LAND AND BUILDING DEPARTMENT THROUGH SECRETARY, GOVERNMENT OF NCT OF DELHI & ANR.versusMAHIPAL SINGH & ORS
- Citation
- 2022 INSC 1251
- Decided
- 2 December 2022
- Disposal
- Appeal(s) allowed
- Bench
- M R SHAH
Holding
Under Section 24(2) of the 2013 Act, acquisition proceedings do not lapse when possession has been taken even if compensation has not been paid, and the High Court’s finding of lapse is overruled.
Summary
The Delhi government had taken possession of land on 3 December 2012 under the Land Acquisition Act, 1894 and sent the compensation award to the Reference Court on 28 October 2014. The Delhi High Court held that, because the compensation was not tendered before the 2013 Right to Fair Compensation Act came into force, the acquisition proceedings were deemed to have lapsed under Section 24(2) of that Act. On appeal, the Supreme Court examined the interpretation of Section 24(2) in light of its recent constitutional‑bench decision in Indore Development Authority v. Manoharlal, which overruled the earlier Pune Municipal Corporation judgment. The Court held that when possession has been taken, the acquisition does not lapse even if compensation has not yet been paid, and that the word “or” in Section 24(2) must be read as “nor”/“and”. Consequently, the High Court’s declaration of lapse was unsustainable and was set aside. The appeal was allowed, and the acquisition proceedings continue under the 1894 Act.
Issues considered
- Whether Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 deems acquisition proceedings to have lapsed when possession has been taken but compensation has not been paid or tendered before the Act's commencement.
- How the word “or” in Section 24(2) should be interpreted for the purpose of determining a deemed lapse.
- Whether non‑deposit of compensation in court constitutes payment under Section 24(2).
- The continued applicability of the Pune Municipal Corporation v. Harakchand decision after the Indore Development Authority judgment.
Legislation cited
- Land Acquisition Act, 1894s. 16, s. 31, s. 34, s. 4
- Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013s. 24(1)(a), s. 24(1)(b), s. 24(2)
Subjects
Judgment
610 [2022]REPORTS
SUPREME COURT 16 S.C.R. 610 [2022] 16 S.C.R.
A LAND AND BUILDING DEPARTMENT THROUGH
SECRETARY, GOVERNMENT OF NCT OF DELHI & ANR.
v.
MAHIPAL SINGH & ORS.
B (Civil Appeal No. 8932 of 2022)
DECEMBER 02, 2022
[M. R. SHAH AND C. T. RAVIKUMAR, JJ.]
Right to Fair Compensation and Transparency in Land
Acquisition, Rehabilitation and Resettlement Act, 2013: s.24(2) –
C Land Acquisition – Possession of land taken on 03.12.2012and
handed over to DDA – Compensation also sent to Reference Court
on 28.10.2014 – Inspite of this, solely on the ground that the
compensation was not tendered prior to coming into force of the
Act, 2013, High Court declared that the land acquisition with respect
D to the land in question was deemed to have lapsed – Held: The view
taken by the High Court is not sustainable in view of the
Constitutional Bench decision of Supreme Court in Indore
Development Authority v. Manoharlal and Ors. wherein it was held
that in case possession was taken but compensation not paid then
there is no lapse – High Court order set aside.
E
Indore Development Authority v. Manoharlal and Ors.
(2020) 8 SCC 129 : [2020] 3 SCR 1 – followed.
Pune Municipal Corporation and Anr. v. Harakchand
Misirimal Solanki and Ors. (2014) 3 SCC 183 : [2014]
1 SCR 783 – referred to.
F
Case Law Reference
[2014] 1 SCR 783 referred to Para 2.1
[2020] 3 SCR 1 followed Para 2.2
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 8932
G of 2022.
From the Judgment and Order dated 31.01.2018 of the High Court
of Delhi at New Delhi in Writ Petition (C) No. 11238 of 2015.
Ms. Sujeeta Srivastava, Adv. for the Appellants.
H Krishan Kumar, Nitin Mishra, Advs. for the Respondents.
610
LAND AND BUILDING DEPT. THROUGH SECY., GOVT. OF 611
NCT OF DELHI v. MAHIPAL SINGH
The Judgment of the Court was delivered by A
M. R. SHAH, J.
1. Feeling aggrieved and dissatisfied with the impugned judgment
and order passed by the High Court of Delhi at New Delhi in Writ
Petition(C) No. 11238 of 2015 by which the High Court has allowed the
said writ petition and has declared that theland acquisition proceedings B
initiated under the Land Acquisition Act, 1894 (hereinafter referred to
as “Act, 1894”) with regard to the landin question isdeemed to have
lapsed under Section 24(2) of the Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and Resettlement Act,
2013 (hereinafter referred to as “Act, 2013”), the Government of NCT C
of Delhi and Anr.havepreferred the present appeal.
2. From the impugned judgment and order passedby the High
Court and even from the counter affidavit filed on behalf of the Land
Acquisition Collector filed before the High Court, which is reproduced
by the High Court in the impugned judgment and order in paragraph 6, it D
was the specific case on behalf of the appellants that the possession of
the land in question was taken over on 03.12.2012 after preparing
possession proceeding on the spot and was handed over to the beneficiary
department, i.e., Delhi Development Authority (DDA) immediately. It
was also pointed out that the compensation was also sent to the Reference
Court on 28.10.2014 as there was an apportionment dispute. E
2.1 In spite of above, solely on the ground that the compensation
was not tendered prior to coming into force of the Act, 2013 and relying
upon the decision of this Court in the case of Pune Municipal
Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors.,
(2014) 3 SCC 183, the High Court has allowed the writ petition and F
has declared that the land acquisition proceedings have lapsed under
Section 24(2) of the Act, 2013.
2.2 The view taken by the High Court relying upon the decision of
this Court in the case of Pune Municipal Corporation and Anr.
(supra) is unsustainable in view of the Constitution Bench decision of G
this Court in the case of Indore Development Authority Vs.
Manoharlal and Ors., (2020) 8 SCC 129. In paragraphs 365 and
366, the Constitution Bench of this Court has observed and held as under:-
“365. Resultantly, the decision rendered in Pune Municipal
Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal Solanki, H
612 SUPREME COURT REPORTS [2022] 16 S.C.R.
A (2014) 3 SCC 183] is hereby overruled and all other decisions in
which Pune Municipal Corpn. [Pune Municipal Corpn. v.
Harakchand Misirimal Solanki, (2014) 3 SCC 183] has been
followed, are also overruled. The decision in Sree Balaji Nagar
Residential Assn. [Sree Balaji Nagar Residential Assn. v. State
of T.N., (2015) 3 SCC 353] cannot be said to be laying down
B
good law, is overruled and other decisions following the same are
also overruled. In Indore Development Authority v. Shailendra
[(2018) 3 SCC 412], the aspect with respect to the proviso to
Section 24(2) and whether “or” has to be read as “nor” or as
“and” was not placed for consideration. Therefore, that decision
C too cannot prevail, in the light of the discussion in the present
judgment.
366. In view of the aforesaid discussion, we answer the
questions as under:
366.1. Under the provisions of Section 24(1)(a) in case the
D award is not made as on 1-1-2014, the date of commencement of
the 2013 Act, there is no lapse of proceedings. Compensation has
to be determined under the provisions of the 2013 Act.
366.2. In case the award has been passed within the window
period of five years excluding the period covered by an interim
E order of the court, then proceedings shall continue as provided
under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it
has not been repealed.
366.3. The word “or” used in Section 24(2) between possession
and compensation has to be read as “nor” or as “and”. The deemed
F lapse of land acquisition proceedings under Section 24(2) of the
2013 Act takes place where due to inaction of authorities for five
years or more prior to commencement of the said Act, the
possession of land has not been taken nor compensation has been
paid. In other words, in case possession has been taken,
G compensation has not been paid then there is no lapse. Similarly,
if compensation has been paid, possession has not been taken
then there is no lapse.
366.4. The expression “paid” in the main part of Section 24(2)
of the 2013 Act does not include a deposit of compensation in
court. The consequence of non-deposit is provided in the proviso
H
LAND AND BUILDING DEPT. THROUGH SECY., GOVT. OF 613
NCT OF DELHI v. MAHIPAL SINGH [M. R. SHAH, J.]
to Section 24(2) in case it has not been deposited with respect to A
majority of landholdings then all beneficiaries (landowners) as on
the date of notification for land acquisition under Section 4 of the
1894 Act shall be entitled to compensation in accordance with the
provisions of the 2013 Act. In case the obligation under Section
31 of the Land Acquisition Act, 1894 has not been fulfilled, interest
B
under Section 34 of the said Act can be granted. Non-deposit of
compensation (in court) does not result in the lapse of land
acquisition proceedings. In case of non-deposit with respect to
the majority of holdings for five years or more, compensation under
the 2013 Act has to be paid to the “landowners” as on the date of
notification for land acquisition under Section 4 of the 1894 Act. C
366.5. In case a person has been tendered the compensation
as provided under Section 31(1) of the 1894 Act, it is not open to
him to claim that acquisition has lapsed under Section 24(2) due
to non-payment or non-deposit of compensation in court. The
obligation to pay is complete by tendering the amount under Section D
31(1). The landowners who had refused to accept compensation
or who sought reference for higher compensation, cannot claim
that the acquisition proceedings had lapsed under Section 24(2)
of the 2013 Act.
366.6. The proviso to Section 24(2) of the 2013 Act is to be E
treated as part of Section 24(2), not part of Section 24(1)(b).
366.7. The mode of taking possession under the 1894 Act and
as contemplated under Section 24(2) is by drawing of inquest
report/memorandum. Once award has been passed on taking
possession under Section 16 of the 1894 Act, the land vests in F
State there is no divesting provided under Section 24(2) of the
2013 Act, as once possession has been taken there is no lapse
under Section 24(2).
366.8. The provisions of Section 24(2) providing for a deemed
lapse of proceedings are applicable in case authorities have failed G
due to their inaction to take possession and pay compensation for
five years or more before the 2013 Act came into force, in a
proceeding for land acquisition pending with the authority concerned
as on 1-1-2014. The period of subsistence of interim orders passed
by court has to be excluded in the computation of five years.
H
614 SUPREME COURT REPORTS [2022] 16 S.C.R.
A 366.9. Section 24(2) of the 2013 Act does not give rise to new
cause of action to question the legality of concluded proceedings
of land acquisition. Section 24 applies to a proceeding pending on
the date of enforcement of the 2013 Act i.e. 1-1-2014. It does not
revive stale and time-barred claims and does not reopen concluded
proceedings nor allow landowners to question the legality of mode
B
of taking possession to reopen proceedings or mode of deposit of
compensation in the treasury instead of court to invalidate
acquisition.”
3. In view of the above and when the relied upon judgment in the
case of Pune Municipal Corporation and Anr. (supra) has been
C specifically overruled by this Court in the case of Indore Development
Authority (supra) and considering the fact that the possession of the
land in question was already taken over in the year 2012 and the same
was handed over to the beneficiary – DDA immediately and in light of
the observations made by the Constitution Bench in the case of Indore
D Development Authority (supra) made in paragraphs 365 and 366
(reproduced hereinabove), the impugned judgment and order passed by
the High Court is unsustainable and deserves to be quashed and set
aside and is accordingly quashed and set aside.
Present appeal is accordingly allowed. No costs.
E Pending applications, if any, also stand disposed of.
Devika Gujral Appeal allowed.
F
G
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.