VIDEOCON INDUSTRIES LTD.versusUNION OF INDIA AND ANR.
- Citation
- 2011 INSC 383
- Decided
- 11 May 2011
- Disposal
- Appeal(s) allowed
- Bench
- R V RAVEENDRAN
Holding
The seat of arbitration remained Kuala Lumpur and the Delhi High Court lacked jurisdiction to entertain the Section 9 petition because the parties had excluded the provisions of Part I of the Arbitration and Conciliation Act, 1996 by agreeing that the arbitration agreement would be governed by English law.
Summary
The dispute arose under a Production Sharing Contract (PSC) between the Government of India and a consortium that included Videocon Industries Ltd. The PSC stipulated Kuala Lumpur as the seat of arbitration, but due to the SARS epidemic the arbitral tribunal held hearings in Amsterdam and London, recording a consent to shift the seat to London without a written amendment. A partial award was challenged in the High Court of Malaysia, and the respondents later filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 in the Delhi High Court seeking a stay of the proceedings. The Delhi High Court held it had jurisdiction, but the Supreme Court reversed this, holding that the seat remained Kuala Lumpur because the parties had not validly amended the seat, and that the parties had excluded Part I of the Act by agreeing that the arbitration agreement would be governed by English law. Consequently, the Delhi High Court lacked jurisdiction to entertain the Section 9 petition. The appeal was allowed and the petition dismissed.
Issues considered
- The contractual (juridical) seat of arbitration under the PSC and whether it was validly shifted from Kuala Lumpur to London.
- Whether the Delhi High Court could entertain a petition under Section 9 of the Arbitration and Conciliation Act, 1996 in respect of an international commercial arbitration whose seat was Kuala Lumpur.
- Whether Part I of the Arbitration and Conciliation Act, 1996 applies to the arbitration despite the parties’ agreement that the arbitration agreement is governed by English law.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 2(1)(f), s. 2(2), s. 2(4), s. 2(5), s. 2(7), s. 3, s. 34, s. 36, s. 49, s. 5, s. 53, s. 58, s. 9
- Code of Civil Procedure, 1908s. Order VII Rule 11
- English Arbitration Act, 1996s. 3, s. 53
Subjects
Judgment
• (2011] 8 S.C.R. 569
VIDEOCON INDUSTRIES LTD. A
v.
UNION OF INDIA AND ANR.
(Civil Appeal No. 4269 of 2011)
MAY 11, 2011
B
[R.V. RAVEENDRAN AND G.S. SINGHVI, JJ.]
Arbitration and Conciliation Act, 1996 - s. 9 -
Jurisdiction for entertaining petition uls. 9 - Seat of
arbitration - Production Sharing Contract (PSC) - Dispute C
between the parties - Matter referred to arbitral tribunal
under clause 34.3 of PSC - In terms of clause 34.12 of
the PSC, the seat of arbitration was Kuala Lumpur,
Malaysia - However, due to outbreak of epidemic SARS,
the arbitral tribunal decided to hold its sittings first at D
Amsterdam and then at London and the parties did not
object to this - Partial award passed - Respondent No. 1
challenged the partial award by filing a petition in the High
Court of Malaysia at Kuala Lumpur - Thereafter, the
respondents made request to the tribunal to conduct the . E
remaining arbitral proceedings at Kuala Lumpur, but the
request was rejected and it was declared that the remaining
arbitral proceedings will be held in London - At that stage,
the respondents filed application uls.9 of the Act in Delhi
High Court for stay of the arbitral proceedings - Appellant F
objected to the maintainability of the application and
pleaded that the Courts in India did not have the
jurisdiction to entertain challenge to the arbitra/ award -
Delhi High Court overruled the objection of the appellant
and held that the said High Court had the jurisdiction to
entertain the petition filed uls.9 - On appeal, held: As per G
the terms of agreement, the seat of arbitration was Kuala
Lumpur- If the parties wanted to amend clause 34.12, they
could have done so only by written instrument which W?S
569 H
570 SUPREME COURT REPORTS [2011) 8 S.C.R.
•
A required to be signed by all of them - Admittedly, neither
there was any agreement .between the parties to the PSC
to shift the juridical seat of arbitration from Kuala Lumpur
to London nor any written instrument was signed by them
for amending clause 34.12 - Mere change in the physical
B venue of the hearing from Kuala Lumpur to Amsterdam
and London did not amount to change in the juridical seat
of arbitration - In cases of international commercial
arbitrations held out of India provisions of Part I of the Act
would apply unless the parties by agreement, express or
c implied, exclude all or any of its provisions - In that case
the laws or rules chosen by the parties would prevail - In
the p(esent case, the parties had agreed that
notwithstanding Clause 33. 1, the arbitration agreement
contained in Clause 34 of PSC shall be governed by laws
0 of England - This necessarily implies that the parties had
agreed to exclude the provisions of Part I of the Act - As
a corollary, the Delhi High Court did not have the
jurisdiction to entertain the petition filed by the respondents
uls.9 of the Act and the mere fact that the appellant had
E earlier filed similar petitions was not sufficient to clothe that
High Court with the jurisdiction to entertain the petition filed
by the respondents -- English Arbitration Act, 1996 - ss.3
and 53.
A Production Sharing Contract (PSC) was executed
F between re~pondent No.1-Government of India on the
one hand and a consortium of four companies
consisting of Oil and Natural Gas Corporation Limited,
Videocon Petroleum Limited, Command Petroleum
(India) Private Limited and Ravva Oil (Singapore)
G Private Limited (hereinafter referred to as "the
Contractor'') in terms of which the latter was granted
an exploration licence and mining lease to explore and
produce the hydro carbon resources owned by
respondent No.1. Subsequently, Cairn Ener:gy U.K. was
H subst!tuted in place of Command Petroleum (India)
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA 571
AND ANR.
Private Limited and the name of the Videocon A
Petroleum Limited was changed to Petrocon India
Limited, which merged the appellant - Videocon
Industries Limited.
In 2000, disputes arose between the respondents B
and the contractor with respect to correctness of
certain cost recoveries and profit. Sinoe the parties
could not resolve their disputes amicably, the same
were referred to the arbitral tribunal under clause 34.3
of the said PSC. The arbitral tribunal fixed the date of
hearing at Kuala Lumpur (Malaysia), but due to C
outbreak of epidemic SARS, the arbitral tribunal shifted
the venue of its sittings to Amsterdam in the first
instance and, thereafter, to London. Thereafter, various
proceedings were held by the arbitral tribunal at
London. Subsequently a partial award was passed. D
Respondent No.1 challenged the partial award by
filing a petition in the High Court of Malaysia at Kuala
Lumpur. On being noticed, the appellant questioned
the maintainability of the case before the High Court E
of Malaysia by contending that in view of clause 34.12
of the PSC only the English Courts had the jurisdiction
to entertain any challenge to the award.
After filing the petition before the .High Court of
Malaysia, the respondents made a request to the F
tribunal to conduct the remaining arbitral proceedings
at Kuala Lumpur, but their request was rejected and it
was declared that the remaining arbitral proceedings
will be held in London. At that stage, the respondents
filed an application under Section 9 of the Arbitration G
and Conciliation Act, 1996 in Delhi High Court for stay
of the arbitral proceedings. The appellant objected to
the maintainability of the application and pleaded that
the Courts in India did not have the jurisdiction to
entertain challenge to the arbitral award. The Single H
572 SUPREME COURT REPORTS [2011] 8 S.C.R.
A Judge of the Delhi High Court overruled the objection
of the appellant and held that the said High Court had
the jurisdiction to entertain the petition filed under
Section 9 of the Act.
8 The question which therefore arose for
consideration in the present appeal was whether the
Delhi High Court could entertain the petition filed by
the respondents under Section 9 of the Arbitration and
Conciliation Act, 1996 for grant of a declaration that
C Kuala Lumpur (Malaysia) was contractual and juridical
seat of arbitration and for issue of a direction to the
arbitral tribunal to continue the hearing at Kuala
Lumpur in terms of clause 34 of PSC.
Allowing the appeal, the Court
D
HELD:1.1. The first issue is as to whether Kuala
Lumpur was the designated seat or juridical seat of
arbitration and the same had been shifted to London.
It is evident that in terms of clause 34.12 of the PSC
E entered into by 5 parties, the seat of arbitration was
Kuala Lumpur, Malaysia. However, due to outbreak of
epidemic SARS, the arbitral tribunal decided to hold its
sittings first at Amsterdam and then at London and the
parties did not object to this. In the proceedings held
at London, the arbitral tribunal recorded the consent of
F the parties for shifting the juridical seat of arbitration
to London. Whether this amounted to shifting of the
physical or juridical seat of arbitration from Kuala
Lumpur to London would depend on a holistic
consideration of the relevant clauses of the PSC. As
G per the terms of agreement, the seat of arbitration was
Kuala Lumpur. If the parties wanted to amend clause
34.12, they could have done so only by written
instrument which was required to be signed by all of
them. Admittedly, neither there was any agreement
H between the parties to the PSC to shift the juridical seat
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA
AND ANR.
573
of arbitration from Kuala Lumpur to London nor any A
written instrument was signed by them for amending
clause 34.12. Therefore, the mere fact that the .parties
to the particular arbitration had agreed for shifting of
the seat of arbitration to London cannot be interpreted
as anything except physical change of the venue of B
arbitration from l<uala Lumpur to London. In this
connection, reference can usefully be made to Section
3 of the English Arbitration Act, 1996. A reading of the
above provision shows that under the English law the
seat of arbitration means juridical seat of arbitration, c
which can be designated by the parties to the
arbitration agreement or by any arbitral or other
institution or person empowered by the parties to do
so or by the arbitral tribunal, if so authorised by the
parties. In contrast, there is no provision in the Act D
under ·~!hich the arbitral tribunal could change the
juridical seat of arbitration which, as per the agreement
of the parties, was Kuala Lumpur. Therefore, mere
change in the physical venue of the hearing from Kuala
Lumpur to Amsterdam and London did not amount to
change in the juridical seat of arbitration. This is E
expressly indicated in Section 53 of the English
Arbitration Act, 1996. [Paras 12, 13) [585-F-H; 586-H;
587-A-C]
1.2. The next issue is whether the Delhi High Court F
could entertain the petition filed by the respondents
under Section 9 of the Act. In Bhatia International v. Bulk
Trading S.A., a three-Judge Bench of this Court held
that the provisions of Part I of the Act would apply to
all arbitrations and to all proceedings relating thereto. G
Where such arbitration is held in India the provisions
of Part I would compulsorily apply and parties are free
to deviate only to the extent permitted by the derogable
provisions of Part I. In cases of international commercial
arbitrations held out of India provisions of Part I would H
574 SUPREME COURT REPORTS [2011) 8 S.C.R.
A apply unless the parties by agreement, express or
implied, exclude all or any of its provisions. In that case
the laws or rules chosen by the parties would prevail.
Any provision, in Part I, which is contrary to or
excluded by that law or rules will not apply. [Para 15]
B [588-C-E; 593-C]
1.3. In the present case, the parties had agreed that
notwithstanding Clause 33.1 of the PSC, the arbitration
agreement contained in Clause 34 shall be governed
G by laws of England. This necessarily implies that the
parties had agreed to exclude the provisions of Part I
of the Act. As a corollary to the above conclusion, the
Delhi High Court did not have the jurisdiction to
entertain the petition filed by the respondents under
Section 9 of the Act and the mere fact that the appellant
D had earlier filed similar petitions was not sufficient to
clothe that High Court with the jurisdiction to entertain
the petition filed by the respondents. In the result, the
impugned order is set aside and the petition filed by
the respondents under Section 9 of the Act is
E dismissed. [Paras 19, 20) [599-0-F]
Bhatia International v. Bulk Trading S.A. (2002) 4 SCC
105: 2002 (2) SCR 411; Dozco India P. Ltd. v. Doosan
lnfracore Co. Ltd. 2010 (9) UJ 4521 (SC) and Venture
F Global Engineering v. Satyam Computer Services Limited
(2008) 4 sec 190: 2008 (1) SCR 501 - relied on.
Hardy Oil and Gas Limited v. Hindustan Oil Exploration
Company Limited and others (2006) 1 GLR 6.58 -
approved.
G
Shreejee Traco (I) Pvt. l:..td. v. Paperline International
Inc. (2003) 9 sec 79; National Thermal Power Corporation
v. Singer Company (1992) 3 SCC 551: 1992 (3) SCR 106
- referred to.
H
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA 575
AND ANR.
Mulamchand v. State of Madhya Pradesh (1968) 3 A
SCR 214 and State of Haryana v. Lal Chand (1984) 3
SCR 715 - cited.
Case Law Reference:
2002 (2) SCR 411 relied on Para 8, 9, B
15, 16, 17,18
(1968) 3 SCR 214 cited Para 10
(1984) 3 SCR 715 cited Para 10
2010 (9) UJ 4521 (SC) relied on Para 14
c
2008 (1) SCR 501 referred to Para 16
(2003) 9 sec 79 referred to Para 17
1992 (3) SCR 106 referred to Para 17 D
(2006) 1 GLR 658 approved Para 17
CIVIL APPELLATE JURISDICTION : Civil Appeal No.
4269 of 2011.
E
From the Judgment and Order dated 30.04.2008 of the
High Court of Delhi at New Delhi in O.M.P. No. 255 of 2006.
R.F. Nariman, Manu Nair, Mark D'Souza and Prashant
Kalra (for Suresh A. Shroff & Co.) for the Appellant.
F
K.R. Sasiprabhu and R. Chandrachud for the
· Respondents.
The Judgment of the Court was delivered by
G
G.S. SINGHVI, J. 1. Leave granted.
2. Whether the Delhi High Court could entertain the
petition filed by the respondents under Section 9 of the
Arbitration and r.onciliation Act, 199Ei (for short, "the Act")
for grant of a declaration that Kuala Lumpur (Malaysia) is H
576 SUPREME COURT REPORTS [2011) 8 S.C.R.
•
A contractual and juridical seat of arbitration and for issue of
a direction to the arbitral tribunal to continue the hearing at
Kuala Lumpur in terms of clause 34 of Production Sharing
Contract (PSC) is the question which arises for consideration
in this appeal.
B
3. Respondent No.1 - Government of India owns
petroleum resources within the area of India's territorial
waters and exclusive economic zones. Respondent No.2 is
an arm of the Ministry of Petroleum and Natural Gas. On
C 28.10.1994, a PSC was executed between respondent No.1
on the one hand and a consortium of four companies
consisting of Oil and Natural Gas Corporation Limited,
Videocon Petroleum Limited, Command Petroleum (India)
Private Limited and Rawa Oil (Singapore) Private Limited
(hereinafter referred to as "the Contractor") in terms of which
D the latter was granted an exploration licence and mining
lease to explore ~nd produce the hydro carbon resoyrces
owned by respondent No.1. Subsequently, Cairn Energy U.K.
was substituted in place of Command Petroleum (India)
Private Limited and the name of the Videocon Petroleum
E Limited was changed to Petrocon India Limited, which
merged the appellant - Videocon Industries Limited. For the
sake of convenience, the relevant clauses of Articles 33, 34
and 35 of the PSC are extracted below:
F "33.1 Indian Law to Govern
Subject to the provisions of Article 34.12, this Contract
shall be governed and interpreted in accordance with
the laws of India.
·G 33.2 Laws of India Not to be Contravened
Subject to Article 17.1 nothing in this Contract shall
entitle the Contractor to exercise the rights, privileges
and powers conferred upon it by this Contract in a
manner which will contravene the laws of India.
H
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA
AND ANR. [G.S. SINGHVI, J.]
577
34.3 Unresolved Disputes A
Subject .to the provisions of this Contract, the Parties
agree that any matter, unresolved dispute, difference or
claim which cannot be agreed or settled amicably within
twenty one (21) days may be submitted to a sole expert
8
(where Article 34.2 applies) or otherwise to an arbitral
tribunal for final decision as hereinafter provided.
34.12. Venue and Law of Arbitration Agreement
The venue of sole expert, conciliation or arbitration c
proceedings pursuant to this Article, unless the Parties
otherwise agree, shall be Kuala Lumpur, Malaysia, and
shall be conducted in the English language. Insofar as
practicable, the Parties shall continue to implement the
terms of this Contract notwithstanding the initiation of 0
arbitral proceedings and any pending claim or dispute.
Notwithstanding the provisions of Article 33.1, tile
arbitration agreement contained in this Article 34 shall
be governed by the laws of England.
35.2 Amendment E
This Contract shall not be amended, modified, varied or
supplemented in any respect except by an instrument in
writing signed by all the Parties, which shall state the
date upon which the amendment or modification shall F
·become effective."
4. In 2000, disputes arose between the respondents and
the contractor with respect to correctness of certain cost
recoveries and profit. Since the parties could not resolve their G
disputes amicably, the same were referred to the arbitral
tribunal under clause 34.3 of the PSC. The arbitral tribunal
fixed 28.3.2003 as the date of hearing at Kuala Lumpur
(Malaysia), but due to outbreak of epidemic SARS, the
arbitral tribunal shifted the venue of its sittings to Amsterdam
in the first instance and, thereafter, to London. In its meeting H
578 SUPREME COURT REPORTS (2011) 8 S.C.R. •
A held on 29.6.2003 at Amsterdam, the arbitral tribunal issued
various directions in Arbitration Case No.1 of 2003. On the
next day, the arbitral tribunal issued similar directions in
Arbitration Case Nos.2 and 3 of 2003. On 19.8.2003, the
arbitral tribunal issued revised time schedule for filing of the
B statement of claim, reply and counter claim, reply to counter
claim, documents, affidavit of admission and denial of
documents in Arbitration Case No.3 of 2003 and fixed the
case for further proceedings to be held at London on
12.12.2003. By another order dated 30.10.2003, the arbitral
c tribunal directed that the hearing of the application filed by -·
the claimants for taking on record the supplementary claim
will take place at London on 15.11.2003, on which date, the
following order was passed in Arbitration Case No.3 of
2003:
D "By consent of parties, seat of the Arbitration is shifted
to London.
Parties will deposit Rs.25,000 each as administrative
cost with the Presiding Arbitrator."
E
5. Thereafter, the following proceedings were held by the
arbitral tribul'lal at London:
(i) 6.2.2004 - Interim Award pronounced in Case
No.1 of 2003 pronounced.
F
(ii) 7.2.2004 - proceedings held in Arbitration Case
No.2 of 2003.
(iii) 17.3.2004 - Case No.2 of 2003 fixed for 13-
19.5.2004 for final arguments.
G
·(iv) 17.3.2004 - Case No.3 of 2003 fixed for
recording of evidence from 3.6.2004 to 9.6.2004.
(v) 17.3.2004 - Case No.3 of 2003 fixed for
H arguments from 20-26.7.2004.
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA
AND ANR. [G.S. SINGHVI, J.]
579
(vi) 27.3.2004 - final arguments rescheduled. to 16- A
20.5.2004 in Case No.2 of 2003.
(vii) 25.11.2004 - Arbitral Tribunal declared that it will
pass award in Case No.2 of 2003 and further
partial award in Case No.1 of 2003.
B
(viii) 3.2.2005 - Case No.2 of 2003 fixed for 25-
26.2.2005 for hearing on the application for
clarification filed on behalf of the Government of
India.
c
(ix) 12.3.2005 - The Tribunal declared that it will
finalise the award in Case No.3 of 2003 and
cross-objections in Case No.1 of 2003.
(x) 31.3.2005 - Partial award passed in Case No.3
of 2003. D
6. Respondent No.1 challenged partial award dated
31.3.2005 by filing a petition in the High Court of Malaysia
at Kuala Lumpur. On being noticed, the appellant questioned
the maintainability of the case before the High Court of E
Malaysia by contending that in view of clause 34.12 of the
PSC only the English Courts have the jurisdiction to entertain
any challenge to the award.
7. After filing the petition before the High Court of F
Malaysia, the respondents made a request to the tribunal to
conduct the remaining arbitral proceedings at Kuala Lumpur,
but their request was rejected vide order dated 20.4.2006
and it was declared that the remaining arbitral pr'oceedings
will be held in London.
G
8. At that stage, the respondents filed OMP No.255 of
2006 under Section 9 of the Act in Delhi High Court for stay
of the arbitral proceedings. They filed another OMP No.329
of 2006 questioning award dated 31.3.2005 on the issue of
H
A
580 SUPREME COURT REPORTS (2011) 8 S.C.R.
exchange rate. The appellant objected to the maintainability
•
of OMP No.255 of 2006 and pleaded that the Courts in India
do not have the jurisdiction to entertain challenge to the
arbitral award. The learned Single Judge of the Delhi High
Court overruled the objection of the appellant and held that
B the said High Court has the jurisdiction to entertain the petition
filed under Section 9 of the Act. The learned Single Judge
extensively referred to the judgment of this Court in Bhatia
International v. Bulk Tradinri S.A. (2002) 4 SCC 105 and
observed:
c "The ratio of Bhatia International, in my understanding,
is that the provisions of Part-I of the Indian Arbitration
Act would apply to international commercial arbitrations
held outside India, unless the parties by agreement
express or implied, exclude all or any of its provisions.
D
It is noteworthy that the respondent, while challenging the
jurisdiction of this Court to entertain the present petition,
has not disputed the applicability of Part I of the Indian
Arbitration Act to international commercial arbitrations
E held outside India. It is not the case of the respondent
that section 9 of the Indian Arbitrations Act does not
apply to international commercial arbitrations held
outside India. What, in fact, learned senior counsel for
the respondent has sought to contend before this Court
F is that the parties herein, by ~dopting the English Law
as the proper law governing the arbitration agreement,
have expressly excluded the applicability of the Indian
Arbitration Act, and consequently, this Court has no
jurisdtction to entertain the present petition. This
contention of the respondent has been resisted by
G
learned senior counsel for the petitioner on the ground
that English law governs the substantive aspects of the
arbitration agreement, whilst the procedural aspect
thereof is governed by the curial law, that is, the
procedural law of the country where the seat of
H
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA
AND ANR. [G.S. SINGHVI, J.)
581
arbitration is. It is thus contended by learned senior A
counsel for the petitioner that the juridical seat of
arbitration being in Kuala Lumpur, it is the Malaysian
laws that would govern the conduct of the arbitral
proceedings. Learned senior counsel for the respondent
has countervailed the said averment of the petitioner by B
submitting that London, and not, Kuala Lumpur is the
'designated seat' of arbitration in view of the order
dated 15.11.2003 passed by the Arbitral Tribunal
whereby the Arbitral Tribunal recorded the consent of the
parties and shifted the seat of arbitration to London. In c
view of the petitioner having already conceded to
London as the juridical seat of arbitration, it is thus
contended by learned counsel for the respondent that
the petitioner cannot know insist on Kuala Lumpur being
the seat of arbitration. D
The averments made by the respondent, without
prejudice to the veracity thereof, entail an examination
on merit and thus cannot be accepted at this preliminary
stage. Whether the Courts at Kuala Lumpur or London
have the jurisdiction to decide upon the seat of E
arbitration squarely hinges on the procedural law
governing the arbitration agreement. However, in a
peculiar situation such as the present one where the
governing procedural law is yet to be determined, I am
of the view that a question regarding the seat of F
arbitration can be best decided by the Court to which
the parties or to which the dispute is most closely
connected. It is important to recall that in the instant case
the parties have expressly stated in Article 33.1 of the
PSC that the laws applicable to the contract would be G
the laws in force in India and that the "Contract shall be
governed and interpreted in accordance with the laws
of India". These words are wide enough to engulf every
question arising under the contract including the disputes
between the parties and the mode of settlement. It was H
582 SUPREME COURT REPORTS [2011] 8 S.C.R. •
A in India that the PSC was executed. The form of the
PSC is closely related to the system of law in India. It
is also apparent that the PSC is to be performed in
ln_dia with the aid of Indian workmen whose conditions
of service are regulated by Indian laws. Moreover, whilst
B the petitioner is an important portfolio of the Government
of India, the respondent is also a company incorporated
under the Indian laws. The contract has in every respect
the closest and most real connection with the Indian
system of law and it is by that law that the parties have
c expressly evinced their intention to be bound in all
respects. The arbitration agreement is contained in one
of the clauses of the contract, and not in a separate
agreement. In the absence of any indication to the
contrary, the governing law of the contract or the "proper
D law" (in the words of Dicey) of the contract being Indian
law, it is that system of law which must necessarily
govern matters concerning arbitration, although in certain
respects the law of the place of arbitration may have its
relevance in regard to procedural matters.
E There is no gainsay that the Courts observe extreme
circumspection whilst affording relief under section 9 of
the Indian Arbitration Act, lest the annals of party
autonomy and sanctity of the arbitral tribunal - the
hallmarks of any arbitration - are jeopardized. It is to
F be appreciated that the object underlying the grant of
interim measures under section 9 of the Indian
Arbitration Act is to facilitate and sub serve any ongoing
arbitral proceedings.
G
It is much apparent that the disparate stands taken by
both parties qua the seat of arbitration has resulted in
a veritable impasse in the arbitral proceedings in the
present case. The petitioner has brought to our notice
that the proceedings initiated by it at the High Court
t<uala Lumpur challenging the Partial award have been
H
virtually brought to a standstill owing the objections
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA 583
AND ANR. [G.S. SINGHVI, J.)
raised by the respondent on grounds of jurisdiction. The A
petitioner has already expressed its dissidence about
the English Court deciding the question of seat of
arbitration for the reason that for the English Court to
assume jurisdiction, it is the place of arbitration which
is the relevant factor. In such a situation, of the Indian B
Court does not adjudicate upon the present petition, the
arbitral proceedings between the parties will invariably
end in a stalemate. This, I am afraid, would not only be
inimical to the interests of the parties but also affront to
section 9 of the Indian Arbitration, the underlying object c
whereof is to sub serve and facilitate arbitral
proceedings."
9. Shri R.F. Nariman, learned senior counsel appearing
for the appellant argued that the impugned order is liable to
be set aside because the learned Single Judge D
misconstrued and misapplied the judgment of this Court in
Bhatia International v. Bulk Trading S.A. (supra) and
erroneously held that the Delhi High Court has jurisdiction to
decide O.M.P. No.255 of 2006. Learned counsel further
argued that the learned Single Judge failed to appreciate that E
the reliefs prayed for in O.M.P. No.255 of 2006 could not
have been granted on an application filed under Section 9
of the Act because stay of arbitral proceedings is beyond
the scope of that section. Learned senior counsel
emphasized that Section 5 of the Act expressly bars F
intervention of the Courts except in matters expressly
provided for in the Act and, therefore, even if the petition filed
by the respondents under Section 9 could be treated as
maintainable, the High Court did not have jurisdiction over
the arbitration proceedings because the same are governed G
by the laws of England. Shri Nariman then argued that after
having expressly consented to the shifting of the seat of
arbitration from Kuala Lumpur to Amsterdam in the first
instance and effectively taken part in the proceedings held
at London till 31.3.2005, respondent No.1 is estopped from H
584 SUPREME COURT REPORTS [2011] 8 S.C.R.
A claiming that the seat of arbitration continues to be a.t Kuala
Lumpur. Learned senior counsel submitted that the learned
Single Judge was not justified in rejecting objection to the
maintainability of the petitions filed by respondent No.1 in the
Delhi High Court merely because the appellant had earlier
B filed O.M.P. No.179 of 2003 before the High Court. He
submitted that the doctrine of waiver and acquiescence
cannot be pressed into service for deciding the issue relating
to jurisdiction of the Delhi High Court to entertain the petition
filed under Section 9 of the Act. Shri Nariman further
c submitted that if respondent No.1 felt aggrieved against
partial award it could have filed petition under Sections 67
and 68 of the English Arbitration Act, 1996.
10. Shri Gopal Subramaniam, learned Solicitor General
submitted that as per the arbitration agreement which is
D binding on all the parties to the contract, a conscious
decision was taken by them that Kuala Lumpur will be the
s.eat of any intended arbitration, Indian law as the law of
contract and English law as the law ')f arbitration and. the
mere fact that the arbitration was held outside Kuala Lumpur
E due to the outbreak of epidemic SARS, the venue of
arbitration cannot be said to have been changed from Kuala
Lumpur to London. Learned Solicitor General emphasised
that once Kuala Lumpur was decided as the venue of
arbitration by written agreement, the same could not have
F been changed except by amending the written agreement as
provided in clause 35.2 of the PSC. He then argued that the
arbitral tribunal was not entitled to determine the seat of
arbitration and the record of proceedings held on 15.11.2003
at London cannot be construed as an agreement between
G the parties for change in the juridical seat of arbitration. He
further argued that the PSC was between the Government
of India· and ONGC Ltd., Videocon Petroleum Ltd.,
Command Petroleum (India) Pvt. Ltd. and Ravva Oil
(Singapore) Pvt. Ltd. and, therefore, the venue of arbitration
H cannot be treated to have been changed merely on the basis
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA
AND ANR. [G.S. SINGHVI, J.]
585
of the so called agreement between the appellant and the A
respondents. Learned Solicitor General submitted that any
change in the PSC requires the concurrence by all the
parties to the contract and the consent, if any, given by two
of the parties cannot have the effect of changing the same.
He then argued that every written agreement on behalf of B
respondent No.1 is required to be expressed in the name
of the President and in the absence of any writt~:n
agreement having been reached between the parties to the
PSC to amend the same, the consent given for shifting the
physical seat of arbitration to London did not result in change C
of juridical seat of the arbitration which continues to be
Kuala Lumpur. In support of this argument, the learned
Solicitor General relied upon the judgments of this Court in
1 Mutamchand v. State of Madhya Pradesh (1968) 3 SCR
214 and State of Haryana v. Lal Chand (1984) 3 SCR 715. D
In the end, he argued that the provisions of the English
Arbitration Act, 1996 would have applied only if the seat of
arbitration was in England and Wales. He submitted that
London cannot be treated as juridical seat of arbitration
merely because the parties had decided that the arbitration
agreement contained in Article 34 will be governed by the E
laws of England.
11. We have considered the respective submissions
and perused the record.
F
12. We shall first consider the question whether Kuala
Lumpur was the designated seat or juridical seat of
arbitration and the same had been shifted to London. In
terms of clause 34.12 of the PSC entered into by 5 parties,
the seat of arbitration was Kuala Lumpur, Malaysia. However, G
due to outbreak of epidemic SARS, the arbitral tribunal
decided to hold its sittings first at Amsterdam and then at
London and the parties did not object to this. In the
proceedings held on 14th and 15th October, 2003 at
London, the arbitral tribunal recorded the consent of the
H
586 SUPREME COURT REPORTS [2011] 8 S.C.R.
A parties for shifting the juridical seat of arbitration to London.
Whether this amounted to shifting of the physical or juridical
seat of arbitration from Kuala Lumpur to London? The
decision of this would depend on a holistic consideration of
the relevant clauses of the PSC. Though, it may appear
B repetitive, we deem it necessary to mention that as per the
terms of agreement, the seat of arbitration was Kuala
Lumpur. If the parties wanted to amend clause 34.12, they
could have done so only by written instrument which was
required to be signed by all of them. Admittedly, neither there
c was any agreement between the parties to the PSC to shift
the juridical seat of arbitration from Kuala Lumpur to London
nor any written instrument was signed by them for amending
clause 34.12. Therefore, the mere fact that the parties to the
particular arbitration had agreed for shifting of the seat of
0 arbitration to London cannot be interpreted as anything
except physical change of the venue of arbitration from Kuala
Lumpur to London. In this connection, reference can usefully
be made to Section 3 of the English Arbitration Act, 1996,
which reads as follows:
E "3.The seat of the arbitration.
In this Part "the seat of the arbitration" means the
juridical seat of the arbitration designated-
(a) by the parties to the arbitration agreement, or
F
(b) by any arbitral or other institution or person vested
by the parties with powers in that regard, or
(c) by the arbitral tribunal if so authorised by the parties,
G or determined, in the absence of any such designation,
having regard to the parties' agreement and all the
relevant circumstances."
13. A reading of the above reproduced provision shows
that under the English law the seat of arbitration means
H
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA
AND ANR. [G.S. SINGHVI, J.]
587
juridical seat of arbitration, which can be designated by the A
parties to the arbitration agreement or by any arbitral or other
institution or person empowered by the parties to do so or
by the arbitral tribunal, if so authorised by the parties. In
contrast, there is no provision in the Act under which the
arbitral tribunal could change the juridical seat of arbitration 8
which, as per the agreement of the parties, was Kuala
Lumpur. Therefore, mere change in the physical venue of the
hearing from Kuala Lumpur to Amsterdam and London did
not amount to change in the juridical seat of arbitration. This
is expressly indicated in Section 53 of the English Arbitration C
Act, 1996, which reads as under:
"53. Place where award treated as made.
Unless otherwise agreed by the parties, where the seat
of the arbitration is in England and Wales or Northern D
Ireland, any award in the proceedings shall be treated
as made there, regardless of where it was signed,
despatched or delivered to any of the parties."
14. In Dozco India P. Ltd. v. Doosan lnfracore Co. Ltd.
2010 (9) UJ 4521 (SC), the· learned designated Judge while E
exercising power under Section 11 (6) of the Act, referred to
the following passage from Redfern v. Hunter:
"The preceding discussion has been on the basis that
there is only one "place" of arbitration. This will be the F
place chosen by or on behalf of the parties; and it will
be designated in the arbitration agreement or the terms
of reference or the minutes of proceedings or in some
other way as the place or "seat" of the arbitration. This
does not mean, however, that the arbitral tribunal must G
hold all its meetings or hearings at the place of
arbitration. International commercial arbitration often
involves people of many different nationalities, from many
different countries. In these circumstances, it is by no
means unusual for an arbitral tribunal to hold meetings H
588 SUPREME COURT REPORTS [2011] 8 S.C.R.
•
A - or even hearings - in a place other than the designated
place of arbitration, either for its own convenience- or for
the convenience of the parties or their witnesses ....
It may be more convenient for an arbitral tribunal sitting
in one country to conduct a hearing in another country -
B
for instance, for the purpose of taking evidence..... In
such circumstances, each move of the arbitral tribunal
· does not of itself mean that the seat of the arbitration
changes. The seat of the arbitration remains the place
initially agreed by or on behalf of the parties."
c
15. The next issue, which merits consideration is
whether the Delhi High Court could entertain the petition filed
by the respondents under Section 9 of the Act. In Bhatia
International v. Bulk Trading S.A. (supra), the !hree-Judge
D Bench considered the important question whether Part I of
the Act is applicable to the international arbitration taking
place outside India. After noticing the scheme of the Act and
argument of the appellant that Part I of the Act would apply
only to the cases in which the venue of arbitration is in India,
E the Court observed:
"A reading of the provisions shows that the said Act
applies to arbitrations which· are held in India between
Indian nationals and to international commercial
arbitrations whether held in India or out of India. Section
F 2(1 )(f) defines an international commercial arbitration.
The definition makes no distinction between international
commercial arbitrations held in India or outside India. An
international commercial arbitration may be held in a
country which is a signatory to either the New York
G Convention or the Geneva Convention (hereinafter called
"the convention country"). An international commercial
arbitration may be held in a non-convention country. The
said Act nowhere provides that its provisions are not to
apply to international commercial arbitrations which take
H place in a non-convention country. Admittedly, Part II only
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA
AND ANR. [G.S. SINGHVI, J.]
589
applies to arbitrations which take place in a convention A
country. Mr. Sen fairly admitted that Part II would not
apply to an international commercial arbitration which
takes place in a non-convention country. He also fairly
admitted that there would be countries which are not
signatories either to the New York Convention or to the B
Geneva Convention. It is not possible to accept the
submission that the said Act makes no provision for
international commercial arbitrations which take place in
a non-convention country.
Now le~ us look at sub-sections (2), (3), (4) and (5) of C
Section 2. Sub-section (2) of Section 2 provides that
Part I would apply where the place of arbitration is in
India. To be immediately noted, that it is not providing
that Part I shall not apply where the place of arbitration
is not in India. It is also not providing that Part I will D
"only" apply where the place of arbitration is in India
(emphasis supplied). Thus the legislature has not
provided. that Part I is not to apply to arbitrations which
take place outside India. The use of the language is
significant and important. The legislature is emphasising E
that the provisions of Part I would apply to arbitrations
which take place in India, but not providing that the
provisions of Part I will not apply to arbitrations which
take place out of India. The wording of sub-section (2)
of Section 2 suggests that the intention of the legislature F
was to make provisions of Part I compulsorily applicable
to an arbitration, including an international commercial
arbitration, which takes place in India. Parties cannot, by
agreement, override or exclude the non-derogable
provisions of Part I in such arbitrations. By omitting to G
provide that Part I will not apply to international
commercial arbitrations which take place outside India
the effect would be that Part I would also apply to
international commercial arbitrations held out of India.
But by not specifically providing that the provisions of H
590 SUPREME COURT REPORTS (2011] 8 S.C.R.
•
A Part I apply to international commercial arbitrations held
out of India, the intention of the legislature appears to
be to ally (sic allow) parties to provide by agreement
that Part I or any provision therein will. not apply. Thus
in respect of arbitrations which take place outside India
B even the non-derogable provisions of Part I can be
excluded. Such an agreement may be express or
implied.
If read in this manner there would be no conflict
between Section 1 and Section 2(2). The words "every
c arbitration" in sub-section (4) of Section 2 and the
words "all arbitrations and to all proceedings relating
thereto" in sub-section (5) of Section 2 are wide. Sub-
sections (4) and (5) of Section 2 are not made subject
to sub-section (2) of Section 2. It is significant that sub-
D section (5) is made subject to sub-section (4) but not
to sub-section (2). To acc~pt Mr. Sen's submission
would necessitate adding words in sub-sections (4) and
(5) of Section 2, which the legislature has purposely
omitted to add viz. "subject to provision of sub-section
E (2)". However read in the manner set out hereinabove
there would also be no conflict between sub-section (2)
of Section 2 and sub-sections (4) and/or (5) of Section
2.
That the legislature did not intend to exclude the
F
applicability of Part I to arbitrations, which take place
outside India, is further clear from certain other
provisions of the said Act. Sub-section (7) of Section 2
reads as follows:
G "2. (7) An arbitral award made under this Part
shall be considered as a domestic award."
As is set out hereinabove the said Act applies to (a)
arbitrations held in India between Indians, and (b)
H international commercial arbitrations. As set out
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA
AND ANR. [G.S. SINGHVI, J.]
591
hereinabove international commercial arbitrations may A
take place in India or outside India. Outside India, an
international commercial arbitration may be held in a
convention country or in a non-convention country. The
said Act however only classifies awards as "domestic
awards" or "foreign awards". Mr. Sen admits that B
provisions of Part II make it clear that "foreign awards"
are only those where the arbitration takes place in a
convention country. Awards in arbitration proceedings
which take place in a non-convention country are not
considered to be "foreign awards" under the said Act. C
They would thus not be covered by Part II. An award
passed in an arbitration which takes place in India
would be a "domestic award". There would thus be no
need to define an award as a "domestic award" unless
the intention was to cover awards which would otherwise
not be covered by this definition. Strictly speaking, an D
award passed in an arbitration which takes place in a
non-convention country would not be a "domestic
award". Thus the necessity is to define a "domestic
award" as including ail awards made under Part I. The
definition indicates that an award made in an E
international commercial arbitration held in a non-
convention country is also considered to be a "domestic
award".
(emphasis supplied) F
The Court then referred to Section 9 of the Act which
empowers the Court to make interim orders and proceeded
to observe:
"Thus under Section 9 a party could apply to the court G
(a) before, (b) during arbitral proceedings, or (c) after
the making of the arbitral award but before it is enforced
in accordance with Section 36. The words "in
accordance with Section 36" can only go with the words
H
592 SUPREME COURT REPORTS [2011) 8 S.C.R.
•
A "after the making of the arbitral award". It is clear that
the words "in accordance with Section 36" can have no
reference to an application made "before" or "during the
arbitral proceedings". Thus it is clear that an application i
for interim measure can be made to the courts in India,
B whether or not the arbitration takes place in India, before
or during arbitral proceedings. Once an award is
passed, then that award itself can be executed. Sections
49 and 58 provide that awards covered by Part II are
deemed to be a decree of the court. Thus "foreign
awards" which are enforceable in India are deemed to
c be decrees. A domestic award has to be enforced
under the provisions of the Civil Procedure Code. All that
Section 36 provides is that an enforcement of a
domestic award is to take place after the time to make
an application to set aside the award has expired or
D
such an application has been refused. Section 9 does
suggest that once an award is made, an application for
interim measure can only be made if the award is a
"domestic award" as defined in Section 2(7) of the said
Act. Thus where the legislature wanted to restrict the
E applicability of Section 9 it has done so specifically.
We see no substance in the submission that there would
be unnecessary interference by courts in arbitral
proceedings. Section .5 provides that no judicial authority
F shall intervene except where so provided. Section 9
does not permit any or all applications. It only permits
applications for interim measures mentioned in clauses
(i) and (ii) thereof. Thus there cannot be applications
under Section 9 for stay of arbitral proceedings or to
G challenge the existence or validity of the arbitration
agreements or the jurisdiction of the Arbitral Tribunal. All
such challenges would have to be made before the
Arbitral Tribunal under the said Act."
The three-Judge Bench recorded its conclusion in the
H
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA
AND ANR. [G.S. SINGHVI, J.]
593
following words: A
"To conclude, we hold that the provisions of Part I would
apply to all arbitrations and to all proceedings relating
thereto. Where such arbitration is held in India the
provisions of Part I would compulsorily apply and parties B
are free to deviate only to the extent permitted by the
derogable provisions of Part I. In cases of international
commercial arbitrations held out of India provisions of
Part I would apply unless the parties by agreement,
express or implied, exclude all or any of its provisions.
In that case the laws or rules chosen by the parties C
would prevail. Any provision, in Part I, which is contrary
to or excluded by that law or rules will not apply."
(emphasis supplied)
D
16. In Venture Global Engineering v. Satyam Computer
SeNices Limited (2008) 4 SCC 190, a two-Judge Bench
was called upon to consider whether the Court of Additional
Chief Judge, City Civil Court, Secunderabad had the
jurisdiction to entertain the suit for declaration filed by the E
appellant to ·set aside the award passed by the sole
arbitrator appointed at the instanc~ of respondent No.1
despite the fact that the arbitrator had conducted the
proceedings outside India. The trial Court had entertained
and allowed the application filed by respondent No.1 under
Order VII Rule 11 of the Code of Civil Procedure, 1908 F
(CPC) and rejected the plaint. The Andhra Pradesh High
Court confirmed the order of the trial Court. Before this
Court, reliance was placed by the appellant on the ratio of
Bhatia International v. Bulk Trading S.A. (supra) and it was
argued that the trial Court had the jurisdiction to entertain the G
suit. On behalf of the respondents, it was argued that the trial
Court did not have the jurisdiction to entertain the suit
because the award was made outside India. The Division
Bench accepted the argument made on behalf of the
appellant and observed: H
594 SUPREME COURT REPORTS [2011) 8 S.C.R. •
A "On close scrutiny of the materials and the dictum laid
down in the three-Judge Bench decision in Bhatia
International we agree with the contention of Mr. K.K.
Venugopal and hold that paras 32 and 35 of Bhatia
International make it clear that the provisions of Part I
B of the Act would apply to all arbitrations including
international commercial arbitrations and tQ all
proceedings relating thereto. We further hold that where
such arbitration is held in India, the provisions of Part I
would compulsorily apply and parties are free to deviate
to the extent permitted by the provisions of Part I. It is
c also clear that even in the case of international
commercial arbitrations held out of India provisions of
Part I would apply unless the parties by agreement,
express or implied, exclude all or any of its provisions.
We are also of the view that such an interpretation does
D not lead to any conflict between any of the provisions
of the Act and there is no lacuna as such. The matter,
therefore, is concluded by the three-Judge Bench
decision in Bhatia International.
E The learned Senior Counsel for the respondent based
on para 26 submitted that in the case of foreign award
which was passed· outside India is not enforceable in
India by invoking the provisions of t:1e Act or CPC.
However, after critical analysis of para 26, we are
F unable to accept the argument of the learned Senior
Counsel for the respondent. Paras 26 and 27 start by
dealing with the arguments of Mr Sen who argued that
Part I is not applicable to foreign awards. It is only in
the sentence starting at the bottom of para 26 that the
G phrase "it must immediately be clarified" that the finding
of the Court is rendered. That finding is to the effect that
an express or implied agreement of parties can exclude
the applicability of Part I. The finding specifically states:
"But if not so excluded, the provisions of Part I will also
H
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA
AND ANR. [G.S. SINGHVI, J.]
595
apply to all 'foreign awards'." This exception which is A
carved out, based on agreement of the parties, in para
21 (placita e to f) is extracted below:
"21 .... By omitting to provide that Part I will not
apply to international commercial arbitrations B
which take place outside India the effect would
be that Part I would also apply to international
commercial arbitrations held out of India. But by
not specifically providing that the provisions of
Part I apply to international commercial
arbitrations held out of India, the intention of the C
legislature appears to be to ally (sic allow) parties
to provide by agreement that Part I or any
provision therein will not apply. Thus in respect of
arbitrations which take place outside India even
the non-derogable provisions of Part I can be D
excluded. Such an agreement may be express or
implied."
The very fact that the judgment holds that it would be
open to the parties to exclude the application of the E
provisions of Part I by express or implied agreement,
would mean that otherwise the whole of Part I would
apply. In any event, to apply Section 34 to foreign
international awards would not be inconsistent with
Section 48 of the Act, or any other provision of Part II F
as a situation may arise, where, even in respect of
properties situate in India and where an award would be
invalid if opposed to the public policy of India, merely
because the judgment-debtor resides abroad, the award
can be enforced against properties in India through G
personal compliance of the judgment-debtor and by
holding out the threat of contempt as is being sought to
be done in the present case. In such an event, the
·judgment-debtor cannot be deprived of his right under
Section 34 to invoke the public policy of India, to set
H
596 SUPREME COURT REPORTS [2011) 8 S.C.R. •
A aside the award. As observed earlier, the public policy
of India includes - (a) the fundamental policy of India;
or (b) the interests of India; or (c) justice or morality; or
(d) in addition, if it is patently illegal. This extended
definition of public policy can be bypassed by taking the
B award to a foreign country for enforcement."
17. We may now advert to the judgment of the learned
Single Judge of the Gujarat High Court in Hardy Oil and Gas
Limited v. Hindustan Oil Exploration Company Limited and
C others (2006) 1 GLR 658. The facts of that case were that
an agreement was entered into between Unocal Bharat
Limited, Hardy Oil and Gas Limited, Netherland B.V. (Hardy),
Infrastructure Leasing and Financial Services Limited,
Housing Development Finance Corporation Limited and
Hindustan Oil Exploration Company Limited on 14.10.1998.
D The agreement had an arbitration clause. A dispute having
arisen between the parties, the matter was referred to the
arbitral tribunal. During the pendency of the arbitration
proceedings, an application was filed by the appellant in the
District Court, Vadodara under Section 9 of the Act. A
E preliminary objection was raised to the maintainability of that
petition. The learned District Judge accepted the objection.
The learned Single Judge of Gujarat High Court referred to
clause 9.5 of the agreement, which was as under:
F "9.5 Governing Law and Arbitration
1. This Agreement (except for the provisions of Clause
9.5.4 relating to arbitration) shall be governed by and
construed in accordance with the substantive laws of
India.
G
2. Any dispute or difference of whatever nature arising
under, out of, or in connection with this Agreement,
including any question regarding its existence, validity or
termination, which the parties are unable to resolve
H between themselves within sixty (60) days of notification
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA
AND ANR. [G.S. SINGHVI, J.]
597
by one or more Parties to the other(s) that a dispute A
exists for the purpose of this Clause 9 shall at the
instance of any Party be referred to and finally resolved
by Arbitration under the rules of the London Court of
International Arbitration (SLCIA), which Rules (Rules) are
deemed to be incorporated by reference into this clause. B
3. The Tribunal shall consist of two arbitrators who shall
be Queen's Counsel, practicing at the English Bar in the
Commercial Division of the High Court, one to be
selected by the Parties invoking the Arbitration clause
acting unanimously and one to be selected by the other C
shareholders acting unanimously, and one umpire who
shall also be a Queen's Counsel, practicing at the
English Bar in the Commercial Division of this High
Court. If the parties are unable to agree on the identity
of the umpire within 15 days from the day on which the D
matter is referred to arbitration, the umpire shall be
chosen and appointed by LCIA. Notwithstanding Article
3.3 of the Rules, the Parties agree that LICA may
appoint a British umpire. No arbitrator shall be a person
or former employee or agent of, or consultant or counsel E
to, any Party or any Associated Company or any Party
or in any way otherwise connected with any of the
Parties.
4. The place of arbitration shall be London and the F
language of arbitration shall be English. The law
governing arbitration will be the English law.
5. Any decision or award of an arbitral tribunal shall be
final and binding on the Parties."
G
The learned Single Judge referred to various judgments
of this Court including Bhatia lntemational v. Bulk Trading
S.A. (supra), Shreejee Traco (I) Pvt. Ltd. v. Paperline
fntemational Inc. (2003) 9 SCC 79, National Thermal Power
Corporation v. Singer Company (1992) 3 SCC 551 and H .
598 SUPREME COURT REPORTS [2011] 8 S.C.R. •
A upheld the order of the learned District Judge by observing
that in terms of clause 9.5.4 of the agreement, the place of
arbitration was London and the law governing arbitration was
the English law. The learned Single Judge referred to
paragraph 32 of the judgment in Bhatia International v. Bulk
B Trading S.A. (supra) and observed that once the parties had
agreed to be governed by any law other than Indian law in
cases of international commercial arbitration, then that law
would prevail and the provisions of the Act cannot be invoked
questioning the arbitration proceedings or the award. This is
C evident from paragraph 11.3 of the judgment, which is
extracted below:
"However, their Lordships observed in Para.32 that in
cases of international commercial arbitrations held out
of India provisions of Part-I would apply unless the
D parties by agreement, express or implied, exclude all or
any of its provisipns. In that case laws or rules chosen
by the parties would prevail. Any provision, in Part-I,
which is contrary to or excluded by that law or rules
would not apply. Thus, even as per the decision relied
E upon by learned advocate for the appellant, if the parties
have agreed to be governed by any law other than
Indian law in cases of international commercial
arbitration, same would prevail. In the case on hand, it
is very clear even on plain reading of Clause. 9.5.4 that
F the parties' intention was to be governed by English law
in respect of arbitration. It is not possible to give a
narrow meaning to this clause as suggested by learned
Senior Advocate Mr. Thakore that it would apply only in
case of dispute on Arbitration Agreement. It can be
interpreted only to mean that in case of any dispute
G
regarding arbitration, English law would apply. When the
clause deals with the place and language of arbitration
with a specific provision that the law governing arbitration
will be the English law, such a narrow meaning cannot
be given. No other view is possible in light of exception
H
• VIDEOCON INDUSTRIES LTD. v. UNION OF INDIA
AND ANR. [G.S. SINGHVI, J.]
599
carved out of Clause 9.5.1 relating to arbitration. Term A
Arbitration, in Clause 9.5.4 cannot be taken to mean
arbitration agreement. Entire arbitral proceedings have
to be taken to be agreed to be governed by English
law."
18. In our opinion, the learned Single Judge of (3ujarat 8
High Court had rightly followed the conclusion recorded by
the three-Judge Bench in Bhatia International v. Bulk Trading
S.A. (supra) and held that the District Court, Vadodara did
not have the jurisdiction to entertain the petition filed under
Section 9 of the Act because the parties had agreed that . C
the law governing the arbitration will be English law.
19. In the present case also, the parties had agreed that
notwithstanding Article 33.1, the arbitration agreement
contained in Article 34 shall be governed by laws of England. D
This necessarily implies that the parties had agreed to
exclude the provisions of Part I of the Act. As a corollary to
the above conclusion, we hold that the Delhi High Court did
not have the jurisdiction to entertain the petition filed by the
respondents under Section 9 of the Act and the mere fact E
that the appellant had earlier filed similar petitions was not
sufficient to clothe that High Court with the jurisdiction to
entertain the petition filed by the respondents.
20. In the result, the appeal is allowed. The impugned
order is set aside and the petition filed by the respondents F
under Section 9 of the Act is dismissed.
8.8.8. Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.