Created byFuzzy Cloud

Supreme Court of India

GUJARAT COMPOSITE LIMITEDversusA INFRASTRUCTURE LIMITED & ORS.

Citation
2023 INSC 470
Decided
1 May 2023
Disposal
Dismissed

Holding

There is no valid arbitration agreement covering the entire subject‑matter of the suit, so the application under Section 8 cannot be entertained.

Summary

Gujarat Composite Ltd. entered into a licence agreement with A Infrastructure Ltd. in 2005 that contained an arbitration clause, and later entered into a tripartite loan agreement with the same party and Bank of Baroda that lacked any arbitration provision. Disputes arose over possession, loan repayment, and conveyance deeds, leading Gujarat Composite to seek reference to arbitration under Section 8 of the Arbitration and Conciliation Act, 1996. The Commercial Court and the Gujarat High Court rejected the application, holding that the arbitration clause applied only to the original licence agreement and could not be extended to the tripartite agreement or to parties who were not signatories. On appeal, the Supreme Court affirmed that no valid arbitration agreement covered the entire subject‑matter of the suit, that the reliefs sought fell outside the licence agreement’s arbitration clause, and that bifurcation of the cause of action was impermissible. Consequently, the appeals were dismissed.

Issues considered

  • The dispute arising from the tripartite loan agreement and related reliefs is arbitrable under Section 8 of the Arbitration and Conciliation Act, 1996 as amended.
  • Whether an arbitration clause in a principal licence agreement can be read into subsequent agreements and bind parties who are not signatories.
  • Whether the court must refer a matter to arbitration when there is doubt about the existence of an arbitration agreement post‑amendment of Section 8.
  • Whether the cause of action can be bifurcated to refer only the arbitrable portion to arbitration while retaining non‑arbitrable claims in court.

Legislation cited

Subjects

ArbitrationArbitrabilitySection 8Arbitration clauseTripartite agreementNon‑party to arbitrationBifurcation of cause of actionCommercial CourtHigh CourtSupreme CourtMortgageLoanConveyance deed

Judgment

                         [2023] 5 S.C.R. 103                              103


                GUJARAT COMPOSITE LIMITED                                 A
                                  v.
            A INFRASTRUCTURE LIMITED & ORS.
                   (Civil Appeal No. 3259 of 2023)
                            MAY 01, 2023                                  B
[DINESH MAHESHWARI AND SUDHANSHU DHULIA, JJ.]
      Arbitration and Conciliation Act, 1996 – s.8 – Arbitrability
of the dispute in question – Held: Except the principal licence
agreement, none of the other agreements contained any arbitration
                                                                          C
clause, even if they related to the same property and also involved
the appellant and the respondent No.1 – Even if the original licence
agreement is said to be the genesis of the contractual relations of
the appellant and the respondent No.1, that does not ipso facto lead
to the availability of the arbitration agreement in relation to the
dispute in question emanating from the tripartite agreement and           D
which cannot be determined without reference to the said tripartite
agreement and without involving all the parties thereto – Thus, no
dispute resolution process, including arbitration, could be
undertaken in relation to the subject-matter of the suit without
reference to the terms of tripartite agreement and without involving
                                                                          E
the bank-respondent No.2 – This is apart from the fact that the
other elements of dispute pertaining to the subsequent purchasers
too cannot be resolved in any forum without reference to the tripartite
agreement and its amended clause, which did not provide for
arbitration – Thus, there is no doubt about non-existence of
arbitration agreement in relation to the dispute in question –            F
Substantive reliefs claimed in the suits fall outside the arbitration
clause in the original licence agreement – Therefore, the view taken
by the Commercial Court and the High Court in declining the prayer
of the appellant for reference to arbitration u/s.8 cannot be faulted
– Arbitration and Conciliation (Amendment) Act, 2015.
                                                                          G
      Dismissing the appeals, the Court
      HELD: 1.1 Except the principal agreement dated
07.04.2005, none of the other agreements contained any
arbitration clause, even if they related to the same property and
                                                                          H
                                 103
104            SUPREME COURT REPORTS                        [2023] 5 S.C.R.


A     also involved the appellant and the respondent No. 1. The later
      transactions involved other parties too like the tripartite
      agreement dated 06.07.2006 whereby the respondent No. 2 bank
      sanctioned loan to the respondent No. 1 and then, supplemental
      to the said tripartite agreement for dealing with the deposit of
      title deeds. Similarly, the other deeds of conveyance dated
B
      23.01.2015 involve the appellant and the other defendants. The
      submissions made by the appellant with reference to the
      amendment of Section 8 of the Act of 1996 and the later decisions
      of this Court in interpretation of the amended Section 8 do not
      inure to the benefit of the appellant. This is for the simple reason
C     that no such conjunction can be provided to the original licence
      agreement dated 07.04.2005 and the tripartite agreement
      involving the Bank dated 06.07.2006 and 23.01.2008, whereby
      the arbitration clause could be held applicable to the tripartite
      agreement too. This is apart from the fact that in the frame of the
      suit and various other reliefs claimed, involving subsequent
D
      purchasers too and the allegations of fraud, the dispute cannot
      be said to be arbitrable at all. The present one cannot be said to
      be a case involving any “doubt” about non-existence of arbitration
      agreement in relation to the dispute in question. [Paras 17,
      17.1][137-F-G; 138-A-C]
E            1.2 There being no doubt about non-existence of arbitration
      agreement in relation to the entire subject-matter of the suit,
      and when the substantive reliefs claimed in the suits fall outside
      the arbitration clause in the original licence agreement, the view
      taken by the High Court does not appear to be suffering from
F     any infirmity or against any principle laid down by this Court.
      Even if by reference to remote pedigree, the original licence
      agreement is said to be the genesis of the contractual relations
      of the appellant and the respondent No. 1, that does not ipso
      facto lead to the availability of the arbitration agreement in relation
      to the dispute in question, which emanates from the tripartite
G     agreement and which cannot be determined without reference to
      the said tripartite agreement and without involving all the parties
      thereto. In other words, no dispute resolution process, including
      arbitration, could be undertaken in relation to the subject-matter
      of the suit without reference to the terms of tripartite agreement
H     and without involving the bank- respondent No.2. This is apart
  GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                       105
                 LIMITED & ORS.

from the fact that the other elements of dispute pertaining to the    A
subsequent purchasers too cannot be resolved in any forum
without reference to the tripartite agreement and its amended
clause, which did not provide for arbitration. Thus, the ancestry
of the tripartite agreement, in the facts of the present case, does
not lead to the result desired by the appellant. Therefore, even
                                                                      B
on the principles enunciated in Vidya Drolia, the prayer of the
present appellant for reference to arbitration under Section 8
cannot be granted. On the facts and in the circumstances of the
present case and in the nature of transactions as also the nature
of reliefs claimed in the suit, the view taken by the Commercial
Court and the High Court in declining the prayer of the appellant     C
for reference to arbitration cannot be faulted. [Paras 17.2, 18,
18.1 and 20][138-D-H; 140-B-C]
      Vidya Drolia and Ors. v. Durga Trading Corporation
      (2021) 2 SCC 1; Ameet Lalchand Shah and Ors. v.
      Rishabh Enterprises and Anr. (2018) 15 SCC 678 :                D
      [2018] 6 SCR 1001; ONGC Ltd. v. Discovery
      Enterprises (2022) 8 SCC 42; Intercontinental Hotels
      v. Waterline Hotels (2022) 7 SCC 662 – distinguished.
      Sukanya Holdings Pvt. Ltd. v. Jayesh H. Pandya & Anr.
      (2003) 5 SCC 531 : [2003] 3 SCR 558; S. N. Prasad v.            E
      Monnet Finance Ltd. and Ors. (2011) 1 SCC 320 :
      [2010] 13 SCR 207; Deutsche Bank Home Finance Ltd.
      v. Taduri Sridhar and Anr. (2011) 11 SCC 375 : [2011]
      5 SCR 674; Himangi Enterprises v. Kamaljeet Singh
      Ahluwalia (2017) 10 SCC 706 : [2017] 10 SCR 139 –
      referred to.                                                    F

                      Case Law Reference
[2003] 3 SCR 558              referred to             Para 5.2
[2018] 6 SCR 1001             distinguished           Para 6.2
                                                                      G
[2010] 13 SCR 207             referred to             Para 7.5
[2011] 5 SCR 674              distinguished           Para 7.5
[2017] 10 SCR 139             referred to             Para 12

                                                                      H
106                 SUPREME COURT REPORTS                                  [2023] 5 S.C.R.


A           CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3259
      of 2023.
            From the Judgment and Order dated 23.04.2018 of the High Court
      of Gujarat at Ahmedabad in FA No. 588 of 2018.
                With
B               Civil Appeal No. 3260 of 2023.
           Nikhil Goel, Aniruddha Deshmukh, Adhitya Koshy Roy,
      Ms. Naveen Goel, Advs. for the Appellant.
            Ramesh Singh, Sr. Adv., Biju Mattam, Rahul Singh, N D Kaushik,
      Satish Kumar, Avishkar Singhvi, Rohan Sharma, Pradhuman Gohil,
C
      Mrs. Taruna Singh Gohil, Ms. Ranu Purohit, Alapati Sahithya Krishna,
      Dushyant Parashar, Bhaskar, Manu Parashar, Dinesh Pandey,
      Harshvardhan Singh Rathore, Muthuvel Palani M., Advs. for the
      Respondents.
                The Judgment of the Court was delivered by
D
                DINESH MAHESHWARI, J.
                Leave granted.
             2. These appeals have been preferred against the common
      judgment and order dated 23.04.2018 passed by the High Court of Gujarat
E     whereby, the High Court has dismissed First Appeal Nos. 588 of 2018
      and 587 of 2018 filed by the appellant against the order passed by the
      Commercial Court, Ahmedabad dismissing the applications under Section
      8 of the Arbitration and Conciliation Act, 19961 in Commercial Civil Suit
      Nos. 90 of 2017 and 91 of 2017 respectively. Both these appeals, involving
      common questions concerning arbitrability of the dispute, have been heard
F     together and are being taken up for disposal by this common judgment.
             3. It would be apposite to take note of the factual and background
      aspects to the extent relevant for the points arising for determination in
      the present appeals. Given the commonalities of the factual chronology,
      it would be proper to accord primacy to facts of the lead matter i.e., the
G     appeal arising from SLP (C) No. 16932 of 2018 [relating to First Appeal
      No. 588 of 2018 in the High Court, arising from the order passed in
      Commercial Civil Suit No. 90 of 2017], apart from noticing a few facts
      that may be of relevance in the cognate appeal.


H     1
          Hereinafter also referred to as ‘Act of 1996’ or simply ‘the Act’.
      GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                            107
          LIMITED & ORS. [DINESH MAHESHWARI, J.]

        3.1. On 07.04.2005, the appellant herein entered into two licence      A
agreements with respondent No. 1 and the sister concern of respondent
No. 12 (against whom the cognate appeal is filed). The first agreement
with respondent No. 1 was for licensing the operation of two
manufacturing units of the appellant, being A.C. Sheet and Cement
Grinding, with the licensing fee per quarter set at Rs. 5,00,000/- (Rupees
                                                                               B
Five Lakh) for the combined use of land and building as well as factory
machinery and equipment. The second agreement with the sister concern
of respondent No. 1 was for licensing the operation of another
manufacturing unit of the appellant, being A.C. Pressure Pipe, with the
cumulative licensing fee per quarter set at Rs. 2,00,000/- (Rupees Two
Lakh). Both agreements were of the same nature and were executed               C
for a term of 7 years (84 months). The relevant clauses of the agreement
entered into between the appellant and respondent No. 1 could be usefully
reproduced as under: -
          “3. The duration of the Licence for manufacture will be for a
          period of 84 months, extendable to a further period of 84 months     D
          on mutual consent from the date on which the LICENSEE takes
          over production and manufacturing facilities after completion of
          the necessary inspection and the compilation of inventories as
          stipulated herein. The said takeover would be fully and duly
          evidenced by acknowledgement of both the parties in writing, and
          will constitute a pan of this Licence Agreement.                     E
          ***                                      ***                ***
          8. LICENSEE shall pay quarterly licence fee of Rs.1,00,000
          (Rupees One lakh only) per quarter towards the use of land and
          building including office building and Rs.4,00,000 (Rupees Four
          lakhs only) per quarter towards the use of factory machinery &       F
          equipments. The Licence fee shall, be paid within 21 days of end
          of the quarter.
          ***                                      ***                ***
          12. LICENSEE shall not be entitled to mortgage, assign, licence
                                                                               G
          or sublet the said Unit. However, LICENSEE shall be at liberty to
          mortgage/ charge, Raw Material stock, Finished Goods book debts
          and equipment brought in and belonging to LICENSEE under this
          arrangement which shall be kept separately identified and insured.
          ***                                      ***                ***
2
    Hereinafter referred to as ‘sister concern’.                               H
108      SUPREME COURT REPORTS                           [2023] 5 S.C.R.


A     15. The LICENSOR will be entitled to a Bonus, in addition to
      licence fee payable under Clause 8, in consideration of the use of
      its manufacturing facilities, licence, brand goodwill etc, as worked
      out below:
         i. 14% of the profit earned will be the retained profit in this
B        arrangement and balance 86% shall be distributable as under:
            a) The Bonus payable by LICENSEE to LICENSOR under
            this Clause would be 43% of the divisible profit minus the
            licence fee payable as per Clause 8 above. In the event the
            amount of Bonus works out to be negative, then LICENSOR
C           shall be liable to reimburse this amount to LICENSEE on
            quarter to quarter basis.
            b) The retained profit shall always belongs to the
            LICENSEE during the continuation or upon determination
            of the licence period.
D           c) The computation of the Profit & Loss and its distribution
            shall be done quarterly.
         ii. Profit for this purpose means operating profits/losses earned
         during the quarter, after deducting interest on working capital
         and depreciation on the assets added by LICENSEE, but before
E        charging the licence fee specified in Clause 8. The operating
         profit shall be worked out on the basis of Accepted Accounting
         principles.
      ***                                 ***                        ***
      17. The LICENSEE at its absolute discretion may advance some
F
      amount to the LICENSOR on the terms/conditions/security as
      may be mutually agreed to facilitate smooth operation of this
      agreement.
      ***                                 ***                        ***
G     32. Disputes if any, arising out of this Agreement shall be referred
      to arbitration of a Sole Arbitrator if mutually agreed, failing which
      Arbitrator will be appointed as per provisions of Arbitration and
      Conciliation Act, 1996. The venue of Arbitration will be as decided
      mutually but preferably at Delhi.”

H
  GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                                109
      LIMITED & ORS. [DINESH MAHESHWARI, J.]

       3.2. On the same date i.e., 07.04.2005, a supplementary agreement       A
was also executed between the appellant-licensor, respondent-licensee,
and the sister concern as confirming party. As per the terms of this
agreement, appellant requested respondent No. 1 for some financial
assistance to arrive at a settlement with its creditors, employees as well
as statutory authorities for discharging their dues. The respondent No.
                                                                               B
1, therefore, agreed to advance a sum of Rs. 5,30,00,000/- (Rupees Five
Crore Thirty Lakh) to the appellant with interest at 10% p.a. and as
consideration for the financial assistance rendered, it was agreed that
respondent No. 1 would be permitted to create a mortgage on the three
licensed manufacturing units in order to secure the ad hoc advance.
This advance was recoverable in ten quarterly instalments commencing           C
from the 90th day of payment of the ad hoc advance out of the licence
fee and bonus under clauses 8 and 15 of the main agreement. A few
relevant clauses of the supplementary agreement dated 07.04.2005 could
also be usefully reproduced as under: -
      “NOW, THEREFORE, in consideration of the premises and the                D
      mutual covenants set forth herein, and also in the main License
      Agreement dated 7th April 2005 and for other good and valuable
      considerations, the parties hereto hereby agrees as follows:
      1. The LICENSOR requested the LICENSEE for some financial
      assistance to arrive at an amicable settlement with the creditors;       E
      employees and statutory authorities for discharging of their dues.
      2. The LICENSEE, in consideration of facilitating the smooth
      operation of the main agreement dated 7th April 2005 between
      LICENSOR and CONFIRMING PARTY and main agreement
      dated 7 th April 2005 between LICENSOR and LICENSEE                      F
      including smooth operation of A. C. Pipes, A. C. Sheets and
      Cement Units, have agreed to advance a sum of Rs. 5,30,00,000
      (Rupees Five Crores Thirty Lakhs only) to the LICENSOR
      fetching interest at 10% per annum to be calculated at monthly
      rests after receipt of the approval of LICENSOR’S secured
      creditors as per Clause 4 of the main agreement and upon creation        G
      of mortgage on A.C. Sheet, A. C. Pipe and Cement manufacturing
      Unit including building, plant, and machineries in favour of
      LICENSEE for securing the above adhoc advance. LICENSOR
      shall use the said (illegible) for entering into a settlement with its
      secured creditors by making a down payment towards their dues            H
110            SUPREME COURT REPORTS                           [2023] 5 S.C.R.


A           and for payment of balance in an agreed manner and for obtaining
            their consent to the above agreement and to pay and discharge
            various other pressing liabilities of LICENSOR including payment
            of dues of workers, statutory liabilities etc. This advance along
            with interest thereon shall be recoverable in Ten. (10) quarterly
            instalments, commencing from the 90th day of the payment of ad-
B
            hoc advance amount, out of the licence fee payable as per Clause
            8 and Bonus as per Clause 15 of the main Agreement.”
            3.3. Subsequently, clauses 11 and 15 of the original licence
      agreement, (pertaining to repurchase of assets and entitlement of licensor
      to bonus) were amended by means of execution of an amendment
C     agreement dated 25.06.2005 between appellant and respondent No. 1.
      The amended clauses read as under: -
            “Clause- 11: LICENSOR will allow LICENSEE to make
            necessary modification/ addition/ changes in the machinery, building
            or any other fixed assets for smooth operation of the plant. Minor
D           expenses to the extent of Rs.25000/- (Rupees Twenty Five
            Thousand only) may be debited to P&L Account and the expenses
            in excess of specified amount will be capitalized and may be
            funded by both the parties in the following ratio.
            i) Licensor : 43%
E
            ii) Licensee : 57%
            Such expenses to be decided mutually and duly minuted.
            Depreciation on these additions to the fixed assets shall be
            calculated at the rates specified in the Companies Act as per
F           Straight Line Method. Upon determination of the license period
            the LICENSOR would be under obligation to buy these assets at
            the Written Down Value.
            b) Clause No.15 : The LICENSOR will be entitled to a Bonus, in
            addition to license fee payable under Clause-8, in consideration of
            the use of its manufacturing facilities, license, brand goodwill etc.
G
            as worked out below.
            i) The Bonus payable by LICENSEE to LICENSOR under this
            Clause would be 43% of the profit. The Bonus so payable shall
            be reduced by the amount of License fee payable as per Clause-
            8 of the Agreement. However, in the event of loss, the LICENSOR
H
      GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                                111
          LIMITED & ORS. [DINESH MAHESHWARI, J.]

          shall be liable to reimburse 43% of the total loss to LICENSEE on        A
          a quarter-to-quarter basis.
          ii) Computation of the Profit & Loss and its distribution shall be
          provisionally based on the annual audited accounts.
          iii) Profit/Losses for this purpose means profits/losses earned, after
          deducting interest on working capital and depreciation on the assets     B
          added by the LICENSEE but before changing the license fee
          specified in Clause No. 8. The profit/loss shall be worked out on
          the basis of accepted accounting principles.”
        3.4. Thereafter, on 06.07.2006, a tripartite agreement was executed
by and amongst the appellant, respondent No. 1 and respondent No. 2                C
(Bank of Baroda3) upon sanctioning of a loan to the tune of Rs. 500 lakh
to respondent No. 1. The appellant agreed to create first charge on
fixed assets, which was to be released only with the consent of respondent
No. 1. However, it was also stipulated that if payment of corporate loan
was made directly by the appellant to the bank, the first charge could be          D
released without the consent of respondent No. 1. The relevant clauses
of the tripartite agreement dated 06.07.2006 could be usefully reproduced
as follows: -
          “WHEREAS Bank of Baroda has sanctioned Corporate loan of
          Rs.500 lacs to M/s. A Infrastructure Limited on the terms &              E
          conditions stipulated in the sanction letter and to secure this above
          loan in addition to other conditions and corporate guarantee also
          provided by M/s. Gujarat Composite Limited.
          Further M/s. Gujarat Composite Limited has agreed to create
          first charge on the fixed assets as stipulated in the sanctioned         F
          letter in favour of Bank of Baroda.
          Further M/s. Gujarat Composite Limited, has agreed that first
          charges will be released by Bank of Baroda only with the consent
          of M/s. A Infrastructure Limited even after repayment of the said
          loan. Bank of Baroda further agreed to release the first charge
                                                                                   G
          only with the consent of M/s. A Infrastructure Limited. However
          in case M/s. Gujarat Composite Ltd. will make payment of this
          corporate loan of Rs.500 lacs directly to Bank of Baroda. Bank
          of Baroda will release the first charges without the consent of
          M/ s. A Infrastructure Limited”
3
    Hereinafter also referred to as ‘the bank’.                                    H
112            SUPREME COURT REPORTS                           [2023] 5 S.C.R.


A            3.5. An amendment was introduced to the aforementioned
      tripartite agreement on 23.01.2008, so as to restrict the transfer of title
      deeds of the land of appellant during the term of licence agreements.
      The amended condition reads as follows: -
            “Further M/ s. Gujarat Composite Limited, has agreed that First
B           Charge will be released by Bank of Baroda only with the consent
            of M/s. A Infrastructure Limited even after repayment of the said
            loan. Bank of Baroda further agreed to release the First Charge
            only with the consent of M/s. A Infrastructure Limited. However,
            in case M/s. Gujarat Composite Ltd. will make payment of dues
            against this corporate loan of Rs.500 lacs directly to Bank of
C           Baroda, Bank of Baroda will release the First Charge without the
            consent of M/s. A Infrastructure Limited. But M/s Gujarat
            Composite agrees that the title Deeds of the land will not be
            transferred to any other party during the currency of Licence
            Agreements executed between M/s. A Infrastructure Limited and
D           M/s. Gujarat Composite Ltd. “
             3.6. The dispute in the present matter arose after respondent No.
      1, by means of representation dated 22.02.2012, invoked clause 3 of the
      original licence agreement and called upon the appellant to extend the
      term of the licence agreement by a further period of 84 months. This
E     extension was sought because appellant was unable to pay certain dues
      owed to respondent No. 1 and sought time to arrange for payment. In
      response to this representation, the appellant, through letter dated
      29.02.2012, denied the proposal of respondent No. 1 to extend the term
      of licence agreement as also the projected outstanding dues. Later, on
      06.04.2012, which was the date of completion of tenure of the original
F     licence agreement, respondent No. 1 did not hand over possession and
      instead, declared its intention to continue with possession. Between April
      2012 and March 2015, according to the appellant, certain attempts were
      made to resolve the dispute, but to no avail. It is also a part of the case
      of respondent No. 1 that certain parcels of land were transferred to
G     respondent Nos. 3 to 5 in January 2015.
             3.7. Then, on 07.04.2015, the appellant issued notice to respondent
      No. 1 claiming recovery of possession of the manufacturing units as
      well as certain monetary dues. In the notice, the appellant stated that the
      licence had expired by efflux of time without any extension, hence
H     possession by respondent No. 1 was illegal. Further, the appellant claimed
  GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                               113
      LIMITED & ORS. [DINESH MAHESHWARI, J.]

that there was a huge outstanding payable by respondent No. 1. In the         A
reply dated 20.04.2015, respondent No. 1 disputed these claims and
asserted that the appellants had not cared to pay back its legitimately
claimed amounts. Yet again, between 26.08.2015 to 17.11.2016, attempts
were made to resolve the dispute but there was no positive outcome.
Seeing that the attempts to resolve the dispute had failed, on 28.02.2017,
                                                                              B
the appellant served a notice on respondent No. 1 under Section 21 of
the Act of 1996 invoking the provision for arbitration contained in the
licence agreement (clause 32). Respondent No. 1 replied to this notice
on 27.03.2017, contesting the arbitrability of the dispute since it was
inextricably interconnected with other related transactions and unresolved
issues arising therefrom. It was asserted that as the jurisdiction of the     C
arbitrator was derived from the agreement, adjudication of the alleged
dispute would go beyond the scope of the said agreement.
       3.8. In this backdrop of events, the appellant preferred a composite
arbitration petition before the Gujarat High Court on 26.04.2017 being
IAAP No. 63 of 2017 against respondent No. 1 and its sister concern.          D
On the other hand, respondent No. 1-A Infrastructure Limited-filed a
commercial civil suit bearing No. 90 of 2017 before the Commercial
Court at Ahmedabad on 27.04.2017 with the following defendants:
      1. Gujarat Composite Limited
      2. Bank of Baroda                                                       E

      3. Real Home Corporation - a partnership firm
      4. M/s. Raj Corporation (Confirming Party) - partnership firm
      5. RJD Buildcon Ltd.
                                                                              F
       3.8.1. In the said suit, the respondent No. 1 (the plaintiff) made
the prayers for multiple reliefs in the following terms: -
      “33) The Plaintiff therefore prays that:
      (A) This Hon’ble Court may be pleased to direct the defendant
      No.1 to pay to the Plaintiff herein a sum of Rs.32,66 crores with       G
      interest @ 14% per annum from the date of suit till realization
      herein under this decree and any further orders to be passed by
      this Hon’ble Court;
      (B) This Hon’ble Court may be pleased to hold and declare that
      the Deeds of Conveyance dated 23rd January, 2015 registered             H
114            SUPREME COURT REPORTS                           [2023] 5 S.C.R.


A           vide registration no. 742 and 750 executed by defendant No.1 in
            favour of defendant Nos.3 and 5, as null and void;
            (C) This Hon’ble Court may be pleased to permanently restrain
            the defendant Nos.1, 3, 4 and 5 or their agent, executors, or
            administrators from disturbing or obstructing the plaintiffs
B           occupation possession of the suit property till the discharged;
            (D) This Hon’ble Court may be pleased to direct the defendant
            No.2 Bank not to release original title papers and other relevant
            documents in favour of defendant Nos.1, 3 and/or 4;
            (E) This Hon’ble Court may be pleased to hold and declare that
C           the Conveyance Deed dated 23 rd January, 2015 entered into
            between the defendant No. 1 and defendant No. 3 to 5 as null and
            void;
            (F) This Hon’ble Court may be pleased to direct the defendant
            No. 2 to take over all the current assets of the plaintiff pertaining
D           to or in connection with the operation of A.C. Sheet and Cement.
            Manufacturing unit under license agreement at their book value
            and make payment to the plaintiff for the current assets available
            at the time of handing over of the possession, if required.”
             3.9. An application was preferred by the appellant under Section
E     8 of the Act of 1996 in the said commercial civil suit bearing No. 90 of
      2017 for reference of the dispute to arbitration. In the written statement
      of the appellant, objection was also raised against the jurisdiction of the
      Commercial Court, given the arbitration clause in the licence agreement.
      Respondent No. 1 filed a reply to the application and the appellant filed
F     an affidavit in rejoinder to the aforesaid reply on 03.07.2017.
             3.10. In relation to the said application moved by the appellant in
      terms of Section 8 of the Act of 1996, another material factor may also
      be noticed. Two memos (pursis), came to be filed before the Commercial
      Court on 06.12.2017. In one of the memos, the respondent Nos. 3 to 5
      (subsequent purchasers of the property in question) purportedly stated
G
      that they were not having any objection if the dispute concerning them
      was resolved by arbitration proceedings. The appellant, by another memo
      of the even date, suggested that the tripartite amended agreement was
      with reference to the licence agreement and it was agreed that till the
      time of the defendant No. 1 (appellant) making payment of a sum of Rs.
H
  GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                               115
      LIMITED & ORS. [DINESH MAHESHWARI, J.]

5 crore to the plaintiff, the title deeds of the immovable property would     A
remain with the bank. The appellant suggested that with a view that the
dispute between the parties should be resolved by arbitration proceedings,
keeping all contentions open, they would be depositing the said amount
of Rs. 5 crore in the Court and that in this manner ‘the dispute with
defendant No. 2 would be ended’ and then, the bank who was handed
                                                                              B
over the title deed, would deposit the same in the Court and the Court
would be pleased to place the same in sealed cover till the dispute of the
other parties was not resolved by arbitration proceedings.
        3.11. Before adverting to the order passed by the Commercial
Court on the prayer of the appellant for reference to arbitration in terms
of Section 8 of the Act of 1996, we may complete the narration                C
concerning the parallel proceedings in terms of Section 11 of the Act of
1996, even while deviating a little from the chronology. The said IAAP
No. 63 of 2017 was withdrawn on 07.07.2017, as it was a composite
petition against both respondent No. 1 and its sister concern with liberty
to file fresh petitions. Thereafter, two separate IAAPs being IAAP No.        D
90 of 2017 and 89 of 2017 were filed by the appellant but, the proceedings
therein ultimately culminated in the common order dated 15.12.2017.
The High Court dismissed those applications in view of the fact that the
prayer of the appellant in terms of Section 8 of the Act had been rejected
by the Commercial Court on 13.12.2017 but, with liberty to the appellant
to file afresh under Section 11 of the Act after decision on the challenge    E
to the order so passed by the Commercial Court. Be that as it may, this
aspect is not as such relevant for the present purpose and could be left
at that.
       4. The Commercial Court at Ahmedabad, in the order dated
13.12.2017, rejected the application of the appellant under Section 8 of      F
the Act of 1996. It was held that there was no arbitration clause in the
tripartite agreement and no reference had been made to the original or
supplementary licence agreement to give effect or consider the arbitration
clause as a part and parcel of the tripartite agreement. While referring
to clause 32 of the Licence Agreement dated 07.04.2005, the Court             G
observed that it was explicitly clear that the arbitration clause was
applicable to the appellant and respondent No. 1, specifically in reference
to the original licence agreement and supplementary licence agreement
but the same could not be extended to apply to subsequent transactions
and agreements with different parties.
                                                                              H
116            SUPREME COURT REPORTS                          [2023] 5 S.C.R.


A            4.1. In consonance with the aforementioned observations, the
      Commercial Court also held that there must be a valid arbitration
      agreement in order to invoke the powers of the Court to refer the parties
      to arbitration under Section 8 of the Act of 1996. It was further observed
      that persons who are not parties to the arbitration agreement cannot be
      referred to arbitration, as the binding effect would only apply to the
B
      parties thereto, i.e., the appellant and respondent No. 1. Hence, if the
      dispute was between parties and non-parties to the arbitration agreement,
      appointment of arbitrator could only be made with respect to the parties.
      The relevant parts of the order passed by Commercial Court could be
      usefully reproduced as under: -
C           “15….As such, no arbitration clause seems to have been inserted
            nor any reference has been made as to the License Agreement
            or Supplementary License Agreement executed between the
            plaintiff and defendant No. 1 so as to give effect and to consider
            as a part and parcel of the tripartite agreement executed between
D           the plaintiff, defendant No. 1 and defendant No. 2.
            16. Even perusing item No. 32 of the Licence Agreement dated
            07/04/2005 executed between the plaintiff and defendant No. 1
            wherein it has been expressly agreed upon between the parties
            thereto that dispute, if any, arising out of this Agreement shall
E           be referred to arbitration…..Thus, it is explicitly clear that the
            arbitration clause is binding to the plaintiff and defendant No. 1
            only and that too pertaining to the Licence Agreement/
            Supplementary Licence Agreement and cannot be given effect
            and extended and made applicable to the subsequent transactions
            and/or agreements so executed between the plaintiff and
F           defendant No. 1 with the strangers.
            ARBITRATION AGREEMENT:
            17. Now the question arises is as to what is an “arbitration
            agreement” and/or “a valid arbitration agreement”? To meet
G           with the aforesaid issue, the provisions of Section 7 of the
            Arbitration Act requires to have a glance wherein the arbitration
            agreement means an agreement between the parties to submit to
            arbitration of or certain disputes which have arisen or which may
            arise between them in respect of a definite legal relationship,
            whether contractual or not.
H
    GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                                           117
        LIMITED & ORS. [DINESH MAHESHWARI, J.]

        18. It is further provided that the arbitration agreement must be in                A
        writing and signed by the parties and also in exchange of statement
        – defence in which the existence of the agreement is alleged by
        one party and not denied by the other party.
        19. Thus, considering the facts of the case on hand while applying
        the provisions of Section 7 of the Arbitration Act, the powers of                   B
        the Court to refer the parties to arbitration are subject to fulfilment
        of the required conditions i.e. there should be an arbitration
        agreement and if the Court finds that no valid arbitration agreement
        exists between the parties, then to invoke the powers under
        Section 8 and the issue thereof does not arise.
                                                                                            C
        20. Hence, on the aforesaid account and as discussed in the
        foregoing paragraphs, the clause of arbitration so inserted is
        between the plaintiff and defendant No.1 as inserted in the Licence
        Agreement and the same cannot be applied to the subsequent
        transactions and with the persons who are not the parties to the
        arbitration agreement who cannot be compelled to or referred to                     D
        arbitration. Hence, in view of the aforesaid, the arbitration clause,
        the binding effect applies to the plaintiff and defendant No.1 only
        and cannot be extended to the rest, admittedly who are not the
        parties to the arbitration agreement.
        21. Thus, the sum and substance of the aforesaid discussion is                      E
        that the reference to the arbitration is possible only if there is a
        valid arbitration agreement between the parties, but if the dispute
        is between the parties to an arbitration with the other parties as
        also non-parties to the arbitration agreement, a reference to the
        arbitration or even the appointment of the arbitrator can only be                   F
        made with respect to only the parties to the arbitration agreement
        and not the non-parties.”
       4.2. In terms of the requirements of Section 8 of the Act of 1996
the Commercial Court held that the matter could be referred to arbitration
only if it were a part of the subject-matter of the agreement. The reliefs                  G
sought by the plaintiff involved its challenge to the conveyance deeds as
violative of the undertaking submitted before the Industrial Tribunal as
also the fact that the transaction was entered into during the operation
of stay granted by the High Court4. Thus, this would not fall within the
4
 We have not elaborated on the other litigations wherein the said orders were passed,
for being not entirely necessary in relation to the core question involved in the matter.   H
118             SUPREME COURT REPORTS                           [2023] 5 S.C.R.


A     scope of adjudication. The Commercial Court further held that the issue
      of mortgage was not arbitrable. In essence, the considerations of the
      Commercial Court had been that the relief sought by the plaintiff related
      to several other transactions which did not provide for arbitration as a
      dispute resolution mechanism. It was observed that the challenge to the
      conveyance deed and also the relief sought against the bank to not release
B
      documents in favour of appellant would only be capable of adjudication
      by the Courts and could not be resolved by arbitrator.
             4.3. Another ancillary observation had been that the conduct of
      respondent Nos. 3 to 5 would indicate collusion with the appellant during
      pendency of litigation. Thus, in substance, it was held that the issues in
C     question were not connected with the licence agreement and that there
      was no valid arbitration agreement between the plaintiff and the rest of
      the defendants apart from defendant No. 1 (appellant). The Commercial
      Court further clarified that a partial reference to arbitration would not be
      possible because the cause of action could not be split into separate
D     parts.
             5. In appeal, the decision of the Commercial Court was upheld by
      the High Court, after extensively taking note of the material aspects of
      the pleadings in plaint and the rival submissions as also the principles
      enunciated in the cited decisions, with the finding that it would not be
E     proper to bifurcate the disputes in terms of arbitrable and non-arbitrable
      disputes.
             5.1. As regards the suit in respect of a matter which falls partly
      within and partly outside the arbitration agreement, and also involves
      non-parties as well as parties, it was held that Section 8 of the Act of
F     1996 would not be attracted, in reference to several decisions of this
      Court. The High Court observed that the licence agreements were only
      executed between the appellant and respondent No. 1 and respondent
      Nos. 2 to 5 were not party to the agreement. There was a tripartite
      agreement between the appellant, respondent No. 1 and the bank,
      however, it was an admitted position that no arbitration agreement existed
G     in that regard. Further, the tripartite agreement was an independent
      agreement for mortgage by deposit of title deeds. It was further observed
      by the High Court, as had also been observed by the Commercial Court,
      that the appellant had breached the injunction granted by the High Court
      as well as the undertaking before the Industrial Tribunal by selling some
H     of the properties to respondent Nos. 3 to 5. Referring to the plaint
  GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                                119
      LIMITED & ORS. [DINESH MAHESHWARI, J.]

averments, the High Court took note of the reliefs sought by respondent        A
No. 1 and the parties against whom reliefs were sought as also the
pleadings with respect to cause of action in the following words: -
      “[8.5] In the present case as observed herein above there are
      license agreements containing the arbitration clause, executed
      between the plaintiff and the original defendant No.1 on one hand.       B
      Admittedly, the original defendant Nos.2 to 5 are not party to the
      arbitration agreement. There is a tripartite agreement between
      the original plaintiff, original defendant No.1 and the original
      defendant No.2 (Bank of Baroda) under which the plaintiff and
      the original defendant No.2 have prayed the reliefs. It is an
      admitted position that in the tripartite agreement between the           C
      original plaintiff, original defendant No.1 and the original defendant
      No.2 (Bank of Baroda), there does not exist any arbitration
      agreement. Under the tripartite agreement the original defendant
      No.1 has placed the title deeds and the said tripartite agreement
      as such can be said to be an independent agreement and under             D
      the said tripartite agreement there is a mortgage by deposit of title
      deeds in respect of immovables and hypothecation of movables.
      It appears that the said tripartite agreement was executed while
      sanctioning a corporate loan of Rs.500 lakh in favour of the original
      plaintiff and the charge and mortgage has been created in favour
      of Bank of Baroda – original defendant No.2. It appears that             E
      during the pendency and subsistence of the aforesaid mortgage
      and as alleged by the original plaintiff surreptitiously and in breach
      of the injunction granted by this Court as well as the undertaking
      before the Industrial Tribunal, the original defendant No.1 has
      sold some of the properties (mortgaged properties) in favour of          F
      original defendant Nos.3 to 5. In light of the above broad facts
      and averments in the plaint, pleadings on the cause of action and
      the reliefs sought are required to be considered.
      [8.6] In the plaint in Commercial Civil Suit No.90/2017, the plaintiff
      has sought the relief against the following defendants:                  G
      1. Gujarat Composite Limited
      2. Bank of Baroda
      3. Real Home Corporation - a partnership firm
                                                                               H
120            SUPREME COURT REPORTS                             [2023] 5 S.C.R.


A           4. M/s. Raj Corporation (Confirming Party) - partnership firm
            5. RJD Buildcon Ltd.
                   The suit is filed for recovery of legitimate dues, cancellation
            of sale deed and for permanent injunction. In the suit the plaintiff
            has prayed for the following reliefs.
B
               “(A) This Hon’ble Court may be pleased to direct the defendant
               No.1 to pay to the Plaintiff herein a sum of Rs.32.66 Crores
               with interest @ 14% per annum from the date of suit till
               realization herein under this decree and any further orders to
               be passed by this Hon’ble Court;
C
               (B) This Hon’ble Court may be pleased to hold and declare
               that the Deeds of Conveyance dated 23 rd January, 2015
               registered vide registration no. 742 and 750 executed by
               defendant No.1 in favour of defendant Nos.3 and 5, as null
               and void;
D
               (C) This Hon’ble Court may be pleased to permanently restrain
               the defendant Nos.1, 3, 4 and 5 or their agent, executors, or
               administrators from disturbing or obstructing the plaintiffs
               occupation possession of the suit property till the plaintiff claim
               made in para (a) and (b) above is fully discharged;
E
               (D) This Hon’ble Court may be pleased to direct the defendant
               No. 2 Bank not to release original title papers and other relevant
               documents in favour of defendant Nos.1, 3 and/or 4;
               (E) This Hon’ble Court may be pleased to hold and declare
               that the Conveyance Deed dated 23rd January, 2015 entered
F
               into between the defendant No. 1 and defendant No. 3 to 5 as
               null and void;
               (F) This Hon’ble Court may be pleased to direct the defendant
               No. 2 to take over all the current assets of the plaintiff pertaining
               to or in connection with the operation of A.C. Sheet and Cement
G              Manufacturing unit under license agreement at their book value
               and make payment to the plaintiff for the current assets available
               at the time of handing over of the possession, if required.”
            [8.7] Necessary pleadings in the plaint with respect to cause of
      action are as under:
H
GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                             121
    LIMITED & ORS. [DINESH MAHESHWARI, J.]

  1. The cause of action has arisen when the defendant No. 1,             A
  behind the back of the plaintiff, entered into Conveyance Deed
  with defendant no. 3 and defendant No. 5.
  2. Even the original title deeds and other documents partially
  pertaining to the suit property are in the custody of defendant No.
  2 Bank and by suppressing the fact that the plaintiff has absolute      B
  right over the suit property qua possession, the defendant No. 1
  has entered into Conveyance Deed with defendant No. 3 and
  defendant No. 5 stating that suit property is free from any
  encumbrance and/or mortgage.
  3. That the cause of action for filing the suit has arisen because      C
  the defendant No. 3 and defendant No. 5 made an application to
  mutate the entry in the revenue record in regard to the Deed of
  Conveyance. As the plaintiff is legitimately in possession of the
  suit property by virtue of license agreement, supplementary
  agreement, tripartite and amended tripartite agreement, it
  vehemently opposed the said entry and ultimately the authority          D
  concerned rejected the application of the defendant No. 3 and
  defendant No. 5 for mutation of entry in regard to Conveyance
  Deed. Thus the mutation entry with regard to mortgage of the
  suit property with defendant No. 2 Bank still exists and the
  defendant No. 2 Bank has not removed/revoked the said mortgage.         E
  4. That though the plaintiff is in possession of the suit property by
  virtue of license agreement, supplementary agreement, tripartite
  agreement and amended tripartite agreement, the defendant No.
  1; behind the back of the plaintiff, entered into Conveyance Deed
  with defendant No. 3 and defendant No. 5.                               F
  5. The defendant No. 1 even did not part with the sale
  consideration with the plaintiff which it has received from defendant
  No. 3 and defendant No. 5 for conveying the suit property to
  defendant No. 3 and defendant No. 5.
  6. That the cause of action for filing the suit has arisen also as      G
  defendant No. 1 had defaulted in repayment to Punjab National
  Bank and hence was not in a position to get any loan whatsoever
  in its own capacity from any financial institution, and as it was in
  need of financial assistance, defendant No. 1 requested the plaintiff
  for financial help, because of which plaintiff obtained corporate
                                                                          H
122             SUPREME COURT REPORTS                           [2023] 5 S.C.R.


A           loan of Rs. 05.00 Crores on its name from defendant No. 2 and
            advanced the same to defendant No. 1.
            7. Even during the currency of the license agreement, plaintiff
            has paid other amounts also for and on behalf of the defendant
            No. 1 towards wages to the workers, revenue taxes, electricity
B           bills, excise duty, etc.
            8. The cause of action has arisen because in lieu of all these
            financial help from plaintiff, defendant No. 1 entered into tripartite
            agreement and subsequently amended tripartite agreement with
            plaintiff and defendant No. 2 Bank, whereby defendant No. 1
C           mortgaged the suit property with defendant No. 2 Bank and stood
            as guarantor towards the corporate loan which was obtained by
            plaintiff in its name to help out the defendant No. 1, wherein it has
            been specifically agreed by defendant No. 1 that unless all and
            full legitimate dues of the plaintiff has been paid up, plaintiff shall
            enjoy the possession of the suit property.
D
            9. That the cause of action for filing of the suit has arisen also
            because the plaintiff has to recover Rs. 32.66 Crores from the
            defendant No. 1 towards corporate loan and other amount, which
            the plaintiff has advanced to the defendant No. 1.”

E            5.2. As far as the first relief under paragraph 33(A) was
      concerned, whereby respondent No. 1 sought recovery of Rs. 32.66
      crore with interest @ 14% p.a. from the date of suit till realisation, the
      High Court observed that this relief would lie against the appellant who
      would be bound by the arbitration clause in the licence agreement. The
      rest of the prayers were against respondent No. 2 - the bank, and
F     respondent Nos. 3 to 5 - the subsequent purchasers, who were not parties
      to the arbitration agreement. In the opinion of the High Court, the fact
      that the reliefs were all interconnected and on the basis of multiple causes
      of action, the dispute could not be bifurcated. Thus, the High Court applied
      the law laid down in Sukanya Holdings Pvt. Ltd. v. Jayesh H. Pandya
G     & Anr.: (2003) 5 SCC 531 and other referred decisions, to hold that
      there was no error by the Commercial Court in rejecting the application
      under Section 8 of the Act of 1996. The relevant observations of the
      High Court are as follows: -
            “[8.8] Considering the above and the reliefs prayed / sought in the
            suit, it can be said that the prayer in terms of para 33(A) can be
H
  GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                                123
      LIMITED & ORS. [DINESH MAHESHWARI, J.]

      said to be against the original defendant No.1 who is a party to         A
      the arbitration agreement contained in the license agreement.
      Prayer in terms of paras 33(B), 33(C) and 33(E) can be said to be
      against the original defendant No.1 and original defendant Nos.3
      to 5. Original defendant Nos.3 to 5 are not party to the arbitration
      agreement and as such they are third parties who have alleged to
                                                                               B
      have purchased the properties from the original defendant No.1
      during the subsistence of the license agreement as well as they
      have purchased the said property surreptitiously. The prayer in
      terms of paras 33(D) and 33(F) can be said to be against the
      original defendant No.2 – Bank of Baroda who admittedly is not
      a party to the arbitration agreement. All these reliefs are              C
      interconnected and the reliefs sought in the plaint are on the basis
      of multiple cause of actions and multiple reliefs against the
      defendants and it is not possible to bifurcate the dispute in the suit
      between the plaintiff and the original defendant No.1 (parties to
      the arbitration agreement) and the original plaintiff and the original
                                                                               D
      defendant Nos.2 to 5 (nonparties to the arbitration agreement).
      Therefore, applying the law laid down by the Hon’ble Supreme
      Court in the case of Sukanya Holdings (P) Ltd. (Supra) and other
      decisions referred to herein above, it cannot be said that the learned
      Commercial Court has committed any error in rejecting section 8
      application and refusing to refer the matter / dispute in the suit for   E
      arbitration.
      ***                         ***                        ***
      [8.13] Considering the facts and circumstances of the case narrated
      herein above and the law laid down by the Hon’ble Supreme Court
      in the case of Sukanya Holdings Pvt. Ltd. (Supra) and other              F
      decisions referred to herein above, it cannot be said that the learned
      Commercial Court has committed any error in rejecting the
      application under Section 8 of the Arbitration Act, 1996 and
      refusing to refer the dispute / matter for arbitration. On facts it is
      not proper, advisable and/or possible to bifurcate the disputes viz.     G
      arbitrable and nonarbitrable. We are in complete agreement with
      the view taken by the learned Commercial Court while rejecting
      the application under Section 8 of the Arbitration Act, 1996.”
      5.3. Accordingly, the High Court proceeded to dismiss both the
appeals and thereby affirmed the order passed by the Commercial Court          H
124             SUPREME COURT REPORTS                             [2023] 5 S.C.R.


A     in rejection of the applications moved by the appellant under Section 8 of
      the Act of 1996. Hence, these appeals.
             6. Learned counsel for the appellant has, after reference to the
      background aspects, strenuously argued that the Commercial Court and
      the High Court have erred in law as also on facts in declining the
B     applications moved by the appellant in terms of the amendment to Section
      8 of the Act of 1996; and with reference to the later decisions of this
      Court including the 3-Judge Bench decisions, has contended that the
      impugned judgment and orders deserve to be set aside and the applications
      made by the appellant deserve to be allowed.
C             6.1. Learned counsel for the appellant has contended that the
      civil suits in question and the application therein for referral to arbitration
      were filed subsequent to the amendment to Section 8 of the Act of 1996
      in the year 2015, and therefore, the present matter is governed by the
      amended Section 8 whereby and whereunder, there is no choice but to
      refer the parties to arbitration, even for deciding the arbitrability of the
D     dispute.
              6.2. Learned counsel has argued that though the High Court relied
      on the decision of this Court in Sukanya Holdings (supra) but the same
      has been doubted and distinguished in various decisions of this Court
      subsequently. In this regard, learned counsel has referred to various
E     decisions in which the said decision in Sukanya Holdings was
      distinguished or clarified; and has particularly referred to the decision in
      Ameet Lalchand Shah and Ors. v. Rishabh Enterprises and Anr.:
      (2018) 15 SCC 678 and a 3-Judge Bench decision in the case of Vidya
      Drolia and Ors. v. Durga Trading Corporation: (2021) 2 SCC 1.
F     Learned counsel would submit that now, the law pertaining to Section 8
      of the Act of 1996 is solely interpreted keeping in view the amendment
      to it. With reference to the case of Vidya Drolia (supra) learned counsel
      has submitted that two major principles have been laid down therein:
      one, that only those cases that are ‘deadwood’ should not be referred to
      arbitration; and second, that whenever there is doubt, the correct course
G     is to refer to arbitration. Further placing reliance on ONGC Ltd. v.
      Discovery Enterprises: (2022) 8 SCC 42 and Intercontinental Hotels
      v. Waterline Hotels: (2022) 7 SCC 662 he has submitted that unless
      the issue before the Court patently indicates existence of deadwood,
      Courts should ensure that arbitration is carried on. Learned counsel would
H     submit that the High Court has adopted a rather restrictive interpretation
  GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                               125
      LIMITED & ORS. [DINESH MAHESHWARI, J.]

of the Act of 1996 in the order impugned, which deserves to be set            A
aside.
       6.3. Learned counsel for appellant has also submitted that the
mandate of Act of 1996 would have ensured the completion of
proceedings within a year, with a reduced scope of interference in the
possible Section 34 proceedings at the instance of either party, but the      B
matter has remained pending with only framing of issues. Learned
counsel would further submit that the licensees are squatting over the
property, under a licence agreement dating back to the year 2005, without
performing any work and have illegally and unauthorisedly prevented
the appellant, who is the owner of the property, from dealing with it.
Learned counsel has underscored the point that the respondent No. 1           C
has not denied the existence of a dispute, but merely argues that the said
disputes cannot be resolved through arbitration due to the involvement
of the bank, an argument that cannot withstand legal scrutiny.
       7. Per contra, learned counsel for the contesting respondent has
also referred to the background aspects and various transactions as also      D
the grievance of the plaintiff- respondent No. 1 to submit that the dispute
as involved in the suit has rightly not been referred to arbitration.
       7.1. Learned counsel for the contesting respondent would submit
that the underlying civil suits are spread over various agreements/
transactions and involve various parties where except the appellant none      E
of the other defendants are parties to the arbitration agreement which is
contained only in the main licence agreement dated 07.04.2005. It has
also been submitted that the cause of action of the suits in question goes
beyond the transaction containing the arbitration agreement where even
the case of serious fraud has been alleged against the appellant and the      F
dispute also pertains to mortgage. It has been particularly emphasised
that the tripartite agreement involving the appellant, respondent No.1
and Bank of Baroda lacks arbitration clause; and the dispute emanating
from the tripartite agreement and also pertaining to the questioned deeds
of conveyance cannot be correlated with the arbitration agreement in
the main licence agreement dated 07.04.2005.                                  G
       7.2. Learned counsel has also argued that for a matter to be
referred to arbitration, the entire subject-matter should be subject to
arbitration and while relying on Sukanya Holdings (supra), has submitted
that the suit cannot be bifurcated partially to refer a part of the suit to
arbitration and to allow the rest of it to continue. It has further been      H
126             SUPREME COURT REPORTS                             [2023] 5 S.C.R.


A     submitted that the reliefs claimed in the suits in question fall outside the
      licence agreement and the disputes pertaining to different agreements/
      transactions and causes of action arising therefrom goes beyond the
      arbitration agreement.
             7.3. Learned Counsel has further submitted that the supplementary
B     agreement dated 07.04.2005 is ancillary to original agreement dated
      07.04.2005 executed between the appellant and respondent No. 1 but,
      the said tripartite agreement does not have any ancillary relationship
      with the main agreement and the tripartite agreement having Bank of
      Baroda as a party is independent of the original agreement.
C            7.4. Learned counsel also highlighted the amendment in the Act
      of 2015, wherein Section 8 was amended envisaging that if the judicial
      authority is of the opinion that prima facie the arbitration agreement
      exists, then it shall refer the dispute to arbitration, and leave the existence
      of the arbitration agreement to be finally determined by the arbitral
      tribunal. However, if the judicial authority concludes that the agreement
D     does not exist, then the conclusion will be final and not prima facie. The
      amendment also envisages that there shall be a conclusive determination
      as to whether the arbitration agreement is null and void.
             7.5. Learned counsel has also placed reliance on S.N. Prasad v.
      Monnet Finance Ltd. and Ors.: (2011) 1 SCC 320 and Deutsche
E     Bank Home Finance Ltd. v. Taduri Sridhar and Anr.: (2011) 11
      SCC 375 wherein guarantors were not held to be bound by arbitration
      agreement as they were not party to tripartite agreements having
      arbitration clause. Learned counsel would also submit that the decisions
      relied upon by the appellant do not apply to the present case because of
F     non-existence of arbitration agreement in relation to dispute in question.
            8. We have given anxious considerations to the rival submissions
      and have examined the record with reference to the law applicable.
            9. For dealing with the vexed question in these appeals as to
      whether the parties were required to be referred to arbitration by allowing
G     the applications moved by the appellant under Section 8 of the Act of
      1996, appropriate it would be to take note of the provisions contained in
      Section 8, as existing before its amendment by Act 3 of 2016 (w.r.e.f.
      23.10.2015) and as existing now.
             9.1. Earlier, Section 8 of the Act of 1996 read as under: -
H
  GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                                 127
      LIMITED & ORS. [DINESH MAHESHWARI, J.]

      “8. Power to refer parties to arbitration where there is an               A
      arbitration agreement.- (1) A judicial authority before which
      an action is brought in a matter which is the subject of an arbitration
      agreement shall, if a party so applies not later than when submitting
      his first statement on the substance of the dispute, refer the parties
      to arbitration.
                                                                                B
            (2) The application referred to in sub-section (1) shall not
      be entertained unless it is accompanied by the original arbitration
      agreement or a duly certified copy thereof:
             (3) Notwithstanding that an application has been made under
      sub-section (1) and that the issue is pending before the judicial         C
      authority, an arbitration may be commenced or continued and an
      arbitral award made.”
      9.2 After the amendment by Act 3 of 2016, Section 8, now, reads
as under: -
      “8. Power to refer parties to arbitration where there is an               D
      arbitration agreement.- (1) A judicial authority, before which
      an action is brought in a matter which is the subject of an arbitration
      agreement shall, if a party to the arbitration agreement or any
      person claiming through or under him, so applies not later than the
      date of submitting his first statement on the substance of the dispute,   E
      then, notwithstanding any judgment, decree or order of the
      Supreme Court or any Court, refer the parties to arbitration unless
      it finds that prima facie no valid arbitration agreement exists.
            (2) The application referred to in sub-section (1) shall not
      be entertained unless it is accompanied by the original arbitration       F
      agreement or a duly certified copy thereof:
                Provided that where the original arbitration agreement
         or a certified copy thereof is not available with the party applying
         for reference to arbitration under sub-section (1), and the said
         agreement or certified copy is retained by the other party to
                                                                                G
         that agreement, then, the party so applying shall file such
         application along with a copy of the arbitration agreement and
         a petition praying the Court to call upon the other party to
         produce the original arbitration agreement or its duly certified
         copy before that Court.
                                                                                H
128             SUPREME COURT REPORTS                            [2023] 5 S.C.R.


A                  (3) Notwithstanding that an application has been made under
            sub-section (1) and that the issue is pending before the judicial
            authority, an arbitration may be commenced or continued and an
            arbitral award made.”
             10. In the case of Sukanya Holdings (supra), while dealing with
B     the question of applicability of Section 8 of the Act, as then existing, this
      Court underscored the requirements of correlation of subject-matter of
      the suit and subject-matter of the arbitration agreement and, inter alia,
      held as under: -
            “12. For interpretation of Section 8, Section 5 would have no
C           bearing because it only contemplates that in the matters governed
            by Part I of the Act, the judicial authority shall not intervene except
            where so provided in the Act. Except Section 8, there is no other
            provision in the Act that in a pending suit, the dispute is required to
            be referred to the arbitrator. Further, the matter is not required to
            be referred to the Arbitral Tribunal, if: (1) the parties to the
D           arbitration agreement have not filed any such application for
            referring the dispute to the arbitrator; (2) in a pending suit, such
            application is not filed before submitting first statement on the
            substance of the dispute; or (3) such application is not accompanied
            by the original arbitration agreement or duly certified copy thereof.
E           This would, therefore, mean that the Arbitration Act does not oust
            the jurisdiction of the civil court to decide the dispute in a case
            where parties to the arbitration agreement do not take appropriate
            steps as contemplated under sub-sections (1) and (2) of Section 8
            of the Act.

F           13. Secondly, there is no provision in the Act that when the subject-
            matter of the suit includes subject-matter of the arbitration
            agreement as well as other disputes, the matter is required to be
            referred to arbitration. There is also no provision for splitting the
            cause or parties and referring the subject-matter of the suit to the
            arbitrators.
G
            14. Thirdly, there is no provision as to what is required to be done
            in a case where some parties to the suit are not parties to the
            arbitration agreement. As against this, under Section 24 of the
            Arbitration Act, 1940, some of the parties to a suit could apply
            that the matters in difference between them be referred to
H
GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                                129
    LIMITED & ORS. [DINESH MAHESHWARI, J.]

  arbitration and the court may refer the same to arbitration provided       A
  that the same can be separated from the rest of the subject-matter
  of the suit. The section also provided that the suit would continue
  so far as it related to parties who have not joined in such application.
  15. The relevant language used in Section 8 is: “in a matter which
  is the subject of an arbitration agreement”. The court is                  B
  required to refer the parties to arbitration. Therefore, the suit should
  be in respect of “a matter” which the parties have agreed to
  refer and which comes within the ambit of arbitration agreement.
  Where, however, a suit is commenced — “as to a matter” which
  lies outside the arbitration agreement and is also between some
  of the parties who are not parties to the arbitration agreement,           C
  there is no question of application of Section 8. The words “a
  matter” indicate that the entire subject-matter of the suit should
  be subject to arbitration agreement.
  16. The next question which requires consideration is — even if
  there is no provision for partly referring the dispute to arbitration,     D
  whether such a course is possible under Section 8 of the Act. In
  our view, it would be difficult to give an interpretation to Section 8
  under which bifurcation of the cause of action, that is to say, the
  subject-matter of the suit or in some cases bifurcation of the suit
  between parties who are parties to the arbitration agreement and           E
  others is possible. This would be laying down a totally new
  procedure not contemplated under the Act. If bifurcation of the
  subject-matter of a suit was contemplated, the legislature would
  have used appropriate language to permit such a course. Since
  there is no such indication in the language, it follows that bifurcation
  of the subject-matter of an action brought before a judicial authority     F
  is not allowed.
  17. Secondly, such bifurcation of suit in two parts, one to be decided
  by the Arbitral Tribunal and the other to be decided by the civil
  court would inevitably delay the proceedings. The whole purpose
  of speedy disposal of dispute and decreasing the cost of litigation        G
  would be frustrated by such procedure. It would also increase the
  cost of litigation and harassment to the parties and on occasions
  there is possibility of conflicting judgments and orders by two
  different forums.”
                                                                             H
130             SUPREME COURT REPORTS                              [2023] 5 S.C.R.


A            11. As explained by this Court in Ameet Lalchand Shah (supra),
      the amendment to Section 8 after the aforesaid decision in Sukanya
      Holdings could be seen in the background of the recommendations of
      246th Law Commission Report in which, inter alia, it was observed that
      as per the proposed amendment, judicial authority would not refer the
      parties to arbitration only if it finds that there does not exist an arbitration
B
      agreement or that it is null and void. If the judicial authority is of the
      opinion that prima facie the arbitration agreement exists, it would refer
      the dispute to arbitration and leave the existence of arbitration agreement
      to be finally determined by the Arbitral Tribunal.
             12.All the relevant aspects of the matter came up for fuller
C     exposition by a 3-Judge Bench of this Court in the case of Vidya Drolia
      (supra). In the said case, basically, the reference came to be made to
      the bench of three judges when the ratio expressed in the case of
      Himangi Enterprises v. Kamaljeet Singh Ahluwalia: (2017) 10 SCC
      706, to the effect that landlord-tenant disputes governed by the provisions
D     of the Transfer of Property Act, 1882 were not arbitrable, was doubted.
      While dealing with the reference, the Court also dealt with the other
      interconnected aspects as to the meaning of non-arbitrability and when
      the subject-matter of the dispute would not be capable of being resolved
      through arbitration; and as to whether the question of non-arbitrability
      would be decided by the Court at the reference stage or by the Arbitral
E     Tribunal in the arbitration proceedings. The 3-Judge Bench of course
      overruled the decision in Himangi Enterprises (supra) and in that
      context, made various observations and enunciated the relevant principles.
      In the process, the decision in Sukanya Holdings (supra) was also
      taken into consideration. In that regard and with reference to the reliance
F     placed by learned counsel for the respective parties, we may refer to
      the following observations and enunciations of the Court, in the lead
      judgment as also in the concurring opinion in the following passages:-
             “28. Another facet, not highlighted earlier, arises from the dictum
             in Sukanya Holdings (P) Ltd. v. Jayesh H. Pandya [(2003) 5
G            SCC 531], a decision upholding rejection of an application under
             Section 8, on the ground that there is no provision in the Arbitration
             Act to bifurcate and divide the causes or parties, that is, the subject-
             matter of the suit/judicial proceedings, and parties to the arbitration
             agreement. The suit should be in respect of a “matter” which the
             parties have agreed to refer and which comes within the ambit of
H
GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                               131
    LIMITED & ORS. [DINESH MAHESHWARI, J.]

  the arbitration agreement. The words “a matter”, it was interpreted,      A
  would indicate that the entire subject-matter of the suit should be
  subject to arbitration agreement. Bifurcation of subject-matter or
  causes of action in the suit is not permissible and contemplated.
  Similarly, the parties to the suit should be bound by the arbitration
  agreement, as there is no provision in the Arbitration Act to compel
                                                                            B
  third persons who have not exercised the option to give up the
  right to have access to courts and be bound by the arbitration
  clause. This would violate party autonomy and consensual nature
  of arbitration. Bifurcation in such cases would result in a suit being
  divided into two parts, one being decided by the Arbitral Tribunal,
  and the other by the court or judicial authorities. This would defeat     C
  the entire purpose and inevitably delay the proceedings and increase
  cost of litigation, cause harassment and on occasions give rise to
  conflicting judgments and orders by two different fora. Cause of
  action in relation to the subject-matter relates to the scope of the
  arbitration agreement and whether the dispute can be resolved by
                                                                            D
  arbitration. Second mandate relating to common parties exposits
  the inherent limitation of the arbitration process which is consensual
  and mutual, an aspect we would subsequently examine.
  ****                        ****                        ****
  31. We are clearly bound by the dictum of the Constitution Bench          E
  judgment in Patel Engg. Ltd. [SBP & Co. v. Patel Engg. Ltd.,
  (2005) 8 SCC 618] that the scope and ambit of court’s jurisdiction
  under Section 8 or 11 of the Arbitration Act is similar. An application
  under Section 11 of the Arbitration Act need not set out in detail
  the disputes or the claims and may briefly refer to the subject-
  matter or broad contours of the dispute. However, where judicial          F
  proceedings are initiated and pending, specific details of the claims
  and disputes are normally pleaded and, therefore, the court or the
  judicial authority has the advantage of these details. There is a
  difference between a non-arbitrable claim and non-arbitrable
  subject-matter. Former may arise on account of scope of the               G
  arbitration agreement and also when the claim is not capable of
  being resolved through arbitration. Generally non-arbitrability of
  the subject-matter would relate to non-arbitrability in law. Further,
  the decision in Sukanya Holdings (P) Ltd. [Sukanya Holdings
  (P) Ltd. v. Jayesh H. Pandya, (2003) 5 SCC 531] has to be read
                                                                            H
132      SUPREME COURT REPORTS                             [2023] 5 S.C.R.


A     along with subsequent judgment of this Court in Chloro Controls
      (India) (P) Ltd. v. Severn Trent Water Purification Inc.(2013)
      1 SCC 641.
      ****                         ****                       ****
             154.3. The general rule and principle, in view of the
B     legislative mandate clear from Act 3 of 2016 and Act 33 of 2019,
      and the principle of severability and competence-competence, is
      that the Arbitral Tribunal is the preferred first authority to determine
      and decide all questions of non-arbitrability. The court has been
      conferred power of “second look” on aspects of non-arbitrability
C     post the award in terms of sub-clauses (i), (ii) or (iv) of Section
      34(2)(a) or sub-clause (i) of Section 34(2)(b) of the Arbitration
      Act.
              154.4. Rarely as a demurrer the court may interfere at
      Section 8 or 11 stage when it is manifestly and ex facie certain
D     that the arbitration agreement is non-existent, invalid or the disputes
      are non-arbitrable, though the nature and facet of non-arbitrability
      would, to some extent, determine the level and nature of judicial
      scrutiny. The restricted and limited review is to check and protect
      parties from being forced to arbitrate when the matter is
      demonstrably “non-arbitrable” and to cut off the deadwood. The
E     court by default would refer the matter when contentions relating
      to non-arbitrability are plainly arguable; when consideration in
      summary proceedings would be insufficient and inconclusive; when
      facts are contested; when the party opposing arbitration adopts
      delaying tactics or impairs conduct of arbitration proceedings. This
F     is not the stage for the court to enter into a mini trial or elaborate
      review so as to usurp the jurisdiction of the Arbitral Tribunal but
      to affirm and uphold integrity and efficacy of arbitration as an
      alternative dispute resolution mechanism.
      ****                         ****                       ****
G     238. At the cost of repetition, we note that Section 8 of the Act
      mandates that a matter should not (sic) be referred to an arbitration
      by a court of law unless it finds that prima facie there is no valid
      arbitration agreement. The negative language used in the section
      is required to be taken into consideration, while analysing the
      section. The court should refer a matter if the validity of the
H
GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                              133
    LIMITED & ORS. [DINESH MAHESHWARI, J.]

  arbitration agreement cannot be determined on a prima facie basis,       A
  as laid down above. Therefore, the rule for the court is “when in
  doubt, do refer”.
  239. Moreover, the amendment to Section 8 now rectifies the
  shortcomings pointed out in Chloro Controls case [Chloro
  Controls (India) (P) Ltd. v. Severn Trent Water Purification             B
  Inc., (2013) 1 SCC 641: (2013) 1 SCC (Civ) 689] with respect to
  domestic arbitration. Jurisdictional issues concerning whether
  certain parties are bound by a particular arbitration, under group-
  company doctrine or good faith, etc., in a multi-party arbitration
  raises complicated factual questions, which are best left for the
  tribunal to handle. The amendment to Section 8 on this front also        C
  indicates the legislative intention to further reduce the judicial
  interference at the stage of reference.
  240. Courts, while analysing a case under Section 8, may choose
  to identify the issues which require adjudication pertaining to the
  validity of the arbitration agreement. If the court cannot rule on       D
  the invalidity of the arbitration agreement on a prima facie basis,
  then the court should stop any further analysis and simply refer all
  the issues to arbitration to be settled.
  ****                        ****                       ****
                                                                           E
  244: Before we part the conclusions reached, with respect to
  Question 1 are:
  244.1. Sections 8 and 11 of the Act have the same ambit with
  respect to judicial interference.
  244.2. Usually, subject-matter arbitrability cannot be decided at        F
  the stage of Section 8 or 11 of the Act, unless it is a clear case of
  deadwood.
  244.3. The court, under Sections 8 and 11, has to refer a matter
  to arbitration or to appoint an arbitrator, as the case may be, unless
  a party has established a prima facie (summary findings) case of         G
  non-existence of valid arbitration agreement, by summarily
  portraying a strong case that he is entitled to such a finding.
  244.4. The court should refer a matter if the validity of the
  arbitration agreement cannot be determined on a prima facie basis,
  as laid down above i.e. “when in doubt, do refer”.                       H
134            SUPREME COURT REPORTS                           [2023] 5 S.C.R.


A           244.5. The scope of the court to examine the prima facie validity
            of an arbitration agreement includes only:
            244.5.1. Whether the arbitration agreement was in writing? or
            244.5.2. Whether the arbitration agreement was contained in
            exchange of letters, telecommunication, etc.?
B
            244.5.3. Whether the core contractual ingredients qua the
            arbitration agreement were fulfilled?
            244.5.4. On rare occasions, whether the subject-matter of dispute
            is arbitrable?”
C            13. In the case of Oil and Natural Gas Corporation (supra),
      another 3-Judge Bench of this Court essentially dealt with the group
      companies doctrine and application of alter ego principle in arbitration
      making a party not assenting to a contract containing arbitration clause
      to be nevertheless bound by the clause if that party is ‘alter ego’ of an
D     entity who is a party to the arbitration agreement. The observations
      relied upon by learned counsel for the appellant from that case could
      also be usefully extracted as under:-
            “38. Explaining the application of the alter ego principle in
            arbitration, Born also notes:
E                 “Authorities from virtually all jurisdictions hold that a party
            who has not assented to a contract containing an arbitration clause
            may nonetheless be bound by the clause if that party is an ‘alter
            ego’ of an entity that did execute, or was otherwise a party to, the
            agreement. This is a significant, but exceptional, departure from
            the fundamental principle … that each company in a group of
F
            companies (a relatively modern concept) is a separate legal entity
            possessed of separate rights and liabilities.
                               *                *                 *
                  “the group of companies doctrine is akin to principles of
G           agency or implied consent, whereby the corporate affiliations
            among distinct legal entities provide the foundation for concluding
            that they were intended to be parties to an agreement,
            notwithstanding their formal status as non-signatories.”
            39. Recently, John Fellas elaborated on the principle of binding a
H           non-signatory to an arbitration agreement from the lens of the
GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                              135
    LIMITED & ORS. [DINESH MAHESHWARI, J.]

  doctrine of estoppel. He situated the rationale behind the application   A
  of the principle of direct estoppel against competing considerations
  of party autonomy and consent in interpreting arbitration
  agreements. Fellas observed that non-signatory parties can be
  bound by the principle of direct estoppel to prohibit such a party
  from deriving the benefits of a contract while disavowing the
                                                                           B
  obligations to arbitrate under the same:
        “There are at least two distinct types of estoppel doctrine
  that apply in the non-signatory context:”the direct benefits”
  estoppel theory and the “intertwined” estoppel theory. The
  direct benefits theory bears the hallmark of any estoppel
  doctrine-prohibiting a party from taking inconsistent positions          C
  or seeking to “have it both ways” by “rely[ing] on the contract
  when it works to its advantage and ignor[ing] it when it works
  to its disadvantage.” Tepper Realty Co. v. Mosaic Tile
  Co. [Tepper Realty Co. v. Mosaic Tile Co., 259 F Supp 688
  (SDNY 1966)]. The direct benefits doctrine reflects that core            D
  principle by preventing a party from claiming rights under a
  contract but, at the same time, disavowing the obligation to
  arbitrate in the same contract.
            *                          *                          *
          By contrast, the intertwined estoppel theory looks not to        E
  whether any benefit was received by the non-signatory, but rather
  at the nature of the dispute between the signatory and the non-
  signatory, and, in particular whether “the issues the non-signatory
  is seeking to resolve in arbitration are intertwined with the
  agreement that the estoppel [signatory party] has signed….the            F
  intertwined estoppel theory has as its central aim the perseveration
  of the efficacy of the arbitration process is clear when one looks
  at the typical fact pattern of an intertwined estoppel case.” [John
  Fellas, “Compelling Signatories to Arbitrate with Non-Signatories”,
  New York Law Journal (28-3-2022)]
                                                                           G
                                                  (emphasis supplied)
  40. In deciding whether a company within a group of companies
  which is not a signatory to arbitration agreement would nonetheless
  be bound by it, the law considers the following factors:
                                                                           H
136             SUPREME COURT REPORTS                            [2023] 5 S.C.R.


A           (i) The mutual intent of the parties;
            (ii) The relationship of a non-signatory to a party which is a
            signatory to the agreement;
            (iii) The commonality of the subject-matter;
B           (iv) The composite nature of the transaction; and
            (v) The performance of the contract.””
              14. In the case of Intercontinental Hotels Group (supra), the
      Court has essentially proceeded on the enunciation in Vidya Drolia
      (supra) even while accepting the requirement of constituting larger bench
C     to settle the jurisprudence of the implication of non-stamping or under-
      stamping on the arbitration agreement. This Court, however, provided
      that until decision by the larger bench, the matters at pre-appointment
      stage be not kept pending. Not much of dilation is required in that regard.
            15. It is at once clear that the observations and enunciations in the
D     aforesaid have no application to the facts of the present case.
             16. As noticed, there had been multiple transactions in this matter.
      Learned counsel for the contesting respondent has placed before us in
      tabular form the relevant agreements, the contracting parties thereto,
      the purpose of the agreement, and availability of arbitration clause therein.
E     We may reproduce the same to facilitate an eye view of the salient
      features of the transactions in question as follows: -




F




G




H
  GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                                 137
      LIMITED & ORS. [DINESH MAHESHWARI, J.]

                                                                                A




                                                                                B




                                                                                C




                                                                                D




                                                                                E



        17. Thus, except the principal agreement dated 07.04.2005, none
of the other agreements contained any arbitration clause, even if they
related to the same property and also involved the appellant and the            F
respondent No. 1. The later transactions involved other parties too like
the tripartite agreement dated 06.07.2006 whereby the respondent No.
2 bank sanctioned loan to the respondent No. 1 and then, supplemental
to the said tripartite agreement for dealing with the deposit of title deeds.
Similarly, the other deeds of conveyance dated 23.01.2015 involve the           G
appellant and the other defendants.
       17.1. The aforesaid position of the dealings of the parties, when
examined with reference to the reliefs claimed in the suit and the cause
of action pertaining to the said reliefs, as extensively noticed by the High
Court and extracted hereinabove, we are clearly of the view that the            H
138             SUPREME COURT REPORTS                            [2023] 5 S.C.R.


A     submissions made by the appellant with reference to the amendment of
      Section 8 of the Act of 1996 and the later decisions of this Court in
      interpretation of the amended Section 8 do not inure to the benefit of the
      appellant. This is for the simple reason that no such conjunction can be
      provided to the original licence agreement dated 07.04.2005 and the
      tripartite agreement involving the Bank dated 06.07.2006 and 23.01.2008,
B
      whereby the arbitration clause could be held applicable to the tripartite
      agreement too. This is apart from the fact that in the frame of the suit
      and various other reliefs claimed, involving subsequent purchasers too
      and the allegations of fraud, the dispute cannot be said to be arbitrable at
      all. The present one cannot be said to be a case involving any “doubt”
C     about non-existence of arbitration agreement in relation to the dispute in
      question.
            17.2. There being no doubt about non-existence of arbitration
      agreement in relation to the entire subject-matter of the suit, and when
      the substantive reliefs claimed in the suits fall outside the arbitration
D     clause in the original licence agreement, the view taken by the High
      Court does not appear to be suffering from any infirmity or against any
      principle laid down by this Court.
              18. Even if by reference to remote pedigree, the original licence
      agreement is said to be the genesis of the contractual relations of the
E     appellant and the respondent No. 1, that does not ipso facto lead to the
      availability of the arbitration agreement in relation to the dispute in
      question, which emanates from the tripartite agreement and which cannot
      be determined without reference to the said tripartite agreement and
      without involving all the parties thereto. In other words, no dispute
      resolution process, including arbitration, could be undertaken in relation
F     to the subject-matter of the suit without reference to the terms of tripartite
      agreement and without involving the bank- respondent No. 2. This is
      apart from the fact that the other elements of dispute pertaining to the
      subsequent purchasers too cannot be resolved in any forum without
      reference to the tripartite agreement and its amended clause, which did
G     not provide for arbitration. Thus, the ancestry of the tripartite agreement,
      in the facts of the present case, does not lead to the result desired by the
      appellant.
            18.1. Therefore, even on the principles enunciated in Vidya Drolia
      (supra), the prayer of the present appellant for reference to arbitration
H     under Section 8 cannot be granted.
  GUJARAT COMPOSITE LIMITED v. A INFRASTRUCTURE                               139
      LIMITED & ORS. [DINESH MAHESHWARI, J.]

        19. So far as the propositions based on the memos before the          A
Commercial Court dated 06.12.2017, as filed by the respondent Nos. 3
to 5 (subsequent purchasers) and by the appellant are concerned, the
submissions made on that basis do not take the case of the appellant any
further. As noticed, in the said memos, the respondent Nos. 3 to 5
purportedly stated that if dispute concerning them was resolved by
                                                                              B
arbitration proceedings, they were not having any objection thereto. The
appellant, on the other hand, suggested that the tripartite amended
agreement was with reference to the licence agreement and it was agreed
that till the time of the defendant No. 1 (appellant) making payment of a
sum of Rs. 5 crore to the plaintiff, the title deeds of the immovable
property would remain with the bank. The appellant suggested that with        C
a view that the dispute between the parties be resolved by arbitration
proceedings, keeping all contentions open, they would be depositing the
said sum of Rs. 5 crore in the Court and that in this manner ‘the dispute
with defendant No. 2 would be ended’ and then the bank, who was
handed over the title deed in their custody, would deposit the same in the
                                                                              D
Court and the Court would be pleased to place the same in sealed cover
till the disputes of the other parties were resolved.
       19.1. The memo submitted by the appellant was not likely to bring
about the desired legal effect. This is for the simple reason that even if
the appellant deposited the said sum of Rs. 5 crore in the Court, the bank
was not directly obliged to deposit the title deed in the Court as presumed   E
by the appellant; and then, there was no reason that the Court was to be
obliged to accept such a proposition and to keep the title deed in its
custody till the completion of proceedings in any other forum. In other
words, if at all the matter was to be referred to arbitration, there would
not be any justification for the Court to retain the title deed. It would     F
appear that the said memo dated 06.12.2017 by the appellant had only
been a desperate attempt to somehow seek arbitration despite being
aware of the fact that the core of the dispute in the civil suit related to
the tripartite agreement wherein the bank was an equal participant and
no effective award could have been made in the arbitration proceedings
in the absence of the bank. The necessity of the bank’s presence in the       G
matter could not have been obviated by such nebulous suggestion as
stated in the memo filed by the appellant on 06.12.2017.
       19.2. The other memo by respondent Nos. 3 to 5 had been of no
effect whatsoever. Consent of the said respondents, the subsequent
                                                                              H
140              SUPREME COURT REPORTS                            [2023] 5 S.C.R.


A     purchasers, for reference to arbitration could not have infused an
      arbitration clause in the tripartite agreement and their memo could not
      have propelled the matter to arbitration, particularly looking to the core
      of the dispute and its obvious non-arbitrability for the reason that it related
      to the tripartite agreement.
B            20. For what has been discussed hereinabove, on the facts and in
      the circumstances of the present case and in the nature of transactions
      as also the nature of reliefs claimed in the suit, the view taken by the
      Commercial Court and the High Court in declining the prayer of the
      appellant for reference to arbitration cannot be faulted.
C            21. Accordingly, and in view of the above, these appeals fail and
      are, therefore, dismissed. No costs.

      Divya Pandey                                                  Appeals dismissed.
      (Assisted by : Roopanshi Virang, LCRA)

D




E




F




G




H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.