Created byFuzzy Cloud

Supreme Court of India

HARBINDER SINGH SEKHON & ORS.versusTHE STATE OF PUNJAB & ORS.

Citation
2026 INSC 159
Decided
13 February 2026

Holding

The Court held that the CLU was ultra vires the Master Plan, the subsequent approval could not cure its defect or amend the Master Plan, the required environmental siting safeguards were not met, and the CPCB’s re‑classification and related notifications were unconstitutional, leading to their quashment.

Summary

The appellants, a group of agriculturists and a nearby school, challenged a Change of Land Use (CLU) dated 13‑12‑2021 that permitted a cement‑related grinding unit on land classified as a rural agricultural zone in the Sangrur Master Plan. The High Court had upheld the CLU, relying on a subsequent approval recorded on 05‑01‑2022 by the Punjab Regional and Town Planning and Development Board, and dismissed the writ petitions. The Supreme Court held that the CLU was invalid because the Master Plan’s zoning prohibited such an industrial activity and that a later approval could not cure the defect or amend the Master Plan under the PRTPD Act. It also found that the required environmental siting norms and safeguards were not complied with, and that the CPCB’s re‑classification of the unit from “Red” to “Orange” and the related MoEF&CC notifications unlawfully diluted preventive safeguards, violating Articles 14 and 21. Consequently, the Court quashed the CLU, the related pollution‑control consent, the CPCB re‑classification, and the notifications, and set aside the High Court’s order. The appeals were allowed and the writ petitions disposed of.

Issues considered

  • Whether a Change of Land Use dated 13‑12‑2021 could be granted for a cement grinding unit when the site fell within a rural agricultural zone under the operative Master Plan for Sangrur.
  • Whether the approval recorded on 05‑01‑2022 by the Punjab Regional and Town Planning and Development Board can lawfully cure the defect in the CLU and operate as an alteration or amendment of the Master Plan under the PRTPD Act.
  • Whether the siting norms and environmental safeguards, including the PPCB notification of 02‑09‑1998 and the EIA Notification 2006, were complied with in relation to the proximity of habitations and a school.
  • Whether the CPCB’s revised industrial sector categorisation of a stand‑alone grinding unit from “Red” to “Orange” and the consequent MoEF&CC notifications GSR 84E and GSR 85E can be sustained in law under Articles 14 and 21 of the Constitution.

Legislation cited

Headnote

Issue for Consideration Issue arose for consideration whether change of land use-CLU dated 13.12.2021 could have been granted for the proposed unit when the land use under the Master Plan for Sangrur treated the site as falling in rural agricultural zone; whether “approval” recorded in Punjab Regional and Town Planning and Development Board dated 05.01.2022 could lawfully cure the admitted defect in the CLU and whether such approval is capable in law of operating as an alteration or amendment of the Master Plan under the PRTPD Act; whether the siting norms and environmental

Subjects

Land use under the Master Plan for SangrurRural agricultural zoneChange of Land Use (CLU)Punjab Regional and Town Planning and Development Board approvalAlteration or amendment of Master PlanSiting norms and environmental safeguardsPPCB notification 02.09.1998Revised industrial sector categorisationStand‑alone grinding unit without CPPRed categoryOrange categoryNotifications GSR 84E 29.01.2025Notifications GSR 85E 30.01.2025Precautionary principleSustainable developmentEnvironmental protectionArticles 14 and 21 Constitution of India

Judgment

                 [2026] 3 S.C.R. 179 : 2026 INSC 159

                   Harbinder Singh Sekhon & Ors.
                                  v.
                     The State of Punjab & Ors.
                       (Civil Appeal No. 2331 of 2026)
                              13 February 2026
              [Vikram Nath* and Sandeep Mehta, JJ.]


                           Issue for Consideration
       Issue arose for consideration whether change of land use-CLU
       dated 13.12.2021 could have been granted for the proposed unit
       when the land use under the Master Plan for Sangrur treated
       the site as falling in rural agricultural zone; whether “approval”
       recorded in the 43rd meeting of the Punjab Regional and Town
       Planning and Development Board dated 05.01.2022 could lawfully
       cure the admitted defect in the CLU and whether such approval is
       capable in law of operating as an alteration or amendment of the
       Master Plan under the PRTPD Act; whether the siting norms and
       environmental safeguards, including the PPCB notification dated
       02.09.1998 and the relevant regulatory framework, were complied
       with in relation to the proximity of habitations and the school; and
       whether the revised industrial sector categorisation issued by CPCB
       in January, 2025, insofar as it reclassifies the activity described
       as “stand-alone grinding unit without CPP” from “Red” category
       to “Orange” category, together with the consequential relaxation
       of siting and regulatory safeguards brought about by Notifications
       GSR 84E dt 29.01.2025 and GSR 85E dt 30.01.2025, can be
       sustained in law.

                                  Headnotes†
       Punjab Regional and Town Planning and Development Act,
       1995 – Legality of the change of land use-CLU – Respondent
       no. 9 purchased land for establishing cement related industrial
       unit in close proximity to the agricultural lands and residential
       houses of the appellants-group of agriculturists, and the
       School located in the immediate vicinity of the proposed site –
       CLU issued in favour of respondent no.9 for the proposed
       unit – Appellant’s case that CLU was granted in a manner not


* Author
180                                                              [2026] 3 S.C.R.

                            Supreme Court Reports


       contemplated by the Act, and the proposed site falls within rural
       agricultural zone under the Master Plan for Sangrur and that
       red category polluting industry could not have been permitted
       at the said location – Writ petitions thereagainst, dismissed
       by the High Court holding that as on 13.12.2021, CLU did not
       have statutory backing in the form contemplated by the Act,
       however, upheld CLU since the Regional and Town Planning
       and Development Board granted approval in its meeting dt
       05.01.2022 and treated the said approval as curing the defect
       and accepted the stand that the land use permissibility stood
       validated thereafter – Justification:
       Held: CLU dated 13.12.2021 could not have been granted for the
       proposed unit when, under the operative Master Plan for Sangrur,
       the site fell in a rural agricultural zone where the proposed activity
       was not permissible – Permission must be lawful when it is granted –
       It cannot be rendered lawful by a later event unless the PRTPD
       Act itself so provides – “Approval” recorded on 05.01.2022 could
       not lawfully cure the defect in the CLU dated 13.12.2021, and it
       is not capable, in law, of operating as an alteration or amendment
       of the Master Plan under the PRTPD Act – Approach adopted by
       the High Court, which treated the subsequent approval as curing
       the illegality of the CLU, cannot be accepted when the statutory
       structure does not permit legality to be supplied to an act which
       was unlawful when done, by a later administrative approval which
       does not itself satisfy the mandatory requirements governing
       alteration or revision of the Master Plan – High Court’s approach,
       which proceeded on the premise that an act lacking statutory
       backing on the date of its issuance may nonetheless be sustained
       by a subsequent ex post facto approval, is inconsistent with this
       statutory structure – Siting norms and safeguards, including the
       PPCB notification dated 02.09.1998 and the regulatory discipline
       underlying prior environmental clearance under the EIA Notification,
       2006, not complied with in the manner required by law – Proposed
       control systems and future-stage compliances cannot substitute
       the obligation to satisfy siting norms and the discipline underlying
       prior environmental clearance at the relevant time – Nor can
       subsequent material or later regulatory developments be invoked
       to retrospectively validate the legality of permissions already found
       to be without statutory foundation – Thus, judgment and order
       passed by the High Court set aside – Change of Land Use granted
       in favour of respondent no.9 quashed. [Paras 9-36]
[2026] 3 S.C.R.                                                             181

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


     Environmental law – Reclassification from “Red” category to
     “Orange” category – Revised industrial sector categorisation
     issued by the CPCB in January, 2025 – Reclassification
     of “stand-alone grinding unit without CPP (Captive Power
     Plant) from “Red” category to “Orange” category with the
     consequential relaxation of siting and regulatory safeguards
     brought about by Notifications GSR 84E dt 29.01.2025 and
     GSR 85E dt 30.01.2025 – Sustainability:
     Held: Revised categorisation and the consequential regulatory
     relaxations elevate a generic classification methodology to a
     position where it overrides preventive environmental safeguards,
     without adequate regard to exposure risks, local conditions, or
     the constitutional obligation to protect life and health – Such an
     approach is inconsistent with the precautionary principle, the
     doctrine of sustainable development, and the content of Art. 21 –
     Revised categorisation and consequential relaxation of siting
     safeguards materially affect the level of protection available to
     civilians, including residents and school-going children, against
     exposure to industrial pollution – By lowering the regulatory
     threshold applicable to an activity with known particulate emission
     characteristics, revised framework permits such units to be located
     closer to habitations and educational institutions – Impact is not
     speculative, it directly implicates public health and safety – Thus,
     the present intervention warranted because the impugned actions
     have the effect of lowering the constitutional minimum of protection
     guaranteed to affected communities – Revised industrial sector
     categorisation issued by the CPCB in January, 2025, insofar as it
     reclassifies the activity described as a “stand-alone grinding unit
     without CPP” from the “Red” category to the “Orange” category,
     cannot be sustained in law – Said reclassification, read together
     with the consequential relaxation of siting and regulatory safeguards
     brought about by Notifications GSR 84E and GSR 85E has the effect
     of diluting preventive environmental protections in a manner that
     infringes the constitutional guarantees u/Arts.14 and 21 – Revised
     industrial sector categorisation issued by the CPCB in January,
     2025 quashed insofar as it reclassifies the activity described as a
     “stand-alone grinding unit without CPP” from the “Red” category
     to the “Orange” category – Notifications GSR 84E and GSR 85E
     quashed insofar as they relax the applicable siting and regulatory
     safeguards for such units on the basis of the said reclassification –
     Any consent, approval or permission that has been granted solely
182                                                               [2026] 3 S.C.R.

                            Supreme Court Reports


       on the basis of the said reclassification of “stand-alone grinding
       unit without CPP” as an “Orange” category activity or on the basis
       of the relaxed siting and regulatory safeguards introduced by
       Notifications GSR 84E and GSR 85E will not survive and stands
       withdrawn – CPCB or MoEF & CC not precluded from undertaking
       fresh exercise of classification or regulatory review in accordance
       with law – Constitution of India – Arts.14 and 21. [Paras 65-68]

       Environmental law – Environmental protection and
       development – Constitutional balance – Explanation:
       Held: Economic development and industrial growth are legitimate
       and important objectives of the State – However, in a constitutional
       framework founded on the rule of law, development is not an
       abstract or absolute goal – It is conditioned by the non-derogable
       obligation to protect life, health, and environmental integrity –
       Development that undermines these foundational values ceases
       to be constitutionally permissible development – Doctrine of
       sustainable development is not a slogan of compromise but a
       principle of prioritisation – It requires that when developmental
       activity poses a credible risk to human health or environmental
       safety, regulatory frameworks must err on the side of protection –
       Constitution does not permit a trade-off where civilian life and health
       are exposed to foreseeable harm on the assumption that economic
       benefit or industrial facilitation justifies such exposure – Arts.14 and
       21 do not tolerate a regulatory calculus that treats environmental
       safety as negotiable – If regulatory dilution were to be accepted,
       it would mark a fundamental shift in environmental governance –
       Sector-level reclassification, divorced from exposure realities and
       local sensitivities, would become a ready instrument to justify siting
       of polluting activities in close proximity to habitations, schools,
       and other sensitive receptors – It would operate as a precedent,
       enabling progressive erosion of preventive safeguards across
       regions, with cumulative and irreversible consequences – Law does
       not permit environmental protection to be weakened incrementally
       until harm becomes inevitable – Environmental harm, once caused,
       is often irreversible or incapable of full remediation – Public health
       consequences, degradation of air quality, and long-term ecological
       damage cannot be undone by subsequent regulatory correction –
       Thus, environmental regulation is designed to be preventive rather
       than reactive – Regulatory framework that allows risk to materialise
       first and seeks to address consequences later is fundamentally
[2026] 3 S.C.R.                                                             183

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


     incompatible with constitutional environmental jurisprudence – This
     Court does not ordinarily interfere with technical classifications or
     policy determinations made by expert bodies, however, judicial
     restraint cannot extend to abdication – Where regulatory action
     results in lowering of the constitutional minimum of protection
     guaranteed to citizens, particularly in matters affecting life and
     health, judicial intervention becomes a constitutional obligation.
     [Paras 60-64]
     Punjab Regional and Town Planning and Development Act,
     1995 – ss.70, 75, 76, 79-81 – Preparation and approval of Master
     Plans – Master Plan, its binding force, and the procedure for
     alteration/revision – Control of development and “change of
     land use” permissions – Explained. [Paras 7.1-7.10]
     Environment (Protection) Act, 1986 – Environment (Protection)
     Rules, 1986 – EIA Notification dated 14.09.2006 – Environmental
     clearance and siting safeguards – Explained. [Paras 7.11-7.13]

                              Case Law Cited
     K. Ramadas Shenoy v. Town Municipal Council, Udipi [1975] 1
     SCR 680 : (1974) 2 SCC 506; Bangalore Medical Trust v. B.S.
     Muddappa [1991] 3 SCR 102 : (1991) 4 SCC 54; Vellore Citizens’
     Welfare Forum v. Union of India [1996] Supp. 5 SCR 241 : (1996) 5
     SCC 647; M.C. Mehta v. Union of India [1996] Supp. 7 SCR 465 :
     (1997) 3 SCC 715; Hospitality Assn. of Mudumalai v. In Defence
     of Environment & Animals [2020] 10 SCR 273 : (2020) 10 SCC
     589; M.C. Mehta v. Union of India (Shriram - Oleum Gas) [1987]
     1 SCR 819 : (1987) 1 SCC 395; Indian Council for Enviro-Legal
     Action v. Union of India [1996] 2 SCR 503 : (1996) 3 SCC 212;
     A.P. Pollution Control Board v. Prof. M.V. Nayudu [1999] 1 SCR
     235 : (1999) 2 SCC 718 – referred to.

                                List of Acts
     Punjab Regional and Town Planning and Development Act,
     1995; Constitution of India; Environment (Protection) Act, 1986;
     Environment (Protection) Rules, 1986.

                             List of Keywords
     Land use under the Master Plan for Sangrur; Rural agricultural zone;
     Approval recorded in 43rd meeting of the Punjab Regional and Town
184                                                              [2026] 3 S.C.R.

                            Supreme Court Reports


       Planning and Development Board dated 05.01.2022; Alteration or
       amendment of the Master Plan; Siting norms and environmental
       safeguards; PPCB notification dated 02.09.1998; Regulatory
       framework; Revised industrial sector categorisation; Stand-alone
       grinding unit without CPP; “Red” category; “Orange” category;
       Relaxation of siting and regulatory safeguards; Notifications GSR
       84E dated 29.01.2025; GSR 85E dated 30.01.2025; Principles of
       environmental jurisprudence; Change of land use; Cement related
       industrial unit; Close proximity to agricultural lands and residential
       houses; Change of land use-CLU dated 13.12.2021; Environmental
       clearance under EIA Notification, 2006; Preparation and approval
       of Master Plans; Master Plan, its binding force, and procedure for
       alteration/revision; Control of development and change of land
       use permissions; Environmental clearance and siting safeguards;
       Reclassification of “stand-alone grinding unit without CPP” from
       “Red” category to “Orange” category; Precautionary principle;
       Doctrine of sustainable development; Environmental protection
       and development.

                               Case Arising From
       CIVIL APPELLATE/ORIGINAL JURISDICTION: Civil Appeal No.
       2331 of 2026
       From the Judgment and Order dated 29.02.2024 of the High Court
       of Punjab & Haryana at Chandigarh in CWP No. 20134 of 2022
       With
       SLP (C) No. 8495 of 2024 and Writ Petition (C) No(s). 481 and
       551 of 2025

                           Appearances for Parties
       Advs. for the Petitioner(s):
       Mukul Rohatgi, Parthiv Goswami, Sr. Advs., Purushottam Sharma
       Tripathi, Ms. Diksha Rai, Abhishek Tripathi, Amit, Ms. Vani Vyas,
       Keshav Seghal, Ravi Chandra Prakash.
       Advs. for the Respondent(s):
       Ms. Aishwariya Bhati, A.S.G., Rajat Bhardwaj, A.A.G., Harin P
       Raval, Rakesh Dwivedi, Anand Chibber, Ms. Ruchi Kohli, Sr.
       Advs., Siddhant Sharma, Ms. Shreya Bansal, Ms. Shrestha
       Narayan, Apoorv Shukla, Ms. Ishita Farsaiya, Ms. Prabhleen
[2026] 3 S.C.R.                                                        185

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


     A. Shukla, Ayush Acharjee, Apoorv Shukla, Ms. Ishita Farsaiya,
     Ms. Prabhleen A. Shukla, Ayush Acharjee, Ateevraj Sandhu,
     Ms. Shradha Deshmukh, Ms. Rajeshwari Shankar, Ms. Sherya Jain,
     Ms. Riddhi Jad, Ms. Anuradha, Gurmeet Singh Makker, Sriram P.,
     Ms. Richa Kapoor, Ms. Udipti Chopra, Ms. Aditi Rathore, Sudeep
     Kumar, Gaurav Dhama, Ms. Sushre Sirpa Sahu, Sumit Gaur.

                Judgment / Order of the Supreme Court

                                Judgment

     Vikram Nath, J.

1.   At the outset, it may be noted that the present judgment is structured
     in two parts. The first part addresses the civil appeals arising out of
     the Special Leave Petitions and examines the legality of the change
     of Land Use and the impugned judgment of the High Court. The
     second part separately considers the writ petitions under Article 32
     of the Constitution of India, which raise an independent challenge
     to subsequent regulatory actions taken during the pendency of the
     appeals.

     Part I: For SLP (Civil) No. 8316 of 2024 and SLP (Civil) No. 8495
     of 2024
2.   Leave granted.
3.   The present appeals arise from the common judgment and order
     dated 29.02.2024 passed by the High Court of Punjab and Haryana
     at Chandigarh in CWP No. 20134 of 2022 and CWP No. 18676 of
     2022. By the impugned judgment, the High Court dismissed the
     writ petitions and upheld the change of Land Use dated 13.12.2021
     granted in favour of “Shree Cement North Private Limited”. Civil
     Appeal arising out of SLP (Civil) No. 8316 of 2024 has been filed by
     the writ petitioners in CWP No. 20134 of 2022. Civil Appeal arising
     out of SLP (Civil) No. 8495 of 2024 has been filed by Vasant Valley
     Public School, which was the writ petitioner in CWP No. 18676 of
     2022. For ease of reference, the parties shall be referred to as per
     their status in SLP (Civil) No. 8316 of 2024. Accordingly, Respondent
     No. 9 is Shree Cement North Private Limited, the main contesting
     respondent, before this Court.
186                                                           [2026] 3 S.C.R.

                            Supreme Court Reports


4.     The facts giving rise to the present appeals are as follows:
       4.1. The Appellant in Civil Appeal arising out of SLP (Civil) No.
            8316 of 2024 is a group of agriculturists residing in and around
            Sangrur, Punjab. The Appellants state that Respondent No. 9
            purchased land admeasuring about 47.82 acres for establishing
            a cement related industrial unit in close proximity to their
            agricultural lands and residential houses. The Appellant in Civil
            Appeal arising out of SLP (Civil) No. 8495 of 2024 is Vasant
            Valley Public School. The School claims that its premises are
            located in the immediate vicinity of the proposed site and that
            the proposed activity would adversely affect the health and
            safety of students and staff.
       4.2. On 13.12.2021, the Punjab Bureau of Investment Promotion
            issued a Change of Land Use1 in favour of Respondent No. 9
            for the proposed unit. On 14.12.2021, consent to establish/No
            Objection Certificate from the pollution angle was granted under
            the Single Window mechanism on the basis of Punjab Pollution
            Control Board’s2 consideration. The Appellants contend that the
            CLU was granted in a manner not contemplated by the Punjab
            Regional and Town Planning and Development Act, 19953. The
            Appellants also contend that the proposed site falls within a rural
            agricultural zone under the Master Plan for Sangrur and that a
            red category polluting industry could not have been permitted
            at the said location.
       4.3. The agriculturist Appellants, therefore, instituted CWP No.
            20134 of 2022 before the High Court challenging the CLU
            dated 13.12.2021 and the consequent approvals. Vasant Valley
            Public School instituted CWP No. 18676 of 2022 raising similar
            objections and specifically relied upon the proximity of the
            school and other habitations to the proposed site. During the
            pendency of the writ proceedings, the High Court passed an
            interim order dated 20.09.2022, and the interim arrangement
            continued till the writ petitions were finally decided.



1    In short “CLU”
2    In short “PPCB”
3    In short “PRTPD Act”
[2026] 3 S.C.R.                                                            187

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


     4.4. By the common judgment and order dated 29.02.2024, the
          High Court dismissed both writ petitions. The High Court noted
          that as on 13.12.2021, the CLU did not have statutory backing
          in the form contemplated by the PRTPD Act. The High Court,
          however, upheld the CLU on the reasoning that the Punjab
          Regional and Town Planning and Development Board granted
          approval in its 43rd meeting dated 05.01.2022. The High Court
          treated the said approval as curing the defect and accepted the
          stand that the land use permissibility stood validated thereafter.
     4.5. The High Court also proceeded on the basis that the decision
          taken by the Planning Board on 05.01.2022 was relatable to the
          power of amendment of the Master Plan. The High Court relied
          upon Section 76 of the PRTPD Act and held that the approval
          recorded in the 43rd meeting dated 05.01.2022 could operate to
          support the CLU and to sustain the proposed industrial activity.
          The High Court further proceeded on the premise that the
          competent authorities had considered the relevant siting aspects
          and that the CLU itself contained conditions and restrictions.
          The High Court observed that if the conditions stipulated in the
          CLU were violated, the affected persons would be at liberty to
          pursue appropriate remedies.
5.   Aggrieved by the dismissal of their writ petitions and by the upholding
     of the CLU dated 13.12.2021, the Appellants have preferred the
     present civil appeals.
6.   We have heard the learned counsel for the parties, and we have gone
     through the comprehensive material on record. In our considered
     opinion, the following questions arise for determination in the present
     appeals:
     I.    Whether the CLU dated 13.12.2021 could have been granted
           for the proposed unit when the land use under the Master Plan
           for Sangrur treated the site as falling in a rural agricultural zone.
     II.   Whether the “approval” recorded in the 43rd meeting of the
           Punjab Regional and Town Planning and Development Board
           dated 05.01.2022 could lawfully cure the admitted defect in the
           CLU and whether such approval is capable in law of operating
           as an alteration or amendment of the Master Plan under the
           PRTPD Act.
188                                                             [2026] 3 S.C.R.

                            Supreme Court Reports


       III.   Whether the siting norms and environmental safeguards,
              including the PPCB notification dated 02.09.1998 and the
              relevant regulatory framework, were complied with in relation
              to the proximity of habitations and the school, and whether the
              process adopted by the authorities satisfies the requirements
              of the prevailing legal norms.
7.     It is apparent that the controversy before us turns principally on
       the statutory scheme governing the Master Plan and control of
       development under the PRTPD Act; and the environmental and siting
       safeguards applicable to a cement grinding unit as in the present case.

       A.     PRTPD Act, the Master Plan, its binding force, and the
              procedure for alteration/revision
       7.1. Chapter X of the PRTPD Act deals with ‘Preparation and
            Approval of Master Plans.’ Under the same, Section 70 of the
            PRTPD Act lays down the foundational statutory scheme for
            the preparation, approval, and legal operation of a Master Plan.
            The same has been reproduced hereunder:
                   “70. Outline Master Plan. - (1) As soon as may be
                   after the declaration of a planning area and after the
                   designation of a Planning Agency for that area, the
                   Designated Planning Agency shall, not later than
                   one year after such declaration or within such time
                   as [the State Government may, from time to time,
                   extend, prepare and submit to the State Government
                   for its approval a plan (hereinafter called the “Master
                   Plan”)] for the planning area or any of its part and
                   the Master Plan so prepared shall –
                   (a) indicate broadly the manner in which the land in
                   the area should be used;
                   (b) allocate areas or zones of land for use for different
                   purposes;
                   (c) indicate, define and provide the existing and
                   proposed highways, roads, major streets and other
                   lines of communication;
                   [(cc) indicate areas covered under heritage site and
                   the manner in which protection, preservation and
[2026] 3 S.C.R.                                                           189

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


                conservation of such site including its regulation and
                control of development, which is either affecting the
                heritage site or its vicinity, shall be carried out.]
                (d) include regulations (hereinafter called “Zoning
                Regulations”) to regulate within each zone the
                location, height, number of storeys and size of
                buildings and other structures, open spaces and the
                use of buildings, structures and land.
                (2) Subject to the provisions of the rules made under
                this Act for regulating the form and contents of the
                Master Plan, any such plan shall include such maps
                and such descriptive matters as may be necessary to
                explain and illustrate the proposals in the Master Plan.
                (3) [As soon as after the Master Plan has been
                prepared under sub – section (1) ,by the Designated
                Planning Agency, the State Government, not later
                than such time, as may be prescribed, shall direct
                the Designated Planning Agency to publish the
                existing land use plan and master plan and the
                place or places, where the copies of the same may
                be inspected, for inviting objections in writing from
                any person with respect to the existing land use plan
                and master plan within a period of thirty days from
                the date of publication.]
                (4) [The State Government, after considering the
                objections and in consultation with the Board, may,
                direct the Designated Planning Agency to modify the
                Master Plan or approve it as such.]
                (5) [The Designated Planning Agency, after approval
                of the State Government, shall publish the final
                Master Plan in the Official Gazette, after carrying
                out the modifications if any, under intimation to the
                State Government within a period of thirty days
                from the date of according approval by the State
                Government.]”
     7.2. The provision makes it clear that the Master Plan is not a
          mere policy document or an internal administrative guideline.
190                                                          [2026] 3 S.C.R.

                          Supreme Court Reports


            It is a statutory instrument which governs how land in the
            planning area is to be used and regulated. The Act places
            the primary responsibility for preparing the Master Plan upon
            the Designated Planning Agency, which is required to prepare
            the plan and submit it to the State Government for approval.
            The contents of the Master Plan, as reflected in the statutory
            scheme, include the identification and allocation of land into
            different zones for specified purposes and the regulatory norms
            that will govern development and land use within those zones.
            Equally significant is the procedure that Section 70 mandates
            before a Master Plan can acquire enforceable effect. The Act
            requires that the proposed Master Plan be brought into the
            public domain, that the public be afforded an opportunity to
            submit objections and suggestions within the prescribed period,
            and that such objections and suggestions be considered by
            the Designated Planning Agency before the plan is placed for
            approval. This is not a procedural formality. It is a statutory
            safeguard intended to ensure transparency, participatory
            planning, and reasoned decision making, particularly because
            zoning and land use decisions have a direct bearing on property
            rights, local habitations, public amenities, and environmental
            and health concerns.
       7.3. The Act then ties enforceability to publication in the Official
            Gazette. In other words, the Master Plan becomes operational,
            and thereby binding for land use regulation, only upon its
            publication in the Official Gazette in the manner contemplated
            by the statute. Section 75 of the PRTPD Act reinforces this
            principle by reiterating that the Master Plan comes into
            operation from the date of such publication, and the same
            reads as follows:
                 “75. [Coming into operation of Master Plan,- The
                 Master Plan come into operation from the date of
                 publication, referred in sub-section(5) of section 70.]”
            The combined statutory scheme indicates that once the Master
            Plan is published and comes into operation, it binds both the
            authorities and the public, and land use permissibility is to be
            determined with reference to its zoning prescriptions unless the
            statute is duly followed to alter or revise the plan.
[2026] 3 S.C.R.                                                           191

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


     7.4. The same statutory discipline governs review and revision.
          Section 76 of the PRTPD Act contemplates periodic review of
          the Master Plan, and it permits revision where the statutory
          authority considers it necessary. Section 76 reads as follows:
                “76(1) At any after time after the date on which the
                Master Plan for an area comes into operation, and
                atleast once after every ten years, after that date, the
                Designated Planning Agency shall after carrying out
                such fresh surveys as may be considered necessary
                or as directed by the [State Government], prepare
                and submit to the Board, a Master Plan after making
                alterations or additions as it considers necessary.
                (2) The provisions of *[Sections 70 and 75] shall
                mutatis mutandis as for as may be possible, apply
                to the Master Plan submitted under sub-section (1).”
           However, the Act does not treat review as a mechanism
           by which land use norms can be altered informally or on
           a case by case basis. The provision expressly applies the
           publication, objection, consideration, and gazette publication
           requirements to a revised Master Plan as well. This legislative
           design ensures that revision of the Master Plan, even when
           undertaken as part of a periodic review cycle, remains subject
           to the same safeguards of notice, participation, and formal
           publication which give the Master Plan its legal force in the
           first place.
     7.5. The Act also provides for the making of minor changes, but
          even that power is not arbitrary. Where changes are proposed
          to the Master Plan, including changes described as minor, the
          statutory scheme requires that the State Government’s direction
          and the fact of change be brought to the notice of the public in
          the manner contemplated by the Act. The underlying principle
          is that a change in zoning or land use permissibility cannot
          rest only upon internal file notings, minutes, or administrative
          approvals. Where the change alters the operative land use
          framework that binds the public and the authorities, the statute
          insists upon transparency and public notice so that the Master
          Plan continues to remain a legally certain and publicly knowable
          instrument of planning regulation.
192                                                         [2026] 3 S.C.R.

                          Supreme Court Reports


       B.   Control of development and “change of land use”
            permissions
       7.6. Once a Master Plan has come into operation in the manner
            contemplated by the PRTPD Act, the statutory command is
            that land use and development within the planning area must
            conform to the zoning and regulatory prescriptions of the Plan.
            Section 79 to 81 in Chapter XI of the PRTPD Act provides for
            the same and has been reproduced hereunder:
                 79. After the coming into operation of any Master Plan
                 in any area, no person shall use or permit to be used
                 any land or carry out any development in that area
                 otherwise than in conformity with such Master Plan:
                 Provided that the Competent Authority may allow the
                 continuance of any use of any land, for a period not
                 exceeding ten year, upon such terms and conditions
                 as may be provided by regulations made in this behalf
                 for the purpose and to the extent, for and to which it
                 was being used on the date on which such a Master
                 Plan came into operation.
                 80. After coming into operation of any Master Plan
                 in any area and subject to the other provisions of
                 this Act, no development in respect of, or change of
                 use of, any land shall be undertaken or carried out,
                 in that area –
                 (a) without obtaining the permission in writing as
                 provided for hereafter; and
                 (b) without obtaining a certificate from the Competent
                 Authority certifying that the development charge or
                 betterment charge as leviable under this Act has been
                 paid or that no such charges are leviable:
                 [Provided that except in the case of development,
                 affecting heritage site or its vicinity, no such
                 permission shall be necessary-]
                 (i) for operational constructions and constructions in
                 the area comprised in the abadi-deh of any village
                 falling inside its Lal Lakir or Phirni;
[2026] 3 S.C.R.                                                             193

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


                (ii) for carrying out such works for the maintenance,
                improvement or other alteration of any building which
                affect only its interior or which do not materially affect
                the external appearance of the building ;
                (iii) [….] for the carrying out by the Central Government
                or the State Government or any local authority of,-
                (a) any work required for the maintenance or
                improvement of a high way, road or public street,
                being work carried out on land within the boundaries
                of such highway, road or public street;
                (b) any work for the purpose of inspecting, repairing
                or renewing any drains, sewers, mains, pipes, cables
                or other apparatus including the breaking open of any
                street or other land for that purpose ;
                (iv) for the excavations (including wells and tubewells)
                made in the ordinary course of agricultural operation
                or for such constructions which are made for
                agricultural purposes subservient to agriculture :
                Provided that such excavation or constructions are
                situated in the areas in which agriculture is permitted
                land use as per the Master Plan ;
                (v) for the construction of unmetalled roads intended
                to give access to land solely meant for agricultural
                purpose.
                81.(1) Any person intending to carry out any
                development in respect of, or a change of use of any
                land or intending to sub-divide his plot or to layout a
                private street shall make an application in writing to
                the Competent Authority for permission in such form
                and containing such particulars and accompanied by
                such documents and plans as may be prescribed.
                (2)(a) In the case of a Department of the State
                Government or the Central Government or a local
                authority intending to carry out any development
                in respect of, or, change of use of, any land, the
                concerned Department or the local authority, as the
194                                                   [2026] 3 S.C.R.

                Supreme Court Reports


       case may be, shall notify in writing to the Competent
       Authority of its intention to do so giving full particulars
       thereof and accompanied by such documents and
       plans as may be prescribed, at least, two months prior
       to the undertaking of such development or change,
       as the case may be.
       (b) Where the Competent Authority has raised
       any objection in respect of the conformity or the
       proposed development either to any Master Plan
       under preparation or to any rules in force at that
       time, or due to any other material consideration, the
       Department of the State Government or the Central
       Government or the local authority, as the case may
       be, shall either make necessary modifications in the
       proposals for such development or change of use to
       meet the objections raised by the Competent Authority
       or submit *[to the State Government the proposal for
       such development or change of use together with
       the objections raised by the Competent Authority
       for decision.]
       (c) The **[State Government] on receipt of such
       proposal together with the objections of the Competent
       Authority shall either approve the proposals with or
       without modifications or direct the Department of
       the State Government or the Central Government
       or the local authority, as the case may be, to make
       such modifications in the proposals as it considers
       necessary in the circumstances.
       (3) Every application under sub-section (1) shall be
       accompanied by such fee as may be prescribed:
       Provided that no fee shall be payable in the case of
       an application made by a Department of the State
       Government or the Central Government.
       (4) On an application having being duly made under
       sub-section (1) and on payment of the development
       charge or betterment charges if any, as may be
       assessed under Chapter XIII, the Competent Authority
       may,-
[2026] 3 S.C.R.                                                         195

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


                (a) pass an order –
                (i) granting permission unconditionally ; or
                (ii) granting permission subject to such conditions as
                it may think necessary to impose ; or
                (iii) refusing permission ;
                (b) without prejudice to the generality of clause (a)
                impose conditions –
                     (i) to the effect that the permission granted is
                     only for a specified period and after the expiry
                     of that period, the land shall be restored to its
                     previous condition or the use of the land so
                     permitted shall be discontinued; or
                     (ii) for regulating the development or use of any
                     land under control of the applicant or for the
                     carrying out of works on any such land as may
                     appear to the Competent Authority expedient.
                (5) The Competent Authority in considering the
                application for permission shall ensure that it is in
                conformity with the provisions of the Master Plan
                prepared or under preparation under this Act and
                where the development or change or use of any land
                is likely in the opinion of the Competent Authority to
                interfere with the operation of the Master Plan or to
                be prejudicial to planned development, or any plan
                for development of the Authority, the Competent
                Authority may refuse such permission.
                (6) Where permission is granted subject to conditions
                or is refused, the grounds of imposing such conditions
                or such refusal shall be recorded in the order and
                such order shall be communicated to the applicant
                in the prescribed manner.
                (7) *[If the Competent Authority does not communicate
                its decision to grant or refuse permission to the
                applicant within a period of sixty days from the
                date of receipt of his application in case other
                than the heritage site, and within a period of one
196                                                           [2026] 3 S.C.R.

                           Supreme Court Reports


                  hundred twenty days in the case of heritage site and
                  development affecting such site, or within a period of
                  sixty days from the date of receipt of reply from the
                  applicant in respect of any requisition made by the
                  Competent Authority, whichever is later, then such
                  permission shall be deemed to have been granted
                  to the applicant on the date immediately following
                  the date of expiry of the later date without prejudice
                  to the provisions of this Act, rules and regulations
                  made thereunder:
                  Provided that any development carried out in
                  pursuance of such deemed permission, which is in
                  contravention of the provisions of the Act, rules and
                  regulations made thereunder, shall be deemed to
                  be an unauthorised development for the purposes
                  of sections 86, 87, 88, 89 and 90.]”
       7.7.   Section 79 is a prohibition in mandatory terms. It does not
              leave the matter to administrative discretion on a case to
              case basis. It interdicts the use of land and the carrying out
              of development in a manner inconsistent with the operative
              Master Plan. The legislative intent is to ensure certainty,
              uniformity, and enforceability in planning control, so that the
              zoning framework is not diluted by ad hoc departures that
              would defeat the Plan’s public purpose.
       7.8.   Section 80 then provides the complementary statutory control.
              Even where a proposed activity is otherwise permissible under
              the Plan, the statute mandates that development or change
              of use can be undertaken only upon written permission of the
              competent authority. This written permission is not conceived
              as a substitute for, or an override of, the Master Plan. It is a
              regulatory permission which must operate within the discipline
              of the Plan and the statute. In other words, Section 80 does not
              create a untrammelled executive power to authorise land use
              contrary to the Master Plan. It creates a permission regime which
              presupposes conformity with the planning framework, and which
              is intended to regulate the manner, conditions, and safeguards
              subject to which permissible development may proceed.
       7.9.   Section 81 sets out the structured decision-making process for
              grant or refusal of permission. The provision contemplates an
[2026] 3 S.C.R.                                                        197

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


            application by the person intending to carry out development,
            a time bound decision by the competent authority, the power to
            impose conditions while granting permission, and an obligation
            to record reasons where permission is refused. The scheme is
            designed to ensure that permissions are granted on relevant
            considerations, that the decision is not arbitrary, and that the
            affected party is informed of the basis of refusal. The deemed
            permission clause is also part of this discipline. It operates
            as a statutory consequence where the authority fails to act
            within the prescribed period. It does not dispense with the
            substantive requirements of conformity with the Master Plan
            or compliance with other applicable laws.
     7.10. The appellate remedy is similarly part of the statutory
           architecture. It provides a supervisory forum within the
           executive framework, but it does not dilute the binding force
           of the Master Plan or the mandatory nature of the statutory
           controls in Sections 79 and 80.

     C.     Environmental clearance and siting safeguards
     7.11. Environmental clearance and siting safeguards stand on a
           distinct but overlapping legal plane. Under the Environment
           (Protection) Act, 1986 and the Environment (Protection) Rules,
           1986, the EIA Notification dated 14.09.2006 (hereinafter referred
           to as the EIA Notification, 2006) is a delegated legislation
           which creates a regime of prior environmental clearance for
           specified projects and activities. The requirement of prior
           environmental clearance is triggered before commencement
           of construction activity or preparation of land at the site. The
           statutory design is preventive. It ensures that environmental
           impacts, mitigation measures, and site-specific concerns are
           assessed at a stage when the project can still be meaningfully
           evaluated, conditioned, modified, or declined.
     7.12. The EIA Notification, 2006 also prescribes a stage wise process
           which includes screening, scoping, public consultation, and
           appraisal. These stages are not interchangeable. Each stage
           serves a distinct function within the regulatory design, and
           public consultation has a specific role in ensuring that persons
           likely to be affected can place their concerns on record and that
           the appraisal is informed by local conditions and stakeholder
198                                                           [2026] 3 S.C.R.

                            Supreme Court Reports


                inputs. Where the project is treated as falling within Category
                “B” under the relevant schedule entry, the appraisal is at the
                State level through the institutional mechanism of the State
                Level Environment Impact Assessment Authority4 and the State
                Expert Appraisal Committee5. This classification determines
                the forum and the process for appraisal. It does not dilute the
                core requirement that the environmental clearance must be
                prior and must be obtained before construction or preparation
                of land.
       7.13. Siting and proximity norms operate as an additional layer
             of safeguards, particularly where habitations and sensitive
             receptors such as educational institutions are involved. The
             PPCB notification dated 02.09.1998 prescribes minimum
             siting distances for cement plants and grinding units, including
             minimum buffers from residential clusters and educational
             institutions, and it also requires development of a green
             belt along the boundary. These norms reflect a regulatory
             framework prescribing that certain minimum separations and
             buffers are required to reduce risk of exposure and nuisance
             from dust, emissions, noise, and traffic. They function as
             minimum protective standards for the purpose of grant of
             consent and related pollution control permissions. Compliance
             with these standards is relevant to evaluate whether the
             regulatory authorities have applied the correct yardsticks
             and whether the safeguards imposed are adequate having
             regard to the site conditions and the proximity of habitations
             and the school.
8.     Having set out the statutory scheme governing planning control and
       the environmental and siting safeguards, we now turn to the three
       issues that arise for determination in these appeals as framed in the
       earlier part of this judgment.

       Issue I: Whether the CLU dated 13.12.2021 could have been
       granted when the site fell in a rural agricultural zone under the
       Master Plan for Sangrur.



4    In short “SEIAA”
5    In short “SEAC”
[2026] 3 S.C.R.                                                           199

      Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


9.    At the outset, it is necessary to notice the legal character of the
      Master Plan for Sangrur and the zoning prescription governing the
      site in question. The material on record, including the reports and
      communications relied upon by the parties, proceeds on the consistent
      premise that the land purchased by Respondent No. 9 fell in a rural
      agricultural zone under the notified Master Plan for Sangrur. It is also
      not in dispute that, as per the zoning permissibility then prevailing,
      a red category industry was not permissible at the said site.
10. In this backdrop, the CLU dated 13.12.2021 has to be tested on its
    own legal footing. This Court has consistently held that a statutory
    development plan is not a mere policy statement. It has binding force
    and regulates land use in the larger public interest. Any development
    contrary to the operative plan is impermissible unless the plan
    itself is altered in the manner known to law. The principle has been
    reiterated in decisions of this Court in K. Ramadas Shenoy v. Town
    Municipal Council, Udipi6 and Bangalore Medical Trust v. B.S.
    Muddappa7, where this Court emphasised that zoning and planned
    development norms cannot be diluted by ad hoc departures at the
    cost of public interest. The relevant portion from Bangalore Medical
    Trust (Supra) is reproduced hereunder:
             “48. Much was attempted to be made out of exercise
             of discretion in converting a site reserved for amenity
             as a civic amenity. Discretion is an effective tool in
             administration. But wrong notions about it results in ill-
             conceived consequences. In law it provides an option
             to the authority concerned to adopt one or the other
             alternative. But a better, proper and legal exercise of
             discretion is one where the authority examines the fact, is
             aware of law and then decides objectively and rationally
             what serves the interest better. When a statute either
             provides guidance or rules or regulations are framed
             for exercise of discretion then the action should be in
             accordance with it. Even where statutes are silent and
             only power is conferred to act in one or the other manner,
             the Authority cannot act whimsically or arbitrarily. It


6    (1974) 2 SCC 506, para nos.26-30
7    (1991) 4 SCC 54
200                                                     [2026] 3 S.C.R.

                     Supreme Court Reports


       should be guided by reasonableness and fairness. The
       legislature never intends its authorities to abuse the law
       or use it unfairly. When legislature enacted sub-section
       (4) it unequivocally declared its intention of making
       any alteration in the scheme by the Authority, that is,
       BDA and not the State Government. It further permitted
       interference with the scheme sanctioned by it only if it
       appeared to be improvement. The facts, therefore, that
       were to be found by the Authority were that the conversion
       of public park into private nursing home would be an
       improvement in the scheme. Neither the Authority nor
       the State Government undertook any such exercise.
       Power of conversion or alteration in scheme was taken
       for granted. Amenity was defined in Section 2(b) of the
       Act to include road, street, lighting, drainage, public works
       and such other conveniences as the government may, by
       notification, specify to be an amenity for the purposes of
       this Act. The Division Bench found that before any other
       facility could be considered amenity it was necessary for
       State Government to issue a notification. And since no
       notification was issued including private nursing home
       as amenity it could not be deemed to be included in it.
       That apart the definition indicates that the convenience
       or facility should have had public characteristic. Even
       if it is assumed that the definition of amenity being
       inclusive it should be given a wider meaning so as to
       include hospital added in clause 2(bb) as a civic amenity
       with effect from 1984 a private nursing home unlike a
       hospital run by government or local authority did not
       satisfy that characteristic which was necessary in the
       absence of which it could not be held to be amenity or
       civic amenity. In any case a private nursing home could
       not be considered to be an improvement in the scheme
       and, therefore, the power under Section 19(4) could not
       have been exercised.
       49. Manner in which power was exercised fell below
       even the minimum requirement of taking action on
       relevant considerations. A scheme could be altered by the
       Authority as defined under Section 3 of the Act. It is a body
[2026] 3 S.C.R.                                                           201

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


           corporate under Section 3 consisting of the Chairman and
           experts on various aspects, namely, a finance member,
           an engineer, a town planner, an architect, the ex-officio
           members such as Commissioner of Corporation of the
           City of Bangalore, officer of the Secretariat and elected
           members for instance, two persons of the State legislature,
           one a woman and other a scheduled caste and scheduled
           tribe member, representative of labour, representative of
           water supply, sewerage board, electricity board, State Road
           Transport Corporation, two elected councillors etc. and the
           Commissioner. This authority functions through committees
           and meetings as provided under Sections 8 and 9. There
           is no section either in the Act nor any rule was placed
           to demonstrate that the Chairman alone, as such, could
           exercise the power of the Authority. There is no whisper
           nor there is any record to establish that any meeting of the
           Authority was held regarding alteration of the scheme. In
           any case the power does not vest in the State Government
           or the Chief Minister of the State. The exercise of power
           is further hedged by use of the expression, if ‘it appears
           to the Authority’. In legal terminology it visualises prior
           consideration and objective decision. And all this must have
           resulted in conclusion that the alteration would have been
           improvement. Not even one was followed. The Chairman
           could not have acted on his own. Yet without calling any
           meeting of the Authority or any committee he sent the
           letter for converting the site. How did it appear to him that
           it was necessary, is mentioned in the letter dated April
           21, because the Chief Minister desired so. The purpose
           of the Authority taking such a decision is their knowledge
           of local conditions and what was better for them. That is
           why participatory exercise is contemplated. If any alteration
           in scheme could be done by the Chairman and the Chief
           Minister then sub-section (4) of Section 19 is rendered
           otiose. There is no provision in the Act for alteration in
           a scheme by converting one site to another, except, of
           course if it appeared to be improvement. But even that
           power vested in the Authority not the government. What
           should have happened was that the Authority should have
202                                                     [2026] 3 S.C.R.

                     Supreme Court Reports


       applied its mind and must have come to the conclusion
       that conversion of the site reserved for public park into a
       private nursing home amounted to an improvement; then
       only it could have exercised the power. But what happened
       in fact was that the application for allotment of the site
       was accepted first and the procedural requirements were
       attempted to be gone through later and that too by the
       State Government which was not authorised to do so. Not
       only that the Authority did not apply its mind and take any
       decision if there was any necessity to alter the scheme but
       even if it is assumed that the State Government could have
       any role to play, the entire exercise instead of proceeding
       from below, that is, from the BDA to State Government
       proceeded in reverse direction, that is, from the State
       Government to the BDA. Every order, namely, converting
       the site from public park to private nursing home and even
       allotment to BMT was passed by State Government and the
       BDA acting like a true subservient body obeyed faithfully
       by adopting and confirming the directions. It was complete
       abdication of power by the BDA. The legislature entrusted
       the responsibility to alter and approve the scheme to the
       BDA but the BDA in complete breach of faith reposed in
       it, preferred to take directions issued on command of the
       Chief Executive of the State. This resulted not only in error
       of law but much beyond it. In fact the only role which the
       State Government could play in a scheme altered by the
       BDA is specified in sub-sections (5) and (6) of Section 19
       of the Act. The former requires previous sanction of the
       government if the estimated cost of executing the altered
       scheme exceeds by a greater sum than five per cent of
       the cost of executing the scheme as sanctioned. And
       later if the ‘scheme as altered involved the acquisition
       otherwise than by agreement’. In other words the State
       Government could be concerned or involved with an altered
       scheme either because of financial considerations or when
       additional land was to be acquired, an exercise which could
       not be undertaken by the BDA. A development scheme,
       therefore, sanctioned and published in the gazette could
       not be altered by the government.”
[2026] 3 S.C.R.                                                         203

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


11. Once a Master Plan has come into operation under Section 70(5)
    of the PRTPD Act read with Section 75 of the PRTPD Act, the
    statutory scheme does not contemplate a permission regime where
    land use contrary to the operative zoning can be authorised merely
    by issuance of a CLU. The prohibition contained in Section 79 of
    the PRTPD Act, read with the written permission requirement in
    Section 80 of the PRTPD Act and the structured decision-making
    framework in Section 81 of the PRTPD Act, makes it clear that a
    CLU is not a source of power to override the Master Plan. A CLU
    operates as a regulatory permission within the statutory discipline of
    the Master Plan. It presupposes that the proposed use is permissible
    under the operative planning framework, or that the framework has
    already been altered or revised in accordance with the procedure
    prescribed by the PRTPD Act. The binding character of the Master
    Plan under Sections 70 and 75 of the PRTPD Act, read with the
    control on development and land use under Sections 79 to 81 of the
    PRTPD Act, requires that land use permissibility be determined with
    reference to the operative zoning prescription. It cannot be displaced
    by ad hoc permissions.
12. It must be emphasized that when a statute prescribes a particular
    manner for doing an act, it must be done in that manner and in
    no other manner. In the present case, where the Master Plan is
    the governing statutory instrument for land use, a departure which
    effectively changes land use permissibility must satisfy the statutory
    procedure for alteration, amendment, or revision contemplated by
    the PRTPD Act. It cannot rest on internal approvals or administrative
    convenience. This is also why the High Court’s recording that, as
    on 13.12.2021, the CLU did not have statutory backing, assumes
    decisive significance. If on the date of its issuance the CLU lacked
    statutory support to permit the proposed use in the relevant zone, the
    defect is not a mere irregularity. It goes to the root of jurisdiction. A
    permission must be lawful when it is granted. It cannot be rendered
    lawful by a later event unless the PRTPD Act itself so provides.
13. The CLU dated 13.12.2021 also proceeds on the footing that the site
    falls within the notified Master Plan and is treated as a non-conforming
    land use zone. In such a situation, a conditional permission issued in
    the course of the Section 80 of the PRTPD Act and Section 81 of the
    PRTPD Act framework cannot be used to invert the statutory order
204                                                        [2026] 3 S.C.R.

                         Supreme Court Reports


       by first granting a CLU in a zone where the use is not permissible
       under Section 79 of the PRTPD Act and then seeking to sustain it
       on the basis of subsequent approvals.
14. We may also note, in this context, that the reliance placed upon
    conditions contained in the CLU, and the observation that affected
    persons may pursue remedies if such conditions are violated,
    cannot answer the foundational objection. Conditions may regulate
    the manner in which a permission that is otherwise lawful may be
    implemented; they cannot supply jurisdiction where the proposed
    land use is impermissible under the operative Master Plan. To accept
    conditions as a substitute for conformity with the Plan would invert
    the statutory order by permitting what is prohibited under Section
    79 of the PRTPD Act first, and leaving compliance with the Master
    Plan to future contingencies.
15. It was also urged that the proposed unit would advance industrial
    development and employment and that the CLU was processed
    under a single-window mechanism. Such considerations cannot
    dilute the binding force of the operative Master Plan or the statutory
    prohibitions governing land use. Administrative facilitation, however
    efficient, must operate within the four corners of the PRTPD Act, and
    cannot legitimise a land use that is impermissible under the Plan.
16. The objection founded on alternate remedy or disputed questions of
    fact does not carry the matter further. The challenge in the present
    appeals goes to the root of statutory competence and legality, namely,
    whether a change of land use contrary to the operative Master Plan
    could be granted at all. Where jurisdictional legality is in issue, the
    matter cannot be non-suited on the plea that factual aspects may
    be disputed.
17. For these reasons, we are of the view that the CLU dated 13.12.2021
    could not have been granted for the proposed unit when, under the
    operative Master Plan for Sangrur, the site fell in a rural agricultural
    zone where the proposed activity was not permissible.

       Issue II: Whether the “approval” recorded in the 43rd meeting
       dated 05.01.2022 could lawfully cure the admitted defect in the
       CLU and whether such approval is capable in law of operating
       as an alteration or amendment of the Master Plan under the
       PRTPD Act
[2026] 3 S.C.R.                                                           205

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


18. We now turn to the reliance placed on the “approval” recorded in
    the 43rd meeting of the Punjab Regional and Town Planning and
    Development Board dated 05.01.2022. The record indicates that the
    item placed before the Planning Board itself described the proposal
    as requiring ex post facto approval, and the minutes record that such
    ex post facto approval was granted. The crucial question, however,
    is not the label applied by the administration, nor the form in which
    the approval is described. The determinative question is whether the
    decision recorded on 05.01.2022 is capable, in law, of operating as an
    alteration or amendment of the Master Plan so as to retrospectively
    validate and cure the admitted defect in the CLU dated 13.12.2021.
19. In our considered view, it is not. Once a Master Plan has come into
    operation under Section 70(5) of the PRTPD Act read with Section
    75 of the PRTPD Act, it acquires statutory force and becomes the
    governing instrument for land use and development within the
    planning area. Any change which has the effect of altering land use
    permissibility, whether described as an amendment, modification,
    or revision, can be brought about only by following the procedure
    expressly prescribed by the statute. The review and revision
    mechanism under Section 76 of the PRTPD Act does not operate in
    isolation. It expressly attracts, by legislative design, the procedural
    discipline embodied in Sections 70 and 75, including publication,
    invitation and consideration of objections and suggestions, and formal
    bringing into operation of the revised position through publication in
    the Official Gazette.
20. A decision recorded in the minutes of a meeting, or an internal
    approval accorded by an executive or statutory body, does not by
    itself amount to an alteration or amendment that has been brought
    into legal operation as part of the Master Plan framework. Section
    76 empowers the initiation of a revisionary process. It does not
    dispense with the mandatory steps that alone give legal efficacy to
    a change in the Master Plan. To treat minutes of a meeting as the
    functional equivalent of a statutory amendment would be to collapse
    the distinction between a proposal to revise and a revision that has
    acquired legal force, and would render the procedural safeguards
    built into the PRTPD Act otiose.
21. This conclusion becomes inescapable where, as in the present case,
    the asserted “approval” has the effect of permitting an otherwise
    impermissible industrial activity in a rural agricultural zone, with direct
206                                                            [2026] 3 S.C.R.

                           Supreme Court Reports


       consequences for residents, habitations, and a functioning educational
       institution. Zoning prescriptions under a Master Plan are not mere
       internal guidelines. They represent a considered legislative balance
       between competing land uses and are intended to protect public
       interest. Any departure which dilutes that balance must satisfy the
       full statutory process prescribed for altering the Plan itself. Executive
       convenience or post facto endorsement cannot be a substitute for
       statutory compliance.
22. Equally, the statutory scheme does not contemplate the curing of
    a jurisdictional defect by retrospective administrative approval. A
    CLU which is unlawful on the date of its grant for want of statutory
    authority does not become lawful merely because a later decision
    purports to validate it, unless the statute expressly confers such a
    power of retrospective validation. The PRTPD Act contains no such
    provision. The legality of the CLU must therefore be tested with
    reference to the law and the operative planning framework as they
    stood on the date the CLU was granted.
23. Therefore, we hold that where the PRTPD Act occupies the field and
    prescribes the manner in which an operative planning instrument
    is to be revised or altered, that manner cannot be substituted by
    executive decision-making or by treating minutes of a meeting as
    the equivalent of an amendment brought into operation under the
    Act. The approach adopted by the High Court, which treats the
    subsequent approval as curing the illegality of the CLU, cannot be
    accepted when the statutory structure does not permit legality to
    be supplied to an act which was unlawful when done, by a later
    administrative approval which does not itself satisfy the mandatory
    requirements governing alteration or revision of the Master Plan.
    The High Court’s approach, which proceeds on the premise that
    an act lacking statutory backing on the date of its issuance may
    nonetheless be sustained by a subsequent ex post facto approval,
    is inconsistent with this statutory structure.
24. It was lastly urged that substantial financial investment has been
    made pursuant to the CLU and that interference at this stage
    would cause prejudice. We are unable to accept this submission.
    Expenditure incurred or steps taken in furtherance of a permission
    that is unlawful or without statutory authority cannot confer legitimacy
    upon the underlying action. No amount of financial investment can
[2026] 3 S.C.R.                                                           207

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


     justify the continuation of an illegal project that operates in derogation
     of the statutory planning framework and directly impacts the rights
     of civilians living in the region.
25. For these reasons, we hold that the “approval” recorded on 05.01.2022
    could not lawfully cure the defect in the CLU dated 13.12.2021, and
    it is not capable, in law, of operating as an alteration or amendment
    of the Master Plan under the PRTPD Act.

     Issue III: Whether the siting norms and environmental safeguards
     applicable to the proposed unit were complied with in the manner
     required by law.
26. The present issue arises at the intersection of two distinct, but
    complementary, safeguards. The first is the requirement of prior
    environmental clearance under the EIA Notification, 2006 before
    commencement of construction activity or preparation of land at the
    site. The second is the siting and proximity discipline applied at the
    level of pollution control permissions, including the siting distances
    prescribed by the PPCB notification dated 02.09.1998 for cement
    plants and grinding units. These safeguards are intended to operate
    in advance. They are designed to prevent avoidable risk to habitations
    and sensitive receptors, including educational institutions, and to
    ensure that regulatory satisfaction is reached on objective material
    and not on assumption.
27. The record indicates that Respondent No. 9 applied for Terms of
    Reference with the SEIAA, Punjab, and that Terms of Reference
    were granted on 28.09.2021 and amended on 25.11.2021. The record
    also indicates that a public hearing was conducted on 19.04.2022
    in connection with the process for environmental clearance, and
    that environmental clearance has not been granted, with the
    parties attributing the pendency to interim orders operating in the
    writ proceedings and thereafter in these appeals. These steps,
    however, do not dilute the basic position that the requirement of
    prior environmental clearance under the EIA Notification, 2006 is not
    a post facto formality. The statutory scheme proceeds on the basis
    that assessment, public consultation, and appraisal must precede
    the commencement of construction activity or preparation of land
    at the site.
208                                                      [2026] 3 S.C.R.

                        Supreme Court Reports


28. Equally, so far as siting is concerned, the PPCB notification dated
    02.09.1998 prescribes minimum distances for cement plants and
    grinding units, including 300 metres from an educational institution
    and 300 metres from a residential area described as a cluster
    of 15 pucca houses, apart from other siting parameters. On the
    material placed before us, Respondent No. 6 has sought to justify
    the grant of the No Objection Certificate dated 14.12.2021 by
    stating that it was based on the SDM certification and a site visit
    dated 17.11.2021. Respondent No. 9 relies upon material which
    states that the school is beyond the prescribed distance when
    measured from the periphery of the proposed site and that there
    is no residential cluster of 15 pucca houses within the prescribed
    radius. The Appellants, on the other hand, dispute this position
    and rely upon material to contend that the school and residential
    habitations are in closer proximity to the proposed site and that the
    prescribed siting safeguards are attracted. The record also refers
    to nearby habitations and other establishments in the vicinity. This
    material, taken as a whole, indicates that the site is not isolated
    and that the proposed unit is in the vicinity of habitations and an
    educational institution, which are precisely the kinds of receptors
    for which siting safeguards exist.
29. A further difficulty arises from the manner in which compliance
    with distance is sought to be established on the material relied
    upon by the authorities. Respondent No. 6 acknowledges that the
    measurement was carried out from the boundary shown by the
    project proponent and then asserts that the distance would increase
    if measured from the source of pollution. This approach does not
    satisfy the minimum regulatory discipline. Siting norms are not
    satisfied by an assumption that the distance may be more when
    measured differently. They require demonstrable compliance on the
    basis of identified emission sources and verified measurements.
    This is more so when, at the relevant stage, the material placed for
    consideration did not demonstrably crystallise the emission sources
    and their configuration in a manner that would permit verified
    assessment of siting compliance on objective parameters. When
    the emission sources and their configuration are not crystallised
    and verified, a conclusion on siting compliance based on boundary
    measurements cannot be treated as a conclusive regulatory
[2026] 3 S.C.R.                                                       209

      Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


      satisfaction, particularly where the school and habitations are
      close to the margin.
30. Respondent No. 9 has also sought to contend that the proposed
    unit is a clinker grinding unit, that it is assessed at the State level
    as a Category “B” project, and that it proposes the use of fly ash
    and control systems such as bag filters. These submissions do not
    answer the core concern we have. Classification for the purposes
    of appraisal under the EIA Notification, 2006 does not displace the
    obligation to comply with siting safeguards. Proposed mitigation
    measures and conditions in a consent to establish do not substitute
    the minimum siting standards, nor do they permit the regulator to
    postpone demonstrable compliance to a later stage. In environmental
    matters, where a school is in close proximity and where there is
    material indicating nearby habitations, the decision-maker must
    proceed on the precautionary approach and must demonstrate, on
    objective material, that the applicable safeguards have been complied
    with. This approach is consistent with the principles reiterated by
    various landmark decisions of this Court in Vellore Citizens’ Welfare
    Forum v. Union of India8, M. C. Mehta v. Union of India9 and
    Hospitality Assn. of Mudumalai v. In Defence of Environment
    & Animals10, among others.
31. The submissions advanced on behalf of Respondent No. 6 (PPCB),
    that the consent to establish/No Objection Certificate was granted on
    the basis of the SDM’s report and a site visit, and that compliance
    with the siting guidelines can be verified at a later stage while
    considering consent to operate, do not meet the legal requirement
    of demonstrable compliance at the threshold. Preventive safeguards,
    by their very design, cannot be treated as matters to be tested
    only after permissions have been granted or after the project has
    advanced. Where the regulatory framework prescribes minimum
    buffers from habitations and educational institutions, the satisfaction
    recorded by the authority must be founded on objective and verifiable
    measurements, and not on an assumption that compliance can be
    ensured later.



8    (1996) 5 SCC 647
9    (1997) 3 SCC 715
10   (2020) 10 SCC 589
210                                                      [2026] 3 S.C.R.

                         Supreme Court Reports


32. Likewise, Respondent No. 9’s reliance on the grant/amendment of
    Terms of Reference, the conduct of public hearing, and proposed
    mitigation measures, does not dilute the requirement that statutory
    safeguards must operate in advance. Proposed control systems
    and future-stage compliances cannot substitute the obligation to
    satisfy siting norms and the discipline underlying prior environmental
    clearance at the relevant time. Nor can subsequent material or
    later regulatory developments be invoked to retrospectively validate
    the legality of permissions already found to be without statutory
    foundation.
33. For these reasons, we are not satisfied that the siting norms and
    safeguards, including the PPCB notification dated 02.09.1998 and
    the regulatory discipline underlying prior environmental clearance
    under the EIA Notification, 2006, were complied with in the manner
    required by law on the material presently relied upon. Issue III is
    accordingly answered in favour of the Appellants.
34. In view of the discussion above, the appeals are allowed.
35. The common judgment and order dated 29.02.2024 passed by the
    High Court of Punjab and Haryana at Chandigarh in CWP No. 20134
    of 2022 and CWP No. 18676 of 2022 is set aside.
36. The Change of Land Use dated 13.12.2021 granted in favour of
    Respondent No. 9 is quashed. Consequently, the No Objection
    Certificate/Consent to Establish dated 14.12.2021 issued from the
    pollution angle in favour of Respondent No. 9, insofar as it proceeds
    on the basis of the said CLU, is also set aside.
37. Pending applications, if any, shall stand disposed of. No order as
    to costs.

       Part II: For Writ Petition (C) 481 of 2025 and Writ Petition (C)
       551 of 2025
38. The appellants in the above civil appeals have also filed the present
    writ petitions under Article 32 of the Constitution of India. The
    appellants in Civil Appeal arising out of SLP (Civil) No. 8316 of 2024
    has instituted WP(C) No. 481 of 2025 and the appellant in Civil Appeal
    arising out of SLP (Civil) No. 8495 of 2024 have instituted WP(C)
    No. 551 of 2025, inter alia, assailing the revised list of industrial
    sector categorization issued by the CPCB in January, 2025 and the
[2026] 3 S.C.R.                                                      211

      Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


      consequential notifications issued by the Ministry of Environment,
      Forest11 and Climate Change12.
39. During the pendency of the above appeals, the CPCB, in January,
    2025, issued a revised list of industrial sector categorisation. Under
    the revised list, the activity described as “stand-alone grinding
    unit without CPP (Captive Power Plant)” was reclassified from the
    “Red” category to the “Orange” category. Shortly thereafter, the
    MoEF & CC issued Notifications GSR 84E dated 29.01.2025 and
    GSR 85E dated 30.01.2025, namely the Control of Air Pollution
    (Grant, Refusal Or Cancellation Of Consent) Guidelines, 2025
    and the Control of Water Pollution (Grant, Refusal or Cancellation
    of Consent) Guidelines, 2025. The Appellants have accordingly
    instituted WP(C) No. 481 of 2025 and WP(C) No. 551 of 2025
    seeking, inter alia, quashing of the revised categorisation and
    the aforesaid notifications to the extent they relax the applicable
    regulatory safeguards for such units.
40. We have gone through the material placed on record in the writ
    petitions, including the revised industrial sector categorisation
    issued by the Central Pollution Control Board in January, 2025,
    the Notifications GSR 84E dated 29.01.2025 and GSR 85E dated
    30.01.2025 issued by the MoEF & CC, and the submissions advanced
    by learned counsel for the parties.
41. In our considered opinion, the question that arises for determination
    in these two Writ Petitions is whether the revised industrial sector
    categorisation issued by the CPCB in January, 2025, insofar as
    it reclassifies the activity described as “stand-alone grinding unit
    without CPP” from the “Red” category to the “Orange” category,
    together with the consequential relaxation of siting and regulatory
    safeguards brought about by Notifications GSR 84E dated
    29.01.2025 and GSR 85E dated 30.01.2025, can be sustained in
    law having regard to the constitutional mandate under Articles 14
    and 21 of the Constitution of India and the governing principles of
    environmental jurisprudence.



11   MoEF
12   Climate Change
212                                                      [2026] 3 S.C.R.

                        Supreme Court Reports


       Rationale advanced by the CPCB for the revised categorisation
42. The determination of the above issue necessarily requires an
    examination of the rationale offered by the Central Pollution Control
    Board for the revised categorisation, the implications of such
    reclassification on preventive environmental safeguards including
    siting norms, and the balance that constitutional and environmental
    law requires to be maintained between developmental considerations
    and the protection of life, health, and the environment.
43. The CPCB has relied upon a revised classification methodology
    based on a modified Pollution Index framework, under which industrial
    activities are assessed on the basis of their potential to cause air
    pollution, water pollution, and waste generation, and are thereafter
    assigned a cumulative pollution index. The stated justification for
    revisiting the 2016 classification is the experience gained over time,
    increased use of cleaner fuels, adoption of cleaner technologies, and
    the need to differentiate between integrated industrial operations
    and standalone units.
44. A central premise of the CPCB’s reasoning is that a stand-alone
    cement grinding unit without a captive power plant has a lower
    pollution potential than an integrated cement plant involving clinker
    manufacturing and kiln operations. On this basis, the CPCB has
    treated such units as a distinct sub-category within the cement sector
    and has placed them in the “Orange” category upon application of
    the revised scoring methodology. The CPCB has also stated that the
    revised methodology was placed in the public domain, representations
    were invited, and the final framework was adopted after examination
    by a duly constituted committee.
45. The CPCB has further asserted that the revised categorisation
    continues to be guided by the precautionary principle and is intended
    to function as a regulatory tool for consent management, inspection
    frequency, siting decisions, and environmental oversight, while also
    incentivising adoption of cleaner fuels and technologies. The PPCB
    has substantially adopted this position and has stated that it has
    implemented the revised categorisation in terms of the directions
    issued by the CPCB.
46. This, in essence, is the rationale advanced by the regulatory
    authorities in support of the revised categorisation. The validity of
[2026] 3 S.C.R.                                                         213

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


     this rationale, when tested against constitutional requirements and
     the governing principles of environmental jurisprudence, now falls
     for consideration.

     Assessment of the CPCB’s rationale and its legal sustainability
47. Having considered the rationale advanced by the CPCB, we are
    unable to accept that the reclassification of a “stand-alone grinding
    unit without CPP” from the “Red” category to the “Orange” category,
    together with the consequential relaxation of regulatory and siting
    safeguards, can be sustained in law.
48. The revised categorisation proceeds on a sector-level assessment
    based on a Pollution Index methodology. While such a framework
    may serve as a regulatory tool for consent management and
    inspection frequency, it cannot be treated as determinative where the
    consequence of reclassification is dilution of preventive safeguards,
    particularly siting norms intended to protect habitations and sensitive
    receptors such as educational institutions.
49. The CPCB’s principal justification rests on a comparative distinction
    between integrated cement plants and stand-alone grinding units,
    on the premise that absence of clinker manufacturing and captive
    power generation necessarily results in lower pollution potential.
    This approach, however, does not address the core concern. The
    relevant question is not whether a stand-alone grinding unit is less
    polluting than an integrated plant in relative terms, but whether its
    pollution potential is sufficiently low to justify a regulatory downgrade
    that materially relaxes safeguards governing proximity to civilian
    habitations.
50. It must be noted that cement grinding units, even without CPP,
    involve extensive handling and processing of powdered material,
    which inherently gives rise to particulate emissions and fugitive dust.
    These emissions have direct public health implications, particularly
    where units are located near residential areas and schools. The
    revised categorisation does not demonstrate, on objective and publicly
    disclosed material, that such exposure risks have diminished to an
    extent that warrants dilution of the precautionary standards earlier
    applied.
51. The reliance on adoption of cleaner fuels and technologies is
    equally unpersuasive. The revised framework proceeds on generic,
214                                                          [2026] 3 S.C.R.

                          Supreme Court Reports


       sector-level assumptions rather than on demonstrated, site-specific
       performance. Preventive environmental regulation does not permit
       safeguards to be relaxed on the assumption that mitigation will suffice
       at a later stage. Where the risk to life and health is foreseeable,
       safeguards must operate at the threshold.
52. Notably, the CPCB itself recognises that the precautionary principle
    governs categorisation and that deviation from a mechanical
    application of methodology is warranted where activities pose a high
    risk of environmental or ecological harm. This recognition undermines
    the argument that a uniform application of the revised methodology
    can justify dilution of siting norms in sensitive contexts. The relaxation
    of minimum siting distances under Notifications GSR 84E dated
    29.01.2025 and GSR 85E dated 30.01.2025 further aggravates the
    concern. Permitting activities with known particulate emission profiles
    to be located closer to habitations and educational institutions, without
    a sector-specific justification demonstrating redundancy of earlier
    safeguards, cannot be regarded as reasonable or proportionate.
53. We are therefore of the view that the revised categorisation and the
    consequential regulatory relaxations elevate a generic classification
    methodology to a position where it overrides preventive environmental
    safeguards, without adequate regard to exposure risks, local
    conditions, or the constitutional obligation to protect life and health.
    Such an approach is inconsistent with the precautionary principle,
    the doctrine of sustainable development, and the content of Article
    21 of the Constitution of India.

       Constitutional threshold for interference with regulatory
       classification
54. As a general rule, this Court exercises circumspection in interfering
    with technical classifications and regulatory frameworks formulated
    by expert bodies. Matters such as industrial categorisation and
    pollution indices ordinarily fall within the domain of specialised
    authorities, and judicial review is not invoked merely because a
    different regulatory choice is possible. Intervention is confined to
    cases where the decision-making process or its consequences
    transgress constitutional limits.
55. However, this principle of restraint cannot apply where a regulatory
    classification has the direct and foreseeable effect of diluting
[2026] 3 S.C.R.                                                         215

      Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


      safeguards that protect fundamental rights. When a classification
      decision results in a blatant erosion of preventive protections
      governing exposure to environmental hazards, the issue ceases to
      be a matter of technical regulation alone and assumes constitutional
      significance.
56. This Court has repeatedly recognised that while judicial restraint is
    the norm in matters involving policy choices and expert regulation,
    environmental adjudication occupies a distinct constitutional
    space. Where executive or regulatory action has the effect of
    exposing communities to foreseeable environmental harm or
    diluting preventive safeguards that protect life and health, judicial
    intervention is not an act of activism but a discharge of constitutional
    duty. This position has been consistently affirmed in landmark
    decisions such as Vellore Citizens’ Welfare Forum v. Union of
    India (Supra), M.C. Mehta v. Union of India (Shriram - Oleum
    Gas) 13, Indian Council for Enviro-Legal Action v. Union of
    India14, and A.P. Pollution Control Board v. Prof. M.V. Nayudu15,
    where this Court held that when scientific uncertainty coexists
    with a credible risk to human health or the environment, courts
    must err on the side of protection. These decisions underscore
    that environmental governance is not immune from constitutional
    scrutiny, and that judicial intervention becomes imperative where
    regulatory choices undermine the fundamental right to a clean
    and healthy environment guaranteed under Article 21 of the
    Constitution of India.
57. In the present case, the revised categorisation and the consequential
    relaxation of siting safeguards materially affect the level of protection
    available to civilians, including residents and school-going children,
    against exposure to industrial pollution. By lowering the regulatory
    threshold applicable to an activity with known particulate emission
    characteristics, the revised framework permits such units to be located
    closer to habitations and educational institutions. The impact is not
    speculative. It directly implicates public health and safety.


13   (1987) 1 SCC 395
14   (1996) 3 SCC 212
15   (1999) 2 SCC 718
216                                                          [2026] 3 S.C.R.

                         Supreme Court Reports


58. The right to life under Article 21 of the Constitution of India
    encompasses the right to a clean and healthy environment.
    Preventive environmental safeguards, including siting norms, are the
    means by which this right is protected. Where such safeguards are
    relaxed without a demonstrable and reasoned basis showing that
    the underlying risk has been materially reduced, the resulting action
    infringes the substantive content of Article 21. Further, Article 14 of
    the Constitution of India also comes into the picture. A regulatory
    downgrade that weakens environmental protection must bear a
    rational nexus to the object of safeguarding life and health. In the
    absence of a proportionate and scientifically substantiated justification,
    such dilution is arbitrary. Arbitrariness that impacts life and health
    cannot be sustained under constitutional scrutiny.
59. The precautionary principle which was recognized as the law of the
    land by this Court under Article 21 of the Constitution of India in
    Vellore Citizens’ Welfare Forum v. Union of India (Supra), and
    which underlines environmental governance in this country, mandates
    that where there is a plausible risk of harm, regulatory frameworks
    must err on the side of protection. In the present case, the revised
    categorisation prioritises sectoral differentiation over preventive
    protection, without adequately addressing exposure risks in sensitive
    contexts. This Court does not interfere with classification merely
    because it concerns industrial activity. The present intervention is
    warranted because the impugned actions have the effect of lowering
    the constitutional minimum of protection guaranteed to affected
    communities. Where regulatory action compromises fundamental
    rights under Articles 14 and 21 of the Constitution of India, judicial
    review becomes a constitutional necessity rather than an intrusion
    into policy.

       Concluding Remarks and Operative Directions
60. Before we proceed to the operative directions, it is necessary to
    underscore, in clear terms, the constitutional balance that must
    govern questions of development and environmental protection.
    Economic development and industrial growth are legitimate and
    important objectives of the State. However, in a constitutional
    framework founded on the rule of law, development is not an abstract
    or absolute goal. It is conditioned by the non-derogable obligation
    to protect life, health, and environmental integrity. Development that
[2026] 3 S.C.R.                                                         217

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


     undermines these foundational values ceases to be constitutionally
     permissible development.
61. We believe that the doctrine of sustainable development is not a
    slogan of compromise but a principle of prioritisation. It requires
    that when developmental activity poses a credible risk to human
    health or environmental safety, regulatory frameworks must err on
    the side of protection. The Constitution does not permit a trade-off
    where civilian life and health are exposed to foreseeable harm on
    the assumption that economic benefit or industrial facilitation justifies
    such exposure. Articles 14 and 21 of the Constitution of India do
    not tolerate a regulatory calculus that treats environmental safety
    as negotiable.
62. If regulatory dilution of the kind impugned in the present case were
    to be accepted, it would mark a fundamental shift in environmental
    governance. Sector-level reclassification, divorced from exposure
    realities and local sensitivities, would become a ready instrument to
    justify siting of polluting activities in close proximity to habitations,
    schools, and other sensitive receptors. Such an approach would not
    remain confined to the present case. It would operate as a precedent,
    enabling progressive erosion of preventive safeguards across regions,
    with cumulative and irreversible consequences. The law does not
    permit environmental protection to be weakened incrementally until
    harm becomes inevitable.
63. Equally important is the recognition that environmental harm, once
    caused, is often irreversible or incapable of full remediation. Public
    health consequences, degradation of air quality, and long-term
    ecological damage cannot be undone by subsequent regulatory
    correction. It is for this reason that environmental regulation is
    designed to be preventive rather than reactive. A regulatory framework
    that allows risk to materialise first and seeks to address consequences
    later is fundamentally incompatible with constitutional environmental
    jurisprudence.
64. At the same time, we reiterate that this Court does not ordinarily
    interfere with technical classifications or policy determinations
    made by expert bodies. Judicial restraint in matters of regulatory
    policy remains a settled principle. However, restraint cannot extend
    to abdication. Where regulatory action results in a lowering of
    the constitutional minimum of protection guaranteed to citizens,
218                                                            [2026] 3 S.C.R.

                           Supreme Court Reports


       particularly in matters affecting life and health, judicial intervention
       becomes a constitutional obligation. The present case falls squarely
       within that exceptional category.
65. For the reasons recorded above, we are of the considered view that
    the revised industrial sector categorisation issued by the CPCB in
    January, 2025, insofar as it reclassifies the activity described as a
    “stand-alone grinding unit without CPP” from the “Red” category
    to the “Orange” category, cannot be sustained in law. The said
    reclassification, read together with the consequential relaxation of
    siting and regulatory safeguards brought about by Notifications GSR
    84E dated 29.01.2025 and GSR 85E dated 30.01.2025, has the
    effect of diluting preventive environmental protections in a manner
    that infringes the constitutional guarantees under Articles 14 and 21
    of the Constitution of India.
66. Accordingly, Writ Petition (Civil) No. 481 of 2025 and Writ Petition
    (Civil) No. 551 of 2025 are allowed to the following extent:
       I.    The revised industrial sector categorisation issued by the CPCB
             in January, 2025 is quashed insofar as it reclassifies the activity
             described as a “stand-alone grinding unit without CPP” from
             the “Red” category to the “Orange” category.
       II.   Notifications GSR 84E dated 29.01.2025 and GSR 85E dated
             30.01.2025 issued by the MoEF&CC are quashed insofar as
             they relax the applicable siting and regulatory safeguards for
             such units on the basis of the aforesaid reclassification.
67. Consequently, any consent, approval or permission that has been
    granted solely on the basis of the aforesaid reclassification of “stand-
    alone grinding unit without CPP” as an “Orange” category activity
    or on the basis of the relaxed siting and regulatory safeguards
    introduced by Notifications GSR 84E dated 29.01.2025 and GSR
    85E dated 30.01.2025 shall not survive and shall stand withdrawn,
    and the concerned authorities shall take all consequential steps in
    accordance with law.
68. We clarify that this judgment shall not preclude the CPCB or the
    MoEF & CC from undertaking a fresh exercise of classification or
    regulatory review in accordance with law, provided that any such
    exercise is supported by a reasoned, transparent, and scientifically
    substantiated assessment, and is consistent with the precautionary
[2026] 3 S.C.R.                                                      219

     Harbinder Singh Sekhon & Ors. v. The State of Punjab & Ors.


     principle and the constitutional mandate to protect life, health, and
     the environment.
69. With the above directions, Writ Petition (Civil) No. 481 of 2025 and
    Writ Petition (Civil) No. 551 of 2025 stand disposed of.
70. Pending applications, if any, shall also stand disposed of.

     Result of the case: Appeals allowed.
                          Writ Petitions disposed of.




     †
         Headnotes prepared by: Nidhi Jain


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Land use under the Master Plan for Sangrur"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.