Created byFuzzy Cloud

Supreme Court of India

UNION OF INDIAversusM/S. AMBLCA CONSTRUCTION

Citation
2016 INSC 265
Decided
16 March 2016
Disposal
Reference answered

Holding

If the contract expressly bars the award of pendente lite interest, the arbitrator cannot award such interest.

Summary

The case concerned whether an arbitrator could award pendente lite interest when the underlying contract expressly barred interest on delayed payments. The dispute arose from a construction contract between the Union of India and M/s. Ambica Construction, which had undergone multiple arbitrations and court interventions. The Supreme Court examined the provisions of the Arbitration Act, 1940, the Arbitration and Conciliation Act, 1996, and the CPC, interpreting the contractual clause that prohibited interest. It held that an express contractual bar on pendente lite interest defeats the arbitrator’s power to award such interest, but a bar only on interest for delayed payment does not automatically extend to pendente lite interest. Consequently, the award of pendente lite interest in the earlier arbitration award was set aside and the award modified. The petition was disposed in favour of the Union of India.

Issues considered

  • The arbitrator's power to award pendente lite interest under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996.
  • Whether an express contractual clause barring interest on delayed payments also bars pendente lite interest.
  • The effect of the Arbitration Act, 1940 (Section 3) and implied terms on the arbitrator's jurisdiction.

Legislation cited

Subjects

ArbitrationPendente lite interestContractual barArbitrator's jurisdictionArbitration Act 1940Arbitration and Conciliation Act 1996Interest award

Judgment

                            (2016] 2 S.C.R. 810



A                           UNION OF INDIA
                                     v.
                    MIS. AMBlCA CONSTRUCTION
              (Special Leave Petition (Civil) No.11114 of2009)
B                            MARCH 16,2016
               [RANJAN GOGOi, ARUN MISHRA AND
                     PRAFULLA C. PANT, JJ.]
       Arbitration Act,19./0: ss.3, 31 - Puwer of arbitrator to award
  pendente lite interest in case contract bars the same - Held: If
c contract expressly bars award of interest pendente lite, the same
  cannot be awarded by the Arbitrator -· Bar to award interest on
  delayed payment by itself will not be readily inferred as express bar
  to award interest pendente lite by the Arbitrator as ouster. of power
  of Arbitrator has to be considered on various relevant aspects -
D The award of pendente lite interest inter alia must depend upon the
  overall intention of the agreement and what is expressly excluded.
       Answering the reference, the Court
       HELD: 1. Section 3 of the Act of 1940 deals with the
  provisions which are implied in the arbitration agreement. The
E provisions of section 3 make it clear that unless a different
  intention is expressed in the arbitration agreement, the
  agreement would include the provisions contained in the First
  Schedule so far as they arc applicable to the reference. Provisions
  in the First Schedule contain 8 paragraphs. It provides for
  reference to a sole Arbitrator and in case there are even numbers
F
  of Arbitrators, appointment of umpire is also provided. An
  Arbitrator is required to pass award within 4 months from the
  date of entering on the reference. In case Arbitrator fails to pass
  an award within the specified time the umpire shall make the
  award within 2 months. Para 6 of First Schedule provides that the
G Arbitrator or umpire shall examine the matters in difference and
  the award shall be final and binding. Arbitrator or umpire has the
  power for examining the witnesses and production of relevant
  documents. Para 8 of Schedule I provides for costs of reference
  and awards shall be in the discretion of the Arbitrator. [Para 5]
  (816-A-D]
H
                                    810
     UNION OF INDIA v. M/S. AMBICA CONSTRUCTION                         811



     2. "Court" has been defined in section 2(c) of the Act to           A
mean a civil court having jurisdiction to decide the questions
forming the subject-matter of the reference. The court can
exercise the power specified in Second Schedule of the Act.
However, Arbitrator is not a court. Arbitrator is the outcome of
agreement. He decides the disputes as per the agreement entered
                                                                         B
into between the parties. Arbitration is an alternative forum for
resolution of disputes but an Arbitrator ipso facto does not enjoy
or possess all the powers conferred on the courts of law. Section
29 of the Act confers on the court power to award interest from
the date of decree. Section 34 of the C.P.C. confers on the court
power to award interest prior to the institution of the suit and         c
during pendency of the suit and post decree. Section 31(7)(a) of
the 1996 Act confers power on Arbitrator to award interest
pendente lite, "unless otherwise agreed by parties". Thus, it is
clear from the provisions contained in section 31(7)(a) that the
coniract between the parties has been given importance and is
                                                                         D
h;nding on t.he Arbitrator. Arbitration clause is also required to
be looked into while deciding the power of the Arbitrator and in
case there is any bar contained in the contract on award of interest,
it operates on which items and in the arbitration clause what are
the powers conferred on Arbitrator and whether bar on award of
interest has been confined to certain period or it relates to            E
pendency of proceedings before Arbitrator. Grant of pemle11te lite
interest may depend upon several factors such as phraseology
used in the agreement, clauses conferring power relating to
arbitration, nature of claim and dispute referred to Arbitrator and
on what items power to award interest has been taken away and
                                                                         F
for which period. (Paras 6, 7, 16, 23] (816-E; 817-A-C; 828-D-E;
836-C-D]
      Board of Trustees for the Port of Calcutta v. Engineers-
      De-Space-Age 1995 (6) Suppl. SCR 327 : (1996) 1 SCC
      516; Madnani Construction Corporation (P) Ltd. v.
      Union of India and Others 2009 (16) SCR 216 : (2010)               G
      1 SCC 549; Secretary, Irrigation Department,
      Government of Orissa & Ors. v. GC. Roy 1991 (3)
      Suppl. SCR 417: (1992) 1 SCC 508; Executii"e
      Engineer, Dhenkanal Minor Irrigation Division, Orissa
      & Ors. v. NC Budharaj (DJ by L.Rs. & Ors. 2001 (1)                 H
812           SUPREME COURT REPORTS                     [2016) 2 S.C.R.


A           SCR 264 :(2001) 2 SCC 721; Sayeed Ahmed & Co. "
            State of UP. & Ors. 2009 (10) SCR 841 : (2009) 12
            SCC 26; Sree Kamatchi Amman Constructions v.
            Divisional Railway Manager (Works}, Pa/ghat & Ors.
            2010 (10) SCR 487: (2010) 8 SCC 767; Raipur
            Development Authority & Ors. v. Mis. Chokhamal
B
            Contractors & Ors. 1989 (3) SCR 144: (1989) 2 SCC
            721; Executive Engineer (Irrigation) Balimela & Ors.
            " Abhaduta Jena & Ors. 1988 (1) SCR 253 : (1988)
            1 SCC 418; Nachiappa Chettiar & Ors, v. Subramaniam
            Chettiar AIR 1960 SC 307 :1960 SCR 209; Satinder
 c          Singh v. Amrao Singh & Anr. AIR 1961 SC 908 : 1961
            SCR 676 ; Firm Madan/al Roshanlal Mahajan v.
            Hukumchand Mills Ltd., Indore, AIR 1967 SC 1030 :
            1967 SCR 105; Union of India " Bungo Steel Furniture
            Pvt. Ltd. AIR 1967 SC 1032 : 1967 SCR 3_24; Ashok
            Construction Company v. Union of India (1971) 3 SCC
D
            66; State of MP" Mis. Saith and Skelton Pvt. Ltd. 1972
            (3) SCR 233 :(1972) l SCC 702; Hindustan
            Construction Co. Ltd. v. State of Jammu & Kashmir
            1992 (1) Suppl. SCR 297: (1992) 4 SCC 217; State of
            Orissa v. B.N. Agarwal/a, 1997 (1) SCR 704: (1997)
 E          2 SCC 469; State of UP. v. Harish Chandra & Co.
            1998 (2) Suppl. SCR 660 : (1999) 1 sec 63;
            Superintending Engineer v. B. Subba Reddy 1999 (2)
            SCR 880 : (1999) 4 SCC 423; State of Rajasthan &
            Anr. v. Ferro Concrete Construction (P) Ltd. 2009 (10)
            SCR 31 :(2009) 12 SCC 1; Union of India v. Bright
 F    .
            Power Projects (India) Pvt. Ltd. 2015 (6) SCR 488 :
            (2015) 9 SCC 695; Union of India v. Krafters
            Engineering & Leasing Pvt. Ltd. 2011 (8) SCR196 :
            (2011) 7 SCC 279; Tehri Hydro Development
            Corporation Limited and Another v. Jai Prakash
 G          Associates Limited 2012 (8) SCR 813 : (2012) 12 SCC
            10 - referred to.
                            Case Law Reference
          1995 (6) Suppl. SCR 327      referred to         Para 1
          2009 (16) SCR 216            referred to         Para 1
 H        1991 (3) Suppl. SCR 417      referred to         Para 1
     UNION OF INDIA v. MIS. AMBICA CONSTRUCTION                         813


  2001 (1) SCR 264                 referred to         Para 1            A
  2009 (10) SCR S41                referred to         Para 1
  2010 (10) SCR 4S7                referred to         Para 1
  19S9 (3) SCR 144                 referred to         Paras
  19SS (f) SCR 253                 referred to         Paras
                                                                         B
  1960 SCR 209                     referred to         Paras
   1961 SCR 676                    referred to         Paras
   1967 SCR 105                    referred to         Paras
   1967 SCR 324                    referred to         Paras
   (1971) 3 sec 66                 referred to         Paras             c
   1972 (3) SCR 233                referred to         Paras
   1992 (1) Suppl. SCR 297         referred to         Para 10
   1997 (1) SCR 704                referred to         Para 11
   199S (2) Suppl. SCR 660         referred to         Para 13
                                                                         D
  .1?99 (2) SCR SSO                referred to         Para 15
  ;?0\19 (10) SCR 31               referred to         Para 15
  7\115 (6) SCR 4SS                referred to         Para 16
  2!111 (S) SCR 196                referred to         Para lS
  2012 (S ) SCR S13                referred to         Para 22           E
     CIVIL APPELLATE JURISDICTION: Special Leaye to Appeal
(Civil) No. 11114 of2009.
    From the Judgment and Order dated 31.03.2008 passed"by the
High Court at Calcutta in A.P.O. No. 5 of 2008.
                                                                         F
                               WITH
     SLP (C) No. 17219 of2009.
     A.K. Panda, Sr. Adv., Ajay Singh~ Ranjeet Kumar, S.N. Terdal
(For Ms. Sushma Suri) Advs. with him for the Appellant.
    Raj Kumar Mehta, Abhishek Upadhyay, Ms. Himanshi Andley,             G
Advs. for the Respondent.
     The Judgment of the Court was delivered by
     ARUN MISHRA, J. I.The issue involved in the reference is in
regard to the power of the Arbitrator to award pendente lite interest
                                                                         H
814             SUPREME COURT REPORTS                            (2016] 2 S.C.R.


A     when contract contains bar for grant of interest in a case covered by the
      .Arbitration Act, 1940 (hereinafter referred to as "the Act"). A Division
      Bench of this Court had doubted the correctness of the decisions in
      Board of Trustees for the Port of Ca/cul/a v. Engineers-De-Space-
      Age ( 1996) I SCC 516; and Madnani Construction Corporation (PJ
      Ltd. v. U11ion of India and Others (20 I 0) I SCC 549. In view of the
B
      decision of the Constitution Bench judgment in Secrelary, Irrigution
       Department, Government of Grisso & Ors. v. G.C. Roy ( 1992) I SCC
      508 and Execulive Engi11ee1: Dlzenkanal Minor Irrigation Division,
       Grisso & Ors. v. N.C. Budlwraj (DJ by L.Rs. & Ors. (200 I) 2 SCC
       721 which held that the Arbitrator had the jurisdiction and authority to
c     award interest for pre-reference period, pe11de11te file and future period
       if there was no express bar in the contract regarding award of interest.
      A doubt was expressed about the correctness of the decision in
      Engineers-De-Space Age (supra) in Sayeed Ahmed & Co. v. State of
       UP. & Ors. (2009) 12 SCC 26 and Sree Kamatchi Amman
      Constructio11s v. Divisional Railway A1anager (Works), Pa/ghat &
D
       Ors. (20 I 0) 8 SCC 767. Hence the matter had been referred to a larger
       Bench for decision.
            2. Jhe case has a chequered history. The tender of M/s. Am bi ca
      Construction for fabrication of tie bars from M.S. Flats in CST-9 sleep-
      ers was accepted on 8.9.1989. Final agreement was executed on
 E    30.11.1989. The work was completed on 21.11.1990. With respect to
      payments, certain differences and disputes arose between the parties.
      Thus Mis. Ambica Construction prayed for appointment of an Arbitra-
      tor. On 5.3.1991 as the petitioner M/s. Ambica Constn1ction was in se-
      rious financial difficulties, it accepted the amount in full and final settle-
 F    ment. Later on, the Union of India informed the petitioner on 11.3.1991
      that the matter was under consideration. However the Arbitrator was
      not appointed. An application under section 20 of the Act was filed be-
      fore the High Court of Calcutta for referring the case to arbitration. On
      2.6.1992 the High Court directed to file the arbitration agreement in the
      court and appointed two Arbitrators in terms of the arbitration clause.
 G    Said Arbitrators failed to publish the award and as such an application
      was filed for revocation of the authority ofjoint Arbitrators and another
      sole Arbitrator was appointed. The sole Arbitrator ultimately published
      the award on 30.12.1997. On an application filed by the Union oflndia,
      the High Court vide order dated 9.4.1998 remitted the award to the
 H    Arbitrator to give an item-wise break-up. On 12.5.1998 the sole Arbitra-
     UNION OF INDIA v. MiS. AMBJCA CONSTRUCTION                              815
                  [ARUN MISHRA, J.]

tor published the item-wise award. Again the Union oflndia questioned         A
the same before the High Court. The award was set aside on the ground
that the Arbitrator had not given an intelligible award in terms of clause
64(3)(a)(iii) of the agreement and had not taken into effect the supple-
mentary agreement dated 5 .3. 1991. The appeal preferred by the peti-
tioner was dismissed by the Division Bench of the High Court on
                                                                              B
15.10.2004 against which an SLP was filed in which leave was granted
and ultimately C.A. No.6621i2005 was allowed and case was remitted
vide order dated 7.11.2005 passed by this Court to the Arbitrator for
assigning reasons and to pass fresh award. Thereafter, Arbitrator passed
a fresh award on 11.2.2006. Again an application was filed by the Union
of India under sections 30 and 33 of the Act. The Single Judge dis-           c
missed the application vide order dated 26.6.2007. Union oflndia filed
an application for recall. The order dated 26.6.2007 was recalled. Yide
order dated 22.8.2007 learned Single Judge set aside the award with
regard to interest for pre-reference period and directed that interest
would be allowed on the principal sum of Rs.9,82,660i- at the rate of
                                                                              D
 10% per annum from 1.9.1992 the date from which the original Arbitra-
tor entered upon the reference. An appeal was preferred before the
Division Bench and the same had been paiily allowed with regard to
claim Nos.6 and 7. Aggrieved thereby, Mis. Ambica Construction had
preferred S.L.P. [CJ No.17219i2009 in this Court and Union of India
has also assailed the judgment and order of the High Court in S.L.P. [CJ      E
No.11114i2009.
     3. The only question for consideration is whether an Arbitrator has
the power to award pendente lite interest in case contract bars the
same in a case covered by Act and decisions of this Court in Engineers
De-Space Age (supra) and Madnani Co11structio11 Corporation (I')              F
Ltd. (supra) have been correctly decided.
      4. !twas submitted on behalfofthe Union oflndia thattheArbitrator
is bound by the terms of the contract and cannot award interest in case
the contract bars the same. On the other hand, learned counsel appearing
on behalf of Mis. Ambica Construction has contended that in view of           G
the decision in E11gi11eers-De-Space Age (supra) followed in Madnani
Constructio11 Corporation {P) Ltd. (supra) notwithstanding the terms
in the contract agreement barring the award of interest would cover the
pre-reference period and not pendente lite interest.
     5. There are certain provisions which are statutorily implied in
                                                                              H
816            SUPREME COURT REPORTS                           [2016) 2 S.C.R.


A     arbitration agreement unless excluded in the agreement. Section 3 of
      the Act of 1940 deals with the provisions which are implied in the
      arbitration agreement. Section 3 is extracted below :
              "3. Provisions implied in arbitration agreement.-An
            arbitration agreement, unless a different intention is expressed
B           therein, shall be deemed to include the provisions set out in the
            First Schedule in so far as they are applicable to the reference."
            The provisions of section 3 make it clear that unless a different
      intention is expressed in the arbitration agreement, the agreement would
      include the provisions contained in the First Schedule so far as they are
c     applicable to the reference. Provisions in the First Schedule contain 8
      paragraphs. It provides for reference to a sole Arbitrator and in case
      there are even numbers of Arbitrators, appointment of umpire is also
      provided. An Arbitrator is required to pass award within 4 months fr~m
      the date of entering on the reference. Jn case Arbitrator fai Is to pass an
      award within the specified time the umpire shall make the award within
D     2 months. Para 6 of First Schedule provides that the Arbitrator or umpire
      shall examine the matters in difference and the award shall be final and
      binding. Arbitrator or umpire has the power for examining the witnesses
      and production of relevant documents. Para 8 of Schedule I provides for
      costs ofreference and awards shall be in the discretion of the Arbitrator.
 E          6. "Court" has been defined in section 2(c) of the Act to mean a
      civil court havingjurisdiction to decide the questions fonningthe subject-
      matter of the reference. Section 41 of the Act is extracted hereunder:
             "41. Procedure and powers of Court. -Subject to the provisions
             of this Act and of rules made thereunder :
 F
            (a) The provisions of the Code of Civil Procedure, I 908 (5 of
                 I 908), shall apply to all proceedings before the Court, and to
                all appeals, under this Act, and
            (b) The Court shall have, for the purpose of, and in relation to
                arbitration proceedings, the same power of making orders in
 G
                respect of any of the matters set out in the Second Schedule
                as it has for the purpose of, and in relation to any proceedings
                before the Court:
             Provided that nothing in CI. (b) shall be taken to prejudice any
             power which may be vested in an Arbitrator or umpire for making
 H
      UNION OF !NOIA v. ~/S. AMBICA CONSTRUCTION                               817
                   [ARUN MISHRA, J.]

      orders with respect to any of such matters."                              A
     The court can exercise the power specified in Second Schedule of
the Act. However, Arbitrator is not a court. Arbitrator is the outcome of
agreement. He decides the disputes as per the agreement entered into
between the parties.Arbitration is an alternative forum for resolution of
disputes but an Arbitrator ipso facto does not enjoy or possess all the         B
powers conferred on the courts of law.
     7. Section 29 of the Act confers on the court power to award interest
from the date of decree. Section 34 of the C.P.C. confers on the court
power to award interest prior to the institution of the suit and during
pendency of the suit and post decree.                                           c
      8. A Constitution Bench of this Court in GC. Roy (supra) has
considered the question of power of the Arbitrator to award pendente
lite interest and it has been laid down that if the arbitration agreement or
the contract itself provides for interest, Arbitrator would have the
jurisdiction to award the interest. Similarly, where the agreement              D
expressly provides that no interest pendente lite shall be payable'on the
amount due, the Arbitrator has no power to award pendente lite interest.
In GC. Roy (supra) this Court has held thus:
       "xxx If the arbitration agreement or the contract itself provides
       for award of interest on the amount found due from one party to          E
       the other, no question regarding the absence of Arbitrator's
       jurisdiction to award the interest could arise as in that case the
       Arbitrator has power to award interest pendent lite as well.
       Similarly, where the agreement expressly provides that no interest
       pendente lite shall be payable on the amount due, the Arbitrator
       has no power to award pendente lite interest. But where the              F
       agreement does not provide either for grant or denial of interest
       on the amount found due, the question arises whether in such an
       event the Arbitrator has power and authority to grant pendente
       lite interest."
     The question involved in GC. Roy (supra) was with respect to the           G
award of interest for the period commencing from the date of Arbitrator
entering upon the reference till the date of making the award. In GC.
Roy (supra), this Court has considered decisions in Raipur Development
Authority & Ors. v: Mis. Chokhamal Contractors & Ors., (1989) 2
SCC 721; Executive Engineer (Irrigation) Balimela & Ors. v.
                                                                                H
818            SUPREME COURT REPORTS                          [2016] 2 S.C.R.


A     Abhaduta Jena & Ors .. (1988) 1 SCC ./18; Nachiappa Chettiw· &
      Ors, v. Subramaniam Chettia~ AIR 1960 SC 307; Satinder Singh v.
      Amrao Singh & Am:, AIR 1961 SC 908; Firm Madan/a/ Roshanla/
      Mahajan v. Hukumchand Mills Ltd.. illdore, AIR 1967 SC 1030;
      Union of India v. Bungo Steel Furniture Pvt. Ltd., AIR 1967 SC
      1032; Asl10k Construction Company v. Union of India, (1971) 3
 B
      SCC 66; State of MP v. Mis. Saith and Skelton Pvt. Ltd., (1972) 1
      SCC 702, various foreign coutts decisions and decisions of the High
      Court. This Court has also referred to Halsbury's Laws of England in
      Paras 36 & 3 7 thus:-
            "36. "534. Express and implied clauses.- In general, the parties
 c          to an arbitration agreement may include in it such clauses as they
            think fit. By statute, however, certain terms are implied in an
            arbitration agreement unless a contrary intention is expressed or
            implied therein. Moreover, it is normally an implied term of an
            arbitration agreement that the Arbitrator must decide the dispute
 D          in accordance with the ordinary law. This includes the basic rules
            as to procedure, although parties can expressly or impliedly consent
            to depart from those rules. The normal principles on which terms
            are implied in an agreement have to be considered in th~ context
            that the agreement relates to an arbitration."

 E          37. At page 303, para 580 (4th edn., Vol. 2) dealing with the
            award of interest, it reads:
            "580. /111erest.- A Arbitrator or umpire has power to award
            interest on the amount of any debt or damages for the whole or
            any part of the period between the date when the cause of action
 F          arose and the date of the award."
           Ultimately, in GC. Roy (supra), this Comt has answered the question
      whether Arbitrator has the power to award interest pendent lite. Their
      Lordships have reiterated that they have dealt with the situation where
      the agreement does not provide for grant of such interest nor does it
      prohibit such grant when the agreement is silent as to award of interest.
 G
      This Court has laid down various principles in para 43 of the report thus:
            "43. The question still remains whether Arbitrator has the power
            to award interest pende111e lite, and if so on what principle. We
            must reiterate that we are dealing with the situation where the
            agreement does not provide for grant of such interest nor does it
 H
UNION OF INDIA v. MIS. AMBlCA CONSTRUCTION                              819
             fARUN MISHRA, J.l

prohibit such grant. In other words, we are dealing with a case          A
where the agreement is silent as to award of interest. On a
conspectus of aforementioned decisions, the following principles
emerge:
(i)A person deprived of the use of money to which he is legitimately
entitled has a right to be compensated for the deprivation, call it      B
by any name. It may be called interest, compensation or damages.
This basic consideration is as valid for the period the dispute is
pending before the Arbitrator as it is for the period prior to the
Arbitrator entering upon the reference. This is the principle of
Section 34, Civil Procedure Code and there is no reason or principle
to hold otherwise in the case of Arbitrator.
                                                                         c
(ii) An Arbitrator is an alternative form (sic forum) for resolution
of disputes arising between the parties. If so, he must have the
power to decide all the disputes or differences arising between
the parties. If the Arbitrator has no power to award interest
pendente lite, the party claiming it would have to approach the          D
court for that purpose, even though he may have obtained
satisfaction in respect of other claims from the Arbitrator. This
would lead to multiplicity of proceedings.
(iii) An Arbitrator is the creature of an agreement. It is open to
the parties to confer upon him such powers and prescribe such            E
procedure for him to follow, as they think fit, so long as they are
not opposed to law. (The proviso to Section 41 and Section 3 of
Arbitration Act illustrate this point). All the same, the agreement
must be in conformity with law. The Arbitrator must also act and
make his award in accordance with the general law of the land             F
and the agreement.
(iv) Over the years, the English and Indian cou1ts have acted on
the assumption that where the agreement does not prohibit and a
paity to the reference makes a claim for interest, the Arbitrator
must have the power to award interest pendente lite. Seth                G
Thawardas· Pherwnal v. Union of India, AIR 1955 SC 468 has
not been followed in the later decisions of this Court. It has been
explained and distinguished on the basis that in that case there
was no claim for interest but only a claim for unliquidated damages.
ft has been said re·; •eatcdly that observations in the said judgment
                                                                          H
820            SUPREME COURT REPORTS                           [2016] 2 S.C.R.


A           were not intended to lay down any such absolute or universal rule
            as they appear to, on first impression. Until Executive Engineer
            (Irrigation) Ba/imela & Ors. v. Abhaduta Jena.& Ors., (1988)
            I SCC 418 almost all the courts in the country had upheld the
            power of the Arbitrator to award interest pendeme lite. Continuity
            and certainty is a highly desirable feature of law.
B
            (v) Interest pendeme lite is not a matter of substantive law, like
            interest for the period anterior to reference (pre-reference period).
            For doing complete justice between the parties, such power has
            always been inferred."

 c          "44. Having regard to the above consideration. we think that the
            following is the correct principle which should be followed in this
            behalf:
            Where the agreement between the parties does not prohibit grant
            of interest and where a party claims interest and that dispute
 D          (along with the claim for principal amount or independently) is
            referred to the Arbitrator, he shall have the power to award interest
            pendente lite. This is for the reason that in such a case it must be
            presumed that interest was an implied term of the agreement
            between the parties and therefore when the parties refer all their
            disputes - or refer the dispute as to interest as such - to the
 E          Arbitrator, he shall have the power to award interest. This does
            not mean that in every case the Arbitrator should necessarily award
            interest pendente lite. It is a matter within his discretion to be
            exercised in the light of all the facts and circumstances of the
            case, keeping the ends of justice in view."
 F         The Constitution Bench of this Court has laid down that where the
      agreement between the parties does not prohibit grant of interest and
      where the party claims interest and that dispute is referred to the
      Arbitrator, he shall have the power to award interest pendent lite. The
      law declared has been held applicable prospectively.
 G         9. Another Constitution Bench of this Court in N.C. Budharaj
      (supra), considered the question of award of interest by the Arbitrator
      for the pre-reference period. In that connection, discussion has been
      made and it has been observed as long as there is nothing in the arbitration
      agreement to exclude the jurisdiction of the Arbitrator entertaining claim
      for interest on the amount due under the contract or any provision to
 H
      UNION OF INDIA v. MIS. AMBICA CONSTRUCTION                               821
                   [ARUN MISHRA, J.]

claim interest on the amount due, the jurisdiction of the Arbitrator to         A
award interest for pre-reference perio:I under section 29 of the Arbitration
Act, 1940 has to be upheld. 111 m<1jority opinion, this Court has held thus:
      "25. If that be the position, courts which oflate encourage litigants
      to opt for and avail of the alternative method of resolution of
      disputes, would be penalising or placing those who avail of the           B
      same in a serious disadvantage. Both logic and reason should
      counsel courts to lean more in favour of the Arbitrator holding to
      possess all the powers as are necessary to do complete and full
      justice between the parties in the same manner in which the civil
      court seized of the same dispute could have done. By agreeing to
      settle all the disputes and claims arising out of or relating to the
                                                                                c
      contract between the parties through arbitration instead of having
      recourse to civil court to vindicate their rights the party concerned
      cannot be considered to have frittered away and given up any
      claim which otherwise it could have succe~sfully asserted before
      courts and obtained relief. By agreeing to have settlement of             D
      disputes through arbirration, the party concerned must be
      understood to have only opted for a different forum ofadjudication
      with less cumbersome procedure, delay and expense and not to
      abandon all or any of its substantive rights under the various laws
      in force, according to which only even the Arbitrator is obliged to
      adjudicate the clajms referred to him. As long as there is nothing        E
      in the arbitration agreement to exclude the jurisdiction of the
      Arbitrator to entertain a claim for interest on the amounts due
      under the contract, or any prohibition to claim interest on the
      amounts due and become payable t.nder the contract, the
      furisdiction of the Arbitrator to consider and award interest in          F
      respect of all periods subject only to Section 29 of the Arbitration
      Act, 1940 al).d that too the powers of the court thereunder, has to
      be upheld. The submission. that the Arbitrator cannot have
      jurisdiction to award interest for the period prior to the date of his
      appointment or entering into reference which alone confers upon
      him power, is too stale and technical to be countenanced in our           G
      hands, for the simple reason that in every case the appointment of
      an Arbitrator or even resort to court to vindicate rights could be
      only after disputes have cropped up between the parties and
    • continue to·su!isist unresolved, and that ifthe Arbitrator has the
      power to deal with and decide disputes v.hich cropped up at a             H
822             SUPREME COURT REPORTS                           (2016] 2 S.C.R.



A            point of time and for the period prior to the appointment of an
             Arbitrator, it is beyond comprehension as to why and for what
             reason and with what justification the Arbitrator should be denied
             only the power to award interest for the pre-reference period
             when such interest becomes payable and has to be awarded as
             an accessory or incidental to the sum awarded as due and payable,
 B
             taking into account the deprivation of the use of such sum to the
             person lawfully entitled to the same.
             26. For all the reasons stated above, we answer the reference by
             holding that the Arbitrator appointed with or without the
             intervention of the court, has jurisdiction to award interest, on the
 c           sums found due and payable, for the pre-reference period, in the
             absence of any specific stipulation or prohibition in the contract to
             claim or grant any such interest. The decision in Je11a case taking
             a contraview does not lay down the correct position and stands
             overruled, prospectively, which means that this decision shall not
 D           entitle any party nor shall it empower any court to reopen
             proceedings which have already become final, and apply only to
             any pending proceedings. No costs."
             It has also been observed that GC. Roy's case (supra) cannot be
       said to have overruled Executive E11gineer (Irrigation) Balimela's case
 E     (supra) insofar as it dealt with the power of Arbitrator to award interest
       for the pre-reference period.
            I 0. A 3 Judges Bench of this Court in Hi11dusta11 Cons/ruction
       Co. Ltd. v. State of Ja111111u & Kashmir (1992) ./ SCC 217 has laid
       down that the Arbitrator has the power to award pe11dente file interest
 F     on the basis of principle of Section 34 of the Code of Civil Procedure
       though same is not applicable. However, the observation has to be
       considered in case there is no express bar in the agreement for awarding
       pendente lite interest as it has simply followed what has been laid down
       in GC. Roy (supra). This Court has laid down thus:

 G           "5. The question of interest can be easily disposed of as it is
             covered by recent decisions of this Court. It is sufficient to refer
             to the latest decision of a five Judge bench of this Court in
             Secretary, lrrigatio11 Departme/lf, Govt. of Orissa & Ors. v.
             GC. Roy. Though the said decision deals with the power of the
             Arbitrator to award interest pell(/e111e lite, the principle of the
 1-1         decision makes it clear that the Arbitrator is competent to award
     UNION OF INDIA v. MIS. AMBICA CONSTRUCTION                               823
                  [ARUN MISHRA, J.]

      interest for the period commencing with the date of award to the         A
      date of decree or date of realisation, whichever is earlier. This is
      also quite logical for, while award of interest for the period prior
      to an Arbitrator entering upon the reference is a matter of
      substantive law. 1' "' grant of interest for the post-award period is
      a matter of procedure. Section 34 of Code of Civil Procedure
                                                                               B
      provides both for awarding of interest pendente lite as well as
      for the post-decree period and the principle of Section 34 has
      been held applicable to proceedings before the Arbitrator, though
      the section as such may not apply. In this connection, the decision
      in Union of India v. Bungo Steel Furniture (PJ Ltd. AIR 1967
      SC 1032 may be seen as also the decision in Gujarat Water                c
      Supply & Sewerage Board v. Unique Erectors (Gujarat) P.
      Ltd. /9891 532 SCC which upholds the said power though on
      a somewhat different reasoning. We, therefore, think that the
      award on Item No. 8 should have been upheld."
      I I.In Sayeed Ahmed (supra) various decisions of this Court have         D
been referred. In State of Orissa 1( B.N. Agarwal/a, (1997) 2 SCC
469, this Court has laid down thus:
      "18. In vie\v of the aforesaid decisions there can now be no doubt
      with regard to the jurisdiction of the Arbitrator to grant interest.
      The principles which can now be said to be well-settled are that         E
      the Arbitrator has the jurisdiction to award pre-reference interest
      in cases which arose after the Interest Act, 1978 had become
      applicable. With regard to those cases pertaining to the period
      prior to the applicability of the Interest Act, I 978, in the absence
      of any substantive law, contract or usage, the Arbitrator has no
      jurisdiction to award interest. For the period during which the          F
      arbitration proceedings were pending in view of the decision in
      GC. Roy case and Hindustan Constrnction Ltd. case, the
      Arbitrator has the power to award interest. The power of the
      Arbitrator to award interest for the post-award period also exists
      and this aspect has been considered in the discussion relating to        G
      Civil Appea!No. 9234of1994 in the later part of this judgment."
     12. The decision in B.N. Agarwal/a (supra) has been considered
and distinguished 'by this Court in Sayeed Ahmed (supra) thus:
      "20. The appellant next relied upon the judgment of this Court in
      State of Orissa v. B.N. Aga111•a/la (1997) 2 SCC 469. In that            H
824            SUPREME COURT REPORTS                            [2016] 2 S.C.R.


A           case, this Court held that the Arbitrator has jurisdiction to award:
            (i) interest for pre-reference period, (ii) interest for pendente lite,
            and (iii) future interest. This Court also held that the following
            part of Clause (4) of the contract dealing with "Rates, materials
            and workmanship" did not bar award of interest by the Arbitrator
            on the claims of the contractor: (SCC p. 478, para 22)
B
               No interest is payable on amount withheld under the item of
               the agreement.
            Interpreting the said clause (which provided that interest was not
            payable on the amount which was withheld), this Court held that
c           it referred only to the amount withheld by the employer State
            towards retention money for the defect liability period. This Court
            in fact clarified the position that ifthe terms of contract expressly
            stipulated that no interest would be payable, then the Arbitrator
            would not get the jurisdiction to award interest. As Clause G 1.09
            in the present case contains an express bar and is different from
D           the clause considered in B.N. Aganl'alla (supra) the said decision
            is also of no assistance."
            In B.N. Aganmlla (supra) this Court has observed that Clause 4
      of the contract dealing with "Rates, materials and workmanship" did not
      bar award of interest by the Arbitrator on the claims of the contractor.
 E    The stipulation was no interest was payable on amount withheld under
      the agreement.
            13. In Sayeed Ahmed (supra), this Court has referred the decision
      in State of U.P. v. Harish Chandra & Co. (1999) I SCC 63, in which
      this Court has interpreted the stipulation contained in clause 1.9 of the
 F    agreement which came up for consideration before a 3 Judges Bench of
      this Court. Clause 1.9 is extracted hereunder:
             "1.9 No claim for delayed payment due to dispute etc.-No
            claim for interest or damages will be entertained by the
            Government with respect to any moneys or balances which may
 G          be lying with the Government owing to any dispute, difference; or
            misunderstanding between the Engineer-in-Charge in marking
            periodical or final payments or in any other respect whatsoever."
            This Court has interpreted the clause 1.9 and held that there is no
      provision which could be culled out against tl1e respondent-contractor
 H    that he could not raise claim of interest by way of damages before the
      UNION OF INDIA v. MIS. AMBICA CONSTRUCTION                                825
                   fARUN MISHRA, J.]

Arbitrator on the relevant items placed for adjudication.                        A
     This Court in Sayeed Ahmed (supra) has also distinguished the
decision in Harish Chandra (supra) in which clause .1.09 came up for
consideration thus:
      "17. xx xx x This Court held that the said clause did not bar
      award of interest on any claim for damages or for claim for                B
      payment for work done. We extract below the reasoning for such
      decision: (SCC p. 67, para I 0)
          "JO. A mere look at the clause shows that the claim for interest
          by way of damages was not to be entertained against the
          Government with respect to only a specified type of amount,            c
          namely, any moneys or balances which may be lying with the
          Government owing to any dispute, difference between the
          Engineer-in-Charge and the contractor; or misunderstanding
          between the Engineer-in-Charge and the contractor in making
          periodical or final payments or in any other respect whatsoever.       D
          The words 'or in any other respect whatsoever' also referred
          to the dispute pertaining to the moneys or balances which may
          be lying with the Government pursuant to the agreement
          meaning thereby security deposit or retention money or any
          other amount which might have been with the Government
          and refund of which might have been withheld by the                    E
          Government. The claim for damages or claim for payment
         ·for the work done and which was not paid for would not
          obviously cover ony money which may be said to be lying
          with the Government. Consequently, on the express language
          of this clause, there is no prohibition which could be culled out      F
          against the respondent contractor that he could not raise the
          claim for interest by way of damages before the Arbitrator on
          the relevant items placed for adjudication."
                                                       (emphasis supplied)
          18. In Harish Chandra ( 1999) I SCC 63 a different version             G
            of Clause 1.09 was considered. Having regard to the restrictive
          . wording of that clause, this Court held that it did not bar award
            of interest on a claim for damages or a claim for payments for
        .. work done aiid which was not paid. This Court held that the
           said cliiuse barred award of interest only on amounts which
                                                                                 H
826            SUPREME COURT REPORTS                             [2016] 2 S.C.R.



A              may be lying with the Government by way of security deposit/
               retention money or any other amount, refund of which was
               withheld by the Government.
               19. But in the present case, Clause G 1.09 is significantly
               different. It specifically provides that no interest shall be payable
 B             in respect of any money that may become due owing to any
               dispute, difference or misunderstanding between the Engineer-
               in-Charge and contractor or with respect to any delay on the
               part of the Engineer-in-Charge in making periodical or final
               payment or in respect of any other respect whatsoever. The
               bar under Clause G 1.09 in this case being absolute, the decision
 c             in Harish Chandra (supra) will not assist the appellant in any
               manner."
           In Harish Chandra (supra), this Court has laid down that clause
      1.09 did not bar award of interest for claim of damages for payment for
      work done and which was not paid for would not obviously cover any
 D    money which may be said to be lying with the Government.
           14. In our opinion, it would depend upon the nature of the ouster
      clause in each case. In case there is express stipulation which debars
      pendente lite interest, obviously, it cannot be granted by Arbitrator. The
      award of pendente lite interest inter a/ia must depend upon the overall
 E    intention of the agreement and what is expressly excluded.
           15. In Sayeed Ahmed (supra), this Court has referred the decision
      in Superintending Engineer v. B. Subba Reddy ( 1999) 4 SCC 423
      and observed thus :
            "11. Two more decisions dealing with cases arising under the
 F
            Arbitration Act, 1940 require to be noticed. In Superintending
            Engineer v. B. Subba Reddy ( 1999) 4 SCC 423 this Court held
             that interest for pre-reference period can be awarded only ifthere
             was an agreement to that effect or if it was allowable under the
             Interest Act, 1978. Therefore, claim for interest for pre-reference
 G           period, which is barred as per the agreement or under the Interest
             Act, 1978 could not be allowed. This Court however held that the
             Arbitrator can award interest pendente lite and future interest."
           In Sayeed Ahmed (supra) this Court has also referred the decision
      in State of Rajasthan & Anr. v. Ferro Concrete Construction (PJ Ltd.
 H    (2009) 12 sec 1 thus :
     UNION OF INDIA v. MIS. AMBICA CONSTRUCTION                                 827
                  fARUN MISHRA, J.l

      "12. The principles relating to interest were summarised by this           A
      Court in State of Rajasthan v. Ferro Concrete Construction
      (P) Ltd. (2009) 12 sec 1 thus:
      (a) Where a provision for interest is made on any debt or damages,
      in any agreement, interest shall be paid in accordance with such
      agreement.                                                                 B
      ( b) Where payment of interest on any debt or damages is barred
      by express provision in the contract, no interest shal I be awarded.
      (c) Where there is no expre~s bar in the contract and where there
      is also no provision for payment of interest then the principles of
      Section 3 of the Interest Act will apply and consequently interest         c
      will be payable:
      (i) where the proceedings relate to a debt (ascertained sum)
      payable by virtue of a written instrument at a certain time, then
      from the date when the debt is payable to the date of institution of
      the proceedings;                                                           D

      (ii) where the proceedings is for recovery of damages or for
      recovery of a debt which is not payable at a certain time, then
      from the date mentioned in a written notice given by the person
      making a claim to the person liable for the claim that interest will
      be claimed.                                                                 E

      (d) Payment of interest pendente lite and future interest shall not
      be governed by the provisions of the Interest Act, 1978, but by the
      provisions of Section 34 of the Code of Civil Procedure, 1908 or
      the provisions of law governing arbitration as the case may be."
                                                                                  F
    In Sayeed Ahmed (supra), the provisions of Arbitration &
Conciliation Act, 1996 were applicable.
    16. A 3-Judge Bench of this Court in Union of India v. Bri>I,ht
Power Projects (India) Pvt. Ltd. (20°15) 9 SCC 695 h~s considered the
provisions contained in section 31 (7)(a) of the Arbitration and Conciliation
Act, 1996 and considered the words "unless otherwise agreed by parties"          G
in the said section and held that the Arbitrator is bound by the terms of
the contract so far as award of interest from the date of execution to the
date of award is concerned. This Court considered clause 13(3) of the
contract and came to the conclusion that once agreed that contractor
would not claim any interest on the amount to be paid under the contract,         H
828            SUPREME COURT REPORTS                           (2016] 2 S.C.R.


A     he could not have claimed the interest. The Arbitrator while awarding
      interest failed to consider the provisions of section 31 (7)(a) and binding
      nature of clause 13(3) of the terms of agreement. With respect to section
      31 (7)(a) of the Arbitration & Conciliation Act, 1996 this Court in Union
      of India v. Bright Power Projects (supra) has observed thus :
B           "18. Section 31(7)(a) of the Act ought to have been read and
            interpreted by the Arbitral Tribunal before taking any decision
            with regard to awarding interest. The said section, which has been
            reproduced hereinabove, gives more respect to the agreement
            entered into between the parties. If the parties to the agreement
            agree not to pay interest to each other, the Arbitral Tribunal has
c           no right to award interest pendente li!e ."
            Section 31(7)(a) of the 1996 Act confers power on Arbitrator to
      award interest pendente lite, "unless otherwise agreed by parties''. Thus,
      it is clear from the provisions contained in section 31 (7)(a) that the
      contract between the parties has been given importance and is binding
D     on the Arbitrator. Arbitration clause is also required to be looked into
      while deciding the power of the Arbitrator and in case there is any bar
      contained in the contract on award of interest, it operates on which
      items and in the arbitration clause what are the powers conferred on
      Arbitrator and whether bar on award of interest has been confined to
 E    certain period or it relates to pendency of proceedings before Arbitrator.
            17. In Sree Kamatchi A111111a11 Constructions (supra), it was
      observed that the words "unless otherwise agreed by the parties" in
      section 31 of new Act of 1996 clarify that Arbitrator i~ bound by the
      terms of contract for award of interest pendente lite. It was also held
 F    thus:
            "19. Section 31 (7) of the new Act by using the words "unless
            otherwise aweed by the parties" categorically clarifies that the
            Arbitrator is bound by the terms of the contract insofar as the
            award of interest fiwn the date of cause of action to the date
            ofaward. Therefore, where the parties had agreed that no interest
G
            shall be payable, the Arbitral Tribunal cannot award interest
            between the date when the cause of action arose to the date of
            award.
             20. We are of the view that the decisions in Engineers-De-Space-
             Age (supra) and Madnani (supra) are inapplicable for yet another
 H
     UNION OF INDIA v. M/S. AMBICA CONSTRUCTION                                    829
                  [ARUN MISHRA, J.]

      reason. In Engineers-De-Space-Age (supra) and Madnani                         A
      (supra) the Arbitrator had awarded interest for the pendente lite
      period. This Court upheld the award of such interest under the old
      Act on the ground that the Arbitrator had the discretion to decide
      whether interest should be awarded or not during the pendente
      lite period and he was not bound by the contractual terms insofar
                                                                                    B
      as the interest for the pendente lite period. But in the instant case
      the Arbitral Tribunal has refused to award interest for the pendente
      lite period. Where theArbitral Tribunal has exercised its discretion
      and refused award of interest for the period pendente lite, even if
      the principles in those two cases were applicable, the award of
      the Arbitrator could not be interfered with. On this ground also              c
      the decisions in Engineers-De-Space-Age (supra) and Mad11a11i
      (supra) are inapplicable. Be that as it may."
     18. This Court in Unio11 of India v. Krafters Engineering &
Leasing Pvt. Ltd. (2011) 7 SCC 279 has held that by a provision in the
agreement, the jurisdiction of the Arbitrator to award interest can be              D
excluded. This Court considered the nature of the claim vis-a-vis the
provision contained in the relevant clause.
      19. It is apparent from various decisions referred to above that in
GC. Roy (supra) Constitution Bench of this Coutt has laid down where
agreement expressly provides that no interest pendente lite shall be                E
payable on amount due. The arbitrator has no power to award interest.
In N.C. Budharaj (supra) a Constitution Bench has observed that in
case there is nothing in the arbitration agreement to exclude jurisdiction
of arbitrator to entertaining claim for interest, the jurisdiction of arbitrator
to consider and award interest in respect to all periods is subject to
section 29 of the Act. I_n Hi11dusta11 Co11structio11 Co. Ltd. (supra) this         F
Court has followed decision in GC. Roy (supra) and laid down that on
the basis of principles of section 34 arbitrator would have the power to
award pendente lite interest also. In B.N. Agarwal/a (supra), this Court
has again followed GC. Roy (supra) and Hi11dusta11 Co11structio11 Co.
Ltd. (supra) with respect to power of arbitrator to award pende/1/e lite            G
 interest and it was held that arbitrator has power to award interest. In
Harish Chandra (supra) this Court interpreted the clause 1.9 which
provided that no claim for interest or damages will be entertained by the
Government in respect to any mon·eys or balances which may be lying
with the Government. It was held that there was no provision which
could be culled out against the contractor not to claim interest by way of          H
830             SUPREME COURT REPORTS                           [2016] 2 S.C.R.



A     damages before the arbitrator on the relevant items placed for
      adjudication. In Ferro Concrete Construction (PJ Ltd. (supra) this Court
      considered clause 4 containing a stipulation that no interest was payable
      on amount withheld under the agreement. It was held that clause 4 dealt
      with rates, material and workmanship did not bar award of interest by
      the arbitrator on claims of the contractor made in the said case. In Sayeed
 B
      Ahmed (supra) this Court has emphasized that award of interest would
      depend upon nature of the clause in the agreement. In Bright Power
      Projects (India) Pvt. Ltd. (supra) this Court has considered the
      expression "unless otherwise agreed by parties" employed in section
      31(7)(a) of the Act of 1996 and laid down that in case contract bars
c     claim of interest contractor could not have claimed interest. The provision
      of section 31 (7)(a) of the Act of 1996 is binding upon the arbitrator. In
      Sree Kamatchi Amman Constructions (supra) similar view has been
      taken.
           20. Now we come to the question of correctness of decision of this
D     Court rendered by a Bench of two Judges in Engineers-De-Space-
      Age (supra) which has been referred for our consideration in which this
      Court after consideration of GC. Roy's case has observed thus:
             "3 ..... It will appear from what the Constitution Bench stated to
             be the legal position, that ordinarily a person who is deprived of
 E           his money to which he is legitimately entitled as ofright is entitled
             to be compensated in deprivation thereof, call it by whatever name.
             This would be in terms of the principle laid down in Section 34 of
             the Code of Civil Procedure. Their Lordships pointed out that
             there was no reason or principle to hold otherwise in the case of
             an Arbitrator. Pointing out that Arbitrator is an alternative forum
 F           for resolution of disputes arising between the parties, it said that
             he must have the power to decide all disputes and differences
             arising between the parties and ifhe were to be denied the power
             to award interest pendente lite, the party entitled thereto would
             be required to go to a court which would result in multiplicity of
 G           proceedings, a situation which the court should endeavour to avoid.
             Reliance was, however, placed on the observation in sub-para
             (iii) wherein it is pointed out that an Arbitrator is a creature of an
             agreement and if the agreement between the parties prohibits the
             payment of interest pe11de11te lite the Arbitrator must act in
             accordance therewith. In other words, according to their Lordships
 H           the Arbitrator is expected to act and make his award in accordance
     UNION OF INDIA v. MIS. AMBICA CONSTRUCTION                               831
                  [ARUN MISHRA, J.]

      with the general law of the land but subject to an agreement,            A
      provided, the agreement is valid and legal. Lastly, it was pointed
      out that interest pendente lite is not a matter of substantive law,
      like interest for the period anterior to reference. Their Lordships
      concluded that where the agreement between the parties does
      not prohibit grant of interest and where a party claims interest
                                                                               B
      and that dispute is referred to the Arbitrator, he shall have the
      power to award interest pendenle lite for the simple reason that
      in such a case it is presumed that interest was an implied term of
      the agreement between the parties; it is then a matter of exercise
      of discretion by the Arbitrator. The position in law has, therefore,
      been clearly stated in the aforesaid decision of the Constitution        c
      Bench".
      4. We are not dealing with a case in regard to award of interest
      for the period prior to the reference. We are dealing with a case
      in regard to award of interest by the Arbitrator post reference.
      The short question, therefore, is whether in view of sub-clause          D
      (g) of clause 13 of the contract extracted earlier the Arbitrator
      was prohibited from granting interest under the contract. Now
      the term in sub-clause (g) merely prohibits the Commissioner from
      entertaining any claim for interest and does not prohibit the
      Arbitrator from awarding interest. The opening words "no claim
                                                                                E
      for interest will be entertained by the Commissioner" clearly
      establishes that the intention was to prohibit the Commissioner
      from granting interest on account of delayed payment to the
      contractor. Clause has to be strictly construed for the simple reason
      that as pointed out by the Constitution Bench, ordinarily, a person
      who has a legitimate claim is entitled to payment within a reasonable     F
      time and ifthe payment has been delayed beyond reasonable time
      he can legitimately claim to be compensated for that delay
      whatever nomenclature one may give to his claim in that behalf."
     21. In Sayeed Ahmed (supra) the decision in Engineers-De-Space-
Age (supra) has been considered and it was observed that it cannot be           G
used to support an outlandish argument that bar on the Government or
department paying interest is not a baron the Arbitrator awarding interest.
This Court expressed doubt as to the correctness of certain observations
made in Engineers-De-Space-Age (supra) to the extent that the
Arbitrator could award interest pendente lite ignoring the express bar
in the contract. But this Court did not consider the question further as        H
832             SUPREME COURT REPORTS                          [2016] 2 S.C.R.


A     the case in Sayeed Ahmed (supra) arose under the Arbitration and
      Conciliation Act of 1996, and there was a specific provision undernew
      Act regarding award of interest by the Arbitrator. From the discussion
      made in Sayeed Ahmed (supra) it is apparent that this Court has
      emphasized that it would depend upon the nature of clause and claim
      etc. and it is required to be found on consideration of stipulation whether
B
      interest is barred, if yes, on what amounts interest is barred under the
      contract.
         22. A three-Judge Bench of this Court in Tehri Hrdro Development
   Corporation Limited and Another v. Jai Prakash Associates Limited,
 c (2012)  12 SCC I 0, has considered the question which has been referred
   in the instant case and it has been laid down in the context of clauses
   1.2.14 and 1.2.15 imposed a clear baron eitherentertainment or payment
   of interest in any situation of non-payment or delayed payment of either
   the amounts due for work done or lying in security deposit. Thus, the
   arbitrator had no power to grant pendente lite interest. This Court has
 D also doubted the correctness of the decisions in Engineers-De-Space
   Age (supra) and Madnani Construction Corporation (P) Ltd. (supra).
   This court has considered the aforesaid clauses and various decisions in
   Tehri Hydro Development Corporation (supra) in which one of us
   Ranjan Gogoi,J. spoke for the Court. This Court has laid down thus:-
 E            "14. This will lead the court to a consideration of what is the
             principal bone of contention between the parties in the present
             case, namely, the issue with regard to payment of interest. Clauses
             1.2.14 and 1.2.15 on which much arguments have been advanced
             by Learned Counsel for both sides inay now be extracted below: ·

 F                                    PART - II
                         CONDITIONS OF CONTRACT
             1.2.14. No claim for delayed payment due to dispute, etc. -
             The contractor agrees that no claim for interest of damages will
             be entertained or payable by the Government in respect of any
 G           money or balances which may be lying with the Government owing
             to any disputes, differences or misunderstandings between the
             parties or in respect of any delay or omission on the part of the
             engineer-in-charge in making immediate or final payments or in
              any other respect whatsoever.
 H          ·-1.2.15. Interest on money due to the comractor. - No omission
UNION OF INDIA v. MIS. AMBICA CONSTRUCTION                        ;,;": 833
             [ARUN MISHRA, J.]

 on the part of the engineer-in-charge to pay the amount due upon       A
·measurement or otherwise shall vitiate or make void the contract,
 nor shall the contractor be entitled to interest upon any guarantee
 or payments in arrears nor upon any balance which may on the
 final settlement of his accounts be due to him.
A reading of the aforesaid two clauses of the contract agreement         B
between the parties clearly reveal that despite some ovei"lapping
of the circumstances contemplated by the two clauses, no interest
is payable to the contractor for delay in payment, either, interim or
final, for the works done or on any amount lying in deposit by way
of guarantee. The aforesaid contemplated consequence would
be applicable both to a situation where withholding of payment is        c
on account of some dispute or difference between the parties or
even otherwise.
15. Of the several decisions of this Court referred to by the learned
counsel for the appellant the judgments of the Constitution Bench
of this Court in Irrigation Deptt., Gow. of Orissa v. GC. Roy,           D
(1992) 1 SCC 508 and Dhenkanal Minor Irrigation Division v.
N. C. Budharaj, (200 I) 2 SCC 721 will require specific notice.
The true ratio laid down in the aforesaid. two judgments have
been elaborately considered in a more recent pronouncement of
this Court in the case of Union </!India v. Krajters Engg. and           E
Leasing (P) Ltd., (2011) 7 SCC 279. In Krajters Engineers's
case (supra) the ratio of the decision in GC. Roy's case (supra)
was identified to mean that if the agreement between the parties
does not prohibit grant of interest and the claim of a party to
interest is referred to the arbitrator, the arbitrator would have the
power to award the interest. This is on the basis that in such a         F
case of silence (where the agreement is silent) it must be presumed
that interest was an implied term of the agreeme·nt and, therefore,
whether such a claim is tenable can be examined by the arbitrator
 in the reference made to him. The aforesaid view, specifically, is
 with regard to pendente lite interest. Jn the subsequent decision       G
 of the Constitution Bench inN.C. Budharaj's case (supra) a similar
 view has been taken with regard to interest for the pre-reference
 period.
     In
 16. Krajters Engineers' case (supr;;,), the somewhat discordant
 note struck by the decisions of this Court in Port of Calcutta v.       H
834      SUPREME COURT REPORTS                               [2016] 2 S.C.R.


A     Engineers-De-Space-Age (supra) and Madnani Construction
      Corporation Private Limited v. Union of India and Ors.
      (supra), were also taken note of. Thereafter, it was also noticed
      that the decision in Engineers-De-Space-Ages case (supra) was
      considered in Sayeed Ahmed & Co. v. State of U.P. (supra) and
      the decision in Madnani Construction case (supra) was
B
      considered in Sree Kamatchi Amman Constructions v. Railways
      (2010) 8 SCC 767. In Sayeed Ahmeds case (supra) (SCC para
      24) it was held that in the light of the decision of the Constitution
      Bench in GC. Roys case (1992) 1 SCC 508 and N.C. Budharaj
      case (200 I) 2 SCC 721 it is doubtful whether the observations in
c     Engineers-de-Space-Age's case (supra) to the effect that the
      Arbitrator could award interest pendente lite, ignoring the express
      bar in the contract, is good law. Jn Sree Kamatchi Amman
      Construction's case (Supra) while considering MadnaniS case
      (supra) this Court noted that the decision in Madnani case (supra)
      follows the decision in Engineers-de-Space-Age's case (supra).
D
      17. From the above discussions, it is crystal clear that insofar as
      pendente lite interest is concerned, the observations contained in
      Para 43 and 44 of the judgment in GC. Roy case (supra) will
      hold the field. Though the gist of the said principle has been noticed
      earlier it would still be appropriate to set out para 44 ofthe judgment
 E    in GC. Roy's case (supra) which is in the following terms:
      44. Having regard to the above consideration, we think that the
      following is the correct principle.which should be followed in this
      behalf.

 F    Where the agreement between the parties does not prohibit grant
      of interest and where a party claims interest and that dispute (along
      with the claim for principal amount or independently) is referred
      to the arbitrator, he shall have the power to award interest
      pendente lite. This is for the reason that in such a case it must be
      presumed that interest was an implied term of the agreement
 G    between the parties and therefore when the parties refer all their
      disputes - or refer the dispute as to interest as such - to the arbitrator,
      he shall have the power to award interest. This does not mean
      that in every case the arbitrator should necessarily award interest
      pendenle lite. It is a matter within his discretion to be exercised
       in the light of all the facts and circumstances of the case, keeping
 H
UNION OF INDIA v. MIS. AMBICA CONSTRUCTION                               835
             [ARUN MISHRA, J.l

the ends ofjustice in view.                                               A
  18. The provisions of the U.P. Civil Laws (Reforms and
  Amendment) Act amending the First Schedule to the Arbitration
  Act, 1940 does not assist the respondent contractor in any manner
  to sustain the claim ofaward of interest pendente lite, inasmuch,
  as Para 7-A of the First Schedule, as amended, is only an enaliling
  provision which will have no application to a situation where there
  is an express bar to the entertainment or payment of interest on
  the delayed payment either of an amount due for the work done
. or of an amount lying in deposit as security. The decision in·B.N.
  Agarwalla case (supra) on which reliance has been placed by
  the learned counsel for the respondent, once again, does not assist
                                                                          c
  the claim of the respondent ·to interesi pende/1/e lite inasmuch as
  in B.N. Aganmlla case (supra) the views of the Constitution
  Bench in GC. Roy case (supra) with regard to interest pende/1/e
  lite could not have been and, in fact, were not even remotely
  doubted. The observation of the Bench in B.N. Aganrnlla case            D
  that in GC. Roy case (supra) the decision in Depll. ofIrrigation
  v. Abhaduta Jena (1988) 1 SCC 418 was not overruled was only
  in the context of the issue of award of interest for the pre-
  reference period. The decision in Asian Techs Limited case
  (supra) also relied on by the respondent takes note of the decision
  in Engineers-De-Space-Age case (supra) to come to the                   E
  conclusion the prohibition on payment of interest contained in
  Clause 11 of the agreement between the parties was qua the
  department and did not bar the arbitrator from entertaining the
  claim. It has already been noticed that the correctness of the
  propositions laid down in Engineers-De-Space-Age case (supra)           F
  have been doubted in the subsequent decisions of this Court,
  reference to which has already been made.
 19. Clauses 1.2.14 and 1.2.15, already extracted and analysed,
 imposed a clear bar on either entertainment or payment of interest
 in any situation of non-payment or delayed payment of either the         G
 amounts due for work done or lying in security deposit. On the
 basis of the discussions that have preceded we, therefore, take
 the view that the grant of pendente lite interest on the claim of
 Rs. 10, 17,461/- is not justified. The award as well as the orders of
 the courts below are accordingly modified to the aforesaid extent."
                                                                          H .
836             SUPREME COURT REPORTS                        [2016] 2 S.C.R.


A       In para 4 in Engineers-De-Space-Age (supra) this Court has
   observed that bar under the contract will not be applicable to Arbitrator
  ·cannot be said to be observation of general application. In our opinion, it
   would depend upon the stipulation in the contract in each case whether
   power of Arbitrator to grant pendente lite interest is expressly taken
   away. If answer is 'yes' then Arbitrator would have no power to award
B
   pendente lite interest.
           23. The decision in Madnani Construction Corporation (supra)
      has followed decision in Engineers-De-Space-Age (supra). Same is
      also required to be diluted to the extent that express stipulation under
      contract may debar the Arbitrator from awarding interest pendente lite.
c     Grant of pendente lite interest may depend upon several factors such
      as phraseology used in the agreement, clauses conferring power relating
      to arbitration, nature of claim and dispute referred to Arbitrator and on
      what items power to award interest has been taken away and for which
      ~riod.
D           24. Thus, our answer to the reference is that if contract expressly
      bars award of interest pendente lite, the same cannot be awarded by
      the Arbitrator. We also make it clear that the bar to award interest on
      delayed payment by itself will not be readily inferred as express bar to
      award interest pendente lite by the Arbitral Tribunal, as ouster of power
 E    of Arbitrator has to be considered on various relevant aspects referred
      to in the decisions of this Court, it would be for the Division Bench to
      consider the case on merits.
      Devika Gujral                                          Reference ans\rered.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.