IN RE FELLING OF TREES IN AAREY FOREST (MAHARASHTRA)versusIN RE FELLING OF TREES IN AAREY FOREST (MAHARASHTRA)
- Citation
- 2022 INSC 1235
- Decided
- 29 November 2022
- Disposal
- Disposed off
- Bench
- D Y CHANDRACHUD
Holding
The Court held that MMRCL may move the Tree Authority for permission to fell the 84 trees, and the Tree Authority may decide independently with or without conditions.
Summary
The Mumbai Metro Rail Corporation Limited (MMRCL) sought permission to fell an additional 84 trees in the Aarey forest for a ramp segment of its Metro Line‑3 car depot. Earlier, permissions had been granted for 2,185 trees (car depot) and 235 trees (ramp), of which 2,144 and 212 respectively had already been cut. The matter involved multiple interim applications, a Suo Moto writ, and competing arguments about environmental protection versus the public interest in completing a large‑scale metro project funded with billions of rupees. The State Government had oscillated between relocating the depot to Kanjur‑Marg and retaining it at Aarey, ultimately deciding on 21 July 2022 to allow the depot work to continue. The Court, weighing the substantial public investment, the fact that most required trees had already been felled, and the necessity of the ramp for the completed work, held that MMRCL may proceed to seek the Tree Authority’s permission to fell the 84 trees, leaving the Tree Authority free to impose conditions. The interim order preserving the status‑quo on tree felling was accordingly modified.
Issues considered
- Whether the Court should stay the application for felling an additional 84 trees in Aarey forest pending final disposal of the petitions.
- Whether any part of the Aarey car depot project should be restrained pending resolution of the environmental and public‑interest concerns.
Legislation cited
Subjects
Judgment
[2022] 14 S.C.R. 435 435
IN RE FELLING OF TREES IN AAREY FOREST A
(MAHARASHTRA)
(IA No. 169860 of 2022 )
In
(Suo Moto Writ (Civil) No. 2 of 2019)
B
NOVEMBER 29, 2022
[DR. DHANANJAYA Y CHANDRACHUD, CJI AND
PAMIDIGHANTAM SRI NARASIMHA, J.]
Metro Projects: Mumbai Metro Rail Corporation Limited
(MMRCL) – Aarey car depot for Metro Line – Court to consider as C
to whether it ought to permit the Tree Authority to decide application
filed by MMRCL for felling of 84 trees or alternatively, whether no
part of the Aarey car shed should be allowed to proceed pending
the final disposal of the proceedings – Held: In projects involving
large outlay of public funds, the Court cannot be oblivious to the
serious dislocation which would be caused if the public investment D
which has gone into the project were to be disregarded –
Considerations pertaining to environment are of concern because
all development must be sustainable – Having regard to the entirety
of the material before it, if the State Government has come to the
conclusion that the original decision to allow the Metro car depot E
for Metro Line-3 be located at Aarey has to be restored, it would
not be possible for the Court at the interim stage to stay the decision
– Moreover, a substantial number of trees pertaining to the area
which falls within the segment of the car shed and the ramp have
already been felled – 2,144 trees were felled in executing the work
pertaining to car depot, while, 212 trees were felled in connection F
with the work of the ramp – What is now sought is permission to
apply to the Tree Authority for the felling of 84 trees pertaining to
the ramp – Without a ramp the work which has already been
completed would be of no consequence and would be wholly
ineffective – Hence, having due regard to the circumstances, MMRCL G
should be permitted to pursue its application before the Tree
Authority for the permission to fell 84 trees for the purpose of the
ramp – However, the Tree Authority would be at liberty to take an
independent decision on the application and determine what
conditions, if any, should be imposed if it decides to grant its
permission. H
435
436 SUPREME COURT REPORTS [2022] 14 S.C.R.
A CIVIL ORIGINAL JURISDICTION: IA No. 169860 of 2022 in
Suo Moto Writ (Civil) No. 2 of 2019.
(UNDER ARTICLE 32 OF THE CONSTITUTION OF INDIA)
With
B IA Nos. 104736, 104886 of 2022 and 178233 of 2019 in SMW
(Civil) No. 2 of 2019, IA No. 105220 of 2022 in SLP (Civil) No. 14933 of
2019 and IA Nos. 107131 and 50314 of 2022 in SLP (Civil) No. 31178 of
2018.
Chander Uday Singh, Ms. Anitha Shenoy, Sr. Advs., Ms. Srishti
C Agnihotri, Ms. Sanjana Grace Thomas, Ms. Mantika Vohra, Ms. Namrata
Sarah Caleb, Amjid Maqbool, Ms. Prerna Priyadarshini, Advs for the
Petitioner.
Tushar Mehta, SG, Ms. Aishwarya Bhati, ASG, Maninder Singh,
Dhruv Mehta, Sr. Advs., Ms. Rukhmini Bobde, Chirag Shah, Kanu
D Aggarwal, Utsav Trivedi, Ms. Soumya Priyadarshini, Ankit Ambasta,
Amit Kumar Srivastava, Amlaan Kumar, Vishal Prasad, Ms. Ruchi Kohli,
S. S. Rebello, Ms. Archana Pathak Dave, Ms. Deepabali Dutta, Siddhanth
Kohli, Ishaan Sharma, Arvind Kumar Sharma, G. S. Makker, Siddharth
Dharmadhikari, Chirag Shah, Aaditya Aniruddha Pande, Akshay Shinde,
Abhikalp Pratap Singh, Bharat Bagla, Ms. Kirti Dadheech, Ashish Wad,
E Mrs. Tamali Wad, Sidharth Mahajan, Ajeyo Sharma, Shyam, Ms.
Anupama, M/s. J S Wad and Co, Tanmaya Agarwal, Ms. Pooja Dhar,
Pratul Pratap Singh, Shree Pal Singh, Advs. for the Respondent.
By Courts Motion.
The Judgment of the Court was delivered by
F
DR. DHANANJAYA Y CHANDRACHUD, CJI
1. On 15 April 2019, this Court, while considering Petition for
Special Leave to Appeal (Civil) No 31178 of 2018, declined to grant
interim relief in IA No 33819 of 2019. The reliefs which were sought in
G the application for interim relief were in the following terms:
“a) … stopping all activities being carried out by the Respondent
No-4 on the land in question inside Aarey Colony;
b) … directing the Respondents to carry out the activities for
setting up Metro Car depot at the alternative sites referred
H to in paragraph 3 of the present application;
IN RE FELLING OF TREES IN AAREY FOREST (MAHARASHTRA) 437
[DR. DHANANJAYA Y CHANDRACHUD, CJI]
c) … staying the operation of the observations made at page A
92 of the impugned order to the effect that Aarey Milk
Colony area cannot be referred to as forest; and
d) … any other order or further order or orders as this Hon’ble
Court may deem fit and proper in the circumstances of the
case.” B
2. Subsequently, on 7 October 2019, this Court, while entertaining
a Suo Moto Writ Petition1, passed an order recording the statement of
the Solicitor General appearing on behalf of the State of Maharashtra
that no further trees were being felled till the next date of listing.
3. On 5 August 2022, this Court directed that all the connected C
writ petitions and Special Leave Petitions could be listed for final disposal.
No specific interim directions were issued in view of the position of
Mumbai Metro Rail Corporation Limited2 that no further trees had been
felled since the order dated 7 October 2019 and none be cut till the next
date of hearing.
D
4. The position in regard to the permissions which have been sought
for the felling of trees in respect of the proposed depot at Aarey for
Metro Line – 3 has been summarized in a plan which has been placed
on the record by the Solicitor General. The position is elucidated below:
A Car Depot E
(i) Permission applied on 21 July 2017;
(ii) Permission granted by the Tree Authority on 13
September 2019;
(iii) Trees permitted to be cut – 2185; and
F
(iv) Actual number of trees cut – 2144.
B Ramp area
(i) Permission applied on 6 September 2017;
(ii) Permission granted by the Tree Authority on 6 July
2018; G
(iii) Trees permitted to be cut – 235; and
(iv) Actual number of trees cut – 212.
1
Suo Moto Writ Petition (Civil) No 2 of 2019
2
MMRCL H
438 SUPREME COURT REPORTS [2022] 14 S.C.R.
A C Shunting area
(i) Permission applied on 11 February 2019;
(ii) Total number of trees affected – 84; and
(iii) Grant of permission awaited.
B 5. The IA which has been moved by MMRCL3 is for permission
to enable it to move the Tree Authority for the felling of 84 trees required
for the purpose of proceeding with the shunting segment of the Aarey
car depot. For convenience of reference, the relief which has been sought
in IA moved by MMRCL is extracted below:
C “a) Direct/permit the Tree Authority to decide the application
dated 11.02.2019 filed by MMRCL pending before it and
pass final order thereof with respect to cutting of the 84
trees under The Maharashtra (Urban Areas) Protection and
Preservation of Trees Act 1975 located on Metro Car Shed
D Land at Aarey Colony admeasuring approximately 33
hectares for the Mumbai Metro Line-3 project in Mumbai
and permit, MMRCL to implement such decision of the Tree
Authority, as the case may be;”
6. Apart from the IA which has been moved by MMRCL, this
Court is seized of the following IAs:
E
i. IA No 104886 of 2022 in Suo Moto Writ Petition (Civil) No
2 of 2019seeking, inter alia,that (a) the order dated 21 July
2022 issued by the Urban Development Department of the
Government of Maharashtra be kept in abeyance as it
permits work on the car depot at Aarey, (b) the Government
F
of Maharashtra submit the Wildlifereport on the Aarey Car
Shed plot and to grant protection to wildlife on the said plot
and declare the area as a forest;
ii. IA No 178233 of 2019 in Suo Moto Writ Petition (Civil) No
2 of 2019 seeking inter alia,the issuance of directions to
G the Government of Maharashtra to declare Aarey as a forest
and direct that no trees be cut;
iii. IA No 107131 and IA 50314 of 2022 in Special Leave
Petition (Civil) No 31178 of 2018 seeking, inter alia, a
H 3
IA No 169860 of 2022 in Suo Moto Writ Petition (Civil) No 2 of 2019
IN RE FELLING OF TREES IN AAREY FOREST (MAHARASHTRA) 439
[DR. DHANANJAYA Y CHANDRACHUD, CJI]
direction restraining the respondents from carrying out all A
work of construction within the 33 hectares area implicating
the Aarey car project;
iv. IA No 105220 of 2022 in Special Leave Petition (Civil) No
14933 of 2019 for restraining the respondents from carrying
out any consequential activities, including clearing of plants, B
excavation of vegetation or proceeding with any construction.
7. In order to appreciate the salient facts insofar as they pertain
to the IAs before this Court, it would be appropriate, at this stage, to
advert briefly to the course of events.
8. On 6 January 2021, the Government of Maharashtra constituted C
a committee chaired by the Chief Secretary for examining whether the
proposed car depot at Aarey should be realigned and relocated. The
Committee submitted its report on 21 January 2021. The Committee
was of the considered view that the location of the car depot at Aarey
should be realigned so that an integrated car depot would be set up both
D
for Metro Lines – 3 and 6 at Kanjurmarg. The report of the Committee
was accepted by the State Government on 23 March 2021.
9. On 17 March 2022, the Union Government in the Ministry of
Housing and Urban Affairs addressed a communication to the Chief
Secretary of the Government of Maharashtra, following a meeting which
E
was convened on 23 September 2021 between the Ministry and the
officials of the State Government “to discuss the Aarey depot issue which
is seriously hampering the progress of Metro Line-3 project”. The letter
recorded that a decision was taken that Delhi Metro Rail Corporation4
and M/s SYSTRA, the consultant appointed by MMRDA, would hold a
meeting to sort out technical issues in the event that the depot was shifted F
to Kanjurmarg. Thereafter, following the meetings between DMRC and
SYSTRA, DMRC submitted a report on 11 February 2022. Both DMRC
and SYSTRA have agreed that there are ‘inherited’ operational and
maintenance constraints in the proposal to have a common depot for
two or more lines at Kanjurmarg. Some of the major observations in the
report are summarized in the communication dated 17 March 2022 and G
are extracted below:
“(i) The simulation exercise done by M/s SYSTRA is incomplete
as no simulation internal to depot has been done. M/s
4
DMRC H
440 SUPREME COURT REPORTS [2022] 14 S.C.R.
A SYSTRA had informed that simulation internal to depot may
require involvement of signalling contractor, which was
beyond their scope of work. Thus, it could not be checked
by DMRC that proposed plan of induction of trains from
depot could really materialise or not. DMRC has recorded
their own experience that inducting trains from the depot
B
consistently at a frequency of 4 minutes continuously for 3
or more hours is a challenging task.
(ii) There is a compromised time of maintenance window due
to running of Line-3 trains for 7.5 km on Line-6 network
upto Kanjurmarg. This will also have an adverse impact on
C restoration time in the event of failure of Line-3 train during
regular operation period.
(iii) There is sub optimal utilization of trains as at least two
trains are to be kept as hot standby at SEEPZ village station.
D (iv) 100% punctual operation throughout the trips all the time
in a day is rarely possible in real life operations as lot of
factors affect train movement.Any deviation in train
movement will lead to detention at L-3 & 6 connections
while transferring of trains between L-3 & 6. Thus, the
detention of trains mid-section seems real and unavoidable.
E
(v) There is a requirement of same signalling system from the
Line-3 supplier for Line-6 and thus related compulsions.”
10. In the above backdrop, the communication of the Union
Ministry of Housing and Urban Affairs noted that the proposed integration
of two lines at SEEPZ village station would be a permanent risk to reliable
F
train operations of both the lines. DMRC’s report had suggested that the
decision to adopt an integrated depot for Metro Lines – 3 and 6 should
be taken only if it is absolutely unavoidable even with possible mitigation
measures in the present plans at Aarey. The communication also records
that the conclusion of the report of the Committee chaired by the Chief
G Secretary to the Government of Maharashtra that the current land and
design of the depot at Aarey would be insufficient to cater to the project
design life requirement of Line-3, thereby necessitating an alternative
location at Kanjurmarg is factually incorrect. In the opinion of the Union
Ministry of Housing and Urban Affairs, the land at Aarey is sufficient to
meet the current and projected requirement up to 2055 and, hence, it
H
IN RE FELLING OF TREES IN AAREY FOREST (MAHARASHTRA) 441
[DR. DHANANJAYA Y CHANDRACHUD, CJI]
would not be prudent to shift the location to Kanjurmarg at the present A
stage of the project. Moreover, it has been stated that:
(i) The project is in a significantly advanced stage of completion;
(ii) The combined depot plans will introduce operational and
maintenance bottlenecks in the functioning of the network
for the entire lifecycle of a high capacity metro line; and B
(iii) While the land at Aarey is free from encumbrances, the
land at Kanjurmarg is under litigation.
11. Consequently, the State Government was requested to
reconsider its decision to shift the depot of Line-3 from Aarey colony to C
Kanjurmarg and to allow the restarting of the depot work of Line-3 at
Aarey colony for expeditious completion of the project in public interest.
12. Responding to the above communication, the State
Government has on 21 July 2022 taken a decision to allow the work of
the Metro Car Depot at Aarey to proceed.
D
13. Appearing on behalf of MMRCL, the Solicitor General has
highlighted that:
(i) The overall cost of the Metro project ranges in the vicinity
of Rs 23,000 crores, which is now projected to escalate to
Rs 37,000 crores; E
(ii) Nearly 95 per cent of the project work has been completed;
(iii) Permission had already been granted for the felling of 2,185
trees envisaged in the segment pertaining to the car depot
and 235 trees for the segment pertaining to the ramp, while,
permission has been sought of this Court to move the Tree F
Authority for the felling of 84 trees which would be
occasioned in the segment pertaining to shunting; and
(iv) Having regard to the overall contours of public interest
bearing on the project, the orders passed by this Court on 7
October 2019 and 5 August 2022 may be clarified to the G
extent that MMRCL may be allowed to move the Tree
Authority for the grant of felling permission.
14. While opposing these submissions, Mr C U Singh and Ms
Anitha Shenoy, senior counsel, have urged that apart from rejecting the
relief which has been sought by MMRCL, there are valid grounds for this H
442 SUPREME COURT REPORTS [2022] 14 S.C.R.
A Court to not allow the decision of the State Government which was
taken on 21 July 2022 to allow the car depot project at Aarey to proceed.
It has been urged that:
(i) The decision which has been taken on 21 July 2022 amounts
to a reversal of a considered view which was taken by the
B State Government on 23 March 2021, while accepting the
report of the Expert Committee chaired by the Chief
Secretary dated 21 January 2021;
(ii) The decision of the Committee was based on cogent
considerations, including the fact that the capacity of the
C proposed car shed at Aarey would be exhausted in 2031
leading to a further need for the felling of approximately
1000 trees should an expansion proposal be taken up in the
future;
(iii) Once a considered decision was taken by the State
D Government to accept the report of the Committee chaired
by the Chief Secretary, there was no valid basis to rescind
the decision in the absence of scientific material which
would indicate that a contrary view was more desirable;
and
E (iv) The area in question is sensitive ecologically having due
regard to its proximity to the Sanjay Gandhi National Park,
which is rich in bio-diversity.
15. Ms Anitha Shenoy, senior counsel, while buttressing the above
submissions, urged that the project involving the construction of a Metro
F Line has high pollution potential falling within the red category. Moreover,
it was submitted that on 12 October 2020, a notification has been issued
under which 286 hectares of land have been notified as forests. Senior
counsel submitted that, in this backdrop, the decision of the State
Government to the effect that full capacity utilization of the car shed at
G Aarey would be reached in 2031 necessitated the realignment of the car
shed at Kanjurmarg. Hence, it was urged that there was no valid basis
for the State Government to rescind its decision.
16. While analyzing the merit of the rival submissions, it must, at
the outset, be noted that the validity of the judgment dated 26 October
H 2018 and of the two judgments dated 4 October 2019 would fall for
IN RE FELLING OF TREES IN AAREY FOREST (MAHARASHTRA) 443
[DR. DHANANJAYA Y CHANDRACHUD, CJI]
determination when the Special Leave Petitions are taken up for final A
disposal.
17. This Court, by an order dated 15 April 2019, declined to grant
interim relief. At that stage, when the Court proceeded to decline interim
relief, the State Government had filed its affidavit indicating the inherent
public interest involved in the execution of the project. In regard to the B
alternate site, the affidavit of the State Government explained that in
November 2011, a detailed project report for the Metro corridor had
been prepared. A six-MemberTechnical Committee chaired by the
Metropolitan Commissioner, MMRDA was constituted to consider
alternate sites. The Technical Committee submitted its report on 11 August
2015 and considered the various sites, including the following: C
“a) Backbay Reclamation, Colaba
b) Mumbai Port Trust
c) Mahalaxmi Race Course
D
d) Dharavi
e) Bandra Kurla Complex
f) Mumbai University, Kalina
g) Aarey Colony
E
h) Sariput Nagar
i) Kanjur Marg.”
18. In its affidavit, the State Government submitted that after
considering the options above, the Committee found that three sites at or
beyond the terminal points meet the requirements. Thereafter, the F
Technical Committee submitted its report recommending as follows:
“i) The Metro-Ill car-depot be located at Kanjur Marg, with
only a small stabling unit at Aarey Depot;
(ii) In case the land was not made available at Kanjur Marg
G
within a period of three months then the car-depot was
proposed to be located at Aarey Colony within a 20.82
hectare area; and
(iii) Measures would have to be taken to mitigate environment
damage at Aarey Colony.”
H
444 SUPREME COURT REPORTS [2022] 14 S.C.R.
A 19. The report of the Technical Committee was accepted by the
State Government on 16 October 2015. The State Government explained
the steps which were taken thereafter pursuant to the report of the
Technical Committee. This Court, after having considered the application
for interim relief, considered it appropriate to decline relief.
B 20. Now, it is in this backdrop that this Court must consider as to
whether it ought topermit the Tree Authority to decide the application
dated 11.02.2019 filed by MMRCL for felling of 84 trees. Alternatively,
there is a wider relief which has been sought in the companion IAs that
no part of the Aarey car shed should be allowed to proceed pending the
final disposal of the proceedings.
C
21. In such projects involving large outlay of public funds, the
Court cannot be oblivious to the serious dislocation which would be caused
if the public investment which has gone into the project were to be
disregarded. Undoubtedly, considerations pertaining to the environment
are of concern because all development must, it is well settled, be
D
sustainable.
The State Government which had taken a decision in the first
place to accept the Technical Committee report in 2015, later on, changed
its view while deciding upon the realignment of the Metro car project at
Kanjurmarg. Subsequently, various aspects were pointed out to the State
E Government by the communication dated 17 March 2022 of the Union
Ministry of Housing and Urban Affairs. At this stage, it cannot be gainsaid
that the factors which have been set out in the communication dated 17
March 2022 cannot be disregarded. Having regard to the entirety of the
material before it, if the State Government has come to the conclusion
F that the original decision to allow the Metro car depot for Metro Line-3
be located at Aareyhas to be restored, it would not be possible for the
Court at the interim stage to stay the decision.
22. Moreover, it must also be noted that a substantial number of
trees pertaining to the area which falls within the segment of the car
G shed and the ramp have already been felled. Consequently, this Court
was apprised on 7 October 2019 and 5 August 2022 that no further trees
were required to be felled. As already noted earlier, 2,144 trees were
felled in executing the work pertaining to car depot, while, 212 trees
were felled in connection with the work of the ramp. What is now sought
is permission to apply to the Tree Authority for the felling of 84 trees
H
IN RE FELLING OF TREES IN AAREY FOREST (MAHARASHTRA) 445
[DR. DHANANJAYA Y CHANDRACHUD, CJI]
pertaining to the ramp. It needs no emphasis that without a ramp the A
work which has already been completed would be of no consequence
and would be wholly ineffective. Hence, having due regard to the above
circumstances, we have arrived at the conclusion that MMRCL should
be permitted to pursue its application before the Tree Authority for the
permission to fell 84 trees for the purpose of the ramp. We clarify that
B
the Tree Authority would be at liberty to take an independent decision on
the application and determine what conditions, if any, should be imposed
if it decides to grant its permission.
23. The order of this Court, which has the effect of directing the
preservation of status quo on the felling of trees, shall accordingly stand
modified to the above extent thereby permitting the MMRCL to move C
the Tree Authority on its application for felling of 84 trees. The state
government would be at liberty to proceed further.
24. The IAs are accordingly disposed of.
25. The entire batch of petitions would be listed for hearing and D
final decision on 7 February 2023.
Devika Gujral IAs disposed of.
(Assisted by : Shubhanshu Das, LCRA)