CITIBANK N.A.versusHITEN P. DALAL & ORS.
- Citation
- 2015 INSC 594
- Decided
- 21 August 2015
- Disposal
- Appeal(s) allowed
- Bench
- VIKRAMAJIT SEN
Holding
Restitution under Section 144 must be based on the actual market value of the bonds at the time they were delivered or sold, and the Special Court's order was set aside.
Summary
The Supreme Court examined a dispute arising from a money decree that was later set aside, where Citibank N.A. had received 9% IRFC bonds worth Rs.50 crore from Canbank Financial Services Ltd. (Canfina) and subsequently sold them in the market. The issue was how to calculate the restitution amount under Section 144 of the CPC when the bonds were no longer in the respondent's possession. The Court held that the value of the bonds must be determined on a realistic, verifiable basis—using the actual market price at the time of delivery or sale—rather than on speculative assumptions that the respondent retained the bonds till maturity. It found that the Special Court erred by ignoring the tradable nature of the bonds and by presuming the respondent’s retention, leading to an excessive restitution figure. Consequently, the Supreme Court set aside the Special Court’s order, accepted the appellant’s calculation of Rs.115.08 crore as the correct restitution amount, and ordered a refund of Rs.22.14 crore with 9% interest to the appellant. Both appeals were allowed.
Issues considered
- The appropriate method for calculating restitution under Section 144 when the subject property has been sold.
- Whether the market value at the time of delivery/sale should be used instead of face value or hypothetical future value.
- Whether a presumption that the respondent retained the bonds till maturity is permissible.
- Whether the Special Court erred in ignoring the tradable nature of the bonds for valuation.
- How to balance equity, fairness and avoidance of unmerited hardship in restitution orders.
Legislation cited
Subjects
Judgment
[2015].9 S.C.R. 583
CITIBANK N.A. A
v.
HiTEN P. DALAL& ORS.
(Civil Appeal No.3580 of2005 etc.)
AUGUST21, 2015 B
[VIKRAMAJIT SEN AND SHIVA KIRTI SINGH, JJ.]
Code of Civil Procedure, 1908 - s. 144 - Restitution of
decree- Money decree in favour of the appellant and against
the respondent - Respondent was directed either to pay c
Rs. 50 crores or to deliver 9% /RFC Bonds of the face value
of Rs. 50 crores alongwith 9% interest - Respondent opted
to deliver the bonds alongwith interest-Appellants disposed
of the bonds in the market, during March/April 1997, when
D
the prevailing market rate was Rs. 851- (face value of the bond
being Rs. 1001- redeemable on 15. 7. 2001) - Subsequently
the decree was reversed by Supreme Court - Demand of
Rs. 135, 18, 28, 0531- by way of restitution -Appellant as per
its own calculation tendered Rs.107, 75,40, 1411- before E
Special Court - Application by appellant before Special
Court for recording satisfaction of Supreme Court Judgment
- Respondent's application, claiming to be entitled to further
amount of Rs. 51. 83 crores- Special Court allowed additional
sum of Rs. 30, 13, 55, 1751- to respondent- On appeal, held: F
Power u/s. 144 has to be exercised to ensure equity, fairness
and justice to both the parties- For ascertaining the value of
the property which is no longer available for restitution, the
Court should adopt realistic and verifiable approach instead
of resorting to hypothetical and presumptive value - The G
Special Court determined the amount for restitution, ignoring
the relevant facts as to the value of the bonds on the date
• when the bonds were handed over to the appellant or the
583 H
584 SUPREME COURT REPORTS [2015] 9 S.C.R.
A date when the appellant sold them to the third party and by
.presuming that the respondent would have retained the bonds
with them till maturity - The alternative calculation of
Rs: 115, 08, 98, 8351- as suggested by the appellant is accepted
- the respondents are directed to refund Rs.22, 14,36, 7561-
B to the appellant with 9% interest.
Allowing the appeals, the Court
HELD: 1. Section 144 of the CPC, vests expansive
c power in the Court, but such power has to be exercised
to ensure equity, fairness and justice for both the parties.
It also flows from more or less common stand of parties
on the principle of law that for ascertaining the value of
the property which is no longer available for restitution
o on account of sale etc., the court should adopt a realistic
and verifiable approach instead of resorting to
hypothetical and presumptive value. It is also one of the
established propositions that in the context of
restitution, the Court should keep under consideration
E not only the loss suffered by the party entitled to
restitution but also the gain, if any, made by other party
who is obliged to make restitution. No unmerited injustice
should be caused to any of the parties. [Para 19] [597-E-
H]
F
2. In the present case, in the course of finding out
the value of the bonds which are no longer available for
restitution, the Special Court committed a clear error of
law in ignoring a relevant fact that the bonds in question
G were a tradable commodity on the stock market and its
value could be easily ascertained either on the date when
the bonds were handed over to the appellant-Bank or at
•
the time when the appellant-Bank sold the bonds to third
parties. Such relevant facts shou.ld not have been lost
H sight of and no presumption should have been made
CITIBANK N.A. v. HITEN P. DALAL & ORS. 585
thatthe respondent would have retained the bonds with A
it till the maturity period. [Para 20] [598-B~D]
3. There are sufficient materials available to lend ·
credence to the view that in all eventuality, the
respondent would have sold the bonds because it was B
· in such business and also because earlier when it had
the option, it chose to hand over the bonds to the
appellant~Bank instead of preferring the other option of
paying its monetary value. Sale of the bonds by the
appellant-Bank to third parties at a verifiable rate not C
being under dispute, it is evidently unjust to saddle the
appellant-Bank with liability to repay the possible gains
made by the third party or subsequent purchasers of
the bonds. Therefore, the amount determined by the
Special Court for restitution and payment by the D
appellant-Bank is unjust and is a result of error in not
keeping under view the relevant facts as well as in
applying the settled legal propositions for the purpose
of compensating the respondent by way of restitution.
[Para 20] [598-D-F] E
4. The appellant, as an alternative submission apart
from the figure of Rs.107 crores, suggested two other
figures by way of possible restitution which are Rs.109
crores, Rs.111.30 crores and 115,08 crores F
approximately. The figure of Rs. 115,08,98,835/- is
accepted to be correct calculation of the amount payable
by way of restitution by the appellant-Bank to the
respondent. After adjusting the further amount paid by
the appellant-Bank to the respondent under protest on G
25.4.2005, the appellant-Bank is entitled to a refund by
... the respondent as on 25.4.2005 to an amount of Rs.
22, 14,36,756/-. Interest on this amount at the rate of 9%
per annum from 25.4.2005 till the date of actual refund is H
allowed. [Paras 10 and 21] [592-B-D] [599-A-C]
586 SUPREME COURT REPORTS [2015] 9 S.C.R.
A Lal Bhagwant Singh vs. Rai Sahib Lala Sri Kishen Das
1953 SCR 559: AIR 1953 SC 136; Kartar Singh & Ors. vs.
State of Punjab 1995 (2) SCR 922 : (1995) 4 sec 101;
Kera/a State Electricity Board and Anr. vs. M.R.t=. Limited
1995 (6) Suppl. SCR 599: (1996) 1SCC597; South Eastern
B Coalfields Ltd. vs. State of M.P. & Ors. AIR 2003 SC 4482:
2003 (4) Suppl. SCR 651; Indian Council for Enviro-Legal
Action vs. Union of India & Ors. 2011 (9) SCR 146: (2011) 8
sec 161 - relied on.
c Lakshmi Amma vs. Thazhathitathil Krishna Kurup AIR
1931 Madras 81; S. Choka/ingam Asari vs. N.S. Krishna
Iyer and Ors. AIR 1964 Madras 404; Surendra Lal Chowdhury
and Ors. vs. Sultan Ahmed and Ors. AIR 1935 Calcutta 206
- approved.
D
Jai Berham vs. Kedar Nath Marwari AIR 1922 PC 269 -
referred to.
Case Law Reference
E AIR 1931 Madras 81 approved Para 13
AIR 1964 Madras 404 approved Para 13
AIR 1935 Calcutta 206 approved Para 13
F
1953 SCR 559 relied on Para 13
1995 (2) SCR 922 relied on Para 13
1995 (6) Suppl. SCR 599 relied on Para 13
G
2003 (4) Suppl. SCR 651 relied on Para 13
•
AIR 1922 PC 269 referred to Para 17 ••
2011 (9) SCR 146 relied on Para 18
H
CITIBANK N.A. v. HITEN P. DALAL & ORS. 587
CIVILAPPELLATE JURISDICTION :Civil Appeal No. 3580 A
of2005.
From the Judgment and Order dated 12.04.2005 of the
Special Court at Mumbai Constituted under The Special Court ,
(Trial of Offences Relating to Transactions in Secirotoes)Act, B
1992, in Miscellaneous Application No. 24 of 2005 in Suit No.
1of1995.
WITH
C. A. NO. 3548 of 2005. c
Kapil Sibal, P.K. Samdani, Bindi Dave, Rashmi Virmani,
Sandeep Narain, Ankit Virmani, Ashish Kothari, Abhishek
Prasad, S. Narain & Co. for the Appellant.
D
Pradeep Sancheti, Sunita Dutt, Shashank Trivedi, Rajiv
Mehta for the Respondents.
The Judgment of the Court was delivered by
SHIVA KIRTI SINGH, J. 1. The simple grievance of the E
appellant is that by impugned judgment and order dated
12.04.2005 passed by a Hon'ble Judge presiding over the
Special Court (Trial of Offences Relating to Transactions in
Securities) at Bombay ~as erred in determining an excessive F
amount payable by the appellant Citibank to the respondent
applicant- Canbank Financial Services Limited (hereinafter
referred to as 'Canfina') by way of restitution.
2. There is no dispute that on account of reversal of a
money decree in favour of Citibank in Suit No. 1 of 1995 filed G
by it against Canfina, by a common order dated 7.7.2004
passed by this Court in Civil Appeal nos. 7426, 9063 and 9138
of 1996, the Citibank is required to restore back the monetary
benefits it received under the decree against Canfina. The H
operative part of the said decree dated 22/23/26.04.1996 in
588 SUPREME COURT REPORTS [2015) 9 S.C.R.
A Suit no. 1 of 1995 is as follows:
"121. xxxxAccordingly, the defendants are directed to
deliver to the plaintiffs, 9% IRFC Bonds of the face value
of Rs. 50 crore within a period of 16 weeks xxx"
B
"122. the question then arises as to the interest the
defendants must therefore pay to the plaintiffs, the interest
@ 9% on these Bonds for the period starting from 151h
July, 1991 till they deliver the Bonds. If the Defendants
c do not deliver the Bonds but choose to return the monies
they must still pay interest. However, in my view the
Plaintiffs would still be entitled to interest at 9% only. This,
however, will be from the date the consideration amount
was received by the Defendants till the date of repayment.
D xxx.·
3. Since the decree gave an option to Canfina, it opted to
deliver to the Citibank the 9% IRFC Bonds of the face value of
Rs. 50 crores on 13.8.1996. It also paid the awarded interest
E at the rate of 9%. The aggregate interest amounted to
Rs.22,34,58,904/- calculated for the period 15.7.1991 to
30.6.1996. There is no controversy so far as the restitution of
interest amount is concerned but there is a strong disagreement
between the parties as to how the market value of the bonds
F be calculated for the purpose of effective and satisfactory
restitution. Admittedly the bonds delivered to Citibank on
13.8.1996, were being traded in the market and there is no
serious dispute that on that date the market value of a bond
was Rs. 81/- and the aggregate value of the bonds on that
G basis would be Rs 40.50 crores.
4. According to learned senior counsel, Mr. Kapil Sibal
the Canfina suffered only the loss of Rs 40.50 crores and Rs.
22.34 crores and on decree being set aside it is entitled only
H to such loss along with 9% interest, by way of restitution.
CITIBANK N.A. v. HITEN P. DALAL & ORS. 589
[SHIVAKIRTI SINGH, J.]
5. There would have been no difficulty in working out the A
loss of Canfina if it had opted to pay the money value of the
bonds instead of delivering the bonds. It is also not in dispute
that after receiving the bonds, Citibank in its wisdom disposed
of the bonds in the market during March/April 1997 when the
prevailing average market rate was Rs. 85/- per bond although B
its face value was Rs. 100/- redeemable on 15.7.2001. The
bonds delivered to City Bank carried with them coupons for
half yearly interest at the rate of 9% on the face value of the
bonds and for one set of coupons for half yearly interest, Rs.
2.25 crores in aggregate was also received by Citibank in C
January 1997. Thereafter between April/March 1997 the
Citibank sold the bonds at average price of Rs. 85/- receiving
in aggregate Rs. 42.56 crores.
6. By the very nature, the bonds, on 15.7.2001 attheirface D
value would be worth Rs. 50 crores. This along with half yearly
interest through coupons redeemed after April 1997 has
presumably gone to third parties who might have purchased
the bonds in the market.
E
7. The appellant Citibank in compliance of the judgment
of this Court dated 7.7.2004 had to offer restitution of "total
amount paid" by Canfina to Citibank (principal and interest)
along with interest at the rate of 9% per annum from the date
of payment. But in case the full amount was not paid by F
1.9.2004, the liability would increase to interest at the rate of
12% per annum till repayment by Citibank. Obviously, the total
amount of principal paid by Canfina to Citibank through delivery
of Bonds on 13.8.1996 had to be worked out in a reasonable
and just manner. This problem has arisen because Canfina G
had opted to deliver the bonds and not the money which it had
received for those bonds. Admittedly the total consideration
· paid by Citibank to Canfina for the 9% IRFC bonds of face
value of Rs. 50 crores was Rs. 49 crores at market value of H
Rs. 98/- on 30.12.1991 along with an interest component of
590 SUPREME COURT REPORTS [2015] 9 S.C.R.
A approximately Rs. 2 crores, bringing the total consideration to
Rs. 51,07, 12,328.77.
8. The issue is, when the bonds are no longer in currency
and not available for return by way of total amount paid by
B Canfina to the Citibank, then for restitution what method of
calculation shall serve the purpose best in arriving at the total
amount paid to Citibank "by way of principal'' which it must
return to Canfina.
c · 9. After the Supreme Court judgment on 12.7.2004
Canfina by a letter to Citibank demanded Rs. 135, 18,28,053/
- by way of restitution. The Citibank made its own calculations
and through its advocate's letter, on 19.7.2004 tendered the
aggregate amount of 107,75,40,141/- to Canfina. When
o Canfina declined to accept this offer the Citibank filed a
praecipe in the Special Court for depositing the aforesaid sum
in Court with notice to Canfina. The Special Court vide its order
dated 20. 7 .2004 recorded the statement of Canfina that it will
accept the amount without prejudice to their rights and
E contentions in view of their stand that the amount is not correct
and Canfina is entitled to claim more. Thereafter Citibank
unsuccessfully attempted to get a recording in this Court that it
had complied with the order of restitution. This Court on
26.10.2004 disposed of Citibank's I .A. no. 5 of 2004 in Civil
F Appeal No. 9063 of 1996 and granted liberty to Citibank to
approach the Special Court. On 24.12.2004 Citibank filed
miscellaneous application no. 24 of 2005 in the Special Court
for recording satisfaction of this Court's judgment. On 2.3.2005
Canfina also filed miscellaneous application no. 118 of 2005
G claiming that it was entitled to further amount of approximately
Rs. 51.83 crores after deducting Rs ..107. 76 crores
approximately already paid by Citibank. By the impugned order
dated 12.4.2005 the Special Court disposed of both the above
H applications and allowed an additional sum of Rs.
30, 13,55, 175/-. This amount has been paid by the appellant
CITIBANK N.A. v. HITEN P. DALAL &ORS. 591
[SHIVAKIRTI SINGH, J.]
without prejudice to its rights sought through the present A
appeals arising out of common judgment dismissing
appellant's miscellaneous application and allowing that
preferred by Canfina.
10. Learned senior counsel for the appellant, Mr. Kapil B
Sibal as well as learned senior counsel for the respondent
Canfina have relied upon various judgments, many of them
being common, to highlight the true meaning of restitution in
the light of Section 144 of the Code of Civil Procedure. It goes
without saying that they highlighted different words and C
sentences to support their respective case. Simply put, the
contention on behalf of the Citibank is that for restitution the
correct amount is required to be calculated on the basis of
"market value" of the bonds when they were delivered by
Canfina to the Citibank i.e, atthe rate of Rs.81/-, aggregating D
Rs. 40.50 crores. This amount and also approximately Rs.
22.34 crores paid by Canfina as interest at the rate of 9% per
annum for the period 15.7.1991 to 30.6.1996 is the "total
amount paid" by Canfina to Citib;mk as principal and interest
and therefore the sum of these two amounts alone is required E
to be repaid by way of restitution along with interest at the rate
of 9% per annum because the Citibank chose to comply with
the order of Supreme Court for the purpose of restitution before
1.9.2004 by tendering the aggregate sum of Rs. F
107, 75,40, 141 /~to Canfina. However, in order to appear more
fair and accommodative, Citibank has placed three more set
of calculations/charts. The first chart claims that in the light of
various judgments on the issue of restitution, it may be proper
to calculate the market value of the bonds on the basis of NSE G
letter showing the rate as Rs. 82.80 per bond. So calculated,
the total amount along with interest payable to Canfina has
been shown as Rs.109,31,28,500/-. The second chart shows
the total amount payable as Rs.111,30,97 ,602/-. This has been
calculated by accepting the market value of the bonds on the H
592 SUPREME COURT REPORTS [2015] 9 S.C.R.
A basis of average sale price during March/April 1997 as
Rs.85.129 per bond aggregating Rs. 42,56,45,000/-. From
the figures in the two charts noted above, it is evident that while
seeking to justify its earlier calculation of approximately Rs.
107 crores as the total value of restitution, as an alternative
B submission Citibank appears to have suggested two other
figures by way of possible restitution which are Rs. 109 crores
and Rs. 111.30 crores approximately. But the last chart (third
in this series) filed on behalf of Citibank acknowledges a further
receipt of Rs. 2.25 crores as coupon interest for half yearly
C coupons dated 1.1.1997 on which interest has been calculated
till 20. 7.2004. That brings the aggregate total amount payable
to Canfina as Rs. 115,08,98,835/-. Since Citibank paid the
sum of Rs. 30, 13,55, 175/- on April 25, 2005 in terms of the
impugned order hence as per the last chart of calculations
0
noted above, it has claimed that on adjustment, it is entitled to
refund by Canfina as on April 25, 2005 of a total sum of Rs.
22, 14,36,756/- along with interest either at the rate of 12%
per annum or as may be awarded by this Court on the aforesaid
E amount from 25th April 2005 till the date of actual refund.
11. On the other hand the stand of the Canfina is that after
the Supreme Court judgment setting aside the decree against
Canfina on 7. 7.2004 the only safe method for calculating the
F value of the bonds delivered to Citibank on 13.8.1996 would
be to accept and act upon its face value, i.e, Rs. 100/- per
bond on the maturity date, 15.7.2001 and add to it the half
yearly interest received after 13.8.1996 and then calculate
interest on and from 15.7.2001 at the rate indicated in the order
G of this Court dated 7.7.2004. The aforesaid claim, according
to Canfina has rightly been accepted by the Special Court in
the impugned order so that status quo ante is restored by way
of restitution by ignoring the intervening circumstance of sale
of the bonds by Citibank to third parties in March/April 1997.
H
12. In reply learned senior counsel for the appellant has
CITIBANK N.A. v. HITEN P. DALAL & ORS. 593
[SHIVAKIRTI SINGH, J.]
criticized the impugned order by highlighting that in paragraph A
7 the Special Court has erred in going beyond the three items
.delivered by Canfina to Citibank i.e, the bonds, the amount of
interest and interest coupons by indulging in speculation that
"had the Canfina not been required to deliver the bonds to
Citibank, the bonds would have remained with it so also the B
amount of interest till the date of redemption." Same criticism
was also made against another observation/opinion of the
Special Court in the same paragraph recorded in the following
words:
c
" ............. in so far as the restitution is concerned the
fact that the bonds were sold by Citibank during the
pendency of the appeal is not relevant."·
The contention of appellant is that the Special Court came o
to an unjust and erroneous conclusion that Canfina would be
entitled to the redemption value of the bonds i.e, Rs. 50 Crores,
mainly on account of aforesaid erroneous presumption and
opinion.
E
13. Learned senior counsel, Mr. Kapil Sibal has advanced
a contention that as per settled principles of law governing
restitution, the respondent Canfina can be given back only what
it lost on the date it satisfied the decree which was ultimately
reversed and not what it could have gained on certain F
presumptions made in the impugned order. In support of this
contention he placed reliance upon two judgments of Madras
High Court in the case of Lakshmi Amma vs.
Thazhathitathil Krishna Kurup (AIR 1931 Madras 81) and
in the case of S. Chokalingam Asari vs. N.S. Krishna Iyer G
and Ors. (AIR 1964 Madras404). He also placed reliance on
Calcutta High Court judgment in the case of Surendra Lal
Chowdhury and Ors. vs. Sultan Ahmed and Ors. (AIR 1935
Calcutta 206) and the following four Supreme Court judgments:
H
594 SUPREME COURT REPORTS [2015] 9 S.C.R.
A 1. Lal Bhagwant Singh vs. Rai Sahib Lala Sri
Kishen Das, 1953 SCR 559=AIR 1953 SC 136
2. Kartar Singh & Ors. vs. State of Punjab,
(1995) 4 sec 101
B
3. Kerala State Electricity Board and Anr. vs.
M.R.F. Limited, (1996) 1 sec 597
4. South Eastern Coalfields Ltd. vs. State of
M.P. & Ors., AIR 2003 SC 4482
c
14. In the case of Lakshmi Amma (Supra), the Madras
High Court noticed certain privy council judgments and also
the contention that Section 144 of the CPC providing for
restitution would apply only to cases where in execution of a
D decree passed by one court a benefit is received by the decree
holder and thereafter that decree is reversed or set aside
·subsequently by a competent court then in such cases the court
should place the parties in the position which they would have
occupied but for such a decree which was varied or set aside.
E However, on the facts of that case the claim of the plaintiff
appellant for restitution was turned down. In the other Madras
High Court judgment in the case of S. Chokalingam (Supra)
the right of a bona fide purchaser for value was upheld in
F paragraph 30 of the judgment and thereafter in paragraph 31
reliance was placed upon judgment of this Court in the case of
Bhagwant Singh (Supra) by extracting the following
passage:
" The doctrine of restitution is that on the reversal of a
G judgment the law raises an obligation on the party to the
record, who received the benefit of the erroneous
judgment to make restitution to the other party for what
he had lost and it is the duty of the Court to enforce that
obligation unless it is shown that restitution would be
H
CITIBANK N.A. v. HITEN P. DALAL & ORS. 595
[SHIVAKIRTI SINGH, J.]
clearly contrary to the interests of justice." A
15. In the case of Surendra Lal (Supra), the Calcutta
High Court explained that it is the duty of the Court under
Section 144 CPC to place the parties in the earlier position
after a decree executed in favour of one be varied or reversed. B
But it was clarified that "in assessing what a party may have
lost or of what he may have been deprived during his
·dispossession the law takes into account not what he could
have made but what his opponent did in fact make or could
with reasonable diligence have made." This conclusion was C
predicated on the reasoning that in vast majority of cases it
would be hypothetical, remote and uncertain to find out what
the party subjected to dispossession could have made if it
was left in possession.
D
16. The ·relevant part of judgment in the case of
Bhagwant Singh (Supra) has been extracted in the Madras
High Court judgment and a1ready noticed earlier. This Court in
the penultimate paragraph has reiterated the salutary and well
established principle of restitution that on the reversal of a E
judgment the party who received the benefit of an erroneous
judgment is obliged to make restitution to the other party for
what he had lost. The Court is also duty bound to enforce such
obligation unless it finds that restitution would be clearly
contrary to the real justice of the case. Similar words have been F
used by this Court in the case of Kartar Singh (Supra) by
holding that the party which had received the benefit of the
erroneous decree is required to make the restitution to other
party for what he had lost.
G
17. In the case of Kerala State Electricity Board
(Supra) also the view taken by this Court was similar. But it
was further clarified that the Court has a duty that in the matter
of restitution justice be done as per facts of the case, In granting
relief of restitution the Court "should not be oblivious of any H
596 SUPREME COURT REPORTS (2015) 9 S.C.R.
A unmerited hardship to be suffered by the party against whom
action by way of restitution is taken." This Court favoured a
pragmatic view and grant of relief in a manner as may be
reasonable, fair and practicable without causing unmerited
hardships to either of the parties. In the case of South Eastern
B Coalfields Limited (Supra), this Court re-emphasized that
restitution is for meeting the ends of justice and depends upon
the peculiar facts and circumstances of the case. This Court
further clarified in para 27 that as held by Privy Council in the
case of Jai Berham vs. Kedar Nath Marwari, AIR 1922 PC
C 269, Section 144 CPC is rather a statutory recognition of an
already existing rule of justice, equity and fair play and therefore
even apart from Section 144 the Court has inherent jurisdiction
to order restitution so as to do complete justice between the
parties. Th is Court approved the view of the Privy Council that
0
the Court has to act rightly and fairly according to the
circumstances, towards all parties involved.
18. Learned senior counsel for the respondent Canfina,
as was indicated earlier also placed reliance upon the
E aforesaid judgments in support of hi~ plea that restitution
requires that the parties be placed in the position which they
could have occupied but for the wrong order or decree which
is ultimately varied or reversed. He amplified his submissions
F by highlighting certain other paragraphs in the earlier noted
judgments that suggest that the status quo as obtaining on the
date of wrongful deprivation should be restored and only if.
same is not possible due to intervening circumstances like
the sale of the property, price and mesne profits may have to ·
G be ordered. According to him the actual sale is of no
consequence for calculating what the wronged party had
actually lost. However, according to him also, for proper
restitution the Court must rely upon verifiable value of the goods
lost due to sale etc. and not indulge in speculation or
H hypothetical presumptions. He placed reliance also upon
CITIBANK N.A. v. HITEN P. DALAL & ORS. 597
[SHIVAKIRTI SINGH, J.]
judgment of this Court in the case of Indian Council for A
Enviro-Legal Action vs. Union of India & Ors. (2011) 8
sec 161. This judgment was in the context of constitutional
provisions such as Article 21 and compensation for loss
suffered by citizenry due to pollution. Advancing the principle
that the polluter pays for the sufferings, the Court propounded B
the principle of disgorgement of gains of wrongdoers and that
the Court could even think of imposing compound interest in
place of simple interest provided by statute. Exercise of such
inherent powers was contemplated only in interest of principles
of justice and equity as warranted by the facts in cases of C
pollution causing sufferings to citizenry. All these principles
were justified on the basis of power to order for restitution under
inherent powers of the Court. But this Court did not over-rule
any of the earlier judgments of this Court laying down classic
0
principles of restitution under Section 144 of the CPC on which
the appellant has placed reliance and which require a just and
fair approach s0 that no unmerited hardship is caused to either
of the parties.
19. In the ultimate analysis we find that the law on. E
restitution under Section 144 of the CPC is quite well settled.
It vests expansive power in the Court but such power has to be
exercised to ensure equity, fairness and justice for both the
parties. It also flows from more or less common stand of parties F
on the principle of law that for ascertaining the value of the
property which is no longer available for restitution on account
of sale etc., the Court should adopt a realistic and verifiable
approach instead of resorting to hypothetical and presumptive
value. It is also one of the established propositions that in the G
context of restitution the Court should keep under consideration
not only the loss suffered by the party entitled to restitution but
also the gain, if any, made by other party who is obliged to
make restitution. No unmerited injustice should be caused to
any of the parties. H
598 SUPREME COURT REPORTS [2015] 9 S.C.R.
A 20. Keeping the aforesaid principles in view it has to be
seen whether the order under appeal suffers from any illegality
requiring interference and correction by this Court. In our
considered view in the course of finding out the value of the
bonds which. are no longer available for restitution, the learned
B Special Court committed a clear error of law in ignoring a
relevant fact that the bonds in question were a tradable
commodity on the stock market and its value could be easily
ascertained either on the date when the bonds were handed
over to the Citibank or at the time when the Citibank sold the
C bonds to third parties. Such relevant facts should not have been
lost sight of and no presumption should have been made that
Canfina would have retained the bonds with it till the maturity
period. There are sufficient materials available to lend credence
D to the view that in all eventuality Canfina would have sold the
bonds because it was in such business and also because
earlier whe~ it had the option, it chose to hand over the bonds
to Citibank instead of preferring the other option of paying its
monetary value. Sale of the bonds by Citibank to third parties
E at a verifiable rate not being under dispute, it is evidently unjust
·to saddle Citibank with liability to repay the possible gains
made by the third party or subsequent purchasers of the bonds.
For these reasons we come to the conclusion that the amount
determined by the Special Court for restitution and payment
F by Citibank is unjust and is a result of error in not keeping
under view the relevant facts as well as in applying the settled
legal propositions for the purpose of compensating Canfina
by way ofrestitution.
G 21. In view of above the impugned order is set aside. In
order to bring the dispute to a just, logical and early conclusion,
instead of remanding the matter to the Special Court we accept
the last chart submitted on behalf of appellant to be correct
calculation of the amount payable by way of .restitution by
H Citibank to Canfina. As noted earlier as per such chart the
CITIBANK N.A. v. HITEN P. DALAL & ORS. 599
[SHIVAKIRTI SINGH, J.]
total amount payable to Canfina on 20.7.2004 is Rs. A
115,08,98,835/- and after adjusting the further amount paid by
Citibank to Canfina under protest on 25.4.2005 the Citibank
is entitled to a refund by Canfina as on 25.4.2005 to an amount
of Rs. 22,14,36,756/-. In line with earlier orders, we allow
interest on this amount at the rate of 9% per annum from B
25.4.2005 till the date of actual refund. Canfina should make a
refund of aforesaid due amount along with interest awarded
by us within four weeks. Both the appeals are allowed to the
extent indicated above. In the facts of the case there shall be
no order as to costs. c
Kalpana K. Tripathy Appeals allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.