UNION OF INDIA & ORS.versusU.P. STATE BRIDGE CORP. LTD.
- Citation
- 2014 INSC 1006
- Decided
- 16 September 2014
- Disposal
- Dismissed
- Bench
- JASTI CHELAMESWAR
Holding
The Supreme Court held that the court may depart from the arbitration agreement and appoint a substitute arbitrator under Section 11(6) and (8) when the original arbitrators default, thereby validating the High Court's appointment.
Summary
The Union of India entered into a construction contract with U.P. State Bridge Corp. Ltd. that contained an arbitration clause under the General Conditions of Contract 2001, Clause 64. An arbitral tribunal of Railway officers was constituted in 2007 but failed to complete the proceedings for four years due to transfers, retirements and adjournments. The respondent approached the Patna High Court, which, after giving the tribunal three months to finish the case, set aside the tribunal and appointed a retired chief justice as a sole arbitrator under its powers. The Union appealed, contending that the High Court had no authority to appoint an arbitrator contrary to the arbitration agreement. The Supreme Court held that while party autonomy and adherence to the agreement is the general rule, the court may invoke the "default procedure" under Section 11 of the Arbitration and Conciliation Act, 1996 when the appointed arbitrators default or are unable to act, and may appoint a substitute arbitrator to ensure a speedy resolution. Consequently, the High Court's appointment was upheld and the appeal dismissed with costs.
Issues considered
- The High Court's power to appoint a substitute arbitrator contrary to the arbitration agreement under Section 11 of the Arbitration and Conciliation Act, 1996.
- Whether the principle of party autonomy requires strict adherence to the arbitration clause when the appointed arbitrators default.
- The applicability of the 'default procedure' in government contracts where the government appoints arbitrators.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 11, s. 14, s. 15
Subjects
Judgment
[2014] 13 S.C.R. 1180
A UNION OF INDIA & ORS. ·
v.
U.P. STATE BRIDGE CORP. LTD.
(Civil Appeal No. 8860 of2014)
B
SEPTEMBER 16, 2014
[J. CHELAMESWAR AND A. K. SIKRI, JJ.]
Arbitration and Conciliation Act, 1996 - ss. 11, 14 and
15- General Conditions of Contract, 2001- Clause 64(1 )(ii)
C - Contracts between Government Corporation-VOi with
private parties-respondent- In terms of the arbitration clause
dispute between the parties referred to arbitral tribunal
constituted in terms of the agreement - Failure of arbitral
tribunal to complete arbitral proceedings for four years -
D Request case by respondent - High Court constituted the
substitute arbitral tribunal, with the appointment of sole
arbitrator - On appeal, held: General rule is that an
f!Jppointment of a substitute arbitrator should be done in
accordance with the provisions of the original agreement -
E When the Government assumes the role of appointment of
arbitrators to itself and the Government nominated arbitrators
are incapable of acting as arbitrators, then the principle of
'default procedure' would be applied in the case of substitute
arbitrators and the Court will step in to appoint the arbitrator
F by keeping aside the procedure agreed between the parties
- Courts are not powerless to remedy such situations by
springing into action and exercising their powers as
contained ins. 11 to constitute an Arbitra/ Tribunal, so that
interest of the other side is equally protected.
G Dismissing the appeal, the Court
HELD: 1.1 The first principle of the Arbitration and
Conciliation Act, 1996 is "fair, speedy and inexpensive
trial by an Arbitr.al Tribunal". The second principle is the
H party autonomy in the choice of procedure. This means
1180
UNION OF INDIA v. U.P. STATE BRIDGE CORP. LTD. 1181
that if a particular procedure is prescribed in the A
Arbitration Agreement which the parties have agreed to,
that has to be generally resorted to. It is because of this
reason, as a normal practice, the Court would insist the
parties to adhere to the procedure to which they have
agreed upon. This would apply even while making the B
appointment of substitute arbitrator and the general rule
. is that such an appointment ·of a substitute arbitrator
should also be done in accordance with the provisions
of the original agreement applicable to the appointment
of the arbitrator at the initial stage. However, this principle c
of party autonomy in the choice of procedure has been
deviated from in those cases where one of the parties
have committed default by not acting in accordance.with
the procedure prescribed. [Para 1.8][1196-F-H;
1197-A-D] D
1.2 In the case of contracts between Government
Corporations/State owned companies with private
parties/ contractors, the terms of the agreement are
usually drawn by the Government company or public
sector undertakings. Government contracts have E
broadly two kinds of arbitration clauses, first where a
named officer is to act as sole arbitrator; and second,
where a senior officer like a managing director,
nominates a designated officer to act as the sole
arbitrator. No doubt, such clauses which give the F
Government a dominant position to constitute the Arbitral
Tribunal are held to be valid. At the same time, it also
casts an onerous and responsible duty upon the
persona designata to appoint such persons/officers as
the arbitrators who are not only able to function G
independently and impartially, but are in a position to
'-
devote adequate time in conducting the arbitration. If the
Government has nominated those officers as arbitrators
who are not able to devote time to the arbitration
proceedings or become incapable of acting as H
1182 SUPREME COURT REPORTS [2014] 13 S.C.R.
A arbitrators because of frequent transfers 'etc., then the
principle of 'default procedure' at least in the cases where
Government has assumed the role of appointment of
arbitrators to itself, has to be applied in the case of
substitute arbitrators as well and the Court will step in
B to appoint the arbitrator by keeping aside the procedure
which is agreed to between the parties. However, it would
depend upon the facts of a particular case as to whether
such a course of action should be taken or not. It is
emphasized that .court is not powerless in this regard.
C [Para 19][1197-F-H; 1198-A-D]
1.3 Leaving the respondent at the mercy of the
appellant thereby giving the power to the appellant to
constitute another Arbitral Tribunal would amount to
adding insult to the serious injury already suffered by
D the respondent because of non conclusion of the arbitral
proceedings even when the dispute were raised in the
year 2007. In case, the cherished and benevolent purpose
and objective of speedy resolution of the disputes by
arbitral proceedings is to be accomplished, it becomes
E the bounden duty of the persona designata to appoint
such arbitrator(s) who have sufficient time at their
disposal to attend to this task assigned to them and to
conclude the arbitral proceedings in a speedily manner.
It is a common sight that the officers who are awfully
F busy in their other routine functions, because of their
status and position, are made arbitrators. For them,
discharge of their other duties assumes more
importance (and naturally so) and their role as the
arbitrators takes a back seat. This kind of behaviour
G s·howing casual approach in arbitration cases is
anathema to the very genesis of arbitration. Therefore,
where the Government assumes the authority and power
to itself, in one sided arbitration clause, to appoint the
arbitrators in the case of disputes, it should be more
H
UNION OF INDIA v. U.P. STATE BRIDGE CORP. LTD. -1183
vigilant and more responsible in choosing the arbitrators A
who are in a position to conduct the arbitral proceedings
in an efficient manner, without compromising with their
other duties. Time has come when the appointing
authorities have to take call on such aspects failing
which (as in the instant case), Courts are not powerless B
to remedy such situations by springing into action and
exercising their powers as contained in Section 11 of
the Act to constitute an Arbitral Tribunal, so that interest
of the other side is equally protected. [Para 22]
[1200-C-H; 1201-A-B] C
North Eastern Railway v. Tripple Engineering
Works 2014 (9) SCC 288; Yashwith Constructions
(P) Ltd. v. Simplex Concrete Piles India Ltd. and
another 2006 (3) Suppl. SCR 96 : (2006) 6 SCC
204 - referred to. D
Department of Economics Policy and
Development of the City of Moscow v. Bankers
.Trust Co. (2004) EWCA Civ 314- referred to.
Commercial Arbitration by Mustil/ and Boyd, E
2001; Law and Practice of Arbitration and
Conciliation by O.P. Malhotra - referred to.
CASE LAW REFERENCE
2014 (9 ) sec 288, referred to. Para 10, F
15, 18, 22.
(2004) EWCA Civ 314 referred to. Para 16.
2006 (3) Suppl. SCR 96 referred to. Para 18.
CIVILAPPELLATE JURISDICTION: Civil Appeal No(s). G
8860of2014.
Fr9m the Judgment and Order dated 03-08-2011 of the
High Court of Judicature at Patna in Request Case No. 3/2011.
H
1184 SUPREME COURT REPORTS [2014] 13 S.C.R.
A Tushar Mehta, ASG, Madhurima Mridul, Ms. Honey
Kumari, S.N. Terdal, B. Krishna Prasad, Advs. for the
Appellants.
Vivek Singh, Lakshmi Raman Singh, Advs. for the
Respondent.
B The Judgment of the Court was delivered by
A. K. SIKRI, J.
1. Leave granted.
2. Counsel for the parties have been heard in detail in
c this appeal. In order to determine the controversy that is raised
in this appeal, which is filed by the Union of India, challenging
the decision dated 03.08.2011 of the High Court, minimal facts
which require a mention, are the following:
The appellant had entered into an agreement with the
D respondent vide which contract for construction of guide bunds,
foundation and substructure of Rail Bridge across river
Gangaes near Digha Ghat, Patna and the said agreement
contained various terms and conditions. Clause 64 (1) (ii) of
the General Condition of the Contract 2001 (for short 'the
E GCC'), contained an arbitration clause that is provided for
. deciding the dispute between the parties through arbitration
by an arbitral tribunal to be constituted iri terms of the said
agreement.
3. Disputes arose between the parties with respect to
F the said contract and on the request of the respondent an
atbitral tribunal of the persons was constituted in the year 2007,
in which all the members were Railway authorities. It is a matter
of regret that inspite of expiry of four years, the said tribunal
did not complete the arbitral proceeding and the matter kept
G hanging due to transfers/ retirement/ adjournments etc.
4. The respondent felt exasperated. due to the
prolongation of the matter before the arbitral tribunal and chose
to file Request Case No.10/2010. Even at the time of filing of
that case, there was a vacancy in the Arbitral Tribunal. When
H
UNION OF INDIA v. U.P. STATE BRIDGE CORP. LTD. 1185
[A. K. SIKRI, J.]
this case was taken up by the High Court on 09.03.2011, by A
that time, the appellant had filled up the said vacancy. Taking
note thereof, the said petition was disposed of by the High
Court vide order dated 09. 03.2011 giving the last chance to
theArbitral Tribunal to complete the arbitral proceeding within
a period of three months with direction to hold regular sittings B
at Patna from the date of receipt/production.of a copy of the
said order. It was also stated in the order dated 09.03.2011
that if arbitration proceedings are not completed within the
period fixed by the Court, the respondent would be at liberty to
approach the Court again and the Court would be constrained C
to pass appropriate order in accordance with the Arbitration
and Conciliation Act, 1996 (hereinafter referred to as 'the Act').
5. The Arbitral Tribunal was made aware of the said
order as the copy thereof was produced before it on
25.03.2011. This means that it was supposed to complete D
the case by 25.06.2011. However, even within the said allotted
time, the proceedings were not broughtto an end and, therefore,
the respondent filed Request Case No.3/2011 dated
29.06.2011.
E
6. The appellant contested the aforesaid petition of the
respondent on various grounds and also gave its own reasons
because of which the Arbitral Tribunal would not complete the
proceedings. It was also pointed out that though the Arbitral
Tribunal was ready to hear the case of the parties and decide F
it finally on 22.07 .2011, the respondent had informed the
Tribunal of the filing of the said petition which led to the
adjournment of the matter by the Tribunal.
7. The High Court took note of the various dates of
hearings that are fixed by the Tribunal between 25.03.2011 G
and 25.06.2011 and came to the conclusion that delay caused
in the arbitral proceedings was intentional. So much so, the
members of the Arbitral Tribunal were continuing their dilatory
tactics in deciding the matter before it since 2007 and four
years had passed in the process. Tribunal had faltered even H
1186 SUPREME COURT REPORTS [2014] 13 S.C.R.
A after giving specific directions to conclude the matter within
three months and lorig adjournments were granted thereby
violating the specific directions of the High Court. Terming
this attitude of the members of the Tribunal as negligent on
their part towards their duties with no sanctity for any law or for
B the orders of the High Court, the High Court allowed the petition
of the respondent herein and set aside the mandate of the
Tribunal with the appointment of sole arbitrator by the Court
itself.
8. In the instant appeal, challenge is made to the
C aforesaid judgment of the High Court with the plea that it was
not open to the High Court to appoint the sole arbitrator as it
was not empowered to constitute Arbitral Tribunal'of its own
and, that too, contrary to the arbitration clause. Mr. Tushar
Mehta, learned ASG appearing for the appellant has made a
D vehement submission, in this behalf, that no such power is
vested in the High Court under the Act. His submission was
. that as per the scheme of tht3 Act even if the mandate of the
Arbitral Tribunal was to be terminated, fresh Tribunal could be
constituted only in accordance with the arbitration agreement.
E It was thus argued that the High Court could have, at the most,
directed the appellant to constitute another Arbitral Tribunal in
accordance with Clause 64 of the GCC.
9. Learned counsel forthe respondent, on the other hand,
F made an effervasive attempt to justify the decision of the High
Court with emphatic plea that when the very purpose of
arbitration is frustrated by the members of the Tribunal who,
were dragging the proceedings, the Court was not powerless
to travel beyond the framework of Clause 64 of the GCC and
G appoint a retired Chief Justice as the arbitrator. He ref~_ffed
to the specific findings of the High Court in the impugned
judgment in this behalf, interalia, observing as under:
"10. The entire facts and circumstances mentioned
abpve depict that the delay caused in the arbitral
H proceedings was intentional. The members of the arbitral
UNION OF INDIA v. U.P. STATE BRIDGE CORP. LTD. 1187
[A. K. SIKRI, J.]
tribunal continued their dilatory tactics in deciding the A
arbitral proceedings since 2007 and when after about
four years specific directions were given by this Court
vide order dated 09.03.2011 passed in Request Case
No.10 of 2011 the said authorities did not flinch for a
moment in disobeying the specific direction of this Court B
and continued their dilatory attitude although the petitioner
had produced the said order of this Court before the
arbitral tril;>_t,rnal on 25.03.2011 and filed his pleadings
and reply by 21.04.2011. Thereafter, long adjournments
were granted in the arbitral proceeding violating the c
specific directions of this Court for holding regular sittings
at Patna and even after the long date fixed by the arbitral
tribunal, sometimes respondent-authorities took long
adjournments to file their counter reply and most of the
times one or the other member of the arbitral tribunal D
were not available and they saw to it that the time of three
months granted by this Court vide order dated
09.03.2011 is expired. This attitude of the arbitral tribunal
· clearly amounts to disobedience of the specific directions
of this Court vide order dated 09.03.2011 passed in E
Request Case No.10 of 2010.
11. All these facts also disclose a very sorry state of
affairs that the members of the arbitral tribunal are inept
& ineffectual by any standard, completely negligent
towards their duties and having no sanctity for any law or F
for the orders of the High Court, which are binging upon
them. All the training courses etc. imparted to them have
clearly proved to be wastage of public exchequer, which
comes from the hard earned money of the people. The
Railways must take note of these observations and the G
order of this Court and act accordingly.
12. So far this case is concerned, it had already been
mentioned in order dated 09.03.2011 passed by this
Court in Request Case No.10 of 2010 that if the
H
1188 SUPREME COURT REPORTS [2014] 13 S.C.R.
A arbitration was not completed within three months from
the date of receipUproduction of a copy of the said order
before the arbitral tribunal, the petitioner would be at
liberty to approach this Court and if the facts claimed by
the petitioner were found to be true, this Court would be
B constrained to pass appropriate orders in accordance
with the Act. In the said circumstances and in view of
the claim of the petitioner having been found to be proved
regarding the attitude of the tribunal, this request case is
allowed and the arbitral tribunal appointed by respondent-
C authorities is hereby set aside and a sole Arbitrator is
appointed to decide the arbitral proceedings
expeditiously without giving any undue adjournment to
any of the parties."
10. He further submitted that in the case of North
D Eastern Railway v. Tripple Engineering Works, decided
on 13.08.2014 in Civil Appeal No.6275 of 2014 (arising out of
S.L.P. (C) No.20427 of 2013), in almost identical
circumstances, this Court had approved the similar directions
of the Patna High Court.
E
11. It is not in dispute that as per Clause 64 of the GCC,
three arbitrators are to be appointed, in the manner prescribed
therein in case of dispute between the parties. The relevant
portion of Clause 64 with which we are concerned with the
F present conditions is extracted below:
"64. (1) (i) Demand for Arbitration - In the event of any
dispute or difference between the parties as to the
construction or operation of this contract, or the respective
rights and liabilities of the parties on any matter in
G question, dispute or difference on any account or as to
the withholding by the Railway of any certificate to which
the contractor may claim to be entitled to, or if the Railway
fails to make a decision within 120 days, then and in any
such case, but except in any of the expected matters
H referred to in clause 63 of these conditions, the contractor,
UNION OF INDIA v. U.P. STATE BRIDGE CORP. LTD. 1189
[A. K. SIKRI, J.]
after 120 days but within 180 days of his presenting his A
final claim on disputed matters, shall demand in writing
the dispute or difference be referred to arbitration.
xx xx xx
64. (3) (a) (I) In cases where the total value of all claims B
in question added together does not exceed 10,00,000/
-(Rupees ten lakhs only), theArbitral Tribunal consist of
a sole arbitrator who shall be either the General Manager
of a gazette officer of Railway not below the grade of JA
grade nominated by the General Manager in that behalf. c
The sole arbitrator shall be appointed within 60 days from
the day when a written and valid demand for arbitration
is received by Railway.
64. (3) (a) (ii) In cases not covered by clause 64 (3)
(a) (I), the Arbitral Tribunal shall consist of a panel D
of three Gazetted Railway Officers not below JA
grade, as the arbitrators. For this purpose, the Railway
will send a panel of more than 3 names of Gazetted
Railway Officers of one or more departments of the
Railway to the contractor who will be asked to suggest E
to General Manager upto 2 names out of the panel for
appointment as contractor's nominee. The General
Manager shall appoint at least one out of them as the
contractor's nominee and will, also simultaneously
appoint the balance number of arbitrators either from the F
panel or from outside the panel, duly indicating the
presiding arbitrator from amongst the 3 arbitrators so
appointed. While nominating the arbitrators it will be
necessary to ensure that one of them is from the Accounts
department. An officer of Section Grade of the Account G
department shall be considered of equal status to the
officers in SA grade of other departments of the Railways
for the purpose of appointment of arbitrators.
H
1190 SUPREME COURT REPORTS [2014] 13 S.C.R.
A 64. (3) (a) (iii) If one or more of the arbitrators
appointed as above refuses to act as arbitrator,
withdraws from his office as arbitrator, or vacates
his/their office/ offices or is/ are unable or unwilling
to perform his functions as arbitrator for any reason
B whatsoever or dies or in the opinion of the General
Manager fails to act without undue delay, the General
Manager shall appoint new arbitrator/arbitrators to
act in his/their place in the same manner in which
the earlier arbitrator/arbitrators had been appointed.
c Such re-constituted Tribunal may, at its discretion,
proceed with the reference from the stage at which it was
left by the previous arbitrator(s)."
12.At this stage, we may take note of the scheme of the
Act as well, by noticing those provisions which would be
D attracted to deal with such a situation. Relevant provisions
are extracted below for ready reference:
"14. Failure or impossibility to act. - (1) The mandate
of an arbitrator shall terminate if-
E (a) he becomes de jure or de facto unable to perform
his functions or for other reasons fails to act without undue
delay; and
(b) he withdraws from his office or the parties agree to
the termination of his mandate.
F
(2) If a controversy remains concerning any of the
grounds referred to in clause (a) of sub-section (1 ), a
party may, unless otherwise agreed by the parties, apply
to the Court to decide on the termination of the mandate.
G (3) If, under this section or sub-section (3) of section 13,
an arbitrator withdraws from his office or a party agrees
to the termination of the mandate of an arbitrator, it shall
not imply acceptance of the validity of any ground referred
to in this section or sub-section (3) of section 12.
H
UNION OF INDIA v. U.P. STATE BRIDGE CORP. LTD. 1191
[A. K. SIKRI, J.]
15. Termination of mandate and substitution of A
;:irbitrator. - ( 1) In addition to the circumstances referred
to in section 13 or section 14, the mandate of an arbitrator
shall terminate -
(a) where he withdrawsfrom office for any reason; or
8
(b) by or pursuant to agreement of the parties.
(2) Where the mandate of an arbitrator terminates, a
substitute arbitrator shall be appointed according to the
rules that were applicable to the appointment of the
arbitrator being replaced. c
(3) Unless otherwise agreed by the parties, where an
arbitrator is replaced under sub-section (2), any hearings
previously held may be repeated at the discretion of the
arbitral tribunal.
D
(4) Unless otherwise agreed by the parties, an order or
ruling of the arbitral tribunal made prior to the replacement
of an arbitrator under this section shall not be invalid
solely because there has been a change in the
composition of the arbitral tribunal. E
32. Termination of proceedings. - (1) The arbitral
proceedings shall be terminated by the final arbitral award
or by an order of the arbitral tribunal Linder sub-section
(2).
(2) The arbitral tribunal shall issue an order for the F
termination of the arbitral proceedings where -
(a) the claimant withdraws his claim, unless the
respondent objects to the order and the arbitral tribunal
recognises a legitimate interest on his part in obtaining G
a final settlement of the dispute,
(b) the parties agree on the termination of the
proceedings, or
(c) the arbitral tribunal finds that the continuation of the H
1192 SUPREME COURT REPORTS [2014] 13 S'.C.R.
A proceedings has for any other reason become
unnecessary or impossible.
(3) Subject to section 33 and sub-section (4) of section
34, the mandate of the arbitral tribunal shall terminate
with the termination of the arbitral proceedings."
B
13.As is clear from the reading of Section 14, when there
is a failure on the part of the Arbitral Tribunal to act and it is
unable to perform its function either de jure or de facto, it is
open to a party to the arbitration proceedings to approach the
c Court to decide on the termination of the mandate. Section
15 provides some more contingencies when mandate of an
arbitrator can get terminated. In the present case, the High
Court has come to a categorical finding that theArbitral Tribunal
failed to perform its function, and rightly so. It is a clear case
0 of inability on the part of the members of the Tribunal to proceed
in the matter as the matter lingered on for almost four years,
without any rhyme or justifiable reasons. The members did not
mend their ways even when another life was given by granting
three months to them. Virtually a pre-emptory order was passed
E by the High Court, buttheArbitralTribunal remained unaffected
and took the directions of the High Court in a cavalier manner.
Therefore, the order of the High Court terminating the mandate
of the arbitral tribunal is flawless. This aspect of the impugned
order is not even questioned by the appellant at the time of
F hearing of the present appeal.
14. However, the contention of the appellant is that even
if it was so, as per the provisions of Section 15 of the Act,
substitute arbitrators should have been appointed "according
to the rules that were applicable to the appointment of the
G arbitrator being replaced". On this basis, it was the submission
of Mr. Mehta, learned ASG, that High Court should have
resorted to provision contained in Clause 64 of the GCC.
· 15. No doubt, ordinarily that would be the position. The
moot question, however, is as to whether such a course of
H action has to be necessarily adopted by the High Court in all
UNION OF INDIA v. U.P. STATE BRIDGE CORP. LTD. 1193
[A. K. SIKRI, J.]
cases, while dealing with an application under Section 11 of A
the Act or there is a room for play in the joints and the High
Court is not divested of exercising discretion under some
circumstances? If yes, what are those circumstances? It is
this very aspect which was specifically dealt with by this Court
in Tripple Engineering Works (supra). Taking note of various B
judgments, the Court pointed out that the notion that the High
Court was bound to appoint the arbitrator as per the contract
between the parties has seen a significant erosion in recent
past. In para 5 of the said decision, those judgments where
departure of the aforesaid "classical notion" has been made c
are taken note of. It would, therefore, be useful to reproduce
the said para along with paras 6 & 7 herein below:
"5. The "classical notion" that the High Court while
exercising its power Under Section 11 of the Arbitration
and Conciliation Act, 1996 (hereinafter for short 'the Act') D
must appoint the arbitrator as per the contract between
the parties saw a significant erosion in Ace Pipeline
Contracts (P) Ltd. v. Bharat Petroleum Corporation
. Ltd., (2007) 5 SCC 304 wherein this Court had taken
the view that though the contract between the parties must E
be adhered to, deviations therefrom in exceptional
circumstances would be permissible. Amore significant
development had come in a decision that followed soon
thereafter in Union of India v. Bharat Battery
Manufaduring Co. (P) Ltd., (2007) 7 SCC 684 wherein F
following a three Judges Bench decision in Punj Lloyd
Ltd. v. Petronet MHB Ltd., (2006) 2 SCC 638 it was
held that once an aggrieved party files an application
Under Section 11 (6) of the Act to the High Court, the
opposite party would lose its right of appointment of the G
arbitrator(s) as per the terms of the contract. The
implication that the Court would be free to deviate from
the terms of the contract is obvious. The apparent
dichotomy in Ace Pipeline (supra) and Bharat Battery
Manufacturing. Company (P) Ltd. (supra) was H
1194 SUPREME COURT REPORTS [2014] 13 S.C.R.
A reconciled by a three Judges Bench of this Court in
Northern Railway Administration, Ministry of
Railway, New De/hiv. Patel Engineering Co. Limited,
(2008) 10 SCC 240 where the jurisdiction of the High
Court Under Section 11 (6) of the Act was sought to be
B emphasized by taking into account the expression "to
take the necessary measure" appearing in Sub-section
(6) of Section 11 and by further laying down that the said
expression has to be read along with the requirement of
Sub-section (8) of Section 11 of the Act. The position
c was further clarified in Indian Oil Corporation Limited
& Ors. v. Raja Transport Private Limited, (2009) 8
SCC 520. Paragraph 48 of the report wherein the scope
of Section 11 of the Act was summarized may be quoted
by reproducing Sub-paragraphs (vi) and (vii) herein
D below:
"(vi) The Chief Justice or his designate while
exercising power under Sub-section (6) of Section 11
st1all endeavour to give effect to the appointment
procedure prescribed in the arbitration clause.
E
(vii) If circumstances exist, giving rise to justifiable
doubts as to the independence and impartiality of the
person nominated, or if other circumstances warrant
appointment of an independent arbitrator by ignoring
the procedure prescribed, the Chief Justice or his
F
designate may, for reasons to be recorded, ignore the
designated arbitrator and appoint someone else."
6. The above discussion will not be complete without
reference to the view of this Court expressed in Union
G of India v. Singh Builders Syndicate, (2009) 4 SCC
523 wherein the appointment of a retired Judge contrary
to the agreement requiring appointment of specified
officers was held to be valid on the ground that the
arbitration proceedings h_ad not concluded for over a
H decade making a mockery of the process. In fact, in
UNION OF INDIA V. U.P. ST" BRIDGE CORP. LTD. 1195
[A. K. SIKRI, J.]
paragraph 25 of the report in Singh Builders Syndicate A
(supra) this Court had suggested that the government,
statutory authorities and government companies should
consider phasing out arbitration cl?uses providing for
appointment of serving officers and encourage
professionalism in arbitration. B
7. A pronouncement of late in Deep Trading Co. v.
Indian Oil Corportation and Ors., (2013) 4 SCC 35
followed the legal position laid down in Punj Lloyd Ltd.
(supra) which in turn had followed a two Judges Bench
decision in Datar Switchgears Ltd. v. Tata Finance C
Ltd., (2000) 8 SCC 151. The theory of forfeiture of the
rights of a party under the agreement to appoint its
arbitrator once the proceedings under Section 11 (6) of
the Act had commenced came to be even more formally
embedded in Deep Trading Company(supra) subject, D
of course, to the provisions of Section 11 (8), which
provision in any event, had been held in Northern
Railway Administration (supra) not to be mandatory,
but only embodying a requirement of keeping the same
in view at the time of exercise of jurisdiction under E
Section 11 (6) of the Act."
16. Speedy conclusion of arbitration proceedings hardly
needs to be emphasised. It would be of some interest to note
that in England also, Modern Arbitration Law on the lines of F
UNCITRAL Model Law, came to be enacted in the same year
as Indian Law which is known as EnglishArbitrationAct, 1996
and it became effective from 31st January, 1997. It is treated
· as the most extensive statutory reform of English arbitration
"law. Commenting upon the structure of this Act, Mustill and
Boyd in their"CommercialArbitration, 2001 companion volume G
to the second edition, have commented that this Act founded
on four pillars. These pillars are described as:
(a) The First Pillar: Three General Principles.
H
1196 SUPREMECOUR~EPORTS [2014] 13 S.C.R.
A (b) The Second Pillar: The General Duty of the Tribunal.
(c) The Third Pillar: The General Duty of the Parties.
(d) The Fourth Pillar: Mandatory and Semi Mandatory
Provisions.
B In so far as first pillar is concerned, it contains V.ree
general principles on which the entire edifice of the said Act is
structured. These principles are mentioned by an English Court
in its judgment in the case of Department of Economics
Policy and Development of the City of Moscowv. Bankers
C Trust Co., (2004) EWCA Civ 314. In that case, Mance, L.J.
succinctly summed up the objective of this Act in the following
words: 'Parliament has set out, in the Arbitration Act, 1996, to
encourage and facilitate a reformed and more independent,
as well as private and confidential, system of consensual
D dispute resolution, with only limited possibilities of court
involvement where necessary in the interests of the public and
of basic fairness'. Section 1 of the Act sets forth the three
main principles of arbitration law viz.- (I) speedy, inexpensive
and fair trial by an impartial tribunal; (ii) party autonomy; and
E (iii) minimum court intervention. This provision has to be
applied purposively. In case of doubt as to the meaning of any
provision of this Act, regard should be had to these principles.
17. In the book "O.P. Malhotra on the Law and Practice
of Arbitration and Conciliation" (Third Edition revised by Ms.
F lndu Malhotra), it is rightly observed that Indian Arbitration Act
is also based on the aforesaid four foundational pillars.
18. First and paramount principle of the first pillar is "fair,
speedy' and inexpensive trial by an Arbitrai Tribunal".
G Unnecessary delay or expense would frustrate the very purpose
of arbitration. Interestingly, second principle which is
recognised in the Act is the party autonomy in the choice of
procedure. This means that if a particular procedure is
prescribed in the Arbitration Agreement which the parties have
H agreed to, that has to be generally resorted to. It is because
UNION OF INDIA v. U.P. STATE BRIDGE CORP. LTD. 1197
[A. K. SIKRI, J.]
of this reason, as a normal practice, the Court will insist the A
. partiE?..~,.to adhere to the procedure to which they have agreed
upon. This would apply even while making the appointment of
substitute arbitrator and the general rule is that such an
appointment of a substitute arbitrator should also be done in
accordance with the provisions of the original agreement B
applicable to the appointment of the arbitrator at the initial
stage. (see Yashwith. Constructions (P) Ltd. v. Simplex
Concrete Piles India Ltd. and another, (2006) 6 SCC 204.
However, this principle of party autonomy in the choice of
procedure has been deviated from in those cases where one C.
of the parties have committed default by not acting in
accordance with the procedure prescribed. Many such
instances where this course of action is taken and the Court
appoint the arbitrator when the persona designata has failed
to act, are taken note of in para 5 of Tripple Engineering D
Works (supra). We are conscious of the fact that these were
the cases where appointment of the independent arbitrator
made by the Court in exercise of powers under Section 11 of
account of 'default procedure'. We are, in the present case,
concerned with the constitution of substituteArbitral Tribunal E
where earlierArbitral Tribunal has failed to perform. However,
the above principle of default procedure is extended by this
Court in such cases as well as is clear from the judgment in
Singh Builders Syndicate (supra).
19. In the case of contracts between Government F
Corporations I State owned companies with private parties/
contractors, the terms of the agreement are usually drawn by
the Government company or public sector undertakings.
Government contracts have broadly two kinds of arbitration
clauses, first where a named officer is to act as sole arbitrator; G ·
and second, where a senior officer like a managing director,
nominates a designated officer to act as the sole arbitrator.
No doubt, such clauses which give the Government a dominant
position to constitute the Arbitral Tribunal are held to be valid.
At the same time, it also casts an onerous and responsible H
1198 SUPREME COURT REPORTS [2014] 13 S.C.R.
A duty upon the persona designata to appoint such persons/
officers as the arbitrators who are not only able to function
independently and impartially, but are in a position to devote
adequate time in conducting the arbitration. If the Government
has nominated those officers as arbitrators who are not able
B to devote time to the arbitration proceedings or become
incapable of acting as arbitrators because of frequent transfers
etc., then the principle of 'default procedure' at least in the
cases where Government has assumed the role of appointment
of arbitrators to itself, has to be applied in the case of substitute
c arbitrators as well and the Courtwill step in to appoint the
arbitrator by keeping aside the procedure which is agreed to
between the parties. However, it will depend upon the facts of
a particular case as to whether such·a course of action should
be taken or not. What we emphasise is that Court is not
D powerless in this regard.
20. In Singh Builders Syndicate (supra) where
pendency of arbitration proceedings for over a decade was
found by this Court to be a mockery of a process. This anguish
is expressed by the Court in the said judgment in the following
E manner:
"15. The object of the alternative dispute resolution
process of arbitration is to have expeditious and effective
disposal of the disputes through a private forum of the
parties' choice. lftheArbitral Tribunal consists of serving
F
officers of one of the parties to the dispute, as members
in terms of the arbitration agreement, and such tribunal
is made non-functional on account of the action or
inaction or delay of such party, either by frequent transfers
of such members of the Arbitral Tribunal or by failing to
G
talffi steps expedititiously to replace the arbitrators in
terms of the arbitration agreement, the Chief Justice or
his designate, required to exercise power under Section
11 of the Act, can step in and pass appropriate orders.
H
UNION OF INDIA v. U.P. STATE BRIDGE CORP. LTD. 1199
[A. K. SIKRI, J.]
16. We fail to understand why the General Manager of A
the Railways repeatedly furnished panels containing
names.of officers who were due for transfer in the near
future. We are conscious of the fact that a serving officer
is transferred on account of exigencies of service and
transfer policy of the employer and that merely because B
an employee is appointed as arbitrator, his transfer
cannot be avoided or postponed. But an effort should
be made to ensure that officers who are likely to remain.
in a particular place are alone appointed as arbitrators
and that theArbitral Tribunal consisting of serving officers, c
decides the matter expeditiously.
17. Constituting Arbitral Tribunals with serving officers
from different far-away places should be avoided. There
can be no hard-and-fast rule, but there should be a
conscious effort to ensure that the Arbitral Tribunal is D
COl'lstituted promptly and arbitration does not drag on for
years and decades.
18. As noticed above, the matter has now been pending
for nearly ten years from the date when the demand for E
arbitration was first made with virtually no progress.
Having regard to the passage of time, if the Arbitral
Tribunal has to be reconstituted in terms of Clause 64,
there may be a need to change even the other two
members of the Tribunal.
F
19. The delays and frequent changes in the Arbitral
Tribunal make a mockery of the process of arbitration.
Having regard to this factual background, we are of the
view that the appointment of a retired Judge of the Delhi
High Court as sole arbitrator does not call for interference G
in exercise of jurisdiction under Article 136 of the
Constitution of India."
21. The appointment of arbitrator by the Court, of its own
choice, departing from the arbitration clause, is therefore not
unknown and has become an acceptable proposition of law H
1200 SUPREME COURT REPORTS [2014] 13 S.C.R.
A which can be termed as a legal principle which has come to
be established by a series of judgments of this Court. Reasons
for debating such a course of action are not far to seek and
already taken note of above.
22. In the present case, we find the fact situation almost
B same as in Tripp/e Engineering Works (supra) and Singh
Builders Syndicate (supra). If the contention of the appellant
is allowed, it would amount to giving premium to the appellant
for the fault of the Arbitral Tribunal's members who were
appointed by none else but by appellant itself. As pointed
C above, the appellant has not questioned the order of the High
Court in so far as it has terminated the mandate of the earlier
Arbitral Tribunal because of their inability to perform the task
assigned to them. In such a situation, leaving the respondent
at the mercy of the appellant thereby giving the power to the
D · appellant to constitute another Arbitral Tribunal would amount
to adding insult to the serious injury already suffered by the
respondent because of non conclusion of the arbitral
proceedings even when the dispute were raised in the year
2007. In case, the cherished and benevolent purpose and
E objective of speedy resolution of the disputes by arbitral
proceedings is to be accomplished, it becomes the bounden
duty of the persona designata to appoint such arbitrator( s) who
have sufficient time at their disposal to attend to this task
assigned to them and to conclude the arbitral proceedings in
F a speedily manner. It is a common sightthat the officers who
are awfully busy in their other routine functions, because of
their status and position, are made arbitrators. For them,
discharge of their other duties assumes more importance (and
. naturally so) and their role as the arbitrators takes a back seat.
G ., This kind'of behaviour showing casual approach in arbitration
cases is anathema to the very genesis of arbitration; Therefore,
where the Government assumes th~ authority and power to
itself, in one sided arbitration clause, to appoint the arbitrators
in the case of disputes, it should be more vigilant and more
H responsible in choosing the arbitrators who are in a position
UNION OF INDIA v. U.P. STATE BRIDGE CORP. LTD. 1201
[A. K. SIKRI, J.]
to conduct the arbitral proceedings in an efficient manner, A
without compromising with their other duties. Time has come
when the appointing authorities have to take call on such
aspects failing which (as in the instant case), Courts are not
powerless to remedy such situations by springing into action
and exercising their powers as contained in Section 11 of the B
Act to constitute an Arbitral Tribunal, so that interest of the other
side is equally protected.
23. In view of the aforesaid, we do not find any merit in
the present appeal which is dismissed with costs.
c
Nidhi Jain Appeal dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.