Created byFuzzy Cloud

Supreme Court of India

THE STATE OF J & K AND ANR.versusDEV DUTT PANDIT

Citation
1999 INSC 358
Decided
27 August 1999
Disposal
Case Partly allowed

Holding

The arbitrator did not exceed his jurisdiction; claims based on the final bill measured by the Local Commissioner were within the contract, and the arbitrator was entitled to award interest at 10% per annum, so the award stands with interest at 10% and the deleted claim items are reinstated, while the cost award is set aside.

Summary

The State of Jammu & Kashmir terminated a measurable‑item rate contract with contractor Dev Dutt Pandit after less than 50% of the work was completed and the contractor filed a petition under Section 20 of the Arbitration Act. An arbitrator awarded Rs. 20,08,000 based on a final bill prepared from measurements taken by a Local Commissioner, and granted interest at 10% per annum. The State objected under Sections 30 and 33, claiming the arbitrator entertained fresh claims (idle labour, monsoon damage, deviation) that were outside the contract and that the interest rate was excessive. The High Court reduced the interest to 6% and deleted two claim items; the Division Bench partially upheld that reduction. The Supreme Court held that the final‑bill claims were within the contract, the arbitrator did not exceed his jurisdiction, and the 10% interest was permissible under the Interest Act and CPC, restoring the award with interest and setting aside the cost award. Both appeals were partly allowed.

Issues considered

  • Whether the arbitrator entertained fresh claims not pleaded in the Section 20 petition or outside the contract terms
  • Whether such claims, if entertained, were beyond the scope of the reference under Sections 30 and 33 of the Arbitration Act
  • Whether the award was contrary to the terms of the contract (idle labour, monsoon damage, deviation without written permission)
  • Whether the arbitrator committed misconduct in granting the award
  • Whether interest at 10% per annum is permissible under the Interest Act, 1978 and Section 34 of the CPC

Legislation cited

Subjects

ArbitrationNon‑speaking awardInterest rateContractual termsIdle labourForce majeureMeasurement of workFinal billSections 30 and 33Commercial transaction

Judgment

                            THE STATE OF J & KAND ANR.                                     A
                                         v.
                                  DEV DUTT PANDIT

                                     AUGUST 27, 1999

                          [D.P. WADHWA AND M.B. SHAH. JJ.]                                 B

               Arbitration Act, I 940 :

               Sections 30 and 33-Measurable item rate contract-Final Bill based
         on measurements of work by local Commissioner-No objection to such                C
         measurements-Claim based on final bill allowed by the arbitrator-Whether
         award against the terms of the contract-Held, under the facts and
         circumstances, claim based on final bill not outside the terms of the contract.

              Arbitration-Object of-Held, it is an important Alternative Disputes          D
         Redressal process which should be encouraged-Situations which bring bad
....,
.        name to the arbitration process should be avoided.

               Interest Act, 1978-Sections 2(b) and 5-Arbitration Award-Interest
         at the rate of I 0% awarded-Challenged-Commercial transaction-Held,
         under the facts and circumstances, interest at the higher rate than 6% can        E
         be awarded-Code of Civil Procedure, 1908-Section 34.

               Words and Phrases- 'Idle labour'-Meaning of

                Appellant-State accepted tender and allotted work of Rs. 12,23,500 to
         respondent-contractor which was to be completed within a stipulated time.         F
         When contractor failed to complete the work within the stipulated time,
         contract was terminated by the State and by that time the contractor had
         executed less then 50% of the work and had been paid a sum of Rs.
         5, 71,900. The contractor filed petition under Section 20 of the Arbitration
    ..   Act claiming a sum of Rs. 39,47,000 which was allowed and the dispute was         G
         referred to an arbitrator. In the proceedings under Section 20 the court
         appointed a Local CommissiOner, to take meas11rements of the work done at
         the site by the contractor and on the basis of the report of the Local
         Commissioner, the contractor prepared a final bill for Rs. 14,32,436.62.
         The contractor filed a claim of Rs. 63,61,000 before the arbitrator which
                                                                                           H
    2                        SUPREME COURT REPORTS [1999) SUPP. 2 S.C.R.

A included cla~ms on account of final bill, idle labour, damage due to mansoon,
    deviation or alteration in work, interest, etc. The arbitrator gave a non-
    speaking award for a sum of Rs. 20,08,000 in favour of the contractor with
    interest at the rate of 10% per annum from the date of application for
    appointment of the arbitrator upto the date of payment.

B          State filed objections to the award under Sections 30 and 33 of the
    Arbitration Act and alleged misconduct by the arbitrator on the grounds that
    the award was against the terms of the contract and that the arbitrator had
    travelled beyond the terms of reference in passing the impugned award and
    contended that as per the order of reference, new claims based on
C   measurements recorded by the Local Commissioner and not mentioned in
    the summary of claims filed with the Section 20 petition could not be advanced.
    Single Judge of the High Court dismissed the objections but reduced the
    rate of interest to 6% per annum from the date of award till payment.
    Aggrieved by the order of the Single Judge, the contractor and the State both
    filed appeals. Divi~ion Bench partly allowed the appeal of the State by deleting
D   the two claims under items 13 and 14 which amounted to Rs. 8,08,250 but
    dismissed the appeal of the contractor against reducti~n in the rate of
    interest. Against the order of the Division Bench, the contractor and the
    State have both appealed to this Court.

E         The State reiterated the contentions advanced in the High Court. The
    contractor contended that it is a non-speaking award and court cannot go
    info the mental process of the. arbitrator in making the award on various
    claims; and that "idle employees" as mentioned in clause 69 of the contract
    is not the same thing as "'idle labour" and it would only mean regular
    employees on the roll of the contractor like engineers etc.
F
          Partly allowing the appeals, the Court

          HELD : 1. Court has certain limitations while examining a non-speaking
    award but there is no complete bar in examining if the award is in terms of
G   the reference or the terms of the contract. [13-D)

          2. Under the terms of the contract, the contractor could not claim any
    loss done to him on account of early onset of monsoon or otherwise; any
    claim towards idle labour; and claim for any work done on account of
    deviation or alteration without the previous permission in writing of the
H   Engineer. When there is no writing for any alteration or deviation the claim
                                STATEv.D.D. PANDIT                                3
      could not have been allowed by the arbitrator on that ground.                    A
                                                               [12-G-H; 13-B-C]

           3. A restricted construction cannot be put on the term "idle employees"
      as not to include idle labour as well. Read as a whole skilled and unskilled
      labour are all employees of the contractor under the contract. [13-A-B]
                                                                                       B
              4. Local Commissioner measured the work done by the contractor in
      presence of both the parties and thereafter he submitted his report. On the
      basis of measurement so recorded by the Local Commissioner the contractor
      prepared the final bill of claim and after taking out the money already paid
      to him, made claim for the balance. There is no objection of measurements C
      recorded by the Local Commissioner and the final bill prepared on that basis.
      It is difficult how the two claims made under items 13 and 14 could have been
      said to be either new claims or outside the terms of the contract. Under
      clause 5 of the contract, contractor is to be paid for the work executed by
      him under the contract at the rates specified therein. The balance after
      deducting from the tif!al bill the amount paid to the contractor would be the D
      sum to which in all the contractor would be entitled to under the award which
      comes to Rs. 8,60,251. [12-E-F; 13-F-G]

            5.1. Under the Interest Act, 1978, which came into force on August 19,
      1981, cqurt includes arbitrator. Under Section.5 of the Interest Act Section
...   34 of Code of Civil Procedure, would, therefore, apply to the arbitrator as      R
      well. Arbitrator is thus entitled to award interest pendente lite and future
      interest at the rate not exceeding the current rate of interest which has also
      been defined in clause (b) of Section 2 of the Interest Act.[13-H; 14-A-B]

            5.2. The arbitrator awarded interest at the rate of 10% per annum
      which was reduced by the courts below to 6% per annum. Under Section 34 F
      of Code of Civil Procedure interest at the higher rate than 6% can be
      awarded where the liability in relation to the sum so adjudged had arisen out
      of commercial transaction. There is nothing on the record to show that
      interest awarded by the arbitrator at the rate of 10% is in contravention of
      Section 34 of Code of Civil Procedure. That being so the courts below were G
      not correct in reducing the rate of interest as granted by the arbitrator.
      Therefore, the award of interest at the rate of 10% per annum as granted
      by the arbitrator from the date the arbitrator entered into reference till
      realisation of the amount under the award is restored. [14-&D]

           6. Arbitration is considered to be an important Alternative Disputes        H
     4 .                      SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.

 A Redressal process which is to be encouraged because of high pendency of
     cases in the courts and cost of litigation. Arbitration has to be looked up to
                                                                                           ,./
     with all earnest so that litigant public has faith in the speedy process of
     resolving their disputes by this process. When claims are inflated out of all·
     proportions, not only that heavy cost should be awarded to the other party but
 B   the party making such inflated claim should be deprived of the cost.


                                                                                           ,--
                                                                  [14-F-G; 15-A-B]

            CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3551of1990
     Etc.

          From the Judgment and Order dated 6.2.89 of the Jammu & Kashmir
 C   High Court in L.P.A. No. 13of1986.

           L.D. Thakur, L.K. Gupta and D.K. Garg for the Appellants, in CA. No.
     3552190.

          D.D. Thakur, Ms. Pumima Bhat Kak, Mahesh Agrawal, Rishi Agrawal,
D    Atul Sharma and E.C. Agrawala for the Respondent. In C.A. No. 3551190.

           B.A. Mahanti, Ms. Mamta Tripathy, G.M. Kawoosa and Ashok Mathur
     for the State.

            The Judgment of the Court was delivered by

E            D.P. WADHWA, J. Both the parties are aggrieved by judgment dated
     February 6, 1989 of the Division Bench of the High Court of Jammu and
     Kashmir passed in an appeal against judgment dated May 10, 1986 by the
     learned single Judge of that High Court. While the learned single Judge made
     the award given under the Arbitration Act, 1940 a rule of the court and also
F    granted interest, the Division Bench in appeal deleted two claims ~om the
     award and also reduced the rate of interest. The award was in favour of Dev
     Dutt Pandit, the Contractor. He is aggrieved by deletion 9f two claims and
     also lowering the rate of interest and the State is aggrieved against the award
     itself. Thus two separate appea1s.
G         Tender of the contractor for. earth work, excavation, minor drainage
   crossing, overhead crossing, road bridges and cement concrete lining of Ravi
   Canal Project was accepted by the State Government and by order dated May
   6, 1976 work was allotted to him. The work was to be completed within 18
 . months, time being the essence of the contract. On May 22, 1976 contractor
                                                                                       \
   commenced work. He could not complete the work within the stipulated time.
H The contract was partially terminated in the structural portion of the work on
                  STATE v. D.D. PANDIT [D.P. WADHWA, J.]                        5
· January 12, 1980. On June 6, 1980 the whole of the contract was terminated        A
  because of default committed by the contractor. The contractor filed a petition
  under Section 20 of the Arbitration Act as the contract stipulated arbitration
  agreement between the parties. Some of the terms of the contract containing
  the arbitration agreement, we may reproduce as under :

          "5. CONTRACT RATES:                                                       B

         The contractor shall be paid for the works executed by him under this
         agreement at the rates specified in Annexure I annexed hereto subject
         to other terms and conditions embodied in this agreement.
                                                                                    c
         8. VARIATION IN QUANTITIES AND EXTRA ITEMS

         The quantities shown in the Annexure III to this agreement shall not
         be taken as final. The Engineer in-charge shall be authorised to direct
         the contractor to execute extra items not shown in the aforesaid
         annexure III or increase/decrease the quantities beyond these described    D
         in the said annexures as may be required to be executed and for such
         increase/decrease quantities the contractor shall be paid at the rates
         specified in the annexure I.

         The quantities shown in the Annexure III may be decreased in detailed      E
         drawings to be furnished to the contractor during execution and the
         contractor shall be paid only for the work done or executed and shall
         have no claim for any compensation on account of any profit or
         advantage that might have accrued or that may accrue to him otherwise.

         14. FORCE MAJOURE                                                          F

         A. The completion schedule is subject to the operation of the force
         Majoure Clause which for the purpose of this contract is defined as
         acts of God, Civil, commotion, sabotage, fires, floods, earthquakes
         explosions or other catastrophes, epidemics, q_uarantines, restrictions,   G
         strikes and other labour troubles, embargoes, or other transportation
         delays beyond the control of the contractor for which only extension
         in time considered reasonable by the department shall be granted and
         the contractor shall have no claim for compensation or increase in
         rates etc. or charges for restoring damages to the works plant or
         material.                                                                  H
                                                                                       ~
    6                     SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.

A        17. DAMAGE TO WORKS

         From the commencement to the taking over of the works by the
         Department the contractor shall be responsible for any damage or loss
         to the works or part thereof caused due to any reason whatsoever.
         The contractor shall ·at his own cost repair and· make good the loss
B        or damage in every respect to the satisfaction of the Engineer whose
         certificate in this behalf shall be conclusive proof of the defects etc~
        ·havmg been removed.

         19. SEIT/NG OUT

c       ·The contractor shall be responsible for the true and proper setting out
         of the works and for the correctness of the positions, levels, bench
         marks alignments and dimensions in works and for the provisions and
         maintenance of all necessary instruments, appliances, bench marks
         and reference marks and labour etc. in connection therewith including
         charges therefor shall be borne by him.
D
         Reference line and bench marks will be set upon at the site of works
         by the site of works by the department at contractor's cost. The
         contractor shall at his own cost and responsibility locate and establish
        temporary bench marks and reference lines for all the structures as
        may be required for the execution of the works according to the
E       detailed drawings and specifications and as required by the Engineer.
        The contractor shall provide at his own cost all labour and materials
        that may be required for checking the works during execution by the
        staff of Engineer in-charge. Such checks shall not absolve the contractor
        of his responsibility from carrying out the works strictly according to
F       the detailed drawings and specifications and as per instructions issued
        to him by the Engineer during the execution of the works.

        23. RESPONSIBILITY OF CONTRACTOR

        Time being the essence of the contract, the responsibility for execution
        of works within eighteen (18) months in an efficient and workmen like
G       manner and in conformity with the department's "drawings and
        specifications shall be of the contractor.

        27. DEVIATIONS ALTERATIONS ETC. IN THE WORKS                                t.,.
                                                                                       ~

        The contractor shall not in any way a'.lter the works or any part thereof
H       in respect of designs, quality, materials or specifications without the
                   STATE v. D.D .. PANDIT [D.P. WADHWA, J.]                    7
          previous permission in writing of the Engineer. The contractor shall      A
          not take advantage of any error or discrepancies occurring in the
          drawings, designs or specifications but shall report the same to the
          Engineer who shall make or approve the corrections if necessary.

          69. CLAIMS NOT ENTERTAINABLE
                                                                                    B
          From the date of allotment of works and taking over on completion
          by .the department no claim shall be entertained in respect of the
          works under this agreement against the department for,

          (a)   Increase in the cost of POL Railway or road freight

          (b)   Taxes duties and octroi, etc.                                       c
          (c)   Increased wages of labour skilled or unskilled and cost of
                materials
          (d) Rise irl cost of living index
          (e)   Business or any other losses, and                                   D
.-.-(

          (t)   Idle employees on any account whatsoever.
          74. ARBITRATION

          If at any time any doubt, question dispute or difference whatsoever,      E
          shall arise between the contractor and the Government upon or in
          relation to or in connection with this contract, either of the parties
          may give to the other notice in writing of the existence of such doubt,
          question, dispute or difference and the same shall be referred to a
          person mutually agreed upon by the parties failing such agreement by
          any officer of the Government as the minister In-charge, P.W.             F

-         Department Jammu and Kashmir Government may nominate for
          arbitration under the Jammu and Kashmir Arbitration Act and rules
          framed thereunder. The decision of the Arbitrator shall be final,
          conclusive and binding upon the parties.

         (b) The contractor s~all not delay the carrying out of works by reason G
         of any reference to Arbitration and shall proceed with the works with
         all one due diligence and shall until the decision of the Arbitrator,
         abide by the decision of the engineer or his representative in-charge
         of the works duly conveyed by him."

        Petition under Section 20 of the Arbitration Act by the contractor was      H
    8                        SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.

A filed on June 12, 1980. On the following day when the petition was taken up
    without any notice to the State the Court appointed Local Commissioner to
    take measurements of the work done at the site by the contractor. In the
    application for seeking interim relief the contractor prayed that "a commissioner
    may be appointed to go on spot and record the measurements of the work
B   done by the petitioner in presence of the parties" and till then "the respondents
    may be restrained from changing the status quo at site or disturbing the
    position of the work already done". Court passed the following order:-

           "An application has also been moved on behalf of the petitioner
           which is O.M.P. No. 136of1980 with the prayer that measurements
           of the work done at site may be got recorded by appointing a
c          Commissioner as the work done by him is (?) obliterated. The
           application is supported by an affidavit. Shri Bashir Ahmed Shah, Ex.
           Engineer, R & B Clo Chief Engineer, P.W.D. Jammu, is appointed as
           Commissioner to visit the spot and record the measurements and
           submit his report within a week. Till the measurements are recorded
                                                                                        .·~
D          the respondent will not execute any fresh work. The Commissioner's
           fee is fixed at Rs. 300 to be borne by the petitioner."

          Subsequently Local Commissioner was changed. Local Commissioner
    submitted his report on December 9, · 1980 which formed part of the record.
    In his petition under Section 20 of the Arbitration Act the contractor claimed
E   a sum of Rs. 39,47,000 under various heads. This petition was allowed by
    order dated April 9, 1982. We quote the operative portion of the order as
    under:

           "The disputes mentioned in the application U/s 20 of the Arbitration
           Act as well as the objections filed thereto by the other side ate,
F          therefore, referred to the aforesaid Arbitrator with a direction that he
           shall enter upon the reference and make his award within four months
           thereafter in accordance with law. The parties shall be at liberty to
           raise any further disputes before him provided it is not against the
           temi of the agreement. The parties, however, shall be mpossession
G          of the original agreement, shall produce the same before the Arbitrator.
           Copy of the application, the objections filed thereto and a copy of this
           order shall be provided to the arbitrator. Arbitration petition No. 72 of
           1980 stands finally disposed of."

         Before arbitrator the contractor now claimed a sum of Rs. 63,61,000. On
H the basis of the report of the Local Commissioner giving details of the
                         STATEv. D.D. PANDIT [D.P. WADHWA,J.]                           9
        measurements of the work done by the contractor a final bill was prepared            A
•       by the contractor which amounted to Rs. 14,32,436.62. He claimed this bill to
        be based on the terms of the contract.

               The arbitrator gave his Award on February 2, 1983. It is a non-speaking
        Award. He awarded a sum of Rs. 20,08,000 to the contractor with interest at
        the rate of 10% per annum from the date of application for appointment of            B
        the arbitrator upto the date of payment. It was also provided that the "interest
        on the amount awarded against claim Nos. 16 and 18 shall start and will be
        computed from the date of the publication of the Award". Claims I 6 and 18
        respectively were claims of interest at the rate of 24% per annum by the
        contractor respectively on recoveries made and delay in release of illegally         C
        deducted amounts for excess consumption of cement. Awards on claims 16
        and 18 were restricted to Rs. 20,400 and Rs. 9,524. Lastly, it was directed that
        if the amount awarded was not paid within three months from the date of the
        Award interest payable shall be I 8% per annum on the amount so awarded
        upto the date of realisation.
                                                                                             D
              As noted above, the contract was for a total sum of Rs. 12,23,500. The
        contractor allegedly committed breach of the contract. It was partially terminated
        on January 12, I 980 in respect of structural portion of the work and the
        contract was finally terminated on June 6, I 980. By this time the contractor
        had executed less than 50% of the work and had been paid a sum of Rs.
        5,71,900.                                                                            E
               The matter now again came to the court. This time for making the Award
        rule of the court. State filed objections to the Award under Sections 30 and
        33 of the Arbitration Act and alleged misconduct by the arbitrator. It was on
        the grounds that the Award was against the terms of the contract and the
        arbitrator travelled beyond the order of reference. It was submitted that new        F
        claims were introduced before the arbitrator which were not made in the
        petition under Section 20 of the Arbitration Act and, therefore, could not be
        taken cognizance of by the arbitrator. What the contractor claimed in Section
        20 petition was given in the annexure thereto and this is how the claims were
        advanced:-                                                                           G
               "Similarly numerous other items in which the petitioner either was not
    J          paid at all or was not paid have been comprehensively indicated in
               the Annexure to this petition which may kindly be treated as a part
               and parcel of the present petition. The petitioner has tentatively
               assessed the various claims on various accounts which he is entitled          H
    IO                       SUPREME COURT REPORTS (1999] SUPP. 2 S.C.R.

A           to from the said department which may be referred to for the purpose
            of convenience."

            Annexure contained summary of claims which included claims on
    account of earth work cutting as the original alignment was later abandoned,
    idle labour, illegal recoveries, interest on illegal recoveries, etc.
B
          It was submitted by the State that the order dated April 9, 1982 referring
    the disputes to arbitration did not allow lhe contractor to advance additional
    claims not mentioned in the summary of claims annexed to the petition. The
    objection was to the claim made by the contractor of Rs. 14,32,436 which was
    based on the measurements recorded by the Local Commissioner of the work
C   done by the eontractor under the contract. This amount is reflected in claims
    13 and 14 before the arbitrator.

           Learned single Judge of the High Court by order dated May l 0, 1986
    dismissed the objections raised by the State and made the Award rule of the
D   Court. He, however, reduced the· rate of interest and now the interest was
    payable at the rate of 6% per annum from the date of the Award till payment.
    Award of penal interest at the rate of 18% was deleted. Matter was then taken
    to the appellate Bench of the· High Court in appeal. Same objections to the
    Award were repeated by the State. Contractor objected to that part of the
    ~rder of learned single Judge by which i~terest awarded by the arbitrator was
E   reduced. The Division Bench upheld the order of the learned single Judge
    except that claims under items 13 and 14 were deleted which amounted to Rs.
    8,08,250. The appeal of the State was thus allowed in part. Plea of the
    contractor against reducing the interest by the learned single Judge was
    rejected. While deleting the claims under items 13 and 14 the Division Bench
F   observed as under:

           "The work done by the contractor was duly measured and the final
           bill prepared in accordance with paragraph 40 (measurements and
           tenns of payment) of the Agreement enclosed by the contractor with
           his statement. of facts and claim before the arbitrator amounting to Rs.
           14,32,436.62 paise out of which deducting the amount of Rs. 5,71,915.60
G
           paise paid to the contractor leaves the balance of Rs. 8,60,521.02 paise
           only over and above this amount any measurement subsequently
           done by the commissioner cannot form part of the agreement and
           could not be allowed to be multiplied to an unlimited extent beyond
           the rates and work prescribed in the agreement. Even the summary of
H          claims submitted before the court for reference do not include the
                     STATE v. D.D. PANDIT [D.P. WADHWA, J.]                      11
            amount claimed under this head. The other heads of claim overlap the      A
            claim No. 20 on which item 13 is awarded. In consideration of the
            foregoing circumstances we have no doubt in our mind to hold, that
            the arbitrator made these items of the award No. 13 granting Rs.
            95,400.00 based on claim No. 20 (due to escalation Rs. 2,86,487 - claim
            rejected by arbitrator) of the subsequent statement of facts and claim,   B
            exceeded his jurisdiction which is against the terms of the agreement
            and thus invalid in view of the reference. The items No. 13 and 14 of
            the Award being independent of the entire award are separable, there
            can be no legal impediment in deleting the two items based on claim
            No. 20 from the Award. The appeal to this extent, in our opinion,
            deseI"Ves to be allowed to disallow the claims of Rs. 7,12,850.00 and     C
            Rs. 95,500.00 totalling to Rs. 8,08,250.00 (Eight lacs, eight thousand
            two hundred and fifty only) and the award to that extent is set aside."

          State still felt aggrieved. Contractor became more aggrieved because of
    deletion of his two claims and rejection of his plea for enhancement of the
    interest as awarded by the Arbitrator.                                            D
           We have noted the relevant terms of the contract. It is not necessary
    for us to set out the claims made by the contractor in detail· except to note
    that out of23 claims under different heads claims 2, 6, 19, 20, 21 and 22 were
    rejected py the arbitrator; claims 1 and 3 relate to the alteration of the work   E
    being excavation done at original site abandoned, refilling of the original
    excavation, fresh excavation on new alignment and shifting of centre line and
    consequent refilling compacting and lean concrete lining; claims 4, 5, 10 (in
    part} and 11 are for damage due to monsoon; claims 8, 9, IO (in part) and 12
    are on account of idle labour; cJaims 7, 13, 14 and 17 are by and large under
    the terms of the contract; claims 15, 16 and 18 are for interest which were not   F
    mentioned in the summary of claims annexed with Section 20 petition and
    claim 23 is for the cost of arbitration.

          Before the learned single Judge four issues were framed arising out of
    the pleadings of the parties. These are:
                                                                                      G
            "(I} Whether any fresh claims were entertained by the Arbitrator
                 during the course of arbitration proceedings?
J
            (2)   In case issue no. 1 is proved in affirmative whether any such
                  claim was beyond the scope of reference made to the arbittator
                  by the court, if so how?                                            H
      12                       SUPREME COURT REPORTS [1999) SUPP. 2 S.C.R.

 A            (3)   Whether the award made by the Arbitrator was against the terms
                    of the agreement? If so, whether the same amounts to
                    misconduct?
              (4)   Whether the arbitrator committed misconduct legal or otherwise
                    in making of the Award? If so, how?"
 B
            The court allowed the parties to lead evidence on the issues so framed.

           The contract has been entered into on the basis of measurable item rate
     contract and the rates of each items were quoted accordingly. According to
     the measurements, as quoted, the contract was for a total value of
 c   Rs. 12,23,500.

           Mr. Mahanti, senior advocate for the State of -Jammu and Kashmir
     reaffumed the arguments advanced in the High Court that the Award travelled
                                                                                              -
     beyond the terms of reference and was also against the terms of the contract.
     He said claims 13 and 14 could not have been advanced before the arbitrator
D    as these claims were not mentioned in the summary of claims· flied with the
     Section 20 petition. He said High Court was right in deleting these two claims.
     The order referring the disputes to arbitration allows those claims to be raised
     before the arbitrator which fell within the terms of the contract.

            The contractor has to be paid on the basis of measurement of the work
E    done by him. Local Commissioner measured the work done by the contractor
      in presence of both the parties and thereafter he submitted his report. On the
     basis of measurement so recorded by the Local Commissioner the contractor
     prepared the final bill of claim for Rs. 14,32,436 and after taking out the amount
     already paid fo him, made claim for the balance. It is difficult to see how claims
F    made under items 13 and 14 could be said to be either new claims or outside
     the terms of the contract. Under clause 5 of the contract, contractor is to be
     paid for the work executed by him under the contract at the rates specified
     therein.

         Under clause 17 of the contract it is the contractor, who is responsible
G for any damage or loss to the works or part thereof caused due to any reason                f'
   whatsoever and he at his own cost is required to repair and to make good
   of loss or damage. Contractor, therefore, could not claim any loss done to him
   on account of early onset of monsoon or otherwise. Similarly under the terms           l
   of the contract he cannot claim any amounts towards idle labour. As a matter
   of fact under clause 69 ·these claims are not entertainable at all. Mr. Thakur
H /for the contractor said that "idle employees" as mentioned in clause 69 of the
                     STATEv. D.D. PANDIT (D.P. WADHWA,J.J                          13
    contract is not the same thing as "idle labour". According to him, the term         A
    "idle employees" would mean regular employees on the roll of the contractor
    like engineers etc. We do not think such a restricted construction can be put
    on the term "idle employees" as not include idle labour as well. Read as a
    whole skilled and unskilled labour are all employees of the contractor under
    the contract.
                                                                                        B
         Any work done on account of deviation or alteration could not be
    undertaken without the previous permission in writing of the engineer. It is
    admitted case of the contractor himself that there is no writing though it was
    promised to him orally. In view of clause 27 of the contract claims 1 and 3



-   could not have been accepted. When the principal claims were wrongly
    awarded there is no question of any award of interest on the amounts claimed
    under those heads.

          It was submitted before us that it is a non-speaking Award and this
                                                                                        C



    Court cannot go into the mental process of the arbitrator in making the award
    on various claims. Court has certain limitations while examining a non-speaking D
    award but there is no complete bar in examining if the award is in terms of
    the reference or the terms of the contract. Regarding the claims made before
    the arbitrator in respect of items 1 and 3 evidence was also recorded by the
    learned single Judge. Admittedly when there is no writing for any alteration
    or deyiation no claim could be allowed by the arbitrator. To accept the claim
    of the contractor on claims 1 and 3 without examining the pre-condition of E
    there being any writing of any alteration or deviation would not be legal.

          Now it does appear to us that the final bill amounting to Rs. 14,32,436.62
    encompasses all the works done by the contractor which were measured by
    the Local Commissioner in presence of both the parties and which perhaps            F
    also includes the work for which contractor could not raise any claim under
    the contract. In the evidence which has been led thefe is no objection to
    measurements recorded by the Local Commissioner and the fmal bill prepared
    on that basis. That is all the amount contractor is entitled to. By raising other
    claims he is merely trying to create confusion with the hope that he may be
    able to get s~me payment outside the contract for which he un~ortunately            G
    succeeded. Out of the final bill of Rs. 14,32,436.62 the contractor has been
    paid Rs. 5,71,915.60 thus leaving a balance of Rs. 8,60,521.02 to which in all
    the contractor would be entitled to under the Award.

          Under the Interest Act, 1978, which came into force on August 19, 1981,
    court includes arbitrator. Under Section 5 of the Interest Act Section 34 of        H
     14                      SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.

A Code of Civil Procedure would, therefore, apply to the arbitrator as well.
     Arbitrator is thus entitled to award interest pendente lite and future interest
     at the rate not exceeding the current rate of interest which has also been
     defined in clause (b) of Section 2 of the Interest Act.

           In the present case arbitrator awarded interest at the rate of 10% per
B   annum which was reduced by the learned single Judge to 6% per annum and
    upheld by the Division Bench. Under Section 34 of Code of Civil Procedure
    interest at the higher rate than 6% can be awarded where the liability in
    relation to the sum so adjudged had arisen out of commercial transac!ion.
    There is nothing on the record to show that interest awarded by the arbitrator
C   at the rate of 10% is in contravention of Section 34 of Code of Civil Procedure.
    That being so we do not think either the learned single Judge or Division
    Bench were correct in reducing the rate of interest as granted by the arbitrator.
    We would, therefore, restore the award of interest at the rate of 10% per
    annum as granted by the arbitrator from the date the arbitrator entered futo
    reference till realisation of the amount under the award.
D
          When the appeal filed by the State of Jammu and Kashmir came up for
    admission before this Court it was ordered on May 1, 1989 that the State
    Government shall "pay 1/2 of the decretal amount payable under the order of
    the High Court against bank guarantee to the respondent. The bank guarantee
E   shall be given to the satisfaction of the Deputy Registrar of the High Court.
    Issue stay of further execution proceedings". If by the order dated May 1,
    1989 excess amount has been paid by the State to the contractor the same
                                                                                            -
    shall be refunded to the State by the contractor with interest at the rate of
    10% per annum from the date the contractor got the excess amount till it is
    refunded to the State Government.
F
           Arbitration is considered to be an important Alternative Disputes
    Redressal process which is to be encouraged because of high pendency of
    cases in the courts and cost of litigation. Arbitration has to be looked up to
    with all earnest so that litigant public has faith in the speedy process of
G   resolving their disputes by this process. What happened in the present case
    is certainly a paradoxical situation which should be avoided. Total contract
    is for Rs. 12,23,500. When the contractor has done less than 50% of the work
    the contract is terminated. He has been paid Rs. 5, 71,900. In Section 20
    petition he makes a claim of Rs. 39,47,000 and before the arbitrator the claim      (.. ~
    is inflated to Rs. 63,61,000. He gets away with Rs. 20,08,000 with interest at
H   the rate of 10% per annum and penal interest at the rate of 18% per annum.
                         STATEv. D.D. PANDIT [D.P. WADHWA, J.]                        15
         Such type of arbitration become subject of witticism and do not help the           A
         institution of arbitration. Rather it brings bad name to the arbitration process
         as a whole. When claims are inflated out of all proportions not only that
         heavy cost should be awarded to the other party but the party making such
         inflated claim should be deprived of the cost. We, therefore, set aside the
         award of cost of Rs. 7,500 given in favour of the contractor and against the       B
         State of Jammu and Kashmir.

               Both the appeals are partly allowed. Judgment and decree passed by the

I
    ••   learned single Judge making the Award dated February 9, 1983 Rule of the
         Court and as modified by the impugned judgment is further modified. Now
         Award is made Rule of the court to the extent of Rs. 8,60,521 with interest at     C
         the rate of 10% per annum from the date of reference till payment is made.
         There shall be no order as to costs in both the appeals. The exact amount
         payable/due to any of the parties shall be worked out while drawing up the
         decree keeping in view the order dated May 1, 1989 of this Court
                                                •
         A.KT.                                                 Appeals partly allowed.      D


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.