THE STATE OF WEST BENGAL REPRESENTED THROUGH THE SECRETARY & ORS.versusRAJPATH CONTRACTORS AND ENGINEERS LTD.
- Citation
- 2024 INSC 477
- Decided
- 8 July 2024
- Disposal
- Dismissed
- Bench
- ABHAY S OKA
Holding
The three‑month limitation period expired on 30 September 2022, the court’s vacation did not extend it, and the petition filed on 31 October 2022 was barred, leading to dismissal of the appeal.
Summary
The State of West Bengal appointed Rajpath Contractors to construct a bridge, and an arbitral award dated 30 June 2022 directed the State to pay Rs.2.11 crore. The State received the award on the same day and filed a petition under Section 34 of the Arbitration and Conciliation Act on 31 October 2022, after the Calcutta High Court’s pooja vacation. The High Court dismissed the petition, holding that the three‑month limitation period expired on 30 September 2022. The Supreme Court examined whether the limitation period should be computed from the receipt of the award, whether Section 4 of the Limitation Act extends the period when the court is closed, and whether the 30‑day extension under the proviso to Section 34(3) applies. It held that the limitation period began on 1 July 2022, ended on 30 September 2022, and the court’s vacation did not extend it; the 30‑day extension also expired on 30 October 2022. Consequently, the petition filed on 31 October 2022 was out of time and the appeal was dismissed.
Issues considered
- How is the limitation period for filing a petition under Section 34 of the Arbitration and Conciliation Act, 1996 to be computed?
- Does Section 4 of the Limitation Act, 1963 apply when the prescribed period expires before a court vacation?
- Can the additional thirty‑day period under the proviso to Section 34(3) be used to save a belated petition?
Legislation cited
- Arbitration and Conciliation Act, 1996s. 34(3), s. 34 proviso, s. 43
- Constitution of Indias. 133(1), s. 134(A)(a)
- General Clauses Act, 1897s. 9
- Limitation Act, 1963s. 12(1), s. 4
Subjects
Judgment
[2024] 7 S.C.R. 1 : 2024 INSC 477
The State of West Bengal represented
through the Secretary & Ors.
v.
Rajpath Contractors and Engineers Ltd.
(Civil Appeal No. 7426 of 2023)
08 July 2024
[Abhay S. Oka* and Pankaj Mithal, JJ.]
Issue for Consideration
Issue arose as regards correctness of the order passed by the
High Court dismissing the petition u/s. 34 of the Arbitration and
Conciliation Act, holding that it was not filed within the period
specified under sub-section (3) of s. 34 of the Act.
Headnotes†
Arbitration and Conciliation Act, 1996 – s. 34 – Application for
setting aside arbitral awards – Period of limitation for filing
petition u/s. 34 – On facts, petition u/s. 34 filed by the appellant
challenging the arbitral award – Dismissed by the High Court,
holding that it was not filed within the period specified under
sub-section (3) of s. 34 – Correctness:
Held: Period of limitation for filing a petition u/s. 34 will have to be
reckoned from the day when the appellants received the award,
i.e. 30th June 2022 – In view of s. 12(1) of the Limitation Act, the
day from which the limitation period is to be reckoned must be
excluded, as such 30th June 2022 will have to be excluded while
computing the limitation period – Thus, in effect, the period of
limitation, started running on 1st July 2022 – Period of limitation is
of three months and not ninety days – Thus, from the starting point
of 1st July 2022, the last day of the period of three months would
be 30th September 2022 – Pooja vacation started on 1st October
2022 – Three months provided by way of limitation expired a day
before the commencement of the pooja vacation – Furthermore,
the prescribed period within the meaning of s. 4 of the Limitation
Act ended on 30th September 2022 – Thus, the appellants are not
entitled to take benefit of s. 4 – As per the proviso to sub-section
(3) of s. 34, the period of limitation could have been extended
by a maximum period of 30 days – Maximum period of 30 days
* Author
2 [2024] 7 S.C.R.
Digital Supreme Court Reports
expired on 30th October 2022 – Petition was filed on 31st October
2022 – Thus, the High Court was right in holding that the petition
u/s. 34 was not filed within the period specified under sub-section
(3) of s. 34 of the Act. [Paras 6, 7, 10,11]
Case Law Cited
State of Himachal Pradesh and Another v. Himachal Techno
Engineers and Another [2010] 8 SCR 1025 : (2010) 12 SCC 210;
Assam Urban Water Supply & Sewerage Board v. Subash Projects
& Mktg. Ltd. [2012] 1 SCR 403 : (2012) 2 SCC 624; Union of India
v. Popular Construction Co. [2001] Supp. 3 SCR 619 : (2001) 8
SCC 470 – referred to.
List of Acts
Arbitration and Conciliation Act, 1996; Limitation Act of 1963;
Constitution of India; General Clauses Act, 1897.
List of Keywords
Arbitral awards; Period of limitation; Limitation period to be
reckoned.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No.7426 of 2023
From the Judgment and Order dated 04.05.2023 of the High Court
of Calcutta in AP No. 737 of 2022
Appearances for Parties
Ms. Madhumita Bhattacharjee, Ms. Urmila Kar Purkayasthe, Ms.
Srija Choudhury, Advs. for the Appellants.
Saurav Agrawal, Priyankar Saha, Sarad Kumar Singhania, Mrs.
Rashmi Singhania, Anshuman Choudhary, Advs. for the Respondent.
Judgment / Order of the Supreme Court
Judgment
Abhay S. Oka, J.
FACTUAL ASPECTS
1. The first appellant – the State of West Bengal appointed the
respondent as a contractor for the construction of a bridge. As there
[2024] 7 S.C.R. 3
The State of West Bengal represented through the Secretary & Ors. v.
Rajpath Contractors and Engineers Ltd.
was a dispute between the parties, the respondent invoked the
arbitration clause in the contract, and a sole arbitrator was appointed.
On 30th June 2022, the Arbitral Tribunal passed an award directing
the appellants to pay a sum of Rs.2,11,67,054.00 (Two Crores
Eleven Lakhs Sixty-Seven Thousand Fifty-Four Rupees Only) to
the respondent with interest thereon, as directed. The counter-claim
made by the appellants was dismissed. The appellants received a
copy of the award on the same day. The High Court of Judicature
at Calcutta was closed for pooja vacation from 1st October 2022 to
30th October 2022 (both days inclusive). On 31st October 2022, the
appellants filed a petition under Section 34 of the Arbitration and
Conciliation Act, 1996 (for short, ‘the Arbitration Act’) to challenge the
award. By the impugned order dated 4th May 2023, the High Court
dismissed the petition under Section 34 of the Arbitration Act filed
by the appellants on the ground of bar of limitation. The High Court
held that the period of limitation for filing a petition under Section
34 expired on 30th September 2022. Therefore, the appellants are
not entitled to the benefit of Section 4 of the Limitation Act of 1963
(for short, ‘the Limitation Act’).
2. Being aggrieved by the view taken by the High Court, the appellants
are in this appeal. We may note here that under the impugned
judgment, the High Court granted a certificate to prefer an appeal
before this Court by exercising powers under Article 133 (1) and
Article 134(A)(a) of the Constitution of India.
SUBMISSIONS
3. The learned counsel appearing for the appellants submitted that as
the period of limitation for filing a petition under Section 34 of the
Arbitration Act ought to have been calculated from 1st July 2022, the
prescribed period of limitation ended on 1st October 2022, which was
the first day of pooja vacation. Therefore, the petition under Section
34 of the Arbitration Act filed immediately after the re-opening of the
Court on 31st October 2022 must be held to be within limitation. The
learned counsel relied upon Section 9 of the General Clauses Act,
1897 (for short, ‘the General Clauses Act’). The learned counsel also
submitted that the petition could not be e-filed in pooja vacation as
the relevant e-filing notification provided for e-filing of only urgent
matters during the vacations. The learned counsel relied upon a
4 [2024] 7 S.C.R.
Digital Supreme Court Reports
decision of this Court in the case of State of Himachal Pradesh
and Another v. Himachal Techno Engineers and Another1.
4. The learned counsel appearing for the respondent supported the
findings recorded by the High Court. He submitted that in any event,
the benefit of Section 4 of the Limitation Act is available only if the
proceedings are filed within the prescribed period of limitation, which
will be three months in this case in terms of Section 34(3) of the
Arbitration Act. The learned counsel relied upon a decision made by
this court in the case of Assam Urban Water Supply & Sewerage
Board v Subash Projects & Mktg. Ltd.2. He also invited our attention
to a decision of this Court in the case of Union of India v. Popular
Construction Company 3. He submitted that, as held by this Court
in the said decision, the applicability of Section 5 of the Limitation
Act is excluded in view of the language used in the proviso to sub-
section (3) of Section 34.
OUR VIEW
5. The facts are undisputed. The award made by the Arbitral Tribunal
on 30th June 2022 was served upon the appellant on the same day.
Between 1st October 2022 and 30th October 2022 (both days inclusive),
the High Court was closed for pooja vacation. The petition under
Section 34 of the Arbitration Act was filed on 31st October 2022.
6. The period of limitation for filing a petition under Section 34 of the
Arbitration Act is governed by sub-section (3) of Section 34. Sub-
section (3) of Section 34 reads thus:
“(3) An application for setting aside may not be made
after three months have elapsed from the date on which
the party making that application had received the arbitral
award or, if a request had been made under section 33,
from the date on which that request had been disposed
of by the arbitral tribunal:
Provided that if the Court is satisfied that the applicant was
prevented by sufficient cause from making the application
1 [2010] 8 SCR 1025 : (2010) 12 SCC 210
2 [2012] 1 SCR 403 : (2012) 2 SCC 624
3 [2001] Supp. 3 SCR 619 : (2001) 8 SCC 470
[2024] 7 S.C.R. 5
The State of West Bengal represented through the Secretary & Ors. v.
Rajpath Contractors and Engineers Ltd.
within the said period of three months it may entertain the
application within a further period of thirty days, but not
thereafter.”
7. As per Section 12(1) of the Limitation Act, the day from which the
limitation period is to be reckoned must be excluded. In this case,
the period of limitation for filing a petition under Section 34 will have
to be reckoned from 30th June 2022, when the appellants received
the award. In view of Section 12(1) of the Limitation Act, 30th June
2022 will have to be excluded while computing the limitation period.
Thus, in effect, the period of limitation, in the facts of the case,
started running on 1st July 2022. The period of limitation is of three
months and not ninety days. Therefore, from the starting point of
1st July 2022, the last day of the period of three months would be
30th September 2022. As noted earlier, the pooja vacation started
on 1st October 2022.
8. We may note here that Section 43 of the Arbitration Act provides
that the Limitation Act shall apply to the arbitrations as it applies to
proceedings in the Court. We may note here that the consistent view
taken by this Court right from the decision in the case of Union of
India v. Popular Construction Co.3 is that given the language used
in proviso to sub-section (3) of Section 34 of the Arbitration Act, the
applicability of Section 5 of the Limitation Act to the petition under
Section 34 of the Arbitration Act has been excluded.
9. Now, we proceed to consider whether the appellant will be entitled
to the benefit of Section 4 of the Limitation Act. Section 4 of the
Limitation Act reads thus:
“4. Expiry of prescribed period when court is closed.—
Where the prescribed period for any suit, appeal or
application expires on a day when the court is closed, the
suit, appeal or application may be instituted, preferred or
made on the day when the court re-opens.
Explanation.—A court shall be deemed to be closed on
any day within the meaning of this section if during any
part of its normal working hours it remains closed on
that day.”
(underline supplied)
6 [2024] 7 S.C.R.
Digital Supreme Court Reports
The meaning of “the prescribed period” is no longer res integra. In
the case of Assam Urban Water Supply & Sewerage Board v.
Subash Projects & Mktg. Ltd.2, in paragraphs nos. 13 and 14, the
law has been laid down on the subject. The said paragraphs read thus:
“13. The crucial words in Section 4 of the 1963 Act are
“prescribed period”. What is the meaning of these words?
14. Section 2(j) of the 1963 Act defines:
“2. (j) ‘period of limitation’ [which] means the period of
limitation prescribed for any suit, appeal or application
by the Schedule, and ‘prescribed period’ means the
period of limitation computed in accordance with the
provisions of this Act;
Section 2(j) of the 1963 Act when read in the context
of Section 34(3) of the 1996 Act, it becomes amply
clear that the prescribed period for making an
application for setting aside an arbitral award is
three months. The period of 30 days mentioned in
the proviso that follows sub-section (3) of Section
34 of the 1996 Act is not the “period of limitation”
and, therefore, not the “prescribed period” for the
purposes of making the application for setting aside
the arbitral award. The period of 30 days beyond
three months which the court may extend on sufficient
cause being shown under the proviso appended to
sub-section (3) of Section 34 of the 1996 Act being
not the “period of limitation” or, in other words, the
“prescribed period”, in our opinion, Section 4 of the
1963 Act is not, at all, attracted to the facts of the
present case.”
(underline supplied)
Even in this case, this Court was dealing with the period of limitation
for preferring a petition under Section 34 of the Arbitration Act.
We may note that the decision in the case of State of Himachal
Pradesh and Another v. Himachal Techno Engineers and
Another 1 which is relied upon by the appellant, follows the
aforesaid decision.
[2024] 7 S.C.R. 7
The State of West Bengal represented through the Secretary & Ors. v.
Rajpath Contractors and Engineers Ltd.
10. In the facts of the case in hand, the three months provided by way
of limitation expired a day before the commencement of the pooja
vacation, which commenced on 1st October 2022. Thus, the prescribed
period within the meaning of Section 4 of the Limitation Act ended
on 30th September 2022. Therefore, the appellants were not entitled
to take benefit of Section 4 of the Limitation Act. As per the proviso
to sub-section (3) of Section 34, the period of limitation could have
been extended by a maximum period of 30 days. The maximum
period of 30 days expired on 30th October 2022. As noted earlier,
the petition was filed on 31st October 2022.
11. Thus, looking from the angle, the High Court was right in holding
that the petition filed by the appellants under Section 34 of the
Arbitration Act was not filed within the period specified under sub-
section (3) of Section 34. Hence, we find no merit in the appeal, and
it is, accordingly, dismissed.
Result of the case: Appeal Dismissed.
†
Headnotes prepared by: Nidhi Jain
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.