Created byFuzzy Cloud

Supreme Court of India

HLV LIMITED (FORMERLY KNOWN AS HOTEL LEELAVENTURE PVT. LTD.)versusPBSAMP PROJECTS PVT. LTD.

Citation
2025 INSC 1148
Decided
24 September 2025
Disposal
Appeal(s) allowed

Holding

The arbitral award, which incorporated the parties’ agreed 21% simple interest and made no provision for compounding, fulfills the requirements of Sections 31(7)(a) and (b), thereby barring any claim for interest upon interest.

Summary

The parties entered into a memorandum of understanding in 2014 for the sale of land, with the respondent paying an advance of Rs.15.5 crore. The MoU was terminated in 2024 and the dispute was referred to arbitration, where the tribunal awarded the advance amount with simple interest at 21% per annum from the date of disbursement until repayment. The appellant paid Rs.44.42 crore in installments, claiming full satisfaction of the award, while the respondent sought additional compound interest under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996. The High Court set aside the executing court’s order and remanded the matter, leading to a special leave appeal. The Supreme Court held that the award, which incorporated the parties’ agreed simple interest and made no provision for compounding, fulfills the requirements of Sections 31(7)(a) and (b), precluding any claim for interest upon interest. Consequently, the Supreme Court restored the executing court’s order and allowed the appeal.

Issues considered

  • Whether the decree holder is entitled to interest upon interest (compound interest) under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996.
  • Whether the interest awarded in the arbitral award pursuant to the MoU satisfies the requirements of Sections 31(7)(a) and (b) of the Act.
  • Whether the High Court was justified in setting aside the executing court’s order and remanding the execution proceedings.

Legislation cited

Headnote

Issue for Consideration Whether in the facts and circumstances of the case, the decree holder (respondent) would be entitled to interest upon interest in terms of s.31(7)(b), Arbitration and Conciliation Act, 1996 or the interest awarded by the arbitral tribunal in of the memorandum of understanding (MoU) entered into between the parties i.e. between the appellant and the respondent fulfil the requirement of s.31(7)(a) and (b) of the said Act. Headnotes† Arbitration and Conciliation Act, 1996 – s.31(7)(a), (b) – High Court set aside the

Subjects

Section 31(7)(a)Section 31(7)(b)Arbitration and Conciliation Act, 1996Interest upon interestCompound interestStage of executionMemorandum of understanding (MoU)Interest in terms of MoUTermination of MoUArbitral tribunal bound by MoUInterest till the date of repaymentAdditional or compound interestPost-award interestParty autonomyExecuting Court

Judgment

                 [2025] 9 S.C.R. 1378 : 2025 INSC 1148

                            HLV Limited
           (Formerly Known as Hotel Leelaventure Pvt. Ltd.)
                                v.
                      PBSAMP Projects Pvt. Ltd.
                      (Civil Appeal No. 12234 of 2025)
                              24 September 2025
                 [Manoj Misra and Ujjal Bhuyan,* JJ.]


                            Issue for Consideration
       Whether in the facts and circumstances of the case, the decree
       holder (respondent) would be entitled to interest upon interest in
       terms of s.31(7)(b), Arbitration and Conciliation Act, 1996 or the
       interest awarded by the arbitral tribunal in the award in terms of
       the memorandum of understanding (MoU) entered into between
       the parties i.e. between the appellant and the respondent fulfil the
       requirement of s.31(7)(a) and (b) of the said Act.

                                   Headnotes†
       Arbitration and Conciliation Act, 1996 – s.31(7)(a), (b) – High
       Court set aside the order of the Executing Court rejecting the
       petition filed by the respondent-decree holder for enforcement
       of the arbitral award on the ground that respondent is not
       entitled to compound interest and that the amount paid by
       the appellant-judgment debtor to the respondent was in full
       satisfaction of the award – Respondent, if entitled to interest
       upon interest in terms of s.31(7)(b) or the interest awarded by
       the arbitral tribunal in the award in terms of the MoU entered
       into between the parties fulfil the requirement of s.31(7)(a)
       and (b):
       Held: 1.1 Clause 6(b) of the MoU expressly provided that in the
       event of termination of the MoU, the appellant must refund all
       advances with interest at the rate of 21% per annum from the
       respective dates of disbursement till repayment – Thus, in the light
       of the express provision contained in clause (a) of sub-section (7)
       of s.31, the arbitral tribunal awarded interest in terms of the MoU
       from the date of the cause of action till the date of repayment –
       As the arbitral tribunal had expressly provided interest till the date

* Author
[2025] 9 S.C.R.                                                                1379

          HLV Limited (Formerly Known as Hotel Leelaventure
                Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.

     of repayment, question of additional or compound interest under
     clause (b) of sub-section (7) of s.31 would not arise. [Para 29]
     1.2 Arbitral tribunal in its award complied with the MoU agreed by
     and between the parties – Thus, it exercised its discretion within
     the overall framework of s.31(7) aligning with the legislative intent
     that the award, rather than the statutory default, should govern the
     parties, more so in a case as in the present one where the parties
     themselves made provision for interest throughout. [Para 29]
     1.3 Reliance placed by the respondent on Hyder Consulting case
     to claim post-award interest is misplaced – That principle would
     apply only when the arbitral tribunal leaves a matter unqualified
     or is silent – In the present case, the arbitral tribunal bound by the
     MoU and exercising its statutory discretion had already specified the
     interest rate (21% per annum) and the duration (until repayment).
     [Para 30]
     1.4 The MoU did not stipulate compounding of interest; the arbitral
     tribunal did not award compound interest; therefore, respondent
     cannot at the stage of execution seek to introduce claim of
     compound interest by drawing on general principles. [Para 31]
     1.5 High Court not justified in setting aside the order of the executing
     court and remanding the matter for fresh determination – Impugned
     judgment set aside – Order of the executing court restored.
     [Paras 32, 33]

     Arbitration and Conciliation Act, 1996 – s.31(7)(a), (b) – ‘sum’;
     ‘unless the award otherwise directs’:
     Held: 1.1 From a conjoint analysis of s.31(7)(a) and s.31(7)(b), it
     is discernible that insofar award of interest from the date on which
     the cause of action arose till the date of the award is concerned,
     the legislative intent is that the parties possess the autonomy to
     determine the interest and the rate of interest for the aforesaid
     period – Clause (a) i.e. discretion of the arbitral tribunal to award
     interest is subject to agreement by and between the parties –
     Therefore, party autonomy takes precedence over the discretion
     of the arbitral tribunal. [Para 20]
     1.2 However, clause (b) is subject to award of interest by the
     arbitral tribunal – As per clause (b), the ‘sum’ directed to be paid
     under an arbitral award shall carry interest at the rate of 18% per
     annum from the date of the award to the date of payment ‘unless
     the award otherwise directs’ – Therefore, this provision is subject
1380                                                          [2025] 9 S.C.R.

                         Supreme Court Reports


    to award of interest by the arbitral tribunal – If it awards interest,
    then the same shall be applicable from the date of the award till the
    date of payment; if not, then the ‘sum’ as adjudged under clause
    (a) shall carry interest at the rate of 18%. [Para 20]

                             Case Law Cited
    Hyder Consulting (UK) Limited v. Governor, State of Orissa [2014]
    14 SCR 1029 : (2015) 2 SCC 189 – held inapplicable.
    Morgan Securities and Credits Private Limited v. Videocon Industries
    Limited [2022] 9 SCR 819 : (2023) 1 SCC 602; Delhi Airport Metro
    Express Private Limited v. Delhi Metro Rail Corporation [2022] 3
    SCR 716 : (2022) 9 SCC 286 – relied on.
    North Delhi Municipal Corporation v. S.A. Builders Limited [2024]
    12 SCR 1581 : (2025) 7 SCC 132; State of Haryana v. S.L. Arora,
    [2010] 2 SCR 297 : (2010) 3 SCC 690 – referred to.

                                List of Acts
    Arbitration and Conciliation Act, 1996.

                             List of Keywords
    Section 31(7)(a), (b), Arbitration and Conciliation Act, 1996;
    Interest upon interest; Compound interest; Stage of execution;
    Memorandum of understanding (MoU); Interest in terms of MoU;
    Termination of MoU; Arbitral tribunal bound by MoU; Interest till the
    date of repayment; Additional or compound interest; Post-award
    interest; Party autonomy; Executing Court.

                            Case Arising From
    CIVIL ORIGINAL JURISDICTION: Civil Appeal No. 12234 of 2025
    From the Judgment and Order dated 22.04.2024 of the High Court
    for The State of Telangana at Hyderabad in CRP No. 60 of 2024

                        Appearances for Parties
    Advs. for the Appellant:
    Dama Seshadri Naidu, Hemandranath Reddy, Sr. Advs., M Srinivas
    R Rao, M.V. Mukunda, Abid Ali Beeran P, Sarath S Janardanan,
    Saswat Adhyapak, Ms. Namita Kumari.
[2025] 9 S.C.R.                                                     1381

          HLV Limited (Formerly Known as Hotel Leelaventure
                Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.

     Advs. for the Respondent:
     P.b. Suresh, Sr. Adv., Mayank Jain, Madhur Jain, Ms. Aakriti
     Dhawan, Arpit Goel, Deepak Jain, Parmatma Singh.

                Judgment / Order of the Supreme Court

                               Judgment

     Ujjal Bhuyan, J.

     Leave granted.
2.   This appeal by special leave is directed against the judgment and
     order dated 22.04.2024 passed by the High Court for the State of
     Telangana at Hyderabad (High Court) in Civil Revision Petition No.
     60 of 2024 (PBSAMP Projects Private Limited Vs. HLV Limited). By
     the impugned judgment and order, the Division Bench of the High
     Court set aside the order dated 02.11.2023 passed by the Principal
     Special Court in the cadre of District Judge for trial and disposal
     of commercial disputes at Hyderabad (referred to hereinafter as
     ‘the Executing Court’) in CEP No. 05 of 2021 rejecting the petition
     filed by the respondent for enforcement of the arbitral award dated
     08.09.2019 on the ground that respondent is not entitled to compound
     interest and that the amount paid by the judgment debtor (appellant)
     to the decree holder (respondent) i.e. Rs. 44,42,05,254.00 was in
     full satisfaction of the award.
3.   Question for consideration in this appeal is whether in the facts and
     circumstances of the case, the decree holder (respondent) would
     be entitled to interest upon interest in terms of Section 31(7)(b) of
     the Arbitration and Conciliation Act, 1996 or the interest awarded
     by the arbitral tribunal in the award dated 08.09.2019 in terms of
     the memorandum of understanding dated 09.04.2014 entered into
     between the parties i.e. between the appellant and the respondent
     fulfil the requirement of Section 31(7)(a) and (b) of the said Act?
4.   The above question arises in the following factual backdrop.
5.   The two parties had entered into a memorandum of understanding
     (MoU) on 09.04.2014. The MoU was with regard to sale and transfer of
     land situated at Road No. 10, Banjara Hills, Hyderabad admeasuring
     approximately 3 acres and 28 guntas. The details of the land are
     mentioned in the schedule to the MoU.
1382                                                         [2025] 9 S.C.R.

                         Supreme Court Reports


     5.1. It may be mentioned that appellant as the vendor had acquired
          absolute ownership of the schedule land under different sale
          deeds which was to be used for construction of a five star hotel
          but for various reasons did not go ahead with the project and
          instead decided to sell the land to the respondent. Under the
          aforesaid MoU, respondent paid a sum of Rs. 15.5 crores as
          advance to the appellant. As differences arose between the
          parties, the MoU was terminated on 09.10.2024 whereafter
          the dispute was referred to arbitration. The arbitral tribunal
          comprised of three arbitrators: Mr. Justice TNC Rangarajan
          being nominated by the claimant i.e. the respondent and Mr.
          Justice A Kulasekaran being nominated by the appellant. The
          two arbitrators in turn nominated Justice Arijit Pasayat as the
          presiding arbitrator.
6.   The arbitral tribunal passed an award dated 08th September, 2019,
     the operative portion of which reads as under:
          The claimant is entitled to Rs. 15.5 crores with interest
          at 21% p.a. from the date it was given to the date it is
          repaid. The respondent has kept the documents of title
          in escrow for security purposes The respondent has
          admitted liability for Rs. 10 crores and disputed only the
          sum of Rs. 5.5 crores. Hence we direct that the respondent
          pay immediately the sum of Rs. 10 crores with interest
          The escrow arrangement will be limited to the disputed
          amount of Rs. 5.5 crores only. The claimant shall give the
          consent letter for release of the balance of Rs. 5.5 crores
          simultaneously with the tender of the amount by way of DD
          or certified cheque, NEFT/RTGS to a designated account
          by the respondent within 3 months from the date of the
          award. The amount will carry interest at 21% p.a. from the
          date it was received till the date of exchange of the DD,
          certified cheque, NEFT/RTGS with the consent letter. The
          respondent’s counterclaim stands rejected. In the peculiar
          facts of the case, it is directed that the parties shall bear
          their respective costs.
7.   Thus, the arbitral tribunal awarded Rs. 15.5 crores to the claimant
     (respondent) with interest at the rate of 21 percent per annum from
     the date it was given to the date it is repaid. Appellant filed a petition
[2025] 9 S.C.R.                                                        1383

            HLV Limited (Formerly Known as Hotel Leelaventure
                  Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.

      under Section 34 of the Arbitration and Conciliation Act, 1996 (briefly,
      ‘the 1996 Act’ hereinafter) before the learned Special Court for trial
      and disposal of commercial disputes at Hyderabad (Special Court)
      for setting aside of the award which was registered as COP No. 118
      of 2019. Learned Special Court vide the judgment and order dated
      19.03.2021 dismissed COP No. 118 of 2019.
8.    It appears that there was no further challenge to the award. Thus,
      the arbitral award dated 08.09.2019 attained finality.
9.    Thereafter, respondent filed execution petition CEP No. 05 of 2021
      before the executing court for execution of the arbitral award dated
      08.09.2019.
10. In the course of hearing, the judgment debtor (appellant) paid a total
    of Rs. 44,42,05,254.00 on various dates and in various amounts
    starting from 22.07.2022 to 31.07.2023 which according to it was in
    full compliance to the award including interest.
11. Decree holder i.e. the respondent filed a calculation sheet before
    the executing court claiming compound interest over and above the
    rate of interest i.e. 21 percent as awarded by the arbitral tribunal.
    The executing court referred to Section 31(7) of the 1996 Act as well
    as to the decision of this Court in Hyder Consulting (UK) Limited
    Vs. Governor, State of Orissa1, and thereafter held that claim of the
    decree holder for compound interest on the awarded amount was
    not sustainable. The executing court cannot go beyond the award
    passed by the arbitral tribunal. The decree holder is not entitled for
    compound interest as claimed. The amount paid by the judgment
    debtor to the decree holder i.e. Rs. 44,42,05,254.00 was in full
    satisfaction of the arbitral award. Accordingly, by the order dated
    02.11.2023 executing court closed CEP No. 05 of 2021.
12. This order came to be assailed by the respondent before the High
    Court in a proceeding under Article 227 of the Constitution of India
    which was registered as Civil Revision Petition No. 60 of 2024.
    By the impugned judgment and order dated 22.04.2024, the High
    Court was of the view that the executing court had reached the
    conclusion in a cryptic and cavalier manner. Therefore, the order
    dated 02.11.2023 was set aside and the matter was remitted back


1    (2015) 2 SCC 189
1384                                                        [2025] 9 S.C.R.

                         Supreme Court Reports


     to the executing court to reconsider the issue of interest under the
     award dated 08.09.2019 to the respondent though clarifying that it
     had not expressed any opinion on the merit of the claim.
13. Aggrieved, the related special leave petition came to be filed. This
    Court by order dated 14.05.2024 had issued notice and in the
    meanwhile, had stayed the order of remand.
14. Mr. Hemendranath Reddy, learned senior counsel for the appellant,
    at the outset, submits that the award neither granted compound
    interest nor granted post-award interest. Arbitral tribunal had awarded
    composite interest i.e. simple interest of 21% per annum from the
    dates payment became due to the date of repayment. Respondent
    did not challenge this part of the award. The award has since attained
    finality. Therefore, it is not open to the respondent now to claim either
    compound interest or post-award interest on the principal amount.
     14.1. Mr. Reddy, learned senior counsel, submits that the executing
           court had specifically reasoned that the award had only granted
           21% simple interest from the date when the cause of action
           arose till payment. For this entire period, the arbitral tribunal
           awarded simple interest at the rate of 21%. Neither any
           compound interest was granted nor any post-award interest.
           Therefore, respondent is not entitled to compound interest. This
           aspect of the matter was overlooked by the High Court which
           also did not consider the fact that the calculation submitted by
           the appellant was accepted by the executing court after due
           consideration of all the facts and circumstances of the case.
     14.2. According to him, the reasoning given by the executing court
           cannot be faulted. Calculation offered by the appellant having
           been accepted by the executing court with sufficient reasons,
           the High Court was not justified in setting aside the order
           passed by the executing court and remanding the matter back
           for fresh consideration.
     14.3. Learned senior counsel submits that by 31.07.2023, the entire
           amount of Rs. 44,42,05,254.00 was paid by the appellant to
           the respondent in full compliance to the award which included
           the interest quotient as well. No further amount remains to
           be paid. Therefore, the executing court rightly closed the
           execution case.
[2025] 9 S.C.R.                                                      1385

           HLV Limited (Formerly Known as Hotel Leelaventure
                 Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.

     14.4. It is submitted that respondent in its claim before the arbitral
           tribunal had itself calculated the interest portion at the rate
           of 21% simple interest from the date the payment became
           due till actual payment. As such, it is impermissible for the
           respondent to now turn around and claim compound interest
           i.e. post-award interest over and above the 21% interest agreed
           upon by the parties and awarded by the arbitral tribunal. Such
           claim virtually amounts to modification of the award which is
           impermissible at the stage of execution.
     14.5. It is also submitted that Section 31(7)(a) and Section 31(7)(b)
           of the 1996 Act has no application to the facts of the present
           case as the arbitral tribunal itself awarded composite interest
           covering the entire period from the time the cause of action
           arose till payment. Arbitral tribunal did not award any post-
           award interest. Therefore, the decision of this Court in Hyder
           Consulting (UK) Limited (supra) would have no application.
     14.6. Placing reliance on a subsequent decision of this Court in
           Morgan Securities and Credits Private Limited Vs. Videocon
           Industries Limited2, learned senior counsel submits that this
           judgment has clarified the proposition laid down in Hyder
           Consulting (supra) by holding that an arbitral tribunal has the
           discretion to grant post-award interest either on the whole ‘sum’
           or part of it. The decision in Hyder Consulting (supra) would
           only be applicable when the award is silent about payment
           of interest and not when the award clearly spells the method
           of paying interest including future interest. In fact, Morgan
           Securities (supra) has clarified the law laid down in Hyder
           Consulting (supra) by holding that when the award specifies
           the method of paying future interest, then Hyder Consulting
           (supra) would have no application. Therefore, the High Court
           clearly fell in error when it held that Morgan Securities (supra)
           would not apply to the facts of the case and remanding the
           matter back to the executing court for fresh decision placing
           reliance on Hyder Consulting (supra).
     14.7. Learned senior counsel finally submits that High Court was
           not justified in summarily dismissing the order of the executing
           court as passed in a cryptic and cavalier manner.


2   (2023) 1 SCC 602
1386                                                      [2025] 9 S.C.R.

                        Supreme Court Reports


     14.8. He, therefore, submits that view taken by the High Court is not
           correct. The same is required to be set aside and quashed.
           Consequently, the appeal should be allowed by restoring the
           order of the executing court.
15. Per contra, Mr. P.B. Suresh, learned senior counsel for the respondent
    submits that the impugned order does not determine any inter se rights
    of the parties. It is only an order of remand with the observation that
    the High Court has not expressed any opinion on merit. Therefore,
    such an order calls for no interference, that too, under Article 136
    of the Constitution of India.
     15.1. As and when the executing court decides the issue finally,
           parties to the lis would have the right to take recourse to the
           remedy as provided under the law. In such circumstances,
           filing of the special leave petition by the appellant is clearly
           an abuse of the process of the court.
     15.2. As per the interest calculation sheet as on 31.07.2023 filed by
           the respondent before the executing court, appellant was liable
           to pay Rs. 57,74,68,490.00. As against this, appellant has only
           paid to the respondent Rs. 44,42,05,254.00 till 31.07.2023.
           Therefore, an amount of more than Rs. 13 crores still remains
           outstanding. It is required to be paid by the appellant to the
           respondent.
     15.3. Learned senior counsel for the respondent submits that the
           interest for the prior period till the date of the award has to
           be capitalized which will then be the ‘sum’ in terms of Section
           31(7)(a) of the 1996 Act. On that basis, the judgment debtor
           is entitled to 21% post-award interest on the above ‘sum’ till
           the date of payment. In addition to placing reliance on the
           decision of this Court in Hyder Consulting (supra), learned
           senior counsel submits that the issue raised by the respondent
           is no longer res integra. The decision in Hyder Consulting has
           since been explained and reiterated by this Court in North
           Delhi Municipal Corporation Vs. S.A. Builders Limited3. As
           per the said judgment, respondent is entitled to compound
           interest under Section 31(7)(b) of the 1996 Act on the ‘sum’
           determined in terms of Section 31(7)(a) of the said Act.


3   (2025) 7 SCC 132
[2025] 9 S.C.R.                                                            1387

          HLV Limited (Formerly Known as Hotel Leelaventure
                Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.

     15.4. He finally submits that the civil appeal is devoid of any merit
           and is, as such, liable to be dismissed.
16. Submissions made by learned counsel for the parties have received
    the due consideration of the Court.
17. At the outset, let us examine Section 31(7) of the 1996 Act which
    at the relevant point of time read thus:

                    31. Form and contents of arbitral award.
                    (7)(a) Unless otherwise agreed by the parties, where
                    and insofar as an arbitral award is for the payment
                    of money, the Arbitral Tribunal may include in the
                    sum for which the award is made interest, at such
                    rate as it deems reasonable, on the whole or any
                    part of the money, for the whole or any part of the
                    period between the date on which the cause of action
                    arose and the date on which the award is made.
                    (b) A sum directed to be paid by an arbitral award
                    shall, unless the award otherwise directs, carry
                    interest at the rate of eighteen per centum per annum
                    from the date of the award to the date of payment.
     17.1. From a perusal of the aforesaid provision, it is seen that
           Section 31(7) has got two clauses: clause (a) and clause (b).
           Clause (a) starts with the expression ‘unless otherwise agreed
           by the parties’. Thereafter, it says that where an award is for
           payment of money, the arbitral tribunal may include in the sum
           for which the award is made interest at such rate as it deems
           reasonable on the whole or any part of the money and for the
           whole or any part of the period from the date when the cause
           of action arose to the date when the award is made. In other
           words, clause (a) empowers the tribunal to include interest in
           the ‘sum’ for which the award is made. The arbitral tribunal
           is further conferred the discretion to award interest on the
           principal sum awarded at such rate as it deems reasonable.
           However, this discretion of the arbitral tribunal is subject to
           any decision which is agreed upon by the parties.
18. Clause (a) of Section 31(7) of the 1996 Act was examined by this
    Court in S.A. Builders (supra) whereafter it was held as under:
1388                                                      [2025] 9 S.C.R.

                        Supreme Court Reports


          36.1. From a minute reading of sub-section (7), it is
          seen that it has got two parts: the first part i.e. clause
          (a) deals with passing of award which would include
          interest up to the date on which the award is made. The
          second part i.e. clause (b) deals with grant of interest on
          the “sum” awarded by the Arbitral Tribunal.
          36.2. Let us now discuss in detail the contours of the
          two clauses. As per clause (a), when an award is made
          by the Arbitral Tribunal for payment of money, the “sum”
          which is awarded may include interest at such rate as the
          Arbitral Tribunal deems appropriate, on the whole or any
          part of the money and for the whole or any part of the
          period. The period for which the interest may be granted
          would be between the date on which the cause of action
          arose and the date on which the award is made. The
          expression which needs to be noticed in this part is the
          following: the Arbitral Tribunal may include in the sum
          for which the award is made interest at such rate as
          it deems reasonable.
          36.3. The word “may” appearing in the above
          expression is quite significant. It implies that the
          Arbitral Tribunal has the discretion to grant interest at
          a reasonable rate. In other words, it may grant interest
          or it may not grant interest; but if it grants interest, it
          would be included in the “sum” which is awarded by
          the Arbitral Tribunal.
19. Insofar clause (b), as it stood at the relevant time is concerned, it
    provides for award of interest by the arbitral tribunal on the ‘sum’
    adjudged under clause (a). It says that ‘unless the award otherwise
    directs’, a sum directed to be paid by an award shall carry interest
    at the rate of 18% per annum from the date of the award to the date
    of payment. In other words, clause (b) is subject to the interest that
    may be awarded by the arbitral tribunal. This provision was explained
    in S.A. Builders (supra) in the following manner:
          36.4. This brings us to the second part i.e. clause (b)
          which deals with post-award interest. The “sum” directed
          to be paid by the Arbitral Tribunal shall, unless the award
          otherwise directs, carry interest @ 18% p.a. from the date
[2025] 9 S.C.R.                                                                1389

          HLV Limited (Formerly Known as Hotel Leelaventure
                Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.

           of the award to the date of payment. Thus, what clause (b)
           provides for is that the Arbitral Tribunal may award interest
           on the “sum” adjudged under clause (a). But if no such
           interest is awarded, then there shall be interest @ 18% on
           the “sum” awarded by the Arbitral Tribunal from the date of
           the award to the date of payment. The two crucial words
           in this part are sum and shall. As seen from clause (a),
           the “sum” awarded by the Arbitral Tribunal would include
           interest if it is granted by the Arbitral Tribunal. Therefore, the
           “sum” as awarded by the Arbitral Tribunal may or may not
           include interest. Whether the “sum” so awarded includes
           or does not include interest, it would carry further interest
           @ 18% from the date of the award to the date of payment
           unless another rate of interest is granted by the Arbitral
           Tribunal. While granting of interest under clauses (a) and
           (b) by the Arbitral Tribunal is discretionary, the interest
           contemplated under clause (b) in the event of failure of the
           Arbitral Tribunal to award interest is mandatory. Therefore,
           the legislature has consciously used the word shall.
20. Thus, from a conjoint analysis of Section 31(7)(a) and Section 31(7)
    (b) of the 1996 Act, what is discernible is that insofar award of interest
    from the date on which the cause of action arose till the date of the
    award is concerned, the legislative intent is that the parties possess
    the autonomy to determine the interest and the rate of interest for the
    aforesaid period. Clause (a) i.e. discretion of the arbitral tribunal to
    award interest is subject to agreement by and between the parties.
    Therefore, party autonomy takes precedence over the discretion
    of the arbitral tribunal. However, clause (b) is subject to award of
    interest by the arbitral tribunal. In other words, as per clause (b), the
    ‘sum’ directed to be paid under an arbitral award shall carry interest
    at the rate of 18% per annum from the date of the award to the date
    of payment ‘unless the award otherwise directs’. Therefore, this
    provision is subject to award of interest by the arbitral tribunal. If it
    awards interest, then the same shall be applicable from the date of
    the award till the date of payment; if not, then the ‘sum’ as adjudged
    under clause (a) shall carry interest at the rate of 18%.
21. The parties here are governed by the MOU dated 09.04.2014.
    Clause (6)(b) of the MoU is relevant and reads as under:
1390                                                         [2025] 9 S.C.R.

                          Supreme Court Reports


                  (b) The proposed purchaser may at its option
                  terminate this MOU by sending to the proposed
                  vendor an intimation of termination of MOU and
                  demand for refund of advance paid together with
                  21% interest per annum from the respective dates
                  of disbursement of the advances till actual date of
                  payment of the same. The proposed vendor shall
                  tender the advances together with 21% interest
                  per annum within 30 days of receipt of intimation
                  of termination from the proposed purchaser. It is
                  clarified that the termination of the MOU will take
                  effect only from the date of receipt of all advances
                  together with 21% interest per annum up to date
                  of receipt by the proposed purchaser. If for any
                  reason the proposed vendor is unable to tender all
                  advances with 21% interest per annum within 30
                  days of the receipt of intimation of termination of the
                  MOU from the proposed purchaser, the proposed
                  purchaser will have the option to call upon the
                  proposed vendor to execute the sale deed in respect
                  of the schedule property on as is where is basis
                  for a total consideration of Rs. 65 crores (Rupees
                  sixty five crores) and pay the balance amount after
                  adjusting advances paid.
     21.1. The aforesaid clause in the MoU gave discretion to the
           respondent to terminate the MOU in which event it would
           be entitled to refund of the advance paid together with
           interest at the rate of 21% per annum from the respective
           dates of disbursement of the advances till the actual date
           of repayment.
22. The arbitral tribunal in the award dated 08.09.2019 applied the
    aforesaid clause of the MOU while declaring that the claimant was
    entitled to Rs. 15.5 crores with interest at the rate of 21% per annum
    from the date it was given to the date it is paid. Therefore, it is evident
    that the arbitral tribunal was guided by the rate of interest provided
    in the MOU and it clarified while passing the award that this rate
    of interest would be available to the respondent from the dates of
    disbursement till the actual date of repayment.
[2025] 9 S.C.R.                                                              1391

           HLV Limited (Formerly Known as Hotel Leelaventure
                 Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.

23. A two-Judge Bench of this Court in State of Haryana Vs. S.L. Arora4
    considered the question as to whether Section 31(7) of the 1996 Act
    authorises and enables arbitral tribunals to award interest on interest
    from the date of the award? In the facts of that case, the consequential
    question formulated was as to whether the arbitral award granted
    future interest from the date of award, only on the principal amount
    found due to the respondent or on the aggregate of the principal
    and interest up to the date of the award? After an analysis of the
    aforesaid provision, the Bench observed that Section 31(7) makes
    no reference to payment of compound interest or payment of interest
    upon interest. It was held that in the absence of any provision for
    interest upon interest in the contract, arbitral tribunals do not have the
    power to award interest upon interest or compound interest either for
    the pre-award period or for the post-award period. It was held thus:
                       18. Section 31(7) makes no reference to payment
                       of compound interest or payment of interest
                       upon interest. Nor does it require the interest
                       which accrues till the date of the award, to be
                       treated as part of the principal from the date of
                       award for calculating the post-award interest.
                       The use of the words “where and insofar as an
                       arbitral award is for the payment of money” and use
                       of the words “the Arbitral Tribunal may include in
                       the sum for which the award is made, interest …
                       on the whole or any part of the money” in clause
                       (a) and use of the words “a sum directed to be
                       paid by an arbitral award shall … carry interest” in
                       clause (b) of sub-section (7) of Section 31 clearly
                       indicate that the section contemplates award of
                       only simple interest and not compound interest or
                       interest upon interest. “A sum directed to be paid
                       by an arbitral award” refers to the award of sums
                       on the substantive claims and does not refer to
                       interest awarded on the “sum directed to be paid
                       by the award”. In the absence of any provision for
                       interest upon interest in the contract, the Arbitral


4   (2010) 3 SCC 690
1392                                                         [2025] 9 S.C.R.

                         Supreme Court Reports


                 Tribunals do not have the power to award interest
                 upon interest, or compound interest, either for the
                 pre-award period or for the post-award period.
     23.1. Thereafter the Bench upon a threadbare analysis concluded
           that Section 31(7) merely authorizes the arbitral tribunal to
           award interest in accordance with the contract and in the
           absence of any prohibition in the contract and in the absence
           of specific provision relating to interest in the contract, to award
           simple interest at such rates as it deems fit from the date on
           which the cause of action arose till the date of payment. The
           Bench further clarified that if the award is silent about interest
           from the date of award till the date of payment, the person
           in whose favour the award is made will be entitled to interest
           at 18% per annum on the principal amount awarded from
           the date of award till the date of payment. In the facts of that
           case, the Bench declared that the calculation that was made
           in the execution petition as originally filed was correct and
           that the modification sought for by the respondent increasing
           the amount due under the award was contrary to the award.
           It was concluded as under:
                 34. Thus it is clear that Section 31(7) merely
                 authorises the Arbitral Tribunal to award interest in
                 accordance with the contract and in the absence of
                 any prohibition in the contract and in the absence of
                 specific provision relating to interest in the contract,
                 to award simple interest at such rates as it deems
                 fit from the date on which the cause of action arose
                 till the date of payment. It also provides that if the
                 award is silent about interest from the date of award
                 till the date of payment, the person in whose favour
                 the award is made will be entitled to interest at
                 18% per annum on the principal amount awarded,
                 from the date of award till the date of payment. The
                 calculation that was made in the execution petition
                 as originally filed was correct and the modification
                 by the respondent increasing the amount due under
                 the award was contrary to the award.
24. The correctness of the view taken in S.L. Arora (supra) came up
    for consideration before a three-Judge Bench of this Court in Hyder
[2025] 9 S.C.R.                                                            1393

          HLV Limited (Formerly Known as Hotel Leelaventure
                Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.

     Consulting (supra). The majority held that the conclusion reached in
     S.L. Arora (supra) was not in consonance with the clear language of
     Section 31(7) of the Act. After extracting Section 31(7) of the 1996
     Act, the Bench explained clause (a) of sub-section (7) of Section 31
     in the following manner:
                    4. Clause (a) of sub-section (7) provides that where
                    an award is made for the payment of money, the
                    Arbitral Tribunal may include interest in the sum
                    for which the award is made. In plain terms, this
                    provision confers a power upon the Arbitral Tribunal
                    while making an award for payment of money, to
                    include interest in the sum for which the award
                    is made on either the whole or any part of the
                    money and for the whole or any part of the period
                    for the entire pre-award period between the date
                    on which the cause of action arose and the date
                    on which the award is made. To put it differently,
                    sub-section (7)(a) contemplates that an award,
                    inclusive of interest for the pre-award period on the
                    entire amount directed to be paid or part thereof,
                    may be passed. The “sum” awarded may be the
                    principal amount and such interest as the Arbitral
                    Tribunal deems fit. If no interest is awarded, the
                    “sum” comprises only the principal. The significant
                    words occurring in clause (a) of sub-section (7) of
                    Section 31 of the Act are “the sum for which the
                    award is made”. On a plain reading, this expression
                    refers to the total amount or sum for the payment
                    for which the award is made. Parliament has
                    not added a qualification like “principal” to the
                    word “sum”, and therefore, the word “sum” here
                    simply means “a particular amount of money”.
                    In Section 31(7), this particular amount of money
                    may include interest from the date of cause of
                    action to the date of the award.
     24.1. On the above analysis, the Bench explained clause (b) of
           sub-section (7) of Section 31 of the 1996 Act to mean that
           the ‘sum’ which is directed to be paid by the award, whether
1394                                                         [2025] 9 S.C.R.

                        Supreme Court Reports


           inclusive or exclusive of interest, shall carry interest at the rate
           of 18% per annum for the post-award period unless otherwise
           ordered. The above provision was explained as under:
                7. Thus, when used as a noun, as it seems to
                have been used in this provision, the word “sum”
                simply means “an amount of money”; whatever
                it may include — “principal” and “interest” or
                one of the two. Once the meaning of the word
                “sum” is clear, the same meaning must be
                ascribed to the word in clause (b) of sub-section
                (7) of Section 31 of the Act, where it provides that
                a sum directed to be paid by an arbitral award
                “shall … carry interest …” from the date of the
                award to the date of the payment i.e. post-award.
                In other words, what clause (b) of sub-section (7)
                of Section 31 of the Act directs is that the “sum”,
                which is directed to be paid by the award, whether
                inclusive or exclusive of interest, shall carry interest
                at the rate of eighteen per cent per annum for the
                post-award period, unless otherwise ordered.
     24.2. Finally, Hyder Consulting (supra) arrived at the following
           conclusion:
                13. Thus, it is apparent that vide clause (a) of
                sub-section (7) of Section 31 of the Act, Parliament
                intended that an award for payment of money may
                be inclusive of interest, and the “sum” of the principal
                amount plus interest may be directed to be paid
                by the Arbitral Tribunal for the pre-award period.
                Thereupon, the Arbitral Tribunal may direct interest
                to be paid on such “sum” for the post-award period
                vide clause (b) of sub-section (7) of Section 31 of
                the Act, at which stage the amount would be the
                sum arrived at after the merging of interest with
                the principal; the two components having lost their
                separate identities.
25. The question as to whether the ‘sum’ awarded under clause (a) of
    sub-section (7) of Section 31 of the 1996 Act would include interest
[2025] 9 S.C.R.                                                                1395

           HLV Limited (Formerly Known as Hotel Leelaventure
                 Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.

     pendente lite or not again came up for consideration before a two-
     Judge Bench of this Court in Delhi Airport Metro Express Private
     Limited Vs. Delhi Metro Rail Corporation5. The Bench analyzed Hyder
     Consulting (supra) in the following manner:
                       15. It could thus be seen that the majority view
                       of this Court in Hyder Consulting (UK) is that
                       the sum awarded may include the principal
                       amount and such interest as the Arbitral Tribunal
                       deems fit. It is further held that, if no interest
                       is awarded, the “sum” comprises only the
                       principal amount. The majority judgment held
                       that clause (a) of sub-section (7) of Section 31 of
                       the 1996 Act refers to the total amount or sum for
                       the payment for which the award is made. As such,
                       the amount awarded under clause (a) of sub-section
                       (7) of Section 31 of the 1996 Act would include the
                       principal amount plus the interest amount pendente
                       lite. It was held that the interest to be calculated
                       as per clause (b) of sub-section (7) of Section 31
                       of the 1996 Act would be on the total sum arrived
                       as aforesaid under clause (a) of sub-section (7) of
                       Section 31 of the 1996 Act. S.A. Bobde, J. in his
                       judgment, has referred to various authorities of this
                       Court as well as Maxwell on the Interpretation of
                       Statutes. He emphasised that the Court must give
                       effect to the plain, clear and unambiguous words
                       of the legislature and it is not for the courts to add
                       or subtract the words, even though the construction
                       may lead to strange or surprising, unreasonable or
                       unjust or oppressive results.
     25.1. Thereafter, the Bench made an analysis of clause (a) of
           sub-section (7) of Section 31 of the 1996 Act and noted that
           it begins with the expression ‘unless otherwise agreed by
           the parties’. This expression was explained by the Bench by
           holding as under:
                       17. It could thus be seen that the part which
                       deals with the power of the Arbitral Tribunal


5   (2022) 9 SCC 286
1396                                                      [2025] 9 S.C.R.

                       Supreme Court Reports


                to award interest, would operate if it is not
                otherwise agreed by the parties. If there is an
                agreement between the parties to the contrary,
                the Arbitral Tribunal would lose its discretion to
                award interest and will have to be guided by the
                agreement between the parties. The provision
                is clear that the Arbitral Tribunal is not bound
                to award interest. It has a discretion to award
                the interest or not to award. It further has a
                discretion to award interest at such rate as it
                deems reasonable. It further has a discretion to
                award interest on the whole or any part of the
                money. It is also not necessary for the Arbitral
                Tribunal to award interest for the entire period
                between the date on which the cause of action
                arose and the date on which the award is made.
                It can grant interest for the entire period or any
                part thereof or no interest at all.
    25.2. Thus, this Court was of the view that power of the tribunal to
          award interest would operate if it is not otherwise agreed by
          the parties. If there is an agreement between the parties to
          the contrary, the arbitral tribunal would lose its discretion to
          award interest and will have to be guided by the agreement
          between the parties. Thus, the expression ‘unless otherwise
          agreed by the parties’ assumes significance and concluded
          as under:
                20. If clause (a) of sub-section (7) of Section 31 of
                the 1996 Act is given a plain and literal meaning, the
                legislative intent would be clear that the discretion
                with regard to grant of interest would be available to
                the Arbitral Tribunal only when there is no agreement
                to the contrary between the parties. The phrase
                “unless otherwise agreed by the parties” clearly
                emphasises that when the parties have agreed
                with regard to any of the aspects covered under
                clause (a) of sub-section (7) of Section 31 of the
                1996 Act, the Arbitral Tribunal would cease to have
                any discretion with regard to the aspects mentioned
                in the said provision. Only in the absence of such
[2025] 9 S.C.R.                                                                1397

           HLV Limited (Formerly Known as Hotel Leelaventure
                 Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.

                       an agreement, the Arbitral Tribunal would have a
                       discretion to exercise its powers under clause (a) of
                       sub-section (7) of Section 31 of the 1996 Act. The
                       discretion is wide enough. It may grant or may not
                       grant interest. It may grant interest for the entire
                       period or any part thereof. It may also grant interest
                       on the whole or any part of the money.
     25.3. From the above, the view of the court is clearly discernible
           in that the discretion to grant interest would be available to
           the arbitral tribunal under clause (a) of sub-section (7) of
           Section 31 only when there is no agreement to the contrary
           between the parties. When the parties agree with regard to
           any of the aspects covered under clause (a) of sub-section
           (7) of Section 31, the arbitral tribunal would cease to have
           any discretion with regard to the aspects mentioned in the
           said provision. Only in the absence of such an agreement,
           the arbitral tribunal would have the discretion to exercise its
           powers under clause (a) of sub-section (7) of Section 31 of
           the 1996 Act.
     25.4. In the facts of that case it was held that in view of the specific
           agreement between the parties, the interest quotient prior to
           the date of the award so also after the date of the award will
           be governed by article 29.8 of the concession agreement
           which was also directed by the arbitral tribunal. This view was
           accordingly affirmed by this Court.
26. In Morgan Securities and Credits Private Limited Vs. Videocon
    Industries Limited6, a two-Judge Bench of this Court again examined
    the decision in Hyder Consulting (supra). After an extensive analysis,
    the Bench was of the view that the decision in Hyder Consulting
    (supra) was on the limited issue of whether post-award interest
    could be granted on the aggregate of the principal and the pre-
    award interest. The opinion authored by Bobde, J. was limited to this
    aspect of post-award interest. Thereafter, the Bench noted that the
    issue before it was whether the phrase ‘unless the award otherwise
    directs’ in Section 31(7)(b) of the 1996 Act only provides the arbitrator
    the discretion to determine the rate of interest or both the rate of


6   (2023) 1 SCC 602
1398                                                       [2025] 9 S.C.R.

                         Supreme Court Reports


     interest and the ‘sum’ it must be paid against. Thereafter it was noted
     that both clauses (a) and (b) of sub-section (7) of Section 31 are
     qualified. While clause (a) is qualified by the arbitration agreement
     between the parties, clause (b) is qualified by the arbitration award.
     The words ‘unless otherwise agreed by the parties’ occurring at the
     beginning of clause (a) qualifies the entire provision. However, the
     words ‘unless the award otherwise directs’ occurring in clause (b)
     only qualifies the rate of post-award interest. Thereafter, this Court
     summarized the findings and we extract only those portions which
     are relevant for our present purpose:
          28.3. The phrase “unless the award otherwise directs”
          in Section 31(7)(b) only qualifies the rate of interest.
          28.4. According to Section 31(7)(b), if the arbitrator does
          not grant post-award interest, the award holder is entitled
          to post-award interest at eighteen per cent.
          28.5. Section 31(7)(b) does not fetter or restrict the
          discretion that the arbitrator holds in granting post-award
          interest. The arbitrator has the discretion to award post-
          award interest on a part of the sum.
          28.6. The arbitrator must exercise the discretionary
          power to grant post-award interest reasonably
          and in good faith, taking into account all relevant
          circumstances.
27. Though learned senior counsel for the respondent placed heavy
    reliance on S.A. Builders Limited (supra), we are of the view that
    S.A. Builders Limited (supra) is a continuum of what was held by
    this Court in Delhi Airport Metro Express Private Limited (supra)
    and in Morgan Securities and Credits Private Limited (supra). We
    have already noted as to how a two-Judge Bench of this Court in
    S.A. Builders Limited (supra) (of which I was also a member) had
    analyzed clauses (a) and (b) of sub-section (7) of Section 31 of the
    1996 Act. We have also noted that this Court had observed that the
    provision in Section 31(7)(a) of the 1996 Act begins with the expression
    ‘unless otherwise agreed by the parties’, thereby highlighting the
    legislative stance that the parties possess the autonomy to determine
    pre-award interest on the payment of money that may be awarded
    by the arbitral tribunal. However, no such discretion is available
[2025] 9 S.C.R.                                                        1399

          HLV Limited (Formerly Known as Hotel Leelaventure
                Pvt. Ltd.) v. PBSAMP Projects Pvt. Ltd.

     to the parties under Section 31(7)(b) of the 1996 Act though such
     discretion is available to the arbitral tribunal. It was in that context
     this Court in the facts of that case noted that it was not the case
     of the appellant that the interest portion is covered by the contract
     agreement between the parties. In the absence thereof, Section 31(7)
     (a) as well as Section 31(7)(b) of the 1996 Act would have their full
     effect. Therefore, it was concluded as under:
           70. That apart, it is not the case of the appellant
           that the interest portion is covered by the contract
           agreement between the parties. In the absence thereof,
           Section 31(7)(a) as well as Section 31(7)(b) of the 1996
           Act would have their full effect. The sum awarded would
           mean the principal amount plus the interest awarded from
           the date of cause of action up to the date of the award.
           Thereafter, as per Section 31(7)(b) of the 1996 Act, the
           sum (principal plus interest) would carry interest @ 18%
           from the date of the award to the date of payment. This
           would be consistent with the law laid down by this Court
           in Hyder Consulting.
28. Therefore, even S.A. Builders Limited (supra) lays down the
    proposition that the discretion of the arbitral tribunal to award interest
    under Section 31(7)(a) of the 1996 Act is subservient to the agreement
    between the parties. In other words, party autonomy, so crucial to
    arbitration, reigns supreme.
29. Reverting back to the facts of the present case, we have already
    adverted to clause 6(b) of the MoU dated 09.04.2014 which expressly
    provided that in the event of termination of the MoU, the appellant
    must refund all advances with interest at the rate of 21% per annum
    from the respective dates of disbursement till repayment. Thus, in the
    light of the express provision contained in clause (a) of sub-section
    (7) of Section 31, the arbitral tribunal awarded interest in terms of the
    MoU from the date of the cause of action till the date of repayment.
    As the arbitral tribunal had expressly provided interest till the date
    of repayment, question of additional or compound interest under
    clause (b) of sub-section (7) of Section 31 of 1996 Act would not
    arise. The arbitral tribunal in its award dated 08.09.2019 has faithfully
    complied with the MoU agreed by and between the parties. Thus, the
    arbitral tribunal exercised its discretion within the overall framework
1400                                                       [2025] 9 S.C.R.

                            Supreme Court Reports


     of Section 31(7) of the 1996 Act aligning with the legislative intent
     that the award, rather than the statutory default, should govern the
     parties, more so in a case as in the present one where the parties
     have themselves made provision for interest throughout.
30. Therefore, reliance placed by the respondent on Hyder Consulting
    (supra) to claim post-award interest is misplaced. That principle would
    apply only when the arbitral tribunal leaves a matter unqualified or is
    silent. In the present case the arbitral tribunal bound by the MoU and
    exercising its statutory discretion had already specified the interest
    rate (21% per annum) and the duration (until repayment). As held
    in Morgan Securities and Credits Private Limited (supra), reaffirmed
    in Delhi Airport Metro Express Private Limited (supra) and explained
    in S.A. Builders Limited (supra), once parties agree on the interest
    regime, the arbitrator’s role is confined to enforcing it and the courts
    would not rewrite or enlarge the award by introducing further interest
    at the execution stage.
31. The MoU did not stipulate compounding of interest; the arbitral tribunal
    did not award compound interest; therefore, respondent cannot at the
    stage of execution seek to introduce claim of compound interest by
    drawing on general principles. Allowing such a claim would amount to
    rewriting the award at the stage of execution which is impermissible.
32. In the circumstances, we are of the view that the High Court was
    not justified in setting aside the order of the executing court and
    remanding the matter for fresh determination.
33. For the reasons aforementioned, the impugned judgment and order of
    the High Court dated 22.04.2024 is hereby set aside. Consequently,
    order of the executing court dated 02.11.2023 is restored.
34. Civil appeal is accordingly allowed. However, there shall be no order
    as to cost.

     Result of the case: Appeal allowed.




     †
         Headnotes prepared by: Divya Pandey


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Section 31(7)(a)"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.