THE VICE CHAIRMAN & MANAGING DIRECTOR, CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LTD.& ANR.versusSHISHIR REALTY PRIVATE LIMITED & ORS. ETC
- Citation
- 2021 INSC 797
- Decided
- 29 November 2021
- Disposal
- Dismissed
- Bench
- N V RAMANA
Holding
The Supreme Court set aside CIDCO’s order cancelling the lease, holding that the enquiry violated natural justice, the change of land use and subdivision were within contractual powers, and no public‑interest loss was shown.
Summary
The City and Industrial Development Corporation of Maharashtra (CIDCO) invited a tender for leasing land for hotel development and allotted the plot to the highest bidder, Metropolis Hotels, which later changed the land use and subdivided the plot, assigning part to Shishir Realty. Complaints of irregularities led to a suo‑motu enquiry, a show‑cause notice, and CIDCO’s cancellation of the lease deeds, which the High Court quashed. On appeal, the Supreme Court examined whether the cancellation violated principles of natural justice, the contractual terms, and the doctrine of promissory estoppel. The Court held that the enquiry was conducted without proper hearing, the change of land use and subdivision were within the statutory powers granted by the tender documents, and CIDCO failed to demonstrate any public‑interest loss. Consequently, the cancellation order was set aside and the appeals dismissed.
Issues considered
- The validity of CIDCO’s cancellation of the lease deeds on grounds of alleged tender irregularities
- Whether the change of land use and subdivision of the allotted plot were permissible under the tender and allotment terms
- Whether the enquiry and cancellation complied with the principles of natural justice
- The applicability of the doctrine of promissory estoppel against a public authority in this context
- Whether the State proved any public‑interest loss justifying reversal of the contract
Legislation cited
- Companies Act
- Indian Contract Act
- Indian Penal Code, 1860s. 120(b), s. 405, s. 406, s. 420
- Maharashtra Co-operative Societies Act
- Partnership Acts. 4
- Public Trust Act
- Society Registration Act
Subjects
Judgment
190 [2021]REPORTS
SUPREME COURT 13 S.C.R.190 [2021] 13 S.C.R.
A THE VICE CHAIRMAN & MANAGING DIRECTOR, CITY AND
INDUSTRIAL DEVELOPMENT CORPORATION OF
MAHARASHTRA LTD.& ANR.
v.
SHISHIR REALTY PRIVATE LIMITED & ORS. ETC
B
(Civil Appeal Nos. 3956-3957 of 2017)
NOVEMBER 29, 2021
[N. V. RAMANA, CJI, VINEET SARAN AND
SURYA KANT, JJ.]
C
Government contracts: Judicial review – Scope of – On facts,
appellant (CIDCO) invited tender for lease of land for the
development of Hotels – Issuance of allotment letter in favour of
the highest bidder – Complaints regarding irregularities in allotment
of plots of land, change of user and deviation from the terms and
D conditions of the tender – On the basis of preliminary enquiry,
issuance of notice to the highest bidder and the respondent-lessee
by the newly appointed Vice Chairman – Thereafter, cancellation
of lease deed, pursuant to the enquiry – Writ petitions – High Court
quashed the cancellation order – On appeal, held: There is an
element of abuse of bureaucratic power behind subsequent change
E
in the tender allotment – When a contract is being evaluated, the
mere possibility of more money in the public coffers, does not in
itself serve public interest – Blanket claim by the State claiming loss
of public money cannot be used to forgo contractual obligations –
On facts, post-decisional hearing given to respondent-lessee was
F just to sanctify the process of cancellation – Change of usage and
the subsequent division was within the statutory limitations – Thus,
the earlier undertakings taken by the appellant-authorities cannot
be set aside with the change of person in power, without any rhyme
or reason – Phenomenon of ‘regime revenge’ is detrimental to the
constitutional values and rule of law – Equity demands that when
G
the State failed to produce an iota of evidence of either financial
loss or any other public interest that has been affected, it should be
compelled to fulfill its promises – Thus, the order of CIDCO, inter
alia, annulling the allotment on hyper-technical grounds cannot be
sustained for being contrary to the doctrine of fairness, and is set
H aside – Judicial restraint.
190
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 191
LTD. v. SHISHIR REALTY PVT. LTD.
Government contracts: Tender process – Judicial review of – A
Power of constitutional courts – Explained.
Government contracts: Constitutional factors – Satisfaction
of – Held: Governmental bodies being public authorities are
expected to uphold fairness, equality and rule of law even while
dealing with contractual matters – Right to equality u/Art. 14 abhors B
arbitrariness – Public authorities have to ensure that no bias,
favouritism or arbitrariness are shown during the bidding process,
unless public interest demands otherwise – Degree of compromise
of any private legitimate interest must correspond proportionately
to the public interest, so claimed – On mere grounds of public interest
or loss to the treasury, the successor public authority cannot undo C
the work undertaken by the previous authority – In that case,
businessmen would be hesitant to enter Government contract or
make any investment.
Administrative law: Administrative orders – Principle of
natural justice – Significance of – Held: Natural justice is an D
important aspect while viewing the administrative orders – To
maintain rule of law, effective natural justice is to be provided to
affected parties, before a decision is taken – Any attempt by authority
to evade the requirement of providing effective hearing before
reaching a conclusion, cannot pass the muster. E
Dismissing the appeals, the Court
HELD: 1.1 The Constitution of India allows the government
to enter into contracts and perform certain commercial activities.
Due to increase in government business, there is a requirement
of this Court to uphold certain discretion accruing to the F
government and disallow certain conduct in light of prevailing
circumstances. Merely instilling an agency with discretion may
not be prohibited by the Constitution, rather it is unfettered use
of such discretion, that is prohibited; the Constitution frowns upon
those decisions which are taken in gross abuse of law. [Para G
25][210-C]
1.2 Being governed under “rule of law” every action of the
State or its instrumentality while exercising its executive powers
must met the aforesaid requirements. While recognising the
existing principle of freedom to enter or not to enter into contracts
H
192 SUPREME COURT REPORTS [2021] 13 S.C.R.
A by the state and its instrumentalities, the manner, method and
motive behind the aforesaid decision can be subjected to judicial
review on the touchstone of equality, fairness, proportionality and
natural justice. The decision of the executive must strike a
balance with the alleged violation with that of the penalty imposed.
This Court, in many of its orders reviewing tender conditions,
B
has vouched for providing sufficient discretion and independence
to administrative authorities so as to enable them to perform
their duties in the interest of the public. Further, the observation
of judicial restraint while reviewing such contracts is a continuing
trend. The power of judicial review accorded to Constitutional
C Court of India and its jurisdiction is supervisory. [Para 26, 27][210-
F-H; 211-A]
1.3 The principles elucidated in Tata Cellular case acquire
importance as the efficacy of commercial activities in the public
sector increases greatly. It appears that public interest litigation
D has opened a large window to entertain any tender, regardless of
scale, which are now sought to be challenged as a matter of
routine. Such disruption could hardly have been the objective of
expanding the need of Constitutional Review. Close scrutiny of
minute details, contrary to the view of the tendering authority,
makes execution of contracts in the public sector a cumbersome
E exercise. Often, it is the case that parties entertain the idea of a
long-drawn-out litigation at the very threshold itself. The purpose
of imbibing the spirit of competition in a process such as that of
the bidding process, is lost in this meandering exercise and delays
suffered due to pending litigation. This causes great disadvantage
F to the government and public sector in general. This Court, in
appropriate cases while interpreting the contract, can restrict
the review mechanism by not inuring to the interpretation so
provided by third parties or parties competing for the tender,
unless the impugned interpretation is shown to be gross abuse
of law. The object of judicial review cannot be that in every
G contract where some parties lose out, a second opportunity is
provided to such parties to pick holes so as to disqualify successful
parties, on grounds which even the party floating the tender find
to be without merit. [Para 30][212-E-H; 213-A-B]
H
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 193
LTD. v. SHISHIR REALTY PVT. LTD.
1.4 The perusal of the materials produced on record shows A
that the initiation of the enquiry by the Principal Secretary, Urban
Development Department was suo-motu, without any natural
justice being provided for the respondents-lessees. After arriving
at a conclusion, a show-cause notice was issued by CIDCO to
sanctify the enquiry. The said fact of post-decisional hearing just
B
to sanctify the process of cancellation is clearly evidenced in the
order dated 16.03.2011, passed by the Vice-Chairman and
Managing Director CIDCO, cancelling the tender. Such illegal
procedure adopted, clearly vitiates the subsequent order by the
Vice-Chairman, due to the irregularity, which goes to the root of
the matter. The conduct of the appellant authorities indicate that C
the enquiry was not conducted with an open mind. The pre-
existing findings of the Principal Secretary recommending the
cancellation of allocation has the potential to color the entire
proceedings held subsequently just to meet the procedural
requirements. [Para 36-37][214-A-B, H; 215-A]
D
1.5 Natural justice is an important aspect while viewing
the administrative orders. Providing effective natural justice to
affected parties, before a decision is taken, it is necessary to
maintain rule of law. Natural justice is the sworn enemy of
intolerant authority. Any attempt by authority to circumvent the
requirement of providing effective hearing before reaching a E
conclusion, cannot pass the muster. Coming to the facts, the post-
decisional hearing given to the respondent-lessee is reduced to
a lip-service, which cannot be upheld in the eyes of law. [Para
38][215-B-C]
1.6 As a first step of judicial review, when statutory F
functionaries such as CIDCO render an order based on certain
grounds, its validity must be judged by the reasons so mentioned
and cannot be supplemented by fresh reasons in the shape of an
affidavit or otherwise. To this extent, the submission that the
scope of this Court is limited is accepted. [Para 39][215-D] G
1.7 The perusal of the bid document clearly indicates that
the respondent at the time of applying for the bid had duly
disclosed that the firm had already applied for registration and
had also forwarded the Registration Form and Partnership Deed
H
194 SUPREME COURT REPORTS [2021] 13 S.C.R.
A along with the tender documents. Subsequently, on 16.01.2009
the Registrar of the firms issued the certificate of registration in
favour of the respondent. Having considered the communication
and legal opinion tendered before accepting the highest bid,
CIDCO’s law officers did their due diligence, who opined that
partnerships being creatures of contracts, the requirement of
B
Board resolutions and other technical objections raised were not
an essential condition. Therefore, at this stage it may not be
equitable to review such issues in detail. Moreover, after
accepting the lease premium of Rs.282,39,99,700/- and a transfer
fee of Rs. 1,38,56,000/-, the appellant authority cannot contend
C that the respondents-lessees lacked the eligibility to contend in
the tender. The respondents-lessees also pointed out that, being
the highest bidder with a margin of Rs. 23 crores over the second
highest bidder, the appellant authority did not go into the
technicalities behind the matter. Even, the High Court while
passing the impugned judgment has commented that the appellant
D
was aware about the pending registration, and even assented to
the same as no objections were raised while assessing the
technical bids. [Para 41- 43][215-G-H; 216-A-D]
1.8 As regards, the second objection by the CIDCO of
multiple offers, there is no reason provided as to what provision
E of law such bids violate. Further, there is no concrete allegation
or adjudication on the suggested cartelization. There is no
reasoning considered as to why such a practice was harmful to
public interest. Such considerations are important elements of
party autonomy and commercial freedoms while framing the
F contract, which is not within the purview of judicial review. As
there is no such law or contract provision which bars such conduct,
the considerations undertaken by the order of CIDCO are
extraneous and the same cannot be accepted. [Para 45][216-F-
G]
G 1.9 Clause 15 of the tender document and the corresponding
Condition 19 of the allotment letter, allows for such modification.
Although the language used in the aforesaid clause is
contradictory, this Court needs to interpret the same to harmonize
and eliminate any absurdity. If the interpretation supplied by
CIDCO, by reading Clause 15 (m) and (n) of allotment letter with
H
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 195
LTD. v. SHISHIR REALTY PVT. LTD.
Clause 15 of the tender document in isolation, is accepted, then A
the phrase ‘If he so desires, may apply for the application of the
modified regulation of the General Development Control
Regulation to CIDCO’, as occurring under Clause 15 of the tender
document, is rendered redundant. In this context, the said clause
needs to be interpreted to mean that, ‘lessee cannot apply for
B
change of land use as a matter of right, rather, CIDCO, on its
discretion could grant such ‘change in land use’ on satisfaction
based on material considerations’. The contradictory contractual
clauses, seen within various documents issued by CIDCO, have
led to this seemingly unending dispute, which required more than
a decade to be settled. This only emphasizes the importance of C
due diligence and careful drafting, which could have avoided such
type of litigation in the first place. In the same breath, the CIDCO
has fairly conceded that the power of change of land of use does
exist with CIDCO and has, on multiple occasions, been used to
change the land use pattern. Most importantly, in the instant case,
D
after accepting the change of user fee, the authorities cannot post-
facto question the same. [Para 47-49][220-C-G]
1.10 The plots fell in the zone of commercial-cum-
residential area, and through the contract, this condition was
earmarked for construction of a five-star hotel. As seen from the
records, the respondents-lessees sought dilution of this condition E
basing on the fact that the airport, which was supposed to come
up near the area had not materialized; similarly situated hotels
were loss-making endeavors; and a general economic slump.
Further, the order of the CIDCO dated 11.02.2010 clearly
indicates the reasons as to the change in land use in view of F
prevailing circumstances. From the said reasoning, CIDCO has
not been able to show as to how the its own order was illegal or
arbitrary. Moreover, they have not been able to identify whether
the consideration taken by CIDCO at that time was deficient.
The prevailing circumstances and changes in the factual conditions
need to be appropriately considered. It may be noted that delay G
in construction of Navi-Mumbai airport, economic slump and loss-
making endeavors by similarly situated hotels are ‘material
considerations’ and the order has appropriately taken the same
into account. [Para 50][221-A-B; 222-A]
H
196 SUPREME COURT REPORTS [2021] 13 S.C.R.
A CIDCO Maharashtra Ltd. v. M/s. Shree Ambica
Developers C.A. No.7581 of 2012 – relied on.
1.11 The submission that the relaxation of land use was
made under the policy of 1997 which has been substituted by a
new policy in 2004, is patently wrong, considering the fact that
B the letter dated 11.02.2010 specifically alludes to the expanded
policy of 2004 whereby additional categories of land use were
added. It is mentioned in the letter that the policy of the CIDCO
was not to impose any limit on the user of an area out of allotted
area which can be converted. In light of the said discussion, the
change of land use from five-star hotel to partly residential-cum-
C commercial purpose cannot be said to be illegal or arbitrary. [Para
51][222-B-C]
1.12 On perusal of the Clause 16 of the General Terms and
Conditions and the corresponding Condition 21 of the allotment
letter, it is clearly revealed that the allottee was permitted to
D transfer or assign his rights, interests or benefits with prior written
permission of the Corporation and on payment of such transfer
charges as may be prescribed by the Corporation. Both the clause
and the condition have further stipulated that such permission
could be granted only after the agreed lease premium has been
E paid in full and after execution of agreement to lease. In the
instant case, agreed lease premium was paid in full. However,
agreement to lease was made on the very next day, i.e. on
30.03.2010. Merely because the agreement to lease was
executed on the very next day, the assignment and transfer would
not be invalidated. Such breach cannot in itself be termed as a
F fundamental to annul the tender, especially after receiving the
lease amount, CIDCO cannot question the subsequent transfer.
Such clause can be construed as a warranty alone rather than a
condition, in light of the circumstances. The CIDCO, being a
public body, had a duty to act fairly. Having acquiescence of the
G facts and allowing such transfer, they ought not to have taken
such a hyper-technical view on contractual interpretation. Thus,
no substantial reason sought to be adduced by the CIDCO to
differ from the High Court is found. [Para 52][222-D-H]
H
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 197
LTD. v. SHISHIR REALTY PVT. LTD.
1.13 There is no substantial deviation as sought to be A
projected by the appellants. The appellants have sought to invoke
the doctrine of promissory estoppel to argue that the CIDCO
could not have walked out of the bargain, merely because of the
possibility of larger profits. It is pertinent to note that, the CIDCO
has failed to prove any losses suffered. [Para 53][223-B-C]
B
1.14 When a contract is being evaluated, the mere
possibility of more money in the public coffers, does not in itself
serve public interest. A blanket claim by the State claiming loss
of public money cannot be used to forgo contractual obligations,
especially when it is not based on any evidence or examination.
The larger public interest of upholding contracts and the fairness C
of public authorities is also in play. Courts need to have a broader
understanding of public interest, while reviewing such contracts.
[Para 54][223-D]
Jagdish Mandal v. State of Orissa (2007) 14 SCC 517;
Andhra Pradesh Dairy Development Corporation D
Federation v. B. Narasimha Reddy (2011) 9 SCC 286 :
[2011] 14 SCR 1 – referred to.
1.15 It is clear that the change of usage and the subsequent
division was well-within the statutory limitations. Therefore, the
earlier undertakings taken by the appellant-authorities cannot E
be set aside with the change of person in power, without any rhyme
or reason. After all one cannot change the rules of the game once
it has started. [Para 57][224-F-G]
1.16 From the contradictory submissions asserted before
this Court and the concessions given regarding practice of CIDCO F
to allow change in land use in other cases, clearly points to a
‘regime revenge’. Such conclusion reached is further buttressed
by the fact that no inquiry or disciplinary proceedings were
initiated against the earlier Vice-Chairman, whose orders have
been annulled. Such phenomenon is clearly detrimental to the G
constitutional values and rule of law. [Para 58][224-G-H; 225-A]
1.17 The respondents-lessees claimed that considering they
have acted upon the directions of the appellant authority and have
H
198 SUPREME COURT REPORTS [2021] 13 S.C.R.
A duly paid the requisite amounts to the tune of Rs. 321.32 crores,
CIDCO is bound by the doctrine of promissory estoppel. On the
contrary, principles of estoppel do not apply if enforcing the
promise would lead to the prejudice of public interest. [Para
59][225-B]
B 1.18 Although the appellants are right in claiming that
Government cannot be compelled to perform its undertaking,
but equity demands that the Government must place on record
sufficient material on record to claim such exemption. [Para
61][227-H; 228-A]
C Motilal Padampat Sugar Mills Co. Ltd. v. State of Uttar
Pradesh (1979) 2 SCC 409 : [1979] 2 SCR 641; Union
of India v. Godfrey Philips India Ltd. (1985) 4 SCC
369 : [1985] 3 Suppl. SCR 123; Vasantkumar
Radhakisan Vora (Dead) by His LRs. v. Board of
Trustees of the Port of Bombay (1991) 1 SCC 761 :
D [1990] 3 SCR 825 – referred to.
1.19 There is no substantial violation portrayed by the
appellants with respect to allotment of the scheduled land. Further,
the tender documents, make it clear that the CIDCO had the
power to change the land use, sub-divide and transfer the plots
E and accordingly, has been carried out in terms of the same. It is
observed that ‘good faith standards’ applicable in Government
contracts, serve an important purpose in reinforcing the ‘reliance
interest’ in contracts. Even, the High Court while passing the
impugned judgment correctly held that respondents-lessees have
F acted pursuant to the permission granted by CIDCO. Moreover,
after getting the commencement certificate and other necessary
clearances, the respondents-lessees borrowed a substantial sum
of money from other financial institutions for the development of
the plot. However, due to the ongoing dispute, no development
could take place for the past decade. [Para 63, 64][228-E-G]
G
1.20 It is admitted as per record that the respondent was
the highest bidder. Moreover, the appellants failed to bring
anything on record to prove that the state exchequer has suffered
losses pursuant to the said allotment. Nothing has been produced
H
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 199
LTD. v. SHISHIR REALTY PVT. LTD.
on record, the public interest that will be prejudiced if the A
respondents-lessees are allowed to go ahead with the said project.
On the contrary, the respondents-lessees acting in furtherance
of the assurances given by the authorities, obtained huge financial
assistance. Equity demands that when the State failed to produce
an iota of evidence of either financial loss or any other public
B
interest that has been affected, it should be compelled to fulfill
its promises. In fact, it is respondents-lessees who shall be gravely
prejudiced if the order of cancellation is upheld by this Court
after investing a significant amount and facing prolonged litigation.
[Para 65][228-H; 229-A-C]
1.21 The public interest as sought to be shown in by the C
PIL petitioner is doubtful in light of his involvement in the
business of construction service. Moreover, the tone and tenor
of the notice dated 12.01.2009, issued by the PIL Petitioner to
the CIDCO, threatening the concerned officers with criminal
prosecution under Sections 405, 406, 420 read with Section 120(b) D
IPC, inter alia, on the ground of allowing partnership firm, which
was in the process of registration, to bid, needs to be viewed
with some suspicion. In fact, the non-prosecution of the erring
officials for the alleged mismanagement and irregularities is quite
telling. [Para 66][229-C-E]
E
1.22 When the Government contracts are spoken about,
the constitutional factors are also in play. Governmental bodies
being public authorities are expected to uphold fairness, equality
and rule of law even while dealing with contractual matters. Right
to equality under Article 14 abhors arbitrariness. Public
authorities have to ensure that no bias, favouritism or F
arbitrariness are shown during the bidding process. A transparent
bidding process is much favoured by this Court to ensure that
constitutional requirements are satisfied. [Para 67][229-E-G]
1.23 Fairness and the good faith standard ingrained in the
contracts entered into by public authorities mandates such public G
authorities to conduct themselves in a non-arbitrary manner
during the performance of their contractual obligations. [Para
68][229-G]
H
200 SUPREME COURT REPORTS [2021] 13 S.C.R.
A 1.24 The constitutional guarantee against arbitrariness as
provided under Article 14, demands the State to act in a fair and
reasonable manner unless public interest demands otherwise.
However, the degree of compromise of any private legitimate
interest must correspond proportionately to the public interest,
so claimed. [Para 69][229-H; 230-A]
B
1.25 By merely using grounds of public interest or loss to
the treasury, the successor public authority cannot undo the work
undertaken by the previous authority. Such a claim must be
proven using material facts, evidence and figures. If it were
otherwise, then there would remain no sanctity in the words and
C undertaking of the Government. Businessmen would be hesitant
to enter Government contract or make any investment in
furtherance of the same. Such a practice is counter-productive to
the economy and the business environment in general. [Para
70][230-B-C]
D 1.26 From the facts and circumstances, it is clear that there
is an element of abuse of bureaucratic power behind subsequent
change in the tender allotment. After conducting a tender process
and receiving money, the Government backtracked which led to
this present prolonged litigation. The impugned order of CIDCO,
E inter alia, annulling the allotment on hyper- technical grounds
cannot be sustained for being contrary to the doctrine of fairness.
The reasons stated in the said order are perverse and per-se
based on extraneous considerations. Any substantive violation
of law or tender conditions, which mandate annulling the allotment
and subsequent arrangements, thereby proving the conduct of
F the appellant authority to be disproportionate are not been
identified. [Para 71][230-D-E]
M/s Star Enterprises v. City and Industrial Development
Corporation of Maharashtra Ltd. (1990) 3 SCC 280 :
[1990] 2 SCR 826; Municipal Corporation, Ujjain v.
G BVG India Ltd., (2018) 5 SCC 462 : [2018] 6 SCR
861; Tata Cellular v. Union of India (1994) 6 SCC 651
: [1994] 2 Suppl. SCR 122; B. S. N Joshi & sons Ltd. v.
Nair Coal Services Ltd. (2006) 11 SCC 548 : [2006] 8
Suppl. SCR 11; Mohinder Singh Gill v. Chief Election
H Commissioner, New Delhi (1978) 1 SCC 405 : [1978] 2
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 201
LTD. v. SHISHIR REALTY PVT. LTD.
SCR 272; Ramana Dayaram Shetty v. International A
Airport Authority of India AIR 1979 SC 1628; Motilal
Padampat Sugar Mills Co. Ltd. v. State of Uttar Pradesh
(1979) 2 SCC 409 : [1979] 2 SCR 641 – referred to.
Council of Civil Service Unions v. Minister for the Civil
Service [1985] AC 374 – referred to. B
Case Law Reference
[1990] 2 SCR 826 referred to Para 28
[2018] 6 SCR 861 referred to Para 28
[1994] 2 Suppl. SCR 122 referred to Para 29 C
[2006] 8 Suppl. SCR 11 referred to Para 30
[1978] 2 SCR 272 referred to Para 39
AIR 1979 SC 1628 referred to Para 47
(2007) 14 SCC 517 referred to Para 55 D
[2011] 14 SCR 1 referred to Para 56
[1979] 2 SCR 641 referred to Para 60
[1985] 3 Suppl. SCR 123 referred to Para 60
E
[1990] 3 SCR 825 referred to Para 61
CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 3956-
3957 of 2017.
From the Judgment and Order dated 06.12.2013 of the High Court
of Judicature at Bombay in Writ Petition Nos.702 and 5245 of 2011. F
With
Civil Appeal Nos. 3959-3961 of 2017
Rakesh Dwivedi, A. S. Nadkarni, Mukul Rohatgi, J. P. Cama, Sr.
Advs., Harinder Toor, Amol Nirmalkumar Suryawanshi, Shikhil Suri, G
Ms. Madhu Suri, Arya Tripathy, Ms. Divya Swami, M/s Karanjawala &
Co., Gaurav Goel, Vilol Khaladkar, Arunabh Chowdhury, Dhawal Mehta,
Pranaya Goyal, Nanki Grewal, Chiranjivi Sharma, Dharav Shah,
Ms. Priyakshi Bhatnagar, Mrs. Pragya Baghel, Ms. Liz Mathew, Rahul
Chitnis, Sachin Patil, Aaditya A. Pande, Geo Joseph, Nishant Ramakantro
H
202 SUPREME COURT REPORTS [2021] 13 S.C.R.
A Katneshwarkar, Sanjay Udeshi, Aditya Udeshi, Darshan Ashar, Gaurav
Nair, Ms. Pranati Bhatnagar, Saurabh Chaudhary, Ms. Anne Mathew,
Advs. for the appearing parties.
The Judgment of the Court was delivered by
N. V. RAMANA, CJI
B
1. These Civil Appeals arise out of the impugned judgment dated
06.12.2013 passed by the High Court of Judicature at Bombay in Writ
Petition No. 702 of 2011, Writ Petition No. 5245 of 2011, and Public
Interest Litigation No. 55 of 2011.
C 2. At the outset, a brief sketch of the facts is necessary for
determining the issue. On 11.06.2008, the appellants in Civil Appeal Nos.
3956-3957 of 2017 (City and Industrial Development Corporation of
Maharashtra, for short “CIDCO”) called for a tender for lease of land
within its jurisdiction, for purposes of development of necessary
infrastructure such as Hotels etc., around Navi Mumbai Airport.
D Respondent- M/s Metropolis Hotels was one of the bidders.
3. Before approval of the tender, technical qualifications of the
bidders were scrutinized and approved by the CIDCO’s legal team on
25.07.2008 in the following manner:
“Metropolis Hotels is a Partnership firm consisting of
E
M/s Sun-n-Sand Hotel Pvt. Ltd. and Shishir Realty Pvt. Ltd
having their share 30% each. A short question arises for the
determination is whether Board Resolution of the partnership
firm is required to be annexed with the offer.
It appears from the technical bid of M/s Metropolis Hotels
F
that the said bid is signed by both the partners jointly. Section
4 of the Indian Partnership Act 1932 defines ‘Partner’ and
‘Partnership’ is the relation between persons who have agreed
to share the profits of a business carried on by all or any of
them acting for all. Persons who have entered into partnership
G with one another are called individually “partners” and
collectively “a firm”, and the name under which their business
is carried on is called the “Firm Name”. Partnership is not
created by status and arises from contract. In the Indian
Partnership Act, 1932, there are no directors, and all the
partners are jointly and severally responsible for all the acts
H of the firm.
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 203
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
In view of this Board Resolution is not required. Therefore, A
the remarks appearing on the scrutiny sheet at Sr. No. 19,
requires to be ignored and technical offer should be
accepted.”
On 25.07.2008, the financial bids were opened, which stood as
under: B
C
4. On 25.07.2008, M/s. Indian Hotels Company Ltd., who were
H2 in the bidding process, wrote to CIDCO, objecting to the eligibility of
the highest bidder in the following manner:
D
“3. We are informed that the highest bidder is a partnership
firm and has relied on the experience of one of this partners
to satisfy the eligibility norm. The same partner has also bid
on its own. This amounts to multiple bidder with the same
experience being concerned for more than one bid.”
E
On 04.08.2008, these objections were considered by the law
officers of the CIDCO and subsequently rejected.
5. On 07.08.2008, the CIDCO issued a letter of allotment in favour
of M/s. Metropolis Hotels. Being the highest bidder, M/s. Metropolis
Hotels was accordingly, allotted Plot No. 5, admeasuring about 47,000
sq. mtrs., for construction of a five-star hotel near the proposed Navi F
Mumbai Airport.
6. Thereafter, on 29.12.2009, M/s. Metropolis Hotels-Respondent
no.1, by way of a letter to CIDCO, applied for change of user of 34,000
sq. mtrs. of the said plot to commercial-cum-residential use. On
11.02.2010, this request for change/expansion of user of Plot No.5 was G
considered and subsequently permitted only for 23,000 sq. mtrs.
7. On 11.03.2010, M/s. Metropolis Hotels requested for subdivision
of the Plot No.5 into two, i.e. 24,000 sq. mtrs. for the five-star hotel and
23,000 sq. mtrs. for the residential-cum-commercial plot. By way of a
H
204 SUPREME COURT REPORTS [2021] 13 S.C.R.
A letter dated 29.03.2010, CIDCO demarcated the said plot as requested,
forming Plot No.5 (admeasuring 24,000 sq. mtrs.) and Plot No.5A
(admeasuring 22,999.08 sq. mtrs). M/s. Metropolis Hotels also requested
assignment of their rights in respect of the plot on which the residential-
cum-commercial user was permitted, i.e. Plot No.5A. Assignment of
this plot to M/s. Shishir Realty Private Ltd. was approved by CIDCO in
B
its letter dated 30.03.2010, wherein it referred to the said assignee as
one of the partners in the original allotment.
8. On 30.03.2010, the CIDCO executed two separate lease deeds
in respect of the two plots, i.e. Plot No. 5 and Plot No. 5A. M/s. Shishir
Realty Private Ltd. took further steps for mortgaging their plot with the
C permission of the CIDCO and obtained loan for development of the said
plot for commercial-cum-residential user. Third-party rights were also
created.
9. As complaints were made regarding irregularities in allotment
of plots of land, change of user and deviation from the terms and
D conditions of the tender, a preliminary enquiry was held by the Principal
Secretary, Urban Development Department as per the directions of the
State Government of Maharashtra. Based on such enquiry, the newly
appointed Vice-Chairman issued a show-cause notice dated 06.12.2010
to M/s. Metropolis Hotels and M/s. Shishir Realty Private Ltd.
E (respondents-lessees) as to why the lease deeds which were executed
in their favour should not be cancelled on account of breach of tender
conditions by M/s. Metropolis Hotels. It may be relevant to note
observations made in the show cause notice which inter alia read as
under:
F “13. Since the tenders were invited for grant of lease of
five-star hotel plot, only bidders interested in development of
5-star Hotel participated in the bidding process. Had the
Corporation invited tenders with residential + commercial use
of the plot, several bidders could have participated in the
bidding process and the Corporation might have fetched
G higher revenue. Due to change of user and sub-division of
the plot contrary to the terms and conditions of invitation of
offer, several eligible bidders were deprived and also caused
financial loss to the public exchequer. Besides this, due to
change of user and sub-division of the plot, the basic object
H of development of 5-star hotel is frustrated.
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 205
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
14. For the bench or benches (sic) of the terms and conditions A
of tender and letter of allotment dated – 07.08.2008, you are
hereby called upon to show cause as to why the Corporation
should not cancel or revoke the agreements concluded vide
Letter of Allotment dated 07.08.2008 and Agremeents to lease
dated 30.03.2010, in respect of Plot No.5, admeasuring
B
24,000 m2 in favour of M/s. Metropolis Hotels and Plot No.5A,
admeasuring 23,000 m2 in favour of M/s. Shishir Realty Pvt.
Ltd.”
10. Vide order dated 16.03.2011, the Vice Chairman, CIDCO,
cancelled the lease deeds, pursuant to the enquiry. The issues under
consideration, as identified in the said order, are reproduced as under: C
SL. NO. ISSUES FINDINGS
1. Whether M/s. Metropolis Hotels was eligible
to participate in the bidding process for
No
allotment of 5-Star Hotel Plot, in accordance
with Clause 4(c) of the invitation of offer?
2. Whether change of user for part of the plot D
admeasuring 23,000 m2 and sub-division of
plot in breach of the terms and conditions Yes
represented in the Tender document and letter
of allotment?
3. Whether transfer of part of the sub-divided
plot of admeasuring 23,000m2 with change
of user in favour of M/s. Shishir Realty Pvt.
E
Ltd. before execution of agreement to lease No
was consistent with Condition No.16 of the
General Terms and Conditions of Tender and
Condition No.21 of the letter of allotment?
4. Whether change of user and sub-division of
plot has adversely affected the object of
development of 5 Star Hotel in Navi
Yes F
Mumbai?
5. Whether change of user and sub-division of
plot and transfer of part of the plot was legal, [No]
just and proper?
11. Pertaining to the first issue of the eligibility of M/s. Metropolis G
Hotels to participate in the bidding process, the order held that Clause
4(c) of the tender document obligated the bidders to have a registered
partnership firm. It concluded that since M/s. Metropolis Hotels was not
registered, on the date of submission of the bid, they were ineligible for
bidding. Accordingly, their offer was void ab initio. The second reason
provided was that M/s. Sun-N-Sand Hotels, being partners in H
206 SUPREME COURT REPORTS [2021] 13 S.C.R.
A M/s. Metropolis Hotels, could not have submitted a separate bid, which
also vitiated the bid made by Metropolis Hotels.
12. On the aspect of whether sub-division of the plots and change
of land use were consistent with the terms and conditions of the tender
document and letter of allotment, the order observed that offers were
B invited for five-star hotels and sub-division/change of use could not have
been permitted as such changes were not conducive to public interest
and were against express terms and conditions mentioned within the
agreement.
13. On the third issue of whether transfer of part of the sub-
C divided plot to Shishir Realty Pvt. Ltd was consistent with terms of the
tender and letter of allotment or not, the order observed that the terms of
the allotment letter read with the General Terms and Conditions clearly
showed that the transferee should fulfil all eligibility criteria prescribed
in the invitation of offer. As there was nothing on record to establish that
M/s. Shishir Realty Pvt. Ltd. had fulfilled such criteria, the transfer was
D held to be in violation of such terms and conditions.
14. On the aspect of whether the change of user and sub-division
of the plot adversely affected the object of development of a five-star
hotel, the order noted that the change of user and sub-division of plots
were in contravention of the terms and conditions initially offered. Due
E to such changes, the basic object of development of a five-star hotel in
Navi Mumbai was frustrated.
15. On the aspect of whether allotment of the plot, change of land
use, and sub-division of plots was arbitrary, illegal, and unjustified, the
order noted that the deviations could be categorized as major deviations
F from the terms and conditions mentioned in both the tender documents
and letter of allotment. Such deviation frustrated the basic purpose of
development of a five-star hotel. Therefore, it was concluded that the
aspect of promissory estoppel against the CIDCO would not be applicable
as specific terms of the tender and letter of allotment were deviated.
G Further, such deviations were not in public interest. Accordingly, the two
lease deeds in favour of the respondents-lessees were cancelled.
16. Aggrieved by the cancellation of the lease deeds,
M/s. Metropolis Hotels and Shishir Realty Pvt. Ltd., challenged the
aforesaid order of the Vice Chairman, CIDCO, through two writ petitions
being Writ Petition No. 702 of 2011 and Writ Petition No. 5245 of 2011
H
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 207
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
before the High Court of Judicature at Bombay. Separately, a PIL was A
also filed challenging the allotment of the plot in question, change of land
use, and sub-division of the said plot.
17. The High Court, vide impugned order dated 06.12.2013, while
quashing the aforesaid cancellation order passed by CIDCO, held that
the change of land use and sub-division of the plot had taken place with B
due authorization of the CIDCO. Further, it held that the CIDCO was
not able to show any concrete violations which go to the root of the
matter. Finally, the High Court held that, without producing any pressing
need on record, the CIDCO is precluded and estopped on the doctrine
of promissory estoppel from canceling the allotment.
C
18. Aggrieved by the impugned judgment, the CIDCO and PIL
petitioner- appellant in C.A. Nos. 3959-3961 of 2017 have filed separate
appeals before this Court.
19. Mr. Rakesh Dwivedi, learned Sr. Counsel, appearing on behalf
of the CIDCO, has argued that: D
a) The High Court judgment cannot be sustained as the same
was delivered ignoring blatant violations and illegalities
committed during the tender process.
b) Primarily, the bid by M/s. Metropolis Hotels itself was illegal
as it has only registered subsequent to the allotment, which is E
a clear violation of clause 4(c) and 8(b) of the tender
document.
c) Moreover, subsequent to the award of the contract,
M/s. Metropolis Hotels went beyond the tender conditions
and expanded the usage to residential-cum-commercial. F
Additionally consequent to change of usage, the
M/s. Metropolis Hotels sub-divided the plot and executed a
fresh lease in favour of Shishir Realty Pvt. Ltd. The aforesaid
acts were in breach of the original allotment letter.
d) This Court while concerned with distribution of State largesse, G
should ensure that no arbitrariness, favouritism has taken place.
e) The Respondents cannot claim any relief based on the doctrine
of promissory estoppel as being a creature of equity, it must
yield when the equity so requires. Considering it would be
inequitable to hold the Government to the promise made by it, H
208 SUPREME COURT REPORTS [2021] 13 S.C.R.
A the Court should not raise an equity in favour of the promisee
and enforce the promise against the Government.
f) It is well settled legal proposition that the private interest would
always yield place to the public interest. Considering, the
irregularities committed by the respondents, it is expedient to
B revoke the allotment in favour of the Respondents especially
when no grave prejudice will be caused to the allottee.
20. Mr. Atmaram Nadkarni, learned Sr. Counsel, appearing on
behalf of the State of Maharashtra while supporting the submissions
made by CIDCO, has argued that:
C a) This court, in a catena of judgments, has held that the
representations made to the public by way of tender conditions
and policies cannot be changed arbitrarily after the allotment.
b) The rules of the game cannot be changed once the game is
played.
D
21. Mr Harinder Toor, learned Counsel, appearing on behalf of
the PIL petitioner-appellant in C.A. No. 3959-3961, has argued that:
a) The PIL petitioner/appellant is a social activist and is involved
in the business of construction services.
E b) The change of land use is in violation of clause 15 of the
letter of allotment, which mandated that the allotted land shall
be used only for the construction of a five star hotel.
c) The change of land use was illegal and arbitrary.
d) The sub-division of plots was also invalid.
F
22. Dr. Abhishek Manu Singhvi, learned Senior Counsel, appearing
on behalf of Shishir Realty Pvt. Ltd., argues that:
a) M/s.Metropolis Hotels was a partnership firm and had applied
for registration. When bid was made, they had declared the
G same to CIDCO. The enforcing committee received the bid
being fully aware that the application for registration of
partnership firm was pending before the registrar and decided
to go with their bid as it was Rs.23 crore higher than the next
bid.
H
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 209
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
b) Additionally, the enquiry that was conducted against the said A
allocation was in complete abrogation of natural justice. No
notice was issued to the respondents during the pendency of
the enquiry. Even while accepting the report of the Principal
Secretary, no hearing was given to the respondents.
c) Not only is CIDCO bound by the principles of estoppel, but B
they have also failed to prove any losses attributable to the
respondent.
d) CIDCO has only raised bald allegations of collusion with
management. Had there been any real apprehension of
collusion or financial losses arising out of this transaction, the C
State would have taken criminal action/disciplinary actions
against the erring officials. However, CIDCO have failed to
place anything on record to prove the same.
23. Mr. Mukul Rohatgi, Learned Senior Counsel, appearing on
behalf of M/s. Metropolis Hotels argues that: D
a) The purpose of construction of a five-star hotel has been
frustrated considering the fact that the same was contingent
on the coming up of Navi Mumbai Airport.
b) Without there being an airport, it would be commercially absurd
to construct a five-star hotel in the middle of nowhere. E
c) The bidding process was conducted in 2008, when there was
a huge recession both globally and in India. The tender had
attracted M/s. Metropolis Hotels because it was stated that
the Navi Mumbai Airport would be built near the concerned
plot, and the area would be declared a Special Economic Zone. F
However, the promises of the tender document were not
fulfilled and hence, an application for change of user was
made. The 1997 policy allows for a change of user and hence,
there is no illegality.
d) There is no violation of any condition of the tender document G
concerning sub-division of plots.
e) Moreover, even after the allotment was made the respondents
have complied with the due procedure and have paid the
requisite fees. After accepting the requisite charges to the
H
210 SUPREME COURT REPORTS [2021] 13 S.C.R.
A tune of Rs. 321 crores, the cancellation of the allotment after
13 years is not only highly inequitable but will also cause grave
prejudice to the respondents.
f) He disputes the bona-fides of the PIL petitioner.
24. Heard learned counsels from both sides.
B
25. Before we delve into analysis of the case, it is pertinent to
examine the role of Constitutional Courts in reviewing the tender process.
The Constitution of India allows the government to enter into contracts
and perform certain commercial activities. Due to increase in government
business, there is a requirement of this Court to uphold certain discretion
C accruing to the government and disallow certain conduct in light of
prevailing circumstances. Merely instilling an agency with discretion may
not be prohibited by the Constitution, rather it is unfettered use of such
discretion, that is prohibited; the Constitution frowns upon those decisions
which are taken in gross abuse of law. English Courts have developed
D many legal standards for evaluating administrative decisions, one of them
being enumerated in the case of Council of Civil Service Unions v.
Minister for the Civil Service, [1985] AC 374, wherein Lord Diplock
has summarized the grounds of challenging such decisions under the
broad heads of illegality, irrationality, procedural impropriety and legitimate
expectation. Beyond these grounds, a recent development in the form of
E proportionality has further increased the scope of judicial review.
26. Being governed under “rule of law” every action of the State
or its instrumentality while exercising its executive powers must met the
aforesaid requirements. While recognising the existing principle of
freedom to enter or not to enter into contracts by the state and its
F instrumentalities, the manner, method and motive behind the aforesaid
decision can be subjected to judicial review on the touchstone of equality,
fairness, proportionality and natural justice. The decision of the executive
must strike a balance with the alleged violation with that of the penalty
imposed.
G 27. This Court, in many of its orders reviewing tender conditions,
has vouched for providing sufficient discretion and independence to
administrative authorities so as to enable them to perform their duties in
the interest of the public. Further, the observation of judicial restraint
while reviewing such contracts is a continuing trend which can be seen
H
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 211
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
in a catena of cases. 1 The power of judicial review accorded to A
Constitutional Court of India and its jurisdiction is supervisory.
28. This court in the case of M/s Star Enterprises v. City and
Industrial Development Corporation of Maharashtra Ltd., (1990)
3 SCC 280 reiterated the aforesaid concerns and stated the necessity
of judicial review even with respect to the commercial transactions B
undertaken by the State. This court held as follows:
“10. In recent times, judicial review of administrative action has
become expansive and is becoming wider day by day. The
traditional limitations have been vanishing and the sphere of judicial
scrutiny is being expanded. State activity too is becoming fast C
pervasive. As the State has descended into the commercial
field and giant public sector undertakings have grown up,
the stake of the public exchequer is also large justifying
larger social audit, judicial control and review by opening
of the public gaze; these necessitate recording of reasons
for executive actions including cases of rejection of highest D
offers. That very often involves large stakes and availability
of reasons for actions on the record assures credibility to
the action; disciplines public conduct and improves the
culture of accountability. Looking for reasons in support of
such action provides an opportunity for an objective review E
in appropriate cases both by the administrative superior
and by the judicial process.”
(emphasis supplied)
29. In this context, this Court in Tata Cellular v. Union of India,
1994 (6) SCC 651, observed certain principles elucidated as under: F
“94.The principles deducible from the above are:
(1) The modern trend points to judicial restraint in
administrative action.
(2) The court does not sit as a court of appeal but merely G
reviews the manner in which the decision was made.
(3) The court does not have the expertise to correct the
administrative decision. If a review of the administrative
1
Municipal Corporation, Ujjain v. BVG India Ltd., (2018) 5 SCC 462 H
212 SUPREME COURT REPORTS [2021] 13 S.C.R.
A decision is permitted it will be substituting its own decision,
without the necessary expertise which itself may be fallible.
(4) The terms of the invitation to tender cannot be open to
judicial scrutiny because the invitation to tender is in the realm
of contract. Normally speaking, the decision to accept the
B tender or award the contract is reached by process of
negotiations through several tiers. More often than not, such
decisions are made qualitatively by experts.
(5) The Government must have freedom of contract. In other
words, a fair play in the joints is a necessary concomitant for
C an administrative body functioning in an administrative
sphere or quasi-administrative sphere. However, the decision
must not only be tested by the application of Wednesbury
principle of reasonableness (including its other facts pointed
out above) but must be free from arbitrariness not affected by
bias or actuated by mala fides.
D
(6) Quashing decisions may impose heavy administrative
burden on the administration and lead to increased and
unbudgeted expenditure.”
(emphasis supplied)
E
30. These principles acquire importance as the efficacy of
commercial activities in the public sector increases greatly. It appears
that public interest litigation has opened a large window to entertain any
tender, regardless of scale, which are now sought to be challenged as a
matter of routine. Such disruption could hardly have been the objective
F of expanding the need of Constitutional Review. Close scrutiny of minute
details, contrary to the view of the tendering authority, makes execution
of contracts in the public sector a cumbersome exercise. Often, it is the
case that parties entertain the idea of a long-drawn-out litigation at the
very threshold itself. The purpose of imbibing the spirit of competition in
G a process such as that of the bidding process, is lost in this meandering
exercise and delays suffered due to pending litigation. This causes great
disadvantage to the government and public sector in general. This Court,
in appropriate cases while interpreting the contract, can restrict the review
mechanism by not inuring to the interpretation so provided by third parties
or parties competing for the tender, unless the impugned interpretation is
H
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 213
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
shown to be gross abuse of law.2 The object of judicial review cannot be A
that in every contract where some parties lose out, a second opportunity
is provided to such parties to pick holes so as to disqualify successful
parties, on grounds which even the party floating the tender find to be
without merit. With this brief background on the standard of judicial
review, we may analyze the case at hand.
B
31. At the outset, the respondents-lessees have argued that entire
process of cancellation of the tender stood vitiated as it was based on
the enquiry conducted by the Principal Secretary, Urban Development
Department, without affording a chance to be heard.
32. It is borne from the records that, upon receiving the certain C
complaints, the State Government initiated enquiry against the alleged
irregularities during the tender process. On 18.09.2010, the Shishir Realty
Private Ltd. received an order from the Navi Mumbai Municipal
Corporation directing them not to carry any further construction and
stay the development.
D
33. On 03.11.2010, the enquiry committee submitted its report to
the State Government recommending the cancellation of tender. On
19.11.2010, the State Government accepted the findings of the enquiry
committee and directed CIDCO, to implement the findings of the enquiry
committee.
E
34. Shishir Realty Private Ltd. has placed on record letter dated
23.12.2010 addressed to the Urban Development Department and
CIDCO, stating that he was shocked to see a newspaper report stating
that a committee appointed by the State Government has recommended
the cancellation of the allotment done in their favour. The aggrieved
Respondent challenged the aforesaid recommendation as it was passed F
without affording an opportunity of hearing them-the aggrieved party.
35. Subsequent to the aforesaid letter, on 28.12.2010, the
Respondents-lessees received a show-cause notice dated back to
06.12.2010. The respondents-lessees submitted their responses on
30.12.2010, 13.01.2011 and on 19.02.2011. Finally hearing was given to G
the respondent on 03.03.2011. Thereafter, finally on 16.03.2011, the
CIDCO cancelled/revoked the letter of allotment and the subsequent
permissions. Vide the aforesaid order, the Manager (Town Services)
was also directed to take over possession of the plots within 15 days.
2
B. S. N Joshi & sons Ltd. v. Nair Coal Services Ltd., (2006) 11 SCC 548 H
214 SUPREME COURT REPORTS [2021] 13 S.C.R.
A 36. The perusal of the materials produced on record shows that
the initiation of the enquiry by the Principal Secretary, Urban Development
Department was suo-motu, without any natural justice being provided
for the respondents-lessees. After arriving at a conclusion, a show-cause
notice was issued by CIDCO to sanctify the enquiry. The afore-said
fact of post-decisional hearing just to sanctify the process of cancellation
B
is clearly evidenced in the order dated 16.03.2011, passed by the Vice-
Chairman and Managing Director CIDCO, cancelling the tender in the
following terms:
“1. The Government of Maharashtra through the Principal
Secretary, Urban Development Department conducted enquiry
C into the irregularities in allotments of plots, change of user and
deviation of the terms and conditions of the tender made by the
then Vice Chairman and Managing Director, CIDCO, during the
period from Ist October, 2009 to 31st March, 2010. The Principal
Secretary Urban Development Department conducted the enquiry
D and submitted his report to the State Government on 03.11.2010.
The change of user, sub-division and transfer of part of plot
no. 5, Sector 46A, Nerul, to M/s Metropolis Hotels was
also covered in the enquiry conducted by the Principal
Secretary, Urban Development Department. The State
Government accepted the findings and recommendations
E of the enquiry committee and directed the Managing
Director, CIDCO, vide letter dated 19.11.2010, to
implement the findings and recommendations of the
Principal Secretary, Urban Development Department. The
Principal Secretary has recorded his findings about the
F irregularities in acceptance of tender and breach of tender
conditions, change of user, sub-division of plot and further
transfer of part of the plot and further recommended
cancellation of the tender process.
2. Although the State Government issued directions to cancel
G the entire tender process, it was felt necessary to re-examine
the entire issue for allotment of land …. by conducting an
enquiry and giving opportunity of hearing to the parties.”
37. Such illegal procedure adopted, clearly vitiates the subsequent
order by the Vice-Chairman, due to the irregularity, which goes to the
H root of the matter. The conduct of the appellant authorities indicate that
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 215
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
the enquiry was not conducted with an open mind. The pre-existing A
findings of the Principal Secretary recommending the cancellation of
allocation has the potential to color the entire proceedings held
subsequently just to meet the procedural requirements.
38. Natural justice is an important aspect while reviewing the
administrative orders. Providing effective natural justice to affected B
parties, before a decision is taken, it is necessary to maintain rule of law.
Natural justice is the sworn enemy of intolerant authority. Any attempt
by authority to circumvent the requirement of providing effective hearing
before reaching a conclusion, cannot pass the muster. Coming to the
facts herein, the post-decisional hearing given to the respondent-lessee
is reduced to a lip-service, which cannot be upheld in the eyes of law. C
39. As a first step of judicial review, we need to note that when
statutory functionaries such as CIDCO render an order based on certain
grounds, its validity must be judged by the reasons so mentioned and
cannot be supplemented by fresh reasons in the shape of an affidavit or
otherwise.3 To this extent, we agree with the submission of Dr. Abhishek D
Manu Singhvi, that the scope of this Court is limited. Hence, we will only
consider the impugned order of CIDCO dated 16.03.2011 and the
reasoning supplied therein.
40. At this juncture, it is pertinent to consider certain allegations
of violation raised by the appellant authorities. The first aspect for the E
consideration of this Court is whether M/s. Metropolis Hotels Ltd. was
disqualified from participating in the bidding process. The impugned order
dated 16.03.2011 of CIDCO provides two reasons: the first being that
M/s. Metropolis Hotels was not a registered partnership firm while
applying for the tender process, and the second that one of the partners F
of M/s. Metropolis Hotels, namely M/s. Sun-N-Sand Hotels Pvt. Ltd,
had submitted a separate bid.
41. The perusal of the bid document clearly indicates that the
respondent- M/s. Metropolis Hotels at the time of applying for the bid
had duly disclosed that the firm had already applied for registration and G
had also forwarded the Registration Form and Partnership Deed along
with the tender documents. Subsequently, on 16.01.2009 the Registrar
of the firms issued the certificate of registration in favour of the
respondent- M/s. Metropolis Hotels.
3
Mohinder Singh Gill v. Chief Election Commissioner, New Delhi, (1978) 1 SCC
405. H
216 SUPREME COURT REPORTS [2021] 13 S.C.R.
A 42. Having considered the communication and legal opinion
tendered before accepting the highest bid, CIDCO’s law officers did
their due diligence, who opined that partnerships being creatures of
contracts, the requirement of Board resolutions and other technical
objections raised were not an essential condition. Therefore, at this stage
it may not be equitable to review such issues in detail.
B
43. Moreover, after accepting the lease premium of
Rs.282,39,99,700/- and a transfer fee of Rs. 1,38,56,000/-, the appellant
authority cannot contend that the respondents-lessees lacked the eligibility
to contend in the tender. The respondents-lessees also pointed out that,
being the highest bidder with a margin of Rs. 23 crores over the second
C highest bidder, the appellant authority did not go into the technicalities
behind the matter. Even, the High Court while passing the impugned
judgment has commented that the appellant was aware about the pending
registration, and even assented to the same as no objections were raised
while assessing the technical bids.
D 44. The second objection which the CIDCO in its order notes as
under:
“Apart from this, M/s. Sun-N-Sand Hotels Pvt. Ltd., one of
partners of M/s. Metropolis Hotels also submitted separate
offer in the bidding process. Such multiple offers were
E submitted by M/s. Sun-N-Sand Hotels Pvt. Ltd. with a view to
get the land allotted. On this count also, the offer of
M/s. Metropolis Hotels stand vitiated, and the concluded
agreement is liable to be terminated.”
45. In our considered opinion, the aforesaid paragraph does not
F indicate sufficient reasons. There is no reason provided as to what
provision of law such bids violate. Further, there is no concrete allegation
or adjudication on the suggested cartelization. There is no reasoning
considered as to why such a practice was harmful to public interest. We
may note that such considerations are important elements of party
G autonomy and commercial freedoms while framing the contract, which
is not within the purview of judicial review. As there is no such law or
contract provision which bars such conduct, the considerations undertaken
by the order of CIDCO are extraneous and the same cannot be accepted.
46. The second aspect considered by the appellant (CIDCO)
was the change of land use. According to CIDCO, such change of land
H
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 217
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
use was not permitted under the contract. Therefore, it was argued to A
be not valid. On the contrary, the respondents have argued that not only
CIDCO was authorized to change the usage but also the Clause 19 of
the allotment letter provided that development of the plot was governed
under the General Development Control Regulations for Navi Mumbai
which also had similar provisions. Moreover, the respondents-lessees
B
contended that, this was not the first instance of change of usage. To
support the said averment, the respondents-lessees placed strong reliance
upon the decision of this Court in the identical matter of CIDCO
Maharashtra Ltd. v. M/s. Shree Ambica Developers, in C.A.
No.7581 of 2012. This Court held therein:
“We have as a measure of abundant caution examined the relevant C
official record which was produced before us by Mr. Bhasme,
counsel appearing for the appellant. While the application for
change may have been filed only a few days after the auction
was conducted, the same was processed at different levels
giving an opportunity to officials dealing with specialised D
fields to record their opinion on the permissibility of the
proposed change. From a perusal of the notings recorded
on the file, we are satisfied that the change was found to be
permissible in – accordance with General Development
Control Regulations. We must say to the credit of M/s Lalit
and Bhasme that they did not question the correctness of the E
views recorded by the officers, who examined the permissibility
of a change as prayed for by the company. It was not their
contention that the change was against the development plan that
could have made the same untenable in law, nor was there any
suggestion that any one of the functionaries associated with the F
decision making process had played a fraud on the statute or the
exercise of power vested in him. It is true that the official
record produced before us, does not reveal that the
question of financial implications, if any, involved in the
change which could and perhaps ought to have been
examined was examined by any one at any stage. But so G
long as the appellant did not make absence of such a
consideration a ground for cancellation of change in use,
we cannot help leave alone permit the Corporation to add
the same as a ground for supporting the order recalling –
the grant of the change. The order passed by the Corporation/ H
218 SUPREME COURT REPORTS [2021] 13 S.C.R.
A its Managing Director cancelling the earlier change was based
entirely on the alleged absence of authority vested in it to direct
such a change.”
(emphasis supplied)
47. Upon the perusal of the above cited decision, we are of the
B opinion that the aforesaid opinion is squarely applicable in the present
case. Although the argument made by the CIDCO is attractive at the
outset, a deeper analysis makes it clear that such argument is devoid of
merit. In this context, it may be necessary to note certain clauses contained
in the Tender Document and Allotment Letter:
C “4. Who is eligible to offer to acquire plot
(a) A person competent to contract under the Indian
Contract Act is eligible to make offer to acquire plot.
(b) A company incorporated under the Indian companies
D Act, 1956 is eligible to make offer to acquire plot.
(c) A partnership firm registered under Indian Partnership
Act, 1932 is eligible to offer to acquire plot. Offer shall
be signed by all partners and enclosed with a true
certified copies of Deed of Partnership and certificate
of registration.
E
(d) A public trust registered under Public Trust Act, 1950
and also registered under Society Registration Act, 1860
is eligible to offer to acquire plot.
(e) A Co-operative society registered under the
F Maharashtra Co-operative Societies Act, 1960. The
Offer form must be signed by the Chairman or the Hon.
Secretary of the society without which it will be held
invalid. The authorization of general body must be
enclosed with the offer.
G 18. General
CIDCO reserves the rights to amend, revoke or modify
the above conditions at its discretion as well as to reject
any or all offers without assigning any reasons.
…
H
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 219
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
General Terms and Conditions prescribed for disposal A
of plots by open offer.
….
….
15. Application of General Development Control B
Regulation for Navi Mumbai
The development of land will be governed by the
prevailing provision contained in the General
Development Control Regulation of Navi Mumbai. Any
modification to the said Regulation and in particular to C
the Floor Space Index and change of use of the land
shall not be made lessee (sic). If he so desires, may
apply for the application of the modified regulation of
the General Development Control Regulation to CIDCO.
The Corporation may at its sole discretion, apply the
modification of such regulation on payment of (1) D
Development charges (2) Additional premium and (3)
other charges if any as may be decided by the
Corporation from time to time. (…)
16. Transfer of assignment of rights
E
The intending lease can transfer or assign his rights,
interests of benefits which may accrue to him from the
Agreement with the prior written permission of the
Corporation and on payment of such transfer charges
as may be prescribed by the Corporation from time to
time. Such permission can however be granted only after F
the agreed lease premium and any other amount required
has been paid in full and after execution of Agreement
to lease. In case of transfer of plot, the Transferee
should fulfill all eligibility conditions prescribed in
condition 4 of the invitation of offer.”
G
Conditions provided in the Allotment letter:
19. Application of General Development Control
Regulation for Navi Mumbai
H
220 SUPREME COURT REPORTS [2021] 13 S.C.R.
A The development of land will be governed by the
prevailing provisions contained in the General
Development Control Regulation of Navi Mumbai. Any
modification to the said regulation and in particular to
the Floor Space index and charge of use of the land
shall not be made automatically applicable but the
B
intending lessee, if you so desire, may apply for the
application of the modified regulation of the General
Development Control.
(emphasis supplied)
C Clause 15 of the tender document and the corresponding Condition
19 of the allotment letter, allows for such modification. Although
the language used in the aforesaid clause is contradictory, this
Court needs to interpret the same to harmonize and eliminate any
absurdity.4 If the interpretation supplied by CIDCO, by reading
Clause 15 (m) and (n) of allotment letter with Clause 15 of the
D tender document in isolation, is accepted, then the phrase ‘If he
so desires, may apply for the application of the modified
regulation of the General Development Control Regulation
to CIDCO’, as occurring under Clause 15 of the tender document,
is rendered redundant. In this context, the aforesaid clause needs
E to be interpreted to mean that, ‘lessee cannot apply for change of
land use as a matter of right, rather, CIDCO, on its discretion
could grant such ‘change in land use’ on satisfaction based on
material considerations’.
48. The contradictory contractual clauses, seen within various
F documents issued by CIDCO, have led to this seemingly unending dispute,
which required more than a decade to be settled. This only emphasizes
the importance of due diligence and careful drafting, which could have
avoided such type of litigation in the first place.
49. In the same breath, the CIDCO has fairly conceded that the
G power of change of land of use does exist with CIDCO and has, on
multiple occasions, been used to change the land use pattern. Most
importantly, in the present case, after accepting the change of user fee,
the authorities cannot post-facto question the same.
4
Ramana Dayaram Shetty v. International Airport Authority of India, AIR 1979 SC
H 1628.
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 221
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
50. In this case, the plots fell in the zone of commercial-cum- A
residential area, and through the contract, this condition was earmarked
for construction of a five-star hotel. As seen from the records, the
respondents-lessees sought dilution of this condition basing on the fact
that the airport, which was supposed to come up near the area had not
materialized; similarly situated hotels were loss-making endeavors; and
B
a general economic slump. Further, the order of the CIDCO dated
11.02.2010 clearly indicates the reasons as to the change in land use in
view of prevailing circumstances in the following manner:
“The plot was aid (sic) in August 2008 for development of a
Five Star Hotel along with the allied activities and it received
a price of Rs.60085.10 per sq. mtr. The plot was initially with C
1.5 FSI which was increasable to FSI 2.0 as per Government
Policy. For the period prior and after the date of sale
instances of sale of plots by tender for various usages are
keep as C/351 to C/377. It is well know fact that the real
estate markets in the later part of the year 2008 literally D
crashed and the downward trend of 25% to 30% was noticed
across various real estate markets and segments. As a result
of this, the Board had also decided to bring down the prices
of NRI Phase-II Pat-II by 10% as well as rescheduling the
installments. Also the DPC rates were brought down to 10%.
The sale instances on the file show that the prices of residential E
and commercial lands during that period were comparable
or some cases lower than the plot in question. But nonetheless
the fact of depressed market cannot be ignored. In cases of
some of the plots which are sold at higher rates, the Bidders
did not pay the first installment and therefore their EMD’s F
were forfeited and in some cases on their request references
have been made to the government for extension of time for
payment.”
From the aforesaid reasoning, CIDCO has not been able to show
as to how the its own order was illegal or arbitrary. Moreover, they have G
not been able to identify whether the consideration taken by CIDCO at
that time was deficient. The prevailing circumstances and changes in
the factual conditions need to be appropriately considered. In our
considered opinion, it may be noted that delay in construction of Navi-
Mumbai airport, economic slump and loss-making endeavors by similarly
H
222 SUPREME COURT REPORTS [2021] 13 S.C.R.
A situated hotels are ‘material considerations’ and the order has appropriately
taken the same into account.
51. The last submission on this aspect which the learned senior
counsel for the CIDCO, Shri Rakesh Dwivedi, takes is that the relaxation
of land use was made under the policy of 1997 which has been substituted
B by a new policy in 2004. However, such submission is patently wrong,
considering the fact that the letter dated 11.02.2010 specifically alludes
to the expanded policy of 2004 whereby additional categories of land
use were added. It is mentioned in the letter that the policy of the CIDCO
was not to impose any limit on the user of an area out of allotted area
which can be converted. In light of the aforesaid discussion, the change
C of land use from five-star hotel to partly residential-cum-commercial
purpose cannot be said to be illegal or arbitrary.
52. The third aspect which needs to be considered is the legality
of sub-division of plots and subsequent transfer of rights. It has been
contended that the terms of the tender and letter of allotment do not
D allow such transfer. However, on perusal of the aforementioned Clause
16 of the General Terms and Conditions and the corresponding Condition
21 of the allotment letter, it is clearly revealed that the allottee was
permitted to transfer or assign his rights, interests or benefits with prior
written permission of the Corporation and on payment of such transfer
E charges as may be prescribed by the Corporation. Both the clause and
the condition have further stipulated that such permission could be granted
only after the agreed lease premium has been paid in full and after
execution of agreement to lease. In the present case, agreed lease
premium was paid in full. However, agreement to lease was made on
the very next day, i.e. on 30.03.2010. In our view, merely because the
F agreement to lease was executed on the very next day, the assignment
and transfer would not be invalidated. Such breach cannot in itself be
termed as a fundamental to annul the tender, especially after receiving
the lease amount, CIDCO cannot question the subsequent transfer. We
can only state that such clause can be construed as a warranty alone
G rather than a condition, in light of the circumstances. The CIDCO, being
a public body, had a duty to act fairly. Having acquiescence of the facts
and allowing such transfer, they ought not to have taken such a hyper-
technical view on contractual interpretation. In light of the aforesaid
reasoning, we do not find any substantial reason sought to be adduced
by the CIDCO to differ from the High Court.
H
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 223
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
53. Ultimately, we need to consider whether there was any illegality A
or unfairness in the aforesaid transaction. Learned senior counsel
representing the appellants have submitted that allowing subdivision of
plots with change in land use, had caused substantive loss to the State
largesse, as many people would have shown a proclivity to buy land with
different land use. On the contrary, the learned senior counsel representing
B
the Respondents-lessees have stated that the allotment, change in land
use and transfer have taken place in accordance with law. There is no
substantial deviation as sought to be projected by the appellants herein.
The appellants herein have sought to invoke the doctrine of promissory
estoppel to argue that the CIDCO could not have walked out of the
bargain, merely because of the possibility of larger profits. It is pertinent C
to note that, the CIDCO has failed to prove any losses suffered.
54. When a contract is being evaluated, the mere possibility of
more money in the public coffers, does not in itself serve public interest.
A blanket claim by the State claiming loss of public money cannot be
used to forgo contractual obligations, especially when it is not based on D
any evidence or examination. The larger public interest of upholding
contracts and the fairness of public authorities is also in play. Courts
need to have a broader understanding of public interest, while reviewing
such contracts.
55. In Jagdish Mandal v. State of Orissa, (2007) 14 SCC 517, it E
was held as under:
“22… The tenderer or contractor with a grievance can always
seek damages in a civil court. Attempts by unsuccessful
tenderers with imaginary grievances, wounded pride and
business rivalry, to make mountains out of molehills of some F
technical/procedural violation or some prejudice to self, and
persuade courts to interfere by exercising power of judicial
review, should be resisted. Such interferences, either interim
or final, may hold up public works for years, or delay relief and
succour to thousands and millions and may increase the project
cost manifold. G
(emphasis supplied)
56. Similarly, this Court in the case of Andhra Pradesh Dairy
Development Corporation Federation v. B. Narasimha Reddy, (2011)
9 SCC 286 held as under:
H
224 SUPREME COURT REPORTS [2021] 13 S.C.R.
A “40. In the matter of the Government of a State, the
succeeding Government is duty-bound to continue and carry on
the unfinished job of the previous Government, for the reason that
the action is that of the “State”, within the meaning of Article 12
of the Constitution, which continues to subsist and therefore, it is
not required that the new Government can plead contrary to the
B
State action taken by the previous Government in respect of a
particular subject. The State, being a continuing body can be
stopped from changing its stand in a given case, but where
after holding enquiry it came to the conclusion that action
was not in conformity with law, the doctrine of estoppel
C would not apply. Thus, unless the act done by the previous
Government is found to be contrary to the statutory
provisions, unreasonable or against policy, the State should
not change its stand merely because the other political party
has come into power. “Political agenda of an individual or a
political party should not be subversive of rule of law.” The
D
Government has to rise above the nexus of vested interest and
nepotism, etc. as the principles of governance have to be tested
on the touchstone of justice, equity and fair play.”
(emphasis supplied)
E 57. In the present case, it was argued by the respondents that
with the change in the executive head in CIDCO, enquiry was initiated
against the allotment made in favour of the respondent- M/s. Metropolis
Hotel during the tenure of the earlier executive head. Even the inquiry,
that was conducted against the respondents-lessees stood vitiated as no
proper notice or hearing was given to them before passing the impugned
F order. Additionally, from the above analysis it clear that the change of
usage and the subsequent division was well-within the statutory limitations.
Therefore, the earlier undertakings taken by the appellant-authorities
cannot be set aside with the change of person in power, without any
rhyme or reason. After all one cannot change the rules of the game
G once it has started.
58. From the contradictory submissions asserted before this Court
and the concessions given regarding practice of CIDCO to allow change
in land use in other cases, clearly points to a ‘regime revenge’. Such
conclusion reached herein is further buttressed by the fact that no inquiry
H or disciplinary proceedings were initiated against the earlier Vice-
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 225
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
Chairman, whose orders have been annulled. Such phenomenon is clearly A
detrimental to the constitutional values and rule of law.
59. As the last leg of the submission, the respondents-lessees have
claimed that considering they have acted upon the directions of the
appellant authority and have duly paid the requisite amounts to the tune
of Rs. 321.32 crores, CIDCO is bound by the doctrine of promissory B
estoppel. On the contrary, principles of estoppel do not apply if enforcing
the promise would lead to the prejudice of public interest.
60. Before we delve into the aforesaid arguments, it is imperative
for us to go to have a look at certain decisions of this Court. This Court
in the case of Motilal Padampat Sugar Mills Co. Ltd. v. State of C
Uttar Pradesh, (1979) 2 SCC 409 laid down the necessity of the
government being bound by the principles of promissory estoppel in the
following words:
“24. … The law may, therefore, now be taken to be settled
as a result of this decision, that where the Government makes D
a promise knowing or intending that it would be acted on
by the promisee and, in fact, the promisee, acting in reliance
on it, alters his position, the Government would be held
bound by the promise and the promise would be enforceable
against the Government at the instance of the promisee,
notwithstanding that there is no consideration for the E
promise and the promise is not recorded in the form of a
formal contract as required by Article 299 of the
Constitution. … It is indeed difficult to see on what principle
can a Government, committed to the rule of law, claim immunity
from the doctrine of promissory estoppel… It was laid down by F
this Court that the Government cannot claim to be immune
from the applicability of the rule of promissory estoppel
and repudiate a promise made by it on the ground that such
promise may fetter its future executive action. If the
Government does not want its freedom of executive action
to be hampered or restricted, the Government need not G
make a promise knowing or intending that it would be acted
on by the promisee and the promisee would alter his
position relying upon it. But if the Government makes such
a promise and the promisee acts in reliance upon it and
alters his position, there is no reason why the Government H
226 SUPREME COURT REPORTS [2021] 13 S.C.R.
A should not be compelled to make good such promise like
any other private individual. The law cannot acquire legitimacy
and gain social acceptance unless it accords with the moral values
of the society and the constant endeavour of the Courts and the
legislature, must, therefore, be to close the gap between law and
morality and bring about as near an approximation between the
B
two as possible. The doctrine of promissory estoppel is a significant
judicial contribution in that direction. But it is necessary to point
out that since the doctrine of promissory estoppel is an
equitable doctrine, it must yield when the equity so
requires. If it can be shown by the Government that having
C regard to the facts as they have transpired, it would be
inequitable to hold the Government to the promise made
by it, the Court would not raise an equity in favour of the
promisee and enforce the promise against the Government.
The doctrine of promissory estoppel would be displaced in such a
case because, on the facts, equity would not require that the
D
Government should be held bound by the promise made by it.
When the Government is able to show that in view of the facts as
have transpired since the making of the promise, public interest
would be prejudiced if the Government were required to carry
out the promise, the Court would have to balance the public interest
E in the Government carrying out a promise made to a citizen which
has induced the citizen to act upon it and alter his position and the
public interest likely to suffer if the promise were required to be
carried out by the Government and determine which way the equity
lies. ….The burden would be upon the Government to show
that the public interest in the Government acting otherwise
F
than in accordance with the promise is so overwhelming
that it would be inequitable to hold the Government bound
by the promise and the Court would insist on a highly
rigorous standard of proof in the discharge of this burden.”
(emphasis supplied)
G
In the aforesaid case, this Court held that it would not be enough
for the Government to merely state that public interest requires that the
Government should not be compelled to carry out the promise. It is
imperative that the Government when seeking exoneration from liability
of enforcing contract, must satisfy the Court as to how public interest
H
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 227
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
overrides the necessity of enforcing the contract. The aforesaid opinion A
has been reiterated in the case Union of India v. Godfrey Philips India
Ltd., (1985) 4 SCC 369 :
“12.There can therefore be no doubt that the doctrine of
promissory estoppel is applicable against the Government in the
exercise of its governmental, public or executive functions and B
the doctrine of executive necessity or freedom of future executive
action cannot be invoked to defeat the applicability of the doctrine
of promissory estoppel. …
13. Of course we must make it clear, and that is also laid down in
Motilal Sugar Mills case[(1979) 2 SCC 409 : 1979 SCC (Tax) C
144 : (1979) 2 SCR 641] that there can be no promissory estoppel
against the Legislature in the exercise of its legislative functions
nor can the Government or public authority be debarred by
promissory estoppel from enforcing a statutory prohibition. It is
equally true that promissory estoppel cannot be used to
compel the Government or a public authority to carry out a D
representation or promise which is contrary to law or which
was outside the authority or, power of the officer of the
Government or of the public authority to make. We may
also point out that the doctrine of promissory estoppel being
an equitable doctrine, it must yield when the equity so E
requires; if it can be shown by the Government or public
authority that having regard to the facts as they have
transpired, it would be inequitable to hold the Government
or public authority to the promise or representation made
by it, the Court would not raise an equity in favour of the
person to whom the promise or representation is made and F
enforce the promise or representation against the
Government or public authority. The doctrine of promissory
estoppel would be displaced in such a case, because on the facts,
equity would not require that the Government or public authority
should be held bound by the promise or representation made by G
it.”
(emphasis supplied)
61. Therefore, although the appellants are right in claiming that
Government cannot be compelled to perform its undertaking, but equity
H
228 SUPREME COURT REPORTS [2021] 13 S.C.R.
A demands that the Government must place on record sufficient material
on record to claim such exemption. The aforesaid opinion was affirmed
by this Court in the case of Vasantkumar Radhakisan Vora (Dead) by
His LRs. v. Board of Trustees of the Port of Bombay, (1991) 1 SCC
761. The court held therein:
B “20. When it seeks to relieve itself from its application
the government or the public authority are bound to place
before the court the material, the circumstances or grounds
on which it seeks to resile from the promise made or
obligation undertaken by insistence of enforcing the
promise, how the public interest would be jeopardised as
C against the private interest. It is well settled legal proposition
that the private interest would always yield place to the public
interest.”
(emphasis supplied)
D 62. The learned senior counsel, Mr. Rakesh Dwivedi, has sought
to argue that promises made to the respondents-lessees are contradicted
by the representation given to the general public, that the land was being
allotted for construction of a 5-star Hotel. He has sought to create an
exception of public interest as a limit to promissory estoppel.
E 63. As we have noted earlier, there is no substantial violation
portrayed by the appellants herein with respect to allotment of the
scheduled land. Further, the tender documents, as analyzed above, make
it clear that the CIDCO had the power to change the land use, sub-
divide and transfer the plots and accordingly, has been carried out in
terms of the same. In this context, we may only observe that ‘good faith
F standards’ applicable in Government contracts, serve an important
purpose in reinforcing the ‘reliance interest’ in contracts.
64. Even, the High Court while passing the impugned judgment
has correctly held that respondents-lessees have acted pursuant to the
permission granted by CIDCO. Moreover, after getting the
G commencement certificate and other necessary clearances, the
respondents-lessees borrowed a substantial sum of money from other
financial institutions for the development of the plot. However, due to
the ongoing dispute, no development could take place for the past decade.
65. It is admitted as per record that the respondent- M/s. Metropolis
H Hotel was the highest bidder. Moreover, the appellants failed to bring
THE VC & MD, CITY AND IND. DEVEL. CORP. OF MAHARASHTRA 229
LTD. v. SHISHIR REALTY PVT. LTD. [N. V. RAMANA, CJI.]
anything on record to prove that the state exchequer has suffered losses A
pursuant to the said allotment. Nothing has been produced on record,
the public interest that will be prejudiced if the respondents-lessees are
allowed to go ahead with the said project. On the contrary, the
respondents-lessees acting in furtherance of the assurances given by
the authorities, obtained huge financial assistance. Equity demands that
B
when the State failed to produce an iota of evidence of either financial
loss or any other public interest that has been affected, it should be
compelled to fulfill its promises. In fact, it is respondents-lessees who
shall be gravely prejudiced if the order of cancellation is upheld by this
Court after investing a significant amount and facing prolonged litigation.
66. Lastly, the PIL petitioner-Appellant in C.A Nos. 3959-3961 of C
2017 has tried to argue the case on the same lines as that of the CIDCO.
The public interest as sought to be shown in his PIL, is doubtful, in light
of his involvement in the business of construction service. Moreover, the
tone and tenor of the notice dated 12.01.2009, issued by the PIL Petitioner
to the CIDCO, threatening the concerned officers with criminal D
prosecution under Sections 405, 406, 420 read with Section 120(b) of
IPC, inter alia, on the ground of allowing partnership firm, which was in
the process of registration, to bid, needs to be viewed with some suspicion.
In fact, the non-prosecution of the erring officials for the alleged
mismanagement and irregularities is quite telling.
E
67. Before we state the conclusions, this Court would like to
reiterate certain well-established tenets of law pertaining to Government
contracts. When we speak of Government contracts, constitutional factors
are also in play. Governmental bodies being public authorities are expected
to uphold fairness, equality and rule of law even while dealing with
contractual matters. It is a settled principle that right to equality under F
Article 14 abhors arbitrariness. Public authorities have to ensure that no
bias, favouritism or arbitrariness are shown during the bidding process.
A transparent bidding process is much favoured by this Court to ensure
that constitutional requirements are satisfied.
68. Fairness and the good faith standard ingrained in the contracts G
entered into by public authorities mandates such public authorities to
conduct themselves in a non-arbitrary manner during the performance
of their contractual obligations.
69. The constitutional guarantee against arbitrariness as provided
under Article 14, demands the State to act in a fair and reasonable manner H
230 SUPREME COURT REPORTS [2021] 13 S.C.R.
A unless public interest demands otherwise. However, the degree of
compromise of any private legitimate interest must correspond
proportionately to the public interest, so claimed.
70. At this juncture, it is pertinent to remember that, by merely
using grounds of public interest or loss to the treasury, the successor
B public authority cannot undo the work undertaken by the previous
authority. Such a claim must be proven using material facts, evidence
and figures. If it were otherwise, then there will remain no sanctity in
the words and undertaking of the Government. Businessmen will be
hesitant to enter Government contract or make any investment in
furtherance of the same. Such a practice is counter-productive to the
C economy and the business environment in general.
71. From a consideration of the aforesaid facts and circumstances,
it is clear that there is an element of abuse of bureaucratic power behind
subsequent change in the tender allotment. After conducting a tender
process and receiving money, the Government backtracked which led to
D this present prolonged litigation. The impugned order of CIDCO, inter
alia, annulling the allotment on hyper-technical grounds cannot be
sustained for being contrary to the doctrine of fairness. The reasons
stated in the aforesaid order are perverse and per-se based on extraneous
considerations. As analyzed above, we are not able to identify any
E substantive violation of law or tender conditions, which mandate annulling
the allotment and subsequent arrangements, thereby proving the conduct
of the appellant authority to be disproportionate.
72. In light of the above discussion, we find no merit in the appeal
of the appellants herein. Accordingly, these civil appeals are dismissed
F with costs.
73. Pending applications, if any, stand disposed of.
Nidhi Jain Appeals dismissed.