B. L. KASHYAP AND SONS LTDversusM/S JMS STEELS AND POWER CORPORATION & ANR.
- Citation
- 2022 INSC 60
- Decided
- 18 January 2022
- Disposal
- Appeal(s) allowed
- Bench
- VINEET SARAN
Holding
The summary suit is maintainable and the appellant‑defendant No.2 is entitled to leave to defend as it has raised genuine triable issues.
Summary
B.L. Kashyap & Sons Ltd., a steel supplier, filed a summary suit under Order XXXVII of the CPC against a real‑estate firm (defendant No.1) and its contractor JMS Steels & Power Corp. (defendant No.2) for non‑payment of Rs 89,50,244. The trial court denied both defendants leave to defend, holding that no triable issues were raised; the High Court affirmed the denial for defendant No.2, calling its defence frivolous and vexatious. On appeal, the Supreme Court examined whether the suit was maintainable and whether the contractor’s defence raised genuine triable issues. It held that the suit was maintainable because the claim was based on written purchase orders and invoices, which constitute a contract under Order XXXVII, and that the contractor had raised substantial and fair issues concerning its liability. Consequently, the Court set aside the lower courts' orders, granted the contractor unconditional leave to defend, and directed the trial court to proceed with the suit only against defendant No.2, treating the Rs 40,00,000 deposit as security for the leave.
Issues considered
- Whether a summary suit under Order XXXVII CPC is maintainable where the claim is based on written purchase orders and invoices.
- Whether the appellant‑defendant No.2 is entitled to leave to defend when it raises triable issues and its defence is not frivolous or vexatious.
Legislation cited
- Code of Civil Procedure, 1908s. Order XXXVII Rule 3
- Indian Contract Act, 1872s. Section 230, s. Section 2(d)
Subjects
Judgment
1024 SUPREME COURT
[2022]REPORTS
1 S.C.R. 1024 [2022] 1 S.C.R.
A B. L. KASHYAP AND SONS LTD.
v.
M/S JMS STEELS AND POWER CORPORATION & ANR.
(Civil Appeal No. 379 of 2022)
B JANUARY 18, 2022
[VINEET SARAN AND DINESH MAHESHWARI, JJ.]
Code of Civil Procedure, 1908 – Or. XXXVII – Summary Suits
– Leave to defend – Plaintiff-respondent no.1 is registered
partnership firm, manufacturer and supplier of iron and steel
C
products – It had supplied 200 tons of steel to defendant no.1
which was a real estate firm – Supply was made in terms of two
purchase orders as raised by appellant-defendant No.2, who was
contractor working with defendant no. 1 – On failure to make
requisite payment, plaintiff filed summary suit by making the
D defendants jointly and severally liable – Trial Court declined to
grant “leave to defend” to both the defendants – Appellant-
defendant no.2 challenged the judgment of trial court – High Court
observed that appellant- defendant no.2 was not entitled to “leave
to defend” because the defenses raised were frivolous and
vexatious and did not give rise to genuine triable issue – High
E
Court further observed that there was no such requirement that
the cheque ought to be dishonored for filing summary suit and
held the suit to be maintainable – On appeal, Held: As per the
plaint averment , the matter is based on written contract arising
out of written purchase orders issued by the appellant on the
F instruction and on behalf of defendant No. 1 – Contention against
maintainability of the summary suit in terms of Or. XXXVII cannot
be accepted – There is no reason to consider any interference in
the decision of the High Court – Grant of leave to defend (with or
without conditions) is the ordinary rule; and denial of leave to
defend is an exception – Even in the case of raising of triable
G
issues, with the defendant indicating his having a fair or
reasonable defence, he is ordinarily entitled to unconditional leave
to defend unless there be any strong reason to deny the leave –
On facts, no reason as to why and how the defence of the appellant
(defendant No. 2) was treated as frivolous or vexatious – Appellant
H had indeed raised triable issues, particularly concerning its
1024
B. L. KASHYAP AND SONS LTD. v. M/S JMS STEELS AND POWER 1025
CORPORATION & ANR. [DINESH MAHESHWARI, J.]
liability and the defence of the appellant cannot be said to be A
frivolous or vexatious altogether – Appellant-defendant No. 2
ought to have been granted the leave to defend the claim made in
the suit concerning its liability.
Allowing the appeal, the Court
B
HELD: 1. Two principal points call for determination in this
appeal: one, as to whether the plaintiff was entitled to maintain a
summary suit under Order XXXVII CPC for the claim in question;
and second, as to whether the appellant-defendant No. 2 has
rightly been declined the leave to defend? [Para 13][1036-C-D]
C
2. As per the plaint averment, the matter is based on written
contract arising out of written purchase orders issued by the
appellant on the instructions and on behalf of defendant No. 1;
and the plaintiff had raised the invoices against such supplies
under the purchase orders. In the overall facts and circumstances
of the case, the contention against maintainability of the summary D
suit in terms of Order XXXVII CPC cannot be accepted and to
that extent, there is no reason to consider any interference in
the decision of the High Court. [Paras 14 and 14.2][1036-E;
1037-B]
3. Grant of leave to defend (with or without conditions) is E
the ordinary rule; and denial of leave to defend is an exception.
The prayer for leave to defend is to be denied in such cases where
the defendant has practically no defence and is unable to give out
even a semblance of triable issues before the Court. In the case
of substantial defence, the defendant is entitled to unconditional F
leave; and even in the case of a triable issue on a fair and
reasonable defence, the defendant is ordinarily entitled to
unconditional leave to defend. In case of doubts about the intent
of the defendant or genuineness of the triable issues as also the
probability of defence, the leave could yet be granted but while
imposing conditions as to the time or mode of trial or payment or G
furnishing security. Thus, even in such cases of doubts or
reservations, denial of leave to defend is not the rule; but
appropriate conditions may be imposed while granting the leave.
It is only in the case where the defendant is found to be having
H
1026 SUPREME COURT REPORTS [2022] 1 S.C.R.
A no substantial defence and/or raising no genuine triable issues
coupled with the Court’s view that the defence is frivolous or
vexatious that the leave to defend is to be refused and the
plaintiff is entitled to judgment forthwith. While dealing with an
application seeking leave to defend, it would not be a correct
approach to proceed as if denying the leave is the rule or that
B
the leave to defend is to be granted only in exceptional cases or
only in cases where the defence would appear to be a meritorious
one. Even in the case of raising of triable issues, with the
defendant indicating his having a fair or reasonable defence, he
is ordinarily entitled to unconditional leave to defend unless
C there be any strong reason to deny the leave. [Paras 17, 17.2
and 17.3][1039-H; 1040-A-B, E-G; 1041-A-B]
4. The Trial Court had observed that the defendants failed
to raise any triable issues. It appears that while recording such
conclusions, the Trial Court as also the High Court totally omitted
D to consider that the appellant-defendant No. 2 has been contesting
its liability with the assertion that it had only been the contractor
executing the work of defendant No. 1. Even as per the plaint
averments and plaintiff’s assertions, the defendant No. 1 had made
various payments from time to time against the supplies of the
building material. The cheques, allegedly towards part payment
E
against the supplies made by the plaintiff, had been issued by the
defendant No. 1. In the given set of circumstances, the conclusion
of the High Court that the defence raised by the appellant was
frivolous or vexatious could only be treated as an assumptive
one and lacking in requisite foundation. No reason has been
F assigned as to why and how the defence of the present appellant
was treated as frivolous or vexatious. The effect and impact of an
admitted position of the plaintiff, that payments were indeed made
from time to time by the defendant No. 1, seems not to have
gone into consideration of the Trial Court and the High Court
while denying leave to the appellant. The appellant has indeed
G
raised triable issues, particularly concerning its liability and the
defence of the appellant cannot be said to be frivolous or vexatious
altogether. [Paras 18,19.1 and 20][1041-D-F; 1042-C-D, E]
H
B. L. KASHYAP AND SONS LTD. v. M/S JMS STEELS AND POWER 1027
CORPORATION & ANR. [DINESH MAHESHWARI, J.]
Mechelec Engineers and Manufacturers v. Basic A
Equipment Corporation AIR 1977 SC 577:[1977] 1
SCR 1060; IDBI Trusteeship 9 Services Ltd. v. Hubtown
Ltd.(2017) 1 SCC 568:[2016] 11 SCR 660 ; Prem Nath
Motors Limited v. Anurag Mittal (2009) 16 SCC
274:[2008] 16 SCR 45 ; V.K. Enterprises v. Shiva Steels
B
(2010) 9 SCC 256: [2010] 9 SCR 647- referred to.
Case Law Reference
[1977] 1 SCR 1060 referred to Para 6.3
[2016] 11 SCR 660 referred to Para 6.3
C
[2008] 16 SCR 45 referred to Para 9.1
[2010] 9 SCR 647 referred to Para 9.2
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 379 of
2022.
D
From the Judgment and Order dated 11.05.2018 of the High Court
of Delhi at New Delhi in RFA No.402 of 2018.
Jayant K. Mehta, Sr. Adv., Abhimanyu Mahajan, Apoorva
Bhumesh, Ms. Madhavi Khare, Ms. Anubha Goel, Advs. for the
Appellant.
E
Sachin Dutta, Sr. Adv., Dr. Farrukh Khan, Ms. Ridhima Goyal,
Abdul Aziz Chaus, Rameshwar Prasad Goyal, Lokesh Bhola, Manish
Kumar Gupta, Karan Grover, Deepak Kumar Singh, A. Ushi Reddy,
Pawan Kumar, Sudhir Kumar Ojha, Debopriyo Pal, Amit Kumar Bhati,
Sriram P., Advs. for the Respondents
F
The Judgment of the Court was delivered by
DINESH MAHESHWARI, J.
Preliminary
1. Leave granted.
G
2. This appeal is directed against the judgment and order dated
11.05.2018 in Regular First Appeal No. 402 of 2018, whereby the High
Court of Delhi at New Delhi has dismissed the appeal filed by the present
appellant and has affirmed the judgment and decree dated 18.09.2017
passed by the Additional District Judge-05: West, Tis Hazari Court, New
H
1028 SUPREME COURT REPORTS [2022] 1 S.C.R.
A Delhi, in the money recovery summary suit, being CivDj/611333/2016,
filed by the plaintiff-respondent No. 1, wherein the present appellant
was arrayed as defendant No. 2 and the present respondent No. 2 was
arrayed as defendant No. 1.
2.1. It may be noticed at the outset that the Trial Court had passed
B the judgment and decree dated 18.09.2017 with its finding that no triable
issues had been raised by the defendants and hence, they were not
entitled to the leave to defend. In the impugned judgment and order
dated 11.05.2018, the High Court has affirmed the decree in relation to
the appellant-defendant No. 2. Hence, the questions involved in the
present appeal are confined to the prayer for leave to defend sought for
C by the appellant. However, it is also relevant to notice that the other
defendant (who is respondent No. 2 herein) had also filed an appeal
against the said judgment and decree dated 18.09.2017 (being RFA No.
743 of 2018), which was dismissed by the High Court by its separate
judgment and order dated 05.09.2018. The said judgment and order dated
D 05.09.2018 is not under challenge before us but, we shall refer to the
same at the relevant juncture and in relation to the implications of the
findings therein.
2.2. For the purpose of continuity of narration and discussion, the
parties shall also be referred herein with reference to their status in the
E suit.
Relevant factual and background aspects
3. The relevant factual and background aspects of the matter are
as follows:
F 3.1. The plaintiff-respondent No. 1 filed the subject suit in terms
of Order XXXVII of the Code of Civil Procedure, 1908 (‘CPC’) while
stating itself to be a registered partnership firm manufacturing and
supplying a wide variety of iron and steel products. According to the
plaintiff, the defendant No. 1 represented itself as a real estate and
infrastructure development firm while the defendant No. 2 (appellant
G herein) represented itself as a contractor working with the defendant
No. 1 for the construction work of its project namely ‘MIST’, being
developed at Plot No.1, Sector 143-B, Noida.
3.2. The plaintiff asserted that in relation to the said construction
work, it had supplied 200 tons of steel at the site address of the defendant
H No. 1; and this supply was made in terms of two purchase orders dated
B. L. KASHYAP AND SONS LTD. v. M/S JMS STEELS AND POWER 1029
CORPORATION & ANR. [DINESH MAHESHWARI, J.]
06.02.2015 and 20.03.2015, as raised by the appellant-defendant No. 2. A
The plaintiff further asserted that payment for the goods so supplied
was to be made by the defendant No. 1 and in that regard, various
invoices were raised, as detailed in paragraph 7 of the plaint. It was also
submitted that an amount of Rs. 89,50,244/- remained due against the
supplies so made and invoices so raised.
B
3.3. The plaintiff further averred that for payment against the
said invoices, the defendant No. 1 issued two cheques drawn on Axis
Bank, Sector-44 Noida Branch, being cheque No. 037274 dated
04.05.2015 for a sum of Rs.14,72,269/- and cheque No. 037272 dated
09.05.2015 for a sum of Rs. 13,34,319/- while asking the plaintiff to
present the cheques only after receiving intimation but no such intimation C
was received. Later on, the plaintiff issued a legal notice dated 28.01.2016
to the defendants demanding the dues and, upon their failure to make
the requisite payment, filed the subject suit under Order XXXVII CPC,
while asserting joint and several liability of the defendants. The plaintiff,
inter alia, averred that the suit was based on written contract inasmuch D
as written purchase orders were issued by the appellant-defendant No.
2 on the instructions, and on behalf of, defendant No. 1.
3.4. In the summary suit so filed, the defendant No. 1 sought
leave to defend with the contentions, inter alia, that it had no privity of
contract with the plaintiff because the purchase orders were issued only E
by the defendant No. 2; that the invoices in question were raised by the
plaintiff in the name of the defendant No. 2; that neither the purchase
orders nor the invoices were bearing the signatures of the defendant
No. 1; and that all the dealings were between plaintiff and defendant
No. 2, where no legal liability was to be discharged by defendant No. 1.
It was contended that the defendant No. 1 was rather a stranger to the F
contract in question.
3.5. In opposition to the contentions sought to be urged by the
defendant No. 1, the plaintiff contended, inter alia, that the application
filed by defendant No. 1 was an attempt to shy away from its responsibility
by shifting the same on the defendant No. 2. In support of this contention, G
the plaintiff placed its ledger account as also the statement of account of
defendant No. 1 which, according to the plaintiff, demonstrated that the
payment of goods delivered to the defendant No. 2 had been made by
the defendant No. 1. It was contended by the plaintiff that if there was
no agreement between the plaintiff and the defendant No. 1, there was H
1030 SUPREME COURT REPORTS [2022] 1 S.C.R.
A no reason for the defendant No. 1 to issue the cheques in the name of
plaintiff. It was also submitted that though the invoices were addressed
to the defendant No. 2 but, they also mentioned “C/o Mist”, which
substantiated the stand of the plaintiff.
3.6. The appellant-defendant No. 2 moved a separate application
B seeking leave to defend. It was contended in this application that the
appellant had been working as civil contractor under the defendant No.
1; that the purchase orders were issued only on behalf of the defendant
No. 1; and that the material supplied by the plaintiff was for the
construction of project undertaken by defendant No. 1, who was the
beneficiary of the said project. The appellant submitted that under the
C contract, it was the duty of owner, i.e., defendant No. 1, to supply the
material for construction and defendant No. 2 was to be paid for the
quantities supplied by it. Further, the copies of statements of accounts
showing the purchase orders placed by defendant No. 2 at the instance
of defendant No. 1 were placed on record; and it was submitted that the
D bills for such supplies were liquidated in due course. In substance, case
of the appellant had been that it had no liability towards the plaintiff.
3.7. The plaintiff also opposed the prayer of the appellant for
leave to defend with the submissions that the appellant-defendant No. 2
had failed to raise any substantial defence and he was rather trying to
E confuse the issue. It was asserted that the goods were supplied on the
purchase orders raised by the defendant No. 2 while acting as an agent
for the defendant No. 1; and it was agreed between the parties that the
defendant No. 1 would make payment for the goods supplied to the
defendant No. 2. It was also submitted that the role of the appellant-
defendant No. 2 was “important” in the present suit as the transaction
F of goods indeed involved this defendant.
Trial Court declined leave to defend to both the defendants
4. In its impugned judgement dated 18.09.2017, the Trial Court
considered both the applications moved by the respective defendants
G seeking leave to defend together; and rejected the same while observing
that the defendants were merely attempting to shift the burden upon
each other.
4.1. The Trial Court observed that the defendant No. 2 was a
contractor working under defendant No. 1 by virtue of the construction
agreement; and as per Clause 10 of this agreement, defendant No. 1
H
B. L. KASHYAP AND SONS LTD. v. M/S JMS STEELS AND POWER 1031
CORPORATION & ANR. [DINESH MAHESHWARI, J.]
was liable to pay the costs of goods, material or articles procured and A
arranged for by the contractor. The Trial Court further observed that the
purchase orders had been placed by defendant No. 2 on plaintiff at the
instance of defendant No. 1 and the goods were indisputably supplied at
the site address of defendant No. 1, who was the ultimate beneficiary of
the transaction. It was also noted that the bills raised for such supplies
B
had been liquidated by the defendant No. 1. The contention urged on
behalf of the defendant No. 1 that there was no privity of contract was
rejected with reference to the facts that the defendant No. 1 had been
making payments to the plaintiff; and reference was made to various
payments made through cheques and demand drafts from time to time.
The Trial Court observed that the transactions clearly indicated that the C
materials were being supplied by the plaintiff to the site address of
defendant No.1 and the defendant No. 1 had been making payments
directly to the plaintiff. Hence, the Trial Court held that the defence
sought to be raised by the defendant No. 1, of want of privity of contract,
was without any substance and was not giving rise to any triable issue.
D
The Trial Court also rejected the contention that the summary suit under
Order XXXVII CPC was not maintainable as the plaintiff did not present
the aforementioned cheques for encashment while observing that the
suit was not merely based on the two cheques issued by the defendant
No. 1, but was also based on the purchase orders and invoices raised for
supply of materials; and the invoices were a complete contract, as E
contemplated by Order XXXVII CPC.
4.2. Having rejected the case of the defendant No. 1, the Trial
Court also proceeded to deny the prayer of the appellant-defendant No.
2 for leave to defend while observing that the goods were received by
the defendant No. 2 as an agent of the defendant No. 1 and, therefore, F
both the defendants were under obligation to make payment. The Trial
Court said,-
“15. The invoices issued by the plaintiff have been addressed to
the site address of defendant no.- 1 and the goods have been
received by defendant no.- 2 acting as an agent of defendant no.- G
1. Therefore, both the defendants are under an obligation to make
payments of the goods supplied by the plaintiff.”
5. Thus, the Trial Court concluded that no triable issues were
raised by the defendants and declined their applications seeking leave to
defend. Consequently, the suit was decreed in favour of the plaintiff for H
1032 SUPREME COURT REPORTS [2022] 1 S.C.R.
A a sum of Rs. 89,50,244/- together with interest at the rate of 10% per
annum with joint and several liability of the defendants to pay the decreetal
amount.
High Court dismissed the appeal filed by appellant
6. The appellant-defendant No. 2 challenged the judgement and
B decree so passed by the Trial Court by way of regular first appeal, being
RFA No. 402 of 2018. The High Court, however, rejected the contentions
urged on behalf of the appellant and dismissed the appeal.
6.1. The High Court, inter alia, observed that merely for the
delivery address of the goods in question having been that of the site of
C defendant No. 1, it would not mean that the purchase orders were those
of the defendant No. 1, when it was ex facie evident that the purchase
orders had been issued only by defendant No. 2; the invoices were raised
by the plaintiff upon defendant No. 2 and not upon defendant No. 1; and
the defendant No. 2 was specifically mentioned as the buyer in those
D invoices.
6.2. The High Court further observed that the appellant-defendant
No. 2 was liable and the suit was maintainable under Order XXXVII
CPC because the invoices for their total value were written contracts,
containing specified amount of liability of the appellant-defendant No. 2
E for payment to the plaintiff-respondent No. 1. As regards the cheques in
question, the High Court observed that though the cheques were issued
by the defendant No. 1, yet a suit under Order XXXVII of CPC would
lie against the defendant No. 2 because there was no such requirement
in Order XXXVII CPC that the cheques which are issued for payments
ought to be of the person against whom the liability is claimed. The High
F Court further observed that as per Section 2 (d) of Indian Contract Act,
1872 consideration under a contract need not flow/pass only between
the parties to a contract. The High Court also observed that even if the
cheques were not presented, the suit would be maintainable under Order
XXXVII CPC because there was no such requirement that the cheque
G ought to be dishonored for filing a summary suit. The High Court further
observed on the maintainability of the summary suit even when there was
a joint and several liability of the defendants in the following words: -
“9. The fact that there is a joint and several liability of the appellant/
defendant no.2 with the respondent no.2/defendant no.1 will not
mean that to enforce this joint and several liability, the subject suit
H
B. L. KASHYAP AND SONS LTD. v. M/S JMS STEELS AND POWER 1033
CORPORATION & ANR. [DINESH MAHESHWARI, J.]
could not have been filed both against the appellant/defendant A
no.2 and the respondent no.2 herein. Once liability is joint and
several of the appellant/defendant no.2 with the respondent no.2/
defendant no.1, and as stated above Section 2(d) of the Indian
Contract Act permits passing/payment of consideration by a person
who is not a party to the contract, therefore merely because
B
respondent no.2/defendant no.1 had agreed to be liable to make
the payment of the goods purchased by the appellant/defendant
no.2, this would not mean that the appellant/defendant no.2 would
no longer be liable and liability will only be of the respondent no.2/
defendant no.1.”
6.3. The High Court further observed that the principles governing C
the issue were not those of the decision of this Court in the case of
Mechelec Engineers and Manufacturers v. Basic Equipment
Corporation: AIR 1977 SC 577,as referred to by the Trial Court; but
the applicable principles were contained in the later decision of this Court
in IDBI Trusteeship Services Ltd. v. Hubtown Ltd.: (2017) 1 SCC D
568. While reproducing the principles so laid down by this Court, the
High Court held that the appellant-defendant No. 2 was not entitled to
leave to defend because the defences raised by it do not give rise to
genuine triable issues; and the defences were frivolous and vexatious,
raised only in order to deny the just dues of the seller of goods, being the
plaintiff. E
High Court also dismissed the appeal filed by defendant No. 1
7. Before proceeding further, we may take note of the fact that
the defendant No. 1 had also filed an appeal, being RFA No. 743 of
2018, in challenge to the judgment and decree of the Trial Court dated F
18.09.2017. The appeal so filed by the defendant No. 1 (respondent No.
2 herein) was considered and decided by the High Court by its separate
(and later) judgment and order dated 05.09.2018 with the finding that
the defence sought to be raised by the defendant No.1 was frivolous or
vexatious and, in support of this finding, the High Court specifically gave
the reason in following words: - G
“The defence of the appellant/defendant no. 1 was clearly frivolous
or vexatious, and it did not raise a genuine triable issue, because if
there was no liability of the appellant/defendant no. 1 then, where
was the question of making payments regularly by the appellant/
defendant no.1 to the respondent no.1/plaintiff.” H
1034 SUPREME COURT REPORTS [2022] 1 S.C.R.
A Rival Contentions
8. Reverting to the case at hand, which pertains to the appellant-
defendant No. 2, we may briefly take note of the rival submissions in
this appeal.
B 9. Learned senior counsel for the appellant-defendant No. 2 has
contended that liability for payment against the material supplied by the
plaintiff was not that of the appellant-defendant No. 2 but had been of
the defendant No. 1, which was evident from the fact that the plaintiff
itself had pleaded that the liability to pay for the supplies made by it was
that of the defendant No. 1. Thus, according to the learned counsel, the
C impugned decree proceeds rather contrary to the plaintiff’s own case
and cannot be sustained.
9.1. Learned counsel for the appellant has further submitted that
the appellant was only acting as an agent of the defendant No. 1, as the
agreement for supply of steel was between plaintiff and defendant No.
D 1; and the appellant, having issued the purchase orders only on behalf of
the defendant No. 1, cannot be held liable for payment to the plaintiff, in
terms of Section 230 of the Indian Contract Act, 1872 which provides
that an agent cannot be held liable for the contract executed on behalf of
the principal. The learned counsel has referred to the decision of this
E Court in the case of Prem Nath Motors Limited v. Anurag Mittal:
(2009) 16 SCC 274. The learned counsel has yet further submitted
that the defendant No. 1 had issued two cheques bearing Nos. 037274
and 037272 towards part payment to the plaintiff against the supplies
made; and when the High Court has observed that a cheque is a written
agreement containing a liquidated amount as per Order XXXVII Rule
F 1(2) of the CPC, the said cheques would only constitute a liability of the
defendant No. 1 and not that of the appellant-defendant No. 2.
9.2. Learned counsel would further submit that the plaintiff’s
summary suit was not maintainable against the appellant under Order
XXXVII CPC in the absence of a legally enforceable debt and, in support
G of this contention, would rely on the decision of this Court in case of V.K.
Enterprises v. Shiva Steels: (2010) 9 SCC 256.
10. Per contra, learned counsel for the plaintiff-respondent No.1
would submit that the present appeal, being only an attempt to avoid the
legal liability, deserves to be dismissed.
H
B. L. KASHYAP AND SONS LTD. v. M/S JMS STEELS AND POWER 1035
CORPORATION & ANR. [DINESH MAHESHWARI, J.]
10.1. The learned counsel has contended that both the appellant- A
defendant No. 2 and the defendant No. 1 are merely trying to evade the
liability, by shifting the burden upon each other. As regards the liability of
the appellant-defendant No. 2, learned counsel would submit that the
appellant had raised purchase orders; that on the basis of the said
purchase orders, goods were supplied and the invoices were raised in
B
the name of the appellant; and that the goods were received by the
appellant. In this fact situation, according to the learned counsel, merely
because delivery address of the goods was that of the site owned by the
defendant No. 1, the appellant cannot avoid its liability and, in fact, the
defendants had been standing in joint and several liability to liquidate the
amount due against the said invoices. C
10.2. The learned counsel would argue that the invoices for their
total value constituted written contracts and hence, the suit has rightly
been filed in terms of Order XXXVII CPC where the defendants cannot
get away by shifting the liability upon each other.
D
11. In different dimensions to the above, the learned counsel
appearing for the defendant No. 1 (respondent No. 2 herein) has
contended that under the construction agreement executed between the
defendant No. 2 and defendant No. 1, the payments toward supply of
material by the plaintiff were to be made by the defendant No. 2. The
learned counsel would submit that the appellant-defendant No. 2 had E
placed purchase orders with the plaintiff and invoices were raised by
the plaintiff in the name of defendant No. 2 and hence, there was no
privity of contract between the plaintiff and defendant No. 1. The mere
fact that the defendant No. 2 was carrying out the work of the defendant
No. 1 and the invoices mentioned the name of the project where the F
goods were to be delivered would not make the defendant No. 1 liable to
make payment to the plaintiff. It has also been submitted that there was
no role of the defendant No. 1 because neither its consent was taken at
the time of execution of agreement for the supply of goods nor the rates
of steel were discussed; and the purchase orders and invoices also do
not bear the name of the defendant No.1 or any signatures on its behalf. G
As regards the payments earlier made by the defendant No. 1, the
submission has been that such payments were made on the request of
the defendant No. 2 when it had shown deficiency in cash flow and
requested to make payment to the vendors including the plaintiff.
H
1036 SUPREME COURT REPORTS [2022] 1 S.C.R.
A 11.1. On behalf of the defendant No. 1, reference has also been
made to the judgment dated 05.09.2018 passed by the High Court in its
appeal (RFA No. 743 of 2018) while contending that the said appeal
came to be dismissed without adverting to the relevant facts. It has also
been pointed out that there were other disputes between the appellant
and the defendant No. 1 for which, other litigation is pending in Delhi
B
High Court.
12. We have given thoughtful consideration to the rival submissions
and have examined the record of the case with reference to the law
applicable.
C Analysis
13. For what has been noticed hereinbefore, two principal points
call for determination in this appeal: one, as to whether the plaintiff was
entitled to maintain a summary suit under Order XXXVII CPC for the
claim in question; and second, as to whether the appellant-defendant
D No. 2 has rightly been declined the leave to defend?
14. The question concerning maintainability of the suit filed by the
plaintiff as a summary suit under Order XXXVII CPC need not detain
us much longer. This is for the simple reason that as per the plaint
averment, the matter is based on written contract arising out of written
E purchase orders issued by the appellant on the instructions and on behalf
of defendant No. 1; and the plaintiff had raised the invoices against such
supplies under the purchase orders. The plaintiff has further pointed out
that two cheques were issued by the defendant No. 1 towards part
payment against the invoices, being cheque No. 037274 dated 04.05.2015
in the sum of Rs. 14,72,269/- and No. 037272 dated 09.05.2015 in the
F sum of Rs. 13,34,319/-.
14.1. The assertion of plaintiff had been of joint and several
liability of the defendants. The question as to whether the appellant
was acting only as an agent of defendant No. 1 in relation to the supplies
in question and had no monetary liability, as sought to be raised by the
G appellant, could be a matter of his defence. This aspect, relating to the
nature of defence shall be examined in the next question but, such a
proposition of defence by the appellant cannot take away the entitlement
of the plaintiff-respondent No. 1 to maintain the summary suit in terms
of Order XXXVII CPC. This is apart from the fact that while asserting
joint and several liability of the defendants, the plaintiff has also relied
H
B. L. KASHYAP AND SONS LTD. v. M/S JMS STEELS AND POWER 1037
CORPORATION & ANR. [DINESH MAHESHWARI, J.]
upon the cheques said to have been issued by defendant No. 1, which A
were allegedly not presented as per the request of the said defendant
No. 1.
14.2. In the overall facts and circumstances of the case, the
contention against maintainability of the summary suit in terms of Order
XXXVII CPC cannot be accepted and to that extent, we find no reason B
to consider any interference in the decision of the High Court. However,
the question still remains as to whether the appellant is not entitled to
leave to defend?
15. In regard to the question of leave to defend, as noticed, the
High Court has observed that the appellant would not be entitled to such C
leave because no triable issues were arising out of the defence sought to
be taken by the appellant. The High Court has also observed that the
defences were frivolous and vexatious; and were raised only in order to
deny the just dues of seller of the goods, i.e., the plaintiff. According to
the High Court, while applying the principles for grant of leave to defend,
D
as delineated in the case of IDBI Trusteeship (supra), the appellant
was not entitled to the leave to defend.
16. The High Court took note of the fact that the Trial Court
relied upon the decision in Mechelec Engineers (supra) and observed
that the applicable principles were those contained in the later decision
E
of this Court in IDBI Trusteeship (supra). Having regard to the question
at hand, it shall be worthwhile to read together the principles stated in
the said two decisions of this Court.
16.1. In the case of Mechelec Engineers(supra),the principles
for consideration of a prayer for leave to defend in a summary suit were F
laid down by this Court in the following terms: -
“8. In Kiranmoyee Dassi Smt v. Dr J. Chatterjee [AIR 1949 Cal
479 :49 CWN 246, 253 : ILR (1945) 2 Cal 145.] Das, J., after a
comprehensive review of authorities on the subject, stated the
principles applicable to cases covered by Order 17 CPC in the G
form of the following propositions (at p. 253):
“(a) If the defendant satisfies the court that he has a good defence
to the claim on its merits the plaintiff is not entitled to leave to sign
judgment and the defendant is entitled to unconditional leave to
defend. H
1038 SUPREME COURT REPORTS [2022] 1 S.C.R.
A (b) If the defendant raises a triable issue indicating that he has a
fair or bona fide or reasonable defence although not a positively
good defence the plaintiff is not entitled to sign judgment and the
defendant is entitled to unconditional leave to defend.
(c) If the defendant discloses such facts as may be deemed
B sufficient to entitle him to defend, that is to say, although the
affidavit does not positively and immediately make it clear that he
has a defence, yet, shews such a state of facts as leads to the
inference that at the trial of the action be may be able to establish
a defence to the plaintiff’s claim the plaintiff is not entitled to
judgment and the defendant is entitled to leave to defend but in
C
such a case the court may in its discretion impose conditions as to
the time or mode of trial but not as to payment into court or
furnishing security.
(d) If the defendant has no defence or the defence set-up is illusory
or sham or practically moonshine then ordinarily the plaintiff is
D
entitled to leave to sign judgment and the defendant is not entitled
to leave to defend.
(e) If the defendant has no defence or the defence is illusory or
sham or practically moonshine then although ordinarily the plaintiff
is entitled to leave to sign judgment, the court may protect the
E
plaintiff by only allowing the defence to proceed if the amount
claimed is paid into court or otherwise secured and give leave to
the defendant on such condition, and thereby show mercy to the
defendant by enabling him to try to prove a defence.”
F 16.2. In the case of IDBI Trusteeship(supra), this Court
modulated the aforementioned principles and laid down as follows: -
“17. Accordingly, the principles stated in para 8 of Mechelec
case [Mechelec Engineers & Manufacturers v. Basic
Equipment Corpn., (1976) 4 SCC 687] will now stand superseded,
G given the amendment of Order 37 Rule 3 and the binding decision
of four Judges in Milkhiram case [Milkhiram (India) (P)
Ltd. v. Chamanlal Bros., AIR 1965 SC 1698 : (1966) 68 Bom
LR 36] , as follows:
17.1. If the defendant satisfies the court that he has a substantial
H defence, that is, a defence that is likely to succeed, the plaintiff is
B. L. KASHYAP AND SONS LTD. v. M/S JMS STEELS AND POWER 1039
CORPORATION & ANR. [DINESH MAHESHWARI, J.]
not entitled to leave to sign judgment, and the defendant is entitled A
to unconditional leave to defend the suit.
17.2. If the defendant raises triable issues indicating that he has
a fair or reasonable defence, although not a positively good defence,
the plaintiff is not entitled to sign judgment, and the defendant
is ordinarily entitled to unconditional leave to defend. B
17.3. Even if the defendant raises triable issues, if a doubt is left
with the trial Judge about the defendant’s good faith, or the
genuineness of the triable issues, the trial Judge may impose
conditions both as to time or mode of trial, as well as payment into
court or furnishing security. Care must be taken to see that the C
object of the provisions to assist expeditious disposal of commercial
causes is not defeated. Care must also be taken to see that such
triable issues are not shut out by unduly severe orders as to deposit
or security.
17.4. If the defendant raises a defence which is plausible but D
improbable, the trial Judge may impose conditions as to time or
mode of trial, as well as payment into court, or furnishing security.
As such a defence does not raise triable issues, conditions as to
deposit or security or both can extend to the entire principal sum
together with such interest as the court feels the justice of the
case requires. E
17.5. If the defendant has no substantial defence and/or raises
no genuine triable issues, and the court finds such defence to be
frivolous or vexatious, then leave to defend the suit shall be refused,
and the plaintiff is entitled to judgment forthwith.
F
17.6. If any part of the amount claimed by the plaintiff is admitted
by the defendant to be due from him, leave to defend the suit,
(even if triable issues or a substantial defence is raised), shall not
be granted unless the amount so admitted to be due is deposited
by the defendant in court.”
G
17. It is at once clear that even though in the case of IDBI
Trusteeship, this Court has observed that the principles stated in
paragraph 8 of Mechelec Engineers’ case shall stand superseded in
the wake of amendment of Rule 3 of Order XXXVII but, on the core
theme, the principles remain the same that grant of leave to defend
(with or without conditions) is the ordinary rule; and denial of leave to H
1040 SUPREME COURT REPORTS [2022] 1 S.C.R.
A defend is an exception. Putting it in other words, generally, the prayer
for leave to defend is to be denied in such cases where the defendant
has practically no defence and is unable to give out even a semblance of
triable issues before the Court.
17.1. As noticed, if the defendant satisfies the Court that he has
B substantial defence, i.e., a defence which is likely to succeed, he is entitled
to unconditional leave to defend. In the second eventuality, where the
defendant raises triable issues indicating a fair or bonafide or reasonable
defence, albeit not a positively good defence, he would be ordinarily
entitled to unconditional leave to defend. In the third eventuality, where
the defendant raises triable issues, but it remains doubtful if the defendant
C
is raising the same in good faith or about genuineness of the issues, the
Trial Court is expected to balance the requirements of expeditious disposal
of commercial causes on one hand and of not shutting out triable issues
by unduly severe orders on the other. Therefore, the Trial Court may
impose conditions both as to time or mode of trial as well as payment
D into the Court or furnishing security. In the fourth eventuality, where the
proposed defence appear to be plausible but improbable, heightened
conditions may be imposed as to the time or mode of trial as also of
payment into the Court or furnishing security or both, which may extend
to the entire principal sum together with just and requisite interest.
E 17.2. Thus, it could be seen that in the case of substantial defence,
the defendant is entitled to unconditional leave; and even in the case of
a triable issue on a fair and reasonable defence, the defendant is ordinarily
entitled to unconditional leave to defend. In case of doubts about the
intent of the defendant or genuineness of the triable issues as also the
probability of defence, the leave could yet be granted but while imposing
F
conditions as to the time or mode of trial or payment or furnishing security.
Thus, even in such cases of doubts or reservations, denial of leave to
defend is not the rule; but appropriate conditions may be imposed while
granting the leave. It is only in the case where the defendant is found to
be having no substantial defence and/or raising no genuine triable issues
G coupled with the Court’s view that the defence is frivolous or vexatious
that the leave to defend is to be refused and the plaintiff is entitled to
judgment forthwith. Of course, in the case where any part of the amount
claimed by the plaintiff is admitted by the defendant, leave to defend is
not to be granted unless the amount so admitted is deposited by the
defendant in the Court.
H
B. L. KASHYAP AND SONS LTD. v. M/S JMS STEELS AND POWER 1041
CORPORATION & ANR. [DINESH MAHESHWARI, J.]
17.3. Therefore, while dealing with an application seeking leave A
to defend, it would not be a correct approach to proceed as if denying
the leave is the rule or that the leave to defend is to be granted only in
exceptional cases or only in cases where the defence would appear to
be a meritorious one. Even in the case of raising of triable issues, with
the defendant indicating his having a fair or reasonable defence, he is
B
ordinarily entitled to unconditional leave to defend unless there be any
strong reason to deny the leave. It gets perforce reiterated that even if
there remains a reasonable doubt about the probability of defence, sterner
or higher conditions as stated above could be imposed while granting
leave but, denying the leave would be ordinarily countenanced only in
such cases where the defendant fails to show any genuine triable issue C
and the Court finds the defence to be frivolous or vexatious.
18. When we apply the principles aforesaid to the facts of the
present case and to the impugned orders, it is at once clear that after
finding the suit to be maintainable under Order XXXVII CPC because
of assertion of the plaintiff about joint and several liability of the D
defendants, the High Court concluded that the defences were frivolous
and vexatious. The Trial Court had observed that the defendants failed
to raise any triable issues. It appears that while recording such conclusions,
the Trial Court as also the High Court totally omitted to consider that the
appellant-defendant No. 2 has been contesting its liability with the assertion
E
that it had only been the contractor executing the work of defendant No.
1. Even as per the plaint averments and plaintiff’s assertions, the
defendant No. 1 had made various payments from time to time against
the supplies of the building material. The cheques, allegedly towards
part payment against the supplies made by the plaintiff, had been issued
by the defendant No. 1. In the given set of circumstances, the conclusion F
of the High Court that the defence raised by the appellant was frivolous
or vexatious could only be treated as an assumptive one and lacking in
requisite foundation.
19. At this juncture, we may also refer to a significant feature of
the case that the defendant No. 1 (respondent No. 2 herein) had questioned G
the same judgment and decree of the Trial Court dated 18.09.2017 by
way of a separate appeal, being RFA No. 743 of 2018, that was
considered and dismissed by the High Court by the judgment and order
dated 05.09.2018. Interestingly, the High Court dismissed the said appeal
with the finding that the defence raised by defendant No. 1 was frivolous
H
1042 SUPREME COURT REPORTS [2022] 1 S.C.R.
A or vexatious and, in support of this finding, the High Court specifically
gave the reason in the form of a query that if at all there was no liability
of the defendant No. 1, where was the question of making payments
regularly by the defendant No. 1 to the plaintiff?
19.1. It is at once noticeable that in contradistinction to the reasons
B stated qua the defendant No. 1 in the judgment and order dated
05.09.2018, the High Court has merely observed in the impugned
judgment and order dated 11.05.2018 concerning the present appellant,
i.e., defendant No. 2, that the defences were frivolous or vexatious and
were raised only to deny the just dues of the seller of goods. No reason
has been assigned as to why and how the defence of the present appellant
C
(defendant No. 2) was treated as frivolous or vexatious. The effect and
impact of an admitted position of the plaintiff, that payments were indeed
made from time to time by the defendant No. 1, seems not to have gone
into consideration of the Trial Court and the High Court while denying
leave to the appellant. The same considerations, which weighed with
D the Courts to deny the leave to defend to the defendant No. 1, could not
have been applied ipso facto to the case of the appellant; rather those
considerations, in our view, make out a case of triable issues qua the
appellant.
20. In the totality of the circumstances of this case, we are clearly
E of the view that the appellant has indeed raised triable issues, particularly
concerning its liability and the defence of the appellant cannot be said to
be frivolous or vexatious altogether.
20.1. In the aforesaid view of the matter, we are inclined to hold
that the appellant-defendant No. 2 ought to have been granted the leave
F to defend the claim made in the suit concerning its liability; and to this
extent, the impugned decree deserves to be set aside.
21. For what has been observed hereinabove, we would have
considered granting unconditional leave to defend to the appellant but
then, it is noticed that by the order dated 17.08.2018, this Court granted
G stay over execution of the decree on the condition of the appellant
depositing a sum of Rs. 40,00,000/- (Forty Lakhs). Thereafter, by the
order dated 24.09.2018, this Court noticed the fact of such deposit and
condoned the delay of four days in making the deposit. Taking these
factors into account and, looking to the nature of claim and the nature of
defence sought to be raised as also the fact that the appeal filed by the
H
B. L. KASHYAP AND SONS LTD. v. M/S JMS STEELS AND POWER 1043
CORPORATION & ANR. [DINESH MAHESHWARI, J.]
defendant No. 1 had been dismissed by the High Court, we find it just A
and proper to grant leave to defend to the appellant-defendant No. 2
while leaving it open for the Trial Court to pass appropriate orders
regarding treatment of the said amount of Rs. 40,00,000/- deposited by
the appellant in terms of the order passed by this Court.
21.1. As the appellant is being granted leave to defend, we are B
not dealing with other contentions urged on behalf of the appellant
concerning its liability; and all the relevant aspects are left open for
consideration of the Trial Court.
22. Accordingly, this appeal succeeds and is allowed in the manner
that impugned judgment and order dated 11.05.2018 as passed by the C
High Court and the impugned judgment and decree dated 18.09.2017 as
passed by the Trial Court, insofar relating to the present appellant
(defendant No. 2), are set aside; the appellant is granted leave to defend;
and the amount of Rs. 40,00,000/- deposited by the appellant shall be
treated to be a deposit towards the condition for leave to defend. The
Trial Court shall pass appropriate orders for treatment of the said amount D
of Rs. 40,00,000/- and then shall proceed with trial of the suit only qua
the appellant-defendant No. 2 in accordance with law.
22.1. No order as to costs of the present appeal.
E
Bibhuti Bhushan Bose Appeal allowed.
(Assisted by : Shubhanshu Das, LCRA)
F
G
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.