GOVT. OF NCT OF DELHIversusSUSHIL KUMAR GUPTA & ORS.
- Citation
- 2023 INSC 121
- Decided
- 10 February 2023
- Disposal
- Appeal(s) allowed
- Bench
- M R SHAH
Holding
The acquisition does not lapse under Section 24(2) because possession was taken, and both conditions of non‑possession and non‑payment of compensation must be satisfied for a lapse.
Summary
The Government of NCT of Delhi had taken possession of certain land on 12 March 1981 but had not paid compensation to the owners. The Delhi High Court, relying on Pune Municipal Corporation v. Harakchand Misirimal Solanki, held that the acquisition had deemed to lapse under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The Supreme Court noted that the Pune Municipal decision had been overruled by the Constitution Bench in Indore Development Authority v. Manoharlal, which clarified that both possession and compensation must be absent for a lapse to occur. Applying this law, the Court found that because possession had been taken, the acquisition could not be said to have lapsed. Consequently, the High Court’s order was set aside and the writ petition dismissed, with the appeal allowed.
Issues considered
- Whether the land acquisition proceedings are deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 when possession has been taken but compensation has not been paid.
Legislation cited
- Land Acquisition Act, 1894s. 16, s. 31, s. 34, s. 4
- Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013s. 24(1)(a), s. 24(1)(b), s. 24(2)
Subjects
Judgment
[2023] 1 S.C.R. 427 427
GOVT. OF NCT OF DELHI A
v.
SUSHIL KUMAR GUPTA & ORS.
(Civil Appeal No. 352 of 2023)
FEBRUARY 10, 2023 B
[M. R. SHAH AND C. T. RAVIKUMAR, JJ.]
Land Acquisition – Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and Resettlement
Act, 2013 – s.24(2) – Lapse under – Land acquisition proceedings
C
– Challenge to – Writ proceedings – Relying upon the decision in
the case of Pune Municipal Corporation on the ground that
compensation with respect to the land in question was not paid, the
High Court allowed the writ petition and declared that acquisition
in respect of the land in question is deemed to have lapsed u/s.24(2)
– Decision in the case of Pune Municipal Corporation has however D
been overruled by Constitution Bench in the case of Indore
Development Authority – Accordingly, for purpose of lapsing the
acquisition u/s.24(2), the twin conditions namely, not taking the
possession and not paying the compensation have to be satisfied
and if one of the conditions is not satisfied there shall not be any
E
lapse of the acquisition – Once possession of the land in question
was taken over on 12.03.1981 then applying the law laid down in
the case of Indore Development Authority the acquisition of the land
in question is not deemed to have lapsed u/s.24(2) – Impugned
judgment passed by the High Court is unsustainable.
F
Indore Development Authority v. Manoharlal & Ors.
(2020) 8 SCC 129 : [2020] 3 SCR 1 – followed.
Pune Municipal Corporation & Anr. v. Harakch and
Misrimal Solanki & Ors (2014) 3 SCC 183 – held
overruled.
G
Case Law Reference
[2020] 3 SCR 1 followed Para 2
(2014) 3 SCC 183 held overruled Para 2
H
427
428 SUPREME COURT REPORTS [2023] 1 S.C.R.
A CIVIL APPELLATE JURISDICTION : Civil Appeal No. 352 of
2023.
From the Judgment and Order dated 30.05.2016 of the High Court
of Delhi at New Delhi in WP (C) No.1399 of 2014.
Chandan Kumar, Chandra Prakash, Vivek Singh, C. P. Rajwar,
B Ms. Somi Sharma, Advs. for the Appellant.
Neeraj Kishan Kaul, Sr. Adv., Jasbir Singh Malik, Ram Chandra
Madam, Varun Punia, Nitin Mishra, Ishaan Sharma, Advs. for the
Respondents.
C The Judgment of the Court was delivered by
M. R. SHAH, J.
1. Feeling aggrieved and dissatisfied with the impugned
judgment and order dated 30.05.2016 passed by the High Court of
Delhi at New Delhi in Writ Petition (C) No. 1399 of 2014, by which,
D the High Court has allowed the said writ petition and has declared
that the land acquisition proceedings in respect of the land in question
is deemed to have lapsed under Section 24(2) of the Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation
and Resettlement Act, 2013 (hereinafter referred to as “Act, 2013”),
the Government of NCT of Delhi has preferred the present appeal.
E
2. It is true that there is a huge delay in preferring the appeal
which is vehemently opposed by Shri Neeraj Kishan Kaul, learned
Senior Advocate appearing on behalf of the contesting respondent(s)
– original writ petitioner, however, taking into consideration the other
similar orders passed by different benches in condoning such delay
F
in preferring the appeal challenging the order(s) passed by the very
High Court declaring that the acquisition is lapsed under Section 24(2)
of the Act, 2013 and taking into consideration the fact that while
passing the impugned judgment and order the High Court has relied
upon and/or followed the earlier decision of this Court in the case of
G Pune Municipal Corporation and Anr. Vs. Harakchand
Misirimal Solanki and Ors., reported in (2014) 3 SCC 183
which has been overruled by the Constitution Bench of this Court in
the case of Indore Development Authority Vs. Manoharlal and
Ors., reported in (2020) 8 SCC 129 and the observations made
in paragraph 365 which is reproduced hereinbelow, in which it is
H
GOVT. OF NCT OF DELHI v. SUSHIL KUMAR GUPTA & ORS. 429
[M. R. SHAH, J.]
observed that all the decisions in which the decision in the case of A
Pune Municipal Corporation (supra) have been relied upon stand
overruled, we condone the delay and consider the appeal on merits.
3. Having gone through the impugned judgment and order
passed by the High Court and even as observed by the High Court in
the impugned judgment and order, as such the possession of the land B
in question was taken over as far as back on 12.03.1981. However,
thereafter relying upon the decision of this Court in the case of Pune
Municipal Corporation (supra) on the ground that the compensation
with respect to the land in question was not paid, the High Court has
allowed the said writ petition and has declared that the acquisition in
respect of the land in question is deemed to have lapsed under Section C
24(2) of the Act, 2013.
4. The decision of this Court in the case of Pune Municipal
Corporation (supra) relied upon by the High Court has been
overruled by the Constitution Bench of this Court in the case of
Indore Development Authority (supra). In paragraphs 365 and D
366, it is observed and held as under: -
“365. Resultantly, the decision rendered in Pune
Municipal Corpn. [Pune Municipal Corpn. v. Harakchand
Misirimal Solanki, (2014) 3 SCC 183] is hereby overruled and
all other decisions in which Pune Municipal Corpn. [Pune E
Municipal Corpn. v. Harakchand Misirimal Solanki, (2014) 3
SCC 183] has been followed, are also overruled. The decision
in Sree Balaji Nagar Residential Assn. [Sree Balaji Nagar
Residential Assn. v. State of T.N., (2015) 3 SCC 353] cannot
be said to be laying down good law, is overruled and other F
decisions following the same are also overruled. In Indore
Development Authority v. Shailendra [(2018) 3 SCC 412], the
aspect with respect to the proviso to Section 24(2) and whether
“or” has to be read as “nor” or as “and” was not placed for
consideration. Therefore, that decision too cannot prevail, in
the light of the discussion in the present judgment. G
366. In view of the aforesaid discussion, we answer the
questions as under:
366.1. Under the provisions of Section 24(1)(a) in case
the award is not made as on 1-1-2014, t he date of
H
430 SUPREME COURT REPORTS [2023] 1 S.C.R.
A commencement of the 2013 Act, there is no lapse of
proceedings. Compensation has to be determined under the
provisions of the 2013 Act.
366.2. In case the award has been passed within the
window period of five years excluding the period covered by
B an interim order of the court, then proceedings shall continue
as provided under Section 24(1)(b) of the 2013 Act under the
1894 Act as if it has not been repealed.
366.3. The word “or” used in Section 24(2) between
possession and compensation has to be read as “nor” or as
C “and”. The deemed lapse of land acquisition proceedings under
Section 24(2) of the 2013 Act takes place where due to inaction
of authorities for five years or more prior to commencement
of the said Act, the possession of land has not been taken nor
compensation has been paid. In other words, in case possession
has been taken, compensation has not been paid then there is
D no lapse. Similarly, if compensation has been paid, possession
has not been taken then there is no lapse.
366.4. The expression “paid” in the main part of Section
24(2) of the 2013 Act does not include a deposit of compensation
in court. The consequence of non-deposit is provided in the
E proviso to Section 24(2) in case it has not been deposited with
respect to majority of landholdings then all beneficiaries
(landowners) as on the date of notification for land acquisition
under Section 4 of the 1894 Act shall be entitled to
compensation in accordance with the provisions of the 2013
F Act. In case the obligation under Section 31 of the Land
Acquisition Act, 1894 has not been fulfilled, interest under
Section 34 of the said Act can be granted. Non-deposit of
compensation (in court) does not result in the lapse of land
acquisition proceedings. In case of non-deposit with respect to
the majority of holdings for five years or more, compensation
G under the 2013 Act has to be paid to the “landowners” as on
the date of notification for land acquisition under Section 4 of
the 1894 Act.
366.5. In case a person has been tender ed the
compensation as provided under Section 31(1) of the 1894 Act,
H
GOVT. OF NCT OF DELHI v. SUSHIL KUMAR GUPTA & ORS. 431
[M. R. SHAH, J.]
it is not open to him to claim that acquisition has lapsed under A
Section 24(2) due to non-payment or non-depos it of
compensation in court. The obligation to pay is complete by
tendering the amount under Section 31(1). The landowners who
had refused to accept compensation or who sought reference
for higher compensation, cannot claim that the acquisition
B
proceedings had lapsed under Section 24(2) of the 2013 Act.
366.6. The proviso to Section 24(2) of the 2013 Act is
to be treated as part of Section 24(2), not part of Section
24(1)(b).
366.7. The mode of taking possession under the 1894 C
Act and as contemplated under Section 24(2) is by drawing of
inquest report/memorandum. Once award has been passed on
taking possession under Section 16 of the 1894 Act, the land
vests in State there is no divesting provided under Section 24(2)
of the 2013 Act, as once possession has been taken there is no
lapse under Section 24(2). D
366.8. The provisions of Section 24(2) providing for a
deemed lapse of proceedings are applicable in case authorities
have failed due to their inaction to take possession and pay
compensation for five years or more before the 2013 Act came
into force, in a proceeding for land acquisition pending with E
the authority concerned as on 1-1-2014. The period of
subsistence of interim orders passed by court has to be
excluded in the computation of five years.
366.9. Section 24(2) of the 2013 Act does not give rise
to new cause of action to question the legality of concluded F
proceedings of land acquisition. Section 24 applies to a
proceeding pending on the date of enforcement of the 2013
Act i.e. 1-1-2014. It does not revive stale and time-barred claims
and does not reopen concluded proceedings nor allow
landowners to question the legality of mode of taking possession G
to reopen proceedings or mode of deposit of compensation in
the treasury instead of court to invalidate acquisition.”
5. Thus, as per the law laid down by this Court for the purpose
of lapsing the acquisition under Section 24(2) of the Act, 2013, the
twin conditions namely, not taking the possession and not paying the
H
432 SUPREME COURT REPORTS [2023] 1 S.C.R.
A compensation have to be satisfied and if one of the conditions is not
satisfied there shall not be any lapse of the acquisition. Therefore,
once the possession of the land in question was taken over on
12.03.1981 then applying the law laid down by this Court in the case
of Indore Development Authority (supra) the acquisition of the
land in question is not deemed to have lapsed under Section 24(2) of
B
the Act, 2013. Under the circumstances, the impugned judgment and
order passed by the High Court is unsustainable.
6. In view of the above and for the reasons stated above, the
present appeal succeeds. The impugned judgment and order passed
by the High Court is hereby quashed and set aside. Consequently,
C the writ petition preferred by the original writ petitioner before the
High Court stands dismissed.
Present appeal is accordingly allowed. No costs.
Pending applications, if any, also stand disposed of.
D
Bibhuti Bhushan Bose Appeal allowed.
(Assisted by : Abhishek Pratap Singh, LCRA)
E
F
G
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.