BHUPENDRA KUMAR CHIMANBHAI KACHIYA PATELversusDIVISIONAL CONTROLLER GSRTC NADIAD
- Citation
- 2018 INSC 218
- Decided
- 7 March 2018
- Disposal
- Dismissed
- Bench
- R K AGRAWAL
Holding
A settlement entered into under Section 18 of the Industrial Disputes Act is binding on both parties and the benefit of permanent absorption and time‑scale for Badali Kamdars is to be granted only from the date of their absorption in the permanent cadre as prescribed in Clause 20 of the settlement.
Summary
The Gujarat State Road Transport Corporation (GSRTC) and the Union of its workers entered into a settlement on 21‑12‑1989, wherein Clause 20 prescribed that Badali Kamdars would be regularised and absorbed into the permanent conductor cadre after completing 180 days of continuous service in that cadre. Several Badali Kamdars, including the appellant, were later absorbed as conductors and were granted the time‑scale benefits from the date of absorption, not from their original appointment as Badali Kamdars. The employees contended that the benefits should accrue from the date of their initial appointment, leading to a dispute resolved by an Industrial Tribunal in their favour, which was subsequently set aside by the Gujarat High Court. The appellants appealed to the Supreme Court, arguing that the Tribunal’s findings were correct and that the settlement should be interpreted to grant benefits from the original appointment date. The Court held that the settlement, being a binding agreement under Section 18 of the Industrial Disputes Act, must be applied as per its terms, and therefore the benefits are rightly granted from the date of absorption in the permanent cadre as per Clause 20. Consequently, the appeals were dismissed.
Issues considered
- The interpretation of Clause 20 of the 1989 settlement regarding the commencement of permanent absorption and time‑scale benefits for Badali Kamdars.
- Whether a settlement entered into under Section 18 of the Industrial Disputes Act is binding on both employer and employees.
- Whether the benefit of permanent status and time‑scale should be calculated from the date of initial appointment as Badali Kamdar or from the date of absorption into the permanent cadre.
Legislation cited
- Industrial Disputes Act, 1947s. 18, s. 25C
Subjects
Judgment
[2018] 3 S.C.R. 567 567
BHUPENDRA KUMAR CHIMANBHAI KACHIYA PATEL A
v.
DIVISIONAL CONTROLLER GSRTC NADIAD
(Civil Appeal No. 2546 of 2018)
MARCH 07, 2018 B
[R. K. AGRAWAL AND ABHAY MANOHAR SAPRE, JJ.]
Industrial Disputes Act, 1947 – s.18 and Explanation to s.25C
– Appellants-employees joined the services of respondent-State Road
Transport Corporation as “Badali Kamdars” – Settlement between
C
Union of the workers and Corporation to resolve several issues in
relation to service conditions of the employees – cl.20 of the
Settlement, dealt with the placement and absorption of the “Badali
Kamdars” in the permanent cadre of conductor and grant of time
scale to such workers –Hundreds of “Badali Kamdars” who were
found eligible and fulfilled the conditions in terms of cl.20 of the D
settlement were absorbed in the services as permanent employees
on the post of conductor and were accordingly given the time scale
on the expiry of completion of 180 days in the cadre – Dispute
between these employees and the Corporation as to from which
date the benefit to make them permanent and the benefit of time
E
scale should be granted to such “Badali Kamdars” – Industrial
Tribunal answered the reference in favour of the employees – High
Court set aside the award of Industrial Tribunal –Held: Settlement
once arrived at between the employer and the employees as provided
in s.18 is binding on the employer and the employees – It is not in
dispute that the Corporation and the Union of workers entered into F
the settlement – Corporation followed the procedure provided in
cl.20 while granting the employees their permanent cadre and the
time scale of conductor– There is no basis for the appellants to
claim the aforesaid benefit on their completing 180 days of the
service from the date of their initial appointment as “Badali
G
Kamdars” as against on the expiry of 180 days from the date when
they were absorbed in the permanent cadre – Appellants neither
challenged the settlement nor its applicability – Settlement is binding
on both parties in terms of s.18.
H
567
568 SUPREME COURT REPORTS [2018] 3 S.C.R.
A Dismissing the appeals, the Court
HELD: 1.1 Settlement once arrived at between the
employer and the employees as provided in Section 18 of the
Industrial Disputes Act, 1947, is binding on the employer and
the employees. It is not in dispute that, the Corporation and the
B Union of the workers of the Corporation had entered into the
settlement in respect of various issues in relation to their service
conditions. One such issue was in relation to the absorption of
Badali Kamdars in the permanent cadre of the Corporation.
Clause 20 provides the manner in which it was to be given effect
to by the parties. [Paras 25, 26] [572-F-H]
C
1.2 It is not in dispute that the Corporation followed the
procedure provided in clause 20 while granting the employees
their permanent cadre and the time scale of conductor. In other
words, all eligible “Badali Kamdars” were absorbed in the set
up and accordingly granted benefit in terms of the procedure
D prescribed in clause 20 of the Settlement. [Para 28] [574-A]
1.3 There is no basis for the appellants (employees) to claim
the benefit from the date of their initial appointment as “Badali
Kamdar”. Indeed, there is neither any factual foundation nor any
legal foundation to claim such benefit. The appellants neither
E challenged the settlement nor its applicability. In other words,
the legality or/and binding nature of settlement was never
questioned in these proceedings. In this view of the matter, the
settlement is binding on both parties in terms of Section 18 of
the Act. The concept of “Badli Kamdar” is statutorily recognized
F under the Act. Explanation to Section 25C defines the term “Badli
Kamdar”. [Paras 30, 33 and 34] [574-D-G; 575-A]
1.4 The appellants referred extensively to the evidence
led by the parties to support their submission. The evidence
cannot be appreciated in the appeals filed under Article 136 of
G the Constitution. It is more so when the Single Judge and Division
Bench did not agree with the factual findings of the Tribunal and
rightly reversed those findings. It is binding on this Court.
[Paras 38 and 39] [575-E-F]
H
BHUPENDRA KUMAR CHIMANBHAI KACHIYA PATEL v. DIVISIONAL 569
CONTROLLER GSRTC NADIAD
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2546 A
of 2018.
From the Judgment and Order dated 28.06.2016 of the High Court
of Gujarat at Ahmedabad in LPA No. 550 of 2016
WITH
Civil Appeal Nos. 2594-2597, 2556-2592, 2547-2555 of 2018. B
Tushar Mehta, ASG, Colin Gonsalves, Sr. Adv., Nikhil Goel,
Ms. Naveen Goel, Ashutosh Ghade, Ms. Aditi Gupta, Satya Mitra, Advs.
for the appearing parties.
The Judgment of the Court was delivered by
C
ABHAY MANOHAR SAPRE, J. 1. Leave granted.
2. These appeals are filed against the final judgments and orders
passed by the High Court of Gujarat at Ahmedabad dated 28.06.2016 in
L.P.A. No.550/2016, dated 22.08.2017 in L.P.A. Nos.1344-1347/2017,
dated 04.07.2017 in L.P.A. Nos.1185/2014, 1199, 1252, 1254-1259, 1261, D
1264-1278, 1281-1282, 1284, 1286, 1288, 1291-1296, 1298/2014, dated
21.06.2016 in L.P.A. Nos.497-500/2016 and dated 04.07.2017 in L.P.A.
Nos.1200, 1287, 1289, 1297 and 1299/2014 whereby the Division Bench
of the High Court dismissed the appeals filed by the appellants herein
and upheld the orders passed by the Single Judge of the High Court.
3. In order to appreciate the issues involved in these appeals, it is E
necessary to set out the facts in detail. The facts and the legal issues
arising in all these appeals are similar in nature except the date of their
initial appointment and absorption, which vary from case to case in the
service of the respondent.
4. For the sake of convenience, the facts mentioned in Reference F
I.T. No.44/2011 (Annexure- 12) of the paper book of SLP Nos. 28519-
28522 of 2017 are mentioned hereinbelow.
5. Prafulbhai Hirabhai Solanki, one of the appellants herein, whose
name appears at page 18 of the SLP paper book joined the services of
the respondent-Gujarat State Road Transport Corporation (hereinafter G
referred to as “the Corporation) on 04.06.1999 as “Badali Kamdar” at
Mangrol Depot of Junagadh Section. He was employed as a daily wager.
6. On 21.12.1989, the Corporation and the Union of the workers
entered into a settlement to resolve several issues in relation to the service
conditions of the employees working in the Corporation. H
570 SUPREME COURT REPORTS [2018] 3 S.C.R.
A 7. Clause 20 of the Settlement, which is relevant for the disposal
of these appeals, deals with the placement and absorption of the “Badali
Kamdar” in the permanent cadre of conductor and grant of time scale
to such workers. It provides a procedure as to how, when and in what
manner, the services of a “Badali Kamdar” shall be regularized and
absorbed in a particular time scale.
B
8. In terms of clause 20 of the settlement dated 21.12.1989, the
Corporation considered the case of the appellant when the vacancy
occurred in the permanent cadre on the post of Conductor and accordingly
he was absorbed as permanent employee in the services of the
C Corporation on 27.08.2008 as Conductor. He was given the time scale
with effect from 27.08.2008 with consequential benefits.
9. Like the appellant, there were hundreds of “Badali Kamdars”
who were working in the set up of Corporation at all relevant time. The
cases of these “Badali Kamdars” were also considered with a view to
D find out as to whether they fulfill the conditions set out in clause 20 for
making them permanent in the set up of the Corporation as and when
permanent vacancy arose in the cadre of the Conductor. Those who
were found eligible and fulfilled the conditions were absorbed in the
services as permanent employees on the post of conductor and were
accordingly given the time scale on the expiry of completion of 180 days
E in the cadre. They were accordingly made permanent in terms of the
procedure prescribed in clause 20 of the Settlement.
10. This led to dispute between these employees and the
Corporation. The dispute was essentially as to from which date this
benefit, namely, to make them permanent and the benefit of time scale
F
should be granted to such “Badali Kamdars”.
11. According to the employee (appellant), he was entitled to
claim this benefit on his completing 180 days of the service from the
date of his initial joining of the service as “Badali Kamdar”, i.e.,
G 04.06.1999 and not from the date of absorption whereas according to
the Corporation, the appellant and all employees alike the appellant were
rightly granted the benefit on the expiry of 180 days from the date when
they were absorbed in the permanent cadre, i.e., as in the
case of the appellant from 27.08.2008 as provided in clause 20
of the Settlement.
H
BHUPENDRA KUMAR CHIMANBHAI KACHIYA PATEL v. DIVISIONAL 571
CONTROLLER GSRTC NADIAD [ABHAY MANOHAR SAPRE, J.]
12. This issue was accordingly referred to the Industrial Tribunal, A
Rajkot at the instance of the appellant under Section 10 of the Industrial
Dispute Act (hereinafter referred to as “the Act”). Several such
references were made to the Industrial Tribunal at the instance of similarly
situated employees.
13. By award dated 08.08.2013 (Annexure-P-12), the Industrial B
Tribunal answered the reference in favour of the employees and
accordingly granted them benefit, which the employees had claimed. In
other words, the Industrial Tribunal held that the appellant (employee) is
entitled to claim the permanent absorption in his service in the time scale
as Conductor with effect from the completion of his 180 days of service C
period from the date of his initial joining, i.e., 04.06.1999. The Corporation
was accordingly asked to pay all consequential benefits from such date.
In substance, the Industrial Tribunal rejected the stand taken by the
Corporation.
14. The Corporation felt aggrieved and filed writ petition in the D
High Court of Gujarat at Ahmadabad. The Single Judge of the High
Court, by order dated 18.09.2014, allowed the writ petition and set aside
the award of the Industrial Tribunal. The Single Judge accepted the
stand taken by the Corporation and accordingly upheld their action in
granting the benefit to the employee (appellant) from 27.08.2008 as
provided in clause 20 of the Settlement. E
15. The appellants (employees) felt aggrieved and filed intra court
appeals before the Division Bench. By impugned judgments and orders,
the Division Bench dismissed the appeals filed by the employees and
upheld the orders of the Single Judge, which has given rise to filing of
F
these appeals by way of special leave by the employees in this Court.
16. Heard Mr. Colin Gonsalves, learned senior counsel for the
appellants and Mr. Tushar Mehta, learned Additional Solicitor General
for the respondent.
17. Mr. Colin Gonsalves learned senior counsel appearing for the G
appellants(employees) while assailing the legality and correctness of the
impugned orders contended that the reasoning and the conclusion arrived
at by the Industrial Tribunal was just, proper and legal and hence it should
not have been interfered with by the High Court (Single Judge and Division
Bench). H
572 SUPREME COURT REPORTS [2018] 3 S.C.R.
A 18. Learned counsel urged that the findings of the Industrial Tribunal
were based on proper appreciation of evidence adduced by the parties
and hence such findings could not be faulted with. Learned counsel took
us through the evidence to show that the findings recorded by the Industrial
Tribunal deserve to be upheld as against the findings of Single Judge and
Division Bench.
B
19. Learned counsel placed reliance on some judicial orders passed
in previous litigation between the Corporation and its employees which,
according to him, decided the issue in question in favour of the employees.
20. Learned senior counsel for the appellants submitted that in
C the light of these judicial orders, the similar order should be passed in
these appeals also.
21. In reply, Mr. Tushar Mehta, learned Additional Solicitor General,
appearing for the respondent supported the impugned judgment and
contended that the concurrent findings of the High Court (Single Judge
D and Division Bench) deserve to be upheld.
22. Placing reliance on clause 20 of the settlement, learned ASG
contended that the action taken by the Corporation is in conformity with
the requirements of Clause 20 and hence deserves to be upheld.
E 23. Having heard the learned counsel for the parties and on perusal
of the record of the case, we find no merit in the appeals.
24. As rightly argued by the learned ASG, the issue in question
has to be decided in the light of clause 20 of the Settlement.
F 25. One cannot dispute the legal proposition that the settlement
once arrived at between the employer and the employees as provided in
Section 18 of the Act, it is binding on the employer and the employees.
26. It is not in dispute that on 21.12.1989, the Corporation and the
Union of the workers of the Corporation has entered into the settlement
G in respect of various issues in relation to their service conditions. One
such issue was in relation to the absorption of Badali Kamdars in the
permanent cadre of the Corporation. Clause 20 provides the manner in
which it is to be given effect to by the parties.
H
BHUPENDRA KUMAR CHIMANBHAI KACHIYA PATEL v. DIVISIONAL 573
CONTROLLER GSRTC NADIAD [ABHAY MANOHAR SAPRE, J.]
27. Clause 20 of the Settlement dated 21.12.1989 reads as under: A
“In reference to the representation made to delete the
provision of the section 29 of the settlement dated 23/11/
1984 and implement the provision of section 43 of the
settlement dated 22/10/1964 it is determined that after
preparing the Division wise list of the selected employees B
they will be given temporary/daily wager appointment
against the permanent posts in the division/unit, and if such
appointed temporary/daily wager has worked continuously
for 180 days including the weekly holiday/paid holiday and
authorize leave then they will be taken on time scale. This
C
provision will not be applicable to the employees on work
charge working in the Civil Engineering Department and
such appointed temporary/daily wager has worked
continuously for 180 days including the weekly holiday/paid
holiday and authorized leave then they will be taken in time
scale and they will be entitled to all benefits available to D
time scale employees. The absence due to authorized leave
for the above purpose will not be considered break and
these days will not be considered for 180 days service.
As per permission of S.T.T. 1981, if the recruitment of the
staff has been done as a temporary or badli kamdar then E
after completion of their 180 days of service on the
permitted vacancies they would be taken on time scale
serially.
Such workers will be granted all benefits as per the Rules
along with the notional increment with effect from 1.8.87 F
and there will not be any recoveries made from them nor
there will be any arrears paid.
The workmen taken into service are not required during
the monsoon, therefore they can be retrenched as per the
requirement and after the monsoon if their services are G
required then again as per seniority they will be taken in
time scale. If there is any permanent post vacant then the
appointment of the administrative staff will be made on time
scale.”
H
574 SUPREME COURT REPORTS [2018] 3 S.C.R.
A 28. It is not in dispute that the Corporation has followed the
procedure provided in clause 20 while granting the employees their
permanent cadre and the time scale of conductor. In other words, all
eligible “Badali Kamdars” were absorbed in the set up and accordingly
granted benefit in terms of the procedure prescribed in clause 20 of the
Settlement.
B
29. It is also clear from the undisputed facts that firstly, the appellant
(employee concerned) was appointed as “Badali Kamdar” in the set up
of Corporation on 04.06.1999; Secondly, clear vacancy arose in the
permanent cadre of Conductor in and around 27.08.2008; Thirdly, as per
the seniority list of the “Badali Kamdars”, the appellant was accordingly
C absorbed in the permanent cadre at the time scale with effect from
27.08.2008 on completion of 180 days of his service in the cadre and, as
a consequence thereof, was given all the benefits of the said post from
the said date; and lastly, since then the appellant and all employees alike
him are continuing on their respective post.
D 30. In our considered opinion, in the light of what we have held
above, there is no basis for the appellants (employees) to claim the
aforesaid benefit from the date of their initial appointment as “Badali
Kamdar”. Indeed, there is neither any factual foundation nor any legal
foundation to claim such benefit.
E 31. Learned counsel for the appellants was also not able to show
any document, such as any term/condition in the appointment letter or in
the settlement or any Rule/Regulation framed by the Corporation
recognizing such right in appellants’ favour to enable them to claim such
benefit from the date of their initial appointment.
F 32. Clause 20 of the Settlement is the only clause which recognizes
the appellant’s right for consideration of his case on individual basis and
to grant him the benefit subject to his fulfilling conditions specified therein
which, in appellant’s case, were found satisfied and accordingly, he was
granted the benefit along with each such employees.
G 33. It is pertinent to mention that the appellants neither challenged
the settlement nor its applicability. In other words, the legality or/and
binding nature of settlement dated 21.12.1989 was never questioned in
these proceedings. In this view of the matter, the settlement is binding
on both parties in terms of Section 18 of the Act.
H
BHUPENDRA KUMAR CHIMANBHAI KACHIYA PATEL v. DIVISIONAL 575
CONTROLLER GSRTC NADIAD [ABHAY MANOHAR SAPRE, J.]
34. The concept of “Badli Kamdar” is statutorily recognized under A
the Act. Explanation to Section 25C defines the term “Badli Kamdar”.
The appellant never questioned his status as “Badli Kamdar”. Indeed, it
is due to the status of “Badli Kamdar”, which he enjoyed for few years
in the service of Corporation, he got the benefit of absorption in permanent
cadre.
B
35. So far as the reliance placed by the learned counsel for the
appellants on some previous judicial orders are concerned, in our view,
they are of no help to the appellants inasmuch as those orders turned on
the facts involved in the case and secondly, we find that in those cases,
parties did not even lead any evidence (see Para-3 of the order dated
27.01.2000 passed in SCA No. 393/2000 page 45 of Paper Book), and C
lastly, one case was based on clause 49 of 1956 settlement and clause
19 of 1985 settlement.
36. In substance, in our view, those orders did not directly deal
with the issues, which are the subject matter of these appeals and, even
if, they deal with the issue in question, as urged by the learned counsel, D
then also, in our view, those cases turned on their own facts.
37. In this view of the matter, those orders were rightly not relied
on by the High Court and we find no good ground to take different view
and accordingly reject this submission.
E
38. Mr. Colin Gondsalves, learned senior counsel for the appellants
then referred extensively to the evidence led by the parties to support
his submission.
39. We are afraid we cannot appreciate the evidence in the appeals
filed under Article 136 of the Constitution. It is more so when the Single F
Judge and Division Bench did not agree with the factual findings of the
Tribunal and rightly reversed those findings. It is binding on this Court.
40. In the light of the foregoing discussion, we find no merit in the
appeals which thus fail and are accordingly dismissed.
G
Divya Pandey Appeals dismissed.
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.