UNION OF INDIA & ORS.versusM/S. MASTER CONSTRUCTION CO.
- Citation
- 2011 INSC 328
- Decided
- 25 April 2011
- Disposal
- Appeal(s) allowed
- Bench
- AFTAB ALAM
Holding
When no‑claim certificates and full payment indicate a full and final settlement and no credible allegation of fraud, duress or undue influence is established, the contract is discharged and no arbitrable dispute exists, rendering the appointment of an arbitrator under Section 11(6) invalid.
Summary
The Union of India and others contracted Master Construction Co. to complete works, which were finished and a completion certificate issued. The contractor submitted no‑claim certificates and signed the final bill, receiving full payment on 19 June 2000, after which it later withdrew the certificates and lodged further claims. The contractor sought appointment of an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996; the High Court Chief Justice appointed an arbitrator, holding that all disputes were arbitrable. On appeal, the Supreme Court examined whether any arbitrable dispute survived after the contractor’s voluntary acceptance of payment and issuance of no‑claim certificates, and whether a bare allegation of fraud, duress or undue influence sufficed to refer the matter to arbitration. Relying on the principles laid down in National Insurance Co. v. Boghara Polyfab, the Court held that the certificates and payment demonstrated a full and final settlement, no credible allegation of fraud existed, and therefore the contract was discharged and no arbitrable dispute remained. Consequently, the order appointing an arbitrator under Section 11(6) was set aside.
Issues considered
- Whether, after the contractor furnished no‑claim certificates and received payment of the final bill, any arbitrable dispute between the parties survived.
- Whether a mere allegation of fraud, coercion, duress or undue influence, without prima facie proof, can justify referral of the dispute to arbitration under Section 11(6) of the Arbitration and Conciliation Act, 1996.
- Whether the order of the Chief Justice appointing an arbitrator under Section 11(6) was valid.
Legislation cited
Subjects
Judgment
[2011) 5 S.C.R. 853
UNION OF INDIA & ORS. A
v.
MIS. MASTER CONSTRUCTION CO.
(Civil Appeal No. 3541 of 2011)
APRIL 25, 2011 B
[AFTAB ALAM AND R. M. LODHA, JJ.]
ARBITRATION AND CONCILIATION ACT, 1996:
s. 11 (6) - Application for appointment of arbitrator after C
submitting 'no-claim certificate' and receipt of payment of final
bill - Arbitrator appointed - Held: Where the dispute raised
by the claimant with regard to validity of the discharge
voucher or no-claim certificate or settlement agreement,
prima facie, appears to be lacking in credibility, there may not o
be necessity to refer the dispute for arbitration at all - It may
not be proper to burden a party, who contends that dispute is .
not arbitrable on account of discharge of contract, with huge
cost of arbitration merely because plea of fraud, coercion,
duress or undue influence has been taken by claimant, as E
mere plea is not enough and the claimant must prima facie
establish the same by placing material before the Chief
Justice/ his designate - In the instant case, the conduct of
contractor clearly shows that 'no claim certificates' were given
by it voluntarily and it accepted the amount of the final bill F
voluntarily and the contract was discharged voluntarily- Order
appointing the arbitrator u/s 11 (6) cannot be sustained and
is set aside.
The respondent-contractor completed the contract
on 31.8.1998. The completion certificate was issued on G
9.9.1999. Thereafter the contractor furnished 'no claim
certificates' on 3-4-2000, 28-4-2000 and 4-5-2000, signed
the final bill on 4-5-2000, and received payment under the
853 H
854 SUPREME COURT REPORTS (2011] 5 S.C.R.
A final bill on 19.6.2000. However, immediately on release
of the bank guarantee on 12.7.2000, the same day the
contractor wrote to the appellant-employers withdrawing
the 'no claim certificate' and also lodged certain claims.
The Chief Engineer declined to entertain the claims. The
B contractor made an application u/s 11 of the Arbitration
and Conciliation Act, 1996 before the Civil Judge (Senior
Division). The application was dismissed. The
contractor's writ petition was also dismissed by the High
Court. The contractor's S.L.P was disposed of by the
C Supreme Court with the direction that the application be
placed before the Chief Justice of the High Court. The
Chief Justice decided the application u/s 11(6) holding
that all disputes between the parties to the contract would
be referred to the arbitration and appointed the arbitrator.
o Aggrieved, the employers filed the appeal.
In the instant appeal filed by the employers, the
question for consideration before the Court was: whether
after furnishing 'no-claim certificates' and the receipt of
payment of final bill, as submitted by the contractor, any
E arbitrable dispute between the parties survived or the
contract stood discharged.
Allowing the appeal, the Court
F · HELD: 1.1 There is no rule of the absolute kind. In a
case where the claimant contends that a discharge
voucher or no-claim certificate has been obtained by
fraud, coercion, duress or undue influence and the other
side contests the correctness thereof, the Chief Justice/
G his designate must look into this aspect to find out at least,
prima facie, whether or not the dispute is bona fide and
genuine. Where the dispute raised by the claimant with
regard to validity of the discharge voucher or no-claim
certificate or settlement agreement, prima facie, appears
H
UNION OF INDIA & ORS. v. MASTER 855
CONSTRUCTION CO.
to be lacking-in credibility, there may not be necessity to A
refer the dispute for arbitration at all. [para 24] [866-D-F]
National Insurance Company Limited v. Boghara Polyfab
Private Limited 2008 (13) SCR 638 -~ (2009) 1 SCC 267; The
Union of India v. Kishorilal Gupta & Bros Limited AIR (1959} B
SC 1362; The Naihati Jute Mills Ltd. v: Khyaliram Jagannath
AIR (1968) SC 522; Damodar Valley Corporatio.n v. K.K..Kar
1974 (2) SCR 240 =(1974) 1 .sec 141; Mis. Bharat H~avy
Electricals Limited, Ranipur v. Mis. Amar Nath Bhan Prakash
(1982) 1 SCC 625; Union of India & Anr. v. Mis. L. K, Ahuja C
& co. 1988 (3) SCR 402 = (1988) 3 sec 76; State. of
Maharashtra v. Nav Bharat Builders 1994 Supp .(3) SCC 83;
Mis. P.K. Ramaiah & Company v. Chairman & Managing
Director, National Thermal Power Corpn. 1994 Supp (3) SCC
126; Nathani Steels Ltd. v. Associated Constructions, 1995
Supp (3) SCC 324; Indian Drugs & Pharmaceuticals Ltd. v.
0
lndo Swiss Synthetics Gem Mfg. Co. Ltd. & Ors. 1995 (5)
Suppl. SCR 189 = (1996) 1 SCC 54; United India Insurance
. v. Ajmer Singh Cotton & General Mills & Ors., 1999 (1)
Suppl. SCR 385 = (1999) 6 SCC 400; Jayesh Engineering
Works v. New India Assurance Co. Ltd. (2000) 10 SCC 178; E
SBP & Co. v. Patel Ertgineering Ltd. & Anr. 2005 (4) Suppl.
SCR 688 = (2005) 8 SCC 618; National Insurance Co. Ltd.
v. Nipha Exports (P) Ltd. 2006 (6) Suppl. SCR 719 = (2006)
8 SCC 156; and National Insurance Company Limited v.
Sehtia Shoes 2008 (3) SCR 451 = (2008) 5 SCC 400 - F
referred to
Chairman & M.D., NTPC Ltd. v. _Reshmi Constructions,
Builders and Contractors 2004 (1) SCR 62 = (2004) 2 SCC
663 and Ambica Construction v. Union of India 2006 (9) G
Suppl. SCR 188 = (2006) 13 SCC 475 - cited
1.2 It cannot be overlooked that the cost of arbitration
is quite huge. It may not be proper to burden a party, who
contends that the dispute is not arbitrable on account of
856 SUPREME COURT REPORTS (2011] 5 S.C.R.
A discharge of contract, with huge cost of arbitration
merely because the plea of fraud, coercion, duress or
undue influence has been taken by the claimant. A bald
plea of fraud, coercion, duress or undue influence is not
enough and the party who sets up such plea must prima
B facie establish the same by placing material before the
Chief Justice/his designate. If the Chief Justice/his
designate finds some merit in the allegation of fraud,
coercion, duress or undue influence, he may decide the
same or leave it to be decided by the Arbitral Tribunal. On
C the other hand, if such plea is found to be an after-
thought, make-believe or lacking in credibility, the matter
must be set at rest then and there. [para 24] [866-G-H;
867-A-B]
0 1.3 In the instant case, the certificates furnished by
the .contractor leave no manner of doubt that upon receipt
of the payment, there has been full and final settlement
of the contractor's ·claim under the contract. That the
payment of final bill was made to the contractor on June
E 19, 2000 is not in dispute. After receipt of the payment on
June 19, 2000, no grievance was raised or lodged by the
contractor immediately. The authority concerned,
thereafter, released the bank guarantee in the sum of Rs.
21,00,000/- on July 12, 2000. It was then that on that day
itself, the contractor lodged further claims. This appears
F to be a case falling in the category of exception noted in
the case of Boghara Polyfab Private Limited, as to
financial duress or coercion, nothing of this kind is
established prima facie. Mere allegation that no-claim
certificates have been obtained under financial duress
G and coercion, without there being anything more to
suggest that, does not lead to an arbitrable dispute.
[para 28-29] [868-A-D]
1.4 The conduct of the contractor clearly shows that
H 'no claim certificates' were given by it voluntarily; the
_UNION OF INDIA & ORS. v. MASTER 857
CONSTRUCTION CO.
contractor accepted the amount voluntarily and the A
contract was discharged voluntarily. Thus, the order of ·
the Chief Justice in the proceedings u/s.11(6) of the 1996 ·
Act cannot be sustained and is set aside. [para 30 to 32)
[868-E-H]
8
Case Law Reference:
2008 (13) SCR 638 referred to para 16
2004 (1 ) SCR 62 cited para 16
2006 (9 ) Suppl. SCR 188 cited para 16 C
AIR (1959) SC 1362 referred to para 19
1974 ( 2) SCR 240 referred to -para 19
(1982) 1-scc 625 · referred to para 19 o-
1988 ( 3 )- SCR 402 . referred to para 19
1994 Supp (3) sec 83 referred to para 19
1994 Supp (3) sec 126 referred to para 19
E
1995 Supp (3) sec 324 referred to para 19
1995 ( 5 ) Suppl. SCR 189 referred to para 19
1999 ( 1 ) Suppl. SCR 385 referred to para 19
(2000) 10 sec 178 referred to para 19 F
2005 (4 ) Suppl. SCR 688 referred to - para 19
2006 (6 ) Suppl. SCR 719 referred to para 19
2008 (3 ) SCR 451 referred to para 19 G
CIVIL APPELLATE JURISDICTION : Civil Appeal No.
3541 of 2011.
From the Judgment & Order dated 08.12.2006 of the High
H
858 SUPREME COURT REPORTS [2011] 5 S.C.R.
A Court of Punjab and Haryana at Chandigarh in Arbitration Case
No. 87 of 2006.
·' Brijender Chahar, Nishant Patel, C.S. Khan, Shamsuddin
. Khan (for D.S. Mahra) for the Appellants.
B lndu Malhotra, Jyoti Mendiratta, Prerna Priyadarshini for
the Respondents.
The Judgment of the Court was delivered by
R.M. LODHA, J. 1. Leave granted.
c
2. This appeal, by special leave, arises from the order
dated December 8, 2006 passed by the Chief Justice of the
Punjab and Haryana High Court in the proceedings under
Section 11 (6) of the Arbitration and Conciliation Act, 1996 (for
D short, '1996 Act') whereby he held that all disputes between the
parties to the contract have to be referred to the arbitration and
appointed Mr. M.S. Liberahan, retired Chief Justice of Andhra
Pradesh High Court, as sole arbitrator to decide the disputes
between the parties.
E
3. The respondent - M/s. Master Construction Company
(for short, 'the contractor') - was awarded a contract (CA No.
CEBTZ-14/95-96) on September 17, 1995 by the first
appellant-Union of India - for the work, 'provisions of OTM
F accommodation and certain essential technical buildings' to be
erected and installed at Bhatinda. The first phase of the work
was to be completed by July 20, 1996 and the second phase
by January 20, 1997.
4. The agreement between the parties made IAFW-2249
G an integral part of the contract. Condition 70 thereof provided
mode for resolution of disputes and differences between the
parties through arbitration.
5. The work is said to have been completed by the
H contractor, albeit belatedly, on August 31, 1998. The completion
UNION OF INDIA & ORS. v. MASTER 859
CONSTRUCTION CO. [R.M. LODHA, J.]
certificate was issued on September 9, 1999. A
6. The contractor furnished no-claim certificates on April
3, 2000, April 28, 2000 and May 4, 2000 and the final bill was
signed on May 4, 2000.
B
7. The payment of final bill was released to the contractor
on June 19, 2000. Thereafter, the bank guarantee amounting
to Rs. 21,00,000/- was also release.d on July 12, 2000.
Immediately after release of the bank guarantee, on that very
day, i.e. July 12, 2000, the contractorwrote to the appellants
withdrawing 'no-claim certificates'; italso lodged certain claims. C
8. The Chief Engineer, Bhatinda Zone, Bhatinda
(Appellant No. 3 herein) vide his letter dated July 13, 2000
declined to entertain the claims of the contractor on the ground
that the final bill has· been accepted by the· contractor after D
furnishing the 'no-claim certificates' and no claim under the
contract remained.
9. The contractor vide its letter dated September 10, 2000
requested the Engineer-in-Chief, Army Headquarters, Kashmir
House; New Delhi (Appellant No. 2 herein) to refer the disputes E
between the parties for resolution to the arbitrator. The
contractor stated in that letter that if the arbitrator was not
appointed within 30 days from the date of request, it may be
constrained to seek the remedy as may be available under the
law. F
10. As no arbitrator was appointed by the appellants
despite the request made in the letter dated September 10,
2000, the contractor made an application under Section 11 of
the 1996 Act before the Civil Judge, (Senior Division), Bhatinda G
on January 10, 2001. The application, after contest, was
dismissed by the Civil Judge, Senior Division, Bhatinda on
January 6, 2003.
11. Being not satisfied with the order dated January 6, H
860 SUPREME COURT REPORTS [2011] 5 S.C.R.
A 2003, the contractor challenged that order by filing a writ
petition before the High Court of Punjab and Haryana.
12. The Division Bench of the High Court heard the parties
and by its order dated May 20, 2004 dismissed the contractor's
B writ petition.
13. The contractor challenged the High Court's order by
filing a special leave petition before this Court. This Court
disposed of the special leave petition on January 3, 2006 by
C directing that the application filed by the contractor under
Section 11 of the 1996 Act shall be placed before the Chief
Justice of the Punjab and Haryana High Court, for appropriate
order thereon. This Court, consequently, set aside the orders
of the High Court and the lower court.
D 14. It was then that the Chief Justice of the Punjab and
Haryana High Court decided the application filed by the
contractor under Section 11 (6) of the 1996 Act and passed the
order impugned in the present appeal.
E 15. Mr. Brijender Chahar, learned senior counsel for the
appellants made two-fold submission : (i) that no arbitrable
dispute existed between the parties as full and final payment
has been received by the contractor voluntarily after submission
of 'no-claim certificates' and the final bill, and (ii) that, in any
case, the Chief Justice in exercise of his power under Section
F 11 (6) ought to have given due regard to the arbitration clause
and appointed the arbitrator in terms thereof.
16. Ms. lndu Malhotra, learned senior counsel for the
contractor, on the other hand, vehemently contended that the
G whole case of the contractor from the very beginning had been
that 'no-claim certificates' were given by the contractor under
the financial duress and coercion as the appellants had
arbitrarily withheld the payment. She would submit that the issue
whether 'no-claim certificates' were given voluntarily or under
H financial duress, is an issue which must be decided by the
UNION OF INDIA & ORS. v. MASTER 861
CONSTRUCTION CO. [R.M. LODHA, J.]
arbitrator alone and it is for this reason that the Chief Justice, A
in the proceedings under Section 11 (6), has referred the
disputes between the parties to the arbitrator. In this regard,
she heavily relied upon a recent decision of this Court in the
case of National Insurance Company Limited v. Boghara
Polyfab Private Limited 1 • She also referred to two earlier B
decisions of this Court, namely, Chairman & M.D., NTPC Ltd.
v. Reshmi Constructions, Builders and Contractors 2 and
Ambica Construction v. Union of lndia 3 •
17. That IAFW-2249 was made an integral part of the C
contract between the parties and condition 70 thereof provided
for mode of resolution of disputes and differences between the
parties through arbitration is not in dispute. Condition 70
(arbitration clause) reads as under :
"70. Arbitration-All disputes, between the parties to the D
Contract (other than those forwhich the decision of the
C.W.E. or any other person is by the Contract expressed
to be final and binding) shall, after written notice by either
party to the Contract to the other of them, be referred to
the sole arbitration of an Engineer Officer to be appointed E
by the authority mentioned in the tender documents.
Unless both parties agree in writing such reference shall
not take place until after the completion or alleged
completion of the works or termination or determination of F
the contract under Condition Nos. 55, 56 and 57 hereof.
Provided that in the event of abandonment of the works
or cancellation of the Contract under Condition Nos. 52,53
or 54 hereof, such reference shall not take place until
alternative arrangements have been finalized by the G
Government to get the works completed by or through any
other Contractor or Contractors or Agency or Agencies.
1. (2009) 1 sec 267.
2. (2004) 2 sec 663.
3. (2006) 13 sec 475. H
862 SUPREME COURT REPORTS [2011] 5 S.C.R.
A Provided always that commencement or continuance of any ·
arbitration proceeding hereunder or otherwise shall not in
any manner militate against the Government's right of
recovery from the contractor as provided in Condition 67
hereof.
B
If the Arbitrator so appointed resigns his appointment or
vacates his office or is unable or unwilling to act due to
any reason whatsoever, the authority appointing him may
appoint a new Arbitrator to act in his place. ·
c The arbitrator shall be deemed to have entered on the
reference on the date he issues notice to both the parties,
asking them to submit to him their statement of the case
and pleadings in defence.
D The Arbitrator may proceed with the arbitration, exparte,
if either party, inspite of a notice from the Arbitrator fails
to take part in the proceedings.
The Arbitrator may, form time to time with the consent of
the parties, enlarge, the time upto but not exceeding one
E year from the date of his entering on the reference, for
making and publishing the award.
The Arbitrator shall give his award within a period of six
months from the date of his entering on the reference or
F within the extended time as the case may be on all matters,
referred to him and shall indicate his findings, along with
sums awarded, separately on each individual item of
dispute.
The venue of Arbitrator shall be such place or places as
G may be fixed by the Arbitrator in his sole discretion.
The award of the Arbitrator shall be final and binding on
both parties to the contract.
If the value of the claims or counter claims in an arbitration
H
UNION OF INDIA & ORS. v.. MASTER 863
CONSTRUCTION CO. [R.M. LODHA, J.]
referred exceeds Rs. 1 lakh the arbitrator shall give A
reasons for the award".
18. The controversy presented before us does not concern
the existence of arbitration agreement butit relates to whet.her
after furnishing 'no-claim certificates' and the receipt of payment
8
of final bill, as submitted by the contractor, any arbitrable
dispute between the parties survived or the contract stood
discharged. Before we turn to the factual aspect, it is
appropriate to carefully consider the decision of this Court in
Boghara Polyfab Private Limited1 at some length as the
learned senior counsel for the contractor placed heavy reliance C
on it.
19. In Boghara Polyfab Private Limited1 , this Court
surveyed a large number of earlier decisions of this Court,
namely, The Union of/ndia v. Kishorilaf Gupta & Bros4., The D
Naihati Jute Mills Ltd. v. Khyaliram Jagannath 5 , Damodar
Valley Corporation v. K.K. Kar°, Mis. Bharat Heavy Electricals
Limited; Ranipur v. Mis. Amar Nath Bhan Prakash7 , Union of
India & Anr. v. Mis. L.K. Ahuja & Co. 8 , State of Maharashtra
v. Nav Bharat Builders9 , Mis. P.K. Ramaiah & Company v. E
Chairman & Managing Director, National Thermal Power
Corpn. 10 , Nathani Steels Ltd. v. Associated Constructions11 ,
Indian Drugs & Pharmaceuticals Ltd. v. lndo Swiss Synthetics
Gem Mfg. Co. Ltd. & Ors. 12 , United India Insurance v. Ajmer
Singh Cotton & General Mills & Ors. 13 , Jayesh Engineering
F
4. AIR (1959) SC 1362.
5. AIR (1968) SC 522.
6. (1974) 1 sec 141.
1. (1982) 1 sec 625.
8. (1988) 3 sec 76. G
9. 1994 Supp (3) 83.
10. 1994 Supp (3) sec 126.
11. 1995 Supp (3) SCC 324.
12. (1996) 1 sec 54.
13. (1999) 6 sec 400. H
864 SUPREME COURT REPORTS [2011] 5 S.C.R.
A Works v. New India Assurance Co. Ltd. 14 , SBP & Co. v. Patel
Engineering Ltd. & Anr. 15 , National Insurance Co. Ltd. v. Nipha
Exports (P) Ltd. 16 and National Insurance Company Limited
v. Sehtia Shoes17 . With regard to the jurisdiction of the Chief
Justice/his designate in the proceedings under Section 11 of
B the 1996 Act, this Court culled out the legal position in
paragraph 51 (page 294) of the report as follows :
"51. The Chief Justice/his designate exercising jurisdiction
under Section 11 of the Act will consider whether there was
really accord and satisfaction or discharge of contract by
c performance. If the answer is in the affirmative, he will
refuse to refer the dispute to arbitration. On the other hand,
if the Chief Justice/his designate comes to the conclusion
that the full and final settlement receipt or discharge
voucher was the result of any fraud/coercion/ undue
D influence, he will have to hold that there was no discharge
of the contract and consequently, refer the dispute to
arbitration. Alternatively, where the Chief Justice/his
designate is satisfied prima facie that the discharge
voucher was not issued voluntarily and the claimant was
E under some compulsion or coercion, and that the matter
deserved detailed consideration, he may instead of
deciding the issue himself, refer the matter to the Arbitral
Tribunal with a specific direction that the said question
should be decided in the first instance. n
F 20. The Bench in Boghara Polyfab Private Limited1 in
paragraphs 42 and 43 (page 291), with reference to the cases
cited before it, inter alia, noted that there were two categories
of the cited cases; (one) where the Court after considering the
facts found that there was a full and final settlement resulting in
G accord and satisfaction, and there was no substance in the
allegations of coercion/undue influence and, consequently, it
14. (2005) 10 sec 118.
15. (2005) 8 sec 618.
16. (2006) 8 sec 1se.
H 11. (2008) 5 sec 400.
UNION OF INDIA & ORS. v. MASTER 865
CONSTRUCTION CO. [R.M. LODHA, J.]
was held that there could be no reference of any dispute to A
arbitration and (two) where the court found some substance in
the contention of the claimants that 'no dues/claim certificates'
or 'full and final settlement discharge vouchers' were insisted
and taken (either in printed format or otherwise) as a condit;on
precedent for release of the admitted dues and thereby giving B
rise to an arbitrable dispute.
21. In Boghara Polyfab Private Limited1, the
consequences of discharge of the contract were also
considered. In para 25 (page 284), it was explained that when
a contract has been fully performed, then there is a discharge C
of the contract by performance and the contract comes to an
end and in regard to such a discharged contract, nothing
remains and there cannot be any dispute and, consequently,
there cannot be reference to arbitration of any dispute arising
from a discharged contract. It was held that the question D
whether the contract has been discharged by performance or
not is a mixed question of fact and law, and if there is a dispute
in regard to that question, such question is arbitrable. The
Court, however, noted an exception to this proposition. The
exception noticed is that where both the parties to a contract E
confirm in writing that the contract has been fully and finally
discharged by performance of all obligations and there are no
outstanding claims or disputes, courts will not refer any
subsequent claim or dispute to arbitration. Yet another
exception noted therein is with regard to those cases where F
one of the parties to the contract issues a full and final discharge
voucher (or no-dues certificate, as the case may be) confirming
that he has received the payment in full and final satisfaction
of all claims, and he has no outstanding <flaim. It was observed
that issuance of full and final discharge voucher or no-dues
certificate of that kind amounts to discharge of the contract by G
acceptance or performance and the party issuing the discharge
voucher/certificate cannot thereafter make any fresh claim or
revive any settled claim nor can it seek reference to arbitration
in respect of any claim.
H
866 SUPREME COURT REPORTS [2011] 5 S.C.R.
A 22. In paragraph 26 (pages 284-285), this Court in
Boghara Polyfab Private Limited1 held that if a party which has
executed the discharge agreement or discharge voucher,
alleges that the execution of such document was on account
of fraud/coercion/undue influence practised by the other party,
B and if that party establishes the same, then such discharge
voucher or agreement is rendered void and cannot be acted
upon and consequently, any dispute raised by such party would
be arbitrable.
23. In paragraph 24 (page 284) in Boghara Polyfab Private
C Limited1, this Court held that a claim for arbitration cannot be
rejected merely or solely on the ground that a settlement
agreement or discharge voucher has been executed by the
claimant. The Court stated that such dispute will have to be
decided by the Chief Justice/his designate in the proceedings
D undsr Section 11 of the 1996 Act or by the Arbitral Tribunal.
24. In our opinion, there is no rule of the absolute kind. In
a case where the claimant contends ~hat a discharge voucher
or no-claim certificate has been obtained by fraud, coercion,
duress or undue influence and the other side contests the
E correctness thereof, the Chief Justice/his designate must look
into this aspect to find out at least, prima facie, whether or not
the dispute is bona fide and genuine. Where the dispute raised
by the claimant with regard to validity of the discharge voucher
or no-claim certificate or settlement agreement, prima facie,
F appears to be lacking in credibility, there may not be necessity
to refer the dispute for arbitration at all. It cannot be overlooked
that the cost of arbitration is quite huge - most of the time, it
runs in six and seven figures. It may not be proper to burden a
party, who contends that the dispute is not arbitrable on account
G of discharge of contract, with huge cost of arbitration merely
because plea of fraud, coercion, duress or undue influence has
been taken by the claimant. A bald plea of fraud, coercion,
duress or undue influence is not enough and the party who sets
up such plea must prima facie establish the same by placing
H material before the Chief Justice/his designate. If the Chief
UNION OF INDIA & ORS. v. MASTER ·867
CONSTRUCTION CO. [R.M. LODHA, J.]
Justice/his designate finds some merit in the allegation of fraud, A
coercion, duress or undue influence, he may decide the same
or leave it to be decided by the Arbitral Tribunal. On the other
hand, if such plea is found to be an after-thought, make-believe
or lacking in credibility, the matter must be set at restthen and
fuere. B
25. In light of the above legal position, we now turn to the
facts of the present case.
26. At the time of receiving payment on account of final
bill, the contractor executed the certificate in the following terms C
"a) I/we hereby certify that I/we have performed the work
under the condition of the contract agreement No.
CEBTZ-14/95-96, for which payment is claimed and
that /!we have no further claims under CA No. 0
CEBTZ-14195~96. ,
b) · Received rupees two lakhs fifteen thousand one
hundred seventy eight only. This payment is in full
and final settlement of all money dues under CA
No. CEBTZ-14195-96 and I have no further claims E
in respect of the CA No. CEBTZ-14195-96."
(emphasis supplied by us)
27. The contractor also appended the following certificate:
"It is certified that I have prepared this final bill for claiming F
entire payment due to me from this contract agreement.
The final bill includes all claims raised by me from time to
time irrespective of the fact whether they. are admitted/
accepted by the· department or not. I now categorically
certify that I have no more claim in respect of this contract G
beyond those already included in this final bill by me and
the amount so claimed by me shall be in full and final
satisfaction of all my claims under this contract agreement.
I shall however, receive my right to raise claim to the extent
disallowed to me from this final bill."
H
868 SUPREME COURT REPORTS [2011] 5 S.C.R.
A 28. The above certificates leave no manner of doubt that
upon receipt of the payment, there has been full and final
settlement of the contractor's claim under the contract. That the
payment of final bill was made to the contractor on June 19,
2000 is not in dispute. After receipt of the payment on June 19,
B 2000, no grievance was raised or lodged by the contractor
immediately. The concerned authority, thereafter, released the
bank guarantee in the sum of Rs. 21,00,000/- on July 12, 2000.
It was then that on that day itself, the contractor lodged further
claims.
C 29. The present, in our opinion, appears to be a case falling
in the category of exception noted in the case of Boghara
Polyfab Private Limited (Para 25, page 284). As to financial
duress or coercion, nothing of this kind is established prima
facie. Mere allegation that no-claim certificates have been
D obtained under financial duress and coercion, without there
being anything more to suggest that, does not lead to an
arbitrable dispute.
30. The.conduct of the contractor clearly shows that 'no
claim certificates' were given by it voluntarily; the contractor
E accepted the amount voluntarily and the contract was
discharged voluntarily.
31. We are, thus, unable to sustain the order of the Chief
Justice in the proceedings under Section 11 (6) of the 1996 Act.
In view of our finding above, it is not necessary to consider the
F alternative submission made by the senior counsel for the
appellants that the Chief Justice in exercise of his power under
Section 11 (6) ought to have appointed the arbitrator in terms
of the arbitration clause and the appointment of Mr. M.S.
Liberahan, retired Chief Justice of Andhra Pradesh High Court,
G was not in accord with the arbitration agreement.
32. The appeal is, accordingly, allowed. The impugned
order dated December 8, 2006 passed by the Chief Justice
of the High Court of Punjab and Haryana is set aside. The
parties shall bear their own costs.
H R.P. Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.