IN RE: FELLING OF TREES IN AAREY FOREST (MAHARASHTRA)versusIN RE: FELLING OF TREES IN AAREY FOREST (MAHARASHTRA)
- Citation
- 2023 INSC 381
- Decided
- 17 April 2023
- Disposal
- Disposed off
- Bench
- D Y CHANDRACHUD
Holding
The Court held that MMRCL was improper in moving the Tree Authority for felling trees beyond the 84‑tree limit and must comply with the earlier order, but the 15 March 2023 permission was not stayed; instead, MMRCL was allowed to act under it subject to a Rs.10 lakh penalty and compliance directives.
Summary
The Supreme Court was approached by Mumbai Metro Rail Corporation Limited (MMRCL) for clarification of its earlier order permitting the corporation to move the Tree Authority to fell 84 trees in Aarey Forest for the Metro Line‑3 project. MMRCL later sought to fell 124 trees and transplant 53 trees, exceeding the authorized limit, without obtaining further permission from the Court. The High Court held that no trees should be felled beyond the 84‑tree limit until the Supreme Court clarified the matter. The Court observed that MMRCL’s action was improper and that any variation required a fresh application to the Supreme Court, but staying the 15 March 2023 permission would halt the public project. Consequently, the Court modified its earlier order, allowing MMRCL to proceed under the 15 March permission subject to a penalty of Rs.10 lakhs and strict compliance monitoring by the Conservator of Forests, and disposed of the application for clarification.
Issues considered
- Whether MMRCL could lawfully seek permission to fell trees beyond the 84 trees authorized by the Supreme Court order without a fresh application to the Court.
- Whether the permission granted by the Superintendent of Gardens on 15 March 2023 should be stayed pending clarification.
- Whether MMRCL should be penalised for contravening the Supreme Court’s earlier order.
Subjects
Judgment
392 [2023]REPORTS
SUPREME COURT 6 S.C.R. 392 [2023] 6 S.C.R.
A IN RE: FELLING OF TREES IN AAREY FOREST
(MAHARASHTRA)
IA No. 68608 of 2023
In
B (Suo Moto Writ (Civil) No. 2 of 2019)
APRIL 17, 2023
[DR. DHANANJAYA Y CHANDRACHUD, CJI,
PAMIDIGHANTAM SRI NARASIMHA AND
J. B. PARDIWALA, JJ.]
C
Environment – Felling of trees – By order dated 29.11.2022,
MMRCL was permitted to move the Tree Authority on its application
for felling of 84 trees – On 02.01.2023, MMRCL, however, sought
permission to cut 185 trees, without moving Supreme Court – On
15.03.2023, the Superintendent of Gardens and Tree Officer granted
D permission for felling 124 trees and transplanting 53 trees, subject
to the condition that 1533 trees would be planted on the property –
The High Court held that propriety would require that trees shall
not be felled in pursuance of the order dated 15.03.2023 until a
clarification was sought from Supreme Court – Application for
clarification filed in Supreme Court – Held: It was improper on the
E
part of MMRCL to move the Tree Authority for the felling of any
trees in excess of 84 trees – If circumstances had transpired which
led to a variation in the number of trees to be cut, the only correct
course of action would have been to move Supreme Court – Now,
any direction to stay permission granted on 15.03.2023 would bring
F the public project to a standstill – Therefore, the previous order is
modified by permitting MMRCL to act in compliance with the order
dated 15.03.2023 – However, it would be necessary to penalize
MMRCL for its conduct – MMRCL directed to deposit an amount of
Rs. 10 lakhs with the conservator of forests – Conservator of Forests
to ensure all directions issued with regard to afforestation and for
G
transplantation of trees are complied with and submit report – I.A.
disposed of.
CIVIL ORIGINAL JURISDICTION: IA No. 68608 of 2023 in
Suo Moto Writ (Civil) No. 2 of 2019.
H
392
IN RE: FELLING OF TREES IN AAREY FOREST (MAHARASHTRA) 393
Under Article 32 of The Constitution of India A
By Courts Motion
Tushar Mehta, Shyam Divan, Gopal Sankaranarayan, Dhruv
Mehta, Maninder Singh, C.U. Singh, Sr. Advs., Chirag Shah,
Ms. Rukhmini Bobde, Ms. Soumya Priyadarshinee, Ankit Ambasta, Amit
Kumar Shrivastava, Amlaan Kumar, Vishal Prasad, Ms. Pooja Dhar, B
Tushad Kakalia, Sudipto Sarkar, Ms. Aditi Gupta, Ashish Wad, Sandip
Patil, Sidharth Mahajan, Ajeyo Sharma, Shyam Agarwal, M/s. J S Wad
and Co, Siddharth Dharmadhikari, Aaditya Aniruddha Pande, Bharat
Bagla, Sourav Singh, Shree Pal Singh, Ms. Anitha Shenoy, Ms. Srishti
Agnihotri, Ms. Sanjana Thomas, Advs. for the Respondent. C
The Judgment of the Court was delivered by
DR. DHANANJAYA Y CHANDRACHUD, CJI
1. Mumbai Metro Rail Corporation Limited1 seeks a clarification
of the order of this Court dated 29 November 2022. By the order of this D
Court, MMRCL was permitted to move the Tree Authority for felling 84
trees. MMRCL submits that 177 trees have to be felled or, as the case
may be, transplanted for the Metro Car Shed Land at Aarey Colony
admeasuring approximately 33 hectares for Mumbai Metro Line-3.
Permission is hence sought to implement the permission which has been
granted on 15 March 2023 by the Superintendent of Gardens of the E
Municipal Corporation of Greater Mumbai for felling 124 trees and
transplanting 53 trees.
2. By the order of this Court dated 29 November 2022, an earlier
order directing the preservation of the status quo on felling trees was
modified, so as to permit MMRCL to move the Tree Authority on its F
application for felling 84 trees. Following the order of this Court, an
application was initially moved on 19 December 2022 for permission to
fell 84 trees. On 2 January 2023, MMRCL, however, sought permission
to cut 185 trees, without moving this Court.
3. By a communication dated 20 December 2022, the Deputy G
Superintendent of Gardens intimated the Deputy General Manager
(Depot) of MMRCL that the site was jointly inspected by his staff, together
with the representatives of MMRCL on 19 December 2022. Following
1
“MMRCL”
H
394 SUPREME COURT REPORTS [2023] 6 S.C.R.
A the inspection, the Deputy Superintendent of Gardens sought compliance
on the following aspects:
“1. Submit updated proposal for the current status of trees as per
a fresh survey.
2. Mention missing/dead/fallen trees and also any new addition to
B the list of affected trees as a long period has lapsed since the last
survey.
3. Number all such trees on the sites with black and white paint;
4. Submit details of land where the trees are to be proposed for
C transplantation and compensatory plantation.”
4. On 12 January 2023, the Superintendent of Gardens issued a
public notice indicating that 185 trees would be affected of which 124
trees would be felled and 53 trees would be transplanted.
5. Since the action proposed was in excess of the 84 trees which
D were permitted to be felled by the order of this Court, a public interest
litigation2 was moved before the High Court of Judicature at Bombay.
The Division Bench, by its order dated 9 March 2023, observed:
“Public Notice has been issued by the Tree Authority. The Petitioner
has already raised objection before the Tree Authority. The
E Petitioner can bring it to the notice of the Tree Authority, the order
of the Apex Court. No final order has been passed by the Tree
Authority. It is for the Tree Authority to consider whether those
trees beyond 84 were shrubs or otherwise.”
6. On 15 March 2023, the Superintendent of Gardens and Tree
F Officer granted permission for felling 124 trees and transplanting 53
trees, subject to the condition that 1533 trees would be planted on the
property. This led to the institution of another public interest litigation 3
before the High Court. The Division Bench, by its order dated 31 March
2023, observed and, in our view, correctly, that this Court had granted
permission to move the Tree Authority only to the extent of 84 trees.
G Hence, the permission which was granted in respect of 177 trees was
beyond the permission granted by this Court on 29 November 2022.
The High Court held that propriety would require that trees shall not be
felled in pursuance of the order dated 15 March 2023 until a clarification
2
“Public Interest Litigation (L) No 2169 of 2023
H 3
Public Interest Litigation (L) No 8655 of 2023
IN RE: FELLING OF TREES IN AAREY FOREST (MAHARASHTRA) 395
[DR. DHANANJAYA Y CHANDRACHUD, CJI]
was sought from this Court. It is in view of the above factual background, A
that the application for clarification has been filed by MMRCL.
7. We have heard Mr Tushar Mehta, Solicitor General appearing
on behalf of MMRCL, Mr Dhruv Mehta, senior counsel appearing on
behalf of the Municipal Corporation, and Mr C U Singh and Mr Gopal
Sankaranarayanan, senior counsel appearing on behalf of the respondents. B
8. At the outset, the Court must take notice of the fact that when
the order dated 29 November 2022 was passed, it was on the specific
request of MMRCL that it should be permitted to pursue its application
before the Tree Authority for permission to fell 84 trees for the purpose
of the work of the ramp. The Court modified the earlier order of status C
quo which held the field, to the above extent. If the number of trees that
are required to be felled was in excess of the permission which was
granted by this Court, to move the Tree Authority to fell 84 trees, propriety
required that an application had to be moved before this Court for its
permission and for modification of its order dated 29 November 2022.
Instead, it appears from the record that though initially the application D
was made for felling 84 trees, subsequently, a stand was adopted that
actual number of trees would be in excess of what was originally
envisaged.
9. As a matter of fact, it would be necessary to refer to the affidavit
which was filed by the Chief Project Manager of MMRCL before the E
High Court of Judicature at Bombay in which the following averments
were incorporated:
“24) In the aforesaid and such other relevant background of facts,
in the humble submission of this Respondent, the number of
trees that are required to be felled is an aspect which is F
incidental to the proposal which is pending for consideration
before the first Respondent in respect of which the Hon’ble
Supreme Court has granted liberty to the present
Respondent to pursue, which is being done by the present
Respondent. I therefore say that not permitting the answering G
Respondents to prosecute the present application in issue
covering more number of trees over and above the number
of trees incidentally mentioned in the aforesaid order of the
Hon’ble Supreme court, in fact would amount to frustrating
H
396 SUPREME COURT REPORTS [2023] 6 S.C.R.
A the said order and/or preventing its implementation in its
true letter and spirit.
*** *** ***
26) I hasten to state that if the contention of the Petitioner is
accepted that will in fact amount to causing impediment in
B the effective implementation of the order of the Hon’ble
Supreme Court. At this juncture, it also will be apposite to
consider the well settled principle of law that the Judgment
of the Hon’ble Supreme Court and/or of this Hon’ble Court
cannot be read as a statute. I say that the Petitioner wants
C this Hon’ble Court to read the order of the Hon’ble Supreme
Court as a statute, which is impermissible.”
10. The above averments in the affidavit which was filed by
MMRCL indicate that it was well aware of the fact that the order of this
Court continued to operate. MMRCL sought to justify its application for
D felling of trees in excess of what was permitted by the specific directions
of this Court. Such an exercise was clearly not contemplated in the
order of this Court. We are constrained to observe that MMRCL has
made an attempt to overreach the jurisdiction of this Court.
11. The issue which, however, needs to be considered in the
E application for clarification is whether permission should be granted in
terms of the order which has been passed by the Superintendent of
Gardens.
12. In the IA for clarification, it has been submitted that subsequent
to the order of 29 November 2022, a joint inspection took place on 19
F December 2022 between the officers of the Municipal Corporation and
MMRCL since a period of approximately three years and ten months
covering four monsoon seasons had elapsed from the date of the previous
inspection which took place on 20 March 2019. It has been stated that in
the course of the joint inspection, it was found that some trees were
“missing/dead/fallen” and additional plants and trees had grown since
G the date of the previous inspection. Hence, it has been sought to be
urged that the updated number of affected trees were estimated at 185,
pursuant to which a public notice notice was issued by the Tree Authority
on 12 January 2023.
H
IN RE: FELLING OF TREES IN AAREY FOREST (MAHARASHTRA) 397
[DR. DHANANJAYA Y CHANDRACHUD, CJI]
13. The Solicitor General, while adverting to the contents of the A
IA, also submitted that a compilation of relevant documents was placed
on the record of this Court on 5 April 2023.
14. On the other hand, it has been submitted by Mr C U Singh and
Mr Gopal Sankaranarayanan that a survey was conducted in 2020 and,
as a matter of fact, it was based on the survey that MMRCL had sought B
permission to prune a certain number of trees and to fell 84 trees. Senior
counsel submitted that this Court permitted MMRCL to move the Tree
Authority specifically with reference to the proposal for 84 trees. In
other words, it has been urged before this Court that the fresh proposal
which was made before the Tree Authority after the order of this Court
dated 29 November 2022 was clearly not bona fide having due regard C
to the events which had transpired, resulting in the order of this Court.
15. It was improper on the part of MMRCL to move the Tree
Authority for the felling of any trees in excess of 84 trees. If circumstances
had transpired which led to a variation in the number of trees to be cut,
the only correct course of action would have been to move this Court. D
We are, hence, of the view that it would be necessary for the Court to
penalize MMRCL for its conduct. Having said that, the issue is as to
whether the permission which has been granted on 15 March 2023 should
be stayed by the Court, at the present stage. Any such direction will
have the consequences of bringing the public project to a standstill. Such E
a course of action would not be desirable. As the Court noted in its
previous order, substantial steps have already been taken by felling over
2000 trees for the purpose of the project. In this backdrop, we modify
the previous order by permitting MMRCL to act in compliance with the
order dated 15 March 2023. However, this shall be subject to the following
directions: F
(i) MMRCL shall, within a period of two weeks, deposit an
amount of Rupees Ten Lakhs with the Conservator of
Forests;
(ii) The Conservator of Forests shall ensure that all directions G
which have been contained in the previous orders of the
Tree Authority for afforestation have been duly complied
with;
(iii) The Conservator of Forests shall submit a report before
this Court indicating the status of compliance in regard to
H
398 SUPREME COURT REPORTS [2023] 6 S.C.R.
A the directions which have been issued up-to-date for
afforestation and for transplantation of trees; and
(iv) In order to enable this Court to have objective assistance
in regard to the compliance of the directions for
afforestation, we request the Director of IIT Bombay to
B depute a team for the purpose of verifying compliance. A
report shall accordingly be submitted before this Court within
a period of four weeks. The costs, charges and expenses
payable shall be borne by MMRCL.
16. The IA is accordingly disposed of.
C
Ankit Gyan IA disposed of.
(Assisted by : Mahendra Yadav, LCRA)
D
E
F
G
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.