THIRUMALAI CHEMICALS LIMITEDversusUNION OF INDIA & ORS.
- Citation
- 2011 INSC 292
- Decided
- 11 April 2011
- Disposal
- Disposed off
- Bench
- R V RAVEENDRAN
Holding
The limitation for filing an appeal under Section 19(2) of FEMA is governed by its own proviso, which is procedural and retrospective, permitting the Appellate Tribunal to condone any delay if sufficient cause is shown; Section 52(2) of FERA does not apply.
Summary
Thirumalai Chemicals Ltd imported goods in 1996 and, due to a bank error, the required exchange control documents were not forwarded to the RBI, leading to penalty orders under FERA. The company sought to appeal these orders after FEMA came into force, filing belated appeals in 2004 before the Appellate Tribunal under Section 19 of FEMA with a condonation of delay application. The Tribunal dismissed the appeals, applying the first proviso of Section 52(2) of the repealed FERA, which limited condonable delay to 90 days, and the High Court upheld this dismissal. The Supreme Court held that the limitation period for appeals filed under FEMA is governed by the proviso to Section 19(2) of FEMA, a procedural provision that operates retrospectively, allowing the Tribunal to condone any delay if sufficient cause is shown. Consequently, the Court set aside the Tribunal and High Court orders and remitted the matter back to the Tribunal for fresh consideration.
Issues considered
- Whether the limitation period for filing an appeal under Section 19(2) of FEMA should be governed by the proviso to that section or by the first proviso to Section 52(2) of the repealed FERA.
- Whether procedural provisions relating to limitation are retrospective and apply to appeals where the cause of action arose under FERA but the appeal is filed under FEMA.
- Whether Section 49 of FEMA and Section 6 of the General Clauses Act affect the right of appeal and the applicable limitation period.
- Whether the Appellate Tribunal can condone delay beyond 45 days under FEMA when sufficient cause is shown.
- Whether the High Court erred in dismissing the writ petitions on the ground of a time-bar.
Legislation cited
- Foreign Exchange Management Act, 1999 (FEMA)s. 19(2), s. 49(5)(a)
- Foreign Exchange Regulation Act, 1973 (FERA)s. 52(2), s. 8(3), s. 8(4)
- General Clauses Act, 1897s. 6
- Limitation Act, 1963s. 5
Subjects
Judgment
[2011] 4 S.C.R. 838
•
A THIRUMALAI CHEMICALS LIMITED
v.
UNION OF INDIA & ORS.
(Civil Appeal Nos. 3191-3194 of 2011)
APRIL 11, 2011
B
[R.V. RAVEENDRAN AND K.S. RADHAKRISHNAN, JJ.]
Foreign Exchange Management Act, 1999 - ss. 19(2)
and 49 - Cause of action arose when FERA was in force, but
C show cause notices and impugned orders issued when FEMA
was in force - Appeal filed uls. 19 of FEMA - Rejection of,
by Appellate Tribunal constituted under FEMA, applying the
first proviso to sub section (2) of s. 52 of FERA instead of
following the proviso to sub section (2) to s. 19 of FEMA -
D Held: Limitation for filing appeal has to be considered uls.
19(2) of FEMA - Provision relating to limitation is procedural
- In absence of any provision to contrary, the law in force on
date of initiation of appeal irrespective of the date of ..~crual
of the cause of action for the original order, would govern the
E period of limitation - Section 52(2) can apply only to an
appeal to the Appellate Board and not to any Appellate
tribunal - Therefore, irrespective of the fact that the
adjudicating officer had passed the orders with reference to
the violation of the provisions of FERA, as the appeal against
F such order was to the appellate tribunal constituted under
FEMA, necessarily s. 19(2) of FEMA alone would apply and
it is not possible to import the provisions of s. 52(2) of FERA
- Tribunal and High Court misdirected themselves in
assuming that the period of limitation was governed by s.
52(2) of FERA - Appellate Tribunal can entertain the appeal
G after the prescribed period of 45 days if it is satisfied, that there
was sufficient cause for not filing the appeal within the said
period - Matter is remitted back to the Tribunal for fresh
H 838
• THIRUMALAI CHEMICALS LIMITED v. UNION OF
INDIA & ORS.
839
consideration - Foreign Exchange Regulation Act, 1973 - ss. A
52(2), 8(3) and 8(4) - General Clauses Act - s. 6.
Substantive law and procedural law - Distinction between
- Held: Substantive law refers to body of rules that creates,
defines and regulates rights and liabilities - Right of appeal
8
may be a substantive right but the procedure for filing the
appeal including the period of /imitation cannot be called a
substantive right - Aggrieved person cannot claim any vested
right claiming that he should be governed by the old provision
pertaining to period of limitation - Procedural law establishes C
a mechanism for determining those rights and liabilities and
a machinery for enforcing them - Procedural law is
retrospective meaning thereby that it would apply even to acts
or transactions under the repealed Act - Right of appeal
conferred u/s. 19(1) of FEMA is a substantive right -
Procedure for filing an appeal under sub-section (2) of s. 19 D
. as a/so the proviso to sub-section (2) of s. 19 conferring power
on the Tribunal to condone delay in filing the appeal if
sufficient cause is shown, are procedural rights.
Ap~ 1ellant Company imported various consignments E
for home consumption and opened letters of credit in the
year 1996. Thereafter, the Company forwarded the
Exchange Control Copies of bills of entry (ECC-bills of
entry) to banks (authorized dealers) for submitting to
Reserve Bank of India. The authorized dealers did not F
forward the ECC bills of entry to RBI. The Directorate of
Enforcement passed orders imposing penalty on the
Company for contravention of Section 8(3), Section 8(4)
of FERA read with sub-sections (3) and (4) of Section 49
of FERA and issued show cause notices to the Company G
as the Company had failed to furnish the required bills/
information/documents and also held that an appeal
would lie before the Appellate Tribunal after depositing
the amount of penalty imposed within 45 days from the
H
840 SUPREME COURT REPORTS [2011] 4 S.C.R.
•
A date on which the order was served. The Company
informed the Enforcement Directorate that it was due to
the mistake of the authorized dealer that the bills of entry
were not forwarded to them in time. Subsequently RBI
carried out necessary corrections and deleted the entries
B from their records and regularized the transactions and
requested the Directorate of Enforcement to drop the
proceedings initiated against the Company. However, the
Company did not hear anything from the Directorate,
thus, filed appeals against the said orders in 2004 before
c the Appellate Tribunal for Foreign Exchange with an
application under Section 5 of the Limitation Act read
with Section 19 and Section 49(5) (a) of FEMA for
condonation of delay. The Tribunal applying the first
proviso to sub section (2) of s. 52 of FERA, dismissed the
D appeals on the ground of delay. The appellant filed writ
petitions before the High Court for quashing the order
and the same were dismissed. Therefore, the appellant
Company filed the instant appeal.
Disposing of the appeals, the Court
E
HELD: 1.1 In the instant case, the cause of action
arose when Foreign Exchange Regulation Act, 1973 was
in force, but show cause notices and impugned orders
were issued when Foreign Exchange Management Act,
F 1999 was in force and the appeals were also preferred
under sub section (1) of Section 19 of FEMA. [Para 11]
[852-G-H; 853-A]
1.2 Substantive law refers to body of rules that
creates, defines and regulates rights and liabilities. Right
G conferred on a party to prefer an appeal against an order
is a substantive right conferred by a statute which
remains unaffected by subsequent changes in law,
unless modified expressly or by necessary implication.
Procedural law establishes a mechanism for determining
H those rights and liabilities and a machinery for enforcing
• THIRUMALAI CHEMICALS LIMITED v. UNION OF
INDIA & ORS.
them. Right of appeal being a substantive right always
841
A
acts prospectively. Every statute is prospective unless it
is expressly or by necessary implication made to have
retrospective operation. Right of appeal may be a
substantive right but the procedure for filing the appeal
including the period of limitation cannot be called a B
substantive right, and aggrieved person cannot claim
any vested right claiming that he should be governed by
the old provision pertaining to period of limitation.
Procedural law is retrospective meaning thereby that it
would apply even to acts or transactions under the c
repealed Act. Unless the language used plainly manifests
in express terms or by necessary implication a contrary
intention a statute divesting vested rights is to be
construed as prospective, a statute merely procedural is
to be construed as retrospective and a statute which 0
while procedural in its character, affects vested rights
adversely is to be construed as prospective. [Paras 14
and 16) [855-E-H; 856-D-E]
Garikapati Veeraya vs. N. Subbiah Choudhry and Ors.
AIR 1957 SC 540; New India Insurance Company Limited Vs. E
Smt. Shanti Mishra (1975) 2 SCC 840; Hitendra Vishnu
Thakur and Ors. vs. State of Maharashtra and Ors. (1994) 4
SCC 602; Maharaja Chintamani Saran Nath Shahdeo vs.
State of Bihar and Ors. (1999) 8 sec 16; Shyam Sundar and
Ors. vs. Ram Kumar and Anr. (2001) 8 sec 24 - relied on. F
1.3 Right of appeal conferred under Section 19(1) of
FEMA is a substantive right. The procedure for filing an
appeal under sub-section (2) of Section 19 as also the
proviso to sub-section (2) of Section 19 conferring power G
on the Tribunal to condone delay in filing the appeal if
sufficient cause is shown, are procedural rights. The
proviso to sub-section (2) of Section 19 operates
retrospectively. [Paras 17 and 18] (856-F-H]
1.4 Law of limitation is generally regarded as H
842 SUPREME COURT REPORTS [2011] 4 S.C.R. •
A procedural and its object is not to create any right but to
prescribe periods within which legal proceedings be
instituted for enforcement of rights which exist under
substantive law. On expiry of the period of limitation, the
right to sue comes to an end and if a particular right of
B action had become time barred under the earlier statute
of limitation the right is not revived by the provision of
the latest statute. Statutes of limitation are, thus,
retrospective insofar as they apply to all legal
proceedings brought after their operation for enforcing
c cause of action accrued earlier, but they are prospective
in the sense that neither have the effect of reviving the
right of action which is already barred on the date of their
coming into operation, nor do they have effect of
extinguishing a right of action subsisting on that date.
D [Para 19) [857-B-D)
THE. YOUN (1899) Probate Division p 236; The King
vs. Chandra Dharma (1905) 2 KB 335; Yew Bon Tew v.
Kenderaan Bas Mara (1982) 3 All E.R. 833 - referred to.
E Bennion on Statutory Interpretation 5th Edn.(2008)
321 - referred to.
1.5 An accrued right to plead a time bar, which is
acquired after the lapse of the statutory period, is
nevertheless a right, even though it arises under an Act
F which is procedural and a right which is not to be taken
away pleading retrospective operation unless a contrary
intention is discernible from the statute. Therefore, unless
the language clearly manifests in express terms or by
necessary implication, a contrary intention a statute
G divesting vested rights is to be construed as prospective.
A statute, merely procedural is to be construed as
retrospective and a statute while procedural in nature
affects vested rights adversely is to be construed as
prospective. The manner of filing an appeal, under sub
H
• THIR.UMALAI CHEMICALS LIMITED v. UNION OF
INDIA & ORS.
section (2) of Section 19 of FEMA and the time within
843
A
which such an appeal has to be preferred and the power
conferred on the Tribunal to condone delay under the
proviso to sub-section (2) of Section 19 are matters of
procedure and act retrospectively, so as to cover causes
of action which arose under FERA. Since the appeal was B
filed under FEMA with an application for condonation of
delay such an appeal has to be considered by the
Tribunal under the proviso to sub-section (2) of Section
19 FEMA and if the Company shows sufficient cause for
not filing the appeal in time then the Tribunal can c
condone the delay and entertain the appeal, especially
when there is no accrued right to the respondent to plead
a time bar. [Para 20] [858-C-H]
Principles of Statutory Interpretation 12th Edition p 541
- referred to. D
1.6 The appellate Board under FERA, stood
dissolved and ceased to function when FEMA was
enacted. Therefore, any appeal against the order of the
adjudicating officer made under FERA, after FEMA came E
into force, had to (?e filed before the Appellate Tribunal
constituted under FEMA and· not to the Appellate Board
under FERA. Section 52 of FERA stipulates the limitation
for an appeal against the orders of the adjudicating officer
to the Appellate Board. It provides the period of limitation F
as 45 days but the Board may entertain an appeal after
the expiry of 45 days but not beyond 90 days. Under
FEMA, an appeal lies to the appellate tribunal constituted
under that Act and Section 19(2) provides that every
appeal shall be filed within 45 days from the date on G
which a copy of the order of the adjudicating authority
is received. The appellate tribunal is however,
empowered to entertain appeals filed after the expiry of
. 45 days if it is satisfied that there was sufficient cause for
the delay in filing the appeal. Though both Section 52(2) H
844 SUPREME COURT REPORTS [2011] 4 S.C.R.
A of FERA and Section 19(2) of FEMA provide a limitation
of 45 days and also give the discretion to the appellate
authority to entertain an appeal after the expiry of 45
days, if the appellant was prevented by sufficient cause
from filing an appeal in time, the appellate authority under
B FERA could not condone the delay beyond 45 days
whereas under FEMA, if the sufficient cause is made out,
the delay can be condoned without any limit. Any
provision relating to limitation is always regarded as
procedural and in the absence of any provision to the
c contrary, the law in force on the date of the institution of
the appeal, irrespective of the date of accrual of the cause
of action for the original order, would govern the period
of limitation. [Para 25] [864-B-G]
1.7 Section 52(2) can apply only to an appeal to the
D appellate Board and not to any appellate tribunal.
Therefore, irrespective of the fact that the adjudicating
officer had passed the orders with reference to the
violation of the provisions of FERA, as the appeal against
such order was to the appellate tribunal constituted
E under FEMA, necessarily Section 19(2) of FEMA alone
would apply and it is not possible to import the provisions
of Section 52(2) of FERA. The concern is with the appeals
to the Appellate Tribunal, limitation being a matter of
procedure, only that law that is applicable at the time of
F filing the appeal, would apply. Therefore, Section 19(2) of
FEMA and not Section 52(2) of FERA would apply. Under
Section 19(2), there is no ceiling in regard to the period
of delay that could be condoned by the appellate tribunal.
If sufficient cause is made out, delay beyond 45 days can
G also be condoned. The tribunal and the High Court
misdirected themselves in assuming that the period of
limitation was governed by Section 52(2) of FERA. [Para
26] [864-H; 865-A-D]
1.8 Clause (b) of sub-section (5) of Section 49 refers
H
• IHIRUMALAI CHEMICALS LIMITED v. UNION OF
INDIA & ORS.
845
to appeal preferred and pending before the Appellate A
Board under FERA at the time of repeal. The said clause
does not specifically refer to appeals preferred against
' adjudication orders passed under FEMA with reference
to causes of action which arose under FERA. The right
of appeal under FEMA has already been saved in respect B
of cause of action which arose under FERA however,
subject to the proviso to sub-section (2) of Section 19, in
the case of belated appeals. Section 49 of FEMA does not
seek to withdraw or take away the vested right of appeal
in cases where proceedings were initiated prior to repeal c
of FERA on 01.06.2000 or after. On a combined reading
of Section 49 of FEMA and Section 6 of General Clauses
Act, it is clear that the procedure prescribed by FEMA
only would be applicable in respect of an appeal filed
under FEMA though cause of action arose under FERA.
0
In fact, the time limit prescribed under FERA was taken
away under the proviso to sub-section (2) of Sectioi:i 19
and the Tribunal has been conferred with wide powers
to condone delay if the appeal is not filed within forty-five
days prescribed, provided sufficient cause is shown.
Therefore, the findings rendered by the Tribunal as well E
as the High Court that the Tribunal does not have
jurisdiction to condone the delay beyond the date
prescribed under FERA is not a correct understanding of
the law on the subject Therefore, the Appellate Tribunal
can entertain the appeal after the prescribed period of 45 F
days if it is satisfied, that there was sufficient cause for
not filing the appeal within the said period. Therefore, the
orders passed by the Tribunal and the High Court are set
aside and the matter is remitted back to the Tribunal for
· fresh consideration in accordance with law on the basis G
of the findings recorded. [Paras 27 to 29] [865-E-H; 866-
A-D]
Anant Gopa/ Sheorey v. State of Bombay AIR 1958 SC
915; Rao Shiv Bahadur Singh and Anr. vs. State of Vindhya H
846 SUPREME COURT REPORTS [2011] 4 S.C.R.
•
A Pradesh AIR 1953 SC 394; State of Punjab v. Mohar Singh
S/o Pratap Singh AIR 1955 SC 84; T. S. Baliah v. T. S.
Rangachari, /TO AIR 1969 SC 701; Gajraj Singh and Ors.
vs. State Transport Appellate Tribunal and Ors. (1997) 1 SCC
650; Gammon India Ltd. vs. Special Chief Secretary and Ors.
B (2006) 3 SCC 354; Harbanslal Sahnia and Anr. vs. IOC Ltd.
and Ors. (2003) 2 sec 107; L.K. Verma vs. HMT Ltd. and
Anr. (2006) 2 SCC 269 - referred to.
Case Law Reference:
c (2003) 2 sec 101 Referred to Para 9
(2006) 2 sec 269 Referred to Para 9
AIR 1957 SC 540 Referred to Para 15
(1975) 2 sec 840 Referred to Para 15
D
(1994) 4 sec 602 Referred to Para 15
(1999) 8 sec 16 Referred to Para 15
(2001) 8 sec 24 Referred to Para 15
E
(1899) Probate Division 236 Referred to Para 20
(1905) 2 KB 335 Referred to Para 20
(1982) 3 ALLER Referred to Para 20
F AIR 1958 SC 915 Referred to Para 24
AIR 1953 SC 394 Referred to Para 24
AIR 1955 SC 84 Referred to Para 24
G AIR 1969 SC 701 Referred to Para 24
(1997) 1 sec 650 Referred to Para 24
(2006) 3 sec 354 Referred to Para 24
H
• THIRUMALAI CHEMICALS LIMITED v. UNION OF 847
INDIA & ORS .
..
CIVIL APPELLATE JUR.ISDICTION : Civil Appeal No. A
3191-3194 of 2011.
From the Judgment & Order dated 24.07.2008 of the High
Court of Judicature at Bombay in Writ Petition Nos. 692, 1528,
1531 & 693 of 2008.
B
Mohan Jayakar, Uma, Javaid Muzaffar, Umesh Kumar
Khaitan for the Appellant.
Vivek Tankha, ASG, T.V. Ratnam, Rahul Kaushik, B.K.
Prasad, Anil Katiyar for the Respondents. c
The Judgment of the Court was delivered by
K. S. RADHAKRISHNAN, J. 1. Leave granted~
2. The question that has come up forconsideration in this 0
case is whether the Appellate Tribunal constituted under the
Foreign Exchange Managem·ent Act 1999 (in short FEMA) was
right in rejecting a belated appeal filed under Section 19 of
FEMA, applying the first proviso to sub section (2) of Section
52 of Foreign Exchange Regulation Act 1973 (in short FERA), E
instead of following the proviso to sub section (2) to Section
19 of FEMA. -
3. M/s Tirumalai Chemicals Limited (in short ·'the
Company') had import~d various consignments of benezene,
orthoxalene etc. for home consumption. For the said purpose, F
the Company had opened Letters of Credit bearing No.MLCO
4359096 and No.529/96048( on 28.09.96 and 07.08.96
respectively on their bankers ICICI Bank and Standard
Chartered Bank (authorized dealers). By letters dated 07.12.96
and 18.01.97 Exchange Control Copies of bills of entry (in short, G
ECC - bills of entry) in relation to those imports were forwarded
by the Company to the above mentioned Banks. As per the
provisions of Exchange Control Manual (in short ECM), the
H
848 SUPREME COURT REPORTS [2011] 4 S.C.R.
A authorized dealers had to submit the ECC-bills of entry
submitted by the importers (the Company) to the Reserve Bank
of India (in short RBI). The Company was under the bonafide
impression that the documents submitted by it were forwarded
by the authorized dealers to the RBI and that the RBI in turn had
B given due intimation to the Enforcement Directorate. The
Company on 22.04.2004 received a telephonic communication
from the office of the 3rd respondent viz., Directorate of
Enforcement, stating that it had passed various orders on
27.01.04 imposing a total penalty of Rs.9,33,63,453/- on the
C Company on the ground that it had contravened the provisions
of Sections 8(3), 8(4) of FERA read with sub-sections (3) and
(4) of Section 49 of FEMA. Copies of the orders dated
27.01.04 were then received by the Company on 22.04.04 on
request. From those orders the Company came to know that
the Directorate of Enforcement had issued four show cause
D notices dated 14.'.05.02 stating that the Company had
contravened Section 8(3), Section 8(4) of FERA read with para
7A.20 (Chapter 7) of ECM and was required to show cause
why adjudication proceedings be not initiated against the
Company under Section 49 of FEMA for contravention of the
E above mentioned provisions. Further, it was also stated that the
Company had failed to furnish the required bills/information/
documents and did not avail of the opportunity of hearing in
spite of notices issued to them on 29.08.02, 27.10.03 and
01.12.03. Orders dated 27.01.04 also indicated that an appeal
F would lie before the Appellate Tribunal after depositing the
amount of penalty imposed within 45 days from the date on
which the order was served. Reference was also made to
Section 19 read with Section 49(5)(a) of FEMA.
G 4. The Company on receipt of the above mentioned orders
dated 27.01.04 approached the authorized dealers and
enquired whether they had forwarded the ECC of bills of entry
to the RBI as required under the provisions of ECM. The ICICI
Bank vide their letters dated 12.05.04 informed the Company
H
• THIRUMALAI CHEMICALS UMIT;EO v, UNION OF
INDIA & ORS. [k.S. RAOHAKRISHNAN, J.]
849
that it had received ECC of bills of.entry, oh 20.01.97 with A
difference of value. The ICICI Sank thef.IJOrwarded a letter dated
15.05.04 to the RBI seeking its permission to accept the bills
of entry stating that the Company had submitted the relevant
documents on 20.01.97 with shortfall of value, The Standard
Chartered Bank also vide their letter dated 12.05.04 informed B
the RBI that they had also received the Exchange Control Copy
of bills of entry for the import in question from the appellant
Company on 09.12.96, but due to an inadvertent mistake had
reported in their BEF Return that bills of entry were not
submitted. The RBI vide letter dated nil of May, 2004 sent by c
registered AD informed the Enforcement Directorate as
follows:-
" ........ Please refer to the> outstanding entries
reported in their respective :s,E'f $ta_tement by the
captioned banks in respect o(M/s. T:irnrttatai Chemicals D·
Ltd., which was forwarded to y.()u by. u$,Jfl this connection
we advise that, based on the documents'and evidence
submitted by authorized dealer, we have deleted the
entries from our records and regularized the transactions
at our end as under :- E
(i) ICICI Bank confirmed that they had received EC copies
of Bill of Entry in respect of the transactions reported at
Sr.No.40 and Sr.No.1 of their BEF Statement referred to
above and the entry at Sr. No.28 of their BEF Statement F
was a repetition of entry at Sr.No.40 of the same
statement.
(ii) Standard Chartered Bank has also confirmed to us that
the relative EC copy of the Bill of Entry in respect of the
transaction reported in their BEF Statement was received G
by them ... .".
5. The Company had also sent a letter dated 17.05.04 to
the Enforcement Directorate stating that it was not due to the
mistake of the Company that the ECG :Of bills of entry were not H
850 SUPREME COURT REPORTS (2011] 4 S.C.R.
A forwarded to the Directorate of Enforcement in time, but due
to the mistake of the authorized dealer (Bank). RBI had
subsequently carried out necessary corrections and deleted the
entries from their records and regularized the transactions and
requested to drop the proceedings initiated against the
B Company.
6. The Company stated that it was under the bonafide
impression that respondents would drop the proceedings since
RBI had deleted the entries from the records and informed the
same to the Enforcement Directorate but nothing was heard
C from the Directorate and hence the Company was constrained
to file appeals against those orders on 02.08.04 before the
Appellate Tribunal for Foreign Exchange (in short the Tribunal)
vide Appeal nos. 787, 788, 789 and 790 of 2004 with an
application under Section 5 of the Limitation Act read with
D Section 19 and Section 49(5) (a) of FEMA for condonation of
delay.
7. The Tribunal, however, without going into the merits of
the case dismissed the appeals on the ground of delay by its
E order dated 25.10.2007. The operative portion of the said order
reads as follows:-
" ..... Therefore, these appeals when filed after 90
days from the date of receipt of the order has to be
dismissed and the exceeding period cannot be condoned
F by this Tribunal because of legislative mandate couched
in clear language.
For the reasons stated herein above, these appeals
are dismissed because these appeals have been filed
G after a total period of 90 days from the date of receipt of
impugned order beyond which this Tribunal is not
empowered to condone the delay."
8. The Company aggrieved by the above mentioned order
H preferred writ petitions nos. 692, 1528, 1531 and 693 of 2008
• THIRUMALAI CHEMICALS LIMITED v. UNION OF
INDIA & ORS. [K.S. RADHAKRISHNAN, J.]
851
before the Bombay High Court for quashing the order dated A
25.10.2007 of the Tribunal as also the order dated 27 .01.04
passed by the third respondent contending that the Tribunal was
not justified in dismissing the appeals on the ground of delay.
The High Court, however, dismissed all the writ petitions by the
following order dated 24.07.2008:- B
"There is no dispute that the appeal was filed beyond
the period of 90 days. Therefore, the tribunal did not have
jurisdiction to condone the delay. The learned counsel,
then, submitted that we should consider these petitions as
the petitions against the original order. C
In our opinion, it will not be appropriate to entertain
these petitions as petitions against the original order. The
Parliament has provided remedy of an appeal against the
original order and has provided for period of limitation for o
filing that appeal. The Parliament has also provided that
delay beyond a certain period cannot be condoned by the
Tribunal/Appellate authority. The Petitioners have allowed
that remedy of appeal to be barred, therefore, now to
entertain these petitions as petitions against the original E
order would amount to permitting the Petitioners to frustrate
the scheme of the Legislation. The scheme of the statute
is that a challenge to the original order is to be raised by
an appeal which is to be filed within a particular period.
The extra ordinary jurisdiction of this court under the
F
Constitution cannot be permitted to be used by the
Petitioners. who have allowed their ordinary remedy to be
barred. Petitions are, therefore, rejected."
9. Mr. Harish Salve, learned senior counsel appearing on
behalf of the appellants submitted that the authorized dealer G
(Bank) had owned up their mistake and had informed the RBI
accordingly and hence there was no reason to penalize the
Company for no fault of it. Learned counsel also submitted that
the Tribunal had committed a mistake in holding that it had no
power to condone the delay beyond 90 days. He also submitted H
852 SUPREME COURT REPORTS [2011] 4 S.C.R. •
A that even if the Tribunal has no power to condone the delay the
High Court could have entertained the writ petitions under
Article 226 of the Constitution of India when the impugned order
of the Tribunal was manifestly illegal. Learned counsel further
submitted that in any view of the matter High Court under Article
8 226 of the Constitution of India has the power to condone delay
in exercise of its extra ordinary jurisdiction and then direct the
Tribunal to consider the appeal on merits. Reference was made
to the judgments of this Court in Harbanslal Sahnia & Anr. vs.
JOG Ltd. & Ors. (2003) 2 SCC 107, L.K. Verma vs. HMT Ltd.
c & Anr. (2006) 2 sec 269.
10. Shri Vivek Tankha, Learned Additional Solicitor
General, appearing for the respondents 'feferred to the first
proviso to sub section (2) of Section 52 of FERA and submitted
that the Tribunal was justified in holding that it had no power to
D condone the delay beyond a period of 90 days. Ld. ASG also
submitted that when a party has availed of the statutory remedy
of appeal and lost on the ground of delay the High Court can
not exercise its extraordinary jurisdiction under Article 226 I 227
of the Constitution of India.
E
11. We are in this case called upon to decide the question
whether the Tribunal was right in dismissing the appeals
preferred under Section 19(1) of FEMA, by applying the first
proviso to sub section (2)of Section 52 of FERA holding that it
had no power to condone the delay beyond 90 days from the
F date on which the order was served on the person committing
the contravention. The Tribunal and the High Court proceeded
on the premises that since the cause of action arose when
FERA was in force the period of limitation for filing an appeal
before the Tribunal even after coming into force of FEMA is as
G provided under the first proviso to sub section (2) of Section
52 of FERA. Admittedly, in this case the cause of action arose
when FERA was in force, but show cause notices and
impugned orders were issued when FEMA was in force and
the appeals were also preferred under sub section (1) of
H
• THIRUMALAI CHEMICALS LIMITED v. UNION OF
INDIA & ORS. [K.S. RADHAKRISHNAN, J.]
853
Section 19 of FEMA. Therefore, the important question that A
.arises for consideration is whether limitation for filing the
appeal has to be considered under the proviso to sub section
(2)of Section 19 of FEMA or under the first proviso to sub
section ( 2) of Section 52 of FERA. In order to answer the
above question, it is nepessary to examine the scope and B
ambit of Section 52 of FERA, Section 19 , 49 of FEMA and
Section 6 of the General Clauses Act, 1897.
12. FERA was enacted to consolidate and amend the law
relating to certain payments dealing in foreign exchange and c
securities, transactions indirectly affecting the foreign exchange
and import and export and import of currency, for conservation
of foreign exchange resources of the country and proper
utilization thereof in the interest of economic development of
the country. Sections 50 and 51 of FERA were the penal
0
provisions which empowered the authority to impose penalty
on persons who had contravened some of the provisions of the
Act. An appeal was provided under FERA against the order
of adjudication before the Foreign Exchange Regulation
Appellate Board (in short the 'Board') under Section 52 of that E
Act within a period of 45 days from the date on which the order
was served on the person committing the contravention. The
Board was also empowered to entertain any appeal after the
expiry of the said period of 45 days but not after 90 days from
the date on which the order was served on the person if it was
satisfied that the person was prevented by sufficient cause in F
not filing the appeal in time. It is useful to extract that provision
for easy reference :-
52. Appeal to Appellate Board -(1) The Central
Government may, by notification in the Official Gazette, G
constitute ,an Appellate Board to be called the Foreign
Exchange Regulation Appellate Board consisting of a
Chairman [being a person who has for at least ten years
held a civil judicial post or who has been a member of the
Central Legal Service (not below Grade I) for .at least three H
854 SUPREME COURT REPORTS [2011] 4 S.C.R.
•
A years or who has been in practice as an advocate for at
least ten years] and such number of other members, not
exceeding four, to be appointed by the Central Government
for hearing appeals against the orders of the adjudicating
officer made under Section 51.
B
(2) Any person aggrieved by such order may, [on payment
of such fee as may be prescribed and] after depositing the
sum imposed by way of penalty under Section 50 and
within 45 days from the date on which the order is served
on the person committing the contravention, prefer an
c appeal to the Appellate Board:
Provided that the Appellate Board may entertain any
appeal after the expiry of the said period of 45 days, but
not after 90 days, from the date aforesaid if it is satisfied
D that the appellant was prevented by sufficient cause from
filing the appeal in time:
Provided further that where the Appellate Board is of
opinion that the deposit to be made will cause undue
E hardship to the appellant, it may, in its own discretion,
dispense with such a deposit either unconditionally or
subject to such conditions as it may deem fit.
"
F 13. FERA was repealed by FEMA which came into force
with effect from 01.06.2000. Chapter IV of FEMA deals with
contravention of penalties. Section 13 of FEMA empowers the
authorized officers to impose penalties for contravention of
certain provisions of the Act. Failure to make full payment of
G penalty, may attract civil imprisonment subject to the provisions
of sub section (2) of Section 19. Chapter V of the Act deals
with adjudication and appeal. Section 19 deals with the appeal
to the Appellate Tribunal. Sub section (2) of Section 19 says
that every appeal under sub-section(1) shall be filed within a
H period of 45 days from the date on which the copy of the order
• THIRUMALAI CHEMICALS LIMITED v. UNION OF
INDIA & ORS. [K.S. RADHAKRISHNAN, J.]
855
made by the adjudicating authority or the Special Director A
(Appeals) is received by the aggrieved person. The Appellate
Tribunal is also empowered to entertain the appeals filed after
the expiry of the said period of 45 days if it is satisfied that there
was sufficient cause for not filing the appeal within that period.
Law is well settled that the manner in which the appeal has to B
be filed, its form and the period within which the same has to
be filed are matters of procedure, while the right conferred on
a party to file an appeal is a substantive right. The question is,
while dealing with a belated appeal under Section 19(2) of
FEMA, the application for condonation of delay has to be dealt c
with under the first proviso to sub- section (2) of Section 52 of
FERA or under the proviso to sub section (2) of Section 19 of
FEMA. For answering that question it is necessary to examine
the law on the point.
D
Substantive and Procedural Law:
14. Substantive law refers to body of rules that creates,
defines and regulates rights and liabilities. Right conferred on
a party to prefer an appeal against an order is a substantive
right conferred by a statute which remains unaffected by E
subsequent changes in law; unless modified expressly or by
necessary implication. Procedural law establishes a
mechanism for determining those rights and liabilities and a
machinery for enforcing them. Right of appeal being a
substantive right always acts prospectively. It is trite law that F
every statute prospective unless it is expressly or by necessary
implication made to have retrospective operation. Right of
appeal may be a substantive right but the procedure for filing
the appeal including the period of limitation cannot be called a
substantive right, and aggrieved person cannot claim any G
vested right claiming that he should be governed by the old
provision pertaining to period of limitation. Procedural law is
retrospective meaning thereby that it will apply even to acts or
transactions under the repealed Act.
856 SUPREME COURT REPORTS [2011] 4 S.C.R.
•
A 15. Law on the subject has also been elaborately dealt with
by this Court in various decisions and reference may be made
to few of those decisions. This Court in Garikapati Veeraya vs.
N. Subbiah Chaudhry & Ors. AIR 1957 SC 540, New India
Insurance Company Limited Vs. Smt. Shanti Mishra (1975)
B 2 SCC 840, Hitendra Vishnu Thakur & Ors. vs. State of
Maharashtra & Ors. (1994) 4 SCC 602; Maharaja Chintamani
Saran Nath Shahdeo vs. State of Bihar & Ors. (1999) 8 SCC
16; Shyam Sundar & Ors. vs. Ram Kumar & Anr. (2001) 8 SCC
24, has elaborately discussed the scope and ambit of an
C amending legislation and its retrospectivity and held that every
litigant has a vested right in substantive law but no such right.
exists in procedural law. This court has held the law relating to
forum and limitation is procedural in nature whereas law relating .
to right of appeal even though remedial is substantive in nature.
D
16. Therefore, unless the language used plainly manifests
in express terms or by necessary implication a contrary
intention a statute divesting vested rights is to be construed as
prospective, a statute merely procedural is to be construed as
retrospective and a statute which while procedural in its
E character, affects vested rights adversely is to be construed as
prospective.
17. Right of appeal conferred under Section 19(1) of
FEMA is therefore a substantive right. The procedure for filing
F an appeal under sub-section (2) of Section 19 as also the
proviso to sub-section (2) of Section 19 conferring power on
the Tribunal to condone delay in filing the appeal if sufficient
cause is shown, are procedural rights.
G 18. We have already indicated that the proviso to sub-
section(2) of Section 19 operates retrospectively, but the
question is in that process, whether it impairs or takes away ·
any accrued right, to plead a time bar and on facts whether the
Company has lost its right of appeal to the Tribunal under
H FEMA.
• THIRUMALAI CHEMICALS LIMITED v. UNION OF
INDIA & ORS. [K.S. RADHAKRISHNAN, J.]
857
Law of Limitation A
19. Law of limitation is generally regarded as procedural
and its object is not to create any right but to prescribe periods
within which legal proceedings be instituted for enforcement of
rights which exist under substantive law. On expiry of the period 8
of limitation, the right to sue comes to an end and if a particular
right of action had become time barred under the earlier statute
of limitation the right is not revived by the provision of the latest
statute. Statutes of limitation are thus retrospective insofar as
they apply to all legal proceedings brought after their operation C
for enforcing cause of action accrued earlier, but they are
prospective in the sense that neither have the effect of reviving
the right of action which is already barred on the date of their
coming into operation, nor do they have effect of extinguishing
a right of action subsisting on that date. Bennion on Statutory
Interpretation 5th Edn.(2008) Page 321 while dealing with
0
retrospective operation of procedural provisions has stated that
provisions laying down limitation periods fall into a special
category and opined that although prima facie procedural, they
are capable of effectively depriving persons of accrued rights
and therefore they need be approached with caution. E
20. Learned author in order to establish the above
proposition referred to the decision of the Court of Appeal in
The Ydun case [THE YOUN (1899) Probate Division at page
236 (The Court of Appeal) where the Court held that the F
amending legislation dealt with procedure only and therefore
applied to all actions whether commenced before or after the
passing of the Act and even in respect of previously accrued
rights. The principle laid down in 'The Ydun'was applied in The
King vs. Chandra Dharma (1905) 2 KB 335 and it was held G
that if a statute shortening the time within which proceedings
can be taken is retrospective then it is impossible to give good
reason, why a statute extending the time within which
proceedings be taken, should not be held to be retrospective.
The Judicial Committee of Privy Council in Yew Bon Tew v. H
858 SUPREME COURT REPORTS [2011] 4 S.C.R.
A Kenderaan Bas Mara (1982) 3 All E.R. 833, opined that
whether statute has retrospective effect, cannot in all cases
safely be applied by classifying statute as procedural or
substantive and pointed out in certain situation the Court would
rule against a retrospective operation. Limitation provisions
B therefore can be procedural in the context of one set of facts
but substantive in the context of different set of facts because
rights can accrue to both the parties. In such a situation, test is
to see whether the statute, if applied retrospectively to a
particular type of case, would impair existing rights and
c obligations. An accrued right to plead a time bar, which is
acquired after the lapse of the statutory period, is nevertheless
a right, even though it arises under an Act which is procedural
and a right which is not to be taken away pleading retrospective
operation unless a contrary intention is discernible from the
0 statute Therefore, unless the language clearly manifests in
express terms or by necessary implication, a contrary intention
a statute divesting vested rights is to be construed as
prospective. A statute, merely procedural is to be construed as
retrospective and a statute while procedural in nature affects
E vested rights adversely is to be construed as prospective. The
manner of filing an appeal, under sub section (2) of Section 19
of FEMA and the time within which such an appeal has to be
preferred and the power conferred on the Tribunal to condone
delay under the proviso to sub-section (2) of Section 19 are
matters of procedure and act retrospectively, so as to cover
F causes of action which arose under FERA. Since the appeal
was filed under FEMA with an application for condonation of
delay such an appeal has to be considered by the Tribunal
under the proviso to sub-section(2) of Section 19 FEMA and if
the Company shows sufficient cause for not filing the appeal
G in time then the Tribunal can condone the delay and entertain
the appeal, especially when there is no accrued right to the
respondent to plead a time bar. The legal position is
summarized thus by Justice G.P. Singh in Principles of
Statutory Interpretation (12th Edition-Page 541) thus:-
H
• THIRUMALAI CHEMICALS LIMITED v. UNION OF
INDIA & ORS. [K.S. RADHAKRISHNAN, J.]
859
"Statutes of Limitation are thus retrospective in so far as A
they apply to all legal proceedings brought after their
operations for enforcing causes of action accrued
earlier .... "
21. We may also examine whether Section 49 of FEMA, B
which is the repealing and saving clause, has in any way taken
away the right of appeal under FEMA for cause of action which
arose under FERA expressly or by necessary implication and
also whether it has any effect on the retrospectivity of the
procedural provision under the proviso to sub-section (2) of c
section 19. For easy reference we may extract Section 49 of
FEMA and Section 6 of the General Clauses Act, 1897.
"49. Repeal and Saving -(1) The Foreign
Exchange Regulation Act, 1973 (46 of 1973) is hereby
repealed and the Appellate Board constituted under sub- D
section (1) of section 52 of the said Act (hereinafter
referred to as the repealed Act) shall stand d.issolved.
(2) On the dissolution of the said Appellate Board, the
person appointed as Chairman of the Appellate Board and E
every other person appointed as Member and holding
office as such immediately before such date shall vacate
their respective offices and no such Chairman or other
person shall be entitled to claim any compensation for the
premature termination of the term of his office or of any F
contract of service.
'
(3) Notwithstanding anything cohtained in any other laws
for the time being in force, no court shall take cognizance
of an offence under the repealed Act and no adjudicating
officer shall take notice of any contravention under section G
51 of the repealed Act after the expiry of a period of two
years from the date of the commencement of this Act.
(4) Subject to the provisions of sub-section (3) all offences
committed under the repealed Act shall continue to be H
860 SUPREME COURT REPORTS [2011] 4 S.C.R.
•
A governed by the provisions of the repealed Act as if that
Act had not been repealed.
(5) Notwithstanding such repeal, -
(a) anything done or any action taken or purported
B
to have been done or taken including any rule, notification,
inspection, order or notice made or issued or any
appointment, confirmation or declaration made or any
licence, permission, authorization or exemption granted or
any document or instrument executed or any direction
c given under the Act hereby repealed shall, in so far as it
is not inconsistent with the provisions of this Act, be
deemed to have been done or taken under the
corresponding provisions of this Act;
D (b) any appeal preferred to the Appellate Board
under sub-section (2) of section 52 of the repealed Act but
not disposed of before the commencement of this Act
shall stand transferred to and shall be disposed of by the
Appellate Tribunal constituted under this act;
E
(c) every appeal from any decision or order of the
Appellate Board under sub-section (3) or sub-section (4)
of section 52 of the repealed Act shall, if not filed before
the commencement of this act, be filed before the High
Court within a period of sixty days of such commencement;
F
Provided that the High Court may entertain such appeal
after the expiry of the said period of sixty days if it is
satisfied that the appellant was prevented by sufficient
cause from filing the appeal within the said period.
G
(6) save as otherwise provided in sub-section(3), the
mention of particular matters in sub-sections (2), (4) and
(5) shall not be held to prejudice or affect the general
application of section 6 of the General Clauses Act, 1897
(10 of 1897), with regard to the effect of repeal."
H
• THIRUMALAI CHEMICALS LIMITED v. UNION OF
INDIA & ORS. [K.S. RADHAKRISHNAN, J.]
861
Section 6 of the General Clauses Act reads as under:- A
6. Effect of repeal - Where this Act, or any [Central
Act ] or Regulation made after the commencement of this
Act, repeals any enactment hitherto made or hereafter to
be made, then, unless a different intention appears, the 8
repeal shall not -
(a) revive anything not in force or existing at the time
at which the repeal takes effect; or·
(b) affect the previous operation of any enactment C
so repealed or anything duly done or suffered
thereunder; or
(c) affect any right, privile~e obligation or liability
acquired, accrued or incurred under any enactment
0
so repealed; or
(d) affect any penalty, forfeiture or punishment
incurred in respect of any offence committed
against any enactment so repealed; or
E
(e) affect any investigation legal proceeding or
remedy in respect of any such right, privilege,
obligation, liability, penalty, forfeiture or punishment
as aforesaid; and
any such investigation, legal proceeding or remedy may F
be instituted, continued or enforced, and any such penalty,
forfeiture or punishment may be imposed as if the
repealing Act or Regulation n.ad not been passed."
Repealing and saving clause is a residuary provision which G
envisages that notwithstanding such repeal of FERA there
would be application of Section 6 of the General Clauses Act
with regard to the effect of repeal Which is discernible from sub
section (6) of Section 49 of the Act.Sub-section (1) of Section
49 of FEMA states that FERA stands repealed and the H
862 SUPREME COURT REPORTS [2011] 4 S.C.R. •
A Appellate Board constituted under sub-section (1) of Section
52 of the said Act stands dissolved. Sub-section (3) of Section
49 incorporates a sunset clause. The said sub-section begins
with a non-obstante clause overriding any other enactment and
states that no court shall take notice of any contravention under
B Section 51 of the repealed Act after the expiry of two years from
the date of commencement of FEMA on 1.6.2000. Sub-section
(4) of Section 49 stipulates that subject to the provisions of sub-
section(3) all offences committed under the repealed Act shall
continue to be governed by the provisions of the repealed Act
c as if that Act had not been repealed.
22. Sub-section (5) of Section 49 of FEMA consists of
three clauses (a), (b) and (c). Clause (a) states that anything
done or any action taken or purported to have been done or
taken including any rule, notification, inspection, order or notice
D made or issued or any appointment, confirmation or
declaration made or any license, permission, authorization or
exemption granted or any document or instrument executed
under the repealed act i.e. FERA to the extent they are not
inconsistent with the provisions of this Act, are deemed to be
E done or taken under the corresponding provisions of this Act.
The said provision has the effect of incorporating or making a
general declaration that the existing rules, notifications,
declarations, authorization and exemptions granted under
FERA will continue to apply in spite of repeal of FERA and after
F enactment of FEMA as long as they are not in consistent with
FEMA. Clause (b) of sub-section (5) of Section 49 states that
any appeal preferred before the Appellate Board under sub-
section (2) of Section 52 of FERA but not disposed of before
the commencement of this Act shall stand transferred to and
G shall be disposed of by the Appellate Tribunal constituted under
this Act. Sub-section (6) to Section 49 of FEMA deals with the
application of Section 6 of the General Clauses Act. The first
part of the said sub-section protects the sunset clause and the
two year limitation period for commencement of proceedings.
H The expression "save as otherwise provided in sub-section (3)"
• THIRUMALAI CHEMICALS LIMITED v. UNION OF
' INDIA & ORS. [K.S. RADHAKRISHNAN, J.]
863
protects the sunset clause in spite of second portion of sub- A
Section 6 and the second portion of sub-section (6) of Section
49 expressly makes Section 6 of the General Clauses Act,
1897 applicable in spite. of repeal of FERA.
23. Section 6 of the General Clauses Act, 1897 which
8
protects the rights,. obligations and actions and liabilities
applies in spite of repeal of FERA subject to two years
limitation period specified in sub-section (3) of Section 49 for
initiation of proceedings. Therefore, in view of Section 6 of the
General Clauses Act read with sub-section (3) of Section 49
of FEMA, proceedings for violation of FERA can be instituted C
within the sunset period of two years with effect from 1.6.2000
till 31.5.2002. But for sub-section(3) there will be no limitation
period of two years in view of Section 6 of General Clauses
Act, 1897 read with sub-section (4) of Section 49 of FEMA.
D
24. We have dealt with the above mentioned repeal and
saving clause to highlight the application of Section 6 of the
General Clauses Act, 1897 which provides that where an Act
is repealed then unless a different intention appears, the repeal
shall not affect any right or liability acquired or incurred under E
the repealed enactment or any legal proceeding initiated in
respect of such right or liability and the legal proceedings may
continue as if the repealing Act has not been passed. The
saving clause thus aimed to preserve the legal effect and
consequence of things done though those effects and F
consequences projected at the time when FERA was in force.
The scope and ambit of such repeal and saving clauses have
been considered by this Court in various decisions. Reference
may be made to the decisions of this Court reported in Anant
Gopal Sheorey v. State of Bombay, AIR 1958 SC 915, Rao G
Shiv Bahadur Singh & Anr. vs. State of Vindhya Pradesh, AIR
1953 SC 394, State of Punjab v. Mohar Singh S/o Pratap
Singh, AIR 1955 SC 84, T.S. Ba/iah v. T.S. Rangachari, /TO,
AIR 1969 SC 701; Gajraj Singh & Ors. vs. State Transport
A
864 SUPREME COURT REPORTS [2011] 4 S.C.R.
Appellate Tribunal & Ors. (1997) 1 SCC 650; Gammon India
•
Ltd. vs. Special Chief Secretary & Ors. (2006) 3 SCC 354.
25. The appellate Board under FERA, it may be noted
stood dissolved and ceased to function when FEMA was
B enacted. Therefore, any appeal against the order of the
adjudicating officer made under FERA, after FEMA came into
force, had to be filed before the Appellate Tribunal constituted
under FEMA and not to the Appellate Board under FERA.
Section 52 of FERA stipulates the limitation for an appeal
C against the orders of the adjudicating officer to the Appellate
Board. It provides the period of limitation as 45 days but the
Board may entertain an appeal after the expiry of 45 days but
not beyond 90 days. Under FEMA, an appeal lies to the
appellate tribunal constituted under that Act and Section 19(2)
provides that every appeal shall be filed within 45 days from
D the date on which a copy of the order of the adjudicating
authority is received. The appellate is however empowered to
entertain appeals filed after the expiry of 45 days if it is satisfied
that there was sufficient cause for the delay in filing the appeal.
Though both Section 52(2) of FERA and Section 19(2) of
E FEMA provide a limitation of 45 days and also give the
discretion to the appellate authority to entertain an appeal after
the expiry of 45 days, if the appellant was prevented by sufficient
cause from filing an appeal in time, the appellate authority
under FERA could not condone the delay beyond 45 days
F whereas under FEMA, if the sufficient cause is made out, the
delay can be condoned without any limit. The question we have
already pointed out is whether Section 52(2) of FERA or
Section 19(2) of FEMA will govern the appeal. As noticed
above, any provision relating to limitation is always regarded
G as procedural and in the absence of any provision to the
contrary, the law in force on the date of the institution of the
appeal, irrespective of the date of accrual of the cause of action
for the original order, will govern the period of limitation.
26. Section 52(2) can apply only to an appeal to the
H
• THIRUMALAI CHEMICALS LIMITED v. UNION OF 865
INDIA & ORS. [K.S. RADHAKRISHNAN, J.]
appellate Board and not to any appellate tribunal. Therefore, A
irrespective of the fact that the adjudicating officer had passed
the orders with reference to the violation of the provisions of
FERA, as the appeal against such order was to the appellate
tribunal constituted under FEMA, necessarily Section 19(2) of
FEMA alone will apply and it is not possible to import the B
provisions of Section 52(2) of FERA. As we are not concerned
with the appeals to Appellate Board, but appeals to the
Appellate Tribunal, limitation being a matter of procedure, only
that law that is applicable at the time of filing the appeal, would
apply. Therefore, Section 19(2) of FEMA and not Section 52(2) c
of FERA will apply. As noticed above, under Section 19(2),
there is no ceiling in regard to the period of delay that could
be condoned by the appellate tribunal. If sufficient cause is
made out, delay beyond 45 days can also be condoned. The
tribunal and the High Court misdirected themselves in assuming
0
that the period of limitation was governed by Section 52(2) of
FERA.
27. We have already indicated that clause (b) of sub-
section (5) of Section 49 refers to appeal preferred and
pending before the Appellat~ Board under FERA at the time E
of repeal. The said clause does not specifieally refer to appeals
preferred against adjudication orders passect under FEMA with
reference to causes of action which arose under FERA. We
have already noticed the right of appeal under FEMA has
already been saved in respect of cause of action which arose F
under FERA however subject to the proviso to sub-section (2)
of Section 19, in the case of belated appeals.
28. Above discussion will clearly demonstrate that Section
49 of FEMA does not seek to withdraw or take away the vested G
right of appeal in cases where proceedings were initiated prior
to repeal of FERA on 01.06.2000 or after. On a combined
reading of Section 49 of FEMA and Section 6 of General
Clauses Act, it is clear that the procedure prescribed by FEMA
only would be applicable in respect of an appeal filed under H
866 SUPREME COURT REPORTS [2011] 4 S.C.R.
A FEMA though cause of action arose under FERA. In fact, the
time limit prescribed under FERA was taken away under the
· proviso to sub-section (2) of Section 19 and the Tribunal has
been conferred with wide powers to condone delay if the
appeal is not filed within forty-five days prescribed, provided
B sufficient cause is shown. Therefore, the findings rendered by
the Tribunal as well as the High Court that the Tribunal does
not have jurisdiction to condone the delay beyond the date
prescribed under FERA is not a correct understanding of the
law on the subject.
c 29. We, therefore, hold that the Appellate Tribunal can
entertain the appeal after the prescribed period of 45 days if it
is satisfied, that there was sufficient cause for not filing the
appeal within the said period. We are therefore inclined to set
aside the orders passed by the Tribunal and the High Court and
D remit the matter back to the Tribunal for fresh consideration in
accordance with law on the basis of the findings recorded by
us. We order accordingly.
30. The appeals stand disposed of accordingly.
N.J. Appeals disposed of.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.