UNION OF INDIA ETC.versusGIANI
- Citation
- 2011 INSC 132
- Decided
- 17 February 2011
- Disposal
- Case Partly allowed
- Bench
- MUKUNDAKAM SHARMA
Holding
The Supreme Court condoned the delay and held that Section 23(1A) does not apply to the respondents because the award was passed before the amendment’s applicability date, so they are not entitled to the additional compensation.
Summary
The Union of India appealed against a High Court order that awarded land owners compensation under Section 23(1A) of the Land Acquisition Act, 1894. The acquisition proceedings began in 1965 and the Collector's award was passed on 9 July 1980, before the amendment (Act 68 of 1984) that introduced Section 23(1A) became applicable to pending cases on 30 April 1982. The Union filed the appeals after a considerable delay, seeking condonation of the delay under Article 136 of the Constitution. The Supreme Court examined whether the delay could be condoned and whether Section 23(1A) applied to the case. Relying on the constitutional bench decision in K.S. Paripoornan v. State of Kerala, the Court held that the amendment did not apply to proceedings whose award was passed before the applicability date, so the respondents were not entitled to the additional compensation. The Court condoned the delay, partly allowed the appeals, and ordered the parties to bear their own costs.
Issues considered
- Whether the delay in filing the appeals can be condoned under Article 136 of the Constitution.
- Whether Section 23(1A) of the Land Acquisition Act, 1894 applies to acquisition proceedings that commenced before 30‑04‑1982 but whose award was passed before that date.
Legislation cited
- Constitution of Indias. 136
- Land Acquisition Act, 1894s. 23(1A), s. 23(2), s. 30(1), s. 4, s. 6
- Land Acquisition (Amendment) Act, 1984 (Act 68 of 1984)
Subjects
Judgment
[2011] 2 S.C.R. 978
A UNION OF INDIA ETC.
v.
GIANI
(Civil Appeal No. 1884 of 2011)
FEBRUARY 17, 2011
B
[DR. MUKUNDAKAM SHARMA AND ANIL R DAVE, JJ.]
DELA YILACHES :
c Application for condonation of delay in filing appeal -
Held: the averments in the application do constitute sufficient
cause for not preferring the appeals within time -There is a
strong arguable case on behalf of the appellants, therefore,
Court would decide the matter or merits by giving the
expression 'sufficient cause' a pragmatic justice oriented
0
approach - Delay condoned - Constitution of India, 1950 -
Article 136.
LAND ACQUISITION ACT, 1894: ·
E Section 23 (1-A) as inserted by amendment Act 68 of
1984- Compensation under- Held: Sub - s. (1-A) was made
applicable to proceedings pending on or after 30.04.1982 -
In the instant case, land owners would not be entitled to get
the benefit under Sub - s. (1-A) as the proceedings had
F culminated in passing the award by the Collector on
09.07.1980 i.e. before 30.04.1982, the date from which the
amendment was made applicable to pending and subsequent
proceedings.
The Union of India filed the instant appeals, though
G after considerable delay, contending that the respondent
land-owners were not entitled to receive compensation
u/s. 23 (1-A) of the Land Acquisition Act, 1897, which was
granted in their favour by the High Court.
H 978
UNION OF INDIA ETC. v. GIANI 979
Partly allowing the appeals the Court, A
HELD : 1.1. The application for condonation of delay
in preferring the appeals must be allowed as the ·
statements in the applications for condonation of delay,
do constitute sufficient cause in not preferring the 8
appeals within the period of limitation. There is a strong
arguable case on behalf of the appellants and, therefore,
it is felt necessary that the Court should decide the matter
on merit by giving the expression 'sufficient cause' a
pragmatic justice oriented approach. Therefore, delay in C
all the appeals is condoned. [para 3) {981-A-C]
2. Section 23 (1-A) was inserted in the Land
Acquisition Act, 1894 w.e.f., 24.9.1984 by way of
amendment to the Act by Act 68 of 1984, which was made
applicable to proceedings pending on or after 30.04.1982. D
The said sub-s.(1A) provides that in addition to the market
value of the land, the Court would in every case award
an amount calculated at the rate of twelve per centum per
annum on such market value for the period commencing
on and from the date of the publication of the notification E
u/s. 4(1 ), in respect of such land to the date of the award
of the Collector or the date of taking possession of the
land, whichever is earlier. In sub-s.(2) of s. 23 of the Act,
the words "thirty per centum" replaced the words "fifteen
per centum", w.e.f., 24.09.1984 and it was also made F
applicable to certain awards made and order passed after
30.04.1982. [para 6) [981-G-H; 982-A-B]
K. s. Paripoornan v. State of Kera/a and others 1994 (3)
Suppl. SCR 405 = (1994) 5 sec 593 and Pralhad and
Others v. State of Maharashtra and another 201 O (11 ) G
SCR 916 = (201 O) 1o sec 458 - relied on.
2.2. In the instant case, the acquisition proceeding
commenced with the notification u/s. 4 issued on
06.03.1965 and it culminated in passing of the award by H
980 SUPREME COURT REPORTS [2011] 2 S.C.R.
A the Collector on 09.07.1980, i.e., before 30.04.1982, the
date from which the amending Act 68 of 1984 was made
applicable to the pending and subsequent proceedings.
Therefore, in terms of the law laid down by the
Constitution Bench of this Court in the case of K.S.
B Paripoornan, the respondents are not entitled to the
benefit of s. 23(1A). [para 8) [983-H; 984-A-B]
Case Law Reference:
·1994 ( 3 ) Suppl. SCR 405 relied on para 6
c 2010 (11 ) SCR 916 relied on para 7
CIVIL APPELLATE JURISDICTION : Civil Appeal No.
1884 of 2011.
0 From the Judgment & Order dated 31.5.2002 of the High
Court of Delhi at New Delhi in RFA No. 465 of 1986.
WITH
C.A. Nos. 1887, 1885, 1886 of 2011.
E
P.P. Malhotra, ASG, Brijender Chahar, Rekha Pandey, M.
P.S. Tomar, Anil Katiyar for the Appellant.
K.L. Janjani, Raj Singh Rana, Pankaj Kumar Singh, A.
~ain, Dr. Vinod Tewari, P.P. Singh for the Respondent.
F
The Judgment of the Court was delivered by
Dr. MUKUNDAKAM SHARMA, J. 1. Leave granted in all
the petitions.
G 2. We propose to dispose of all these appeals by this
common judgment and order. In all these appeals not only the
issues arising for our consideration on merit are identical but
also all these appeals were filed by the appellants herein after
considerable delay.
H
UNION OF INDIAETC. v. GIANI 981
[DR. MUKUNDAKAM SHARMA, J.]
3. Having examined the averments made in the A
applications for condonation of delay in filing all the appeals
and after hearing the learned counsel for the parties, we are
satisfied that the application for condonation of delay in
preferring the appeals must be allowed as the statements in
the applications for condonation of delay, in our view, do B
constitute sufficient cause in not preferring the appeals within
the period of limitation. We, therefore, condone delay in all the
appeals. We have taken such a view in this matter as we feel
that there is a strong arguable case on behalf of the appellants
and, therefore, it is felt necessary that the court should decide c
the matter on merit by giving the expression sufficient cause a
pragmatic justice oriented approach.
4. In all these appeals counsel appearing for the appellant
has raised just one issue, namely, that the respondent in each
of the appeals is not entitled to receive compensation under D
Section 23 (1A) of the Land Acquisition Act, 1891 [for short "the
Act"] which has been granted in their favour by the orders of
the High Court.
5. On 06.03.1995 by issuing notification under Section 4 E
of the Act, land situated in village-Ziauddinpur, Delhi was sought
to be acquired for public purpose, namely, planned
development of Delhi. The aforesaid notification was followed
by issuance of a declaration under Section 6 of the Act which
was issued on 07.01.1969. The Collector passed the award F
on 09.07.1980 vide his award No. 39/80-81.
6. Section 23 (1A) of the Land Acquisition Act, 1894 was
inserted, w.e.f., 24.9.1984, by way of amendment to the Act
which was made applicable to proceedings pending on or after
30.04.1982. The said sub-section (1 A) provides that in G
additional to the market value of the land, the Court would in
every case award an amount calculated at the rate of twelve
per centum per annum on such market value for the period
commencing on and from the date of the publication of the
notification under Section 4, sub-Section (1), in respect of such H
982 SUPREME COURT REPORTS [2011) 2 S.C.R.
A land to the date of the award of the Collector or the date of
taking possession of the land, whichever is earlier. In sub-
section 2 of Section 23 of the Act the words "thirty per centum"
replaced the words "fifteen per centum", w.e.f., 24.09.1984 and
it was also made applicable to certain awards made and order
B passed after 30.04.1982. The specific and the only issue which
was agitated by the counsel appearing for the appellant before
us, during the course of hearing was that, since the aforesaid
amendment by Act No. 68 of 1984 inserted a new provision in
the nature of sub-section (1A), which was inserted, w.e.f.,
c 24.09.1984 [and was made applicable to proceedings pending
on or after 30.04.1982) sub-section (1A) would not be
applicable in the present case. In support of the said contention
reference was made to the decision of the Constitutional Bench
of this Court in K. S. Paripoornan v. State of Kera/a and others
D reported in (1994) 5 SCC 593 in which this Court upon a
combined reading of Section 23(1A) and Section 30(1) of the
Act held as follows: -
"74 ........... A perusal of sub-section (1) of Section 30 of
the amending Act shows that it divides the proceedings
E for acquisition of land which had commenced prior to the
date of the commencement of the amending Act into two
categories, proceedings which had commenced prior to
30-4-1982 and proceedings which had commenced after
30-4-1982. While clause (a) of Section 30(1) deals with
F proceedings which had commenced prior to 30-4-1982,
clause (b) deals with proceedings which commenced after
30-4-1982. By virtue of clause (a), Section 23(1-A) has
been made applicable to proceedings whic": had
commenced prior to 30-4-1982 if no award had been
G made by the Collector in those proceedings before 30-4-
1982. It covers (i) proceedings which were pending before
the Collector on 30-4-1982 wherein award was made after
30-4-1982 but before the date of the commencement of
the amending Act, and (ii) such proceedings wherein
H award was made by the Collector after the date of the
UNION OF INDIA ETC. v. GIANI 983
[DR. MUKUNDAKAM SHARMA, J.]
commencement of the amending Act. Similarly Section. A
30(1)(b) covers (i) proceedings which had commenced'
after 30-4-1982 wherein award was made prior to the
commencement of the amending Act, and (ii) such
proceedings wherein award was made after the
commencement of the amending Act. It would thus appear B
that both the clauses (a) and (b) of sub-section (1) of
Section 30 cover proceedings for acquisition which were
pending on the date of the commencement of the
amending Act and to which the provisions of Section 23(1-
A) have been made applicable by virtue of Section 30(1}. c
If Section 23(1-A}, independently of Section 30(1 ), is
applicable to all proceedings which were pending on the
date of the commencement of the amending Act, clauses
(a} and (b) of Section 30(1) would have been confined to
proceedings which had commenced prior to the 0
commencement of the amending Act and had concluded
before such commencement because.by virtue of Section
15 the provisions of Section 23(1-A) would have been
applicable to proceedings pending before the Collector on
the date of commencement of the amending Act. There
was no need to so phrase Section 30(1) as to apply the E
provisions of Section 23(1-A) to proceedings which were
pending before the Collector on the date of the
commencement of the amending Act. This only indicates
that but for the provisions contained in Section 30(1)
Section 23(1-A) would not have been applicable to F
proceedings pending before the Collector on the date of
commencement of the amending Act."
7.A similar issue again came up for consideration before
this Court in Pralhad and Others v. State of Maharashtra and G
another reported in (2010) 1O sec 458 wherein reference was
made and reliance was placed in the decision of K. S.
Paripooman (supra).
1 8. In the present case the acquisition proceeding H
984 SUPREME COURT REPORTS [2011] 2 S.C.R.
A commenced with the notification under Section 4 issued on
06.03.1965 and it culminated in passing of the award by the
Collector on 09.07.1980, i.e., before 30.04.1982, the date from
which the amending Act 68 of 1984 was made applicable to
the pending and subsequent proceedings. Therefore, in terms
B of the law laid down by the Constitution Bench decision of this
Court in the case of K.S. Paripooman (supra) the respondents
are not entitled to the benefit of Section 23(1A).
9. All the appeals, therefore, are partly allowed to the
C aforesaid extent and disposed of leaving the parties to bear
their own costs.
R.P. Appeals partly allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.