KIRPAL SINGHversusGOVERNMENT OF INDIA, NEW DELHI & ORS.
- Citation
- 2024 INSC 944
- Decided
- 21 November 2024
- Disposal
- Disposed off
Holding
Section 14 of the Limitation Act applies to applications under Section 34 of the Arbitration and Conciliation Act, and the period from 20 October 2011 to 23 February 2012 is excluded as sufficient cause, entitling the appellant to the statutory remedy.
Summary
The appellant's land was acquired under the National Highways Act, leading to an arbitral award on 25 July 2011. A regular first appeal was filed on 20 October 2011, but the High Court registry notified defects on 9 November 2011, which the appellant's counsel received only on 20 January 2012. Consequently, the appellant filed a Section 34 petition under the Arbitration and Conciliation Act on 23 February 2012, which the District Judge dismissed as time‑barred. The Supreme Court examined whether the period from 20 October 2011 to 23 February 2012 could be excluded under Section 14 of the Limitation Act, relying on the precedent set in Consolidated Engineering Enterprises v. Principal Secretary. It held that Section 14 applies to Section 34 applications and that the exclusion period is justified by sufficient cause. Accordingly, the Court allowed the appeals, set aside the lower courts' orders, and restored the Section 34 petition.
Issues considered
- Whether the period from 20 October 2011 to 20 January 2012 (or to 23 February 2012) should be excluded under Section 14 of the Limitation Act when computing the limitation period for a Section 34 application under the Arbitration and Conciliation Act, 1996 incorporated in the National Highways Act, 1956.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 34, s. 37, s. 43
- Limitation Act, 1963s. 14
- National Highways Act, 1956s. 3(G)
Headnote
Issue for Consideration Whether the period commencing from 20.10.2011 to 20.01.2012 should be condoned u/s.14 of the Limitation Act while reckoning the period of limitation for filing objections under Arbitration and Conciliation Act, 1996 incorporated in the National Highways – s.14 – Arbitration and Conciliation Act, 1996 – s.34 and s.37 – National Highways Act, 1956 – A land belonging to appellant was acquired under the NH Act leading to passing of an award dated 25.07.2011 – A Regular First Appeal was filed before the High
Subjects
Judgment
[2024] 11 S.C.R. 1329 : 2024 INSC 944
Kirpal Singh
v.
Government of India, New Delhi & Ors.
(Civil Appeal No(s). 12849-12856 of 2024)
21 November 2024
[Pamidighantam Sri Narasimha and Manoj Misra, JJ.]
Issue for Consideration
Whether the period commencing from 20.10.2011 to 20.01.2012
should be condoned u/s.14 of the Limitation Act while reckoning
the period of limitation for filing objections under Arbitration and
Conciliation Act, 1996 incorporated in the National Highways Act,
1956.
Headnotes†
Limitation Act, 1963 – s.14 – Arbitration and Conciliation
Act, 1996 – s.34 and s.37 – National Highways Act, 1956 –
A land belonging to appellant was acquired under the NH
Act leading to passing of an award dated 25.07.2011 – A
Regular First Appeal was filed before the High Court on
20.10.2011 on an erroneous understanding – The Registry
of the High Court notified certain defects on 09.11.2011 and
it is said to have been received by the concerned Advocate
only on 20.01.2012 – Appellant filed an application u/s.34
of the Arbitration Act before the District Judge, however,
the same was dismissed on the ground that it was barred by
limitation – Correctness:
Held: When the substantive remedies u/ss.34 and/or 37 of the
Arbitration Act are by their very nature limited in their scope due
to statutory prescription, it is necessary to interpret the limitation
provisions liberally, or else, even that limited window to challenge
an arbitral award will be lost – The remedies u/ss.34 and 37 are
precious – Courts of law will keep in mind the need to secure and
protect such a remedy while calculating the period of limitation for
invoking these jurisdictions – Applying s.14 of the Limitation Act,
there is sufficient cause for excluding the period commencing from
20.10.2011 to 23.02.2012 – In view of the fact that this period is
excluded, the appellant will be entitled to the statutory remedy
u/s.34 of the Act. [Paras 10, 11]
1330 [2024] 11 S.C.R.
Digital Supreme Court Reports
Case Law Cited
Consolidated Engineering Enterprises v. Principal Secretary,
Irrigation Department and Others [2008] 5 SCR 1108 : 2008 (7)
SCC 169 – relied on.
Union of India v. Popular Construction Co. [2001] Supp. 3 SCR
619 : 2002 (1) RCR (Civil) 124 – referred to.
List of Acts
Arbitration and Conciliation Act, 1996; National Highways Act,
1956; Limitation Act, 1963.
List of Keywords
Section 14 of Limitation Act, 1963; Section 34 of Arbitration and
Conciliation Act, 1996; Period of limitation; Exclusion of period;
Arbitration; Sufficient Cause.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No(s). 12849-
12856 of 2024
From the Judgment and Order dated 19.10.2019 of the High Court
of Punjab & Haryana at Chandigarh in FAO Nos. 800 of 2013, 1278
of 2015, 1290 of 2015, 7453 of 2014, 7454 of 2014, 2887 of 2015
and 8136 of 2014
Appearances for Parties
Chritarth Palli, Nilanjan Sen, Vijay Kumar Dwivedi, Deepak Samota,
Shubham Bhalla, Advs. for the Appellant.
Alok Sangwan, Sumit Kumar Sharma, Rajat Sangwan, Sunny
Kadiyan, Advs. for the Respondents.
Judgment / Order of the Supreme Court
Order
1. Leave granted.
2. These appeals arise from the judgment and order passed by the
High Court of Punjab & Haryana at Chandigarh dated 19.10.2019
[2024] 11 S.C.R. 1331
Kirpal Singh v. Government of India, New Delhi & Ors.
in FAO Nos. 800/2013, 7453, 7454, 8136/2014, 1278, 1290, 2000
and 2887/2015. The short question that arises for consideration is
whether the period commencing from 20.10.2011 to 20.01.2012
should be condoned under Section 14 of the Limitation Act while
reckoning the period of limitation for filing objections under Arbitration
and Conciliation Act, 19961 incorporated in the National Highways
Act, 1956.2
3. The facts relevant for our decision are that the land belonging to the
appellant was acquired under the NH Act leading to passing of an
award dated 25.07.2011. Application for a certified copy of the award
was made on 12.08.2011 and the same was received on 08.09.2011.
Thereafter, a Regular First Appeal was filed before the High Court
on 20.10.2011 on an erroneous understanding.
4. The Registry of the High Court notified certain defects on 09.11.2011
and it is said to have been received by the concerned Advocate
only on 20.01.2012. It is only thereafter when the appellant came
to know about the appropriate action available to him, being the
statutory remedy under Section 34 of the Arbitration Act, and he
took steps and instituted proceedings under Section 34 of the said
Act on 23.02.2012.
5. The District Judge took up the application under Section 34 of the
Act and by his order dated 16.05.2012 dismissed the same on the
ground that it is barred by limitation as determined by this Court in
the case of Union of India Vs. Popular Construction Co.3 The
appeal under Section 37 of the Arbitration Act was also dismissed
by the order impugned before us.
6. Mr. Gaurav Agarwal, learned Senior Advocate appearing for the
appellant has submitted that his client is entitled to the exclusion
of period from 20.10.2011 to 20.01.2012 under Section 14 of the
Limitation Act. For this purpose, he relied on the judgment of this
Court in Consolidated Engineering Enterprises vs. Principal
Secretary, Irrigation Department and Others.4 The relevant portion
of the judgment is quoted hereunder:
1 Hereinafter referred to as “the Arbitration Act”
2 Hereinafter referred to as “the NH Act”
3 [2001] Supp. 3 SCR 619 : 2002 (1) RCR (Civil) 124
4 [2008] 5 SCR 1108 : (2008) 7 SCC 169
1332 [2024] 11 S.C.R.
Digital Supreme Court Reports
“23. At this stage it would be relevant to ascertain whether
there is any express provision in the Act of 1996, which
excludes the applicability of Section 14 of the Limitation
Act. On review of the provisions of the Act of 1996 this
Court finds that there is no provision in the said Act which
excludes the applicability of the provisions of Section 14
of the said Act…..
Hence, Section 43 incorporating the Limitation Act will
apply to the proceedings in the arbitration as it applies
to the proceedings of a suit in the court. Sub-section (4)
of Section 43, inter alia, provides that where the court
orders that an arbitral award be set aside, the period
between the commencement of the arbitration and
the date of the order of the court shall be excluded in
computing the time prescribed by the Limitation Act, 1963,
for the commencement of the proceedings with respect
to the dispute soc submitted. If the period between the
commencement of the arbitration proceedings till the award
is set aside by the court, has to be excluded in computing
the period of limitation provided for any proceedings with
respect o the dispute, there is no good reason as to why
it should not be held that the to provisions of Section 14
of the Limitation Act would be applicable to an application
submitted under Section 34 of the Act of 1996, more
particularly d where no provision is to be found in the Act
of 1996, which excludes the applicability of Section 14 of
the Limitation Act, to an application made under Section
34 of the Act. It is to be noticed that the powers under
Section 34 of the Act can be exercised by the court only if
the aggrieved party makes an application. The jurisdiction
under Section 34 of the Act, cannot be exercised suo
motu. The total period of four months within which an
application, for setting aside an arbitral award, has to be
made is not unusually long. Section 34 of the Act of 1996
would be unduly oppressive, if it is held that the provisions
of Section 14 of the Limitation Act are not applicable to
it, because cases are no doubt conceivable where an
aggrieved party, despite exercise of due diligence and good
faith, is unable to make an application within a period of
[2024] 11 S.C.R. 1333
Kirpal Singh v. Government of India, New Delhi & Ors.
four months. From the scheme and language of Section
34 of the Act of 1996, the intention of the legislature to
exclude the applicability of Section 14 of the Limitation Act
is not manifest. It is well to remember that Section 14 of
the Limitation Act does not provide for a fresh period of
limitation but only provides for the exclusion of a certain
period. Having regard to the legislative intent, it will have to
be held that the provisions of Section 14 of the Limitation
Act, 1963 would be applicable to g an application submitted
under Section 34 of the Act of 1996 for setting aside an
arbitral award.”
7. On the other hand, Mr. Rajat Sangwan, learned counsel appearing
for respondent Nos.1 and 2 (National Highway Authority of India)
has vehemently contended that the periods of limitation under the
Arbitration Act are sacrosanct and these provisions are strictly
interpreted by the Courts. He would further submit that, even
assuming that Section 14 of the Limitation Act is applicable, the
benefit of the said section cannot be extended beyond 20.10.2011.
In other words, his submission is that the period commencing from
09.11.2011 to the filing of Section 34 petition being 23.02.2012,
should not be condoned.
8. Further, Mr. Rajat Sangwan, would also submit that the language
of Section 14 is mandatory and on the basis of the said provision
it cannot be said that the appellant has exercised due diligence
in approaching the Court by filing the Section 34 petition. He also
argued that strict enforcement of time-lines under the Arbitration
Act are recognized and incorporated under the National Highways
Act. For this purpose, he referred to sub-section 7 of Section 3(G)
of the NH Act.
9. Having considered the matter in detail, we are of the opinion that
the issue is covered by the decision of this court in Consolidated
Engg. Enterprises v. Principal Secretary, Irrigation Dept.5 (supra).
10. We may hasten to add that when the substantive remedies under
Sections 34 and/or 37 of the Arbitration Act are by their very nature
5 [2008] 5 SCR 1108 : 2008 (7) SCC 169.
1334 [2024] 11 S.C.R.
Digital Supreme Court Reports
limited in their scope due to statutory prescription,6 it is necessary to
interpret the limitation provisions liberally, or else, even that limited
window to challenge an arbitral award will be lost. The remedies
under Sections 34 and 37 are precious. Courts of law will keep in
mind the need to secure and protect such a remedy while calculating
the period of limitation for invoking these jurisdictions.
11. Applying Section 14 of the Limitation Act, we hold that there is
sufficient cause for excluding the period commencing from 20.10.2011
to 23.02.2012. In view of the fact that this period is excluded, the
appellant will be entitled to the statutory remedy under Section 34
of the Act.
12. In view of the above, we allow the appeals, set aside the judgment
and order passed by the High Court in FAO Nos. 800/2013(O&M),
2000/2015(O&M), 1278/2015(O&M), 1290/2015(O&M),
7453/2014(O&M), 7454/2014(O&M), 2887/2015(O&M) and 8136/2014
(O&M) dated 19.10.2019 and also the order of the District Judge,
Jalandhar dated 16.05.2012 and restore the Section 34 petition in
Arbitration No.3435/2012 to its original number. We further direct
the District Judge, Jalandhar to issue notice to all the parties, hear
them and decide the petition as per law.
13. With the above observations, the civil appeals are disposed of.
14. There shall be no order as to costs.
Result of the case: Appeals disposed of.
†
Headnotes prepared by: Ankit Gyan
6 Arbitration and Conciliation Act, 1996.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.