Created byFuzzy Cloud

Supreme Court of India

DELHI DEVELOPMENT AUTHORITYversusBHIM SAIN GOEL AND ORS.

Citation
2022 INSC 472
Decided
25 April 2022
Disposal
Appeal(s) allowed

Holding

The respondents cannot rely on Section 24(2) of the 2013 Act; the award under the 1894 Act remains valid and the land is already vested with the Government, precluding any further acquisition under the 1956 Act.

Summary

The Delhi Development Authority (DDA) issued a notification under the Land Acquisition Act, 1894 in 2003, followed by a declaration in 2004 and an award in 2005 for land needed for a road project. The respondents obtained interim stay orders that prevented DDA from taking possession, and later filed a writ petition under the 2013 Act claiming that the acquisition had lapsed under Section 24(2) because the award was more than five years old and compensation was unpaid. The High Court accepted this argument and set aside the award, but DDA appealed to the Supreme Court. While the appeal was pending, the National Highways Authority initiated acquisition proceedings under the 1956 Act, culminating in a declaration in 2019. The Supreme Court held that the respondents could not invoke Section 24(2) of the 2013 Act because their own litigation caused the delay, and that the land was already vested with the Government under the 1894 Act, precluding any double vesting. Consequently, the High Court judgment was set aside, the 1894 award was affirmed, and the respondents were permitted to file an application under Section 18 of the 1894 Act for enhanced compensation.

Issues considered

  • The applicability of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 to the 1894 acquisition proceedings.
  • Whether the respondents can claim benefits of the subsequent acquisition under the National Highways Act, 1956 when the land is already vested under the 1894 Act.
  • The effect of interim stay orders obtained by the respondents on the lapse provision and on the doctrine of estoppel or restitution.
  • The permissibility of double vesting of the same land under two different acquisition statutes.

Legislation cited

Subjects

land acquisitionSection 24(2) lapseinterim staydouble vestingrestitutionary principleestoppel1894 Act2013 Act1956 Actcompensationpublic purpose

Judgment

1164            SUPREME COURT
                          [2022]REPORTS
                                 2 S.C.R. 1164              [2022] 2 S.C.R.


 A                  DELHI DEVELOPMENT AUTHORITY
                                         v.
                         BHIM SAIN GOEL AND ORS.
                          (Civil Appeal No. 3151 of 2022)
 B                               APRIL 25, 2022
               [K. M. JOSEPH AND HRISHIKESH ROY, JJ.]
              Land Acquisition Act, 1894: ss. 4, 6, 16 and 18 – Right to
       Fair Compensation and Transparency in Land Acquisition,
 C     Rehabilitation and Resettlement Act, 2013 –s. 24(2) – Notification
       u/s 4 to acquire land of the respondent, followed by declaration u/
       s. 6 – Challenge to, by the respondent in a writ petition – High
       Court granted the stay and directed the parties to maintain the status
       quo with regards to nature, title and possession of the land and
       dismissed thewrit petition – In appeal, this Court granted interim
 D     stay – Meanwhile, Act of 2013 passed – Writ petition by respondent
       claiming that the land acquisition proceedings under the Act of 1894
       stood lapsed as per the s.24(2) of the Act of 2013 – Allowed by the
       High Court as the award in the matter was made 5 years prior to
       the commencement of the Act of 2013 and the compensation had
 E     not been paid – Appeal before this Court – During the pendency
       thereof, the proceedings under the 1956 Act that land in question
       needed for public purpose – Held: Respondents cannot take shelter
       u/s. 24(2) of the Act of 2013 – Barring 81 days, the appellant-
       acquiring authority was prevented for taking possession of the lands
       on account of interim stay obtained by the respondents – If not for
 F     the stay, the lands would have been taken and the land would have
       stood vested with the Government under the 1894 Act – Furthermore,
       Government cannot acquire the the land already vested in it and
       the Government cannot be compelled to shell out public funds to
       acquire land which already belongs to it – The fact that proceedings
 G     under the 1956 Act reached the stage of declaration cannot give
       the respondents a right to claim the fruits of the said proceedings,
       when the land already would stand vested under the 1894 Act and
       there cannot be vesting twice over – Thus, the judgment of the High
       Court set aside and the land stood vested to the Government –
       However, the respondents granted an opportunity to file an
 H
                                       1164
DELHI DEVELOPMENT AUTHORITY v. BHIM SAIN GOEL AND ORS. 1165


application u/s 18 of the 1894 Act seeking reference and claiming       A
enhanced compensation – National Highways Act, 1956 –
Subsequent events.
      Allowing the appeal, the Court
       HELD: 1.1 Notification came to be issued under Section 4
of the Land Acquisition Act, 1894 on 21.03.2003. This was followed      B
up by declaration under Section 6 on 18.03.2004 which was
followed up by Award passed on 22.08.2005. An interim order
was passed undoubtedly which effectively prevented the appellant
from taking possession of the lands in question. Though the writ
petition came to be dismissed on 20.08.2007, the respondents            C
carried the lis to this Court and it is again not in dispute that the
interim order continued to haunt the appellants as it prevented
the appellants from taking possession of the lands which it could
otherwise have taken. With the enactment of the Right to Fair
Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013 with effect from              D
01.01.2014, even when the civil appeal was pending, the
respondents filed a fresh round of litigation in the form of a writ
petition. Therein the claim was that the earlier Award has lapsed
on the basis of Section 24(2) of the 2013 Act. This argument has
found favour with the High Court in the impugned judgment. It is        E
the case of the appellant that except for 81 days, there was an
interim order prevailing, which effectively prevented the appellant
from taking possession of the lands at the instance of the
respondents. [Para 10][1173-C-F]
      1.2 There cannot be any doubt that the respondents cannot         F
take shelter under Section 24(2) of the 2013 Act. This is for the
simple reason that it is by their conduct in approaching the Courts
and obtaining interim orders that the appellant was prevented
from taking possession of the lands. This is indeed one such case
where the respondents have launched litigation, obtained orders
and it has clearly prevented the appellant from taking possession       G
and therefore, the impugned judgment of the High Court would
have to be set aside. [Para 12][1176-A-C]


                                                                        H
1166            SUPREME COURT REPORTS                        [2022] 2 S.C.R.


 A            1.3 It is true that a notification has been issued under Section
       3A of the 1956 Act also. It is equally true that acting upon the
       notification after calling for the objections, declaration has been
       made under Section 3D of the 1956 Act. The scheme of the 1956
       Act essentially consists of issuance of notification under Section
       3A corresponding to Section 4 of the 1894 Act, followed up by an
 B
       inquiry ordinarily and culminating in a declaration under Section
       3D. It is undoubtedly true that the legal effect of the declaration
       under Section 3D of the 1956 Act is that the property would vest
       thereupon. [Para 13][1176-D-F]
             1.4 This Court is presented with a situation where, on the
 C
       one hand, the vesting has already taken place under Section 16
       of the 1894 Act. No doubt, under Section 16, possession is to be
       taken on passing of the Award. But here, it is only solely on account
       of the conduct of the respondents in filing a writ petition and
       orders being passed by courts that possession could not be taken.
 D     On the other hand, during the pendency of the challenge against
       the impugned judgment, undoubtedly, proceedings have been
       launched under the 1956 Act. Here, the land in question was
       needed for a public purpose-construction of the road. It is
       apparently, no doubt, during the pendency of the litigation before
       this Court that proceedings under Section 3A have been taken,
 E
       followed up by declaration under Section 3D. [Para 14][1176-F-H]
             1.5 On the one hand, it is a case where the so-called
       subsequent developments had taken place during the pendency
       of the appeal before this Court. On the other hand, the authority
       obviously realizing the need to acquire the land for public purpose
 F
       that is for construction of road resorted to the provisions of the
       1956 Act. The principle that the Government cannot acquire the
       land which has already vested in it must be borne in mind. The
       other aspect must be borne in mind is realizing the fact that the
       lands in question are the subject matter of the appeal and what is
 G     more, they would stand vested in terms of the Constitution Bench
       judgment of this Court the lands have been excluded when the
       final Award was passed under the 1956 Act. The respondents do



 H
DELHI DEVELOPMENT AUTHORITY v. BHIM SAIN GOEL AND ORS. 1167


not have a case that they have laid any challenge to the exclusion      A
of their lands in the final Award. Whatever that may be, the fact
remains that all these developments took place during the
pendency of the appeal. [Para 16][1178-G-H; 1179-A-B]
      1.6 When the Court finally decides the lis, it is undoubtedly,
open, particularly this Court, having powers as it has under Article    B
142, to do complete justice between the parties and the counsel
for the respondents is seeking to invoke the said jurisdiction.
[Para 17][1179-B-C]
      1.7 If it is the principle of estoppel which can be invoked as
it would appear from the line of argument taken by the counsel          C
for the respondents, it is not tenable. Estoppel flows from equity.
[Para 18][1179-C-D]
      1.8 It could be contended that it may not be fair to allow the
appellant to proceed under the 1956 Act and for the proceedings
to culminate in the vesting of the property under Section 3D of         D
the 1956 Act and having elected to take proceedings under the
1956 Act apparently on the basis of the impugned judgment
namely that the proceeding under the 1894 Act stood lapsed, the
authorities cannot be permitted to resile from their action. It would
be wholly inequitable on facts to deprive the appellant of its
                                                                        E
rights when it is finally adjudicated in its favour in the facts of
this case. It is also a case where the appellant has promptly
approached this Court against the impugned judgment.
Furthermore, in the facts the balancing of equity must be worked
out in favour of the appellant. In other words, the mere fact that
proceedings were taken during the pendency of the case and it           F
had reached the stage of declaration under Section 3D of the
1956 Act cannot suffice to cloth the respondents with a right to
claim the fruits of the said proceedings, when on the final disposal
of the appeal it was found that in law as declared by this Court
in the Constitution Bench, the land already would stand vested
                                                                        G
under the 1894 Act and as already noticed there cannot be vesting
twice over. [Para 20][1180-C-F]



                                                                        H
1168            SUPREME COURT REPORTS                        [2022] 2 S.C.R.


 A          1.9 Having regard to the fact that barring 81 days the
       respondents succeed on the strength of interim order passed
       from preventing the appellant from taking possession of the lands
       must be the crucial aspect. [Para 21][1180-F-G]
              1.10 The public authority which had set the law in motion
 B     under the earlier regime cannot be put to a loss when at the end
       of the day or on the day of reckoning it is found that they must
       succeed in law. The appellant is fully justified in contending that
       but for the orders passed by the High Court and this Court, the
       possession would have been taken, and the land would have
       vested under the law. This Court must proceed on the basis that
 C     but for the interim orders passed which cannot survive the final
       disposal of the cases, the land would have stood vested with the
       Government under the earlier regime. The subsequent vesting
       which is attributed to Section 3D of the 1956 Act, must pale into
       insignificance and cannot estop the appellant from contending
 D     that in law the land would vest under the notification/ award issued
       under the 1894 Act.There is no right for the respondents to plead
       equity for they have by their acts effectively prevented the public
       authority from enjoying the fruits of law by which, in the exercise
       of power embedded in the 1894 Act, the land is vested with the
       appellant, and the land is one which is needed for an important
 E     public project like construction of the road for that matter.It would
       be completely antithetical to public interest were the Government
       be compelled to shell out public funds under the 2013 Act to
       acquire land which already belongs to it. This Court cannot be
       oblivious to the said sublime principle as well.The restitutionary
 F     principle must be borne in mind. Realizing that the lands are
       already vested, the lands are already excluded under the final
       award. The inevitable outcome is that the appellant must succeed.
       The impugned judgment is set aside. [Para 22-25][1180-G-H;
       1181-A-E]
 G           1.11 However, in the facts of this case and in the interest of
       justice, it is fit to direct that if the respondents have not filed any
       application under Section 18 of the 1894 Act seeking reference
       and claiming enhanced compensation pursuant to the Award dated
       22.08.2005, the respondents should be granted an opportunity

 H
DELHI DEVELOPMENT AUTHORITY v. BHIM SAIN GOEL AND ORS. 1169


to make an application under Section 18 and the matter be                 A
adjudicated under the earlier Act. The impugned judgment came
to be passed based on the law as it was laid down by this Court.
Accordingly, it is directed that in case, the respondents have
already not filed an application within the meaning of section 18
of the 1894 Act, they are permitted to file application under Section
                                                                          B
18 of the 1894 Act within the stipulated period. In case such an
application is made, it would be dealt with in accordance with law
as it stood under the 1894 Act. The application would not be
dismissed on the ground of delay. This order is passed in the
peculiar facts of this case and taking note of the fact that it is with
the judgment rendered that this Court is giving imprimatur to             C
the Award dated 22.08.2005 under the 1894 Act. [Para 26][1181-
F-H]
        Indore Development Authority v. Manoharlal and Others
        (2020) 8 SCC 129 : [2020] 3 SCR 1 – followed.
        Jaipur Development Authority v. Mahesh Sharma and                 D
        Another (2010) 9 SCC 782 : [2010] 11 SCR 1002 –
        referred to.
        SPENCER BOWER: RELIANCE-BASED ESTOPPEL
        5th Edition – referred to.
                                                                          E
                       Case Law Reference
[2020] 3 SCR 1             followed          Para 12, 16, 20, 22, 24
[2010] 11 SCR 1002         referred to       Para 15
        CIVIL APPELLATE JURISDICTION: Civil Appeal No.3151 of
                                                                          F
2022.
      From the Judgment and Order dated 02.02.2016 of the High Court
of Delhi at New Delhi in W.P. (C) No.3209 of 2015.
      Ms. Aishwarya Bhati, ASG, Sanjay Poddar, Sr. Adv., Vishnu B.
Saharya, Viresh B. Saharya, M/s Saharya & Co., Akshay Dhatwalia,          G
Ms. Kumud Nijhawan, Ashwani Kumar, Pranab Kumar Mullick, Soma
Mullick, Biswaranjan Kumar, Sebat Kumar Deuria, Siddharth Singla,
Praveen Swarup, Shivam Goel, Anil Kumar Goel, Pratish Goel, Ramya
Goel, Ms. Payal Swarup, Manvendra Singh, Ms. Shivika Mehra, Ms.
BLN Shivani, Aman Sharma, Ms. Priyanka Das, Abhishek Sarkar, Ms.
                                                                          H
1170             SUPREME COURT REPORTS                              [2022] 2 S.C.R.


 A     Noor Rampal, Raghvendra S. Srivatsa, Atul Kumar, Ms. Sweety Singh,
       Rahul Pandey, Rajiv Ranjan, Advs. for the appearing parties.
              The Judgment of the Court was delivered by
              K. M. JOSEPH, J.
 B            (1) Delay condoned.
              (2) Applications for condonation of delay in filing substitution, setting
       aside abatement and substitution are allowed.
             Mr. Pranab Kumar Mullick, learned counsel, appears for the legal
       representatives of deceased respondents.
 C
              (3) Leave granted.
              (4) A notification dated 21.03.2003 was issued under Section 4 of
       the Land Acquisition Act, 1894 (hereinafter referred to as ‘1894 Act’)
       purporting to acquire lands belonging to the respondents. This was duly
       followed up by declaration under Section 6 of the 1894 Act on 18.03.2004.
 D
       On 22.08.2005, an Award was passed in the matter. Writ Petition No.
       21639/2005 came to be filed before the High Court laying challenge to
       the declaration under Section 6. What is more pertinent is that, the High
       Court directed on 18.11.2005 that status quo with regard to nature, title
       and possession of the land in question be maintained. It is the case of the
 E     appellant that the authority could not take possession of the land as a
       result of the interim order. The writ petition came to be dismissed.
       However, on the application of the respondents, by order dated
       18.09.2007, the High Court extended the stay order by a week. The
       respondents approached this Court by filing SLP (C)No. 17504-08/2007.
       This was later converted into Civil Appeal No. 4116-4120/2009. Again,
 F
       what is apposite to note is that an interim order of stay was passed. In
       the meantime, the Right to Fair Compensation and Transparency in Land
       Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter
       referred to as ‘2013 Act’) came into force with effect from 01.01.2014.
       In the meantime, the respondents filed Writ Petition No. 3209/2015. This
 G     writ petition was premised on the lapsing of the proceedings under the
       1894 Act, based on Section 24(2) of the 2013 Act. The writ petition
       came to be allowed by the High Court on 02.02.2016. Thereafter, the
       respondents withdrew Civil Appeal No. 4116-4120/2009. It is this judgment
       of the High Court dated 02.02.2016 which is the subject matter of the
       present appeal.
 H
DELHI DEVELOPMENT AUTHORITY v. BHIM SAIN GOEL AND ORS. 1171
                  [K. M. JOSEPH, J.]

      (5) The findings of the High Court can be gleaned from the following      A
paragraphs:
      “2. The Land Acquisition Collector claims that possession of the
      said land was taken on 24.12.2008. Interestingly, they claim that
      immediately on taking over possession of the subject land the same
      was handed to the DDA. However, the affidavit filed on behalf             B
      of the DDA states that possession was not handed over by the
      Land Acquisition Collector to the DDA. Apart form this the learned
      counsel for the petitioners points out that the respondents/LAC
      could not have taken possession of the subject land because there
      was a status quo order which had been passed by a Division
      Bench of this court on 18.11.2005 in W.P. (C) 21639/2005. That            C
      writ petition was dismissed on 20.08.2007. Thereafter a special
      leave petition was filed before the Supreme Court being S.L.P.
      (C)No. 17504/2007 (later the special leave petition was admitted
      and has now become Civil Appeal Nos. 4116-4120 of 2009) in
      which stay was granted on 19.09.2007 and that has continued till          D
      date. Therefore, according to the learned counsel for the petitioners,
      possession of the said land has not been taken by the respondents.
      Insofar as the issue of compensation is concerned, it is an admitted
      position that the same has not been offered or paid to the petitioners.
          3. Without going into the controversy of physical possession,         E
          this much is clear that the Award was made more than five
          years prior to the commencement of the 2013 Act and the
          compensation has also not been paid. The necessary ingredients
          for the application of Section 24(2) of the 2013 Act as
          interpreted by the Supreme Court and this Court in the following
          cases stand satisfied:-                                               F

          (1) Pune Municipal Corporation and Anr. v. Harakchand
          Misirimal Solanki and Ors.: (2014) 3 SCC 183;
          (2) Union of India and Ors. v. Shiv Raj and Ors: (2014) 6
          SCC 564;                                                              G
          (3) Sree Balaji Nagar Residential Association v. State of
          Tamil Nadu and Ors: Civil Appeal No. 8700/2013 decided on
          10.09.2014;
          (4) Surender Singh v. Union of India & Others: WP(C)2294/
          2014 decided on 12.09.2014 by this Court; and                         H
1172            SUPREME COURT REPORTS                           [2022] 2 S.C.R.


 A               (5) Girish Chhabra v. Lt. Governor of Delhi and Ors:
                 WP(C)2759/2014 decided on 12.09.2014 by this Court.”
             (6) We have heard learned counsel for the appellant and the learned
       counsel for the respondents.
              (7) Learned counsel for the appellant would submit that the
 B     impugned judgment will not stand scrutiny of this Court in the light of the
       later Constitution Bench judgment of this Court in Indore Development
       Authority v. Manoharlal and Others (2020) 8 SCC 129 hereinafter
       referred to as the Constitution Bench decision. It is his case that the
       conduct of the respondents in filing the writ petitions we have adverted
 C     to and the special leave petition later converted into civil appeal and
       what is more important, obtaining interim orders prevented the appellant
       from taking possession of the property in question clearly, disentitles the
       respondents from claiming the benefit of the alleged lapsing of the
       proceedings under Section 24(2) of the 2013 Act.

 D            This position is clear from the perusal of the judgment of the
       Constitution Bench which we have adverted to. He would submit that
       the respondents cannot be permitted to take advantage of order obtained
       by them from the Court and then set up a case under Section 24(2) of
       the 2013 Act.

 E            (8) Per contra, learned counsel for the respondents would point
       out that quite apart from the issues which arise from judgment of the
       Constitution Bench, there is another dimension which has unfolded. This
       later development consists of the following:
              The National Highways Authority of India came to notify the lands
 F     in question acting under the National Highways Act, 1956 (hereinafter
       referred to as ‘1956 Act’ for brevity) by issuance of a notification under
       Section 3A of the said Act on 01.12.2018. The notification under Section
       3A comprehend the lands in question. What is more, the matter progressed
       further to the stage of declaration under Section 3D. The declaration
       was published on 22.03.2019. He would, therefore, submit that whatever
 G     would be the effect of the later judgment in the facts of this case, the
       interest of justice demands, that the respondents are given the benefit of
       the compensation under the 2013 Act.
              (9) This is sought to be countered by the learned counsel for the
       appellant by pointing out that again, on the facts, the respondents are not
 H     entitled to any benefit based on the subsequent developments. He does
DELHI DEVELOPMENT AUTHORITY v. BHIM SAIN GOEL AND ORS. 1173
                  [K. M. JOSEPH, J.]

not dispute that a notification was indeed issued under Section 3A of the         A
1956 Act on 01.12.2018 including the lands of the respondents in question
in this case. He also does not dispute that the declaration under Section
3(D) followed on 22.03.2019. However, he points out that the Collector,
finding that the lands of the respondents which are the subject matter of
the appeal before this Court stood already vested, has excluded the lands
                                                                                  B
when it made the final Award on 05.11.2020. Learned counsel for the
appellant would also point out that this Court has held that State cannot
acquire land which is already vested with it [See in this regard (2010)
9 SCC 782].
      (10) There is no dispute about certain facts. Notification came to
be issued under Section 4 of the 1894 Act on 21.03.2003. This was                 C
followed up by declaration under Section 6 on 18.03.2004 which was
followed up by Award passed on 22.08.2005.
       An interim order is passed undoubtedly which effectively prevented
the appellant from taking possession of the lands in question. Though the
writ petition came to be dismissed on 20.08.2007, the respondents carried         D
the lis to this Court and it is again not in dispute that the interim order
continued to haunt the appellants as it prevented the appellants from
taking possession of the lands which it could otherwise have taken. With
the enactment of the 2013 Act with effect from 01.01.2014, even when
the civil appeal was pending, the respondents filed a fresh round of litigation   E
in the form of a writ petition. Therein the claim was that the earlier
Award has lapsed on the basis of Section 24(2) of the 2013 Act. This
argument, as we have noted, has found favour with the High Court in
the impugned judgment.
      It is thereafter, that the civil appeal came to be withdrawn. It is         F
the case of the appellant that except for 81 days, there was an interim
order prevailing, which effectively prevented the appellant from taking
possession of the lands at the instance of the respondents.
       (11) At this juncture, it is appropriate to take note of what this
Court has laid down in the Constitution Bench decision regarding the              G
effect of orders by Courts operating as an obstacle in the path of Acquiring
Authority taking possession of the land which is acquired:
       “300. In our considered opinion, litigation which initiated by the
       landowners has to be decided on its own merits and the benefits of
       Section 24(2) should not be available to the litigants. In case there
                                                                                  H
1174            SUPREME COURT REPORTS                              [2022] 2 S.C.R.


 A           is no interim order, they can get the benefits they are entitled to, not
             otherwise as a result of fruit of litigation, delays and dilatory tactics
             and sometime it may be wholly frivolous pleas and forged documents
             as observed in V. Chandrasekaran [V. Chandrasekaran v.
             Administrative Officer, (2012) 12 SCC 133 : (2013) 2 SCC (Civ)
             136 : (2013) 4 SCC (Cri) 587 : (2013) 3 SCC (L&S) 416] mentioned
 B
             above.
             306. When the authorities are disabled from performing duties
             due to impossibility, would be a good excuse for them to save
             them from rigour of provisions of Section 24(2). A litigant may be
             right or wrong. He cannot be permitted to take advantage of a
 C           situation created by him of interim order. The doctrine
             “commodum ex injuria sua nemo habere debet” that is
             convenience cannot accrue to a party from his own wrong.
             Provisions of Section 24 do not discriminate litigants or non-litigants
             and treat them differently with respect to the same acquisition,
 D           otherwise, anomalous results may occur and provisions may
             become discriminatory in itself.
             309. It may not be doubtful conduct to file frivolous litigation and
             obtain stay; but benefit of Section 24(2) should not be conferred
             on those who prevented the taking of possession or payment of
 E           compensation, for the period spent during the stay.
             314. The maxim “lex non cogit ad impossibilia” means that the
             law does not expect the performance of the impossible. Though
             payment is possible but the logic of payment is relevant. There
             are cases in which compensation was tendered, but refused and
 F           then deposited in the treasury. There was litigation in court, which
             was pending (or in some cases, decided); earlier references for
             enhancement of compensation were sought and compensation was
             enhanced. There was no challenge to acquisition proceedings or
             taking possession, etc. In pending matters in this Court or in the
             High Court even in proceedings relating to compensation, Section
 G           24(2) was invoked to state that proceedings have lapsed due to
             non-deposit of compensation in the court or to deposit in the
             treasury or otherwise due to interim order of the court needful
             could not be done, as such proceedings should lapse.
             We may notice further that the Court elaborately dealt with the
 H     principle of restitution and had this to say:
DELHI DEVELOPMENT AUTHORITY v. BHIM SAIN GOEL AND ORS. 1175
                  [K. M. JOSEPH, J.]

    338. A wrongdoer or in the present context, a litigant who takes         A
    his chances, cannot be permitted to gain by delaying tactics. It is
    the duty of the judicial system to discourage undue enrichment or
    drawing of undue advantage, by using the court as a tool. In
    Kalabharati Advertising v. Hemant Vimalnath Narichania
    [Kalabharati Advertising v. Hemant Vimalnath Narichania,
                                                                             B
    (2010) 9 SCC 437 : (2010) 3 SCC (Civ) 808] , it was observed
    that courts should be careful in neutralizing the effect of
    consequential orders passed pursuant to interim orders. Such
    directions are necessary to check the rising trend among the
    litigants to secure reliefs as an interim measure and avoid
    adjudication of the case on merits. Thus, the restitutionary principle   C
    recognizes and gives shape to the idea that advantages secured
    by a litigant, on account of orders of court, at his behest, should
    not be perpetuated; this would encourage the prolific or serial
    litigant, to approach courts time and again and defeat rights of
    others — including undermining of public purposes underlying
                                                                             D
    acquisition proceedings. A different approach would mean that,
    for instance, where two landowners (sought to be displaced from
    their lands by the same notification) are awarded compensation,
    of whom one allows the issue to attain finality — and moves on,
    the other obdurately seeks to stall the public purpose underlying
    the acquisition, by filing one or series of litigation, during the       E
    pendency of which interim orders might inure and bind the parties,
    the latter would profit and be rewarded, with the deemed lapse
    condition under Section 24(2). Such a consequence, in the opinion
    of this Court, was never intended by Parliament; furthermore, the
    restitutionary principle requires that the advantage gained by the
                                                                             F
    litigant should be suitably offset, in favour of the other party.
    366.2. In case the award has been passed within the window
    period of five years excluding the period covered by an interim
    order of the court, then proceedings shall continue as provided
    under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it
    has not been repealed.                                                   G
    366.8. The provisions of Section 24(2) providing for a deemed
    lapse of proceedings are applicable in case authorities have failed
    due to their inaction to take possession and pay compensation for
    five years or more before the 2013 Act came into force, in a
    proceeding for land acquisition pending with the authority concerned     H
1176             SUPREME COURT REPORTS                            [2022] 2 S.C.R.


 A           as on 1-1-2014. The period of subsistence of interim orders passed
             by court has to be excluded in the computation of five years.
                (12) On the application of the aforesaid principles to the facts of
       this case, there cannot be any doubt that the respondents cannot take
       shelter underSection 24(2) of the 2013 Act. This is for the simple reason
 B     that it is by their conduct in approaching the Courts and obtaining interim
       orders that the appellant was prevented from taking possession of the
       lands. We are clear in our minds that this is indeed one such case where
       the respondents have launched litigation, obtained orders and it has clearly
       prevented the appellant from taking possession and therefore, the
       impugned judgment of the High Court would have to be set aside.
 C
             (13) The problem, however, is sought to be projected by the learned
       counsel for the respondents based on the subsequent developments which
       we have already noted.
              It is true that a notification has been issued under Section 3A of
 D     the 1956 Act also. It is equally true that acting upon the notification after
       calling for the objections, declaration has been made under Section 3D
       of the 1956 Act.
              The scheme of the 1956 Act essentially consists of issuance of
       notification under Section 3A corresponding to Section 4 of the 1894
 E     Act, followed up by an inquiry ordinarily and culminating in a declaration
       under Section 3D. It is undoubtedly true that the legal effect of the
       declaration under Section 3D of the 1956 Act is that the property would
       vest thereupon.
              (14) Here, therefore, we are presented with a situation where, on
 F     the one hand, the vesting has already taken place under Section 16 of
       the 1894 Act. No doubt, under Section 16, possession is to be taken on
       passing of the Award. But here, it is only solely on account of the conduct
       of the respondents in filing a writ petition and orders being passed by
       courts that possession could not be taken. On the other hand, during the
       pendency of the challenge against the impugned judgment, undoubtedly,
 G     proceedings have been launched under the 1956 Act, as already noted.
       Here, we must bear in mind that the land in question was needed for a
       public purpose-construction of the road. It is apparently, no doubt, during
       the pendency of the litigation before this Court that proceedings under
       Section 3A have been taken, followed up by declaration under Section
       3D.
 H
DELHI DEVELOPMENT AUTHORITY v. BHIM SAIN GOEL AND ORS. 1177
                  [K. M. JOSEPH, J.]

      (15) At this juncture, we must notice the principles laid down in       A
Jaipur Development Authority v. Mahesh Sharma and Another (2010)
9 SCC 782:
      “26. Despite vesting of the land with the Government under the
      provisions of the Jagir Act and also resumption of the said land
      measuring 29 bighas and 17 biswas by the Government, a                  B
      notification proposing acquisition of the said land was issued by
      the Government under Section 4(1) of the Act followed by the
      notification under Section 6 of the Act. The Land Acquisition
      Officer even proceeded to pass an award in respect of the land,
      which already belonged to the Government, by determining
      compensation, and proceeded further in directing retention of           C
      interim compensation paid under the Jagir Act and also by directing
      the allotment of a plot of developed land measuring 2500 sq yd.
      Although there was no law supporting such action, the said action
      on the part of the Land Acquisition Officer directing the payment
      of compensation and also allotting a plot of land in favour of the      D
      respondent indicates as to how government officials, who are
      protectors of the government property, abuse their power and
      trust under the camouflage of performance of their public duty.
      32. In State of Orissa v. Brundaban Sharma [1995 Supp (3)
      SCC 249] this Court has held that the Land Acquisition Act does         E
      not contemplate or provide for the acquisition of any interest
      belonging to the Government in the land on acquisition. It reiterated
      the settled position of law that the Government being the owner
      of the land need not acquire its own land merely because a person
      mistakenly resorted to acquire the land and later on mistakenly
      published notifications under Sections 4 and 6 of the Act.              F

      33. The aforesaid position was reiterated in a subsequent decision
      of this Court in Meher Rusi Dalal v. Union of India [(2004) 7
      SCC 362] . In SCC para 15 of the said judgment, this Court has
      held that the High Court has clearly erred in setting aside the
      order of the Special Land Acquisition Officer declining a reference     G
      since it is settled law that in land acquisition proceedings the
      Government cannot and does not acquire its own interest. While
      laying down the aforesaid law, this Court has referred to its earlier
      decision in Collector of Bombay v. Nusserwanji Rattanji Mistri
      [AIR 1955 SC 298 : (1955) 1 SCR 1311].                                  H
1178            SUPREME COURT REPORTS                           [2022] 2 S.C.R.


 A           34. We may at this stage appropriately refer to the decision of this
             Court in Kiran Singh v. Chaman Paswan [AIR 1954 SC 340 :
             (1955) 1 SCR 117] . In the said case this Court has held that
             judgment passed by a court without jurisdiction is a nullity and
             such a judgment could be challenged even in execution or collateral
             proceedings. The Court at SCR p. 121 at para 6 held thus: (AIR
 B
             p. 342, para 6)
             “6. … It is a fundamental principle well established that a decree
             passed by a court without jurisdiction is a nullity, and that its
             invalidity could be set up whenever and wherever it is sought to
             be enforced or relied upon, even at the stage of execution and
 C           even in collateral proceedings.”
             36. In view of the aforesaid decisions of this Court, it is crystal
             clear that the issuance of notifications under Sections 4 and 6 of
             the Act as also the award passed for acquisition of the land was a
             nullity and the subsequent action of the Government
 D           derequisitioning land by issuance of notification under Section 48
             was just and proper as that was an action for rectification of the
             mistake. The subsequent Land Acquisition Officer was justified
             in refusing to refer to the Reference Court in view of the fact that
             the land was already a government land and was so described in
 E           the revenue record itself. The Land Acquisition Officer, who
             passed the award, committed an illegality by not only determining
             the compensation under the Land Acquisition Act but also directing
             for retention of the interim compensation paid under the Jagir Act
             and also in directing for allotment of a developed plot of land
             admeasuring 2500 sq yd.
 F
             (16) We have to call into play certain principles in view of the
       peculiar nature of the facts.
              On the one hand, it is a case where the so-called subsequent
       developments had taken place during the pendency of the appeal before
 G     this Court. On the other hand, the authority obviously realizing the need
       to acquire the land for public purpose that is for construction of road
       resorted to the provisions of the 1956 Act. Here again, we must bear in
       mind the principle that the Government cannot acquire the land which
       has already vested in it. The other aspect we must also bear in mind is
       realizing the fact that the lands in question are the subject matter of the
 H     appeal and what is more, they would stand vested in terms of the
DELHI DEVELOPMENT AUTHORITY v. BHIM SAIN GOEL AND ORS. 1179
                  [K. M. JOSEPH, J.]

Constitution Bench judgment of this Court the lands have been excluded        A
when the final Award was passed under the 1956 Act. We may note
here that the respondents do not have a case that they have laid any
challenge to the exclusion of their lands in the final Award. Whatever
that may be, the fact remains that all these developments took place
during the pendency of the appeal.
                                                                              B
      (17) When the Court finally decides the lis, it is undoubtedly, open,
particularly this Court, having powers as it has under Article 142, to do
complete justice between the parties and we take it that the learned
counsel for the respondents is seeking to invoke the said jurisdiction.
       (18) If it is the principle of estoppel which can be invoked as it     C
would appear to us from the line of argument taken by the learned counsel
for the respondents, we are of the view that it is not tenable. Estoppel
flows from equity.
    (19) In the work SPENCER BOWER: RELIANCE-BASED
ESTOPPEL 5th Edition, we notice the following discussions.
                                                                              D
      “1.68 The requirement of unconscionability is that B cannot in
      good conscience assert that which he is estopped from asserting.
      Its use derives from equitable jurisprudence, ‘… reflecting in the
      word “conscience” the ecclesiastical origins of the long-departed
      Court of Chancery’ sitting as a court of conscience. Honesty and
                                                                              E
      innocence of intention will not, however, excuse B from liability to
      estoppel: what is material is not the state of B’s morals, but the
      effect of his representation or silence on the mind and will of A.
      B’s conduct need not, moreover, be shocking in any particular
      degree, beyond that, absent an estoppel, it would give rise to an
      unfair result. Lord Walker in Cobbe v Yeoman’s Row Management           F
      Ltd referred to the need for the result, without an estoppel, to
      ‘shock the conscience of the court’ but should not, it is submitted,
      be understood as requiring the court to find more than that B has
      by his representation caused A so to act (or omit to act) that the
      result would otherwise be unfair. The caution of Lord Radcliffe in
      Bridge v Campbell Discount as to its use in the context of equitable    G
      mitigation of the common law must also be exercised here.
      “Unconscionable” must not be taken to be a panacea for adjusting
      any contract between competent persons when it shows a rough
      edge to one side or the other…’. A flexible definition has been
      provided by Deane J in Common-wealth of Australia v Verwayen:           H
1180             SUPREME COURT REPORTS                             [2022] 2 S.C.R.


 A            ‘The doctrine of estoppel by conduct is founded upon good
              conscience… The most that can be said is that “unconscionable”
              should be understood in the sense of referring to what one party
              “ought not, in conscience, as between (the parties) to be allowed”
              to do (see Storey, Commentaries on Equity Jurisprudence, 2nd
              Eng Ed (1892) para 1219; Thompson v Palmer).”
 B
              (20) No doubt it could be argued that perhaps it may be the doctrine
       of election which is apposite. It is in connection with the cases related to
       election that terms like approbate and reprobate find mention. It could
       be contended that it may not be fair to allow the appellant to proceed
       under the 1956 Act and for the proceedings to culminate in the vesting
 C     of the property under Section 3D of the 1956 Act and having elected to
       take proceedings under the 1956 Act apparently on the basis of the
       impugned judgment namely that the proceeding under the 1894 Act stood
       lapsed, the authorities cannot be permitted to resile from their action.
       We would think that it would be wholly inequitable on facts to deprive
 D     the appellant of its rights when it is finally adjudicated in its favour in the
       facts of this case. It is also a case where the appellant has promptly
       approached this court against the impugned judgment. Furthermore, in
       the facts the balancing of equity must be worked out in favour of the
       appellant. In other words, the mere fact that proceedings were taken
       during the pendency of the case and it had reached the stage of declaration
 E     under Section 3D of the 1956 Act cannot suffice to cloth the respondents
       with a right to claim the fruits of the said proceedings, when on the final
       disposal of the appeal by us we only find that in law as declared by this
       court in the Constitution Bench, the land already would stand vested
       under the 1894 Act and as already noticed there cannot be vesting twice
 F     over.
              (21) We would think that in the facts of this case having regard to
       the fact that barring 81 days the respondents succeed on the strength of
       interim order passed from preventing the appellant from taking possession
       of the lands must be the crucial aspect which we have referred to.
 G            (22) The principle which has appealed to the Constitution Bench
       of this Court is squarely applicable to the facts of this case. The public
       authority which had set the law in motion under the earlier regime cannot
       be put to a loss when at the end of the day or on the day of reckoning it
       is found that they must succeed in law. Here we have found that the
 H     appellant is fully justified in contending that but for the orders passed by
DELHI DEVELOPMENT AUTHORITY v. BHIM SAIN GOEL AND ORS. 1181
                  [K. M. JOSEPH, J.]

the High Court and this Court, the possession would have been taken,               A
and the land would have vested under the law. We must proceed on the
basis that but for the interim orders passed which cannot survive the
final disposal of the cases, the land would have stood vested with the
Government under the earlier regime. The subsequent vesting which is
attributed to Section 3D of the 1956 Act, in our view must pale into
                                                                                   B
insignificance and cannot estop the appellant from contending that in
law the land would vest under the notification/ award issued under the
1894 Act.
       (23) Having seen the background of the facts, we do not think
that there is any right for the respondents to plead equity for they have
by their acts effectively prevented the public authority from enjoying the         C
fruits of law by which, in the exercise of power embedded in the 1894
Act, the land is vested with the appellant, and the land is one which is
needed for an important public project like construction of the road for
that matter.
      (24) It is clear as daylight that it would be completely antithetical        D
to public interest were the Government be compelled to shell out public
funds under the 2013 Act to acquire land which already belongs to it.
We cannot be oblivious to the said sublime principle as well.
      (25) We must again also bear in mind the restitutionary principle
which has been adverted to by the Constitution Bench. As we have                   E
already noticed, realizing that the lands are already vested, the lands are
already excluded under the final award. The inevitable outcome of the
above discussion is that the appellant must succeed.
        (26) However, in the facts of this case and in the interest of justice,
we think it fit to direct that if the respondents have not filed any application   F
under Section 18 of the 1894 Act seeking reference and claiming enhanced
compensation pursuant to the Award dated 22.08.2005, the respondents
should be granted an opportunity to make an application under Section
18 and the matter be adjudicated under the earlier Act. The impugned
judgment came to be passed based on the law as it was laid down by this
Court. Accordingly, we direct that in case, the respondents have already           G
not filed an application within the meaning of section 18 of the 1894 Act,
they are permitted to file application under Section 18 of the 1894 Act
within a period of one month from today. In case such an application is
made, it will be dealt with in accordance with law as it stood under the
1894 Act.                                                                          H
1182                SUPREME COURT REPORTS                       [2022] 2 S.C.R.


 A            The application will not be dismissed on the ground of delay. We
       make this order in the peculiar facts of this case and taking note of the
       fact that it is with our judgment rendered today that we are giving our
       imprimatur to the Award dated 22.08.2005 under the 1894 Act.
               The appeal is allowed. The impugned judgment will stand set aside.
 B             Parties to bear their own costs.

       Nidhi Jain                                                  Appeal allowed.



 C




 D




 E




 F




 G




 H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "land acquisition"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.