agreement. In the recital of
    the Supplementary Agreement, it is mentioned that L&T has made
    only partial compliance with the requirement under the Development
    Agreement to pay EDC to DTCP. Moreover, L&T has failed to
    furnish a bank guarantee for the balance payment of EDC. In fact,
    it records that L&T had taken a stand that in view of the adverse
[2025] 4 S.C.R.                                                          2841

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


     market conditions, the project had become unviable and sought
     further time from PCL to allow the prevailing real estate market
     conditions to improve. Clauses I, II and III of the Supplementary
     Agreement read thus:
     I.     “That the terms of the Development Agreement will
            continue to bind the parties hereto, unless otherwise
            agreed to in these presents, which shall come into
            effect on happening of the following events :
            (a)   DEVELOPER replacing or taking over the Bank
                  Guarantees furnished by the OWNERS through their
                  Banker to DTCP, Haryana;
            (b)   Payment of EDC amounting to Rs. 6 Crore by Lord
                  Krishna Bank to DTCP Haryana, in terms of the
                  Tripartite Agreement between the parties hereto with
                  Lord Krishna Bank;
            (c)   Reimbursement of expenses incurred by the OWNER
                  as detailed in Annexure I, on production of proof of
                  payment thereof;
            (d)   Compliance of the terms and conditions of the
                  tripartite agreement between the parties hereto
                  with Lord Krishna Bank, inter-alia the DEVELOPER
                  paying Rs. 5.19 Crore to Lord Krishna Bank, on
                  behalf of OWNERS towards discharge of the loan
                  availed by the OWNERS for payment of EDC. The
                  said sum of Rs. 5.19 Crore shall be a secured
                  interest free loan by the DEVELOPER to the
                  OWNERS.
     II.    The Bank Guarantees would be furnished by the
            DEVELOPER to the DTCP after final approval of term loan
            by Lord Krishna Bank to the OWNER and escrow account
            arrangement finalisation, either through the Bankers of
            the OWNERS or any other Bank acceptable to DTCP.
            The said bank guarantees shall remain valid and in force
            upto the date of receipt of completion Certificate of the I
            phase of the project.
     III.   The parties hereto agree that the Clause 19 of the
            Development Agreement shall stand modified as under:
2842                                                      [2025] 4 S.C.R.

                         Supreme Court Reports


          (a)   The EDC Charges of Rs. 1013.14 Lacs paid so far
                by the OWNERS shall be reimbursable only after
                receipt of the same from the prospective purchasers
                of the apartments in the Project.
          (b)   The Developer agrees to pay the balance EDC as
                under:
                i.    Rs. 6 Crore through M/s. Lord Krishna Bank as
                      provided in Clause I(b) supra;
                ii.   Pay the remaining EDC charges over a period
                      of 18 months in terms of licenses.
          (c)   The EDC paid by the parties shall be reimbursable
                to each of the parties from out of the sale proceeds,
                as agreed in the Agreement for Development.”
                                                  (emphasis added)

44. We may note here that, as stated in Clause (I) of the Supplementary
    Agreement, the terms of the Supplementary Agreement were to come
    into effect upon the occurrence of the events mentioned therein,
    which included the condition that L&T would replace or take over the
    bank guarantees furnished by PCL through their banker to DTCP.
    Other condition was of compliance of the terms and conditions of
    the Tripartite Agreement which provided for L&T paying sum of Rs.
    5.19 crores to the Bank on behalf of PCL. The Arbitral Tribunal
    found that Clauses (I) and (II) were not fully complied with by L&T.
    The Tribunal also found that Clause (III) was not complied with by
    L&T due to non-payment of EDC charges as provided therein. On
    a plain reading of these three clauses, the learned Single Judge’s
    finding that Clauses (II) and (III) were not required to be fulfilled
    is based on a complete misreading of Clauses (II) and (III). The
    Division Bench rightly agreed with the Tribunal that conditions
    included in the said clauses were required to be complied with, but
    were not complied with. The Division Bench noted that even the
    Supplementary Agreement revealed that the DTCP had issued a
    show-cause notice for non-payment of EDC, threatening cancellation
    of licenses. Clause (I) of the Supplementary Agreement makes it
    very clear that the Supplementary Agreement shall come into effect
    only upon the occurrence of the four events specified therein. That
    is how the Supplementary Agreement remained a non-starter.
[2025] 4 S.C.R.                                                     2843

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


45. We now turn to the Tripartite Agreement, which in turn refers to
    the Supplementary Agreement. It is recorded that PCL and L&T
    had approached the Bank to avail a term loan of Rs. 6 crores for
    payment of EDC charges. Under the said agreement, the Bank
    agreed to pay Rs. 6 crores EDC to DTCP on behalf of PCL. It was
    agreed that the 15 acres of land already mortgaged by PCL with the
    Bank will continue to serve as a guarantee for the said term loan of
    Rs. 6 crores. The Tripartite Agreement provides that the Bank shall
    forthwith release, in favour of the PCL, the counter-guarantees
    outstanding for the bank guarantees given by the Bank for a sum
    of Rs. 466.175 lakhs in favour of DTCP, Haryana. It was provided in
    the Tripartite Agreement that L&T will open an Escrow account with
    the Bank in New Delhi, wherein all sale proceeds of the proposed
    flats will be deposited. Out of the funds in the escrow account, the
    Bank will first appropriate the interest part for the respective period
    and out of the balance portion, appropriate 50 per cent towards
    repayment of the term loan and release the remaining 50 per cent
    balance to L&T, subject to review on a later date. It was provided
    that PCL and L&T have undertaken to launch the sale of apartments
    in the Schedule ‘A’ property, covering an area of 3.84 lakhs sq.
    ft., by 15th February, 2000. L&T had also undertaken to complete
    the said development within 30 months of the commencement of
    construction. Even all sale proceeds were to be collected by L&T
    and deposited with the Bank in an escrow account. The Tripartite
    Agreement provided that L&T shall pay to the Bank a sum of Rs.
    5.19 crores on behalf of PCL towards discharge of the loan availed
    by PCL for payment of EDC on or before 19th January, 2000. Lastly,
    it was provided that upon full set-off and/or repayment of the term
    loan of Rs. 6 crores, including interest thereon, PCL shall be relieved
    of its obligation under this Agreement.
46. Looking to the clauses in the Supplementary Agreement, the finding
    recorded by the Tribunal that, as the conditions precedent in the
    relevant clauses were not complied with by L&T, the Supplementary
    Agreement was a non-starter is undoubtedly a possible finding
    which could not have been interfered with under Section 34 of the
    Arbitration Act. Moreover, it is a finding of fact.
47. Coming to the issue no. 2, it is apparent from the recitals in the
    Supplementary Agreement as well as Tripartite Agreement that
    as L&T did not discharge its obligation under the Development
2844                                                      [2025] 4 S.C.R.

                        Supreme Court Reports


     Agreement to pay EDC, the Bank was required to be brought
     into the picture so that it could advance a sum of Rs. 6 crores by
     way of loan for making payment of the said amount to DTCP. We
     must mention here that Clause 19 of the Development Agreement
     provided that L&T shall reimburse PCL the EDC amount already
     paid up to the date of the Development Agreement by mutually
     agreed instalments. The amounts paid by PCL towards EDC up
     to the date of execution of the Development Agreement were also
     mentioned, as L&T did not pay the amount already paid by PCL
     towards EDC. By Clause (III) of the Supplementary Agreement,
     Clause 19 was modified. The main reason for the execution of the
     Supplementary Agreement and the Tripartite Agreement was the
     default on the part of L&T. The Tribunal looked into various terms
     and conditions of the Development Agreement and the obligation of
     L&T to carry out its activities in a time-bound manner. The Tribunal
     considered the pleadings of PCL and the failure of L&T to deny
     material paragraphs. The tribunal also referred to a letter dated 7th
     October, 1999, addressed by L&T that its consultant had reported
     that it would not be favourable to pursue the project and therefore
     requirement of payment of EDC by L&T does not arise. In fact, L&T
     relied upon the report of BCG. However, in respect of order dated
     08th November, 2001, L&T did not produce the relevant documents.
     The Tribunal has noted that L&T was aware about PCL’s financial
     conditions and its obligations towards ITCREF. The Tribunal also
     referred to the fact that on 02nd November, 1999, DTCP issued a
     show cause notice proposing cancellation of licenses due to non-
     payment of EDC. These facts and the default by L&T left no choice
     to PCL but to execute the Supplementary Agreement as well as the
     Tripartite Agreement.
48. The Division Bench referred to Section 16(3) of the Contract Act which
    provides that where a person who is in a position to dominate the
    will of another, enters into a contract with him, and the transaction
    appears, on the face of it or on the evidence adduced, to be
    unconscionable, the burden of proving that there was no undue
    influence is on the person in a position to dominate the will of the
    other. Illustrations (c) and (d) of Section 16(3) of the Contract Act
    were also relied upon, which deal with cases of economic duress
    and undue influence. After examining the evidence, the Division
    Bench held that there was no patent illegality in the findings recorded
[2025] 4 S.C.R.                                                      2845

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


     by the Arbitral Tribunal that the Supplementary Agreement and the
     Tripartite Agreement were tainted by coercion. On consideration
     of the facts discussed before, such a view by the Arbitral Tribunal
     cannot be said to be contrary to justice and morality. We agree with
     the view taken by the Division Bench.
49. Dealing with issue no. 3, the Division Bench referred to Clause 26
    of the Development Agreement and Clause 5 of the Supplementary
    Agreement. The Tribunal found that L&T committed a breach of Clause
    19 of the Development Agreement by not making payment of a single
    instalment of EDC. Moreover, interest free deposit of Rs. 5 crores
    in terms of Clause 12 of the Development Agreement was not paid
    by L&T to PCL. The Tribunal found that there was no Development
    work carried out and not a single floor of any residential building was
    constructed for which development plans were sanctioned. Therefore,
    the finding recorded by the Tribunal that L&T committed fundamental
    breaches of the agreement cannot be interfered within the limited
    jurisdiction under Section 34 of the Arbitration Act.
50. As regards issue no. 4 and 5, the Division Bench has considered
    material on record. The Division Bench recorded that approval of
    the competent authority under the Income Tax Act, 1961 was given
    on 30th June, 1998 and the building plans were sanctioned on
    30th September, 1998. The title deeds were handed over by PCL to
    L&T on 16th October, 1998. There are letters on record addressed
    by PCL complaining to L&T about failure to make any progress on
    the site. No EDC payments were made by L&T. Even planning of
    the project was not completed by L&T till December, 1999. That is
    how the inspection of the Arbitral Tribunal revealed that L&T did
    not commence the development work. From the recital of clauses
    in the Development Agreement, it is apparent that L&T was aware
    of the obligations of PCL towards ITCREF. Considering the material
    on record, the Arbitral Tribunal recorded that there was a conscious
    decision on the part of L&T to abandon the development and not to
    fulfil its obligations under the contract. Therefore, the Division Bench
    accepted the correctness of the finding recorded by the Tribunal that
    there was an abandonment of the project on the part of L&T. The
    Division Bench rightly declined to find fault with the findings recorded
    by the Tribunal on this aspect based on evidence. Obviously, such
    conduct on the part of L&T caused loss to PCL, which ultimately
    resulted in the termination of the Development Agreement. The
2846                                                      [2025] 4 S.C.R.

                        Supreme Court Reports


     issues based on the rejection of the counter-claim of L&T have been
     rightly addressed by the Division Bench on the ground that there
     were no submissions made on the rejection of the counter-claim
     before the learned Single Judge in a petition under Section 34 of
     the Arbitration Act.
51. The Division Bench dealt with the Tribunal’s direction to L&T to
    pay Rs. 50 crores to PCL on crystallization of ITCREF’s claims.
    The Division Bench held that the type and kind of losses incurred
    by ITCREF would not be reasonably foreseeable for PCL to be
    indemnified against. Therefore, the Division Bench rightly observed
    that while granting a sum of Rs. 50 crores to PCL, the Tribunal had
    gone overbroad. The said finding of the Division Bench cannot be
    faulted with.
52. As regards the damages of the sum of Rs. 35 crores to be paid by
    L&T to PCL on account of breach of the Development Agreement,
    the basis taken by the Tribunal was the figures given by L&T in
    its counter-claim. Mr. Mohinder Puri estimated the loss of PCL at
    Rs. 117 crores. However, PCL did not prove the said loss, and the
    Tribunal did not rely upon any evidence to arrive at a fair assessment
    of the loss actually incurred by PCL. The Division Bench held that
    instead of basing the findings on the figures set out by L&T in its
    counter-claim, the correct approach would have been to determine
    the prevailing market rate for sale of built-up area at the time of the
    breach and thereupon determine the proceeds that PCL would have
    received from the sale of its 25 per cent share under the Development
    Agreement. Therefore, the award of Rs. 35 crores as damages was
    fundamentally contrary to Section 73 of the Contract Act. Such an
    approach was completely contrary to substantive law in the form of
    Section 73. This finding cannot be disturbed.
53. As regards the direction to pay the amount of Rs. 6 crores with
    interest, we need not record any finding as the amount has been
    paid by L&T. The award in the alternative of Rs. 75 crores, without
    proof of the value of land, cannot be sustained at all. There was no
    evidence on record to indicate that the value of the 15-acre area would
    be Rs. 5 crores per acre. Similarly, there was no basis for granting
    Rs. 5 crores to PCL due to L&T’s failure to return the licenses and
    other statutory permits. In these circumstances, we find the view
    taken by the Division Bench to be correct.
[2025] 4 S.C.R.                                                              2847

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


54. As the termination of the Development Agreement is upheld, obviously,
    L&T cannot deal with the property in any manner and PCL can
    always deal with the same.
55. In para 119, the Division Bench held thus:
           “119. In the circumstances, the Court concludes as follows:
           a. The finding of the Tribunal that the Development
           Agreement was not novated by the Supplementary
           Agreement is upheld; similarly the Tribunal’s findings that
           the conditions which were to be fulfilled by L&T subject to
           which the said Supplementary Agreement was to come
           into force (but were not fulfilled) are upheld;
           b. The finding of the Tribunal that the Supplementary
           Agreement was a non-starter as it was vitiated by economic
           duress is upheld. The impugned judgment’s ruling to the
           contrary is set aside.
           c. The finding of the Tribunal that L&T committed
           fundamental breach of the Development Agreement is
           upheld. The impugned judgment’s ruling to the contrary
           is set aside.
           d. The Tribunal’s dismissal of L&T’s counterclaim is upheld.
           e. The Tribunal’s quantification of damages for breach of
           contract (35 crores), compensation in lieu of securing title
           deeds with respect to 15 acres of land (75 crores) and
           compensation for default in returning licences and other
           permits is set aside (5 crores). The permanent injunction
           granted in favour of PCL restraining L&T from interfering
           with PCL’s development of Schedule A property of the
           Development Agreement is upheld. The relief granting
           indemnification in favour of PCL for ITCREF’s claims is
           set aside. It is clarified that this is without prejudice to the
           indemnification for ITCREF’s claims relating to the transfer
           of 2,20,416 sq. ft. of land to the extent envisaged under
           the Development Agreement, The Tribunal’s order to the
           extent that it awards costs of arbitration to PCL is upheld.
           f. Title deeds deposited with the Registrar of this Court
           pursuant to the directions in FAO 319/2001 are directed
           to be released to PCL.”
2848                                                      [2025] 4 S.C.R.

                        Supreme Court Reports


56. The powers of the Appellate Court under Section 37 of the Arbitration
    Act are not broader than those of the Court under Section 34 of the
    Arbitration Act. Therefore, what cannot be done in the exercise of
    the powers under Section 34 cannot be done in an Appeal under
    Section 37. An Arbitral Award cannot be modified. Thus, even after
    recording the conclusions in paragraph no. 119, the Division Bench
    has not modified the Award by partly setting aside the Judgment
    under Section 34. In paragraph 121 of the Judgment, the Division
    Bench held thus:
          “121. In light of the above conclusions, parties are left to
          pursue the appropriate course of action under law. This
          Court notices that since the dispute has been in subsistence
          for a considerable period of time, an attempt may be
          made at settling the claims through mediation. FAO (OS)
          21/2009, 22/2009 and 23/2009 are partly allowed to the
          above extent; FAO (OS) 194/2009 is dismissed, for the
          same reason.”
     On a conjoint reading of Paragraph 119 and 121, we find that the
     remedy of PCL has been kept open to pursue appropriate course
     of action under law as there cannot be a remand to the Arbitral
     Tribunal for quantification of monetary claim. As the finding of the
     Arbitral Tribunal regarding breaches committed by L&T was affirmed,
     the Division Bench has rightly segregated that part of the Award by
     which, cost of arbitration was ordered to be paid to PCL by L&T. This
     part has been severed from rest of the Award. Therefore, this part
     of the Award must be complied with by L&T, if not already done. As
     documents of title were deposited with the Registrar, the direction
     to hand over the same to PCL cannot be faulted with. We cannot
     find any fault with the operative part in paragraph 120.
57. Before we part with Judgment, we must reproduce what is observed
    by Division Bench in paragraph no. 120 with approval:
          “120. Before concluding, the court would like to highlight -
          more as a post script, the prolix and near interminable
          arguments which were addressed by senior counsel on
          either side, who were insistent that the arbitral records,
          such as pleadings and documents, had to be examined,
          and read out in court. The court unsuccessfully entreatied
          them to limit oral arguments; equally unsuccessful were
[2025] 4 S.C.R.                                                         2849

 Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. and Others


           attempts at ensuring that written briefs were kept within
           limits. The citation of numerous authorities on similar
           propositions, and reference to factual material, reduced an
           arbitration appeal (against the decision in Section 34) to
           the Division Bench into an appeal on facts, which Section
           37 was clearly not intended to be. One hopes that there
           is some clarity within the legal system about the kind of
           time limit to arguments in such cases, to ensure timely
           disposal of appeals.”
58. We agree with the views expressed by the Division Bench which
    we have quoted above. In several appeals arising out of Sections
    34 and 37 proceedings, we have noticed that there is a tendency
    on the part of the senior members of the Bar to argue as if these
    proceedings were regular appeals under Section 96 of the Code of
    Civil Procedure, 1908 (for short ‘CPC’). In this case, while making
    submissions, the learned counsel appearing for both the parties have
    gone into the minutest factual details. As the Members of the Bar are
    aware of the limited jurisdiction of the Courts in proceedings under
    Sections 34 and 37 of the Arbitration Act, they must show restraint.
    Similarly, we observe a tendency on the part of the Members of the
    Bar to rely upon a large number of decisions, whether relevant or
    irrelevant, while arguing Section 34 petitions and Section 37 appeals
    as well as appeals arising therefrom. Multiple decisions are cited on
    the same proposition of law. This makes hearing time-consuming. As
    there are long oral arguments, the Courts permit written submissions
    to be filed. That is how very long written submissions come on
    record. The Courts have to devote page after page for dealing with
    many submissions which ought not be made considering the limited
    jurisdiction under Section 34 of the Arbitration Act. This results in
    very lengthy judgments. The high monetary stakes involved in the
    proceedings should not result in unnecessarily long oral submissions
    or bulky written submissions. All this results in the criticism about
    the arbitrations in India. Therefore, there is a need to impose time
    limit on oral submissions in such cases. We cannot forget that this
    Court and the High Courts have the appellate jurisdiction in civil
    and criminal cases. These Courts should be in a position to also
    devote sufficient time to the cases of the common man. What we
    have expressed is a matter of serious concern and introspection
    for everyone.
2850                                                      [2025] 4 S.C.R.

                            Supreme Court Reports


59. In view of what we have held earlier, there is no merit in the appeals
    and the same are dismissed.


     Result of the case: Appeals dismissed.



     †
         Headnotes prepared by: Divya Pandey


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Power of court under s.34 Arbitration Act"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.